Doc No:

AAWSA-Water and Sanitation Development & SWS/KBTS/374/17


Rehabilitation Project Office
Issue No: 22/03/17

Short summary of Progress Report


(Up to March 21, 2017)

Client : AAWSA-Water and Sanitation Development & Rehabilitation Project Office


Contractor: ASER Construction JV IFH Engineering PLC
Consultant: SWS Consultancy

Project : Construction of New Sewer Lines for Bethel Area & Resizing of the Existing
Trunk Sewer Lines from MW-KL Kality Catchment
Subject: Short Summary of Progress Report upto March 21, 2017
Date : 22 March, 2017

#1.Project Data

Contract signing date 18th of May, 2015

Project handing over date 26th of May, 2015

Project commencement date 15 days after signing of the contract


agreement

Project Start Date (for Non Imported items) June 3, 2015

Project Start Date (for Imported Items). January 14, 2016

Project completion period 18 months

Project Completion date for all works July 14, 2017

Project cost (original Contract) ETB 371,961,348.42 and


USD 2,067,812.20

Revised Project Cost (including Variation No.1) ETB 433,763,577.77 and


USD $ 4,072,906.82
Table-1.1: Project Information

Item No. Description Total Quantity (km)

Bill No. 1 General Items


Section-I: Establishment of Facilities & Services
Section-II: Miscellaneous Items
Bill No. 2 New Trunk Sewer Lines 26.65
Bill No. 3 Resizing of the Existing Trunk Sewer Line 4.40
Total 31.05

1
Doc No:
AAWSA-Water and Sanitation Development & SWS/KBTS/374/17
Rehabilitation Project Office
Issue No: 22/03/17

Short summary of Progress Report


(Up to March 21, 2017)

#2. TO DATE CONSTRUCTION ACTIVITIES STATUS REPORT


Bill No.2 & 3: New Sewer Lines and Resizing of existing sewer line

Preparation of Ground/Working Platforms and access roads

Clearing, grubbing works, excavation, fill for platform construction, cart


away unsuitable material and preparation up to sub grade level completed for 12.55km

Gravity Sewers

Total to date trench Excavation and GRP Pipe Installation


No. Sewer Section DN Size Pipe Laid Length
(mm) (m)
1 MW03X to MW03AB, MW57F11 to MWB520, MW57F04A 300 2790
MW57F05, MW177 to MW171, MW55AK-MW55AV

2 57m to MW57BG, MW135 to MW168, MH447-MW55AK 600 8530


MW03A-MW03M, MW03s02-MW03s03A1, MW98- MW108

3 MW57D1-MW57N1, MW87 to MW98 900 1529


4 MW31-MW43, MW03 to MW28, MW58 MW71 1000 3580

5 LJ-ME 1500 1200


6 LK - KL 1600 1606
Total 19,235 M

Manholes and Structures

Total to date Manholes and Structures Construction Completed Sections


No. Description Station/Size unit Qty
1 Construction of manholes DN1000mm, DN1200mm, DN1500mm, No 230
DN1800mm, 2.2 X 2.2 m Square Man
holes
2 RCC Retaining Wall m3 125
3 Masonry Retaining wall m3 1875
4 Pipe culvert 42, 48, 2x48 m 76
5 Box culvert - No 1 Completed
6 Slab culvert - No 1 on progress & 1
completed

River Crossing and Pipe Support Structures

o Structural Steel bridge between MW and MW01, MW79 and MW80 has been
completed and installed ; and construction of minor piers for pipe support on
progress

2
Doc No:
AAWSA-Water and Sanitation Development & SWS/KBTS/374/17
Rehabilitation Project Office
Issue No: 22/03/17

Short summary of Progress Report


(Up to March 21, 2017)

To date Progress summary for major activities


Major Activities Physical Progress
No Description unit Contract Revised Actual Executed %age
Qty Contract Qty Qty Executed as
Qty per Actual
1 Trench excavation, Backfill Km 32.11 39.24 31.04 19.24 62%
& Cart away
2 GRP Sewer pipe Supply & Km 32.11 35.45 31.04 19.24 62%
Installation
3 Manhole Construction No 1433 1482 423 230 54.4%

4 Leakage Test Km 32.11 35.45 31.04 4.8 15.5%

Financial Progress with 15% VAT (77.5%)

No Contract Revised Executed % age Paid Amount as % age


Amount Amount Amount Executed of IPC 11 Paid as of
as of contract
contract
1 619,935,580.7 739,844,296.28 471,483,269.11 77.5% 452,490,019.52 73%

4. PROBLEMS ENCOUNTERED
Problems Encountered
Right of way problems along different sewer sections as listed in Table below;
Revised Work Schedule
Leakage Test for laid and constructed manholes was delayed as end plugs are not
appropriate for the already constructed manholes;
Sewer Sections with ROW issues;
No Sewer Section Length(m) Remarks
1 MW5706-MW5708 154 Radio fana
2 MW55-MW56 38 Alert Round about
3 MW56-MW56G 373 Alert-Aweliya School
4 MW76A-MW78 40 Kolfekeranyo youth center
5 MW-MG1 500 Mekanisa Gofa
6 MG2- ME 124 Gofa Garage
7 MB-MC-MD 122 Gofa Garage
8 MA-LZ 40 Gofa Garage
Total 1391m

3
Doc No:
AAWSA-Water and Sanitation Development & SWS/KBTS/374/17
Rehabilitation Project Office
Issue No: 22/03/17

Short summary of Progress Report


(Up to March 21, 2017)