INTRODUCTION
Value Management introduced into the Malaysian
Government project implementation framework
through Economic Planning Unit, Prime Ministers
Department Circular No. 3-2009.
Designed as a key management tool in the
execution of the 10th Malaysia Plan .
Reasons for implementation: to enhance project
optimisation and maximise value
This presentation demonstrates the value
management process as practised by the Malaysian
Government for flood mitigation projects.
2
1/29/2015
RATIONALE
VA VE VR
value value
criteria criteria
Clear value objectives Ensure value transition Ensure value transition
Ensure value transition Ensure value continuity Ensure value continuity
Ensure value continuity Ensure value consistency Ensure value consistency
Ensure value consistency Manage project risks Review value realization
Manage strategic risks Learn the lessons & improve
3
1/29/2015
VE LAB STAGE
6. Presentation 5. Development
4.Evaluation Phase
Phase Phase
value engineering
VE study duration
1 - 2 WEEKS The more time that is spent on
PRE LAB STAGE pre study information gathering &
PRIOR TO LAB
preparing, the better the study will be
- Steven male et al, 1998 -
2013JKRMALAYSIA
4
1/29/2015
value engineering
VE study composition
Entities with executive
Authorize authority to take decisions
or resolve issues in lab
2013JKRMALAYSIA
5
1/29/2015
1. INFORMATION PHASE
LAB PARTICIPANTS
Reference : JKR.VE.Lab.06
VALUE MANAGEMENT Page No : 1
Issue No : 1
Revision
List Of Participants No : 00
Date
6
1/29/2015
PROJECT : Rancangan Tebatan Banjir Sg Kedah/Anak Bukit, Kedah Darul Aman. GROUP : A
LEVEL : PROJECT / SPACE/ ELEMENT / COMPONENT PAGE : 8/10
SCOPE : DATE : 10/11/2013
: Construction and completion of 'Viaduct' and associated works at Section 49, Passage #4
PROJECT (KM 157 Gerik - Kota Bharu), Ecological Corridoor Central Forest Spine (CFS), Gerik, GROUP : A
Perak Darul Ridzuan
LEVEL : PROJECT / SPACE/ ELEMENT / COMPONENT PAGE : 1/10
SCOPE : GENERAL & PRELIMINARIES ITEMS DATE : 24/06/2013
7
1/29/2015
: Construction and completion of 'Viaduct' and associated works at Section 49, Passage #4
PROJECT (KM 157 Gerik - Kota Bharu), Ecological Corridoor Central Forest Spine (CFS), Gerik, GROUP : A
Perak Darul Ridzuan
LEVEL : PROJECT / SPACE/ ELEMENT / COMPONENT PAGE : 1/10
SCOPE : EARTHWORK / DRAINAGE / PAVEMENT / GEOTECHNICAL / PROVISIONAL SUM DATE : 24/06/2013
: Construction and completion of 'Viaduct' and associated works at Section 49, Passage
PROJECT #4 (KM 157 Gerik - Kota Bharu), Ecological Corridoor Central Forest Spine (CFS), Gerik, GROUP : A
Perak Darul Ridzuan
LEVEL : PROJECT / SPACE/ ELEMENT / COMPONENT PAGE : 3/10
8
1/29/2015
PROJECT GROUP :
LEVEL PAGE :
SCOPE DATE :
Notes:
FUNCTION -
B - BASIC FUNCTION
TYPE:
S - SECONDARY
FUNCTION
RS - REQUIRED SECONDARY
FUNCTION
9
1/29/2015
: Construction and completion of 'Viaduct' and associated works at Section 49, Passage #4 (KM 157
PROJECT GROUP : A
Gerik - Kota Bharu), Ecological Corridoor Central Forest Spine (CFS), Gerik, Perak Darul Ridzuan
LEVEL : PROJECT/ SPACE/ELEMENT/ COMPONENT PAGE : 1/5
:
: General & Preliminaries Item, Drainage Work, Pavement Works, Road Furniture, Traffic
SCOPE DATE 24/06/201
Management & Temporary Road Diversion
3
Notes:
FUNCTION -
B - BASIC FUNCTION
TYPE:
S - SECONDARY
FUNCTION
RS - REQUIRED SECONDARY
FUNCTION
3. CREATIVITY PHASE
10
1/29/2015
3. CREATIVITY PHASE
RULES OF BRAINSTORMING
Sincere
Be open mind
Respect others
Create permissive environment
Good human relations
Participate
Respond
Appreciate
Do not pre-judge
Quantity first, quality later
3. CREATIVITY PHASE
11
1/29/2015
PROJECT
LEVEL PAGE
SCOPE DATE
4. EVALUATION PHASE
12
1/29/2015
: Membina Dan Menyiapkan 'Viaduct' Dan Lain-lain Kerja Yang Berkaitan Di Seksyen 49, Laluan 4 (KM
PROJECT :A
157 Gerik - Kota Bharu), Koridor Ekologi Central Forest Spine (CFS), Gerik, Perak Darul Ridzuan
LEVEL : PROJECT / SPACE / ELEMENT / COMPONENT PAGE : 1/8
SCOPE : EARTHWORK / DRAINAGE / PAVEMENT / GEOTECHNICAL / PROVISIONAL SUM DATE : 25/06/2013
4. EVALUATION PHASE
3.Creativity 4.Evaluation
Phase Phase
DECISION
NOT AGREE
AGREE
6.Presentation 5.Development
Phase Phase
13
1/29/2015
4. EVALUATION PHASE
WHETHER:
EVALUATE Potential solution
INFORMATION Potential idea for future
DISCARD Non potential ideas
PROJECT
LEVEL PAGE
SCOPE DATE
14
1/29/2015
5. DEVELOPMENT PHASE
PROJECT WORK Establish or review project work programme (CPM) Project Work
Develop and agree Action Plan for post lab Programme
PROGRAMMING implementation Agreed Action Plan
& ACTION
PLANNING
INITIATE
Identify and register project risks Identified project
Discuss mitigation measures & responsible party (if risks
PROJECT RISK possible) [RISK REGISTER
MANAGEMENT TEMPLATE
ASSESS VE
Assess achievement of each VE Study Objective VE Study
Identify lessons learned assessment
STUDY Identified lessons
OBJECTIVES learned
GROUP RECOMMENDATIO
PROJECT N BOX:
:
EVALUATED
IDEA
YES/
PAGE :
(From Can We) NO
REGISTRATION
DATE : 25/06/2013
NO:1
EXISTING DESIGN / SKETCH COST BREAKDOWN
COST BREAKDOWN
15
1/29/2015
: Membina Dan Menyiapkan 'Viaduct' Dan Lain-lain Kerja Yang Berkaitan RECOMMENDATIO
GROU
PROJECT Di Seksyen 49, Laluan 4 (KM 157 Gerik - Kota Bharu), Koridor Ekologi :A N BOX:
P
YES/
Central Forest Spine (CFS), Gerik, Perak Darul Ridzuan
EVALUAT : A1: Can we increase percentage of preliminaries value
ED IDEA (from 6.7% to 7.0% or higher)? PAGE : 1/26
NO
REGISTRATION
DATE : 25/06/2013
NO:1
EXISTING DESIGN / SKETCH COST BREAKDOWN
EXISTING preliminaries is 6.7%
16
1/29/2015
6. PRESENTATION PHASE
3.Creativity 4.Evaluation
Phase Phase
NOT AGREE
DECISION?
NOT AGREE
AGREE
DECISION?
6.Presentatio 5.Development
n Phase Phase
AGREE
IMPLEMENTATION
6. PRESENTATION PHASE
17
1/29/2015
PART 2
35
CONTENTS
Ite
Topic Page
m
1 PROJECT INFORMATION
1.1 PROJECT BACKGROUND 3-5
1.2 PROJECT INTRODUCTION 6-7
1.3 Project Background Information
OBJECTIVE 8
1.4 SCOPE 9
1.5 OUTCOME 10
1.6 PROJECT GIVENS / CONSTRAINTS 11
1.7 PROJECT MUST 12
1.8 FAST DIAGRAM 13
1.9 PRE-LAB PROJECT COSTS 14
2 LAB ANALYSIS 15-16
3 POST-LAB PROJCET COSTS 17
18
1/29/2015
INFORMATIO
PROJECT BACKGROUND N PHASE
Pekan town lies at near the mouth of the Pahang River where
monsoonal floods are common during the months of November till
March
37
INFORMATIO
PROJECT BACKGROUND N PHASE
LOCATION PLAN
SOUTH
CHINA
PROJECT SITE SEA
LIPIS
To Kuantan
JERANTUT
RAUB KUANTAN
TEMERLOH
MARAN
ROMPIN
SOUTH
CHINA
SEA
19
1/29/2015
INFORMATIO
INTRODUCTION N PHASE
20
1/29/2015
INFORMATIO
PROJECT INTRODUCTION N PHASE
INFORMATION
OBJECTIVE PHASE
42
21
1/29/2015
INFORMATIO
ORIGINAL SCOPE N PHASE
Under the 10th Malaysia Plan, the original scope of works for Pekan
Flood Mitigation was as follows:-
43
INFORMATIO
PRE LAB PROJECT COSTS N PHASE
AMOUNT
NO. DESCRIOPTION (RM)
1. Preliminary works
Upgrading and Construction of Pump houses at Sungai
2.
Belibis (Parcel 1)
3. Construction of Flood Protection Bund/levees (Parcel 1)
Construction of Flow Control Structures (hydraulic
4.
structures) (Parcel 1)
Jumlah : 44
22
1/29/2015
INFORMATIO
OUTCOME N PHASE
45
INFORMATIO
PROJECT GIVENS / CONSTRAINTS N PHASE
No. ITEM
PROJECT GIVEN
1. Approved total project cost RM 600 million and implemented in phases
PROJECT CONSTRAINTS
1. 10th Plan (RP3-RP4) allocation of RM140 million to be completed by
2015.
2. Phase implementation causes cost increase and delayed achievement
of full project benefits
46
23
1/29/2015
FUNCTION
PROJECT MUST ANALYSIS
TEMPLATE
FUNCTION
FAST DIAGRAM ANALYSIS
PHASE
Divert flow
Divert flow
HOW WHY
Build channel /
Survey // SI
Survey SI tunnel
Earthworks
Earthworks
Build flood bund
Study
Study / wall
Flood
Flood
occurrences
occurrences Improve river
Improve river
Detail conveyance
Detail Design conveyance Geotechnical
Design Geotechnical works
works
Flood area
Flood area Widen / deepen
Implement rivers Drainageworks
Drainage works
Structures
structural
Flood depth
Flood depth measures Remove MM
&&E Eworks
works
constriction
Acquire Landscapeworks
Landscape works
Reduce flood land Replace
Reduce flood risk
risk bridges
Relocate Construction
Flood damages
Flood damages utilities
Install system
Flood losses
Flood losses Flood
Forecast flood and
Instrument
Implement forecasting
instrument
Non-
non
Flood victims
Flood victims Structures Alert Install siren
structural Flood warnings
community
measures
Produce flood
Flood maps
hazard map Flood Mitigation 48
24
1/29/2015
49 8. Examine size of Ketapang Link and replace with bridge with road E Lampiran 4a
culvert
9. Re-examine size of control room at Sungai Belibis pump station E
15. Change Type 1design from vertical flood wall to earth bund E
16. Review land area to acquire for bund type 1 design
17. Add land acquisition area for type 1 flood protection bund E
18. Review need of pump of 2500 l/s capacity for Sungai Belibis pump D
house
19. Provide mobile gen-set to replace standby gen-set E
(E = Evaluated, D = DISCARD, I = Information Only)
50 Lampiran 4
25
1/29/2015
Total Ideas = 23
Total Ideas Evaluated = 20
Total Ideas Discarded = 3
26
1/29/2015
EVALUATION
VALUE IMPLICATIONS / RECOMMENDATIONS OF CAN/DEVELOPME
WE
NT PHASE
53 Lampiran 5a
EVALUATION
VALUE IMPLICATIONS / RECOMMENDATIONS OF CAN WE /DEVELOPME
samb
NT PHASE
QUANTIT AMOUNT
NOS. ITEM / WORK RATE (RM)
Y (RM)
1 Bund type 1 Pahang River 21
4 Collector Drain 56
JUMLAH (RM)
Original cost RM
Proposed cost RM
Lampiran
54
5a
27
1/29/2015
EVALUATION
VALUE IMPLICATIONS / RECOMMENDATIONS OF CAN/DEVELOPME
WE
NT PHASE
2) CAN WE Add power sub station at Belibis Pump Station if Rujukan: *refer slide Can
we use existing pump We for item Parcel 1 Phase II
no. 4/22 sahaja
55 Lampiran 5a
EVALUATION
VALUE IMPLICATIONS / RECOMMENDATIONS OF CAN WE /DEVELOPME
samb
NT PHASE
Kadar
Bil. ITEM / Perihal Kerja Kuantiti Amaun (RM)
Harga (RM)
1 TNB Sub Station 1
JUMLAH (RM)
Kos Cadangan RM 0
Lampiran
56
5a
28
1/29/2015
PRESENTATIO
REPORT SUMMARY N PHASE
IDEA
TOTAL
TOTAL SUBMITTED TOTAL ACCEPTED
EVALUATED
22 19 17
COST REDUCTIONS RM 0
COST ADDITIONS RM 0
FINAL TOTAL
RM 0
(reduction/addition)
57 Lampiran 6
2) River Bund Type 2 Piling system can be switched to spun piles at lower cost 2.1) River Bund Type 2 Spun
Borepile pile
3) Land acquisition 15 km Parcel 3 bund/leveee can be targeted at residential and 3.1) Land acquisition 9.5km
marked-for-development areas only
4) Not in scope Necessary to extend bunding to Junection at Pasir Panjang 4) Flood control levee 1.6km long
village to increase protection of lands marked placed under
East Coast Economic Region (special areas of economic
development)
7)Ketapang Link: 10 m Size of Ketapang link can be reduced based on current 7) Ketapang Link channel size
channel, bridge 1 unit needs. A bridge is unnecessary and can be replaced with a 5m, twin box
culvert culvert 1 unit
58
29
1/29/2015
PRESENTATIO
LAB ANALYSIS N PHASE
9) TNB sub station at Sungai TNB (power company) assures that existing sub-stations can 9) Removed from scope
Mat Dulang support additional load requirements
10) Not in scope Lab agrees the need for additional power sub-station to 10) TNB sub station for control
support control structures along Pahang river bunds due to structures along Pahang River
long distance to existing sub-stations bund
11) Control house - area Lab agrees that size of control house can be reduced if 11) Control house area reduced
240 m2 standby gensets are replaced by portable genset to 180m2
12) Quality Assurance Quality Assurance elements have already been included 12) Removed from project scope
elements under preliminary costs
13) 3 nos. standby Gen-sets Lab agrees that mobile Gen-sets are more suitable as usage 13) 1 nos. mobile genset
at the control house is not frequent
59
PRESENTATIO
POST-LAB PROJECT COSTS N PHASE
AMOUNT
BIL. DESCRIPTION (RM)
1. Preliminary works
Upgrading and Construction of Pump houses at Sungai Belibis
2.
(Parcel 1)
3. Construction of Flood Protection Bund/levees (Parcel 1)
Construction of Flow Control Structures (hydraulic structures)
4.
(Parcel 1)
30
1/29/2015
PRESENTATIO
LAB SUMMARY N PHASE
To protect Pekan town and its surrounding, Miang River village to the south, Pulau Keladi to the west, Pasir
Panjang to the east from bank overflow of Pahang River with a protection level of 30 years ARI.
To minimise destruction of property, loss of lives and road connections due to floods in order to sustain economic
activities
Original Now
Project Area: Pekan and surroundings (2600 ha.) Project Area: Pekan and surroundings (6,200 ha.)
1. Land acquisition from local government Pahang 1. Land acquisition from local government Pahang
Project scope
Cost
MYR 35.14
ct
PRESENTATION
ACTION PLAN PHASE
VA report (draft) to VM
1 JPSM 14 December 2012 Finalise report
Section, EPU
Report circulated :-
a. EPU (2 set)
b. NRE (1 set)
Records and
4 c. JPS Pahang State (1 set) JPSM 11 January 2013
reference/action
d. JPS Malaysia HQ (1 set)
e. National Audit Dept. ( 1
set)
62
31
1/29/2015
Letter of
5 Appointment of consultant JPSM 25 February 2013
Appointment
Complete land
8 Land acquisition JPS / Consultants 30 September 2013
acquisition
Tender Documents
9 Prepare Tender Documents JPS / Consultants 30 October 2013
ready
63
10 Issue Letter of Acceptance JPS / Consultants 25 March 2014 Tarikh milik tapak
Certificate of
11. Construction completed JPS / Contractor 30 October 2017
Completion
64
32
1/29/2015
Issue appointment
12. Appoint study consultant JPSM 01 February 2016
letter
Land acquisition
15. Prepare Tender Documents JPS / Consultants 15 February 2017
completed
16. Prepare Tender Documents JPS / Consultants 15 July 2017 Tender Documents
65
PRESENTATION
ACTION PLAN PARCEL 2 CONTINUED PHASE
Certificate of
18. COMPLETION of works JPS/Contractor 30 October 2019
completion
66
33
1/29/2015
19. PREPARE Tender Documents JPS / Consultants 15 July 2017 Tender Dokumen
Date of Site
20. Issue Letter of Acceptance JPS / Consultants 25 March 2018
Possession
Certificate of
21. Completion of works JPS/Contractor 30 October 2019
Completion
67
PRESENTATION
SUMMARY OF OVERALL PROPOSAL - VM PHASE
Reductio
Value Addition
NO. ORIGINAL PROPOSED n
Added (RM)
(RM)
Harga tanah parcel 1 Harga tanah parcel 1
1/22 -
RM250,000/ ekar RM200,000/ ekar
Kos Pengalihan Utiliti Kos Pengalihan Utiliti
3/22
RM1.5Juta RM1.0Juta
Tiada dalam skop asal Bund Type 3 ext 500m
5/22 Bund Type 4 800m
Bund Type 5 250m
1 no TNB sub station di Tiada
6/22 Struktur Kawalan Mat
Dulang
Tiada dalam skop asal TNB sub station di Ban Sg
7/22
Pahang Control Structure
Skop Ketapang Link - channel 5 m, twin box
channel 10m, jambatan 1 culvert
8/22
unit
Control house with meeting Control house without
9/22
room meeting room
34
1/29/2015
PRESENTATIO
ENDORSEMENT OF VALUE MANAGEMENT LAB CONCLUSIONS
N PHASE
Project Cost : RM XXX,XXX,XXX.00 The Ministry of Natural Resources and Environemnt and the Economic Planning
Unit, Prime Ministers Dept. agree with the scope and costs as decided/agreed in
the Value Management Lab of 03-07 December 2012 for the Proposed Pekan
Finalised Project Scope Flood Mitigation Project Phase II
Name : XXXXXXXXXX
Project Area: Pekan town and Position : Undersecretary
surroundings (6,200 ha.) Development Division
Ministry of Natural Resources and Environemnt
1. Land acquisition from lcoal
government along Pahang River Date : .
(756 acres) Signature
2. Consultancy and Survey Costs
3. Upgrading and construction of Name : XXXXXXXXX
pump houses at Sungai Belibis Position : Director Economic Section-Environment and Natural Resources,
4. Construction of flood protection Economic Planning Unit, Prime Ministers Dept.
bund along Pahang River (4.25
km)
5. Construction of control Date : .
structures Signature
6. Construction of internal Name : XXXXXXXXXXXXX
drainage system Position : Director General
7. Bund construction - Parcel 2 (15 Department of Irrigation and Drainage
km)
8. Bund construction - Parcel 3 Date : .
(9.5 km) Tandatangan
69
Closing Remarks
VM relatively new but gaining strong
momentum
To adopt VM into various types of
development projects and fine tuning
intervention criteria
Establishing pool of experienced facilitators
and subject matter specialists
Improving lab process
70
35
1/29/2015
Thank you
Acknowledgment: Idrus Ahmad & Rohani Ahmad, Dept. of Irrigation & Drainage ;
Zawidatul Asma Ghazali (Dept. Of Public Works), Malaysia
36