The Three Phases of Mine Planning

November 14, 2014


By GEOVIA Team
This is Part Three in a series on Strategic Mine Planning by Darrienne Thobaven,
one of our Strategic Mine Planning Knowledge Consultants. Part One focused on
Putting the Strategy Back into Strategic Mine Planning. Part Two discussed Taking
the Pain out of Tactical Planning.
A good quality mine plane employed to avoid this tactical planning pain in an open
cut mine.
The threePV Schedules
The first phase results in practical NPV-based schedules. The schedules include pit
stage selection (chosen from a series of nested pit shell candidates and Lerch
Grossman algorithm, the truly strategic planning begierefore, optimum interim pit
shell selection is vitplanning success. Interim pit shells are not an input to the
schedule, bunterim pit shells are not an input to the schedule, but ra
The threePV Schedulese from.
The pit shells also need to be modified for minimum mining dimensions while
minimizing the reduction in NPV. GEOVIA Whittles NPVP module automatically finds
the pThe Three Phases of Mine Planning
November 14, 2014
By GEOVIA Team
This is Part Three in a series on Strategic Mine Planning by Darrienne Thobaven,
one of our Strategic Mine Planning Knowledge Consultants. Part One focused on
Putting the Strategy Back into Strategic Mine Planning. Part Two discussed Taking
the Pain out of Tactical Planning.
A good quality mine plane employed to avoid this tactical planning pain in an open
cut mine.
The threePV Schedules
The first phase results in practical NPV-based schedules. The schedules include pit
stage selection (chosen from a series of nested pit shell candidates and Lerch
Grossman algorithm, the truly strategic planning begierefore, optimum interim pit
shell selection is vitplanning success. Interim pit shells are not an input to the
schedule, bunterim pit shells are not an input to the schedule, but rather an
output of an automated scheduler which has all of the pit shell candidates to
choose from.
The pit shells also need to be modtrategic planning success. Interim pit shells are
not an input to the schedule, but rather an output of an automated scheduler which
has all of the pit shell candidates to choose from.
The pit shells also need to be modified for minimum mining dimensions while
minimizing the reduction in NPV. GEOVIA Whittles NPVP module automatically finds
the p Lerch Grossman algorithm, the truly strategic planning begierefore, optimum
interim pit shell selection is vital for strategic planning success. Interim pit
shells are not an input to the schedule, but rather an output of an automated
scheduler which has all of the pit shell candidates to choose from.
The pit shells also need to be modified for minimum mining dimensions while
minimizing the reduction in NPV. GEOVIA Whittles NPVP module automatically finds
the p