Sie sind auf Seite 1von 2

Project : AVIC Mixed Development Project

Daily Diary : By Supervision Consultant, CECB. (Zone A)

Date : 06/05/2016

1.0 Weather:

Duration 06hrs 08hrs- 10hrs 12hrs 14hrs 16hrs 18hrs 22hrs 24hrs 02hrs 04hrs
_
08hrs 10hrs 12hrs 14hrs 16hrs 18hrs 20hrs 24hrs 02hrs 04hrs 06hrs
Weather S S S S S S LR
* S Sun Shine, HR-Heavy Rain, LR Light Rain, G- Gloomy, W Windy

2.0 Manpower:
A: Main contractor:

Category Nos. Category Nos. Category Nos.


Project manager 01 Masonry workers - Surveyor 01
Site Manager 02 R/f fabricators 22 Carpenters 31
Site Engineer 02 Mech. Workers 02 Welders -
Tech. assistant 04 Operators 04 General workers 04
Foreman 09 Concreters - Survey Helper 01
B: Nominated sub-contractor:

Category Nos. Category Nos. Category Nos.


Kents officers 7 Kents workers 14

3.0 Machineries & Equipment:

Category Nos. Category Nos. Category Nos.


Tower crane 2 Breakers 1 Excavators 0
Mobile crane 0 Vibrators 2 Mixers 0
Bar bending machines 2 Pump car 1 water pumps 1
Bar cutting machines 2 Survey instruments 2 Jack Hammers 2
compressors 1 Welding plants 1

4.0 Inspection Carried out:

Location Element Works inspected By whom Status


TF at 23- Slab Slab top r/f Situge,Sampath, Completed
27/A-D Lasitha
TF at 27- Slab Slab r/f Situge,Sampath In progress
32/A-E
TF at 24- Slab Shear links Sampath In progress
27/A-D
TF at Tower 1 RC wall R/f Sampath,Mahinda In progress

TF at tower 2 Lift wall R/f Sampath In progress

TF at Tower 1 MS rod Vertical extending Chathura Done


TF at Tower 2 MS rod Horizontal laying Chathura Done

1 of 2
5.0 Drawings / Sketches referred for inspection:

Description Construction Shop Sketches/


Issue Drawings Log note
Transfer Level-Civil X X X

6.0 Effects of work (accidents, breakdown, delay etc...):

7.0 Details of Material used for construction:

Material Approved Brand Material Approved Brand


Reinforcement Plumbing
R/f Melwa
Concrete
Electrical
Water proofing

8.0 Defects observed:

Location Element Type of defects Action taken Status

9.0 Site Instruction / Defect Notification issued:

Description Instruction Ref No Remarks

10.0 Approved Method statements referred and received:


A: referred

B: received
Description Ref. No By whom

11.0 General Comments:

Prepared By: S.M.J.M.T.Situge Date: 11/05/2016

2 of 2