SUMMARY

SR.# DELAYING EVENTS DELAY (DAYS) ANNEXURE


Delay due to exceptionally adverse climatic conditions
1 190 A
Under clause 44.1 (c)

Delay due to strikes at Rawalakot


2 11 B-1
Under clause 44.1 (e)

Delay due to strikes by Brick Kiln owners


3 28 B-2
Under clause 44.1 (e)

Delay in giving possession of sites


4 C-1
Under clause 42.2

Delay in providing drawings & construction data


5 C-2
Under clause 6.4

Variations
6 D
Under clause 51.1
ANNEXURE A

DELAY DUE TO EXCEPTIONALLY


ADVERSE CLIMATIC CONDITIONS

DELAY: 190 Days


ANNEXURE B-1

DELAY DUE TO STRIKES AT RAWALAKOT

DELAY: 11 Days
ANNEXURE B-2

DELAY DUE TO STRIKES BY BRICK KILN OWNERS

DELAY: 28 Days
ANNEXURE C-1

DELAY IN GIVING POSSESSION OF SITES


ANNEXURE D

VARIATIONS
ANNEXURE C-2

DELAY IN PROVIDING DRAWINGS &


CONSTRUCTION DATA