Sie sind auf Seite 1von 5

ARAR AIRPORT DEVELOPMENT PROJECT

Ref No. : 104- EL. 01-10-2016 ELECTRICAL SECTION


Meduim Voltage Network Report
Cable
Total Installed Cable Excavation Deliveried Cable(25%)
Installed test& connection Backfilling Total Work Done
CABLE SIZE in mm2 in L.M (20%) (15%) (15%) 100%
( 25%)
300 6050 20% 25% 25% 0% 15% 85%

Low Voltage Network( Armoud cable direct buried in ground) Report


Cable
Total Installed Cable Excavation Deliveried Cable(25%)
Installed test& connection Backfilling Total Work Done
CABLE SIZE in mm2 in L.M (20%) (15%) (15%) 100%
( 25%)
MTB (15.3.10) 300 mm2 1900 20% 25% 25% 0% 15% 85%
CFR (15.3.1.8) 300 mm2 1250 20% 25% 25% 0% 8% 78%
ADM (15.03.6) 70 mm2 100 20% 25% 25% 0% 5% 75%
ADM (15.03.7) 300 mm2 100 20% 25% 25% 0% 5% 75%

Low Voltage Network Report

Total Installed Duct Excavation Warning tabe Backfilling Total Work Done
Duct bank Duct Bank Installed (65%)
Bank In L.M (15%) (5%) (15%) 100%

Duct bank (2x2), 4'' UPVC 580 15% 65% 0% 0% 80%


conduit
Duct bank (2x3), 6'' UPVC 80 15% 65% 0% 0% 80%
conduit
Duct bank (6x3), 6'' UPVC 0 0% 0% 0% 0% 0%
conduit
Duct bank (3x3), 6'' UPVC 0 0% 0% 0% 0% 0%
conduit
Duct bank (4x3), 6'' UPVC 0 0% 0% 0% 0% 0%
conduit

Low Voltage Manholes Report


Manholes
Total Installed Excavation Deliveried Manholes Manholes cover Backfilling Total Work Done
Manholes Types Manholes In Qty (15%) Installed (25%) (20%) (15%) 100%
( 25%)
(I)Man hole class MH1 6 15% 25% 21% 0% 0% 61%
(L)Man hole class MH2 10 15% 25% 10% 0% 0% 50%
(T)Man hole class MH3 1 15% 25% 0% 0% 0% 40%

Low Current Network Report


Total Installed Duct Excavation Warning tabe Backfilling Total Work Done
Duct bank Duct Bank Installed (65%)
Bank In L.M (15%) (5%) (15%) 100%
Duct bank (2x3), 4'' UPVC 1735 15% 65% 0% 0% 80%
conduit

Low Current Manholes Report


Manholes
Total Installed Excavation Deliveried Manholes Manholes cover Backfilling Total Work Done
Manholes Types Manholes In Qty (15%) Installed (25%) (20%) (15%) 100%
( 25%)
(I)Man hole class MH1 34 15% 25% 20% 0% 0% 60%
(L)Man hole class MH2 7 15% 25% 10% 0% 0% 50%
(T)Man hole class MH3 10 15% 25% 10% 0% 0% 50%

Earthing (power&communication) system


Materials
Deliveried test&
Excavation Ancillary works Backfilling Total Work Done
Building LUMPSUM (30%) connection
(15%) (20%) (15%) 100%
(20%)
Power Earthing (1) 0% 0% 0% 0% 0% 0%
MTB
Comm. Eaething(1) 0% 0% 0% 0% 0% 0%
Power Earthing (1) 5% 0% 0% 5% 0% 10%
ADM
Comm. Eaething(1) 0% 0% 0% 0% 0% 0%
Power Earthing (1) 5% 0% 0% 5% 0% 10%
CFR
Comm. Eaething(1) 0% 0% 0% 0% 0% 0%
Power Earthing (1) 5% 0% 0% 5% 0% 10%
CRB
Comm. Eaething(1) 0% 0% 0% 0% 0% 0%
Power Earthing (1) 5% 0% 0% 5% 0% 10%
MES
Comm. Eaething(1) 0% 0% 0% 0% 0% 0%
Power Earthing (1) 5% 0% 0% 5% 0% 10%
TS1
Comm. Eaething(1) 0% 0% 0% 0% 0% 0%
Power Earthing (1) 5% 0% 0% 5% 0% 10%
TS2
Comm. Eaething(1) 0% 0% 0% 0% 0% 0%
Power Earthing (1) 5% 0% 0% 5% 0% 10%
IRR
Comm. Eaething(1) 0% 0% 0% 0% 0% 0%
Power Earthing (1) 0% 0% 0% 0% 0% 0%
GTB
Comm. Eaething(1) 0% 0% 0% 0% 0% 0%

Lightning Protection System


Connect
Materials Materials Ancillary works test& connection with Total Work Done
Building LUMPSUM Deliveried Installed (20%) (20%) earthing 100%
(30%) (25%) sys.(5%)
MTB 1 0% 0% 0% 0% 0% 0%
ADM 1 5% 0% 0% 0% 5% 10%
CFR 1 5% 0% 0% 0% 5% 10%
CRB 1 5% 0% 0% 0% 5% 10%
MES 1 5% 0% 0% 0% 5% 10%
TS1 1 5% 0% 0% 0% 5% 10%
TS2 1 5% 0% 0% 0% 5% 10%
1RR 1 5% 0% 0% 0% 5% 10%
GTB 1 0% 0% 0% 0% 0% 0%
Lighting Outlets
Materials Materials test&
Total Outlet
Building Deliveried Installed connection Total Work Done 100%
Installed (40%) (30%) (30%)
E & T Rooms 36 30% 20% 0% 50%
4+8+32+17+
CFR(15.4.1- +23+9+93+26+24+6
1,2,3,4,5,6,7,8,9,10,12,15,1 +1+2+27+14+79+29 35% 25% 0% 60%
8,19,20,21,22,23,25) +25+32+31=464
TS1(15.4.1-1,2,3,4,5) 8+19+20+6+1=54 35% 25% 0% 60%
ADM (15-4-1- 9+52+19+3+30+6+ 30% 20% 0% 50%
1,4,5,6,11,13,14) 50=169
CRB(15-4-1- 42+46+4+8+2+1+10
1,2,3,4,5,6,7,8,9,10,11,12,1 +10+4+3+4+3+7= 30% 20% 0% 50%
5) 123

MES( 15-4-1-
3,4,5,6,7,8,9,10,11,12,13, 22+45+24+2+7+7+3 30% 20% 0% 50%
+3+3+3+28+3=100
15)

Lighting Switch Outlets


Materials Materials test&
Total Outlet
Building Deliveried Installed connection Total Work Done 100%
Installed (40%) (30%) (30%)
E & T Rooms 2 20% 20% 0% 40%
CFR(15.4.2.1,2,3,4) 25+5+2+8=40 20% 20% 0% 40%
TS1 9 20% 20% 0% 40%
ADM (15-4-2-1,2,3,4) 25+3+2+5=35 20% 20% 0% 40%
CRB(15-4-2-1,3,4,5,6,7,8) 3+4+4+2+1+1+2=17 20% 20% 0% 40%
MES(15-4-2-1,2,3,4,5,7) 5+2+3+1+1+2=14 15% 15% 0% 30%

Socket Outlets
Materials Materials test&
Total Outlet
Building Deliveried Installed connection Total Work Done 100%
Installed (40%) (30%) (30%)
E & T Rooms 18 10% 10% 0% 20%
CFR 25 10% 10% 0% 20%
32 Outler for
single phase duplex 10% 10% 0% 20%
socket 16 A.
TS1
3 Outler for three
phase socket 16 A. 10% 10% 0% 20%
(Weather Proof)

Switch Disconnectors (Isolators) Outlets


Materials Materials test&
Total Outlet
Building Deliveried Installed connection Total Work Done 100%
Installed (40%) (30%) (30%)
E & T Rooms 8 5% 5% 0% 10%
CFR 8 5% 5% 0% 10%
2 Outlet for 220 V,
20 A, disconnect 5% 5% 0% 10%
switch
5 Outlet for 380 V,
32 A, disconnect 5% 5% 0% 10%
TS1
switch

3 Outlet for 380 V,


32 A, disconnect 5% 5% 0% 10%
switch (explosion
Proof)
ADM (15-4-4-1) 10 5% 5% 0% 10%

Das könnte Ihnen auch gefallen