PROJECT: CHLEF 1 Cement plant project, Production line of 6000T/D

of Clinker

SITE INFORMATION : N093

Erection Works

Subject: Detail drawings of the rod fixing accessories - Premix 18

Attention: Mr.ELLEITHY Tharwat - CTU ARESCO EA Project Manager

Dear Sir,

With reference to the subject, please find attached detail drawings of the rod fixing accessories - Premix 18

C-D23-EC.1 C-D23-EC.15
C-D23-EC.2 C-D23-EC.16
C-D23-EC.3 C-D23-EC.17
C-D23-EC.4 C-D23-EC.18
C-D23-EC.5 C-D23-EC.19
C-D23-EC.6 C-D23-EC.20
C-D23-EC.7 C-D23-EC.21
C-D23-EC.8 C-D23-EC.22
C-D23-EC.9 C-D23-EC.23
C-D23-EC.10 C-D23-EC.24
C-D23-EC.11 C-D23-EF.4
C-D23-EC.12 C-D23-EF.5
C-D23-EC.13
C-D23-EC.14

Best Regards,
KHOUALDIA Haroun

Copy : Ahmed Mohsen Zaki ; Maged Yehia; Ramy Zayed;


Mahmoud Hassan ; KHALES Redha ; TARABA Frdric ;
BUHR Marc
Confirmed by : H. KHOUALDIA Received by : Mr ELLEITHY Tharwat
Date : 18/05/2017 Date :

Signature: Signature: