PURCHASE ORDER
Order No: PD.2312/394-MECD/RK/PIPE
Sunlion Piping Engineering Co. Ltd., Date : 21/07/2015
Room 1112, Floor 11, Wanda Plaza Bld 2,
Your Ref : Quotation No. SPECL/2015-30
Baoshan, Shanghai,
Dated : 12/03/2015.
P. R. China.
Mode of Dispatch : By Sea Freight
Fax : +86 (21) 6129 9377. By Date : Within 90 days on receipt of L/C.
Terms : CFR Chittagong Basis.
Through: Shajib Polymers & Engineering Co., Dhaka.
Phone : +88 02 9332836.
Please supply the goods shown below on the terms and conditions indicated in this purchase order.
Item Unit Price Total Price
Description Quantity Unit
No. (USD) (USD)
A. Line Pipe.
As per attached Technical Specifications enclosed
herewith. Size and quantity are as follows:
168.30 mm OD (6" ND) x WT 7.9 mm x 12 Meter 7,008 Meter US$ 24.75 US$ 173,448.00
A.1.
ERW API 5L, X-46 Line Pipe. Meters.
168.30 mm OD (6" ND) x WT 6.4 mm x 12 Meter Meter US$ 42.00 US$ 2,016.00
A.2. 48 Meters.
API 5L, X-42 Seamless Line Pipe.
TOTAL FOB PRICE (including Packing, Handling, Inland Freight & Documentation) ... US$ 175,464.00
(+) Estimated Ocean Freight Charges up to Chittagong Sea Port (Bangladesh)
(to be paid at actual subject to maximum allowed here). ... ... US$ 14,931.00
TOTAL CFR (CHITTAGONG) BY SEA PRICE, PAYABLE THROUGH L/C ... ... US$ 190,395.00
(-) 0.25% Agency Commission on Total FOB Price to be paid in
Local Currency to Shajib Polymers & Engineering Co. Ltd., Dhaka. ... ... ... US$ 438.66
NET CFR (CHITTAGONG) BY SEA PRICE, PAYABLE THROUGH L/C. ... ... US$ 189,956.34
Note:- a) Please acknowledge receipt of this order and return one copy with seal and signature on each
b) Manufacturer: i) Tianjin Boyu Steel Pipe Co. Ltd., China for ERW Line Pipe.
ii) Shandong Luxing Steel Pipe Co. Ltd., China for Seamless Line Pipe.
Page 1 of 10
TITAS GAS TRANSMISSION & DISTRIBUTION CO. LTD.
(A COMPANY OF PETROBANGLA)
TITAS Titas Gas Bhaban, 105, Kazi Nazrul Islam Avenue, Kawran Bazar C/A, Dhaka-1215, Bangladesh.
GAS
Fax: +880-2-9120513 Phone: +880-2-8119380 PABX: +880-2-9103960-69 E-mail: titas_gas2009@yahoo.com
1964
Technical Specifications
API 5L ERW X46 Line Pipe 6"DN (168.30mm) WT 7.9mm
This Specification covers the manufacturer, acceptance and delivery of steel pipes with Electric Resistance
Welded Longitudinal seam for gas line pipe. Said pipes shall be manufactured in accordance with the following
listed in the order of precedence:
(a) This specification
(b) API 5L Spec. (Latest edition)
(c) ASME Guides for Transmission and Distribution Piping System (Latest edition)
1. MATERIAL:
Steel of Grade-X46, PSL-2 in accordance with API 5L shall be used. The steel shall be fully- killed, fine
grained steel and shall comply with the following Heat Analysis requirements at maximum:
C = 0.22%
Mn = 1.30%
P = 0.025%
S = 0.015%
Si = 0.45%
Heat analysis shall be made and the results of the analysis shall be recorded in the inspection certificate.
2. METHOD OF MANUFACTURING:
Electric Resistance Welding: Longitudinal welding without filler metal.
3. DELIVERY ALLOWANCE AND PIPE LENGT:
The pipe shall not have any girth welds. The length of each batch of pipe shall be 12m50mm.
Delivery Allowance : +Nil, -(minus) 1%, Delivery Allowance and Pipe length beyond this shall not be
acceptable.
4. HYDROSTATIC TESTING:
Each length of pipe shall be tested hydrostatically in accordance with API 5L Spec. PSL-2.
5. LONGITUDINAL WELD:
The hardness of the longitudinal weld and the heat affected zone shall not exceed 250 HV 10. Complete
penetration shall be warranted and NON-Destructive Inspection shall be carried as per API 5L Spec.
6. TOLERANCES:
6.1 Diameter Tolerance
The tolerance for diameter of pipe body shall be 0.75%.
The tolerance for diameter at Pipe Ends (within 100.0mm of the pipe end) shall be:
Plus Tolerance = 1.60mm, Minus Tolerance = 0.4mm.
Page 2 of 10
TITAS GAS TRANSMISSION & DISTRIBUTION CO. LTD.
(A COMPANY OF PETROBANGLA)
TITAS Titas Gas Bhaban, 105, Kazi Nazrul Islam Avenue, Kawran Bazar C/A, Dhaka-1215, Bangladesh.
GAS
Fax: +880-2-9120513 Phone: +880-2-8119380 PABX: +880-2-9103960-69 E-mail: titas_gas2009@yahoo.com
1964
The internal weld bead of each pipe shall be ground flush with the parent material over a length of 150
mm from each end of pipe.
The finished pipe ends shall be free of lamination and other defects Ends shall be checked for such defects
by ultrasonic testing of 25mm from each end of each pipe.
P.O.NO. PD.2312/394-MECD/RK/PIPE dt.21/07/2015.
8. COATING:
The pipes shall be cleaned and be given a mill coating on external surface to protect it from rusting during
transit/transportation.
The individual pipe numbers shall be selected consecutively. In case of pipe manufactured by more than
one Manufacture, the individual pipe number shall be on the basis of individual mill with a three letters
abbreviation of the mill identifying the Manufacturer to be followed by pipe number starting with 1(one).
Heat number shall be traceable by means of pipe number and vice versa. The pipe length (in meter with
two decimals) shall be painted in white color on the surface of the each pipe at one end.
9. MARKING:
The identification markings shall be in accordance with API. The following identification markings shall
paint stencil on one end of each pipe length approximately 140mm from the pipe end:
- API Monogram;
- Manufacturer's mark;
- Material grade;
- Outside diameter times specified wall thickness;
- Pipe number;
- Process of manufacturing;
- Test pressure;
- Weight per meter;
- Country of origin;
- Contract Number
- Destination.
The pipe length (in meter with two decimals) shall be painted in white color on the surface of each pipe at
one end.
10. In addition to the warranty certificate required under clause-6 of the tender document, the supplier shall
have to furnish the following special warranty certificate with the shipping document:
"purchaser is to be reimbursed for direct replacement costs of any Pipe furnished that falls under field
Hydrostatic Tests due to defect of materials, workmanship, or lack of compliance with all aspects of the
specifications agreed upon. Such tests shall be applied at the time of construction of the pipeline and before
the pipe line is placed in service. The test pressure shall not exceed the one with which the pipes are tested
in mill(s) in accordance with the specifications agreed upon. These replacement costs shall include and be
limited to Pipe, Labour & Equipment Rental for locating, cutting out and replacing defective Pipe.
Suppliers/Manufacturer shall be responsible only for the failures which are proved to be attributable to his
own responsibility and Supplier's/Manufacturer's liability shall be in any case not more than 5% of the
contract amount. Supplier's/Manufacturer's liability shall be, in any case limited to the above and shall
terminate after 12 months of delivery of the pipes at Chittagong Port or after 18 months of final shipment
whichever date comes earlier".
Page 3 of 10
TITAS GAS TRANSMISSION & DISTRIBUTION CO. LTD.
(A COMPANY OF PETROBANGLA)
TITAS Titas Gas Bhaban, 105, Kazi Nazrul Islam Avenue, Kawran Bazar C/A, Dhaka-1215, Bangladesh.
GAS
Fax: +880-2-9120513 Phone: +880-2-8119380 PABX: +880-2-9103960-69 E-mail: titas_gas2009@yahoo.com
1964
This Specification covers the manufacturer, acceptance and delivery of seamless steel pipes for gas line pipe.
Said pipes shall be manufactured in accordance with the following listed in the order of precedence:
(a) This specification
(b) API 5L Spec. (Latest edition)
(c) ASME Guides for Transmission and Distribution Piping System (Latest edition)
1. MATERIAL:
Steel of X42. PSL-2 in accordance with API 5L shall be used. The steel shall be fully- killed, fine grained
steel and shall comply with the following Heat Analysis requirements at maximum:
C = 0.24%
Mn = 1.20%
P = 0.025%
S = 0.015%
Si = 0.40%
Heat analysis shall be made and the results of the analysis shall be recorded in the inspection certificate.
2. METHOD OF MANUFACTURING:
Seamless Pipe: Cold/Hot finished.
3. PIPE LENGTH AND DELIVERY ALLOWANCE:
The pipe shall not have any girth welds. The lengths of each batch of pipes shall be 12m 50mm. Delivery
allowance: + Nil, -(minus) 1%, Pipe length & delivery allowance beyond this shall not be acceptable &
rejected.
4. HYDROSTATIC TESTING:
Each length of pipe shall be tested hydrostatically in accordance with API 5L Spec. PSL-2.
5. TOLERANCES:
5.1 Diameter Tolerance
The tolerance for diameter of pipe body shall be 0.75%.
The tolerance for diameter at Pipe Ends (within 100.0mm of the pipe end) shall be:
Plus Tolerance = 1.60mm, Minus Tolerance = 0.4mm.
The internal weld bead of each pipe shall be ground flush with the parent material over a length of 150
mm from each end of pipe.
The finished pipe ends shall be free of lamination and other defects Ends shall be checked for such defects
by ultrasonic testing of 25mm from each end of each pipe.
P.O.NO. PD.2312/394-MECD/RK/PIPE dt.21/07/2015.
7. COATING:
The pipes shall be cleaned and be given a mill coating on external surface to protect it from rusting during
transit/transportation.
The individual pipe numbers shall be selected consecutively. In case of pipe manufactured by more than
one Manufacture, the individual pipe number shall be on the basis of individual mill with a three letters
abbreviation of the mill identifying the Manufacturer to be followed by pipe number starting with 1(one).
Heat number shall be traceable by means of pipe number and vice versa. The pipe length (in meter with
two decimals) shall be painted in white color on the surface of the each pipe at one end.
8. MARKING:
The identification markings shall be in accordance with API. The following identification markings shall
paint stencil on one end of each pipe length approximately 140mm from the pipe end:
- API Monogram;
- Manufacturer's mark;
- Material grade;
- Outside diameter times specified wall thickness;
- Pipe number;
- Process of manufacturing;
- Test pressure;
- Weight per meter;
- Country of origin;
- Contract Number
- Destination.
The pipe length (in meter with two decimals) shall be painted in white color on the surface of each pipe at
one end.
9. In addition to the warranty certificate required under clause-6 of the tender document, the supplier shall
have to furnish the following special warranty certificate with the shipping document:
"purchaser is to be reimbursed for direct replacement costs of any Pipe furnished that falls under field
Hydrostatic Tests due to defect of materials, workmanship, or lack of compliance with all aspects of the
specifications agreed upon. Such tests shall be applied at the time of construction of the pipeline and
before the pipe line is placed in service. The test pressure shall not exceed the one with which the pipes
are tested in mill(s) in accordance with the specifications agreed upon. These replacement costs shall
include and be limited to Pipe, Labour & Equipment Rental for locating, cutting out and replacing
defective Pipe. Suppliers/Manufacturer shall be responsible only for the failures which are proved to be
attributable to his own responsibility and Supplier's/Manufacturer's liability shall be in any case not more
than 5% of the contract amount. Supplier's/Manufacturer's liability shall be, in any case limited to the
above and shall terminate after 12 months of delivery of the pipes at Chittagong Port or after 18 months of
final shipment whichever date comes earlier".
Page 5 of 10
TITAS GAS TRANSMISSION & DISTRIBUTION CO. LTD.
(A COMPANY OF PETROBANGLA)
TITAS Titas Gas Bhaban, 105, Kazi Nazrul Islam Avenue, Kawran Bazar C/A, Dhaka-1215, Bangladesh.
GAS
Fax: +880-2-9120513 Phone: +880-2-8119380 PABX: +880-2-9103960-69 E-mail: titas_gas2009@yahoo.com
1964
Page 6 of 10
TITAS GAS TRANSMISSION & DISTRIBUTION CO. LTD.
(A COMPANY OF PETROBANGLA)
TITAS Titas Gas Bhaban, 105, Kazi Nazrul Islam Avenue, Kawran Bazar C/A, Dhaka-1215, Bangladesh.
GAS
Fax: +880-2-9120513 Phone: +880-2-8119380 PABX: +880-2-9103960-69 E-mail: titas_gas2009@yahoo.com
1964
3.2 Expenses or Port Demurrage incurred due to delay in dispatching shipping document by the
Supplier or defects therein will be debited to the Supplier or their Local Agent.
3.3 Care should be taken that the Shipping Document are prepared free of any discrepancy. The
Supplier or their Local Agent will have to bear Local Banks Commission, if any, accrued on the
Shipping Document received on collection basis, pursuant to caluse-5(b) (iii).
6. Warranty Clause :
The Shipping Documents must accompany the following Warranty:
a) The Supplier warrants that all goods supplied under the contract are new, unused, of the most recent
or current models and incorporate all recent improvements in design and materials unless provided
otherwise in the Purchase Order. The Supplier further warrants that all goods supplied under this
Purchase Order shall have no defect arising from design, materials or workmanship (except in so far
as the design or materials is required by the Purchasers specifications) or from any act or omission of
the Supplier, that may develop under normal use of the supplied goods in the conditions obtaining in
the country of final destination.
b) This warranty shall remain valid for 12 (twelve) months after the goods or any portion thereof as the
case may be, have been delivered to the final destination indicated in the Purchase Order, or for 18
(eighteen) months after the date of shipment from the port of loading in the source country, whichever
period concluded earlier, unless specified otherwise in the Purchase Order.
c) The purchaser shall promptly notify the Supplier in writing of any claim arising under this Warranty.
d) Upon receipt of such notice, the Supplier shall, with all reasonable speed, repair or replace the
Page 7 of 10
TITAS GAS TRANSMISSION & DISTRIBUTION CO. LTD.
(A COMPANY OF PETROBANGLA)
TITAS Titas Gas Bhaban, 105, Kazi Nazrul Islam Avenue, Kawran Bazar C/A, Dhaka-1215, Bangladesh.
GAS
Fax: +880-2-9120513 Phone: +880-2-8119380 PABX: +880-2-9103960-69 E-mail: titas_gas2009@yahoo.com
1964
defective goods or parts thereof, as per Terms & Conditions of the Purchase Order at no cost to the
Purchaser.
e) If the Supplier, having been notified, fails to remedy the defect(s) within a reasonable period, the
Purchaser may proceed to take such remedial action as may be necessary, at the Suppliers risk and
expenses and without prejudice to any other rights which the Purchaser may have against the Supplier
under the Purchase Order.
P.O.NO. PD.2312/394-MECD/RK/PIPE dt. 21/07/2015.
7. Inspections and Test :
a) The Purchaser reserves the right to inspect the ordered materials before shipment through its
appointed inspection agent as stated below at its own cost but such inspection shall not absolve the
Supplier from responsibility/or liability nor be interpreted in any way to imply acceptance of such
goods. Name and Address of our appointed Inspection Agent:
M/S. GEO-CHEM FAR EAST PTE LTD.,
B1k 47, Ayer Rajah Crescent,
#05-01, Ayer Rajah Industrial Estate, Singapore 139947.
Tel: +65 67774620 Fax: +6567774650
Email: singapore@geochemgroup.com or
Continental Inspection Co., Dhaka Or their affiliate.
b) The inspection and test may be conducted on the premises of the Supplier or its subcontractor(s), at
point of delivery and at the goods final destination. Where conducted on the premises of the
Supplier or its sub-contract(s), all reasonable facilities and assistance, including access to drawings
and production data, shall be furnished to the inspectors at no charge to the Purchaser.
c) Should any inspected or tested goods fail to conform to the specifications, the Purchaser may reject
them, and the Supplier shall either replace the rejected goods or make all alternations necessary to
meet the requirements of the specifications, free of cost to the Purchaser.
d) The purchasers right to inspect, test and where necessary, reject the goods after the goods arrival
in the Purchasers country shall in no way be limited or waived by reason of the goods having
previously been inspected, tested and passed by the Purchaser or its representatives prior to the
goods shipment from the country of origin.
8. Insurance :
The Marine Insurance coverage for the goods ordered will be done by the Purchaser through
Sadharan Bima Corporation, Tejgaon Branch, 115/A Airport Road, Farmgate, Dhaka, Bangladesh,
for which the Supplier shall be bound to submit promptly necessary particulars of each shipment as
stated in clause-3.1 above to the Deputy General Manager (Purchase) of the Purchaser.
9. Liquidated Damage :
Subject to clause-10 below, if the Supplier fails to deliver any or all of the goods within the time
period specified in the Purchase Order, the Purchaser shall, without prejudice to its other remedies
under the terms and conditions of the Purchase Order, deduct from the order price as liquidated
damage, a sum equivalent to 0.10% of the invoice value of the delayed goods for each day of delay
until actual delivery up to a maximum deduction of 10% of the Order Price. Once the maximum is
reached, the Purchaser may consider termination of the Purchase Order.
c) Shipping Marks :
A white band shall be painted all around each package which shall be distinctly marked. Each
package shall have the following information printed on it in bold letters: (i) Port of Landing, (ii)
Name of Consignee, (iii) Purchase Order No. (iv) Brief Description of Goods, (v) Package Number
(vi) Gross and Net Weights and (vii) Measurements. FURTHER, the following Monogram
measuring about 1/4th of the package, must also be painted in red on at least two sides of each
package:
T COY T
above, the Purchaser may procure, upon such terms and in such manner as it deems appropriate,
goods similar to those undelivered, and the Supplier shall be liable to the Purchaser for any excess
costs for such similar goods. Notwithstanding the above, the Supplier shall continue performance
of the Contract to the extent not terminated.
13 Settlement of Disputes :
In the event of any dispute or difference arising between the parties upon any terms or clause of the
Purchase Order, the same shall be attempted by both parties for amicable settlement. In case the
parties cannot amicably resolve their disputes or differences within 28 days from the date of raising
the dispute by either party, then the same shall be referred to an arbitration of two Arbitrators, one
appointed by each party. If the Arbitrators fail to reach a decision then the matter be referred to an
Umpire appointed by the Arbitrators before entering on the reference. The award of the Arbitration
shall be final and binding on the parties and shall be in lieu of any other remedy. The Arbitration
shall be conducted in accordance with the UNCITRAL Arbitration Rules as at present in force. The
venue of Arbitration will be at Dhaka, Bangladesh.
-0-