Sie sind auf Seite 1von 8

Code No: 117CU Set No.

1
JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD
IV B.Tech. I Sem., I Mid-Term Examinations, September - 2017
ELECTRICAL ESTIMATING AND COSTING
Objective Exam
Name: ___________________________ _ Hall Ticket No. A
Answer All Questions. All Questions Carry Equal Marks. Time: 20 Min. Marks: 10.

I. Choose the correct alternative:

1. For what voltage is the H type of poles used? [ ]


A) 22 kV B) 130 kV C) 11 kV D) 33 kV

2. What is the formula to calculate the number of poles required in LT line distribution? [ ]
A) Length/Span+1 B) Length/Span+10 C) Span/Length+1 D) Span/Length+10

3. What is the angle between the pole and stay? [ ]


A) 100 B) 450 C) 600 D) 300

4. Which among these tests are to be conducted on wiring installations. [ ]


A) Testing of polarity of non-linked single pole switches B) Testing of earth continuity path
C) Testing of earth resistance D) All the above

5. What is the amount of charcoal and salt needed for GI Pipe earthing. [ ]
A) Charcoal 5 kg, salt 8 kg B) Charcoal 10 kg, salt 8 kg
C) Charcoal 10 kg, salt 10 kg D) Charcoal 5 kg, salt 5 kg

6. What is the specification of GI earth plate. [ ]


A) 60 cm * 60 cm * 3 mm B) 60 cm * 60 cm * 6 mm
C) 60 cm * 60 cm * 4 mm D) 60 cm * 60 cm * 5 mm

7. Which Indian Electricity rule is applicable to service mains? [ ]


A) Rule 30 B) Rule 39 C) Rule 73 D) Rule 51

8. What is the factor of safety used for current ratings in a power installation? [ ]
A) 1 B) 1.5 C) 1.75 D) 2

9. What should be the value of earthing resistance for large power stations? [ ]
A) 1 B) 0.5 C) 2 D) 5

10. Which among the following information is required for a good estimation? [ ]
A) Availability of products B) Sources of production, vendor selection
C) Both A and B D) Prices of each product without discount

Cont..2
Code No:117CU :2: Set No. 1

II Fill in the Blanks

11. The types of loads are _________________________ .

12. The disadvantage of underground service mains is ____________ .

13. Which state in India does not follow Indian Electricity rules___________ .

14. Branch circuit must not feed more than __________ points.

15. The purpose of Earth wire in Transmission lines is ____________________________ .

16. The objective of Service Mains is _________________________________________________ .

17. An electrical schedule is ____________________________________.

18. The maximum span upto which the wooden poles can be used is ________________.

19. The types of supports used for transmission lines are _________________________.

20. The difference between Neutral and Earth wire in Distribution networks is _________________.

-oOo-
Code No: 117CU Set No. 2
JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD
IV B.Tech. I Sem., I Mid-Term Examinations, September - 2017
ELECTRICAL ESTIMATING AND COSTING
Objective Exam
Name: ___________________________ _ Hall Ticket No. A
Answer All Questions. All Questions Carry Equal Marks. Time: 20 Min. Marks: 10.

I. Choose the correct alternative:

1. Which among these tests are to be conducted on wiring installations. [ ]


A) Testing of polarity of non-linked single pole switches B) Testing of earth continuity path
C) Testing of earth resistance D) All the above

2. What is the amount of charcoal and salt needed for GI Pipe earthing. [ ]
A) Charcoal 5 kg, salt 8 kg B) Charcoal 10 kg, salt 8 kg
C) Charcoal 10 kg, salt 10 kg D) Charcoal 5 kg, salt 5 kg

3. What is the specification of GI earth plate. [ ]


A) 60 cm * 60 cm * 3 mm B) 60 cm * 60 cm * 6 mm
C) 60 cm * 60 cm * 4 mm D) 60 cm * 60 cm * 5 mm

4. Which Indian Electricity rule is applicable to service mains? [ ]


A) Rule 30 B) Rule 39 C) Rule 73 D) Rule 51

5. What is the factor of safety used for current ratings in a power installation? [ ]
A) 1 B) 1.5 C) 1.75 D) 2

6. What should be the value of earthing resistance for large power stations? [ ]
A) 1 B) 0.5 C) 2 D) 5

7. Which among the following information is required for a good estimation? [ ]


A) Availability of products B) Sources of production, vendor selection
C) Both A and B D) Prices of each product without discount

8. For what voltage is the H type of poles used? [ ]


A) 22 kV B) 130 kV C) 11 kV D) 33 kV

9. What is the formula to calculate the number of poles required in LT line distribution? [ ]
A) Length/Span+1 B) Length/Span+10 C) Span/Length+1 D) Span/Length+10

10. What is the angle between the pole and stay? [ ]


A) 100 B) 450 C) 600 D) 300

Cont..2
Code No:117CU :2: Set No. 2

II Fill in the Blanks

11. Branch circuit must not feed more than __________ points.

12. The purpose of Earth wire in Transmission lines is ____________________________ .

13. The objective of Service Mains is _________________________________________________ .

14. An electrical schedule is ____________________________________.

15. The maximum span upto which the wooden poles can be used is ________________.

16. The types of supports used for transmission lines are _________________________.

17. The difference between Neutral and Earth wire in Distribution networks is _________________.

18. The types of loads are _________________________ .

19. The disadvantage of underground service mains is ____________ .

20. Which state in India does not follow Indian Electricity rules___________ .

-oOo-
Code No: 117CU Set No. 3
JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD
IV B.Tech. I Sem., I Mid-Term Examinations, September - 2017
ELECTRICAL ESTIMATING AND COSTING
Objective Exam
Name: ___________________________ _ Hall Ticket No. A
Answer All Questions. All Questions Carry Equal Marks. Time: 20 Min. Marks: 10.

I. Choose the correct alternative:

1. What is the specification of GI earth plate. [ ]


A) 60 cm * 60 cm * 3 mm B) 60 cm * 60 cm * 6 mm
C) 60 cm * 60 cm * 4 mm D) 60 cm * 60 cm * 5 mm

2. Which Indian Electricity rule is applicable to service mains? [ ]


A) Rule 30 B) Rule 39 C) Rule 73 D) Rule 51

3. What is the factor of safety used for current ratings in a power installation? [ ]
A) 1 B) 1.5 C) 1.75 D) 2

4. What should be the value of earthing resistance for large power stations? [ ]
A) 1 B) 0.5 C) 2 D) 5

5. Which among the following information is required for a good estimation? [ ]


A) Availability of products B) Sources of production, vendor selection
C) Both A and B D) Prices of each product without discount
6. For what voltage is the H type of poles used? [ ]
A) 22 kV B) 130 kV C) 11 kV D) 33 kV

7. What is the formula to calculate the number of poles required in LT line distribution? [ ]
A) Length/Span+1 B) Length/Span+10 C) Span/Length+1 D) Span/Length+10

8. What is the angle between the pole and stay? [ ]


A) 100 B) 450 C) 600 D) 300

9. Which among these tests are to be conducted on wiring installations. [ ]


A) Testing of polarity of non-linked single pole switches B) Testing of earth continuity path
C) Testing of earth resistance D) All the above

10. What is the amount of charcoal and salt needed for GI Pipe earthing. [ ]
A) Charcoal 5 kg, salt 8 kg B) Charcoal 10 kg, salt 8 kg
C) Charcoal 10 kg, salt 10 kg D) Charcoal 5 kg, salt 5 kg

Cont..2
Code No:117CU :2: Set No. 3

II Fill in the Blanks

11. The objective of Service Mains is _________________________________________________ .

12. An electrical schedule is ____________________________________.

13. The maximum span upto which the wooden poles can be used is ________________.

14. The types of supports used for transmission lines are _________________________.

15. The difference between Neutral and Earth wire in Distribution networks is _________________.

16. The types of loads are _________________________ .

17. The disadvantage of underground service mains is ____________ .

18. Which state in India does not follow Indian Electricity rules___________ .

19. Branch circuit must not feed more than __________ points.

20. The purpose of Earth wire in Transmission lines is ____________________________ .

-oOo-
Code No: 117CU Set No. 4
JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD
IV B.Tech. I Sem., I Mid-Term Examinations, September - 2017
ELECTRICAL ESTIMATING AND COSTING
Objective Exam
Name: ___________________________ _ Hall Ticket No. A
Answer All Questions. All Questions Carry Equal Marks. Time: 20 Min. Marks: 10.

I. Choose the correct alternative:

1. What is the factor of safety used for current ratings in a power installation? [ ]
A) 1 B) 1.5 C) 1.75 D) 2

2. What should be the value of earthing resistance for large power stations? [ ]
A) 1 B) 0.5 C) 2 D) 5

3. Which among the following information is required for a good estimation? [ ]


A) Availability of products B) Sources of production, vendor selection
C) Both A and B D) Prices of each product without discount

4. For what voltage is the H type of poles used? [ ]


A) 22 kV B) 130 kV C) 11 kV D) 33 kV

5. What is the formula to calculate the number of poles required in LT line distribution? [ ]
A) Length/Span+1 B) Length/Span+10 C) Span/Length+1 D) Span/Length+10

6. What is the angle between the pole and stay? [ ]


A) 100 B) 450 C) 600 D) 30 0

7. Which among these tests are to be conducted on wiring installations. [ ]


A) Testing of polarity of non-linked single pole switches B) Testing of earth continuity path
C) Testing of earth resistance D) All the above

8. What is the amount of charcoal and salt needed for GI Pipe earthing. [ ]
A) Charcoal 5 kg, salt 8 kg B) Charcoal 10 kg, salt 8 kg
C) Charcoal 10 kg, salt 10 kg D) Charcoal 5 kg, salt 5 kg

9. What is the specification of GI earth plate. [ ]


A) 60 cm * 60 cm * 3 mm B) 60 cm * 60 cm * 6 mm
C) 60 cm * 60 cm * 4 mm D) 60 cm * 60 cm * 5 mm

10. Which Indian Electricity rule is applicable to service mains? [ ]


A) Rule 30 B) Rule 39 C) Rule 73 D) Rule 51

Cont..2
Code No:117CU :2: Set No. 4

II Fill in the Blanks

11. The maximum span upto which the wooden poles can be used is ________________.

12. The types of supports used for transmission lines are _________________________.

13. The difference between Neutral and Earth wire in Distribution networks is _________________.

14. The types of loads are _________________________ .

15. The disadvantage of underground service mains is ____________ .

16. Which state in India does not follow Indian Electricity rules___________ .

17. Branch circuit must not feed more than __________ points.

18. The purpose of Earth wire in Transmission lines is ____________________________ .

19. The objective of Service Mains is _________________________________________________ .

20. An electrical schedule is ____________________________________.

-oOo-