Beruflich Dokumente
Kultur Dokumente
Project : Construction of New Sewer Lines for Bethel Area & Resizing of the Existing
Trunk Sewer Lines from MW-KL Kality Catchment
Subject: Short Summary of Progress Report upto March 21, 2017
Date : 22 March, 2017
#1.Project Data
1
Doc No:
AAWSA-Water and Sanitation Development & SWS/KBTS/374/17
Rehabilitation Project Office
Issue No: 22/03/17
Gravity Sewers
o Structural Steel bridge between MW and MW01, MW79 and MW80 has been
completed and installed ; and construction of minor piers for pipe support on
progress
2
Doc No:
AAWSA-Water and Sanitation Development & SWS/KBTS/374/17
Rehabilitation Project Office
Issue No: 22/03/17
4. PROBLEMS ENCOUNTERED
Problems Encountered
Right of way problems along different sewer sections as listed in Table below;
Revised Work Schedule
Leakage Test for laid and constructed manholes was delayed as end plugs are not
appropriate for the already constructed manholes;
Sewer Sections with ROW issues;
No Sewer Section Length(m) Remarks
1 MW5706-MW5708 154 Radio fana
2 MW55-MW56 38 Alert Round about
3 MW56-MW56G 373 Alert-Aweliya School
4 MW76A-MW78 40 Kolfekeranyo youth center
5 MW-MG1 500 Mekanisa Gofa
6 MG2- ME 124 Gofa Garage
7 MB-MC-MD 122 Gofa Garage
8 MA-LZ 40 Gofa Garage
Total 1391m
3
Doc No:
AAWSA-Water and Sanitation Development & SWS/KBTS/374/17
Rehabilitation Project Office
Issue No: 22/03/17