Sie sind auf Seite 1von 35

COST CLASSIFICATION

CLASSIFICATION COST MARGIN IN PER SQ.M.

CLASS A 25,000.00 UP
CLASS B 17,000.00 23,000.00
CLASS C 14,000.00 16,000.00
CLASS D 12,000.00 - BELOW
CLASS B MORTAR MIXTURE:
MORTAR AND PLATER MIXTURE PER CUBIC METER:
CLASS MIXTURE CEMENT 40KGS SAND
A 1:2 18 1.0
B 1:3 12 1.0
C 1:4 9 1.0
D 1:5 7.5 1.0

Therefore:
Cement = 2.12. cu.m. x 12 bags / cu.m. = 25.44 bags
Sand = 2.12 cu.m. x 1.0 cu.m. = 2.12 cu.m.
Rebars = 2180 kgs.
CHB 6 = 708 pcs.
Tie wire = 2180 kgs x 0.0048632 = 10.60 kgs

Cement Plastering at an average of 16 mm thk.:


Total wall Area (expose, one face) = 44.57 s.m. x 2 = 89.14 s.m.
Solve for the Volume = 89.14 s.m. x 0.016 = 1.43 cu.m.
Using the table above = 1.43 cu.m.
Cement = 1.43 cu.m. x 12 bags = 17.16 bags
Sand = 1.43 cu.m. x 1.0 / cu.m. = 1.43 cu.m.
CHB WALL:
In computing the wall area, segregate the wall from floor to beam suffit
and wall to wall footing for you can easily compute for your cement plaster
and painting requirements.

Say if you have a total of 20 lm wall x the height of 2.80 m.


Therefore you have = 56.0 s.m.
Within this wall you have windows with an open area of 5.76 s.m.
And doors of 5.67 s.m. or a total of 11.43 s.m.
Computing for Chb Wall = 56.00 s.m.
= 11.43 s.m.
Wall = 44.57 s.m.
Add the embeded chb below floor:
Wall Length of 20 l.m. x 0.60 m. = 12.00 s.m.
Total chb wall = 56.57 s.m.
Computing for materials required:
For 6 CHB = 12.5 pcs / 1.0 s.m. = 708 pcs.
For 10 mm dia. Rebars = 5.0 l.m. / s.m. = 3,540 l.m. or 2180 kgs.
For Mortar Hole Volume = .05 x .075 x .20 = 0.00075 cum.
= 4 cells
= .003 cu.m.
For wall of 56.57 x 12.5 = 707.12 pcs x .003 per pc. = 2.12 cu.m.
Concrete Volume Computation:

Volume = Length x width x height

Vol. = 0.40 x 0.20 x 1.00


Vol. = 0.08 cu.m.

Convert it to Materials under TABLE 1-2 CONCRETE PROPORTION:


In its 1.00 cubic meter of Class B Concrete mixture:
= 8 bags of cement
= 1 cu.m. of Gravel
= cu.m. of Sand

Therefore:
Cement = 0.64 Bag x 4.50 l.m. =2.88 or 3 bags
Sand = 0.04 cu.m. x 4.50 l.m.= 0.18 cu.m.
Gravel = 0.08 cu.m. x 4.50 l.m. = 0.36 cu.m.
Kilograms per linear meter:
16 mm dia. X 1.00 mtr. = 1.788 kgs
12 mm dia. X 1.00 mtr. = 0.888 kgs.
10 mm dia. X 1.00 mtr. = 0.616 kgs.

For this column design, from footing to Beam, we have a nominal


length of 4.50 meters plus a bend below at column footing of atleast 0.30m,
Total Length = is 4.50 m + 0.30m
TL = 4.80 m.
Computing for the column rebars:
CR = TL x no. of rebars,
CR = 4.80m. x 6 pcs.
CR = 28.80 lm.
Convert it to Kilograms:
WEIGHT = 28.80 lm x 1.788 kgs/ lm.
WEIGHT = 51.49 Kgs.
Computing for ties:
Column Total length is 4.50 m. less top and bottom of 1.050 m. or 2.010m.
(1@0.50, 2@.10, 4@.15m.)
Therefore:
TL = 4.50 m. 2.01 = 2.40 m. / 0.20m of ties space = 12 pcs.
and for the top and bottom ties is 11 pcs x 2 sets = 22 pcs + 12 = 34 pcs.
Total lengths of ties needed = 0.90 m. x 34 pcs. /col. = 30.6 mtrs.
= 30.6 m. or 18.85 kgs. Or 5 lengths of 6 mtrs.
TABLE: CONCRETE PROPORTION
Class Mixture Cement Sand Gravel
AA 1:1-1/2:3 12 .50 1.0
A 1:2:4 9.0 .50 1.0
B 1:2-1/2:5 7.5 (8.0) .50 1.0
C 1:3:6 6.0 .50 1.0

Computing for Tie Wires of Ga. 18


Just add all your rebars in kilo Gram then multiply it by 0.0048632
Then the product is your total Tie wire needed in kilogram.
For the Tie wires needed:
Rebars = 51.49 kgs.
Ties = 18,85 kgs.
Total = 70.34 Kgs. X 0.048632
Tie Wire = 3.40 kgs.
Compute for Material Cost:
16 mm dia. = 51.49 kgs. X P34.00 = P1,750.00 Total = P3,740.00
10 mm dia. = 18.85 kgs. X P34.00 = P 640.90
G.I. Tie wire = 3.40 kgs. X P28.00 = P 95.20
Cement = 3 bags x P220.00 = P 660.00
Gravel dia. = .18 cu.m. X 900.00 = P 162.00
Sand = .36 cu.m. x 1200.00 = P432.00
Computation of Beam Rebars:
Find first the continues rebars, determne how many are they then
Compute for the total lengths including bends:
Beam Length say: 4.00 mtrs.
Dimensions is .250 x .400 mtrs.
Total Rebar length = 4.00 + 0.20 + 0.20 = 4.80 mtrs.
Compute all the cont. rebars:
Rebars = 4.80 x 4 pcs = 19.20 mtrs
Compute for L/4 and L/5:
Direct counting say;
Rebar Length for L/4 = 4mtrs / 4 + 0.20 = 1.20 mtrs x 4 pcs = 4.80 m.
Rebar Length for L/5 = (4 mtrs /5 x 3 ) + 0.40 bends = 2.80 m.
= 2.80 m. x 2 pcs = 5.60 m.
Total Rebars required = 19.20 m.
4.80 m.
+ 5.60 m.
Total Beam Rebar = 29.60 m. x 1.788 kgs /lm = 52.98 kgs.
Ties computation is similar of the Column ties Computation:
Total beam Length = 4.0 m. 2.02 m. = 1.98 m.
= 1.98 / 0.15 m. = 13.2 or 14 pcs.
Total Ties Length = 1.40 m. x 14 pcs. = 19.60 m.
= 1.40 m. x 22 pcs. = 30.8 m. or 50.40 m.
= 50.49 m. x 0.616 kgs/ lm. = 31.10 kgs.
Total of Vertical Bars and Ties:
Total Column Rebars = 51.49 kgs x 10 columns
= 514.90 kgs.

Total Column Ties = 18.89 kgs


= 18.85 kgs. x 10 columns
= 188.50 kgs.

Computing for Column Footing:


CONCRETE:
Use Class B Mixture:
Size of Footing: 1.20 x 1.20 x .30 mtrs. Or 0.432 cu.m.
Total Volume : footing 1 x qty
Total Vol. = 0.432 cum x 10 Col. footing
Total Vol. = 4.32 cum.

Breaking this into materials:


Using Class B Mixture:
Portland Cement = 4.324 x 8 bags = 34.56 bags
W. Sand = 4.324 x 0.50 = 2.16 cum
Gravel = 4.324 x 1.00 = 4.324 cum
Computation for the column forworks:
Get the total column wall surfaces first,
Total Column Wall Surface = width x length x height
= 2(0.20 + .40) 1.50 m
= 1.2 m. (1.50 m.)
= 1.80 s.m.
Within 1 sheet of plywd. 0f 2.88 s.m. per sheet

For Coco Lumber:


Direct counting there are about 4 horizontals for a 1.50 m high column.
Since width is 1.20 m. x 4 pcs = 4.80 m. length
Coco commercial length available is 8 or 2.4 m.
For verticals is = 1.5 x 8 pcs = 12 m. or

Therefore:
Nailer Coco of (2 x 3 x 8) = 16.80 lm. = 7 lengths
Braces Coco of (2 x 4 x 8) = 9.60 lm. = 4 lengths
Formply ( thk x 1.20 x 2.40 m.) = 1 sheet
CWN = (1-1/2 to 2) = Kilo
CWN = ( 3) = Kilo
IMPORTANT!:

PLEASE TAKE NOTE OF THE SPLICING AND DEVELOPMENT


LENGTH AS SPECIFIED BY THE CODE IN THE DESIGN
STEEL TRUSS Computation:

LENGTH

Method of estimate is by Direct counting of length of each kind of steel.


First Identify the kind of Materials and Make tabulation.
Add all the length in linear meter per type of material.
SOLVING FOR THE FLOOR TILES REQMNTS:
1. Measure the floor area and add all the tiles with
the same specification.
2. Study carefully and stablish your starting point
3. Look for a more profitable and with less cutting
loose (Siroho).
Then compute for the Materials needed.
For Living and Dining Tiles:
Area= (8.00 x 4.00) + (3.00 x 4.00)
= 32 + 12 or 44 s.m.
Considering the tile size of 400 x 400 mm.
Tiles = 44 / 0.16 = 275 pcs.
Since the area dimensions are
all divisible by 400 so it would be easy for
us to compute for the quantity.
For Tile Adhesive:
Area= 44 s.m.
Adhesive of 20 kgs/ bag covers 5 s.m. of tiles
to be installed.
Therefore:
Qty= 44 / 5.0 s.m. / 20 kgs bag = 8.8. or 9 bags
Then for tile grout:
Qty= 44 / 3.0 s.m. / 5.0 kgs bag = 14.6 or 15 bags
And consider the cost of your cylinder tile cutter.
Say for this area: assume 1 cutter / 100 pcs. = 3 pcs.
Cost:
Tiles = 275 x 59.00/pc. = P16,225.00
Adhesive = 9 bags x P250.00 / bag = P2,250.00
Grout = 15 bags x P100.00 / bag = P1,500.00
Grinder blade = 3 pcs. X P250.00 / pc. = P750.00
Total = P20,725.00 / 44.0 s.m. = P471.00
For air vents computation, Solving for Ceiling Materials:
Just count the corner vents. Base on this ceiling plan, the total ceiling area
Is 132.8 s.m. and eaves is 49.20 and has a cove
ceiling of .25 deep x 17 l.m. = 4.25 s.m.
I have a total of = 132.80 s.m.
= 49.20 s.m.
= 4.25 s.m.
Total ceiling Area = 186.25 s.m.

Compute for Metal furrings:


186.25 x 5 l.m. = 931.25 l.m. / 2.4 m.
= 388 lengths.
Compute for carrying channels:
186.25 x 1.0 l.m. = 186.25 l.m. / 2.4 m.
= 77 lengths
Compute for Rivets = 19 + 9 = 28 pcs
= 28 x 186.25 s.m.
= 5,215 pcs or 3 boxes
Compute for wall angle:
Direct wall length computation say:
250 l.m. / 2.40 m. = 104.17 lengths
Concrete nail = 250 l.m. / .30 m. =833 pcs.
For CONCRETE Moulding:
Study your skilled worker efficiency and speed. Then calculate the cost
base on his accomplishment per hour.
Say = If his Salary is P500/ day and for that particular type of moulding
he could only be able to finish 10 l.m. / day = P 50/ l.m.
Then Add the cost of the cement.
Compute all the window opening
Compute all the indoor doors opening
Compute all the exterior door opening
Doors and Jambs is
by direct counting
Compute for the total window area:
W-1 = 2.00 x 2.40 1 set = 4.80 s.m.
W-2 = 2.00 x 1.60 1 set = 3.20 s.m.
W-3 = 1.60 x 1.60 1 set = 2.56 s.m.
W-4= 1.20 x 1.20 3 sets = 4.32 s.m.
W-5 = 1.00 x 1.20 1 set = 1.20 s.m.
W-6 = .60 x 1.20 1 set = 0.72 s.m.
W-7 = 1.20 x .60 2 sets = 1.44 s.m.
Total = 18.24 s.m.

Total Quotation for this item is P87,000.00 / 18.24 s.m.


= P4,769.00 or safe at P4,800.00 s.m.
For Doors:
Just segregate the Solid panels against Flush doors:
By Direct Counting:
Panel Doors = 9 sets ( 700,800 mm) P 4,600-P 5,500.00 /set
Flush Door = 7 sets ( 700,800 mm) P1,850-P2,200.00 /set
Indoor Jambs 2 x 5 (700,800,900 mm ) = P1,600.00 / set
Exterior Jambs 2 x 6 ( 700, 800, 900 mm) = P 1,800.00 / set
For ROOF Costing:
Compute for the following
1. Roof Area = 243 l.m. x 265 = P64,395.00
2. Ridge Roll = 26 l.m. x P250,00 = P6,500.00
3. Valley = 8.0 l.m. x P240.00 = P1,920.00
4. Gutter = 57.2 l.m. x P260.00 = P14,300.00
5. Accessories= 1.0 lot x 20,000.00 =P20,000.00
6. Insulation = 243 l.m. x P70.00 = P17,010.00
7. Labor 5 x 600 x 6 days = P 18,000.00
8. Total = P!42,125.00

Covert it into per sq. meter methd?


Floor area of the house is 123.9 s.m.
Therefore = 142,125.00 / 123.90 s.m.
= P 1,147.09
POWER LAYOUT
LIGHTING LAYOUT To compute for the Electrical wires and conduit
Requirements just measures the total lengths of
each circuit then add all of the same in size.

Materials:
1. THHN Stranded 2.0 mm2 = 190 l.m. x 2 = 380 l.m.
2. THHN Stranded 3.5 mm 2 = 100 l.m. x 2 = 200 l.m.
3. THHN Solid 5.5 mm 2 = 40 l.m. x 2 = 80 l.m.
4. THHN Solid 8.0 mm 2 = 20 l.m. x 2 = L.m.
5. Conduit dia. X 6.00 = 32 lengths
6. Conduit dia. X 6.00 = 17 lengths
7. Conduit 1 dia . X 6.00 = 4 lengths
8. Couplings dai. = 40 pcs
9. Couplings dia. = 20 pcs.
9. Couplings 1 dia. = 5 pcs.
10. Elbows dia. = 20 pcs
11. Elbows dia. = 16 pcs.
12. Elbows 1 dia. = 3 pcs.
13. Utility Boxes = L.O + C.O. = 38 pcs.
14. Junction Boxes w/ plate cover= 25 pcs
15. Ellectrical Tape big Nitto= 20 Rolls
16. FB Condulet 1 dia. = 1 pc.

Electrical Fixtures:
By Direct Counting.
DIRECT COMPUTATION:
PLUMBING LAYOUT Make Tabulation for same pipe sizes:
Pipe w/ hub::
4 dia. = 66 + 8 + 2 = 76 l.m. or 26 lengths
3 dia.= 54 + 2 = 56 l.m. or 18.67 or 19 lengths
2 dia. = 3 + 3 + 2 + 6 + 2 = 16 l.m. or 5.33 or 6 lengths
Fittings:
Wye 4 x4 = 2
4 x 2 = 4
Elbow 1/8 bend x 4 dia = 14 pcs
Elbow x 3 dia. = 36 pcs
Elbow x 2 dia. = 8 pcs.
P-trap 2 = 4 pcs
P-trap 1-1/4 dia. = 2 pcs.
P trap 1-1/2 dia. = 2 pcs.
San Tee 4 da. = 3 pcs.
Clean Out 4 dia. = 3 sets
Solvent cement: 4 quarts
Water Line System
Pipes Hot & Cold PPR PN-20
Pipes dia. =16+6+8+8+2+2+4+4+2+2 = 54 l.m.
= 13.6 lengths or 14 lengths
Fittings:
Coupling dia. = 12 pcs
Elbow dia. = 8 pcs
Tee w/ Female socket = 8 pcs
Cap dia. = 10 pcs.
Union Patente dia. = 12 pcs
Gate Valve dia. = 5 sets
Check Valve dia. = 1 set
Flexible hose dia x 12 = 8 pcs
Angle valve dia. = 8 pcs.
Nipple x 4 = 8 pcs
Teflon Tape = 140 rolls
STRUCTURAL FOUNDATION PLAN
CATCH BASIN
SEPTIC TANK
SUMMARY
4.08%
4.99%
671,199.00

21.07%

933,000.00

29.30%

288,481.00

9.06%
184,004.00

5.78%
25.9%
100.00%
August 23, 2013
PROJECT: AMISTAD SPA (PLUMBING INSTALLATION)
LOCATION: 2/F Maybank Tomas Morato St., Quezon City
OWNER: AMISTAD
CONULTANT: ARCHT. JONATHAN LEONARDO, UAP
RE: THIRD PROGRESS BILLING (Updated)
Dear Sir,
We would like to request for the release of payment for our Third Progress Billing (Updated) f
or the project mentioned above, to wit;

ORIGINAL CONTRACT PRICE: PHP 550,000.00


Accomplishment to Date:
As of August 23, 2013 is NINETY- SIX PT. FORTY-TWO
PERCENT (96.42 %) 530,300.00
(See attached Progress Report-4)

DEDUCTIVE:
Recoupment from the Down Payment:
P 165,000.00 x 96.42 % = P 159,093.00
First Progress Billing 100,000.00
Second Progress Billing 130,000.00
Less Retention (10%) From original contract 55,000.00
SUB-TOTAL : PHP 86,207.00

ADDITIONAL:
Change Order No. 1(All pipe revisions, additional plumbing fixtures) P 23,493.00
Change Order No. 2(Repair works at restaurant, 2 nights) 2,340.00
Change Order No. 3(Removal of existing fixtures at old spa) 4,875.00
Change Order No. 4(Repair of pipe hole at restaurant, 1 night) 1,170.00
SUB-TOTAL-2: P 31,818.00
AMOUNT DUE THIS BILLING PHP 118,025.00

For 2 sets f 1.5 HP Pumps w/ Bladder tank of 24 Gals cap.(Optional) 120,000.00


AMOUNT DUE THIS BILLING:( If with pump) P 238,085.00

Submitted by: CONFORME BY:

Archt. Flynn B. Arana, uap,rmp Archt. Jonathan Leonardo, uap


Plumbing Contractor General Contractor

SAMPLE BILLING:

Das könnte Ihnen auch gefallen