Beruflich Dokumente
Kultur Dokumente
Downloaded from ascelibrary.org by GADJAH MADA UNIVERSITY on 03/04/15. Copyright ASCE. For personal use only; all rights reserved.
INTRODUCTION
At present, ground settlement caused by the excavation of new tunnels has been a
great issue in complex construction situations. Due to limited underground space or
unchangeable design layout, new tunnels will inevitably go under existing
underground structures, such as pipelines, tunnels, underground metro stations and
other similar structures. The excavation of a new tunnel will induce displacement in
these underground structures. Numerous damages in underground structures were
reported in the past decades (Kastner et al. 2003; Kunita et al. 1994).It is
indispensable to investigate the tunneling effects imposed on the above existing
structures although it is difficult to estimate the influence of new excavation activities
on them. Little research has focused on the evaluation of tunneling-induced
subsurface settlements. Mairet al. (1993) and Loganathan (1998) proposed theoretical
methods to estimate subsurface settlements caused by new tunnel excavation, but
little effort was put into ground volume loss control as well as the assessment of
settlement are estimated by evaluating the ground volume loss. The methods
proposed in this paper provide avalid approach to estimate and reduce tunnel-induced
displacement on existing underground structures.
Fig. 1. Surface and subsurface settlement profiles (modified from Peck 1969).
Vs 2 iS max (2)
4Vs
VL (3)
D2
0.313VL D 2
Smax (4)
KZ 0
The tunneling-induced subsurface settlement is of significance when analyzing the
effects of boring a new tunnel on the above existing underground infrastructures. For
instance, the pipelines, pile foundation, tunnel, and other facilities were found to be
affected by the tunneling underneath them (Vorster et al. 2005; Harris et al. 1994). It
is assumed that the shape of the subsurface settlement profiles can be characterized
by a Gaussian distribution (see the lower curve in Fig. 1). Thus the Eq. 4 is also
applicable by substituting the distance above the tunnel axis for , which can
be presented as the Eq. 5-8 proposed by Mairet al. (1993).
Note: Layer 1: Medium sandy loess, Layer 2: Stiff sandy loess, Layer 3:
Clayey loess, Layer 4: Weathered shale, Layer 5: Shale. (unit: m).
Fig. 4. The engineering geology conditions at the tunnel construction area.
and economic feasibility. The LPS enhancement method was utilized above the new
tunnel vault zone, which is shown in Fig. 5.
Downloaded from ascelibrary.org by GADJAH MADA UNIVERSITY on 03/04/15. Copyright ASCE. For personal use only; all rights reserved.
1993). The subsurface settlement will increase with the increment of volume loss,
which is shown in Fig.6.The subsurface settlements are calculated by Eq. 8. The
depth value chosen for calculation is 60 m, and the diameter D of the tunnel
chosen is 13.8 m. The subsurface settlements have a linear relationship with the
ground volume loss, and Eq. 9 can be derived from Fig.6.
13
S max 23.353VL 110 (9)
It is difficult to directly determine the ground volume loss, while it is possible to
examine the relationship between the subsurface settlement and ground volume loss.
Eq. 9 provides an example to determine the ground volume loss from the subsurface
settlement. In practice it is convenient to measure the surface or subsurface
settlement. For instance, the subsurface settlement can be obtained through
measuring the displacement of existing underground structures. In this paper, the
existing tunnel provides an example to measure the subsurface settlements.
Furthermore, the ground volume loss due to tunneling can be identified.
Downloaded from ascelibrary.org by GADJAH MADA UNIVERSITY on 03/04/15. Copyright ASCE. For personal use only; all rights reserved.
tunnel and the existing tunnel is selected as the point of interest. The excavating
length for every step is 1.25m, and there are 32 steps in this model, and thus the total
excavating length is 40m.
The settlements at the vault and bottom (y=15m) of the existing tunnel caused by
the excavation of the new tunnel are analyzed and the results are presented in Fig.7(a)
and Fig.7(b). The settlement curves caused by the excavation of the new tunnel
correspond to the excavation step. It indicates that the excavation around the existing
tunnel may cause significant displacement of both the vault and bottom of the
existing tunnel. For instance, the excavation step 15 and step 20 (z15, z20 in
Fig.7(a)) of the new tunnel will result in about 14mm settlement at the vault of the
existing settlement; the excavation step15 and step 20 (z15, z20 in Fig.7(b)) of the
new tunnel will result in about 8.3-9.5mm settlement at the vault of the existing
settlement. In addition, the vault of the existing tunnel is much more affected than
the bottom of the existing tunnel by the excavation of the new tunnel.
During the construction of tunneling without LPS (case 1), significant ground
settlement of the existing tunnel is presented in both Fig.8(a) and Fig.9(a). The
ground near the existing tunnel generates large settlement ranging from 160mm ~ 834
mm at the depth of the vault. Typically, the vault of the existing tunnel reaches the
peak value of 834mm. However, at the depth of the bottom of the existing tunnel, the
ground around the existing tunnel has large movement range from 232mm
(settlement) to 187mm (upheaval). Typically the bottom of the existing tunnel
Downloaded from ascelibrary.org by GADJAH MADA UNIVERSITY on 03/04/15. Copyright ASCE. For personal use only; all rights reserved.
reaches the peak value of 187mm of upheaval, which is probably caused by the
discharge of stress in the ground. All these displacements cannot meet the settlement
requirement (30 mm, given by Brandl 2004), and may result in serious damage to the
existing structures.
The settlement of the ground can be greatly reduced by applying the LPS during
tunneling, which can be shown in Fig.8(b) and Fig.9(b). The ground settlement at the
depth of the vault of the existing tunnel is reduced within 14mm-18mm. The ground
settlement at the depth of the bottom of the existing tunnel is reduced to within 4mm-
26mm. All these displacements can meet the settlement control requirement (30mm,
given by Brandl 2004).
The significant effects of applying LPS into the excavating process are shown in
Fig. 10(a) and (b). The settlement of the vault and bottom of the existing tunnel, both
increases with the new tunnel excavating without LPS, can dramatically be reduced
by applying the support LPS. For instance, it indicates that the settlement at the
Downloaded from ascelibrary.org by GADJAH MADA UNIVERSITY on 03/04/15. Copyright ASCE. For personal use only; all rights reserved.
bottom of the existing tunnel will be 138mm for the case of tunneling without LPS,
while the settlement will be reduced to 14.7mm when tunneling with LPS. Thus, the
LPS will significantly reduce the displacement caused by the excavation of the new
tunnel.
Table 3. The volume loss control with the application of LPS enhancement.
Position Enhancement Settlement, (mm) VL, (%)
No LPS -138 5.91
Bottom
LPS -14.7 0.63
No LPS -828.5 35.48
Vault
LPS -14.5 0.62
CONCLUSIONS
In this article, the subsurface settlements as well as ground volume loss caused by
the excavating of the new tunnel are analyzed. The relationship between subsurface
settlement and ground volume loss is derived based on Mairs theory of immediate
settlement of soil. LPS ground stabilization technique is applied prior to the
construction of the new tunnel. The results of this study are summarized below:
Downloaded from ascelibrary.org by GADJAH MADA UNIVERSITY on 03/04/15. Copyright ASCE. For personal use only; all rights reserved.
REFERENCES