C/M or P/M

Reviewed:
CONSTRUCTION JOB HAZARDS ANALYSIS
Electrical Work
Rev: 2015
Building & Room(s): Contractor/Subcontractor Name:

Project: Date:

Scope of Work: Please list the scope of work in this area. (and remove these directions).

Tasks being Performed Potential Safety Risks/Hazards Safety Controls / Mitigations


You are required to LOTO All hazardous & potentially hazardous energy sources.
Risk of Shock, Electrocution or (This includes working On or Near, Exposed or Potentially exposed energy.)
This is a TEMPLATE Arc Flash
An Approved LOTO permit or EEWP is Required before work begins.
Please identify your scope of work
along with your means & methods to Follow all details in the LOTO Permit or EEWP (Simple LOTO).
complete your scope of work.
Multiple energy sources will be indentified (Complex LOTO) and Approved Equipment LOTO procedures may be
Such As; required. (Check with P/M in charge with this Project)
-Roto hammering holes
-Installing uni-strut All LOTOs shall be Assisted & isolation of energy verified by LBL employees.
-Installing Conduit (unless otherwise noted per permit)
-Pulling wire
-Make up Procedures are to be Approved by Facilities prior to the start and release of LOTO.
-Start up
-Programming Proper PPE shall be worn in accordance with All Permits, Procedures & Calculations.

LOTO permits are obtained at http://electricalsafety.lbl.gov


Working on electrical < 50 volts Half face respirators are required for rotohammering drilling into concrete.
(Low voltage: No Permit Required ) Risk of exposure to silica based
products Respirator Program with medical eval & fit test shall be submitted for review & acceptance by EH&S prior to the start
Working on or near electrical > of work
50 volts
( LOTO Permit Required ) Ensure all Areas to be cored drilled have been scanned.
Risk of hitting unknown utilities.
Working on or near Exposed Follow Penetration Permit
Energized parts
( EEWP Permit Required ) Ensure all moving, rotating and potential hazards have been LOTOed prior to the start of work.
Risk of injury from mechanical or a
release of unexpected hazards Ensure that All Pipes, Hoses, hydraulic rams & lines have been bleed & blocked(blanked) at Point of Operation.

Employee Signatures: Date: Employee Signatures: Date: Employee Signatures: Date:

A signed copy of this JHA must be posted while the applicable subcontractor is working on-site and be available to any LBNL employee upon request.

1 of 1