Test Summary for BSNL Ph7 VT Lab test for ZTE Core Equipment

Element TC No. Test Content Mapping VT Item * No. Test Date Test Result

6.1.1 Call admission feature for overload control CS GR 2.3.1 8/16/2017 Pass
6.1.2 MSC Server Access overload control CS GR2.9 (i) 8/16/2017 Pass
6.1.3 Internal overload control Test CS GR 2.9 (ii) 8/16/2017 Pass
6.1.4 MSC Server overload and recovery Test CS GR 2.17.2 (ii) 8/16/2017 Pass

MSCS CS GR 11.18.1 8/17/2017 Pass


6.1.5 MSC Server overload more than 50% Test
CS GR 11.18.2 8/17/2017 Pass
GR11.18.3&11.18.4&11.18
6.1.6 MSC Server overload control Test 8/17/2017 Pass
.5&10.11.1(vi)
6.1.7 MSC Server paging congestion control Test DTR 2.34(ii) 8/17/2017 Pass
6.1.8 Typical MSC Server Dimensioning Test DTR 2.53.1& DTR 1.44 8/17/2017 Pass
6.2.1 MGW System VAD and Jitter-Buffer Test GR 3.1.12 8/18/2017 Pass
MGW 6.2.2 Typical MGW Dimensioning Test DTR 2.59.2 8/18/2017 Pass
6.2.3 MGW troubleshooting Test DTR 3.2.3 8/18/2017 Pass
GR 4.1.6 & GR 10.11.1
6.3.1 Load Regulation in HLR&AUC 8/21/2017 Pass
(vi) &R 4.5.8
HLR
6.3.2 The capacity of one FE board in HLR DTR 2.60.12 8/21/2017 Pass
6.3.3 The capacity of DSA and DST board in HLR DTR 2.60.12 8/21/2017 Pass

3.1.1 &
GSM/GPRS to UMTS QoS mapping GR/DTR 6.4.5 8/23/2017 Pass
3.1.2

3.2 Access Control Lists (ACL) GR 3.2.13.3 8/23/2017 Pass


GGSN
3.3.1 Fall-back (UMTS only) GR 3.2.25 8/23/2017 Pass
3.3.2 Fall-forward (UMTS only) GR 3.2.25 8/23/2017 Pass
3.4 OverLoad Test GR 6.6.1 & 6.6.2 & 6.6.3 8/23/2017 Pass
GR 6.6.2 & 6.6.3&
3.5 SGSN Overload Control Function 8/22/2017 Pass
6.6.1&3.1.17
SGSN 3.6 SGSN QoS Mapping Function GR/DTR 6.4.5 8/22/2017 Pass
3.7 SGSN Gs Function GR 3.1.13 (ii) 8/22/2017 Pass
3.8.1 Throughput capacity test (based on one board) DTR 14.4.6 i) d) 8/24/2017 Pass

PCRF
3.9 Upgrade and update of Operating System DTR 14.4.6 i) f) 8/24/2017 Pass
PCRF
3.3.10 Online backup DTR 14.4.6 i) g) 8/24/2017 Pass
3.3.11 Sliding window usage DTR 14.4.5 xix 8/24/2017 Pass