RESOLUTION NO. 03
SERIES OF 2016
WHEREAS, one of the priority project of this barangay is the improvement of its
Barangay Road network top enhance the mobility and social interaction of the
residents;
WHEREAS, this road becomes muddy and hardly passable to motorize vehicles
during rainy season thereby causing inconvenience to motorists and residents thereat;
WHEREAS, this body is aware of the thrusts of the Hon. Governor Manuel N.
Mamba in the concreting of Barangay road;
Certified Correct:
GRETCHEN C. MARAMAG
BARANGAY SECRETARY
SIMON S. BARIZO
PUNONG BARANGAY
CONCURRED:
NOEL C. CHUA
KAGAWAD
MEMORANDUM OF AGREEMENT
This memorandum of agreement made and entered in to this 13th day of December 2016 at
Tuguegarao City, Philippines by and between:
The PROVINCIAL GOVERNMENT OF CAGAYAN with principal office at the Capitol Hills,
Tuguegarao city, Cagayan, herein presented by its Provincial Governor, Hon. Manuel N. Mamba, and
herein referred to as First Party;
--and--
BARANGAY NATTANZAN, IGUIG, CAGAYAN (name of beneficiary) represented herein by its Barangay
Chairman SIMON S. BARIZO and herein after referred to as the Second Party;
WITNESSETH:
WHEREAS, under section 33 of RA 7610 otherwise known as the local government code 0f 1991, local
government units may undertake cooperative undertakings for their common benefits.
Whereas, the provincial government of Cagayan sees the importance of such joint undertaking for
effective local governance and in promoting general welfare;
Whereas, the provincial government of Cagayan is extending a financial assistance to the second party
for the augmentation of the concreting of barangay road.
Whereof, therefore, for and in consideration of the concerns and purposes of the parties, they
voluntarily agree and stipulate the following terms and conditions:
Section 1. The Project. This MOA governs the implementation of the augmentation of the concreting of
barangay road;
Section 2. Release And Use Of Project Fund. This party shall release the second party the fund within 5
days from the signing of the MOA. The second party shall use the fund only for the above mentioned
project;
Section 3. Period Of Implementation. The project has to be implemented within 45 days from the
release of the fund to the second party;
Section 4. Monitoring. The first party shall monitor the implementation of the project in the conformity
with the approved program of work and specification submitted;
Section 5. Return of UnusedFfunds. In the event that funds will not be utilized for the project, the
second party shall balance to the first party within 30 days from the completion of the project;
Section 6. Report and Liquidation. The second party shall provide the first party with the appropriate
report of implementation and liquidate the project funds within 30 days from the completion of the
project. The second party, upon the request of the first party shall make available all papers,documents,
reports and records relating to the project for inspection and examination.
Section 7. Amendment. Any modification or amendment of the terms, conditions and covenants of this
memorandum of agreement in order to be valid and binding must be mutually agreed upon in writing
by the parties.
Section 8. Effectivity. This agreement shall take effect on the date of signing hereof by the parties
concerned and shall be terminated upon the satisfactory fulfillment of all terms and conditions
embodied herein.
IN WITNESS THEREOF, the parties hereto affix their signatures on this instrument in Tuguegarao city,
Philippines this 13th day December 2016.
WITNESSETH
AKNOWLEDGEMENT
Who personally made known to me to be the same persons who signed this instrument and
aknowleged that this is their free act and indeed.
WITNESS MY HAND AND NOTARIAL SEAL, this 13th day of December 2016 at Tuguegarao City,
Philippines.
Series of 2016