Research and community service core process V/President office
Summary of research project cost breakdown
Coordinators name:
Research title:
Summary of total research cost breakdown
No Activity/Item Approved budget
1 Stationary costs - 2 Per diem cost Researchers Mille 75 days x 169 = 12675 birr Chifra 75 days x 121 = 9075 birr Total; 21750 birr Data collectors - Field assistants - Laboratory assistants 2675 birr 3 Transportation (392.00+ 571.2) X 2 = 1926.40 birr 4 Laboratory equipment purchase cost 12450.00 birr 5 Data purchase cost - 6 Chemicals purchase cost - 7 Laboratory analysis cost - 8 Rental cost - Ground total 38801.40 birr
Work plan for the activities of research
No Activities Responsible Time
body 2017 Mar Apr May June July Aug Sep Oct Nov Dec Jan 1. Data collection
NB: All (38801.40 birr) budget were granted by samara university research directors at once to conduct this research. That is 100% at once. Duration of the research is 6 month