Beruflich Dokumente
Kultur Dokumente
ABB Group
Slide 1
PowDoc id
Agenda
Oil
Flange/box body
Insulator
ABB Group
October 26, 2011 | Slide 8
HVDC Light JDC joint
Insulation
Conductive layer
Deflector
ABB Group
October 26, 2011 | Slide 9
ABB Group
October 26, 2011 | Slide 13
Vertical extruder
Material handling at our Suppliers premises
ABB Inc.
October 26, 2011 | Slide 19
ABB Inc.
October 26, 2011 | Slide 20
Assembling
Installation
Underground Cables
Considerations:
Load profile (load factor)
Maximum conductor temperature
70C for HVDC Light Cable
Conductor size
Thermal resistivity of ambient soil and backfill
Temperature of ambient soil and air
Laying depth
Spacing between cables
Cable Ampacity Rating
Burial Depth
Installation of Solid Dielectric Cables
Duct bank system:
Advantages solid mechanical protection against dig-ins and external
damage to the cables. (Important characteristic in roads and in areas with
other utilities close by.)
Disadvantages costly civil construction, more difficult cable pulling, higher
thermo-mechanical stresses on joints, etc.
Off-shore education
Off-shore training
Health and safety
Correct equipment
RELIABILITY
HVDC Light
No internal cable fault in 1566 km HVDC Light cables put into operation
HVAC for comparison
HVDC - HISTORY AND REFERENCE
PROJECTS
2009
Eirgrid
400 kV (200 kV), 500 MW
44 miles (+116 miles subsea)
Solid Dielectric HVDC Light Submarine Cable
Significant technology milestone events
2002 Cross Sound: 300kV(150kV), 330MW, 25 miles
2005 Troll A: 120kV (60kV), 240MW, 242 miles
2006 EstLink: 300kV (150kV), 350MW, 46 miles
2007 Circuit ratings up to 640kV (320kV), 1100MW
2008 BorWin: 300kV (150kV), 400MW, 80 miles
2009 Eirgrid: 400kV (200kV), 500MW, 116 miles
2010 DolWin: 640kV (320kV), 800MW, 46 miles
100 kV DC cable
system for State
Project
Power Board,
Sweden
Cable Mass-impregnated
type 1 x 90 mm2 Cu
Length 100 km
Year 1953
ABB Group
October 26, 2011 | Slide 52
450 kV MI Cable System, NorNed
MI 700 mm2 Cu
2 x 150 km
DWA
Constru-
2005 - 2008
ction
ABB Group
October 26, 2011 | Slide 53
Cable
MI 1 x 1430 mm2 Cu
type
494 km submarine
Length
cable 16 km land cable
ABB Group
October 26, 2011 | Slide 54
+/-150 kV HVDC Light cable system, Cross Sound
New Haven
ABB Group
October 26, 2011 | Slide 55
80 kV HVDC Light
submarine cable
system for feeding gas
Project
compressors at
Statoils Troll A gas
production platform
HVDC Light 1 x 300
Cable mm2 Cu, double
type armoured submarine
cable
Length 4 x 68 km
Cable system design,
project
Scope
management, cable
of
and accessories,
supply
land- and offshore
installation and testing
Year 2002 - 2004
ABB Group
October 26, 2011 | Slide 56
150 kV HVDC Light cable system, Estlink
ABB Group
October 26, 2011 | Slide 57
ABB Group
October 26, 2011 | Slide 58
200 kV HVDC Light cable system, EWIP
Year 2012
ABB Group
October 26, 2011 | Slide 59
ABB Group
October 26, 2011 | Slide 60
+/-300 kV HVDC Light cable system, Nordbalt