Sie sind auf Seite 1von 4

WeFix Construction Services Incorporated

(Weekly Activity Report)

Name: ARBUIS, JENELYN M. Project: Opol 138kV-69kV Substation


Position : OJT Location : Brgy. Awang Opol, Misamis Oriental

We were accepted at WeFix Construction Services Incorporated and were assigned at different
field on a rotational basis. I and my partner was assigned at NGCP 138 kV-69 kV Substation
Project. This station will be a distributor of power to Cepalco and Moresco. The following were
activities observed last week:

Day 1 (Tuesday, April 14/2015)

Safety Management Awareness


Site Visit (NGCP OPOL)

Day 2 (Wednesday, April 15/2015)

Tool Box Meeting


- this meeting elaborates the safety measures need to observed in the
workplace.
Cable Trench
-Layout (surveying the elevation)
Control Building
Slab
-Installation of Reinforcement
-Setting Forms for Blockouts(for electrical purposes)

Wall
-Installation of CHB
-Plastering/Finishing
Drainage
-Excavation
- Installation of Culverts
Riprap
- Excavation(slope protection)
- Installation of Boulders on the Prepared Slope
-Pouring of Concrete Mix
Fence / Perimeter
-Installation of Reinforcements for wallfooting & columns
- Installation of CHB & Reinforcement for wall

Day 3 (Thursday, April 16/2015)


Cable Trench
-Layout
-Installation of Reinforcement
Control Building
Slab
-Installation of Reinforcement
Wall
- Installation of CHB
-Plastering/Finishing
Drainage
-Excavation
-Placing of Culverts
-Setting forms for Junction Box/
-Installation of Reinforcement for Junction Box
Riprap
-Preparation for Slope/Excavation
-Placing of Boulders on the Prepared Slope
-Pouring of Concrete Mix
Fence / Perimeter
-Installation of Spikes
-Placing of CHB & Reinforcement for wall
Road
-Compaction of Base Course
-Pouring of Concrete
Steelworks
-Fabrication of trusses
Testing of materials
- Delivering Sample Cylinders to NGCP 138 kV Substation (Mindanao
Material Testing Laboratory, Villanueva Mis. Or.)

Day 4 (Friday, April 17/2015)


Cable Trench:
-Installation of Reinforcement
-Finishing/Plastering
Control Building
Slab
-Installation of Reinforcement
Wall
-Placing of CHB
-Plastering/Finishing
Drainage
- Installation of Culverts

-Sealing of Culverts using Mortar/Concrete


Riprap
- Installation of Boulders on the Prepared Slope
-Pouring of Concrete Mix
Fence / Perimeter
-Installation of Spikes
-Installation of CHB & Reinforcement for wall

Day 5 (Saturday, April 18/2015)


Office Works
-organizing/paper cutting workers pay roll slip
-checking papers
- writing weekly report
-visiting warehouse and familiarizing materials

GOOD DAY