Beruflich Dokumente
Kultur Dokumente
GUIDANCE NOTES ON
JUNE 2008
Copyright 2008
American Bureau of Shipping
ABS Plaza
16855 Northchase Drive
Houston, TX 77060 USA
This Page Intentionally Left Blank
Foreword
Table of Contents
GUIDANCE NOTES ON
SURVEYS DURING CONSTRUCTION OF
MEMBRANE TANK LNG CARRIERS
CONTENTS
CHAPTER 1 Introduction ............................................................................1
Section 1 General Provisions....................................................3
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 iii
This Page Intentionally Left Blank
Chapter 1: Introduction
CHAPTER 1 Introduction
CONTENTS
SECTION 1 General Provisions ................................................................3
1 Applicability ............................................................................3
2 Scope.....................................................................................3
3 General Requirements...........................................................4
4 Qualifications of NDE Operators............................................4
5 Materials ................................................................................4
6 Survey/Inspection Methodology.............................................4
6.1 Patrolling ........................................................................... 4
6.2 Official Inspection.............................................................. 4
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 1
This Page Intentionally Left Blank
Section 1: General Provisions
CHAPTER 1 Introduction
1 Applicability
These Guidance Notes provide guidance on shipbuilding quality standards for the inspections, surveys
and repairs of membrane tank LNG carriers during construction. However, no indications contained
herein are to be interpreted as the Bureaus requirement for the construction of LNG carriers.
These Guidance Notes are only intended to apply to those parts of a Liquefied Natural Gas Carrier
(LNGC), which are unique to these highly specialized vessels. For other features, the normal criteria
of inspections and surveys remain applicable.
Additionally, these Guidance Notes are intended to discuss the installation and tests of Cargo
Containment Systems and Cargo Handling Systems.
2 Scope
These Guidance Notes provide advice relative to the construction, inspection and survey of typical
Membrane Cargo Containment System technologies fitted on todays LNG carriers. Unless explicitly
stated elsewhere in these Guidance Notes, the standards and the level of workmanship reflected herein
will, in principle, be acceptable for the todays Membrane Cargo Containment Systems constructed by
experienced shipyards in accordance with the designers specifications. A more stringent standard
may, however, be required for shipyards becoming involved in the construction of LNG carriers for
the first time, or those shipyards which have recently changed their standard procedures and/or
design. Additionally for highly stressed areas of the cargo containment and cargo handling systems, a
more stringent standard may be required taking into consideration the intended service of the vessel.
The content of these Guidance Notes should be used as general guidance for Surveyors and shipyard
personnel. However, no indications contained herein, are to be interpreted as the Bureaus requirements
for the construction of LNG carriers. The figures, sketches and diagrams indicated in these Guidance
Notes are to be interpreted as an acceptable practice for current standard designs of LNG carriers
presently under construction in shipyards. It is highly recommended that an official inspection plan be
agreed upon between shipyards and the attending surveyors for each individual project. In the case of
a discrepancy between the agreed Inspection Plan and the content of these Guidance Notes, the agreed
Inspection Plan should take precedence.
The content of these Guidance Notes is, in general, based on ABS experience, the Installation
Specifications and Handbooks of Gaztransport and Technigaz for membrane type LNG carriers taking
into consideration the construction and installation practices of the most experienced shipyards in the
construction of LNG carriers. Should designers specifications and/or shipyard practices change, the
content of these Guidance Notes may need to be reconsidered in light of the reasons for these
changes. In the case of conflict between the content of the ABS Guidance Notes and the last revision
of Gaztransport and Technigaz or other Designers documents, the latter shall prevail.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 3
Chapter 1 Introduction
Section 1 General Provisions 1-1
3 General Requirements
The inspections and surveys are to be carried out in accordance with the Rules. At a kick-off meeting,
aimed at facilitating the surveys and build schedule, all parties are encouraged to agree to the in place
shipyard practices and design specifications for the cargo containment system, and the development
of inspection test plans (ITPs).
Provisions are to be made to ensure proper accessibility, staging, lighting and ventilation.
Welding operations are to be carried out under shelter from rain, snow and wind.
Welding operations relative to the installation of insulation, membrane and cargo tanks are to be
carried out by qualified operators, in accordance with approved welding procedures and with welding
consumables also approved by the Bureau and/or training plans established by the shipyards, as applicable.
Gluing procedures are to be in strict adherence with the instructions provided by the glue manufacturers
and by trained and qualified installers.
5 Materials
All materials, including welding consumables, to be used for the fabrication of the cargo containment
and cargo handling systems are to be in accordance with Bureau approved construction plans and the
ABS Rules for Materials and Welding (Part 2).
6 Survey/Inspection Methodology
Surveyors tasks and activities in the shipyards are to be performed by combining two different yet
complementary survey methodologies.
6.1 Patrolling
The Surveyor will carry out patrolling on his own, observing production before its presentation for
formal inspection. The main advantage of patrolling is to assist the shipyard by identifying possible
problems as early as possible so as to enable the shipyard to find adequate solutions before adversely
affecting the construction of the vessel. This is one key area where the experience of a Surveyor could
be used to assist the shipyard to the maximum extent possible whilst still working within the intent of
the Rules and specifications.
4 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 2: Membrane LNG Carriers Cargo Containment Systems
CONTENTS
SECTION 1 Mark III Systems .....................................................................9
1 Mark III System ......................................................................9
2 Welders and Welding Procedures Qualifications ................10
2.1 Types of Welding ............................................................ 10
2.2 Welding Parameters........................................................ 11
2.3 Welders, Operators and Machine Qualifications ............. 11
2.4 Nondestructive Tests for Qualifications........................... 14
2.5 Destructive Tests for Qualifications................................. 14
2.6 Welding of Membrane Sheets ......................................... 15
2.7 Tack Welding Sequences ............................................... 15
2.8 Intermittent Welding ........................................................ 16
2.9 Repairs............................................................................ 17
2.10 Acceptability Criteria ....................................................... 17
3 Panel Bonding to Inner Hull .................................................18
3.1 General Principle............................................................. 18
3.2 Mastic Procedure Qualification Test................................ 18
3.3 Checking Operations at Application Time ....................... 18
4 Triplex Bonding ....................................................................20
4.1 S-Triplex Strip Bonding on Flat Panels ........................... 20
4.2 Bonding Procedure Qualification Test for S-Triplex ........ 20
4.3 Checking of Epoxy Glue Depositing Process .................. 21
4.4 Special Recommendations for Bonding .......................... 21
4.5 Qualification of Bonders .................................................. 22
5 Welding ................................................................................22
5.1 Stud Welds...................................................................... 22
5.2 Membrane Welding ......................................................... 22
6 Summary of Surveys to be Carried Out at Manufacturers
Facilities of Mark III System Components ...........................23
6.1 Types of Surveys to be Carried Out ................................ 23
6.2 Plywood .......................................................................... 23
6.3 Reinforced Polyurethane Foam....................................... 23
6.4 Load Bearing Mastic ....................................................... 23
6.5 Stainless Steel for Membrane ......................................... 23
6.6 Stainless Steel for Special Pieces, as Anchoring
Strips and Corner Angles ................................................ 23
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 5
6.7 Adhesive Products ..........................................................23
6.8 Triplex..............................................................................23
6.9 Other Products (Glass Wool, Aluminum Rivets,
Studs, etc.) ......................................................................23
6.10 Fabricated Insulation Panel .............................................24
6.11 Fabrication of Membrane.................................................24
6.12 Fabrication of Angle Pieces.............................................24
6.13 Fabrication of Corner Pieces ...........................................24
7 Summary of Surveys to be Carried Out During
Installation of Mark III System..............................................24
7.1 Types of Surveys to be Carried Out ................................24
7.2 Hold Measurement ..........................................................24
7.3 Marking-out .....................................................................25
7.4 Cleaning ..........................................................................25
7.5 Stud Bolt Welding............................................................25
7.6 Mastic and Epoxy Glue Application .................................25
7.7 Panels Installation ...........................................................25
7.8 Leveling Wedge Installation.............................................25
7.9 Secondary Barrier Bonding and Top Bridge Pad
Installation .......................................................................25
7.10 Completion of Insulation Installation................................26
7.11 Membrane Installation .....................................................26
7.12 Tightness Test of Membrane (NH3 Test) ........................27
7.13 Global and Tightness Test...............................................27
7.14 Side Opening Closure .....................................................27
7.15 Scaffolding Dismantling and Final Inspection ..................27
7.16 Liquid and Vapor Dome...................................................27
8 Inspection Plans for Mark III System ...................................27
6 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
FIGURE 7 Membrane Sheet Tack Welding.................................16
FIGURE 8 Intermittent Welding Principle 1.2 mm Sheet on
2 mm Anchoring Strip ................................................16
FIGURE 9 Repair Patch Over Membrane ...................................26
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 7
TABLE 1 NO 96 System Components Materials ...................66
TABLE 2 NO 96 System Wooden Boxes Fabrication ............68
TABLE 3 NO 96 System Fabrication of Invar Tubes and
Other Invar Special Pieces ........................................71
TABLE 4 NO 96 System Secondary Insulation and
Secondary Barrier Installation....................................75
TABLE 5 NO 96 System Secondary Membrane Tightness
Tests ..........................................................................92
TABLE 6 NO 96 System Primary Insulation and Primary
Installation ..................................................................94
TABLE 7 NO 96 System Primary Membrane Tightness
and Final Tests.........................................................100
8 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Section 1: Mark III Systems
FIGURE 1
GTT Mark III Membrane Containment System
The primary membrane is a 1.2 mm thick stainless steel corrugated membrane. The membrane is
fitted and welded to stainless steel strips built into insulation panels.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 9
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 1 Mark III Systems 2-1
FIGURE 2
Typical Corner Assembly for Mark III System
10 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 1 Mark III Systems 2-1
ii) Sheet to Anchor Strips (1.2 2). For sheet to anchor strip, welding qualification is to be carried
out in all positions as indicated above for sheet to sheet:
iii) Crossing of Four Sheets (1.2 2, 1.2 1.2). For crossing of four sheets, welding qualification
is to be carried out in the following three positions
Flat position
Vertical position
Overhead position
iv) Sheet to Stainless Steel Corner (1.2 8). For sheet to stainless steel corner, welding qualification
is to be carried out in all positions as indicated above for sheet to sheet:
If one of the tests does not meet the requirements, the welder may carry out two new tests of the same
type as the rejected one. Should the weld fail to satisfy the visual examination and dye penetrant test
after completing the retest in the previously failed position, the welder is considered to be
unacceptable for that position and is to be retested at a later date as determined by the shipyard in
conjunction with the attending Surveyor.
Where the weld passes the visual examination and dye penetrant test after completing the retest, the
weld is to undergo a macrographic examination and bend test. Upon successful passing of these tests,
the welder is considered as being qualified; unsatisfactory results will require the welder to attend
additional welding school, or supplemental training as specified in the shipyard process.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 11
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 1 Mark III Systems 2-1
FIGURE 3
Manual Welders Qualification Process
TEST SPECIMEN
FOR MANUAL WELDING
VISUAL EXAMINATION
DYE PENETRANT TEST
FAIL PASS
VISUAL EXAMINATION
DYE PENETRANT TEST FAIL PASS
REJECTED MACROGRAPHIC
EXAMINATION VISUAL EXAMINATION
BEND TEST DYE PENETRANT TEST
FAIL PASS
12 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 1 Mark III Systems 2-1
For automatic welding machines, daily production tests shall be performed. 2-1/Figure 4 is a flowchart
summarizing the automatic welding machine qualification process. For experienced shipyard having
continuous work, and with the confirmation of the attending Surveyor, the welding performed by the
automatic welding machine may continue while these production test results are being developed and
evaluated.
FIGURE 4
Welding Machine Qualification Process
TEST SPECIMEN
FOR AUTOMATIC
WELDING
VISUAL EXAMINATION
FAIL PASS
MACROGRAPHIC
EXAMINATION
FAIL PASS
FAIL PASS
MACROGRAPHIC
EXAMINATION
FAIL PASS
CONTROL OF WELDING MACHINE
AND WELDING PARAMETERS
Where adjustments to the automatic welding machines are required to accommodate new positions,
federates, or to correct a problem that resulted in the failure of the production test, the attending
Surveyor is to be satisfied that the adjustments are adequate and that the welds are acceptable.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 13
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 1 Mark III Systems 2-1
2.5.1 Macros
2 macrographic tests for each position in flat section (ASTM E 3 and E 340)
4 macrographic tests for each position in corrugated section
2-1/Figures 5 and 6 show the macro criteria for manual and automatic welding.
FIGURE 5
Macro Acceptance Criteria for Manual Welding
d criteria
3 < d < 4.2 for t2 = 1.2 mm
t1 = 1.2 mm
d
Weld throat > 0.8 mm
P > 0.6 mm
L > 2 mm
t2 = 1.2 mm, 2 mm, 8 mm or more
FIGURE 6
Macro Acceptance Criteria for Automatic Welding
d criteria
3.5 < d < 6 for t2 = 1.2 mm
t1 = 1.2 mm
d
Weld throat > 0.8 mm
P > 0.6 mm
L > 2 mm
t2 = 1.2 mm, 2 mm, 8 mm or more
14 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 1 Mark III Systems 2-1
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 15
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 1 Mark III Systems 2-1
FIGURE 7
Membrane Sheet Tack Welding
Small corrugation
1 2 5 6
3 4 8 7
No gap at the
corrugation foot
Tack weld
1 2 7 8
Large corrugation
6 5 12 11
3 4 9 10
FIGURE 8
Intermittent Welding Principle: 1.2 mm Sheet on 2 mm Anchoring Strip
m
2m
h . 1.
et t
She 10 uou
s
co ntin 20
10 is
6 d ld 2 0
we
Rivet
Anchoring 480
strip th. 2 mm
10 uous
in
i sc ont 20
10 8 d ld 2 0
we
Welding on fixation rivets is not allowed. These rivets are made of aluminum. Aluminum dilution of
the weld may lead to fracture. To avoid welding on fixation rivets, the membrane marking line should
be positioned on the center of the anchor strip with an offset tolerance of 6 mm.
Tack welding must be made before intermittent weld.
16 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 1 Mark III Systems 2-1
2.9 Repairs
All repairs are to be executed by qualified welders according to approved procedures.
The defective portion of the weld is to be removed without substantial removal of the base metal and
is to be done in such a manner that the remaining weld metal or base metal is not nicked or undercut.
The repair area should have acceptable contours and is to be inspected visually and by dye penetrant
prior to re-welding to ensure the defect has been completely removed.
Every possible care is to be taken with repairs to minimize welding stresses. Local repairs are
normally inspected at 100% by the method prescribed for the original weld.
If planar defects (cracks) are to be repaired, every effort is to be made to prevent propagation of the
defect during its removal.
2-1/Table 1 indicates the repair methods to be applied for the most common welding defects.
TABLE 1
Welding Defects and Repair Methods
Welding Defect Repair Method
Overlap or excessive convexity Remove excessive weld metal
Excessive concavity of weld or craters, undersized Prepares surfaces and remelting the weld with or
welds or undercutting without filler metal
Incomplete fusion, planar defects, tungsten inclusion Grind unacceptable portion and reweld with filler metal
TABLE 2
Acceptability Criteria of Welding Defects
Defect Acceptance Limits
Cracks Not acceptable
Lack of fusion Not acceptable
Lack of penetration Not acceptable
Burn through Not acceptable
Poor weld restart Not acceptable
External concavity Not acceptable
Arc strike Not acceptable
Tungsten inclusion Not acceptable
Width of Weld Seam , W
a) Steel welded 1.2 mm on 1.2 mm Automatic: 4 W 6 mm and Manual 3 W 4.2
b) Steel welded 1.2 mm on 2 mm Automatic: 4 W 6 mm and Manual 3 W 4.8
c) Steel welded 1.2 mm on 8 mm Automatic: 4 W 6 mm and Manual 3 W 4.8
Gap before welding Maximum 0.3 mm
Maximum length 10 mm on flat part and 20 mm on corrugation part
Oxidation in back side
Maximum width 3 mm (see note)
Mechanical damages (i.e., scratches or dents) on
To be repaired in accordance with GTT specifications
membrane sheet surface
Note: Two isolated defects are considered as one if the distance between the defects is less than one times the length of the
longer defect
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 17
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 1 Mark III Systems 2-1
3.3.2 Every Day Prior to Starting Production and at Each Exchange of Component Drum
The mixing process is to be checked visually for homogeneous color of a crushed bead. No
veining (tiger stripes) is to be detected.
Dosing and mixing is to be checked:
By keeping one bead (1 meter long) at ambient temperature for 24 hours and by confirming
proper curing rates for the given thickness.
By keeping a mastic sample in a standard oven at 110C for 10 minutes and checking the
normal hardness (hardness value is to be confirmed by the manufacturer). Oven test
positive result is not a guarantee of good mixing; however a negative result is a certainty
of bad mixing. The oven test is carried out 24 hours in advance of panel installation whilst
ambient temperature cure sample is verified.
18 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 1 Mark III Systems 2-1
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 19
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 1 Mark III Systems 2-1
4 Triplex Bonding
20 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 1 Mark III Systems 2-1
4.3.1
The correct amount of resin and hardener by weight or volume is to be verified by independent
means.
4.3.2
The mixing process is to be checked visually by confirming homogeneous color of glue. Tiger
stripes or veining in the deposited glue if detected is an indication of a fault in the mixing
process. The dosing and mixing is to be checked by keeping a sample in an oven at a
temperature and time prescribed by the glue manufacturer and checking the hardness value
according to glue manufacturer specification. The mixing process is also to be checked after
each exchange of the component drum.
4.3.3
The proper functioning of the glue depositing machine is to be checked at regular intervals
including during start up. The characteristics of the glue are checked from samples taken
directly from the machine every hour. The samples are to be tested to confirm the characteristics
of the glue including:
The mixing ratio between resin and hardener by observing the constancy of the color.
Variation of color is the result of a wrong dosing.
Mixing process is to be verified and checked by keeping samples. These samples are to be
provided with a unique identification number (with reference to time and temperature)
which will correspond to those numbers noted on each concerned S-triplex strip.
The shape and unitary quantity of depositing glue is checked by weighing and/or by
measuring template.
Ambient temperature and humidity is to be recorded.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 21
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 1 Mark III Systems 2-1
When repair of bonding areas occurred, a sanding at 50 to 80% of the thickness of glue (generally
0.7 mm) of the previous glue on the rigid triplex should be performed.
A means to avoid contamination from installer perspiration on the bonding areas should be provided
by the shipyard (towel, hair band, etc.).
It is important to spread the glue evenly on each panel, to ensure an equal amount is applied to each
panel.
Uniform pressure is to be applied for the required duration and is to be, established as a function of
the actual temperature in the cargo tank. This pressure is essential for obtaining a good gluing bonding.
In particular, before starting a project, the attending Surveyor is to investigate the methodology used
to keep the pressure constant in the air bags for the triplex bonding in case of shifting (compressor
generally on shore).
5 Welding
22 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 1 Mark III Systems 2-1
6.2 Plywood
Plywood, used for the construction of the insulating panels, should be inspected during fabrication by
an ABS Surveyor. However, attendance during construction may be reduced if the product is ABS
Type Approved.
6.6 Stainless Steel for Special Pieces, as Anchoring Strips and Corner Angles
It is to be certified by the Bureau.
6.8 Triplex
Rigid triplex and flexible triplex should be inspected during fabrication by an ABS Surveyor. However,
attendance during construction may be reduced if the product is covered by ABS Type Approval.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 23
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 1 Mark III Systems 2-1
24 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 1 Mark III Systems 2-1
7.3 Marking-out
Since the marking out of tanks is not specifically addressed in the Rules, the attendance by an ABS
Surveyor is not required. However, shipyard procedures and operations may be observed by the
Surveyor during patrolling activity.
7.4 Cleaning
Cleanliness and house keeping are to be observed during patrolling, as cleanliness is one of the most
important factors for a trouble-free installation of the insulation and membrane.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 25
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 1 Mark III Systems 2-1
Soft triplex is to be laid down in full compliance with the tolerances indicated in the specification,
with particular regard to the overlaps of different layers. In general, overlaps of more than two
layers of triplex are not permitted.
- Installation air bags are to be of proper design to assure uniform pressure in all positions and
are to be kept in position for the complete time indicated in the GTT specification.
- Vacuum test are to be witnessed as far as possible and deemed necessary.
- For bridge pads, the same considerations made above for triplex apply.
FIGURE 9
Repair Patch Over Membrane
26 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 1 Mark III Systems 2-1
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 27
28
TABLE 3
Mark III System Components Materials Section
Chapter
Physical Properties
Thermal Properties
Mark III Systems
GLASS CLOTH
Physical Properties ALUMINUM FOIL
Designers/manufacturers
Triplex TA/R/MA
specifications
Mechanical BONDING COMPOUND
Physical Properties
Chemical Designers/manufacturers
Stainless Steel H*
Characteristics specifications
Membrane LNG Carriers Cargo Containment Systems
Mechanical
Characteristics
* To be ABS certified
2-1
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 3 (continued)
Mark III System Components Materials
Section
Chapter
Physical Properties
Designers/manufacturers
Adhesives Products MA
specifications
Mechanical
Characteristics
Mark III Systems
Physical Properties
Designers/manufacturers
Plywood TA/MA
specifications
Mechanical
Characteristics
Physical Properties
Membrane LNG Carriers Cargo Containment Systems
Mechanical
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Characteristics
2-1
29
30
TABLE 4
Mark III System Components Prefabricated Components Section
Chapter
Thickness
Pad-on-panel thickness: 0.5 mm
Flatness 2.0 mm by meter of length
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 4 (continued)
Mark III System Components Prefabricated Components
Section
Chapter
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Third wings, where
As per detailed drawing
applicable
2-1
31
32
TABLE 5
Mark III Cargo Containment System Insulation Installation Section
Chapter
HBA ABE
Center
punch
B marks L B D: 80 mm MA
A
H HDA ADE
JBH
E EBF
nal Diago
EF
Diago DE HDA nal Edge
-A -EDF
E
JDH
CD
D
JDH
Dia E-
-A nal
l
D
BF
go HD
DK o
-E
na A
C iag
G
FD
F
EDF Bulkhead: +80 mm, 40 mm
al
l
Dia
gon DF
na
a DJ-E
Mark III Systems
DA
Dia
l FD
go
E-J al K
ia
DH gon
D
Dia
JDH-CD
gon
al
Diagon
DJ-H
Diagon K
CDG-ED
al A
al K
J F
gon
DE-F
Edge DF
Dia
DG
Dia
go
n
Edge BF
al
Hold measurement Main dimensions D
ED
F-
KDJ
FB
Diagonal
CDK-FDG FDG
G
KDJ-CDG
Z2 Diagonal Z3
Ed
ge
FG
CDK CDG G Ceiling length: 40 mm NA
K
KBJ C
Z1 Z4 FBG
CBK CBG
Reference surface
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 5 (continued)
Mark III Cargo Containment System Insulation Installation
Section
Chapter
Gap 4 mm maximum
Straightedge 1 m
Deformation of
Inner hull flatness Between stiffeners,
plating between P
(contd) max offset: 4 mm/1 m
stiffeners
Mark III Systems
Welding visual
100% H
inspections
NDT 100% MA
Inner hull
inspections Air test of welding 0.2 bar H
Cleanliness and
environmental No dust, rust, grease, oil P
conditions
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
2-1
33
34
TABLE 5 (continued)
Mark III Cargo Containment System Insulation Installation Section
Chapter
Positioning and
straightness
Retainer tolerance 3 mm
Geometry Straightness: 3 mm
cm
Weld seam 40
Retainer bars R
Inner Hull
Calculation of
dz1
dz5
GTT program NA
dz4
dz2
dz3
reference surface
Inner Hull
Reference surface
determination
Membrane LNG Carriers Cargo Containment Systems
Installation of
Thickness check P/R
reference wedges
2-1
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 5 (continued)
Mark III Cargo Containment System Insulation Installation
Section
Chapter
m
2 m
2 mm
m
1 m
E
1 mm
D
C
B Panel corner studs: 1 mm
Location tolerance A P
Panel intermediate studs: 2 mm
Stud bolt m
1 m
Mark III Systems
installation
1 mm
2 max
Perpendicularity Inclination: 2 P
at random)
Studs tensile test 800 kg no failure P
Corner panels (first
100 studs, then
10% random)
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
2-1
35
36
TABLE 5 (continued)
Mark III Cargo Containment System Insulation Installation Section
Chapter
No tiger stripes,
Visual inspection
homogeneous color
Curing test
Oven test
As per sketch
Note: Some tanks have
additional high load
Definition of high areas in upper areas R
loaded areas due to sloshing
H2
H1
impact loads when
in partial filling
conditions.
Membrane LNG Carriers Cargo Containment Systems
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 5 (continued)
Mark III Cargo Containment System Insulation Installation
Section
Chapter
Positioning of
epoxy mastic beads 100 mm Pitch 105 mm
high loaded area
100
100
55
Mark III Systems
55
30
P
30 80 20140.5 Epoxy ropes width = 25 mm
Positioning of
epoxy mastic beads 140 mm Pitch 145 mm
normal loaded area
100
100
Mastic application
55
55
30
341.5
45 10
0
5
6 45
45
Se 31.
co 5
Positioning of nd
ar
yb
ar
epoxy patches high rie
r
105 mm Mesh 110 mm
1413
Membrane LNG Carriers Cargo Containment Systems
511.5
loaded area
45
534.1
45
5
1004
Secondary barrier
10
45
45 P
2 1002
0
10
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Mesh of epoxy
mastic patches 125 mm Mesh 130 mm
normal loaded area
10
0
4
2-1
37
38
TABLE 5 (continued)
Mark III Cargo Containment System Insulation Installation Section
Chapter
Width: 25 mm
Resin bead size
(average after crushing)
Mark III Systems
Mastic application
P/R
(contd)
Resin bead patch Diameter: 60 mm
Visual examination
Appearance
after crushing
Membrane LNG Carriers Cargo Containment Systems
Corner panel
Positioning 30 mm 3 mm P/R
erection
2-1
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 5 (continued)
Mark III Cargo Containment System Insulation Installation
Section
Chapter
Flatness 1 mm
Mark III Systems
Out of plane
between corner and 6 mm/1 m P/R
flat panels
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
2-1
39
40
TABLE 5 (continued)
Mark III Cargo Containment System Insulation Installation Section
Chapter
30 3 mm between
Flat panel erection Gap P/R
adjacent panels
Membrane LNG Carriers Cargo Containment Systems
2-1
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 5 (continued)
Mark III Cargo Containment System Insulation Installation
Section
Chapter
P/R
Membrane LNG Carriers Cargo Containment Systems
Out of plane
1.5 mm/0.5 m
between flat panels
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
2-1
41
42
TABLE 5 (continued)
Mark III Cargo Containment System Insulation Installation Section
Chapter
Panel identification
NA
and traceability
Mark III Systems
Contact with P
Appearance
wedges
Membrane LNG Carriers Cargo Containment Systems
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 5 (continued)
Mark III Cargo Containment System Insulation Installation
Section
Chapter
Foam plug
Detail A
Detail A
Cylindrical foam
Protrusion +0 mm, 2 mm P
+0,2
plug
+0 mm, 5 mm,
Filling R
Gap 3 mm
Gaps between
panels Joint filler and flat
1.5 mm R
joint flatness
Membrane LNG Carriers Cargo Containment Systems
Final inspection of
100% visual H
panel installation
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
2-1
43
44
TABLE 5 (continued)
Mark III Cargo Containment System Insulation Installation Section
Chapter
Absence of
possible
contaminants
Color homogeneity, no
Membrane LNG Carriers Cargo Containment Systems
Visual inspection
tiger stripes
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 5 (continued)
Mark III Cargo Containment System Insulation Installation
Section
Chapter
Color homogeneity, no
Visual inspection
tiger stripes
Extremities from 0 to
Panel position
15 mm
Erection tolerance P/R
Overlapping
between Flexible Overlap: 75 5 mm
triplex edges
Installation of air
Appearance
bag
Bonding P/R
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Squeeze out check Appearance
2-1
45
46
TABLE 5 (continued)
Mark III Cargo Containment System Insulation Installation Section
Chapter
Local vacuum tests All overlap areas 200 mbar for 45 seconds, H
after bonding and suspect areas no bubbles
Mark III Systems
Pre-qualification
Color homogeneity, no
tests Visual
tiger stripes
inspection
According with
Pre-qualification
manufacturers
tests Curing test
specification
Daily before
Epoxy glue for Color homogeneity, no
production test
Membrane LNG Carriers Cargo Containment Systems
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 5 (continued)
Mark III Cargo Containment System Insulation Installation
Section
Chapter
Epoxy drum
Color homogeneity, no
exchange test
tiger stripes
Visual inspection
Daily before
Epoxy glue for
production Check
bonding hardwood P
of curing in the According with
keys (contd)
oven manufacturers
Daily before specification
production
Mark III Systems
Hardness
Position 2 mm tolerance
Fixation bar
Hardwood key
P/R
erection
Installation of Le
vel
Secondary barrier
ing
0
Appearance
retainer bars .5
mm
Squeezing out
of epoxy glue
As per graphs depending on
Membrane LNG Carriers Cargo Containment Systems
Bonding time
ambient temperature
Pre-qualification
Color homogeneity, no
tests Visual
Epoxy glue for tiger stripes
inspection
bonding top bridge P
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
pads According with
Pre-qualification
manufacturers
tests Curing test
specification
2-1
47
48
TABLE 5 (continued)
Mark III Cargo Containment System Insulation Installation Section
Chapter
Daily before
Color homogeneity, no
production test
tiger stripes
Visual inspection
Daily before
production test
Check of curing in According with
the oven manufacturers
Daily before specification
production test
Mark III Systems
m
4m
Erection of top Different level of
Membrane LNG Carriers Cargo Containment Systems
m
4m
2-1
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 5 (continued)
Mark III Cargo Containment System Insulation Installation
Section
Chapter
Gap 4 mm
Alignment of top
bridge pads at tank Thermal protection should be higher than SUS corner From 0 to 0.7 mm
edges
Mark III Systems
Gluing Appearance
Erection of top
bridge pads
between P/R
flat panels
(contd)
Installation of
Membrane LNG Carriers Cargo Containment Systems
Appearance
setting bars
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
As per graphs depending on
Bonding time
ambient temperature
Final check of Gap between panels and
Flatness
insulation bridge pads: 1.5 mm H
completion Cleanliness Appearance
2-1
49
50
TABLE 6
Mark III Cargo Containment System Membrane Installation Section
Chapter
Dimensional
tolerances of P/R
membrane panels
Width of joggle 45 1 mm
Membrane LNG Carriers Cargo Containment Systems
Positioning of first
Tolerance +8 mm, 10 mm P
membrane sheet
2-1
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 6 (continued)
Mark III Cargo Containment System Membrane Installation
Section
Chapter
Positioning of
second membrane Gap 0.3 mm P
sheet
Membrane sheet
Tolerance 6 mm with respect to edge corrugation P
adjustment
Mark III Systems
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
2-1
51
52
TABLE 7
Mark III Cargo Containment System Testing Section
Chapter
Reference document:
General MA
GTT external document 1139
Cleaning with slightly acid
No dust, epoxy glue, grease, oil, etc.
water
Temperature during paint
> 20C
application
Humidity during paint
< 70%
application
Mark III Systems
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 7 (continued)
Mark III Cargo Containment System Testing
Section
Chapter
Tightness test of
Mark III Systems
membrane
(Ammonia test) Checking of reference leaks 100%
(contd)
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
2-1
53
54
TABLE 7 (continued)
Mark III Cargo Containment System Testing Section
Chapter
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Section 2: NO 96 Systems
SECTION 2 NO 96 Systems
1 NO 96 System
2-2/Figures 1 and 2 are sketches showing the design principle and the typical corner assembly of the
GTT NO 96 membrane system.
FIGURE 1
GTT NO 96 Membrane Containment System
The NO 96 system is based on two identical membranes made of Invar. Invar is a 36% nickel alloy
with a very low shrinkage coefficient, about 10 times less than that of steel (1.2 10-6 m/m/C).
The insulating elements both, primary and secondary, are plywood boxes filled with perlite. Perlite is
an insulation material based on expanded silica. The secondary boxes are bolted to the inner hull and
are set against resin beads, which compensate for the lack of flatness of the inner hull and provide the
necessary bearing surface. A sheet of craft paper rests between the resin and the inner hull to allow the
boxes free movement for hull deflection.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 55
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 2 NO 96 Systems 2-2
FIGURE 2
Typical Corner Assembly for NO 96 System
56 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 2 NO 96 Systems 2-2
FIGURE 3
Typical Pillars and Chairs
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 57
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 2 NO 96 Systems 2-2
In addition to standard Invar tubes, trihedrons are fabricated from 3.0 mm Invar plate using manual
TIG processes with filler metal.
Invar tubes can be attached to the anchoring bars by manual welding. However, it is preferable to use
automatic welding for a more consistent, even bead along its length. This welding is accomplished
after careful positioning, alignment and measuring of the Invar tube and installation of corresponding
insulation boxes. This type of procedure is specifically used in way of Invar-to-Invar connections such
as strake end welds, corner strakes, anchoring strips, stainless steel anchoring strips, collar studs and
coupler socket welds.
The Invar anchoring strip which connects the Invar tube to the anchoring bar requires two separate
procedures, one for each end. First, the connection to the stainless steel anchoring bar will require an
Invar-to-stainless steel procedure. Next, the connection to the Invar tube itself will require an Invar-to-
Invar procedure. Several weld procedures are used in close proximity to each other and care needs to
be exercised to insure that the correct procedure is applied to the appropriate location. These welding
procedures can be developed with or without filler metal.
FIGURE 4
Rotary Welding Machine on Magnetic Base
The second and less used variation is a 304 stainless steel coupler socket, which is fit in way of liquid
dome 316L stainless steel insert plates. These coupler sockets are welded using manual TIG process
in a fillet joint with an ER 316L filler metal.
A third autogenous welding process, with certain similarities to that of coupler base sockets, is the
weld process for stud welding. As before, material forming the skirt becomes the weld material with
the difference being that instead of a magnetic base holding the weld machine to the hull, this smaller,
lighter machine fastens to the stud itself for the duration of weld and is removed after.
Additionally, collar studs are welded to 0.7, 1.0, 1.5 and 3.0 mm Invar secondary membranes using a
similar autogenous weld machine and procedure.
58 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 2 NO 96 Systems 2-2
FIGURE 5
Connection of Invar Strakes
Additionally, this process is used in way of trihedrons, Invar tube extremities, pillar stainless steel- to-
stainless steel and stainless steel-to-Invar and stopper pieces.
The process involves a Resistance Spot Weld machine, with pincer-like copper electrodes, fitted to a
self-traveling carriage. This carriage has a set of mated drive wheels, which simultaneously grip the
tongue, propelling itself along, forming a joggled channel and producing intermittent tack welds along
the length of strakes. These tack welds are above (relative to) where the seam ERW weld path will be
as described below. Tack welding in way of manual TIG welding is carried out in similar fashion to
welding, whereby individual tacks are made approximately each 10 mm for length of weld area. See
2-2/Figure 6.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 59
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 2 NO 96 Systems 2-2
FIGURE 6
Resistance Spot Welding Machine
60 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 2 NO 96 Systems 2-2
In cases where welders fail these qualification tests, a re-training program must be established to
provide the appropriate skills and re-testing. Constant and vigilant attention to welding qualifications
and details are paramount to ensuring that all welds are carried out as designed and properly.
3 General Considerations
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 61
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 2 NO 96 Systems 2-2
5.2 Marking-out
No official inspection is required during this phase, however, shipyard procedures and operations may
be observed during patrolling activity.
5.3 Cleaning
Cleanliness and housekeeping are to be observed during patrolling, as cleanliness is one of the most
important factors for a trouble-free installation of the insulation and membrane.
62 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 2 NO 96 Systems 2-2
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 63
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 2 NO 96 Systems 2-2
64 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 2 NO 96 Systems 2-2
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 65
66
TABLE 1
NO 96 System Components Materials Section
Chapter
Chemical properties
Invar plates Designers/applicable steel specification H*
Mechanical properties
Plywood for Appearance
Designers/manufacturers specifications TA/R/MA
insulation boxes Mechanical properties
Physical characteristics
Perlite Designers/manufacturers specifications TA/MA
Granulometry
Physical Properties
NO 96 Systems
* To be ABS certified
2-2
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 1 (continued)
NO 96 System Components Materials
Section
Chapter
Couplers
Studs
Designers/manufacturers specifications TA/MA
Self locked nuts
Securing devices Collar studs
Washers
MA
Spring washers Designers/manufacturers specifications
Studs TA/MA
NO 96 Systems
Chemical properties
Material for
Applicable SUS specification H*
anchoring flat bars Mechanical properties
* To be ABS certified
Membrane LNG Carriers Cargo Containment Systems
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
2-2
67
68
TABLE 2
NO 96 System Wooden Boxes Fabrication Section
Chapter
fitting machine
Machine check Manufacturers specification NA
Plywood thickness Tolerance: 0.5 mm
Penetration: 2. 0mm
Stapling Longitudinal direction alignment: 5.0 mm
Transverse direction arrangement: 2.0 mm
Box assembly Length tolerance: 1.0 mm
P/R
Width tolerance: 0.5 mm
Height tolerance: 0.5 mm
Box dimensions
Partition space tolerance: 0.5 mm
Partition deformation: 2.0 mm
Diagonal: 1.2 mm
Visual inspection Appearance
Grooving P/R
Membrane LNG Carriers Cargo Containment Systems
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 2 (continued)
NO 96 System Wooden Boxes Fabrication
Section
Chapter
Final inspection of
Dimensions and twisting Diagonal: 1.2 mm R
boxes
Height of cleat from bottom plate:
Membrane LNG Carriers Cargo Containment Systems
0.5 mm
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
2-2
69
70
TABLE 2 (continued)
NO 96 System Wooden Boxes Fabrication Section
Chapter
Defective staples: 6
1 defective staple/every 3 in line
2 defective staple/every 5 in line
3 defective staple/every 7 in line
Final inspection of
Stapling Penetration: 2.0 mm FR
boxes (contd)
Longitudinal direction alignment:
5.0 mm
NO 96 Systems
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 3
NO 96 System Fabrication of Invar Tubes and Other Invar Special Pieces
Section
Chapter
defects
Height of seam welding: 5 mm
Internal dimensions of tube tolerance:
+0.2 mm/0.5 mm
Folding radius: 1.5 mm r
Pre-assembly P/R
Height of raised edges: 20 mm 1 mm
Punched hole diameter: 4.5 mm
Invar tubes Tolerance on spacing between punched
holes: 1 mm
Tolerance on distance between punched
hole and piece ends: 0.5 mm
Check welding parameters as per WPS R
Surface condition: no visible defects
Membrane LNG Carriers Cargo Containment Systems
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Visual inspection of TIG welding:
no visible defects
* May be R, if TA
2-2
71
72
TABLE 3 (continued)
NO 96 System Fabrication of Invar Tubes and Other Invar Special Pieces Section
Chapter
* May be R, if TA
2-2
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 3 (continued)
NO 96 System Fabrication of Invar Tubes and Other Invar Special Pieces
Section
Chapter
No visible defects
(oblique type)
Surface-no visible defects
H*
Length tolerance: 1.0 mm
Final inspection
Width tolerance: 1.0 mm
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Diameter of punched holes: 4.5 mm
* May be R, if TA
2-2
73
74
TABLE 3 (continued)
NO 96 System Fabrication of Invar Tubes and Other Invar Special Pieces Section
Chapter
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 4
NO 96 System Secondary Insulation and Secondary Barrier Installation
Section
Chapter
50 mm
50 mm
+20 mm
l
50 mm
50 mm
50 mm
NO 96 Systems
Feeler gauge
Gap 4 mm maximum
Inner hull flatness P
Straightedge 1 m
Membrane LNG Carriers Cargo Containment Systems
Deformation of
Max offset: 4 mm/1 m
plating between
straightedge
stiffeners
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Feeler gauge
2-2
75
76
TABLE 4 (continued)
NO 96 System Secondary Insulation and Secondary Barrier Installation Section
Chapter
R2a R2 R2b
R1 1 mm deviation from
straight line
Accuracy and R1a
Marking out 1.2 m NA
perpendicularity R2 1.5 mm
R1 perpendicularity offset on
NO 96 Systems
10 m length
1.0 m
R1b
dz1
dz5
GTT program NA
dz4
dz2
dz3
determination reference surface
Inner Hull
COUPLER SOCKET
WELDING PROFILE From reference line: 3 mm
Alignment
DETAIL A
R
From close box: 1 mm
Membrane LNG Carriers Cargo Containment Systems
La
Dye penetrant: 3%
Before welding
3% of couplers: 2040 kg
Strength test
applied for 15-20 sec
2-2
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 4 (continued)
NO 96 System Secondary Insulation and Secondary Barrier Installation
Section
Chapter
Positioning 1 mm
No visible defects
Installation of studs Welding
Hammering P
for corner boxes
1 time/day 450 kg
Strength test
apply for 20 sec
Detail A
Discontinuous weld
Fit-up L1 L1
NO 96 Systems
Stiffener axis
8
weld
Continuous V Dye penetrants: 5%
weld
Anchoring flat bar Anchoring flat bar
for trihedron Continuous weld
Membrane LNG Carriers Cargo Containment Systems
Position 1.0 mm
Installation of
P/R
reference wedges
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Thickness As per GTT program
2-2
77
78
TABLE 4 (continued)
NO 96 System Secondary Insulation and Secondary Barrier Installation Section
Chapter
Gap between
5 mm
plywood bridge
Quantity of staples
6
for bridge
Position and As per shipyard approved
deformation Standards
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 4 (continued)
NO 96 System Secondary Insulation and Secondary Barrier Installation
Section
Chapter
30 mm nominal
10 mm minimum
Anchoring bar
NO 96 Systems
7B 7B
Screwing of box
Appearance
Membrane LNG Carriers Cargo Containment Systems
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
flexible wedge slightly reshaped Spring back effect 8 mm
boxes
2-2
79
80
TABLE 4 (continued)
NO 96 System Secondary Insulation and Secondary Barrier Installation Section
Chapter
Flexible wedges
Resin ropes
Box bearing
Installation of
Appearance R
boxes type 1
Temporary screwing 312
Installation of
special boxes
type 1A in Step of boxes 0.5 mm R
longitudinal
corners
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 4 (continued)
NO 96 System Secondary Insulation and Secondary Barrier Installation
Section
Chapter
Beam bearing 1 mm
Spacing between
beams and between
5 mm
beams and
trihedron
Gap between
Mounting of prefabricated 10 mm R
composite beams in beams
way of longitudinal
NO 96 Systems
Fit-up
installation
No visual defects on
weldings
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
2-2
81
82
TABLE 4 (continued)
NO 96 System Secondary Insulation and Secondary Barrier Installation Section
Chapter
Steps: 0.5 mm
Installation of
Out of plane: 0.6 mm/1m R
corner boxes
NO 96 Systems
Leveling: 1.5 mm
0.5 mm
Gap between bridge and
Stopper
box: 3.0 mm
Installation of
R
plywood bridges Plywood beam
Screw
Step between bridges and
Membrane LNG Carriers Cargo Containment Systems
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 4 (continued)
NO 96 System Secondary Insulation and Secondary Barrier Installation
Section
Chapter
Reinforced
area
As per sketch, unless
Definition of tank
otherwise indicated on R*
reinforced areas
approved drawings
Standard
area
Mixing ratio of
1/0.26 10%
hardener and resin
Positioning of resin Deviation from partition
ropes axis: 3.0 mm
P
Homogeneous, no tiger
Color check
Membrane LNG Carriers Cargo Containment Systems
stripes
As per designers/shipyard
Insulation boxes Sampling tests
procedure
bearing mastic
depositing Width of crushed
12 mm
rope
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Rope length at each
80% of length P
box partition
83
84
TABLE 4 (continued)
NO 96 System Secondary Insulation and Secondary Barrier Installation Section
Chapter
Height to be case-by-case
Measurement of the
in accordance with GTT P/R
height
recommendation
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 4 (continued)
NO 96 System Secondary Insulation and Secondary Barrier Installation
Section
Chapter
Fit-up
Locking plate Appearance
Spot weld of 50 32 2 mm
locking plate secured by spot weld
Allowable
0 + 0.5 mm
Recommended
+0.3 + 0.5 mm
Between 0 mm and
Final leveling
+0.5 mm
Installation of
secondary boxes
NO 96 Systems
P/R
in flat panel area Tack weld of screw Appearance
(contd)
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
border boxes Out of plane 1.5 mm/1 m
Step with
0.5 mm
composite beam
2-2
85
86
TABLE 4 (continued)
NO 96 System Secondary Insulation and Secondary Barrier Installation Section
Chapter
Thickness 15 mm
Spacing between
Between 58 and 62 mm
boxes
Alignment of
1.5 mm
T groove
Between 2 and 3 mm H
Gap between boxes (3.5 mm for ceiling/bottom
boxes)
Secondary
insulation boxes Step between two
0.7 mm
final inspection boxes
Membrane LNG Carriers Cargo Containment Systems
Step between
transverse. border 0.5 mm
boxes
Out of plane of
transverse. border 0.6 mm/1 m H
boxes
Offset of
transverse. border
0.5 mm
boxes and Invar
tube
2-2
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 4 (continued)
NO 96 System Secondary Insulation and Secondary Barrier Installation
Section
Chapter
Step between
longitudinal. border 0.7 mm
boxes
Secondary Out of plane of
insulation boxes longitudinal. border 1.5 mm/1 m H
final inspection boxes
(contd) Offset of
longitudinal. border
1.5 mm
NO 96 Systems
a
Max 2.5 mm
Max 4 mm
3<R<4
Radius of raised a = 90 +1.5
0 3 mm r 4 mm
edge
Membrane flanging 2 meters 0.5 m
2* m test specimen Difference of raised Maximum deflection of the test sample Raised edges difference allowance P
1.5 mm
(2 times per tank) edge height 2 meters
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Width of strake 498.2 0.2 mm
0 < 2 mm
87
88
TABLE 4 (continued)
NO 96 System Secondary Insulation and Secondary Barrier Installation Section
Chapter
Visual inspection
test specimen P
(300 mm)** Metallographic test
Position of weld
12 mm L*** 14 mm
beads
Overlap between
10 mm L 30 mm
two beads
Aspect of weld
No defect
bead
Distance between
axis cutting and 20 mm
seam weld
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 4 (continued)
NO 96 System Secondary Insulation and Secondary Barrier Installation
Section
Chapter
Installation and
welding of strake ue
R
tong
end ous abt) L
c ontinu 20 (
m
0.5 m ing
Weld R100
TIG ce No visible defects
istan
Res Weld
e a m
S
160 for 45 strake-end (abt)
160 for 90 strake-end (abt)
Welding
R100
40 min 20 min
+2
12 0
10 min
Arch deflection 2 mm/2 m
Counter arch
0 mm/2 m
deflection
Corner strake shop Straightness of
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
test of uncoiling 2mm/7 m
raised edges P
machine (7 m
sample)* Edge folding radius 2.5 mm r 3.5 mm
Height of raised
20 mm 1 mm
edges
Surface condition No defect
89
90
TABLE 4 (continued)
NO 96 System Secondary Insulation and Secondary Barrier Installation Section
Chapter
between
Welding R
longitudinal
composite beams DPT: 100%
No visible defects
Connection
between pump
Welding H
tower base and
membrane
DPT: 100%
Visual inspection
Membrane LNG Carriers Cargo Containment Systems
Collar studs
specimen test P
before welding
Metallographic test
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 4 (continued)
NO 96 System Secondary Insulation and Secondary Barrier Installation
Section
Chapter
M18
Off center: 3.5 mm
Installation
Strake overlap: 2.5 mm
Collar stud 2.5 R
installation
No visible defect
d 3.5
Welding
NO 96 Systems
Membrane repairs H
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
2-2
91
92
TABLE 5
NO 96 System Secondary Membrane Tightness Tests Section
Chapter
Mechanical test of
Stress test H
welding joints
Absence of defects
2-2
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 5 (continued)
NO 96 System Secondary Membrane Tightness Tests
Section
Chapter
No visible defects
Welding
DPT: 100%
Repairs of defects H
Helium test As above
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Maximum temperature variation: 1C
2-2
93
94
TABLE 6
NO 96 System Primary Insulation and Primary Installation Section
Chapter
Secondary
No defects
membrane surface
Maintenance of Pressure: between
Preparation of
insulation space
secondary 500 and 800 mbar
vacuum
J = 0.7 mm max
membrane for P
installation of Gap between
primary insulation secondary
0.7 mm
membrane and
NO 96 Systems
Lengthwise gap
3 mm
between boxes
Crosswise gap
14 mm P/R
between boxes
Insulation fitting of
Appearance
between boxes
Installation of
primary boxes Plywood bridge
+0.7 mm/1 mm
step with box
Membrane LNG Carriers Cargo Containment Systems
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 6 (continued)
NO 96 System Primary Insulation and Primary Installation
Section
Chapter
dihedral
Box bearing Clamping tool Appearance
Screwing of box to
Appearance
Invar wing
Installation of the Offset between bias
10 mm/(7%)
primary transverse wedges P/R
corners Confirm installation of
Connection of thermal protection
Invar tube and
No welding visible defects
trihedron
DPT: 100%
Installation of box
Appearance
type 3
Appearance of beam
screwing
3A
Membrane LNG Carriers Cargo Containment Systems
Installation of the
primary Installation of 3A Local gap of bearing:
composite beams 1 mm P/R
longitudinal
corners
Gap between prefabricated
beams: 10 mm
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
1A
95
96
TABLE 6 (continued)
NO 96 System Primary Insulation and Primary Installation Section
Chapter
Fiberglass fitting in
NA
Invar tube
Installation of tank
Pillar plate head
1 longitudinal No visible defects
welding
oblique dihedral
NO 96 Systems
Plywood bridge
Invar Stapling
1B 3B tube 8 staples per meter
Stapling LG
8 staples per m
8B 9B 7B U6B 3B Max gap 3 mm LB
7B
6B 9B 1B
Installation of 8B
plywood bridges at P/R
corners
Plywood bridge
Membrane LNG Carriers Cargo Containment Systems
3A
Gap 3A
3 mm
1A
1A
No visible defects
Surface condition No protruding stapling
Secondary
No glue
insulation boxes H
final inspection Step between two
0.7 mm
boxes
Out of plane 1.5 mm/1 m
2-2
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 6 (continued)
NO 96 System Primary Insulation and Primary Installation
Section
Chapter
3 mm (length)
Gap between boxes
5 mm (cross)
Step on bridge Between +0.7 mm/1 mm
Offset between box
1.5 mm
and Invar tube
Secondary Out of plane of
insulation boxes transverse. border 0.7 mm/1 m
H
NO 96 Systems
Check clipping of
Fitting of sliding
continuous tongue
tongues in the Stapling and appearance P
to non continuous
boxes
tongues
Step 1 Step 2 Step 3
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
1.5 mm
edge height
Width of strake 498.2 0.2 mm
Surface condition No visible defect
Raised edge angle 90 + 1.5/ 0
97
98
TABLE 6 (continued)
NO 96 System Primary Insulation and Primary Installation Section
Chapter
Visual inspection
welding test P
specimen (300 mm) Metallographic test
Position of weld
12 mm L* 14 mm
beads
Overlap between
10 mm L 30 mm
two beads
Aspect of weld bead No defect
Resistance welding Offset of two beads 1 mm
of membrane Distance from 90 P/R
strakes L = 160 mm
strake end
Distance from 45
L = 100 mm
strake end
Distance between
axis cutting and 20 mm
seam weld
Membrane LNG Carriers Cargo Containment Systems
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
* L = distance from strake edge
TABLE 6 (continued)
NO 96 System Primary Insulation and Primary Installation
Section
Chapter
edges
Surface condition No defect
Corner strake Visual inspection
welding test
P
specimen
(200 mm)* Metallographic test
No visible defects
Corner strake
Welding DPT: 100% manual, 20% P/R
installation
automatic
Overlap pieces
between
Welding No visible defects P/R
longitudinal
composite beams
Connection DPT: 100%
between pump
Welding H
tower base and
No visible defects
Membrane LNG Carriers Cargo Containment Systems
membrane
Final inspection of Complete
No visible defects H
the membrane membrane
Visual inspection No defects
Membrane repairs H
Welding DPT: 100%
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
* Every third joint for symmetrical welds,
Every joint for non-symmetrical welds,
At every change of equipment
2-2
99
TABLE 7
100
NO 96 System Primary Membrane Tightness and Final Tests Section
Chapter
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 7 (continued)
NO 96 System Primary Membrane Tightness and Final Tests
Section
Chapter
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
2-2
101
This Page Intentionally Left Blank
Section 3: CS1 Systems
1 CS1 Systems
CS1 is a combination of the Mark III system and the NO 96 system.
2-3/Figures 1 and 2 are sketches showing the design principle and the typical transverse corner assembly
of the GTT CS1 membrane system.
The insulation and the secondary membrane are of construction similar to the Mark III system
(polyurethane foam and triplex, glued assembly), while the primary membrane closely resembles the
NO 96 system (Invar). The corner assembly of the CS1 system is similar to the NO 96 system corner
assembly utilizing Invar tubes.
FIGURE 1
GTT CS1 Membrane Containment System
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 103
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 3 CS1 Systems 2-3
FIGURE 2
Typical Transverse Corner Arrangement for CS1 System
TYPICAL TRANSVERSE
CORNER ARRANGEMENT
Reinforced Foam
Glass wool
Plywood
60 450
95
285
190
10
600
104 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 2 Membrane LNG Carriers Cargo Containment Systems
Section 3 CS1 Systems 2-3
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 105
TABLE 1
106
CS1 System Components Materials Section
Chapter
Physical Properties
Reinforced PUF
Mechanical Characteristics Designers/Manufacturers specifications TA/R/MA
Foam
Thermal Properties
Physical Properties
Triplex Designers/Manufacturers specifications TA/R/MA
Mechanical Characteristics
Physical Properties
CS1 Systems
* For pictures and sketches please refer to the Tables relative to Mark III (Chapter 2, Section 1) and NO 96 systems (Chapter 2, Section 2), as applicable for CS1 system.
** To be ABS certified
Membrane LNG Carriers Cargo Containment Systems
2-3
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 2
CS1 System Components Fabrication
Section
Chapter
Squareness
exceed 1.0 mm by meter of length
* For pictures and sketches please refer to the Tables relative to Mark III (Chapter 2, Section 1) and NO 96 systems (Chapter 2, Section 2), as applicable for CS1 system.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
107
2-3
TABLE 2 (continued)
108
CS1 System Components Fabrication Section
Chapter
* For pictures and sketches please refer to the Tables relative to Mark III (Chapter 2, Section 1) and NO 96 systems (Chapter 2, Section 2), as applicable for CS1 system.
** May be R, if TA
2-3
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 2 (continued)
CS1 System Components Fabrication
Section
Chapter
R
Visual inspection of TIG welding:
no visible defects
Dye penetrant test: minimum 10%
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
* For pictures and sketches please refer to the Tables relative to Mark III (Chapter 2, Section 1) and NO 96 systems (Chapter 2, Section 2), as applicable for CS1 system.
** May be R, if TA
109
2-3
TABLE 3
110
CS1 Cargo Containment System Insulation Installation
Section
Chapter
L B D: 80 mm MA
Bulkhead: +80 mm, 40 mm
Hold measurement Main dimensions
Ceiling length: 40 mm NA
Ceiling width: +80 mm, 40 mm
Offset of inner hull stiffeners Max offset: 4 mm/3 m
Inner hull flatness Deformation of plating between P
CS1 Systems
Perpendicularity Inclination: 2
Visual examination
Sample tests of 4 studs at each
Tensile test: 800 kg P
shift
Stud-bolts welding Bending test: 90
Soundness: 100% with mallet
Visual examination P/R
Undercut: 0.5mm
Flat panels (10 studs per day at
random)
Studs tensile test 800 kg no failure P
Corner panels (first 100 studs,
than 10% random)
* For pictures and sketches please refer to the Tables relative to Mark III (Chapter 2, Section 1) and NO 96 systems (Chapter 2, Section 2), as applicable for CS1 system.
2-3
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 3 (continued)
CS1 Cargo Containment System Insulation Installation
Section
Chapter
P
Contact with wedges Appearance
Mastic curing Appearance
Cylindrical foam
Protrusion +0 mm, 2 mm P
plug
Gaps between Filling +0 mm, 5 mm, Gap 3 mm
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
R
panels Joint filler and flat joint flatness 1.5 mm
Final inspection of
100% visual H
panel installation
* For pictures and sketches please refer to the Tables relative to Mark III (Chapter 2, Section 1) and NO 96 systems (Chapter 2, Section 2), as applicable for CS1 system.
111
2-3
TABLE 3 (continued)
112
CS1 Cargo Containment System Insulation Installation
Section
Chapter
* For pictures and sketches please refer to the Tables relative to Mark III (Chapter 2, Section 1) and NO 96 systems (Chapter 2, Section 2), as applicable for CS1 system.
2-3
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 3 (continued)
CS1 Cargo Containment System Insulation Installation
Section
Chapter
* For pictures and sketches please refer to the Tables relative to Mark III (Chapter 2, Section 1) and NO 96 systems (Chapter 2, Section 2), as applicable for CS1 system.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
113
2-3
TABLE 4
114
CS1 Cargo Containment System Membrane Installation Section
Chapter
Deflection 4 mm/2 m
Number of folds 3 folds/2 m
Height of folds 1.5 mm
Membrane flanging
2** m test Radius of raised edge 3 mm r 4 mm
P
specimen (2 times Difference of raised edge height 1.5 mm
per tank)
Width of strake 498.2 0.2 mm
Raised edge angle 90 + 1.5/ 0
Surface condition No visible defect
Strake end
Distance from invar tube 430 mm + 0 mm/ 1.5 mm P
positioning
Check of tongue and raised
Appearance
Spot weld of edges
P
strakes Application (bearing) defect 1.5 mm
Opening 3.2 mm
Membrane LNG Carriers Cargo Containment Systems
* For pictures and sketches please refer to the Tables relative to Mark III (Chapter 2, Section 1) and NO 96 systems (Chapter 2, Section 2), as applicable for CS1 system.
** 7 m for new machine test specimen
2-3
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 4 (continued)
CS1 Cargo Containment System Membrane Installation
Section
Chapter
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
* For pictures and sketches please refer to the Tables relative to Mark III (Chapter 2, Section 1) and NO 96 systems (Chapter 2, Section 2), as applicable for CS1 system.
** New machine only
*** Every third joint for symmetrical welds,
Every joint for non-symmetrical welds,
At every change of equipment
115
2-3
TABLE 4 (continued)
116
CS1 Cargo Containment System Membrane Installation Section
Chapter
the membrane
Visual inspection No defects
Membrane repairs H
Welding DPT 100%
* For pictures and sketches please refer to the Tables relative to Mark III (Chapter 2, Section 1) and NO 96 systems (Chapter 2, Section 2), as applicable for CS1 system.
Membrane LNG Carriers Cargo Containment Systems
2-3
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
TABLE 5
CS1 System Primary Membrane Tightness and Final Tests
Section
Chapter
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
test Large repair areas Helium test
117
2-3
TABLE 5 (continued)
118
CS1 System Primary Membrane Tightness and Final Tests Section
Chapter
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 3: LNG Carriers Cargo Handling Systems
CONTENTS
SECTION 1 Common Features for All LNG Carrier Types .................123
1 Typical Cargo Handling System ........................................123
1.1 General Considerations ................................................ 123
1.2 Typical Cargo Handling System Description ................. 123
2 Typical Cargo Handling System Pipe Lines.......................124
2.1 Main Cargo Handling System Lines .............................. 124
2.2 Common Features of Piping Systems........................... 125
3 Typical Components of LNG Carriers Cargo Handling
System ...............................................................................126
3.1 Cargo Tank Venting and Relief Systems ...................... 126
3.2 Cargo Pumps ................................................................ 126
3.3 Cargo Compressors ...................................................... 126
3.4 Boil-off/Warm-up Heaters.............................................. 127
3.5 LNG Main Vaporizers.................................................... 127
3.6 Forcing Vaporizer.......................................................... 127
3.7 Mist Separator............................................................... 127
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 119
FIGURE 1 Interbarrier and Insulation Spaces Pressurization
and Inerting System .................................................130
FIGURE 2 Typical Cofferdam Heating System .........................131
FIGURE 3 Reliquefaction Plant .................................................133
FIGURE 4 Gas Combustion Unit for Dual Fuel Diesel Engine
Option.......................................................................133
120 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
11 Inspection Requirements for Cargo Handing Systems
and Gas Management Systems ........................................141
11.1 Inspection Requirements for Machinery and
Equipment ..................................................................... 141
11.2 Inspection Requirements for Machinery, Equipment
and Systems During and After Installation Onboard ..... 150
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 121
This Page Intentionally Left Blank
Section 1: Common Features for All LNG Carrier Types
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 123
Chapter 3 LNG Carriers Cargo Handling Systems
Section 1 Common Features for All LNG Carrier Types 3-1
FIGURE 1
Typical Cargo Handling System for Membrane LNG Carrier
LNG MANIFOLD TYPICAL LNG CARGO HANDLING
Z1
Z1
SYSTEM
Z1
Z1
Z1
Z1
VAPOR MANIFOLD
NITROGEN LINE
VENT MAST Nr. 1
Z1
Z1
Z1
Z1
Z1
Z1
Z1
GAS MAIN
VAPOR MAIN
LNG MAIN
SPRAY MAIN
Z1
Z1
ELECTRIC MOTORS ROOM
VAPOR LINE
Z1
SPRAY LINE
Z1
Z1
M L
VAPORIZER
VAPORIZER
E
FORCING
Z1
Z1 Z1
Z1
LNG
DEMISTER
Z1 BOIL-OFF TO SPRAY NOZZLE
ENGINE ROOM
TANK
HEATER
HEATER
Z1
H = HIGH DUTY COMPRESSOR
M H L = LOW DUTY COMPRESSOR
E M = ELECTRIC MOTOR
Z1
CARGO
EMERGENCY PUMP PIPE
Z1
Z1
Z1
COMPRESSOR
M H ROOM FILLING LINE
E
CARGO PUMP
SPRAY/STRIPPING PUMP
124 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 3 LNG Carriers Cargo Handling Systems
Section 1 Common Features for All LNG Carrier Types 3-1
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 125
Chapter 3 LNG Carriers Cargo Handling Systems
Section 1 Common Features for All LNG Carrier Types 3-1
All sections of piping related to cargo handling systems that can be isolated, and thus possibly
trapping liquid between closed valves, are to be provided with safety valves that relieve excess
pressure to the nearest vapor dome.
Blank flanges and sample points are to be fitted in the various lines so as to facilitate inerting,
purging, cooling and aeration of the system during repairs.
All sections of the liquid line outside the cargo tanks are to be insulated with rigid polyurethane foam
covered with a molded GRP (glass reinforced plastic) surface treatment. The surface treatment is to
act as a tough water and vapor tight barrier. In some cases the pipes may be insulated with two layers
of insulating material with the tight barrier in between.
126 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 3 LNG Carriers Cargo Handling Systems
Section 1 Common Features for All LNG Carrier Types 3-1
An automatic surge control system is provided for each compressor to ensure that the compressor
flow rate does not fall below the designed minimum.
Inlet guide vanes are fitted at the suction end of each compressor to achieve the required gas flow.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 127
This Page Intentionally Left Blank
Section 2: Features Which Are Not Common to All LNG Carrier Types
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 129
Chapter 3 LNG Carriers Cargo Handling Systems
Section 2 Features Which are Unique to Membrane Tank LNG Carriers 3-2
FIGURE 1
Interbarrier and Insulation Spaces Pressurization and Inerting System
Opening Impulse if
P 2 mb pres. gauge Excess Air
To the nearest Tank Vent Mast
3-Way Generator N. 2
Delivery P P
Valve
To Engine Room
Nitrogen Purging Generator N. 1
O Cooling Unit
12 m3 Air Compressor
7 bar Nitrogen Generators
N2 Gas Storage Tank 2 65 Nm3/h
Opening Impulse if To the
P 2 mb pres. gauge nearest
2 1100 m3/h
Tank Vent NITROGEN GAS GENERATORS ALTERNATIVE
Mast
3"
3"
3"
T P
From
Vacuum Pumps Cross-Over
4
P
4"
4"
4"
Opening Set-Point
4"
6"
4"
4"
10 mb pres. gauge
4"
6"
Primary
Water Draining
Insulation
Pump Wol
Venting Mast
6" 6"
130 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 3 LNG Carriers Cargo Handling Systems
Section 2 Features Which are Unique to Membrane Tank LNG Carriers 3-2
FIGURE 2
Typical Cofferdam Heating System
From cargo motor To cargo motor
room glycol room glycol
Gycol water A system heater heater
Gycol water B system
Heater B Heater A
Heater B Heater A
2 Pump Towers
2.1 General
As the cargo and stripping pumps used for LNG carriers are of the submerged type and since the
internal surface of most of the LNG tanks is smooth and without possible attachment point for the
pumps and their relative pipes and appurtenances, it is necessary to install a special structure inside
the tank, which provides support for the pumps and piping systems.
Pump towers are designed to hang from the liquid dome and have bottom sliding supports provided in
such a way as to permit to the tower vertical movements during its cyclical elongations and shrinkages
due to tank warming- up and cool-down, while restraining horizontal movement of the tower.
The purpose of the pump tower is not only to support the pumps and to provide the necessary risers,
but it is also to support the tank access ladder and other piping and instrumentation equipment.
The instrumentation includes temperature and level sensors, independent high level alarm sensors and
cargo pump electric cables.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 131
Chapter 3 LNG Carriers Cargo Handling Systems
Section 2 Features Which are Unique to Membrane Tank LNG Carriers 3-2
The pump towers are fabricated of stainless steel and are designed in triangular boom sections with
three chords, lacings, stringers, platforms, piping supports. The base section serves to provide a
foundation of the pumps as well as to ensure the vertical alignment of tower.
As already mentioned, the chords are utilized for two distinct purposes; first, these constitute the main
structural members of the pump tower and secondarily as discharge piping for the main and
emergency cargo pumps. Chords are supported by horizontal braces and diagonal lacings, which are
saddle fit and welded to main chords.
132 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 3 LNG Carriers Cargo Handling Systems
Section 2 Features Which are Unique to Membrane Tank LNG Carriers 3-2
FIGURE 3
Reliquefaction Plant
2 low duty
The system consists of: compressors Cold box
(plate fin heat exchanger)
y Cargo cycle
VENT
y Nitrogen cycle
BOG FEED
MAX
y Auxiliaries MAX
MIN
MIN
PX
Separator
RECYCLING
COOLING LC
WATER
2 3 BY-PASS
1 E
TO TANKS
SUCTION THROTTLE
3 stage N2 centrifugal
compressor with
expander
Reliquefaction plants are installed on the deck above the cargo tanks. Attention is to be paid to the
segregation of the safe areas from the hazardous areas.
TT
2 COMBUSTION
AIR FANS
(each 60% capacity)
BURNER
DUTY/STANDBY
RELIEF VALVE COMPRESSORS
GAS VALVE TRAINS IN
SET @ 0.225 BarG
VENTILATED ENCLOSURE
HEATER PT
BOIL
OFF
GAS
(BOG) 4.5 BarG
DUAL HIGH BOG FLOW RANGE
PT
FUEL
-40C
ENGINE
LNG FORCING
VAPORISER
DUAL
FUEL
FREEFLOW BYPASS
TANK ENGINE
DUAL
FUEL
MDO SUPPORT
ENGINE LOW BOG FLOW RANGE
DUAL
LNG
FUEL FREEFLOW BYPASS
ENGINE
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 133
Chapter 3 LNG Carriers Cargo Handling Systems
Section 2 Features Which are Unique to Membrane Tank LNG Carriers 3-2
134 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Section3:SummaryofSurveys tobe Carried OutDuringConstructionandInstallationofLNGCarriers CargoHandlingSystems
1 General Considerations
1.1 Scope
General considerations applicable to hull surveys on LNG carriers under construction also apply to
machinery surveys. All machinery and equipment, which are subject of class, are to be surveyed and
functionally tested after installation or during sea/gas trials. Machinery and equipment, which are
subjects of class, are to be properly certified in accordance with the standard ABS Rules and Procedures.
1.2 Exclusions
This Section does not cover the certification, installation and testing of the machinery, equipment and
systems that are not related to cargo handling and typical operations of LNG carriers. For these
systems, and for the equipment which are part of them, reference should be made to the standard ABS
inspection and testing procedures.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 135
Chapter 3 LNG Carriers Cargo Handling Systems
Section 3 Summary of Surveys to be Carried Out During Construction and Installation of
LNG Carriers Cargo Handling Systems 3-3
136 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 3 LNG Carriers Cargo Handling Systems
Section 3 Summary of Surveys to be Carried Out During Construction and Installation of
LNG Carriers Cargo Handling Systems 3-3
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 137
Chapter 3 LNG Carriers Cargo Handling Systems
Section 3 Summary of Surveys to be Carried Out During Construction and Installation of
LNG Carriers Cargo Handling Systems 3-3
Alternatively, the function of one of the valves in series and the vent valve can be incorporated into
one valve body so arranged that, when one of the above conditions occurs, flow to the gas utilization
unit will be blocked and the vent opened. The three shutoff valves should be arranged for manual
reset.
6.1 Actuators
Spring-loaded, single-acting actuators operating on the principles of pressure to open, spring to
close are considered to be the fail-safe type.
Where double acting actuators are fitted, there is to be a single accumulated motive power provided at
each valve which will, without recharging, close each valve upon activation of the emergency
shutdown (ESD) system. One accumulator may serve more than one valve if the valves are located in
the same area such as the cargo manifold.
7 Pump Towers
138 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 3 LNG Carriers Cargo Handling Systems
Section 3 Summary of Surveys to be Carried Out During Construction and Installation of
LNG Carriers Cargo Handling Systems 3-3
Particular care is to be paid to check the installation of the pump tower support at the bottom of the
tank. In particular, the in-plane alignment of the upper face of the support is to be checked after
installation. The accuracy of the construction and installation of the support should be verified to be in
accordance with the tolerances established by the designer and the shipyard.
After installation of the pump tower, the clearances of the pumps inlets from the tank bottom and the
distances of certain selected points of the tower from the adjacent bulkhead and/or bottom should be
recorded and referenced during subsequent surveys. These recorded values, are to be used to confirm
that no subsequent permanent deformation of the tower have been induced by the loads (sloshing) that
the tower had to withstand during its service.
8 Instrumentation
8.1 Gauges
Each cargo tank is to be provided with gauges to indicate the level, pressure and temperature of the
cargo. In addition pressure gauges and temperature indicating devices should be installed in the liquid
and vapor piping systems, in the cargo refrigerating installations, and the inert gas system.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 139
Chapter 3 LNG Carriers Cargo Handling Systems
Section 3 Summary of Surveys to be Carried Out During Construction and Installation of
LNG Carriers Cargo Handling Systems 3-3
10 Miscellaneous Systems/Equipment
140 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 3 LNG Carriers Cargo Handling Systems
Section 3 Summary of Surveys to be Carried Out During Construction and Installation of
LNG Carriers Cargo Handling Systems 3-3
Even though this is not a particular requirement for LNG carriers, it is stressed and important to verify
on board the fire control plans and safety plan against the location, condition and data of the approved
equipment, with particular reference to: all items of fire fighting, fire detection, safety equipment
(including emergency escape route breathing apparatus (EEBD).
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 141
Chapter 3 LNG Carriers Cargo Handling Systems
Section 3 Summary of Surveys to be Carried Out During Construction and Installation of
LNG Carriers Cargo Handling Systems 3-3
TABLE 1
Inspection Requirements for Machinery and Equipment
Item Inspection Requirements Remarks Sketch/Photo
142 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 3 LNG Carriers Cargo Handling Systems
Section 3 Summary of Surveys to be Carried Out During Construction and Installation of
LNG Carriers Cargo Handling Systems 3-3
TABLE 1 (continued)
Inspection Requirements for Machinery and Equipment
Item Inspection Requirements Remarks Sketch/Photo
DA is not required if in
compliance with
recognized Standards
Valves for cargo system
(working temp. range DA, MT, FS, OB, MD
163C to +80C) FS refers to type test
(tightness test for all types
and all dimensions of
valves
DA is not required if in
Safety valves for cargo
DA, FS, OB, MD compliance with
tank and insulation space
recognized Standards
DA is not required if in
Safety valve for cargo line DA, FS, OB, MD compliance with
recognized Standards
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 143
Chapter 3 LNG Carriers Cargo Handling Systems
Section 3 Summary of Surveys to be Carried Out During Construction and Installation of
LNG Carriers Cargo Handling Systems 3-3
TABLE 1 (continued)
Inspection Requirements for Machinery and Equipment
Item Inspection Requirements Remarks Sketch/Photo
DA is not required if in
Control valve for cargo
DA, FS, OB, MD compliance with
system
recognized Standards
DA is not required if in
Control valve for glycol
DA, OB, MD compliance with
heating system
recognized Standards
Cargo pipe insulation OB, MD
Emergency shut-down
system and safety system OB, MD
components
Gas detection system
OB, MD
components
Water drain pump (for
pumping out drain water
OB, MD
from secondary insulation
space)
Custody transfer system
OB, MD
components
Float type level gauge for
DA, OB, MD
cargo tank
Temperature pressure
sensor components
installed in secondary
OB, MD
insulation space, water
ballast tanks, cofferdam,
etc.
DA is limited to
Water detectors in
DA, OB, MD intrinsically safety aspects
insulation space
only
Valve remote control
system for cargo and OB, MD
ballast system
Compliance with Rule
requirement is to be
Cryogenic cargo hose for
MD demonstrated sending
ship to ship cargo transfer
proper documentation to
Engineering office
Fender for ship to ship
MD
system
Bellows for cargo lines DA, FS, OB, MD
Pipes for cargo lines If design T < 110C, a
(working temp. range complete stress analysis
DA, MT, MS, FS, OB
for piping system is to be
163C to +80C)
submitted
Pipes exceeding 10.3 bar
pressure for insulation
space pressurization MT, MS, FS, OB
(working temp. range
50C to +80C)
Pipes not exceeding 10.3
bar pressure for insulation
space pressurization OB, MT
(working temp. range
50C to +80C)
144 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 3 LNG Carriers Cargo Handling Systems
Section 3 Summary of Surveys to be Carried Out During Construction and Installation of
LNG Carriers Cargo Handling Systems 3-3
TABLE 1 (continued)
Inspection Requirements for Machinery and Equipment
Item Inspection Requirements Remarks Sketch/Photo
Pipes exceeding 10.3 bar
pressure for cofferdam
heating system (working MT, MS, FS, OB
temp. range 50C to
+80C)
Pipes not exceeding 10.3
bar pressure for cofferdam
heating system (working OB, MT
temp. range 50C to
+80C)
Pipe fittings (elbow, DA is not required if in
reducer, tee, flange) DA, OB, MD compliance with
for cargo line recognized Standards
Gasket for cargo line OB, MT
Bolt/nut for cargo line MT
DA is limited to
Flow-meter for cargo
DA, OB, MD intrinsically safety aspects
system
only
Spray nozzle for cargo
OB, MT
tank cooling-down
Strainer for cargo pipe They are also to be
(manifold, spray line and OB, MT checked according to
cargo comp. inlet) pressure vessels
Strainer for control air and
N2 gas (cargo comp. OB, MT
sealing, T.N.)
SOLAS requirement EC
Personal protection
RA flag ships are subject to
equipment
MED Directive
SOLAS requirement EC
Breathing apparatus and
RA flag ships are subject to
clothing, etc.
MED Directive
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 145
Chapter 3 LNG Carriers Cargo Handling Systems
Section 3 Summary of Surveys to be Carried Out During Construction and Installation of
LNG Carriers Cargo Handling Systems 3-3
TABLE 2
Inspection Requirements for Electrical and Automation Components
Item Inspection Requirements Remarks Sketch/Photo
Ship/shore communication
MD
system components
Lighting fixtures for
To be certified by an
hazardous areas (explosion MD
Authorized Organization
proof)
Safe certified electric
To be certified by an
apparatus for hazardous MD
Authorized Organization
areas
Cargo control Room
DA, FS, OB
Console
DA is limited to
Electric temperature and
DA, OB, MD intrinsically safety aspects
pressure sensors
only
DA is limited to
Electric and electronic
DA, OB, MD intrinsically safety aspects
level sensors
only
Electric motors > 100 kW
for LNG cargo or vapor DA, FS. OB
handling services
146 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 3 LNG Carriers Cargo Handling Systems
Section 3 Summary of Surveys to be Carried Out During Construction and Installation of
LNG Carriers Cargo Handling Systems 3-3
TABLE 3
Inspection Requirements for Means for Boil-off Disposal
and Gas Combustion Units
Item Inspection Requirements Remarks Sketch/Photo
As per standard
LNG separators (where
requirements for pressure
fitted)
vessels
DA not required, anyway
detailed drawings showing
Refrigerant compressors/ materials and geometry of
FS, OB
expanders the equipment to be
included for reference
purposes
As per standard
Cryogenic heat exchanger/
requirements for pressure
cold box
vessels
As per standard
Refrigerant sea water
requirements for pressure
cooler
vessels
As per standard
Refrigerant accumulators requirements for pressure
vessels
LNG return to cargo tank
DA, MT, MS, FS, OB
piping system
Re-liquefaction control
DA, FS, OB
system
Gas burner unit including
OB, MT
oil pilot burner
Burner management
DA, FS, OB
system
Combustion chamber and
OB, MD
associated refractory
Forced draft fans and
OB, MD
dilution fans
Exhaust trunk FS, OB, MD
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 147
Chapter 3 LNG Carriers Cargo Handling Systems
Section 3 Summary of Surveys to be Carried Out During Construction and Installation of
LNG Carriers Cargo Handling Systems 3-3
TABLE 4
Inspection Requirements for Means for Boil-off Dual Fuel Engines
Item Inspection Requirements Remarks Sketch/Photo
Gas valve enclosure OB, MD
As per standard
Gas storage pressure
requirements for pressure
vessels
vessels
As per standard
Dual fuel diesel engine requirements for pressure
vessels
Crankcase, inlet manifold
If not in compliance with a
and exhaust manifold
FS recognized standard it
explosion protection
should be also DA
systems
148 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 3 LNG Carriers Cargo Handling Systems
Section 3 Summary of Surveys to be Carried Out During Construction and Installation of
LNG Carriers Cargo Handling Systems 3-3
TABLE 5
Inspection Requirements for Means for Boil-off Dual Fuel Gas Turbines
Item Inspection Requirements Remarks Sketch/Photo
Gas valve enclosure OB, MD
As per standard
Gas storage pressure
requirements for pressure
vessels
vessels
Dual fuel gas turbine DA, MT, MS, FS, OB
Gas turbine enclosure
DA
ventilation system
Gas turbine enclosure fire
DA
fighting system
Dual fuel gas turbine
DA, MS, FS, OB
(package)
Gas turbine combustion
DA, OB Design verification only
air supply ducting
Gas turbine exhaust
DA, OB Design verification only
system
Gas turbine combustion
DA, FS, OB
control system
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 149
Chapter 3 LNG Carriers Cargo Handling Systems
Section 3 Summary of Surveys to be Carried Out During Construction and Installation of
LNG Carriers Cargo Handling Systems 3-3
11.2 Inspection Requirements for Machinery, Equipment and Systems During and
After Installation Onboard
The following table is a list of items (plants, systems, installations, operations) that are in general inspected
during the outfitting of a todays Standard LNG carrier after completion of hull construction and
cargo containment system installation.
This table is given as an example only and to provide guidance to the Surveyor on the inspection
requirements for the typical equipment used for LNG carriers. Considering the variety of machinery
and equipment, the large number of manufacturers and sub-contractors and the different shipyards
procedures, it is considered impossible to prepare typical inspection plans, including acceptance
criteria, for each of item. For this reason the following tables are only intended to list the essential
requirements of attendance to the various tests, trials and commissioning. The inspections are to be
carried out in accordance with ABS Rules and are following inspection plans and, for the most
complex systems, test memoranda prepared by the shipyard, manufacturer and/or sub-contractors and
agreed with ABS.
The Tables below include only those machinery, equipment and systems, which are connected with
the Cargo Handling and Gas Management Systems. All other machinery, equipment and systems,
essential for ship propulsion, operation and safety (such as propulsion and fire fighting systems) are
not listed in the following table. Reference should be made to the ABS Rules and procedures
applicable to all the vessels.
The following symbols are used in the Table:
I Inspection required
R Random inspection or inspection of selected samples by ABS Surveyor
P As part of the ABS Surveyors patrolling activity
S To be inspected by the Shipyard Quality Assurance/Quality Control Department and
relative inspection reports should be made available to ABS Surveyor, if requested
150 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 3 LNG Carriers Cargo Handling Systems
Section 3 Summary of Surveys to be Carried Out During Construction and Installation of
LNG Carriers Cargo Handling Systems 3-3
TABLE 6
Inspection Requirements for Machinery, Equipment and Systems
During and After Installation Onboard
Activity Inspection Remarks
Rules do not require leak test. Leak test will be verified by QM and
Inert gas system pipe leak test S/R
Surveyor can monitor leaks during capacity test or operational test.
As part of patrolling activity if cable is accessible at all time Shipyard
Cable trunk installation inspection I/P to give notification of work progress to Class for scheduling patrol
inspections.
As part of patrolling activity if cable is accessible at all time Shipyard
Cargo area cable installation inspection I/P to give notification of work progress to Class for scheduling patrol
inspections
As part of patrolling activity if cable is accessible at all time Shipyard
Passage way cable installation inspection I/P to give notification of work progress to Class for scheduling patrol
inspections
Duct keel cable installation inspection I
Shipyard shall provide a list of the installed equipment, including up to
Hazardous area electrical equipment
R/P date certificates for the installed equipment. Surveyor will perform
confirmatory inspection
random checks to confirm
Insulation resistance measurement R/P Record to be submitted
As part of patrolling activity if cable is accessible at all time Shipyard
Cofferdam cable installation inspection I/P to give notification of work progress to Class for scheduling patrol
inspections.
As part of patrolling activity if cable is accessible at all time Shipyard
Motor/compressor room for cargo system
I/P to give notification of work progress to Class for scheduling patrol
cable installation inspection
inspections.
As part of patrolling activity if cable is accessible at all time Shipyard
Trunk deck space cable installation
I/P to give notification of work progress to Class for scheduling patrol
inspection.
inspections.
Cargo hold temperature sensor cable
I It may be included in the cargo containment system inspections.
installation inspection.
High voltage cable test I
As part of patrolling activity if cable is accessible at all time or
Cargo pump tower cable installation
I/P alternatively as part of official pump tower inspection, prior to
inspection.
installation of pump tower in cargo tank.
Installation inspection may be performed at same time as hydrotest or
Deck steam and conditioning system pipe
I air test as applicable. Access to all parts of the piping system shall be
hydrotest and installation
provide to allow proper inspection
Installation inspection may be performed at same time as hydrotest or
Valve remote control system pipe
I air test as applicable. Access to all parts of the piping system shall be
hydrotest (main line) and installation
provide to allow proper inspection
Installation inspection may be performed at same time as hydrotest or
Cofferdam and liquid dome heating coil
I air test as applicable. Access to all parts of the piping system shall be
hydrotest and installation
provide to allow proper inspection
Cargo line (SUS) welding inspection I
Liquid/spray line pipe leak test (1bar) I
Insulation barrier N2 pressurization pipe
I
leak test (1bar)
Gaseous pipe bellows installation & bolt
I
tightening general inspection
Cargo piping system pipe welding
I
inspection
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 151
Chapter 3 LNG Carriers Cargo Handling Systems
Section 3 Summary of Surveys to be Carried Out During Construction and Installation of
LNG Carriers Cargo Handling Systems 3-3
TABLE 6 (continued)
Inspection Requirements for Machinery, Equipment and Systems
During and After Installation Onboard
Activity Inspection Remarks
Installation inspection may be performed at same time as hydrotest or
Cargo piping system pipe air test and
I air test as applicable. Access to all parts of the piping system shall be
installation
provided to allow proper inspection.
Cargo piping system pipe inside camera
I
inspection
Safety exhaust line instrumentation
I May be checked during the general survey
inspection
Purge/sample line instrumentation
I May be checked during the general survey.
inspection
Installation inspection may be performed at same time as hydrotest or
Fuel gas pipe hydrotest and inspection I air test as applicable. Access to all parts of the piping system shall be
provided to allow proper inspection.
Fuel gas pipe welding inspection. I
Punching device system inspection (only
I
no.96 systems)
Steel door, hatch & vent cover in cargo
I Chalk test may be considered
area
Second barrier temperature sensor
I
installation inspection
Pump tower guide (base plate) installation
I
inspection
Vapor dome installation inspection I
Liquid dome installation inspection I
Cargo pump safety device function test I
Ship/shore communication tel. function
I
test
I.A.S. function test (cargo) (10% random) I
Nitrogen gen. safety device function test I
Custody transfer sys sensor function test I
Vacuum pump safety device test I
Gas flow meter function test I
Valve remote cont. system. Function test
I
(20% random)
Gas detection system function test I
I.G. blower capacity confirm I to be checked with the IG system running
Dry powder sys. operation test I
Main deck CO2 sys. air blowing test I
Emergency cargo pump handling davit
I
operation test
Emergency shut down sys. function test I
Cargo compressor safety device function
I
test
Cargo compressor running test I See gas trials
Water curtain and deicing operation test
I See gas trials
(water spray pump)
Emergency cargo pump running test I See gas trials
Stripping pump running test I See gas trials.
Vacuum pump function test I See gas trials.
152 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 3 LNG Carriers Cargo Handling Systems
Section 3 Summary of Surveys to be Carried Out During Construction and Installation of
LNG Carriers Cargo Handling Systems 3-3
TABLE 6 (continued)
Inspection Requirements for Machinery, Equipment and Systems
During and After Installation Onboard
Activity Inspection Remarks
Boil-off/warm-up heaters function test I See gas trials
N2 generator operation test (with feed air
I
comp.)
Water detection sys. function test I See gas trials
Vaporizer function test I See gas trials
Glycol heater on-board test I See gas trials
Control v/v for cargo sys. operation test I
Control v/v for glycol heating sys.
I
operation test
Water drain pump operation test I
Float type level gauge function test I
Custody transfer sys. operation test I See gas trials
Emergency cargo pump installation
I See gas trials.
demonstration
Cold test I
Gas trial I
Class I pipe fabrication inspection I
Class II pipe fabrication inspection I
Cargo pipe leak test I
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 153
This Page Intentionally Left Blank
Chapter 4: Final Tests and Trials
CONTENTS
SECTION 1 Gas Trials and First Loading-Unloading Operation ........159
1 Hydrostatic Test of Membrane Type LNG Carriers
Ballast Tanks .....................................................................159
2 Sea Trials...........................................................................159
3 Gas Trials...........................................................................159
3.1 Purpose and Scope of Gas Trials ................................. 159
3.2 Gas Trials Steps............................................................ 160
4 Cold Test............................................................................160
4.1 Barrier Spaces Nitrogen Filling...................................... 160
4.2 Cargo Tank and Piping Drying ...................................... 161
4.3 Inerting .......................................................................... 161
4.4 Cargo Pipelines Cool Down .......................................... 162
5 Cargo Handling Systems Tests During Gas Trials ............162
5.1 Connection to the Terminal and Emergency
Shutdown System Test ................................................. 162
5.2 Purging (Gassing-up) .................................................... 163
5.3 Cool Down .................................................................... 163
5.4 Loading ......................................................................... 164
5.5 Purging (Gassing-up) at Sea......................................... 165
5.6 Cooling Down at Sea .................................................... 165
5.7 Cargo Transfer and Pump Operations .......................... 165
5.8 Unloading ...................................................................... 166
5.9 Warming-up .................................................................. 166
5.10 Inerting and Aeration..................................................... 167
6 Gas Management System Tests During Gas Trials ..........167
6.1 Gas Burning Operations Confirmation Tests................. 167
6.2 BOG and Vaporized Gas Operations Confirmation
Tests ............................................................................. 167
6.3 Other Tests ................................................................... 167
7 First Loading-Unloading Operation....................................168
7.1 Surveyors Attendance During First
Loading-Unloading Operation ....................................... 168
7.2 Verification of Filling Limits............................................ 168
7.3 Verification of Cold Spots.............................................. 168
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 155
SECTION 2 SNAME Guide for LNG Vessels Gas Trials and First
Loading-Unloading Operation .......................................... 169
1 Why SNAME Gas Trial Guide for LNG Vessels?............169
2 Introduction ........................................................................169
2.1 Origin.............................................................................169
2.2 Purpose .........................................................................169
2.3 Trial Objectives..............................................................170
2.4 Selective Invocation ......................................................170
2.5 Recognition of Uncertainty ............................................170
2.6 Planning ........................................................................171
2.7 Pre-trial Check List ........................................................171
2.8 Builders Trials...............................................................172
3 Pre-trial Preparations .........................................................172
3.1 Tests Completion ..........................................................172
3.2 Tanks.............................................................................172
3.3 Piping Systems..............................................................172
3.4 Pumps ...........................................................................173
3.5 Cargo Equipment ..........................................................173
3.6 Prerequisites to Cold Trials ...........................................173
4 Drying and Inerting.............................................................174
4.1 Inert Gas Plant ..............................................................174
4.2 Nitrogen Systems ..........................................................174
4.3 Cryogenic Piping ...........................................................174
4.4 Hold Spaces ..................................................................174
4.5 Cargo Tanks..................................................................174
4.6 Insulation .......................................................................175
4.7 Scope and Duration of Tests .........................................175
5 Cold Testing of Deck Machinery and Piping......................175
5.1 General..........................................................................175
5.2 LNG Vaporizer...............................................................176
5.3 Vapor Header Pressure Control Valve ..........................176
5.4 Vapor Header Mast Heater............................................176
5.5 Boil-off Gas Compressors .............................................176
5.6 Boil-off and Warm-up Gas Heaters ...............................176
5.7 Boil-off Disposal System................................................176
6 Displacement of Inert Gas and Cool-down ........................177
6.1 Displacement of Inert Gas .............................................177
6.2 Cool-down .....................................................................177
7 LNG Handling ....................................................................178
7.1 General..........................................................................178
7.2 Loading and Testing Phase 1........................................178
7.3 LNG Loading and Testing Phase 2 ...............................178
7.4 Fill One Cargo Tank and Test .......................................179
7.5 Filling and Discharging Each Cargo Tank .....................179
7.6 Observations .................................................................179
7.7 Special Remarks ...........................................................180
156 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
8 Boil-off Handling.................................................................180
8.1 General ......................................................................... 180
8.2 Gas Compressor ........................................................... 180
8.3 Boil-off Heaters ............................................................. 180
8.4 Operational Trials, Venting Permitted ........................... 180
8.5 Operational Trials, No Venting. ..................................... 181
8.6 Alternate Propulsion System......................................... 181
9 Warm-up and Gas Freeing ................................................181
9.1 General ......................................................................... 181
9.2 Tests and Operations.................................................... 181
9.3 Scope and Duration ...................................................... 182
9.4 Safety Precaution.......................................................... 182
10 First Full Load and Discharge............................................182
10.1 Checks at Loading Port................................................. 182
10.2 Inerting and Drying........................................................ 182
10.3 Cargo Piping Cool-down ............................................... 182
10.4 Cofferdam and Ballast Tank Checks............................. 183
10.5 Tank Cool-down ............................................................ 183
10.6 Loading ......................................................................... 183
10.7 Inert Gas Monitoring...................................................... 183
10.8 Cargo Characteristics Monitoring .................................. 183
10.9 Filling Limits Check ....................................................... 183
10.10 Hull Checks ................................................................... 183
10.11 Strain Measurements .................................................... 183
10.12 Items to be Recorded During Voyage ........................... 183
10.13 Tank Pressure Control System Check .......................... 184
10.14 Checks of Cargo Handling System Before
Unloading ...................................................................... 184
10.15 Checks of Cargo Before Unloading............................... 184
10.16 Cargo Unloading ........................................................... 184
10.17 Measurements During Unloading.................................. 184
11 Glossary.............................................................................184
11.1 As Agreed ..................................................................... 184
11.2 Boil-off........................................................................... 184
11.3 Boil-off Rate .................................................................. 184
11.4 Cargo Containment System .......................................... 184
11.5 Cargo Tank ................................................................... 185
11.6 Classification Society .................................................... 185
11.7 Cofferdam ..................................................................... 185
11.8 Cold Test....................................................................... 185
11.9 Cool-down ..................................................................... 185
11.10 Dry Air ........................................................................... 185
11.11 Hold Space ................................................................... 185
11.12 Inert............................................................................... 185
11.13 Insulation Space............................................................ 185
11.14 Interbarrier Space ......................................................... 185
11.15 Operational Test............................................................ 185
11.16 Performance Test.......................................................... 185
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 157
11.17 Primary Barriers ............................................................186
11.18 Regulatory Bodies .........................................................186
11.19 Red Hand Setting ..........................................................186
11.20 Secondary Barriers........................................................186
11.21 Shall ..............................................................................186
11.22 Should ...........................................................................186
11.23 Tank Cover....................................................................186
11.24 Tank Dome....................................................................186
11.25 Tank Dome Altitude .......................................................186
11.26 Void Space ....................................................................186
158 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Section 1: Gas Trials and First Loading-Unloading Operation
2 Sea Trials
After completion, LNG carriers perform sea trials as any other type of vessels. As there are no
particular differences of the sea trials procedures, sea trials are not covered by these Guidance Notes.
3 Gas Trials
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 159
Chapter 4 Final Tests and Trials
Section 1 Gas Trials and First Loading-Unloading Operation 4-1
4 Cold Test
160 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 4 Final Tests and Trials
Section 1 Gas Trials and First Loading-Unloading Operation 4-1
During the purging operations the following items are to be checked and/or recorded, as applicable.
Tank pressure
Insulation space and interbarrier space pressure
O2 content
4.3 Inerting
The following atmosphere composition should be obtained inside the inerted tanks:
Oxygen content less than 2%
Dew point lower than 40C.
Some terminals require that the first inerting operation before loading of the LNG necessary for the
gas trials be made using gaseous nitrogen rather than CO2.
The typical procedure of inerting with gaseous nitrogen employed by shipyards is as follows:
1. The spray line between the cargo manifold and the tanks is cooled down
2. Liquid nitrogen is supplied to the LNG vaporizer from a shore tank through the liquid manifold
and the spray line
3. The gaseous nitrogen generated by the LNG vaporizer is supplied to the cargo tanks through
the cargo vapor line. The displaced air is led to the vent mast through the cargo liquid line and
dispersed into the atmosphere.
4. Dew point and O2 content are measured at the sampling point of the tank
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 161
Chapter 4 Final Tests and Trials
Section 1 Gas Trials and First Loading-Unloading Operation 4-1
During the operation the following items are to be checked and/or recorded, as applicable.
Supply rate, pressure and temperature of liquid nitrogen
Pressure and temperature of nitrogen at the vaporizer outlet
Dew point and O2 content in the cargo tank.
The correct functioning of the LNG vaporizer should be confirmed during the test.
162 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 4 Final Tests and Trials
Section 1 Gas Trials and First Loading-Unloading Operation 4-1
Is verified by telephone communication that the signal sent by the ship has been received at the
terminal and vice-versa
Measure the manifold ESD valves closing time, in particular;
- The time from the actuation of the signal and the time the valve closing starting
- The time from the actuation of the signal and the time the full closure of the valve
Reset the ESDS.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 163
Chapter 4 Final Tests and Trials
Section 1 Gas Trials and First Loading-Unloading Operation 4-1
4. The boil-off gas generated in the tank is sent back to the terminal by free flow through the
cargo vapor line
5. The cargo temperature is measured at every hour.
During the operation of cool-down the following items are to be checked and/or recorded, as applicable:
Atmospheric pressure and temperature
Sea water temperature
Cargo tank pressure, temperature and level
Insulation spaces, temperature and nitrogen flow rate
Stripping main pressure and temperature in way of each tank
Flow rate to shore
Liquid and vapor manifold pressure and temperature
Differential pressure between cargo tank and primary insulation space
Cofferdam and inner hull temperature.
During cooling-down operations the cargo piping is inspected to confirm the absence of apparent
problems, the Custody Transfer System (CTS) is also checked.
Gas detection system and cofferdam heating are to be operating.
The nitrogen and barrier space pressurization system are also to be in operation, since during the cool-
down operation, it would be necessary to supply some nitrogen in the barrier spaces to compensate for
the change of pressure due to the lowering of the temperature.
Megger test for all cargo pumps is measured and recorded before and at completion of cool-down
operation. Some times this operation is carried out during loading operation.
5.4 Loading
Once the cool-down has been completed, one tank is loaded with the LNG quantity of cargo that will
be used for the gas trials. The loaded LNG is in the range of 4000 to 5000 m3 for todays standard
LNG carriers.
The typical procedure employed by shipyards is as follows:
1. The cargo liquid lines are cooled-down to a temperature of about 100C.
2. Upon completion of the cool down of the cargo liquid lines, the loading of LNG is initiated
3. Liquid level, pressure and temperature are regularly checked during the loading
4. When the planned quantity of LNG has been received the ESD liquid valve is closed,
however the filling valve is left open to avoid pressure building-up.
During the operation of loading the following items are to be checked and/or recorded, as applicable.
Atmospheric pressure and temperature
Sea water temperature
Cargo tank pressure, temperature and level
Insulation spaces, temperature and nitrogen flow rate
Vapor flow rate to shore
Liquid and vapor manifold pressure and temperature
Differential pressure between cargo tank and primary insulation space
Cofferdam and inner hull temperatures.
164 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 4 Final Tests and Trials
Section 1 Gas Trials and First Loading-Unloading Operation 4-1
Cargo piping is inspected during cooling down for absence of cold spots (ice), contraction and lateral
movement in way of supports and valves are examined for absence of leaks.
Emergency shut down is tested, as deemed necessary during this phase.
The CTS and the floating gauges are checked during loading,
Correct functioning of interbarrier spaces control system (N2 flow), level measuring systems and
cofferdam heating are to be checked during this phase.
Megger test for all cargo pumps is measured and recorded before and at completion of loading operation.
After completion of cargo loading and purging the cargo lines with nitrogen, the ship disconnects
from the terminal to continue gas trials at sea.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 165
Chapter 4 Final Tests and Trials
Section 1 Gas Trials and First Loading-Unloading Operation 4-1
5.8 Unloading
At completion of cargo transfer operation the ship connects again to the terminal to unload the remaining
cargo.
The typical procedure employed by shipyards is as follows:
1. Before reaching the terminal all tanks are stripped as far as possible with the stripping (spray)
pump and all the LNG is collected in one tank
2. The liquid cargo line is cooled using the LNG and the spray pump of the loaded tank before
the arrival at the terminal
3. After the connection the terminal unloading arm is cooled down using the spray pump of the
loaded tank
4. The cargo is discharged using the cargo pump and the stripping pump.
During this operation the following items are to be checked and/or recorded, as applicable:
Atmospheric pressure and temperature
Sea water temperature
Cargo tank pressure temperature and level
Insulation spaces pressure, temperature and N2 flow rate
LNG vaporizer discharge pressure and temperature, gas flow rate, if vapor return from shore is
not available/operated
Cargo pumps and stripping/spray pump discharge pressure and load
Liquid main and cross-over pressure and temperature
Vapor flow rate from shore, If applied
Differential pressure between cargo tank and primary insulation space
Cofferdam and inner hull temperature.
The proper functioning of all equipment including instrumentation, monitoring control and alarm systems
are also to be verified during this operation.
5.9 Warming-up
Returning to the shipyard the tanks are warmed-up before inerting and aerating operations can be
carried out.
The typical procedure employed by shipyards is as follows:
1. Cold LNG vapor is led to the high duty compressor and gas heater through the cargo vapor line
2. Hot gas is returned to the bottom of the tank through the cargo filling line
3. The unpumpable LNG in the bottom of the tank vaporizes
4. The produced vapor is burned in the main boilers. Any vapor excess may be vented to the
atmosphere through the vent mast
During cargo warming-up the following items are to be checked and/or recorded, as applicable:
Atmospheric pressure and temperature
Sea water temperature
Cargo tank pressure temperature
Insulation spaces pressure, temperature and nitrogen flow rate
166 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 4 Final Tests and Trials
Section 1 Gas Trials and First Loading-Unloading Operation 4-1
Heavy duty compressor discharge pressure and temperature and gas flow rate
Gas heater pressure and temperature
Liquid main and cross-over pressure and temperature
Vapor flow rate to boilers and to atmosphere
Differential pressure between cargo tank and primary insulation space
Cofferdam and inner hull temperature
Noise level in cargo compressor and electric motors
Cargo piping displacement as well as proper functioning of all equipment including instrumentation,
monitoring control and alarm systems are checked during this operation.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 167
Chapter 4 Final Tests and Trials
Section 1 Gas Trials and First Loading-Unloading Operation 4-1
168 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Section 2: SNAME Guide for LNG Vessels Gas Trials and First Loading-Unloading Operation
2 Introduction
2.1 Origin
This Guide was developed by a panel composed of representatives of American shipbuilder, ship
owners, and operators, the Maritime Administration, the American Bureau of Shipping, the U.S. Coast
Guard and other experts in the LNG industry under the auspices of the Marine Systems Committee of
the SNAME.
Publications of other SNAME Technical Panels were consulted to check compatibility.
2.2 Purpose
The purpose of the guide is to provide ship owners, designers, operators and builders with definitive
information on LNG trials to form a basis for contractual agreement.
Nothing in the Guide should be construed to delete or modify requirements of specified regulatory
bodies.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 169
Chapter 4 Final Tests and Trials
Section 2 SNAME Guide for LNG Vessels Gas Trials & First Loading-Unloading Operation 4-2
170 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 4 Final Tests and Trials
Section 2 SNAME Guide for LNG Vessels Gas Trials & First Loading-Unloading Operation 4-2
No measurement is perfect and shipboard conditions preclude the use of the most precise techniques.
Since the major ship performance parameters involve measurement of many fluctuating quantities,
each with an element of uncertainty, the cumulative effect might be considerable. By applying
probability techniques to the degree of fluctuation and the inherent revision of the instruments
involved, including their calibration, it is possible to identify the degree of certainty with which a
ship's performance can be determined.
It is important that all parties to a ship construction program recognize the uncertainty of trial results
and take it into consideration when establishing performance target/bonus/penalty levels.
Knowledge of how and how much the precision of the individual measurements affects the
performance determination and the range of precision available for the instruments involved enables
the trial planner to make an intelligent and economic decision on instrumentation.
2.6 Planning
From award of a contract until delivery of the official trial reports LNG trials require planning.
Trial instrumentation requirements must be incorporated in design; prearrangements may be
required for obtaining and calibrating trial instruments; trial readiness checks must be included in
production planning; trial data acquisition, processing, and reporting systems must be developed,
installed and checked; instructions and procedures must be developed for trial operating and data
crews and these crews must be trained.
These actions have an optimum time of accomplishment beyond which there is added expense and
disruption.
A prerequisite to all planning is a clear understanding as to the tests and trials to be conducted, the
depth of instrumentation and the data to be reported.
If this Guide is properly cited in the ship's specifications, requirements should be clear, but if the
Guide is not cited or there remains an area of doubt, the shipbuilder, owner and government
authorities (if involved) should reach agreement as soon as possible after award, using the Guide as a
basis for understanding.
Presuming that agreement has been reached, the actions outlined below can be taken as applicable.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 171
Chapter 4 Final Tests and Trials
Section 2 SNAME Guide for LNG Vessels Gas Trials & First Loading-Unloading Operation 4-2
3 Pre-trial Preparations
3.2 Tanks
i) Tanks shall be strength and leak tested as specified by Classification Society, Regulatory and
Contractual requirements.
ii) After testing, the tanks shall be substantially dried, visually checked for evidence of overstress
or distortion, carefully searched for foreign matter, cleaned and then the tanks closed.
iii) If built and tested independent of the hull and installed aboard intact, the tanks shall be
visually examined internally, externally, or internally and externally (as appropriate to the
tank design) for signs of distortion or distress after installation.
172 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 4 Final Tests and Trials
Section 2 SNAME Guide for LNG Vessels Gas Trials & First Loading-Unloading Operation 4-2
3.4 Pumps
i) Pumps and motors shall be adequately protected from moisture and other contaminants
during shipment and storage at shipyard and during holding period after installation in tanks.
Motor heating circuit desiccant packaging, conditioned storage, or a combination of these
methods may be employed.
ii) Proper direction of rotation shall be demonstrated, where possible, after pumps are electrically
connected.
iii) Freedom of rotation shall be demonstrated, where possible, just prior to final closing of tanks.
iv) Electrical insulation resistance tests should be performed periodically during all storage and
idle periods and shall be performed just prior to final closing of the tanks and just prior to
introduction of LNG, and the results recorded and compared.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 173
Chapter 4 Final Tests and Trials
Section 2 SNAME Guide for LNG Vessels Gas Trials & First Loading-Unloading Operation 4-2
174 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 4 Final Tests and Trials
Section 2 SNAME Guide for LNG Vessels Gas Trials & First Loading-Unloading Operation 4-2
4.6 Insulation
If required by the design of the system, the insulation shall be inerted with gaseous nitrogen, until the
CO2 content is less than 5 percent, the dew point is 40C or as agreed. Operation of the pressure
control (replenishment and venting) system shall be demonstrated.
5.1 General
i) All deck piping and cargo equipment and related instrumentation and controls should be
tested with cold nitrogen gas in the shipyard prior to gas trials. This cold tests is conducted
before the cool-down and test loading so that hot work or other modifications can be made
without having to gas free cargo tanks.
ii) Before the commencement of cool-down and test loading of the tanks, a ''cold test of all deck
piping and cargo equipment should be made using cold LNG gas or gaseous nitrogen down to
160C.
iii) Prior to commencement of cold tests, the following precautions should be taken:
a) Fire pumps, fire hoses, water monitors deck spray systems, and dry chemical fire
fighting equipment should have been tested, and fire hoses laid out and charged as
required by Regulation.
b) Drip pans and their heating coils, if fitted, should be operational.
c) All connections, including ship/shore grounding connections and communication
facilities should be operational.
d) Mechanical ventilation systems serving enclosed spaces containing cargo handling
equipment should be operational.
e) All cargo piping should be inerted with gaseous nitrogen to preclude the presence of
air or inert gas containing carbon dioxide.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 175
Chapter 4 Final Tests and Trials
Section 2 SNAME Guide for LNG Vessels Gas Trials & First Loading-Unloading Operation 4-2
176 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 4 Final Tests and Trials
Section 2 SNAME Guide for LNG Vessels Gas Trials & First Loading-Unloading Operation 4-2
6.2 Cool-down
i) Prior to start of cool-down operation, ensure that the cargo liquid fill valves at all cargo
tanks are closed.
ii) The vapor piping system should be aligned to allow proper disposal of LNG vapor generated
during cool-down. Vapor normally should be directed to the shores but may be vented to
atmosphere through ship's vent piping if applicable regulations permit.
iii) Gas detection equipment shall be operating during cool-down of cargo tanks and piping. All
points should be monitored regularly during entire operation.
iv) Void space or interbarrier space pressure control equipment shall be operating during cool-
down. Void space or interbarrier space pressures shall be monitored regularly, as should
inert gas or nitrogen consumption.
v) Cofferdam and/or wing tank heating systems if fitted shall be operating during cool-down.
vi) Hull steel temperature sensors shall operate continuously during cool-down. Hull steel
temperatures shall be monitored regularly.
vii) Cargo tank and insulation temperature sensors shall operate continuously during cool-down.
All temperatures shall be monitored at regular intervals throughout the cool-down.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 177
Chapter 4 Final Tests and Trials
Section 2 SNAME Guide for LNG Vessels Gas Trials & First Loading-Unloading Operation 4-2
viii) Open valves to cool-down spray nozzles on one or more cargo tanks and adjust LNG flow
rate or pressure drop across spray nozzles to meet requirements of the approved containment
system design.
ix) Monitor cargo tank vapor pressure regularly throughout cool-down to ensure that proper
disposal of LNG vapor can be maintained, particularly if vapor is being returned to the shore
terminal. LNG flow rate should be adjusted as necessary, if vapor pressure rises to the point
where relief valves open.
x) The criteria established by the approved containment system design shall be followed in all
cool-down operations. In general, the cool-down rate should be adjusted to ensure that
thermal gradients in the tank structure do not lead to stresses, which exceed tank requirements.
xi) The end of cool-down shall be determined in accordance with the approved cargo containment
system design. In general, end of cool-down may be assumed to occur when tank bottom
temperature has reached between 140C and 162C depending upon the composition of
the LNG. Vertical thermal gradients must also be considered with certain containment system
designs. When cool-down is complete tanks are ready for loading.
7 LNG Handling
7.1 General
The tests and procedures as described in this sub-chapter determine the adequacy of operation of all
portions of the cargo system that handles LNG. The tests of previous sub-chapters shall be completed
and the tanks are cooled down prior to the commencement of LNG handling tests. All necessary
equipment shall be operational and in service for the safe handling of LNG.
178 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 4 Final Tests and Trials
Section 2 SNAME Guide for LNG Vessels Gas Trials & First Loading-Unloading Operation 4-2
7.6 Observations
i) Monitor all gas detection points regularly during time LNG is aboard the vessel.
ii) Monitor the operation of nitrogen system and boil-off gas system including gas burning if in
use during above operations.
iii) Record and plot where fitted and applicable:
a) Tank vapor header pressures and temperatures.
b) LNG tank temperatures insulation temperatures, and inner hull temperatures.
c) Top key temperatures: where pertinent.
d) Void space or inter- barrier space pressures.
e) Ambient air and sea temperatures, and barometric pressures.
f) Interbarrier gas concentration and purge rate.
iv) Record weather and sea conditions at hour intervals.
v) Check operation of bulkhead and hull heating arrangements, if fitted, and record temperatures.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 179
Chapter 4 Final Tests and Trials
Section 2 SNAME Guide for LNG Vessels Gas Trials & First Loading-Unloading Operation 4-2
8 Boil-off Handling
8.1 General
i) In order to prevent cargo tank pressure from increasing due to heat leak through the
insulation, boil-off vapors are removed from the tanks by means of a piping system and the
gas compressor(s). Normally the gas is compressed, heated to ambient temperature, and used
as fuel in the propulsion system to augment the normal fuel.
Note: This Guide does not cover propulsion machinery trials, which should previously have been satisfactorily
completed if such machinery is involved with handling boil-off.
During gas trials, all components of the boil-off handling system should be tested for
individual performance and as an integrated system. The following is a list of those functions
and components, which require testing.
180 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 4 Final Tests and Trials
Section 2 SNAME Guide for LNG Vessels Gas Trials & First Loading-Unloading Operation 4-2
iii) Start compressor and heater and place in automatic control mode. By manual throttling of
compressor inlet and heater discharge, variation of boil-off rate and engine room demand
can be simulated. Response of compressor and heater controls can be checked.
iv) By quickly shutting gas flow a trip of gas-to-engine room valve is simulated to test operation
of surge controls (centrifugal compressor) or pressure relief system (positive displacement
compressor).
9.1 General
The warm-up and gas freeing system shall be tested to demonstrate satisfactory operation.
This test may be performed at the completion of gas trials, after service voyages, or as agreed.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 181
Chapter 4 Final Tests and Trials
Section 2 SNAME Guide for LNG Vessels Gas Trials & First Loading-Unloading Operation 4-2
iii) When the required tank temperature of 5C, or as agreed, is reached, the cargo tanks shall be
purged with inert gas (which may be required to be done at sea). At the end of inerting, the
gas composition shall be 5 percent by volume hydrocarbons or less or as agreed.
iv) Then the cargo tanks and hold spaces (as required for inspection) shall be aerated. At the end
of aerating the gas conditions shall be at least 18 percent oxygen, 0.25 percent hydrocarbons,
or as agreed. Safe conditions shall be maintained by adequate ventilation throughout the test
and inspection period, and they shall be monitored.
182 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 4 Final Tests and Trials
Section 2 SNAME Guide for LNG Vessels Gas Trials & First Loading-Unloading Operation 4-2
10.6 Loading
Simultaneously load all tanks, using shipboard compressor(s), if so designed, to return cargo vapor to
shore. Note loading time required and compressor performance.
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 183
Chapter 4 Final Tests and Trials
Section 2 SNAME Guide for LNG Vessels Gas Trials & First Loading-Unloading Operation 4-2
11 Glossary
11.1 As Agreed
As used herein, means as defined by contract, specification, approved trials procedure or agenda or
other written agreement.
11.2 Boil-off
Is the gas resulting from vaporization of the LNG cargo.
184 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008
Chapter 4 Final Tests and Trials
Section 2 SNAME Guide for LNG Vessels Gas Trials & First Loading-Unloading Operation 4-2
11.7 Cofferdam
Is the isolating space between two adjacent steel bulkheads or decks. This space may be a void space
or ballast space.
11.9 Cool-down
Is the procedure on a vessel for reducing to service temperature; piping, tanks and associated equipment
and instruments prior to the vessel receiving LNG.
11.12 Inert
Is an atmospheric condition in a space whereby the oxygen content is a maximum of 1/2 of that
percentage which, when mixed with any quantity of cargo vapor, will produce a combustible mixture
(typically: 5% oxygen, 40C dew point).
ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008 185
Chapter 4 Final Tests and Trials
Section 2 SNAME Guide for LNG Vessels Gas Trials & First Loading-Unloading Operation 4-2
11.21 Shall
Used to express obligation for compliance with this Code.
11.22 Should
Expresses recommendation of this Code.
186 ABS GUIDANCE NOTES ON SURVEYS DURING CONSTRUCTION OF MEMBRANE TANK LNG CARRIERS . 2008