Schedule Up - date 19 Maret 2010

ID Task Name Duration Start Finish Nov 29, '09 Dec 6, '09 Dec 13, '09 Dec 20, '09 Dec 27, '09 Jan 3, '10 Jan 10, '10 Jan 17, '10 Jan 24, '10 Jan 31, '10 Feb 7, '10 Feb 14, '10 Feb 21, '10 Feb 28, '10 Mar 7, '10 Mar 14, '10 Mar 21, '10 Mar 28, '10 Apr 4, '10 Apr 11, '10 Apr 18, '10 Apr 25, '10 May 2, '10 May 9, '10 May 16, '10 May 23, '10 May 30, '10
F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F
1 Firewater Tank Fondation CGS 1 & 5 133 days Tue 12/1/09 Thu 6/3/10

2 Project Start 0 days Tue 12/1/09 Tue 12/1/09 12/1

3 Site Preparation 47 days Tue 12/1/09 Wed 2/3/10

4 Site Visite 1 day Tue 12/1/09 Tue 12/1/09 Site Visite

5 PEP & Documentation 4 days Tue 12/1/09 Fri 12/4/09 PEP & Documentation

6 Pick up material from Warehouse 5 days Tue 12/1/09 Mon 12/7/09 Pick up material from Warehouse

7 Site KOM 1 day Thu 1/21/10 Thu 1/21/10 Site KOM

8 Mobilization 9 days Fri 1/22/10 Wed 2/3/10 Mobilization

9 Construction Works at CGS Area 1 82 days Mon 2/1/10 Tue 5/25/10

10 Survey Works 1 day Wed 2/3/10 Wed 2/3/10

11 Survey Stake out 1 day Wed 2/3/10 Wed 2/3/10 Survey Stake out

12 Earthwok 3 days Mon 2/1/10 Wed 2/3/10

13 Excavation & Compacted for Fondation 3 days Mon 2/1/10 Wed 2/3/10 Excavation & Compacted for Fondation

14 Equipment 32 days Thu 2/4/10 Fri 3/19/10

15 Drive Pile 8" 32 days Thu 2/4/10 Fri 3/19/10 Drive Pile 8"

16 Piping Works 10 days Mon 3/22/10 Fri 4/2/10

17 Cutting Pipe Pile and Install cap base 10 days Mon 3/22/10 Fri 4/2/10 Cutting Pipe Pile and Install cap base

18 Civil Works 37 days Mon 4/5/10 Tue 5/25/10

19 Sand Bedding 2 days Mon 4/5/10 Tue 4/6/10 Sand Bedding

20 Lean Concrete 4 days Wed 4/7/10 Mon 4/12/10 Lean Concrete

21 Fab Formwork 4 days Tue 4/13/10 Fri 4/16/10 Fab Formwork

22 Install Formwork 6 days Mon 4/19/10 Mon 4/26/10 Install Formwork

23 Fab Rebar 4 days Tue 4/27/10 Fri 4/30/10 Fab Rebar

24 Install Rebar 7 days Mon 5/3/10 Tue 5/11/10 Install Rebar

25 Delivery & Puring Concrete ready mix 4 days Wed 5/12/10 Mon 5/17/10 Delivery & Puring Concrete ready mix

26 Curring Concrete K 225 @ 28 days 0 days Mon 5/17/10 Mon 5/17/10 5/17

27 Dismantle Formwork 4 days Thu 5/20/10 Tue 5/25/10 Dismantle Formwork

28 Construction Works at CGS Area 5 86 days Thu 2/4/10 Thu 6/3/10

29 Survey Works 2 days Thu 2/4/10 Fri 2/5/10

30 Survey Stake out 2 days Thu 2/4/10 Fri 2/5/10 Survey Stake out

31 Earthworth 3 days Mon 2/8/10 Wed 2/10/10

32 Excavation & Compacted for Fondation 3 days Mon 2/8/10 Wed 2/10/10 Excavation & Compacted for Fondation

33 Equipment 11 days Mon 3/22/10 Mon 4/5/10

34 Drive Pile 8" 11 days Mon 3/22/10 Mon 4/5/10 Drive Pile 8"

35 Piping Works 6 days Tue 4/6/10 Tue 4/13/10

36 Cutting Pipe Pile and Install cap base 6 days Tue 4/6/10 Tue 4/13/10 Cutting Pipe Pile and Install cap base

37 Civil Works 33 days Wed 4/14/10 Fri 5/28/10

38 Sand Bedding 2 days Wed 4/14/10 Thu 4/15/10 Sand Bedding

39 Lean Concrete 4 days Fri 4/16/10 Wed 4/21/10 Lean Concrete

40 Fab Formwork 4 days Thu 4/22/10 Tue 4/27/10 Fab Formwork

41 Install Formwork 6 days Wed 4/28/10 Wed 5/5/10 Install Formwork

42 Fab Rebar 4 days Thu 5/6/10 Tue 5/11/10 Fab Rebar

43 Install Rebar 5 days Wed 5/12/10 Tue 5/18/10 Install Rebar

44 Delivery & Puring Concrete 3 days Wed 5/19/10 Fri 5/21/10 Delivery & Puring Concrete

45 Curring Concrete K 225 @ 28 days 0 days Fri 5/21/10 Fri 5/21/10 5/21

46 Dismantle Formwork 3 days Wed 5/26/10 Fri 5/28/10 Dismantle For

47 House keeping 2 days Mon 5/31/10 Tue 6/1/10 Hous

48 PSSR and Commissioning 2 days Wed 6/2/10 Thu 6/3/10

49 Project Finish 0 days Thu 6/3/10 Thu 6/3/10

Project: WR - 208387 Firewater Tank Fondation CGS 1 & 5 Task Milestone Rolled Up Task Rolled Up Progress External Tasks Group By Summary
Note : The Project Fire water foundation running after the project Site Prepara
Progress Summary Rolled Up Milestone Split Project Summary Deadline

Riduan Harun Page 1