PART-B

DETAIL OF QUANTITY
Bailey Bridge at ch.87+625

( 1x30m E/J to E/J,Open Foundation, Double truss single story stee

Item
Description Unit No. Length
No.
BRIDGES
6.01 Earth work in excavation of foundation for structure
complete including all leads and lifts as per drawing
and technical specification clause 304

In all types of Soil Cum


Abutment 1 6.20
Abutment 1 6.20

6.02 Backfilling behind abutment, wing wall and return wall


or any other area with selected granular materials of
approved quality complete as per drawing or technical
specification clause 305.

Abutment A1 - Straight portion Cum 1 3.6


Abutment A2 - Straight portion Cum 1 3.6

6.03 Providing and laying filter media behind abutment,


wing wall and return wall complete as per drawing and
technical specification clause 309 and 2504..

Behind Abutments Cum 1 4.8


Cum 1 4.8
Behind Return wall 2 3.30
2 3.30

6.04 Providing & laying plain cement concrete complete for


leveling course as per drawing and technical
specification section 1500, 1700 & 2100.

M-15 Grade Cum


Abutment 2 6.20
DETAIL OF QUANTITY
Bailey Bridge at ch.87+625

( 1x30m E/J to E/J,Open Foundation, Double truss single story stee

Item
Description Unit No. Length
No.
6.05 Providing and laying Reinforced Cement Concrete in
Foundation complete excluding Reinforcement as per
Drawing and Technical Specification Section 2100

Grade M-25
Abutment uniform portion 2 6.00
tapered portion 2 6.00

6.06 Plain Cement Concrete/ Reinforced Cement Concrete


for substructure complete excluding reinforcement as
per drawings and Technical Specifications Sections
1500, 1700 and 2200.

Grade M-25 Cum


Abutment A1 1 1 6.00
A2 1 1 6.00
Abutment Cap(I) 2 6.00
Abutment Cap(II) 2 6.00
Return wall A1 2 3.30
Return wall A2 2 3.30
Dirt wall 2 6.00
Bracket 2 6.00

Transverse Seismic arrestor 2 0.50


Longitudinal Seismic Arrestor 4 0.50

Grade M-40
Pedestal 4 0.80
Kerb Stone 0 0.30
DETAIL OF QUANTITY
Bailey Bridge at ch.87+625

( 1x30m E/J to E/J,Open Foundation, Double truss single story stee

Item
Description Unit No. Length
No.
6.07 Providing & fixing in position HYSD Fe 500D grade
reinforcement bars in foundations, substructures,
superstructure etc. complete as per drawings and
Technical Specifications Section 1600 or as directed by
Engineer.

i c) Footing 76.68 x 120/1000


ii) Sub Structure 106.12 x 150/1000

6.08 Supplying and fixing of bearings complete as per


drawings and Technical Specifications Section 2000.

POT cum PTFE bearings


a) Free Sliding POT Cum PTFE Nr. 4.00

6.09 Supplying and fixing of expansion joints complete as


per drawings and Technical Specifications Section
2600.

Strip Seal Type ( 100 mm ) 2.00 6.000

6.10 M15 Grade PCC below approach slabs as per drawings


and Technical Specifications Sections
Cum 2 6.00

6.11 Reinforced Cement Concrete in approach slabs


including reinforcement complete as per drawings and
Technical Specifications Sections 1500, 1600, 1700
and Clause 2704.

M-30 grade Cum 2 6.00


DETAIL OF QUANTITY
Bailey Bridge at ch.87+625

( 1x30m E/J to E/J,Open Foundation, Double truss single story stee

Item
Description Unit No. Length
No.

6.12 Providing weep holes in abutments, wing walls,


retaining walls, return walls etc. complete as per
drawings and Technical Specifications Clause 2706.
Nr.
Abutment,Return wall 68

6.13 Providing, fabricating and erecting structural


steel(IS:2062,Quality 'E' grade designation 410(BR))
including plainting viz tubular rolled sections, trusses, I
sections C sections, plates angles handrails etc.,
profiled to required shapes, as per drawings &
specifications including cost of insert plates, fasteners,
fabricating, jointing, welding, threading, cost of enamel
paints of approved make and colour, transportation to
final worksite, erection in position etc. complete with MT 1 48
all leads and heights as per hte drawings &
specifications and approval of engineer. (Note : Rate
shall include preparation of shop fabrication drawings
for the approval of Engineer).
TAIL OF QUANTITY
ey Bridge at ch.87+625

ation, Double truss single story steel Bailey Bridge )

Breadth Height Quantity

7.30 2.10 95.05


7.30 2.10 95.05
Total 190.09

3.90 8.25 115.83


3.90 4.50 63.18
Total 179.01

0.60 6.85 19.73


0.60 3.10 8.93
0.60 7.95 31.48
0.60 2.80 11.09
Total 71.23

7.30 0.10 9.05


Total 9.05
TAIL OF QUANTITY
ey Bridge at ch.87+625

ation, Double truss single story steel Bailey Bridge )

Breadth Height Quantity

7.10 0.30 25.56


7.10 0.60 51.12
Total 76.68

1.01 4.80 29.16


1.01 1.50 9.11
(1.325+1.325)1/2 0.50 7.95
1.325 0.50 7.95
0.60 7.95 31.48
0.60 2.80 11.09
0.30 0.97 3.47

(0.3+0.3+0.3)1/2 0.30 1.62

1.00 1.00 1.00


1.00 1.00 2.00
Total 104.84

0.80 0.500 1.28


0.30 0.300 -
Total 1.28
TAIL OF QUANTITY
ey Bridge at ch.87+625

ation, Double truss single story steel Bailey Bridge )

Breadth Height Quantity

9.20
15.92
Total 25.00

133.00 532.00

12.00
12.00

3.600 0.15 6.48

3.500 0.30 12.60


TAIL OF QUANTITY
ey Bridge at ch.87+625

ation, Double truss single story steel Bailey Bridge )

Breadth Height Quantity

12.60

68.00
Total 68.00

48.000
DETAIL OF QUANTITY

I PSC Girder M-45 grade


Sectional area at centre of Girder =1.05 x 0.15 + ( 1.05 + 0.29 )/2 x 0.1 =
1.1 x 0.29 =
0.75 x 0.25 + (0.29 + 0.75 )/2 x 0.15 =

Sectional area at support 0.75 x 1.559 + (1.05 + 0.75)/2 x 0.041 + 1.05 x 0.15 =

Total Quantity 1x1x4 [1.364 x 2+(1.364+0.809)1/2x1.5+0.809x10.65] x 2

II Cast in situ cross girder and slab


RCC Slab M-45 grade = 1x30 x 12x0.225 =
Cross girders on centre
1x1x0x (12x1.72-4 x(0.809-0.75x0.25) x0.45 =
Cross girders on end support
M-45 grade 1x2 x [12 x 1.72 -4 x (1.36365-0.75x0.25)] x0.45 =

Total Quantity =
DETAIL OF QUANTITY

0.225
0.319
0.266
0.809 Sqm

1.364

104.0

81.00 Cum

0.00 Cum

14.34 Cum

95.0
199.0
SUMMARY OF BOQ Bailey Bridge at ch.87+625

73+928
Item Total Quantity Rates (Rs) Amount(Rs)
Description Unit
No.
BRIDGES
6.01 Earth work in excavation of foundation for structure
complete including all leads and lifts as per drawing
and technical specification clause 304
In all types of Soil Cum 190.09 66.80 12,698.15

6.02 Backfilling behind abutment, wing wall and return wall Cum
or any other area with selected granular materials of
approved quality complete as per drawing or technical
specification clause 305.
179.01 1303.80 233,393.2

6.03 Providing and laying filter media behind abutment, Cum


wing wall and return wall complete as per drawing and
technical specification clause 309 and 2504.. 71.23 4131.40 294,263.10

6.04 Providing & laying plain cement concrete complete for


leveling course as per drawing and technical
specification section 1500, 1700 & 2100.
M-15 Grade Cum 9.05 7180.80 65,000.60

6.05 Providing and laying Reinforced Cement Concrete in


Foundation complete excluding Reinforcement as per
Drawing and Technical Specification Section 2100
Grade M-25 Cum 76.68 7332.00 562,217.76

6.06 Plain Cement Concrete/ Reinforced Cement Concrete


for substructure complete excluding reinforcement as
per drawings and Technical Specifications Sections
1500, 1700 and 2200.
Grade M-25 104.84 8817.00 924,343.42
Grade M-40 1.28 11324.90 14,495.87

6.07 Providing & fixing in position HYSD Fe 500D grade


reinforcement bars in foundations, substructures,
superstructure etc. complete as per drawings and
Technical Specifications Section 1600 or as directed by
Engineer.
T
25.00 75435.00 1,885,875.00

6.08 Supplying and fixing of bearings complete as per


drawings and Technical Specifications Section 2000.
POT cum PTFE bearings
a) Free Sliding POT Cum PTFE Nr. 532 296.00 157,472.00

6.09 Supplying and fixing of expansion joints complete as


per drawings and Technical Specifications Section
2600.
Strip Seal Type (40 mm ) RM 12.00 16811.00 201,732.00

M15 Grade PCC below approach slabs as per drawings


and Technical Specifications Sections
6.10 Cum 6.48 6904.60 44,741.81

6.11 Reinforced Cement Concrete in approach slabs


including reinforcement complete as per drawings and
Technical Specifications Sections 1500, 1600, 1700
and Clause 2704.

M-30 grade Cum 12.60 12651.00 159,402.60

6.12 Providing weep holes in abutments, wing walls,


retaining walls, return walls etc. complete as per
drawings and Technical Specifications Clause 2706. Nr. 68.00 229.10 15,578.80
Abutment,Return wall,median wall,Retaining wall
6.13 Erection of Double truss single story steel Bailey
Bridge as per drawing with required camber. Including
cartage of fabricated parts from the place of stack near
site including submission of launching plan by the
contractor, (duly weighted by a recognised reputable
institution/consultant if required) and approved by the
engineer-in-charge-. service bolts to used shall be of
GKW make or any other as approved by engineer-in-
charge, including cost of labour, T&P, equipmenta and
consumables required for proper completiion of the
work as per MORTH specification no. 1905 and as per
directions of the engineer-in-charge.
1. Add 15% extra for scaffolding, Ropes,
winch, chain pully and all other T&P and euipment
2. Red Oxide Zinc Chrome Painting conforming to
IS:2074, IS:1477 and IS:5666

MT 55 100000.00 5,520,000

TOTAL COST 10,091,214.3


Summary of Rate Analysis
Item No. Descriptions Unit
CHAPTER-12
FOUNDATIONS
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical
12.1 specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter,
dressing of sides and bottom and backfilling with approved material.)

I Ordinary soil
A Manual Means
(i) upto 3 m depth cum
(ii) 3 m to 6 m depth cum
(iii) Above 6 m depth cum
B Mechanical Means
(i) Depth upto 3 m cum
(ii) Depth 3 m to 6 m cum
(iii) Depth above 6m cum
II Ordinary rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m cum
B Mechanical Means cum
III Hard rock ( requiring blasting )
A Manual Means cum
IV Hard rock ( blasting prohibited )
A Mechanical Means cum
V Marshy soil
(i) upto 3 m depth
A Manual means cum
B Mechanical Means cum
VI Back Filling in Marshy Foundation Pits cum
Filling Annular Space Around Footing in Rock (Lean cement concrete 1:3:6 nominal mix. Rate may be taken as per
12.2 items 13.4.)
12.3 Sand Filling in Foundation Trenches as per Drawing & Technical Specification cum
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm
12.4 nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.) cum

Brick masonry work in cement mortar 1:3 in foundation complete excluding pointing and plastering, as per
12.5 drawing and technical specifications cum

12.6 A Cement mortar1:3 (1cement :3 sand) cum


B Cement mortar1:2 (1cement :2 sand) cum
C Cement mortar1:4 (1cement :4 sand) cum
D Cement mortar1:6 (1cement :6 sand) cum
12.7 Stone masonry work in cement mortar 1:3 in foundation complete as drawing and Technical Specification
(a) Square Rubble Coursed rubble masonry( first sort ) cum
(b) Random Rubble Masonry cum
12.8 Plain/Reinforced cement concrete in open foundation complete as per drawing and technical specifications
A PCC Grade M15 cum
B PCC Grade M20 cum
C RCC Grade M20
Case I Using concrete mixer cum
Case II With Batching Plant, Transit Mixer and Concrete Pump cum
D PCC Grade M25
Case I Using concrete Mixer cum
Case II With Batching Plant, Transit Mixer and Concrete Pump cum
E RCC Grade M25
Case I Using concrete Mixer cum
Case II With Batching Plant, Transit Mixer and Concrete Pump cum
F PCC Grade M30 Page 15 of 19
Case I Using Concrete Mixer cum
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum
Rate

113.00
146.00
194.00

50.00
57.00
71.00

162.00
63.00

409.00

478.00

486.00
129.00
364.00

1438.00

5353.00

7158.00

4900.00
6002.00
4166.00
3494.00

4211.00
3884.00

6162.00
6607.00

6641.00
7002.00

7154.00
7519.00

7195.00
7555.00
Page 16 of 19
7198.00
7556.00
PART-C
S.No. Description Unit Quantity Rates Cost

Dismantling structures & pavement including


disposal of resulting material and/or salvaging
1 useful materials with all lifts and leads complete as
per Technical Specifications Clause 202.

Superstructure
Parapet Wall (Stone Masonry) Rm 43.2 70 3024
RCC Girder cum 37.632 950 35750.4
Cross Girder cum 1.944 950 1846.8
Deck Slab cum 21.952 950 20854.4
Substructure
Abutment (Stone Masonary) cum 142.8 250 35700
Return Wall (Stone Masonary) cum 204 250 51000
Foundation (Stone Masonary) cum 152 250 38000

total 186175.6
Badethi Bridge (Ch. 87+625)
S.No. Description Cost

1 Construction cost of New 2 Lane Bridge 26754211.18998

2 Construction cost of New Temporary Bailey Bridge 10091214.3421

3 Dismantling cost of Existing Bridge 186175.6

Salvage value of the Steel Bailey Bridge Components


after its use for about 3 years during construction
period of the new permamnent bridge (considering
4 -3091200
20% cost for launching the bailey bridge and further
depriciation in cost of steel Bailey Bridge after 3
Years of its use)

Total Cost 33940401.13208