Sie sind auf Seite 1von 6

Upgrading CO2 removal systems

Simple modifications to three carbon dioxide removal systems raised their


efficiencies with short payback periods

V K ARORA
Kinetics Process Improvements

A
cid gas removal is an impor-
tant step in petrochemi-
Treated
cal plants, refineries and syngas CO2 product
syngas production. This article
describes experience in cost effec-
tively upgrading CO2 removal sys- Water
tems in three ammonia plants with
an attractive payback of just a few
months. One of the plants uses a Absorber
MDEA system and the other two
use Benfield systems. A similar
approach can be used in acid gas Raw Stripper
removal systems in petrochemicals syngas
plants and refineries.
LC
MDEA based CO2 removal system
The existing single stage MDEA
CO2 removal system scheme is
shown in Figure 1. This conver-
sion of an old MEA based system
was implemented as a part of the Figure 1 MDEA-piperazine CO2 removal scheme
overall ammonia plant capacity
revamp from the original name- at the current operating conditions:
plate capacity of 600 t/d to about 20 15 10 5 0 Mass transfer limits of the
1100 t/d. The original absorber and existing packing type and height
stripper columns were used, with Adequacy/limitations of liquid
trays replaced with packings and distributor
other internals. The current oper- Adequacy/limitations of feed
ating capacity is 1140 t/d to 1170 Base vapour distributor
operation
t/d, depending on seasonal varia- Hydraulic adequacy/limita-
tion. This plant was stretched to its tions of the solvent circulation loop
design limits and beyond. Solvent and activator concen-
Dry density: 15 lb/ft3

A holistic review of the reference tration for optimal performance.


CO2 removal system was carried Figures 2-5 represent the base
out by KPI to identify all the poten- operating performance at 1140 t/d
tial bottlenecks contributing to a as modelled and reconciled with
shortfall in performance. To sup- actual operating performance. A
port this, the following steps were gamma scan of the absorber indi-
taken: cates the liquid density variation
Gamma scan of the columns to profile in Figure 2, with a variation
determine any maldistribution Figure 2 Absorber liquid density profile between 8 and 15 units indicating
Representative operating data maldistribution. The absorber is
corresponding to maximum operat- Simulation of the existing scheme operating at about 85% flood while
ing capacity to match the reconciled operating the stripper has enough hydrau-
Reconciliation of the operating data lic capacity available (see Figure 5).
data Evaluation of potential bottlenecks The absorber temperature profile in

www.eptq.com PTQ Q2 2017 67


fall in performance. The potential
0 causes identified in the absorber
2 system were:
Packing height, ft (top down)
4 Liquid maldistribution deter-
6 mined through gamma scan
8
Under-sized liquid distribu-
10
Base operation tor in the absorber, leading to
12
maldistribution
14
16
High momentum through the
18
vapour distributor in the absorber,
20 leading to maldistribution
22 Mass transfer limitations due to
24 short packing height and incorrect
26 loading
28 Hydraulics and mass transfer lim-
100 115 130 145 160 175 itations of the existing packing.
Temperature, F The stripper column did not indi-
cate any hydraulic or mass trans-
Figure 3 Absorber temperature profile fer limitations or any performance
issues.

0 Options to reduce CO2 slip


Packing height, ft (top down)

As the next step, several options


5 were evaluated with relevant inputs
Base operation
gathered from vendors. The fol-
10
lowing options were further simu-
lated and reviewed for improved
15
performance, including cost-benefit
20
analysis:
New efficient packing configura-
25 tions with improved mass transfer
and hydraulics
30 Increase in packing height, as
0 500 1000 1500 2000 2500 3000 3500 4000 noted later for different options
CO2 concentration, ppmv New liquid distributor
New feed vapour distributor
Figure 4 Absorber vapour CO2 concentration profile Increase in circulation rate
Optimise solution concentration.

0 New liquid distributor


The existing trough type V-notch
Packing height, ft (top down)

5 liquid distributors were inadequate


and considered less efficient for
10
the service conditions. They were
Base operation
15 replaced with new efficient ori-
fice deck distributors rated with
20 sufficient design margin over the
new service conditions for current
25
and future operating cases. Most
30 Stripper importantly, the new distributors
Absorber were designed for installation and
35 removal through the existing 17in
30 40 50 60 70 80 90
manways to facilitate correct load-
Flood, %
ing of packing.

Figure 5 % flood: absorber and stripper New feed vapour distributor


The existing feed vapour distributor
Figure 3 seems reasonable while the Potential causes of high CO2 slip was also found to be inadequate,
CO2 concentration profile in Figure Based on an initial evaluation, the with a much higher momentum
4 indicates about 2600 ppmv of CO2 absorber column indicated major than recommended and also insuf-
slip. limitations, resulting in a short- ficient coverage of the cross section.

68 PTQ Q2 2017 www.eptq.com


It was replaced with a T-type lat-
eral distributor rated with sufficient 0 Base capacity with existing packing

Packing height, ft (top down)


design margin over the new ser- Base capacity with new packing
5
vice conditions for both the current Future capacity with new packing
and future operating cases. Most 10
importantly, the new distributors
15
were designed for installation and
removal through the existing 17in 20
manways. 25

30
Increase in circulation and
hydraulics adequacy 35
Increasing the solvent circulation
40
rate was reviewed along with a 55 65 75 85
complete hydraulics evaluation of Flood, %
the lean circuit and the lean MDEA
pumps, with a clear premise not to Figure 6 % flood: absorber with new and old packing
replace any of the existing pumps
and drivers. Interestingly, a mar-
ginal increase in circulation rate 2000
Existing packing height (h)
was possible with replacement of
Modified height (h 127%)
the existing impellers at the maxi-
mum possible size, well within the 1500
CO2 slip, ppmv

maximum design rating of the exist-


ing drivers. Further, the impact of
1000
the higher circulation rate was also
evaluated for both absorber and
stripper columns with new pack- 500
ing type, size and different bed
configurations.
0
New efficient packing 1140 1250
To improve the limitations of both Plant capacity, stpd
mass transfer and hydraulics in the
absorber, new and efficient packings Figure 7 Performance estimation with modifications
from two suppliers were evaluated
with extensive in-house modelling and modelled performance, it was gated (see Table 1) with all the prac-
for their quantitative impact on per- decided to go ahead with only one tical constraints for this old column.
formance. The improved hydrau- deeper bed for the most value. Based on a thorough review of
lics with the selected new efficient all the options with the owners
packing with increased packing Incremental packing height and operations and engineering groups,
height (127% of the existing height) practical constraints together with the inspection his-
is shown in Figure 6 and compared The existing packing height was tory and construction group, it was
with the hydraulics of the existing determined to be a limiting fac- decided to pursue the maximum
packing for both base and future tor to achieve the target CO2 slip height option #3 with some hot
capacities (1140 t/d and 1250 t/d, despite changes with the most effi- work within the absorber column.
respectively). The hydraulic capac- cient packing and the vapour-liquid
ity of the absorber indicates a sub- distributors along with optimised Estimated performance
stantial improvement with the new solution concentration. Therefore, improvements
efficient packing. several options to maximise the The new performance of CO2
packing bed height were investi- removal is estimated using the
New packing configurations
The latest and most efficient proven
Options to maximise packing bed height
packings from two suppliers were
reviewed and modelled to evalu-
Option# Packing height CO2 slip target Bed configuration Tower modifications
ate their impact on CO2 slip and Base 100% of base Way below target Single Wall clips
hydraulics. A combination of split 1 112% Below target Single Wall clips
bed with two different packing 2 123% Closer to target Split bed Wall clips, complex supports
sizes with and without liquid 3 127% Meets target Single bed Wall clips and ring
redistributors was also reviewed.
Based on the detailed evaluation Table 1

www.eptq.com PTQ Q2 2017 69


new efficient packing, new efficient
60 vapour and liquid distributors and
1140 stpd

Incremental ammonia, stpd


an optimised solution concentra-
1250 stpd
tion. The performance with new
internals/packing with optimised
40
solvent is further compared for two
capacity cases using the modified
packing height (127% of the exist-
ing packing height) in the existing
20
absorber to provide the most value
with the least cost. The two capacity
cases compared are:
0 Base capacity (1140 t/d)
100 200 300 400 500 Future capacity (1250 t/d).
CO2 slip, ppmv The additional packing height
provides a significant reduction in
Figure 8 Incremental ammonia production with reduced CO2 slip CO2 slip to achieve a figure well
below 300 ppmv for the base capac-
ity and <500 ppmv for future capac-
1140 stpd Base capacity payback <8 months
ity (see Figure 7).
8
1250 stpd Future capacity payback <4 months
7 Incremental ammonia production
Simple payback, months

Reducing CO2 slip benefits ammo-


6
nia plant efficiency with a propor-
5 tionate increase in production for
the same amount of feed gas used
4
with high CO2 slip.
3 Incremental ammonia produc-
2 tion with improved performance
of the CO2 removal system for the
1
base operating capacity (1140 t/d)
0 and the future operating capacity
100 200 300 400 500 (1250 t/d) are estimated and shown
CO2 slip, ppmv in Figure 8. This indicates a capac-
ity and efficiency improvement of
Figure 9 Estimated payback of modifications about 2.4% for the base case and
about 3.6% for the future case.

Economics of CO2 removal system


Treated Flash / upgrade
syngas fuel gas
Based on the modifications being
LP flash carried out and the expected perfor-
Water Stripper mance improvements, the payback
CO2 period for the base case is estimated
product to be less than eight months and the
PC payback for the future capacity case
would be less than four months (see
Absorber
Figure 9). The basis of this estimate
is the incremental ammonia produc-
tion relative to the base case ammo-
Raw nia production corresponding to
syngas a high CO2 slip for the two capac-
ity cases and median netback on
LC HP flash ammonia.

Additional CO2 removal schemes


under review
Another MDEA based two stage
CO2 removal system is under
review for high CO2 slip and corro-
Figure 10 MDEA-piperazine scheme: two stage sion related issues (see Figure 10).

70 PTQ Q2 2017 www.eptq.com


ment space in the absorbers and
Treated syngas to syngas knockout drums could
methanator feed / lead to channelling with inefficient
effluent exchanger vapour-liquid separation.
Make-up water quality with
CO2 carry-over of any undissolved sol-
Syngas ids could eventually deposit in the
KO drum downstream methanator feed/efflu-
ent exchangers.
Excessive foaming could poten-
LP
steam Eductor flash tially result in carry-over.
system Lower velocities with carry-over
coupled with higher localised tem-
perature in the downstream meth-
anator feed/effluent exchanger
could promote fouling rates.
Absorber Stripper
Findings and recommendations
Semi-lean Based on an adequacy check and
Feed pump further analysis of the absorber
overhead system, the following rec-
ommendations were made based on
the findings:
The vapour-liquid disengagement
Lean
pump space in the syngas knockout drum
was found to be inadequate. This
was considered to be a significant
Figure 11 Benfield process schematic for ammonia plants 2 and 3 cause of uneven flow distribution
and channelling, resulting in poor
Benfield CO2 removal system in carry-over, KPI was engaged separation efficiency and potential
The existing Benfield process to study and review the poten- carry-over.
scheme for CO2 removal in ammo- tial deficiencies and recommend The existing slotted pipe feed dis-
nia plants 2 and 3 is shown in Figure suitable cost effective improve- tributor was recommended to be
11. Both plants operated at about ments to minimise or eliminate the replaced with an even flow distrib-
108% of their name plate capacity carry-over. utor to overcome this limitation.
of about 2000 t/d and consistently The following potential causes of Recently replaced demister pads
experienced a significant carry-over carry-over were identified: in the absorbers and syngas knock-
from the absorber, resulting in out drums of both plants were also
pressure drop build-up across the found to be inadequate to efficiently
downstream methanator feed/
Reducing CO2 slip capture the smaller liquid droplets,
effluent exchanger. Based on plant
historical data, the system segment
benefits ammonia potentially resulting in carry-over.
It was recommended that the
pressure drop increased from 20 plant efficiency with demister pads be replaced with a
psi to 30 psi in about three months, new design using a combination of
resulting in a gradual reduction in a proportionate co-knit polymer with metal.
ammonia production and in the Syngas velocities in the shell
plants efficiencies. This situation increase in production side of the feed/effluent exchang-
forced the operators to undertake ers were initially concerning but
a short plant shutdown every three for the same amount no modification was warranted
months to clean up the exchanger, as the intent was to simply min-
which also resulted in additional
of feed gas used with imise or eliminate carry-over as
loss of ammonia production for
nearly 10 hours with reduced plant
high CO2 slip opposed to pushing the carry-over
through higher exchanger veloc-
reliability. This problem contin- ities into the downstream cata-
ued despite replacement with new A significant fraction of smaller lyst beds. Therefore, no change in
efficient liquid distributors and droplets (<10 microns) in the the downstream exchanger was
demisters in both the absorbers and carry-over: recently replaced sep- recommended.
syngas knockout drums. aration devices were considered A phase 2 recommendation was
Following replacement with new inadequate to efficiently capture the made for an in situ spray system for
liquid distributors and demisters smaller droplets. the syngas knockout drums, should
with only marginal improvement Insufficient vapour disengage- the recommended modifications

72 PTQ Q2 2017 www.eptq.com


34
Pressure drop, 30 Just before modifications
After modifications
26
lb / ft3

22
18
14
10

0
0
0
0
0
0
0
0
0
0
0
0
0
0
30
60
90
12
15
18
21
24
27
30
33
36
39
42
45
48
Elapsed time, days

Figure 12 P trend before and after modifications

in phase 1 not yield the expected Conclusions


performance. High CO2 slippage is a common
problem in ammonia plants as well
Modifications as acid gas removal systems in pet-
Based on the above findings and rochemical plants and refineries. It
recommendations, the following mainly occurs when plant capaci-
modifications were engineered ties are stretched with the following
and supplied through KPI for both common limiting factors:
plants: Limited mass transfer due to:
Special co-knit polymer demisters Inadequate vapour/liquid
for the absorbers and syngas knock- distribution
out drums in both ammonia plants Inefficient packing
Even flow distributors engineered Packing height limitations

to be supported within the existing Heat transfer limitations due to:


vessels without any hot work on Cooling

the vessel shell. Reboiling

Insufficient circulation due to lim-


Performance improvements iting pump capacities:
A performance chart of the P Non-optimal solution concentration.
trend over more than 450 days, KPI implemented simple and cost
before and after the modifications, effective solutions with a MDEA-
clearly indicates a fairly steady piperazine based system in an
pressure drop (see Figure 12). No ammonia plant with a payback
plant shutdown or any loss of period of four to eight months.
ammonia production was experi- Carry-over in a Benfield CO2
enced for the next four years before removal system is experienced in
a turnaround for the lingering car- several plants. Plant operators have
ry-over problem in both ammonia adopted different measures to miti-
plants. The simple modifications gate this problem. KPI successfully
were successful and were carried implemented simple and cost effec-
out within a day. tive systems in two large ammonia
Further, the phase 2 recommen- plants with a payback of less than
dation to include a spray sys- three months.
tem was not required during this
period.

Economics of a CO2 removal V K Arora is Director of Process & Operations


system upgrade with KPI through its Houston & Bahrain
offices and is the companys founder. He has
The modifications implemented
led and directed development of two major
were very simple and engineered
petrochemicals projects in Saudi Arabia and
and supplied within a month. They several revamps. Prior to joining KPI, he was
were installed quickly within a day with CBI/Lummus in various positions. A
shift by the operator. Based on a licensed professional engineer in the state of
reclaim of production lost following Texas, he holds a chemical engineering degree
the modifications, the real payback from IIT, Delhi.
time was less than three months. Email: vka@kpieng.com

www.eptq.com PTQ Q2 2017 73

Das könnte Ihnen auch gefallen