APPENDIX J

PERT-CPM

Project Name: Construction/ Eco-Park Adventure Zip line


Location: Brgy. Cabibihan, Caibiran, Biliran
Duration: 103 Calendar Days

Event Duration ES EF LS LF TF FF CRITICAL


Scope of Works
ID (day) (Earliest Start) (Earliest Finish) (Latest Start) (Latest Finish) (Total Float) (Free Float) PATH
A 1-2 Clearing and Demolition 10 0 10 10 20 10 10
B 1-3 Structure Excavation/Grubbing 7 0 7 6 13 6 6
C 3-4 Embankment 7 7 14 13 20 6 6
D 1-4 Purchase of Materials/Delivering of Materials 20 0 20 0 20 0 0 **
E 2-4 Dummy 0 10 10 20 20 10 10
F 4-5 Positioning of steel bar for footing 7 20 27 20 27 0 0 **
G 5-6 pouring of footing 10 27 37 27 37 0 0 **
H 6-7 Layout installation for column 5 37 42 37 42 0 0 **
I 7-8 Welding and steel connections 25 42 67 42 67 0 0 **
J 8-9 Installation for floor framing 10 67 77 67 77 0 0 **
K 8-10 Installation for roofing 7 67 74 84 91 17 17
L 9-11 Installation of cable wire and accesories 14 77 91 77 91 0 0 **
M 10-11 Dummy 0 74 74 91 91 17 17
N 11-12 Painting 7 91 98 91 98 0 0 **
O 12-13 Move out. 5 98 103 98 103 0 0 **

Legend: ES EF
LS LF
TF FF

CRITICAL PATH = D/F-G-H-I-J/L/N-O


Total Duration = 103 Calendar Days