Beruflich Dokumente
Kultur Dokumente
Guidance Note
Summer Edition 2010
2
Pinsent Masons: regional presence, international expertise
receives the Final Payment Certificate pay to Contract for which the Contractor has not
the Contractor the certified amount therein.10 included an amount expressly in:
8. In the case of a Final Statement under the a. the Final Statement, and
EPCT, the Employer must pay to the
Contractor the amount which is finally due, b. (assuming the matter or things had arisen
less all amounts previously paid by the by the time the Taking-Over Certificate
Employer and any deductions.11 had issued) in the Statement at
completion,
Figure 1 (below) illustrates the procedure
concerning certification and payment under the are tolerably clear: The Employer shall not be liable
CONS, the CONS MDB and the P&DB. to the Contractor for that matter or thing, and so
(except in exceptional factual or legal
circumstances) the claim will fail.
project and the incidence of any disputes irrecoverable for want of express inclusion
under or in connection with the Contract. in the Statement as a contingent expense.
If a dispute has arisen when it comes time If you are ever unsure as to what (if any)
to issue the Statement at completion, a information needs to be submitted to the
draft final statement or the Final Statement, Engineer (or in the case of the EPCT, the
do include in the Statement an estimate of Employer) check this immediately with your
all future costs of the anticipated dispute trusted specialist legal advisor.
adjudication and arbitration, to ensure that
such costs will not be rendered
Figure 1 - Timeline for Certification and Payment under the CONS, CONS MDB and P&DB
This bulletin does not constitute legal advice. Specific legal advice should be taken before acting on any of the topics covered
www.pinsentmasons.com/asiapacific
Pinsent Masons 2010