Beruflich Dokumente
Kultur Dokumente
The tunnel was
1,476 feet in length and
consumed 125 tons of
site was begun.
Soil from the tunnel
would fill more than
20 living rooms in an
At the confluence of the East cal analysis of the tunnel
River and the Hudson River, average American structure.
there was a deep submarine home!
canyon, a leftover from the
In the spring of 1953, I flew to
extensive land erosion caused Frankfurt, Germany, to meet
by the violent runoff of melt with a senior case officer at the
waters from the retreating Con-
CIA station. The officer told me
tinental Glacier. The canyon showed that the amount of soil that the tunnel site had not yet
was filled with the muck and expected to be brought out from been selected. He also advised
detritus of eons of erosion. This the tunnel and vertical shaft me that Lt. Col. Leslie M. Gross
fact required that a pressur- would fill to the brim more than had been selected as the tun-
ized shield, solely for the 20 living rooms in an average nels resident engineer. He
prevention of blowouts on the American home! Security and expressed regret that I had not
East River crossing, had to be silence dictated that not one been selected. I told him not to
moved the entire length of the cubic foot of soil be removed worry. 3
tunnel. The concept of such a from the site. A warehouse,
shield surfaced in design dis- with a basement for the stor-
cussions for the Berlin Tunnel age of the excavated soil and a The next subject we discussed
project. The Brooklyn-Battery first floor reserved for record- was a meeting with the British
Tunnel demonstrated the mag- ers and signal equipment, was in London. We would attend
nitude of the job of marshaling the solution. this meeting with Bill Harvey,
the experienced personnel, chief of our Berlin base. At the
materials, and equipment for My task began with an inspec- beginning of the meeting, I
the huge task of constructing a tion of existing tunnels in the started to discuss some notes I
tunnel and disposing of the Washington, DC, area, which had on the unfinished mathe-
excavated soil. Work on the 18- included utility bores, pedes- matical analysis of the tunnel
foot bore tunnel could not have trian walkways, storm drains, structure. Clearly the attend-
been done in silence. These and railroad maintenance tun- ees were not interested in
matters were a warning, nels. From this research, I mathematics. The discussion
because silence would be a top concluded that our tunnel turned to the matter of the form
priority in constructing the Ber- should be 6 feet in diameter of the tunnel design. The Brit-
lin Tunnel in secret. with a structure of steel-flanged ish proposed using heavy
corrugated liner platesthe 6- concrete blocks, which were
foot diameter would provide a common in the London Under-
Design Decisions comfortable working room at ground. I countered with the
the tunnel face. Next came idea of using steel liner plates,
Once the Berlin project received research at the Library of Con- which would be lighter and eas-
a green light, design specifica- gress to check the available ier to use in the tunnel and at
tions had to be determined; literature dealing with earth the tunnel face. This proposal
men and materials assembled; pressures on tunnels. I already was accepted.
and questions of site selection, had two textbooks and found
training, and transportation three relevant papers pub-
3 Time magazine of 7 May 1956 reported
answered. The big question lished by the American Society
that some Army people saw friends whom
that loomed was how to dispose of Civil Engineers. Together, they knew to be engineers appearing in
of the tons of soil that would be these provided the procedures I Berlin wearing the insignia of the Signal
excavated! Rough calculations needed to start the mathemati- Corps.
The circuit method of
computing earth
The next subject was a ques- pressures on tunnels of computing earth pressures
tion of using a shield. I did not required solving six on tunnels. It was a sort of cir-
offer an opinion because it was simultaneous cumferential calculus. The
a topic that I felt should be dis- equations. downside was that the circuit
cussed with Les Gross. Bill method of calculation required
Harvey got the impression that solving six simultaneous equa-
I did not know the difference tions! Perhaps this
between a shield and a coat-of- sophisticated method was a bit
advantage of keeping the align-
arms. When we returned to of overkill; however, the design
ment of the tunnel on course.
Frankfurt, it was suggested assumptions called for precise
We selected a prime contractor
that I make a drawing of a planning. The tunnel not only
for the liner plates and shield,
shield. Normally, a shield needed to be able to withstand
negotiated a classified con-
such as the one used on the a dead load of 10 or more feet of
tract, and work commenced.
Brooklyn-Battery Tunnel
soil overburden, but also had to
would not be used in a tunnel
bear a potential surcharge
as small as 6 feet. Other meth-
Assembling Men and loadto wit, Soviet or East
ods, such as poling, would be
Materials German 60-ton tanks riding
used to prevent a collapse of the
down Schoenefelder Chausee or
tunnel roof. However, I drew an
Working out of an office in one maneuvering around the open
engineering plan for a 6-foot
shield, and Bill Harvey later of the World War II temporary field above the tunnel.
used the drawing in his request buildings along the Reflecting
for final approval of the Pool near the Lincoln Memo- While Les narrowed the search
tunnel. 4 rial, Les started the process of for a site to test the installa-
recruiting his team. He selected tion of the shield and liner
Corps of Engineers officers and plates to New Mexico, I flew
I had my first meeting with
non-commissioned officers. He back to London for a meeting
headquarters. A short confer- also began to look into a site
ence resulted in an agreement with Bill Harvey. We traveled
out West where the liner plates with one of Bills British col-
that a shield should be used. A and shield could be assembled
shield would have the added leagues to a location to view the
for training for the up-coming
operation of the vertical shield
real thing.
needed to gain access to the
4 A shield is made of a steel tube slightly
Soviet communications cables.
larger than the tunnel bore. Hydraulic Les left the structural analysis
jacks are fitted inside the outer rim oppo- The vertical shield was demon-
to me. Ordinarily, earth pres-
site the cutting edge. The shield, support- strated by the British sappers
ed by an external framework, is assembled sure on a tunnel is figured at
four points: the overhead, both who would operate it at the
in a shaft at the beginning of a tunnel. The
shield then makes its first shove forward, sides, and the invert. This tech- site. This was a process that
and the face is dug out until 12 or more nique did not seem adequate. I required extreme patience and
inches of soil have been removed. The skill. During the motor trip, I
jacks are retracted and liner plates are in- spent nearly a week at the
stalled in the space uncovered when the Library of Congress searching suggested that as a cover for
soil is removed. The flanges of the liner for a better way of analyzing the tunnel site, we should build
plates are bolted to a reinforced concrete earth pressures. I found two one or two communications sta-
wall and then bolted to each other, com-
pleting the first ring of the structure of the technical papers that offered a tions that would exchange false
tunnel. The shield is then moved forward better approach. The papers traffic. This idea was met by icy
for construction of the second ring. discussed the circuit method stares.
Army Quartermaster Corps field of the compounds sani-
boxing facility near Richmond, tary system. The drainage
Virginia, for final packing for problem was quickly solved
most secret cargo was trans-
shipment to Berlin. Now he dis- with a pump. History does not
ported to West Berlin on an
covered that the boxing plant record what was used to allevi-
ordinary goods trainno armed
was due for closure and he ate the odor!
guards or security arrange-
quickly had to negotiate a 30-
ments of any kind. The cargo
day hold. At Richmond, the The dig proceeded. A wooden-
arrived in West Berlin without
metal parts were sprayed with rail track was built to keep the
incident.
a rubberized compound to elim- forklift on course. About one-
inate clanking as they were eighth of the spoil never left the
taken into the tunnel and The dig began in August 1954. tunnel. Sandbags were filled
assembled. We wanted to avoid A 10-foot-diameter vertical and stacked halfway up the
any kind of cowbell chorus deep shaft, 10 feet deep, was exca- sides of the finished tunnel.
in the tunnel. The shield, liner vated 15 feet inside the They were secured with steel
plates, conveyor belts, and a warehouse foundation. The cables and gave the tunnel
small, battery-powered forklift shield was assembled in this cross section a T-square look.
were shipped to Hamburg, Ger- shaft below the basement floor. The benches formed by the
many. From Hamburg, this The excavation of the tunnel sandbags were used to support
and store air-conditioning ducts
and power and message cables
running back and forth between
the equipment-room amplifiers
and the Ampex recorders,
which packed the first floor of
the warehouse.
out, grout under high pressure removed; then that slot was The electronic equipment room,
was pumped in, and then the closed and the next one opened. located under the roadway, was
plugs were replaced. The grout This sequence was repeated jammed with amplifiers, trans-
selected was called Vollclay, a until the target cables were formers, and tuners. All of
molecular composite of clay, reached, a process that required these devices used vacuum
minerals, and other ingredi- extreme patience and skill. tubesvalves, under British
ents. Once, a full boxcar of nomenclaturethat were high
Vollclay disappeared between The tap of the first cable was heat generators. The maximum
Chicago and Baltimore! It took completed in May 1955. A team expected heat load of these gen-
five days for the Office of Logis- of British specialists started the erators had been used to
tics to find the shipment, but work of transferring the cable calculate the required level of
the grout reached Berlin with- voice and signal circuits to the air-conditioning. Something
out delaying the progress on recording equipment. The full was wrong, however, because
the tunnel. tapes were collected and sent to the temperature in the equip-
London and Washington. ment room was rising.
The British team of sappers
startedand completed in the This problem had to be solved
spring of 1955the construc- Unexpected Development before winter set in. Some cold
tion of the vertical shaft needed morning, a frost-free black
to gain access to the Soviet On two occasions, I was invited mark might appear on the road-
communications cables. This to visit the tunnel site. I way over the equipment room,
was the most delicate and declined, suggesting that, with- perhaps extending into the field
tedious job in the entire pro- out a good reason for such a between the road and the ware-
cess. The vertical shaft was visit, we might be turning the house, calling attention to
carved out using a window tunnel site into a tourist attrac- something strange occurring
blind shield: A slot was opened tion. Then, a good reason below the surface. Emergency
and about an inch of soil was surfaced. action was needed.
A chilled-water air-condition-
ing system was the only
The completion of this
demanding project is a
tribute to the
over the equipment room were
dropping, almost certainly due
solution because there was no to the supplemental cooling
room for extra ducts on the
resourcefulness and system.
sandbag benches. Such a sys- expertise of an
tem, including about 1500 feet outstanding team of Further monitoring of ground
of newly developed 3/4-inch professionals. temperatures became irrelevant
plastic irrigation tubing, was when the tunnel was discovered
shipped to the site. The tubing
fitted nicely alongside the exist-
ing air ducts.