The GL Group (including the companies listed above) does not warrant or assume
any kind of liability for the up-to-date nature, accuracy, completeness, or quality of Technical Assurance Services
the information provided. Liability claims against any member of the GL Group
in relation to any loss or damage arising out of or in connection with the use
or non-use of information provided, including the use of incorrect or incomplete
information, are excluded to the fullest extent permissible by law.
All offers are subject to alteration and are non-binding. Each GL Group member
Marine Warranty Survey
expressly reserves the right without notice to change, supplement, or delete parts
of the pages or the entire offer or to stop the publication temporarily or definitively.
2 3
DETAILED METHOD STATEMENT DETAILED METHOD STATEMENT
Within GL the following organisational way will be applied for projects relevant for Project Personnel Execution of Marine Warranty Survey
marine warranty survey:
Following GL personnel will be involved in the close-knit framework for marine The main elements of the warranty survey service are:
Responsible Technical Office for engineering support carries out warranty survey:
the verification and approval of documentation for the project Review and approval of design / engineering documents
depending on the project location
- Location Survey Analysis (Pile Driveability, Soil Condition,
Responsible Country Offices provide Project Management and Environmental Condition)
control the certified and authorised warranty surveyors for on-site
surveillance - Loadout Analysis (..., winches, cranes, moorings)
All towing vessels, cargo barges and crane vessels will be audited
prior to mobilisation to ensure that they are fit for purpose and up to
standard (towing equipment, towline recovery equipment,
navigation lights, pumping equipment, mooring ropes, fenders) on
GL is working with certified own or authorised Marine Warranty Surveyors. Survey.
- Loadouts
- Seafastening
- Transportation
- Structure Installation
- Pipe / Cablelaying
The marine warranty surveyor issues the MWS Certificates of Approval (Warranty
Certificate) prior to start of each operation.
4 5
CASE STUDIES CASE STUDIES
Project Location: The Netherlands (Offshore North Sea) Project Location: Offshore Port Said, Egypt
Owner/Client: Van Oord Dredging & Marine Contractors B.V. Owner/Client: Petrobel, Egypt
Project Duration: 2006 - 2007 Project Duration: 2007 - 2008
Issue: GL Activities:
Q7 Offshore Wind farm located 25km West of Ijmuiden on the Dutch GL has provided Document Review and
Continental shelf - comprises 60 wind turbines (Vestas V80 2MW) is assembled
on monopole foundations and will be connected in 8 strings of 7 or 8 wind turbines On site surveillance of Load-out, Transportation and Installation of
to an offshore high voltage station (OHVS) where the 22kV current from the various Jackets, Topsides and Pipelines
turbines will be transformed to 150kV for transport to shore. A single HV cable
will be laid to connect the Wind farm to shore where on a seaward side of the
dune barrier connection will be made to an onshore grid feed.
GL Activities:
6 7