Sie sind auf Seite 1von 5

PAPER DESIGN OF LOW-PROPPED EMBEDDED RETAINING WALLS IN STIFF CLAYS

Recent. papers have discussed the construction of embedded retaining walls which are propped at or close to excavation
level. The advantages of such a method of providing restraint are significant, and the use of this structural form has been
most commonly adoptedin transportation projects such as highway and railway underpasses. This paper considers the
available methods of analysis and design and concludes that the common assumptions and earth pressures adopted are
not truly representative. While the walls already constructed are safe in terms of stability, they may be overlong. A
modified pressure distribution has been adopted and shown by numerical analysis to be conservative. Significantly
shorter depths of wall embedment are predicted for this structural form, associated with potential major cost savings.
The use of numerical analyses, with careful modelling of construction sequences, is considered to be a fundamental and
important aspect of design. The Observational Method is the most suitable for assessing and utilising the available short
term properties of stiff overconsolidated clays.

ed whereby the required embedment is determined by equating the


moments of limiting active earth pressures to those of the limiting pas-
',lesic n sive earth pressures divided by a factor of safety. The reason for fac-
toring passive pressures is to provide a gross factor on failure, and to
o~'w-
limit the relatively large movements that would be required to develop
the limiting passive pressures. For heavily overconsolidated clays

~ro s )ec (Potts & Fourie, 1986) similar magnitudes of displacement are required
to reach both of the limiting states.

el'ec ec c
Low level support
There are situations where the use of high level support may not be
practicable, for example in deep road cuttings where lines of sight
would be impaired; ground anchors may not be acceptable where they

reI:aininc! wa s in have to be installed beneath property or because of concerns with


durability or maintenance. An option which has received attention
recently is to use a propping system which is at or below the final exca-
vation level. Examples of road schemes where this has been adopted

sl,'ill'c aI!ts include several underpasses on the A406 in London, the Blackwater
Valley road scheme, and the Batheaston Bypass. The propping action at
low level is provided by either discrete props below the finished car-
riageway level, or as is more commonly the case, by the carriageway
Steven Evetton, Senior Project Engineer, Sir Alexander slab itself. The merits of these forms are discussed later. By moving the
Gibb L Ptns Ltd, Earley House, London Road, Reading, permanent prop close to the excavation level, and therefore closer to
the centre of the wall, the load transfer from the earth to the wall and
Berkshire RG61BL. then to the prop is a more efficient process.
An examination of the geometry of several constructed walls sug-
e use of retaining walls formed in situ allows a considerable gests however, that no clear difference in wall lengths has been made by
reduction in the space required to be taken when compared with the use of low level propping, even though it would be expected to be
construction of traditionally backfilled walls, and reductions in more efficient. From the published literature the as-constructed
construction periods. With in situ walls excavation follows installation. embedment ratios (defined as the ratio of wall embedment to retained
Stability of the system is provided by embedment of the wall below for- height) from eight schemes have been collated. These are shown on
mation level, or by propping. Figure 1, and are seen to range between 0.9 to 1.9. The embedment
The design of embedded walls, which are commonly of sheet pile, ratios adopted in numerical analyses in research projects also follows
secant or contiguous pile, or diaphragm panel construction, includes a trend of embedment ratios close to or greater than unity
the determination of bending moments and shear forces imposed on (Nyaoro,1989; Li, 1990; Miles, 1991; Richards & Powrie, 1994). Figure 1
the structure due to earth and water pressures. These pressures vary also shows the trends of a study performed by Mott McDonald (1992) of
with time as a result of the construction sequence, imposed sur- retaining walls on roarl schemes in the London area. It can be seen that
charges, magnitude of deformation, changes in soil properties and the embedment ratio increases with retained height for high propped
groundwater conditions. walls, but decreases for low-propped walls.
Historically, the assessment of earth pressures acting on structures
has been studied at least as far back as Coulomb's memoires. The devel-
opment of active and passive pressures adjacent to unpropped can- ~ Walthamstow
tilever walls is well understood, where wall and ground displacements
are sufficient to develop these limiting states of stress. Mott McDonald ~ Rayleigh Weir
Review '.
(low prop)
Use of support L
The incorporation of support to a wall in either the temporary or per- A406
manent case allows for greater earth and water pressures to be resist- O Great Cambridge
ed, greater heights to be economically retained and serves to reduce
displacements of the wall. The effect of a support on the development Mott McDonald,
of active and passive earth pressures is not necessarily straightfor- Review
ward however. For double or multi-propped walls empirical or complex (high prop) A3 (Maiden)
Waltham
numerical methods are relied upon for design. stow,'lackwater

If the wall is singly supported then the system becomes statically Valley
determinate and the relatively simple conventional equilibrium meth-
ods are used. Design standards and codes of practice, based on the
experiences of observations and back analyses, recommend the use of
the limiting active and passive pressures on the retained and excavat-
0 0''
ed sides for design. CIRIA 104 gives a series of definitions for the appli- .':1.' . 8,,:.;4':6':,::..'6'---'8,::",,"9"':10"'".1'I 12;;;...18"t4
cation of a factor of safety which serve to increase the wall length, Retutrse'd.height,:(Iii)
reduce the resisting earth pressures by an amount, or by limiting the
available strength of the soil. Commonly the 'CP2'efinition is adopt- Ftgure f.As constructed ernbedments for several low-propped walls ln london Clay.

GROIIND ENGINEERING OCTOBER 1996 37


PAPER DESIGN OF LOW-PROPPED EMBEDDED RETAINING WALLS IN STIFF CIAYS

Hyd

water pressure

< Hydr

KA (y(h+d) -uJ yield+


J KR(yd - uj KF (y (h+d) - u J K~(yd - uj
y (d+ J

Rgure 2. Conventtonal assumed earth and water pressure dlstrlbutlons for an Rgure 4. Shnln compatible earth pressures for an embedded wall singly propped at
embedded wall singly propped at high level. low level, due to Nyaoro. G ross pore water pressure distribution as Figure 2.

High prop (1<FF<2)

Ka jyh - uj ster pressure

Kp fyh - uj

Low prop (1<Fp<2)

'f'5"::.:::;:::.::::::::S}:::::::::':": :'30::::;:::;:::.:'3S:::::
35::::::'::.":: '::":.:'40.:::::::': -"::4S
Kp (y (h+d) - uj KA (yd - uj
'Ar'igle 'Of frioburi '(:)

Rgure 3. Fugy reversed earth pressures for an embedded wag singly propped at low Figure g. Embedment ratio for singly propped embedded walls
lmrel. Gross pore water pressure distribution as Figure 2.

The codes and standards governing embedded wall design (BS8002, In the case of a low propped wall however, the situation changes. For a
CIRIA 104) give little guidance for designing low-propped walls. CIRIA 104 perfectly rigid wall the mode of deformation is rotation about the low
does however state that limit equilibrium techniques are only applicable prop, and it is assumed that the wall above the prop moves towards the
in cases where the prop is close to the top of the wall. If the limit equilib- excavation. This deformation mode has been studied by Li (1990),
rium methods themselves are not really suitable, then the use of conven- Nyaoro (1989) and Miles (1991) using numerical techniques. They con-
tional factors of safety (which were in reality empirically determined) firmed this forwards type rotation for relatively small embedments,
have no basis in design, unless they can be shown to be conservative. and a backwards rotation for relatively deep embedments. An interest-
ing point was seen in Nyaoro's work where it was impossible to simu-
Factors of safety and earth pressures late mass failure of the wall purely by placing large surcharges on the
In conventional calculations (CP2 method) a triangular active pressure retained side. Failure was only inevitably caused by structural failure
distribution is generally considered to act against the wall, being of the wall or prop.
resisted by a triangular passive distribution (Figure 2). A net water The forward rotation mode is often noted by designers, but has lead
pressure distribution with linear seepage around the toe of the wall is to a rigid use of active and passive limits in the zones surrounding the
commonly adopted. The assumed mode of deformation is of rotation of wall (eg Symons, 1992). Figure 3 shows the resulting pressure distrib-
the rigid wall about the prop towards the excavation. The active earth ution from these assumptions. As a result of the assumed stress rever-
pressures and the net water pressures are treated as overturning sal a major stress discontinuity occurs in the retained soil immediate-
moments, and the passive pressures as restoring moments. Note that in ly behind the prop. For a plastic clay (say (l = 22') the ratio of this dis-
this definition net water pressures are used in order to prevent factor- continuity (KF/KA) is approximately 5, and for a dense granular soil
ing them, as they are usually more accurately and reliably determined. (g = 40') the ratio is approximately 20. Bolton 5 Stewart (1994) consider
The conventional definition of factor of safety on moments (CP2 defin- a horizontal frictionless discontinuity at this level to simplify the
ition) is thus: analysis. In practice this is considered to be unreasonable, as at this
level immediately behind the wall the soil will undergo little, if any,
Restoring Passive shear strain due to being restrained by the prop, and the soil will not
Overturning Active + Net Water approach the strain softening region of its stress-strain behaviour.

3g ('RDDND FNGINEFRING 0(yroRRR 1996


PAPER DESIGN OF LOW-PROPPED EMBEDDED RETAINING WALLS IN STIFF CLAYS

Depth r
O(( (mmumrdd( SUMQB (ud(u"( (dd( SU (measured) SUMQB/SU
(m) (kN/m') (kN/m') (kN/mz) (%)
I excavated retained excavated retained
-: Bell Common retained height 8m 2 170 65 105 62
4.5 205 58 120 48
6 85 18 75 23
9 80 50 90 11
12 160 40 110 5
Walthamstow retained height 8.8m 3.5 387 159 150 106
(Carswell et al) 5.5 321 106 150 70
8.7 383 105 120 87
2.8 56 0 45 0
9.6 204 6 100 6
16.2 359 18 150 12
Rayleigh Weir retained height 8.5m 2.2 200 78 104 75
6 271 76 123 62
10 337 69 143 48
15.3 659 177 169 104
6 94 13 80 16
8.5 180 5 93 5
14.7 333 20 124 16
21.3 459 17 133 12

Depending on the nature of the soil it is unlikely that the full passive over the whole length for example, thereby giving a false indication of
limit could be reached at this depth to provide resistance to overturn- factor of safety.
ing. At the toe of the wall however the strains may be sufficient for the
passive pressures to develop. To account for this, Nyaoro proposed the Effect of method of analysis on wall embedment
pressure distribution shown in Figure 4. The actual effect of the low prop on stability and embedment is shown
With both of these pressure distributions the definition of factor of on Figure 5. Embedments were calculated using effective stresses for
safety necessarily changes, as restoring moments are instead generat- a c'=0 material in saturated conditions. There are significant reduc-
ed in the retained earth, and overturning moments are generated on tions in wall length due to the use of the low prop, and embedment can
the excavated side. Taking the essence of the CP2 definition to be be seen to be relatively independent of both factor of safety and angle
restoring moments divided by overturning moments, a quite sizeable of friction.
net water pressure acts here to provide stability. In line with general The simple calculations were extended by considering a real design
practice, water pressures would not be factored. However, care must be case. A series of calculations for a wall retaining 8.5m of saturated
taken where water conditions may not be (returnedfully understood or are granular material, embedded into London clay were performed to
unable to be relied upon (for example, leakage through the wall would determine the variation in calculated embedment for various assump-
in this case serve to reduce the stability of the wall) and it may be nec- tions regarding propping, factors of safety and mobilised soil
essary for factored water pressures to be included. strengths. This process is typical of that commonly performed for the
The factor of safety equation now becomes: actual design of a specific wall. For the low propped sections Nyaoro's
Restoring Passive Ide)
distribution was used. The results are summarised on Figure 6. It can
P be seen that, were common design practice to be followed rigidly (using
Overturning Active(umumd >+ Net Overturning Water Net Restoring Water the current recommendations of CIRIA 104 say) then the short term
temporary construction case (with a high prop) would govern wall
This fundamental point can be relatively easily addressed in limit equi- length, and the benefits of the low-prop system would not be obtained.
librium calculations performed by hand. Extra care needs to be taken, This may well be the reason for the deeply embedded low-propped walls
however, when using computer software for the calculations. Some shown in Figure 1.
codes may automatically assume active pressures on the retained side The reason why the temporary case is significant is due to the con-


ni I)rs 1.35

mp"-tomf iljjsla:l(p,:,::,=,,:,:i5),: 0.8

liiis ~la; wutiBI'rs(Ss


8.6
piiap= relained off ive slrese; exon ed - late( stress
P'=.2'0) 8.4
3.3

oryu prop; femian sroo geatiue.gfreW; total:Oficog.eigevrhere



(FP 8 0) 4.9
((Fm = $.,6) 3.8

Love peiriiansnt pgop ar. 1 gm bid: el(ective stress (pP m r 8)

Ldwper(r(snerrtprapsfror(baal=-nurr(erlcal yarsmdlridaiody(ps~ I 9) ------------------- 34


t I d I \
4 6 8
Ernbedntsntu length far 8.5m retained height (rn}

Figure 6. Calculated wall embedment for an 6.6m retained height using a variety of design assumptions.

GROUND ENGINEERING OCTOBER 1996 39


PAPER DESIGN OF LOW-PROPPED EMBEDDED RETAINING WALLS IN STIFF CLAYS

rary works design. The aim is to reduce cost and save time whilst assur- Conclusions
ing safety. The rigid use of limiting earth pressures has been examined and found
Powderham (1994) presents a case study of retaining walls for the to be not truly representative for the design of low-propped walls. The
Channel Tunnel. The Observational Method was used to reduce the simplistic assumption of fully reversed pressures below the prop pro-
amount of temporary support required for a multi-propped wall. The vides a design which relies on passive pressures which are unlikely to
design was based on CIRIA 104's 'mixed total/effective stress'pproach be developed in practice. Rigid and consistent definitions of factor of
using 'most probable'arameters. Even so, this approach was consid- safety need to be adopted and care taken with the use of historically
ered to be conservative due to the use of plane strain analysis, and a determined factors.
relatively high factor on restoring moments. Construction/excavation Design in heavily overconsolidated clay using current recommenda-
was monitored and kept within predefined tolerances by control of tions developed for other propping conditions provides a considerably
phasing of works. Additional propping was available in the case of tar- overconservative solution. A modified earth pressure distribution pro-
get measurements being exceeded. Excavation phasing was controlled posed by Nyaoro which accounts for low strains close to the low prop,
by limiting the maximum width open at any one time, thereby not rely- in conjunction with a mixed total/effective stress approach using con-
ing on any three-dimensional behaviour of the ground. Following ventional factors of safety, has been shown to produce an economic yet
small measurements of wall movements this width was increased to still safe and conservative design.
ease construction without compromising stability or serviceability. Numerical methods are recommended as a fundamental part of the
This is a good example of how an observational approach could be design of low-propped walls. This will enable the potential cost savings
adopted for low-propped walls in stiff clays, whereby contingency mea- to be realised in reducing wall lengths, and allow better determination
sures (such as additional propping or the ability to partially backfill if of bending moments, shear forces and displacements. Observational
necessary) are provided for the short term case in order to obtain the techniques should be adopted wherever possible in the construction of
benefits of reduced embedment for the permanent (long term) case. low-propped walls.
Other aspects of wall design
The design of walls has been centred in this paper on determining a Bolton, MD & Steward, DI (1994). 'The effect on propped diaphragm walls of rising
safe economic wall length. The numerical analyses are an important groundwater in stiff clay'. Geotechnique 44 Nol.
BS 8002 (1994). 'Earth Retaining Structures'. BSI.
part of the general design process however because, for this structural Carder, DR; Carswell, IG & Watson, GVR (1994). 'Behaviour during construction of a
form, the use of lower bound soil strength parameters is not conserva- propped diaphragm wall in stiff clay at Walthamstow'. TRL Project Report 17.
tive. This can be seen in the increase in bending moments in the wall Carswell, I; Carder, DR & Gent, AJC (1993). 'Behaviour during construction of a propped
beneath the prop when soil strength increases. As interpretation of contiguous bored pile wall in stiff clay at Walthamstow'. TRL Project Report 10.
Darley, P; Carder, DR & Alderman, GH (1994). 'Behaviour during construction of a
soil parameters is generally a highly conservative process, this does propped contiguous bored pile wall in stiff clay at Rayleigh Weir'. TRL Project Report 23.
not provide a correct approach to design. Attempts must be made for Li, ESF (1990). 'On the analysis of singly-propped diaphragm walls'. PhD Thesis,
this case to determine the 'best estimate'r 'most probable'arameters University of London.
Miles, SR (1991). 'On the stability of retaining walls propped at carriageway level'. MSc
and design accordingly. Thesis, University of London
The structural design work which needs to be considered is usually Mott McDonald (1992). 'LRO retaining wall review'. Proceedings of the Retaining Wall
directed towards the form of the permanent prop and its connection to Symposium, Department of Transport, London Regional Office.
the wall. Two options which have been considered are: Naoro, DL (1989). 'Analysis of soil-structure interaction by finite elements'. PhD Thesis,
University of London.
~ discrete reinforced concrete props below carriageway level; and Padffield, CJ & Mair, RJ (1984). 'Design of retaining walls embedded in stiff clay'. CIRIA
~ a continuous unreinforced slab forming the road carriageway. Report 104.
The choice of option is not straightforward, although it is interesting Peck, RB (1989). 'Advantages and limitations of the observational method in applied soil
mechanics'. Geotechnique 19 No2.
to note that recent designs performed by contractors tend towards the Potts, DM & Fourie, AB (1984). 'The behaviour of a propped retaining wall: results of a
slab, suggesting cost, time and ease of construction benefits. numerical experiment'. Geotechnique 34 No3.
Designs with discrete props usually place the props sufficiently Powderham, AJ (1994). 'An overview of the observational method: development in cut
below the road carriageway to allow for installation and maintenance and cover and bored tunnelling projects'. Geotechnique 44 No4.
Richards, DJ & Powrie, W (1994). 'Finite element analysis of construction sequences for
of drains placed above them. This requires greater depths of excava- propped retaining walls'. Geotechnical Engineering, Proc Institution of Civil Engineers
tion, and hence a deeper wall. There are also concerns with ride quali- 107.
ty over the props. Symons, IF (1992). 'Design of embedded retaining walls in stiff clays'. TRL Research
For the unreinforced slab, the system relies on the self-weight of the Report 359.
Tedd, P; Chard, BM; Charles, JA & Symons IF (1984). 'Behaviour of a pi'opped embedded
slab and the compressive forces from the walls to overcome any tensile retaining wall in stiff clay at Bell Common Tunnel'. Geotechnique 34 No4.
actions caused by heave of the ground. Attention has to be given to the
expected long term heave, and to providing suitable drainage measures
to deal with this throughout the design life of the wall. Any build up of
water pressure beneath the slab will reduce its effective self weight and
reduce its stability. Other options are to precamber the slab/prop such
that the heave forces serve to prestress it, or to provide a tension pile at
the centre of the excavation.
Whichever option is adopted, its connection to the wall must be con-
sidered. 'Pinned'oints have been constructed using PTFE coated semi-
circular seatings for both individual props or slabs. For partially or
fully fixed connections the possibility of transfer of moments from the
wall to the prop, or vice versa, should be addressed. Analyses show that
with discrete props the wall transfers quite sizeable moments to the
props due to the large relative stiffness between the wall and the prop.
With continuous slabs the stiffnesses are of similar order. It is also pos-
sible for a sufficiently stiff slab to transfer moment to the wall during
long term heave.
The measurements of prop forces and bending moments from the
instrumented schemes are important. Most, if not all, cases show that
the major factor in prop loads is temperature, with large daily varia-
tions being recorded. Experience seems to show that measured loads
are significantly less than those 'predicted'uring design. This is prob-
ably due to overconservatism in design, 'poor'implistic methods of
analysis, and the effects of construction sequence. It may also be linked
to the low bending moments which have been measured in the instru-
mented walls. At Bell Common this was attributed to the low stresses
measured in the Sm zone behind the wall. It is not clear however
whether the pressures will come back onto the wall in the intermediate
to long term. It would not be unexpected for the prop forces to then also
increase. Without further long term measurements it would not be pru-
dent to reduce safety factors in permanent prop design.

GROUND ENGINE()RING OCTOBER 1996


41

Das könnte Ihnen auch gefallen