ANALISIS DE PRECIOS UNITARIOS

OBRA: BUENAVENTURA PLAZA DE MERCADO


ITEM: CONCRETO 3000

UNIDAD M3 FECHA 5/11/2016


I - EQUIPO
DESCRIPCIN UND TARIFA RENDIMIENTO V/R VR PARCIAL
HERRAMIENTA MEJOR GLB 2,750.00 0.33 $ 907.50
MEZCLADORA DIA 42,000.00 0.03 $ 1,260.00
$ 0.00
$ 0.00
$ 0.00
SUB TOTOAL EQUIPO $ 2,167.50
II- MATERIALES
DESCRIPCIN UND TARIFA RENDIMIENTO V/R VR PARCIAL
ARENA M3 41400 0.53 $ 21,942.00
GRAVA M3 65550 0.80 $ 52,440.00
CEMENTO BULTO 30000 7.00 $ 210,000.00
$ 0.00
$ 0.00
SUB TOTAL MATERIALES $ 284,382.00
III. TRANSPORTE
DESCRIPCIN UND TARIFA RENDIMIENTO V/R VR PARCIAL
VOLQUETA TRANSPORTE MA
M3 25714.3 1.33 $ 34,200.00
$ 0.00
$ 0.00
SUB TOTAL TRANSPORTES $ 34,200.00
IV. MANO DE OBRA
DESCRIPCIN UND TARIFA RENDIMIENTO V/R VR PARCIAL
3 AYUDANTE-1 OIF HC 38,000 1.05 $ 39,900.00
$ 0.00
$ 0.00
$ 0.00
SUB TOTAL MANO DE OBRA $ 39,900.00
SUBTOTAL COSTOS DIRECTOS $ 360,649.50

V. COSTOS INDIRECTOS
DESCRIPCIN % VR PARCIAL
ADMINISTRACIN A 0.15 $ 54,097.43
UTILIDAD U 0.05 $ 18,032.48
IMPREVISTOS I 0.05 $ 18,032.48
IMPUESTOS ESPECIALES 0.05 $ 0.00
I.V.A SOBRE LA UTILIDAD 0.16 $ 2,885.20
SUBTOTAL COSTOS INDIRECTOS $ 93,047.57
TOTAL PRECIO UNITARIO $ 453,697.07
34500

65550

65550

41400 7

180000
25714.2857