INTERVENCION
POZO: SURUBI A1
BLOQUE: MAMORE
PROVINCIA: CARRASCO
DEPARTAMENTO: COCHABAMBA
_________________________________________________________________________
SANTA CRUZ DE LA SIERRA BOLIVIA
AO 2006
INDICE
1. DATOS GENERALES [Well Summary]
2. SECUENCIA DE OPERACIONES [Event Summary]
3. FLUIDOS
3.1. PROPIEDADES [Mud Summary]
3.2. VOLUMENES [Mud Volume]
3.3. MATERIAL [Mud Products Summary]
4. TIEMPOS
4.1. DISTRIBUCION [Time Distribution Summary]
4.2. DIAGRAMA [Operations Chart]
5. COSTOS
5.1. COMPARACION [AFE vs. Actual Report]
5.2. GRAFICO [Cum. Cost vs Days]
6. COMENTARIOS [Hotnotes]
ANEXOS
A) ESTADO SUBSUPERFICIAL
[Wellbore Equipment]
B) ESTADO SUPERFICIAL
C) REPORTE DE OPERACIONES
[Operations Summary]
Repsol-YPF Page 1 of 1
Well Location
Country: BOLIVIA
API #: BO0200000123 Well ID: State/Prov: COCHABAMBA County: CARRASCO
Location: X = 328.052,805 Y = 8.110.241,681 Z = 260,131
Field Name: SURUBI
Block: MAMORE Slot No: Platform:
License No: License Date: Licensee: MAMORE
Spud Date/Time: 27/11/1991 - 13:00 P&A Date:
Reference Elevations
Event Summary
Event Type Objective Start Date End Date Auth. Cost Last Est.
08/02/2006 3,555.00 (m) CONCLUYE MONTAJE, EFECTUA CHECK LIST, PREPARA FI (670 BBL) , VERIFICA PRESIONES
EN EA 580 PSI, EN TUB 600 PSI. (INTERGAS PRESENTA ACCESORIOS DE EQUIPO DE RAD
09/02/2006 3,378.00 (m) CIRCULA POR CAMISA, NORMALIZA FI, CON SL MANIOBRA PARA CERRAR CAMISA, PRUEBA,
10/02/2006 3,378.00 (m) TERMINA DE INSTALAR PREVENTORES, PRUEBA MISMOS. EQUIPETROL SACA TAPON DW,
REALIZA TRES CARRERAS INTENTANDO SACAR TAPON PX, SIN EXITO; ABRE CAMISA, SACA
SIN MOVIMIENTO. COLOCA Y PRUEBA BOP, LIMPIA ANTEPOZO, ALISTA PARA MOVER
SUBESTRUCTURA.
12/02/2006 3,378.00 (m) APARTA SUBESTRUCTURA, INSTALA INTENSIFICADOR (CASING JACK) TENSIONA HASTA
13/02/2006 3,378.00 (m) TERMINA DE SACAR ARREGLO DE GAS LIFT DESARMADO PZA X PZA (100% RECUPERADO) ,
COLOCA SALIDA DE LODO , CORRE CABLE, BAJA ARREGLO DE LIMPIEZA RNM 6.1/16"+ ESC
14/02/2006 3,378.00 (m) BAJA ARREGLO CON RNM + ESC, HASTA 3322,9 m ; SACA HTA. BAJANDO TR (TS-U 7")
HASTA 2316 m
15/02/2006 3,378.00 (m) BAJA Y ANCLA TR EN 3299 m LLENA POZO CON 400 BBL FI, PRUEBA SELLO TR CON 800 PSI,
CONEXIONES
16/02/2006 3,378.00 (m) TERMINA DE INSTALAR Y PROBAR PREVENTORES, PRUEBA VALVULAS LATERALES Y
LINEA AL MANIFOLD; BAJA HTA PARA PESCAR TR, MANIOBRA PESCA Y SACA TR HASTA
1215 m
17/02/2006 3,378.00 (m) SACA TR , BAJA RETRIEVING TOOL (HALL) HASTA CONTACTAR PACKER VTL (3326,9 m)
DE TENSION, REPITE MANIOBRA, LEVANTA SIN RESISTENCIA, SACANDO HTA HASTA 240 m
18/02/2006 3,378.00 (m) SACA RETRIEVING TOOL SIN PESCA. CON HUELLAS DE FRICCION EN "J" . BAJA BHA CON
DESVINCULAR SPEAR.
19/02/2006 3,378.00 (m) SACA HERRAMIENTA, CAMBIA SPEAR. BAJA HERRAMIENTA. ENCHUFA SPEAR EN PACKER
20/02/2006 3,378.00 (m) CONTINUA GOLPEANDO C/TIJERA (205 GOLPES) P/LIBRAR PACKER S/EXITO. MANIOBRA
EMULSIONADO.
21/02/2006 3,378.00 (m) TERMINA S/HTA. DESARMA BHA Y RECUPERA SPEAR SIN DAO. BAJA TUB. 2.7/8", PJD
HASTA 1484 m
23/02/2006 3,378.00 (m) SACA ARREGLO FINAL HASTA 1146 m EQUIPETROL INTENTA PESCAR TAPON XR, HTA
24/02/2006 3,378.00 (m) BAJA INSTALACION FINAL, DIMENSIONA, PRUEBA HERMETICIDAD TUB CON 1700 PSI,
EN NA"XN", PRESURIZA HASTA 1400 OPSI, PARA ANCLAR PACKER PFH EN 3323.8 m
25/02/2006 3,378.00 (m) LLENA EA CON 330 BBL FI, PRUEBA SELLO PACKER CON 800 PSI. COLOCA BPV, SACA BOPs,
Nombre De Pozo: REP.CB.SRB.A-1 Evento: WORKOVER Fecha Inicio: 04/02/2006 Fecha Fin: 25/02/2006
Fecha del Preparado [Bls] Recibido [Bls] Perd. Sup. [Bls] Perd. Pozo [Bls] Vol.Pozo [Bls] Vol.Sup. [Bls]
reporte
1 05/02/2006 .00 298.00 .00 .00 0.00 298.00
2 06/02/2006 .00 .00 .00 .00 0.00 298.00
3 07/02/2006 .00 .00 .00 .00 0.00 298.00
4 08/02/2006 675.00 .00 .00 .00 0.00 973.00
5 09/02/2006 292.00 .00 22.00 .00 784.00 459.00
6 10/02/2006 200.00 .00 10.00 .00 784.00 649.00
7 11/02/2006 .00 .00 2.00 .00 784.00 647.00
8 12/02/2006 .00 .00 3.00 7.00 778.00 643.00
9 13/02/2006 .00 .00 20.00 39.00 765.00 597.00
10 14/02/2006 .00 .00 .00 50.00 765.00 547.00
11 15/02/2006 590.00 .00 19.00 411.00 790.00 682.00
12 16/02/2006 .00 .00 4.00 7.00 776.00 685.00
13 17/02/2006 .00 .00 .00 120.00 787.00 554.00
14 18/02/2006 .00 .00 .00 19.00 833.00 489.00
15 19/02/2006 .00 .00 .00 50.00 833.00 439.00
16 20/02/2006 .00 .00 61.00 50.00 819.00 342.00
17 21/02/2006 .00 .00 43.00 48.00 838.00 232.00
18 22/02/2006 .00 .00 26.00 10.00 838.00 196.00
19 23/02/2006 .00 .00 .00 47.00 885.00 102.00
20 24/02/2006 386.00 .00 .00 120.00 765.00 488.00
21 25/02/2006 .00 .00 47.00 340.00 744.00 122.00
22 Sum: 2143.00 Sum: 298.00 Sum: 257.00 Sum: 1318.00
TOTAL 4,769.06
06I VIAJE C/B (EXCLUDA MBRA.,PESCA, INST.PROD.) TRIP, TUBING 21.25 4.27
09 CORRER Y CORTAR CABLE SLIP & CUT DRILL LINE 2.00 0.40
13E FIJA/LIBRA TPN, PKR, HERRAMIENTA PRODUCCION SET / UNSET RBP, PKR, PROD. TOOLS 2.50 0.50
13G BAJAR C/B USADOS/DEL POZO - INS. PRODUCCION RUN, RE-RUN/INSPECT. TUBING 19.00 3.82
24 BAJAR / SACAR CAMISA PROTECTORA Y TAPON DE TEST RUN / PULL WEAR BUSHING / TEST PLUG 5.25 1.06
35A MANIOBRAR/BAJAR TAPONES CON CABLE SLICKLINE, W/L PLUGS 15.00 3.02
Operations Chart
01E - (12%)
- Other (16%)
05A - (3%)
29G - (4%)
28 - (3%)
20F - (3%)
06H - (19%)
20B - (5%)
19 - (4%)
15A - (3%)
06I - (4%)
13B - (4%) 14A - (7%)
13G - (4%)
2.0
1.8
1.6
1.4
Cum Cost (Millions)
1.2
1.0
0.8
0.6
0.4
0.2
0.0
0 5 10 15 20 25 30 35 40 45 50
Hotnotes Report
Legal Name: SRB-A1
Common Name: SURUBI A1
Country: BOLIVIA
API #: BO0200000123 Well ID: State/Prov: COCHABAMBA County: CARRASCO
Location: X = 328.052,805 Y = 8.110.241,681 Z = 260,131
Field Name: SURUBI
Block: MAMORE Slot No: Platform:
License No: License Date: Licensee: MAMORE
Spud Date/Time: 27/11/1991 - 13:00 P&A Date:
25/02/2006 WORKOVER 1.- EL DTM DEL POZO PLM- A4 AL POZO SRB -A1 SE DEMOR POR CONSTANTES E
INTENSAS LLUVIAS (QUE NO PERMITIERON REALIZAR TRABAJOS EN FORMA
NORMAL); POR REPARACION MECANICA DEL EQUIPO (DIRECCION DEL CAMION) Y
POR LAS CARACTERISTICAS DE LA LOCACION, LA UBICACIN DEL CAMION DEL
EQUIPO EN EL LUGAR DE TRABAJO, FUE DIFICULTOSA.
2.- EL DTM DEL EQUIPO EMPIEZA EL 04/02/2006 , LAS OPERACIONES EN SRB-A1
EMPIEZAN EL 08/02/2006 Y SE SUSPENDEN EL 25/02/2006 COMPRENDIENDO UN
PERIODO DE 21 DAS
3.- EL OBJETIVO DEL PROGRAMA NO PUDO SER ALCANZADO, DEBIDO A LA
DIFICULTAD EXISTENTE PARA RECUPERAR EL PACKER VTL ANCLADO EN 3326,98
m Y EL ARREGLO DE EMPAQUE DE GRAVA, LO CUAL OBLIGO A TOMAR LA
DECISION DE SUSPENDER MOMENTANEAMENTE LAS OPERACIONES
4.- CONSIDERANDO, QUE LAS OPERACIONES DESTINADAS A RECUPERAR LA HTA
EN PESCA, PUEDEN TENER UN PERIODO DE DURACION LARGO Y QUE EL EQUIPO
DE RAD TECH ESTA ESPERANDO PARA REALIZAR OPERACIONES, SE DECIDE,
BAJAR ARREGLO DE PRODUCCION PROVISIONAL Y TRASLADAR EL EQUIPO A
PLM-C7 DONDE EL POZO ESTA LISTO PARA REALIZAR OPERACIONES CON RAD
TECH.
5.- DURANTE LAS PRIMERAS OPERACIONES, SE OBSERVO NOTABLE ADMISIN DE
LA FORMACIN, FIJO TR EN 3299 m LLENO POZO CON 400 BBL FI (NIVEL 1718 m)
Hotnotes Report
Legal Name: SRB-A1
Common Name: SURUBI A1
Country: BOLIVIA
API #: BO0200000123 Well ID: State/Prov: COCHABAMBA County: CARRASCO
Location: X = 328.052,805 Y = 8.110.241,681 Z = 260,131
Field Name: SURUBI
Block: MAMORE Slot No: Platform:
License No: License Date: Licensee: MAMORE
Spud Date/Time: 27/11/1991 - 13:00 P&A Date:
6.- EL POZO QUEDO CON ARREGLO DE GAS LIFT SIMPLE CONVENCIONAL, CON
PACKER ANCLADO EN 3323,8 m , EN LA PUNTA TIENE UN CATCHER (ID 1.1/4") QUE
DEBERIA HABER SIDO UTILIZADO PARA ANCLAR EL PACKER; FINALMENTE NO SE
LO UTILIZ POR QUE EL PACKER SE ANCLO DURANTE LA PRUEBA DE
HERMETICIDAD DE LA TUBERIA, AL CAER EL TAPON PX , DEL NIPLE ASIENTO X AL
NIPLE ASIENTO XN.
3347.0-3350 m
3352.5-3354 m
3358-3373 m
3384-3393 m
CIBP 7" @ 3439 m-MD Note: Ultimo Workover, en enero 97, se cambio tubera de Produccin.
ESTADO SUPERFICIAL POZO: SRB-A1
2.1/16 - 5M PSI
MMA
2.9/16 - 5M PSI
7.1/16 5M
SECCION C
11- 5 M
11- 10 M
SECCION B
13.5/8 - 3M
SECCION A
CA 13.3/8
.
Repsol-YPF Page 1 of 11
19:00 - 00:00 5.00 01B P 01 EQUIPO PI-249 EN DTM ESPERANDO LUZ DEL DIA.
07/02/2006 00:00 - 06:00 6.00 01B L L1 01 EQUIPO PI-249 EN DTM ESPERANDO LUZ DEL DIA.
PARALELAMENTE REPARO DIRECCION HIDRAULICA DEL
CAMION DEL EQUIPO PI-249.
06:00 - 00:00 18.00 01B P 01 TERMINO TRASLADAR EQUIPO PI-249 A LOCACION POZO:
SRB-A1.
MONTAJE EQUIPO.- 90 %. CON DIFICULTAD Y APOYADO
POR PLUMA DE CAMIONES PETROLEROS COLOCO
CAMION EQUIPO PI-249 EN POSICION, POR TERRENO
PANDO. IZO MASTIL . ALINEO Y CONECTO CAJONES
SISTEMA LODOS. POSICIONO ACUMULADOR Y LINEAS
SUPERFICIALES DEL MISMO. CONECTO LINEAS AL
CHOKE MANIFOLD.
EN PLM-A4.- PARALELAMENTE EQUIPETROL, EFECTUO
CUATRO CARRERAS SLICKLINE C/ SACAMIESTRAS 1.5/8",
EXTRAYENDO EN CADA CARRERA RESTOS DE SARRO.
LUEGO EFECTUO DOS CARRERAS C/ HIDROSTATICA,
CON MISMO RESULTADO,RECUPERA RESTOS DE SARRO
FINO Y UNA CARRERA CON PESCADOR "GS", SIN
LOGRAR RECUPERAR TAPON "XR". TOTAL RESTOS DE
07/02/2006 06:00 - 00:00 18.00 01B P 01 SARRO RECUPERADO.- +/- 1 Kgr. SUSPENDE
OPERACIONES ESPERANDO LUZ DEL DIA.
10/02/2006 05:00 - 11:15 6.25 10 P 11 Y 4000 PSI, PROBO TAMBIEN HCR, INTENTO PROBAR
VALV. MECANICA, OBSERVO PERDIDA, REALIZO LIMPIEZA
DE VALVULA; REPITIO PRUEBA CONTINUA PERDIENDO
(SOLICITA UNA PARA CAMBIO). PRUEBA TAMBIEN
VALVULA CHECK Y MECANICA
11:15 - 11:45 0.50 10 P 11 (B) EQUIPETROL PESCA Y SACA TAPON DW
11:45 - 13:30 1.75 10 P 11 (A) CIERRA RAMS CIEGOS PRUEBA CON 500 PSI, SIN
OBSERVAR INCREMENTO DE PRESION EN EA, ABRE
VALV. LATERAL DE EA. PRESURIZA POR KILL LINE HASTA
800 PSI, EA NORMAL, NUEVA CAIDA DE PRESIN POR
VALVULAS DE MANIFOLD.
13:30 - 15:30 2.00 10 L L4 11 (B) REALIZA LIMPIEZA DE VALVULAS DE MANIFOLD (6)
15:30 - 16:15 0.75 10 L L4 11 (A) PRUEBA VALVULAS DE MANIFOLD CON 4000 PSI (+)
16:15 - 17:45 1.50 10 P 11 (B) EQUIPETROL BAJA PESCADOR RS, PESCA TAPN PX,
MANIOBRA EN REITERADAS OPORTUNIDADES , SIN
EXITO, EN LTIMA MANIOBRA, ROMPE PASADOR DEL
PESCADOR, DESVINCULA PESCA Y SACA PESCADOR
(ADMISIN POR DIRECTA)
17:45 - 21:00 3.25 10 T T2 11 (B) EQUIPETROL BAJA PESCADOR RS, NIVEL DE FLUIDO
EN 183 m, PESCA TAPON PX, (VERIFICA DESCENSO DE
FLUIDO EN EA) MANIOBRA EN REITERADAS
OPORTUNIDADES, NUEVAMENTE ROMPE PASADOR DEL
PESCADOR, DESVINCULA PESCA, SACA PESCADOR
21:00 - 22:45 1.75 10 T T2 11 (B) EQUIPETROL REALIZA TERCERA CARRERA CON
PESCADOR RS, NIVEL DE FLUIDO 579 m, MANIOBRA EN
REITERADAS OPORTUNIDADES, SIN EXITO; ROMPE
PASADOR, DESVINCULA Y SACA PESCADOR
22:45 - 00:00 1.25 10 T T2 11 (B) EQUIPETROL BAJA HTA, NIVEL DE FLUIDO EN 701 m,
MANIOBRA, ABRE CAMISA, SACA HTA, APARTA
LUBRICADOR Y ACCESORIOS
11/02/2006 00:00 - 00:15 0.25 10 P 11 (B) REUNION DE SEGURIDAD Y COORDINACION
OPERATIVA
00:15 - 08:15 8.00 10 P 11 (A) ALISTA PARA TENSIONAR, APLICA TENSION
PAULATINA HASTA 95M LBS (PESO HTA APROX 70M LBS)
SIN LOGRAR MOVER TUBING HANGER DE SU POSICION,
MANIOBRA EN REITERADAS OCASIONES SIN EXITO.
REVISA ESPARRAGOS (ANTES DE COLOCAR EL
PREVENTOR VERIFICO QUE TODOS ESTABAN AFUERA) ,
INTENTA AFLOJAR ESPARRAGO UBICADO DEBAJO DE LA
BRIDA, SIN EXITO (GUIADOR). CONTINUA MANIOBRANDO
TENSIONANDO HASTA 95M LBS; EVACUA FLUIDO
UBICADO SOBRE EL TUBING HANGER, VACIA FLUIDO
LUBRICANTE, CONTINUA TENSIONANDO HASTA 100M LBS
SIN EXITO. UTILIZANDO SPRAY PENETRANTE Y
HABLANDADOR, AFLOJA ESPARRAGO INFERIOR; REPITE
MANIONBRAS EN REITERADAS OPORTUNIDADES
INCREMENTANDO TENSIN HASTA 120M LBS.
08:15 - 09:00 0.75 10 T T4 11 (B) CAMBIA PUP JOINTS DE MANIOBRA UBICADOS SOBRE
EL TUBING HANGER, SACA PUP JOINTS 2.7/8 8RD,
COLOCA PUP JOINTS 2.7/8 PJD
09:00 - 13:00 4.00 10 T T4 11 (A) CONTINUA MANIOBRANDO INTENTANDO SACAR
TUBING HANGER DE CABEZAL DE PRODUCCIN,
REALIZA REITERADAS MANIOBRAS, INCREMENTANDO LA
11/02/2006 09:00 - 13:00 4.00 10 T T4 11 TENSION PAULATINAMENTE HASTA 135M LBS, SIN EXITO
13:00 - 14:00 1.00 10 T T4 11 (A) AFLOJA PERNOS DE LA BRIDA SUPERIOR DEL
CABEZAL DE PRODUCCIN (11 - 10M) ; MANIOBRA
TENSIONANDO HASTA 125M LBS SIN EXITO
14:00 - 18:00 4.00 10 T T4 11 (A) LEVANTA BRIDAS REDUCTORAS Y PREVENTOR;
TENSIONA CON 125 LBS, TUBING HANGER, NO SE MUEVE
DE SU ACTUAL POSICION; NUEVAMENTE BRIDAS Y
PREVENTORES; CAMBIA VALVULA MECANICA DE LA
LINEA DE FLUJO; PRUEBA PREVENTORES Y VALVULA
MECANICA CON 4000 PSI
18:00 - 20:30 2.50 10 T T4 11 (A) CONTINUA MANIOBRANDO, TENSIONANDO CON 125M
LBS EN ULTIMA MANIOBRA, ROMPE MEDIA LUNA DE
ELEVADOR . AFLOJA COMPLETAMENTE CONTRATUERCA
Y ESPARRAGO INFERIOR (GUIADOR) , REALIZ
MANIOBRAS DE TENSION SIN EXITO.
20:30 - 21:45 1.25 10 T T4 11 (B) EVACUA FLUIDO Y LIMPIA ANTEPOZO
21:45 - 00:00 2.25 10 T T4 11 (B) APARTA CABALLETES , RAMPLA, CORRAL DE HTAS,
ALISTA PARA LEVANTAR SUBESTRUCTURA Y TRABAJAR
CON GATO HIDRULICO
12/02/2006 00:00 - 06:00 6.00 10 T T4 11 (B) APARTA HERRAMIENTAS Y ACCESORIOS UBICADOS
EN LA SUBESTRUCTURA, SACA PUP JOINTS
CONECTADOS AL TUBING HANGER, RECORRE
SUBESTRUCTURA
06:00 - 08:30 2.50 10 T T4 11 (B) DESCARGA INTENSIFICADOR (CASING JACK), ALISTA
PARA TRABAJAR, INSTALA SOBRE PREVENTOR DE RAMS
13.5/8-5M
08:30 - 11:30 3.00 10 T T4 11 (A) REALIZA PRUEBA DE FUNCIONAMIENTO DEL
INTENSIFICADOR, HACIA ARRIBA Y HACIA ABAJO,
TENSIONA HASTA 78M LBS, INCREMENTA TENSION
GRADUALMENTE HASTA 157M LBS, 173M LBS, 196M LBS ,
LLEGANDO A 235M LBS DESPRENDE TUBING HANGER DE
CABEZAL DE PRODUCCIN. REALIZA MOVIMIENTO HACIA
ABAJO (POSICION ORIGINAL) LEVANTA APROX. 60 cm
DONDE OBSERVA INCREMENTO DE TENSIN. APARTA
INTENSIFICADOR, VERIFICA MOVIMIENTO TENSIONANDO
LA HTA CON EL APAREJO LEVANTA 70 cm TENSION 88M
LBS
11:30 - 14:00 2.50 10 T T4 11 (B) APARTA PUP JOINTS Y VALVULA DE MANIOBRA,
COLOCA EN POSICION DE TRABAJO LA SUBESTRUCTURA
DEL EQUIPO, COLOCA PUP JOINTS Y VALVULA DE
MANIOBRA, EFECTA CONEXIONES, COLOCA HTAS Y
ACCESORIOS
14:00 - 16:00 2.00 10 P 11 (A) MANIOBRA TUBERIA, PARA DESENCHUFAR NIPLE
SELLO DE PACKER VTL (3326,93 m) TENSIONA
PAULATINAMENTE HASTA 105M LBS, OBSERVA
DESCENSO HASTA 100m LBS, REPITE MANIOBRA
TENSIONA HASTA 100M LBS OBSERVA DESCENSO HASTA
95M LBS, EN ULTIMA MANIOBRA TENSIONA HASTA 100M
LBS, OBSERVA SUAVE DESCENSO HASTA 70M LBS,
LEVANTA HTA, SIN RESISTENCIA; APARTA VALVULA , PUP
JOINTS DE MANIOBRA, XOs, TUBIMG HANGER (SIN DAO
NI HUELLAS DE GOLPE O RAYADURAS) Y XO (3.1/2" PH
(PIN) x 2.7/8 8RD (BOX) , ALISTA PARA SACAR TUBERIA
12/02/2006 16:00 - 00:00 8.00 10 P 11 (A) SACANDO ARREGLO DE GAS LIFT SIMPLE
TERMINACIN, HASTA 1503 m DESARMANDO PZA X PZA (
1 PUP JOINT 2.7/8 8RD, 168 PZAS TUB 2.7/8 8RD Y 3
MANDRILES) BOMBEANDO FI CADA 5 PZAS , TOTAL
BOMBEADO 20 BBL FI
13/02/2006 00:00 - 08:30 8.50 10 P 11 (A) TERMINA DE SACAR ARREGLO DE GAS LIFT SIMPLE
TERMINACIN, DESDE 1503 m DESARMANDO PZA X PZA
( 2 PUP JOINT 2.7/8 8RD, 344 PZAS TUB 2.7/8 8RD, 11
MANDRILES, 4 FLOW COUPLING , CAMISA (ABIERTA), NA
"X" C/TAPON "PX" Y NIPLE SELLO.) BOMBEANDO FI CADA
5 PZAS , TOTAL BOMBEADO 40 BBL FI
08:30 - 09:30 1.00 06 P 11 (B) COLOCA SALIDA DE LODO
09:30 - 10:30 1.00 06 P 11 (A) BAJA ARREGLO DE LIMPIEZA: RNM 6.1/16"+ ESC +XO +
3 PM 4.3/4"+ TJR+1 PM 4.3/4"+ XO (42.2 m)
10:30 - 11:00 0.50 06 P 11 (A) PROFUNDIZA CON TUB 2.7/8 PJD ARMANDO PZA POR
PZA HASTA 85 m
11:00 - 13:00 2.00 06 P 11 (B) CORRE 6.1 m , CORTA 18,3 m CABLE 1"
13:00 - 00:00 11.00 06 P 11 (A) CONTINUA PROFUNDIZANDO ARREGLO DE LIMPIEZA
CON TUB 2.7/8 PJD HASTA 2170 m , CALIBRANDO Y
ARMADO TUBERA 2.7/8 PJD PZA x PZA (225 PZAS) NO
OBSERVA DESPLAZAMIENTO DE FLUIDO
14/02/2006 00:00 - 08:30 8.50 06 P 11 (A) CONTINUA PROFUNDIZANDO ARREGLO DE LIMPIEZA
CON TUB 2.7/8 PJD DESDE 2170.0 HASTA 3322.9 m ,
CALIBRANDO Y ARMADO TUBERA 2.7/8 PJD PZA x PZA
(345 PZAS) NO OBSERVA DESPLAZAMIENTO DE FLUIDO.
PROF. REPORTADA DE PACKER VTL 3326,9 m
08:30 - 17:00 8.50 06 P 11 (A) SACA TUBERIA 2.7/8 PJD TIRO X TIRO,
RECIPROCANDO HTA PARA LIMPIEZA CAERIA, HASTA
3259 m LUEGO CONTINUA SACANDO NORMAL HASTA 44
m (172 TIROS) BOMBEA 48 BBL FI.
17:00 - 17:45 0.75 06 P 11 (A) DESARMA ARREGLO DE LIMPIEZA, PZA x PZA , XO + 1
PM4.3/4" + TJR + 2 PM 4.3/4" + XO + ESCARIADOR + RNM
6.1/16" , SIN NINGUNA PARTICULARIDAD
17:45 - 18:45 1.00 06 P 11 (A) ARMA ARREGLO CON TR : TR TS-U 7" + PSC+ XO +1
PZA TUB 2.7/8 PJD (12.98 m)
18:45 - 00:00 5.25 06 P 11 (A) PROFUNDIZA ARREGLO ANTERIOR CON TUBERA
2.7/8 PJD HASTA 2316 m (121 TIROS) NO OBSERVO
DESPLAZAMIENTO DE FI (VOLUMEN PERDIDO 25 BBL)
15/02/2006 00:00 - 03:00 3.00 06 P 11 (A) CONTINUO PROFUNDIZANDO TR CON TUB 2.7/8 PJD
DESDE 2316 m HASTA 3300 m (173 TIROS) NO OBSERVO
DESPLAZAMIENTO DE FI (VOL PERDIDO 11 BBL)
03:00 - 03:30 0.50 06 P 11 (A) ANCLA TR EN 3299 m (CENTRO GOMAS) CABEZA DE
PESCA EN 3297,5
03:30 - 03:45 0.25 06 P 11 (B) ALISTA CONEXIONES PARA LLENAR POZO
03:45 - 05:45 2.00 06 T T2 11 (A) BOMBEA 400 BBL FI, LLENA POZO (NIVEL CALCULADO
1718 m)
05:45 - 06:00 0.25 06 P 11 (A) PRUEBA SELLO TR, BOCA LINER Y CAERIA CON 800
PSI (+)
06:00 - 14:30 8.50 06 P 11 (A) SACA TUBERIA 2.7/8 PJD + PSC DE TR HASTA
SUPERFICIE (173 TIROS+ 1 PZA) LLENA POZO CON 35 bbl
FI (normal)
14:30 - 00:00 9.50 06 P 11 (B) DESARMA CONEXIONES Y LINEAS LATERALES, SACA
VALVULAS LATERALES, APARTA BOP 13.5/8 -5000 Y
17/02/2006 13:30 - 14:15 0.75 10 P 11 ASIENTA 20M LBS PESO, LEVANTA HTA SACA VASTAGO
OBSERVA 5M SOBRE PESO HERRAMIENTA (AL SACAR
INDICADOR DE PESO, MARCA 110M LBS)
14:15 - 14:45 0.50 10 P 11 (B) APARTA VASTAGO
14:45 - 21:45 7.00 10 P 11 (A) SACA PUP JOINT TUB 2.7/8 PJD+ TUBERIA 2.7/8 PJD,
OBSERVA MOVIMIENTO OSCILATORIO DE LA AGUJA DEL
INDICADOR DE PESO, PERO NO OBSERVA INCREMENTO
DE PESO; PROFUNDIZA NUEVAMENTE ASIENTA 20M LBS
PESO, LEVANTA HTA SIN RESISTENCIA, SACA TUBERIA
2.7/8 PJD HASTA 1100 m (116 TIROS) BOMBEANDO
FLUIDO CADA 3 TIROS
21:45 - 22:30 0.75 10 L L1 11 (B) PRIDE REPARA ACELERADOR DE MOTOR EQUIPO
22:30 - 00:00 1.50 10 P 11 (A) CONTINUA SACANDO TUBERIA 2.7/8 PJD DESDE 1100
HASTA 240 m (TOTAL 162 TIROS)
18/02/2006 00:00 - 00:30 0.50 10 P 11 (A) TERMINA DE SACAR TUBERIA 2.7/8 PJD TIRO x TIRO
(172 TIROS) BOMBEO AL POZO 48 BBL FI
00:30 - 02:30 2.00 10 P 11 (A) DESARMA ARREGLO DE PESCA, APARTA RETRIEVING
TOOL, SIN RECUPERAR PESCA. OBSERVA "TRABAS" DE
LA PARTE INFERIOR DE LA HTA COMPRIMIDAS Y EN LA
PARTE SUPERIOR "J" CON HUELLAS DE FRICCIN Y
RELLENO METALICO, CAUSADA POR SEGUROS DE
PACKER, QUE SE DEFORMARON Y QUEDARON
INUTILIZADOS.
02:30 - 04:00 1.50 10 L L7 11 (A) BAJO TUBERIA 2.7/8 PJD HASTA 765 m. COLOCO
VALVULA DE SEGURIDAD Y ASEGURO POZO.
04:00 - 10:30 6.50 10 L L7 11 (B) ESPERA PESCADOR SPEAR 3.25" DE SCZ.
10:30 - 12:00 1.50 10 L L7 11 (A) SACA TUBERIA 2.7/8", PJD HASTA SUPERFICIE.
12:00 - 13:00 1.00 10 A 11 (A) ARMA BHA-SPEARS CON PSCD-SPEARS 3.1/4" + X-O +
2 PM 4.3/4" + TH 4.3/4" + 2 PM 4.3/4"+ X-O
13:00 - 21:30 8.50 10 A 11 (A) PROFUNDIZA BHA-SPEARS C/ TUB. 2.7/8", PJD HASTA
3324 m.
21:30 - 21:45 0.25 10 A 11 (B) LLENA TUBERIA C/ 50 Bbl FI
21:45 - 22:15 0.50 10 A 11 (B) COLOCA VASTAGO Y CONEXIONES. DETERMINA
PESO HTA. EN SUBIDA.- 105 M Lbs, EN BAJADA.- 105 MLbs
22:15 - 00:00 1.75 10 A 11 (A) PROFUNDIZA HTA. Y TOCA BP EN 3226.9 m. MANIOBRA
Y ASIENTA 12 M Lbs DE PESO, GIRA 3 VUELTAS
IZQUIERDA E INCREMENTA PESO A 20MLbs. LEVANTA
HTA. OBSERVA TENSION DE 15 MLbs CONTINUA
TENSIONANDO HTA. HASTA 40 M Lbs SOBRE PESO HTA.
SIN LOGRAR LIBRAR PESCA. CONTINUA
INCREMENTANDO TENSION HASTA 75 M Lbs SOBRE
PESO HTA, CON MISMO RESULTADO NEGATIVO. SE
QUITA TENSION Y SE ASIENTA PESO PARA ASEGURAR
PESCA Y CARGAR TIJERA. VUELVE A TENSIONAR C/ 75
Y 80 M Lbs SOBRE PESO, SIN LOGRAR ROMPER JUNTA
DE SEGURIDAD. REPITE MANIOBRA VARIAS VECES, SIN
EXITO. DURANTE MANIOBRA OBSERVA CAER TENSION
POR HABERSE SOLTADO PESCA (EFECTUO 3 GOLPES DE
TIJERA). REPITE MANIOBRA ASENTANDO PESO
C/VUELTAS A LA IZQUIERDA, AL TENSIONAR 10 M Lbs, SE
OBSERVA CAIDA TENSION, REPITE MANIOBRA VARIAS
VECES, SIN CONSEGUIR INCREMENTAR TENSION MAYOR
A 10 M Lbs.
23/02/2006 01:15 - 03:15 2.00 10 A 11 MISMA EN PESCA CON BARRA 1.1/2" DE 5 ' + TIJERA 1.1/2"
+ TAPON "XR".
03:15 - 08:00 4.75 10 A 11 (A) CONTINUA S/HTA. C/ARREGLO FINAL HASTA
SUPERFICIE, ENCONTRANDO RESISTENCIA AL PASO DEL
PACKER "PFH-7" EN SALIDA POR SECCION "C". SE
MANIOBRA REPETIDAS VECES, SIN EXITO.
08:00 - 14:00 6.00 10 A 11 (A) APARTA SALIDA DE LODO + BOP's + SECCION "C",
CON CUA ARAA. SACA HTA.CON PACKER PFH-7",
OBSERVANDO UNA DE LAS GOMAS DEL PACKER ROTA Y
SUELTA, TAMBIEN SE ADVIERTE QUE LOS FLEJES DE
LAS MORDAZAS DEL PACKER FUERON ACTIVADOS.
PARALELAMENTE RECUPERA TAPON "XR" DEL NIPLE
ASIENTO "XN" Y 100 % DE LA PESCA CON PESCADOR
"GS" + TIJERA + BARRA DE PESO 1.1/2". VOLVIO A
INSTALAR Y ASEGURAR SECCION "C" + BOP's + SALIDA
DE LODO + SALIDA LATERAL. + CONEXIONES DE
VALVULAS LATERALES Y CONEXIONES AL KOOMEY.
14:00 - 17:00 3.00 09 A 11 (A) BAJO 2 PZAS TUB 2.7/8 8RD + COLGADOR DE TUB +
NIPLES DE MANIOBRA, PROBO BOPs, CONEXIONES
LATERALES, LINEA BOPSs - MANIFOLD CON 500 Y 4000
PSI ; BOP ANULAR CON 500 Y 3500 PSI
17:00 - 19:15 2.25 09 A 11 (A) INTENTA SACAR COLGADOR DE TUB , SIN EXITO,
MANIOBRA EN REITERADAS OPORTUNIDADES,
INCREMENTANDO TENSION PAULATINAMENTE HASTA
60M LBS, LOGRANDO SACAR COLGADOR DE TUBERIA DE
CABEZAL DE PRODUCCION. APARTO NIPLES DE
MANIOBRA, COLAGDOR Y DOS PZAS TUB 2.7/8 8RD
19:15 - 19:30 0.25 09 A 11 (B) REALIZA REUNION DE SEGURIDAD Y COORDINACION
OPERATIVA
19:30 - 21:15 1.75 09 A 11 (A) BAJA INSTALACION FINAL: SUMP CATCHER+ 1PJ 2.7/8
8RD + NIPLE xn + 1 PJ 2.7/8 8RD + PACKER PFH + 1 PZA
TUB 2.7/8 8RD + NIPLA "X" + 1 PZA TUB 2.7/8 8RD +
CAMISA "XD" + 2 PUP JOINTS 2.7/8 + MDL 1
21:15 - 00:00 2.75 09 A 11 (A) CONTINUO PROFUNDIZANDO INSTALACION FINAL
TIRO X TIRO, HASTA 615 m : 20 PZAS TUB 2.7/8 8RD + MDL
2 + 20 PZAS TUB 2.7/8 + MND 3 + 20 PZAS TUB 2.7/8 8RD +
MDL 4.
24/02/2006 00:00 - 15:45 15.75 09 A 11 (A) CONTINUA BAJANDO INSTALACION FINAL (GAS LIFT
SIMPLE TERMINACION) DESDE 615 m HASTA 3327.4 m.
CALIBRANDO Y ARMANDO TUB 2.7/8 8RD PZA X PZA
15:45 - 16:30 0.75 09 P 11 (A) DIMENSIONA HTA, APARTA UNA PZA DE TUBERIA,
COLOCA UN PUP JOINT (SIN CUPLA) Y COLGADOR DE
TUB; COLOCA TAMBIEN NIPLES DE MANIOBRA Y BAJA
COLGADOR DE TUB CERCA DEL CABEZAL DE
PRODUCCION
16:30 - 19:45 3.25 09 P 11 (B) EQUIPETROL REALIZA TRES CARRERAS, EN 1RA
CARRERA, BAJA MANDRIL DE TAPON PX, MISMO QUEDA
DESELECTIVADO A LA ALTURA DE LA CAMISA, NO LOGRA
LLEGAR HASTA NA"X". EN 2DA CARRERA ANCLA
MANDRIL DE TAPON PX EN NA"X" Y EN 3RA CARRERA
CARRERA INTRODUJO IGUALADOR DE PRESION EN
TAPN PX.
19:45 - 20:00 0.25 09 P 11 (B) COLOCA ARBOLITO
24/02/2006 20:00 - 20:30 0.50 09 P 11 (A) LLENA TUBERIA CON 20 BBL FI (CALCULADO 30 BBL)
20:30 - 21:45 1.25 09 P 11 (A) REALIZA PRUEBA DE HERMETICIDAD DEL ARREGLO,
PRESURIZANDO POR DIRECTA CON 500 PSI ,
INCREMENTA PRESION LENTAMENTE HASTA 1700 PSI,
OBSERVA CAIDA DE PRESION, HASTA 1200 PSI, DONDE
ESTABILIZA. LUEGO DESFOGA TUBERIA.
21:45 - 23:30 1.75 09 P 11 (B) EQUIPETROL BAJA CALIBRADOR 2.3/16" PASA NA "X",
LLEGA HASTA NA "XN" VERIFICANDO DESPLAZAMIENTO
DEL TAPON DESDE NIPLE "X" HASTA NA"XN".
23:30 - 00:00 0.50 09 P 11 (A) PRESURIZA INSTALACION FINAL POR DIRECTA
HASTA NA"XN" CON 1400 PSI (+) ANCLA PACKER EN
3323.8 m (CENTRO GOMAS)
25/02/2006 00:00 - 03:45 3.75 09 P 11 (B) EQUIPETROL BAJA HTA, ABRE CAMISA, PESCA
IGUALADOR DE PRESION, LUEGO PESCA MANDRIL DE
TAPON PX; FINALMENTE CIERRA CAMISA , APARTA
LUBRICADOR
03:45 - 04:00 0.25 09 P 11 (B) APARTA ARBOLITO
04:00 - 04:15 0.25 09 P 11 (B) ASIENTA COLGADOR DE TUB EN SECCION "C" (5000
LBS DE PESO SOBRE EL PACKER; peso de la hta 70M lbs)
04:15 - 05:15 1.00 09 P 11 (B) AJUSTA ESPARRAGOS, REALIZA CONEXIONES PARA
LLENAR EA
05:15 - 07:30 2.25 09 P 11 (A) BOMBEA FI LLENA ESPACIO ANULAR CON 330 BBL
07:30 - 08:15 0.75 09 P 11 (A) PRUEBA SELLO PACKER, CA 9.5/8, BOCA LINER Y
CAERIA DE 7" HASTA 3323.8 m CON 400 Y 800 PSI (NIVEL
DE FLUIDO EN INTERIOR TUBERIA 1600 m)
08:15 - 08:45 0.50 09 P 11 (B) BPE COLOCA BPV
08:45 - 14:15 5.50 09 P 11 (B) APARTA BOPs. COLOCA ARBOLITO DE PRODUCCION
SIMPLE TERMINACION MMA 2.9/16-5M BRIDA INFERIOR
7.1/16-5M
14:15 - 15:00 0.75 09 P 11 (B) BPE PRUEBA HERMETICIDAD ANILLA R-46 Y
COLGADOR DE TUB. CON 3300 PSI
15:00 - 17:30 2.50 09 P 11 (A) PRUEBA HERMETICIDAD ARBOLITO DE PRODUCCION
CON 600 Y 3600 PSI. VERIFICA EA LLENO, CIERRA
VALVULAS, CONCLUYE OPERACIONES.