Beruflich Dokumente
Kultur Dokumente
Services
Core & Mandatory Competencies
Quantity Surveying & Construction
Presented by:
Fred Cooksey & Gerry OLoughlin
Programme morning
Main text
16.15 Questions
16.30 Close
Objectives
Main text
5
Commercial management of construction
Main text
Overview
6
Commercial management of construction
7
Commercial management of construction
What are the sources of cost data that are often used by
Quantity Surveyors when preparing estimates?
8
Commercial management of construction
9
Commercial management of construction
A covering letter
Executive summary
Specification note Main text
Assumptions
Exclusions
Cashflow forecast
Drawings and other information on which the estimate is based
Risk register
Value engineering proposals etc.
10
Commercial management of construction
11
Commercial management of construction
12
Construction technology & environmental
services
Main text
Overview
13
Construction technology & environmental
services
Level 1 Main text
14
Construction technology & environmental
services
Level 1 Sample Question Main text
Can you explain what a composite slab is and when would you
use it?
15
Construction technology & environmental
services
Level 2 Main text
16
Construction technology & environmental
services
Level 2 Sample Question & Answer Main text
Client requirements The chosen system and design needs to align with
what the client wants to achieve from the project and the functional space
requirements of the building. Main text
Occupants requirements
Cost in terms of the budget available for the project
External conditions The location of the building
Control requirements for the system
Space The amount of space available for plant rooms
Award criteria e.g. BREEAM, LEED, Estidama
17
Construction technology & environmental
services
Level 3 Main text
18
Construction technology & environmental
services
Level 3 Sample Question & Answer Main text
19
Contract practice
Main text
Overview
20
Contract practice
You should focus your attention on the following aspects of a
Main text
construction contract.
Insurances What insurances are specifically required by the contract
and who is responsible for providing them?
Payments What payment provisions are set out in the contract (e.g.
monthly valuation procedure, certification and payment periods, retention)?
21
Contract practice
contract for issuing an EOT and what are the consequence of an EOT
award? (pay particular attention to the different formulae used to calculate
head office overhead contribution during prolongation periods)
Reporting What are the reporting requirements set out in the contract
and what information is to be provided within these reports?
Notice Periods Are there any clauses within the contract that require
notice to be given by the contractor and what are the consequences of not
giving this notice within the period stated?
22
Contract practice
This is about your basic awareness of contract types and will involve you
having a knowledge and understanding of the following.
23
Contract practice
24
Core Contract practice
This contract creates a rigid separation of the parties and their rights,
obligations and risks. Sometimes resulting in Main
a lack of co-operation thus
encouraging defensive and adversarial behaviour with time and cost
text
problems being left to the end of the project to be resolved. This presents a
risk of protracted final accounts and disputes.
Risks are normally passed down the supply chain to contractors and sub-
contractors and there is usually little opportunity for overlap of design and
construction.. Traditional forms of contract have a long history so are
therefore tried and tested and are focussed on the clients main requirements
of cost and time.
25
Contract practice
Design and Build Form This is probably the most popular form of
procurement giving the client single point responsibility.
26
Contract practice
27
Contract practice
Framework and Term service arrangements where the client has an ongoing
or rolling construction programme which can provide continuity for
contractors on the framework thus avoiding repeated tendering. The
framework agreement consists of 2 contracts one of which will be for the
length of the framework and the second for a specific project.
Term service contracts are a single contract with the client and contractor
Main text
agreeing a plan or schedule of works to be performed over the period of the
contract and generally used for planned maintenance type projects.
28
Contract practice
Main text
29
Contract practice
What advice did you give to the client on the level of Liquidated
Damages to be inserted into the contract?
30
Contract practice
Main text
31
Contract practice
32
Design economics & cost planning
Main text
Overview
Main text
33
Design economics & cost planning
Adjustments that may be required - location, specification, time and market forces.
34
Design economics & cost planning
This will involve consideration of costs over the whole life of a building and
not just the capital costs. Main text
35
Design economics & cost planning
36
Design economics & cost planning
How do you develop your initial cost plan through the pre-
tender stage of the project ensuring all parties understand the
financial position of the project?
Depending on the amount of information available you will develop your cost
plan by preparing an initial approximate estimate and then dividing up your
estimate into the different building elements.Main
You need to review this cost
plan with the client identifying areas of uncertainty and risk along with the
text
contingency allowances.
As the design develops you must engage in constant cost checks on the
information as it develops so that any differences can be highlighted and any
risks can be eliminated.
37
Design economics & cost planning
38
Design economics & cost planning
Mention the risk register and the importance of completing the register and
mitigating the risk as much as possible.
39
Commercial management of construction
Main text
In your groups
40
Commercial management of construction
Main text
41
Commercial management of construction
42
Commercial management of construction
Risk identification
Structured interviews with key parties
Risk workshop with design team, client
Prepare risk checklist from previous schemes
Use lessons learned from previous similar projects
Risk response
Take action first to reduce uncertainty
Eliminate features in the design causing the risk
Main text
Transfer the risk to another party
Tolerate risk of low impact
Allow a contingency to deal with risk
Risk quantification
Use a Monte Carlo risk analysis to determine the financial impact of the identified
risk and also the likely contingency to be set.
43
Commercial management of construction
Main text
44
Construction technology & environmental
services
1. Can you outline the most common ventilation systems
Main text
used in a building?
45
Construction technology & environmental
services
1. Can you outline the most common ventilation systems
Main text
used in a building?
Natural ventilation which describes the process of air entering and circulating
in a building and will be provided using windows which are manually
controlled or programmed to open in different conditions.
Stack ventilation which allows air to rise through high level openings.
Main text
Mechanical ventilation using an air handling unit which can produce cool and
warm air depending on the temperature required within the room.
46
Construction technology & environmental
services
2. What factors should be considered when choosing between
Main text
a
concrete or steel framing solution for a commercial office
building?
47
Construction technology & environmental
services
3. What ventilation system was used on your project and how did you work
Main text
with the team to ensure the most cost effective design solution was
achieved?
48
Contract practice
1. The key client requirement for your project was the Main
contract
text
49
Contract practice
1. The key client requirement for your project was the Main
contract
text
50
Contract practice
51
Contract practice
No the QS, along with the other design team members, can
advise the client of the situation and the onus is on the client to
deduct them provided a certificate of non-completion has
Main text
been prepared.
52
Design economics & cost planning
Main text
Main text
3. How would you deal with a cost plan that is over the clients
budget?
53
Design economics & cost planning
54
Design economics & cost planning
55
Design economics & cost planning
Main text
3. How would you deal with a cost plan that is over the clients
budget?
Use a project you have been involved in where you dealt with
such a situation drawing on all your experience.
56
Procurement & tendering
Main text
Overview
57
Procurement & tendering
58
Procurement & tendering
Types of procurement.
Design and build
Traditional
Management contracting
Construction management
Measured term
Serial contracting Main text
Lump sum
Re-measured
Reimbursable
Target costs
Guaranteed maximum price
59
Procurement & tendering
If you have worked on a Partnering scheme then outline the scheme and how
it worked from a Partnering perspective. Main text
60
Procurement & tendering
In 1998 the Construction Task Force set up by the Government to deal with
these issues published its report Rethinking Construction. This gave birth to
the Movement for Innovation (M4I) and a pool of demonstration projects,
which in the new spirit of openness, provide Main
a text bank of knowledge on
good practice and innovation. The Government has followed this up with its
own guidance documents produced by the Treasury.
One of the initiatives recommended was a more open and less adversarial
approach to construction projects partnering.
61
Procurement & tendering
contractual details.
Carry out tendering and negotiation processes e.g. single and two stage
tendering
Use of codes of practice and electronic tendering.
Identifying the advantages and disadvantages associated with each
procurement route
62
Procurement & tendering
What are some of the benefits and pitfalls of using the different
procurement routes?
Main text
63
Procurement & tendering
Traditional Control over design process No one person is responsible for the
design and construction
Quality control through the direct Design will be developed as fully as
reporting of the design team to the client possible
No risk premium built in by the Main text Time and cost are likely to escalate
contractor
Design & Build Single point responsibility Lack of control over quality
64
Procurement & tendering
65
Procurement & tendering
Framework
Agreements The contractor only needs to May not always be the best value
negotiate once for a series of contracts for money
66
Procurement & tendering
PFI/PPP Risks borne by the private sector Loss of control by the public sector
Partnering Less adversarial approach to the project Difficult once the partnership breaks
down
Buildability achieved through the Can be non competitive
contractors early involvement
and all parties in partnership
67
Procurement & tendering
68
Procurement & tendering
69
Project financial control & reporting
Main text
Overview
70
Project financial control & reporting
The use of the brief to describe both the scope of the design work and
construction works.
71
Project financial control & reporting
72
Project financial control & reporting
73
Project financial control & reporting
74
Project financial control & reporting
Where you have initiated a change yourself, can you tell me the
information that you included on the change control proposal
form prior to presenting it to the client?
75
Project financial control & reporting
76
Project financial control & reporting
77
Project financial control & reporting
Your final assessment record states that you established the cost
reporting protocol on project X. What approach did you take to
this?
While you may have standard cost report formats within your organisation,
you would be expected to agree the cost reporting protocol with the client
and/or project manager at the start of the commission,
Main text including the
following.
78
Quantification & costing of construction
works
Main text
Overview
79
Quantification & costing of construction
works
Level 1 Main text
80
Quantification & costing of construction
works
Level 1 Sample Questions & Answers Main text
81
Quantification & costing of construction
works
Level 2 Main text
82
Quantification & costing of construction
works
Level 2 Sample Questions & Answers Main text
83
Quantification & costing of construction
works
Level 3 Main text
84
Quantification & costing of construction
works
Level 3 Sample Question & Answer Main text
You need to identify where the basement is. Is it in a city centre site or
is it on a brownfield site. You should develop a take-off list and identify
each of the measureable items stating its unit of measurement as
appropriate. Main text
85
Commercial management of construction
Main text
In your groups
86
Procurement & tendering
Main text
3. How do you make partnering happen and how do you
facilitate this?
87
Procurement & tendering
Main text
Two Stage Tender (The Contractor is selected for the first stage on
the basis of limited scope i.e. preliminaries, overheads and profit.
The second stage will involve negotiation on an open book
tendering basis) Main text
89
Procurement & tendering
Main text
90
Procurement & tendering
Main text
91
Procurement & tendering
Main text
You may want to try and relate this to a specific project you worked on. Once
instigated a properly set up and effective partnering contract has many
benefits in the terms of time, cost and quality.
92
Procurement & tendering
Main text
93
Procurement & tendering
Main text
94
Project financial control & reporting
Main text
1. What is the purpose of change control on a construction
project?
2. What information would you include within the cost report for
a project procured under a single stage traditional
procurement route?
Main text
95
Project financial control & reporting
Main text
Q. What is the purpose of change control on a construction
project
A. This provides a method of assessing and managing change giving
details of consequent cost, programme and scope effect.
96
Project financial control & reporting
Main text
97
Project financial control & reporting
Final account progress Main text
Contract position
Cash flow position
Progress in the period and current financial position
Outstanding information
Major risks or causes for concern
98
Project financial control & reporting
Main text
Q. I see from your submission that you advised the client of
the change control procedure implemented on your project. Can
you tell me the key issues you considered in advising the client
on the procedure you adopted?
99
Project financial control & reporting
Main text
What was the procurement process on your project and will this
have any effect on your change control process
At what point in the design process of your project was it
appropriate to start measuring change and why?
Confirm with the client and/or the project manager what costs need
to be included within the change e.g. professional fees, v.a.t. etc
Who takes responsibility for raising the change proposal
How will the change control procedure
Main text
link with contract
instructions and contractors procedures(RFIs) during the
construction period
100
Quantification & costing of construction
works
1. What are the standard methods of measurements that you are
Main text
aware of?
101
Quantification & costing of construction
works
Main text
102
Quantification & costing of construction
works
Main text
103
Quantification & costing of construction
works
2. What are Nominated Sub-contractors Main text
104
Quantification & costing of construction
works
3. The client is thinking of using a design & build Main text
procurement strategy but is concerned as to what form of
pricing documentation he will receive from the contractor
Under a design & build procurement route the contractor will normally
supply a schedule of rates so that in the event of variations occurring
the clients representative will have rates available to determine
whether or not he is getting value for money.
Main text
105