Sie sind auf Seite 1von 594

Main Editorial Panel

D. J. Littler, BSc, PhD, ARCS, CPhys, FlnstP, CEng. FIEE (Chairman)

* Professor E. J. Davies, DSc, PhD, CEng, FIEE

H. E. Johnson

F. Kirkby, BSc, CEng, MIMechE, AMIEE

P. B. Myerscough, CEng, FIMechE, FINucE

W. Wright, MSc, ARCST, CEng, FIEE, FIMechE, FInstE, FBIM

Volume Consulting Editor


* Professor E. J . Davies, DSc, PhD, CEng, FIEE

Volume Advisory Editor


P. Hambling, CEng, MIMechE

Authors
Chapters 1 8 - 2 G. F. Hunt, BSc(Eng), CEng, MIEE

Chapter 3 M . Douglass, CEng, MIMechE

Chapter 4 A. R. Woodward, BSc(Eng)


D. L. Howard, BSc, CEng, MIMechE
E. F. C. Andrews, CEng, MIMechE, ABTC

Chapter 5 B. J. Beecher, BSc, CEng, MIMechE

Chapter 6 * J. J. Arnold, BSc, CEng, MIEE


J. R. Capener, BSc, CEng, MIEE

Series Production
Managing Editor P. M. Reynolds

Production Editor H. E. Johnson

Resources and T. A. Dolling


Co-ordination J. R. Jackson
MODERN
POWER STATION PRACTICE
Third Edition

Incorporating Modern Power System Practice

British Electricity International, London

Volume C
Turbines, Generators and Associated Plant

PERGAMON PRESS
OXFORD . NEW YORK . SEOUL . TOKYO
U.K. Pergamon Press pic, Headington Hill Hall,
Oxford 0X3 OBW, England
U.S.A. Pergamon Press, Inc., (395, Saw Mill River Road,)
Elmsford, New York 10523, U.S.A.

SEOUL Pergamon Press Korea, KPO Box 315, Seoul 110-603,


Korea

JAPAN Pergamon Press, 8th Floor, Matsuoka Central Building,


1-7-1 Nishi-Shinjuku, Shinjuku-ku, Tokyo 160, Japan

Copyright 1991 British Electricity International Ltd


All Rights Reserved. No part of this publication may be
reproduced, stored in a retrieval system or transmitted
in any form or by any means: electronic, electrostatic,
magnetic tape, mechanical, photocopying, recording or
otherwise, without permission in writing from the copy-
right holder.
First edition 1963
Second edition 1971
Third edition 1991
Library of Congress Cataloging in Publication Data
Modern power station practice: incorporating modern
power system practice/British Electricity International.
3rd ed. p. cm.
Includes index.
1. Electric power-plants. I. British Electricity Inter-
national.
TK1191.M49 1990
62.3V21 dc20 90-43748

British Library Cataloguing in Publication Data


British Electricity International
Modern power station practice. 3rd. ed.
1. Electric power-plants. Design and construction
I. Title II. Central Electricity Generating Board
621.3121.
ISBN 0-08-040510-X (12 Volume Set)
ISBN 0-08-040513-4 (Volume C)

Printed in the Republic of Singapore


by Singapore National Printers Ltd
Colour Plates
(between pp 482 and 483)

FIG. 4.24 Heysham 2 condenser modular construction


FIG. 6.31 Flux test on completed core
FIG. 6.41 View of a 660 MW generator stator end-windings
FIG. 6.90 Condition monitor (NEI Parsons Ltd)
FIG. 6.97 Dinorwig motor-generator during site winding

VI
Foreword
G. A. W. Blackman, CBE, FEng
Chairman, Central Electricity Generating Board
and Chairman, British Electricity International Ltd

FOR OVER THIRTY YEARS, since its formation in 1958, the Central Electricity Generating
Board (CEGB) has been at the forefront of technological advances in the design,
construction, operation, and maintenance of power plant and transmission systems. During
this time capacity increased almost fivefold, involving the introduction of thermal and
nuclear generating units of 500 MW and 660 MW, to supply one of the largest integrated
power systems in the world. In fulfilling its statutory responsibility to ensure continuity of a
safe and economic supply of electricity, the CEGB built up a powerful engineering and
scientific capability, and accumulated a wealth of experience in the operation and
maintenance of power plant and systems. With the privatisation of the CEGB this
experience and capability is being carried forward by its four successor companies
National Power, PowerGen, Nuclear Electric and National Grid.
At the heart of the CEGB's success has been an awareness of the need to sustain and
improve the skills and knowledge of its engineering and technical staff. This was achieved
through formal and on-job training, aided by a series of textbooks covering the theory
and practice for the whole range of technology to be found on a modern power station. A
second edition of the series, known as Modern Power Station Practice, was produced in
the early 1970s, and it was sold throughout the world to provide electricity undertakings,
engineers and students with an account of the CEGB's practices and hard-won experience.
The edition had substantial worldwide sales and achieved recognition as the authoritative
reference work on power generation.
A completely revised and enlarged (third) edition has now been produced which updates
the relevant information in the earlier edition together with a comprehensive account of
the solutions to the many engineering and environmental challenges encountered, and which
puts on record the achievements of the CEGB during its lifetime as one of the world's
leading public electricity utilities.
In producing this third edition, the opportunity has been taken to restructure the
information in the original eight volumes to provide a more logical and detailed exposition
of the technical content. The series has also been extended to include three new volumes on
'Station Commissioning', 'EHV Transmission' and 'System Operation'. Each of the eleven
subject volumes had an Advisory Editor for the technical validation of the many
contributions by individual authors, all of whom are recognised as authorities in their
particular field of technology.
All subject volumes carry their own index and a twelfth volume provides a consolidated
index for the series overall. Particular attention has been paid to the production of draft
material, with text refined through a number of technical and language editorial stages and
complemented by a large number of high quality illustrations. The result is a high standard
of presentation designed to appeal to a wide international readership.
It is with much pleasure therefore that I introduce this new series, which has been
attributed to British Electricity International on behalf of the CEGB and its successor
companies. I have been closely associated with its production and have no doubt that it will
be invaluable to engineers worldwide who are engaged in the design, construction,
commissioning, operation and maintenance of modern power stations and systems.

March 1990

VII
Preface

The increase in generating capacity of the Central Electricity Generating Board (CEGB)
during the last thirty years has involved the introduction of new 500 MW and 660 MW
turbine-generator plant for a variety of operational duties from base load to that of flexible
two-shift operation. These plants have been installed in nuclear, coal and oil fired power
stations.
The early operational experience of the 500 MW units provided important data for the
design development of the 660 MW turbine-generator plant. These latter machines
benefited from the high quality approach to the design of major components by UK
manufacturers using their developed analysis techniques in the areas of aerodynamics and
stress analysis. The soundness of this approach has been demonstrated by the improved
reliability and performance of the later plants.
The Third Edition of Modern Power Station Practice gives a detailed account of ex-
perience obtained in the development, design, manufacture, operation and testing of
large turbine-generators in the last twenty years. The practice of testing and evaluation of
modern plant has proceeded as before; the advance in analytical and computational
techniques has however meant that the application of this experience to future design and
operation of large turbine-generator plant is of greater benefit than ever before.
One of the major tasks of the Turbine-generator Plant Branch in the CEGB was to secure
the development of Turbine-generators and their associated Plants to meet the needs of the
CEGB with due regard to economics, performance and reliability. As Head of the Branch
for some years I have felt privileged to have been asked to edit Volume C.
The authors of this volume have wide experience of the plant engineering field and all
are authorities in their particular field of Technology. I would like to record my sincere
thanks to these colleagues who have produced Volume C. They have undertaken the task
with an enthusiasm derived from the knowledge that this work will be of the greatest
assistance to engineers in this field of technology worldwide.

P. HAMBLING
Advisory Editor Volume C

IX
Contents of All Volumes

Volume A Station Planning and Design


Power station siting and site layout
Station design and layout
Civil engineering and building works

Volume B Boilers and Ancillary Plant


Furnace design, gas side characteristics and combustion equipment
Boiler unit thermal and pressure parts design
Ancillary plant and fittings
Dust extraction, draught systems and flue gas desulphurisation

Volume C Turbines, Generators and Associated Plant


The steam turbine
Turbine plant systems
Feedwater heating systems
Condensers, pumps and cooling water plant
Hydraulic turbines
The generator

Volume D Electrical Systems and Equipment


Electrical system design
Electrical system analysis
Transformers
Generator main connections
Switchgear and control gear
Cabling
Motors
Telecommunications
Emergency supply equipment
Mechanical plant electrical services
Protection
Synchronising

Volume E Chemistry and Metallurgy


Chemistry
Fuel and oil
Corrosion: feed and boiler water
Water treatment plant and cooling water systems
Plant cleaning and inspection
Metallurgy
Introduction to metallurgy
Materials behaviour
Non-ferrous metals and alloys
Non-metallic materials
Materials selection

xi
Contents of All Volumes

Welding processes
Non-destructive testing
Defect analysis and life assessment
Environmental effects

Volume F Control and Instrumentation


Introduction
Automatic control
Automation, protection and interlocks and manual controls
Boiler and turbine instrumentation and actuators
Electrical instruments and metering
Central control rooms
On-line computer systems
Control and instrumentation system considerations

Volume G Station Operation and Maintenance


Introduction
Power plant operation
Performance and operation of generators
The planning and management of work
Power plant maintenance
Safety
Plant performance and performance monitoring

Volume H Station Commissioning


Introduction
Principles of commissioning
Common equipment and station plant commissioning
Boiler pre-steam to set commissioning
Turbine-generator/feedheating systems pre-steam to set commissioning
Unit commissioning and post-commissioning activities

Volume J Nuclear Power Generation


Nuclear physics and basic technology
Nuclear power station design
Nuclear power station operation
Nuclear safety

Volume K EHV Transmission


Transmission planning and development
Transmission network design
Overhead line design
Cable design
Switching station design and equipment
Transformer and reactor design
Reactive compensation plant
HVDC transmission plant design
Insulation co-ordination and surge protection
Interference
Power system protection and automatic switching
Telecommunications for power system management
Transmission operation and maintenance

XII
Contents of All Volumes

Volume L System Operation


System operation in England and Wales
Operational planning demand and generation
Operational planning power system
Operational procedures philosophy, principles and outline contents
Control in real time
System control structure, supporting services and staffing

Volume M Index
Complete contents of all volumes
Cumulative index

xiii
Evan John Davies
Emeritus Professor of Electrical and Electronic Engineering
at Aston University in Birmingham, died on 14 April 1991.

John was an engineer, an intellectual and a respected author


in his own right. It was this rare combination of talents that
he brought to Modern Power Station Practice as Consulting
Editor of seven volumes and, in so doing, bequeathed a
legacy from which practising and future engineers will
continue to benefit for many years.

xiv
C H A P T E R 1

The steam turbine

Introduction
4 Economics of t h e steam cycle
1 Turbine types 4.1 Choice of exhaust pressure
1.1 Direction of flow 4.1.1 Thermodynamic optimisation
1.2 Cylinder and exhaust arrangements 4.1.2 General economic optimisation of plant
1.3 Speed of rotation 4.1.3 Economic optimisation of exhaust pressure, condenser
and C W system
2 Efficiency and output 4.2 Regenerative feedheating
2.1 Output limitations 4.2.1 Feedheating plant stages superheat cycles
2.1.1 Steam valve pressure drop 4.2.2 Feedheating plant stages w e t steam cycle
2.1.2 Swallowing capacity 4.2.3 Feedwater de-aeration
2.2 Moving blades 4.2.4 Low pressure feedwater heaters
2.2.1 Impulse-type turbine 4.2.5 High pressure feedwater heaters
2.2.2 Reaction-type turbine 4.2.6 Summary
2.2.3 Effect on turbine design 4.3 Choice of feed pump and drive system
2.2.4 Blade efficiency 4.3.1 Feed pump size and number
2.2.5 Modern blading designs 4.3.2 Feed pump duty, margins, and the need for variable
2.2.6 LP turbine blading speed
2.3 The effect of clearances on real designs 4.3.3 Economic comparison of steam turbine drives with
2.3.1 Profile loss electric motor drives
2.3.2 Secondary loss 4.3.4 Economic comparison of variable-speed motor (VSM)
2.3.3 Tip leakage drive with induction motor plus fluid-coupling drive
2.3.4 Disc windage 4.3.5 Example of the results of an overall comparison of the
2.3.5 Lacing wires through-life costs of four feed pump system options.
2.3.6 Other losses 4.4 Turbine by-pass systems
2.3.7 Wetness loss 4.4.1 Superheat plant
2.3.8 Annulus loss 4.4.2 By-pass capacity
2.4 Stage efficiency and the condition line 4.4.3 System effects
2.4.1 Efficiency of stage 4.4.4 Improvement of start-up capability
2.4.2 The condition line 4.4.5 PWR wet steam plant
2.4.3 Cylinder efficiency
5 Turbine blading
2.4.4 Leaving loss
2.4.5 Hood loss 5.1 Impulse stages
2.4.6 Wetness loss 5.1.1 Moving blades details and construction
2.4.7 Partial admission 5.1.2 Fixed blades details and construction
5.1.3 Velocity-compounded stage
3 Thermodynamics of t h e steam cycle 5.2 Reaction stages
3.1 Development of the modern steam cycle 5.2.1 Fixed and moving blades details and construction
3.1.1 The steam cycle 5.3 Low pressure stages
3.1.2 The Rankine cycle 5.3.1 Aerodynamic and mechanical constraints
3.1.3 Practical cycle using superheat 5.3.2 Blade tip restraint
3.1.4 The reheat cycle 5.3.3 Baumann exhaust
3.1.5 Regenerative feedheating 5.4 Moving blade root attachments
3.2 Cycle efficiency and heat rate 5.4.1 Fir-tree roots
3.2.1 Cylinder efficiency 5.4.2 Pinned roots
3.2.2 Heat rate 5.5 Diaphragm construction and support
3.3 Terminal conditions 5.5.1 Kinematic support
3.3.1 Effect of steam inlet conditions 5.5.2 Radial support pads
3.3.2 Effect of reheat conditions 5.5.3 Diaphragm construction
3.3.3 Effect of pressure loss in pipework and valves 5.6 Blading materials
3.3.4 Effect of final feed temperatures 5.6.1 12% Cr steels
3.3.5 Effect of exhaust pressure 5.6.2 Titanium
3.4 Superheat cycle 5.7 Blade vibration control
3.4.1 Steam conditions 5.7.1 Natural frequencies and excitation frequencies
3.4.2 Reheat 5.7.2 Sources of vibration excitation
3.4.3 Double reheat 5.7.3 Verification of estimated natural frequencies and wheel
3.4.4 CEGB cycles chamber tests
3.4.5 Turbine designs 5.7.4 Methods of vibration control
3.5 W e t steam cycle 5.8 Erosion protection
3.5.1 The PWR steam cycle 5.8.1 Erosion mechanism
3.5.2 Cycle considerations 5.8.2 Erosion progression
3.5.3 Full-speed or half-speed machines 5.8.3 Protection and erosion shield materials

1
The steam turbine Chapter 1

6 Turbine casings 7.3.4 Critical speeds


6.1 Forms of casing construction 7.3.5 Rotor fast fracture risk assessment
6.1.1 High pressure casings 7.4 Couplings
6.1.2 Intermediate pressure casings 7.4.1 Flexible couplings
6.1.3 Low pressure casings 7.4.2 Semiflexible couplings
7.4.3 Rigid couplings
6.2 Horizontal joints
7.5 Rotor alignment
6.2.1 Flange design
7.5.1 Alignment technique
6.2.2 Bolting
7.5.2 On-line monitoring
6.3 External connections
6.3.1 Steam inlets HP and IP 8 Bearings, pedestals and turning gear
6.3.2 HP exhausts 8.1 Journal bearings
6.3.3 IP exhausts 8.1.1 Construction
6.3.4 Use of thermal skirts and piston rings 8.1.2 Instrumentation
6.3.5 LP cylinders 8.1.3 Bearing performance
6.3.6 Bled-steam connections 8.1.4 Factors affecting bearing life
6.4 Casing materials 8.2 Thrust bearings
6.5 Support and alignment 8.3 Pedestals
6.5.1 HP and IP cylinder supports 8.4 Oil sealing arrangements
6.5.2 LP cylinder supports 8.5 Turning gear
6.6 Casing and diaphragm glands 8.5.1 Hand barring arrangement
6.7 Lagging 8.5.2 Electrical turning gear (ETG)
7 Turbine rotors and couplings 9 Turbine applications
7.1 Types of rotor construction 9.1 Power generation
7.1.1 Design for high temperature operation 9.2 Mechanical drive
7.1.2 Cooling of IP rotors 9.3 Combined heat and power (CHP)
7.2 Rotor materials 9.4 Combined-cycle plant
7.2.1 HP and IP rotors
10 Future outlook
7.2.2 LP rotors
7.3 Rotor testing and balancing 10.1 Unit size and rating
7.3.1 Thermal stability 10.2 Supercritical plant
7.3.2 Overspeed testing 10.3 Turbine blading development
7.3.3 Rotor balancing 11 References

Introduction turbine have been presented by Traupel [1] and Harris


In order to function, a turbine requires a suitable [2].
working fluid, a source of high grade energy and a sink
for low grade energy. When the fluid flows through
the turbine, part of the energy content is continuously
1.1 Direction of flow
extracted and converted into useful mechanical work.
Steam and gas turbines use heat energy, while water Almost without exception, modern large steam turbines
turbines use pressure energy. The main objectives of are of the axial-flow type (Fig 1.1). Even from the
the turbine designer are to ensure that this process is early days in the late nineteenth century, this has been
carried out with 'maximum efficiency by means of the preferred solution for steam turbines of all ratings.
plant having 'maximum reliability9 at 'minimum cost\ The principal exception to this rule has been the
Second objectives are that the plant should require radial-flow turbine (Fig 1.2), originally introduced by
'minimum supervision' and 'minimum starting time\ Ljungstrom, and developed to its most recent form
These five objectives conflict with each other and by Stal-Laval (now ASEA-Stal). In this design, steam
the final outcome will be an acceptable compromise is admitted to the centre of the machine, expanding
between them. outwards through two contra-rotating rotors to the
Chapters 1 and 2 outline modern power station exhaust at the periphery. The concept was success-
practice as implemented by UK turbine makers. The fully executed and has been applied at ratings up to
reasons behind every facet of turbine development are about 60 MW. ASEA-Stal still offer the radial-flow
explained and, where necessary, technical terms are turbine for small industrial sets up to about 30 MW
defined quantitatively and qualitatively to emphasise output. However, the design is not adaptable to large
standard practice. outputs because of the mass of the blades which would
be mounted at the outer periphery. The largest ap-
plication of the radial-flow turbine is for the high
pressure (HP) cylinder of a 460 MW unit associated with
a boiling water reactor at Oskarshamn in Sweden.
1 Turbine types Axial flow is therefore the characteristic feature of
Thorough reviews of the development of the steam modern steam turbines. These are often categorised
Turbine types

(a) Single flow

FIG. 1.1 Axial-flow turbine

(b) Double flow

f
\i m
W M\
mM
mm
M m\
p M\

(c) Reversed flow

FIG. 1.3 Direction of flow for different categories


of turbine

(Fig 1.3 (b)), in which the steam is admitted at the


centre of the cylinder and is divided to flow in op-
posite axial directions towards the ends of the rotor.
This arrangement is used to avoid the excessively
long blades which would be incurred by a single-flow
arrangement. For turbines of large output, it is nor-
mal to have several double-flow low pressure (LP)
FlG. 1.2 Radial-flow turbine
cylinders operating in parallel. The second benefit is
that the double-flow cylinder effectively reduces to
zero the axial thrust caused by the steam forces on
the moving blading.
according to the type of blading used (see Section 5 One or both of these objectives are also the reasons
of this chapter), but in terms of direction of flow, for other arrangements of stage groups within a tur-
the steam approaches a group of stages at one end, bine cylinder. Thrust reduction is the main target for
flows axially through the radially-mounted blading the reversed-flow cylinder (Fig 1.3 (c)), in which the
and exhausts at the other end of the group of stages. steam flows in one direction through one group of
The simplest configuration of blading is in single-flow stages and is then ducted (internally or externally) to
(Fig 1.3 (a)). flow through a second group of stages in the opposite
Groups of stages within a turbine cylinder may be axial direction. In some cases, the second group of
arranged for flow in opposing axial directions. The stages may have several sections in parallel to accom-
normal situation for this is the double-flow turbine modate the increasing volumetric flow rate.

3
The steam turbine Chapter 1

In axial turbines, the steam is admitted to the cyl- number of LP cylinders being required: the use of a
inder and exhausted from it, by one or more circular very long shaft can be avoided by the use of a cross-
pipes in a radial or near-radial orientation (see Section compound machine. Further, the number of LP cylin-
6 of this chapter). At the LP turbine exhaust, the ders can be reduced if the LP turbine shaft rotates at
connection flange(s) to the condenser will however 1800 r/min, while the HP shaft rotates at 3600 r/min.
normally be rectangular, at an appropriate location The arrangement of the LP turbine and its con-
and orientation to match the condenser design. This nection to the condenser depends critically on the
always involves radial flow in one or more directions. location of the condenser, and the orientation of the
The steam is therefore required to turn through a condenser tubes with respect to the turbine axis.
right angle to enter the axial-flow blading and to The condenser has traditionally been mounted below
exhaust from it, at the same time redistributing itself the turbine, with the condenser tubes either axial or
around the circumference. The inlet and exhaust areas transverse. During the 1960s and 1970s, many 500 MW
therefore require sufficient space to allow an orderly and 660 MW turbines were built in the UK with side-
flow without undue pressure loss or flow separation. mounted condensers and axial tubes. Variants of this
In some cases, particularly low pressure turbine ex- design are called the pannier condenser (Fig 1.6 (a))
hausts, flow guides may be incorporated. and the integral condenser (Fig 1.6 (b)). The main
objective was to reduce the overall height of the
turbine, with a view to reducing the height and size
of the turbine hall. Because the tubes were axial, the
condenser steam space could be sectionalised, thus
1.2 Cylinder and exhaust arrangements allowing a lower condenser pressure in the cold end.
For turbines driving electrical generators, the limit of
This provided a small efficiency benefit.
a single-cylinder turbine is around 100 MW, depending
The main disadvantage of this design is that the
on the design concepts, the initial steam conditions
condenser becomes an important part of the turbine in
(pressure and temperature), whether or not a reheat
terms of structural integrity, loading, foundations, etc.
cycle is used, the exhaust conditions and the speed
This makes the condenser design dependent on the
of rotation.
number and size of LP turbines, thus inhibiting the
Frequently turbines of this size are designed and concept of modular design and complicating the de-
built on a modular basis, with the inlet sections, blad- sign interface between a turbine maker and a number
ing sections, and exhaust sections selected from a range of possible condenser makers. This design may also
of standard designs to suit a range of output powers, complicate access to the turbine for maintenance,
initial and exhaust conditions and special applications for example, to the bearing pedestals.
such as extraction steam for process heating or district
Later plant in British stations has therefore reverted
heating.
to the use of underslung condensers with transverse
For larger machines, multi-cylinder designs are used
tubes (Fig 1.6 (c)), using a connecting duct between
(Fig 1.4). The number of cylinders depends on a simi-
the turbine outlet flange and the condenser inlet flange.
lar list of terminal conditions and design considerations.
Because the condenser tubes are normally much longer
A typical turbine of 500-900 MW output in a fossil-
than the width of the turbine casing, this duct is
fired power station (coal, oil, or gas) or a gas-cooled
trapezoidal in shape.
nuclear station would have one HP turbine, one inter-
On some turbines built between 1920 and 1960, where
mediate pressure (IP) turbine and two (LP) turbines,
the available last stage blading provided a limitation
rotating at 3000 or 3600 r/min, depending on the grid
on turbine output or efficiency, the Baumann exhaust
frequency (see Section 1.3 of this chapter). The IP and
LP turbines would probably be double-flow. turbine (Fig 1.7) has been used by certain manufac-
turers, particularly Metropolitan-Vickers in the UK.
In a power station with a water-cooled reactor
In this design, the penultimate turbine stage is divided:
(PWR, BWR, CANDU, etc.), the initial steam is at lower
pressure and temperature, so the steam mass flow rate the steam flow through the outer annular part of
and volumetric flow rate are likely to be much higher the stage is led directly to the condenser, while that
for a given output. The turbine might then have one flowing through the inner part flows through the final
double-flow HP turbine and two or three LP turbines. stage on its way to the condenser. Because the two
The turbine with a number of cylinders on a single parts of the penultimate stage moving-blading have
shaft is described as a tandem-compound machine (Fig different duties, there is a discontinuity in the blade
1.5 (a)). The other main type is the cross-compound profile which makes it a difficult concept to use in
machine (Fig 1.5 (b)), in which the turbine cylinders the most highly-rated turbines.
are mounted on two separate parallel shafts driving
two separate generators. The steam connections and
the auxiliary systems are arranged as for a single
generating unit. This design of plant has been more 1.3 Speed of rotation
widely used where the grid frequency is 60 Hz and In the normal case, steam turbines are directly cou-
the available LP turbine blading results in a large pled to the electrical generator, no gearbox being

4
Turbine types

GENERATOR

/'

GENERATOR

I I REHEATER I I

1
"-rWr-

GENERATOR

HP IP

I I REHEATER I I

LU/

I REHEATER I

rjWr-i
GENERATOR

A/

4wH
ncncien i

FIG. 1.4 Multi-cylinder turbine arrangements

5
The steam turbine Chapter 1

(a) Tandem-compound

GENERATOR B

GENERATORA

(b) Cross-compound

FIG. 1.5 Tandem-compound and cross-compound machines

necessary. The speed of rotation is thus given Machine type Rotational speed (r/min)
by: System frequency 50 Hz 60 Hz
f = pn Two-pole (full-speed) 3000 (50 Hz) 3600 (60 Hz)
where f = frequency of the electrical grid system Four-pole (half-speed) 1500 (25 Hz) 1800 (30 Hz)

p = number of generator pole pairs


It is, however, not uncommon for smaller turbines
n = the rotational speed
particularly those associated with special applications
such as Combined Heat and Power, or Combined Cycle
Although there have been exceptions in the past, to operate at a higher speed, but driving the
effectively the only two grid frequencies in use world- generator through a speed-reducing gearbox. This re-
wide are 50 Hz and 60 Hz, and generators are usually sults in a smaller and less costly turbine, although the
either of two pole or four pole design. Large turbine- gearbox may introduce losses and affect availability.
generators therefore fall into one of the following Mechanically-driven turbines are required to operate
four categories: at variable speed to cover the operational range of

6
Turbine types

EXHAUST

(a) Pannier or side-mounted

FIG. 1.7 The Baumann exhaust turbine

(b) Radial or integral

Relative size and weights, affecting cost and transport.

/ ^ " \ TURBINE AXIS ^ * \ Relative expectations of reliability, operational flexi-


X ^. X ^ - " OF ROTATION \ X ^ X bility and ease of maintenance.
Relative thermal efficiency and economic comparison
of alternatives.

m Available LP turbine modules, with choice of exhaust


s ^:TBE$r
area to suit output and exhaust pressure.
23
For superheat plant, a full-speed machine is normally
" U preferred. However, when a plant is proposed of
AXIAL TRANSVERSE
(c) Underslung or bridge higher output than a current range which would have
led to very high stresses or very high LP turbine
FlG. 1.6 Types o f condenser i n c o m m o n use exhaust loadings, this favours a half-speed machine.
Half-speed tandem-compound machines are almost
unknown for superheat plant, but cross-compound
machines with a full-speed HP/IP line and a half-
the driven machine. In the power generation field, speed LP line have been used, particularly in 60 Hz
the largest such turbines are used to drive the boiler systems where the exhaust loading is exacerbated.
feed pumps for large units (see Section 4.3 of this For saturated-steam plant, the balance is much
chapter). The maximum operational speed range may more even. The higher steam volumetric flow rate for
be as high as 8500 r/min. Variable-speed turbines a given output makes the exhaust loading more critical
have also been used to drive the gas circulators in so, for 60 Hz systems, the rotational speed is almost
some gas-cooled reactors, and small single-stage tur- universally 1800 r/min. In 50 Hz systems, this exhaust
bines may also be used to drive emergency feed pumps loading is less critical, so there are a number of full-
in nuclear stations. speed machines. However, at the time the choice was
The selection of the rotational speed of a turbine- made of standard reactor sizes, 1500 r/min machines
generator depends on a number of factors, as follows: were often chosen as stress levels on 3000 r/min ma-
chines would have been beyond the experience at that
Unit size, initial steam conditions and availability time. In some cases, including Sizewell B (the first
of designs. PWR in the UK), two half-size, but full-speed, ma-
chines were selected, to take advantage of modules
Standardisation, affecting spares holdings. such as the LP turbine and the generator developed

7
The steam turbine Chapter 1

and proven for the full-speed superheat machines then relationship is known as the Klipse Law'.
in service. A comprehensive review of the choice of The relationship was later modified to include the
speed for saturated-steam machines in 50 Hz systems effect of inlet temperature:
has been made by Harris and Kalderon [3]. They
indicate that 1500 r/min machines may be more K
economical for the lowest optimum exhaust pressures, qm = P,2 - P22^ (1.2)
VT:
i.e., in those countries with the lowest cooling water
temperatures. By contrast, 3600 r/min machines could where Tj is the inlet absolute temperature.
only become the preferred solution in 60 Hz systems A more comprehensive analysis is given by Traupel [5]
where the optimum exhaust pressure is above 90 mbar; who showed that:
such high values are rarely the optimum, even in the
warmest climates.
qm = K ( P i / V j P,/P, n + 1/n (1.3)

where V represents the specific volume and n is the


polytropic exponent, related to the efficiency and
2 Efficiency and output isentropic exponent k by:

k - 1 n - 1
X
2.1 Output limitations
When steam passes through a narrow orifice or noz- The Ellipse Law is a useful tool when modelling
zle, it acquires kinetic energy at the expense of heat the effects of partial load on a turbine. Generally,
(enthalpy). The expansion of steam beyond the nozzle sufficient accuracy is obtained by using the version
causes some of the generated kinetic energy to be given in Equation (1.2) where steam is the working
converted to frictional heat. The result is the retention fluid. The Ellipse Law constant K can be obtained
of some enthalpy, but a loss in pressure and increase from either design or test data for the turbine, and
in entropy (loss in availability of energy). knowing the required flow, the pressures at each stage
of the unit can be evaluated successively from the
exhaust end where the conditions remain at constant
2.1.1 Steam valve pressure drop condenser levels.
An example of this occurs in turbine governor valves,
where the steam expands rapidly after passing through
the valve, converting all its generated kinetic energy
to frictional reheat. This has the effect of maintain- 2.2 Moving blades
ing the enthalpy at the valve inlet value, but at the The moving blades of a turbine stage receive steam
expense of a large increase in entropy and pressure that has been accelerated in a nozzle or fixed blades
drop. This is known as throttling and is used to shed and convert its kinetic energy into mechanical work on
load. More load is shed by reducing the valve area, so the turbine shaft. The impingement of the steam on
permitting less mass flow and increasing the pressure the blades produces a change in direction of motion
drop across the valve. of the steam which gives rise to a change in momen-
tum and therefore to a force. Ideally, the angle through
which the steam is turned is as near to 180 as
2.1.2 Swallowing capacity possible. Figure 1.8 shows a typical velocity vector
Whilst the effect of pressure drop is useful in throttle diagram in relation to the moving blade profile.
valves for reducing load it is a restriction on the The manner by which the transfer of energy occurs
turbine itself. The pressure drop produced at the in the moving blades is dependent upon whether the
nozzles of the turbine inlet and all subsequent fixed turbine is of an impulse or reaction type.
blades restricts the mass flow through the turbine
and hence the power output. A relationship between
mass flow and the fall in pressure across the turbine 2.2.1 Impulse-type turbine
was first produced by Stodola in 1927 [4]. Invented by Professor Rteau, an impulse turbine
converts a proportion of the heat in the steam into
velocity in the fixed blades. There is no heat drop
qm - K(p! Pi (1.1)
and therefore no pressure drop across the moving
blades. The mechanical work done in the moving
where qm is the mass flow rate, p{ and p 2 are the blades is therefore solely due to the loss of a propor-
inlet and exhaust pressures and K is a constant. The tion of the velocity gained in the fixed blades.

8
Efficiency and output

2.2.2 Reaction-type turbine


Strictly speaking such turbines should be termed
'impulse/50% reaction' turbines. The term 50% reaction
was used because only half the stage heat drop occurs
in the fixed blades, the remaining half occurring in the
moving blades. This results in a rise in steam velocity
at the moving blades, creating a thrust or reaction in
the opposite direction to the flow leaving the blades.
Some impulse also occurs in the moving blades due
to the change of direction of the flow but it is not
sufficient to cause a net drop in velocity. The fixed
blades behave in the same way as the impulse turbine
fixed blades by converting heat drop into velocity.
Figure 1.10 shows a typical reaction-type stage
velocity diagram. The relative velocity of the steam
leaving the moving blades (W 2 ) is greater than the
relative velocity of the steam entering the moving
blades (Wj): this is because of the increase in velocity
through the moving blades due to the presence of
the heat drop there.

FIG. 1.8 Typical blade velocity vector diagram


U = linear velocity of moving blade, m/s
Cj = absolute velocity of steam at moving blade inlet, m/s
C2 = absolute velocity of steam at moving blade outlet, m/s
Wj = steam velocity relative to moving blade at inlet, m/s
W2= steam velocity relative to moving blade at outlet, m/s
a = outlet angle of fixed blade
= outlet angle of moving blade
= inlet angle of moving blade
FIG. 1.10 Reaction-type stage velocity diagram
= inlet angle of steam to following stage

Figure 1.9 shows a typical impulse-type stage velocity 2.2.3 Effect on turbine design
diagram. The relative velocity of the steam leaving the The different characteristics of impulse and reaction
moving blades (W 2 ) is less than the relative velocity blading means that there are significant differences
of the steam entering the moving blades (Wj). This in the turbine designs. Impulse-turbine moving blades
emphasises the point stressed earlier that conversion are carried on discs which are either integral with or
of kinetic energy to mechanical energy takes place in attached to a small diameter shaft. The axial thrust
the moving blades. on the rotor is small since there is no pressure drop
across the blades and therefore no pressure forces
across the discs. The presence of a pressure drop
across the moving blades of the reaction turbine makes
discs unviable. Instead, the discs are replaced by a
greatly expanded hollow shaft known as a drum rotor.

2.2.4 Blade efficiency

X v
The efficiency with which the transfer of energy to
the moving blades occurs is essentially dependent
- - - ' upon the ratio of moving blade velocity and the steam
absolute velocity (U/Cj = ). As one might expect,
the effect of the velocity ratio on efficiency in an
impulse stage is somewhat different to that in a
FIG. 1.9 Impulse-type stage velocity diagram reaction stage.

9
The steam turbine Chapter 1

Ideal impulse-stage blade efficiency

Work done by moving blades


Blade efficiency (77) =
Available energy

For the simplest case we will assume W 2 = Wj and


= (no friction present) as shown in Fig 1.9.
For the work done WD = mUAV, where m is the
mass flow rate and AV = Wjcos + W 2 cos =
2WJCOS . Also, Wjcos = Cjcos a - U. Therefore
WD = mUAV = 2mU (C,cos a - U).
The available energy to the rotor blades is that
delivered by the fixed blades = (mC 1 ) 2 /2.
Hence = 2mU(C1cos a - Vy^mCrf/l]
= (4U/C!)/(cos a - U/CO 0.6

= 4(cos a - 0 VELOCITY RATIO

FIG. 1.11 Ideal efficiency curves


This describes a parabola and is shown in Fig 1.11.
The maximum value of efficiency may be derived by
differentiating the above expression with respect to
U and equating to zero. In reality there are a number of factors that affect
blade efficiency and these will be discussed in section
2.3 of this chapter. To achieve the best efficiency for
drj/dU = (4/C,)(cos a - 2Q = 0 both designs, reaction turbines require twice the num-
ber of stages of an impulse turbine. This is because
Therefore rymax = cos 2 a when = cos a / 2 . By the high velocity ratio (U/Cj) for the reaction turbine
inspection of Fig 1.11, it can be seen this occurs means only a small heat drop can be accommodated
when the outlet velocity is axial (</> = 90). at each stage.

Ideal reaction-stage blade efficiency 2.2.5 Modern blading designs


For an ideal 50% reaction stage the velocity diagram Modern turbines are neither purely impulse or re-
will appear as Fig 1.11. Since the fixed and moving action but a combination of both, for the following
blades have the same shape, = a and = , AW reasons. Impulse turbines began employing reaction
= 2C,(cos a - U). Therefore, WD = mUAV = of up to 20% at the root of the moving blades in
mU(2C,cos a - U). order to counteract the poor efficiency incurred from
In a reaction stage, there is an enthalpy drop across zero or even negative reaction. On the other hand,
the moving blade as well as the fixed; the available reaction at the root of reaction turbines has come
energy is therefore: down to as little as 30-40% resulting in the reduction
of the number of stages required and the sustaining
mKCj) 2 /^ + (W 2 2 - W^/2] of 50% reaction at the midpoint. Today it may be
more accurate to describe the two designs as:

and since by symmetry W 2 = Cx the available energy 'Disc and diaphragm' turbine, using low reaction
= m(C! 2 - W, 2 )/2 furthermore W ^ = C, 2 + U2 - blading.
2 Q U cos a, therefore, available energy = m/2(C 1 2 -
U2 + 2C1Ucos a) Orum-rotor' turbine, using high reaction blading [2].

and hence
2.2.6 LP turbine blading
= 2U(2C1cos a - U ) / [ ( C 1 ) 2 - U 2 + 2C 1 Ucos a] Steam passing through the stages of an LP turbine ex-
= 2(2cosa - 0/(1 - 2 + 2 cos a) pands rapidly and accelerates to a high velocity, often
and supersonic. Steam at exit from the cylinder can have
^max = 2cos 2 a/l + cos 2a when = cos a up to 10% moisture content. The flow then is complex
and the design of LP blading reflects this. The blades
are long and have a highly-twisted profile so that the
Figure 1.11 shows the diagram efficiency of a reaction inlet and outlet angles conform to the three-dimensional
stage in comparison to the impulse stage. flow characteristics at all blade heights.

10
Efficiency and output

When large plant was being designed in the late


1950s and early 1960s there were no analytical tools MOVING BLADE LEAVING
available to confidently predict the three-dimensional VELOCITY, DESIRED TO
BE UNIFORMLY AXIAL.
nature of the flow in LP cylinders. Today, traverse
tests on these machines reveal the significant radial
components of velocity in the highly divergent flow.
Techniques of through-flow analysis now employed
permit the calculation in detail of the flow around
each individual blade, using modern computational
techniques, and have enabled the complex flow field
TIP
in LP cylinders to be analysed effectively. These methods
have been refined and validated by input of data
from flow measurement probes on model turbines in
manufacturers' works and on full-scale machines in
service. The accuracy of prediction of flow is now
high and blading can be designed to obtain the de-
sired three-dimensional flow pattern. Modern final MEAN
stage blades are twisted considerably, since the flow
is at its most complex at the exit plane. The cross-
sectional area at the tip is only around 15% of that
at the root (Fig 1.12).

ROOT

SECTION AT
TIP DIAMETER

SECTION AT
MEAN DIAMETER

FIG. 1.13 LP last stage velocity profiles

to change the direction of the incident velocity of


the steam relative to the moving blade, so the blade
inlet angle would not line up with the direction of
the oncoming steam flow. Furthermore, the leaving
velocity would depart substantially from the axial
FIG. 1.12 LP last stage moving blade direction, thus increasing the leaving loss and reduc-
ing efficiency. This is overcome by changing the shape
of the moving blade section. The outlet angle is re-
duced to restrict the flow area so that a pressure
To illustrate the point let us assume, for the drop develops across the moving blades, and the
moment, that the final stage is designed to have a steam leaves the moving blades at a higher speed to
fairly low degree of reaction at the base diameter, offset the higher peripheral speed and arrive at an
near the periphery of the rotor disc. The fixed and axial leaving velocity. This causes the pressure drop
moving blade profiles are then as shown in Fig 1.13. across the fixed blading to fall in order to maintain
Let us now move to the region half-way up the the same pressure drop over the stage as a whole.
moving blade, i.e., to the stage mean diameter. Typi- There is therefore a substantial degree of reaction at
cally, on modern blading, the tip diameter is about the mean diameter. Figure 1.13 shows the effect that
double the base diameter so at the mean, the blade increasing reaction from root to tip has on the profile
pitch (i.e., the circumferential distance between ad- and on the velocity vectors at root, mean and tip
jacent blades) is about 1.5 times the pitch at the base sections.
diameter. The peripheral speed of the blading is also The effect of these changes leads to a more order-
1.5 times as great as at the base. If the same moving ly streamline flow with substantial increase in the
blade section was used at the mean diameter as at efficiency of LP turbines. The pressure losses after
the base, the flow passage through the moving blading the last stage moving blades (proportional to the
would be rendered incorrect by the increased pitch; velocity squared) have also been reduced by achieving
whilst the effect of increased blade speed would be a reduced and substantially uniform velocity over the
11
The steam turbine Chapter 1

annular region immediately downstream of the last


stage blades. A further beneficial effect of reducing
crowding of flow at the blade-tip is that the excessive
steam leakage over the moving blade-tips, which did
no useful work, has been reduced. TIP

2.3 The effect of clearances on real designs


Blade efficiencies are far from ideal and the main
causes of this are aerodynamic factors. The three
most important factors are profile loss, secondary
loss and tip leakage loss. These are of roughly the same
magnitude whilst other sources of aerodynamic loss,
such as windage and lacing wires, are much smaller.

2.3.1 Profile loss


ROOT
This is due to the formation of boundary layers on
the blade surfaces. The fluid in the boundary layer
is subject to viscous forces which slow it down and
increase its entropy relative to the flow in the main-
stream. This results in the steam downstream of the
moving blades having a higher entropy than the steam
upstream. At a given flow rate this would result in a
larger pressure drop across the blades than there would
be in isentropic flow. Since the pressures in a turbine FIG. 1.14 Secondary flows
are fixed, the flow rate becomes less than isentropic
and the entropy of the exhaust steam greater than
isentropic. This means the heat drop obtained across
the stage is less than that for an isentropic expansion
and is therefore less efficient. cumference of the moving blades, joining the tips.
Profile loss is a boundary layer phenomenon and The shroud is sealed against the casing by several
is therefore subject to factors that influence bound- knife edges.
ary layer development. These factors are Reynolds The extent of the leakage depends on whether the
Number, Surface Roughness, Exit Mach Number and turbine is of an impulse or reaction type. Reaction
Trailing Edge Thickness. turbines suffer a pressure drop across the moving
blades, so encouraging flow through the clearances.
Consequently, it is more important for a reaction
2.3.2 Secondary loss turbine to have good tip sealing than it is for an
impulse turbine (Fig 1.15).
This is due to friction on the casing wall and on the
blade root and tip. It is a boundary layer effect and
therefore dependent upon the same considerations as
those for profile loss. Figure 1.14 shows how the
interaction of the boundary layer phenomenon be-
tween tip and casing and between root and shaft,
creates the secondary flows A and B.

FIXED BLADES
2.3.3 Tip leakage
This leakage, as its name implies, arises from steam
passing through the small clearance required between MOVING BLADE

the moving blade tip and the casing, or between the


end of the fixed blades and the rotating shaft. The
problem is overcome to a certain extent through the
use of inter-stage seals. At the blade tips there is a
shroud band which extends around the entire cir- FIG. 1.15 Reaction and impulse turbine interstage sealing

12
Efficiency and output

2.3.4 Disc windage 2.4 Stage efficiency and the condition line
This is the friction loss due to the surface friction
created on the discs of an impulse turbine as the disc
rotates in the steam atmosphere. The result is the 2.4.1 Efficiency of stage
forfeiture of shaft power for an increase in kinetic The efficiency of a turbine stage will always be some-
and heat energy of the steam. what less than ideal because of the losses discussed
in Section 2.2 of this chapter. The efficiency of a
well designed stage in a modern HP turbine is about
2.3.5 Lacing wires 85-90%. This stage efficiency is obtained in the
The long blades of the LP cylinder are stiffened following way:
towards the tip with lacing wires. Their purpose is
to damp vibrations and raise the resonant frequency Actual stage heat drop
of the blade so that it does not coincide with any 100% or:
Isentropic stage heat drop
exciting frequency present in the turbine. The pre-
sence of these wires, however, produces losses in blade
efficiency because of the passage area that they block. (enthalpy at fixed blade inlet) -
(enthalpy at moving blade outlet) |
x lOOvo
(enthalpy at fixed blade inlet) -
2.3.6 Other losses (enthalpy at isentropic moving blade outlet)
There are further losses which, though not due to
the design of the moving blades, do affect the blade This can be more clearly envisaged through the
efficiency. These losses are Wetness loss and Annulus use of a turbine condition line.
loss.

2.4.2 The condition line


2.3.7 Wetness loss
The condition line is the locus of the conditions of
This is incurred by moisture entrained in the low the steam as it passes from the stop valve at the inlet
pressure steam towards the exit plarie of the LP tur- to the HP cylinder, through all the turbine stages to
bine. The loss is a combination of two effects; the the exit plane of the final moving blade of the LP
first is the reduction in efficiency due to absorption cylinder (Fig 1.16). Ideally the expansion of steam
of energy by the water droplets and the second is through the turbine will occur isentropically, that is,
the erosion of the final moving blades leading-edges. at constant entropy shown by the vertical dotted line.
Erosion occurs because the water droplets travel In reality the friction effects, such as profile and sec-
far slower than steam, consequently their velocity ondary loss, cause an increase in the heat and entropy
relative to the blades is significantly different in di- of the steam.
rection as well as speed. The result is the impact of Figure 1.17 shows a section of the condition line
condensation droplets on the blades, in particular at displaying one stage only.
the tip where the blade rotational velocity is highest. Hj - H 2 represents the isentropic heat drop and
In the past, the leading edge has been protected Hj - H3 the actual heat drop. Cylinder efficiency
either by an edge-hardening process or by the brazing- then is obtained for HP, IP and LP turbines by
on of stellite, which is a very hard material. More considering the heat drop across all the stages of the
recently, a better understanding of the mechanism of cylinder.
droplet erosion has produced means of alleviating
much of the problem. Higher last-stage heat drops
are employed, along with higher mass flow loading. 2.4.3 Cylinder efficiency
The result is a higher pressure at the inlet to the
There are two commonly used cylinder efficiency
moving blades leading to the reduction in the size
definitions for HP and IP turbines. The first is the
of droplets.
one described above and is known as the internal
efficiency. The second includes the effect of the pres-
sure drop through the stop and governor valves on
2.3.8 Annulus loss the HP turbine and intercept, stop and governor
This occurs when there is a significant amount of valves on the IP turbine and is known as the external
diffusion between two adjacent stages or where wall efficiency (Fig 1.18).
cavities occur between the fixed and moving blades. It can be seen that, though the pressure drop across
The extent of the loss is greatly reduced at high an- the valves is at constant enthalpy, the change in
nulus area ratios (inlet/outlet) if the expansion of entropy affects the moving blade-exit isentropic en-
the steam is controlled by a flared casing wall. thalpy so that:

13
The steam turbine Chapter 1

SPECIFIC ENTROPY

FIG. 1.16 Turbine condition line FIG. 1.17 Stage condition line

H, - H 2 x 100% and Both exhaust conditions are displayed in Fig 1.19


(internal) =
H, - H 3 from which the following LP efficiencies can be
obtained:
H, - H 2 x 100%
(external) =
H, HA Total Static/Total Static efficiency (TS/TS)

Hi . _ ^
1 4
H, H, x 100%
For HP and IP steam turbines, the kinetic energy
effects at inlet and exhaust are small and usually
ignored. The kinetic energy at inlet to the LP turbine Total Total/Total Static efficiency (TT/TS)
is also negligible but at the exhaust it is not. As
Hl
a result LP efficiencies are derived by considering ~ Hl x 100%
H, - H 5
either:

The total exhaust conditions which includes Total Total/Total Total efficiency (TT/TT)
the steam kinetic energy and is measurable with a
Hj - H 2
correctly aligned pitot. x 100%
H, H,
The static exhaust conditions which represents
conditions when the kinetic energy has been re- TT/TS efficiencies are usually obtained from heat
duced to zero and is measurable with pressure gauge. rate tests (see Section 3 of this chapter). The exhaust

14
Efficiency and output

TOTAL P,

STATIC P,

Fl. 1.19 LP cylinder efficiency

through the conversion of its kinetic energy to flow


FIG. 1.18 HP and IP cylinder efficiencies friction losses. This is a constant enthalpy process
since the steam cannot do work on blades that it
has already left. Consequently the steam comes to
rest at the point X on Fig 1.19.
total enthalpy is derived from the measured power The heat loss between the total conditions at blade
output and the static isentropic enthalpy is normally exit (H2) and the static pressure line (H4) is known as
taken at condenser pressure. TT/TT efficiencies are the leaving loss. The significance leaving loss has on
commonly derived from wetness probe (traverse) tests. efficiency can be seen in the following example:
The isentropic exhaust enthalpy in this case is at the
blade exit plane total pressure/Traverse tests measure Leaving loss = v e 2 /2 J/kg
the wetness and other properties of the steam along
the height of a moving blade. The test is restricted where ve is the velocity of steam leaving the last row
to the measurement across LP turbine stages where of blades. For a 500 MW turbine, the velocity ve is
there is sufficient distance between stages to permit typically 170 m/s:
the free passage of the probe.
1702
thus leaving loss = = 14450 J/kg = 14.45 kJ/kg

2.4.4 Leaving loss This would be responsible for a 2% reduction in LP


Steam leaves the final stage of an LP turbine with cylinder efficiency.
kinetic energy at the total pressure and enthalpy
shown in Fig 1.19. If the steam could be slowed down
isentropically to zero kinetic energy, it would be at 2.4.5 Hood loss
static pressure and enthalpy. In practice the steam Another loss which occurs between the final stage
does slow down after leaving the last blade, but and the condenser inlet is a pressure drop known as
15
The steam turbine Chapter 1

hood loss (Fig 1.20). Normally the condenser static 2.4.7 Partial admission
pressure is less than that at blade exit. The steam Partial admission gives a loss in turbine efficiency if
expands in the hood which joins the exhaust of the the steam supply to the turbine is governed by the
LP cylinder to the condenser inlet. The expansion number of nozzles in use. The alternative means of
converts enthalpy to kinetic energy which is then steam governing is throttle-control, where admission
converted back to heat by flow friction losses. is over the complete circumference of the first stage,
In some cases the hood loss is negative and the and control is achieved by reducing the main steam
condenser pressure is higher than blade-exit static supply. Partial admission is therefore not experienced
conditions. This occurs when the steam kinetic energy by throttle-controlled turbines.
is converted to pressure, a process known as diffusion. The problem with reducing steam flow by the use of
nozzle-control is that when the blades are aligned with
a nozzle group they run full of steam, but when they
pass into a blank arc, eddies are produced, so caus-
ing a loss. The first and last blades in line with the
nozzle group will only be partially full of steam and
therefore the flow in them will be considerably dis-
turbed. This is often referred to as 'blade windage',
'blade ventilation' or Vane action' loss.
There is also an additional factor to consider. As
the idle blades come under the influence of the noz-
zles, the steam in the blade passages has to be ac-
celerated rapidly, so causing a loss in power. The
magnitude of this loss increases with the work done
per row, the heat drop, the blade speed, blade width
and height, and the number of steam admissions. This
factor, known as the steam inertia loss, can account
for 15-20% of the total windage loss in a stage with
single arc admission.
In the UK, there are many interconnected units in
service so that each can be kept in efficient operation
at high load. System load reduction is achieved by
shutting down complete units, so that there is no
benefit from the adoption of nozzle control for individual
units. Alternatively, load reduction is accomplished
by reducing the boiler pressure, so that the turbine
valves are maintained wide open over most of the
load range up to 100%. Part-load efficiencies obtained
in this manner are comparable to nozzle-governed
machines, whilst the full-load efficiency is better.

3 T h e r m o d y n a m i c s of t h e s t e a m cycle
FIG. 1.20 Hood loss

3.1 Development of the modern steam cycle


2.4.6 Wetness loss
This section will outline a modern steam cycle and
Figure 1.16 shows how the condition line curves sub-
then discuss its development from the basic thermo-
stantially towards higher entropy values below the
dynamic power cycle. Having developed a modern
saturation line. The reason for this is the increasing
steam cycle, the means of assessing its efficiency and
wetness towards the exhaust in an LP turbine, dis-
economic implications will be introduced.
cussed in Section 2.2 of this chapter. If the efficiency
is adjusted to exclude the wetness loss, it is called the
dry stage efficiency. It is common practice to assume
that the total wetness loss is proportional to the 3.1.1 The steam cycle
mean stage wetness. Baumann suggested that 1% total A power station operates using a closed steam power
wetness loss be assumed per 1% mean stage wetness. cycle, where water undergoes various thermodynamic

16
Thermodynamics of the steam cycle

LP
HEATERS CONDENSATE
EXTRACTION
PUMP

TO CONDENSER

FIG. 1.21 Simplified steam power plant cycle

processes in a cyclic process. Figure 1.21 is a sim- The main steam, having been condensed in the
plified diagram of a modern steam plant, showing condenser, is now in a liquid state at a very low pressure
most of the essential elements. and approximately saturation temperature. This water
One half of the cycle consists of the boiler (or heat drains from the condenser, where it enters the hotwell.
source) and its auxiliaries; the other, the turbine The water in the hotwell is pumped by the condensate
cycle, consists of turbine, generator, condenser, feed extraction pump through the low pressure feedheating
pump and feed water heaters. system to another pump, the boiler feed pump.
Consider first the boiler plant involved in the cycle. In a modern regenerative cycle, some of the steam
Feedwater is supplied to the boiler drum, where water passing through the turbine cylinders is bled from a
is boiled and converted into dry saturated steam. series of extraction belts located after selected moving
This dry steam is further superheated in the super- blade stages and fed to the condensate and feedwater
heater and then fed to the HP cylinder of the tur- heaters. This steam is used to heat the condensate in
bine. The steam expands in the turbine giving up heat the LP heaters and the feedwater in the HP heaters,
energy, a high proportion of which is transferred which are of a surface type.
into work energy on the turbine shaft. The shaft The boiler feed pump increases the water pressure
turns an electrical generator which produces electric to a level in excess of the drum pressure, to provide
power. Steam leaving the HP cylinder returns to the for the pressure loss in the boiler circuit and HP
boiler, where it is reheated. The reheated steam is feedheating train. The cycle is now complete.
further expanded in the IP and LP cylinders, before
passing into the condenser.
In the condenser, which is a large surface-type heat 3.1.2 The Rankine cycle
exchanger, the steam is condensed by transferring its Having presented a modern practical steam power
latent heat of vaporisation to the cooling water (CW). cycle, attention will now be given to the development
17
The steam turbine Chapter 1

of such a cycle from a basic vapour power cycle steam is expanded through the turbine isentropically,
the Rankine cycle. i.e., without loss. This process (C-D) produces work
For the purpose of illustrating the various power along the turbine shaft. Finally the wet steam issuing
cycles, the Temperature-Entropy (T-S) and Enthalpy- from the turbine gives up its heat in the condenser and
Entropy (H-S) diagrams will be used. An understand- returns to water (process O-A).
ing of thermodynamic properties Entropy and The heat input to the boiler or 'the energy paid
Enthalpy is assumed. However, in the context of for' is represented by the area EABCDF on the T-S
the following description of steam cycles, a review of diagram. The work done by the cycle is represented
Entropy will be beneficial. by the area within the polygon ABCD. The heat
Entropy is an abstract property of steam which rejected to the condenser is represented by the rec-
increases when heat is added and decreases when tangle ADFE. In the context of power generation,
heat is rejected. Its magnitude is such that if the Thermal Efficiency is defined as:
temperature at which heat is transferred is multiplied
by the change in entropy that results in the pro-
Work done = (Energy for generation)/Heat input
cess, then that product equals the amount of heat
(i.e., energy paid for). Hence the Thermal Efficiency
transferred.
of the Rankine cycle, based upon Fig 1.23, 1.23 is
Now consider the simple Rankine cycle for steam,
(Rankine) = Area ABCD/Area EABCDF.
shown schematically in Fig 1.22 and on the T-S dia-
gram in Fig 1.23.
Water is pumped into the boiler by the feed pump The economic implication of cycle efficiency is a
(process A-B). In the ideal Rankine cycle, there is no major factor behind the development of the cycle,
temperature rise across the pump and points A-B are whilst maintaining or reducing capital cost per elec-
coincident. The water is then heated to produce dry trical unit supplied. The other major consideration in
saturated steam (process B-C). The dry saturated the choice of cycle, is the engineering feasibility of

BOILER

LL 'WORK

((I!
HEAT
REJECTED
CONDENSER

&
FEEDPUMP

FIG. 1.22 Simple Rankine cycle power plant

18
Thermodynamics of the steam cycle

No saturated steam must enter the condenser, i.e.,


point D must be within the vapour boundary (Fig
1.23).

The exhaust wetness in the last turbine stage must


not exceed 12%, i.e., DD' must be less than 12%
of AD'.

Material properties limit the maximum temperature


within the cycle.

3.1.3 Practical cycle using superheat


The first development of the Rankine cycle into a
more practical steam cycle involves raising the pres-
ENTROPY, S F sure and temperature of the steam entering the turbine.
The superheated steam cycle is shown schematically
FIG. 1.23 Rankine cycle T-S diagram
in Fig 1.24, and on the T-S diagram in Fig 1.25.
In the superheat cycle, the saturated dry steam leaving
the boiler drum is further heated before entering the
various terminal conditions. The effect of changing turbine. For the same quality of steam entering the
terminal conditions is dealt with thoroughly in Section condenser (i.e., same point D), the increase in work done
3.3 of this chapter. However, it is useful to consider is shown on Fig 1.25. The quantity of heat rejected to
the following criteria when attempting to change the condenser is the same as for the Rankine cycle.
cycle terminal conditions: Hence, there is an improvement in the cycle efficiency.

FIG. 1.24 Superheat cycle plant

19
The steam turbine Chapter 1

The superheat efficiency is greater than the Rankine


efficiency as Area (P + Q)/(P + Q + R) is greater
than Q/(Q + R).
This superheat cycle was chosen to have the same
turbine exhaust conditions as the previous Rankine
SUPERHEAT
REGION
cycle. However, a major advantage of superheating
steam is that for increasing cycle temperature and
ADDITIONAL (AREA A) pressure, the exhaust wetness in the turbine can be
WORK DONE
maintained within the physical limits mentioned earlier.

AREAB

3.1.4 The reheat cycle


AREA C The desire for further increases in cycle conditions and
consequent increases in cycle efficiency, led to the
addition of steam reheat during turbine expansion. The
reheat cycle is shown schematically in Fig 1.26 and
FIG. 1.25 Superheat cycle T-S diagram on the T-S diagram in Fig 1.27.
In the reheat cycle, steam at a given initial tem-
perature is partially expanded through the turbine
Area ABCtD (process C-D) doing some work, and then is fed back
^(Superheat) _
Area EABQDF to the boiler, where it is reheated to about original
temperature (process D-E). The heated steam is then fed
Area (P + Q) through the remainder of the turbine before being
Area (P + Q + R) condensed (process E-F).

BOILER TURBINE

WORK

FIG. 1.26 Reheat cycle plant

20
Thermodynamics of the steam cycle

thermal efficiency from the T-S diagram is *?(Reheat) =


c E (Area ABCDEF)/(Area GABCDEFH).
The reheat cycle benefits from reduced wetness in
the turbine exhaust, but presents an increased capital
outlay in terms of reheater pipework to, from and within
the boiler. The turbine is usually split into HP and
LP cylinders to avoid the high thermal gradients
which would be introduced between stages of reheat
on a single-cylinder machine.

3.1.5 Regenerative feedheating


To complete the cycle development of the steam cycle
to that of Fig 1.21, the inclusion of regenerative
G ENTROPY, S H feedheating must be discussed. Physically, a propor-
tion of the steam is bled from various points on the
FlG. 1.27 Reheat cycle T-S diagram
turbine, which is then condensed to heat feedwater
on its return to the boiler. Figure 1.28 illustrates
the improvement in thermal efficiency for a simple
The reheat cycle incorporates an improvement in Rankine cycle (Fig 1.29), by virtue of the bled-steam
thermal efficiency over the superheat cycle. The releasing all of its heat to the feedwater, and little

BOILER

(111 HEAT IN

FEEDHEATERS

Q>
FEED CONDENSATE
PUMP EXTRACTION PUMP

FIG. 1.28 Rankine cycle with regenerative feedheating

21
The steam turbine Chapter 1

3.2 Cycle efficiency and heat rate


The last section dealt with the theoretical aspects of
steam cycles. An attempt is now made to investigate
the differences between an ideal turbine expansion
(one which is isentropic) and an actual turbine ex-
pansion, leading to expressions for turbine heat rate
/ __BLED^ FH and efficiency.
/ STEM_ FHI @ j The general cycle efficiency was illustrated with the
/ FH j
\ WORK LOST TO CYCLE
use of the T-S diagram; for the turbine alone, effi-
/ FHJ_ * ciency is best discussed using the Mollier or enthalpy-

^v ,
\ HEAT GAIN TO CYCLE entropy (H-S) diagram. A comparison of actual and
isentropic turbine expansions is illustrated in Fig 1.31.
/ j HEAT REJECTED |l|)Pilll The turbine expansion shown is that for an HP cylin-
der, i.e., wholly in the superheat region.
ENTROPY, S

FIG. 1.29 T-S diagram for the Rankine cycle


with feedheating

or none to the condenser. There will be a small


loss of work available from the bled-steam not ex-
panding in the turbine; however, this loss is out-
weighed by the gain in cycle efficiency.
The greater the number of feedheaters installed,
the greater the improvement in thermal efficiency.
However, the incremental gain for each additional
feedheater reduces as the number of heaters increases.
The methods of optimising the number of heaters for
a particular size of plant are covered in Section 4.2.
of this chapter.
The cycle has now been developed to the modern
plant cycle that was first considered. Before going
on to discuss this in detail, the T-S diagram for a
reheat cycle with regenerative feedheating is given in
Fig 1.30.

ENTROPY,
> HP HEATERS

FIG. 1.31 Comparison of isentropic and


actual turbine expansions

3.2.1 Cylinder efficiency


In Section 2, the stage efficiency was defined. Re-
ferring to Fig 1.31, the overall cylinder efficiency is
given by:

HA Hr (Useful work done)


FIG. 1.30 Rankine cycle with reheat and V (cylinder)
regenerative feedheating HA ~~ H B (Isentropic enthalpy change)
22
Thermodynamics of the steam cycle

A real turbine expansion incorporates losses or ir- H, - H 2


HP cylinder
reversibilities corresponding to an increase in entropy. H, - H' 2
It can be seen from the Mollier diagram, that for
an expansion between two pressures, the greater the H3 - H4
IP cylinder
entropy rise (i.e., the greater number of losses), the H 3 - H' 4
less energy there is available for work. Refinement
in turbine design aims to reduce the losses and in- H4 - H5
LP cylinder
crease the available energy. H 4 - H' 5
Now consider the whole turbine expansion process
through HP, IP and LP cylinders on a Mollier dia- In the case of the HP and IP cylinders, these are
gram, as shown in Fig 1.32. external efficiencies because the throttling loss is
included.
One small advantage of the irreversibilities in the
IP and LP turbines is the reduction in exhaust steam

P, p2 p3
wetness, causing less erosion on the final stages of
/ / REHEATER
blading. The condition of the plant can be monitored
1 /PRESSURE LOSS
/ ^ ^ ^ e * T, - INLET AND by measuring the temperature and pressure of the
3 / .>
steam at points between the cylinder, hence deriving
/PRESSURE LOSS, REHEAT TEMPERATURE

1 |p
/4 the steam enthalpy. It should then be possible to
Id
compare cylinder efficiencies with the original design
1 CYLINDER /

values. Turbine blade erosion or steam leakage results


in a reduced cylinder efficiency. In practice, the LP
cylinder exhaust enthalpy is not directly measurable
X4 and it must be derived from an overall heat balance.
HP
CYLINDER
j
[ /'- y
2
^ I 1 LP CYLINDER

3.2.2 Heat rate


The principles of stage and cylinder efficiency having
**0s4P^ been introduced, consideration is now given to the
~\ definition of turbine heat rate. The heat rate is deter-

'* 1 1 \^ X
mined by measurement of various plant operating
parameters. These include:
Je5
\

~^~ !
**>^ j " " ^ - ^ ^ LEAVING / HOOD LOSSES Flow rate, using a differential pressure device.
1 ^r*^^.^

Sb' Enthalpy, based on calibrated pressure and tem-


yt
perature measurement.
Electric power, based on calibrated voltage and
ACTUAL PROCESS 12345
current measurements.
ISENTROPIC PROCESS 12'34'5'
P, -HP INLET PRESSURE
P2 - HP EXHAUST PRESSURE
P3- IP INLET PRESSURE
P4 - LP INLET PRESSURE
P5 - CONDENSER PRESSURE
Consider a steam cycle with single reheat and re-
generative feedheating, shown in Fig 1.33.

The heat rate is defined by:


FIG. 1.32 Mollier chart for actual turbine expansion
Heat input from boiler (kJ/h)
HEAT RATE =
Electrical output from generator (kW)
Using measurements around the cycle from Fig 1.33
The actual turbine expansion line includes the ma-
jor losses encountered: HP throttling loss through M^H, - H f ) + M3(H3 - H2)
the governor valve and associated pipework; reheater HEAT RATE = ^ ^ kJ/kWh
pressure loss through pipework (to, within and from
the boiler); the leaving and hood losses at the last
The corresponding thermal efficiency is given by:
stage of the LP turbine (see Section 2 of this chapter).
From Fig 1.32 it is possible to derive the following 3600 (kW)
x 100%
cylinder efficiencies: HEAT RATE (kJ/s)
23
The steam turbine Chapter 1

M 1 - FLOW RATE OF SUPERHEATED STEAM FROM BOILER (kg/h)


H, - ENTHALPY OF SUPERHEATED STEAM BASED UPON PRESSURE AND TEMPERATURE T., (kJ/kg)
P g - ELECTRICAL POWER AT THE GENERATOR TERMINALS ( kW)

FIG. 1.33 Cycle used for derivation of heat rate

A means of measuring cycle heat rate having been


defined, consideration can now be given to varia-
tions between the design heat rates quoted by the
turbine manufacturers and the heat rates achieved
in operation.
First, consider the variation of the hourly heat
consumed by the turbine-generator with the load
produced. This characteristic is known as Willans
line (Fig 1.34), and is based on turbine test runs at
100%, 80%, 60% and 40% load. It is British practice
to specify performance and test at these four loads.
A linear relationship exists and extrapolation to the
no-load output condition reveals a no-load heat con-
sumption of about 3% of the full-load value. The
variation in heat rate with load (Fig 1.35) shows the
high thermal cost of operating plant on part-load.
The optimum heat rate (i.e., the minimum condition)
should correspond to the design output (100% load).
NO LOAD HEAT CONSUMPTION
The major contributory loss comes from the throttling -l 1

loss across the turbine governor valves. The effects LOAD, o/oMCR
of throttling are discussed later in this chapter.
Operating the unit at part-load is one of the
'external' factors preventing the achievement of the FIG. 1.34 Willans line for a typical 660 MW unit
design heat rate. The other major external factor,
which increases average heat rate, is the need to start
the unit as required by the operating regime. During Plant operating losses cause the other major in-
start-up, the unit is unloaded and additional works crease in design heat rate. In practice, turbine heat
power is needed for start-up systems. rates increase due to:
24
Thermodynamics of the steam cycle

FIG. 1.35 Variation of heat rate with load for a typical


660 MW unit (throttle governed) ENTROPY, S

FIG. 1.36 The effect of increasing temperature


on available energy
Deterioration of cylinder clearances. As temperature is increased from Tj to T 3 the available
energy increases, as the slope of the constant pressure line
Deterioration in feedheating efficiency. is greater than the condenser pressure line, i.e.,
A3B3 > A 1 B 1
Poor control of superheat and reheat temperature,
(particularly in older designs).
in entropy. As the temperature is increased from Tj
to T 3 , the available energy increases, since A3B3 >
These factors become more prevalent as the plant
AiBp
ages.
Now consider the effect of increasing the inlet steam
pressure at a constant temperature. The additional
available energy is shown on Fig 1.37. The increase in
available energy is less than that for temperature for
3.3 Terminal conditions the same entropy change. The significant advantage
In this section, the effects of certain terminal con- of increasing both temperature and pressure is illus-
ditions of the steam cycle are considered in detail. trated on Fig 1.38.
The impact on efficiency is evaluated and the con- There are limitations to the selection of inlet steam
straints faced by the designer are discussed. conditions. As mentioned in the previous section
there are criteria which affect the choice of inlet
conditions:
3.3.1 Effect of steam inlet conditions
Maximum turbine exhaust wetness 12%.
Firstly, consider the effect of steam inlet conditions
to the turbine. The temperature of the steam supplied No dry steam to enter the condenser.
to the turbine stop valve is a major factor in the
cycle efficiency and the efficiency of the turbine in Metallurgical constraints on the choice of turbine
converting available energy into work. The effect of and boiler materials.
increasing the steam inlet temperature for a turbine
expanding between set pressures is shown on the
Mollier diagram (Fig 1.36). The expansion process The metallurgical limit on temperature is 565C for
shown is for a single-cylinder turbine with no increase coal-fired plant brought into service with the CEGB
25
The steam turbine Chapter 1

ENTROPY, S ENTROPY, S

FIG. 1.37 The effect of increasing pressure on FIG. 1.38 The effect of increasing both pressure and
available energy temperature upon available energy
As pressure increases from Pj to P3 the available energy
increases, as the slope of the condenser pressure line is
greater than the temperature line, i.e., A 3 B 3 > A i B j

over the years 1960 to 1986. This limit reflects


a compromise between ease of manufacture, creep
strength and cost. The practice on CEGB 500 MW
and 660 MW sub-critical units has been to select a
pressure of 159 bar at the turbine stop valve.

3.3.2 Effect of reheat conditions


Now consider the selection of reheat conditions for
a single reheat cycle. Having established the steam
conditions at entry to the HP turbine, there are several
design compromises involved in the choice of reheat
pressure and temperature. First, consider the boundary
conditions. The HP cylinder exhaust steam must be
sufficiently superheated to avoid any wetness in the
cold reheat pipework, which would cause severe ero-
sion. As in the previous section, the exhaust steam
from the LP cylinder must be wet, but not greater
than 12% wetness. These boundaries are illustrated,
together with the effects of changing pressure, on
the Mollier diagram (Fig 1.39). Now consider the
effect of changing reheat temperature for a constant ENTROPY, S
pressure drop in the HP cylinder (Fig 1.40). The
effect of reducing the pressure or of raising the
temperature of the reheat steam is to reduce LP FIG. 1.39 Boundary conditions for a reheat line and the
exhaust wetness. effect of changing pressure at constant temperature

26
Thermodynamics of the steam cycle

has been mentioned in previous sections and is now


discussed in more detail. Simply, the effect of pres-
sure loss anywhere in the steam path causes a loss
in cycle efficiency by reducing the energy available for
conversion into work.
Valve gear at the inlet to the HP and IP turbines
is used to control the inlet mass flow and hence the
load on the machine by a throttling process. Figure
1.41 shows a Mollier diagram comparing the condition
lines of a reheat turbine at full load with all the
valves wide open and one at part load, where the load
has been reduced by 40% by throttling on the inlet
valves to the HP turbine. Other pressure losses are
neglected. The throttling effect is to reduce the inlet
pressure by a constant enthalpy process (represented
by horizontal line AB). The result is a loss in en-
tropy and also a slight fall in temperature with some
reduction in the available heat drop. This accounts
for a small loss in efficiency. However, the major
flow reduction which results is the main reason for
the reduction of work done in the HP, IP and LP
cylinders. In this example, the condenser pressure is
assumed to remain constant and the pressure drop

ENTROPY, S

FIG. 1.40 The effect of variation in reheat temperature

Although reducing LP exhaust wetness is desirable,


too high a temperature could lead to some diffi-
culties with materials. The common practice has been
to reheat to the original superheat steam condition,
i.e., 565C.
Another important factor in the design of the re-
heater is the effect of pressure losses in the pipework.
The pressure loss results from a throttling effect which
reduces the available energy for work (to be discussed
later in this section). The pressure at which steam is
reheated is about 25% of the stop valve condition,
representing approximately a fourfold increase in
volume. This necessitates the use of increased pipe
sizes which are expensive and inflexible. The plant
designer has to weigh the merit of using larger pipes,
or pipe runs in parallel, versus the improvement in
cycle efficiency. The usual pressure drop is 7.5 to
10% of the HP cylinder exhaust pressure. Finally,
constraints will exist in the boiler on the range of
conditions attainable.
ENTROPY, S

3.3.3 Effect of pressure loss in pipework and


valves FIG. 1.41 Loss of available energy due to throttling
The effect of pressure loss in pipework and valves the governor valve

27
The steam turbine Chapter 1

across the turbine cylinders is controlled by the Ellipse


law relationship described in Section 2.1.2 of this
chapter.
Pressure losses along pipe runs can be calculated
using equations and charts [6]. Pressure loss is associated
with pipe diameter, of surface roughness, steam flow rate
and the pipe geometry (number of bends, expansions,
contractions). Simply reducing piping losses by re-
designing pipe runs, or by adding to the number of
pipes, may increase the capital cost of the plant in
excess of the benefit gained in running costs.

3.3.4 Effect of final feed temperatures


In the previous section, the concept of regenerative
feedheating was introduced as a means of improving
cycle efficiency. The thermodynamic optimum final
feed temperature for Rankine cycle plant is, by defini-
tion, that which gives the highest cycle efficiency.
However, raising the final feed temperature would
reduce the required size of the boiler conomiser
surface. In order to avoid an increase in the stack
temperature, the air heater would have to be increased
in size, and the cost of this would exceed any sav-
ing on the conomiser. Consequently the economic
FIG. 1.42 The effect of condenser saturation temperature
optimum feed temperature is somewhat lower than on cycle work done
the thermodynamic optimum.
Raising the final feed temperature also has impli-
cations for the design of the HP turbine. Past prac-
tice has been to use bled-steam from the HP turbine However, there are several plant constraints affect-
exhaust. The saturation temperature of the bled-steam ing the selection design exhaust pressure. Consider
controls the maximum feed temperature obtainable. the effect of lowering the exhaust pressure on the tur-
To provide steam at a higher pressure with a higher bine condition line on the Mollier diagram (Fig 1.43).
saturation temperature, requires steam to be bled Expansion to a lower pressure results in increased
from an intermediate point on the HP cylinder. This wetness, and increased specific volume at the exhaust.
is an additional complication and cost to the turbine The increase in exhaust wetness tends to increase
plant. Despite the increases in capital cost, the benefit the erosion of the last-stage blades. However, more
from improved cycle efficiency is such that the addi- significant is the effect of increased specific volume,
tional heater is worth including. implying the need for a higher volume flow rate.
The design of the Advanced Gas-cooled Reactor The volume flow rate through the condenser is the
(AGR) has resulted in limitations on the final feed product of the mean steam axial velocity and the
temperature. The feed train is curtailed in order to annular exhaust area. The annular exhaust area is
limit the final feed temperature to about 150C. This limited by the maximum length of LP blade. At 3000
limitation is imposed because of the allowable tem- r/min, the centrifugal forces on the long blades be-
peratures in the gas cooling circuit. come very high and there is a limit to the mechani-
cal stress which blade roots can sustain. Hence, having
established a maximum annular area, the increase in
3.3.5 Effect of exhaust pressure volume flow rate must be accommodated by an in-
The efficiency of the cycle is strongly influenced crease in exit velocity. Steam issuing from the last
by the LP turbine exhaust pressure. The back pres- stage of the turbine with high residual velocity re-
sure of the condenser sets the saturation temperature presents a loss of kinetic energy. This kinetic energy
at which the expanded steam rejects its latent heat performs no useful work on the turbine blades and
of vaporisation to the cooling water. Consequently, therefore is a loss of available energy, known as the
changes in back pressure affect the temperature of 'leaving loss\ and varies with the square of velocity.
cycle heat rejection. The effect of a change in con- The other loss associated with the turbine exhaust is
denser saturation temperature on the cycle work done the 'hood loss\ which defines the hydraulic pressure
is shown on a T-S diagram in Fig 1.42. Generally, loss between the last row of moving blades and the
a low exhaust pressure is sought as it improves cycle condenser; this also varies with the square of the
efficiency. same velocity.
28
Thermodynamics of the steam cycle

and its development to the current reheat cycle used


in CEGB fossil-fuel and AGR power stations.

3.4.1 Steam conditions


The effects of increasing turbine stop valve pressure
and temperature and the effect of reheat have been
discussed in regard to cycle efficiency in Section 3.3
of this chapter.
It is also relevant to consider the major influences
on turbine efficiency. The most important factor in
turbine efficiency is blade length. Generally, an in-
crease in blade lengths implies reduced leakage losses
and secondary losses [5,7].
An increase in steam pressure at a given steam flow
reduces the volumetric steam flow and hence reduces
blade length. Increased steam pressure also requires
thicker casing walls and larger horizontal joint flanges
and joint bolts. It also implies thicker steam pipe
walls which require additional length to obtain the
required flexibility. These difficulties are only partly
mitigated by the reduction in casing size and pipe
diameter made possible by the smaller volume flow.
Another important effect of increased steam pres-
sure is the requirement of increased pumping power
to raise the feed water to the higher pressure.
It follows that increases in steam pressure are only
ENTROPY, S
a benefit in practice when associated with an increase
in unit size and/or an increase in steam temperature.
An increase in steam temperature has the effect of
FIG. 1.43 The effect of exhaust pressure on turbine increasing the specific volume and hence blade length
expansion and therefore tends to increase turbine efficiency with-
out any increase in unit size. There are practical
disadvantages, which include the required increase in
casing size and pipe diameter, and increased thermal
The sizing of the LP turbine exhaust area affects
stresses especially when starting and loading.
the overall design of machine, in particular the ther-
mal design of the condenser (see Chapter 3). The The influence of the combined effects of tem-
requirement to provide a certain volume flow rate perature and pressure changes and turbine efficiency
affects the configuration of the LP cylinders since considerations on unit size can be illustrated by a
1, 2, 3 or even 4 double-flow LP cylinders may be study of the 'standard' steam conditions specified by
operated in parallel to give the desired flow rate. the BEA and CEGB from 1945 onwards.
The number and size of the chosen arrangement of Table 1.1 has been simplified by the exclusion of
LP turbines affects many other areas of design the a number of units of close to the 'standard' 60 MW
rotor dynamics; the plant arrangement; size of civil size, some of which employed reheat. It shows the
structures. general trend.
Having introduced all factors against decreasing There is a progressive increase in unit size accom-
exhaust pressure, the design compromise is once more panied by a series of step increases of pressure and
between improvements in cycle efficiency versus the temperature, with a few notable exceptions. The main
increase in plant complexity and therefore reliability exceptions are the two 375 MW supercritical units
and cost. Finally, a major factor affecting the choice for Drakelow C, commissioned in 1967-68 and the
of exhaust pressure is the ambient temperature at two 550 MW cross-compound units for Thorpe Marsh,
which the CW can reject heat. This factor seasonally commissioned in 1963-65. These units could be said
effects the thermal efficiency of the plant. to have been ordered before their time and have not
been followed by further development.
The steam temperatures can be seen to reach a
plateau of 538C and 565C. The 538C limit applies
to oil-fired units to avoid the use of austenitic ma-
3.4 Superheat cycle terials in the boiler. These suffer heavy corrosion due
This section deals with the superheated steam cycle to the sodium and vanadium content of the fuel oil.
29
The steam turbine Chapter 1

1.1
The influence of the combined effects of oerature and pressure changes on unit size

Year TSV TSV Reheat Reheat


Station Rating (fully pressure temp EV EV
(typical) (MW) commissioned) (bar) (C) pressure temp
(bar) (C)

Blackwall 30 45-58 42.4 454


Point
Uskmouth 60 45-60 63.1 482
Castle 100 56-69 104.4 566
Donnington
Ferrybridge B 100 57-63 104.4 528 25 528
Blythe A 120 59-63 104.4 538 25 538
High Marnham 200 59-63 160 565 29 538
Blythe B 275 62-63 160 566 40 566
Thorpe Marsh 550 63-65 160 566 40 566
West Thurrock 300 64-66 160 566 41 566
Tilbury B 350 65-72 160 566 40 566
Drakelow C 375 67-68 242 593 47 566
West Burton 500 67-73 160 566 26 566
Grain 660 74 160 538 26 538

The 565C limit for coal-fired plant is to avoid at the blading.


increasing costs due to the extended use of austenitic The IP turbine casing has to provide openings
materials to avoid creep failure. Creep is the phe- large enough to pass the exhaust steam on to the
nomenon of slow progressive yielding which occurs LP turbine at moderate velocities without unduly
at high temperature. In the turbine, it leads to re- reducing its stiffness. The casing inlet end must be
duced clearances and increased stress levels over a carefully designed to reduce thermal stress.
period of time, and in the boiler (where temperatures The pipework to and from the reheater and in the
are higher) to time-dependent tube failures. reheater section of the boiler represents a significant
Current worldwide practice for modern large units storage volume. It is therefore necessary to supply
is to limit steam temperatures to the 540C level. additional valves to protect the turbine from over-
speeding in the event of a sudden loss of load. As in
the HP turbine, these valves must be in series-pairs
3.4.2 Reheat to provide back-up in the event of one valve failing
Table 1.1 also shows the general adoption of reheat to close when required. They operate at the same high
for all units over 100 MW. It has been shown earlier temperature but must be considerably larger than the
in this chapter that reheat allows a closer approach HP valves. To handle the flow, up to four sets of
to the ideal Carnot cycle. Its adoption has cost and valves may be provided.
design significance. There is, of course, the require-
ment of additional piping to and from the boiler,
the latter requiring high temperature with larger bore 3.4.3 Double reheat
size than the HP steam pipes. The higher volume
flow of the reheated steam requires the IP turbine A further approach to the Rankine cycle can be made
to have a larger rotor diameter and longer blades by using additional stages of reheat. A second stage
than the HP turbine. Sometimes there is a choice of reheat involves similar additional cost and design
between increased outlet blade angle and double flow considerations to those already described for single
in the IP cylinder, resolved in the case of CEGB 500 reheat. There are obviously greater difficulties in
and 660 MW units by using double flow. matching steam and metal temperatures during start-
To reduce creep in the high temperature regions, ing and load changes.
it is common to admit a supply of lower temperature Figure 1.44 shows a simplified Mollier diagram for
cooling steam to the space between the inlet fixed a single and double reheat supercritical cycle, and
blades and rotor. This steam tends to flow through Fig 1.45 shows the T-S diagram. In practice a second
the balance holes in the discs and the diaphragm stage of reheat is only normally justifiable with a
glands, thus shielding the rotor from the hotter steam supercritical cycle.
30
Thermodynamics of the steam cycle

into superheated steam without boiling in the accepted


sense. The latent heat of vaporisation is zero and,
since the densities of the water and steam are the
same, there is no well defined water-to-steam transi-
tion interface.
A brief explanation from physical data source may
be helpful. Water at high temperature consists of
clusters of molecules held together by strong potential
binding forces of short duration. These clusters per-
mit angular or linear displacement which gives rise
to the liquid characteristics.
Evaporation of a liquid into a gaseous space nor-
mally consists, at the molecular level, of a surface
molecule in a liquid cluster acquiring sufficient thermal
(and thus kinetic) energy to overcome the potential
binding forces of its neighbouring molecules to break
away clear of the cluster and leave the surface of the
liquid to enter the gaseous space. The binding forces
between the surface molecule and molecules well below
the surface are not significant as potential forces drop
off extremely rapidly with increasing distance. Liquids
subjected to high pressures logically require higher
thermal energy, and therefore higher temperature, for
the surface molecule to break free of the molecular
cluster. At supercritical pressures, the potential forces
exerted between molecules in a molecular cluster are
too large to be overcome by increases in thermal
ENTROPY, S
energy and hence no surface molecules escape from
the molecular clusters. However, as the supercritical
FIG. 1.44 Single and double reheat cycles H-S diagram pressure fluid undergoes a temperature rise, the aver-
age size of its clusters diminishes. With further in-
creases in fluid temperature, the molecular clusters are
reduced to isolated molecules and all traces of any
form of crystalline structure has disappeared. Thus
the supercritical pressure fluid acquires its steam-like
qualities not by evaporation of isolated surface mole-
cules, but rather by the gradual diminution in the
number of molecules contained within molecular
clusters.
A double-reheat supercritical cycle can show ap-
proximately a 3.9% efficiency advantage over a single
reheat subcritical cycle (242 bar/540C/540C compared
with 166 bar/540C/540C).
For single-reheat, the reheat pressure is commonly
about 25% of the initial pressure while for double-
reheat the first reheat is usually at about 30% and the
second 10% or less. There are no known proposals
for triple-reheat, and it is most unlikely that the
additional cost could be justified. There is also the
difficulty of designing an LP turbine with the high
inlet temperature required. This is already about 370C
ENTROPY. S
for double-reheat machines.
FIG. 1.45 Single and double reheat cycles T-S diagram

3.4.4 CEGB cycles


It is instructive to consider some recent and current
The critical pressure of steam CEGB design cycles by comparing their Mollier diagrams
At 221.1 bar, water heated to 374C turns directly (Fig 1.46), the selected cycles are:
31
The steam turbine Chapter 1

(b) 660 MW AGR 160 bar/530C reheating to 538C at


37.4 bar (23.3% TSV) with 41 mbar condenser
pressure.
(c) New subcritical coal-fired 176 bar/565C reheating
to 565C at 50 bar (20.8% TSV) with 57 mbar
condenser pressure.
(d) New supercritical coal-fired 240 bar/565C re-
heating to 565C at 60 bar (25.0% TSV) with
57 mbar condenser pressure.

In this example, single-reheat has been selected for


the supercritical cycle. The advantages and disadvantages
of double-reheat require careful consideration. All CEGB
coal or oil-fired plant is designed to be capable of
'two-shifting' for a significant part of its life. It is
clearly more difficult to achieve this kind of flexibility
with double-reheat and the type of plant eventually
built will need to take these factors into account.
The two 660 MW cycles are typical of the latest
units in service, although the coal-fired 660 MW units
use 565C TSV and reheat temperatures.
Both the AGR and the oil-fired 660 MW units use
a back pressure boiler feed pump turbine, supplied
with steam from the HP exhaust and returning it to
the IP/LP crossover point.
The oil-fired unit has bled-steam extractions at HP
exhaust, at BFPT midpoint, at BFPT/IP turbine ex-
haust and from three positions in the LP turbine.
The AGR requires cooler feedwater and takes bled-
steam from the BFPT/IP exhaust and from four posi-
tions in the LP turbine.
The new large coal-fired units will use motor-driven
feed pumps. They can take advantage of higher final
feed temperature and the economics justify bled-steam
ENTROPY, S
extraction from the HP turbines at approximately 70-76
(1)660MWOIL
(2) 660MW AGR
(3) NEW COAL SUBCRITICAL
bar. They also have bled-steam extraction from HP
(4) NEW COAL SUPERCRITICAL exhaust, IP exhaust and four stages from the LP
turbine.
FIG. 1.46 Condition lines for current CEGB designs The diagram shows how much larger are the IP
and LP heat drops than those of the HP turbines.
It is also notable how close together are the IP and
(a) 660 MW oil-fired with BFP turbine. LP expansion lines for all four examples. The HP
expansion line for the subcritical coal-fired machine
(b) 660 MW AGR with BFP turbine. is not very different from that for the two 660 MW
units, although its higher pressures will mean reduced
(c) New subcritical coal-fired with motor-driven feed specific volumes throughout. The new supercritical unit
pump. has larger HP and IP heat drop than the subcritical
machine. This implies additional available work but
(d) New supercritical coal-fired with motor-driven feed this is bought at the price of increased feed pump
pump. power.
The feed pump power is an important part of the
The steam conditions for these cycles are summarised cycle selection.
below: The low back pressure of the AGR is clearly ap-
parent. This pressure is largely site-dependent and is
(a) 660 MW oil-fired 160 bar/538C reheating to a function of the mean year-round cooling water
538C at 39 bar (24.4% TSV) with 61 mbar con- temperature. The oil-fired 660 MW unit is located
denser pressure. on the Thames where the water temperature is quite
32
Thermodynamics of the steam cycle

high. The two new coal units assume tower cooling, below, the turbine centreline. The 'above centreline'
while the AGR is at a coastal site with cold water. arrangement requires removal of the pipework before
the LP turbine can be opened for inspection. The
'below centreline' location has sometimes been thought
to be responsible for some turbine misalignment, due
3.4.5 Turbine designs
to heat transmission to bearing pedestals and casings.
It is now proposed to consider these cycles from the The IP exhaust is considered to be the most suit-
viewpoint of turbine cylinder designs. The 660 MW able point for connection to the de-aerator. This is a
fossil fuel and the 660 MW AGR turbines are quite direct contact heater which is vented to the condenser
similar. The use of the same steam conditions and and designed to remove air from the feedwater before
rating clearly implies this. In fact, the AGR machine it enters the main feed pumps. It is always combined
has about 15% less HP steam flow and 5% more with a large capacity storage vessel and elevated to
IP steam flow for similar power output due to its provide a static head to the main feed pump suction.
reduced feedheating requirement. It also has about The CEGB has used reheat cycles for all power
7% greater LP turbine inlet steam flow. station turbines above 100 MW rating. This is not
These differences are accommodated by small blade true worldwide. In some countries there is a need for
height or pressure level changes. In the cases chosen, large units operating on a simple non-reheat cycle for
there is an apparent contradiction in that LP inlet peak-load lopping duty. These machines run for only
pressure for the oil-fired unit is lower, while its re- a few hours a year, so maximum efficiency is not
heater pressure is higher. This arises from the fact important, but they must be able to run-up to full-
that this machine uses a four-flow LP turbine with load quickly and be inexpensive.
only five stages while the AGR uses six flows with For this class of turbine, the feedheating cycle is
six stages. The IP turbines are also rather different. kept as simple as possible and the expense and com-
The choice of IP exhaust/LP inlet pressure is en- plication of reheating is not economic. A typical
tirely a matter for the turbine designer. It is the point machine of this type would deliver 280 MW from a
where steam passes from the two flows of the IP single-casing condensing turbine in double-flow.
turbine to the four or six flows of the LP. A low
pressure results in large crossover pipework and long
last-stage IP blading, while a high pressure results
in short LP inlet blading and higher LP inlet tem- 3.5 W e t steam cycle
perature. The selected pressure represents a com-
promise between these considerations and must give The wet steam cycle is mainly associated with the
heat drops in the IP and LP turbine appropriate to evolution of nuclear power. Nuclear power has been
the number of stages and the stage diameters required. developed mainly on conventional lines, by using the
With modern designs, an effort is made to select nuclear fission reaction as a source of heat for the
pressures to permit the use of standard turbine mod- steam cycle. In this section, discussion will be con-
ules. This leads to increased reliability and reduced centrated upon the thermodynamic and economic
manufacturing costs and also reduces the number of aspects of nuclear-powered plants, in particular those
spares required notably spare rotors. aspects relating to the steam cycle for a Pressurised
Water Reactor (PWR).
Turning now to the new coal-fired proposals, it
must be remembered that, although the condition lines
are similar, these turbines will be very different from
the 660 MW units because they will be designed for 3.5.1 The PWR steam cycle
something of the order of 30% increase in power The PWR power plant features three principal heat
output. They will also embody the most recent blading transfer processes. In the primary circuit, fuel is
and a whole range of detail design improvements. irradiated, liberating heat which is transferred to a
It is noticeable how little difference there appears secondary steam cycle. In a nuclear power station
between the subcritical and supercritical condition the plant performing this function is known as the
lines for the IP and LP sections. It should be added Nuclear Steam Supply System (NSSS). In the second
that the reheater pressures quoted are approximate cycle, the steam generated is expanded to drive tur-
and are not fully optmised values. bines which generate electrical power. Finally heat is
The IP exhaust/LP inlet 'crossover' pipework merits rejected to the Cooling Water (CW) in the condenser
comment. This pipework handles low pressure steam this is the third heat transfer process. The PWR
and is of large diameter to minimise pressure losses. general arrangement is shown in Fig 1.47.
The pipework has separate branches where the IP The NSSS consists of the reactor, the reactor coolant
exhaust steam enters and where the LP inlet steam system (RCS) and a number of auxiliary and safety
leaves. It is always provided with a number of flexible systems. The RCS consists of the reactor within its
sections to allow for pipe/casing expansion differ- pressure vessel and three or four cooling loops con-
entials. It is sometimes installed above, and sometimes necting the reactor to the primary/secondary heat
33
The steam turbine Chapter 1

CONDENSATE
EXTRACTION
PUMP

SECONDARY CIRCUIT

FIG. 1.47 PWR power cycle

exchangers (steam generators). The reactor vessel and


cooling loops are filled with deminer alised water, which L Tmax (SATURATION)

2
is pumped around the primary circuit. In this system, ^ f IPRIMARY CIRCUIT
boiling within the reactor is suppressed by maintain- -WATER

ing coolant water pressure in excess of the saturation j^


pressure corresponding to the coolant temperature at
^ PINCH POINT

outlet from the reactor. The pressure is controlled


by a control system and a surge tank, known as the
pressuriser, connected to one of the cooling loops.
rIT 'SECONDARY CIRCl
| WATER/STEAM

!/
The secondary circuit is of major interest to this
discussion. The feedwater enters the steam generator,
where its temperature increases up to its saturation
temperature. At the saturation temperature, the water "^
Q=mH

changes state to steam which leaves the steam genera-
tor slightly wet. The heat exchange process for both
cycles is shown on a Temperature-Enthalpy (T-H) 1
diagram (Fig 1.48). MASS FLOW X SPECIFIC ENTHALPY, m x H

The wet steam produced in the steam generator is


of a lower quality than the superheated steam con- FIG. 1.48 Temperature plotted against (mass flow x
ditions from both fossil-fired and AGR-powered plant. specific enthalpy) for the primary and secondary circuits
However, there are limitations to the steam conditions in the steam generator of a PWR
Note that the x-axis, is the product of mass flow and
attainable. On the primary side, the maximum tem- specific enthalpy of the two fluids. Aqh must be the
perature is restricted by the desirability of avoiding same for both processes as it equals the quantity of
nucleate boiling in the reactor core, as heat transfer heat transferred
coefficients for steam are considerably lower than
that for water. Consequently the primary circuit outlet
temperature, T 2 , is less than the saturation value for steam conditions are designed accordingly. The feedwater
that pressure. Having established the primary circuit is heated and the resulting steam/water mixture passes
conditions, the steam generator and secondary circuit through moisture separators, which improve the steam
34
Thermodynamics of the steam cycle

quality by reducing wetness. The incorporation of a


superheating surface would necessitate an unwarranted
complication in the design of the steam generator. The
design practice is to reduce the 'pinch point' to a
minimum (see Fig 1.48) whilst optimising steam gen-
erator cost against improvements in overall cycle
efficiency.
Consider now the cycle for the turbine-generator
(Fig 1.47). The slightly wet steam leaves the steam
generator, passes through governor valves and enters
the HP turbine. The steam is expanded through the
HP turbine where its pressure reduces and its wetness
increases. The wet steam then passes through a mois-
ture separator which returns the steam to a near-dry
saturated state. The steam is then reheated in two
stages. The first reheat process uses steam bled from
a tapping on the HP cylinder, the second uses live
steam taken upstream of the governor valves. The
steam leaving the reheaters is in a superheated con-
dition before entering the LP turbine where it is
expanded to a low pressure. The low pressure steam
is condensed in the condenser, rejecting heat to the FIG. 1.49 Expansion of steam from initial conditions
without reheat or moisture separation
CW. The condensate is pumped through several stages
of LP heaters to the de-aerator.
The de-aerator is a large direct contact feedheater
which provides for oxygen removal, a buffer store
of feedwater and sufficient gravity head to overcome This expansion results in steam at the later stages
the net positive suction head of the boiler feed pump. with a moisture content of 25%. A high moisture
The feedwater is pumped through several stages of content is intolerable as it results in blade erosion and
HP heaters before return to the steam generator. stage efficiency losses. The undesirability of blade
erosion was discussed earlier in this chapter. As steam
is expanded through the turbine it starts to condense
in the wet region along the Wilson line' which
3.5.2 Cycle considerations corresponds to a wetness factor of 3-4% (see Fig
Consider now the effects of the various processes 1.50). Above the Wilson line, the steam behaves as
upon the thermodynamics and economics of the wet dry steam; below the line, wetness becomes apparent
steam cycle. Earlier it was concluded that the inclu- in the turbine expansion. Water droplets entrained in
sion of a superheating surface within the steam gen- the steam flow only accelerate to a small proportion
erator was economically impractical. However, it is of the dry steam velocity as they pass through the
desirable to reduce the steam wetness as far as possi- fixed blades. The resultant mist has a velocity which
ble with the moisture separating equipment within does not suit the inlet velocity triangle of the moving
the steam generator. The Westinghouse four-loop 3425 blade (Section 1.2.2 of this chapter), neither in mag-
MW (thermal) design, which has been adapted for the nitude nor direction. As the mist progresses through
UK's first PWR station at Size well, provides steam to the turbine, the droplets migrate toward the blade
the turbine whose full load conditions are nominally: tips by virtue of centripetal inertia. The resultant effect
of the wet steam is a mechanical drag corresponding
Pressure = 66.6 bar to a 1% cylinder loss for every 1% wetness.
The effects of a high moisture content are un-
Temperature = 282C attractive from the viewpoints of turbine efficiency
and operational economics. The cycle described earlier
Maximum wetness factor = 0.25% included a moisture separator reheater (MSR), which
takes partially expanded steam, removes the moisture
and reheats to a superheat temperature. The choice
The exhaust pressure in the condenser is of the order of reheat or crossover pressure is affected by various
of 50 mbar. The expansion of the steam from the parameters for a machine rotating at 3000 r/min;
initial conditions to this pressure would result in an these are:
intolerable wetness factor in the final stages. The
expansion is shown on a Mollier diagram (Fig 1.49) The maximum wetness in the LP turbine exhaust
for a turbine with 85% efficiency. (10-12%).
35
The steam turbine Chapter 1

BEHAVES AS DRY STEAM

DESIGN WINDOW

FIG. 1.50 The 'Wilson line' dividing the wet and dry
expansion

FIG. 1.51 Constraints on crossover pressure for MSR


The maximum wetness in the HP turbine exhaust Note that pressure P 3 is outside the 'window'
as it corresponds to an excessively-high value
(14-15%). of HP exhaust wetness
The temperature to which reheat steam can be
raised, limited by the maximum steam temperature
available at the turbine stop valve (TSV). The need for steam reheating has been addressed,
but the means of reheating has not been discussed in
Overall cycle efficiency. detail. The objective of the reheating process is to
Plant capital costs. produce the best steam conditions for the minimum
cycle and plant capital cost. The factors to be con-
sidered are:
The wetness in the HP turbine can be a little higher The choice of live steam (single-stage reheating) or
than that for the LP turbine as the blades are shorter live and bled-steam (double stage reheating).
and the tip velocities are considerably less.
Considering these parameters on the Mollier chart The final terminal temperature difference achieved
(Fig 1.51) presents a 'window' within which the cross- between reheated steam and live steam.
over pressure can vary. The resultant LP condition
line is very similar to that of a conventional LP cyl- The pressure loss across the reheater.
inder on a fossil-fired or AGR plant. The option to
replicate the LP cylinder is attractive, as it presents
savings in terms of design and manufacture and of- Although all these factors are considered simul-
fers a utility, such as the CEGB, the option to ra- taneously in the design, consider the choice between
tionalise its national spares holding. The replication single and double-stage reheating. The plant arrange-
of the LP cylinder would, however, restrict the varia- ments for single and double-stage reheating are shown
tion in crossover pressure still further. in Fig 1.52. The variation in net cycle output against
The inclusion of steam reheating following mois- total reheater surface area (Fig 1.53), shows a con-
ture separation has obvious advantages in terms of sistent advantage over the single stage reheating.
improving the LP exhaust wetness. The more effective The thermodynamic benefit derives from using a
the moisture separator, the less reheating is required; higher proportion of the high quality, dry steam pass-
modern separators can produce steam with wetness ing through the turbine to do work. Hence the HP
factors of 0.25% or better. turbine efficiency is improved, since wetness reduces

36
Thermodynamics of the steam cycle

MOISTURE
SEPARATOR

TO FEEDTRAIN TO FEEDTRAIN

(a) Single stage reheater

TOLP
CYLINDERS

V
TO FEEDTRAIN
(b) Double stage reheater

FIG. 1.52 Single and double-stage reheating plant

37
The steam turbine Chapter 1

UyL
10 12 14 16

HP EXHAUST PRESSURE, % OF HP INLET PRESSURE

140 160
FIG. 1.54 Advantage of double-stage over single-
TOTAL REHEATER AREA, <
stage reheat

FIG. 1.53 Comparison of output with reheater surface area


for single and double-stage reheating
speed machine. Whilst small differences in efficiency
exist, they are much smaller than those arising in
the steam turbine area.
stage and cylinder efficiency. The other benefit of
The principal factors involved in a comparison of
two stages over one concerns the efficiency improve-
half and full-speed turbines are:
ment associated with dividing the temperature rise
across an increased number of heaters (in a similar Relative sizes and weights of the turbines and
way, the increase in the number of feedheaters in- differences in their constructional features.
creases overall cycle efficiency). The benefits to op-
erating efficiency must be judged against the increased Relative expectations of reliability, operational flexi-
capital cost of the additional plant. The increased bility, and ease of maintenance.
capital cost includes extra heating surface, a HP cylinder
bled-steam tapping, extra pipework and increased pres- Relative thermal efficiencies.
sure loss in the reheater.
Economic comparisons.
The effect of HP exhaust pressure upon the choice
between single and double-stage reheating, is shown
in Fig 1.54. Size, weight and construction
The optimum pressure is shown, but there is little
For equal stress levels in geometrically-similar turbine
penalty associated with deviating from the optimum.
rotating components, all linear dimensions should be
However, this curve shows the general benefit of double-
inversely proportional to the speed. Theoretically,
stage reheating over a range of exhaust pressures.
the last-stage blades of a half-speed turbine could be
made twice as long as those of a full-speed turbine
and could be carried on a rotor of twice the diameter,
3.5.3 Full-speed or half-speed machines leading to an exhaust area of four times the size.
The final issue dealt with in this section involves a However, practical half-speed turbines are limited
comparison of half-speed (1500 r/min) and full-speed by weight and physical size to be about 40% larger
(3000 r/min) machines. The study is limited to the than full speed turbines: Table 1.2 gives a comparison
steam turbine rather than the generator, as the tur- between realistic half and full-speed machines in terms
bine is more affected by the wet steam cycle. It is, of relative sizes and weights.
however, pertinent to observe that generators at 3000 Note that the total relative volume and weight of
r/min and 1500 r/min are technically feasible up to the rotors and casings per unit exhaust area for the
the largest required outputs. There are substantial half-speed turbine is 2.85 times the full-speed turbine.
differences in the weights and manufacturing costs The manufacturing costs associated with the larger
of 2-pole and 4-pole generators favouring the full- half-speed machine are higher as more materials are

38
Thermodynamics of the steam cycle

TABLE 1.2
Sizes and weights of a 1500 r/min turbine relative to a
3000 r/min turbine

Scaling ratio for linear dimensions 1.4


1500 r/min to 3000 r/min turbine
Relative turbine blade exhaust 1.42 = 1.96
annulus area
Relative number of turbine stages 2.0V 1.5 = 2.05
Relative volume and weight of rotor 1.43 = 2.74
material per turbine stage
Total relative volume and weight of 2.05 x 2.74 = 5.60
all turbine rotors
Total relative volume and weight of 5.60/1.96 = 2.85
turbine rotors, per unit exhaust area
Relative diameter of turbine casings 1.4
Relative thickness of turbine shells 1.4
Relative volume and weight of turbine 1.43 = 2.74
casings, per turbine stage
Total relative volume and weight of
turbine casings, per unit exhaust area 2.85

used and a greater number of turbine stages have to FIG. 1.55 Comparison of half-speed and full-speed
HP cylinders
be built. The constructional differences between the
two types are largely associated with the increased
size and weight of the half-speed turbine. The dimen-
sional limitations to the forgings of HP rotors of achievement of zero erosion is likely to be more
the half-speed turbine have resulted in a crossover difficult with a half-speed machine.
pressure higher than optimum. These higher crossover The LP cylinder for the full-speed machine is si-
pressures require an additional inner casing in the milar to that of a fossil-fired plant. Consequently,
LP cylinder to avoid excessive thermal gradients. In though there are few differences in blading erosion
summary, the large size of the individual components problems, the experience of UK utilities is in the
of the half-speed turbine, forces the designer to 'over full-speed area. The design of half-speed LP rotors
design' some constructional features (see Fig 1.55). involves a shaft with various discs, shrink fitted; this
type of rotor presents poorer dynamic behaviour
and is more susceptible to stress corrosion cracking
Reliability, operational flexibility and maintenance problems.
The reliability of full and half-speed turbines are just There are two disadvantages associated with the
as important in the choice of machine as efficiency half-speed machine which are related to plant op-
comparisons, and need to be considered. eration. The larger diameter of the HP rotor leads
to increased thermal stress. In addition, the rate of
It is important to observe that there is no valid
increase of steam temperature at the inlet to the LP
statistical evaluation of experience to support any
cylinder may have to be restricted during start-up, to
argument for one design being more reliable than the
avoid losing the shrink fit rotor.
other. Reliance must be placed upon objective assess-
ments of technical (including engineering) differences There is no reason to suggest that the frequency of
and potential sources of difficulty in various areas maintenance of the half-speed machine is significantly
of turbine design and operation. different from that of the full-speed machine. However,
there will be increased problems in lifting, handling,
There are no systematic differences between the transporting and machining components of the half-
two turbines with regard to the HP blade and rotor speed turbines, due to their weight and size.
erosion. The stationary components of the HP cylinder
are subjected to pressure differences with wet steam
at their joint faces; if leakage flows are generated,
there is a danger of wire-drawing erosion. The in- Relative thermal efficiencies
creased radial dimensions of the half-speed turbine Marginal differences exist between the two designs
result in pressure loadings at the joints as great as with regard to the internal cylinder efficiences. They
twice that for the full-speed machine. Therefore the can be summarised as:
39
The steam turbine Chapter 1

The enforced high crossover pressure of the half-


speed machine results in higher leakage loss in the DETAILED ECONOMIC
ASSESSMENT REQUIRED
last few stages of the LP cylinder. 65-70m2
(EXHAUST AREA)

The half-speed LP cylinder experiences higher tip


losses due to the increased radial clearances asso-
ciated with a more flexible rotor.
REGION WHERE 3000 r/min REMAINS ECONOMIC

The full-speed machine has marginally higher tip * 3000 r/min MOST ECONOMICAL
losses in the last stage LP blade due to aero-
dynamic effects.
WET COOLING TOWERS

Economic comparisons WARM SEA. LAKES

It has already been shown that the half-speed turbine


is more expensive than the full-speed turbine of equal
output and exhaust area, with no advantage in effi-
ciency or reliability. Hence the full-speed turbine will 90 100 110 120 130
be advantageous whenever its exhaust area can match CONDENSER PRESSURE, mbar
the value which is desirable for an economically achiev-
able condenser pressure. FIG. 1.56 Regions of power output and cooling water
In order to establish the regions of potential eco- temperatures favouring economic application of 3000 r/min
and 1500 r/min turbines, assuming current, last-stage blade
nomic application of the two types of turbine, it is lengths are used to give an exhaust area of 65-70 m2
necessary to consider:

The relationship of desirable exhaust areas to


different combinations of outputs and condenser
The turbine comprises one HP cylinder and three
pressures.
LP cylinders on a single shaft. The six-flow exhaust
The economically achievable condenser pressures provides an area of 47 m 2 , which is sufficient for the
available. rated output, whilst using seawater cooling. However,
modern blading developments will enable the design
Available total turbine blade exhaust areas for full- of high speed machines with much larger exhaust
speed turbines and the regions of outputs and areas, suitable for outputs in excess of 1000 MW.
condenser pressures where they are economically
advantageous.

4 Economics of t h e s t e a m cycle
Half-speed turbines are economical only in circum-
stances where the largest outputs are combined with
very low condenser pressures, favouring the adoption
4.1 Choice of exhaust pressure
of larger exhaust areas than those which could be
The turbine efficiency depends, to a certain extent,
provided by currently available full-speed turbines
on the choice of turbine exhaust pressure. This choice
(see Fig 1.56). Even this region of economic appli-
is based on both thermodynamic and economic grounds.
cation of the half-speed turbine is under threat from
Following consideration of thermodynamic optimisa-
the impending availability of full-speed machines with
tion, the economic factors influencing the whole
greater exhaust areas.
spectrum of turbine-generator plant optimisation is
described. The form of economic study to permit
Turbine-generator for the CEGB PWR selection of the turbine exhaust pressure, condenser
and cooling water parameters is then given.
The proposed station at Sizewell B will incorporate
a single 3425 MW (thermal) PWR of a four-loop
design. The NSSS will provide steam to two full- 4.1.1 Thermodynamic optimisation
speed turbine-generators, each with a gross output of The power developed by a steam turbine supplied
622.5 MW. with a constant mass flow rate varies on the exhaust
The current turbine design incorporates a means pressure changes for the following reasons:
of isolation of the steam supply to enable main-
tenance work to be performed on one machine whilst (a) As the exhaust pressure is reduced, the isentropic
continuing to operate the other. This means of iso- heat drop across the last stage increases and so
lation will improve generating availability. additional work is done in the turbine.

40
Economies of the steam cycle

(b) The additional work is not as large as it could


be because the volumetric flow rate, and therefore 0-T

the velocity of the steam, increases as the exhaust


pressure is reduced. An increase in velocity means
an increase in kinetic energy of the steam at the
turbine exhaust and therefore a loss of power due
to the increased leaving loss.
3
o
-6 H
LU

(c) As the exhaust pressure is reduced, the cor-


responding saturation temperature is reduced.
Therefore, more steam is extracted from the tur-
bine to heat the condensate in the first feedwater
heater, so that less steam passes through the last
LU ^ W

-12J >V
stages of the turbine, giving a further loss in
output. -14-| 1 1 1 1 1 1 1 1 1 ^
0 1 2 3 4 5 6 7 8 9 10
EXHAUST PRESSURE
OPTIMUM EXHAUST PRESSURE

These conflicting points mean that there is an 'op-


timum exhaust pressure' where the greatest net power FIG. 1.58 Output characteristic
is produced. This occurs when the effect of point (a)
is equal to points (b) and (c). At exhaust pressures
lower than optimum, the increase in power due to (a)
is less than the decrease due to (b) and (c), so a net also involved in the choice of design exhaust pres-
reduction in power generation and increase in heat sure, resulting in the exhaust pressure being some-
rate will occur as exhaust pressure is lowered further. what greater than the thermodynamic optimum.
At exhaust pressures higher than optimum, the op-
posite effects occur. This is shown graphically in
Fig 1.57, where the percentage increase in heat rate
4.1.2 General economic optimisation of plant
has been plotted against (exhaust pressure/optimum
exhaust pressure). A central theme so far in this chapter, has been the
Figure 1.58 shows the corresponding characteristic improvement of cycle efficiency. The importance of
for the change in power output. efficiency in reducing the unit cost of electricity can
The variation of turbine heat rate with exhaust best be seen by examining its relation to other factors
pressure, shown in Fig 1.57, is obtained from the affecting cost. What matters most to the utility man-
basic turbine design data relating to the turbine ex- ager is the reduction of the total lifetime cost of the
haust area, exhaust mass flows and the heat rejected. plant (refer to Volume A for the full discussion).
The term 'optimum' is used here with respect to the The major concern of this chapter is the lifetime gen-
power generated and heat rate. Economic factors are eration costs of turbine-generator plant, which breaks
down into:

Capital cost.
14
Fuel cost.
12
Operating and maintenance costs.

ui
For a valid comparison of new designs, all these
Is cost elements must be considered simultaneously at a
5: certain reference date, e.g., the commissioning date. The
LU
X
Z 6 Capital cost is conditioned by the timing of stage
payments and the interest rates predicted over the
construction period. Similar considerations apply to
- f the Fuel cost and Operating/Maintenance costs, with
2-J ^r
interest rates being the determining factor. To enable a
0 + - ^ I
0 1 2 3
1
4
1
5
1
6
1
7
1
8
1
9
1 1
10 comparison between plant of different ratings, these
EXHAUST PRESSURE costs are expressed as a Capital cost factor, measured
OPTIMUM EXHAUST PRESSURE in /kW.
The Capital cost comprises not only the cost of
the turbine-generator itself, but also the costs of the
FIG. 1.57 Heat rate characteristic turbine hall to house it and the services required.
41
The steam turbine Chapter 1

The historical trend has been to larger, higher output 4.1.3 Economic optimisation of exhaust
plant of compact design, which has had a consider- pressure, condenser and CW system
able impact on reducing the Capital cost factor. The Up to now we have only considered the design of
practical problems of transport and assembly indicate the turbine. The economic optimisation is highly
diminishing returns in this trend, which suggest that dependent upon the Cooling Water (CW) system as
plant with an output of about 1000 MW may be a well. The general economic considerations given in
maximum limit. the previous section will now be developed to examine
The Fuel cost expended over the power station the combination of the turbine, condenser and CW
lifetime is of course directly influenced by the design system.
cycle efficiency, and the means of achieving this is Figure 1.60 shows a typical 'direct cooled system',
the prime topic of this section. It has been shown that using sea water as a coolant. The system is called direct
the cycle efficiency can be improved by increasing the cooled because the water is used once and then dis-
provision and complexity of the plant, e.g., increasing charged. A circulating pump forces water through
the number of reheating stages. The designer carries screens, which removes any debris large enough to
out a cost-benefit analysis to reach a reasonable block the condenser. There are valves at inlet and
compromise, to ensure that the benefits of improved outlet to the condenser to ensure flexibility of op-
efficiency are not eclipsed by excessive capital costs, eration during changes in climatic conditions. Flexi-
or by complication leading to reduced reliability. bility is developed further by increasing the number
In different parts of the world and in a rapidly of circulating pumps available. The CW system there-
changing economic environment, the cost of fuel can fore makes a significant contribution to the capital cost
show wide variations. For new plant, it is desirable of the plant. On inland stations, using indirect cooling
for the utility to present the designer with a cost with large cooling towers, the costs can be higher still.
expressing the capitalised value of 1% improvement
in the heat rate. This will enable him to identify the
options best suited to the application. CONDENSER
COOLING WATER
Plant Operating and Maintenance Costs are reduced OUTLET VALVE

by improving the reliability of plant and by mini-


mising the maintenance and overhaul outage times.
Increased plant automation permits a reduction in the _ibtJJE__.
IVEL
manpower required per MW produced.
Figure 1.59 depicts the typical breakdown of lifetime
generation costs. Fuel costs form the largest element,
such that a 1% improvement in efficiency of the
plant is equivalent to a saving of approximately 2% COOLING
WATER CIRCULATING
of the Capital cost. PUMP

FIG. 1.60 A once-through (coastal) CW system

The task is to optimise the overall design so as


to minimise the lifetime generation costs. This means
minimising the capital and running costs over the
lifetime of the plant. The capital costs usually con-
sidered for a direct cooled system are:

The capital cost of the turbine and of the build-


ing to house it (this will vary if longer last-stage
blades or a different number of turbine cylinders
are chosen).
The capital cost of the CW culvert system (this will
vary with CW flow).
The capital cost of the CW pump (rated to suit the
CW flow).
The capital cost of the condenser surface (an indepen-
FIG. 1.59 Lifetime costs of a turbine-generator unit dent variable, subject to constraints).
42
Economies of the steam cycle

The running costs are: A site study is undertaken to obtain the tempera-
ture of the water source over a period of a year, so
The cost of additional pumping power (this will that an estimate of the average annual CW inlet
vary with CW flow). temperature can be made. The specific heat and den-
sity of the water are also measured.
The cost of a small change in turbine efficiency. Using these fixed parameters, the heat transfer cal-
culations can be made. As well as the effect of the
exhaust pressure on output and heat rate, there are
Plant operating and maintenance costs are ignored other variables needing optimisation. Increasing the
unless there are exceptional circumstances. number of tubes in the condenser, for a given CW flow
It is clear that there are many variables to be rate, results in a reduction in CW velocity, and hence
considered and it is therefore necessary to fix certain a reduction in friction losses and pumping power
turbine design parameters (the number and area of costs. However, low CW velocity needs a larger heat
the LP exhausts) so that the characteristic relation- transfer surface, which could be achieved by increas-
ship between the power output and exhaust pressure ing the length of the condenser tubes. This is not
can be maintained. With the turbine exhaust design possible because, as stated earlier, the length of the
fixed, constraints are automatically imposed on the tubes is usually constrained.
size of the condenser. Increasing condenser outlet temperature reduces
The condenser surface can vary in two ways: the mass flow of CW but increases the turbine ex-
Increasing the number of tubes (and adjusting the haust pressure, resulting in a rise in heat rate, a fall
flow to give the same velocity). in power and therefore a drop in efficiency.
Figure 1.62 shows the results from the heat trans-
Increasing the length of the tubes. fer calculations. Lines of constant CW velocity and
turbine exhaust pressure are displayed. If we consider
increasing the condenser tube surface area by increas-
Having fixed the turbine design, for a typical trans- ing the number of tubes, then as discussed above,
verse under slung condenser, the maximum tube length at constant CW flow, both CW velocity and turbine
will also be fixed (Fig 1.61). The condenser tube sur- exhaust pressure decrease. The effect on output of the
face area can only be changed by varying the number changing exhaust pressure, may be determined from
of tubes used up to limits imposed by the available the output/exhaust pressure characteristic (Fig 1.58).
height. Since these are basically heat transfer calcula-
tions, the condenser tube materials, diameter and
thicknesses must all be fixed according to the prin-
ciples set out in Chapter 4.

TUBE LENGTH
FIXED

37500-^

COOLING WATER FLOW RATE kg/s

FlG. 1.62 Relationship between heat transfer parameters

It is customary to consider a reference or nominal


design having a given surface area and CW flow rate,
and to compute the change in cost from the reference.
The effect of the variables on the following economic
FIG. 1.61 Transverse underslung condenser data can now be considered:
43
The steam turbine Chapter 1

Increments of CW flow will affect CW pump costs. quite possible that these will not be used, because
there are further constraints on the design yet to be
Increments of CW flow will affect CW system costs. considered.
The most significant constraints, after the turbine
Increments of condenser surface will affect con-
exhaust area and condenser length previously men-
denser costs.
tioned, are the limits on CW velocity. There is a
Changes in output will affect the running costs. maximum velocity permissible to prevent tube erosion
and a minimum velocity to avoid silting. Environ-
Increments of CW flow and head will affect the mental considerations enforce a limit on the maximum
consumed CW pump power and will therefore af- temperature of the CW discharge into the river or sea
fect the running costs. so that fishing is not affected.
The exercise can be repeated with one of the fixed
parameters changed to a new value. In this way, the
If the individual costs are calculated for the grid of change in costs using different exhaust annulus areas
points on Fig 1.62 and then summated to give the can be found. A similar analysis can be undertaken for
total cost at each point, we can plot contours of a tower-cooled system, where CW is cycled between
constant cost, as shown in Fig 1.63. the condenser (where it receives heat from the steam),
Computer programs have been devised which will and the cooling tower where it transfers the heat to
evaluate the best design combination of parameters the rising air. (For a full explanation of the 'indirect
for minimum total cost and Fig 1.63 is a typical cooling' system see Chapter 4.)
graphical output. From Fig 1.63 it can be seen that The economic optimisation calculations are based
the smaller the contour, the lower the total cost. The on a constant CW inlet temperature and the assump-
most economic design parameters therefore exist at tion that all the condenser tubes will be available. In
the centre of the smallest contour. It is, however, reality, the seasonal changes in temperature in the

o 50000

w 47500

COOLING WATER FLOW RATE, kg/s

FIG. 1.63 Effect of cost

44
Economies of the steam cycle

UK produce a range of CW inlet temperature of be shown by comparing the heat rate (kJ/kWh) of
between 5-17C, corresponding to a variation from modern large capacity turbine-generator plant, in-
the ideal turbine exhaust pressure of 15 mbar. This volving seven stages of heating, with a hypothetical
could be responsible for a change in turbine efficiency plant of equivalent electrical generating capacity, but
of around 0.7%. without feedheating plant. The comparison is made
It cannot be assumed, either, that all the condenser with the assumptions that the cylinders of a multi-
tubes will be operational throughout the lifetime of cylinder tandem turbine have the capacity to pass
the condenser. Material too small to be trapped by the total quantity of steam supplied by the boiler,
the screens may build up in the tubes, restrict the that the exhaust pressure is identical, that the 'leav-
flow and eventually block it entirely (known as fouling). ing loss' is identical and that the condensate from
The problem can be alleviated either by regular main- the turbine condensers is pumped, as feedwater to
tenance or through the provision of automatic cleaning the boiler, at a typical condensate temperature of
by circulating foam rubber balls that clean away the 35C (for a temperate climate plant).
dirt and scale formation. The effects of erosion at The difference in 'heat rate' of the two turbine
the higher velocities can be practically eliminated by plants is found to be significant, the heat rate of the
the use of hard materials such as Titanium for the plant equipped with the seven-stage regenerative plant
condenser tubes. Changes in tube material and in being only 0.86 of the hypothetical plant of equivalent
fouling factor, are evaluated during the design to capacity but without feedheating plant.
confirm the most economic choice for the full range A full treatment of the economic benefit of the
of operating conditions. turbine plant with feedheating would involve consi-
deration of a boiler plant designed for a high feed-
water temperature and a hypothetical boiler design
suitable for feedwater delivered to it at condenser
temperature, but the figure 0.86 provides a good
4.2 Regenerative feedheating measure of the improvement wrought by bled-steam-
The principle of 'preheating' boiler feedwater before heated feedwater plant and of its benefit in terms
its admission to a boiler was well established before of reduced fuel consumption.
the turn of the century. The expression 'regenerative'
implies that latent heat in steam, or sensible heat in
boiler flue gases, is captured, reclaimed and set to 4.2.1 Feedheating plant stages superheat
work again in the fluid cycle. cycles
Early examples of feedheating involved the dis-
The optimum number of feedheating stages, in strict
charge of exhaust steam into the tanks from which
terms of cycle efficiency, could be as high as the
the feed pumps draw their water and the use of
number of steam expansion stages in the associated
'economised, which captured heat from flue gas and
turbine cylinders. But it is not practical, in engineer-
led to economy in the use of fuel.
ing terms, to provide steam extraction points at each
The practice of preheating the boiler feedwater has stage in the cylinders, because of the casting/casing
contributed as much to efficiency improvements as
complexity that would arise and the additional and
any other single development in steam power plant.
excessive length of the complete turbine, with cor-
In this section 'regenerative' feedwater heating plant
respondingly long rotors.
using steam extracted from the turbine is covered;
As with most engineering designs, a compromise
feedheating plant involving the 'conomiser' is dis-
cussed and described in Volume B. between the academic optimum design and a design
which is practical; producible and commercially viable
From the early days of utilising latent heat from
is necessary.
the exhaust steam from steam engines and small tur-
The type of power plant with which the turbine
bines to preheat feedwater, the principle of feedwater
plant is associated also influences the number of feed-
heating has been progressively widened; modern plant
heating stages because the steam-raising plant eco-
is very sophisticated, involving multiple steam ex-
tractions from steam turbine cylinders, LP heaters, nomics interact with the turbine plant.
combined heating/de-aerating plant, HP heaters, LP For electricity generation in the UK, the following
drains pumps, HP drains pumps, pressure cascading steam-raising plant sources have featured in recent
of drains and the incorporation of other plant, such years:
as moisture separator/reheaters, which are used in
wet steam cycles. Coal-fired.
The academic treatment of regeneratve feedwater Oil-fired.
heating and its place within the cycle was covered
in Section 3.1 of this chapter and illustrated by Advanced gas-cooled reactors (AGRs).
Rankine cycle diagrams. The impact of feedwater
heating plant upon the turbine cycle efficiency can Pressurised water reactors (PWRs).
45
The steam turbine Chapter 1

Coal-fired and oil-fired plants yield similar numbers slightly different systems, such as either one or two
of feedheating stages as optimum, about three LP extraction points on a boiler feed pump turbine, with
stages, a heating/de-aerating stage and two HP stages, a corresponding number of HP feedwater heaters,
leading to a final feedwater temperature of about depending on their manufacturing costs and their
250C. relationship to the then prevailing worth of cycle
An optimisation technique is used to determine efficiency. The final HP feedwater heater has, in every
the number of feedwater heaters, with practicalities case, used steam exhausted from the HP cylinder of
still dominating. the main turbine (i.e., the same point in the cycle as
In a world of changing economics in the field of the supply to the feed pump turbine).
fuel supply, an upset in prices, upward or downward, For large capacity plant, HP feedwater heaters of
such as experienced with oil supply prices can lead the 'tubeplate' type (as illustrated later in Fig 1.69),
to a significant difference in turbine and turbine plant cannot be made sufficiently large to perform the
configuration. It is necessary at the inception of a entire feedheating plant stage duty because of manu-
power station project to revalue cycle efficiency in facturing limitations. These limitations involve tube
the light of prevailing fuel prices and best predictions. plate diameter and thickness and tube hole drilling
AGR plants are found to be most economic with a length.
moderate final feedwater temperature of about 150C. The provision of heaters in pairs has proved ne-
This is because the lower temperature produces a cessary at each heating stage to permit the stage duty
wider 'approach temperature' to the reactor coolant to be performed. Each 'line' (or bank, or 'string')
gas, and a greater log mean temperature difference' of heaters can be by-passed in the event of a fault
(LMTD) for the steam generators associated with the to permit continuity of feedwater flow to the boiler.
reactor. This wider LMTD, produced by the feed- The heat transfer surface area for heaters (of all
water temperature of 150C, is beneficial in that the types), and therefore the overall size of the heater,
steam generators, encompassed within the concrete is carefully optimised. The optimisation involves manu-
pressure vessel with the reactor, can be smaller, so facturing cost versus the lifetime value of efficiency
the pressure vessel is smaller and lower in capital based on fuel cost and the predicted utilisation for
cost. the type of plant.
The final feedwater temperature is 'optimised' For relatively high fuel cost applications, an ad-
i.e., the value of cycle efficiency, costed at a rate ditional heat transfer section is incorporated in heaters
appropriate to the use of nuclear fuel over the life as a 'drains cooling9 section. The condensate of the
of the plant, is related to the capital cost variations heating steam is cooled to a temperature lower than
of steam generators, etc. The lowest sum of lifetime saturation temperature by the ingoing feedwater, there-
operating cost and capital cost determines the op- by increasing the effectiveness of the heater in the
timum design, which includes the corresponding final cycle.
feedwater temperature as a design parameter. Further features of feedheating plant and suitable
The outcome of this AGR plant optimisation is for any type of main plant are those of 'pressure
that three LP feedwater heaters are used, in con- cascading9 and 'drains pumping9. Heating steam, after
junction with a fourth combined heating and de- being condensed in a heater, is led, as drains, to a
aerating stage, to provide a final feedwater temperature lower pressure heater where it 'flashes-off and sur-
of about 150C to the complete exclusion of HP renders part of its remaining heat to the lower pressure
feedwater heaters. The boiler feed pumps draw their heater. This principle can be applied to all heaters
supply of water from an elevated tank, forming the in a bank as a 'cascade'.
combined heating and de-aerating stage, and deliver Drains pumping involves collecting drains after
the water directly to the 'conomiser' section of the cascading and pumping them back into the condensate
reactor steam generators. feed system at a point that closely corresponds to
Economic systems evolved during the past two their temperature. Figure 1.65 illustrates both cascad-
decades for both fossil-fired and AGR plants involved ing and pumping for the two LP heaters.
'back-pressure turbines' (driving the boiler feed pump),
with one or two steam extraction points for HP feed-
water heaters.
4.2.2 Feedheating plant stages wet steam
The driving steam for the boiler feed pump turbine
cycle
is taken from the exhaust of the HP cylinder of the
main turbine, and is therefore steam which has been A PWR station is now under construction in the UK,
expanded and has lost part of its superheat (Fig 1.64). based upon a standard design for large capacity plant
Steam extracted from the boiler feed pump turbine (1200, 1300 MW). This design, designated 'Standard
is therefore relatively low in superheat and the heat Nuclear Unit Power Plant System' has a feedheating
to be surrendered to the feedwater is mainly the latent plant involving LP heaters, a de-aerator /heater and
heat which is beneficial to cycle efficiency. HP heaters but with certain variations arising from
Various main plant manufacturers have evolved the wet steam cycle of the PWR.
46
TWO ELECTRICALLY DRIVEN [3_
BOILER FEED PUMPS
MAIN STEAM SUPPLY
REHEAT/BLED STEAM
FEEDWATER/CONDENSATE
HP HEATERS DRAINS
LP HEATERS

FIG. 1.64 Cycle diagram incorporating a boiler feed pump turbine

47
Economics of the steam cycle
The steam turbine Chapter 1

Steam admitted to the HP cylinder of the turbine is recovered and introduced into the HP feedwater
is at a dry saturated condition, i.e., without superheat. heaters at appropriate temperature points in the cycle.
On expansion through the cylinder, the steam be- The PWR steam generators have a continuous
comes wet. The water fraction is removed in a passive Slowdown* system to limit the concentration of slight
Moisture separator' and the water and its heat is impurities in the steam generators. The Slowdown'
reclaimed and pumped into the feedheating system at water, at a temperature approximating to boiler satura-
the de-aerator (where separator water temperature tion temperature, is passed through a heat exchanger
and de-aerator temperature coincide) for maximum incorporated in the LP feedheating plant upstream of
efficiency (Fig. 1.65). The dried steam is then passed the de-aerator/heater, where the heat is recovered.
through two-stage reheaters for superheating, steam Condensate, formed from bled-steam extracted from
being the heating medium. Steam bled from the HP the LP turbines and supplied to LP feedwater heaters,
cylinder is used in the primary reheater and live steam is collected in a drains receiver and pumped into the
(i.e., at boiler conditions) is used in the secondary de-aerator/heater tank for recovery of both condensate
reheater. Condensate formed from the reheating steam and heat.

BLED STEAM LIVE STEAM


REHEATER REHEATER
(BSR) (LSR)

GENERATOR

TCONDENSATE
EXTRACTION
PUMP

GLAND
STEAM
CONDENSER

tNj3tNj3N^-
HP HEATERS
HEATER
DRAINS PUMP

MAIN STEAM SUPPLY


REHEAT/BLED STEAM
. FEEDWATER/CONDENSATE
DRAINS

FIG. 1.65 Simplified feedwater heater arrangement for a PWR

48
Economies of the steam cycle

The cycle involves four stages of LP feedheating, of typically 5 % (of oxygen) per kg (of water), i.e.,
the de-aerator/heater and three stages of HP feed- five parts per billion.
heating, with an ultimate heater utilising condensate Design practice has been to install high level plant
from the secondary reheater to preheat the feed to in an auxiliary plant annexe between the boiler house
a temperature of 226C before admission to the steam and turbine hall, at a level set by boiler house steel-
generators. work. Provision of generous margins over the steady
state NPSH requirements of suction stage feed pumps
has proved possible.
4.2.3 Feedwater de-aeration Typically, tanks have had a total volume equal to
about ten minutes feedwater flow rate, with an eight
Feedwater chemistry requirements are stringent with
minute store to provide a buffer for transients and time
regard to the permissible level of dissolved oxygen.
to unload the plant should the condenser extraction
The main concern is that of minimising waterside
pumps fail. The mass of water stored is about half a
corrosion of boiler tubes. Waterside corrosion and
tonne per megawatt of plant capacity (i.e., about
fireside corrosion lead to thinning of tube walls and
330 t for current 660 MW plant).
the subsequent risk of rupture by the internal fluid
pressure. In summary, this type of combined plant, which
is described in detail in Chapter 3, fulfils important
A significant feature of British designed feedheating
plant has been the combined 'feedheating/de-aerating/ primary functions:
water storage plant'. This is illustrated in Fig 1.64
which shows the position of the de-aerating/feedheating It serves as a feedwater heater.
plant within typical turbine plant and Fig 1.66 is a Feedwater is de-aerated down to the necessary low
simple illustration of a typical high level de-aerating/ gas content.
feedheating plant.
Feedwater from LP feedheaters is admitted to the It acts as a 'buffer' to the fluctuations of condensate
twin towers on the tank. Steam, typically bled either feedwater flow that occur in service.
from the main turbine or boiler feed pump turbine,
or taken from the feed pump turbine exhaust, is sup- The tank height provides a hydrostatic head to satisfy
plied for heating and de-aerating the ingoing feed- the suction pressure requirements of the boiler feed
water. Feedwater, de-aerated to a boiler quality standard pumps.

VENT
CONDENSER

STORAGE VESSEL

U S
FTT^L

CONDENSATE TO FEED PUMPS


INLET

FIG. 1.66 Typical high level de-aerator/feedheater

49
The steam turbine Chapter 1

Reliable and effective service over several decades has British practice for the steam supply to the boiler
been obtained from plant of the designs described, feed pump turbine has been, as explained earlier, to
but changing economics and competitiveness have now use steam partly expanded through and exhausted from
led to a change in design. the HP cylinder of the main turbine (sometimes known
The design illustrated in Fig 1.67 involves the as 'cold reheat steam'). This steam, after further ex-
direct injection of steam into the body of stored pansion through the boiler feed pump turbine, contains
water through a series of vertical perforated tubes only a modest amount of superheat and this exhaust
immersed in the water, and the admission of con- steam is used to supply the combined feedheating/
densate through self-regulating sprays. The condensate de-aerating plant.
is heated almost to saturation temperature; steam Because the steam requirement of the boiler feed
rises through the water and gases are liberated and pump turbine cannot be exactly matched to the
conducted away through small vents adjacent to the steam requirement of the feedheating/de-aerating plant
sprays. throughout the load range, arrangements are necessary
The water passes at low velocity through the tank to pass any excess steam, or to supply any steam
at a rate corresponding to the plant load and is deficiency from another part of the cycle.
almost at saturation temperature. The remaining dis- An effective means of accomplishing these require-
solved gases are liberated: they rise to the surface ments is to design the boiler feed pump to exhaust at
and steam space and are then conducted away through a pressure approximately equal to the pressure of the
small vents, the water being brought up to saturation main turbine IP cylinder exhaust. This exhaust steam
temperature by the injected steam. This design and is supplied to the LP cylinders and the boiler feed
its function are covered fully in Chapter 3. pump turbine exhaust, the heater/de-aerator and the
For thermodynamic economy, the bled-steam used main turbine IP/LP crossover pipes are connected
in the de-aerator should ideally be without superheat together.
the use of superheat is a wasteful way of heating water The steam pipework is arranged so that, during
when it could be more effectively used by being con- plant operation, the feed pump turbine exhaust steam
verted to mechanical work in a turbine. is preferentially used by the heater/de-aerator, with

CONDENSATE

STEAM DISTRIBUTION P I P E S -
PERFORATED TO ALLOW DISCHARGE OF STEAM
BELOW WATER LEVEL

DETAIL OF PERFORATIONS

FIG. 1.67 Waterspray/steam injection-type de-aerator

50
Economies of the steam cycle

any excess being 'spilt' into the crossover pipe. If a for heating the condensate, with consequential im-
steam deficiency exists, that deficiency is supplied provement in cycle efficiency. Bled-steam valves are
from the IP/LP crossover, at the same pressure but omitted both the traditional isolating valve and
with greater superheat. the non-return valve. It has been established by ex-
This configuration, where the heater/de-aerator 'floats' periment and experience that steam reflux on turbine
on the boiler feed pump turbine exhaust and the trip, when the stage pressure collapses to condenser
IP/LP crossover interconnected piping, has proved pressure, is negligible and hence there is no significant
very successful. If the feed pump turbine is unavail- contribution to rotor overspeed.
able and standby electric pumps are used, the heater/ With the heaters being almost completely within the
de-aerator can be supplied entirely from the IP/LP condenser 'neck', there is economy in turbine hall area
crossover and operation can continue unimpaired. Such and in the elimination of supporting steelwork, access
'flexibility' of operation is advantageous and removes ladders and platforms.
the 'interdependence' of one plant item upon another. The omission of an isolating steam valve prompted
For plants involving a steam turbine drive for the the development of improved methods of prevent-
feed pump, the economic benefits and the flexibility ing heater flooding. Neck heaters are equipped with
of the described system are clear. If boiler feed pump valveless primary drains and a valveless secondary
drives are not used, the system described above would drain, the latter being arranged physically a little higher
involve steam supply from the main turbine only. than the primary drain outlet.
External LP heaters, although still of the traditional
form, are now arranged in a horizontal attitude, elevated
4.2.4 Low pressure feedwater heaters so that the bled-steam piping from the turbine falls
Low pressure (LP) feedwater heaters are basically to the heaters, thus assuring drainage. This minimises
simple straightforward 'tube and shell' heat exchangers, the risk of water entering the cylinder and the possi-
with the condensate passing through the tubes and bility of damage by impact on rotating components.
the bled-steam being admitted to the shell. This type The heaters are 'stacked', so that the ultimate
of heater, arranged vertically, has been used for many LP heater can drain its bled-steam condensate into
decades, but two advances worthy of note have been the next heater, and that heater can drain its con-
made in recent years and are now treated as modern densate into the condenser above the working level
practice. of condensate in its base.
With the turbine exhaust being connected to its
underslung condenser by a large, deep, transition piece, 4.2.5 High pressure feedwater heaters
a significant volume of unused space exists between High pressure (HP) feedwater heaters are also gen-
the exhausts of a double-flow cylinder and above erally of traditional form, but are arranged in a
the condenser tubenests (see Fig 1.68). This space can horizontal attitude to ensure free gravity drainage of
be effectively utilised by inserting one or two LP their bled-steam lines and heater-to-heater drainage.
feedwater heaters in a horizontal attitude. The arrangement of internal components is revised
A number of advantages accrue from such an to provide a drains cooling section, involving a part-
installation. The bled steam piping is short in length, length of some of the bottom tubes (of the inlet
giving a cost saving and a lower pressure drop, the section of the tube bundle) instead of a part-length of
lower drop resulting in a slightly higher temperature all tubes in a vertical heater (Fig 1.69).

DRAINSTODRAIN COOLER

DRAINS FROM LP2 DRAINS FROM LP2 TO LP1

O - OVERFLOW DRAIN USED WHEN DRAINS FLOW IS ABOVE LEVEL OF NORMAL DRAIN OUTLET
N - NORMAL DRAIN

FIG. 1.68 Arrangement of condenser with an LP heater in the neck

51
52
The steam turbine

(b) Desuperheating section

DIP TUBES
(d) Part section of heater

(c) Drain cooling section PRESSURE RELIEF VALVE OUTLET FLANGE TUBENEST
AIR VENT
BLED STEAM CONDENSING SECTION
SIGHT GLASS ISOLATOR
AIR VENT
STANDPIPE ISOLATOR

WATER LEVEL STANDPIPES & 'B'

STEAM INLET DIFFUSER


BLED STEAM INLET
DESUPERHEATING SECTION
TUBEPLATE LIFTING TRUNNION

FEEDWATER OUTLET \ STAY ROD


LIFTING EYE
\ SLIDING FOOT
LEVEL SETTING SCREW
BAFFLE PLATE
DIVIDING PLATES HORIZONTAL & SIDE BAFFLES
INSPECTION COVER
CONDENSING SECTION MAIN SUPPORT
HIGH WATER LEVEL SWITCH
WATERBOX MANHOLE
DOOR SIGHT GLASS ASSEMBLY
SIGHT GLASS DRAIN
- AIR SUCTION DRAIN COOLING SECTION (a) Cutaway perspective
-j STEAM LEVEL CONTROL TAPPING of complete heater
DIVIDING BAFFLE DRAIN COOLING INLET POT
FEEDWATER MAIN SHELL DRAIN
CONDENSATE FIXED FOOT
DRAIN COOLING SECTION TOP PLATE
FEEDWATER INLET \ DRAIN COOLING INLET POT
SHELL START-UP DRAIN
DRAIN COOLING SECTION OUTLET VENT
CONDENSING SECTION OUTLET VENT

FIG. 1.69 Arrangement of a tubeplate-type horizontal HP heater


Chapter 1
Economies of the steam cycle

A variation on the traditional design of HP heater areas and increased unit rating, serve to reduce capital
with its thick hemispherical pressure head, tubeplate and operating costs and are therefore beneficial to
and steam shell, is a design based on boiler tech- the consumers.
nology in which inlet/outlet headers and serpentine
tubes are all contained within a steam shell, as il-
lustrated in Fig 1.70.
The pressure parts associated with such a design, 4.3 Choice of feed pump and drive system
known as a 'header' type heater are smaller (relative to
the thick walls of a hemi-head and tubeplate heater) A full description of feed pump design and develop-
and are more amenable to temperature changes as a ment is given in Chapter 3. In this section, feed
consequence of load change than the traditional type pump size, number, duty, margins and the need for
of heater. Furthermore, it can be made in larger variable-speed are discussed; comparisons on economic
capacities than the traditional design. For large unit grounds are also made between steam turbine and
sizes, a single line of 'header' type HP heaters could electric-motor drives, and between variable-speed motor
be used instead of a double line of hemi-head/ tubeplate (VSM) and induction motor/fluid coupling drives.
heaters, which may yield space and cost savings, The section is concluded with a typical example of
depending on suppliers' specific designs and manu- an overall comparison of through-life costs of four
facturing costs. feed-pump system options, that was performed for a
future 900 MW turbine-generator unit.
Boiler feed pumps now being designed for future
4.2.6 Summary large units are tandem arrangements, i.e., the slow-
In summary, in the field of feedwater heating, there speed booster pump (suction stage pump) is driven
have been a number of changes in recent years but in tandem with the main pressure stage pump, using
these have been of an evolutionary, not a revolutionary, either a step-up gearbox (to the high speed pressure
nature. The first two stages of LP feedheating are stage) or a reduction gearbox (to the suction stage),
incorporated in the 'neck' of the condenser, with the depending on the speed of the driving motor or steam
external LP stages being arranged in a horizontal turbine.
attitude below the LP turbines. The position of the feed pumps in the steam cycle
Combined de-aerating/feedheating plant is now of of a modern turbine-generator unit was shown in
the 'steam-injection' type and more compact than Fig 1.65 (in this case for a PWR unit) physically they
hitherto. HP feedwater heaters are arranged in a are situated beneath the de-aerator, upstream of the
horizontal attitude below the turbine cylinders. The HP heaters.
feedwater is now raised to a higher temperature by
the extraction of steam from the HP cylinder. For
large capacity plants the use of 'header' type heaters 4.3.1 Feed pump size and number
may permit space and cost savings to be made which, The choice of feed pump size and number is based
in conjunction with improvements in other plant upon the principle of ensuring that full turbine-

FEEDWATER ^
INLET ^

FEEDWATER ^
OUTLET W

DRAIN COOLING CONDENSING


SECTION SECTION

FIG 1.70 Arrangement of a header-type horizontal HP heater

53
The steam turbine Chapter 1

generator unit output can be maintained with the


loss of one main duty feed pump. This ensures 140
maximum plant availability.
For the majority of 500 and 660 MW units, the
most economic solution has been a 100% duty steam
turbine-driven feed pump with two x 50% electric
motor-driven start/standby sets (higher capital costs
but lower running costs than all-electric pumps).
The situation is now changing for units over 660
MW in that the saving in capital costs of having
150% (three x 50%) feed pump capacity compared
with 200%, begins to outweigh the increased com-
plication of having two pumps running in parallel
for full-load operation. Other advantages of having 'DESIGN
QUANTITIES
three identical 50% duty pumps include reduced 60 J
APPROXIMATE PRESSURE IN BOILER AFTER SIX HOURS SHUTDOWN
spares holdings, quicker maintenance, modular con- I
I
struction with a more compact layout occupying less I
I
station floorspace, and less complex and expensive 40 I
I
1
pipework. 0 20 40 60
FLOW, % OF TURBINE CMR FLOW
80 100 120

Feed pump size has more recently been influenced


by two other factors:
FIG. 1.71 Boiler feed pump and system characteristics

International market appeal 50% duty pumps


for large (over 660 MW) units have the greatest
worldwide market potential, whereas 100% duty
pumps would require new pumps to be designed that the boiler is designed, and also to allow for a
that have very little export potential. deterioration of plant capability in service. In addi-
tion to the effect of the boiler margin, the boiler
The choice of feed pump driver influences, to a feed pump is designed to produce a rather higher
certain extent, the pump size for example, the feedwater flow than that needed by the normal boiler
current international trend to electric motors and design condition. This is intended to cope with pump
50% duty pumps means that no variable-speed wear and transient conditions, and to act as an op-
motors or couplings large enough for 100% duty erational margin.
have yet been developed. At the value of feed flow corresponding to the
turbine design quantity, the head produced by the
pump is in excess of that required to pump the water
4.3.2 Feed pump duty, margins, and the need to the boiler. This excess pressure can be minimised
for variable speed if the pump can be driven at reduced speed: if this
The duty of the boiler feed pump as determined by is not possible the excess pressure has to be broken
the boiler and turbine pressure flow conditions, is down across the feedwater regulating valve. As can
given by Fig 1.71. Shown on the diagram are the be seen from Fig 1.71, at low values of feed flow,
boiler feed-pump characteristics, i.e., the relation- the excess of head produced by the pump over the
ships between the head produced by the boiler feed system resistance head is considerable. On typical
pump corresponding to the particular value of feed British sets of 500 MW and over, variable-speed drive
flow pumped, and the boiler feed pump speed. Various is always adopted because the cost of providing it is
head/flow characteristics corresponding to the operat- much less than the operational and financial losses
ing range of pump speeds are indicated. The curve that would be incurred by this breakdown of pres-
denoted as 'system resistance' is the relationship sure. In addition to this, all conventional plant is
between feedwater flow and the head that has to required to be capable of two-shift operation, i.e.,
be produced by the boiler feed pump to pump the to be shutdown overnight and started in the morning.
feedwater into the boiler. Also shown in the dia- During an overnight shutdown the boiler pressure
gram are the design values of feedwater flow for the falls significantly, such that during the start-up period
turbine plant, boiler plant and the feed pump itself. next morning, the boiler feed pump is only required
It is normal practice to design the boiler to pro- to deliver some 100-200 bar instead of the approxi-
duce a higher rate of steam generation than that mate 230 bar closed-valve full-speed pressure of the
appropriate to the value used in the turbine-generator pump. For this reason, the pump that is used during
design. This margin is normally about 5% and is the start-up period should have a speed range down
intended to cover application variations (e.g., site to approximately 70% full speed to avoid excessive
conditions such as available cooling water) at the time wear on the feedwater regulating valve.
54
Economies of the steam cycle

As the power requirement of a boiler feed pump provision necessary for 50% electric feed pumps, which
for a typical 500 MW unit is approximately 10 MW, includes equivalent bled-steam pipework for the HP
it can be seen that the choice of an economic and heater alone, plus electric motors (including reinforce-
technically acceptable variable-speed boiler feed pump ment of the station electrical system to cope with the
drive is a decision of major importance. The possible high motor-starting currents). Also, the first option
types of boiler feed pump variable-speed drives which usually includes a live steam connection direct from
have been considered by the CEGB for use on large the boiler to the feed pump turbine for operational
generating units are: flexibility, even though the electric pumps are often
used for starting. The live steam pipework is expensive,
Fixed-speed electric motor with variable-speed due to its high pressure duty.
coupling. There is usually no extra capital cost attributable
to the required increase in rating of the main IP/LP
Converter-fed variable-speed (electric) motor (VSM).
turbines and the generator needed to supply the extra
Back pressure steam turbine. power for electric motor-driven feed pumps, since it
requires only a marginal increase in steam flow (3%)
Condensing steam turbine. of the main unit.
With all-electric feed pumps, the system is more
compact (less floorspace) and simpler, needing fewer
In addition to these choices, the option of slipring spares holdings. Because the pumps are freed from
induction motor, regulated by resistance in the rotor the constraints of steam pipework they can be placed
circuit, has been considered and used in the past. in the ideal position for NPSH considerations, on
This relatively cheap and simple solution, using large the basement floor (instead of a few metres above
liquid rheostats with mechanically-movable tapping it to accommodate the steam inlet pipework below
points, has proved unreliable in practice, with a high the pumps) directly beneath the de-aerator (NPSH is
maintenance burden. defined in Chapter 4 and de-aerator height, etc., is
Variable-speed electric motors and condensing steam discussed in Chapter 3). These factors can lead to
turbines have only recently become viable options savings in capital costs for the de-aerator and its
(for future units over 900 MW) due to the trend to civil engineering costs and the feed pump suction
slower (6000 r/min or less) 'International Class' boiler pipework between the de-aerator and the pump.
feed pumps, to limit erosion and cavitation in the
pump, to the NPSH required and de-aerator height,
etc. These two types of drive are not feasible for
use with the higher speed 'Advanced Class' pumps Running costs
used on 500 and 660 MW units so far, due to con- A steady state model of the thermal performance of
verter size limitations and blade vibration and stressing the turbine and feedheating/pumping plant can be
difficulties. incorporated in a computer simulation program. Such
A technical description of electric motor drives a program can then be used to compare overall cy-
(variable-speed, induction, synchronous, etc.) for feed cle efficiencies (it calculates the cycle heat rate) for
pumps is given in Volume D. A description of the different input data and can be used to compare the
use of steam turbines for driving feed pumps can thermodynamic effects on the overall cycle of steam
be found in Section 9 of this chapter. turbine-driven and electric motor-driven feed pumps.
Figure 1.72 illustrates these thermodynamic effects
graphically for a fixed 900 MW sent-out (SO) unit
4.3.3 Economic comparison of steam turbine with a fixed main turbine exhaust area and pressure,
drives with electric motor drives for 50% feed pumps. Also shown, is an example
calculation to determine the additional work done
in the main turbine due to changing from a back-
Capital costs pressure feed-pump-turbine drive to an electric-motor
On the majority of 500 and 660 MW units, a variable- drive. This calculation is continued in Fig 1.73, where
speed drive to the 100% duty feed pump is provided the additional work done in the main turbine due to
by a back pressure steam turbine, using bled-steam not having steam turbine driven pumps is compared
from the main turbine HP cylinder exhaust and ex- with the electrical power used (and associated gen-
hausting to the main IP/LP crossover. Bled-steam erator, transformer, cabling, motor, gears and converter
tappings on the feed pump turbine itself have been or fluid-coupling losses) to drive the motor-driven
used in the past to supply steam to one or more pumps. It can be seen that in this case, which is for
stages of HP feedheaters. a back-pressure feed pump turbine with no bled-
For large modern units (over 660 MW), the capital steam tappings to HP heaters (for a future 900 MW
costs of the extra bled-steam pipework and the boiler unit), there is a unit heat rate improvement with
feed pump turbine are significantly greater than the electric motor-driven feed pumps.

55
The steam turbine Chapter 1

BACK PRESSURE BFP TURBINE MOTOR DRIVEN FEED PUMPS


2x50% FEED PUMPS 2x50% FEED PUMPS

3588.2

3500J 3500

3000 3000

I
<
I

o
LU
CL

2500' 1-2500

2000 2000
7.4 7.6 6.4 6.6
SPECIFIC ENTROPY, kJ/kgK

A ADDITIONAL HEAT SUPPLIED IN REHEATER


=62.9(3588.2-3123.2) = 29.24MW = 1.49% TOTAL HEAT SUPPLIED
B ADDITIONAL WORK DONE IN IP TURBINE
=62.9(3588.2 - 2973.5) = 38.65MW = 4.29% TOTAL POWER OUTPUT
C ADDITIONAL WORK DONE IN LP TURBINE
(DUE TO DIVERGENT CONSTANT PRESSURE LINES)
=62.9(765.4 - 689.8) x 0.852 = 4.44MW = 0.48% TOTAL POWER OUTPUT
(DUE TO REDUCED WETNESS LOSS) = 0.22% TOTAL POWER OUTPUT

MW TOTAL
HEAT SUPPLIED
MW GENERATED MW SENT OUT (BOILER & REHEATER) kg/s TSV
BASIS:
1 BACK PRESSURE BFPT 900 900 1962.4 772.0
2 INDUCTION MOTOR 925 900 1954.2 757.5
3 VARIABLE SPEED MOTOR 923.5 900 1951.0 756.3

FIG. 1.72 Thermodynamic effects of the change to motor-driven feed pumps

The back pressure turbine option considered above problems have occurred with this type of system.
has no bled-steam tappings for HP heaters because Overseas electricity utilities have tended to use con-
it has been found that, in practice, the improvement densing turbines with their slower 'International Class'
they give to the overall cycle efficiency can be offset pumps because they can give a better overall steam
by the effect of the main boiler feed pump availability cycle efficiency (heat rate). Steam is usually extracted
on HP heater availability. Also, feed system stability from the main turbine IP cylinder exhaust instead of
56
Economies of the steam cycle

CHANGES DUE TO USE OF MOTOR DRIVE


(expressed as % of unit (Sent Out) output or total heat supplied)

FIGURES FOR VARIABLE SPEED MOTORS IN BRACKETS WHERE DIFFERENT


(50% DUTY PUMPS)

ADDITIONAL HEAT SUPPLIED !N REHEATER = 1.49% ADDITIONAL WORK DONE IN IP TURBINE = 4.29%
ADDITIONAL POWER REQUIRED = 2.60% ADDITIONAL WORK DONE IN LP TURBINE.
DUE TO DIVERGENT CONSTANT PRESSURE LINES = 0.48%
BY FEED PUMP
DUE TO LOWER WETNESS LOSS = 0.22%
LOSSES ASSOCIATED WITH MOTOR DRIVE:

ADDITIONAL GENERATOR LOSS = 0.04% (0.04%)


TRANSFORMER = 0.01% (0.01%)
CABLING = 0.05% (0.05%)
MOTOR (& INVERTER) = 0.09% (0.13%)
GEARBOX/FLUID COUPLING = 0.20% (0.00%)
= 0.39% (0.23%)

DETERIORATION IN HEAT RATE = 4.48% (4.32%) IMPROVEMENT IN HEAT RATE : 4.99%

NET HEAT RATE IMPROVEMENT = 4.99 - 4.48 = 0.51% (INDUCTION MOTORS)


4.99 - 4.32 = 0.67% (VARIABLE SPEED MOTORS)

FIG. 1.73 Comparison of turbine-driven and motor-driven feed pumps

the HP exhaust, and is therefore a lower grade of speed, has a soft-start capability (only 1.5 times against
heat than that used for the back pressure turbine, 4.5 times full-load current) which solves the station
and the steam is exhausted to the feed pump turbine's electrical system problems.
own condenser or to the main condenser. This has
the advantage of reducing the steam flow (and hence
leaving loss) through the main LP turbine, or of Running costs
reducing its required exhaust area.
In addition to the flow and head margins applied
CEGB operating data demonstrates that feed pumps to the feed pump (and hence to the drive) that have
can achieve the same availability figure regardless of already been described, electric motor drives are cur-
type of driver. Hence the savings in overall CEGB rently required to be able to give their full rated
system running costs from the higher feed pump system output at a minimum electrical system frequency of
availability of a 100% steam and two x 50% electric 49.5 Hz so, at the normal operating condition of
feed pumps, compared with three x 50% electric
50 Hz, there is again a margin to be compensated
feed pumps, are not significant. (Typical feed pump
for, in this case by VSM converter or by fluid cou-
system availabilities would be 99.96% compared with
pling slip. Hence, the normal duty point for the feed
99.92%.)
pump drive has significantly less power output than
its 100% rated output. Figure 1.74 compares the
overall efficiencies of VSM and motors with fluid
4.3.4 Economic comparison of variable-speed couplings, for decreasing pump outputs. Even at the
motor (VSM) drive with induction motor plus normal duty point, the advantage of VSM drive can
fluid-coupling drive clearly be seen, and the difference in efficiency affects
station lifetime costs signficantly. This difference at
the duty point is mainly due to two factors:
Capital costs
Fluid coupling slip it is an inherent feature
At the presently preferred auxiliary electrical system
of fluid-drive designs that there is still some slip
voltage of 11 kV, the direct on-line starting of squirrel-
between the input impeller and output turbine,
cage induction motors for 50% duty feed pumps on
even at their rated output, which creates losses in
large modern units (900 MW and over) would involve
the form of heat in the working fluid (removed
the development of quick-switching techniques not
by oil coolers).
currently available. The squirrel-cage motor and geared
hydraulic coupling gives the minimum first cost, but Gearbox losses VSMs have the same advantage
the direct drive high speed synchronous motor (about as steam turbine drives in that they can drive
6000 r/min), fed from a converter to give variable the high speed (high power) pressure stage pump
57
The steam turbine Chapter 1

the four feed pump options that were the subject


VARIABLE FREQUENCY CONVERTER FED SYNCHRONOUS MOTOR of detailed investigation for a typical future large
coal-fired turbine-generator unit. This histogram sum-
marises the effects of the factors already discussed
REDUCTION IN EFFICIENCY MAINLY
in this section, the main points of which are repeated
DUE TO: FLUID COUPLING SLIP AND
GEARBOX LOSSES below.
From this study, the three x 50% feed pump
option became the only viable one for many reasons,
but mainly because it is the best compromise between
feed pump system availability (no interruption to
full-load output with one feed pump unavailable)
and capital cost. Operations data from CEGB sources
suggests the same level of pumpset availability regard-
less of the type of drive, so for these four options
(all three x 50%) the loss of availability' costs shown
INDUCTION MOTOR PLUS GEARED
on the histogram are all the same.
Repair and maintenance costs are significantly higher
.FLUID COUPLING

for the two options with two steam turbines and one
variable-speed motor (VSM) options (3) and (4)
due to not having three identical pumps (increased
maintenance times and spares holdings), and the fact
that operating data shows that repair and maintenance
RAPID FALL-OFF costs are directly related to capital costs, which are
IN EFFICIENCY DUE TO INCREASED
FLUID COUPLING SLIP higher for the steam options.
Capital costs reflect the higher cost of steam turbines
DUTY POINT and their associated bled-steam pipework, valves, etc.,
h" compared to electric motors, with the condensing steam
RATED OUTPUT, , turbine (option 3) being the most expensive, due to
the larger steam volume and the design problems
FIG. 1.74 Variation of electric motor drive efficiency involved with the last-stage blade. The VSM and con-
with output, for boiler feed pumps verter equipment (option 1) is more expensive than
the simple induction motor with fluid coupling (option
2), but there is more uncertainty in the latter cost due
to the development costs of equipment to cater for the
directly, so that the gearbox (reduction) only has high starting current with existing 11 kV station electrical
to transmit the suction stage power, which is about systems.
20% or less of the total feed pump power. For the Running costs are presented in Fig 1.75 relative to
same gearbox efficiency the actual power lost in the the condensing steam turbine-driven pumps (3) which
gearbox will therefore be up to four times as much was found to be the most efficient option. For turbine-
for an induction motor/fluid coupling pump, where driven pumps, the differential heat rates, calculated
the slow-speed motor has to transmit over 80% of by computer program using data from CEGB refer-
its power to the pressure stage pump through a ence designs, have been used to obtain the equivalent
step-up gearbox (usually incorporated in the fluid lifetime running costs between the turbine and elec-
coupling). trically-driven options. The back pressure turbine option
is based on the most efficient designs but without
bled-steam tappings for HP heaters, to avoid possible
Rapidly increasing slip losses in the fluid coupling feed system stability problems and loss of heater
lead to a much sharper decrease in drive efficiency availability.
than the VSM, for decreasing pump speed (output). For the motor-driven pumps, the lifetime running
Lifetime running costs will increase even further, costs take account of the power input required at the
relative to the VSM, if the fixed-speed motor and pump couplings (calculated for all pumps, whatever
fluid-coupling feed pump has to be run at part-loads the type of driver, using pump efficiencies consistent
for any significant periods of time. with what might be expected for international stand-
ard machines), augmented by efficiency losses in the
drive package, associated cabling, and transformer. The
4.3.5 Example of the results of an overall com- traditional pump head and flow margins (3%/5%)
parison of the through-life costs of four feed and the requirement to be able to produce full out-
pump system options put with a minimum electrical system frequency of
Figure 1.75 shows the capital and running costs of 49.5 Hz ensure that the pump duty point is at a
58
Economies of the steam cycle

(1) 3 x 50% VARIABLE SPEED MOTORS (VSM)


(2) 3 x 50% INDUCTION MOTOR WITH FLUID COUPLING
(3) 2 x 50% CONDENSING STEAM TURBINE + 50% VSM
(4) 2 x 50% BACK-PRESSURE TURBINE + 50% VSM

M COST OF LOSS OF AVAI LABI LITY

I I REPAIRS AND MAINTENANCE COSTS

E551 CAPITAL COST

1 RUNNING COSTS RELATIVE TO OPTION (3)

FIG. 1.75 Ranking of feed pump options

significantly lower load than its rated output. Since 4.4 Turbine by-pass systems
the efficiency of the induction motor with fluid This comprises a pipework system with valves and
coupling falls off with decreasing load much quicker pressure dropping devices to enable live steam from
than the VSM efficiency (due to coupling slip losses the steam raising plant to by-pass the turbine complete-
see Fig 1.74), the through-life running costs of this ly and be dumped into the condenser. The associated
option (2) are greater than for the VSM option (1). control system will open the by-pass according to
An example of how an electric motor-driven feed the specific needs of the plant. The need for a by-pass
pump system can give a better overall steam cycle system and the purposes to which it may be put are
efficiency, i.e., a better heat rate, than a back pressure discussed in this section. The details of its physical
turbine-driven system is shown in Figs 1.72 and 1.73, implementation are discussed in Chapter 2.
which are largely self explanatory. This efficiency The requirement for, and configuration of, by-pass
gain can lead to the improvement in through-life systems are mainly governed by the boiler arrange-
running costs that can be seen on the histogram if ment. The general considerations applicable to fossil-
options (1) and (2) are compared with option (4). fired and AGR superheat cycles are discussed first.
The above conclusions relate to a specific set of The special considerations for PWR wet steam plant,
economic circumstances. Different applications, studied using steam reheat, follow.
against a scenario of changing fuel prices, capital costs
and operating costs may result in different conclusions. 4.4.1 Superheat plant
Nevertheless, these considerations exemplify the need The superheater and reheaters are an integral part of
to analyse not only the capital cost, but also the other the boiler. The basic system for a single reheat turbine
components of lifetime cost in arriving at a solution. is shown in Fig 1.76.

59
The steam turbine Chapter 1

SUPERHEATER GOVERNOR NON-RETURN INTERCEPTOR

-H-wv
VALVE VALVE " VALVE

*-M 1

IP&LP
TURBINES

CONDENSER

-M-
HP BYPASS
VALVE

FIG. 1.76 Basic turbine by-pass system


When on full by-pass, the governor valve and interceptor valve are closed, the steam passes from the superheater
to the HP by-pass valve, then through the reheater and LP by-pass valve. The steam is fully attemperated by
spray water before passing to the condenser. The non-return valve in the HP turbine exhaust prevents a reverse
flow into the turbine. In practice, where a single valve is shown, there are usually two or more parallel
valves performing each duty

The system depicted permits completely independ- can be slowly reduced in load to a low level, ready
ent boiler operation. Although the system operation for reloading when required. If the boiler load is
seems quite straightforward, the function of reducing maintained and the system fault cleared, the unit
the steam pressure from turbine inlet conditions down may be reloaded to a generator load corresponding
to exhaust conditions involves a major change in the to the capacity of the by-pass within a few minutes.
energy available which imposes a heavy duty on the Subsequent loading to full load is then accomplished
components involved. The need to supply a by-pass at the normal rate.
system must therefore be carefully evaluated against If provided for this basic reason, the turbine by-
the benefits. pass system may also provide other benefits, although
The prime reason why UK manufacturers have these are not always significant. A full list of the
supplied by-pass systems for certain applications is other possible benefits are summarised as follows:
to permit continued operation of the boiler and turbine
following a large load reduction or a circuit-breaker For hot starts, following less than a 1 h shutdown,
trip to the house load. In a weakly-connected supply the boiler flow through the by-pass can be adjusted
network, this may be an overriding consideration, to raise the main and reheat steam temperatures
since the ability to run-through such a transient would to the values required by the turbine. When the
allow rapid reconnection of the unit following fault turbine valves are opened, the thermal stresses in
clearance. Without a by-pass, the power mismatch turbine components is minimal. The subsequent
following opening of the circuit-breaker causes the run-up and loading may then be selected to mini-
turbine governing and interceptor valves to close mise either the time to load or the thermal stress,
rapidly. To accommodate the reduction in steam or some compromise between the two.
flow, the boiler firing rate must be rapidly reduced On warm starts, the by-pass may be used to bring
to a minimum. On most boilers, with the possible the main and reheat steam temperatures to a posi-
exception of some oil-fired units, this involves a firing tive mismatch in order to minimise the time to
trip which necessitates a purging operation for several load within available stress margins.
hours prior to reloading. If a by-pass is supplied, a
large proportion of the excess steam can be diverted In general, the by-pass provides for a smooth
through the by-pass system. If necessary, the boiler warm-up of boiler components, including the re-
60
Economies of the steam cycle

heater and the main steam pipework. A more rapid


boiler run-up may be possible, thus saving fuel.

Water loss during start-up is minimised since, if


no by-pass is fitted, superheater vents are used
to discharge steam to provide a flow of steam
through the superheater.

Independent operation of the boiler is more readi-


ly achieved with the full capability of de-aeration
and condensate polishing.

4.4.2 By-pass capacity


Sizing of the by-pass system is based on the most
arduous duty, in this case the ability to run-through
a trip to house load. The HP by-pass size is usually
expressed as a percentage of the HP stop valve flow
at rated full-load conditions. To cater for a load
rejection to house load, the size of the by-pass will
be given by:

HP by-pass capacity
HP BYPASS SIZE,1
,w /house load\ <
100% - x 100 FIG. 1.77 Typical heat load on condenser
V full load /
[inherent boiler load rejection capacity]
70% (typically)
The additional throughput of condensate flow must
also be taken into account in the design of the LP
The LP by-pass size is generally expressed as a heaters.
percentage of the interceptor valve flow at rated full-
load conditions. For a trip to house load, rapid closure
of the interceptor valves causes a pressure rise and 4.4.3 System effects
the LP by-pass opens to contain this. The LP by- In operation, other problems arise from the intro-
pass is usually sized at well below the 100% capa- duction of the by-pass systems. Following a load
bility since, under the worst case of rejection from rejection, the HP governor valves close fully and once
full-load, any excessive pressure rise is accommodated the by-pass is operating, the non-return valves in the
by lifting of reheater safety valves for a few minutes. HP turbine exhaust prevent reverse flow into the HP
A by-pass system sized on the basis of load rejec- turbine. However, the steam already in the turbine
tion capability can readily accommodate the duties cylinder is effectively bottled up' and the continuing
imposed for start-up and independent boiler operation. rotation of the turbine causes rapid overheating of
To reduce the enthalpy of the steam, it is neces- the blading due to turbulence and frictional heating
sary to inject spraywater, derived from the condensate of the contained steam.
system, after both HP and LP by-pass valves. The A similar problem arises during start-up. Without a
spraywater flow adds to the HP by-pass flow to give by-pass, the HP turbine exhaust pressure prior to
the mass flow rate through the LP by-pass system; synchronisation is at a very low value, controlled by
this is therefore used in sizing calculations. the flow through the IP and LP turbines. With a by-
The supply of a by-pass system reflects on the pass, there will be a much higher flow through the
design of other plant in a major way. To cater for by-pass and the turbine exhaust pressure is consider-
the supply of spraywater on top of the maximum ably higher. Normally this value of exhaust pressure
HP by-pass flow, it is necessary to increase the rat- would only be attained with a much higher flow
ing of the condensate extraction pumps. through the turbine. The HP turbine is therefore
The increased flow and high enthalpy of the by- operating with its efficiency considerably reduced and
pass steam increases the size and cost of the con- in addition is producing some rotation loss heating.
denser significantly. Figure 1.77 shows how the A typical condition line for the HP turbine is shown
additional heat load relates to the HP by-pass size. on the Mollier diagram in Fig 1.78.
61
The steam turbine Chapter 1

up of the boiler and turbine. Its economic impact is


most readily appreciated by considering the effect on
hot starts following an overnight shutdown. This is
the duty normally seen by a unit allocated to two-
shifting. Figures 1.79 (a) and (b) depict the differ-
ences in unit start-up with and without the by-pass
in operation. The start-up time is roughly 15 minutes
less if the by-pass is used. The saving may be con-
siderably more if the boiler/turbine is not a flexible
unit designed for two-shifting.
Depending on the intended duty of the plant, this
may represent a significant saving to lifetime costs.
There is also a small saving because, without a by-
pass, water would be lost through the superheated
vents as part of the standard start-up procedure. A
further advantage of the by-pass system for start-up
is that inexperienced operators are more easily able
to bring the steam conditions to appropriate values
before rolling-off the turbine. Against these advantages
must be set the cost and maintenance burden asso-
ciated with the supply of a by-pass system. In general,
a small capacity (35%) by-pass system is unlikely to be
justified on the grounds of improvement of start-up
capability.
One notable exception is the once-through boiler,
where a substantial bypass flow is required for a
lengthy period during start-up. The CEGB AGR ma-
chines, which use a superheat steam cycle, are examples
of this. The AGR also needs to use the by-pass for a
lengthy period during shutdowns, particularly if the
reactor is to be maintained at temperature in readiness
for the next start-up.

ENTROPY, kJ/kg

FIG. 1.78 HP turbine condition line 4.4.5 PWR wet steam plant
The reheater is not part of the boiler. This function
is carried out by live steam from the reactor and
bled-steam from the HP turbine in vessels mounted
These problems are effectively dealt with by pro- adjacent to the turbine. There is therefore no require-
viding a connection from the HP turbine exhaust to ment for separate HP and LP by-passes to permit
the condenser, sized to take approximately the HP independent operation of the reactor and steam gen-
flow that obtains prior to synchronisation and ar- erators. A single by-pass circuit to dump HP stop
ranged to open only when the by-pass is in operation. valve inlet steam to the condenser is employed. Warm-
During by-pass operation, there is a transient loss through of the reheater is accomplished as part of
in the water stored in the de-aerator due to the re- the turbine start-up. Rapid starting and utilisation for
circulation of spraywater. An assessment of the worst two-shifting is not the role of PWR plant.
case transient is normally made to ensure that feed The reasons for the supply of by-pass systems on
system stability is maintained. PWR plant are therefore:
The remaining problems concern the malfunction
of the by-pass system and associated plant. To pro- (a) To enable the nuclear plant to accept transients
tect the LP turbine, it is necessary to trip the by- without tripping or actuating safety valves.
pass valves closed in the event that loss of conden-
ser cooling water causes a high LP turbine exhaust (b) To remove stored energy and residual heat follow-
pressure. Failure of spraywater valves and other as- ing a turbine and reactor trip to bring the plant
pects are covered in more detail in Chapter 2. to equilibrium.
(c) To permit a manually controlled cooldown of the
4.4.4 Improvement of start-up capability plant to the point where the residual heat removal
The provision of a by-pass system improves start- system can be put into operation.
62
Economies of the steam cycle

HP & IP/LP BYPASSES IN SERVICE

30 40 50
TIME FROM LIGHTING BURNERS, min

(a) Hot start (6 - 8 hours shutdown) with bypass system LOAD


SPEED
TEMPERATURE
FLOW
PRESSURE

30. 40 50
TIME FROM LIGHTING BURNERS, min

(b) Hot start (6 - 8 hours shutdown ) without bypass system

FIG. 1.79 Comparison of unit start-up with and without a by-pass system

63
The steam turbine Chapter 1

(d) Following a turbine trip or shutdown, to maintain only requires a by-pass capacity of 40% and is ac-
the reactor and steam generators in a hot-standby complished without discharge to atmosphere.
condition, ready for turbine restarting. Both condenser and atmospheric sets of valves are
required to open fast, particularly for duties (b) and
A diagram of a typical by-pass system configuration (d). The opening time of approximately three seconds
is shown in Fig 1.80. The main by-pass is through permits containment of the steam pressure rise with-
six parallel sets of control valves into the three con- in the settings of the atmospheric valves for the
denser sections. Valves 1, 3 and 5 are modulating reactor trip case. The valve closing rates are designed
valves used for all three functions but sized to be to protect the turbine and condenser in the event
capable of performing the cooldown duty (c) on their of a system failure. A closure time of 5 seconds is
own. Valves 2, 4 and 6 are capable of being switched provided to protect against high condenser/turbine
open or closed and are only used for duties (a), (b) exhaust pressures in the event of a condenser cooling
and (d). An additional dump to atmosphere is also water failure. The effects on other plant are similar
provided for duty (d), since infrequent discharges to those discussed for superheat plant and are taken
to atmosphere are permissible for short durations. into account in the design.
This reduces the duty on the condenser, permitting The provision of sufficient by-pass capacity to
considerable economies to be made. Thus, in the avoid tripping the reactor in the event of a turbine-
event of a turbine-generator trip, valves 1, 3 and 5 generator trip justifies the by-pass on economic grounds.
are opened first, followed by valves 2, 4 and 6 and If the reactor were allowed to trip for a turbine
finally, if necessary, the atmospheric dump valve. problem lasting for perhaps only 30 minutes, there
For one reactor, the total capacity is arranged to be would be a severe availability penalty.
approximately 70% of the full MCR steam flow with The problems of implementing a by-pass system
about 10% being accommodated by the atmospheric are addressed in Chapter 2. These matters are proper-
dump valve. In association with further relief valve ly dealt with at the design stage and result in systems
capacity in the reactor system, this permits a trip of which provide economic benefits by achieving better
the total turbine-generator capacity. A reactor trip co-ordination between the turbine and boiler systems.

) DUMP VALVE TO ATMOSPHERE

HP BYPASS - 1
CONTROL VALVES

ZXtzXt

MAIN STEAM LP
MANIFOLD CYLINDER 1

i=xt=xt

FIG. 1.80 Turbine by-pass system for a wet steam machine

64
Turbine blading

5 Turbine blading and blades need to be very robust. The diaphragm


has the advantage of a relatively small diameter at
the steam seal between diaphragm and rotor, but
this labyrinth seal must be as good as possible to
5.1 Impulse stages deal with the high pressure drop. The radial labyrinth
seal ensures adequate insensitivity to axial displace-
5.1.1 Moving blades details and construction ment between the rotor and the casing. A typical
In the impulse stage, invented by Professor Rteau, impulse stage arrangement is shown in Fig 1.81.
the majority of the heat drop occurs in the station-
ary blading and the driving force on the stage arises
from the change in momentum of the steam across
the moving blades. The impulse design possesses the
advantages of compactness and comparative insen-
sitivity to blading clearance since little pressure drop
takes place over the moving blading. However, the
moving blades are subject to disturbances from the
nozzle wakes, so resonance must be avoided and
steam bending stresses must be kept low; also, since
the momentum change is relatively high, the moving
blades have to be robust and tend to be heavy. It
is therefore regular practice to attach the individ-
ually manufactured blades to a wheel disc, often by
straddle roots which engage with corresponding axial
shoulders machined on the wheel rim.
One or more protrusions are left at the outer end
of the moving blade. These pass through holes in a
coverband which may in turn fit into a slot machined
in the outside of the blade: when these protrusions
or tenons are formed into rivets, they keep the cover-
band in place. The coverband acts as a seal and braces
the blading to reduce vibration. Each length of cover-
band ties a short length of blades together and may
butt up to the next length or overlap, so that an
extremely robust construction is created. Since a cer-
tain degree of reaction builds up towards the outer
diameter of all impulse blades, axial sealing fins are
formed integral with the moving blade shroud or
coverband.

5.1.2 Fixed blades details and construction


There are two methods of constructing the stationary
nozzle blading. Built-up blades, machined from the
solid, are used for nozzle plates and steel diaphragms, FIG. 1.81 Modern impulse stage with labyrinth sealing
whilst cast-in blades, formed from steel plates em-
bedded into cast iron diaphragms, are used where
temperatures are below 230C. On some of the latest
machines, HP blades have been electrochemically ma- 5.1.3 Velocity-compounded stage
chined. An impulse stage is frequently used for the The first HP stage of a turbine, where it is desired
first stage of the HP turbine. The fixed blades may to give a large pressure drop to the first row of noz-
then be incorporated in an integral nozzle box, there- zles, sometimes incorporates two impulse stages on
by obviating the problem of pressure sealing at the the same wheel. This is done to protect the casing
inside of the blade ring. By absorbing a high heat and rotor from higher pressure and temperature con-
drop, the nozzle box arrangement also reduces the ditions. As a velocity-compounded stage uses ap-
pressure and temperature of the steam impinging on proximately the same heat drop as four impulse
the HP rotor and inner casing. stages, it is used to provide a shorter and cheaper
Since impulse stage diaphragms have to withstand turbine, although with some sacrifice in efficiency.
the bulk of the stage pressure drop, both diaphragm It is no longer used in large base-load turbines.

65
The steam turbine Chapter 1

Figure 1.82 shows the arrangement of such a This type of blading was designed and developed by
stage. The nozzles, of the convergent-divergent type, Sir Charles Parsons and lends itself to economical
produce very high steam kinetic energy, some of production of blades from standard rolled sections.
which is absorbed by the first row of blades, the Only a small heat drop can be accommodated per
remainder being deflected back by the stationary blade row, due to the comparatively high velocity
guide blades and used in the second row. Both moving ratio required for good efficiency; this means that a
blades and nozzles are machined from the solid and large number of expansions are required. Steam ap-
are necessarily very robust. proaches the moving blades with a velocity that is
low and substantially axial in direction. Consequently,
the driving force applied to the moving blades arises
almost entirely from the reaction force of the steam
as it accelerates through the moving blades. The force
applied to the moving blades is thus fairly steady, with
very little disturbance arising from the nozzle wakes
of the fixed blades, so fairly high bending stresses
can be employed in the moving blades without risk
of fatigue failure due to vibration.
Since the pressure drop across the fixed blades is
small, diaphragms are not required, but small tip
clearances are needed throughout the turbine to pre-
vent excessive leakage losses. This was achieved in
earlier turbines by axial sealing and end-tightening.
With solidly-coupled shafts which expand either
side of a single thrust bearing and with multi-casing
arrangements, end-tightening is not feasible and a
compromise has to be reached between fine clearances
to reduce leakage and large clearances to accom-
modate differential expansion when starting.
Modern reaction turbines generally employ a com-
bination of axial and radial sealing at the stators and
rotors, and for this purpose, the rotor blades are
STEAM CHEST . provided at their outer edge with shrouds formed
PRESSURE
of sections integral with the blade (see Fig 1.83).
These mate with replaceable finned sealing segments
in the casing. Fins formed on the inner diameter of
the fixed blades provide sealing at the rotor.
VELOCITY
REMAINING
CONDENSER
Small reaction-type blades can be manufactured
INITIALSTEAM
VELOCITY PRESSURE by cutting from rolled bar of the requisite profile
or machining from bar, while larger blades may be
separately cold-rolled after which the root portion is
i} heated and forged. Blades may also be machined from
MOVING BLADES envelope forgings or produced by precision forging, so
FIXED BLADES
that the profile requires no further machining; this
STEAM VELOCITY
STEAM PRESSURE
is valuable where tough materials make machining
difficult. Final machining can also be awkward where
integral shrouds and root fixings interfere with the
machine tool. To facilitate manufacture, modern prac-
FIG. 1.82 Velocity-compounded (Curtis) stage tice is to braze together short groups of blades before
machining the circumferential serrations on the sides
of the roots, see Fig 1.84. The brazing also permits
easier assembly. Groups of blades are fitted in the
5.2 Reaction stages rotor or casing in circumferential grooves which have
corresponding circumferential serrations machined in
their walls. The blades arc secured in the grooves
5.2.1 Fixed and moving blades details and by similarly serrated side-locking pieces cut from rolled
construction strip. A suitable stop plate at the half joint locates
Although called 'reaction', these stages in fact employ the fixed blades in the circumferential groove and
equal degrees of impulse and reaction, resulting in prevents the blade segments from rotating due to
the fixed and moving blades being of identical section. torque reaction.

66
Turbine blading

FIXED BLADE

FlG. 1.84 Brazed reaction blade group

FIG. 1.83 Section through a reaction stage sure drop develops across the moving blades and
the steam leaves the moving blades at a higher speed
to offset the higher peripheral speed, enabling the
steam to leave the blades with the minimum of swirl.
5.3 Low pressure stages The stage is designed to have a fairly low degree of
reaction at the base and, since the pressure drop
across the fixed blades decreases in response to the
5.3.1 Aerodynamic and mechanical constraints increasing pressure drop across the moving blades,
In early machines, the last few low pressure moving reaction increases with blade height. The radial ten-
blades were of constant cross-section. The stress in sion due to centrifugal force and the aerodynamic
this type of blade increased quadratically from the effect of change of steam flow results in a highly-
tip to the base and attained its maximum value in twisted moving blade, having a robust low reaction
the transition from blade to root: this placed a re- section at the root and a slim high reaction section
striction on the length of blade that could be used at at the tip, see Fig 1.85.
synchronous speed. Modern last-stage blades have a
cross section which reduces exponentially with the
square of the radius. The tensile stress due to centri- 5.3.2 Blade tip restraint
fugal stress is then virtually constant over the greater The use of long blades and large blade chords in-
part of the blade length and this has enabled blades volves an increase in pitch and this creates compli-
up to 940 mm long to be used on 3000 r/min cations in the various devices used to stiffen the
machines. blade assembly and dampen vibration. A coverband or
On modern blading, the tip diameter is typically lacing wire must behave as a beam spanning the blade
about double the base diameter, so that at the mean, pitch in resisting centrifugal loading, and must also
the blade pitch, i.e., the circumferential distance be- accommodate the substantial circumferential strains
tween adjacent blades, is about 1.5 times the pitch due to radial elastic extension of the blades and the
at the base diameter. The peripheral speed is also tendency of the blade to untwist at speed.
1.5 times as great as at the base and the effect of When lacing wires are used, they are usually of
this increased blade speed is to change the direction the 'loose' type with circumferential restraint on only
of the incident velocity of the steam relative to the one blade in each group, and are free to move
moving blade. The moving blade inlet angle is there- circumferentially in adjacent blades, centrifugal forces
fore set to line up with the direction of the incoming providing the necessary damping through friction. The
steam flow and the moving blade section is also gaps between adjacent lacing wires can introduce
changed. This reduces the outlet angle so that a pres- complications in vibration patterns on long blades
67
The steam turbine Chapter 1

FIG. 1.86 Arch coverbands

liable. Some thickening of the blade is required, how-


ever, in the region of the tip tie to accommodate the
ball-joint sockets.
A few manufacturers have dispensed with all forms
of stiffening, relying on the stiffening effect of cen-
trifugal forces, which can be very substantial on
freely-cantilevered blades. This type of blading tends
to be wider and heavier than blading with stiffening
and introduces difficulties in manufacture and rotor
design. Freely-cantilevered blades are most suitable
FIG. 1.85 Final blade envelopes
for the last stages of very small high speed turbines,
where it is not possible to introduce complicated stif-
fening devices and where the increased blade width
is not an embarrassment.
and overlapping lacing wires are sometimes used to
give some measure of continuity around the annulus.
A coverband of conventional design is not feasible
for slim sections and where the peripheral speed may 5.3.3 Baumann exhaust
be approaching Mach 2, but a continuous ring of A special type of exhaust blading, invented by Dr
stiffening devices of sufficient elasticity may be used Baumann, has been used by one manufacturer in
to accommodate circumferential strains. The elastic order to achieve greater exhaust area without undue
arch banding, shown in Fig 1.86, braces the blade lengthening of the blades of the last moving row.
tip and provides some resistance to blade untwist as Known as the 'multi-exhausV, it used two-tier blades
well as largely permitting circumferential strain. for the penultimate stage, steam from the outer tier
Zigzag spool rods shown in Fig 1.87 are frequently exhausting directly to vacuum. The net result was
incorporated in the tips of the last-stage LP blades that, without lengthening the blades of the last row,
of modern turbines. The spool rods provide no re- but by lengthening those of the previous row, the
straint against circumferential expansion or centri- leaving loss was appreciably reduced.
fugal untwist, but the reduced sections at the ends
of the rods are forced against the holes in the blades
by centrifugal action and the sliding friction provides
effective damping, minimising blade vibration and 5.4 Moving blade root attachments
high frequency flutter at the blade tip. The last-stage blades of large turbines develop centri-
A recent variant to the spool rod is the ball- fugal forces of hundreds of tonnes when running,
jointed tip tie. The dumb-bell-shaped tie rod fits into very efficient methods of attachment are therefore
a fixed ball-shaped socket in one blade and into a needed.
sliding ball socket in the next blade. In common with Systems in use at present include rhombus fixings
the spool rods, centrifugal strains are not restrained in a peripheral slot, finger-shaped pinned fixing and
but the ball-joints provide more controlled damping straight or curved fir-tree roots. Fir-tree roots provide
and the evaluation of tie rod stressing is more re- an excellent method of attachment, since they permit

68
Turbine blading

5.4.1 Fir-tree roots


Fir-tree serrations may be in line with the axis of
the machine, inclined to the axis, or curved, see
Fig 1.88. Curved fir-tree roots follow the blade chord
at the root section. The straight root, in line with
the axis, is used for slightly-twisted end blades. Both
the inclined and the curved fir-tree roots are used
for highly-twisted blades to achieve a closer blade
pitch at the inner steam path. Optimum selection
of the dimensions and number of serrations of the
fir-tree root has been made possible by finite ele-
ment calculations of stresses in the shaft and root.
Because of unavoidable inaccuracies in manufacture,
the pit between the supporting planks of the individual
fir-tree tips varies. This is also taken into account
in the calculations. Pull-out tests on fir-tree roots
have confirmed their reliability. In view of their high
strength and close packing capability, side entry fir-
tree roots are generally used for fixing last stage
LP blading.
In earlier turbine stages, fir-tree serrations are ma-
chined circumferentially in grooves in the rotor, and
groups of blades are secured in the grooves by simi-
larly-serrated side locking pieces cut from rolled strip.
The blades of the first row of the HP turbine are
axially attached to a short wheel disc on the rotor
by straddle roots, which engage with corresponding
shoulders machined circumferentially on the wheel
rim. The straddle fixing therefore acts as an inverted
fir-tree, the tree shape, usually with only one or two
branches, being formed on the rotor disc.

5.4.2 Pinned roots


Multifork pinned roots are generally easier to manu-
facture than fir-tree roots, since the machined faces
are plain with no undercutting, and the pin or rivet
holes are simply drilled and reamed. The enormous
force on moving blade roots, particularly in the LP

(a) Straight

FIG. 1.87 Zigzag spool rod tip-ties

(c) Curved

very close staggering of the blade cascade and the


centrifugal force is produced in an optimum manner
in the shaft teeth. FIG. 1.88 Types of fir-tree root

69
The steam turbine Chapter 1

stages ensures rigidity in any type of root fixing at to take into account the torque reaction on the
synchronous speed but, contrary to the fir-tree root, diaphragm.
the multifork pinned root provides a rigid fixing All keys have provision for adjustment, so that
when the machine is stationary. This enables the correct alignment of the diaphragms can be achieved.
zero speed vibration characteristic of the blades to A typical arrangement of diaphragm support and
be confirmed with confidence and ensures a smooth location keys is shown in Fig 1.89.
unstepped spectrum of characteristics, as the machine
is run up. Replacement of multiforked blades, how-
ever, involves further reaming of the securing pin 5.5.2 Radial support pads
holes. This is awkward in-situ and can only be carried
The provision of this system of kinematic support
out a limited number of times.
becomes progressively more difficult as the diameter of
the diaphragm increases. As the size of turbine has
increased, the basic concept of kinematic support has
been modified to suit the circumstances.
5.5 Diaphragm construction and support One alternative has been to fit keys in both half-
diaphragms so that each is supported independently
at the horizontal joint. This arrangement requires that
5.5.1 Kinematic support there is a gap between the half-diaphragms for ex-
pansion, resulting in a steam leakage across the half
All diaphragms are divided at the horizontal joint
joint: it also requires more machining and fitting.
into two semicircular halves to permit assembly.
The difficulty in providing kinematic support for
Diaphragms are located in the turbine cylinder as
large diaphragms occurs mainly in LP turbines, where
close as practical to the horizontal and vertical axes
the outer ring diameter is large. In the LP turbine,
of the machine, in order to reduce to a minimum
the differential temperature between diaphragm and
the effects of differential expansion. Particularly when
cylinder that has to be accommodated is much reduced.
the machine is small, the loss in output arising from
This, together with the need to provide some form
the internal clearances can be significant. It is for
of stop-plate for the top half-diaphragms, led to an
this reason that the practice developed of supporting
alternative arrangement where, in the running condition,
and guiding the diaphragms in the inner cylinder by
the top half-diaphragm is supported on the bottom
keys in each half. This method of location, which
half-diaphragm, which itself just rests in the recess
is known as kinematic support, is generally used on
in the cylinder. The clearance for differential expan-
current HP and IP turbines of the disc and diaphragm
sion is achieved by exact machining of the outer
type, and on the early stages of LP turbines.
diameter of the diaphragm.
The details of a kinematic support system are in-
A more practical arrangement is to machine a
fluenced by the method of manufacture. As the
generous radial clearance between cylinder and dia-
adjacent surfaces of the cylinder and diaphragm are
phragm and to fit the half-diaphragm with a number
circular, the diaphragm has to be supported on keys
of radial support pads which are then dressed to
fitted into milled recesses in both cylinder and dia-
obtain the required location of the half-diaphragm.
phragm, as close to the horizontal joint as practical.
Differential steam pressure forces the diaphragm
Transverse location of the diaphragm is achieved by
outer rings against the downstream axial face of the
keys on the vertical centreline fitted into milled key-
circumferential recess in the inner cylinder. To prevent
ways. Adequate clearances are provided on fitting the
the diaphragms seizing in this recess, and to permit
keys to ensure freedom of movement for differential
adjustment, small crushing pegs are fitted in the up-
expansion. To avoid steam leakage between the two
stream face of the locating spigot.
halves of the diaphragm, the top half sits on the
Temporary support pads may be fitted and adjusted
bottom half, and keys at the half-joint are arranged
in line with, and transverse to, the machine centreline. to achieve the correct positioning of the diaphragm
This locates the top half-diaphragm axially and ra- in the cylinder. The packing bush radial clearances
dially with the bottom half-diaphragm, and provides are bored to a charted size and checked with the
an effective steam seal. The keys on the bottom half rotor in position. If necessary, the temporary pads
horizontal joint have to be sized to take the weight are adjusted to optimise radial clearances. When the
of the complete diaphragm. desired alignment has been obtained, the thickness
of the temporary support pads is gauged and the final
To enable the top half-diaphragm to be retained
support pads ground to size.
in the top half cylinder when it is raised, stop-plates
are provided at the horizontal joint on each side.
The diaphragm is located axially against a machined
recess in the cylinder which offers frictional resistance 5.5.3 Diaphragm construction
to the expansion of the diaphragm relative to the HP and IP diaphragm nozzles may be individually
cylinder. When sizing the support keys, it is usual machined or cast and the inner and outer blade up-
70
Turbine blading

CASING

HORIZONTAL JOINT BOLT

DETAIL OF
BOTTOM HALF
TRANSVERSE LOCATION
KEY

TOP HALF DIAPHRAGM

STOP PLATE FITTED


TO BOTTOM HALF
DIAPHRAGM

SUPPORT KEY

FlG. 1.89 Diaphragm support and location keys

stands fitted into grooves machined in half rings, The first four LP diaphragms are usually a welded
which may be machined from plate or may also be construction, similar to the HP and IP, with stainless
cast. The diaphragm half rings are then built up by steel blades, rims and centres. Later stages may have
welding the nozzles to the inner and outer half rings pre-machined blades cast into cast-iron inner and
on the axial faces of the half rings. Castings in stain- outer rings. Cast iron enables optimum shapes of
less steel suffer from the formation of regions of steam passages to be formed. These diaphragms may
delta ferrite, particularly near the trailing edges of also be cast as complete halves in stainless steel.
fixed blades, and cracking near changes in section Very large modern last-stage LP diaphragms have
unless cooling rates are very carefully controlled. Also, massive sections for the rims and centres and can be
since the welds penetrate only part way into the inner extremely heavy if made from solid castings. The rims
and outer half rings, a circumferential crack exists and centres are therefore sometimes fabricated from
in the middle of the rings. Radial cracks also exist plate into semicircular hollow box sections. Welded
between each nozzle section where they butt against constructions are always heat treated to remove locked-
one another. These cracks weaken the assembly and in stresses and allowance must be made for distortion.
can provide initiation points for fatigue crack propaga-
tion. Investigations are being carried out to develop
welded diaphragms, using full-penetration electron
beam welding. This will largely avoid the problems 5.6 Blading materials
of internal cracks or voids.
A more modern method of construction is to
electrochemically machine each complete half ring 5.6.1 12% Cr steels
out of a solid stainless steel blank, thus obviating Turbine blading alloys are chosen for their ability to
the problems of welding and casting. provide properties particular to the mechanical and
71
The steam turbine Chapter 1

environmental service which they must endure. One perature blades. All steels of this type require the
of the first considerations of LP blading, for example, addition of an austenite-forming element to prevent
is the ability to resist corrosion and scaling in fast- the formation of zones of delta ferrite in the material.
flowing wet steam. This generally rules out low alloy Nickel is employed for this purpose but its content
steel and blades are made from either stainless steel is limited in high temperature blades because higher
or titanium alloys. A second requirement is adequate percentage additions reduce creep strength. The addi-
tensile strength to resist steady centrifugal and bend- tion of niobium to the 12% Cr Mo V steels increases
ing stresses. Strength without ductility is not desirable; stress rupture strength and creep strength in the short
ductility is needed to accommodate stress peaks and term, but the strengthening effect falls off with time
concentrations. Ductility also is needed to resist rub- so that the long term properties are no better than
bing, and, in the case of shrouded blades, to permit those of the 12% Cr Mo V steels without niobium.
the peening of tenons to secure the shroud. Impact Typical British steels for high temperature blad-
strength is also necessary, since contact with foreign ing include FV 507, a ferritic casting alloy with good
objects is sudden. Water slugs can produce impact tensile and creep properties combined with low thermal
loading. expansion, and Esshete CRM 12 from British Steel,
Since most blade failures are due to fatigue, ade- a heat treatable martensitic 12% Cr steel alloyed with
quate fatigue strength is a crucial property. The blades molybdenum and vanadium. Both these alloys have
are under steady centrifugal stress while operating, good long term creep strength at temperatures up
and this must be incorporated into the fatigue strength to 650C.
considerations. Since LP turbines can see wet 'aggres- The intermediate blades, which are neither highly
sive environments', the fatigue strengths upon which stressed nor very hot, can be made from 12% Cr steels
designs are based must account for environmental with leaner alloying content and heat-treated to the
degradation. appropriate hardness. A typical steel is FV 448, an
Material damping is also considered of high im- 11% Cr, 0.6% Mo, 0.25% V, 0.3% Nb steel with good
portance. The vibratory stress developed in a turbine creep resistance up to 550C.
blade is inversely proportional to the damping. One The corrosion and scaling resistances of the latest
of the reasons 12% Cr stainless steels are so widely so-called 'Super 12% Cr' steels are at least equal to
used in blades is due to their superior material those of the simple 12% Cr steels and in many cases
damping. significantly better. General corrosion resistance in
Notch sensitivity also affects fatigue response and, steam is better than the grades containing less than
since stress concentrations are unavoidable, parti- 12% chromium: the ferritic grades are much less
cularly near the root, a low notch sensitivity is very prone to stress corrosion cracking than the austenitic
desirable for good blade life. Unfortunately, whereas steels.
high tensile strength desirably increases fatigue strength, Welding is considered the most complicated fabri-
it also increases notch sensitivity. cation process for the Super 12% Cr steels because
The short blades in the HP turbine work at tem- of their high hardenability. The martensite formed
peratures near to the maximum steam temperature, in the weld metal and heat affected zone (HAZ) is
so creep strength is vitally important in this region, hard and brittle and must be tempered. However,
with the amount of permissible creep usually restricted when temperature recommendations outlined by the
to 0.2% deformation in 100 000 h. various producers of Super 12% Cr steels are fol-
The conventional 12% Cr steels have an ideal set lowed, welding does not present any unusual problems.
of properties for turbine blading as long as the Information concerning production, constituents,
temperature does not exceed about 480C. Austenitic properties and application of the Super 12% Cr steels
steels have been tried but, in general, have not been is given in [8].
satisfactory, except for the short blades in the HP
turbine where damping capacity is not as crucial as
it is for the longer blades in the later stages of the 5.6.2 Titanium
LP turbine. Austenitic steels, however, have relatively Because of its high strength/weight ratio and excellent
high coefficients of expansion and tend to be avoided corrosion resistance, titanium has been considered as
because of this. Ferritic steels of the FV 520 type an alternative to 12% Cr steel for low pressure tur-
have been used for last-stage LP blading but have bine blading. Since the density of titanium is about
now been generally superseded by steels such as FV 60% of that of steel, a titanium blade nearly 40%
566, which were designed for applications where good longer than a steel blade can be substituted, assuming
impact properties are required at medium-to-high comparable stress levels in the blade root.
strength levels. Mechanical properties have been im- The corrosion resistance of titanium makes the
proved by the addition of molybdenum and vana- material highly attractive for blading subject to pit-
dium, and suitable heat treatments to give adequate ting, stress corrosion and corrosion fatigue. Laboratory
creep resistance in the short high temperature blades, tests have also shown that certain titanium alloys are
and adequate proof strength in the long low tem- superior to 12% chrome stainless steel in erosion

72
Turbine blading

resistance but not as good as Stellite 6, which is The vibration characteristics of turbine machine
commonly used as an erosion shield on steel LP blades, as measured under operating conditions, are
blading. usually found to be extremely complex and often
The yield strength of a typical titanium alloy in quite different from theoretical predictions. There
the annealed condition is approximately 50% better are several reasons for this.
than standard 12% chromium stainless steel material, First, in spite of the advances in finite element
and even slightly superior to the Super 12% Cr steels: computation in recent years, the intricate geometry
the ductility is somewhat less. The fatigue strength of a blade, which is demanded for aerodynamic per-
of titanium alloy is, however, generally higher than formance, makes it a very difficult component to
the 12% Cr steels. analyse theoretically. Consequently, predictions for
Titanium alloy is not as readily forgeable as 12% the modes and frequencies of a single cantilevered
Cr materials. The titanium alloy has to be forged at blade may not always be very accurate. Then, a second
a lower temperature which means that more energy factor which compounds the problem, is the existence
is required to forge a certain amount. Also, since all of multiple interactions between each blade and all
titanium alloys are very active chemically at high the other blades in the same stage due to coupling
temperatures, surface contamination is another pro- through the disc and shrouds or lacing wires linking
blem encountered when forging. adjacent blades. These interactions lead to the predic-
Machining is possible, if slow speeds are used, tion of a multiplicity of modes in the working fre-
but a propensity for embrittlement by contamination quency range, where for a single blade there are only
and lack of heat penetration make welding difficult. two or three. The vibration of a fully-bladed disc is
Inert gas welding is the normal solution but this is therefore much more complicated than is suggested
time consuming and costly. by the characteristics of a single cantilever blade.
The main problems of titanium are high cost and An individual blade, cantilevered at its root, has a
poor vibration characteristics. The cost of titanium set of natural frequencies in the operating range which
alloy is several times that of standard 12% Cr blade are classified in three groups: 'flap' modes, 'edgewise'
material and a row of titanium blades normally costs modes and torsion modes. The disc carrying a set of
two to three times that of a steel row, all factors such blades itself possesses several natural frequencies
considered. within the same range, each one of these being associated
The material damping of titanium is very poor, with a mode mode shape having n nodal diameters
varying from 10% to 40% of that of 12% Cr blade (and possibly one or two nodal circles as well). The
material. Thus there is a potential for higher vibratory complete bladed disc has a very large number of
stresses when operating the titanium blade at or near modes of vibration in the same frequency range, and
resonance. Also Young's Modulus of titanium is low each of these will constitute a unique mix of the
and, since the flexibility is relatively high, natural individual blade and disc modes. Some of these as-
frequencies are depressed and harmonics are more sembly modes will be identified as being 'predo-
crowded in the running range. minantly disc' modes, while others will be immediately
In view of the lower cost and improved properties associated with one of the blade cantilever modes,
of the Super 12% Cr steels, it is unlikely that ti- in both cases by virtue of the respective natural
tanium alloys will supersede these steels for LP mov- frequencies.
ing blading on UK steam turbines in the near future. Other modes exist which are associated with the
However, because of its high strength/weight ratio, fully-bladed wheel assembly and are quite distinct from
titanium is used extensively for lacing wire and for disc or blade modes. When there is additional inter-
coverbanding and shrouding. blade coupling provided by some form of shrouding
either at the tip or part-span, then most of the modes
of the complete structure will tend to be wheel modes,
and small modifications to the shrouding or lacing
can result in significant changes in the pattern of
5.7 Blade vibration control wheel natural frequencies.

5.7.1 Natural frequencies and excitation 5.7.2 Sources of vibration excitation


frequencies
Vibration excitation can arise from a variety of sources
In view of the large number of blades in any turbine but principally involves the following categories:
machine, the existence of unavoidable sources of
vibration excitation and the serious consequences of (a) Non-uniform pressures, velocity or changes in the
the failure of just one blade, an intimate knowledge angle of steam flow resulting in a periodic fluc-
and understanding of the vibration characteristics of tuating force on the rotating blades. This may be
the blades in their operating environment is essential. caused by:
73
The steam turbine Chapter 1

Steam entering the rotating row over only a the stationary flow passages, these can include:
portion of its circular path (partial admission).
This may exist in the control stage of some Acoustic resonances in inlet passages, extraction
HP turbines but not in LP stages. lines or other cavities, excited by the flow past
them.
A change in the direction of flow, particu-
larly from axial to radial at exit from moving Vortex-shedding from stay bars, etc.
blades. Good aerodynamic design should mini- Unsteady flow separation from stationary blades, etc.
mise the magnitude of this non-uniformity
and ensure that multiple harmonics of the Unsteady shocks in choked stationary blade pass-
synchronous speed are not produced. ages.

Flow distortions produced by the presence Surface pressure fluctuations, due to impingement
of steam extraction passages for feedheater of turbulent flow onto rotating blade shrouds, discs,
tappings. etc.

(b) Periodic effects due to manufacturing constraints In the rotating blades themselves, flow instability,
or structural features. These can include: and hence excitation, can arise from:
Inexact matching of stationary blade geometry Boundary layer pressure fluctuations.
at horizontal joints. Blade-pitching at diaphragm
horizontal joints may not be uniform and this Vortex-shedding from blade trailing edges, causing
can give rise to excitation at even multiples unsteady aerodynamic force.
of rotational frequency.
Recirculating flow, particularly in last-stage LP
Leakage through gaps in stationary blade blades.
shrouds and diaphragm discs at horizontal
Unsteady condensation shocks, caused by super satura-
joints. The current arrangement of diaphragm
tion in supersonic diverging passages.
support precludes this effect.

Eccentricity of diaphragms and other station-


A necessary condition for high resonant vibratory
ary elements with respect to the rotating blade stresses is the coincidence between the frequency of a
assembly. Again, current design practice should harmonic component (of significantly high magnitude)
minimise this. and the natural frequency of a mode of vibration of
a blade, or a blade group, or bladed disc assembly.
Ellipticity of stationary parts, such as end
With a continuously-connected blade row, a resonance
walls, seals, etc.
condition is associated with a multinodal standing
Non-uniformity in the gauge or thickness of wave pattern around the circumference. This, how-
stationary blades. Modern quality control and ever, is not always a sufficient condition. It is also
manufacturing normally obviates this effect necessary that the distribution of vibratory deforma-
tions and the distribution of exciting forces have a
Moisture removal slots. relationship that permits a net input of energy into the
vibration.
For example, consider a long blade vibrating in a
All the above sources give rise to excitation fre- mode with one displacement node (point of zero dis-
quencies at the rotational frequency or low multi- placement). The upper portion of the blade deflects
ples (harmonics) of that frequency. in one direction when the lower portion deflects in
the opposite direction. If the distribution of exciting
(c) Nozzle wake excitation caused by the aerodynamic force along the height of the blade is essentially
force-fluctuations seen by the rotating blade as uniform, then the upper portion of the blade wants
it passes each stationary blade or traverses each to respond at a phase angle 180 different from that
stationary blade pitch. This is seen by the rotating of the lower portion. The net response of the blade
blades as excitation at the nozzle passing fre- to this exciting force would therefore be very low.
quency (rotational frequency x number of stationary
blades) and its multiples.
5.7.3 Verification of estimated natural frequencies
and wheel chamber tests
A number of sources can also give rise to excitation After a prototype blade has been designed on paper,
having no direct relationship to rotational speed. In a single blade is made in mild steel so that the cal-
Turbine blading

culation of natural frequencies can be checked. Pro-


vided that cantilever vibration tests confirm that the
single-blade frequencies are in accordance with re-
quirements, a complete bladed disc is manufactured.
The bladed disc is then tested by fitting piezo-
electric crystals at selected positions on the wheel and
recording the modal shapes and natural frequencies.
Since the natural frequencies of all blade rows,
except the last few LP stages, are generally above
the eighth engine order (400 Hz for a 3000 r/min
machine), static testing is usually sufficient to confirm
that possible resonances will be well removed from
excitations which the blades will experience in service.
The natural frequencies of the longer LP blades,
however, are lower and may coincide with harmonics
of rotational frequency below the eighth order. Also,
since the flexibility of longer twisted blades changes
slightly with speed, the bladed discs must be tested
over the running range to ensure that natural fre-
quencies do not coincide with synchronous harmonics.
Driving large bladed wheels in air would absorb
large amounts of power and would require large prime
movers. Also windage, particularly near the blade FIG. 1.90 Typical 'Campbell Diagram' for a
tips, would cause overheating and make the results low pressure blade
difficult to interpret. For these reasons, the complete
bladed disc is run in a vacuum wheel chamber, where
an array of magnets is used to stimulate impulses If a wheel mode and a harmonic of rotational
acting on each blade as it passes. The disc is run up frequency coincide below the eighth engine order,
to 115% synchronous speed and the blade vibration selected modes may be 'tuned out' by adjusting the
is detected by strain gauges or crystals. Signals are blade mass, particularly near the tip. The geometry
brought out either through sliprings on the shaft or, of tip ties or coverbands can be altered, or material
more recently, by telemetry and the frequency and added to/removed from shrouding, or the material
amplitude recorded. of these components may be changed. Altering the
By examining particular resonances, it is possible position of the shrouding may change the natural
to trace families of modes over the speed range. frequency of certain modes and it may even be pos-
These are drawn on a 'Campbell Diagram' similar to sible in certain circumstances to adjust the blade
that shown in Fig 1.90. Radial order lines through profile. Experience has shown that a continuous lacing
the origin represent events that occur a fixed number or tip tie arrangement is less likely to form complex
of times in each revolution. Where the vibrational modes of vibration than blades connected in groups
frequency trace for a particular mode crosses an order or packets, and is more predictable. Complex modes
line, there is the prospect of resonance occurring dur- are likely to be excited by high frequencies and are
ing service. It is usual to confine attention to within almost impossible to 'tune out'.
+ 6% of synchronous speed (i.e., 2820 to 3180 r/min). The damping afforded by 'loose' pins, tip ties,
Within this speed range, the specified requirement is lacing wire, etc. and the choice of blade material,
to have no resonances up to the eighth engine order. minimises the effect of random or broadband exci-
Experience has shown that, if resonances are avoided tation which is difficult to quantify. Damping re-
in this speed range, the blade assembly will experience duces the response to resonances as erosion or impact
minimal alternating stress during service. damage changes the natural frequencies of particular
modes and bring these natural frequencies into closer
coincidence with harmonics of rotational speed.
5.7.4 Methods of vibration control
It is not practical to 'tune' blades to avoid reso-
nances above the eighth engine order. The harmonics 5.8 Erosion protection
lie too close together and natural frequencies cannot
be calculated or controlled to sufficient accuracy.
Fortunately, excitation forces at these high frequen- 5.8.1 Erosion mechanism
cies are small and are incapable of exciting complex The last stages of large condensing turbines operate
modes. in the wet steam region, where the steam contains
75
The steam turbine Chapter 1

5-12% water. Turbine blade erosion is initiated by there follows a tertiary period during which the ma-
a relatively small proportion of the water droplets terial lost by erosion falls logarithmically with time
in the steam separating out and collecting on the and after about a year may almost cease. The pro-
concave pressure face of the diaphragm blades, where bable explanation for this is that the pores in the
a film is formed which is drawn towards the trailing surface of the blade where erosion has taken place
edge by the drag of the steam. Here the film grows are partly-filled with water. This cushions the impact
and passes around the trailing edge on to the convex of the drops striking the blade and the impact forces
face where, usually in a region of strong secondary are only transferred to the material in a damped
flow, droplets move back and forth increasing in form.
size until they are torn away by the shearing action of
the main steam flow. Relatively large drops (50-200
in diameter) are produced and have to be acce- 5.8.3 Protection and erosion shield materials
lerated from rest by the steam. These large drops
Methods have been investigated for collecting water
arrive at the inlet plane of the moving blade row at
from the stationary blade passage, including removal
only a fraction of the absolute velocity of the steam
by suction through slots near the outer edge of hol-
and are subsequently struck by the convex surfaces
low fixed blades or by bled-steam belts immediately
of the moving blade row. This causes the abrasion
before the last stages. These methods have the dis-
on the leading edge of the blade known as erosion
advantage that they automatically reduce performance.
Fig 1.91.
The adoption of higher heat drops in the last stage,
together with higher mass flow loading and higher
pressure at inlet to the moving blades, can lead to
smaller droplets whose velocities more rapidly ap-
proach that of the entraining steam. This can result
in reduced impact velocity and erosion effect.
It has been the practice for many years to protect
the leading edge and part of the convex surface of
the last-stage moving blades by surface hardening
or by the attachment (by silver soldering, or more
recently by electron beam welding) of a shield made
from a hard material such as tungsten, chromium tool
STEAM VECTOR
TRIANGLE steel or Stellite 6B.
V. EROSION Attachment is always followed by the most stringent
non-destructive examination of the joints. Erosion of
Vi
$>v. SHIELD

* MOVING ^ * * 5
* * ^ ^ ^ ^ ^ > ^ the original blade material around the shield can
BLADES ^ < ^ v . ^ ^ * ^ > ^
lead to undercutting of the shield material and eventual
shield detachment. Coverbands, blade upstands and
tip ties can also suffer from droplet erosion. It is
therefore considered prudent to inspect the blades
FIG. 1.91 Relative impact velocity onto last-stage during overhauls. Even if the erosion shield does
moving blades not become detached, the shields will erode in time
and will probably need to be replaced at least once
during the life of the machine.

5.8.2 Erosion progression


When a drop impinges on to the blade surface, a
very high pressure shock is generated for a short
period. The pressure wave causes plastic deformation 6 Turbine casings
of the material and repeated plastic deformation
leads to an increase in the internal stress. After a
certain time, the stress concentrations in some areas
exceed the tensile strength of the material, and cracks 6.1 Forms of casing construction
form. During this incubation, or primary period of A turbine cylinder is essentially a pressure vessel with
erosion, there is little or no weight loss. When the its weight supported at each end on the horizontal
cracks spread and join, however, the result is material centreline. It is designed to withstand hoop stresses
breakdown. Tiny pieces of surface material are re- in the transverse plane, and to be very stiff in the
leased and, during this secondary period, erosion rate longitudinal direction in order to maintain accurate
increases to a maximum. clearances between the stationary and rotating parts
After the surface has become uniformly pitted, of the turbine.

76
Turbine casings

The design is complicated by the need for internal shell at the expense of the outer shell. It also permits
access, all casings being split along their horizontal simple bled-steam tapping at the inter-shell conditions
centreline, allowing the rotor to be inserted as a com- and reduces the net thrust on the HP rotor.
plete assembly. Substantial flanges and bolting are Triple casings have been used on some modern
required to withstand the pressure forces at the hori- turbines to further reduce the stresses on the hot
zontal joints. The relatively massive flanges respond inner casing, and hence reduce thermal distortion.
more slowly to temperature changes than the rest The inner casing is enclosed in a barrel-like sleeve
of the casing, resulting in different rates of expan- which has no horizontal joint. The inner casing is only
sion and the setting-up of temperature stresses and lightly stressed and can be relatively thin with light
distortion, although these are minimised by the ap- flanges, whilst the barrel casing which encloses it is
plication of flange warming steam. Further stress more highly stressed. The barrel casing, however, having
complexities are set up by the gland housing and steam no flanges and being of uniform thickness, can easily
entry and exit passages. be designed to accommodate the stresses whilst also
HP and IP casings are of cast construction and are remaining relatively thin. The pressure between the
circular in cross-section to minimise non-membrane inner casing and the barrel is controlled by small
stresses. Flanges, bolting, steam penetrations and other radial passages through the inner cylinder walls and
features are as far as possible symmetrically arranged piston ring seals between the inner and barrel casings.
to reduce thermal asymmetry and hence distortion. One disadvantage of this form of triple casing is
LP casings may be fabricated or a combination of the difficulty in assembling and dismantling the HP
castings and fabrications. cylinder. On assembly, the rotor has to be fitted into
As with all pressure vessels, the integrity of the the inner and outer lower half, the inner casing bolted
design is checked after manufacture with a hydraulic up, and then the rotor and inner casing lifted and
pressure test, to 150% of the highest working pressure. mounted in a special jig to allow the barrel to be
threaded over them. The assembly can then be lowered
back into the bottom half of the outer casing, and the
6.1.1 High pressure casings top-half outer casing added.
Most modern turbines, with steam pressures over 100 The steam inlet pipes pass through the outer casing
bar and ratings greater than 100 MW, have HP casings and deliver the steam into the inlet belt of the inner
of double-shell design (Figs 1.92 and 1.93). This has casing. The inlet belt is formed by an extension to
been adopted because of the difficulty of designing a the main casing which ensures that the inlet steam
single casing to withstand the thermal and pressure cannot come directly into contact with the rotor but
stresses and yet be capable of flexible operation. With must first pass out through the nozzles and the first
a double-shell casing, the space between the shells is row of moving blades. The inlet belt is often blanked
filled with steam at exhaust conditions, allowing each at the casing joint to reduce the pressure on the joint
casing to be designed for smaller temperature and face, although care must be taken that the admission
pressure differentials. A baffle is formed between the of steam to the first stage is not interrupted.
two casings near the exhaust end as part of the inner- With steam temperatures at inlet in excess of
casing casting. The baffle extends almost to the outer 538C, separate nozzle boxes of heat-resistant steel
casing but does not seal against it. The turbulent ex- are sometimes used to protect the casing from the
haust steam is directed by the baffle to the exhaust full temperature. These take the place of the inlet belt,
connections and prevented from cooling the inner casing; delivering steam from the inlet penetrations to the
this reduces the temperature differentials and hence first stage nozzles.
stresses on the inlet end of the inner casing. Steam leaking Some overseas units have nozzle governing instead
through the gland between the inner casing and the rotor of the throttle governing employed on all large CEGB
at the inlet end is piped away to the exhaust connec- machines. With nozzle governing, the inlet belt is
tions, so the space between the casings contains divided into sections, each controlled by a separate
steam at exhaust conditions with a gentle flow being valve opening in sequence, resulting in a more com-
maintained by leakage through the outer casing gland. plicated casting and the need for stronger first-stage
The smaller pressure differential permits a thinner moving blades.
shell which, combined with the larger surface area of The stationary blading is carried in diaphragms
a double casing, allows quicker warming of the turbine which are supported and guided in the inner cylinder
on start-up. Thinner shells are also easier to cast and by keys near the horizontal joint and vertical centre-
are likely to have fewer defects. line, permitting concentric expansion. On modern
On some machines, reversed flow blading has been machines the tip seals and shrouding for the moving
adopted, where the steam is diverted back between blades are usually carried on an extension of the
the casings part way through its expansion, continuing adjacent diaphragm. Earlier designs had separate
through the final stages in the opposite direction. sealing strips supported between the diaphragms.
This arrangement gives a higher inter-shell pressure HP cylinders on wet steam machines, such as those
and temperature, reducing the stress on the hot inner on PWR stations, are different in design, being more
77
The steam turbine Chapter 1

INNER CASING

OUTER CASING

VERTICAL GUIDE KEY

THERMAL SKIRT
EXHAUST
STEAM

FIG. 1.92 Axial section of an HP cylinder


The features include: a double casing with blades supported in diaphragms in the inner casing, two inlet pipes symmetrically
arranged with two exhausts at the bottom, a baffle between the casings, keys between casings near the exhaust end, vertical
guide keys at both ends of the outer casing, thermal skirts on inlet pipes and glands between casing/rotor.

like standard IP cylinders. Further details are given for IP cylinders are similar to those for HP cylinders,
in Chapter 2. the steam being at a similar temperature but lower
pressure, which allows IP casings to be thinner. In
general, machines over 300 MW rating have at least
6.1.2 Intermediate pressure casings a partial double-casing covering the first few stages,
In modern reheat machines, the design considerations subsequent stages being supported by carrier rings
78
Turbine casings

construction with an inner casing containing dia-


phragm supports, bled-steam and water extraction
belts, and an outer casing directing the exhaust to
the condensers and providing structural support for
the inner casing (Fig 1.96). This is not always so,
however, particularly with pannier condensers where
a single casing may be employed. The large size of
LP outer casings combined with their low pressure
loading favours a fabricated rather than cast con-
struction. Inner casings which are more complex can
be fabricated or cast depending on economic consi-
OUTER
derations. All casings have bolted horizontal joints.
CASING
LP cylinders are virtually all of double-flow design
but vary greatly in layout due to the different con-
denser configurations. The latest practice for con-
INNER
densers is similar to early 'underslung' designs with
CASING
separate condensers underneath each cylinder, tubed
THERMAL SKIRT transversely, allowing easy access to both condenser
and LP cylinder. Foundation columns, bearing and
STEAM
INLET PIPE cylinder supports are located between condensers.
However, during the development of 500 MW ma-
chines, variations of the turbine and condenser ar-
FIG. 1.93 Cross-section of an HP turbine cylinder through rangement were tried, both to simplify the LP casing
the steam inlet pipes
Features include: nozzle boxes, bolts on outer casing with support arrangements, to increase the area and shorten
studs on inner casing, support paws between casings at the the exhaust connections. The four arrangements used
horizontal joint, with locating dowels top and bottom. were:

The axial condenser, which permits the LP turbines


(Figs 1.94 and 1.95). Both the inner casing and the to be supported on two parallel walls. Space has
carrier rings reduce pressure and temperature loading to be allowed beneath the generator for tube
on the outer casing and also allow a smooth outer withdrawal.
casing which is simple to design and manufacture
and has better thermal response. Carrier rings allow The bridge condenser, which bridges the gap be-
greater flexibility in design, as changes in blading tween the IP turbine block and the generator. It
do not require changes to the main casings, and one is constructed in the form of two deep girders,
casing design can serve different stage arrangements. which carry two parallel rigid soleplates for the
IP cylinders are often of double-flow design and LP turbine support. The condenser tubes are
always so on large modern machines. The decision mounted transversely. This construction uses a lot
for single or double-flow is primarily made on blad- of steel.
ing design and efficiency, but a double-flow casing also
has the advantage of eliminating the rotor gland at The pannier condenser, here the tubes are mounted
the high pressure end. As with the HP cylinder, the axially with the condensers themselves mounted
rotor is protected from the high temperature steam on either side of the turbine, so that the steam
at the inlet; a deflector ring directs inlet steam to is exhausted horizontally into the condensers. The
the nozzles, whilst a supply of cooler HP exhaust advantage of this arrangement is that the exhaust
steam is piped into the centre of the deflector ring steam flow from the turbines is facilitated, which
adjacent to the rotor. The deflector ring is supported cuts down the hood loss; in addition, construction
either independently on keys in the inner casing, or savings are made by having a reduced basement
from the inside of the first-stage nozzles. depth.
A cooling flow of steam around the partial inner
casing can be achieved by slight differences in the The integral condenser, which is a development of
blading in the two flows producing different pressures the pannier type; the condensers and LP turbine
either end; this keeps the outside of the casing and outer casings are combined in a single structure
the bolts cooler, allowing smaller diameter bolts to containing internal ribs to give it adequate stiffness.
be used. Access to the bearings is obtained via wells, and
access to the turbine inner shells is obtained by
removing the top cover plates. Here again, the
6.1.3 Low pressure casings basement depth is small and there is direct support
LP cylinders (Fig 1.96) are often of double-casing beneath the bearings.

79
The steam turbine Chapter 1

CENTRAL INNER CASING


EXHAUST
STEAM

CARRIER RING

OUTER
CASING

BLED STEAM BLED STEAM


TAPPING TAPPING

FlG. 1.94 Axial section of an IP turbine cylinder


Features include: the central inner casing with carrier rings either side, four exhausts on the top of the outer casing and two
bled-steam tappings on the bottom, thermal skirts on the steam inlet pipes, deflector ring to protect centre of rotor supported
by first-stage nozzles, vertical guide keys at both ends of outer casing, glands between outer casing and motor.

The LP exhaust casings are designed to give the be used, steam from the top sections of the exhausts
maximum possible area of flow for the exhaust steam, passing down the side of the casing and exiting to
so that the pressure drop is kept to a minimum. To the condenser in the centre of the lower casing in an
turn the huge volume of steam through 90 without underslung condenser design.
Punching', curved vanes are employed and, by careful In many designs of LP cylinder the outer casing also
design, these can be made to have a diffusing action provides support for the LP bearings; if not, then the
(i.e., they can make use of the kinetic energy of the bearing may be supported on a pedestal located in a
steam to produce a pressure difference) so that the recess at the end of the outer casing, in order to keep
pressure at the blading exhaust annulus is slightly the rotor length between bearings as short as pos-
lower than that in the condenser. sible. The outer casing contains structural members
To minimise the losses in the flow to the con- to transfer the weight to the support points at the
denser, the entire volume of the outer casing may ends, sides, or corners of the casing and to withstand
Turbine casings

SHAFT COOLING
STEAM INLET

STEAM INLET BRANCH STEAM INLET BRANCH

LEAK-OFF BRANCH- ^ JOINT RING

- PISTON RING
THERMAL SKIRT -
TOP HALF
DEFLECTOR RING

CAP NUTS

OUTER CASING -

-STUD BOLTS

INNER CASING

INNER CASING - BOTTOM HALF


DEFLECTOR RING

OUTER CASING

LEAK-OFF BRANCH

STEAM INLET BRANCH STEAM INLET BRANCH

SHAFT COOLING
STEAM INLET

FIG. 1.95 Cross-section of an IP turbine cylinder through steam inlet pipes


Features include: the deflector ring supported directly from the inner casing, and the shaft cooling steam inlets which have
been passed through the centre of the inner cylinder location dowels.

the atmospheric pressure, as the inside of the outer the construction and maintenance of the turbines,
casing is entirely at condenser vacuum conditions. but cause several problems. The flanges have to be
Watersprays are provided in the exhaust area of substantially thicker than the rest of the casing to
the casings to cool the exhausts during prolonged allow room for the bolts and bearing surfaces for
periods of light load or poor vacuum running. the nuts (Fig 1.97). Because of the extra thickness,
To prevent overpressurisation of the LP outer the flanges warm up less quickly than the rest of
casing, 'bursting disc' pressure relief valves are fitted the casing, setting up thermal stresses and distortion.
at the top of the casing. These can be minimised by a flange warming system
which passes steam through passage ways or holes
drilled in the flanges, warming them up at a rate
similar to the rest of the casing. The bolt holes
6.2 Horizontal joints themselves may be used for this, with small inter-
Horizontal joints in turbine casings are essential for connecting passages drilled diagonally between them.

81
The steam turbine Chapter 1

OUTER
CYLINDER

TURNING VANES

FIG. 1.96 Axial section of an LP turbine cylinder


Features include: fabricated inner and outer cylinders, bled-steam belts in the inner cylinder, turning vanes at the exhaust,
and glands supported by bearings with a bellows connection to the outer casing.

6.2.1 Flange design after a period in service, they are often found to
The forces taken into account in flange design are have distorted so that they no longer fit, typically
illustrated in Fig 1.98. The flange is assumed to seal leaving a gap between the flanges on the inside face.
at the inside edge, with the faces subject to a contact This is due to temperature differences through the
pressure greater than the internal cylinder pressure. casing on-load causing thermal stresses which relax
To minimise bending stress on the flanges, the bolt by creep. When off-load, opposite stresses are then
centreline is arranged tangential to the shell as can induced which distort the casing. This is generally
be seen in Figs 1.93 and 1.95; this produces the typi- confined to inner casings as there is very little tem-
cal thick narrow flange seen on HP and IP cylinders. perature differential through an outer casing on-load
The seal is obtained by simple metal-to-metal contact due to the external lagging. In addition, distortion
of fhe flange faces, after careful bedding on initial can occur due to relaxation of residual casting stresses.
assembly. If distortion causes a small flange leak on an inner
When flanges on HP and IP cylinders are unbolted casing, it may not be noticed unless large enough to

82
Turbine casings

FIG. 1.97 Work assembly of HP and IP cylinders of a 660 MW turbine. The lower half casings and rotors
are in position . Note the thick flanges and bolts closely spaced near the inside of the joint; the bolt holes in
the inner cylinder having square facings to support collars on the bolts (GEC Turbine Generators Ltd).

83
The steam turbine Chapter 1

head of the nut or entirely circular nuts with small


holes drilled in them, allowing them to be turned by
tommy bars. Because of friction, the necessary bolt
tension could not be achieved in the large diameter
casing bolts simply by turning the nuts, even if large
flogging spanners could be used. Instead, the nuts
HOOP TENSION
INCASING are first tightened by hand; the bolts are then heated
to expand them, and the nuts again tightened by
BOLT
FORCE hand through an angle calculated to give the correct
bolt-tension after the bolt cools down. By measuring
the bolt length before and after tightening, the ex-
tension (and hence the bolt tension) can be checked.
The bolts are heated by inserting an electric heating
rod into a thin hole drilled down the centre of each
bolt, thus heating the bolt without significantly warm-
REACTION ing the flanges (Fig 1.99). The same method can be
AT FLANGES used for undoing or retightening the bolts.
An alternative method of tightening the bolts is
by hydraulic tightening. This is similar to the heat-
ing method except that the elongation is achieved
by stretching it with hydraulic jacks reacting against
the flange or adjacent bolts, instead of by thermal
expansion. The hydraulic equipment is more cumber-

FlG. 1.98 Diagram of forces on casing flanges


The reaction at the flanges is higher at the outside of the
casing than the inside. The pressure between the flanges at
the inside must exceed the internal cylinder pressure to
prevent steam leaking between the joint faces.

have an effect on the measured efficiency of the


turbine, unless it is a wet steam turbine, when rapid
erosion of the joint face at the leak may occur.
LP inner casings may also distort substantially due
to their complicated design of webs, bled-steam belts,
etc., and to the substantial temperature differences
between different parts of the casing. This can lead
to crushing of the webs and distortion of horizontal
joints, though leakage can be minimised by incor-
porating spring sealing-strips in the half-joint faces.

6.2.2 Bolting
The design of bolting on HP and IP cylinders is
complicated by the need to place the bolts close to- FlG. 1.99 Thermal-tightening of flange bolts
gether to get the necessary distribution of stress in The heating element is inserted into the hollow bolt
to expand it. The nut is then hand-tightened by a pre-
the flange. Special nuts are used to allow close spac- determined amount and the bolt is allowed to cool, taking
ing, either cap nuts with faces cut on the reduced up its full tension as it contracts.

84
Turbine casings

some but has the advantage of allowing immediate by the barrel casing, it is possible to have exhausts
checking of the bolt tension without waiting for tem- at all four bottom corners of the lower casing.
peratures to stabilise, again by measuring the extension.
Inner cylinders are assembled with the lower half
of the casing resting in its final position inside the 6.3.3 IP exhausts
outer casing. It is thus awkward to use normal bolts IP cylinders generally have two or four inlets ar-
on the inner casing and studs are often used instead, ranged in a similar manner to the HP. The IP exhaust
being screwed into the lower casing and then tight- positions are determined by the positions of the
ened in the normal manner. Alternatively, a square crossover pipes to the LP inlets. With underslung
collar on the bolt at the horizontal joint allows the condensers, the LP inlets and crossovers are usually
lower nut to be assembled and tightened before the on the top half, hence IP exhausts are also at the
casing is positioned. top. However, arranging IP exhaust and LP inlet
HP and IP casings are only bolted together around pipes in the lower half casing reduces the amount
the external flange, but LP casings may also be bolted of pipework to be disconnected when cylinders are
along some of the internal webs if access through opened, and is thus easier if the condenser arrange-
manholes is possible. The bolts used on LP casings, ment allows it.
being of small diameter, are tightened by spanner
in the conventional manner to a controlled torque.
High temperature bolts operating above 370C
suffer from stress relaxation in use due to creep and 6.3.4 Use of thermal skirts and piston rings
such bolts need periodic retightening to prevent leak- To allow for differences in temperature where the
age of steam at the joint, typically after 30 000 h inlet pipes enter the cylinder, the HP and IP pipes are
service. Some nickel-based alloy bolts operating below attached to the outer casing through flanged thermal
538C may, however, increase their tension with time skirts (Figs 1.92 and 1.94). The skirt, which is bolted
and require slackening and retightening to prevent to the outer casing, reduces the conduction of heat
early bolt failure. A record of the history of all high from the inlet pipe to the casing and accommodates
temperature bolts is kept, so that they can be re- the differential expansion between the hot pipe and
tightened or replaced at appropriate times. Bolts must the cooler casing by elastic deformation. It also carries
be replaced before the accumulated creep strain ex- the pipe forces into the outer casing; minimising the
ceeds the creep ductility of the material; this often load on the inner. The outer casing is reinforced to
means changing steam chest cover bolts, but this is minimise stresses and thermal discontinuities at the
rarely necessary for turbine casing bolts. joint. Piston rings are used to seal the joint between
the pipe and the inner casing; these allow for differ-
ential expansion in the radial direction between the
casings and a small degree of transverse movement.
The piston rings may be of the conventional split
6.3 External connections type, housed in a groove, or unsplit rings in the
'stacked' ring design. The split type may be 'outspring-
ing', housed in grooves in the pipe and springing out
6.3.1 Steam inlets HP and IP against the casing; or 'inspringing', which are housed
between spacers in the casing and spring in to seal
Steam inlets to HP and IP cylinders are usually ar-
against the pipe. The 'stacked' design uses unsplit
ranged symmetrically in top and bottom casings, with
rings stacked in the gap between the pipe and the
the centreline of the inlet pipe along a radial direc-
casing. They are not sprung against either surface
tion in order to minimise inlet losses. Usually either
but are a close tolerance against the pipe and the
two or four inlets are used; with two, the pipes are
casing alternately (Fig 1.100). Several rings are used
vertical, making it easy to withdraw the inlet pipe
in series to reduce the pressure drop across each,
from the casing; with four, all the pipes enter at an
angle. and hence reduce steam leakage; however, there should
not be too many rings, as a lightly loaded ring can
vibrate and wear excessively. The split rings are made
of a high temperature creep-resistant material, such
6.3.2 HP exhausts as Stellite or a Nimonic alloy, in order to retain their
HP exhausts are arranged in such a way as to keep springiness; the unsplit rings are made from a low
the cold exhaust steam away from the hot inner cas- alloy steel. Stellite-coated bearing surfaces or Stellite
ing to reduce temperature differentials and stresses. inserts in the casings reduce wear.
Hence, on double-casing machines, a baffle is used The exhaust steam connections are attached directly
and all the exhausts are at one end. They are usually to the outer casing. When attached to the lower cas-
in the bottom half to facilitate dismantling. On triple- ing, where they are unlikely to need disconnecting,
casing machines, where the inner casing is protected they are simply welded to stubs on the casing.
85
The steam turbine Chapter 1

and additionally from either the IP turbine or the


boiler feed pump turbine. In current practice, steam
is not bled from the HP turbine except at the ex-
haust, although future designs with higher final feed
temperatures may bleed steam from the later HP
INLET
cylinder stages.
PIPE In LP cylinders (Fig 1.96), the steam is bled-off
into annular belts within the fabricated inner casing
from which it is piped to the feedheaters, bellows
being used to take up differential expansions between
inner and outer cylinders. The connection to the bled-
steam belt is usually made at the bottom; if made
elsewhere, a drain connection must be provided at
'OUTSPRINGING
PISTON RING
the bottom. The bled-steam connections are identical
in each half of the double-flow LP cylinder so that
changes in steam flow to the heater do not affect
the thrust forces on the rotor. However, the connec-
tions may not be the same on all LP cylinders on
a unit. If, for instance, bled-steam is required at
stage 2, stage 3 and stage 4 conditions, it may be
taken from each stage on each cylinder, or it may
be taken from stage 2 on one cylinder, stage 3 on
another and stage 4 on the third (for a three LP
cylinder machine). The latter method involves sim-
pler pipework but has the penalty of less interchange-
ability of spares between the cylinders. Usual practice
is to favour the arrangement requiring minimum spares
holdings.
IP cylinders usually only have one stage of bled-
steam from within the cylinder, although it may also
be taken from the IP exhaust.
On double-casing cylinders, the steam may be bled
FIG. 1.100 Inlet pipe piston rings between the inner casing and a carrier ring, or be-
The piston rings shown here, seal between the inlet pipe tween carrier rings, into a belt between the ring and
and the HP barrel and the inner casings in a triple-casing the outer casing. On single-casing IP turbines the
HP turbine Outspringing' rings are shown between the
pipe and the barrel casing, and 'stacked' rings between bled-steam belt is cast into the casing, with slots cut
the pipe and inner casing. to allow the steam to bleed from the main steam
path into the belt. The bled-steam pipework can then
simply be bolted to the outer casing. Many IP cyl-
inders have no bled-steam tappings, as steam is taken
6.3.5 LP cylinders from the boiler feed pump turbine instead; however,
Steam connections to LP casings are made with bel- latest practice with development of variable-speed
lows pieces to accommodate differential expansions. electric drives, is for electric boiler feed pumps and
The bellows are short sections of pipe with thin hence bled-steam is taken from the IP cylinder.
corrugated walls, allowing relative movements of the Steam bled from HP turbines in the future is likely
ends in both longitudinal and transverse directions. to be via a belt cast into the inner cylinder wall, with
With underslung condensers, a rigid bolted joint can connections similar to the HP inlet connections.
be used between the LP outer casing and the con-
denser, the condenser being mounted on springs to
support its weight but allowing the required flexi-
bility. Bellows can be used on the exhausts with a
floor-mounted condenser but are inconvenient because 6.4 Casing materials
of the large area of the exhausts and because the HP and IP casings, where temperatures over 350C
bellows, being flexible, transfer the vacuum forces to are encountered, are made from creep-resistant ma-
the cylinder and condenser foundations. terials. Two different low alloy steels are used; 2.25Cr
IMo for temperatures up to 538C and 0.5Cr 0.5Mo
0.25V for temperatures up to 565C. The 2.25Cr
6.3.6 Bled-steam connections material is slightly weaker and more ductile in creep,
Steam for feedheating is bled from the LP turbines but it is also tougher (i.e., less prone to fast fracture
86
Turbine casings

at low temperatures) and easier to weld. Casings in reaction from the rotor into the foundations. In some
these materaals are cast rather than fabricated be- cases, the paws are part of the lower half casing as
cause of the difficulty of quality control and like- illustrated, alternatively they may be part of the upper
lihood of thermal distortion in the thick sections half, simplifying the casting but necessitating tem-
involved. LP cylinder casings are generally fabricated porary supports for the lower half casing when the
from carbon steel, although the inner cylinder may be halves are unbolted. Vertical guides on the vertical
cast from spheroidal graphite iron. Large defects in centreline of the rotor act in conjunction with sliding
castings are ground out and repaired by welding, but at the paw faces to ensure that the outer casing re-
nevertheless the materials are chosen to have a high mains concentric with the bearing pedestal and rotor
tolerance to the presence of defects which may grow during expansion. Similar arrangements support the
during service. inner casing inside the outer, with paw supports on
High temperature bolts are either made from low either side to take the weight and torque reaction,
alloy steels designed specially for creep-resistant bolt- radial keys in the plane of the steam inlets permitting
ing, for example, Durehete 1055, or from nickel alloys concentric expansion only, and axial keys at the ex-
such as Nimonic 80A. The nickel alloys are more haust end allowing for differential axial expansions.
creep-resistant and stronger, allowing a more compact The paw supports of the outer casings contain trans-
flange with better thermal properties; however, they verse keys so that the HP and IP casings and bearing
are subject to stress corrosion cracking, particularly if blocks expand axially as one unit away from a fixed
wet or contaminated with sulphur compounds. Nickel point between IP and LP cylinders. The axial location
alloy bolts are thus used mainly on inner cylinders between the rotor and the casings is at the thrust
where the compact flange is most advantageous. bearing between HP and IP cylinders: this arrangement
Low temperature bolts on LP casings are made ensures that the close clearances between fixed and
from normal high tensile bolting steels. moving blades in these cylinders are affected as little
High temperature wet steam is considerably more as possible by differential axial expansion between
erosive than dry steam, consequently HP casings for rotor and casing on start-up and shutdown.
wet steam machines are either made from 2.25Cr
IMo steel with stainless steel cladding at the joint
faces or entirely from a higher alloy steel. 6.5.2 LP cylinder supports
The LP cylinder casings are supported on feet in
a similar manner to the HP and IP casings, but
because of their relationship with the condenser they
6.5 Support and alignment are limited in axial movement. Consequently they are
To achieve maximum efficiency in a steam turbine, either joined together and fixed axially to the foun-
only small clearances are permitted between fixed and dation at the centre or each fixed individually at one
moving parts at casing and diaphragm glands, and at end. This causes larger differential axial expansion
blade tip seals. These clearances must be maintained between rotor and casing than in the other cylinders,
under all operating conditions, so the inner and outer so the axial clearances are greater.
casings must be supported in such a way as to main- Diaphragms and carrier rings are located axially
tain concentricity with the rotor as they expand and within cylinders by circumferential grooves in the
contract. casings. They are maintained concentric with the cas-
ing by radial keys at the horizontal and vertical
The total axial expansion of a 500 MW turbine
centrelines.
rotor between cold and hot conditions is about 50
mm, occurring mainly in the HP and IP cylinders, The casings are all aligned by reference to the
where the temperature change is greatest. The casings horizontal and vertical centrelines of the rotor at each
are supported to allow axial expansion and yet main- bearing. The alignment of the rotor itself is discussed
tain the axial clearances between fixed and moving in Section 7.5 of this chapter.
blades which may be only a few millimetres. Main-
taining both concentricity and correct axial expansion
leads to a complicated system of sliding supports and
keys (Fig 1.101). 6.6 Casing and diaphragm glands
Glands are used to provide a steam seal between
fixed and rotating parts of the turbine; in particular,
6.5.1 HP and IP cylinder supports between the rotor and the diaphragms and between
HP and IP cylinders are fitted with 'paw' supports the rotor and the cylinder casing. The glands are of
at each end which rest on the bearing pedestals (Fig the labyrinth type, consisting of a series of fins on
1.102). The paws are horizontal with the palms aligned the inside of the diaphragm or casing in close proxi-
with the horizontal joint; they are well spaced towards mity to the rotor surface. Steam trying to escape
the outer edges of the casing, as they carry the torque between the fins and the rotor suffers a series of
87
The steam turbine Chapter 1

HP TURBINE IP TURBINE LP1 TURBINE LP2 TURBINE LP3 TURBINE

(f) (9)

A N T I - F R I C T I O N BEARING PLATE BRACKET LINER


CENTRE GUIDE KEY

LINER BEARING KEEP

KEY
No 1 BEARING PEDESTAL

(c) HP Cylinder centre guide key


(a) Pedestal guide key
(upper)

CENTRE GUIDE KEY


KEY
BRACKET

(b) HP Cylinder centre LINER


guide key (lower)

F /K
BEARING KEEP

BEARING KEEP

(d) HP Cylinder centre guide key (IP end)


(e) IP Cylinder centre guide key (HP end)

KEY,

RACKET
LOCKING
PLATE
^ S Q U A R E KEY
| \ * LOCATION BLOCK
BEARING PLATE SUPPORT PAD
HALF & HALF
DOWEL

BEARING KEEP (g) IP Cylinder palm (LP end)

(f) IP Cylinder centre guide key (LP end)

FIG. 1.101 Support and alignment keys for outer HP, IP and LP casings

88
Turbine casings

HP TURBINE IP TURBINE LP1 TURBINE LP2 TURBINE LP3 TURBINE


\/ W s/

(I) (k) (j) (h)

EXHAUST
DOWEL
HALF & HALF E X H A U S T BOTTOM
PACKER
DOWEL

FOUNDATION
STEELWORK

(h) LP frame supports

(j) LP Cylinder anchor

GUIDE BRACKET

LINER
GUIDE BRACKET

(k) LP frame centre guide key (I) IP Cylinder centre guide key to LP frame

BEARING PLATE

L O C A T I O N BLOCK

ANTI-FRICTION
BEARING PLATE BEARING
BLOCK

ANTI-FRICTION
BEARING PLATE

\\ BEARING
PEDESTAL

(m) HP and IP Cylinder palms (n) HP Cylinder palm

FIG. 1.101 (cont'd) Support and alignment keys for outer HP, IP and LP casings

89
The steam turbine Chapter 1

The insulation consists of up to 150 mm thickness


of mineral fibre which is applied either as fibre
'mattresses' or sprayed on as loose fibres, with a
binder to set them in position. The thickness is large-
ly dependent on the temperature of the surface to
be covered, enough insulation being used to reduce
the outside temperature to about 50C. Asbestos was
used extensively for sprayed insulation in the past,
but all modern insulation is asbestos-free, because of
the health risk of inhaled asbestos fibres.
The mineral fibre is held in position by wire mesh
CASING
which covers it and is attached to studs welded to
EXPANSION the outer casing and passing out through the mineral
fibre (Fig 1.103). If the mineral fibre is thicker than
FIG. 1.102 Detail of support for HP and IP outer casing 100 mm it is applied in two layers with an additional
wire mesh support between them. The outside wire
mesh is then covered with 6-8 mm of cement fol-
lowed by a thin coat of oilproof and waterproof
expansions which reduces its pressure in stages and sealant. A glass reinforced plastic may be used as
restricts the flow through the gland. A detailed ex- the sealant to provide suitable mechanical strength
planation of the working of glands and the different and life.
types is given in Chapter 2. The insulation extends over the horizontal joint
The HP cylinder has glands at both ends of the covering the bolt heads and has to be chipped off
outer casing and the inlet end of the inner casing before the casings can be separated: the joint relagged
(Fig 1.92). They are housed in gland carriers, which on reassembly.
are supported either on keys to allow differential ex- It is essential that oil is not allowed to enter the
pansion or simply on spigots in machined recesses lagging through gaps or damage to the covering, as
in the casing. hot oil-soaked lagging has been responsible for some
The HP glands are longer than those in other severe turbine fires.
cylinders because of the higher pressure drop required
across the gland, and are often divided into several
sections. The IP glands are similarly supported (Fig
1.94), but the LP glands may differ; if the bearings 7 Turbine rotors and couplings
are separate from the LP outer casing, then the LP
gland carriers may be supported from the bearings
and connected to the rest of the casing by a bellows 7.1 Types of rotor construction
piece (Fig 1.96). Four different types of rotor construction have been
The LP glands prevent air entering the cylinder, used on large turbine-generator units on the CEGB
unlike the HP and IP glands which prevent steam system:
escaping. Thus the LP glands need a continuous sup-
ply of higher pressure steam, whereas the HP and IP The monobloc or integral rotor, in which the wheels
glands need additional steam only at start-up. This and shaft are formed from a single-piece forging
is explained in detail in Chapter 2. (Fig 1.104(a)).
The gland carriers are split, like casings, along the
horizontal centreline and bolted together.

6.7 Lagging
The hot external surfaces of the cylinders are lagged,
i.e., covered with a thick layer of thermal insulation.
There are several reasons for this:

The loss of heat from the steam is reduced.


The thermal stresses in the outer casing are sub-
stantially reduced.
Danger to personnel is reduced. FIG. 1.103 Thermal insulation on turbine casing

90
Turbine rotors and couplings

Drum type rotor manufactured from solid or hollow


forgings (Fig 1.104 (c) and 1.104 (d)).

J nJlARAlUirLni The welded disc rotor (Fig 1.104 (e)). These rotors
are not too common in the UK, where they have
been applied to LP turbine rotors. Overseas ap-
plications have included HP and IP turbine rotors.

For various reasons, monobloc forgings are preferred


(a) Monobloc LP rotor but where the size has exceeded the forging capa-
bility, the built-up disc construction has been used.
The current 660 MW UK designs all have monobloc

rotor forgings.
Built-up rotors required very careful attention to
shrink fit and location geometries to avoid problems
in running and with fatigue cracking. While the discs
may have facilitated non-destructive testing (NDT),

V
the NDT capability on monobloc rotors has been
developed to meet all the needs. With the monobloc
method of construction, the LP rotors are more rigid,
(b) Built-up disc rotor resulting in better dynamic behaviour. 660 MW plant
employs rotors of this construction almost exclusively,
and experience has been good.
It was the practice to provide test material from a
bore-hole down the forging axis but, as confidence
in forging practice and material properties has in-
creased, the central bore has been omitted on some
current designs. The benefit of reduced stress levels
gives enhanced confidence in the longer-term fatigue
(c) Monobloc drum IP rotor (reaction blading)
integrity of the rotor.
Welded rotor construction has the advantage of
smaller forging components at the expense of high
integrity welding. The welded design, having been
adopted by countries lacking an intrinsic large forging
capability, has been successfully applied by them to
HP, IP and LP rotors. There are a limited number
L
[fuirii^ nnry-y of welded LP rotors in service in the UK.
High temperature drum-type rotors, manufactured
(d) Monobloc drum IP rotor (impulse blading) from hollow cylinders bolted to stub shafts, have
been prone to differential creep and have been re-
placed by monobloc drum rotors in current designs.
Where constraints on last-stage blading design dic-
tate, double-flow cylinders replace the single-flow
design as used in the HP turbine. Double-flow IP
and LP turbines are standard for 660 MW designs.
With the single-flow HP turbine, the axial thrust has
to be balanced to some extent by a 'balance piston'
to reduce thrust bearing loads: for reaction turbines
particularly (with a high pressure drop across the
moving blades) the balance piston is of substantial
(e) Welded disc LP rotor proportions, as shown on Fig 1.105.
In contrast, an HP turbine rotor with impulse blad-
FIG. 1.104 Types of turbine rotor construction ing is illustrated on Fig 1.106. This arrangement is
characterised by the reduced number of blading stages
and larger blading pitch diameter compared with the
The built-up or shrink-on disc rotor, consisting reaction design. In addition, a very much reduced
of a forged steel shaft onto which separate forged balance piston is necessary, as the axial thrusts are
steel discs are shrunk and keyed (Fig 1.104 (b)). lower.

91
The steam turbine Chapter 1

CYLINDER CASING

SHAFT

No.1 GLAND

I.R TURBINE SHAFT

No.1 BEARING

GLAND STEAM ^
LEAK-OFF EXHAUST TO
PORTS REHEATER

FIG. 1.105 Section through a monobloc HP turbine with reaction blading

7.1.1 Design for high temperature operation operation, due to the cyclic reversals of thermal stresses
The increase in size of large turbines over recent resulting from the transient temperature gradients es-
years, together with the higher steam inlet conditions tablished during the heating and cooling periods. The
often used, has made the design of turbine components thermal fatigue problem is accentuated by the increased
in contact with high temperature steam more critical. scantlings on larger machines which result in higher
Fundamental considerations include creep and thermal thermal stresses occurring within components during
fatigue, both requiring control of the temperature transient conditions.
distribution in components during steady and transient The inlet sections of HP and IP rotors are the
operation. At the design stage of high temperature critical areas for thermal fatigue, demanding careful
turbine components, temperatures and thermal stresses attention to design detail and operational practices.
are assessed to ensure that creep, which occurs as a A typical cycle of events undergone by material in
function of time, temperature and stress levels do the critical region of a turbine rotor is illustrated in
not exceed specified values and that thermal stresses Fig 1.107. The material undergoes plastic strain com-
due to cyclic operation are not of sufficient magni- pression during the heating period to point 1 on the
tude to cause thermal fatigue during the life of the diagram, at which point the thermal stress has reached
turbine. its maximum value. The stress then falls as the tem-
Creep can be limited by close attention to detailed perature of the rotor interior increases towards that
geometry in critical areas, such as blade fastenings, of the surface, causing the stress and strain at the
in order that stress-concentrating features are con- stress concentration to move along the line 1-2. At
trolled. Rotor stresses generally are kept low in re- point 2, the nominal thermal stress is virtually zero
lation to the high temperature mechanical properties and stress at the concentration is the residual stress
of the creep-resisting steels employed. arising from the plasticity which occurred at 1. During
Thermal fatigue is associated with changes in op- the period of full-load running, the temperature of
erating conditions, such as occur during two-shift the rotor is such that this residual stress relaxes to

92
Turbine rotors and couplings

HIGH PRESSURE
STEAM INLET
(TOP)

STEAM INLET CONNECTION (TOP)


ROTATING BLADES
OUTER CASING HP-IP COUPLING

No.2 BEARING / No.3 BEARING


SHAFT GLANDS (FRONT)

No.1 BEARING

No.1 PEDESTAL

HP ROTOR
No.2 PEDESTAL

THRUST BEARING

SHAFT GLAND (REAR)

INNER CASING GLANDS


INNER CASING SLEEVE CASING
HIGH PRESSURE STEAM INLET CONNECTION (BOTTOM)
STEAM INLET
(BOTTOM)

FIG. 1.106 Section through an HP turbine with impulse blading

point 3, due to creep. The shutdown or load reduc- same steam temperature at the inlet as HP rotors
tion which follows, causes cooling of the rotor surface and, because of their larger diameters, are subject to
and consequently tensile thermal stress in the surface larger centrifugal stresses. The bore of an IP rotor
layers. The stress-strain condition at the concentration under the first few stages is therefore a critical region
then follows the line 3-4 with possibly some further for creep.
plasticity, in tension, at 4. As the rotor temperature On large machines operating with reheat steam at
becomes more uniform at the part-load or shutdown 565C, forced cooling of the rotor by cooler steam
condition, the material stress-strain moves along the is employed. This method is particularly effective in
line 4-5 to point 5. At this point, the rotor tem- cooling the bore under the first wheel (Fig 1.109);
perature will generally be too low for significant creep with further increases in turbine size, additional cool-
to occur and there is no stress relaxation, such as ing is needed to cool the bore of the second wheel.
occurred between 2 and 3. This can be effectively provided by introducing a sec-
When the material at the point of strain concen- ond cooling steam flow between the first two stages,
tration is held at reasonably high stress (point 3), so that gland leakage steam is replaced by cooler
there is a damaging effect of the hold-time due to steam.
irreversible creep strain. The effect of this is shown
on Fig 1.108.
Thermal fatigue, which shows as surface cracks,
can occur when there is a net amount of plastic strain
7.2 Rotor materials
in the thermal cycle. Material property curves are
derived for combinations of plastic strain range, num- Developments in the field of steam turbine design
ber of thermal cycles and hold-time at the peak of would not have been possible without corresponding
the tensile part of the cycle. materials developments. The development of alloys
with properties which provide good creep-resistance
at high temperature and of other alloys with good
7.1.2 Cooling of IP rotors mechanical and high fracture toughness has been one
The IP rotors of reheat turbines are subject to the area of considerable metallurgical accomplishment.

93
The steam turbine Chapter 1

where E = creep strain


STRAIN DURING
UNLOADING = stress, N/mm2
t = time,
T = absolute temperature, K
n, m and B are material constants

Typically, high temperature turbine design is based


on a creep strain of 0.2% during 105 h of operation.
STRESS Typical curves of time to produce 0.2% strain and
rupture are shown on Fig 1.110 for Cr Mo V rotor
RELAXATION
DUE TO CREEP
(DWELL TIME)
steel, and show the powerful effect of stress and
3 temperature in controlling creep strain.
While the best possible creep properties are required
on both HP and IP rotor forgings, the HP problem
is simplified by modest dimensions of HP rotors. The
IP rotor poses a much more serious problem, es-
pecially in turbines employing a reheat cycle. Full
steam temperature is encountered on discs at the IP
/ / inlet stages, which have larger diameters and blades
/ / / than equivalent stages on the HP rotor exposed to
/ / / steam at the same temperature. Both at the rim and
/ / /
/ * I\ the bore, the stresses are such that steam cooling may
\ / i I \ be necessary, even with steels having the best creep
\/ i 1 properties.
\l * y \
The reduced temperatures encountered at the last
two stages of the IP turbine are offset by increased
STRAIN DURING
LOADING bore stress due to the longer blade length, which
demands an adequately high proof strength.
The requirement for good creep strength and the
TOTAL STRAIN RANGE necessary proof strength in conjunction with a rotor
forging of heavy section is achieved on current rotors
FIG. 1.107 Typical stress-strain cycle at rotor surface
by the use of lCr IMo 0.25V steel alloy.

7.2.2 LP rotors
Also, the ability to produce components for use both For low temperature rotors, the main requirements
at high and low temperatures, having large physical are relatively high tensile strength combined with high
size and uniform material properties which meet ri- toughness.
gorous inherent defect acceptance requirements, testi- The 3.5Ni Cr Mo V monobloc rotor forging is
fies to the improvements in steel-making techniques. currently used as it avoids the complication of shrink
fits in the case of built-up rotors. The manufactur-
ing facilities and forging technology required for the
7.2.1 HP and IP rotors manufacture of monobloc rotor forgings of very large
High temperature rotors are required to have a com- size and weight are fully able to meet the designers
bination of creep strength, rupture strength and duc- requirements. No limitations are identified for the
tility. This is conferred by rotors manufactured from forgings of 2-pole 900 MW units currently under
forged Chromium Molybdenum Vanadium steel (Cr consideration.
Mo V), a ferritic material which provides the best The use of vacuum degassed ingots, single and
possible creep properties. Creep is a high temperature double upsetting procedures and the use of larger
phenomenon and traditional design methods involve presses capable of such forging operations, have all
the selection of materials which provide the required contributed to a marked improvement in quality of
creep strength and creep rupture ductility during the large LP rotor forgings. Rotor forging for 660 MW
required design life. designs of 100 tonne forged weight, produced from
ingots twice this size, are provided for LP rotors.
Vacuum degassing has eradicated the former pro-
The equation for creep is of the form E = c^^e" 8 7 7 blems of hydrogen embrittlement cracking and gives
94
Turbine rotors and couplings

10

16 HOUR DWELL

ZERO DWELL
G

<
1.0

<
CE

110 HOUR DWELL

0.1 I 1- i
10 102 103 104
CYCLES TO CRACK INITIATION

FIG. 1.108 Typical strain range plotted against a number of thermal cycles to crack initiation at 540C,
showing the effect of dwell time

spection of the axial bore with ultrasonic examina-


tion was the accepted approach to non-destructive
examination of the rotor forging whose simple geo-
metry, in the rough machined state, permits accurate
location and diagnosis of any internal defects pro-
ducing ultrasonic indications. Ultrasonic techniques allow
the material in the vicinity of the bore hole,
which is subjected to the highest tangential stresses
during overspeed, to be examined critically. This pro-
vides reassurance of integrity in circumstances where
the complex geometry of the machined rotor prohibits
< 495 H the use of external examination.
The purpose of the bore was to permit internal
inspection, but it also removed some of the central
part of the forging which is where defects or segre-
gation in the original ingot might be located and
provided the opportunity to obtain fracture appear-
ance transition temperature measurements.
Inspection techniques have now developed to the
*25 450 475 500 extent where external ultrasonics can replace the former
COOLING STEAM INLET TEMPERATURE, C bore inspection. This is very significant as the LP
rotor is subjected to high centrifugal stresses, the
last-stage disc being the most heavily stressed part of
FIG. 1.109 The effect of cooling steam temperature on the the turbine. The centrifugal load of the large rotating
maximum IP rotor bore temperature under the first disc blades sets up a tensile stress in the rim of the disc,
and this stress increases with decreasing radius, its
maximum value being at the hub. The larger the bore
of the hub, the larger the maximum stress. If the
good fracture toughness. Ultrasonic inspection techni- bore is small, the hoop stresses are lessened.
ques ensure freedom from any internal discontinuities Ni Cv Mo V steel containing up to 3.5% Ni has
greater than 5 mm effective diameter. been used for both shafts and discs for built-up LP rotors
The parallel application of visual and magnetic in- and is the first choice to achieve the tensile properties
95
The steam turbine Chapter 1

provides the necessary framework for the safe operation


of LP turbines.
3.5% Ni Cr Mo V steel has a low value of FATT.
In the water-quenched and tempered condition, and
with careful control of composition, high tensile pro-
perties can be matched with a FATT well below
ambient temperature and a consequential high fracture
toughness.

7.3 Rotor testing and balancing

7.3.1 Thermal stability


During the manufacture of turbine shafts, great efforts
are made to ensure that the physical properties of
the forging do not change in service. There are three
types of instability:

Permanent, due to asymmetrical coefficients of


expansion across the diameter. This is avoided by
close metallurgical control of the forging process.

Temporary, due to residual stresses in the rotor.


This is eliminated by stress relieving the rotor, both
before and after machining, in a special furnace
in which the shaft is rotated.

Transient, due to differences in conductivity and


emissivity. The use of ferritic materials throughout
has obviated the difficulties that occur.

An unstable shaft is likely to develop a 'bow' in


service, producing out-of-balance forces and conse-
quential vibration.

400 450 500 550 7.3.2 Overspeed testing


TEMPERATURE, C
A 20% proof overspeed test is specified on all large
turbine-generator rotors at the time of manufacture.
FIG. 1.110 Typical 0.2% strain and rupture properties of This allows the rotor balance to be satisfactorily
Cr Mo V steels for rotor forgings
established throughout its operational speed range,
thereby providing sufficient margin over normal op-
erational overspeeds caused by electrical grid system
necessary for large monobloc rotors. Welding tech- disturbances, and the regular 10% overspeeds experi-
niques are established for the design of fabricated enced during overspeed bolt testing. Overspeeding the
LP rotors employing a series of solid discs. Alloy rotor also proof tests the forging, as it applies centri-
steels for this application are subject to the conflicting fugal stress in excess of that experienced during normal
demands for tensile strength and weldability. operation, thereby providing a quantifiable measure
Since LP turbine rotors may run at temperatures of the margin against spontaneous fast fracture.
not much in excess of ambient, the provision of
safeguards against the danger of brittle fracture is
important. The use of materials for discs, shafts and 7.3.3 Rotor balancing
monobloc rotors of the lowest possible fracture ap- When assembled with blades, the rotor is balanced
pearance transition temperature (FATT) and subject both statically and dynamically. For built-up rotors,
to stringent non-destructive testing and fracture me- each bladed disc is balanced individually prior to
chanics assessment (see Section 7.3 of this chapter) assembly.

96
Turbine rotors and couplings

Static balance means that the weight is evenly dis- rotors via access holes in each gland housing. Figure
posed around the axis of the shaft. It can be checked 1.111 shows the balance planes and site trim balance
by rolling the rotor on horizontal knife-edge supports. arrangements for a typical 660 MW LP rotor.
Dynamic balance means that the moments of the
out-of-balance weights along the axis about either
bearing add up to zero. This is checked by spinning MOVING BLADE STAGES
the rotor on resilient bearings, detecting the vibration, REAR
and adding or subtracting weights until the vibration FRONT 4 2 1 3

is negligible. 5

A modern balancing machine enables balancing to


be carried out with a high degree of accuracy and
eliminates to a large extent the trial and error pro-
cesses used in the past.
Rotors are normally balanced at low speed (400 r/min)
and weight adjustment made in two convenient planes,
one at each end of the rotor. This adjustment may
be by varying screwed plugs in tapped holes, or by BALANCE WEIGHT ARRGT.
adding balance weights at specific circumferential po- STAGE 1 & 5 FRONT & REAR
DISCS BALANCE WEIGHT ARRGT.
sitions. Tee-slots are machined circumferentially in FRONT & REAR COUPLING
FLANGE GROOVES
the periphery of the rotor front and rear half-coupling
flanges to permit the weights to be positioned and (a) Balance planes
retained.
The aim of balancing is to reduce the amplitude
of vibration to a tolerable level, which can be taken
to be about 25 at the bearing pedestals.
As rotors become larger and more flexible, it is
increasingly important to understand their modal be- ROTOR BALANCE
WEIGHT ACCESS PORT
haviour so that balancing can ensure smooth running COVER PLATE
over the speed range.
The larger LP rotors and generator rotors having GLAND/PEDESTAL
LOCATING KEYWAYS
critical speeds below running speed are overspeeded
and, if necessary, balanced in the fully-bladed con-
dition in a vacuum chamber, where they can be run
without being overheated due to windage.
In the vacuum chamber and the high speed pit, rotors
are run in bearing bushes and pedestals as nearly as
possible simulating site conditions. Facilities are avail- GLAND CASING
able for measuring journal or pedestal vibration and
balancing can be carried out at closely controlled
speeds anywhere in the range required. Standards of ROTOR
balance obtained during the factory testing must pro-
vide sufficient vibration margin to take account of
site conditions. Balance on-site is likely to be affected
by variations in the stiffness of the bearing, possible (b) Site trim balance arrangements
shaft misalignment and the coupling of the indi-
vidually balanced rotors to form the complete shaft
system. FIG. 1.111 LP rotor balancing facilities
Multi-plane balancing is carried out at speeds
associated with each critical within the running range.
Balance weights are attached to correct imbalance in
any of the modes related to these criticals, as well 7.3.4 Critical speeds
as for imbalance in the modes of up to two criticals A stationary shaft supported between bearings has
above running speed. Typical HP and IP turbines a natural frequency of vibration, depending on its
are provided with two balance planes. The LP rotors diameter in relation to the distance between bearings.
have three balance planes and generators have faci- If its speed of rotation corresponds to its natural
lities to attach balance weights in almost any axial vibration frequency, the residual out-of-balance forces
position. are amplified, and can build up to a dangerous extent.
Should site vibration levels exceed those specified, This critical speed is either above or below running
provision is made for site trim balancing on the LP speed, depending on rotor construction. If below, the

97
The steam turbine Chapter 1

shaft is regarded as flexible, and care must be exer- critical speeds of a complete line are shown as func-
cised during run-up to ensure that the critical is tions of bearing flexibility, expressed as the deflection
passed as quickly as possible. of an equivalent spring under the static load upon
Critical speeds decrease with increased rotor length the bearing.
and with reduction in rotor diameter. On current large
units, the trend is to provide a rigid rotor (criticals
above running speed). Because of the increased rotor 7.3.5 Rotor fast fracture risk assessment
length (necessary to accommodate the required num- There have been major advances in the quality of
ber of moving blade stages) on large units, rigidity monobloc rotor forgings (see Section 7.2 of this chapter)
has been accomplished by an increase in diameter. and in understanding the problems of brittle fracture.
The rotors of large machines are joined by solid Rotor forgings can now be produced with greatly
couplings, so that the complete shaft, which may enhanced fracture resistance and the presence of sig-
comprise seven individual rotors, has to be treated nificant defects can be readily detected ultrasonically.
as a whole. Each rotor is supported on two bearings However, large steam turbine rotor forgings cannot
which are not simple supports. The hydrodynamic be produced entirely free of small, residual defects
oil films have flexibilities that significantly affect the and, for the high temperature rotors under consi-
critical speed of the shaft. In Fig 1.112, calculated deration, the forging ductile/brittle transition tem-

4000

3000

Q
LU
LU 2000
Q.
C/D

1000

0.02 0.04 0.06 0.08 0.10


BEARING DEFLECTION, mm

FIG. 1.112 Critical speeds of a complete line of rotors, calculated as a function of bearing flexibility
Each curve is associated with a particular span in which the maximum amplitude occurs. The black curves (a and h) refer to
the modes in which the maximum amplitude occurs within the generator span and are called the first and second criticals of
the generator. Similarly, curve (g) refers to the exciter span, curve (b) to the HP span, curve (c) to the IP span and curves
(d, e, 0 to the associated LP span.

98
Turbine rotors and couplings

peratures are not significantly below the temperature High temperature steam turbine rotors operate in
range experienced in operation. The possibility of a the creep range and cracks within them could there-
rotor brittle fracture cannot be dismissed without a fore grow under steady loading. Rates of growth
careful assessment. under creep can be correlated with the linear elastic
Having carried out a 100% volumetric NDT in- fracture mechanics parameter K, via an equation of
vestigation, the defects identified must be assessed the form (see Fig 1.114):
for acceptability. Acceptable defect size is defined
primarily by the requirement that it shall introduce
no risk of rotor brittle fracture in service. The initial
defect assumed on the basis of the inspection stand-
ard will be subjected to centrifugal and thermal stress
cycling. Stress cycling could cause the defect to grow
by fatigue. Extensive testing of materials has permitted
crack growth rate to be expressed in fracture me- X 550C
chanics form (see Fig 1.113). O 525C
475C

10 J

TURBINE STEEL DATA


' SCATTERBANDAT20C

E 10

10 40 60 80 100
DELTA K, MN/m 3

-r i r
20 30 60 70 80
40 50
FIG. 1.113 Typical fatigue crack growth data for various
K, MN/m 3 /2
turbine steels between 100 and 550C

FIG. 1.114 The effect of temperature on creep crack


da/dN = CAK" growth resistance of a turbine rotor forging

where a = crack length


= cyclic stress intensity range da
C, m = constants = AKn
dt

The operational duty of large generating plant is where A, n constants


such that upper bounds can be reliably established K stress intensity
for stress cycles. In actual service, the stresses during t time
start-up are limited by established operational pro-
cedures (see Chapter 2) to protect the plant against
high strain fatigue. The total fatigue growth can then The design criteria normally adopted for high tem-
be calculated on the basis of the upper bound stress cycles perature turbine rotors limits the maximum rotor
and combined centrifugal and thermal stress. stress in relation to the 105 hour creep rupture stress

99
The steam turbine Chapter 1

and limits the accumulated creep strain to 0.2% in growth during the specified lifetime service, survive
105 hours, ensuring that the stress in critical high without failure caused by instantaneous fast fracture.
temperature regions is acceptably small. Calculated This will depend on whether the extended defect is
creep crack growth is therefore small and may be longer or smaller than the critical defect size calcu-
simply added to calculated fatigue crack extensions. lated for the most adverse combination of events.
The region of maximum combined centrifugal and To further complicate the assessment, variations of
thermal stress, near the rotor centreline, coincides with rotor temperature during machine start-up produce
the region where, for reasons of ingot cooling and a corresponding variation in rotor forging fracture
heat treatment, the material fracture toughness is toughness properties which influence the instantan-
lowest. Valid plane strain fracture toughness specimens eous critical crack size. Assessments must therefore
cannot be obtained without removing an unacceptably be undertaken at each critical operating condition
large diameter core and samples taken elsewhere may for complete confidence.
not provide a reliable basis from which to estimate
centreline properties. Consequently it is most common
to measure toughness indirectly by using Charpy FATT
specimen results. Established correlations between FATT
and fracture toughness (see Fig 1.115) are used to 7.4 Couplings
determine a KIC for the rotor material. The need for couplings arises from the limited length
In all cases, the crucial judgement to be made is of shaft which it is possible to forge in one piece and
whether the rotor forging can, given the longest fea- from the frequent need to use different materials for
sible initial crack and maximum fatigue and creep the various conditions of temperature and stress. The

160 X 150

150
3V2 NCMV ROTORS

X 1 CMV ROTORS
130

130
120

^ 100
it
90
E

1 90

80 x
xxxx
x X x w
# x
xX
70 | x
y>
60

xX i -
X X
XX X XX X -
60 H 6600

55
X _
nin) 60-(T-FATT)
x
" (JONES'CORRELATION)
X % X x xtfxx*
X XX X x>

X X x x
40

30

I 20
-200 -180 -160 -120 -100 -80 -60 -40 -20 20
TEST TEMPERATURE (FATT),C

FIG. 1.115 Relationship between KJC and FATT for rotor materials

100
Turbine rotors and couplings

multicylinder construction of large turbine-generators


necessitates the use of a coupled shaft system.
Couplings are essentially devices for transmitting
torque but they may also have to allow relative angular
misalignment, transmit axial thrust and ensure axial
location or allow relative axial movement. They may
be classified as flexible, semiflexible or rigid. On
smaller turbine-generators (i.e., up to 120 MW) semi-
flexible and flexible couplings were commonly used,
but for large turbine-generators it is now common
practice to use rigid couplings.

7.4.1 Flexible couplings


These are capable of absorbing small amounts of an-
gular misalignment, as well as axial movement. Double
flexible couplings can also accommodate eccentricity. (a) Claw coupling

Figure 1.116 shows some designs in common use.


The claw coupling, which may be single or double, is
robust and slides easily when transmitting light load;
on heavy load, however, friction causes it to become
axially rigid. The Bibby coupling is satisfactory up to
medium sizes and provides (in addition to the other
features) torsional resilience, the torsional stiffness
increasing with load.
The multitooth coupling transmits torque by inter-
nal and external gear teeth of involute form, which
are curved to accommodate angular misalignment.
All these couplings require continuous lubrication,
normally obtained from a jet of oil feeding into an
annular recess, from which it is fed centrifugally to
the coupling teeth through drilled passage-ways.

7.4.2 Semiflexible couplings


This type of couplings will allow angular bending
(b) Multi-tooth coupling
only. They require no lubrication and consist of a
bellows piece having one or more convolutions. Figure
1.117 shows a semiflexible coupling.

7.4.3 Rigid couplings


On large turbines, the high torque to be transmitted
renders the use of flexible couplings impracticable.
Consequently, it is now normal practice for rigid
couplings to be employed between the turbine cyl-
inders, so that the turbine shaft behaves as one con-
tinuous rotor.
The long shaft that is formed naturally bends under
its own weight to form a natural catenary (see section
7.5 of this chapter). Because of this, the use of rigid
couplings means that the shaft alignment must be set
to ensure that the coupling bending moment forces
are minimised.
Rigid couplings are either integral with shaft forg-
ing (monobloc) or are shrunk on to the shaft. It is
(c) Bibby coupling

now common practice for the turbine rotors to have


monobloc half couplings. Shrunk-on couplings have FIG. 1.116 Flexible couplings

101
The steam turbine Chapter 1

Half couplings, which are forged separately from


the shaft, are assembled by heating and shrinking
them on to the shaft. Dowels are then inserted be-
tween the bore of the coupling and the diameter of
the shaft. For additional security against axial move-
ment of the coupling, a screwed ring, secured by a
locking screw, is fitted to the shaft end outboard of
the flange. An oil injection point may be provided
on the coupling through which oil can be supplied
under pressure to one or two annular grooves in the
coupling. This allows the coupling to be 'floated' to
ensure that it is seated correctly following the shrink-
on procedure and also assists removal. Figure 1.119
shows a typical arrangement of a shrunk-on type
half coupling with oil injection facility, bolted to a
monobloc half coupling.
Fill. 1.117 Semiflexible coupling Earlier designs of shrink-on couplings employed a
tapered seat, with a corresponding shaft taper. With
this type, an oil injection system was used to remove
the coupling from the shaft.
been used on turbines and still are used on the gen-
A forged steel spacer plate is normally fitted in
erator. They allow the couplings to be taken off for
each coupling to provide a means of axial adjustment
the removal of turbine rotor discs, or the generator
of the rotor relative to the cylinder. This ensures that
rotor endwinding retaining rings (end bells). To mini-
operational design clearances between the stage dia-
mise stress concentration in the coupling region, the
phragms and the rotor blades are always maintained
monobloc design of half coupling has a large transi-
and also facilitates rotor interchangeability. The spacer
tional fillet radius. Figure 1.118 shows a typical
plate is annular in shape and dowelled to one half
monobloc coupling.
coupling and secured by screws with countersunk
heads. The spacer plates must be sufficiently robust
to avoid distortion.
SPACER PLATE
The couplings are connected by fitted bolts which
are arranged so that torque is transmitted by a com-
RECESSED HEADS
bination of axial clamp load (resulting in friction at
the coupling faces) and radial grip (resulting in shear
TO REDUCE
WINDAGE _ load on the cross-sectional area of the bolt). The
bolts are tightened in a controlled manner to a pre-
LARGE determined extension. The use of fitted bolts means
FILLET RADIUS jj
that some final on-site reaming of the bolt holes is
necessary at the assembly stage, which can make this
a prolonged operation. In an attempt to reduce as-
sembly time, it is now normal practice only to 'fit'
sufficient bolts to enable system fault torques to
be transmitted without damage to the bolts. The re-
ROTOR AXIS
maining bolts are installed with larger clearances to
permit speedier assembly.
Couplings should be designed to withstand a close
up three-phase fault or out-of-phase synchronising
without damage. The highest torque under these con-
ditions (typically 4 - 5 times full load torque) occurs
at the generator/turbine coupling and would almost
certainly cause Stepping' of the fitted bolts.
To further reduce the assembly time of couplings,
hydraulic bolt fitting techniques have been developed.
These have the advantage that bolts can be fitted
quickly and also removed quickly without damage to
the bolt hole or the bolt.
The standard coupling bolts have cylindrical heads,
with an internal hexagon for tightening, and are re-
FIG. 1.118 Rigid monobloc coupling cessed into the coupling to cut down windage losses
102
Turbine rotors and couplings

OIL INJECTION
LOCKING SOCKET SCREW POINT

GRUBSCREW

BALANCE WEIGHT
GROOVE

DOWEL PINS

COUPLING NUT

MONOBLOC SHRUNK ON
HALF COUPLING FLANGE HALF COUPLING FLANGE

FIG. 1.119 Typical arrangement of a shrunk-on half coupling

and noise. Each coupling is normally surrounded loading and hence alter the shaft vibration behaviour.
by a stationary steel guard to reduce windage heat- A long shaft bends naturally under its own weight
ing of the adjacent pedestal and the creation of oil to form a catenary, but nevertheless revolves around
mist. its curved centreline during rotation. The alignment
is arranged so that the shaft system has minimum
bending moments at the shaft couplings. The catenary
depends solely on the mass and stiffness of the shaft
7.5 Rotor alignment system. Figure 1.120 shows a typical shaft catenary
The main objective in setting and maintaining rotor for a large turbine-generator.
alignment is to achieve satisfactory dynamic behaviour During initial erection, bearings are set at appro-
of the running shaft line. priate heights relative to one another to form the
Excessive misalignment can affect the vibration catenary shape.
behaviour of the multi-bearing shaft line. It imposes The final bearing height must ensure that adjacent
an effective bending moment at the couplings which coupling faces are square and true to one another, so
acts like a rotating out-of-balance. Changes between that there is no transmission of bending moment
hot and cold running vibration behaviour may be through the coupling. Final adjustment of bearings
indicative of misalignment, with the effect showing must be made with all the cylinders fully assembled
as a once-per-revolution vibration. Very drastic mis- and all pipes, which may exert a strain on any turbine
alignment may have the capacity to cause bearing un- cylinder, fully assembled and attached to that cylinder.

103
The steam turbine Chapter 1

HP CYLINDER IP CYLINDER LP.1 CYLINDER

No.1 PED No.2 PED No.3 PED


I & o
z 7 z z
K
< <
LU III < <
LU UJ
CD 00
OU CO
m CD
*< m
o o o
| Z Z z Z
(^ o> C^ 1

*
HORIZONTAL JOINT
T 1 0FLP.2
t f OUTER CASING

E E E
E F E F
b E F r^
R
CM ^ CO co
CO
CO
*~ *-
CO C\J CM

44469mm
OVERALL LENGTH
^
FIG. 1.120 Typical shaft catenary for a large turbine-generator

7.5.1 Alignment technique wave output as the shaft is rotated. To use this tech-
The basic intention is to have zero shear and bending nique fully, it would be necessary to establish a datum
moment at the couplings, so that drivng torque is at each coupling for a properly aligned machine, and
the only force transmitted. This means that the shaft to carry out a calibration exercise to see how bending
centrelines must be coincident at the point where the stress is affected by shaft alignment changes.
coupling faces meet, and that the axes of the two Low power laser-based optical alignment techniques
shafts must be parallel at the same point. Using one can also be used with the shaft fully coupled. These
rotor as a datum, it is possible to set the next rotor are suitable for initially setting up the pedestals to
relative to the datum rotor, using coupling gap and the required catenary. These techniques have the dis-
periphery measurements, and so on down the line. advantage that, when adjacent turbines are operating,
To carry out gap measurements, it is necessary the resulting atmospheric disturbances and structure-
to separate the couplings slightly. The gap between borne vibration may preclude their use.
the coupling faces is then measured at a number of Alignment of the shaft necessitates the outer bear-
points around the rotor, for a number of different ings being raised. On large turbine-generators, the
rotor positions. If the coupling is correctly aligned, outer bearings could be up to 25 mm above the level
the gap should be uniform all the way round. If of the central bearings.
this is not so, the bearing positions can be modified It is often necessary to deliberately misalign par-
by the appropriate amount and the gap remeasured. ticular bearings when cold so that an acceptable hot
alignment is achieved. This makes allowance for support
The concentricity of the two rotors is checked by
structure expansions when the turbine is at operating
measuring, using dial gauges, the radial difference
temperature. The required offsets are included either
between the periphery of one coupling and the peri-
by removing/adding shims from/to the bearings to
phery of the other coupling while rotating the separate
be adjusted, or by deliberately allowing a known error
rotors. Any errors can be corrected by bearing ad-
in a coupling. The amount of offset can be decided
justments, as for gap errors.
by measurements taken from a multilimb-manometer
Other methods of alignment, based on strain gauges
system, or derived from operational experience.
and optical techniques, have been developed.
The strain gauge technique is not widely applied
but can be used on the coupled shaft at a suitable
point near the coupling to be checked. It measures 7.5.2 On-line monitoring
the bending stress of the shaft at that point by the Manometric systems are used for on-line monitoring
application of strain gauges. The presence of bending of the bearing pedestal positions. Connections to
stress is indicated by the strain gauge giving a sine each pedestal provide information on the relative level
104
Bearings, pedestals and turning gear

changes during service. A description of such a sys- be rather longer, with L/D ratios of 0.6 to 1.0 to
tem is given in Chapter 2. take account of the heavier generator rotor in relation
to the weight of individual turbine rotors. In this
way, a typical load on projected bearing area is kept
below about 15 kPa.
Two main white metal profiles are in common use
8 Bearings, pedestals and turning gear in modern UK turbine plant; these are known as
elliptical and three-land respectively.
The elliptical bore is produced by first machining
a circular bore with shims in the bearing horizontal
8.1 Journal bearings half joint and then assembling the bearing without the
The purpose of a turbine bearing is to retain the rotor shims. This results in typical clearance ratios (diametral
system in its correct radial position, relative to the clearance/diameter) of 0.001 vertically and 0.0015
cylinders, and to provide a low friction support which horizontally. Oil is fed into the bearing via lead-in
will withstand the static and dynamic loads of shaft ports at two diametrically opposite points on the
rotation, together with the frictional and conducted horizontal centreline.
heat, and to remain free from maintenance except The three-land design has three separate bearing
at major outages. surfaces, or lands, of equal width but of different
arc lengths; one land in the bottom half and two in
the top half.
8.1.1 Construction There is an oil supply groove with lead-in at the
Two bearings normally support each section of the beginning of each land, and a drain groove at the
turbine shaft, although, with solid couplings, some end. Recirculation of oil is limited by an axial strip
designs only use one bearing between cylinders in of bearing surface between each drain groove and
order to save length and bearing losses. Plain white- the following supply groove. The three-land bearing
metalled journal bearings are invariably used because is generally of circular bore with a clearance ratio of
of their high loading capacity, reliability and absence about 0.0013. This design is more resistant to low
of wear due to hydrodynamically generated films of frequency whirl (see later).
lubricating oil. These films are formed automatically, Oil is supplied, to cool and lubricate the bearings,
when running, by a high pressure wedge of oil between at about 1 bar and 30-40C, from the main turbine
the whitemetal and the shaft the maintenance of lubricating-oil pump. Each bearing also has a separate
which ensures that no metal-to-metal contact is made. high pressure (300 bar maximum) jacking oil supply
The oil is continuously fed into the wedge by frictional which is injected at the bottom of the bearing. This
drag and leaks away axially towards the edges of lifts the journal in the bearing when starting from
the bearing. rest, thereby preventing wear and reducing the starting
torque required from the turning-gear drive motor.
The white metal surface is either cast into a mild
steel liner to form a bearing shell, which is supported
in the bearing body, or cast directly into the bearing
body itself. Both types are in use in modern UK 8.1.2 Instrumentation
turbines (Fig 1.121). Instrumentation specific to the performance of the
All bearing assemblies are split in halves on the bearing normally comprises white-metal temperature
horizontal centreline and held together by bolts, the and oil inlet pressure, indicated both locally and in
halves being dowelled together to assure precise lo- the Control Room. Bearing oil outlet temperature is
cation on assembly. normally indicated locally, with remote alarm facili-
The bearings are normally spherically seated in their ties. Provision is also made at the bearing housing
pedestals on four pads under which shims are placed to monitor vertical and horizontal vibration modes.
to facilitate precise horizontal and vertical alignment Jacking oil pressure is monitored local to each bear-
of the shaft line. The spherical seating feature assures ing, with alarm indication in the Control Room.
that, on assembly, the bearing will automatically align
to its correct axial tilt; this is necessary because, when
coupling faces are set and bolted flat together, the 8.1.3 Bearing performance
outer bearing on each shaft needs to be higher than The first step towards understanding the performance
the inner bearing due to the natural bending catenary of a bearing under dynamic conditions is to know
adopted by each shaft under its self weight (for further the condition of the bearing oil film in vibration; as
detail of alignment refer to Section 7 of this chapter). described by Smith [9], this is different from the
The spherical seat is restrained in normal operation. steady state hydrodynamically-generated oil film noted
Typical large turbine bearings are up to 530 mm earlier.
in diameter and have length/diameter (L/D) ratios in When a sufficiently large journal vibration is super-
the order of 0.5 to 0.7. Generator bearings tend to imposed on the steady state running condition, changes
105
The steam turbine Chapter 1

PAD RETAINING STOP PEG


SCREW

BEARING PAD

SHIMS

PACKER

SHIMS

HOLE FOR BEARING


SHELL THERMOCOUPLE

LUBRICATING OIL TOP HALF


CHANNEL BEARING BODY

LUBRICATING OIL
INLET PORT

TOP HALF
BEARING SHELL

STOP SCREW
OUTER
INNER
TOP HALF BAFFLE
RINGS

HOUSING STUD

REGISTER RING

BOTTOM HALF
BEARING SHELL

BOTTOM HALF
BEARING BODY

BOTTOM HALF BAFFLE


RING

JACKING OIL INLET JACKING OIL PORTS

FIG. 1.121 Main rotor bearing showing steel-back white metal liner
An alternative arrangement has the white metal cast directly into the bearing body

106
Bearings, pedestals and turning gear

in the oil film thickness and circumferential move- with the whirl. The pressure-bearing film then travels
ment of the pressure bearing oil film take place, round with the journal and the operating condition
accompanying the movement of the journal. The way is no longer closely related to the steady running
in which the oil film is redistributed depends on the condition.
character of the vibration. This is one of the sources In a journal whirl of sustained magnitude at con-
of complication of the dynamics of turbine bearings. stant eccentricity, the idealised bearing is in a condition
Figure 1.122 illustrates the steady running state film of steady running relative to axes rotating with the
and other film regimes which may apply to the pres- whirl. There is an effective speed of rotation, relative
sure bearing oil film with the journal vibrating. Figure to these axes, of (N-2F), where N is the speed of
1.122 (a) illustrates the steady state film, with the rotation of the journal and F is the frequency of
film starting at the position of maximum clearance, whirl measured in the same direction. The position
(b) an oscillating film, (c) rotating trailing film, (d) of formation of the pressure-bearing film depends
rotating leading film and (e) rotating transition film. on the direction of the mean peripheral speed of
bearing and journal relative to the rotating axes, that
is on whether N is greater or smaller than 2F.
When the frequency of whirl is less than half the
STEADY LOAD journal speed, the pressure-bearing film is built up
on the trailing side of the minimum film thickness,
as in Fig 1.122 (c). When the frequency of whirl is
greater than half the journal speed, the pressure-
bearing film is built up on the leading side of the
minimum film thickness, as in Fig 1.122 (d). The
diagrams show, for each case, the direction of the
(b) Oscillating film reaction applied by the journal to the bearing.
When a rotating load is superimposed, on a much
smaller steady load, there is a variation of eccentri-
city during each whirl rotation, but the film regimes
obtained resemble those given by whirl of constant
REACTION eccentricity.
With rotating trailing film the reaction of the bear-
(c) Rotating Trailing Film (d) Rotating Leading Film
ing on the journal (opposite to the reaction just
mentioned) has a component normal to the attitude
radius in the direction of the whirl. This component
tends to increase the whirl. An explanation is thus
offered of why a rotating trailing film is associated
with tendency to instability. As reaction force in-
creases and minimum film thickness decreases, the
(e) Rotating Transition Film direction of the reaction swings closer to the attitude
LOCUS OF JOURNALc - J i * " "
JOURNAL AXIS
radius, so that if there is damping elsewhere in the
DISPLACEMENT
H- BEARING AXIS system, a steady condition of whirl may be attained.
With rotating leading film the corresponding com-
ponent tends to damp the whirl. A bearing in this
regime does not excite instability.
FIG. 1.122 Oil film regimes in journal bearing vibration The transition between these last two conditions
is of importance, because it may exhibit a sharply
resonant tendency to maintain rotor whirl when there
is a natural frequency close to half running speed.
Figure 1.122 (d) gives a diagrammatic representation of
The oscillating-film condition, (b), is obtained when this film condition; the angular extent of the pressure-
a small amplitude of vibration is superimposed on bearing film is not known.
the steady-running condition; this vibration is sus- Prediction of rotor dynamic behaviour depends
tained by a fluctuating force superimposed on the on an adequate understanding of the bearing per-
steady load. The motion of the journal axis results formance, for which full-size bearing test rigs are
in both squeeze and angular swing of the film. This commonly used. Dynamic behaviour can also be in-
oscillating-film condition is of frequent occurrence fluenced by the stiffness of the support structure and
in bearings in service. It is closely related to the the effectiveness of the connection between bearing
steady-running condition. pedestals and the turbine foundations. In this latter
In severe vibration, the journal motion may become respect, bolting to steel foundations is more predict-
a whirl of such large amplitude that the position of able than bolting to soleplates grouted into mass
minimum film thickness travels round the bearing concrete foundation blocks.
107
The steam turbine Chapter 1

8.1.4 Factors affecting bearing life during load reduction and following a turbine trip.
Wear of journal bearings mainly occurs with an oil In operation, the pad faces are slightly inclined to
film of very small minimum thickness and mild local the face of the thrust collar and the wedge-shaped
wear, especially as new bearings 'bed-in', is to be cavity thus formed fills with oil. As thrust pressure
expected. However, severe wear is a symptom of is applied, the wedge narrows and oil is forced to
trouble and can be caused by: the restricted end. This ensures that metal-to-metal
contact between the pads and the thrust collar is
Contacting asperities on substandard journal and prevented. The pads are shaped and mounted so that
bearing surfaces. each is able to pivot independently.
Since the function of the thrust bearing is critical
Scoring by oil-borne solid particles.
in controlling axial clearances between stationary and
Excessive local pressure or temperature. rotating turbine components, particular precautions
are taken to protect its integrity.
Electrical pitting. Because of the close tolerances between the pads
and the shaft collar, the oil supply to the thrust bear-
Fatigue cracking of the white metal surface can be ing is individually filtered. A portion of the oil is fed
caused by heavy vibration or cavitation within the straight to the thrust pad/shaft collar interface to
oil film; the latter is usually caused by a restricted maintain the load bearing oil film. The balance of the
supply of oil. oil supply is diverted around and behind the thrust
Corrosion rarely occurs, due to the control by pads to provide cooling; since as a result the thrust
treatment plant of moisture in the turbine lubricating- bearing runs flooded, the consequent churning loss
oil system (see Chapter 2). has also to be removed and therefore this portion of
Electrical erosion of bearings and journals has oc- the oil supply is a significant proportion of the whole.
casionally given trouble. Small shaft voltages are set Thrust pad wear measurement is facilitated by the
up by electromagnetic induction in the generator provision of oil pressure nozzles between the white
rotor. Higher voltages sometimes occur in the turbine, metal pads and mounted on the thrust and surge sides
produced electrostatically. Bearing erosion is prevented of the shaft collar (Fig 1.124).
by effective insulation of the generator bearings from These nozzles are set at a distance slightly greater
earth and the application of an earthing brush to from the shaft collar than the normal pad running
a suitable point on the turbine rotor system. Both clearance. A separately-filtered constant pressure oil
insulation and earthing brushgear require good main- supply is delivered to these nozzles and the discharge
tenance as well as good design to assure their correct pressure is continuously monitored. As pad wear takes
functioning. place, the nozzle-to-collar gap is reduced and the in-
creasing nozzle discharge pressure is locally indicated
and alarmed in the Control Room to give indication
of worn white metal thrust pads.
Thrust pad temperatures are monitored by embedded
8.2 Thrust bearings thermocouples, with local and remote indication and
The purpose of the turbine thrust bearing is to pro- alarm facilities.
vide a positive axial location for the turbine rotors
relative to the cylinders. To achieve this, it must be
able to withstand the unbalanced thrusts due to blade
reaction and steam pressure acting on unbalanced
areas. It must be free from maintenance, except at 8.3 Pedestals
major outages. Since it is universal practice to use The main purpose of the bearing pedestals is to sup-
solid couplings between rotors, only one thrust bear- port the turbine rotor, via the journal bearings, in a
ing is required in each complete shaft line. It is fixed relationship to the cylinders so that gland clear-
normally located close to the areas where blade/ ances are maintained in all phases of operation. To
cylinder clearances are minimum and operating tem- this end, all pedestals and covers are rigidly fabricated
peratures are highest and is split on the horizontal in steel, amply stiffened by ribs and gusset plates,
centreline for ease of asssembly and maintenance. to support the bearings in a fixed relation to the
All large UK steam turbines use the Michell tilting- cylinder supports. Fabrication of pedestals has been
pad thrust bearing (Fig 1.123). adopted on large turbines because of the advantages
Although the net thrust on the white-metalled pads offered in terms of increased support stiffness, whilst
in the on-load condition is always in one direction, maintaining a compact overall pedestal size with good
i.e., typically towards the generator, a second set of resistance to impact loading.
pads, termed surge pads, are incorporated on the Improved cast materials, such as spheroidal graphite
opposite side of the integral shaft collar to take ac- iron, may find future application with improved cast-
count of transient reversals of thrust which occur ing techniques.
108
Bearings, pedestals and turning gear

TOP HALF HP/IP BEARING HOUSING ANTI-ROTATION LUBRICATING OIL DRAIN


PIN ANNULUS

PAD STOP
PLATES

LOWER HALF
BEARING SHELL

BEARING LUBRICATING
OIL INLET HOLES

WHITE METAL
FACING RING

LUBRICATING OIL INLET


ANNULUS-LOWER HALF
BEARING HOUSING ONLY

FIG. 1.123 Tilting-pad thrust bearing

109
The steam turbine Chapter 1

ADAPTOR FLANGE AXIAL INDICATOR THRUST PAD THRUST PAD STOP


BODY

THRUST COLLAR

WHITE METAL END CAP

PACKING RING

ADJUSTING WASHER

OIL SUPPLY PIPE THRUST BLOCK _*J U - 01 in


" ^ ^~ FROM PAD FACE

^ ,

NOZZLE

DETAIL OF THRUST AND SURGE


PAD NOZZLE SETTINGS

OIL SUPPLY FROM


MAIN OIL PUMP

CONTROL ROOM

LOCAL INDICATION
AND ALARM
-

NO 1 NOZZLE NO 2 NOZZLE

THRUST PADS SURGE PADS


FRONT REAR

FIG. 1.124 Thrust pad wear measurement system, relying upon decreasing gap at the nozzle head causing a rise in
indicated discharge oil pressure

110
Bearings, pedestals and turning gear

Pedestals in the LP area of the turbine are normally all round the joint flange inside the line of the half-
firmly bolted and dowelled to the foundations. It joint bolts; any seepage from the ends of these grooves
is, however, common practice at the high temperature is collected and piped away to a dirty-oil drains tank.
end of the turbine to make provision either for the
cylinders to expand at sliding mounting points on top
of their pedestals or for the pedestal to slide relative
to the foundations. For details of cylinder support 8.5 Turning gear
and expansion arrangements refer to Section 6 of
The turbine rotors must be turned continuously
this chapter.
throughout the process of warming-through the unit
The pedestals incorporate facilities for the attach-
prior to start-up and, in addition, during the cooling
ment of lubricating and jacking oil supply pipework
process following a shutdown. Rotor and cylinder dis-
and the associated bearing oil drain pipework. Mounted
tortion could occur as a result of uneven heating or
within (or on) the enclosure are all necessary instru-
cooling if the facility for turning the rotors were not
mentation connections, e.g., bearing temperature, dif-
available to provide circulation within the cylinders.
ferential expansion pick-ups, together with eccentricity
Cylinder metal temperatures, specified by the manu-
and vibration detectors. A manometric level system
facturer, are the normal criteria for allowing a warm
is attached to the pedestals adjacent to each bearing
turbine to cease barring.
to detect misalignment due to support structure settle-
Two independent turning gear facilities are usually
ment, for details of this system refer to Chapter 2.
provided:
Particular care is taken to ventilate around the
pedestals, keeping them cool so that any vertical ther- Hand barring arrangement.
mal expansion effects, which might disturb the overall
vertical alignment of the turbine, are minimised. For Electrical turning gear (ETG).
example, many pedestals contain couplings which are
surrounded by coupling guards; these guards are
themselves cooled by oil sprays tapped-off the lubri- 8.5.1 Hand barring arrangement
cating oil supply to remove windage heat generated
Should the ETG be unavailable, provision is made
by coupling rotation.
to turn the rotors manually by mounting a lever and
In addition, those pedestals adjacent to the high
fulcrum apparatus at a prearranged point on the cover
temperature components of the turbine are frequently
of a bearing pedestal. This lever operates on a per-
protected by thermal radiation shields, with provision
manent toothed-wheel between two turbine rotors
for air circulation in the space between the shield
(Fig 1.125). This is usually an operational feature
and the pedestal structure, also to minimise thermal
to protect the turbine in a heat-soaked condition.
expansion effects.
Further hand barring, for maintenance purposes
only, can often be carried out by using a simple
crowbar against a toothed barring ring, replacing the
normal spacing ring between rotor couplings, and lever-
8.4 Oil sealing arrangements ing against a simple fulcrum plate secured to the ped-
estal horizontal joint face (Fig 1.126).
The ends of the pedestals where the turbine rotors
emerge are fitted with oil catchers. The baffle fins
on the oil catchers, in conjunction with oil throwers
on the shaft, prevent egress of bearing lubricating 8.5.2 Electrical turning gear (ETG)
oil from the pedestal. The rotors are turned slowly, typically less than
Having regard for the speed and size of the bearing 30 r/min, during start-up and shutdown by the ETG.
and coupling assemblies within the pedestals, the pro- An electric drive motor turns the rotors through a
duction of oil mist is inevitable. The escape of this wormshaft and worm wheel, thereby providing a re-
mist is prevented by the main oil tank vapour ex- duction gear. A jacking oil pump supplies high pres-
tractors which, since the bearing drain lines do not sure lubricating oil to the reduction gear.
run full, maintain the inside of the pedestal at a Manual control of the motor is provided in the
slightly lower air pressure than the turbine hall. There Control Room, and automatic stop and start faci-
is thus a small flow of air through the baffle ring and lities are also included in the motor switchgear. The
across the surface of the shaft; this purges the oil motor overload trip is set at a value which prevents
mist back into the pedestal and via the bearing drains excessive torque being applied to a seized rotor. Elec-
to the main oil tank, whence it is discharged at a safe trical interlocking prevents the motor being started
location. For details of the lubricating oil system see until jacking oil pressure is established.
Chapter 2. A self-shifting synchronous (SSS) clutch is installed
Oil leakage from the horizontal joint of the ped- between the drive motor and the turbine shaft and
estals is commonly prevented by machining a groove provides a simple mechanical means of automatically

111
The steam turbine Chapter 1

BARRING RING

FULCRUM
PLATE

BARRING GEAR SLOT CLOSED

FIG. 1.126 View on the end of a turbine coupling,


showing provision for hand barring during outages for
maintenance
PAWL

FULCRUM PIN BARRING GEAR

pawls 'bite' and reactive torque is applied to the


helically-splined sleeve which moves axially and slides
the clutch teeth into engagement.
The positions of the pawls and ratchet teeth en-
sure that the clutch teeth pass between each other
TOOTHED BARRING
RING
exactly, without making contact until full engagement
is reached; at this point the pawls leave the ratchet
teeth, and the flanks of the clutch teeth meet to take
up the drive.
It is important to note that the pawls merely sense
zero relative speed and angular location, they do not
MANUAL BARRING GEAR ASSEMBLED carry the main torque. To prevent ratcheting and
consequent wear when the relative speed is high, the
FlG. 1.125 Assembly of hand barring equipment; this is an pawls are designed to disengage centrifugally.
operational alternative in the event of the main electrical The only load imposed on the pawls is the force
turning gear being unavailable required to engage the clutch. In a very large clutch,
this could overload the pawls and so a relay clutch
is used. Here the primary mechanism is exactly as
described above, but the helically-splined sleeve, in
connecting or disconnecting the turning gear drive. moving forward, engages teeth to move a much heav-
The SSS clutch is a positive tooth-type overrunning ier helically-splined sleeve on which the clutch teeth
clutch which is self-engaging when passing through are cut. A further refinement is an oil dashpot, which
synchronism, that is, immediately the speed of the cushions the engaging action, and prevents disengage-
input shaft exceeds that of the output shaft. The ment as a result of rapid transient torque reversal.
clutch disengages automatically when the torque re-
verses, that is, when the speed of the output shaft
exceeds that of the input shaft (Fig 1.127).
At standstill, when the driving shaft begins to pro-
vide torque, the clutch will engage; if after this the 9 Turbine applications
torque ceases, the clutch will disengage. It will re-
engage if the speed of the driving shaft exceeds that
of the driven shaft, whether at full barring speed or
at any lesser speed. 9.1 Power generation
Spring-loaded pawls, acting on a ratchet, sense the The main concern of this volume is turbines for the
relative speeds of the input and output shafts; when generation of electric power via a constant speed
the input shaft is about to overtake the other, the generator. In this area of technology, as applied in
112
Turbine applications

WORMWHEEL

WORMWHEEL
FLANGE

OIL FEED
CONNECTION

PIVOT PIN

PAWL

CLUTCH IN DISENGAGED POSITION CLUTCH IN ENGAGED POSITION

FIG. 1.127 Self-shifting synchronous clutch

113
The steam turbine Chapter 1

large central power stations, the steam turbine has The development of higher turbine ratings and
firmly established itself as pre-eminent during the the increased steam inlet temperatures and pressures
20th century. soon led turbine makers away from the single-cylinder
The previous sections have mainly described the designs to multiple-cylinder designs comprising high
thermodynamic and mechanical features of turbines pressure (HP), intermediate pressure (IP) and low
used for power generation. The condenser and feed- pressure (LP) cylinders. Because of the limitations
heating plant have been identified as essential features in the length of the last-stage blading and the im-
necessary to obtain a reasonable thermodynamic effi- portance of having sufficient exhaust area to allow
ciency. Boiler feed pumps are required to pressurise operation at an economically low exhaust pressure,
the system. Cycles employing a variety of inlet steam double-flow cylinders were introduced as shown in
conditions and options for reheating have been dis- Fig 1.128. This example shows a further development
cussed and, depending on the source of steam and where two double-flow LP cylinders, connected on
the prevailing economics, all these are possible. The the same shaft, accept the exhaust flow from a double-
mechanical features described in earlier sections have flow IP turbine supplied by a single-flow HP turbine.
embraced those which are necessary to achieve plant This is often described as a 4-flow exhaust machine.
capable of high efficiency and flexible operation. Many other combinations are possible, with 6-flow
It is helpful to examine briefly the history of and 8-flow turbines being constructed from three and
turbine development, as it has led to the principal four LP cylinders respectively.
features of current machines. The earliest turbines The principle of improving turbine efficiency by
had ratings of a few MW and were of the single cylinder reheating the steam in the boiler after it has com-
type driving a DC generator. The speed of rotation pleted an initial expanson was well known even at
was therefore not dependent on the electrical system the beginning of the century. However, the first proto-
and was purely a choice for the designer. Subse- types of commercial generating plant using reheat did
quently, fixed speed AC generators were developed, not appear until the 1920s and, although now almost
giving major advantages in the economy and ease of universal, it was only introduced gradually. Since the
distribution of electrical power. reheated steam returns to the turbine at a much higher
Higher unit ratings have been employed to reduce temperature than that at which it was exhausted,
the capital cost per kW output and to improve the there is a further strong incentive to provide a se-
efficiency. Basically, doubling the length of the tur- parate turbine cylinder to expand the reheated steam
bine blading gives four times the cross-sectional area so that high temperature gradients are avoided on
through which the steam flows and the possibility of adjacent stages.
four times the output for double the cost. This simple Manufacturers now have a wealth of experience
example cannot be directly related to the practical behind them and some of the more fanciful options
case, as many other factors influence the precise of the past have been eliminated. Development to
ratio of the costs, for example the costs of assembly improve efficiency and reliability continues on a broad
and manufacture, and the costs of buildings and front. The division of the overall turbine expansion
construction work to house the turbine. The efficiency between separate cylinders has enabled them to offer a
is also improved because the smaller turbine has a modular design concept for a whole range of unit sizes
higher frictional loss (per kW output) due to the for power generation. The modular concept centres
smaller blade height. Also, the blading clearances will around several standard cylinder designs which may
not necessarily double for the larger size turbine, so be combined in a number of different ways to cover
the leakages (allowing steam to by-pass the blading) variations both in steam conditions and in unit output.
will be greatly reduced (per kW output) for the larger Figure 1.4 illustrates this concept, as applied by both
machine. Similar economies of scale also apply to UK turbine manufacturers.
condensing and feedheating plant, and to the auxiliary
systems.
Apart from the difficulties of making and trans-
porting larger components, the main limitation to 9.2 Mechanical drive
this process is the extent to which the blade length Figure 1.128 shows a typical cycle diagram of a unit for
can be increased without exceeding centrifugal and power generation. The turbine exhaust flow is ducted
bending stress criteria. This is discussed in Section 5 to the condenser where the condensation temperature
of this chapter. Turbine ratings up to 1200 MW are fixes the exhaust pressure of the turbine. The con-
now commonplace. However, the user must bear in densate is routed back to the boiler by LP feedheating
mind the relative size of his power distribution system plant followed by one or more feed pumps which
and the consequences arising if a large unit is tripped. pump the condensate back to the boiler, often through
Will the other plant on the system be able to pick up HP feedheating plant. The boiler outlet pressure is
the load without interruption of the electricity supply determined by the feed pump, and the pre-heating of
to consumers or must a proportion of the consumer the feedwater by the feedheating plant improves the
load be disconnected? thermal efficiency by using low-grade heat from bled-
114
Turbine applications

LP TURBINES

K3

Fie 1.128 A 4-flow exhaust turbine cycle with a motor-driven feed pump

steam tappings on the main turbine rather than high good matching of their characteristics over most of the
grade heat obtained by burning more fuel. flow range, with very little throttling of the turbine
One of the options for driving the feed pump is required. Furthermore, control of the feed flow is
to use a small auxiliary turbine, supplied by steam accomplished by varying the speed of the drive system
from the main turbine and exhausting either to the so that the throttling losses of feed regulating valves
condenser or back into the main turbine, as shown in a constant speed drive system are avoided. At low
in Fig 1.129. The advantages of these forms of feed feed flows, however, the variable-speed turbine drive
pump drive, compared with the electric drive shown is incapable of providing sufficient output. Electrically-
in Fig 1.128, are fully discussed in Section 4.3 of driven feed pumps may be used to provide start-up
this chapter. In practice, there are numerous examples and operation at low loads. An alternative system,
of turbine-driven feed pumps, usually in the power often used in the UK, is to provide a live steam stage
range of 10-20 MW. The characteristic curves of to the feed pump turbine so that it can be used over
the pumping system were shown on Fig 1.71. The the full load range. Live steam is normally reduced
system resistance is made up of a static component to a warming flow only at high load on the main
set by the required boiler outlet pressure, modified turbine. The maximum pumping power requirement
by the relative suction level and water level within for a fossil-fired supercritical plant (with a once-
the boiler. There is also a frictional component gen- through boiler) will be approximately 3.5% of the
erated by the pressure drops through the boiler and main unit output. For a fossil-fired superheat unit
feed water system following the pump. This frictional or an AGR nuclear application, this will reduce to
component of the pressure drop is proportional to 2.5%, while the low pressure operation of PWR tur-
the square of the flow. The operating point for the bines will only require 1.5%. Typical speed ranges
system is determined by superimposing the pump are 5000-7000 r/min for fossil-fired plant and 3500-
characteristics of the system resistance curve. From 5000 r/min for nuclear, wet steam plant.
the pump efficiency curve and pump power versus Back-pressure boiler feed pump turbines are usually
speed curve, the power required by the pump is deter- arranged to exhaust into the LP inlets of the main
mined. The maximum power available from the drive turbine. This poses operational problems when the
turbine over the flow range (proportional to main main turbine has not been started or if the main
turbine load) follows a linear characteristic if its turbine is tripped. Under these conditions, the feed-
throttle valves are kept wide open (see Section 3 of pump turbine exhaust flow must be routed to the
this chapter). The proximity of the pump power re- condenser. This disadvantage is partly offset by their
quired and the turbine power available curve shows facility for supplying bled-steam to feedheaters which
115
The steam turbine Chapter 1

K3

FEED
PUMP

FIG. 1.129 A 4-flow exhaust turbine cycle with back pressure BFPT

would otherwise need to be fed from tappings on domestic and industrial use. It is the purpose of
the main turbine IP cylinder. It is generally simpler CHP schemes to exploit this potential.
to arrange this with shorter pipe runs from the feed The condenser pressure in a typical turbine for
pump turbine (usually a single-cylinder, single-flow unit) power generation is in the range of 50-120 mbar.
rather than from a double-flow IP turbine. However, The function of the cooling water in the condenser
as discussed in Section 4 of this chapter, the option is to extract the latent heat of evaporation from the
of tapping points on feed pump turbines is not being steam exhausted by the turbine and this is done at
pursued for future plant. the saturation temperature corresponding to the steam
Condensing-type boiler feed pump turbines are also pressure, i.e., at 33-45C to 49.5C for pressures of
of single-cylinder single-flow design and, because they 50-120 mbar. Unfortunately, temperatures as low as
exhaust into the condenser, their inlet steam conditions these would be unacceptable for transmission to do-
are much lower than the back pressure type, often mestic heating systems, so it is necessary to consider
being supplied from the IP exhaust. They are favoured higher temperatures in the range 80-120C which
in applications where the exhaust area of the main give corresponding pressures in the range 0.5-2.4 bar.
machine may be a limiting factor as they provide a Industrial processes may need even higher tempera-
ready means of increasing the total effective exhaust tures; so a turbine used in a CHP scheme will either
area. incorporate steam extraction at a pressure higher than
condensing pressure, or will exhaust directly at the
higher pressure. The former is known as an extraction
or pass-out turbine whereas the latter is called a back
pressure turbine.
9.3 Combined heat and power (CHP) Many plant configurations exist to suit the parti-
The inherently poor efficiency of the turbine-generator cular requirements of each specific application. Two
in power generation applications has always been re- examples are given here to illustrate the range of
garded with concern by turbine designers. The reasons plant and some of the possibilities. The first example
for this are discussed in Section 3 of this chapter, is of a condensing turbine designed at the outset for
where it will be seen that the major part of the heat a domestic heating installation with electrical power
produced by the burning of fuel in the boiler is generation as well. The second example illustrates
rejected as low grade energy in the condenser cooling how an existing large power station might be con-
water. It has long been appreciated that there is a verted for a similar heat load.
major thermal advantage to be obtained if such low In both cases, steam is extracted from the turbine
grade energy can be employed to provide heating for at two different pressures, as shown in Figs 1.130
116
Turbine applications

MAIN TURBINE INLET


CONTROL VALVE

BULK TRANSMISSION PIPELINE

FiG. 1.130 District heating supply scheme with special turbine design

and 1.131. More than two pressures could be used of achieving controlled extraction pressures, since con-
with the advantage of higher thermal efficiencies but trol valves can readily be supplied in the inter-cylinder
at the expense of greater complication. The extraction crossover piping downstream of the IP exhausts. The
steam is passed to two district water heaters, so that asymmetry is provided by designing for a different
an equal temperature rise is obtained across each number of stages in each flow of the turbine.
of them. Figure 1.131 depicts three large existing turbines
The condensing turbine shown in Fig 1.130 meets for power which have been modified to incorporate
the usual requirement of a domestic heating appli- steam extractions to a bled-steam range. This sup-
cation where, depending on the ambient temperature, plies an auxiliary back pressure turbine providing
a variable quantity of hot water at the required further electrical power generation and feeding two
temperature must be supplied. It comprises a con- district water heaters from its asymmetric double-flow
ventional single-flow HP cylinder with an asymmetric cylinder. For clarity, the feedheater systems of the
double-flow IP cylinder supplying steam to two series- three main turbine-generators have not been shown.
connected district water heaters. The steam from each Because steam is bled from all three main units if
IP exhaust is also supplied to two separate different they are running, there is a loss in the water inven-
design double-flow LP cylinders, being throttled before tory of each unit which must be made good by the
expansion. This enables the steam pressure at the IP provision of a condensate return system, suitably con-
exhausts, and hence the heated water temperature, trolled to return the correct water quantity to each
to be held constant over a wide load range. unit.
Electrical power is also generated by means of a All the plant shown in Fig 1.131 would normally
conventional shaft-driven generator. The asymmetric be installed at the existing power station. The only
IP cylinder provides a neat solution to the problem modification to the existing turbine-generators would
117
The steam turbine Chapter 1

|LP INLET CONTROL


VALVE (NEW)

FIG. 1.131 CHP conversion for a district heating supply scheme

be the provision of bleed and condensate return tap- the economics of such schemes are likely to find
pings, with control valves as shown. The district water increasing favour.
system would include the heaters, pumps and pro-
vision for make-up and heat storage so that the
operating periods of the auxiliary turbine generator
and its loading schedule can be controlled with a 9.4 Combined-cycle plant
degree of independence from the heat demand. The term 'combined cycle' implies any heat and power
Such a scheme could provide heat as well as power producing process where the prime movers employ
to a large city located many kilometres away from more than one working fluid in a combination of
the power station. turbines. The most common and practical form of
The total 'efficiency' or utilisation of heat in the such plant is the combination of one or more gas
fuel in district heating schemes may be over 80%, turbines with a steam turbine; this section will deal
which makes it attractive for countries with cold with variants of this basic theme.
winters. One difficulty which has prevented a more Figure 1.132 shows a combined-cycle plant in its
widespread use of such schemes is the cost and com- simplest form with the heat from the gas-turbine
plication of distributing the heat thus provided to exhaust utilised to generate steam in a heat-recovery
hundreds of domestic premises. The most successful steam generator. This cycle makes use of the inher-
schemes have been applied to new developments of ent characteristics of the gas turbine process, where
large apartment blocks. With ever increasing fuel combustion takes place and, following expansion in
costs and the need to conserve valuable fossil fuels, the turbine, heat is rejected at a relatively high tem-
118
Turbine applications

FIG. 1.132 Simple 'combined cycle' plant, employing one gas turbine and one steam turbine

perature suitable for steam generation. The comple- The advantages of such an arrangement are most
mentary steam turbine is able to make use of this applicable to countries having an abundant supply
because of the low temperature exhaust made possible of oil or natural gas where there is a need to rapidly
by its condenser. The condensate is returned to the extend the utilisation of these resources to meet the
steam generator, via a single combined feedheater populations' demands for electrical power. A phased
and de-aerator, followed by a pump. Typically the development could be implemented, the first stage
steam turbine output will be about 50% of the gas being the installation of gas-turbine generators to
turbine output. meet the immediate needs for electrical power, thus
119
The steam turbine Chapter 1

exploiting the potential short delivery times and simple depends on:
installation of packaged units associated with gas tur-
bine technology. The second stage would be the in- The economies of scale; i.e., the generally lower
stallation of the steam generators, steam turbine and capital cost per unit output given by larger output
auxiliaries, thus providing a further increase in power plant.
output at a high overall thermal efficiency of about
45%. The steam cycle and conditions associated with the
A third stage might be considered if a further selected steam generation system.
increase in output for short periods during load peaks
The availability of plant designs for the steam
is desired. Supplementary firing would be fitted to
generator and the turbine-generator.
the boiler to generate more steam to meet the full
capability of the steam turbine in respect of steam
The size of the grid system and the individual
inlet temperature. Because gas turbines are normally
generating units on it.
operated with a high excess air factor, there would
be sufficient air in the gas turbine exhaust to support The size of the organisation owning the plant, and
the combustion of the additional fuel.
its economic environment.
Plant using a high proportion of supplementary
firing is sometimes constructed making use of the The available construction time.
gas turbine primarily as an air supply for the main
combustion process. In this type of plant, the steam The available site area.
turbine may generate as much as eight times the
power of the gas turbine and employ a multistage
feedheating system to maximise efficiency. This may In the late 1970s and early 1980s, there was a gen-
be more thermally efficient than a steam turbine on eral period of consolidation worldwide, with relatively
its own, but is prone to giving a lower availability few new stations being ordered. Those that were
unless a means of changeover from gas turbine to ordered were generally established design, or part of
forced-draught fan is provided. a deliberate series ordering of plants. In the larger
A more common variant is to use one or more industrial countries, tandem-compound turbine sizes
gas turbines in a dual-pressure heat-recovery steam have stabilised in the range 600-800 MW for super-
generator. This permits more heat extraction from the heat plant, and 900-1300 MW for saturated steam
gas turbine exhaust since the low pressure circuit heat plant. There have, however, been a few individual
transfer can take place at a lower temperature than exceptions, with superheat plant including a 1200 MW
in the high pressure circuit. A typical arrangement is tandem-compound unit in the USSR, and 1300 MW
shown in Fig 1.133. If more than one gas turbine is cross-compound units in the USA. Saturated steam
used, additional flexibility of steam turbine operation plant has included a 1500 MW tandem-compound
is possible, since shutdown of one gas turbine will design in France in association with a PWR.
not prevent steam turbine operation. More efficient
With the adoption of modular design principles, a
part-load operation can be obtained in this way.
turbine manufacturer can offer a range of outputs
Combined-cycle plant developments are likely to
in his product range of large machines, typically from
follow the development of the gas turbine. Higher
200 MW upwards. There are many smaller or less-
combustion and exhaust temperatures will lead to
developed countries where the size of the grid system
higher overall efficiencies. As the practicability of
burning a wider range of fuels (including coal) in will preclude the larger plants, and the 250-350 MW
the gas turbine improves, the application of combined- range is often favoured.
cycle plant will become more widespread. With the Looking to the future, it appears that the selection
current state of the art, there are no limitations to of the unit size will be increasingly determined by
such further development in respect of the steam the system size, the plant ownership and the rating
turbine. A wide range of outputs is generally offered by of nuclear steam supply systems. In the USA, where
manufacturers, using various numbers and size-ranges there are a number of relatively small utilities, the
of standard gas turbines in combination with steam preferred unit sizes for fossil-fired plant are likely
turbines of modular design. to be around 350 MW and 700 MW. If new nuclear
plant is ordered, it is expected that this would be
at most only a modest development of the 1300 MW
reactors. In France, with a large utility (EDF), the
plan is likely to be a series of orders for 1500 MW
10 Future outlook
PWRs, with little or no fossil-fired plant. In Germany,
with a number of utilities, the American pattern is
more likely. In Japan, there is a committed plan of
10.1 Unit size and rating development towards fossil-fired units rated at up to
The selection of unit size for a particular application 1000 MW, and nuclear plant up to about 1200 MW.
120
Future outlook

FEEDWATER ,
TANK AND
DEAERATOR I

^ HEAT "

e
RECOVERY
STEAM
GENERATOR

ECONOMISER (LP)

EVAPORATOR (LP)

SUPERHEATER(LP)

ECONOMISER (HP)
^
EVAPORATOR (HP)

SUPERHEATER

COMBUSTION
CHAMBER
STEAM TURBINE
SUPPLEMENTARY
FIRING

CONDENSER
GASTURBINE

FEEDHEATER
-

FIG. 1.133 Dual pressure 'combined cycle' plant

121
The steam turbine Chapter 1

The United Kingdom has also gone through a 10.2 Supercritical plant
period of consolidation in the 1970s and 1980s. After One effective way of achieving increased thermal effi-
a relatively rapid increase in unit size from 30 MW in ciency is to increase steam pressure. The limits of a
1945 to 500 MW in 1970, this has only increased to natural circulation boiler are around 180 bar, and
660 MW subsequently. The earliest 660 MW unit was although assisted circulation may be used at higher
ordered in 1966 and was in service by 1974. This pressures, an overall improvement in station efficiency
modest rate of development has produced plant of is not achieved unless the pressure is advanced to
excellent thermal efficiency and reliability, and UK about 240 bar, i.e., above the critical pressure of
manufacturers' designs have been progressively devel- water/steam (221.2 bar). Although the use of super-
oped and refined to take advantage of new technology, critical pressure requires special consideration in the
design methods, and manufacturing methods in the design of the boiler, the implications for the turbine
intervening years. only concern the higher pressure as such.
In the late 1980s, it has been judged that the time A further improvement may be obtained by in-
is right for a further increase in unit size for super- creasing steam temperature. Most of the supercritical
plant in service worldwide operates at 538C, although
heat plant to 900 MW, in order to meet both domestic
some 565C plant exists, and there are some pioneer-
and overseas requirements. For the domestic UK needs,
ing units with temperatures as high as 650C. At the
this offers substantial benefits from the economies
higher temperatures, the efficiency is often boosted
of scale typified by the physical dimensions of
still further by using double reheat. Apart from the
the turbine-generator being only marginally increased
efficiency benefit, this has the merit of reducing the
from the 660 MW units. The initial steam conditions turbine exhaust wetness from the high level that such
have been advanced from 160 bar, 565C to 176 bar, advanced initial conditions would otherwise entail.
565C, thus providing an increase in thermal efficiency
The use of supercritical plant has varied consider-
without sacrificing operational flexibility. ably through the world. In both the USA and Japan,
For nuclear plant, the choice will be determined it has been used to a considerable degree for large
mainly by the reactor type and size. For advanced gas- units for base-load operation, typically up to 700 MW
cooled reactor plant (AGR), the preferred reactor size tandem-compound and 1300 MW cross-compound.
is in the 660-750 MW range. Being a superheat cycle, The initial steam conditions have normally been around
this requires a steam turbine almost identical to that 240 bar, 538C. In Germany, supercritical plant has
for a fossil-fired unit of similar output. Any turbines been in the smaller range, up to about 200 MW. In
required can therefore be derived from the existing the United Kingdom, two prototype units were built
families of modules covering plant up to 900 MW at Drakelow C with steam conditions of 240 bar,
or more. 593C.
For water-cooled reactors, the reactor sizes are up At temperatures up to 565C, low-alloy creep-
to 1200-1300 MW, although some enhancement of resistant steels such as 0.5%Cr Mo V and 2.25Cr
this may be expected. For the first UK PWR at Mo are used for the high temperature components.
Sizewell B, the decision was made in 1979 to employ The pressure determines the thickness of pressure-
two 630 MW turbine-generators with the 1260 MW(e) containing sections such as steam chests and pipe-
reactor, as these made substantial use of modules work. The combination of steam conditions, material,
developed and proven for the 660 MW fossil-fired thickness, and operating regime determines the plant
life in terms of creep and thermal fatigue. At pres-
plant, in particular the LP turbines and the generator.
sures of 240 bar and above, and particularly at the
Those elements specific to the saturated steam cycle,
higher temperatures or where reasonable operational
such as the HP turbine, moisture separator, and
flexibility is required, other high temperature materials
steam/steam reheater (see Chapter 2), had been de-
are used, such as high-Chromium (9-1297) ferritic
veloped and proven in plant supplied to overseas alloys, or austenitic alloys. Austenitic alloys have some
by UK manufacturers at ratings up to 110 MW. It adverse properties, such as poor thermal conductivity
is expected that, if there is a series of PWR stations and high thermal expansion, so the current trend is
in the UK, the decision will be made at some stage to develop the ferritic alloys for use in the large cast
to select a single turbine-generator per reactor, thus and forged components. Development programmes are
taking advantage of recognised savings in capital cost, under way in the USA, Europe, and Japan for de-
construction time and operational costs. In line with signs and materials for the so-called 'ultra-supercritical'
developments elsewhere, it is not expected that reactor plants of 350-1000 MW with steam conditions such
size, and hence turbine-generator size, will advance as 310 bar 590C, and later up to 350 bar 650C,
beyond 1500 MW in the foreseeable future. all with double-reheat cycles. These plants are not,
There is therefore no perceived need for unit sizes to however, likely to be in service until after the year
advance substantially in the next ten or twenty years, 2000.
beyond about 1000 MW for superheat plant or 1500 The use of the double-reheat cycle introduces
MW for saturated steam plant. additional complexity. First, additional boiler controls
122
References

are required for steam temperature, and secondly the As most modern turbine blading in HP and IP
turbine must either have an extra cylinder or it must turbines already has an internal efficiency in the range
use a combined cylinder for the first two expansions. 90% to 95%, the potential improvement is not large.
The extra cylinder increases machine length and cost, Turbine makers have developed standard blading fa-
while the combined cylinder may give the possibility milies of high efficiency which are tolerant to the
of problems due to sealing between the two expan- range of steam flow incidence angles, which arise in
sions or due to the close proximity of sections at different applications and different conditions of op-
hot and cold reheat temperatures. Combined HP/ eration. Root and tip clearances are as small as
IP cylinders have, however, been widely used by practicable, with as many flow constrictions as the
American companies and their associates in machines design permits. The detailed geometry of these restric-
up to 700 MW. tions can allow some reduction of the flow discharge
None of these developments presents technical coefficient, so that steam leakage through these clear-
problems, given sufficient time and resources. Their ances is minimised.
application in practice depends on potential customers The development of LP turbine modules is a costly
being satisfied that the potential return in improved and lengthy process, yet there is always an incentive
efficiency is not accompanied by additional risk either to increase the exhaust area of each flow section to
to plant life, operational flexibility, or availability. reduce the exhaust kinetic energy (the leaving loss).
To this end, the development programmes embody This development may also permit, for particular unit
the full range of research, design, rig testing, and sizes and steam cycles, a reduction in the number of
prototype component testing, which, coupled with the LP cylinders: this is a worthwhile objective to save
first full-size prototype unit, will give the necessary cost and reduce the size of turbine hall required. The
assurance. last-stage and penultimate stage blading is always
The rate at which such plant will be introduced is the limiting area of design; in terms of the steam
however uncertain, depending as it does on factors bending stresses on the blades and the large mass of
such as electricity demand, fuel costs, the economic the blades which imposes a large centrifugal stress
environment, the extent of alternative energy sources, on the blade fastening to the disc. Last-stage blades
and the refurbishment of existing plant for extended for 3000 r/min turbines have been developed up to
life. 1200 mm long: this is believed to be about the limit
for conventional 12% Cr blade materials. Indeed,
the 1200 mm blades in service in the USSR are made
from titanium alloy, and this is likely to be the pre-
ferred material for longer blades. In particular, the
10.3 Turbine blading development introduction of longer last-stage blades is likely to
The development of turbine blading can be expected permit the use of 3000 r/min machines with the lar-
in the future to meet three objectives: gest nuclear reators in 50 Hz systems, although the
3600 r/min equivalents are much further away.
Reduced manufacturing cost.

Improved integrity.

Improved efficiency, including new LP blading of 11 References


increased exhaust area.
[1] Traupel, W.: Steam turbines, yesterday, today and tomorrow:
Proc. IMechE 193 No 38, 391-400: 1979
[2] Harris, F. R.: The Parsons Centenary a hundred years of
The cost of blade manufacture can be minimised steam turbines: Proc. IMechE 198 No. 53, 1-42: 1984
by the application of computer-aided design and [3] Harris, F. R. and Kalderon, D.: The choice of design speed for
manufacture, in which the optimised geometry from PWR turbines for 50 Hz generating systems: IMechE Conference,
performance, vibration, and stress considerations is Steam Plant for Pressurised Water Reactors: 1983
transferred directly to the numerically-controlled [4] Stodola, A.: Steam and Gas Turbines, Volume 1 p 316: Peter
Smith, New York: 1945
machines.
[5] Traupel, W.: Thermische Turbo Maschinen, Volume 1 p 491:
Improved integrity blading can be obtained by at- Springer-Verlag: 1966
tention to detailed design to reduce stress concen-
[6] Miller, D. S.: Internal Flow Systems, Volume 5: British Hydraulics
tration, by controlling the vibration characteristics to Research Assocation: 1978
avoid resonances near running speed, and by reducing [7] Craig, H. R. M. and Cox, H. J. A.: Performance Estimation
the use (or improving the quality) of attachments such of Axial Flow Turbines: Proc. IMechE 185, 32-71: 1970-71
as shrouding lacing wires, and erosion shields. There [8] Briggs, J. Z. and Parker, T. D.: The Super 12% Cr Steels
is a balance to be made between robust blading with an update: Climax Molybdenum Company
thicker sections and efficient blading which favours a [9] Smith, D. M.: Journal Bearings in Turbo machinery: Chapman
higher aspect ratio (length/chord). and Hall: 1969

123
C H A P T E R 2

Turbine plant systems

1 Governing systems 6 Lubrication systems


1.1 Introduction 6.1 Lubrication requirements and typical arrangements
1.2 Governor characteristics 6.2 Oil pumps
1.2.1 Simple scheme boiler on pressure control 6.2.1 Main lubricating oil pump
1.2.2 Turbine master load controller with boiler on pressure 6.2.2 Turbine-driven oil booster pump
control 6.2.3 AC and DC motor-driven auxiliary oil pumps
1.2.3 Boiler master load controller 6.2.4 Jacking-oil pumps and priming pumps
1.3 Subsidiary functions 6.2.5 Other pumps
1.3.1 Acceleration feedback 6.3 Oil tanks
1.3.2 Unloading gear 6.4 Piping
1.3.3 Governor speed reference 6.5 Oil coolers
1.3.4 Closed-loop control of turbine electrical load 6.6 Oil strainers and filters
1.3.5 Overspeed testing 6.7 Oil purifiers and coalescers
1.3.6 On-load testing 6.7.1 Centrifugal separation systems
1.3.7 Automatic run-up and loading systems 6.7.2 Static oil purifiers/coalescers
1.4 Electronic governing 6.8 Oils and greases
1.4.1 Digital processing 6.8.1 Oils
6.8.2 Greases
1.5 Governor valve relays
6.9 Jacking oil systems
1.5.1 Governor valve relay and control unit Type 1
6.10 Greasing systems
1.5.2 Governor valve relay and control unit Type 2
1.5.3 Governor valve relay and control unit Type 3 7 Gland sealing system
1.5.4 Reheater relief valves
7.1 Function and system layout
1.6 Hydraulic fluid system 7.1.1 Labyrinth glands
1.6.1 Filtration 7.1.2 System layout
1.7 Boiler feed pump turbine governors 7.2 Temperature and pressure control
2 Steam chests, valves and loop pipes 7.2.1 Temperature control
7.2.2 Pressure control
2.1 Steam chest arrangements and construction
7.3 Gland steam condenser
2.2 Steam chest materials
2.3 Cover seals 8 Flange heating system
2.4 Steam strainers 8.1 Function and system layout
2.5 Stop valves 8.2 Control
2.6 Governor valves
2.7 Loop pipework 9 LP exhaust spray cooling system
2.8 Crossover pipework 9.1 Function and system layout
3 Turlsine protective devices 9.2 Control

3.1 Possible hazards 10 Drains systems


3.2 Protection scheme 10.1 Function and system layout
3.3 Electrically-signalled trips 10.1.1 Start-up drains
3.4 Overspeed trip 10.1.2 Continuous drains
3.5 Mechanically-operated trips 10.2 Control
3.6 Operator tripping facilities
11 By-pass systems
4 Turbine instrumentation
11.1 Configuration
4.1 Classification of instrumentation 11.1.1 Pressure control valves
4.1.1 Supervisory instrumentation 11.1.2 Isolating valves
4.1.2 Efficiency instrumentation 11.1.3 Dump tube
4.1.3 Auxiliary system instrumentation 11.2 By-pass systems for nuclear plant
4.1.4 Condition monitoring instrumentation 11.3 By-pass systems for fossil-fired plant
4.1.5 Instrumentation associated with protection and control 11.4 Problems with by-pass systems
equipment 11.4.1 Noise
4.1.6 Instrumentation to provide post-incident records 11.4.2 Water ingress
11.4.3 Thermal shock
5 Turbine foundations
11.4.4 Leakage flows
5.1 Tuning
5.2 Concrete foundations 12 Operational flexibility
5.3 Steel foundations 12.1 Typical operational regimes
5.4 Spring foundations 12.1.1 Base load
5.5 Sub-foundation 12.1.2 Two-shifting

124
Governing systems

12.1.3 Load cycling 13.4 Moisture separator reheaters (MSRs)


12.2 Influence on machine design 13.4.1 Separators
12.2.1 Turbine cylinders 13.4.2 Steam-to-steam reheaters
12.2.2 Turbine rotors 13.5 Steam supply and drains systems
12.2.3 Stress monitors 13.5.1 First-stage reheat
12.3 Forced-air cooling 13.5.2 Second-stage reheat
12.3.1 Cooling of turbine 13.5.3 Performance monitoring
12.3.2 Cooling system 13.5.4 System drains
13.5.5 Separator drains
13 Wet steam turbine plant
13.5.6 Reheater drains
13.1 Influence of steam on components
13.2 Water extraction devices 14 References
13.3 Erosion protection 15 Additional references

1 Governing systems system. The initial transient speed rise following such
a load rejection, contained by the governor, is pri-
marily due to two factors:
1.1 Introduction
The stored energy of steam within the turbine and
The main functions of the governing system of a large
its associated pipework.
turbine-generator unit used for electricity production via
an extensive power network are: The time taken by the turbine valves to close in
To contain the speed rise within acceptable limits response to the sensed overspeed.
should the unit become disconnected from the load.
It is always well inside the overspeed trip setting and a
To control the steam valve positions (and hence full analysis is given in Heilbronn [1].
the load generated) in response to signals from the An electrical governing system for a typical turbine-
operator, or from a separate station automatic control generator with multiple steam admission paths comprises
system. many elements, as depicted in Fig 2.1. Since it includes
at least one closed-loop control function, the machine
To control the initial run-up and synchronisation of
and network characteristics form an integral part of the
the machine.
system. The primary feedback is of turbine shaft speed
To assist in matching the power generated to which is usually measured by a toothed-wheel and probes
that demanded by responding to network frequency at the HP end of the machine. This signal is processed
changes. by a modular electronic system, often mounted in a
cubicle quite remote from the turbine, to form output
signals which are directed back to each steam valve on
The first of these functions is a vital one for the safety the turbine. The processing is complex and is subject to
and availability of the plant. Consider a unit at full-load detailed variations for each application; it generally
supplying a power network through its generator con- includes the following:
nections. If these connections are opened, either by a
power system fault or by the unit's own protection The speed/load characteristics of the machine when
system, the steam flow at the instant of disconnection synchronised.
exceeds the steam flow necessary for steady state opera-
tion at 50 Hz (3000 r/min) by the amount necessary to A predetermined relationship between the high
generate full-load. The excess energy input must be pressure (HP) and interceptor valve position.
reduced rapidly if an unacceptable overspeed is to be
avoided. The governor performs this function by re- Facilities for operator control.
sponding to the initial change in speed to close the Features to limit the maximum speed of the machine.
steam valves.
Separate overspeed trips (described in Section 3.5 Features to limit the output in the event of abnormal
of this chapter) are provided to guard against possible operating conditions.
governor failure and ensure that the safety of the plant
and personnel is always maintained. The governor Features to permit routine proving and testing of the
supplements this safety function and, since it maintains system.
the unit at the running speed, ensures the continuity
of unit supplies from its own generator as well as The above functions are described in detail in Sections
the ability to reconnect the generator to the power 1.2 and 1.3 of this chapter.
125
Turbine plant systems Chapter 2

ELECTRICAL
LUMPED INERTIA, SHAFT TORSION & MECHANICAL DAMPING CONSTANTS COUPLING

WHEEL & PROBE


SYSTEM

FIG. 2.1 Electrical governing system applied to a wet steam turbine

Fitted to each steam valve is a relay, whose function unit characteristics are described later in this section.
is to convert the low power electrical signal formed One of the features of an electrical governing system
by the processing equipment into the movement of is that since the conversion to mechanical movement is
the steam valve. Since the mechanical forces involved made at the steam valve relay, all other interfaces are
are substantial (150 kN) and the time for full stroke electrical. This facilitates connections to station
may be less than 200 ms in the case of a load rejec- automatic control systems, alarm systems, data process-
tion, several stages of hydraulic amplification may be ing systems, switches and indicators both on the
necessary. Conversely, in order to obtain fine control operator's desk and at the governor cubicle. All these
over load (or speed when unsynchronised), the gov- other systems are closely associated with either the opera-
erning system needs to be very sensitive and capable of tion or maintenance of governing systems.
moving the valves to within about 0.2% of the required
position. The needs of high resolution and the ability
to amplify small electrical signals, necessitates the use
of precision hydraulic components with fine clearances. 1.2 Governor characteristics
Although earlier mechanical/hydraulic governing systems In normal operation the turbine-generator is synchro-
shared the lubricating oil supply, adequate reliability nised with and connected into an electrical power sys-
of the precision systems is only assured by the use tem, comprising other generating units and an extensive
of a separate high quality fluid supply unit. Various network for distributing power to the consumer. Typi-
configurations of valve relay and typical fluid supply cally, in the UK, the power supplied at any instant is
126
Governing systems

in the range 15 to 50 GW and many turbine-generators


are needed in parallel to supply the power at a steady
z o
voltage and frequency. Consumers expect to switch Q
LU
cc z
their loads on and off at will. On a large power system,
Z Q
LU LU
CL Q LU
C/5
the minute-by-minute fluctuations will be a small per-
LU
LU
_
CL

centage of the total load. On a local power system, S C/)
<

Q 1
supplying only a few consumers from a small number _J LU _l

fei O
of generating units, similar consumer demands may apply LLI DC 1 Z

and the fluctuations may be a significant percentage


of the total load.
Nevertheless, on both large and small systems, faults
will occur, and to maintain safety in such an event protec-
tive equipment operates to open circuit-breakers to isolate
the fault. .
O
2
For the individual turbine-generator unit and its gover-
ning system, these power system requirements imply a Q

need to withstand a full-load rejection safely and to


provide appropriate contributions to system frequency
regulation.
The main characteristic of a governing system is
therefore the relationship between the generated load of
the controlled machine and speed, which is the prime
governor input. This is known as the speed-loop droop
or frequency regulation characterstic of the governor and
is shown in Fig 2.2. The steady state overall frequency
regulation is defined as: 2880 3000 3120
SPEED, r/min

Nn - N PR FlG. 2.2 Governor frequency regulation characteristic


x 100%
Nt

where N R = rated speed


NPR = speed at full-load
N0 = speed at no load

This regulation permits a machine to share load with


other machines in a stable manner and also allows
the operator to adjust the load contribution made
by the machine relative to the others on the system. C1 c
2 Lb3


1
Figure 2.3 shows how the droop characteristic is varied
by altering the speed setpoint. If the machine is at \
no-load and unsynchronised, point aj on the diagram, \ \
and the setpoint is raised, the frequency will change
from aj to a 2 and then to a 3 . If, however, the machine
is synchronised to an infinite system running at constant o
frequency a 1? an increase in speed setpoint will cause
the load to be raised to b 2 and eventually to b 3 . It
\ I
\ "1
should be noted that the linear characteristics drawn
are idealised; in practice they may be non-linear.

1
^Ab2
Nevertheless, the degree of adjustment of the speed
\

1
setpoint should permit no-load to be set at the lowest \
normal operating frequency and also full-load at the \
highest normal frequency, with a margin. Typically the \ \ .
range of operation is 6 % of nominal system frequen- ai a2 a3
\
cy with the turbine unsynchronised at no-load. FREQUENCY
Another feature to be noted from Fig 2.3 is the
phenomenon of an 'overwound' speed setpoint. If the
operator has set the unit to run at full-load at fre- FIG. 2.3 Effect of variation of speed setpoint

127
Turbine plant systems Chapter 2

quency f by adjusting the speed setpoint to give char- below the overspeed trip setpoint on a high droop gover-
acteristic a 3 b 3 , then a fall in frequency by an amount nor. On a low droop governor (say 4% or less), the
f will give a notional load of value c 3 . However, this overspeed may be contained by the normal droop
value of load will not be attained, as the turbine valves characteristic without any need for the special overspeed
are already fully open at point b 3 . The speed setpoint limiting facilities.
is said to be 'overwound'. The disadvantage of this condi- In either case, to meet the requirement of containing
tion is that, if asked to reduce load on the unit, the the overspeed within the trip setpoint, it will be necessary
operator is unable to do so immediately until he has to close all the turbine valves within a fraction of a
reduced the speed setpoint to the line given by c 2 a 2 . second. When the speed error reduces, the governor
Normal practice is either to draw the operator's atten- reopens the valves to the amount necessary to maintain
tion to the overwound condition by an alarm or to the speed at the reduced value of load.
provide an automatic reduction at the setpoint so On reheat machines such as that depicted in Fig 2.1,
that an immediate response is possible, if required. it is necessary to control not only the HP governing
Facilities for droop adjustment are often provided. valves but also the interceptor governing valves follow-
Typically a high value of droop, like 25%, may be ing the reheater. If the HP valves only were closed rapidly
beneficial in reducing transient steam pressure varia- on a full-load rejection, the amount of stored steam in
tions if the system frequency fluctuates to a marked the reheater and associated pipework would be sufficient
degree. The droop may be adjustable within a range to overspeed the machine to destruction. Therefore,
or alternatively switched from a selection of two or similar rapid response to close the interceptor governing
more values. Droop adjustment, or switching, on-load valves is provided.
generally implies a load change unless carried out at Most large turbine-generators employ reheating of the
the pivot point of the characteristic or unless coupled intermediate pressure (IP) steam to improve thermal
with a simultaneous change in speed setpoint. Many efficiency. Thermal efficiency is reduced if throttling
governors incorporate facilities for a 'bumpless' change takes place in the interceptor valves, so these valves are
in this fashion. usually fully open over the normal load range of the
Figure 2.4 is a development of Fig 2.3, showing the machine. This operating regime is referred to as HP
characteristics of additional overspeed limiting facilities governing and is achieved by applying a fixed bias to
that have to be built into the design so that the speed the interceptor governing valves, thus giving them the
rise on a load rejection can be adequately contained same speed/load characteristics as the HP governor
valves but more open by the amount of the fixed bias
(typically 50%). In the event of an overspeed, these valves
will close, albeit at a greater speed-error than the HP
governor valves.
Another possible mode of operation (often provided
as a switched option) is to allow the interceptor govern-
ing valves to operate in a throttled condition. Although
the thermal efficiency is reduced, 'the spinning spare
capability' of the plant is enhanced: the capability of
the machine to increase load rapidly in response to
either a reduction in the power system frequency or
a demand by the operator to increase load. This may
be important in power systems where there are large
fluctuations in network frequency, or where there are
insufficient machines with good regulating character-
istics. This mode of control is referred to as HP plus
IP governing or sometimes as parallel governing. In the
HP governing mode, the reheater pressure is normally
proportional to the load on the machine, but in the HP
plus IP governing mode, the aim is for a constant re-
48 49 50 51 52 53 heater pressure, at least over the load range of 50-100%.
MINIMUM SPEEDER GEAR RANGE AT NO LOAD I This means that at 50% load, instead of the pressure
FREQUENCY, Hz in the reheater being say 20 bar, it will be at the
NOTE full-load value of 40 bar and the 'spinning spare'
THE REQUIRED RANGE OF OPERATION IS INDICATED BY THE SHADED AREA.
GOVERNOR CHARACTERISTICS MAY EXTEND OUTSIDE THIS AREA PROVIDED capability will be improved by the additional thermal
THIS DOES NOT IMPAIR THE SAFETY OF THE SYSTEM OR CAUSE THE SET TO
TRIP ON OVER-SPEED OR LOSS OF FULL LOAD. storage available through having reheater steam at the
full-load pressure. Thus the IP and LP cylinders will be
able to provide their full-load torque almost immedi-
ately, although there may later be some decay until the
FlG. 2.4 Turbine speed governor characteristics boiler firing rate has picked up to its full-load value.
128
Governing systems

The characteristics described so far in this section are


those that suit the parallel connection of turbine- MEASURED LOAD MASTER LOAD
CONTROLLER
generators onto the power system. However, some of
the features of a governing system arise from a considera- DEMANDED LOAD
tion of the types of plant being controlled and the way ERROR SIGNAL
TO INCREASE OR
in which the control of the separate boiler and turbine DECREASE
units is integrated to form an overall Station Control SPEED SET-POINT

scheme. The purpose of this description is to note the VOLTAGE ANALOGUE


main features affecting the governor. Three basic options OF FREQUENCY
SET LOAD
are described, each of which may include enhancements LOOP DROOP
(not described) to improve the response to particular
operational circumstances. FlG. 2.5 Schematic of a simple load frequency controller

1.2.1 Simple scheme boiler on pressure


control speed setpoint, which changes the load on the turbine
In this scheme the governor speed setpoint is controlled to reduce the error. This form of slow-acting integral
by the operator to load the machine by means of the error correction gives accurate droop characteristics
governor droop characteristics. Options for droop adjust- or control to a fixed load (infinite droop), if selected.
ment are often incorporated. The master load controller may be included as part of
For commissioning purposes it may also be an ad- the governing system or may be provided separately in
vantage to include a valve position limiter or a load a unit control scheme. Apart from providing accurate
limiter. These would either prevent the turbine valves linear droop characteristics, the performance of this
from opening above a certain proportion of their travel scheme is very similar to the scheme described in the
or, by load measurement, would prevent further valve previous subsection.
opening above a certain load setpoint. The main dis-
advantage of the overall scheme is that a load rejection
would cause the turbine steam valves to close rapidly, 1.2.3 Boiler master load controller
thus losing all flow through the boiler, possibly with In this scheme, the output of the master load controller
maximum firing rate applied. Although the boiler safety described in the previous case is used to set the boiler
valves would lift a few seconds later, there is some firing rate. The governor speed setpoint is controlled by
likelihood of thermal damage to superheater tubes. a boiler pressure error signal, so that the turbine valves
A turbine by-pass system (described in Section 11 increase or decrease steam consumption in a sense to
of this chapter) is one option which could ameliorate reduce the error. This responds very satisfactorily to load
this effect. changes demanded by the operator as the boiler firing
Another disadvantage is that any load increase, rate correction is made first and, subsequently, the rapid
whether applied to the turbine manually by the opera- response of the turbine can easily control any pressure
tor or automatically because of a fall in frequency, fluctuations.
is necessarily matched by the boiler. Because the flow
However, rapid changes in frequency, particularly
increases, the pressure will fall to a degree dependent
the increase arising on load rejection, still produce
on the response of the boiler control system. Addi-
the necessary governor safety response and abrupt
tionally, the droop characteristics provided in the
changes in firing which cause large boiler pressure
basic governor are usually derived by measurement
valve position rather than electrical load. This may fluctuations.
result in incremental droop deviations at any operating
point due to the imperfection of valve linearisation
characteristics (see Section 1.4 of this chapter).
1.3 Subsidiary functions
This section describes additional functions of gov-
1.2.2 Turbine master load controller with boiler ernors, giving typical characteristics of these features.
on pressure control Not all governors include all these features; in some
To overcome the previous point about non-linear droop cases they may not be essential to the plant being
characteristics, a separate load/frequency controller is controlled, or they may be carried out in other equip-
built having the features shown in Fig 2.5. For any ment but operating through the governor. Equipment
operating frequency, depending on the characteristics, for HP rotor stress control during run-up and load-
there will be a demanded load determined by this ing is a typical example of the latter. It can be
characteristic which is compared with the measured performed by an external computer modulating the speed
electrical load in the master load controller. The result- setpoint of the governor or it can be an intrinsic part
ing error signal provides the input to the governor of the governor.
129
Turbine plant systems Chapter 2

1.3.1 Acceleration feedback of which would normally cause a turbine trip. It is


Acceleration feedback is commonly used to provide a incorporated so that the condition likely to cause a
secondary stabilising term to improve the damping of trip is sensed early and the turbine load is decreased
the governor and to assist the prime safety function of to reduce the probability of tripping. If a trip does
the governor in preventing overspeed due to a load occur, then the transient effect on the plant is reduced
rejection. because it occurs at a lower load.
With a disconnection from the power system, the Low exhaust pressure unloading-gear is normally
response of a governor without acceleration feedback provided. The pressure is usually sensed at tapping points
would be controlled by the speed error term as modified on the condenser. During normal operation the unloader
by the droop law. If the speed droop is set to 4%, the has no effect. However, if a condenser or cooling water
valves would have fully closed by the time the speed was system fault causes the exhaust pressure to rise above
4% above nominal. A typical value of the initial accelera- a threshold value, typically 120 mbar, any further rise
tion rate is 12% per second, so it would be at least 0.33 causes the turbine to progressively unload, the degree
seconds before the valves had been signalled to the fully- of unloading being linearly proportional to the further
closed state. In addition, inherent delays in the hydraulic rise in exhaust pressure. A typical unloading character-
system mean that the valves do not achieve the signalled istic is shown in Fig 2.7. The purpose of unloading
closure response. Taking a linear acceleration rate of is to reduce the effects or probability of a trip. The
12% per second, the time to reach an overspeed of 10% reason for providing a trip is discussed separately in
would be 10/12 = 0.833 seconds. Because of the Section 3.1 of this chapter. The degree of unloading
expansion of steam entrained between the steam valves is usually limited to about 20% load to avoid the pos-
and the turbine, the turbine will continue to accelerate sibility of motoring. The rate of unloading is generally
after the steam valves are closed. To contain the consistent with the rate of increase in exhaust pressure.
overspeed within the trip setting of 10%, it is generally However, if the initiating cause of unloading is remov-
necessary to incorporate an acceleration term. ed and the exhaust pressure falls to a normal value,
A governor incorporating acceleration detection can the turbine remains unloaded until the operator or a
sense the need to close the steam valves as soon as its separate external automatic control function restores
measurement circuits are able to respond. The valves can the load. This is achieved by resetting the governor
be instructed to close at maximum rate within 30 ms of speed setpoint which has been independently reduced
the load rejection and should be fully closed 100 ms later. to track the degree of unloading that has taken place.
Figure 2.6 shows a typical response to a load rejection. On initial start-up and loading, it may be necessary
To ensure that this form of acceleration feedback only to veto the operation of the loading gear until the
comes into play during a significant load rejection, a exhaust pressure has reduced to a value such that it is
threshold is preset into the sensing system below which unlikely to restrict the initial loading up to full-load.
there is no output. The acceleration signal must also be The veto is normally removed by the operator but, if
present for a preset time before it takes effect. forgotten, the veto will be automatically removed when

1.3.2 Unloading gear


Unloading gear may take several different forms, depen-
ding on the plant being controlled. It is usually
complementary to a protective function, the operation

80

o
2
60
Q
<
O
OPeRAHN$
REGIME
40

20

Mr ^50 -L
100 150 200

f TURBINE EXHAUST PRESSURE, mbar

TYPICAL FULL LOAD SETTING OF HIGH


TIME OPERATING PRESSURE EXHAUST PRESSURE TRIP

FIG. 2.6 Turbine response to load rejection FIG. 2.7 Turbine exhaust pressure unloading characteristic
130
Governing systems

the exhaust pressure reaches the value which permits corporates an inverse function so that all upstream gover-
full load (about 120 mbar, as shown on Fig 2.7). nor processing has an almost linear effect on the steam
demand at one nominal set of steam input conditions.
However, if the conditions vary, the significant non-
1.3.3 Governor speed reference linearities will give rise to imperfections. Closed-loop load
The governor speed reference is the prime input by control overcomes these imperfections by superimpos-
which the turbine can be controlled, either by the ing a trimming signal onto the governor speed reference.
operator or by one or more external automatic con- A block diagram of the load loop is shown in Fig 2.8
trolling functions. The range of speeds over which the and the characteristic it produces in Fig 2.9.
reference can be set will depend on whether the turbine
is synchronised or unsynchronised. Prior to synchronisa-
tion, the speed reference range will extend from the MEASURED LOAD MASTER LOAD
lowest controllable speed (typically 3% of nominal) up CONTROLLER

to the highest speed at which the turbine-generator


must be capable of synchronisation (104%). Once DEMANDED LOAD
ERROR SIGNAL
synchronised, the speed reference will be limited to the TO INCREASE OR
range 94-106%. DECREASE
SPEED SET-POINT

Different maximum rates of increase or decrease of VOLTAGE


the speed reference also apply. Prior to synchronisation, ANALOGUE
OF FREQUENCY
the rate of increase may be selected by the operator or
FUNCTION GENERATOR
it may be a quite rapid fixed rate which is compatible LOAD LOOP FREQUENCY

with the maximum conceivable rate at which the turbine CHARACTERISTIC

speed could be increased if warmed through and all


conditions were at an optimum. In this latter case, the
FIG. 2.8 Block diagram of load loop
setpoint would either be manually raised by the operator
in small steps, subject to the observed conditions, or
raised by a separate automatic run-up system. The rate
of decrease is usually a single fixed rate.
When the turbine-generator comes under control 1l 4% DROOP
of the auto-synchroniser, or if manual synchronisation
is to be performed, another rate-of-change of speed V2% DROOP
reference will apply. This must be compatible with the
autosynchronising unit and is usually designed to give
,1
fast and certain synchronisation. 10% D R O O P N X
When synchronised and under operator control, the ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ ^ H 00 DROOP

rate-of-change is conventionally set to give full travel 3% MCR TO


from - 6 % to +6% of nominal speed in 2 minutes. Q
30% MCR

The governor speed reference now acts as a load S


reference and, if a 4% droop is applicable, this means
_l

^ADJUSTABLE
that the equivalent rate of load change is 2.5% per RANGE

second. Whether or not this rate-of-change can be


DEMANDED
\\ ! '
LOAD
^^^^^\
sustained is dependent on the steam supply system, so V t ^ 4% DROOP

the operator must take care to control the appropriate


parameters if a prolonged increase or decrease is 0.05 Hz
required. to 0.20 Hz

An automatic unit controller is generally used to raise 1

or lower the governor speed setpoint in preference to


50 ~~
FREQUENCY, Hz
the operator. In this case a specific rate, usually slower
than 2.5% load per second, will apply.

FIG. 2.9 Load loop frequency 'box' characteristics


1.3.4 Closed-loop control of turbine electrical load
Closed-loop control of turbine electrical load is added
to the basic governing system to give accurate load droop
characteristics and facilitate the provison of variable- The frequency range over which the load loop is
droop settings. The basic governor incorporates a speed operative is limited so that, even when the load loop
droop system where the trimming signal is derived from droop is set to high or infinite values, the unit responds
steam valve position. Because the steam flow/position to any large frequency errors in a manner matched
relationship is non-linear, the basic speed governor in- to the characteristics of the normal 4% droop of the
131
Turbine plant systems Chapter 2

basic speed governor. By limiting the load range over then the HP stop, IP governing and IP stop valves until
which the load loop is operative, the magnitude of the whole group is closed. Valves are opened in the
sudden load changes on the boiler system is limited if a reverse sequence and there is also the capability for rever-
low speed droop is used. For obvious reasons (Fig 2.9), sing the sequence at any point when the group test is
speed and load variations over which variable-droop only partially complete.
is permitted are known as the box characteristics. On a typical wet steam (PWR) turbine, there will be
Consider a sudden fall in network frequency on a four HP inlet and six LP inlets so a group cannot be
number of machines operating in parallel with different defined in the above manner.
droops but similar box size. Because the load loop is A vital part of the on-load test equipment is the provi-
slow-acting, through the governor speed reference, all sion of some means for the operator to monitor the
machines initially contribute an increase in demanded performance of the valves. This may be done by
load. Then those machines with high or infinite load loop automatic initiation of a chart recorder, giving a time-
droops will slowly reduce in load, returning to a value base against which the opening and closing times of the
at or near their original load. This allows the other valves may be judged for conformity to the specifica-
machines with low droop to pick-up load at a rate tion. Another method is to use an XY plotter with the
compatible with their boilers. The advantage of this actual valve position being plotted against the demand-
arrangement is that some units can be designated for ed position. This can be arranged to give a well-defined
rapid load pick-up, whilst those unable to sustain such characteristic for a correct test, so that an incorrect test
a transient can still contribute usefully to the control of is readily identified. A third method, likely to be
falling frequency. employed in the future, is to make use of the VDUs
provided in the control room for data processing. A
similar type of record to that described for the XY plotter
1.3.5 Overspeed testing may be obtained, using a temporarily enhanced scann-
Overspeed testing to prove the actual value of trip ing rate for the valve position signal of the valve under
setpoint of overspeed protection systems is an essential test.
subsidiary function of governing systems. The testing is
carried out on an unsynchronised turbine. Initially, the
operator has to operate a key-locked test switch which 1.3.7 Automatic run-up and loading systems
permits a higher than normal governor speed range Automatic run-up and loading systems are provided for
up to + 13% rather than + 6 % . The normal governor two main reasons:
raise button is used to increase speed to the trip set-
points. The full method of testing is described in To assist the operator in making the complex sequence
Section 3.5 of this chapter. of checks necessary prior to and during start-up.
The ability to test the correct functioning of each
To run-up and subsequently load the turbine in a
turbine steam valve is necessary for both on-load opera-
safe and consistent manner. Sophisticated schemes
tion and also prior to run-up. The latter is described as
can be provided where the rate of run-up or loading
valve exercising, the requirement being to stroke each
is faster and less stressful for the machine than a
valve open and closed individually, to test valve freedom
human operator could reasonably achieve.
of movement. As far as the operator is concerned this
uses the same controls as on-load testing, with the excep-
tion that selecting exercise' ensures that the valves can The primary output of a typical system is to the basic
only be opened if the boiler stop valves are closed. speed governor, either to increment the speeder gear
or to the governor in such a way that failure of the
output signal gives a similarly rate-limited change in
1.3.6 Onload testing demand. Some outputs of digital state signals provide
On-load testing can only be carried out on groups of interlock or initiation signals to the governor and auto-
valves in turn. Thus, on a four-inlet turbine, one group synchroniser, whilst others provide indications to the
of valves comprises the left-hand front HP governing, operator. The inputs and outputs are shown on Fig
HP stop, IP governing and IP stop valves. The on-load 2.10. The inputs to system depend on the degree of
test system includes facilities for checking the operation sophistication, in the most comprehensive case they
of all the valve relay inputs. On HP and IP governing would be as shown.
valves the ability to close in response to governor signals The scope of the system described here assumes that
is checked and also the means of tripping the valve in separate operator actions or sequencing systems bring
response to the action of the protection system. On HP all the auxiliary systems necessary for the safe opera-
and IP stop valves, the normal tripping and resetting tion of the turbine to a satisfactory state of readiness.
action from the protection system is checked and also Thus lubricating oil, main and auxiliary CW systems,
the facilities provided as back-up for emergency closure. etc., will have previously been brought into service.
Testing of a group of valves is carried out sequentially, A digital state signal will indicate that each of these
starting with the closure of the HP governing valve, conditions or prestart interlocks has been satisfied.

132
Governing systems

HP STRESS REFERENCE

HP PROBE INNER/MIDWALL SIGNAL


CONDITIONER COMPENSATOR
TEMPERATURE DIFFERENTIAL

HP STEAM/METAL
SIGNAL
HP THROTTLE DROP CONDITIONER

CALCULATED FROM
TEMPERATURES AND PRESSURES

ru
HP GOV. VALVE CHEST SIGNAL
STEAM/METAL CONDITIONER
TEMP DIFFERENTIAL
HP GOVERNOR VALVE CHEST STRESS REFERENCE HOLD SIGNALSl PROPORTIONAL GOVERNOR
LOW VALUE PLUS
COMPENSATOR AND


GATE
LOGIC NTEGRAL TERMS
HP GOVERNOR VALVE INNER/
MIDWALL SIGNAL
CONDITIONER
TEMPERATURE DIFFERENTIAL

VIBRATION

ECCENTRICITY TURBINE
SUPERVISORY
LIMITS
DIFFERENTIAL EXPANSION

PLANT INTERLOCKS PRE-START


CHECKS

FIG. 2.10 Automatic run-up and loading equipment

Because of the large number of plant-mounted trans- and load. The method of controlling these is dependent
ducers providing inputs, careful consideration is given on the type and size of the turbine and the steam condi-
at the design stage to provide enough redundancy to tions for which it is designed. Thus large turbines
permit fully automatic run-up and loading with high working at high main and reheat temperatures, when
availability. Most inputs are either duplicated by f a s t e r ' specified for two-shifting duty, require the most
and 'check' transducers at the same measuring point, or sophistication if optimum run-up and loading rates are
there is functional duplication built into the system to be achieved. A large wet-steam turbine for base load
because of measurements made at entirely different operation requires control of stress in the HP chests and
measuring points (e.g., separate measurement of inlet rotor, but the LP chests and rotors do not need any
steam pressure in left-hand and right-hand steam chests). separate control at all. Direct measurement of stress, by
Thus, if one of the minor input signals is lost, fully thermocouples measuring the difference between inner
automatic operation may still be possible. The failed and midwall metal temperatures at suitable measuring
transducers are identified to the operator. points, provides a means ofcontrolling run-up or load
If several minor input signals are lost or one of a changes to the optimum values. Control is of a closed-
duplicate pair of major signals, automatic control may loop proportional form, acting into the governor as
be restricted such that there is only a fixed safe accelera- shown in Fig 2.10, so that stress is held constant at the
tion rate (if in run-up mode) or fixed safe loading rate reference value throughout most of the run-up.
(if on load control). One exception to this concerns the critical speed bands
If further signals fail, only manual control may be of the turbine, which are determined by rotor dynamics.
possible. The turbine governor will provide a limitation Here the strategy is to ensure that there is a large stress
on the rate-of-change of speed or load, but this will not margin before entering the critical speed band and then
necessarily be safe, particularly if a cold start is in to provide a rapid acceleration through it. Any 'hold'
progress. The operator must then decide whether there signals from the operator (or any other source) are vetoed
are sufficent desk indications to permit progress, or to whilst within the band.
hold at a safe condition whilst a repair is effected, or Provision is often made to 'hold' run-up and loading
to shut down the turbne. by vibration, eccentricity or differential expansion signals
The main requirement of the automatic run-up and sensed by the separate Turbine Supervisory Equipment
loading system is to limit the thermal stresses within the (TSE). These will also be vetoed within critical speed
turbine rotor and valve chests during changes of speed bands or during block loading; outside these bands

133
Turbine plant systems Chapter 2

they act first to hold and then to advise the operator tions. The speeder gear provides the basic setpoint to
if any of the TSE signals exceeds a predetermined the governor. The acceleration feedback is normally
limit. The 'hold' will be released if the controlling not effective in the steady state but comes into op-
parameter reduces to 80% of the application level. If eration transiently when required. Unloading gear can
the TSE signal continues to increase above the 'hold' reduce the steam demand when required. Other in-
limit, a second limit is reached at which the operator puts, such as the overspeed test speed demand or valve
is advised to trip the machine. testing controls, are switched into service by the op-
When the turbine reaches synchronous speed, a num- erator when required. Auto run-up and loading rates
ber of pre-synchronising checks are made (e.g., the apply the demands of operator or the unit control
Automatic Voltage Regulator must be on 'Auto') and system for a change in turbine output to the speeder gear
then a signal is given to the autosynchronising system in the optimum manner. Note that the governor can
that the turbine is ready and in a safe state to accept be split into two parts a common processing system
load. The governor speed demand is then increased or and a number of individual valve controllers.
decreased automatically by pulses from the autosyn-
chroniser until synchronism is achieved, the circuit-
breaker being automatically closed by the synchroniser
following the operator's command to autosynchronise.
1.4 Electronic governing
Alternatively, the synchronisation and circuit-breaker
closure is carried out manually. Traditionally, the early mechanical and mechanical-
hydraulic governors, performed their main function of
Following synchronisation, a block load of about 5%
maintaining the safety of the unit reliably. The provi-
is applied automatically. This is to ensure that changing
sion of series emergency stop and governor valves has
network frequency does not act through the governing
provided protection against the occasional failure of a
speed loop to unload the turbine completely and produce
undesirable motoring of the generator. valve to respond to its control signal, while the failure
mode of the mechanical speed error sensing arrange-
Thereafter loading takes place as required by the
ment has generally been to deteriorate slowly in per-
operator or by the unit control system. As described
formance rather than to fail suddenly. Even so, the
previously, the rates-of-change are controlled by limiting
provision of two sets of steam valves in series, with one
stress levels, default rate limits or by TSE 'hold' signals.
set operated directly by a separate protection system has
The operator interface is an important factor taken
also negated the effect of a sudden failure. The relia-
into account in auto run-up and loading schemes. The
bility of mechanical governing systems has therefore
essentials are that the operator has the ability to ini-
not been closely monitored in the past.
tiate the sequence of run-up and the synchronising
action. He must also have overriding control to hold or Before discussing the configuration of the electro-
to reduce speed at all points in the sequence if required, hydraulic governing systems current on modern turbine
apart from critical speed bands and when block loading. plant, it is necessary to understand the meaning of
Information must be presented to the operator so that reliability in this context. The general definition of
he knows the state of the turbine, the limitation being reliability is the probability of successfully achieving a
applied at the time and the status of the control inputs. desired task, usually over some specified time period.
Failed signals must be brought to his attention and Taking the total task of the governing and protection
abnormal turbine operating conditions alarmed. systems to prevent a dangerous overspeed, the probability
In a wider context than auto run-up and loading of success in this must be of such a high order that failure
schemes, it is vitally important to keep the operator aware is never encountered. This is achieved by providing
of any abnormal control action, such as the operation completely independent governing and protection sys-
of unloading gear or any governor fault which is causing, tems, using different hardware and different techniques
or likely to cause, a load reduction if not rectified. for speed sensing, operating by different routes to the
Typically an unloading gear operated' alarm and a two series-connected sets of valve gear. Obviously, the
'governor fault' alarm would be provided. If a governor reliability of the speed governor should be as high as
fault developed into a situation where the governor could possible to achieve this and may be defined as the
no longer control the machine, a further alarm 'gover- probability of not exceeding the overspeed trip setpoint.
nor tripped' would be generated concurrently with the However, in any general governing system, the valve
signal to trip the turbine. position output has three failure modes. A valve can close
The component parts of governing systems have down, open up or stick in its current position. It is
now been discussed fully in functional terms. The only when either of the last two occurs and is followed
subsidiary functions described may be provided in total by an event leading to a sudden unloading of the
or in part for any particular application. Irrespective turbine, for example, the opening of the circuit-breaker
of the method of implementation, it is necessary to on a turbine driving a generator, that the overspeed
understand how the subsidiary functions are connected trip is brought into operation. There is also the pos-
into the main governor. Figure 2.11 shows the most sibility, in an uncoupled turbine, that a failure will
complex scheme, incorporating all the described func- occur through an excessive speed demand.

134
Governing systems

OPERATOR
CONTROLS WIDE RANGE
RUN-UP
SPEED
CONTROLS
CONTROL

WIDE RANGE
SPEED
DETECTOR =Ch
STABILISING HP GOVERNOR
VALVE SERVO &| HP
LINEARISING VALVES
CHANNELS
ACCELERATION
NARROW FEEDBACK
RANGE
PLANT
SPEED
INPUTS ON-LOAD
DETECTOR [SPEED LIMITING!
AND TEST

a
OVERSPEED CONTROLS
TEST MAIN 1& INTERLOCKS!

m
LIMITER
(LOW VALUE [ I I INTERCEPTOR I
INTERCEPTOR!
LrOJ
H
DROOP GATE) : T
l GOVERNOR I
(VALVE OFFSET W VALVE SERVO &l _ _
VARIATION SEQUENCE |
: LINEARISING I
J I CHANNELS |
OPERATOR INTERCEPTOR
(SPEEDER GEARI VALVES
CONTROLS- LOADING AND MAIN
CONTROLS LOAD/SPEED
CONTROL

UNLOADING
GEAR

PLANT OUTPUTS
INTERLOCKS -GOVERNOR

GOVERNOR
-^"
INTERNAL OPERATOR
SIGNALS INDICATIONS
H ALARMS

FIG. 2.11 Governor overall block diagram

Failures caused by spurious valve opening can be liability. They will, however, be embraced in the overall
designed to be less likely than failures resulting in valve 'mean time between failures' statistics for the governor
closure. For instance, loss of hydraulic or electrical and will obviously be of importance to the user of gover-
supplies can be made to close the valve by a closing spring ning systems.
or by a preset electrical null bias. Figure 2.12 shows a detailed block diagram of a typical
In practice, the most likely effect on operation will governing system. The main feature of an analogue
be a fault causing a load reduction or a complete loss system is that each function is performed by a discrete
of load. It will be seen from the block schematic diagram set of circuit components, whose sole task is to perform
(Fig 2.11) that single faults in a valve channel can cause that function by converting input signals into output
one valve to close, giving a partial loss of load. A signals whose amplitude (in voltage or current terms) is
complete loss of load would require a failure in the directly proportional to the required transfer function.
common processing part of the governor. There are thus This feature is particularly suited to the adoption of a
strong grounds for enhancing the reliability of this part modular approach to the hardware, where a function
of the governor by providing redundancy or monitoring (or a group of functions) are performed by a module
techniques. These are described later in this section. The and the output (or outputs) passed on to following
probability of not achieving a complete loss of load is modules. This permits a simple approach to fault finding
therefore another important governor characteristic. by monitoring signal levels.
Because redundancy or monitoring is normally em- A three-channel system can be made to satisfy the
ployed, when faults occur in the common processing reliability requirements established for governing systems.
part of the governor, they will be annunciated to the If a failure occurs in one channel, it causes the output
operator so that maintenance can be carried out. Faults of that channel to deviate from the other two channels.
can also occur in individual valve channels causing Detection circuits are incorporated, in addition to the
only a partial loss of load. These can usually be re- three processing channels, to identify failed channels
paired on-line without interfering with operation or and to disconnect them before they can contribute an
registering in any of the previous definitions of re- erroneous output. Because the detection circuits deter-
135
136
EXHAUST CONDENSER
PRESSURE "
TRANSDUCERS

GENERATORU
Turbine plant systems

INTERCEPTOR
OFFSET
CONTROL

FIG. 2.12 Detailed block diagram of a single-channel governing system


Chapter 2
Governing systems

mine the output on the basis of the correctly operat- signals into forces large enough to position the steam
ing channels, they are often called 'majority voting valves. The variety of configurations employed are fully
cireuits\ Figure 2.13 shows the block diagram of Fig described in Section 1.5 of this chapter. For the moment,
2.12 divided into three independent parallel channels. it should be noted that a degree of self-monitoring is
The central processing part of the governor terminates provided so that a faulty valve, hydraulic relay or servo
where the three outputs of each linearising network amplifier will identify itself to the operator and apply
are monitored by the final majority rating circuits a closing signal to the valve. Inter-valve monitoring is
associated with the steam valve servos. These circuits performed in some governors, since it is usual for all
are extremely simple and therefore reliable. They have valves of one type (e.g., HP governor valves) to have
the characteristic that for small discrepancies in the the same percentage opening, within limits. However,
input signals, the output signal is the average of the this form of monitoring must be vetoed during on-load
inputs whilst, for large discrepancies, the mode of testing of valves where only one valve of a set is closed
action becomes that of a median-selector. at any time.
It will be noted from the diagram that the exhaust Having now outlined the basic structure of a three-
pressure unloader is isolated from the main signal path channel analogue governing system, it is now appropriate
by a triplex majority-voting system. Since transducer to examine in more detail some of the functional blocks
failures are a major factor in system reliability, this gives shown in Fig 2.12. The provision of separate narrow
a further measure of protection for the basic governor range and wide range speed detectors stems from the
which will continue to operate as a full three-channel requirement (for a turbine driving a generator) for
system. accurate control at the network frequency.
Each valve servo amplifier is ostensibly single-channel The narrow range speed detector uses either the
and the precise configuration is closely associated with characteristics of a tuned circuit or pulse timing tech-
the hydraulic system used to amplify the electronic niques to determine the deviation from the reference

WIDE RANGE
SPEED
CONTROL

FINAL GOVERNOR
MAJORITY VALVE
VOTES SERVOS

EXHAUST
PRESSURE
TRANSDUCERS

ACCELERATION
CIRCUITS

FIG. 2.13 Block diagram of a three-channel governing system

137
Turbine plant systems Chapter 2

speed corresponding to the nominal network frequency. An automatic run-up mode; this may be selected as
The detector circuit provides a linear frequency to an alternative to the fixed ramping rate which requires
voltage conversion over a limited range only. The rea- close operator supervision of machine parameters.
son for providing a separate narrow range signal is
that, by using such techniques, better long-term accu- Therefore, as in the case of the narrow range governor,
racy can be obtained. However, neither technique will these requirements are conveniently carried out by a
function correctly when there is a substantial deviation motorised potentiometer suitably controlled by the
(e.g., >10%) from the reference frequency. In the operator. More recent practice employs the electronic
tuned circuit, this is because of a loss of linearity away equivalent of the motorised potentiometer (shown in
from the null point to the extent that gross errors in Fig 2.14).
the sense of the output will occur at sub-harmonic The speed control on the operator's terminal pro-
frequencies. The timing circuit measures the time for vides an input to two signal comparators Cl and C2,
a number of teeth on a speed-sensing wheel to pass whose other input is equivalent to the demanded speed.
the detector and compares this with a fixed accurate If there is no difference between these two speed
time reference. The number of teeth passing in one demands, neither oscillator is activated and the counter
revolution of the wheel and the number of teeth taken retains its existing count, giving the defined demand
for measuring purposes are determined to provide a signal at the output of the digital-to-analogue converter
compromise between accuracy of measurement (the (DAC). If the operator demands a higher terminal
more teeth the better) and adequate transient response, speed, the appropriate comparator activates its asso-
particularly of the derived acceleration signal (the more ciated oscillator to increase the count until the DAC
measurements per second the better). The accuracy with output reaches the terminal speed selected by the op-
which the teeth are cut on the wheel and the combina- erator. The effect is that the DAC output is ramped-up
tion of speed detector and trigger circuitry for register- until it reaches the terminal speed, the rate of increase
ing the passage of teeth are also considered carefully being proportional to the oscillator frequency, set by
in the design. the run-up rate control which is also on the operator's
Some of the latest governors employ a pulse timing desk. Although typically there is a choice of five run-
technique for speed sensing with auto-ranging to deter- up rates, the 'lower' oscillator is normally fixed to
mine the optimum number of teeth which are to be give a single fast rate-of-speed decrease.
timed. This gives an adequate range of the speed signal The demanded speed is compared with the measured
over the whole operating regime of the turbine from speed in the speed error amplifier, the gain of which
approximately barring speed to the overspeed range. is set such that a 10% change in valve position is
For turbines where there is a narrow range detector, achieved for about 1% change in turbine speed error.
a separate wide range speed-sensing circuit must be This implies a lower loop gain than the normal 4%
provided. Typically, this comprises a diode pump cir- droop of the narrow range governor, giving a large
cuit, giving a linear conversion of frequency to voltage stability margin. The speed error amplifier acts through
over a required range from barring speed up to the either the stop or governing valve controllers to give
maximum synchronous speed. Wide range governing precise control of the actual turbine speed to that
systems may operate to control the run-up by means selected by the operator. Since the turbine-generator
of either the governing valves or the HP stop valves. remains unsynchronised during run-up, the loading
Run-up on the governor valves has the advantage is light and with near normal steam pressures only a
that the HP steam chest can be 'warmed through' small proportion of the full valve opening is necessary
prior to steam admission to the turbine, but this to achieve run-up to speed. Often a steam demand
arrangement requires very sensitive control at small limit is applied during run-up and if this limit is
valve openings in order to provide a smooth increase exceeded the operator is alerted to a possible fault.
in speed. Control of the HP stop valves permits the Two types of speed-sensing device are in common
use of a built-in pilot valve for steam control of use, both employing non-contact sensing of the rota-
the run-up phase. Since this has a lower-gain valve tion of a toothed wheel directly keyed to the main
position/steam flow characteristic, the required sensi- turbine shaft. For safety reasons, the toothed wheel is
tivity of the valve position controller is less critical. mounted at the HP end of the machine so that in the
The typical facilities required by the operator are: unlikely event of a shaft or coupling failure, the sudden
loss of load torque would be sensed by the overspeed-
The ability to preset the terminal speed. ing of the HP end of the machine and the governor
would act to close all the turbine steam valves.
A 'hold' button so that the speed can be held at the
The first type of speed-sensing device is the mag-
current value.
netic pick-up shown in Fig 2.15. The sensing coil is
A 'release' button to allow the run-up to continue. wound round the pole-piece which directs the magnetic
field from the permanent magnet towards the toothed
The ability to preselect speed ramp rates to any one wheel. A voltage is generated whenever the magnetic
of several values (usually five). field is disturbed.
138
Governing systems

RUN-UP
RATE
SELECTOR
'RAISE'
OSCILLATOR
SIGNAL
COMPARATOR
CI
DEMANDED
SPEED
TERMINAL 0-10V RUN-UP 8-BIT DIGITAL 0-10V DC
SPEED HOLD REVERSIBLE TO ANALOGUE
DC
SETTING RUN-DOWN COUNTER CONVERTER

SIGNAL
'LOWER'
COMPARATOR
OSCILLATOR
C2

FIG. 2.14 Digital speed setpoint block diagram

If a tooth on the wheel is opposite the pole piece, the ever, a spare probe is often fitted, which can be sub-
magnetic field is concentrated by the tooth. In the stituted for a faulty probe by manual connection whilst
absence of a tooth, the field is less concentrated. The on-line.
passage of teeth on the wheel past the pole piece causes The second type of speed-sensing device is the proxi-
the flux linking the coil to vary and generate a voltage, mity transducer which consists of a probe connected to
which is of near-sinusoidal waveform at normal running an oscillator-demodulator unit by an interconnecting
speeds. However, at low speeds the waveform will be extension cable. The advantage of this system is that it
more distorted and below some well-defined threshold can sense the passage of teeth down to zero speed, which
the probe output will be inadequate. This is acceptable may be important in applications requiring a low barring
for governing purposes since speed integrity checks are speed. The equipment is more complex though and relies
built in from an early stage in the run-up. Probe output on the use of specially trimmed interconnecting cables
voltage amplitude depends on the gap setting, which between the two units. The principle of operation is that
should be checked against the turbine maker's recom- a radio frequency signal is generated by the oscillator
mendations during overhauls. In general, a triplicated and radiated in the region of the probe tip. As this
analogue governing system requires three probes; how- electromagnetic field is intercepted by the toothed wheel,
eddy currents are generated in the material and depen-
ding on whether or not a tooth is present, a varying
energy loss occurs in the strength of the return signal
which is sensed by the demodulator.
A characteristic feature of most electronic governors
is that they exercise individual control over each steam
control valve in the turbine in response to an overall
steam demand signal. This permits on-load testing of
individual valves and also fault monitoring with the
capability to close a valve in the event of a failure.
Particular mention is made here of the characteristics
of the valve position loop and its significance in achiev-
ing the desired control of turbine load.
Given constant steam inlet conditions, the power
output of a turbine is a linear function of steam flow
passing through the no-load point at a small percentage
of maximum steam flow. This characteristic is known
as the Willans line and is shown in Fig 2.16 (a). In the
conventional condensing turbine used for driving a power
generator, the pressure drop across the turbine is also
directly proportional to the steam flow through it.
The desired characteristic is therefore that the steam
demand input to the valve position controller should have
a linear relationship with steam flow. However, inherent
FIG. 2.15 Magnetic pick-up speed sensing device features of valve design are non-linear so that a valve
139
Turbine plant systems Chapter 2

linearising function has to be introduced into the gov-


ernor to restore the required linearity. In particular, the
valve area/steam flow relationship is non-linear for val-
ues of pressure ratio (across the valve) less than the
critical value. Refer to Kearton, page 628 [2] and the
typical characteristic is shown in Fig 2.16 (b). Depend-
ing on the valve shape, there will also be a non-linear
STEAM FLOW relationship between valve lift and valve area, giving
the characteristic shown in Fig 2.16(c). To linearise
these two effects, the steam demand is shaped by
linearising circuits to give a characteristic of the form
(a)
shown in Fig 2.16 (d). Additional versine effects arising
from the lever arrangement driving the valve position
pick-off may also be included in the compensation.
LOAD 10 0/
Each individual valve controller has three-channel
PRESSURE RATIO P2/Pi valve steam demand signals as input. Its function is
100%
to take a majority vote of these signals to form a sig-
nal demand, to provide linearisation and to provide
position control of the turbine steam valve, using the
signal derived from a valve position transducer as feed-
VALVE AREA' back. Additionally, monitoring of majority voter opera-
tion and of servo-valve or position transducer faults is
carried out, with the capability of automatic shutdown
in the event of loss of accurate valve position control.
(b)

1.4.1 Digital processing


Two types of digital processing are employed on the latest
100%
STEAM FLOW
governing systems for CEGB machines. Both provide
highly accurate measurement of turbine speed and have
precise functions, such as steam valve linearisation
characteristics, resident in the software for accuracy and
ease of setting-up.
One type uses the triplex, modular redundant
VALVE AREA 4
configuration very similar to that previously shown in
Fig 2.13. Each single channel uses a combined processor
and memory module which is an independent speed-
(c) computing element in its own right. The module also
includes all the built-in features to permit its use in the
triplex system. Parallel bus-links are used for the
communication with peripherals, whilst secure serial links
provide interchannel communication for channel
harmonisation and fault detection purposes.
As with an analogue governor, '2 out of 3' majority
voting is carried out at key points in the system. Control
variables are entered by means of setpoints which can
be ramped up or down by the user. High priority
STEAM DEMAND
setpoints such as the speed and load setpoints are avail-
able to the operator by direct access to the processor.
Lower priority setpoints, which alter the control char-
acteristics (e.g., droop variation), are accessed via a serial
(d)
communications link to the interface processor. Control
modifiers, such as vacuum unloading, are sent to the
channels from the interface processor via serial links.
The system timing, the synchronisation between channels
and the fault monitoring process are chosen to suit the
needs for adequate transient response and to allow for
abnormal operation, such as operation with a faulty
FIG. 2.16 Typical steam flow/load/valve characteristics channel and the subsequent channel reinstatement.
140
Governing systems

As with the analogue governor, individual valve the BLG, are processed by the UCL. Output commands
amplifiers accept the three triplex speed channel outputs from the UCL to alter the speed, load or operating
in analogue form and process them to drive the servo- mode take effect through the BLG, but only if they
valve coils on each steam valve. meet the acceptability criteria stored at base level. This
The second type of governor employing digital form of digital governor is shown diagrammatically
processing uses a completely different configuration. A in Fig 2.17.
separate single-channel, basic speed governor is pro- The BLG hardware'and software are totally standard
vided for each steam valve. At this level, termed the base for all applications whereas, at the UCL, the hardware
level governor (BLG), there is high integrity due to the is a standard minicomputer but the software incor-
multiple redundancy and built-in error checks which porates all functions and parameters special to the
initiate closure of the related steam valve in the event application. A particular feature of the design is the
of a valve channel fault. ability of the UCL to provide communications to the
At the upper control level (UCL), a single Unit Pro- operator via a multi-character display panel. This permits
cessor provides all the other functions required in a the interactive prompting of the operator for every mode
governing system. All interfaces to the operator and of operation and enables him to see the response to
plant, except the basic signals connected directly to his actions. Additionally, precise details are given of

FIG. 2.17 Microgovernor block diagram

141
Turbine plant systems Chapter 2

any governor fault alarm which might occur. The op- spool is shown in the central position with the control
erator may also select particular forms of display, for ports blanked-off. This is referred to as the 'null posi-
example, to facilitate turbine run-up. tion'. When the spool moves, one control port is opened
The BLG channel includes all the hardware and to the supply port and the other opens to the drain port.
signal routes from the speed probe signal-bus to the The flow rate is proportional to the spool deflection.
electrohydraulic servo-valve of its associated steam When connected as a position controller, as shown
valve relay. As well as validating data inputs from the diagrammatically, the null position of the spool
UCL, the BLG incorporates extensive self-checking corresponds to the condition of equal 'demanded' and
facilities. In the event of a fault, the steam valve is 'actual' positions. Any discrepancy with the position
closed by an independent means through its own measured by the LVDT causes a current to flow, resulting
failsafe watchdog hardware. in a hydraulic fluid flow to the power piston until the
required position is achieved.
To avoid stiction of the valve it is usual practice
to superimpose a 'dither' current on the servo-valve
1.5 Governor valve relays amplifier output. This is a medium frequency (1 kHz)
The output of the electronic speed governor requires low amplitude current which plays no part in the overall
conversion from a current signal to a mechanical force position control, but keeps the servo-valve spool in a
of sufficient power to actuate the steam valves. It is the 'live' condition, the effect being to vibrate it by a negli-
function of the governor relays to perform this duty. gible amplitude at the 'dither' frequency.
The hydraulic relay has no competitor as a force The null is adjusted by altering the spring bias applied
amplifier for steam valve actuation. It has the capabili- to the armature. In the event of a loss of the electrical
ty to develop the high power needed for rapid valve signal driving the servo-valve, it is essential that the valve
opening or closing, without a significant deadband or relay and hence the power piston is driven to a closed
hysteresis. position, so a 'null bias' is set to give a small offset in
The usual arrangement for electronic governing is to this direction. The control characteristic of the servo-
employ a single separate relay for each steam valve, the valve in this condition is shown in Fig 2.19 (a). Also
conversion being carried out by a proprietary plotted (in Fig 2.20) is the corresponding valve internal
electrohydraulic servo-valve. There are many different leakage which reaches a peak at the normal controlling
forms of valve relay, of which three are used on CEGB point of the valve. The servo-valve is likely to be the
turbines with electronic governing. These will be refer- most sensitive item in the hydraulic system owing to the
red to as Types 1, 2 and 3 in the descriptions which small clearances, especially in the nozzles, and the align-
follow. Types 1 and 2 use the same proprietary servo- ment of the control edges of the spool with the ports
valve which will be described first. The servo-valve used in the valve body. The hydraulic fluid must be kept in
with the Type 3 relay is included in the description of a pure condition with a low contamination level, other-
the relay. wise the control edges will become eroded and the inter-
Figure 2.18 shows a servo-valve in cross-section, nal leakage will increase substantially. If this leakage
together with a diagrammatic representation of how persists, it will result in an excessive fluid consumption
it is connected in a simple position-loop controlling and a reduction in the fluid pressure, eventually resulting
a primary ram. The feedback to the amplifier in the in the need to shut down the turbine and replace all the
governing system is provided by a linear variable worn components.
differential transformer (LVDT). The needs for the control of the fluid characteristics
The function of the servo-valve is to provide an are described in the section on the fluid pumping system.
output flow rate of hydraulic fluid proportional to the However, at this point, it should be noted that CEGB
input current. The input current, derived by the gover- standard practice is to provide a test rig in the laboratory
nor servo-amplifier is applied to the coils of a force for checking the characteristics of servo-valves removed
motor thereby deflecting the armature and drive arm from the turbine.
mounted in a flexure tube. The high pressure supply is Before going on to describe the details of the valve
filtered and supplied via orifices to the boost chambers relays following the servo-valves, it is necessary to set
and at either end of the spool. The fluid from each out the requirements of the final drive to the steam valve.
boost chamber is cross-connected via porting to the re- In the event of a failure of the hydraulic system, the
verse ends of the servo-spool. It travels down the centre steam valve must be capable of closing in less than 200
of the spool and returns to low pressure via the drain ms against any force acting to open the valve. The flow
port. The deflection of the drive arm will block one or of steam through the valve usually generates an opening
other of the nozzles and create a high pressure in one force over some part of the travel. Figure 2.21 shows
boost chamber and a low pressure in the other, thus a typical case where the steam force acts to open the
creating a force to move the servo-spool until the pres- valve over the last 70% of the valve lift. A substantial
sures are equalised. The spool deflection is thus pro- spring (or even a nest of springs) is provided to give
portional to the drive arm deflection which is itself the closing force with a large margin over the steam
proportional to the current. In the diagram, the servo- valve opening force to overcome frictional effects. The
142
Governing systems

ARMATURE

MAGNET

DEMAND POSITION
NULL VOLTAGE
ADJUSTMENT

DITHER

FLEXURE TUBE

OSCILLATOR
AND
DEMODULATOR

LINEAR VARIABLE

o
DIFFERENTIAL TRANSFORMER

FIG. 2.18 Basic servo-loop

143
Turbine plant systems Chapter 2

APPROXIMATE FLOW GAIN


LINEARITY & SYMMETRY
ENVELOPE

INPUT CURRENT

INPUT CURRENT, + mA

(a) Point-by-point data

(a) Point-by-point data

INPUT CURRENT, + mA
APPROXIMATE FLOW GAIN
LINEARITY, SYMMETRY (b) Continuous data
& HYSTERISIS ENVELOPE

FIG. 2.20 Internal leakage flow characteristics

These requirements are best met by a single-acting


power piston opened by hydraulic fluid pressure and
closed by the closing spring. Once the steam force and
spring force are known, it is a straightforward design
task to calculate the size of power piston required. Again,
a large margin is provided to allow for friction and,
(b) Continuous data where appropriate, the weight of the valve and linkage.
The valve closing rate of 200 ms for full stroke (typical
superheat unit) is set by the need to control overspeed
FIG. 2.19 No-load flow characteristics in the event of a load rejection. The capability of opening
at the same rate is designed into the valve, as it is needed
in some applications to improve the transient stability
of power system networks. However, this facility is
figure shows a typical spring force characteristic and not provided on turbines supplied to the CEGB and the
the net force closing the valve. Frictional forces are opening of the steam valve is rate-limited to give a time
kept to a minimum by designing the valve so that side for full stroke of about 5 s. To achieve fast opening and
loads on the valve spindles are minimised. To open the closing, the servo stages which feed the power piston
valve, it is necessary for the valve relay to supply a must be designed with the appropriate size of porting
force sufficient to overcome the spring force and any to provide the required flow into and out of the power
steam closing force, such as that occurring over the piston. As well as the porting, there must be pipework
first 30% of movement shown in Fig 2.21. of adequate size to supply the fluid flow from the high
144
Governing systems

1.5.1 Governor valve relay and control unit Type 1


Having covered the requirements, the Type 1 system will
be examined in detail. This is used on large reheat
turbine-generators having four steam inlets to both HP
and IP cylinders, each inlet being fitted with series-
connected emergency stop and governor valves. Since
all control for both the run-up and loading phases is
carried out by the governor valves, the stop valves must
be fully open whenever the turbine is needed for opera-
tion. The simple form of open/closed control required
for the stop valves will be described separately.
Figure 2.22 shows a diagram of the governor valve
relay and control unit. The input stage, comprising the
servo-valve and actuator piston controlled by the
electronic system, is identical to Fig 2.18. The heart of
the unit is the relay plunger, rigidly connected to the
actuator piston and sliding in the relay plunger sleeve.
In the normal position of the sleeve, as shown in the
diagram, the relay plunger is moved upwards by the
actuator piston when the steam valve is required to open.
This admits power fluid above the relay power piston
to move it downwards against the force of the valve
spring (not shown), and hence open the valve until such
time as the sweep-resolver position signal is in balance
with the valve position demand. This returns the servo-
amplifier output to zero with the actuator piston and
its transducer restored to the null position. Closing is
effected in a similar manner, with the relay plunger being
FIG. 2.21 Typical governor valve forces moved downwards to allow fluid to be drained out of
the upper power piston chamber.
Tripping is accomplished by the relay plunger sleeve
which, in the running condition, is held downwards (in
pressure source to the power piston to meet opening the position shown) against its internal spring by the
demands, and from the power piston to the drain presence of high pressure tripping fluid in chamber F.
line to meet closing demands. To assist in this, parti- If a trip occurs, tripping fluid pressure is lost and the
cularly where fast opening is required, hydraulic ac- relay plunger sleeve moves upwards due to the spring
cumulators are often provided adjacent to each steam force. For any position of the actuator piston, this will
valve relay. cause the power piston to be drained.
A secondary means of closing the valve relays of Figure 2.23 shows a diagram of the emergency stop
a main turbine unit from the unit protection system valve relay unit. Examining the operation of the relay
must also be provided. This will be described in detail plunger only; in the tripped condition, this is held on
in a later section, but from the valve relay point of view, its bottom stop so that power fluid entering chamber
each relay is supplied with power oil at high pressure B through port A is prevented from gaining access to
for normal functions. It is also separately supplied with port F. When high pressure tripping fluid is applied
tripping fluid at high pressure, which is routed through through port C to chamber D, the relay plunger will lift,
the protection system. In the event of protection system thereby allowing high pressure power fluid through port
operation, this supply is cut off to all valve relays F to lift the relay power piston.
and independently ensures their closure. Even so, the The dump piston acts as a parallel means of ensuring
valve relays all employ sliding pistons of relatively small that the valve is closed if tripping pressure is lost. In
clearance, and a postulated failure mode exists in that the normal running condition it will be held against its
it is remotely possible for a failure process in the top seat by high pressure tripping fluid in chamber E,
hydraulic fluid supply unit to generate widespread fluid thus sealing the power piston fluid from port H apart
contamination, thus causing sticking of a number of the from a small warming flow.
steam valve relay spools. To provide a back-up for this The orifice arrangement permits warming flows to the
eventuality, emergency stop valve relays (and sometimes lower end of the dump piston. In the event of a loss
governor valve relays as well) are provided with a dump of tripping pressure, the dump piston will unseat and
valve having generous clearances and operated by the allow fluid to be drained rapidly from the power piston
tripping system so that safety is assured. into chamber H.
145
Turbine plant systems Chapter 2

SIGNAL FROM ELECTRONIC GOVERNOR


I
I

r "^O AMPLIFIEJ>- -*"0


I ^ S W E E P RESOLVER \yS^^ 4 .

ISOLATING &
RELAY SHOWN IN VALVE OPENING POSITION FLUSHING
BLOCK

DRAIN TRIPPING POWER ACCUMULATOR


] TRIPPING FLUID FLUID IN FLUID IN TEST

POWER FLUID

DRAIN FLUID

ELECTRICAL CONNECTIONS

FlG. 2.22 Governor valve relay and control unit (Type 1)

146
Governing systems

mmmmzm DRAIN FLUID

FIG. 2.23 HP emergency stop valve relay and control unit (Type 1)

The dump piston has clearances one order higher than Figure 2.24 shows the control arrangements for a
the relay plunger and other servo components. The governing valve. Again, the input stage, comprising a
probability of its seizure in the event of widespread fluid servo-valve and primary ram, is positioned by a servo-
contamination is therefore remote. valve amplifier using the LVDT connected to the primary
The orifices fitted to the systems of both the gover- ram as feedback. In this case, however, the positioning
nor and stop valves ensure appropriate rates of valve of the main ram is accomplished by mechanical and
travel in normal operation and prevent excessive rates hydraulic means without a further electronic feedback
of valve travel when on-load testing. loop. The primary ram provides the input onto a
The arrangements of trip and test valves shown permit feedback linkage, the other end being connected to
on-load testing of the valves in all their functioning measure main ram position. A pilot valve is connected
modes. to the linkage so that, with the spool aligned with its
ports, the main ram will be in equilibrium with the
primary ram. A dump valve is interposed in the outlet
1.5.2 Governor valve relay and control unit Type 2 port of the pilot valve supplying the main ram. In the
Type 2 control units are fitted to similar machines to normal operating condition, if the primary ram lifts, it
Type 1, but in this case run-up is carried out on the HP will lift the pilot valve, allowing fluid to flow at high
stop valves, with the governor valves partially open. The pressure to open the main ram. This will move
control units for HP stop and HP and IP governor valves downwards to open until the main ram position
are therefore similar. The IP stop valves require simple corresponds to the primary ram input and the pilot valve
open/closed control only. is restored to the null condition.

147
Turbine plant systems Chapter 2

VALVE SPINDLE FORK END

LINEAR VARIABLE DIFFERENTIAL TRANSFORMERS

PILOT ARM

DUMP VALVE

ISOLATING VALVE

CONTROL VALVES MANIFOLD BLOCK

FIG. 2.24 Governor valve relay and control unit (Type 2)

148
Governing systems

When protection fluid is present, the dump valve is are of a spring-loaded type, set to open at a defined
held down against its seat against the opening spring. pressure.
If the protection fluid pressure is lost, the dump valve In addition, on some machines, there is a need to
is unseated by its spring and releases the fluid supply supply relatively small release valves to release steam in
to the main ram to drain, thereby closing the valve rapid- the reheater system to atmosphere when the governor
ly. The dump valve lower seat is also closed by the spring valves and interceptor valves close suddenly in an emer-
force, thus cutting off the high pressure supply from the gency. Although the steam may not be at a sufficiently
accumulator adjacent to the valve relay. The dump valve high pressure to cause the relief valves to open, any
may also be operated by an electrical signal to the residual steam trapped in the HP cylinder and reheater
solenoid valve in the protection fluid line, thereby could give rise to overheating of HP blading due to
providing a back-up means of tripping individual valves. churning in the relatively high density steam. The release
Energising the solenoid valve maintains the tripping valves, located in the connecting steam piping between
pressure to the remainder of the valves, but locally the reheater and the interceptor valves, are signalled to
releases the high pressure fluid above the dump valve open under the appropriate conditions to prevent this
to drain, causing the valve to trip. from happening.
The release valves may be hydraulically or pneu-
matically operated. Where an electronic governor is
1.5.3 Governor valve relay and control unit Type 3 fitted, they are opened by energising a solenoid. Condi-
Type 3 relays are similar to Type 2 but employ a different tions which signal their opening are:
form of primary ram and servo-valve, known as a
'positioner'. The primary ram displacement is directly Loss of tripping pressure.
proportional to the input current to the servo-valve. The
servo-valve employs a similar principle and configura- High acceleration detected by governor.
tion to that described in Fig 2.18, but feedback of ram Closure of all interceptor steam valve relays.
position is introduced magnetically onto the force motor
and subtracts from the armature deflection produced by
the current coils. The primary ram is used to drive the These conditions cover circumstances of machine tripp-
main ram via a feedback linkage and pilot valve as in ing or turbine load rejection without tripping, where
the Type 2 relay, but there is also feedback of main ram churning could occur either during rundown of the
position to the servo-valve amplifier by means of an machine after a trip or during the period of interceptor
LVDT. This ensures accurate fine control over the full valve closure on load rejection.
range of valve openings.
The Type 3 relay is now superseding the Type 2 relay
on new plant and some retrofit applications, with the
advantage that it has reduced dependency on the LVDT 1.6 Hydraulic fluid system
signal, being able to operate without it. Additionally, Universal use is made on large turbine-generators of
the servo-valve has generally larger clearances than the hydraulic fluid at high pressure to provide the large
Type 2 and is less susceptible to the effects of wear and opening forces and rapid stroking times. This section
contamination. deals with the design of the pumping system for supply-
Types 1 and 2 relays have seen many thousands of ing fluid at high pressure to the steam valve relays and
hours service on large turbine-generators and have been to the protection system.
developed to provide a high degree of reliability and The design and construction of the system is close-
freedom from problems. Nevertheless it is essential that ly related to the choice of operating fluid and to the
all types of valve relay, and indeed all hydraulic use of small-clearance components in the valve relay
components, are treated with care and that maintenance operating systems. System pressure is chosen to allow
is carried out in a clean environment by experienced the use of an economically-sized relay capable of meet-
personnel. If plant is shut down or awaiting commis- ing the required opening forces. For small turbines
sioning for more than three months, then fluid should (<500 MW), system pressures may be 35 bar or less.
be circulated round the system periodically to maintain For larger turbines, system pressures of 70-150 bar are
a protective coating on components and prevent corro- needed.
sion problems. Components kept in store must also be These high pressures represent a significant fire risk,
kept free from dirt and corrosion. The manufacturer will as a small leakage can result in a jet of oil being sprayed
be able to provide further information to cover specific over a considerable distance. The proximity of steam
cases. pipes at high temperatures (typically 565C on coal-fired
plant) makes it necessary either to provide for double
enclosure of the pipework and components or to use
1.5.4 Reheater relief valves a fire-resistant fluid (FRF). All CEGB systems falling
Reheater relief valves are supplied on all machines into the latter category use phosphate ester fire-resistant
to prevent over pressurisation of the reheater. These fluids. These systems are completely separate from
149
Turbine plant systems Chapter 2

lubricating oil systems and one pumping unit is sup- components are necessary to ensure that the fluid is
plied for each main turbine-generator unit. Where a supplied to the relays in good condition. These will be
boiler feed pump turbine is associated with the main described as the needs of the basic components are
unit, its control and protection systems are powered by considered.
the same supply unit for convenience. Screw-type pumps may be of the submersible kind,
Phosphate-ester fluids are used because of their mounted on the reservoir top plate, or they may be
superior thermal stability compared with water-based separately mounted. Axial-piston pumps and screw-type
fire-resistant fluids which would be unsuitable for the pumps require that the pump suction pressure is adequate
high temperatures normally found in the vicinity of steam to provide a lengthy service life. Failure to meet the
valves. They also have the advantage that their viscosity suction pressure requirements will result in cavitation-
and lubricating characteristics are similar to lubricating erosion of the pump components and eventual break-up
oil, so that conversion of earlier units running on high of the pump, with the release of numerous metallic
pressure oil is possible with some care, subject to the particles. This would necessitate shutdown of the whole
fitting of compatible sealing materials. These fluids also turbine-generator to replace the faulty pump and to flush
have the necessary fire resistance and provide for a long the entire hydraulic system.
service life from the system components. They can be The phenomenon of cavitation results from the char-
maintained in good condition for an indefinite period acteristics of air in the fluid. The solubility of air is
without the need for replacement. proportional to the fluid pressure, so that air bubbles
The fluid system is designed to permit either on-line present in the fluid at low pressure become dissolved into
monitoring or manual sampling of the fluid condition. the fluid at high pressure. Consider a reservoir open to
The parameters to be monitored, their limiting values atmosphere and full of fluid connected by a pipe to a
and the frequency of monitoring depend on the perfor- pump, so that the pump suction is flooded under static
mance requirements of the most critical items in the conditions (Fig 2.25). When the pump is started, the flow
system (usually the servo-valves). This monitoring through the pipe causes a friction loss and the pump
programme is set out by the turbine supplier to suit the suction pressure may well become sub-atmospheric. This
system components. Deviations outside limits should be will cause air, normally dissolved in the fluid at
investigated promptly, otherwise component life will be atmospheric pressure, to come out of solution in the
very seriously affected. suction pipe and form bubbles. At some point within
In basic form, the fluid supply system comprises a the pump, the pressure increases to the extent that the
fluid reservoir and a pump to deliver high pressure air returns into solution with an abruptness which causes
fluid. To ensure high availability two pumping lines collapse of the bubble and damage to any metal in the
are needed, one being the duty line and the other on vicinity. Although such cavitation is usually avoided by
standby. Pumps are either of the screw-type (for use in good design, the user must be aware that blockage of
systems up to 80 bar) or of the axial piston variable- any suction filters could lead to a similar effect. Also,
delivery type (for use up to 150 bar). Additional system the reservoir is provided to give a definite fluid dwell

BREATHER

^RESERVOIR

NORMAL FLUID LEVEL

TO SYSTEM

SUCTION FILTER PUMP SUCTION PUMP DISCHARGE


PORT PORT

FIG. 2.25 Pump suction arrangement for a separately-mounted pump

150
Governing systems

time to allow any entrained air to be released. Should variable-delivery capability makes the use of a spill-type
the fluid be allowed to deteriorate for any reason or pressure control valve unnecessary. A cross-section of
should there be a fault causing excess air to be entrained a variable-swashplate pump is shown in Fig 2.28. It will
in the fluid returned to the reservoir, the air release be immediately apparent that this is a much more
process may be affected and excess air could be supplied complex device than the screw-pump shown in Fig 2.25.
to the pump in this way. However, since the flow can be made to exactly match
In the case of the submersible screw-pump, a coarse the system requirements, the reservoir, pipework, coolers
suction filter only is fitted and there is very little scope and system filters can be scaled down accordingly. From
for creation of low pressure conditions at the pump Fig 2.28 it can be seen that the axial-pistons are forced
suction. For the separately-mounted pump, it is normal to reciprocate in their cylinders by rotation of the pump
to provide a separate boost pump of the centrifugal type, barrel at constant speed and the movement of the slippers
having an outlet pressure of about 7 bar. This type of against the fixed angle of the swashplate. The piston
pump is not susceptible to cavitation damage and has displacement and hence the pump output can be varied
the additional advantage of being able to circulate viscous by tilting the swashplate. Fixed inlet and outlet ports
fluid on initial start-up from cold. However, the pump supply and deliver the hydraulic fluid. The fluid is
must be provided with relief valve facilities and LP filters pumped against the system resistance and a pressure
are needed, following the boost pump, to protect the controller senses the outlet pressure and modulates the
main pump from possible damage by the boost pump. swashplate to regulate it to the desired value. Some
The main screw-pump shown in Fig 2.26 is a constant pressure oscillation is produced at a frequency equal to
flow device when driven at constant speed. In these rotation frequency times number of pistons, but this is
systems it is designed to deliver the maximum flow damped out by a local accumulator.
requirements of the system, plus a margin. Under normal
conditions, the system flow will be a fraction of this,
so the outlet pressure is controlled by a spring-loaded 1.6.1 Filtration
pressure control valve and the excess flow is returned Filtration is an essential part of any fluid supply system
to the reservoir. Again, a separate pressure relief valve and the standards required are set by the smallest
must be provided as an overall protection. A non-return clearances in the system usually the servo-valve. The
valve is fitted in the outlet flow of the pump line, so purpose of the filters is to remove debris from the system.
that two pumping lines can be coupled together. It is quite normal for debris to be continuously generated
Although only one line is needed for operation, the within the system, some from wear processes by the
standby line can be brought into operation either man- pumps and other moving components, some introduced
ually or automatically by sensing loss of pressure in externally via air entering through the reservoir breather
the duty line. or in the valve relays. Debris will be in the form of small
Pumping generates heat, and circulation of the fluid particles suspended in the fluid and will be irregular in
through the valve relays adjacent to hot steam pipes size, shape and chemical composition. Filters are usual-
causes a further rise in fluid temperature. Phosphate- ly given 'nominal' and 'absolute' ratings, suggesting that
ester fluids have a high temperature gradient of visco- no particles larger than the absolute rating are passed.
sity. At 40C, the fluid has optimum conditions for the In fact this is not the case. Because of lack of uniformi-
main pump. At higher temperatures, the viscosity will ty in the size of passages in filters, a whole spectrum
have a lower value and excessive pump and system of particles will be passed, although the general
leakages may occur. At still higher temperatures the characteristics ensure that there is an increasing probabili-
fluid begins to break down. Conversely, at low tem- ty that the larger the particle, the more likely it is to
peratures, the fluid starts out as extremely viscous be 'captured' by the filter.
and difficult to pump, system pressure drops may be If a sample of fluid from the filter outlet is ex-
excessive and it may not be possible to achieve the amined, its contamination level is described by the
required rate of response from the steam valve relays. number of particles greater than a given size encountered
For these reasons, coolers are necessary in all systems in 100 ml of fluid. With a 5 micron absolute filter in
and, in some systems where cold-starting is essential, circuit, typical sizes of interest would be 1 micron, 5
heaters may also be required. Coolers are of the cross- microns, 10 microns, 15 microns, 25 microns and 100
flow, double-pass shell and tube type, using demin- microns. The total number of particles greater than each
er alised water as the cooling medium. Temperature of these sizes would be recorded and if plotted on a
control to 40C is achieved by an electrical controller log/(log)2 plot (as shown in Fig 2.29), would give a
and pneumatic actuator. Heaters are of the electrical nearly linear form. Using these techniques, various con-
immersion type, fitted either in the reservoir or in a tamination classes can be defined. A number of standards
flow-line. A schematic diagram of a typical pumping are in existence; the one gaining some international
system is shown in Fig 2.27. recognition is the American NAS 1638 Standard, based
Systems employing axial-piston variable-swashplate on measurements taken with an electronic particle de-
pumps have similar arrangements for boost pumps, tector, using a light-blocking principle. Another standard
LP filters, coolers and pressure relief valves, but their in widespread use in the UK is one published by a
151
Turbine plant systems Chapter 2

SCREW PUMP AND MOTOR ASSEMBLY

AUXILIARY SCREWS

INSERT

MECHANICAL
SEAL ASSEMBLY

SEAL RING

COVER

ADJUSTING
SCREW SPRING
COLLAR VALVE
CONE
MAIN
SCREW

FlG. 2.26 Typical screw pump

152
Governing systems

izl IE
-V\r h
FROM MAIN & BFP TURBINES
TRIPPING SYSTEMS & RELAYS

Hxh

i-M-

-
F R F PRE-HEAT PUMP

FlG. 2.27 Fire-resistant fluid pumping system

commercial organisation, Thermal Control Company Ltd Differential pressure drops across such filters are normal-
of Brighton, England. This standard is based on extrac- ly alarmed and provision is made for on-line filter
ting a 100 ml sample of fluid from the system, passing replacement. Prompt maintenance in these circumstances
it through a filter membrane, and then comparing the enables the fluid cleanliness to be maintained and helps
sample under a microscope with a series of reference to ensure trouble-free service from the system
slides representing different classes. components.
Because of the different measurement techniques and As well as particulate contamination, which is readily
ways of defining the 'size' of an irregularly-shaped parti- visible albeit under a microscope, contamination by
cle, the standards lay down different acceptability criteria water or chemical means is also possible. The former
(in terms of numbers of particles) for systems incor- is likely to cause an increase in fluid acidity and possible
porating fine clearance servo-valves. The system user is formation of gels or salts, which cause components to
advised to opt for one of the available techniques and stick. Chemical contamination can result in severe
use it on a regular basis. Results taken from a normal electrokinetic erosion of fine clearances, especially if a
system then provide a reference point for what is abnor- source of free chlorine ions is introduced to the system.
mal, which therefore requires investigation. For further information on these effects refer to Nelson
In a system incorporating components with clearances and Waterman [3].
of 2 microns it would be normal practice to fit 0.5 The likely effects on turbine-generator operation,
micron nominal filters in the system to give typically if contamination is allowed to persist, would be high
NAS Class 7 or Thermal Controls Class 3 conditions. leakage flows through the hydraulic system even-

153
Turbine plant systems Chapter 2

100 000

FRONT

0 5 10 15 25 50 100

FIG. 2.28 Variable swashplate pump PARTICLE SIZE urn

FIG. 2.29 Plot of particle size against total number


of particles/100 ml sample
tually giving a low system pressure and a unit trip.
Those associated with maintaining and operating such
systems should avoid any possible introduction of
water, especially seawater. Chlorinated solvents should earth filter so that possible escape of the earth due
never be used for cleaning reservoirs, pipework or to accidental rupture of this filter will not affect the
components. Nevertheless, some water will be present main system.
in the system due to contact of the fluid with air in the Fuller's earth filtration is sometimes carried out in
reservoir and in the valve relays and drain lines. To a separate sub-loop supplied from, and returning to,
maintain it at an acceptably low level (<2000 PPM), the main reservoir. Since the phosphate-ester fluid is
a vacuum dehydration unit is normally incorporated in delivered in 40 gallon drums by the oil supplier, a
the FRF pumping system. This usually works on a transfer pump is normally provided with each system
separate sub-loop, taking fluid from the reservoir and to permit the initial filling and topping-up of the main
then returning the conditioned fluid to the reservoir tank.
(Fig 2.30). The main features of the pumping unit have now
Fluid is pumped from the main reservoir into the been described. All these features are combined into a
conditioner reservoir, where it is heated to 80C and single baseplate-mounted unit which is factory assembl-
then passed through a coalescer unit into a vacuum ed and shipped to site as a complete package. Pipework
chamber where the water is drawn off. The processed joints are kept to a minimum and are welded wherever
fluid is then often passed through a fuller's earth possible. All pipework is fabricated in stainless steel
filter which further reduces the water content and also to avoid long-term problems of corrosion and the
reduces its acidity. A trap filter normally follows the generation of rust particles. A typical packaged unit
154
Governing systems

FULLERS EARTH
FILTER

VACUUM RECEIVER AUTOMATIC


C O O L I N G WATER AIR VENT
OUTLET

VACUUM
RECEIVER

FLUID HEATER

TRAP
FILTER

FILTER UNIT

C O N T R O L PANEL

CLEAN FLUID
PUMP

DIRTY FLUID
PUMP DIRTY
FLUID

VACUUM
PUMP

FIG. 2.30 Fire-resistant fluid conditioner

155
Turbine plant systems Chapter 2

is shown in Fig 2.31. The system also includes local rangements for achieving feed flow control are outside
instrumentation and facilities for the connection of the scope of this chapter, but the part played by the
remote instruments and the motor starter unit. Interlocks boiler feed pump turbine (BFPT) is to drive the pump
are built into the system to shut down a pumping line at a speed such as to maintain a constant pressure
in the event of low pump suction or outlet temperature, drop across the feed regulating valves which follow the
and alarms of abnormal conditions are given. pump. The feed flow may then be controlled by setting
the feed valve position. This requires a variable-speed
turbine whose speed or steam valve position demand may
be set by the feed control system.
The normal exhaust route for the BFPT is to the
1.7 Boiler feed pump turbine governors IP/LP crossover pipe of the main turbine, although at
On CEGB 660 MW turbine-generator systems, it is low loads it will be routed through to the condenser,
normal practice to use an auxiliary back-pressure turbine automatic changeover from one exhaust to the other
to drive the main feed pump. The feed pump is required being sensed by a load-dependent parameter of the main
to maintain the boiler drum level during steam raising turbine usually crossover pressure.
prior to start-up of the main turbine, and also over the The steam supply to the BFPT may be derived from
full load range of the main turbine. The precise ar- one or other of two sources, or from a mixture of

FLUID C O N D I T I O N E R-

TANK BREATHER

ACCUMULATOR

FLUID SUPPLY
a TO MAIN SET
b TO B.F.P.T
5-WAY CONTROL VALVE
(EMPTYING CONNECTION)

FLUID OUTLET MANIFOLD

MAIN PUMP UNIT

FIG. 2.31 Fire-resistant fluid packaged unit

156
Steam chests, valves and loop pipes

the two. Normally, when the main turbine is on-load,


the second-stage blading of the BFPT is supplied with
steam from the main turbine HP exhaust via bled-steam
emergency and governing valves. Either one pair, or two ^ BLED
oo STEAM
pairs in parallel, of these valves are fitted. Because of o
u
z 5
1 VALVES

non-availability of steam from the main turbine HP zS


U JH
DL-CO LIVE 1 X
exhaust prior to start-up and when the main turbine is STEAM 1

operating at low loads, the first-stage blading of the ^ VALVE 1

BFPT may be supplied with boiler steam through a single


2 Q
pair of live steam emergency and governing valves. In 5S
the event of non-availability of the bled-steam supply o 5
z oc ^^V^J ^
at full-load on the main turbine, the live steam valves -10 -8
1 1 1 -2 0
-6 -4
will supply sufficient steam to enable full-load to be NOMINAL SPEED LOOP ERROR, %

maintained. 1 1 1 1 1
1C0 80 60 40 20 0
The nominal maximum power rating of such a boiler NET VALVE DEMAND FROM EITHER LOOP, %
feed pump turbine is about 15 MW and the possibility
of a load rejection leading to a potential over speed (a) Live/bled steam valve sequencing
must be considered. The loss of load could occur as a
result of loss of feed pump suction. If this occurred with
the turbine speed and power output close to the full-
load value, an extremely rapid acceleration would result
due to the low rotor inertia. In the unlikely event that
the turbine did overspeed to destruction, the strength ; 100-1
of the casing would contain the disaster and protect
personnel. However, it is normal practice to follow
main turbine practice and fit the BFPT with a three-
IS
channel electronic governor, coupled with separate over-
speed protection.
The turbine governor is a modular arrangement using
many of the same elements applied to the main turbine.
Thus, speed-sensing and on-load testing facilities will 1^ ~~"
60 80 100
be similar in principle. The emergency valves upstream 20
NOMINAL BLED STEAM PRESSURE
of the governing valves provide protection shutdowns AS PERCENTAGE OF MAXIMUM RATED
of the BFPT in the event of failure of more than one
governor channel or in the event of a mechanical trip (b) Bled steam pressure limit sequencing
condition (e.g., loss of lubricating oil) being sensed.
The valve relay systems use similar servo-valves to FIG. 2.32 Valve and pressure sequencing diagrams
those fitted to the main turbine and the following stages for the BFPT
of hydraulic operation are often similar in principle to
those of the main turbine. It has sometimes been possi-
ble to omit the pilot stage associated with the main
until the HP exhaust pressure has risen to the value
turbine valve relays and to drive the power piston direct
at which it can sustain the feed flow demand via the
with the servo-valve. Referring back to Fig 2.24, this
BFPT.
would be equivalent to considering the relay to comprise
These features and others, engineered by techniques
only the servo-valve and primary ram. In all cases, the
similar to those of the main turbine governor, enable
hydraulic fluid is supplied from the main turbine system.
convenient interfaces to be provided for automatic feed
Live and bled-steam governing valves are controlled control systems and automatic run-up.
in parallel, with an offset being applied to the live steam
valves so that they only begin to open when the bled-
steam valves are fully open on a speed loop droop of
about 5%. Any additional speed error, requiring further
steam supply, progressively opens the live steam valves 2 Steam chests, valves and loop pipes
until they are also fully open.
During start-up of the main turbine, the steam is
supplied via the live steam valve. A common means of
ensuring this automatically is to superimpose on the 2.1 Steam chest arrangements and
bled-steam channel a limited maximum opening char- construction
acteristic as a function of bled-steam pressure, as shown Steam is admitted to a turbine from the superheater
in Fig 2.32. This will keep the bled-steam valves closed outlets, via the high pressure steam mains, to the

157
Turbine plant systems Chapter 2

emergency stop valves and the associated governing there would be problems of creep ratcheting.
valves which are housed in steam chests. In order The valves close onto removable-plate type seats,
to reduce the thermal stresses and hence the risk of which can be replaced when worn or damaged. These
thermal fatigue, these steam chests are of simple shapes seats are secured in place either by means of a screwed
and are manufactured either from closed-die alloy steel ring or by screws that are locked in place, and sometimes
forgings welded together, or from alloy steel castings. the seats are additionally prevented from rotating with
Similar steam chests containing emergency stop valves radial dowels. A diffuser is generally provided; this is
and interceptor valves are used in the hot reheat pipes either integral with the valve seat or machined as part
from the reheater to the intermediate pressure cylinder of the valve chest.
of the turbine. These steam chests are invariably The mating faces of the valves and their seats are faced
manufactured from alloy steel castings, which are thinner with Stellite in order to resist wear, mainly due to erosion
but larger than the HP steam chests because of the much by steam. Such wear is most likely to occur when the
lower steam pressure conditions. valve is cracked open: a jet of steam is then propelled
The steam chests are usually mounted alongside the at high velocity by the large pressure differential through
turbine: on 660 MW machines they are either on swing the narrow port opening. The Stellite facing also protects
links or on springs to accommodate movement due to against impact damage when the valves shut normally,
thermal expansion and flexibility of the HP steam mains. or during frequent high speed test closures. Cushioning
The steam chests on 500 MW machines were keyed to devices in the relay system or slow motion testing can
the foundations. In some instances, the steam chests are be used to alleviate this.
mounted in the steam mains, and thus are able to move The valve spindles are supported and guided by means
freely with the steam piping. of specially treated alloy steel sleeves in the valve covers,
On modern large machines, the usual practice is to the materials of the spindles and the sleeves being selected
have four steam mains together with four emergency stop both to avoid excessive oxide build-up between 30 000
valves and four governor valves, two on each side of h overhauls and to ensure the minimum wear of the
the turbine. On some of the early 660 MW nuclear components when subjected to the forces imposed on
turbine-generators, however, the two steam mains on the valve from steam, vibration and the operating gear.
each side join into one large steam chest, so that there The bushes are securely locked in place, the clearance
are only two steam chests in total. These steam chests, between spindle and bush being suitable for the operating
one on each side, contain one large emergency stop valve conditions of the valves. In order to prevent steam
and one governor valve each. Similar arrangements are leakage to atmosphere, there is a gland steam leak-off
used for the reheat steam chests at the IP cylinder. sub-atmospheric connection from a chamber between the
On some current 660 MW machines, the steam chest spindle and the bush to the turbine gland steam system.
arrangement is such that there is one steam chest on each Steam leakage from emergency stop valves is also
side of the machine, which has an emergency stop valve prevented by means of a stellite back seat on the back
at each end and the two governor valves are connected of the valve head against the lower valve spindle bush.
to the common chamber between the stop valves. A
typical arrangement is shown in Fig 2.33.
Another steam chest arrangement employs the reverse
flow type of governor valve (see Section 2.6 of this 2.3 Cover seals
chapter), permitting a more compact arrangement of stop On large modern HP valve chests, it is difficult to
and governor valves. This requires two steam chests each provide an adequate bolted joint between the valve
side of the machine, which have sometimes been inter- chest and its cover. Current practice on these chests
connected before the emergency stop valve. generally is to utilise pressure-assisted seal joints si-
milar to that shown in Fig 2.34. On reheat steam
chests, bolted flanged joints are used. These joints
usually have gaskets that are either of the Metaflex
2.2 Steam chest materials type backed up by a metal-to-metal joint face, or they
employ an Inconel ring. All such bolted joints are
As stated in Section 2.1 of this chapter, the chests are designed not to require retightening for at least 30 000
manufactured from alloy steel. On current 660 MW hours of operation.
machines operating at 565C, the material is usually
0.5Cr Mo V steel, and on some recent machines operating
at 538C, the chest material is 2.25Cr steel. However,
on larger units operating at 565C, it may be necessary
to utilise higher-chrome ferritic steels with improved 2.4 Steam strainers
creep resistance in order to avoid unduly thick chest walls In order to prevent solid particles of foreign matter from
which would prejudice operational flexibility. Austenitic being carried into the turbine by the incoming steam and
steels would provide a greater improvement in creep causing damage to the blading, each stop valve is
resistance but experience with these has shown that surrounded by a cylindrical strainer which has many
158
STEAM I N L E T
FROM BOILER

STEAM CHEST
SUPPORT

FOUNDATION
STEELWORK

FIG. 2.33 Typical steam chest arrangements

159
Steam chests, valves and loop pipes
Turbine plant systems Chapter 2

the specific volumes (and hence valve diameters) were


large.
COVER PLATE

2.6 Governor valves


The governor valves provide accurate control of the
steam flow rate entering the turbine, thus controlling the
generator load when the machine is synchronised to the
MAIN SEALING
PLATE
grid. The present practice for the control of the steam
flow rate during turbine run-up to speed is also to use
the governor valves; however, on earlier 660 MW
STEAM
CHEST machines and also on 500 MW units, run-up is controll-
ed by use of the emergency stop valve pilot-valves, in
conjunction with the governor valves. On 660 MW
FIG. 2.34 Pressure-assisted seal type valve cover joint machines, the interceptor valves can also be used in a
governing mode, if required, to use the stored energy
in the reheater to provide a quick response to frequency
variations.
small diameter holes, ranging from 5-2 mm depending The diameters of valve opening are generally cal-
on the manufacturer. Even particles of this size can culated to give maximum steam velocities of about 120
cause serious blading damage, it is therefore essential m/s for the valves. Valve head designs are such that
that a thorough steam blow of all pipework is carried they are not subject to steam-induced vibration during
out before a set is commissioned. The risk of damage operation.
to new plant from debris, pieces of weld metal, etc., Figure 2.36 shows a design of governor valve in which
which may be swept through the pipe, used to be the upstream steam pressure is prevented from acting on
minimised by fitting extra-fine commissioning strainers the back of the valve by a fine annular clearance. The
in place of the final strainers. However, because of the space behind the valve head is usually vented downstream
time associated with strainer removal, modern practice of the valve by means of holes drilled in the valve head.
is to rely on the final strainers to trap all debris. A similar design of governor valve is also used for
the reverse flow type of governor valve, see Fig 2.37.
As with the stop valves, it is essential that these valves
close in an emergency; they are therefore similarly on-
2.5 Stop valves load tested.
Figure 2.38 shows the Mushroom' type of governor
The purposes of the emergency stop valves are to cut
valve which has a profiled head to give a more linear
off the steam supply during periods of shutdown and
flow/lift relationship. A 'guided flow' type of valve head
to provide prompt interruption of the steam flow in an
has also been developed in order to control the flow
emergency trip.
downstream of the seat so as to minimise noise and vibra-
In order to ensure that the valves will close in an
tion, see Fig 2.39.
emergency, it is a requirement that they are tested on-
load regularly, at least once a month. During such testing
there is a load reduction, which can be minimised by
a suitable interconnection downstream of the valves. The
on-load testing is carried out in sequence so that only 2.7 Loop pipework
one valve is tested at a time. The steam chests are connected to the turbine through
Single-seated unbalanced plug type valves are normally loop pipes. On present machines these are arranged to
used, with an internal pilot valve that opens first. The be relatively short, in order to reduce the quantity of
pilot valve is small so that it may be opened against main entrained steam between the governing valves and the
steam pressure. It also provides initial fine control and turbine when the valves are shut. On earlier (500 MW)
reduces the loads required to operate the valve. Normal- machines, where the chests are firmly anchored to the
ly, once the machine has run-up to speed, the governor supporting steelwork or the concrete foundations, the
valves which have been open, close in. It is then possi- loop pipes are long and flexible in order to allow the
ble to open the main stop valves as the pressures turbine and the pipes to expand freely without undue
upstream and downstream of the valve are equalised. forces/moments on the turbine cylinder.
A typical emergency stop valve is shown in Fig 2.35. All loop pipe joints with the steam chests are welded,
On some 500 MW units and on some early 660 MW as are all other loop pipe joints, except where dis-
machines, flap valves were used for reheat emergency mantling flanges (see below) are provided. The loop
valves, where the steam pressures were moderate and pipes enter the cylinders, preferably radially, at the
160
Steam chests, valves and loop pipes

OPERATING LEVER LINK PIN

FULCRUM PIN CONNECTING ARMS

LEVER BRACKET

VALVE SPRING

VALVE COLUMN LINK PIN

SPRING PLATE
HALF COUPLING
SPHERICAL WASHERS

COVER PLATE

TOP RUSH
BUSH RETAINING
PLATE

CAP NUT
STEAM LEAK-OFF *

LAGGING SHIELD

RING N U T

GASKET STEAM C H E S T
COVER

PRESSURE TAPPING - f r

LOWER S P I N D L E BUSH

BOTTOM BUSH

WOVE SPACE

STEAM CHEST

STEAM STRAINER

* SHOWN OUT OF POSITION

FIG. 2.35 Typical emergency stop valve

161
Turbine plant systems Chapter 2

VALVE HEAD
LOCKING RING-
WROUGHT
VALVE SEAT
STELLITE BUSH

PISTON RINGS

RETAINING DOWEL

DOWEL FOR
.VALVE SEAT

- TOP BUSH

.DOWEL

^VALVE GUIDE

VALVE STEAM CHEST

CENTRE BUSH

_SEGMENTAL RING

^SPIRAL WOUND GASKET

1ST STAGE SPINDLE


LEAK-OFF

_VALVE CHEST COVER

PRESSURE TAPPING ,

2ND STAGE SPINDLE


VALVE SPINDLE . LEAK-OFF

.RETAINING RING

HEAT SHIELD .
_TOP HALF COUPLING

BOTTOM BUSH
-BOTTOM HALF COUPLING

SPRING CARRIER- .SPRING LOCATING PEG

VALVE COLUMN
SPACER RING
LINK PIN
SPHERICAL WASHERS
SPRING (INNER)

FORK END SPRING (OUTER)

. BELLOWS

v SPRING LOCATING RING


CONNECTING ROD
, GUARD PLATE
FORK END

FIG. 2.36 Governor valve

162
Steam chests, valves and loop pipes

SPINDLE
LEAK-OFF

VALVE SEAT SEAT PISTON RING


RETAINING DOWEL SEAL
BALANCE PROFILED HEAD
HOLE

FIG. 2.37 'Reverse flow' type governor valve

FIG. 2.39 'Guided flow' type governor valve

SPINDLE LEAK-OFF
SPINDLE LEAK-OFF

of the loop pipes is made, to ensure that there is


no risk of water entering the turbine during start-up.
Where the pipes or the tee-pieces enter the double-
shell cylinder, provision is made on the pipe connecting
to the cylinder for a thermal sleeve which secures the
pipe to the outer cylinder. The loop pipe passes to the
inner cylinder and the expansion between the pipe and
cylinder is allowed for by a sliding joint on the outside
of the pipe, using either stacked continuous rings or split
piston rings. A more detailed description of this type
of joint is given in Chapter 1, Section 3.

PROFILED HEAD 2.8 Crossover pipework


The steam from the intermediate pressure cylinder passes
to the low pressure cylinders through large diameter
IP/LP crossover pipes, which have to accommodate the
FlG. 2.38 'Mushroom' type governor valve
thermal expansion between cylinders by a combination
of various designs of bellows which allow either bending
or axial movement. The bellows arrangements either
top and bottom of the cylinders. On many current incorporate hinge links or have tie rods in order to
machines, the loop pipes from each side combine to form transmit the pressure forces in the pipe, thus protecting
one inlet into each half of the cylinder by means of a the bellows convolutions from the tendency to open out.
tee-piece connection. The loop pipes into the top half Any bellows units at the horizontal ends of the crossover
cylinder are provided with dismantling flanges for pipes are usually of the balanced type, incorporating tie
maintenance purposes, used when the cylinder is opened rods. A typical arrangement of this piping which includes
up. These flanges have a gasket-type joint that has a both types of bellows is shown in Fig 2.40.
design life of 30 000 h between replacements. On some designs of 500 MW machine, these pipes
It is important that adequate provision for drainage are run along the sides or underneath the machine.
163
Turbine plant systems Chapter 2

PRESSURE BALANCE
BELLOWS UNITS

TIED BELLOWS UNITS


REAR

PRESSURE BALANCE
BELLOWS UNITS #^- LP INLET

FORCED COOLING LP2 CYLINDER


OUTLETS

FRONT LP1 CYLINDER

IP CYLINDER
IP EXHAUSTS TIED BELLOWS UNIT

FIG. 2.40 IP/LP crossover pipework

Some early 660 MW machines with pannier condensers Excessive temperature differentials.
used both crossover pipes and cross-under pipes. Similar
bellows arrangements were used to accommodate thermal Excessive eccentricity.
expansion.
If the plant is manned by responsible operating staff on
a continuous basis, the last four items can be monitored
by supervisory equipment having preset alarm levels. This
3 Turbine protective devices allows the operator freedom to manoeuvre the operating
conditions to reduce the dangerous condition. If unable
to do this, the operator must trip the plant manually.
The other dangers have more immediate effects on
3.1 Possible hazards the plant and are generally detected by special trip gear
Abnormal operating conditions, including those where which releases the protection system hydraulic pressure,
the turbine and its systems are not working as designed, and thus closes all the steam valves and disconnects
will cause damage to the plant and possibly to person- the generator.
nel if allowed to persist. The dangers likely to be The above list only includes those dangers which
encountered are: are special to the turbine. Other hazards specific to
the boiler, generator, transformers and high voltage
Over speeding. connections may also initiate a turbine-generator trip.
The system described here can be tripped by signals
Lubricating oil failure. from these devices, which are described in the relevant
High turbine exhaust pressure (low condenser volume of this series. The arrangements to trip the
vacuum). field switches and the high and low voltage circuit-
breakers are described in detail in Volume D.
Governor failure. Overspeed would have serious consequences for
both plant and personnel, therefore the protective
Water ingress to blading. arrangements have been designed to eliminate any
Thrust bearing failure. possibility of a dangerous overspeed.
The turbine governing system provides the first line
Excessive vibration. of defence against overspeed and the second line of
164
Turbine protective devices

defence is provided by separate overspeed trips. The pipe. The turbine is then tripped on low lubricating-oil
turbine cannot overspeed when the generator is connected pressure.
and in synchronism with the electrical power system In the event of a complete failure of the turbine gover-
network. The turbine is at risk during run-up and also ning system, i.e., failure of more than one channel or
when a disconnection occurs on-load. Since disconnec- a failure which renders the governor operative, the gover-
tion can occur as a result of another trip function, nor is designed to send trip-initiating signals to the protec-
e.g., loss of lubricating oil, it is desirable to reduce tion scheme.
the potential for overspeed by co-ordinating the trip- Water ingress to the turbine can occur due to malfunc-
ping of the circuit-breaker and the closure of the steam tion of boiler or feed controls, especially during a change
valves. An overspeed will only occur if the steam passing in load. In this case, wet steam or even slugs of water
through the turbine exceeds that required to match the could be introduced through the HP steam line. The
load. Thus, if possible, tripping of the turbine-generator degree of hazard and the type of protection required
should first close the turbine steam valves. When the depends on the boiler type and steam conditions at the
steam flow has reduced nearly to the no-load value, the inlet to the turbine. When a drum boiler is used to supply
generator may be disconnected from the power system superheated steam, turbine protection may not be
network without risk of overspeed. This is known as a necessary, providing loss of boiler firing is adequately
Category B trip and is particularly important in the detected and alarmed so that the operator can take the
case of water-ingress trips or a manual trip following necessary corrective action. In the case of a once-through
such an incident. If the event caused distortion of the boiler supplying superheated steam, it is necessary to trip
steam valves and they failed to close, simultaneous the turbine on low steam temperature before saturated
disconnection of the generator would promptly lead steam conditions reach the turbine. The danger is that,
to destructive overspeed. However, if the generator if not tripped, severe distortion could occur, causing
maintains its connection, the unit can be safety shut down seizure of the turbine steam valves or fracture of the
by closing the boiler stop valves. All tripping conditions turbine blading. Once-through boilers supplying dry
where this sequence of events is desirable are made saturated steam represent less of a hazard due to chill-
Category B trips. These include governor failure and ing. However, the sudden ingress of wet steam could
lubricating oil failure as well as overspeed, water-ingress result in severe thrust loadings on the turbine and
trips and the operator's emergency stop button. blading, so the plant must be designed to accept this or
Other tripping functions, such as turbine high exhaust- be protected against it. Water ingress may also occur
pressure trips and certain electrical trips, require im- from feedheating plant via back-flow to the tapping
mediate generator disconnection. As these trips are points on the main turbine. The arrangements to protect
unlikely to have a cause common with any condition against this are discussed in Chapter 3 on feedheating
which is likely to lead to jamming of the turbine steam plant.
valves, this can be done without any significant degrada-
tion to the overspeed integrity of the unit. These are
referred to as Category A trips.
The high exhaust-pressure trip is, like the overspeed 3.2 Protection scheme
trip, the last line of defence against an abnormal The trip-initiating devices as described in the previous
operating condition. The danger is that if the exhaust paragraph will be of two types:
pressure is excessive, the last-stage LP turbine blading
will become overheated and damaged. Since the prime Devices where an electrical changeover contact
cause of poor exhaust-pressure is likely to be loss of operates.
CW flow, it is usual practice to provide high exhaust Devices capable of direct tripping of the hydraulic
pressure unloading gear as part of the governing system fluid system.
in an effort to reduce turbine load and avoid tripping.
LP exhaust temperature sprays are often provided as The result of a trip initiation will be to close the turbine
another stage of protection, coming into operation when steam valves and trip the generator circuit-breaker,
a high temperature is sensed or when the turbine load having regard to the division into Categories A and B.
falls below a predetermined value. Note that there is a The tripping system includes redundancy, so that the
greater potential for heating the blading at very low loads failure of any one element in the system does not prevent
as there is no steady flow through the turbine and recir- tripping, and is also designed to avoid spurious tripping
culation can occur. The final line of defence is provided as far as possible. Figure 2.41 shows schematically the
by bursting diaphragms fitted to the LP turbine casing. main functions of the hydraulic tripping system much
These are normally set to operate at slightly above simplified. The interfaces with the electrical tripping
atmospheric pressure. system and the stop and governor valve relays are also
Although a continuous supply of lubricating oil is shown. The diagram does not show the redundancy
practically ensured by separate AC and standby DC associated with the electrical tripping system, which is
pumps, there is always the possibility of a fractured described later in this section.
165
Turbine plant systems Chapter 2

FIELD
LOSS OF SPEED GOVERNOR TRIP BOILER LVCB
SWITCHES
AND OTHER AND
ELECTRICAL TRIPS AUXILIARIES ELECTRICAL HP
PROTECTION STOP
VALVE
CATEGORY A A A CATEGORY B
CATEGORY A AND B TRIPS TRIPS TRIPS

BJI
-o o VALVE
TRIP
TRIP RELAY FLUID ,I, LOV
LOW FORWARD SOLENOID
TURBINE
PRESSURE
TRIP PLUNGER
SWITCHES
[pyi POWER RELAYS
POV
SOLENOID PROTECTION FLUID

CM -J VALVE RELAY

o c l FRONT
EMERGENCY
oocf TRIP VALVE H P GOVERNOR i

KM
BLOCKED VALVE J
. IF FRONTH
DRAIN [TESTED VALVE
TRIP
BLOCKED SOLENOID-
CN o o o o |
n=a
IF REAR-H

Cza I iL TESTED
lo o ol REAR VALVE RELAY
MANUAL EMERGENCY
TRIP o o d TRIP VALVE

(1 5
TEST TEST
FRONT REAR CONTROL FLUID

ORIFICE
PLATES

INTERLOCK UNIT
FROM FRF I II
SUPPLY UNIT I L
OTHER STOP AND
^GOVERNOR
_LL ' VALVE RELAYS

NOTES:
1. SHOWN IN THE NORMAL RUNNING UNTRIPPED CONDITION
2. ISOLATING AND RESET FACILITIES NOT SHOWN

FIG. 2.41 Hydraulic trip unit simplified block diagram

The heart of the unit comprises two sets of emergen- ditional hydraulic units before the subsequent turbine
cy trip valves and trip plungers, each associated with a run-up. For clarity, these have not been shown on the
set of overspeed-trip bolts mounted in the main turbine diagram.
shaft. Fluid at high pressure is supplied to the emergen- To exercise the system and ensure that any faults in
cy trip valves so that if either is caused to trip, i.e., move the tripping system are identified and rectified without
to the left, protection fluid is connected to drain via pipe delay, regular on-load testing is recommended. To test
A or pipe B and closure of all the turbine steam valves the front emergency trip valve, the interlock unit is
results. Control fluid pressure is maintained to avoid shifted so that the left-hand ends of the trip cylinders
excess fluid consumption from the FRF supply unit. are isolated from each other. The same operator action
The emergency trip valves are operated by spring- also blocks port A on the front emergency trip valves.
loaded trip plungers. When in normal operation, the While in this condition, any solenoid, manual or over-
spring is held compressed by a spigot held in place by speed trip acting on the front trip valve will cause the
the Y-shaped trip arm and latch. Initiation of the emergency trip valve to move to the tripped position.
overspeed trip, the manual trip or the solenoid trip causes Due to the isolation, protection fluid pressure is not lost
the spring-loaded latch to be released. High pressure and the unit will run undisturbed throughout the test.
protection fluid in the chamber at the left-hand end of A genuine trip occurring during the test period will be
the emergency trip valve is thus released to drain and initiated by the rear trip valve and will result in the unit
causes them to move to the tripped condition. It should tripping in the normal way.
be noted that when the interlock unit is in its normal The detailed implementation of the hydraulic tripp-
mid-position, operation of any one overspeed trip will ing system by each turbine manufacturer will vary. GEC
cause both emergency trip valves to move to the tripped Turbine Generators, mounts the complete unit in the
condition. front pedestal, with a short direct connection to the
The trip plungers and latches must be reset by ad- overspeed trip units. In the case of NEI Parsons, the
166
Turbine protective devices

overspeed trip, latch lever and trip plunger are in the contacts operating the auxiliary relay OP. Individual
front pedestal of necessity. However, all the other units sets of contacts in this relay then energise the solenoid
including the emergency trip valves, test interlock, dump valves of each steam valve relay, these being of
isolating and reset facilities are implemented by means Type 2.
of proprietary components mounted on a large manifold Circuit 1 shows a typical Category A tripping function,
block outside the turbine casing. high LP turbine exhaust pressure, sensed by pressure
switches PS6 and 7. These are shown in the normal
running position; when there is a trip condition, PS6
closes and energises flag relay AXR1.1. Providing PS7
3.3 Electrically-signalled trips also closes, TR3 is energised through contacts AXR1.1
The electrical tripping scheme is also shown in outline and AXR1.2. If the 'front' system is being tested, the
on Fig 2.41. Any electrical trip function is signalled test switch will be in the Tl position and, instead of a
to the front and rear trip solenoids via duplicated trip initiation, lamp LP1 will illuminate when PS6 and
relay contact systems. These relays are segregated into PS7 close. Test facilities, interlocked with the test switch,
Category A and Category B trips. Separate contact sets enable atmospheric pressure to be supplied to pressure
on the same relays trip the circuit-breakers directly in switches PS6 and PS7, thus comprehensively testing the
the case of the Category A trips and via low forward- functioning of all components through to the lamp.
power relays in the case of Category B. To enable Circuit 4 is very similar, in this case PS1 and PS2
the mechanically-signalled trips, e.g., the overspeed provide the Category B low relay fluid pressure trip
trip, to signal opening of the circuit-breakers, loss of shown in Fig 2.41. Auxiliary relay TPR2.1 is used to
protection fluid pressure is sensed by sets of pressure provide other interlocks as well as trips. One contact,
switches that provide further inputs to initiate Category TPR2.1 is connected in parallel with other Category B
B trips via the low forward-power relays. The pressure trip contacts to energise trip relay TR7. In turn, contacts
switches may also be used to trip the boiler and auxiliary on this relay, which are not shown, initiate circuit-breaker
devices, e.g., bled-steam non-return valves, dependent tripping via the low forward-power relay.
on the application. The out of 2' tripping concept is provided by the
The low forward-power relays use power sensing via duplication in the rear channel circuit, where complete-
voltage and current transformers to determine when the ly independent sets of transducers initiate tripping.
power generated is less than about 1%. This ensures that Because of the configuration of the turbine hydraulic
the steam valves are very nearly closed and that an tripping system, a trip occurs as soon as any one of the
overspeed cannot result when the circuit-breakers are turbine trip solenoids is energised.
opened, even if no further steam valve closure occurs. The examples chosen to illustrate typical Category A
The above general principles may be implemented in and B trips have each used two pressure switches in each
different ways with either out of 2' or '2 out of 3' channel. For other tripping functions some other form
redundancy. Although the hydraulic tripping system of redundancy may be appropriate. Thus, in some
previously described is a out of 2' system, it will be applications, high LP exhaust temperature is used for
seen that compatibility with a three-channel electrical tripping, the sensing being carried out in each flow of
system is still possible. Each of the two systems is each exhaust. For a six-exhaust machine, 12 transducers
now described in detail. would be used, six in each channel combined in three
The redundancy of the out of 2' system is more pairs to provide immunity from spurious tripping.
complex than a simple interpretation of this title suggests. Figure 2.43 shows the second method of implemen-
Additional transducers are incorporated in each of the ting the turbine-generator electrical tripping scheme using
two channels so that at least two transducers per channel, a '2 out of 3' majority voting system. Using this techni-
or four transducers in total, are employed. Series- que, it is virtually impossible for any single component
connection of the two trip-initiating contacts in each or transducer failure to cause a spurious trip. Likewise,
channel permits any single transducer to fail without a single failure will not prevent a trip from occurring.
causing a turbine trip. However, no single failure of an Auxiliary contacts, not shown in the figure, give the
electrical component will prevent a genuine trip from operator an alarm if there is a failure and inhibits on-
occurring. Identification of faulty components is picked load testing until the fault is rectified.
up either by supervision circuits or by routine on-load The circuit is very simple, with the main functional
testing of the trip-initiating transducers of the 'front' blocks being triplicated or duplicated as necessary. The
and 'rear' systems in turn. Figure 2.42 shows a simplified transducers are connected in three similar auxiliary tripp-
trip circuit for one Category A trip, one Category B trip ing circuits. In auxiliary tripping circuit 1, PS7 provides
and the operator's emergency pushbuttons. The 'front' a typical Category A tripping function such as high LP
and 'rear' circuits are completely independent being turbine exhaust pressure. It operates auxiliary relay RL7
powered by two different DC battery supplies. It is through a flag relay. The equivalent auxiliary relays
necessary to energise the turbine trip solenoid SOL to in channels 2 and 3 are relays RL8 and RL9. On the
initiate a turbine trip via the emergency trip valve (circuit right-hand side of the diagram there are four circuits
2). As a back-up, circuit 3 shows a duplicate set of each using a set of contacts from relays RL7, RL8
167
Turbine plant systems Chapter 2

FRONT CHANNEL REAR CHANNEL


DC SUPPLY DC SUPPLY

PS6 A AXR1. PS8 / ^ A X R 1.13


-o o- -o o-
PS7 PS9 AAXR 1.14
^ y ^ A X R ^
-o o- -o o-
TRIP T1 T2
N N
CIRCUIT 1 AXR 1.1 AXR 1.2 I I AXR 1.13 AXR 1.14 I I
o oo o ' ^f Oo I U n , CATEGORY A
TR AY o oo o-
I ' ^W^H. j^5^ 1
L MJ ^ f
: Q\A/iTru
TEST SWITCH
v
*' I
I 4-CHKSH
TEST SWITCH

TURBINE TRIP
TR3 SOLENOID
-o o-
LOCAL

TRIP EMERGENCY STOP SIMILAR TO FRONT CHANNEL


CIRCUIT 2 REMOTE TRIP CIRCUITS 2, 3 & 4
PUSHBUTTONS
-EL
-o o-
TR7
-o o-
NOT SHOWN:
LATCH RELAYS WITH RESET COILS
CUT-THROAT CONTACTS
TR3 AUXILIARY RELAY ARMING INTERLOCKS
-o o- SUPERVISORY CIRCUITS
LOCAL TRANSDUCER TEST FACILITIES

TRIP .EMERGENCY STOP


CIRCUIT 3 REMOTE
PUSH BUTTONS

-o o-
TR7
-o o-

PS1 AXR 2.1


-o o-
PS2 AXR 2.2
-o o-
T1 T2

P
M
N
AXR 2.1 AXR 2.2 i I
fcO OO Of~0 AUXILIARY
TRIP RELAY

TPR2.1
TRIP TO OTHER
CIRCUIT 4 CATEGORY B
TRIPS
-o
TPR2.1
-o o-
ii!<H=zHgH
TEST SWITCH

CATEGORY B
(LOCAL) TRIP RELAY TR7

(REMOTE) EMERGENCY STOP


PUSHBUTTONS

o o

FIG. 2.42 Simplified trip circuit employing out of T redundancy, with additional redundancy of transducers

168
Turbine protective devices

FLAG
DC+ RELAY CATEGORY A
PS7 A TRIP RELAY
RL7

LOW FLUID PRESSURE


INTERLOCK
CATEGORY B
PS1 RL11A TRIP RELAY
AUXILIARY TRIP
CIRCUIT 1 <5 rWr^ RL1

-^ 1
OTHER
-rYs\ CATEGORY B
TRIPS

FLAG
DC+ RELAY CATEGORY A DC-
PS8 TRIP RELAY
-o o- _y^W-
RL8
RL18

CATEGORY B
PS2 RL12
L12 A TRIP RELAY
AUXILIARY TRIP
CIRCUIT 2 -o o-

-ryfo1 OTHER
CATEGORY B
TRIPS
""/^T

FLAG
RELAY CATEGORY A
PS9 A TRIP RELAY
o ryr^ RL9

loi CATEGORY B
TRIP RELAY
PS3 RL13 A
AUXILIARY TRIP
CIRCUIT 3 -o o-

-o o- OTHER
CATEGORY B

-o o- _ry\1 TRIPS

NOT SHOWN:
LATCH RELAYS WITH RESET COILS
CUT-THROAT CONTACTS
ARMING INTERLOCKS
SUPERVISION CIRCUITS
TRANSDUCER TEST FACILITIES

FIG. 2.43 Simplified trip circuit employing '2 out of 3' redundancy

169
Turbine plant systems Chapter 2

and RL9 connected in a '2 out of 3' voting fashion. overspeed trip) and the governing valves will therefore
The first two sets operate the front and rear turbine have similar requirements for their maximum closure
trip solenoids, while the second two sets operate trip rates. The overspeed trip is set in the range of 110-111 %
relays TR3 and TR4 to give a direct trip of the circuit- speed. This recognises normal governor action over a
breaker. 1% speed range.
A feature of this system is that on-load testing can Overspeed is detected by means of a pair of spring-
be carried out on each transducer in turn and circuit loaded trip bolts mounted in an extension to the tur-
operation checked right through to the operation of the bine shaft at the HP end of the machine. A typical
turbine trip solenoid. Thus, if the front solenoid is arrangement is shown in Fig 2.44. One trip bolt as-
hydraulically isolated and test switch contacts TF are sembly is used for each trip channel and each assembly
closed, transducer PS7 can be vented to atmosphere so is provided with independent on-load test facilities. The
that it gives contact closure, energising RL7 and the front bolt has its centre of gravity a short distance from the
turbine trip solenoid. axis of rotation and, at low speeds, is held retracted by
Actual operation of this can be indicated to the a spring. At 10% overspeed, the out of balance force
operator via a relay fluid pressure switch monitoring the overcomes the spring force, causing the bolt to extend
protection fluid pressure at an appropriate point on the beyond the shaft where it trips the static trip lever and
front emergency trip valve. During testing, the rear releases the latch to trip the turbine. Adjustment to
turbine trip solenoids provide protection in the event of the tripping speed is carried out when the turbine is
a genuine trip. Similar test facilities are provided for most stationary and access to the adjusting plug is possible.
of the transducers, the test inputs being applied by a The overspeed trip can be tested without actually
solenoid valve adjacent to each transducer. This enables overspeeding or taking the set off-load. This is done by
all on-load testing to be carried out from the trip gear selecting either the 'front' or 'rear' system for testing,
cubicles, with a full set of indications to the tester so thus automatically isolating the associated emergency
that faults can readily be traced and rectified. trip valve. An interlocked movement of the trip test
The Category B circuit is very similar to that describ- lever and trip test valve then injects a supply of lu-
ed for Category A, Here the tripping contacts from all bricating oil under pressure into the rotating turbine
the tripping parameters are connected in parallel. Thus shaft, through porting which directs it to the over-
several similar sets in channel 1 are in parallel with PS1 speed bolt under test. This then flies out and trips its
and RL11 and they all operate relay RL1, which is one emergency trip valve via the lever and trip plunger.
of the auxiliary tripping relays forming the '2 out of 3' Following release of the test pressure, these items are
contact sets to operate the turbine trip solenoids and the reset and the second bolt selected for test.
Category B tripping relays TR7 and TR8.

3.5 Mechanically-operated trips


3.4 Overspeed trip Included under this heading are any trips which may
The overspeed trip is the final protection against catas- be implemented by means of a direct mechanical or
trophic failure of the turbine following a load rejection, hydraulic action onto the latching trip lever.
causing the unit to become disconnected from the power The low lubricating-oil pressure trip is sometimes
system. Additionally, an overspeed may be caused by implemented in this manner (Fig 2.45). Lubricating oil
a governor failure on an unsynchronised turbine causing under pressure is supplied to a single-acting spring-loaded
an excessive steam demand. An excess approaching 100% trip cylinder. The oil is supplied via a deadweight
would cause a rapid acceleration of over 10% speed per accumulator common to front and rear channels. This
second. In documented cases where this has occurred, smooths out fluctuations in oil pressure and, in the event
the centrifugal stress limits of the rotating parts have of a sudden loss of oil pressure, will maintain the pressure
been exceeded and a major rupture has taken place with to the trip cylinder for several seconds, thus allowing
components penetrating the casing. Speeds as high as possible recovery by starting of the emergency pumps.
180% have been recorded. Similarly, a direct high exhaust-pressure trip is often
The manufacturer normally carries out a works implemented using the same spring-loaded trip cylinder
overspeed proof test at 120%, well below the design limit as shown in the upper part of Fig 2.45. For the front
at which failure could occur. The setpoint of the tripping system, there are two sets of detectors labelled
overspeed trip is such that this speed would never be 1 and 2. Lubricating oil is supplied to the detectors via
exceeded even at the maximum acceleration rate of the an orifice plate. The downstream pressure is controlled
turbine. Because of the delay time associated with the by a leak-off valve, actuated by a bellows unit. The top
mechanisms, the finite response time of the valve relays half of the bellows is evacuated and sealed at a reference
and the stored energy in the form of steam and water pressure close to zero mbar absolute. The lower half of
within the turbine, it is logical to split the 20% range the bellows is connected to the condenser. The leak-off
of available' overspeed equally between the governor and valve is normally fully seated, since the force supplied
the overspeed trip. The stop valves (operated by the by spring A exceeds that exerted by the condenser
170
Turbine protective devices

SEAL HOUSING

END PLATE
LOCKING PIN
* RINGS
STOP SCREW

H.R TURBINE SHAFT

STOP RING

OIL TO
BOLT V
OIL TO
BOLTX

FIG. 2.44 Overspeed governor

pressure. As the condenser pressure rises, a point is the front protection system is isolated, its two asso-
reached where the spring force is counter-balanced ciated exhaust pressure detectors can be tested in turn
and a further pressure increase causes the leak-off valve by slowly raising the pressure by a needle valve admit-
to unseat. As lubricating oil pressure is lost within the ting atmospheric air. This permits resetting of the trip
vacuum trip unit, plunger B is moved downwards by point if desired.
spring force and the pressure in the short length of
pipe C is lost. If detector 2 also trips, lubricating oil
supplying the front trip cylinder is connected to drain,
thus releasing the trip latch. A similar pair of exhaust 3.6 Operator tripping facilities
pressure detectors operate into the trip cylinder of It is normal practice to provide some direct mechanical
the rear system. On-load testing is enabled by a me- means of tripping the turbine from the front pedestal.
chanical interlock on the trip test lever, so that when Originally, this was an essential safeguard for personnel
171
Turbine plant systems Chapter 2

DETECTOR 1 DETECTOR 2

SPRING A -

FiG. 2.45 Mechanically-operated trips (front tripping system only)

when carrying out overspeed tests either on-load various instruments to guide him. Typically, the operator
oil-injection tests or off-load tests actually overspeed- may decide to trip the machine in the event of per-
ing the machine. This form of trip is still retained, even sistent high vibration. This pushbutton is also the
where complete remote testing can be carried out, as it normal means of shutting down a turbine from a low
provides an independent and very direct means of load.
shutting down the turbine-generator, should a plant
attendant observe local conditions which are hazardous
to men or the machine. For the same reason an
electrically-signalled pushbutton trip is provided near 4 Turbine instrumentation
the generator-end of the machine. A large modern turbine-generator comprises a num-
A remote emergency stop pushbutton is also pro- ber of cylinders coupled together to form a rotating
vided in the control room, where the operator has shaft line, Chapter 1 has described this arrangement
172
Turbine instrumentation

in detail. The nature and complexity of this arrange- Shaft eccentricity The peak-to-peak radial excursion
ment requires information to be presented to the op- of the rotor relative to the non-rotating parts is
ator clearly and concisely. Associated turbine systems, measured on each rotor to monitor qualitative changes
described in this chapter, need to be controlled and any in the behaviour of the rotor which may indicate
abnormal conditions drawn to the operator's attention. abnormal or unsafe conditions.
Particular requirements for instrumentation are dealt
with in the appropriate subsection. Specific transducer Shaft speed A single measurement of shaft speed is
types and techniques of measurement are described required, independent of the turbine governor, for
in Volume F, Chapter 4. The purpose of this section operator reference, particularly during turbine run-up.
is to describe, in broad terms, the different categories
Steam valve positions An analogue measurement
of instrumentation that are supplied and the part they
of the position of each steam valve is useful to
play in plant operation.
the operator for general reference, to check the
These categories are:
capability for carrying more load or for assistance
Supervisory instrumentation. in fault finding.

Efficiency instrumentation. Metal temperature measurements These provide a


knowledge of the thermal state of the turbine during
Auxiliary system instrumentation. both transient and steady state operation. Measuring
points are located in the walls of the HP and intercep-
Condition monitoring instrumentation. tor steam valve chests, and in the HP and IP cylinders.
Instrumentation associated with protection and Thrust bearing wear This measurement ensures that
control equipment. thrust pads wear is maintained within safe design
limits.
Instrumentation to provide post-incident records.

All of these parameters are displayed to the operator


either on continuous, direct-reading instruments or on
4.1 Classification of instrumentation a VDU format associated with a computer-based data
processing system. If a VDU display is used, it is se-
lectable for continuous access and scanned at intervals
4.1.1 Supervisory instrumentation of less than 10 s to ensure that the operator is kept
These are instruments required on a continuous basis informed of the current value. Certain parameters, such
to determine the present conditions and trends of the as steam valve positions and speed, can change substan-
main rotating and stationary components, (a) to ensure tially in a fraction of a second. It is essential that the
safe operation within the defined limits and (b), to operator has available a true value of the present reading,
give advance warning of deterioration or change in the therefore direct reading is always employed.
main turbine-generator behaviour, which may require Because of their close association with the running
either maintenance attention or a temporary restriction machine, generally using transducers mounted in a
in the operating role. severe environment, highly specialised and thoroughly
The parameters measured are: proven equipment is essential. This aspect is described
in Volume F. The processing equipment is cubicle-
Rotor axial position In conjunction with cylinder mounted and includes, where necessary, alarm outputs
expansion measurements, this enables the relative so that the operator's attention can rapidly be drawn
axial movement to be measured so that adequate to parameter excursions requiring corrective action.
clearance margins are maintained under all conditions Where computer processing is involved, the whole
of operation. Typically this measurement is provided scheme is subject to careful review to ensure that
on each cylinder of the machine. if the computer fails, the operator still has sufficient
information to continue running at a steady load or
Cylinder expansions In addition to its use in deter- to permit safe shutdown.
mining clearance margins between the rotor and
All of the turbine supervisory parameters are used
cylinders, differential measurement systems are pro-
to provide post-incident records. Some are also used
vided to monitor the expansion and movement of
in the control equipment for turbine run-up.
cylinders relative to each other and their support struc-
tures. Measurements are provided on each cylinder
of the machine.
4.1.2 Efficiency instrumentation
Bearing pedestal vibrations These are measured at These are instruments required to determine or infer
each bearing to continuously monitor the dynamic the operating efficiency of the plant, both for short
behaviour of the machine. term monitoring and the detection of long term trends.
173
Turbine plant systems Chapter 2

The temperatures and pressures of steam and water in British Standard 752. Since many of the transducers
are measured to confirm that the plant components are have to be precalibrated, UK practice requires that the
operating efficiently and in the intended manner. For plant is built with provision for fitting the instruments
example, measurement of the steam and water condi- when a test is required. Thus the manufacturer supplies
tions at the inlet and outlet of a feedwater heater enables pockets for insertion of thermocouples and pressure
an operator to confirm its satisfactory operation. tapping points up to and including the primary isolating
Unsatisfactory operation is unlikely to prejudice the valve. Where possible, steam and condensate flows are
continued running of the plant but does affect its ef- measured by differential pressure devices and so the
ficiency. This category of instrumentation therefore provision made on the plant as-built can again be confin-
draws attention to maintenance activities which are ed to fixed orifices with suitable tapping points. The main
efficiency-related. condensate flow measurement is one of the most critical.
Alarms are derived from some parameters in this Provision is generally made to insert the calibrated orifice
category, for example, steam temperatures upstream of plates in sections of condensate pipework parallel to the
the HP stop valves. These alarms are less critical than main path. When tests are to be performed, the main
those derived from supervisory instrumentation and path is isolated and all the flow passes through the orifice
therefore the alarm processing may be carried out plates. Provision is also made for the connection of a
exclusively in the data processing computer. Steam transmission-type dynamometer to measure the power
temperatures upstream of the turbine HP stop valves are supplied by the boiler feed pump turbine (if fitted).
used to provide data for the long term history. In some plants, a more limited range of parameters
Some of the parameters in the efficiency instrumen- is measured on a permanent basis to provide a routine
tation category are used for the heat rate test instrumen- on-line efficiency monitoring scheme, usually combined
tation identified in the condition monitoring category. with boiler plant. Such schemes inevitably provide
The requirement for accurate, calibrated instruments for less-accurate information than would be obtained from
a heat rate test often precludes the use of the same plant acceptance tests, using recently calibrated trans-
transducers as those used for efficiency instrumentation. ducers. The value of on-line monitoring is that it enables
trends to be identified and appropriate maintenance work
scheduled. Where alternative plant operating strategies
4.1.3 Auxiliary system instrumentation are possible, for example, selection of a standby feed
These instruments confirm the satisfactory operation pump instead of a faulty duty pump, then the operator
of plant auxiliary systems. The description of these can take measures to improve the efficiency of the plant
systems forms the content of this section and more on-line. The scheme is implemented by a series of
systems are described in Chapters 3 to 6. All these algorithms processed by a dedicated computing system
systems require instrumentation for local operation or and is capable of displaying trends in overall performance
fault finding. Wherever their operation is essential given by changes in heat rate, as well as the performance
to the main turbine-generator unit, facilities for re- of individual components.
mote alarms and indications in the control room are
necessary. Machine level instrumentation
This comprises equipment for automatically measuring
4.1.4 Condition monitoring instrumentation and recording changes in the relative levels of the turbine-
This defined list of instruments is used on a periodic generator bearing pedestals. Primarily used for fault
basis to confirm the absence of long term trends which diagnosis, this equipment is sometimes supplied built-in
might lead to unplanned outages and to define acti- by the turbine manufacturer. An alternative approach
vities for future outages. To this extent, some of the is to provide facings and connection points on the
instrumentation in this category is of a diagnostic pedestals so that portable equipment can be used to make
nature. the checks during maintenance outages.
The defined subcategories are:
Heat rate test intrumentation. Shaft vibration instrumentation
The scope of the measuring points required for this
Machine level instrumentation. is more complex than the provision made for turbine
Shaft vibration instrumentation. supervisory purposes. At each bearing, two transducers
measure vibration in the same plane but displaced at
90 to each other. This facilitates the recording of shaft
The purpose and scope of each of these subcategories vibration signatures on run-down and also orbit plots
is described below.
may be taken on-load so that a complete picture of
changes in shaft dynamics can be formulated by an expert
Heat rate test instrumentation or an expert computing system. Such an analysis can
This comprises all the equipment necessary to conduct lead to improvements in the prediction of maintenance
a thermal performance test on the plant as described routines.
174
Turbine foundations

4.1.5 Instrumentation associated with protection Accommodate the thermal expansion of the structure
and control equipment and static parts of the plant under all operating
This comprises instrumentation used in conjunction conditions.
with a control loop, either locally or for the main plant
control systems. The turbine governing system (de- Raise the plant above the turbine house floor to
scribed in Section 1 of this chapter) is an example of provide access for electrical connections and pipe-
the latter, whilst any local control loops not covered work. Bottom connection of the main steam pipe-
by Auxiliary Systems form part of the former. These work is particularly desirable to avoid dismantling
local controls are used to operate plant prior to a unit pipework during maintenance and to prevent the
start-up or following maintenance, where operator action pipework draining into the turbine. The height of
from the control room is not necessary. Also, some plant the turbine above the basement floor level is partly
requires controls which may not be immediately con- determined by the need to accommodate the con-
nected with the minute-by-minute operation of the unit. denser and condenser neck, when an under slung
Further local controls are sometimes needed to permit condenser is used, and partly by consideration of
a detailed fault analysis to be carried out following condensate drainage requirements. The bled-steam
identification of a problem in the central control room. piping should drain away from the turbine and the
drains from LP heaters must be returned to the
condenser. For this to be achieved with gravity
drainage requires a certain minimum height differ-
4.1.6 Instrumentation to provide post-incident ence between turbine and condenser hot well.
records For main turbine-generator plant, these require-
The detectors required to provide these records are ments have been satisfied by either reinforced concrete
derived from other categories of instrumentation, mainly or steel support structures, which are described in
from the supervisory instrumentation. These records more detail in later sections.
provide critical plant data for designated periods be- It is also necessary to monitor the movement of
fore and after an incident to enable the cause to be the foundations throughout the life of the station.
investigated. The recording is initiated by a unit or Settlement of the whole foundation in service is
plant trip (for example, the trip of a feed pump), or not very serious, provided that it is not large enough
directly by the operator on demand. These records are to affect electrical and steam connections, but dif-
produced by data processing computers and, since con- ferential movement between bearing supports must
tinuous scanning of all the input parameters is necessary, be avoided if the alignment of the plant is to be
some compromises have to be made in the scanning maintained within reasonable limits. Multi-limb mano-
speed. Thus, assuming a minimum scanning interval metric level measuring systems are therefore installed
of 3 s and depending on their relative positions in the on the bearing supports to monitor relative level
scanning cycle, a parameter might respond up to 3 s changes. A schematic diagram of such a system is
before or 3 s after the recording shows the trip to have shown in Fig 2.46.
operated. In specifying the requirements of the data 'Slave' units are fitted to each bearing support, with
logging system, the turbine plant designer considers these a master reference unit at one point and the whole
limitations to provide a compromise which is both cost system is filled with water. A uniform level is thus
effective and valuable to operators. established by the water surface and movement of
the bearing support relative to the fixed water level
can be detected by suitable sensors fitted on each
slave unit. Sensors using micrometer adjustment of
5 Turbine foundations an electrical contact probe, and floats with LVDT
position measurement have been used in the past,
The turbine-generator foundations consist of the support but both systems have disadvantages. Present day
structure, the sub-foundation and the subsoil; they systems use an ultrasonic sensor fitted in the base
perform the following functions: of each slave unit which measures the position of
the water surface by sound reflection technique.
Support the static load of the turbine-generator and
Accuracy of measurement is typically 0.05 mm, with
associated pipe loads, and transmit these forces to
a minimum measurement range of 2.5 mm about
the subsoil.
nominal level.
Restrain the plant from undue movement due to Cooling water is circulated around jackets on each
dynamic forces resulting from the load torque, slave unit to eliminate errors due to manometer water
unbalance forces, electrical faults, etc., by trans- temperature variations. Air pressure variations are
mitting and absorbing the associated energy. nullified by connecting the air spaces of each slave
unit together in an 'air balance box' (not shown in
Maintain the alignment of the plant under all op- figure). The balance box is then vented to atmos-
erating conditions. phere at a single point.
175
Turbine plant systems Chapter 2

SLAVE UNITS MASTER UNIT

;y
LEVEL
CONTROLLER
^

SLAVE
DATA UNITS
EXCITATION UNIT PROCESSING
SYSTEM

DISPLAY

FIG. 2.46 Schematic diagram of a turbine manometric level indication and measuring equipment

To allow any relationship between bearing support Analysis during the design process and before con-
level changes and foundation structure temperatures struction to establish design values of natural frequen-
to be studied, temperature sensors are buried in the cy (and harmonics of that frequency) well removed
foundations during construction or attached during from running frequency and its harmonics.
erection.
Incorporation within the support structure of a means
for adjusting the natural frequency after erection and
commissioning to remove or control unwanted
5.1 Tuning resonances and forced vibrations.
The foundations need to combine rigidity, to avoid
excessive movement, and flexibility, to prevent excessive Analysis methods used at the design stage model the
forces being present at the bearings. Dangerous re- plant and its foundations mathematically as a series
sonances at all speeds must be avoided and the natural of masses, beams and springs as shown in Fig 2.47.
frequencies of the foundation as a whole must not be Because of the complexity of the model and the num-
close to running speed. ber of possible modes and frequencies of vibration,
Two methods of avoiding resonant conditions and computer programs are used to assess the forces and
unacceptable vibrations are possible: deflections in the structure in response to a variety of
static, transient and oscillatory forces. The design studies
Overtuned or high-tuned, the natural frequency of also consider the response of the foundation to the
vibration of the foundation structure is above the effects of shaft misalignment, out-of-balance forces, and
running speed of the machine and away from any load and electrical fault torques.
harmonics of this speed. This is referred to as a The subsoil elasticity is important at some sites but
stiff foundation. the effects vary with subsoil type and foundation type.
Undertuned or low-tuned, the natural frequency of These can sometimes be ignored.
vibration of all or some of the foundation structure Rigidity is achieved by establishing the mass of the
is below the operating speed of the machine. This is support structure and sub-foundation at about ten times
sometimes referred to as a flexible foundation. the mass of the rotating shafts. With flexible support
structures, the foundation mass can sometimes be re-
duced as the elasticity of support reduces the dynamic
In designing turbine-generator foundations it is therefore forces transmitted to the sub-foundation and subsoil.
necessary to consider 'tuning' the foundations and there In calculating the loads on the structure, account
are two aspects to this: must be taken of pipework loads (both hot and cold)
176
Turbine foundations

5.2 Concrete foundations


The traditional foundation used in the CEGB for
turbine-generator units up to 500 MW was reinforced
concrete. For small units, the support structure was a
rigid monolithic block on a substantial sub-foundation,
with openings to accommodate plant and pipework.
This type of foundation was invariably high-tuned and
movement at the bearings was restricted at the expense
of high bearing forces. The dynamic energy associated
with machine vibration was transmitted through the
support structure and sub-foundation and absorbed
by these structures and the subsoil.
As unit size increased, the problems of designing a
high-tuned foundation with adequate access for pipes,
connections and ancillary plant became more severe, and
the larger units now in service with concrete support
structures generally use a low-tuned design. Examples
FIG. 2.47 Representation of a turbine-generator and its of low-tuned reinforced concrete support structures are
foundation used for analysis
In practice, the complete turbine and support structure are shown in Figs 2.48 and 2.49. The structure is generally
represented by a full three-dimensional assembly of masses, in the form of a series of portal frames, linked with
beams and springs. The effect of the subsoil is not signifi- horizontal beams at the top to form the platform on
cant in some circumstances and can then be ignored.
which the turbine and generator are mounted. The struc-
ture is designed to limit the differential settlement of
bearing supports to about 0.5 mm, although for bearings
close together differential movement of half this value
and the effects of condenser weight, condenser water is more appropriate.
weight and vacuum forces within the condenser and LP When designing a concrete foundation, margins on
turbine. When underslung, the condenser itself is usual- calculated natural frequency have to be allowed because
ly spring-supported, so only a proportion of the weight of the wide range of values of Young's modulus for
is taken by the support structure. All the condenser concrete which can be met in practice. Concrete also
weight is taken by the sub-foundation. shrinks during curing and this can continue for a long
In this way, design variations can be assessed to reach time after construction. Most of the shrinkage occurs
the best compromises of foundation size, weight, ease during the first six months, so turbine-generator erection
of construction and erection, and the balance between on the support structure is normally programmed to
deflection amplitudes and transfer of forces. occur nine months after construction. Further shrinkage
For high-tuned foundations, natural frequencies above continues to a lesser extent for some time and minor
60 Hz would be expected for vibration in a vertical di- changes to machine alignment may be necessary for up
rection. For low-tuned steel foundations, natural fre- to four years. Concrete also creeps under stress and this
quencies of 12-18 Hz in the vertical direction and continues throughout the life of the support structure.
1.5-3 Hz for transverse vibrations are possible. With In fact creep is one of the mechanisms by which the
spring foundations, the vertical natural frequency can stresses resulting from shrinkage are relieved. Special
be reduced even further. concrete mixes have been developed for minimum
If, despite careful analysis at the design stage, shrinkage to alleviate this problem but these are some-
resonance or excessive movement is experienced in the times difficult to pour and compact.
foundation, it becomes necessary to tune the structure Thermal expansion of concrete is significant and,
on-site. Two basic methods are available for this: together with its poor thermal conductivity, can give rise
to alignment changes between hot and cold conditions
Adding mass to columns or panels at selected locations due to differential expansion. Thermal shielding of parts
to reduce vibration amplitude. of the concrete support structure is therefore employed
to reduce these effects and one UK power station has
Adding (or removing) structural strength to (from) been fitted with cooling pipes embedded in the concrete
the foundation structure to change its stiffness and to control temperatures directly.
move the natural frequency away from a plant ex- As concrete is a site-prepared material and its struc-
citation frequency. tural properties are likely to be variable (within limits)
between sites, the risk of resonance or excessive vibra-
tion might be expected to be greater than with other
Both methods have been used, separately or in com- types of support structure. This has not been the case
bination, on occasions, although post-commissioning in practice, and post-construction tuning of reinforced
tuning is generally not necessary. concrete support structures is rarely necessary. If tun-
177
Turbine plant systems Chapter 2

FIG. 2.48 Reinforced concrete support structure for a 500 MW turbine-generator with underslung condenser
This is a low-tuned design.

FIG. 2.49 Concrete support structure for a 500 MW turbine-generator with side-mounted condensers integral
with the LP cylinders
The HP end of the structure is similar to that of Fig 2.48, but the structure is lower and is not required to provide LP
cylinder support. The mass of concrete used is about 60% that of the structure in Fig 2.48. This is also
a low-tuned design.

178
Turbine foundations

ing is necessary, it is much easier if specific provision A steel support structure is more flexible than the
is made for this in the original design. equivalent reinforced concrete structure and is always
Methods of achieving this, reported from outside the low-tuned. The flexibility of the support columns isolates
UK include: the dynamic forces produced by the rotating shafts from
the sub-foundation to some degree and may allow a
Incorporation of redundant members in the support reduction in sub-foundation mass. This isolation also
structure which can be removed later if it is found helps the causes of unusual vibration behaviour of
necessary to reduce the stiffness of the structure. the plant to be determined as the effects are more lo-
calised than with stiffer support structures. Any attach-
Incorporation of attachment points for the later ments necessary on the support columns are strictly
addition of structural members to increase stiffness.
controlled to ensure that the structure characteristics
Constructing the supporting columns in a pocket in and integrity are maintained.
the sub-foundation. The free column length can then With a steel foundation, the responsibility for de-
be later reduced by filling the gap between column signing and supplying the support structure usually rests
and sub-foundation with additional concrete. with the turbine-generator contractor, rather than with
the civil engineering contractor. This is generally regarded
as an advantage, as the same contractor is responsible
As unit size increases, the mass of the support structure both for the plant which generates the dynamic forces
necessary to provide a sufficiently rigid foundation for and the structure which must respond to, and partially
the plant and to limit bearing deflections increases. absorb them. Shrinkage is not a problem with a steel
Access for pipes and ancillary plant is also restricted structure and working support structure temperatures are
so, despite the economic advantages of concrete in many below those liable to give creep in the steel. The use of
situations, some 500 MW and all larger CEGB turbine- good-quality weldable steel is very important to accom-
generators are mounted on steel support structures. modate the static and dynamic loads, and the steel must
have good impact properties. Steel to BS4360 grade C
is typical of the types used. Thorough non-destructive
testing (NDT) is used on a random check basis for all
5.3 Steel foundations welds, with particular emphasis on critical and site welds,
The use of a welded steel support structure for the to ensure freedom from defects.
turbine-generator has several advantages: The thermal expansion coefficient of steel is less
than that of concrete and, together with the good
A steel support structure is lighter than one of thermal conductivity, reduces problems of differential
reinforced concrete, reducing the static load on the thermal expansion upsetting shaft alignment in the
sub-foundation. vertical direction. In the axial and transverse direc-
tions, the thermal expansion characteristics of the
Steel is a uniform material with accurately known and
support structure are almost the same as those of the
dependable properties, giving greater accuracy in
static parts of the plant which it supports: this ex-
analysis.
pansion is readily accommodated by flexing of the
Offsite fabrication is possible, independent of the support columns. Attachment of bearing pedestals to
weather, and site erection time is reduced. A site the support structure is quite simple for there is no
erection programme time of three months would be need to use grouted-in fixing plates, as on a concrete
typical for this type of support structure. structure.
The design analysis includes for the effects of ro-
Plant erection can be done immediately the support tating out-of-balance loads and considers the fatigue
structure is complete, as it is not necessary to wait conditions at welded joints to ensure the long term
for curing or shrinkage. This has obvious advantages integrity of the structure.
for the construction programme. The accuracy of analysis possible with a steel struc-
ture gives confidence in the performance of the struc-
A steel support structure gives improved access for ture in service and post-commissioning problems have
pipework and generator connections. only rarely been experienced. If problems do occur, the
structure can be 'tuned' more easily than a reinforced
concrete structure by three methods:
Steel support structures are fabricated as a 'table
top' of cellular construction supported from the sub-
Adding steel struts to the structure.
foundation on box construction columns. The 'table
top' is designed to provide support to the bearing Adding weight external to the columns.
pedestals, turbine cylinders, generator and exciter.
Examples of steel support structures are shown in Adding weight inside the sections of a box construc-
Figs 2.50 and 2.51. tion column.

179
Turbine plant systems Chapter 2

EXCITER LOCATION

GENERATOR LOCATION

No. 2 L.P. TURBINE


LOCATION

No. 1 L.P. TURBINE


LOCATION

H.P.TURBINE
LOCATION

I.P. STEAM CHEST


SUPPORT

H.P. STEAM CHEST


SUPPORT

BEAM SUPPORT
COLUMNS

FIG. 2.50 Steel support structure for a 660 MW turbine-generator with two LP cylinders and an underslung condenser

Differential settlement can also be corrected by jacking- Springs mounted in rows on structural concrete walls
up each of the affected columns and inserting packing or in groups at the top of support columns have been
between the column base and the sub-foundation. used and viscous dampers are sometimes employed in
conjunction with the springs. Natural frequencies of
about 3 Hz for movement in the vertical direction are
claimed for these systems. A hydraulic locking system
5.4 Spring foundations is used to pre-load the springs to a set deflection for
As the natural frequency of a low-tuned foundation construction and plant erection purposes. The same
support structure decreases, the isolation between the locking system can be used to allow the insertion of
support structure and the sub-foundation increases, packers, above a spring or spring-group, to correct for
and the sub-foundation is called upon to absorb less foundation column settlement: this also allows springs
of the energy resulting from dynamic and transient to be changed after erection for others having a different
forces generated in the shaft line and static sections springrate, if it is necessary to change the characteristics
of the plant. of any part of the spring support system.
The closest practical approach to complete dynamic Such low natural frequencies are accompanied by
isolation results from mounting the turbine-generator the possibility of greater plant deflection under tran-
plant on springs and this approach has been used sient conditions. Under generator load rejection or
successfully overseas. In the UK, condensers of the short-circuit conditions, torsional rocking of the plant
underslung type have been spring-mounted, as have can impose vertical movements of 1.5 mm at the
smaller items of plant, but spring mounting has not yet springs, so pipe and electrical connections must be
been used for main turbine-generators. designed to accommodate this.
Established overseas practice uses springs of the Because the sub-foundation is well isolated from
helical-coil or plate type supporting a reinforced con- dynamic loads, it is possible to reduce the mass of the
crete deck on which the turbine-generator is mounted. sub-foundation towards that necessary to support the
180
Lubrication systems

FIG. 2.51 Steel support structure for a 500 MW turbine-generator with three LP cylinders and pannier condensers
The condenser support columns are not shown.

static load only, or even to dispense with a mass The thickness of the sub-foundation should not be
concrete sub-foundation and install individual foun- less than one tenth of its length. The need for piling is
dations for each support column. The precise design, determined by the nature of the subsoil at a particular
of course, depends on subsoil conditions at the par- site. Discontinuity between the sub-foundation, the
ticular site. basement floor of the station and the foundations of
The spring support, concrete deck and support other plant is attempted to prevent transmission of vibra-
columns are no cheaper than other support structure tions to other plant and the building structure.
types: the economic advantage claimed for spring
foundations lies in the possible reduction in mass of the
sub-foundation. Cost reductions of 25% are claimed in
favourable circumstances. 6 Lubrication systems

6.1 Lubrication requirements and typical


5.5 Sub-foundation arrangements
Apart from any special designs associated with spring Forced lubrication of the turbine bearings is essential
foundations, the sub-foundation must be a massive in order to prevent damage due to wear or excessive
and rigid concrete base designed to transmit and dis- white metal bearing temperature. Before starting to
tribute the static and dynamic loads of the support turn the main rotating elements, it is necessary to lift
structure and plant above it to the subsoil. Rigidity is the rotors clear of the bearing surface: the jacking oil
necessary to limit differential settlement of the bases system used to achieve this is described later in Section
of the support columns to a value acceptable to the 6.9 of this chapter.
turbine-generator, and the sub-foundation mass is es-
The purposes of the forced lubrication of the main
tablished from design analysis to limit plant vibration.
bearings are:
For the sub-foundation of a modern turbine-generator
installed on a CEGB station, the mass is typically (a) To provide a hydrodynamic oil wedge between
1.3 times the combined mass of the plant and struc- the bearing surface and the journal bearing of
ture above it. sufficient thickness so that the particles of debris
181
Turbine plant systems Chapter 2

normally present in the oil will not damage the experience has shown that limiting the oil temperature
bearing surfaces. leaving a bearing to 71C, gives satisfactory bearing
life.
(b) To provide a flow of cooling fluid sufficient to On older units, the lubricating oil system was
maintain the bearing white metal temperature be- integrated with the turbine control and protection oil
low 110C, dissipating the heat at the bearing system, with the lubricating oil being supplied through
due to: a pressure control valve. A typical arrangement is shown
Thermal conduction. on Fig 2.52.
On modern units, the control system (see Section 1.6
Friction between the journal, oil film and white of this chapter) normally requires a fire-resistant fluid
metal. (FRF) system with a pressure between 70 and 175 bar.
Turbulence with the oil itself. The lubricating oil system on these units (Fig 2.53)
is provided using a directly-driven centrifugal pump
delivering oil at around 11 bar. The oil from the pump
The majority of the oil flow is needed to cool the passes through an oil turbine which drops the oil
bearing. Because of the problems of accurately mea- pressure to around 3 bar; the oil turbine drives a
suring the white metal temperature at the point of booster pump which supplies oil from the main oil
maximum hydrodynamic pressure in the oil wedge, tank to the centrifugal oil pump suction. This arrange-

MAIN OIL PRESSURE FEED

MAIN OIL DRAINS

JACKING OIL

JACKING OIL DRAINS

MAKE-UP OIL

rH
OIL
PURIFICATION AUXILIARY OIL FEED
SYSTEM

GEAR CASE BRGS.


Nos.11-15
.16

HIGH PRESSURE
OIL PUMP

OIL COOLERS OIL SERVICING TANK


AC AC DC
AUXILIARY TURNING EMERGENCY
OIL PUMP GEAR LUBRICATION
OIL PUMP OIL PUMP

FIG. 2.52 Lubricating and relay oil system for older turbine-generator plant

182
Lubrication systems

I MAIN I I L -J I
FEED
PUMP

AC TURBINE
LUBRICATING BOOSTER
OIL PUMP OIL PUMP
JACKING OIL
LUBRICATING OIL COMPARTMENT OF MAIN OIL RESERVOIR PRIMING PUMP
MAIN OIL SUPPLY
JACKING OIL SUPPLY
DRAIN OIL
PRESSURE OIL

FIG. 2.53 Lubricating oil system for modern turbine-generator plant

ment allows the oil tank location to be optimised with seal-oil system (see Chapter 6, Section 5) is provided to
regard to oil drainage under gravity, whilst meeting the prevent hydrogen transfer to the main oil system; on
centrifugal pump suction-head requirements. To protect these units, the supply from the main lubricating oil
the system against overpressurisation, a connection is system is used as a back-up.
taken from the bearing oil supply line to a relief valve On modern units, the lubricating oil system supplies:
mounted on the oil tank.
The directly-driven main oil pump provides an Each journal bearing on the turbine/generator/exciter
extremely secure source of lubricating oil under normal rotating line.
running conditions. For normal start-up and shutdown,
an AC auxiliary oil pump provides the lubricating oil The main thrust/surge bearing.
supply. For emergency shutdown, when the AC supplies
are not available or the AC pump fails to start when The generator hydrogen seals, either as the sole supply
required, a DC auxiliary oil pump is provided. Auto- or as a back-up system.
matic sequential starting of these pumps is arranged The bearings on the turbine-driven boiler feed pump,
upon falling lubricating oil pressure to ensure that the where this plant is provided.
unit can be brought to a standstill without damage to
the bearings, and to ensure that the bearings do not
overheat due to conducted heat. Oil filters and strainers, oil cooler, tank vents and
Lubricating oil is also used for the generator hydrogen oil purifier connections are provided on the lubricat-
seals and the supply is taken from the 70-170 bar oil ing oil system. Details of these features are described
pressure manifold. On some modern units, a separate below.
183
Turbine plant systems Chapter 2

The unit lubricating oil tank is connected to the A schematic arrangement of the systems used is shown
station clean and dirty oil tanks, and also to the oil in Fig 2.54.
purification system, with the pipework and pump
necessary to permit the transfer of oil:
From the station clean-oil tank to the unit oil tank.* 6.2 Oil pumps
From the station used-oil tank to the unit oil tank.* Details of the various oil pumps used are described
in the paragraphs that follow.
To drain the whole of the oil inventory from the
unit oil system into the unit oil tank, and from the
unit oil tank into the station used-oil tank. 6.2.1 Main lubricating oil pump
For security of supply the main lubricating oil pump is
From a road oil-tanker into the station clean-oil driven directly from the main rotating line. On older
tank. units, this was a gear-driven positive displacement gear
pump. On modern units, the large volume of oil required
From the station used-oil tank into a road oil-tanker. (around 100 litres/s) enables a centrifugal pump to be
used economically; a typical example is shown in Fig
Through the oil purifier to process either the oil
2.55.
in the unit tank or the oil in the station clean-oil
The pump is not self-priming and requires a suction
tank.
oil pressure of around 3-4 bar.
Through a portable unit oil purifier to process
the oil in either the unit tank or the station clean-oil
tank. 6.2.2 Turbine-driven oil booster pump
In order to ensure the security of lubricating oil sup-
ply, oil from the main oil pump discharge is passed
* These transfers are made using the oil purification through an oil turbine. The oil turbine is mounted
unit. on top of the oil tank and drives a submerged cen-

FROM
OTHER
UNITS

> OTHER
UNITS
- LUBRICATING OIL

BYPASS

MISCELLANEOUS

DRAINS

VENT

^ \ NON RETURN VALVE

?
RELIEF VALVE

FIG. 2.54 Lubricating oil transfer and conditioning system

184
Lubrication systems

VAPOUR BLEED IMPELLER VAPOUR BLEED INLET VOLUTE JOURNAL BEARING


TUBE TUBES / O I L INLET

THRUST BEARING
OIL DISCHARGE

JOURNAL BEARING

LOCKING PLATE

SHAFT THRUST
SHOULDER

TOP HALF
NECK RING

VENTILATION HOLE
TO EXPANSION
COUPLING

COUPLING FLANGE
TURBINE ELECTRICAL TO DRIVE SHAFT
TURNING GEAR END

THRUST BEARING
OIL INLET

BOTTOM HALF
NECK RING PUMP SHAFT

BOTTOM HALF
WEAR RINGS
JOURNAL BEARING
OIL OUTLET

TEST PRESSURE
GAUGE CONNECTION

OIL INLET FLANGE

OIL DISCHARGE
FLANGE

FlG. 2.55 Main lubricating oil pump

trifugal pump. This pump delivers the oil to the main motor replacing the oil turbine. The AC pump delivers
pump suction. A typical example is shown on Fig oil to the lubricating oil pipework feeding the oil filters
2.56. and coolers at around 3 bar, and primes the main oil
pump. The DC pump feeds either the same pipework
system as the AC pump, or the pipework which feeds
6.2.3 AC and DC motor-driven auxiliary oil oil directly to the bearings at around 1.5 bar. Each pump
pumps has a capacity of around 70-120 litres/s.
The AC and DC auxiliary oil pumps which supply oil
to bearings under start-up and normal shutdown, or
under emergency shutdown respectively, are centri- 6.2.4 Jacking-oil pumps and priming pumps
fugal pumps with a submerged suction. They are also The jacking oil pumps deliver oil at around 300 bar
suspended from the tank top and their arrangement to the individual bearings. The pumps used are motor-
is very similar to Fig 2.56, but with an AC or DC driven positive displacement and either multi-plunger
185
Turbine plant systems Chapter 2

GUIDE RING WEAR RING LOCKNUT TURBINE RUNNER

WEAR RING

TURBINE CASING

WEAR RING

DISCHARGE PIPE
TURBINE TOP
CHAMBER

VAPOUR BLEED
JOURNAL BEARING

HIGH PRESSURE
SHAFT
MEASUREMENT
TAKE-OFF

PEDESTAL
VENTURI

LOW PRESSURE THRUST & JOURNAL


MEASUREMENT BEARING
TAKE-OFF

PUMP COVER

VAPOUR BLEED
WEAR RING

IMPELLER

DISCHARGE BEND
PUMP BODY

WEAR RING

BLEED PIPE STRAINER

FIG. 2.56 Turbine-driven oil booster pump

pumps or two-shaft gear pumps, see Figs 2.57 and lubricating oil manifold and the gear pumps have
2.58. a motor-driven positive displacement two-shaft gear
The arrangement utilises either one gear pump per pump.
bearing or one motor/pump unit for either one or On some designs the turning gear is provided with
two bearings. The pumps require a positive suction a separate jacking oil pump. This pump is a motor-
pressure. The multi-plunger pumps are fed from the driven, positive displacement, two-shaft gear pump;

186
Lubrication systems

PUMP BODY

OIL INLET

SEALING RING

ECCENTRIC
SHAFT

INLET VALVE

INLET PORT

SHAFT THRUST
BEARING
OUTLET PLUG

PISTON SPRING
OUTLET PORT

OUTLET VALVE
ASSEMBLY

STEEL BALL

FIG. 2.57 Multi-plunger jacking oil pump

the discharge pressure is the same as for the other Pump duty Type Drive
jacking oil pumps. Purifier/oil conditioner Gear Electric motor
oil
6.2.5 Other pumps Purifier/oil conditioner Electric motor
Various other pumps are used on the lubricating oil water
system and oil transfer systems as follows:

Pump duty Type Drive


Oil tank water/oil Centrifugal Electric motor 6.3 Oil tanks
vapour extraction On modern units, the main oil tank has a capacity of
Oil tank hydrogen/
around 75 m3 for the lubricating oil system oil inven-
Centrifugal Electric motor
tory, with a normal working level volume of 50 m3:
oil vapour extraction
a typical arrangement is shown on Fig 2.59. The tank
Clean and used Gear or Electric motor, is designed with the oil return and the pump suction
oil transfer diaphragm or air separated by baffle plates, to assist in de-aeration and
187
Turbine plant systems Chapter 2

END COVER

BODY
STRAIGHT
/CONNECTOR
O-RING
DRIVEN GEAR
WOODRUFF KEY
COMPOUND BUSH
BACKING WASHER

MOUNTING
FLANGE

ELBOW
CONNECTOR

OIL SEAL

FIG. 2.58 Gear type jacking oil/priming pump

settlement and also to prevent the formation of stag- valves, two vapour extraction pumps are also mounted.
nant pockets of oil. The quantity of oil in the tank One to remove water and oil vapour from the tank and
and the internal design of the tank provide around the other to extract hydrogen and oil vapour from the
seven minutes oil transit time from return to suction, detraining tank.
with the normal time limits being between five to
ten minutes.
The trend on modern systems is to provide a self-
contained section of the overall oil tank for the hy- 6.4 Piping
drogen seal-oil system, the objective being to eliminate Pressure oil piping for both jacking oil systems and
the risk of hydrogen gas passing into the main lubri- lubricating oil systems on modern units is subject to
cating oil system. Where a self-contained system is special design precautions against oil leakage and fire
used, a back-up supply of oil to the hydrogen seals risk. The oil piping is sized so that the oil velocity is
is provided. Where the lubricating oil system provides between 1-5 m/s. Oil piping from the pump discharge
the hydrogen gas-side seal-oil, special precautions are is contained within an enclosure/duct and the pipe-
taken to ensure that any entrained hydrogen is released runs between pipe joints are as long as is possible.
and vented to atmosphere. A separate seal-oil loop All pipe joints are of Class 1 welded construction.
detraining chamber is used to ensure that all hydrogen At the exit from the ducted area, the pressure oil pipe
is removed before the oil is mixed with the main oil is contained within a protective pipe, so that any oil
system. leakage would be contained and would be detected at
Coarse-mesh strainers are provided on all oil returns 'tell-tale' drains. Pipe material up to the filters is mild
to the tank to assist de-aeration and to catch any large steel; on some designs, the pipe-runs after the filters
foreign material. Problems have arisen in the past with are in stainless steel to minimise the risk of corrosion
corrosion at the air/oil interface in the main oil tank products damaging the bearings. Automatic air venting
due to the presence of water/water vapour in the oil. of the pipework system from its highest points to the
The main oil tank is now fabricated either in stainless oil tank is provided where the air is not vented through
steel or mild steel with a special phenolic paint protec- the bearings. Oil filters are also provided with air vents
tion against corrosion. to the oil tank; these ensure that any air accumulation,
On the top of the oil tank, in addition to the sus- either in service or as a result of servicing or inspection,
pended oil pumps and the bearing oil pressure relief is vented to the oil tank.
188
Lubrication systems

A.C. MOTOR-DRIVEN A.C. MOTOR -DRIVEN


LUBRICATING OIL PUMP SEAL OIL PUMP
D.C. LUBRICATING OIL
PUMP DISCHARGE DETRAINING COMPARTMENT
NON-RETURN VALVE D.C. LUBRICATING OIL
PUMP DISCHARGE - * OIL FLOW
ISOLATING VALVE ^ VAPOUR
BOOSTER PUMP
DISCHARGE TO MAIN D.C. MOTOR DRIVEN SEAL
OIL PUMP OIL PUMP

A.C. LUBRICATING OIL PUMP


DISCHARGE NON-RETURN VALVE
A.C. LUBRICATING OIL PUMP
ISOLATING VALVE
DISCHARGE TO ATMOSPHERE
BOOSTER PUMP TURBINE BEARING OIL SUPPLY
INLET FROM MAIN OIL PUMP MAIN SET
LUBRICATING OIL -BOILER FEED PUMP
BOOSTER PUMP TURBINE TURBINE OIL SUPPLY
DISCHARGE ISOLATING
VALVE MAIN OIL RETURN

LUBRICATING OIL
BOOSTER PUMP TURBINE DUPLEX HYDROGEN
DISCHARGE ISOLATING DETRAINING TANK
VALVE
OIL STRAINER RELIEF VALVE
OIL DRIVEN BOOSTER
PUMP TURBINE
DETRAINING TANK DRAIN
OIL SUPPLY TO COOLERS

OIL TURBINE DRIVEN


BOOSTER PUMP
FILTER CHANGE-OVER VALVE
OIL STRAINER
TANK MAIN COMPARTMENT
VAPOUR EXTRACTION FAN
GAS DETRAINING COMPARTMENT
VAPOUR EXTRACTION FAN DUPLEX FILTER

SUPPLY TO PURIFIER
RETURN FROM PURIFIER AND TRANSFER SYSTEM
DETRAINING COMPARTMENT VENT
GENERATOR BEARING
GENERATOR BEARING DRAIN No. 10 BEARING FROM OIL COOLER DRAIN PIPE VENT
TO FILTER

FIG. 2.59 Main oil tank general arrangement

6.5 Oil coolers dissipation requirements are around 2 MW per cooler.


The function of the oil coolers is to ensure that the oil On some designs, the oil coolers have the main
temperature leaving the bearings is below the permitted lubricating oil filters integral with the cooler shell. A
limit by removing the heat absorbed by the oil within typical example of an oil cooler, which also shows the
the pumps and the bearings. Redundant coolers are integral oil filters, is shown on Fig 2.60.
provided in order to enable repairs and tube cleaning Arrangements are made for automatic by-pass of
to be carried out whilst the unit is on-load. Normally, the oil coolers upon excessive pressure drop across the
three 50% duty coolers are provided, but two 100% units coolers. Automatic control of the oil outlet temperature
are sometimes used. is provided.
The oil coolers are mounted vertically with a two-pass
water flow through the tubes and a single-pass oil flow
through a series of baffles, to ensure even cooling. The
cooler shells are of mild steel and modern practice 6.6 Oil strainers and filters
is for the tubes to be made of titanium. The tube The oil strainers are coarse wire-mesh basket type
nest has a fixed and a floating tubeplate to contain assemblies which are designed to catch large foreign
thermal expansion. The coolers are provided with re- material from the oil drains into the main oil tank,
movable end plates so that cleaning can be carried thus ensuring that material reaching the centrifugal
out without dismantling the water pipes. The heat pump suction will not cause pump damage. They can

189
Turbine plant systems Chapter 2

C.W. INLET

BOSS FOR
THERMO POCKET WATERBOX AIR
RELEASE CONNECTIONS
BOSS FOR
DISTANCE
THERMOMETER
C.W.
C.W. OUTLET COOLER BODY AIR
RELEASE CONNECTIONS
WATERBOX COVER

INLET/OUTLET
WATERBOX
JJ
TUBENEST
ii u m ii, BAFFLE PLATES
TOP TUBEPLATE [pi! !!
OIL OUTLET < m u utt
(Bin urn ii l!
BOSS FOR DISTANCE'
THERMOMETER II mu in!
BAFFLE PLATES

FILTER CHAMBER TUBES


COOLER BODY ACCESS COVERS (Ni

BOSS FOR
BOSS FOR DISTANCE THERMO POCKET
THERMOMETER
FILTER CHAMBER

OIL INLET
FILTER CHAMBER AIR
RELEASE CONNECTION

DIFFERENTIAL PRESSURE WATER DRAIN


GAUGE CONNECTIONS

RETURN WATERBOX
FLOW DIAGRAM

FILTER ELEMENTS
BOTTOM TUBEPLATE

FIG. 2.60 Oil cooler with integral filter

be lifted out of the tank to remove and inspect any of one compartment whilst the unit is on-load.
debris collected. Facilities are provided to enable a filter to be
Two main systems of filtration of the lubricating primed and pressurised after service, before put-
oil are used: ting a filter compartment back into service. The filter
normally provides a capacity of around 106 litres/s
(a) Cartridge filters fitted into the oil cooler casing under a pressure drop of 0.3 bar with both com-
which are designed to filter 13 litres/s of hot oil partments in service. Normal filter cleaning is
per cartridge, to a nominal particle size of 10 carried out automatically when a rising pressure
microns. Each cooler can have up to four dispos- differential reaches 0.45 bar across the filter. Ro-
able cartridges giving a total filtration capacity of tation of each plate filter assembly then occurs
around 52 litres/s, with two coolers required for against a scraper bar; the debris off each filter falls
100% duty. into a sump at the bottom of the filter housing and
is cleaned out on a regular basis. A typical arrange-
(b) Duplex filters fitted after the oil coolers. These ment of a plate-type filter is shown on Fig 2.61.
can be either multiple disposable filters, with facilities
for on-load replacement, or a duplex plate filter Where a plate-type filter is used in the main oil supply
which can be cleaned on-load. The plate-type filter to the bearings, additional filtration is required for
consists of two compartments, each with five filter the oil supply to:
assemblies. Each assembly consists of a series of
plates and spacers, which give the required degree The main thrust and surge bearings.
of filtration of 75 micron. Each compartment
The shaft turning gear, jacking oil pump, gearing
normally passes 50% of the oil; facilities exist to
and clutch.
pass 100% flow through one compartment in order
to allow replacement, maintenance or inspection The main oil pump, thrust bearing and cooling sprays.
190
Lubrication systems

MFD 227 GEARBOX

CHAIN DRIVE

PLATE WHEEL

PLATE WHEEL

CHAIN DRIVE

NAMEPLATE

JUNCTION BOX
3-WAV CHANGEOVER VALVE

DIFFERENTIAL
PRESSURE GAUGE

5-WAY MANIFOLD VALVE

DEMOUNTABLE STOP
FILTER PACK

DIFFERENTIAL
PRESSURE SWITCH

DRAIN CONNECTION

CLEANING DOOR

PRESSURE EQUALISING VALVE

VALVE POSITION POINTER

FIG. 2.61 Plate type oil filter

The oil for these duties is taken from the filtered oil housing and the cold lubricating oil, which results in
supply to the bearings and passed through a duplex condensate being dispersed through the oil. The oil
plate-type filter system similar to that described above also collects wear particles, oxides, soluble acids and
and shown on Fig 2.61. This additional filter has only sludge. These need to be removed from the oil to
four plate filter assemblies in each compartment and ensure its long life and efficient lubrication. There
has only manual filter cleaning. The filter provides are two main systems used on continuous by-pass duty
a capacity of 16 litres/s under a pressure drop of whilst the unit is in operation, and an oil regeneration
0.2 bar with both compartments in service. system is also used in the station oil system. The on-line
systems are described in the sections which follow.

6.7.1 Centrifugal separation systems


6.7 Oil purifiers and coalescers This type of system has been used for many years but
The main source of contamination of lubricating oil requires careful adjustment for maximum efficiency,
is the leakage of steam from the rotor gland seals. as well as considerable maintenance. A schematic ar-
This steam condenses upon contact with the bearing rangement of the system is shown on Fig 2.62.
191
192
WATER
INLET WATER INLET
Turbine plant systems

ANT I-FLOOD
LIMIT SWITCH

K
=IXM WASTE WATER TANK SLUDGE TANK
::::<:: CLEAN OIL
ANTI-FLOOD TANK

FIG. 2.62 Oil purifying system


Chapter 2
Lubrication systems

The principle of operation is that if a mixture of Oil is taken from the main oil tank at a rate of 17%
solids and fluids is centrifuged, they settle out radially of the oil inventory per hour. The oil initially passes
according to their specific gravities. Dirty oil is deli- through a series arrangement of fine-mesh sloping
vered from the main oil tank into the purifier and screens. The water coalesces on the screens in water
is heated through a regenerative heater/cooler to the droplets which run down to the bottom of each screen
optimum temperature for centrifugal separation, around and are led to drain. The oil then passes through a series
75C. The oil is delivered into the separator bowl and of polyolefinic bags which filter out the particulate
separates into its various densities under centrifugal matter. Finally, the oil is pumped through a 5 micron
force. A series of inverted cones collect the lighter oil pressure filter and delivered back into the main oil tank.
(see Fig 2.63), and deliver it to the clean oil outlet. The The oil passes through the purifier at its operating
water and acids are discharged through the outer drain: temperature and because it is not heated the risk of
the solids accumulate in the bowl and are discharged bacterial/fungal growth may be greater (see Section
at regular intervals. The clean hot oil is pumped through 6.8 of this chapter).
the regenerative heater/cooler, heating the incoming oil Provision is made for the regeneration of used oil
and is then returned to the main oil tank. The oil flow within the station oil transfer system. Oil for regen-
rate through the purifier is 10% of the oil inventory eration is taken from the unit oil tank or the station
per hour. dirty-oil tank at around 1.1m3 per hour and processed
in the plant shown schematically on Fig 2.65.
The oil is heated to 54.4C and is then sprayed into
6.7.2 Static oil purifiers/coalescers a chamber with a vacuum maintained at 913 mbar
An alternative system which is now coming into use below atmospheric. Under these conditions the water
is the static purifier, which is shown diagrammatically boils off, is removed by the vacuum pump and con-
on Fig 2.64. densed. The dry oil is then pumped out of the vacuum
chamber and through a filter. The filter comprises a
pack of nylon-backed filter papers clamped between
perforated steel plates, and filters the oil to 10 microns.
From the filter, the oil is taken into the clean oil tank
prior to being pumped back into the unit oil tank after
it has been cleaned.

6.8 Oils and greases

6.8.1 Oils
The oils used in steam turbines must provide clean,
stable and efficient lubrication whilst exposed to the
severe operational conditions. They are also required
to be efficient at absorbing the heat generated in the
bearing. These conditions require the use of oils in-
corporating additives, particularly for the inhibition
of corrosion and oxidation.
The basic turbine lubricating oils are to British
Standard 489: 1983; CEGB Standard 207001 covers
lubricants for use by the CEGB and Table 2.1 is an
extract which covers turbine lubricating oils. The spe-
cific grade used on the modern 3000 r/min tandem
turbine-generator is TO-32.
Additives are now used to inhibit oxidation, corro-
sion and foaming. An oxidation inhibitor is added to
stabilise the oil against oxidation and to passivate the
metals which act catalytically to increase oxidation. These
inhibitors maintain a low neutralisation value (acidity)
of an oil over many years of service. A rust inhibitor
in the oil protects carbon-steel surfaces from rusting
when in contact with water or moist air entrained within
FIG. 2.63 Oil purifier bowl operation the oil circulating system.
193
Turbine plant systems Chapter 2

OIL/WATER BLEED
TO
MAIN OIL
TANK

OIL
INLET '

PRESSURE
FILTER

RECIRCULATING
PUMP
PRECIPITATOR POLISHING
CHAMBER FILTER
CHAMBER

FIG. 2.64 Static oil purifier

Detergent additives are used to inhibit high tem- 6.8.2 Greases


perature oxidation, the formation of low temperature Although the products of many manufacturers are
sludge and the deposition of contaminants. utilised, there are three basic greases used for turbine
Viscosity index improvers reduce the fall in viscosity plant:
with temperature rise. Pour-point depressents have
the opposite effect and reduce the temperature at which Silicone-based grease containing molybdenum
the oil becomes immobile. disulphide. This has a working range of - 50C to
Anti-foaming agents are added to suppress the ten- 300C.
dency of aerated oil to foam and assist in the release Mineral oil with Bent one filler; this grease has a
of air from the oil. slightly lower temperature limit of 260C.
The acidity (total) of new oils is normally within the
range 0.02 to 0.10 mg of KOH/g, or slightly higher in Lithium-based grease. These greases are used for a
additive-conditioned new oil. In service, oils tend to wide range of lubricating duties including ball and
oxidise to organic acids and this is accompanied by an roller bearings. The requirements for the testing of
increase in total acidity. The acidity level of the oil this type of grease are laid down in CEGB Standard
is therefore a useful guide to the condition of the oil No. 207001.
and the need for purification or conditioning.
Water ingress into the turbine oil is the most com- The first two greases listed are for the lubrication of
mon problem with oil systems. The presence of excess high temperature sliding surfaces, such as turbine
water in oil, particularly if stationary for any length palms and steam valve pivots.
of time, may result in bacterial and fungal contamina-
tion of the oil systems. This can reveal itself as a
yellow/black stringy grease-like material. This growth
can take place in sediment in oil tanks or other plant 6.9 Jacking oil systems
items. It can be particularly difficult to clear from When a turbine-generator shaft is rotating very slowly,
tube nests. The basic precautions are: the normal lubricating oil supply cannot ensure that
a hydrodynamic oil wedge will be maintained. Also,
To ensure that the water content of the oil in
additional lubrication measures are required to prevent
operation is kept low by regular use of the oil puri-
bearing damage and to minimise breakaway torque
fier; the water content should not exceed 0.05%.
when starting a turbine-generator from standstill. In both
To remove sludge deposits from the oil system circumstances the jacking oil system provides high
plant-sumps on a regular basis. pressure oil to the base of the bearing and floats the
rotors on a film of oil. Until the turbine shaft speed
If bacterial/fungal growth becomes a problem, the is capable of sustaining an adequate bearing oil wedge
addition of the correct biocide to the oil will kill the (above 200 r/min), the jacking oil system and the nor-
bacterial/fungal growth. mal lubricating oil system are run in parallel.

194
Lubrication systems

SPRAY PIPE
HIGH LEVEL CUT OFF SWITCH

2 CONTROL
THERMOSTATS HEATER DRUM LAGGING FILTER

1 MASTER
THERMOSTAT

RELIEF

AIR RELEASE

ACCESS DOOR
TO FILTER

SILENCER DRAIN

HEATER
DRAIN

DIRTY OIL (WITH WATER)

DIRTY OIL (WATER FREE)

CLEAN OIL

DRAIN

VACUUM

FIG. 2.65 Oil regeneration plant flow diagram

195
Turbine plant systems Chapter 2

TABLE 2.1
Turbine lubricating oil requirements

Type prefix TO TO TO TO
ISO VG grade designation (BS4231) 32 46 68 100

Viscosity, kinematic at 40C, mm /s (cSt) min 28.8 41.4 61.2 90


max 35.2 50.6 74.8 110
Viscosity index min 70 70 70 70
Flashpoint, closed, C, Pensky-Martens min 168 168 168 168
Pour point, C max -6 -6 -6 -6
Total acidity, mg KOH/g max 0.20 0.20 0.20 0.20
Copper corrosion, classification (3 hours at 100C) max 2 2 2 2
Rust-preventing characteristics rusting rusting rusting rusting
absent absent absent absent
Demulsification number, s max 300 300 360 360
Foaming tendency:
Foam, ml, at 24C max 450 450 600 600
at 93.5C max 50 50 100 100
at 24C after test at 93.5C max 450 450 600 600
Foam stability after 300 s
Foam, ml, at 24C max Nil Nil 100 100
at 93.5C max Nil Nil 25 25
at 24C after test at 93.5C max Nil Nil 100 100
Air release properties, minutes to 0.2% air content at 50C 5 6 7 10
Oxidation characteristics:
Total oxidation products (TOP) with sludge limited to
40% of the determined TOP
No catalyst, % max 0.1 0.1 0.1 0.1
Solid copper catalyst, % duration of tests 164 hours max 1.0 1.0 1.0 1.0
Soluble metal catalysts, 7o max 1.0 1.0 1.0 1.0

The oil pressure used to lift the rotors is around components include:
300 bar and with the use of mineral oil in close prox-
imity to high temperature components, this represents Turbine pedestals/baseplates.
a fire hazard unless special precautions are taken. Steam valve gear pivots.
Older units used a single pump with long pipelines
to feed each bearing and with this arrangement oil
leakage does occur. On modern units, the high pres- Previously, attempts were made to provide automa-
sure pumps are mounted in or on the bearing pedestals tic greasing systems, using a motor-driven multi-
(see Fig 2.66). Details of the pumps used are given piston pump with long pipelines conveying the grease
in Section 6.2 of this chapter. A pressure relief valve to the various components. Unfortunately, separation
is fitted in the discharge line from each pump in order and hardening of the grease constituents in the pipe-
to prevent over pressurisation and overload damage. lines resulted in frequent blockages and inadequate
Jacking oil is also provided to the turning gear journal lubrication.
bearings during start-up and shutdown. Modern plant uses bearings consisting of a sintered-
The pipework systems use Class 1 welded pipe joints bronze matrix, impregnated with PTFE, on a steel
and all the high pressure pipework is contained within backing strip. These bearings are now used under the
the pedestal. Figure 2.67 shows the arrangement used main pedestals and are provided with manual greasing
for the turning-gear jacking oil pump, but is typical of points. The greasing channels are provided with suffi-
these installations. cient area so that the total grease pressure can over-
come the deadweight and allow the grease to spread
over the bearing surfaces. Grease leakage 'tell tales'
are provided so that the effectiveness of the greasing
operation can be checked. In order to prevent the ingress
6.10 Greasing systems of grit and foreign matter, the pedestals are provided
Various components require greasing in operation to with dust shields.
ensure smooth linear or rotational movement between Examples of the greasing points provided on the
components; oil lubrication is not appropriate. These main steam valve gear pivots are shown on Fig 2.68.
196
/ J.O.P. & E.T.G
PREVENT START & TRIP
I PRE
FROM LUBRICATING
OIL SUPPLY AFTER : z^> TO Nos. 11 AND 12 BRGS.
MAIN STRAINERS AND MAIN OIL PUMP BRGS.
' PREVENT START- LOW SUCTION PRESSURE
SAFETY TRIP - FALLING SUCTION PRESSURE APPLIED TO ALL JACKING OIL PUMPS
. AUTO START - SPEED BELOW 30r/min
FROM LUBRICATING fD
OIL SUPPLY AFTER
THRUST BEARING
STRAINER

L
yiR ox
TO TURNING G E A R l j
BEARINGS,SPRAYS I !
& MAIN PUMP !
BEARINGS f * \ ^
JACKING
OIL
PUMP G

P I L OT
EXCITER

v
RETURN TO
MAIN OIL TANK JACKING OIL
LUBRICATING OIL
LUBRICATING AND JACKING OIL RETURN
DRAIN
INSTRUMENT SIGNAL
Fl FLOW INDICATOR
(ZZZl SCROLL BLEED VALVE

FIG. 2.66 Jacking oil system


Lubrication systems

197
Turbine plant systems Chapter 2

PRESSURE RELIEF VALVE


PEDESTAL CASING FULCRUM PIN LINK PIN
FULCRUM PIN
PRESSURE GAUGE

DRIVE MOTOR

LINK PIN
LINK PIN
OUTPUT TO TURNING
GEAR BEARINGS

MOUNTING PLATE
LANTERN RING

SWINGING LINK
TO PRESSURE SWITCH

JACKING OIL PUMP / PRESSURE RELIEF TO DRAINS


LINK PIN
PUMP INLET LINK PIN

FIG. 2.67 Shaft turning gear, jacking oil pump


HP VALVES

FULCRUM PIN FULCRUM PIN


7 Gland sealing system LINK PIN

7.1 Function and system layout LINK PIN

Glands and seals are used on turbines to prevent or


reduce the leakage of steam or air between rotating LINK PIN

and stationary components that have a pressure


difference across them, for example, where the turbine
shaft is extended through the cylinder endwalls to
the atmosphere. When the cylinder pressure is higher
than atmospheric, there will be a general steam leakage
outwards: if the cylinder contains steam below atmos- LINK PIN

pheric pressure, the tendency is for air to leak inwards LINK PIN

and the sealing system is designed to prevent the air


IP VALVES
from entering the cylinder and the condenser.
As most of the steam leakage from glands does not FIG. 2.68 Main and reheat steam valves location
pass through the turbine stages, a loss of power output of grease points
is involved and every effort is made to reduce this
power loss by an efficient arrangement of seals and
glands.
In the more recent larger steam-turbines, the labyrinth of pressure energy; ideally, when the steam enters the
gland is in general use, although the carbon ring gland expansion chamber, the kinetic energy is converted
and the water seal gland may be found in older tur- by turbulence into heat with no recovery of pressure
bines. The labyrinth gland acts as a restrictor to both energy. In practice, as the steam is throttled at suc-
steam and air leakage. cessive restrictions at approximately constant enthalpy
the pressure is progressively reduced.
To ensure that the maximum kinetic energy is con-
7.1.1 Labyrinth glands verted in the expansion chambers, the finned ring and
The labyrinth gland has superseded the carbon ring the shaft are usually stepped as shown in Fig 2.69 (b).
gland on large steam turbines because it can withstand This type of gland can only be used where the axial
higher steam conditions. The labyrinth gland consists differential expansions between the rotor and casing
of a ring with a series of machined fins that form a are small. Stepped labyrinth glands may have an alter-
number of fine annular restrictions, every restriction native arrangement with two or more large diameter
being followed by an expansion chamber. A simple form fins as shown in Fig 2.69 (c). This arrangement is able
of labyrinth seal is shown in Fig 2.69 (a). to accept a larger change in relative axial dimensions
As steam enters the restriction, the velocity in- since, under all conditions, at least two of the three
creases and kinetic energy is developed at the expense fins per pitch form effective restrictions.
198
Gland sealing system

This principle can be extended to a greater number


of large diameter fins, but the number of effective
restrictions per unit of axial length becomes progres-
sively less and it becomes preferable to adopt a simpler
form of seal, such as those shown in Fig 2.69 (a), where
the larger number of restrictions compensate for the
decreased efficiency compared with the stepped gland.
Another design of gland that is independent of
differential expansion is the vernier gland shown in
Fig 2.69 (d). Both the shaft and seal ring are finned,
(a) Plain labyrinth the pitch of the fins being slightly different on the
two seal components. This has the advantage that some
of the fins will always be directly opposite, providing
a greater restriction.
Figure 2.70 (a) shows a form of labyrinth gland with
axial as well as radial fins which increases the number
of restrictions in a given length of gland.
The tip thickness of labyrinth glands is made as
thin as practicable so that if an accidental rub occurs
between the shaft and the gland, the fins will rub away
with little heating of the shaft. A heavy rub would
quickly generate so much heat that the shaft would
bend and become unbalanced.
(b) Stepped labyrinth

(c) Double stepped labyrinth


(a) Axial radial labyrinth

(d) Vernier labyrinth (b) Spring-back labyrinth

FIG. 2.69 Plain, stepped and vernier labyrinth glands FIG. 2.70 Axial radial and spring-back labyrinth glands

199
Turbine plant systems Chapter 2

The radial clearance and diameter of the labyrinth leading steam back to an appropriate stage in the
gland is made as small as possible, since the leakage turbine or to a feedheater after each section. As a
flow through the gland is directly proportional to the result, heat is returned to the cycle.
leakage area. In practice, the minimum radial clear- The arrangement of the final glands section for an
ance adopted is approximately 0.5 mm. To minimise HP cylinder is shown in Fig 2.72 (a).
the effects of a 'rub' with close-clearance glands, The HP leak-off belt is usually connected to the
the gland rings are often spring-loaded as shown in IP/LP crossover pipes and the pressure is thereby
Fig 2.70 (b). The gland rings are usually made up of maintained at the IP exhaust pressure. The pressure at
four or more segments. the packing/leak-off point is usually stabilised slightly
The flow through a labyrinth gland is a function of above atmospheric by the pressure control system.
the initial pressure and temperature, the final pressure The steam bled from this leak-off is normally used to
and the clearance area under the restrictions. As the seal the glands of the LP cylinders; the LP cylinder
mass flow through a series of restrictions is constant, gland arrangement is shown in Fig 2.72 (b). The out-
the velocity of the steam through the successive throt- flowing steam prevents the ingress of air into the
tlings must increase as the steam is expanding; the cylinder and condenser. The final belt in all of the
velocity through the final restriction cannot exceed glands is connected to the gland steam condenser,
the sonic velocity. The pressure ratio across the last which maintains the pressure at the belts slightly below
restriction is then equal to the critical value and if atmospheric. This prevents steam leaking into
the back pressure is further reduced, no increase in the turbine hall by maintaining an inward flow of air
mass flow will occur. Thus for a gland with a given through the outboard gland section.
number of restrictions, there is an associated pressure At low loads, live steam enters the system through
ratio that produces the maximum leakage through a motorised isolating valve and a pressure reducing
the gland. valve to the HP desuperheater. Here the steam is cooled
The gland sealing system is designed to supply to a temperature suitable for the H P / I P glands. It
steam to seal the turbine shaft glands at all operating then passes through a motorised isolating valve to the
conditions and to extract leak-off steam from the H P / I P glands or, via a separate motorised valve, to the
glands. LP desuperheater which further cools the steam to a
temprature suitable for the LP glands.
At higher loads, when the H P / I P glands are self-
7.1.2 System layout sealing, excess steam from these glands flows to the
A typical gland sealing system is shown in Fig. 2.71. LP desuperheater and is used to seal the LP glands.
In order to accommodate the range of temperatures The steam flowing from the H P / I P glands tends to
experienced throughout the turbine, the system is us- increase the pressure in the system. This is sensed by the
ually divided into two parts: one part supplies steam control system (see below) which closes the pressure
to the HP and IP turbine glands and the other to the reducing valve in the live steam supply line. If more steam
LP turbine glands. is available from the H P / I P glands than is required
Two modes of operation are used: one employs to seal the LP glands, the control system opens the
a supply of steam at superheater outlet conditions, dump valve which allows the excess steam to pass to
which is referred to as 'live steam' and is used during an appropriate LP heater.
start-up, shutdown and low load operation. In the To prevent any foreign matter from entering the
other mode, steam leaked off from the HP and IP turbine shaft glands, two strainers are provided, one
turbine is employed to seal the LP glands when the for the H P / L P system and the other for the LP sys-
turbine is operating on-load. The use of H P / I P glands tem, with each strainer positioned after the appropriate
leak-off steam produces a useful thermal gain over desuperheater.
the permanent use of live steam. The changeover from
one source of sealing steam to the other is entirely
automatic.
To ensure that the steam is supplied to the glands
at a suitable temperature, it is cooled by desuper- 7.2 Temperature and pressure control
heaters. An HP desuperheater regulates the tempera-
ture of the steam of the H P / I P glands and an LP
desuperheater regulates the temperature of the steam 7.2.1 Temperature control
to the LP glands. Some systems also employ a third The temperature of the steam supplied to the glands
desuperheater to cool the steam which is bled to an is controlled by two desuperheaters; one for the H P / I P
LP heater during on-load operation. system and the other for the LP system. The waterspray
In order to reduce the loss of energy in external type of desuperheater is generally used although the
glands at the ends of the HP and IP cylinders, and tube and shell type of heat exchanger may be in use
to promote a gradual temperature gradient along a on some smaller units. A typical desuperheater is shown
shaft, it is usual to divide such glands into sections, in Fig 2.73.
200
Gland sealing system

LIVE
STEAM SUPPLY

TEMPERATURE
SIGNAL

' I

STEAM
CONDENSATE AND AIR
OUT

AIR TO CONDENSATE

>
ATMOSPHERE IN

AIR BLOWER GLAND


CONDENSER

TO
CLEAN
DRAIN

FlG. 2.71 Typical gland sealing system

The two types of desuperheater are basically similar trained by this steam jet, atomised and evaporated,
and each consists of a cylindrical steel body, provided thus desuperheating the steam before it is discharged
with a steam outlet branch, which has a cover incor- via the outlet branch.
porating a steam inlet branch with a nozzle bolted An electronic or pneumatic controller is provided
to it. for each of the H P / I P and LP sealing lines which, via
In operation, the steam enters the desuperheater a temperature transmitter, senses the line temperature
through the nozzle plate to form a high velocity jet. and transmits electric signals to the controller mounted
The water being injected through the nozzle is en- near to the desuperheater nozzle.

201
Turbine plant systems Chapter 2

AIR

HP LEAK-OFF
STEAM
PACKING/LEAK-OFF
i Q BLOWER

STEAM

GLAND
CONDENSER

(a) HP final glands

LP CYLINDER
STEAM AND AIR TO
GLAND CONDENSER

(b) LP glands

FIG. 2.72 Final gland arrangements

The desuperheaters require cooling water which heater is compensated by the automatic opening or
is supplied from the reserve feedwater tank through closing of the valve to admit the amount of water
a motorised isolating valve. The water supply is then necessary to maintain the correct outlet steam tem-
controlled by regulating valves. Each valve is ad- perature.
justed by a controller on receipt of a signal from a The steam temperatures are indicated in the con-
sensor in the appropriate desuperheater outlet. Any trol room and locally; high and low temperature
increase or decrease in temperature at the desuper- alarms are included to indicate a fault condition.
202
Gland sealing system

COVER PLATE

DISTANCE PIECE
NOZZLE
STEAM CHAMBER
NOZZLE PLATE

STEAM
INLET

STEAM
' OUTLET

BAFFLE TUBE

SKIRT

BOTTOM DOOR

EROSION PLATE DRAIN

FIG. 2.73 Gland steam desuperheater

There are drain connections on the desuperheaters glands progressively reduces and eventually reverses,
which allow drainage to pass to the clean drains tank as leak-off steam becomes available. Consequently,
via an isolating valve, a strainer and a drain trap. the rise in pressure at the glands causes the live steam
pressure regulating valve to close progressively, thus
7.2.2 Pressure control maintaining a constant supply pressure at the glands
During start-up and shutdown, when live steam is and eventually closing completely. The LP glands are
used, the pressure at the glands is controlled by the now sealed by steam leaking from the HP and IP
pressure reducing valve in the live steam supply line. glands, and the pressure at the glands is controlled by
As load increases, the steam flow to the HP/IP a leak-off valve which dumps steam to an LP heater.
203
Turbine plant systems Chapter 2

This arrangement ensures that only one regulat- circulated through the U-tubes to condense the steam.
ing valve is in control at any one time and that the When the gland steam condenser is out of service,
changeover from live steam to leak-off steam is fully steam is prevented from escaping into the turbine hall
automatic. by operating the vent fans.
The steam pressure in the sealing line is indicated
in the control room and locally; a fault condition is
indicated by low pressure alarms.
8 Flange heating system

7.3 Gland steam condenser


8.1 Function and system layout
The function of the gland steam condenser is to main-
tain a sub-atmospheric pressure at the outermost leak- The cylinder casings of the turbine each consist of
off belt of the glands and thereby prevent the leakage top and bottom halves; the top halves may be lifted
of steam from the glands into the turbine hall, where clear for inspection and maintenance. The two halves
it would condense on the walls and plant. of each casing are bolted together at the horizontal
flange (see Fig 2.75).
The condenser is vented to the atmosphere via a
During turbine starting, the relatively thin walls of
blower. The small vacuum created by the blower is
the HP and IP casings tend to heat up more rapidly
sufficient to draw air into the glands where it mixes
than the large masses of metal in the horizontal joint
with steam leaking from the cylinder; the air is se-
flanges. The function of the flange heating system is
parated in the gland condenser and passed back to the
to provide steam heating (at appropriate conditions)
atmosphere via the vent fans. The steam is condensed
to the HP and IP outer cylinder flanges, thereby re-
and the condensate passes to the main condenser. A
ducing the difference in temperature between each of
typical gland steam condenser is shown in Fig 2.74.
the cylinder casings and their associated flanges and
The condenser typically consists of a steel shell
bolts. This prevents excessive thermal stressing and
closed by a dished-end waterbox cover incorporating a
cylinder distortions.
tubeplate into which are expanded U-tubes. Cooling
There are two flange heating systems, one supplying
water, provided by local river water or seawater, is
the HP and the other supplying the IP. Although they
are completely separate systems, both are similar in
function and layout and a typical flange heating system
is shown in Fig 2.76.
WATER
WATER
The flanges on the HP cylinder are supplied with
steam from after the HP governing valves and the
IP flanges are supplied with steam from after the IP
governing valves.
Each cylinder flange heating supply line is provided
with an isolating valve, a preset regulating valve or
orifice and a permanent drain controlled by an orifice

FLANGE

VACUUM
CONNECTION

TO DRAIN

FIG. 2.74 Gland steam condenser FlG. 2.75 Turbine half-casings joined at horizontal flanges

204
Flange heating system

STEAM SUPPLY
TO FLANGES

STEAM DISCHARGE
FROM FLANGES

DRAINS

CONTROL SIGNAL

STRAIGHT BORE ORIFICE

DIRT TRAP
CONDENSER
FLASH

TEMPERATURE INDICATOR
BOX

PRESSURE TRANSMITTER

FIG. 2.76 Typical HP and IP turbine flange heating system

plate. The drain incorporates a dirt trap which pre- valves. Each cylinder flange heating system then op-
vents a blockage of the hole in the orifice plate. Each erates automatically and no further action should be
supply line separates into two, feeding the right-hand required until the system is shut down by reclosing the
flange and the left-hand flange. motorised isolating valves. The system may be shut
Between adjacent flange bolt holes, there are al- down when a load of 40% or more has been reached
ternate top and bottom cross-drillings which provide or, alternatively, when the cylinder barrel and flanges
passages enabling the hot steam to flow freely through are heated to about 250C.
the flange. This is shown diagrammatically in Fig 2.77. The flow of steam is controlled by preset regulat-
The heating steam enters and leaves the flanges at ing valves and orifices. These valves, in each cylinder
several points by way of drillings from the flange outer supply line, are sized in conjunction with their corre-
surface into the bolt holes, the inlets and exits being sponding flange outlet orifice plates to give maximum
suitably spaced to give even heating throughout the pressure in the flanges. This pressure is approximately
flanges. The annular spaces between the bolts and equal to the pressures on the inner surface of the re-
holes are swept throughout their length by the hot spective outer cylinder under full-load conditions. As
steam, thus preventing the accumulation of water in each cylinder flange heating supply is taken from after
the recesses. the governing valves, any change in the cylinder inlet
Steam leaves each flange from outlet pipes which steam pressure has a corresponding effect on both
converge into one pipe, fitted with a flow regulating flange and cylinder steam pressures. As a result, rapid
orifice. heating due to condensation heating is maintained at
Subsequently, the combined flows from each side the same relative levels, thus enabling the difference
of the turbine are joined and led either to a suitable in temperature between the casing and the flange to
feed water heater or to a drains receiver. be maintained within acceptable limits.
Suitable steam distribution is achieved using bal-
ancing orifices installed and set during commissioning.
Once the correct orifice size has been determined, it
8.2 Control remains unaltered.
The HP and IP flange heating systems are brought With the system as described above, the flange
into operation by the remote manual opening, from heating steam temperature is always higher than that
the central control room, of the motorised isolating of the steam within the cylinder casing. In some de-
205
Turbine plant systems Chapter 2

TOP OUTER CASING

STEAM OUTLET

STEAM OUTLET

FIG. 2.77 Steam flow through flanges

signs, however, the steam supply is taken from inside the possibility of excessive casing distortion. This is
the relevant casing and hence its temperature is always done by spraying cooling water into the exhaust space,
equal to that of the steam within the casing. whenever necessary, downstream of the exhaust guide
vanes. The exhaust steam is cooled and then recir-
culated to cool the casing. A typical LP exhaust cooling
system is shown in Fig 2.78.
9 LP exhaust spray cooling system During normal running of the turbine, the conden-
sate extraction pump supplies the spraywater to the
system. The condensate supply, before reaching the
spray nozzles in each end of the LP turbine cylinder
9.1 Function and system layout exhaust, normally passes through a manual isolating
During the low-load running of a turbine-generator valve, a pressure reducing valve, a strainer to remove
unit, the volume of steam flowing through the last row dirt particles, a flow indicating switch (measuring water
of the LP turbine blades is reduced considerably and flow to sprays) and a pneumatic flow control valve,
the smooth aerodynamic flow of steam through these with manual inlet and outlet isolating valves. A pres-
blades is lost. The LP exhaust steam is recirculated sure switch is usually fitted across the strainer to mea-
and, as a result, energy is transferred from the blades sure any difference in pressure, thus indicating whether
to the steam, resulting in a significant temperature rise blocking has occurred. A by-pass, with a manual iso-
of the circulating steam. In addition, if the condenser lating valve, is usually provided round the spray control
back pressure is high, a smaller volume of steam will valve and its associated isolating valves.
flow through the system, causing a significant worsen- An emergency spraywater pump driven from a DC
ing of the situation. protected power supply will cut in automatically in
The excessive temperature rise caused by these ef- the event of a failure of the normal spraywater sup-
fects can result in an undesirable restriction on the ply. The emergency pump draws its water from an
length of time that the turbine can run with no load, auxiliary water tank and discharges into the spray-
and possible uneven heating of the exhaust casings water line upstream of the strainer. The emergency
leading to serious distortion and adverse effects on supply line normally contains a manual isolating valve,
turbine alignment. an emergency spraywater pump and a self-activated
The LP spray cooling system is provided to ensure isolating valve.
that exhaust temperatures under these conditions are Each LP turbine exhaust flow incorporates a split
maintained within defined limits, thereby minimising ring of spray nozzles, the ring being located outboard
206
LP exhaust spray cooling system

TEMPERATURE
CONTROLLER
H
DIFFERENTIAL
PRESSURE SWITCH
SPRAY
I CONTROL VALVE
V,
FROM CONDENSATE
EXTRACTION PUMP

L J
MANUAL
FROM AN AUXILIARY BYPASS
WATER TANK

EMERGENCY SPRAY
WATER PUMP

FIG. 2.78 LP exhaust spray cooling system

of the exhaust guide vanes. Initially, a number of these keep the LP exhaust steam temperature within accep-
nozzles may be blanked off, to be used as additional table operational limits during no-load or light load
spray nozzles if extra spraywater is found to be ne- operation. A temperature detector, incorporating
cessary during the subsequent running of the turbine. thermocouples, is situated in one exhaust flow of each
The arrangement of the spraywater nozzles is shown LP cylinder and this measures the exhaust temperature.
in Fig 2.79. In operation, a signal is passed to the temperature
Each nozzle is designed to provide a spray of atomis- controller, via an amplitude selector (this ensures that
ed particles which will evaporate quickly, thus promoting the LP exhaust with the highest temperature is selected),
rapid cooling of the exhaust steam. which operates the spraywater control valve.
Suitable safety measures are built into the system to When any individual sensing element detects a pre-
correctly maintain spraywater supplies so that an effec- set low exhaust steam temperature, the controller will
tive atomised spray is available when required. This is open the spray control valve to pass a minimum quan-
normally achieved by installing an automatic valve in tity of water. Further increases in temperature will
the supply system to ensure that the spraywater flow is allow proportionally-greater quantities of water, rising
above a set minimum level. This valve is arranged to to a maximum water flow at a preset high exhaust
open or close rapidly near this minimum set point. The steam temperature.
minimum flow requirement may result in a slow cycle The temperature detectors can have an inherent
of valve opening and closing during low load, but this time lag and, under certain circumstances, an overriding
is acceptable. control is necessary to produce a two-minute burst of
A temperature detector is located in the path of the spraywater at maximum flow.
exhaust steam downstream of the spray nozzles to In the event of the condensate extraction pumps
provide the signal for the automatic start and control failing, the emergency spraywater pump is brought
of the spraywater quantity. into operation automatically, provided that the turbine
gland steam isolating valve is open. This condition is
detected by a limit switch situated on the isolating
valve. Loss of supply from the extraction pumps is
9.2 Control indicated by a pressure switch located on the supply
An automatic temperature control system is fitted to line from the pumps, which is able to detect low water
207
Turbine plant systems Chapter 2

NOZZLE ADAPTOR

EXHAUST COVER

SPRAY WATER FEED


TO OTHER EXHAUST END EXHAUST BOTTOM
SPRAY WATER FEED FROM
EXTRACTION PUMP DISCHARGE 11

FIG. 2.79 Arrangement of spraywater nozzles

208
Drains systems

pressure. The emergency pump continues to run until which collects during start-up. The drains may incor-
stopped by the operator. porate master and martyr valves in series. The master
Should the automatic system fail, a manually-operated valve, located upstream, is normally open, but can
by-pass is provided round the spray control valve to be closed manually when isolation is required. The
enable the operator to maintain the spraywater supply martyr valve is motorised and, during normal operat-
to LP exhausts. This valve is normally closed. ing conditions, provides adequate control for the
The pressure reducing valve in the line from the start-up drains. In some systems, the martyr valves are
condensate pumps is set during initial commissioning replaced by an orifice plate and the master valve is
of the system to give the required pressure at the closed either automatically or manually when the
spray valve inlet (while it is open). Once set, it should machine is on load. On other systems, steam traps are
not require any further adjustment. used in place of the martyr valves, but these are
The emergency pump discharge isolating valve is not favoured in high pressure areas.
activated by the upstream pressure and is arranged so
that it remains closed against the static head of the
feedwater tank, but opens when subjected to the emer- 10.1.2 Continuous drains
gency pump discharge head. This feature automatically In regimes such as the LP cylinder, where the steam
prevents the condensate storage tank draining via the is wet during normal operation, drain lines are ne-
sprays during shutdown. cessary to provide continuous drainage. Such lines
If the steam temperature in any of the exhausts reaches have orifice plates to restrict the flow. In places where
a predetermined level, an alarm is given. If the exhaust there is likely to be a large collection of condensate
temperature exceeds this level or the load falls below a during start-up, the line incorporates a valved by-pass
certain value, a turbine trip will be initiated. These levels in addition to the orifice.
are determined by the turbine manufacturers. All clean drain lines lead to the drains receivers,
located near the condenser. On entering this vessel
some of the drains water flashes into steam which
is vented to the main condenser. Sometimes the vents
10 Drains systems are fitted with desuperheating sprays. The coolant for
the spray is supplied by the condensate extraction
pump and a temperature sensor regulates the amount
of water supplied to the sprays.
10.1 Function and system layout The remaining condensate drains to the bottom of
During the start-up period of a turbine, the steam
the condenser. On some units, pumps are required to
coming into contact with cooler metals results in the
lift the condensate from the drains receiver to the
formation of condensate within the turbine cylinders,
condenser. A sight glass gives local indication of the
the steam piping and the valve chests. This condensate
level in the drains vessel.
must be removed before the turbine can be run-up fully,
to prevent a loss of efficiency and possible damage to
the turbine. Condensation occurs mostly during a cold
start, but also forms during normal operation when a 10.2 Control
change in load or steam conditions results in a dif- The flow of drains water in those drains which are
ference between steam and metal temperatures. The normally closed during operation of the plant, is usu-
drains system provides an outlet for the condensate, ally controlled by the master and martyr valves. At
whilst minimising leakage of steam from the turbine start-up, the master valve opens first followed by the
processes. A typical drains system is shown diagram- martyr valve. In this way, possible deterioration of
matically in Fig 2.80. the valve seals from throttling the drains water is con-
Each drain line is taken from the lowest point of fined to the martyr valve. The master valve is then always
the associated pipe system, where condensate is likely able to provide tight isolation.
to collect, and the clean drains are led into the drains Each drain line is provided with a pressure gauge
receivers where the water is eventually routed to the (calibrated to show saturation temperature) at the drain
condenser. source and a temperature gauge. At a temperature of
To prevent loose pipe-scale and other foreign matter approximately 30C above the saturation temperature
from blocking the drains, each drain is provided with corresponding to the line pressure, it is reasonable to
a dirt trap. Dirty water drains are led to the station assume that only dry steam will be passing through
drains. Drains are classified as being either start-up or the drains and the motorised martyr valves can be
continuous. closed. Alternatively, the valve can be closed automa-
tically from a load or temperature signal. The master
and martyr valves are usually opened after shutdown
10.1.1 Start-up drains or there may be provision for automatic opening when
Drain lines are provided to dispose of the condensate the load falls below a value of say 10%.

209
Turbine plant systems Chapter 2

HP STEAM IP STEAM
HP STEAM CHEST CHEST CHEST IP STEAM CHEST
(LH) (RH)

CONDENSER
CONDENSER

TEMPERATURE TEMPERATURE
INDICATOR INDICATOR

CONDENSATE
SUPPLY

FIG. 2.80 Typical turbine HP drains system

When the drain valves are shut during on-load op- valve seat is activated by a bimetallic element which,
eration, a column of water will collect in the drain on a rise in temperature, deflects against the line
line above the valve due to cooling of the stagnant steam pressure and closes the valve. The force of the ball
in the pipe. If a turbine trip is initiated or rapid unloading valve increases in relation to the steam temperature
occurs, the pressure in the turbine decreases and this and pressure.
water tends to reflux into the plant: this could cause The trap usually discharges water after a certain
unacceptable chilling of the plant components or pipes. amount has collected. The trap then closes and is
To minimise this refluxing, the martyr valves are ready for refilling. However, some traps are able to
sometimes replaced by an orifice plate which provides differentiate between steam and condensate by sensors
a permanent opening for the condensate to escape. The which can detect a temperature drop in the conden-
small diameter of the orifice allows an adequate flow sate. These traps are set so that only condensate, air
of water but limits steam flow. or wet steam will pass through to the drains vessel.
In other cases, the valves are opened automatically As soon as steam at saturation temperature (or above)
on reducing load or steam traps are used in place enters the trap, the ball valve is held tightly on its
of the martyr valves. The steam trap is designed to seat, thus preventing the escape of live steam to the
allow water to escape, but not steam. There are various drains vessel. The controlling temperature can be
types of trap such as ball float, inverted-bucket and constant, or can be varied depending on conditions in
thermostatic traps. The traps are similar in operation the steam system.
and construction, although detailed differences are Most steam trap installations incorporate a by-pass,
needed to meet the various operating conditions. so that the traps can be isolated for inspection and
As an example, the thermostatic trap consists of maintenance. This by-pass permits the blowdown of
a forged-steel body with a removable cover. Inlet debris or contaminated condensate during commis-
and outlet ports are divided by a vertical wall. A sioning or subsequent run-ups, and prevents undue
ball valve situated on the downstream side of the contamination of the trap strainer.
210
By-pass systems

11 By-pass systems
IDEAL ADIABATIC FLOW
WITH FRICTION
11.1 Configuration
By-pass systems provide facilities to redirect steam from
entry to the turbine. There are several reasons why
this may be needed and they differ, depending upon
whether the plant is fossil-fired or nuclear. The one
common reason (and possibly the most important) is
when there is a large loss of turbine load. For a more
detailed discussion of the reasons for by-pass systems
refer to Chapter 1.
Though nuclear and fossil-fired by-pass systems
differ somewhat in design, their fundamental modes
of operation are similar. They both redirect steam from
the turbine inlet and pass it to the condenser via a series
of isolating valves, pressure control valves and dump
tubes.
CONVENTIONAL
SINGLE ORIFICE
VALVE
11.1.1 Pressure control valves
These valves are designed to greatly reduce the pressure
of the hot steam so that its conditions correspond
better to those inside the condenser.
The simplest way of creating a large pressure drop
across a valve is by the conversion of heat energy to
velocity (kinetic energy) by passing the steam through
a small orifice. Downstream from the orifice, tur- FIG. 2.81 Pressure control valve characteristics
bulence accompanied by shock waves reconverts the
velocity into heat energy. The change in energy for a
conventional single-orifice valve is shown in Fig 2.81.
Although this is a satisfactory means of creating a
pressure drop, the shock waves created produce a large
amount of undesirable throttling noise. Consequently,
valves have been developed that produce the same
pressure drop but with considerably less noise, Fig 2.82
shows a typical example. In such a valve, the reduc-
tion in pressure is obtained through the principle of
'adiabatic flow with friction'. Steam is passed through
a number of restrictions called a disc stack. The stack
provides a complicated flow path which results in the
dissipation of energy through a high loss of head rather
than through Shockwaves (Fig 2.81). The flow area
inside the stack is gradually increased towards the DISC STACK
downstream end. This helps maintain an almost con- AND TRIM ASSEMBLY

stant steam velocity over the expansion caused by the


pressure drop. Generally, these valves are capable of
going from fully-closed to fully-open within three FlG. 2.82 Pressure control valve
seconds and from fully-open to fully-closed in five
seconds.

Isolating valves are not required to create a large


11.1.2 Isolating valves pressure drop and their design is simpler than that of
These valves are usually situated either side of a the pressure control valve. A typical isolating valve is
pressure control valve for two reasons. First, to en- shown in Fig 2.83. The valve is a parallel-slide type,
sure the total isolation of the control valve if it so called because it does not rely on a wedge action.
requires maintenance whilst the turbine is running; Instead, the discs slide over the seat faces when the
second, to provide a back-up should the control valve valve is being opened or closed, resulting in a minimum
fail. pressure drop.

211
Turbine plant systems Chapter 2

the tube section diverges here to accommodate the


associated expansion of the steam. The steam then
enters a spray-water section where it is desuperheated.
Several water-jet entry ports circumscribe this section
through which spray water is injected. The spray water
is taken from the condensate extraction pump discharge
and enters the dump tube via its own set of isolation
and control valves. The steam at the reduced pressure
and temperature leaves the dump tube through a sec-
tion known as the dispenser.

11.2 By-pass systems for nuclear plant


A by-pass system is important in a nuclear plant for
the following reasons:

Sudden large load rejection can be accepted without


incurring a reactor trip or actuation of the steam
generator safety valves. (The reactor control system
will accommodate either a sudden load rejection of
10% of full-load or a gradual rejection of 5% per
minute. Load rejection beyond these figures results
in the need for system by-pass.)

Stored energy and residual heat can be removed


following a turbine or reactor trip. This will bring
the plant to no-load conditions without the actua-
tion of the steam generator safety valves.
The plant can be maintained at hot standby con-
ditions.
Manually-controlled cooldown of the plant can be
achieved to the point when the Residual heat removal
system' can be operated.

Figure 2.85 shows the arrangement of the by-pass


DISC SPRING system for a nuclear plant.
The by-pass consists of a steam line that begins
FlG. 2.83 Typical isolating valve
at the main steam manifold and has three pairs of
lines branching off it to the three condenser shells
via the isolation/control/isolation valve arrangement
and the dump tubes. For each pair of lines, one line
The isolating valve downstream from the pressure is designated 'Bank and is used in a modulating mode
control valve has a back-seating arrangement on the so that the required conditions can be regulated. The
spindle to prevent the ingress of air to the condenser other line is designated 'Bank 2' and is either open or
under normal running conditions. closed.
There is another bank on a separate line from the
manifold (not shown in Fig 2.85) which exhausts di-
11.1.3 Dump tube rectly to atmosphere. This 'Bank 3' is used when there
The dump tube is the final section of a by-pass system, is a large loss in load or a reactor trip. Once steam
where the steam is passed into the condenser at the temperature has reduced sufficiently (usually after a few
correct pressure and temperature. Figure 2.84 shows minutes), the 'Bank 3' valves are closed.
an example. The by-pass pressure control valves may be operated
Steam enters at the narrow section after leaving the either pneumatically or hydraulically; but a pneu-
pressure control valve. It passes through a number of matically-controlled system will be discussed here.
plates (five or six) each containing a number of orifices. When load is rejected, a load rejection controller
These plates further reduce the steam pressure and opens all the by-pass valves (Banks 1, 2 and 3) se-
212
By-pass systems

STEAM EXHAUSTS

ORIFICE PLATES

^..^3 ~5 M I I I I I I I I I I/JCT
(
I J

7SSS S /T

STEAM V\
ENTRY '

U
V ^ " " " T-r-r-rH-rr- TTTI I I I I I I I I I I

DESUPERHEATER
INLET PORTS

1
' ' ' ' ' ' ' '
FIG. 2.84 Dump tube

quentially in about three seconds. The controller re- supply, the pressure control valves will fail-closed. The
ceives a signal obtained from the difference between spraywater control valves, however, remain fixed in
the actual and the programmed reactor-coolant tem- their last held position and control is regained by using
perature. The controller subsequently closes the valves remote manual operation. The pressure control valves
when load is regained. will also fail closed when the condenser pressure is too
The plant trip controller opens a proportion of the high. The by-pass system carries alarms to warn of low
pressure control valve when the reactor trips and spraywater pressure and high dump tube steam
subsequently reduces the opening to suit the reactor decay temperature.
heat generation. The controller receives a signal ob-
tained from the difference between the actual pri-
mary average temperature and the no-load primary
temperature. 11.3 By-pass systems for fossil-fired plant
The steam header controller operates the first valve The importance of system by-pass in fossil-fired plant
bank of pressure control valves in two different modes is as follows:
of operation, depending upon whether the plant is
required to be on hot standby or cooldown. In the first After large load decreases, the turbine can still run
mode, the <Bank valves are modulated to maintain at the much reduced load while the boiler conditions
a constant steam header pressure. This enables the can be maintained. This permits rapid restarting when
plant to be automatically maintained at the hot shut- load is restored.
down condition. It is also used to maintain steady
conditions while the turbine-generator is being syn- The required steam conditions can be established
chronised. In the second mode, the operator controls the when initially starting the boiler.
signal to the valve directly. This permits the operator
to open the 'Bank valves progressively to cool the Steam flow is provided through the reheater circuit
plant down. during start-up but before steam is admitted to the
turbine.
Each of the spraywater control valves opens to
deliver a preset minimum flow whenever its associated
steam by-pass control valve is not closed. Thereafter The by-pass scheme comprises two systems an HP
the spraywater flow is arranged to be directly pro- system and an LP system. A schematic representation
portional to the steam pressure measured in the dump of the HP system can be seen in Fig 2.86.
tube, after the control valve downstream isolating The HP steam is taken from each of the main
valve and before the first orifice plate. As the flow steam lines after the main steam stop valves. The steam
through the dump tube is critical, the spraywater passes into the cold reheat inlet via four pressure
flow is proportional to the steam flow. control valves and their associated isolating valves.
In the event of a loss in electrical power or air The correct temperature to the cold reheat is achieved
213
Turbine plant systems Chapter 2

SIDE VIEW

TURBINE EXHAUST HOOD STEAM


BUSMAIN

I1 i i <j>
ISOLATING
VALVE
J LU
DRAIN I

DRAINS ^
(Ml ^-DRAINS
M ^DRAINS-^^
BANK 1 BANK 2 BANK 1 BANK 2
BANK 1 BANK 2

CONDENSER 1 CONDENSER 2 CONDENSER 3

END VIEW

FIG. 2.85 By-pass configuration for a nuclear plant

214
By-pass systems

MAIN STEAM
FROM BOILER

MAIN STEAM
COLD REHEAT FROM BOILER
TO BOILER

COLD REHEAT
TO BOILER

BYPASS PIPING
WARMING PIPING

FIG. 2.86 HP by-pass system for fossil-fired plant

through the employment of desuperheater spray water. If condenser pressure is too high.
The spraywater supply to the pressure control valve is
taken from the main feed pumps and has its own set Unlike the nuclear by-pass system, the pressure control
of pressure control and isolating valves. The presence valves will fail locked in their last-held position if
of warming piping and drains in Fig 2.86 will be dis- there is a loss in electrical power. The spraywater
cussed later in this section. pressure control valves also fail locked in their last-
During start-up the pressure control valves are held position.
opened manually until the valves are more than 10% The LP by-pass system consists of four lines taken
open, at which point the system is controlled auto- from the four hot reheat pipes (upstream of the IP
matically. When the boiler steam pressure reaches a turbine control valves). These four lines are then con-
specified value, the by-pass system automatically keeps verged into two. The steam in each line flows through
the boiler at that value. In the event of a turbine trip, an isolating valve, a pressure control valve and then
a signal is sent to the control valves to open rapidly. into the condenser dump tube. The LP by-pass system,
Alternatively, in order to protect the cold reheat piping therefore, is very similar to the by-pass system on a
system, the pressure control valves can be ordered to nuclear plant: it behaves in the same way as the HP
close rapidly under the following conditions: system, the pressure control valves opening or closing
under exactly the same circumstances.
When the spraywater pressure is low.
If any spraywater valve fails to open within three
seconds of its associated pressure control valve. 11.4 Problems with by-pass systems
The presence of by-pass systems, as has been seen,
If the steam entering the cold reheat pipes is at too
high a temperature. can greatly benefit the plant. Their addition, however,
does result in a few problems such as noise, water
If the pressure in the cold reheat system is too high. ingress and thermal shock.
215
Turbine plant systems Chapter 2

11.4.1 Noise on the control valves that exit to atmosphere (Bank 3


It was discussed earlier how large pressure drops across on nuclear plant) by including a silencer.
valves induce considerable noise. Figure 2.87 shows
how the proportion of energy loss converted to noise
(acoustic efficiency) increases with the size in pressure 11.4.2 Water ingress
drop. This effect is reduced dramatically by using valves With the pressure control valves shut, a large build-up
that employ adiabatic flow with friction, as discussed of condensation will occur in the steam lines. If this
earlier. Noise can be reduced further by increasing the condensation were allowed to remain, water would be
thickness of the downstream piping and covering it passed through the system when the valves are opened,
with acoustic insulation. Figure 2.88 shows the ratios resulting in damage to the valves and condenser. To
of pipe thickness to pipe length used to create further avoid this build-up, drains are located at strategic posi-
noise attenuation. Even more attenuation is achieved tions, for example, in the busmain and upstream of
each control valve shown in Fig 2.85. Drains are also
present on the HP system of the fossil-fired plant shown
10-
in Fig 2.86 to prevent ingress of water from the
spray water system.

3
5x10
11.4.3 Thermal shock
c, = 0.6 The drain lines at the upstream section of the control
\
\ valves serve a dual function. As well as maintaining the
C, = 1.0 pipework free from water, they also maintain the valve
c,= 0.7 bodies at a temperature which will avoid any large ther-
\ mal shock to the valves when the by-pass comes into
10 3 - Iff/ / operation.
9- /
8- /,
7- IIi ^ C, = ( .9
6-
5x 10 4 -
1
mi /7/ 11.4.4 Leakage flows
An almost inevitable problem with by-pass systems, as

1
with most steam systems, is leakage flows. Leaks from
4-

3- H valves reduce the efficiency of the plant, so valves are


\ :0.8 designed to be as secure from leaks as possible. During
the life of the plant, leaks are likely to occur, but are
kept in check with regular maintenance. Taking all these
considerations into account ensures a safe, efficient
[/ and reliable system which provides flexibility between
I/ the boiler/reactor and turbine conditions.
5x 10"5
3 4 5 6 7 8 910 15 20

P1/P2
12 Operational flexibility

12.1 Typical operational regimes


FIG. 2.87 Acoustical efficiency characteristics
Power station output, and therefore generation, needs
to be regulated constantly to match consumer demands.
Economics demand that the base load should be pro-
FLOW
vided by the most efficient plant, which mainly includes
nuclear and large-capacity coalfield-sited coal-fired sta-
tions. More expensive, or less efficient, generating plant
(small-capacity coal and oil-burning stations) are
therefore needed to vary output to match demand. The
^= iA -> plant that is required to run intermittently to match
demand operates what is known as a two-shift regime,
10 D, so called because of the requirement to run during the
two daytime shifts but to shut down during the night
shift. Such plant may also be called upon to shut down
over the weekend. It is now common for 500 MW and
FIG. 2.88 Ideal pipe dimensions 660 MW machines to carry out two-shifting operations
216
Operational flexibility

in addition to load-following cycles. This requirement unnecessarily. Steam conditions at the stop valves
for improved flexibility has resulted in all 500 MW and should allow for the temperature drop due to throt-
660 MW turbine-generator units on the UK system tling at steam admission to the turbine (see Section
being designed to be capable of operating a two-shifting 1.3 of this chapter). It is particularly important when
regime, in addition to the requirement for high effi- carrying out hot starts, that the rate of run-up to
ciency base-load operation during early life. Typical speed and initial block loading is sufficient to prevent
operational requirements for modern high merit tur- a reduction in turbine temperature. The range of tem-
bine plant are shown in Table 2.2. perature cycling should be controlled as far as possible
to minimise the risk of thermal fatigue.
Figures 2.91 and 2.92 show typical run-up curves
TABLE 2.2
for a warm start (after a weekend shutdown) and a
Typical operational requirements hot start (after an overnight shutdown) respectively.
The rapid loading shown during the hot start indicates
Description Definition Required cycles
the importance of maintaining a steady rate of rise
Hot starts Approx 6 hours shutdown of temperature. Run-up procedures must be adhered
(Two-shifting) with run-up to full-load 5000 to in order to minimise cyclic thermal stresses in the
in 30 minutes turbine and thus prevent thermal fatigue problems
Warm starts 24-72 hours shutdown 1000 during the life of the turbine.
Cold starts Starts following > 120 hours 200
prolonged shutdown
12.1.3 Load cycling
Load-following Changes of load in 50-100% 4000
The amount of load cycling that a turbine is expected
load range. Assuming
minimum of 3 hours between to carry out (i.e., defined as cycling between 50%
cycles. and 100% load) needs to be controlled. In addition
to specifying the number of load-following cycles
required during the life of the plant, the time taken
to carry out load changes should be such as to mini-
12.1.1 Base load mise cyclic thermal stress. This means avoiding rapid
Under normal conditions, all high merit plant would be cooling or heating of the turbine when inlet steam
expected to operate in a base load regime. This involves throttling is applied or removed to achieve the desired
long periods of continuous operation, with infrequent load change.
'down times' to facilitate statutory testing, inspection
and overhaul/maintenance periods. Base load units
do not normally accumulate a high number of hot or 12.2 Influence on machine design
warm start cycles or load-following cycles. Figure 2.89 The need for flexibility has brought with it inherent
shows typical run-up curves for a cold start on a problems which have needed to be redressed at the
660 MW turbine-generator. In this particular example, design stage of the turbine, with the knowledge of
full-load is achieved after nearly six hours, excluding future operational requirements. The main problem
the time taken to achieve satisfactory steam conditions is the effect of thermal cycling with respect to thermal
at the turbine stop valves. This long run-up time is fatigue damage. The flexible mode of operation in-
not only to limit differential expansion rates and rotor volves some degree of temperature cycling of com-
eccentricities, but also to limit thermal stresses within ponents, leading to strain cycling of material in the
the turbine. critical regions. The damaging cumulative effects of
thermal cycling (i.e., stress-strain cycling) must be
assessed over the turbine life to ensure that sufficient
12.1.2 Two-shifting margin exists in the design for the effects of steady state
One of the most important factors when considering creep.
two-shifting operation is to keep the turbine tempera- Figure 2.93 shows a typical stress-strain cycle as
tures as high as possible during shutdown. This means experienced by the surface of a large HP rotor. The
that the machine needs to be deloaded as rapidly as cycle shows the effects of two-shifting using a typical
possible. Figure 2.90 shows typical shutdown curves 'warm' start where the temperature gradients cause
for a 660 MW turbine-generator, in which the machine thermal strain. On heating with steam at 565C, the
is shut down within 20 minutes, with the last 50% surface attempts to expand but is compressed by
of load being shed in approximately 2 minutes. Main- restraint from the underlying material. This compres-
taining the turbine temperatures in such a way ensures sion, represented by line A-B in the figure, may cause
a faster run-up and reduces thermal cycling of the the surface to go into compressive yield, represented
turbine components. When starting, it is important to by line B-C, in areas of high stress concentration.
ensure that the steam inlet temperature is matched to Subsequent heating and expansion of the underlying
the metal temperatures to avoid cooling the turbine material then causes tensile stressing of the surface
217
Turbine plant systems Chapter 2

400

o
2
<

700 -i

3000

O 1500-

480

FlG. 2.89 Typical 660 MW turbine-generator run-up curves for a cold start from 15C metal temperature

218
Operational flexibility

STOP VALVE

100-1

0-1-

o
<
o
200

TIME, min

FIG. 2.90 Typical 660 MW turbine-generator shutdown curves

219
Turbine plant systems Chapter 2

170 --

150 H

3 450-^

50 H

3000-r

Q 1500 H

TIME, min

FlG. 2.91 Typical 660 MW turbine-generator run-up curves for a warm start

220
Operational flexibility

o
5<H

0 -L

3000-p

E
Q 1500

TIME, min

FIG. 2.92 Typical 660 MW turbine-generator run-up curves for a hot start

221
Turbine plant systems Chapter 2

eration has influenced the design of turbines in several


areas.

il
STRESS,tf
i

A
12.2.1 Turbine cylinders
450C
Probably the most significant change in turbine design
has been the adoption of multishell cylinders. The
565 C
advantage of this type of construction is that pressure

f\
1i
difference and temperature gradients across each shell
is reduced compared with single-shell construction. It is
STRESS
RELAXATION
now normal practice in one form or another, in high
temperature machines, for HP and most IP cylinders,
and is usual for most LP cylinders. Low pressure
'
/1
1 \ E

cylinders sometimes have a larger temperature range


f
56 5 C

from inlet to exhaust than any other cylinder, and the


inner casing may itself be of double-shell construction
STRAIN X
to reduce thermal stresses and distortion. As ratings
have increased, component size has increased and with
it the problem of transient temperature gradients within
B a component and thus thermal stress. The use of
multishell cylinders has allowed temperature distribution
and gradients to be controlled, thus minimising cyclic
I '1 thermal stresses. In addition, this design allows the heavy
c Jf
flanges which were necessary on single-shell designs to
_ 1 _ be reduced in size. In some cases, the use of one-piece
1^ " 1 " shells, with no horizontal split, obviates the need for
1 " flanges, thus removing the problem of axial thermal
stresses due to uneven heating of flanges and cylinder
walls. The use of flange heating has also contributed to
SHUTDOWN 565-450 C
matching the rate-of-rise of temperature of the flanges
STEADY RUNNING 565 C
and cylinders more closely.
START-UP 450-565 C
The adoption of multishell casings and the separation
of steam chests from the turbine cylinder, has allowed
FiG. 2.93 Typical stress-strain loop for two-shifting a
large, high temperature rotor
simplification of the geometry of each component. This
means that the design has fewer changes in section and
more attention is paid to radii to avoid high stresses in
areas where a change in section is unavoidable. Figure
as full power is attained (line C-D). Stress relaxation 2.94 shows a triple-shell HP cylinder with an unsplit
(line D-E) can then occur at the maximum operating intermediate sleeve. To further reduce temperature
temperature, during which elastic strain is converted gradients, particularly in the first stage of the HP
to creep strain and may cause microstructural damage. turbine, pure throttling of the governor valves has been
Shutdown causes a drop in temperature at the surface, adopted for load control. Although this type of control
the thermal contraction being constrained by under- reduces efficiency at part-load, this can be tolerated in
lying material, resulting in further tensile stressing. two-shifting operation, where the machine tends to be
However, this straining takes place outside the creep operating at rated load or is shut down. The practice
range of CrMoV steels used in rotor construction. Details of using nozzle control to maintain part-load efficiency
of rotor materials and their properties with reference has the disadvantage of reduced efficiency at full-load
to creep resistance are given in Chapter 1. The stress- and leads to temperature gradients because of the
strain cycle of Fig 2.93 is similar to that experienced circumferential non-uniformity of steam admission.
by the inner surface of a high temperature casing This reduces the rate at which load can be changed
under severe starting transients. without inducing thermal stresses. Rapid starting and
The magnitude of thermal stresses produced during loading, which are essential requirements for modern
two-shifting or cycling, depends on the amount of tem- machines, are therefore achieved more securely with
perature change imposed in a given time in relation to throttle control.
the sizes of components involved; for example, casing During run-ups and rapid loading, the turbine is
thickness or rotor diameter. Stress concentrations in most at risk from a 'rub' between stationary and rotating
casings and rotors must be reduced to a practical components. Apart from localised damage at the area
minimum by the avoidance of rapid changes of section of contact, the resulting heat generated by the 'rub'
and by proper fillet radii. The need for flexible op- can cause a bend in the rotor shaft. Continuous asym-

222
Operational flexibility

OUTER CASING

UNSPLIT SLEEVE CASING

INNER CASING

FIG. 2.94 Triple-shell HP cylinder of a 660 MW turbine with unsplit intermediate sleeve

metrical rubbing, which bends the rotor even more, requirements of steady and cyclic operation. One
can cause so much heating that the heated area of the example of this is the rotor bore size. A large rotor
rotor, expanding and constrained by the surrounding bore, often with a diameter of half the external dia-
unheated material, yields in compression. As a result, meter, gives improved performance for transient or
when it is allowed to cool, local tension is applied cyclic operation, as the temperature gradients and
leading to a permanent bend. Such 'rubs' are usually thus thermal fatigue is reduced. However, large dia-
caused by distortion of gland seal positions from their meter bores cause an increase in the hoop stress which
normal concentric location due to rapid thermal cycl- will accelerate creep at steady load. In large modern
ing. The adoption of spring-back gland seals allows machines, the requirement to reduce the hoop stress
retraction of the seal should contact with the rotor dictates that the bore diameter should be kept to a
occur. This limits the damage caused by a rub and practical minimum. The main requirement for rotors
reduces the risk of a shaft bend. is to reduce thermal fatigue by ensuring that all stress-
Cylinder expansion and contraction during run-up concentrating features are controlled so as to mini-
and run-down, requires that cylinder/pedestal sliding mise the stress levels.
surfaces are well maintained, to prevent unnecessary A fracture mechanics approach is adopted to assess
external forces on the cylinders due to sticking. the growth of any initial inherent forging defects. The
repeated application of stress during cycling could cause
the defect to propagate to the stage where fast fracture
12.2.2 Turbine rotors of the forging would occur. With knowledge of the
Rotor design is influenced by the often conflicting operational requirements of the turbine and assuming
223
Turbine plant systems Chapter 2

that the largest undetectable defect is initially present, cal probe arrangement. One end of the core is in
the criticality of that defect can be assessed. contact with the main steam flow and the other end is
insulated. Because it cannot be in contact with the
rotor it is situated to measure the temperature of
12.2.3 Stress monitors the steam as admitted to the rotor. For correct simu-
The life of the turbine-generator is based on its op- lation, the probes are positioned so that during natural
erational requirements and the assumption that a cooling, the probe and critical areas of the rotor cool
particular stress level related to each start is reached, at the same rate. This means that steam/metal tem-
but not exceeded. During runs-up it is beneficial that perature mismatch is the same for both probe and rotor.
thermal stress levels within critical components, e.g., This data is then fed into a computer, where detailed
HP and IP rotors, are monitored so that the maximum stress analysis is carried out to evaluate the thermal
allowable thermal stress levels are not exceeded. This stress within critical areas of the rotor.
should ensure that thermal fatigue damage will not
occur in the operational life of the turbine. This moni-
toring requirement brought about the development of
stress monitors or life expenditure monitors, as they 12.3 Forced-air cooling
are sometimes called.
The purpose of forced-air cooling of the main turbine
The monitoring is achieved by the use of tempera-
is to allow the machine to be taken off barring in the
ture probes with a central core which simulates the
shortest possible time, thus enabling maintenance work
critical section of the rotor. Figure 2.95 shows a typi-
to be carried out as soon as possible after unloading
the unit. Forced-air cooling greatly reduces outage
times; typically, with the use of forced-air cooling, a
machine can be removed from barring within about
20-25 h of coming off-load. This compares with times
of 90-120 h when employing natural cooling.

12.3.1 Cooling of turbine


For this technique to be employed, the turbine is
designed to be suitable for injection of cooling air into
the HP and IP cylinders via special injection points
located around the cylinders. Diffusers are normally
provided at the injection points to ensure that un-
acceptable local chilling of the cylinder or other com-
ponents does not occur. To prevent the rotor cooling
faster than the casing, which would cause unacceptable
positive differential expansion, cooling is achieved by
injecting the air into the interspace between the inner
and outer casings. This ensures that the rate at which
the casing cools is higher than that of the rotor, thus
allowing better control of the differential expansion.
A typical forced-air cooling system for a 660 MW
generator is shown in the diagrammatic arrangement
of Fig 2.96. This shows the direction of air flow for the
HP and IP turbines. Air entering between the outer
cylinder and the inner sleeve of the HP turbine flows
in both directions to the cold reheat pipes and reheater,
exhausting to atmosphere via the reheater dump valves.
Air from the IP turbine exhausts via vents from the
IP/LP crossover pipes. The heated air must be dis-
charged in such a way as to present no hazard to either
personnel or to other plant.
STEAM FLOW
During cooling, it is essential that close attention
is paid to HP and IP turbine rotor eccentricities; HP,
IP and LP differential expansions; HP and IP metal
temperatures and the barring motor current, which
FIG. 2.95 Replaceable rotor simulating probe for could give indication of contact between rotating and
monitoring thermal stresses in HP and IP rotors stationary components. The air flow must be controlled
224
Operational flexibility

8 RADIAL INLETS

;Ln/\iii
ON OUTER CASING

n
, 4 RADIAL INLETS
ON OUTER CASING

HP TURBINE IP TURBINE

T
\ k
V
s
^ff
DOUBLE ISOLATION
LOCKING VALVES
V-MAIN IP
AIR FLOW VENTS
FROM IP/LP
CROSSOVER PIPES
MAIN HP AIR FLOW
VENTS FROM
REHEATER
DUMP VALVE

SECONDARY HP AIR
TO ATMOSPHERE TO ATMOSPHERE
FLOW VENTS FROM SECONDARY IP AIR FLOW
MAIN STEAM PIPE VENTS FROM IP
DRAINS LOOP PIPE DRAINS

/~ ~\
DOUBLE ISOLATION
LOCKING VALVE

1 m .
<> 1 i\ 1
1 11
<> 1
4

DRAIN V <\LVES ^
NORM/\LLY ]
CLOS ED M

CONTROL VALVES

FORCED AIR
TO OTHER UNITS

AIR INLET

FlG. 2.96 Forced-air cooling system for a 660 MW turbine-generator

225
Turbine plant systems Chapter 2

to give a cooling rate which allows eccentricities and flow at the entry to the LP cylinders, and thereby an
differential expansions to be maintained within the adequately high efficiency of blading. Higher reheat
manufacturer's specified limits. pressures help to minimise the size of the moisture
separator/reheater, and the mean diameter and length
of the HP cylinder exhaust blading.
12.3.2 Cooling system The inlet steam conditions also dictate the scantlings
The cooling air is provided by a system consisting of of the HP stop and governor valves, which are very
oil-free compressers or blowers, distribution and ex- similar in arrangement, size and thickness to reheat
haust pipework, supports, valves and control gear, and valves on a conventional unit. A typical back-to-back
filters or air conditioning plant. The system shown in arrangement is shown in Fig 2.98. Because the low
Fig 2.96 employs a single multistage compresser. It is temperature (about 280C) and pressure do not dictate
normal to install sufficient capacity to meet the cooling a material with high temperature strength and, since the
requirements of one turbine only, with pipework pro- steam at inlet is insufficiently wet to cause erosion,
vided to enable cooling air to be supplied to any of a low carbon steel is used for the valve chest. The
the units in the station. loop pipes supplying steam from the chests to the
It is important that the air supply is filtered to ensure HP cylinder may also be made from carbon steel for
the removal of small particles and also that it is free the same reason. The loop pipes are generally arranged
of any corrosive gases, such as sulphur dioxide and to be as short as possible to limit the quantity of
chlorides, as emitted from the stack of fossil-fuelled steam which might overspeed the machine in the event
stations. Moisture separators should also be installed, of load rejection.
along with suitable pipework drains to ensure that the The HP turbines of large wet steam machines are
air supply is dry. usually of double-flow design, similar in appearance
Figure 2.96 also shows locking double-isolating valves to the IP turbines of conventional units. As many as
and removable flexible connections which are used to seven stages of moving blades in each flow are carried
ensure that the forced-air cooling system is fully isolated by a rotor which, in the UK, is normally of a monobloc
from the turbine when not in use. construction. Diaphragms or fixed reaction blading
are supported by carrier rings bolted to the outer casing
at the horizontal joint as in conventional machines.
This effectively forms a double-shell construction and
permits moderate casing thickness, flange and bolt sizes
13 Wet steam turbine plant to be employed.
For impulse blading and an adopted rotational speed
of 3000 r/min, the bladed wheel diameters tend to be
13.1 Influence of steam on components relatively small and, with the high specific steam con-
The steam produced by a modern light-water reactor, sumption, the blade lengths become relatively large.
such as a PWR or BWR, is of poor thermodynamic The double-flow arrangement serves to keep the blade
quality. The pressure is typically in the range of 65-70 lengths, and hence the blade stresses, to conservative
bar and since the steam is around 3% wet, the tem- values.
perature corresponds to saturation conditions. It there- Care must be taken in the design of the HP casing
fore follows that the steam mass flow per unit of to eliminate crevices and pockets where water may
generation is about 80% higher than in fossil-fired or collect, otherwise, during sudden load reduction, pools
AGR power stations. of standing water could flash-off and overspeed the
The very modest steam conditions at the turbine turbine.
stop valves results in a very large volumetric flow. It is normal practice to pack the shaft end glands
The turbines consist of one high pressure and two or with live steam which has been throttled and has
three low pressure cylinders, with the steam exhausted therefore acquired a small amount of superheat. This
from the HP cylinder being dried and reheated in also removes the possibility of erosion damage to the
external moisture separators and reheaters before be- rotor and other components in an area of high mois-
ing readmitted to the LP cylinders. A typical turbine ture content at the end of the HP expansion.
arrangement is shown in Fig 2.97. Unlike high tem- The steam leaves the HP turbine with a wetness
perature reheat turbines for fossil-fuelled power stations, of between 10% and 15% dependent upon the se-
where reheat pressure affects boiler design and is lected crossover pressure. If the steam were then passed
therefore not a free choice of the turbine designer, the directly into the LP cylinder without any form of
reheat pressure in turbines for light-water reactors is mechanical drying or reheat, the terminal wetness at
chosen by the turbine builder to suit the turbine and condenser pressure would exceed 20%. This would cause
moisture separator/reheater design, performance and unacceptable LP moving blade erosion, particularly in
economics. Due to the very large mass flow of steam, the last stages, and turbine efficiency would be im-
it is not necessary to select a low reheat pressure paired. Reheating is therefore always employed in
in order to preserve an adequately high volumetric saturated steam cycles.
226
LP2 TURBINE LP3 TURBINE

HP TURBINE

THRUST BEARING

LOW TUNED FOUNDATION BLOCK

MAIN EXCITER

(a) Elevation (b) Plan MOISTURE SEPARATOR AND REHEATER


Wet steam turbine plant

227
FIG. 2.97 Typical turbine arrangement for a pressurised water reactor installation
Turbine plant systems Chapter 2

HP GOVERNOR VALVE

rrr

CONTROL GEAR CONTROL GEAR

FROM TO HP TURBINE
STEAM GENERATOR

FIG. 2.98 Back-to-back arrangement of HP stop and governor valves

In order to avoid the complication of additional


large penetrations into the reactor, steam is passed
from the HP exhaust to moisture separators in the
turbine hall where the wet steam is dried mechanically
before entering a reheater, also situated in the turbine
hall. Here the steam is superheated by the use of live
steam which results in a performance improvement of
about 1.5%. The thermal efficiency can be increased
by a further 0.3-0.5% by two-stage superheating, i.e.,
by using bled-steam from the HP turbine as heating
steam in the first stage and live steam in the second
stage. The efficiency improvement gained by bled-
steam reheating has to be balanced against the in-
creased capital cost, and is dependent on the cross-
over pressure, bled-steam pressure and the reheater
terminal temperature differences. The bled-steam re- FiG. 2.99 Butterfly type low pressure interceptor valve
heater improves the cycle efficiency by reducing the
steam demand of the live steam section, but it also
incurs an additional pressure drop of the reheated
steam through the tube bundle and requires additional shedding to zero load, the interceptor valves close
drainage facilities. Despite these factors, bled-steam rapidly, preventing the steam present in the separator
reheating is becoming increasingly economically viable and reheater, together with any water which might
and is normally offered on present wet steam machines. evaporate off hot walls and pipework, from overspeed-
Because of the large volumetric flow at LP cylinder ing the turbine to unacceptable limits. The valves are
inlet, the interceptor valves tend to be very large. designed so that steam forces assist closure as soon as
This precludes the use of normal plug valves; instead, a small degree of rotation is imparted. The valves are
butterfly valves similar to that shown in Fig 2.99 are fitted with bearings which are capable of operating at
normally used for this application. Since there are no relatively high temperatures and have shock absorbing
right angle bends and no restriction to the flow, they characteristics.
have the advantage of providing very low pressure The thermodynamically optimum choice of the cross-
drop in the normal operating fully-open position. over pressure between HP and LP cylinders, and the
Butterfly valves are used for both stop and governing universal application of steam reheat, result in inlet
valves, the two valves being arranged in a single chest conditions to the LP cylinders which are closely sim-
welded into each hot reheat pipe. ilar to those encountered in a high temperature re-
The valves may be used in a reheat governing mode, heat fossil-fuelled cycle. As a result, LP cylinders
as in conventional machines, but in the event of load- for water-cooled reactors are subjected throughout
228
Wet steam turbine plant

all their stages to steam pressures and temperatures HP cylinder into bled-steam pipes and into the cold
virtually identical to those for fossil-fuelled stations. reheat pipes, which are drained at all times to the
It is therefore possible and desirable to use LP cyl- drains receiver; the LP cylinders into bled-steam pipes
inders of identical design to those used in turbines for and the condenser. If pockets at each end of the HP
fossil-fuelled stations. However, exhaust volume flow cylinder are formed in the casting between the cold
is 60-70% greater than for a fossil-fired unit of the reheat branches, these are drained continuously into
same rating. If, therefore, exhaust losses are to be the cold reheat pipes.
kept to a minimum, either the exhaust annulus of each Interstage drainage introduces considerable quanti-
LP turbine must be increased or the number of LP ties of water to the feedheater system and the provi-
turbines must be increased. sion of extra large drain arrangements in the design of
In the USA, half-speed machines have been adopted this system requires careful consideration. In common
for use with large output light-water reactors. Power with conventional machines, every effort is normally
generation is at 60 Hz, which limits the choice of made to ensure that there is no possibility of water
rotational speed to 3600 r/min or 1800 r/min. The refluxing to the turbine. Present specifications require
stresses in the exhaust blades impose a limit to their individual routing of drains to the turbine drains re-
length in full-speed machines and hence a limit in ceiver and prohibit the commoning of drains from
the exhaust area per turbine. This, together with the sources at different potentials.
widespread use of 1800 r/min LP turbine elements in
conventional power plants, has led naturally to 1800
r/min as the design speed for PWR turbines in the
60 Hz system. 13.3 Erosion protection
In a 50 Hz system the position is entirely different. Steam enters the HP turbines slightly wet and it be-
Much larger turbine exhaust blade annulus areas are comes progressively wetter with each stage of expan-
available and still longer blades are being developed; sion, but the moisture droplets are very small and
making 3000 r/min turbines economical for large out- are so well entrained in the bulk steam flow that the
puts and different condenser pressures. Half-speed velocities of droplets and main steam do not differ
machines are invariably more expensive than full-speed significantly. Blade path erosion is not therefore a
machines. The design of the LP turbine elements can significant problem and the blades can be made from
be based upon extensive experience of identical proven 12% chrome stainless iron coupled to a NiCr MoV
components for conventional power stations. However, forged rotor, as in conventional machines.
nuclear power generation leads in itself to increases Centrifugal stresses are generally low and, since the
in the size of generating units, and it may be necessary steam temperature is far below that at which creep has
to consider half-speed machines for future very large to be taken into account, only medium-strength ferritic
units requiring large annulus areas, particularly in stainless iron need be used for the blading.
combination with the low cooling water temperatures
Where changes in flow direction are induced in the
likely in UK plants.
casings or pipework, or where pressure differences exist
across joint surfaces or pressure seals, water droplets
can combine and there is considerable potential for
13.2 Water extraction devices erosion. The HP casings, fixed blade carriers and cold
Since the steam enters the turbines wet and becomes reheat pipes must therefore be made from a chromium
progressively wetter as it expands through the HP alloy steel such as 2.25%Cr l%Mo. Such alloys resist
blading, arrangements are usually made for internal the formation of the surface oxide layers, which would
moisture extraction at each stage. Where appropriate, be continuously removed and reformed by an erosion-
tip seals fitted to stationary components are slotted corrosion mechanism. It is also essential to protect joint
to permit extraction of water collecting on the outer faces subject to a pressure drop against cutting by wire-
flow boundary. This water is either removed with steam drawing erosion, and to protect surfaces which might
bled from extraction points between the fixed blade be subjected to impact from water droplets flung off
carriers or, in stages which have no bled-steam tap- the shrouding of the rotating blades. This requires
ping, drained through the casing via pipes, drillings the use of very erosion-resistant alloys, such as 13%Cr
and orifices to a stage at lower pressure. or 18%Cr stainless steel. Austenitic steel facing can be
Water extraction grooves may also be incorporated provided by weld deposition and 13%Cr inserts may
where necessary to assist the feedheating belts in ex- be located by seal welding.
tracting additional moisture. These consist of an annular To minimise the possibility of joint jacking by cor-
groove in the cylinder wall at the trailing edge of the rosion products, horizontal joint bolting must be ar-
moving blades connected to a series of nozzles which ranged to ensure that water penetration is restricted.
discharge water and a small quantity of steam into It may be necessary to protect certain joints by placing
the space between blade rings and outer cylinder. short stainless steel sleeves around them and incor-
The turbine cylinders should be self-draining; the porating stainless steel barrier keys.

229
Turbine plant systems Chapter 2

Severe erosion has been experienced by continental normally horizontal inlet pipe through a diverging con-
manufacturers on low alloy and carbon steel casings ical channel to a row of s wirier blades. The s wirier
and pipework in wet steam machines. 'Alsthom' ori- blade ring imparts tangential velocity, or swirl, to the
ginally made HP casings in -y CrMoV but, in view of steam and helps to agglomerate the water droplets. The
experience gained at Muhleberg, Beznau and Oskar- water films forming on the aerofoil surfaces of the
shamm and in Germany, intend using a steel with at swirler blades are subsequently detached as coarse
least 11 % chrome in future to give satisfactory erosion droplets by the main steam flow. The droplets are then
protection. They currently make pipework bends in centrifuged by the steam flow and deposited onto the
2 j % chrome steel and apply a high-chrome cladding inner surfaces of a louvred liner which removes and
protection on interceptor valves. CEM (Asea Brown partitions the free water from the main steam flow.
Boveri) protected low alloy diaphragm groove facings The louvred liner is provided with a series of narrow
and similar facings for gland grooves with 13% chrome axial apertures uniformly distributed around its peri-
cladding but, having found the cost of achieving a phery to entrain the water droplets. Separated water
satisfactory 13% chrome deposit prohibitive, now supply films then cascade around the outer surfaces of the
13% chrome castings for wet steam HP inner and outer louvred liner. To encourage the separated water to
casings. flow over to the louvres, steam is extracted from the
separator vessel and passed to a heater in the feed
train. The separated water is also passed from the
vessel, via drain pipes, to a convenient point in the
13.4 Moisture separator reheaters (MSRs) regenerative feed train.
Separators and reheaters fall into two main types. In order to ensure that steam leaves the separator
Manufacturers such as Westinghouse, Asea Brown with the minimum of swirl, anti-swirl vanes are fitted
Boveri, GEC, etc., combine the two units into a single into the outlet nozzle. These vanes ensure that a low
vessel or MSR; whereas Parsons, Stein Industrie, etc., energy axial flow of steam enters the reheater, mini-
favour individual vessels connected by large bore mising the risk of disturbance to the reheater tube
pipework. bundles.
The performance of cyclone separators is very de-
pendent on the droplet size of the water entering the
13.4.1 Separators vessel. Very high efficiencies (of the order of 98%)
can be achieved with a wetness of, say, 12% if the
droplets are relatively coarse, but efficiency falls con-
Cyclone separators
siderably if the separator is presented with steam of
In the NEI-Parsons design of separator, shown in the same wetness with droplets in the sub-micro metre
Fig 2.100, water droplets are recovered from the steam range. Tests to determine separator efficiency, using
by centrifugal action. The vessels are conveniently located superheated steam artificially wetted in a spray-type
in the cold reheat pipes from the HP turbines, generally desuperheater, generally give optimistic efficiencies
one vessel per pipe. The wet steam is passed from a since the large water drops produced by the desuper-
heater are easily separated from the steam. Measure-
ments taken on site on practical installations have
confirmed separation efficiencies in excess of 95%
EXTRACTION STEAM BRANCH for an inlet wetness of 12%, and 93% at very high
SWIRLER BLADES /
moisture contents above 20%.
A major factor in achieving these high efficiencies
is the growth in droplet size from a mean diameter of
about 10 microns at HP turbine exhaust to about 120
microns in the transfer pipe to the separator. Further
agglomeration of water films on the surface of the
swirler blades results in droplets of about 240 micron
diameter being centrifuged to the louvred drum.
Erosion and corrosion are minimised by employing
suitably resistant materials in areas subject to im-
pingement. At the separator inlet, where moderate
steam velocities and water droplet sizes generally prevail,
2.25%Cr l%Mo steel is used for the inlet pipe and
cone pieces. In the main steam space, where velocities
and droplet sizes are greater, the swirler blades, louvres
and internal cladding on the pressure vessel are of
12% Cr low carbon steel. The basic pressure vessel
FIG. 2.100 Cyclone separator is manufactured from carbon steel.
230
Wet steam turbine plant

High velocity cyclone separator


The major problem with cyclone or centrifugal se-
parators is the pressure drop produced by swirling the
steam in a relatively large diameter drum and then
straightening the flow at exit from the separator. One
method of reducing the pressure drop through the
separator is by swirling the wet stem through a number
of relatively small diameter tubes or cells arranged in
a bundle in an enlarged section of cold reheat pipe. A
typical separating cell and vertical assembly arrange-
ment used in the Stein Industrie design is shown in
Fig 2.101.
In common with the NEI-Parsons design of cyclone
separator, a set of turning vanes at the cell inlet im-
parts a swirling motion to the steam/water mixture.
Instead of a louvred drum, an annular skimmer slot
is employed to collect the water and a small flow of
extraction steam is allowed through the slot to improve
moisture removal. Another set of guide vanes at the
cell outlet straightens the flow and helps recover rota-
tional kinetic energy. Since the flow does not depart
significantly from the axial direction throughout the
separation process, pressure drops are generally small.
Also, because the cell bundle is not much larger than
the diameter of the pipe on which it is fitted, the
separator may be retrofitted into existing installations
with the minimum of disturbance.
In tests carried out at Bugey II power station, the
pressure drop for an inlet velocity of 50 m/s was about
150 mbar and the moisture content at outlet from the
separator was 0.3% compared with 11.4% at inlet.
However, 10% of the main steam flow was extracted
to assist water removal.
Stein Industrie have also developed a horizontal
high velocity separator, in which a portion of the
steam from the bleed-off is passed into the central tube
in the separating cell and recirculates through slots
in this tube just downstream of the inlet vanes. The
net leak-off flow is thereby reduced and good sepa-
ration efficiencies have been reported from rig tests.
The performance of this type of separator has not
however been repeated on site, possibly because the
drainage systems are less than adequate on site and
also because of the difficulty, expressed above, of
reproducing an an HP turbine exhaust water droplet
size distribution in a test rig.

Wire mesh separators


The early designs of combined moisture separator/
reheater supplied by GEC, Asea Brown Boveri and
Westinghouse incorporated a wire mesh separator.
The water separation characteristics had been sub-
ject to theoretical and experimental investigation and
was established in a number of industrial applications.
Brodie [4], who studied the extraction properties of
wire mesh in an atmospheric air/water flow, had de-
monstrated that a residual steam wetness of 0.1-0.2%
could be obtained but only over a narrow range of FIG. 2.101 High velocity cyclone separator

231
Turbine plant systems Chapter 2

very low steam velocities of the order of 1-2 m/s. is collected on the sloping base of each tray and
Further tests carried out by GEC confirmed that good drained to the base of the vessel through funnels and
separation performance could be obtained for cross- pipework.
over conditions in wet steam turbines and gave good A scheme devised by GEC is shown in Fig 2.103.
correlation with the previously predicted upper limit- Steam enters from the base of the vessel and is dis-
ing velocity. These, and other investigations, showed tributed along the length of the vessel by a series of
that water is extracted when the approach velocity is perforated plates which also act as water collectors.
sufficient to cause inertia impaction of droplets on Each hole in the distribution plates is provided with a
the wires of the mesh. After deposition, the droplets raised lip on the upper surface of the plate to prevent
coalesce and run along the surface of the wire under the separated water draining into the steam flow and
the influence of gravity until they reach a point where becoming re-entrained. The holes are of such a size
two wires cross. This point soon becomes overloaded and pitch that they ensure diffusion and downstream
with water and large drops fall from the mesh against mixing of the steam. Water is collected in drainage
the direction of the steam flow. troughs set into the perforated distribution plates and
The wire-mesh mats must be disposed as near hori- is led to the bottom of the vessel. From there, the
zontally as possible and, in view of the necessary low separated water is piped to a heater in the feed train.
velocity, the mats have to be very large (80 m2 for
a 300 MW machine). This, in turn, requires a steam Chevron or corrugated-plate separators
distribution system capable of collecting and draining
the separated water falling from the mesh without Although mesh separators are most effective in re-
causing re-entrainment, or impairing the uniformity moving moisture, their major limitation is the massive
of the steam flow. Different manufacturers achieve size imposed by the low limiting velocity. A mesh
this using different ingenious methods. Figure 2.102 separator which is almost 100% efficient at 1.5 m/s
shows a cross-section through an Asea Brown Boveri may only be 60% efficient at 1.7 m/s, since the steam
arrangement. In common with all mesh separator velocity is then just sufficient to prevent the water
designs, the wire-mesh mats are conveniently incor- falling, and re-entrainment occurs. Chevron separating
porated in the same vessel as the reheater tube banks.
Steam is channelled along the lower side of the vessel
(the left-hand side in the figure) and directed dia-
gonally through three mesh trays in parallel. Water

FIG. 2.103 Cross-section of an early single-stage MSR


FIG. 2.102 Wire mesh separator with mesh separators

232
Wet steam turbine plant

elements do not have a clear upper limiting velocity


and are therefore more tolerant of possible excessive REHEATED STEAM

local velocities. Chevron separator performance also


tends to be as good as wire mesh performance at
twice the steam velocity. Modern designs of chevron
separator regularly extract 98 % of the water from
12% wet HP exhaust steam. Because chevron sepa-
rators are able to give satisfactory performance at
higher steam velocities, they require a smaller frontal
area for the same steam flow, giving a more compact
arrangement.
Chevron separating elements are produced in various
forms. Basically, the elements are parallel corrugated
plates which induce separation of the water droplets
by inertia and impaction. Earlier types incorporated
hooks or stops in the corrugations to induce even
more sudden changes in the steam flow. These elements
were complex to make and the slight performance
improvement did not warrant the additional complex-
ity and expense. Current designs employ simple cor-
rugated plates, sometimes with curved sides or, more
recently, with flat plates in a zigzag pattern.
The droplets captured on the corrugated plates
coalesce to form a film of water which drains down
the corrugations. If this film is allowed to accumulate
over a large depth of plate it could grow to a thickness
which would result in re-entrainment of water by the
steam flow. Hence, the chevron plates must be either
of a limited depth or the corrugations must be fitted
with water-collecting channels shielded from the steam
flow. The design of the final drain-collecting device, at
the bottom of the vane, also requires detailed atten- FIG. 2.104 Cross-section of a two-stage MSR with
tion to ensure that it does not induce re-entrainment. chevron separators
A typical MSR design using chevron separators is
shown in Fig 2.104. After general steam distribution
within the vessel, the flow through the separators is structure is supported on two integral tubular sup-
controlled by perforated plates located in front of ports which penetrate the shell and provide support for
each packet of chevrons. the tube elements and integral framework. The tube
In order to avoid any problems from wet steam elements are therefore allowed to expand vertically from
erosion and off-load corrosion, components used in this tubular support near the base inside a sliding
the construction are normally stainless steel. Separator linkage arrangement. The tube elements are also posi-
plates, for example, may be in austenitic stainless steel tioned centrally within a support frame which locates
and the distribution plates in 13% chrome ferritic the elements inside the shell and ensures that the shell-
steel. Internal supports for these elements are designed side steam does not by-pass the tube elements. A full
to avoid resonant vibration and to allow for differ- diameter bolted joint is provided near the top of the
ential thermal expansions. shell to allow the upper dished end to be removed for
access to the tube elements.
Each identical tube element contains a number of
13.4.2 Steam-to-steam reheaters straight externally-finned tubes welded into similar up-
per and lower headers. Welding is done with an auto-
matic TIG welding system, using a two-pass technique
Vertical reheaters
followed by full NDT. The headers are rectangular in
Vertical reheaters have been developed in recent years section and trough-like in shape, the side opposite
by NEI-Parsons for Canadian machines and by Deutsche the tube sheet being in the form of a coverplate or
Babcock and Wilcox for machines in Europe, parti- lid. The covers are bolted to the headers and a soft
cularly in Germany. metal gasket is incorporated between the cover and
A typical NEI-Parsons steam-to-steam reheater is the trough section to ensure a leak-tight seal.
shown in Fig 2.105. The shell consists of a large ver- The tubes in each element are arranged in a narrow
tical cylinder with dished ends top and bottom. The rectangular pattern with the long span being perpen-
233
Turbine plant systems Chapter 2

rather than the heat transfer coefficient of the extended


tube surface.
On recent wet steam machines, economic factors
dictate two stages of reheat. The exhaust steam from
the external separators is directed across the outside
of the tubes in a single pass in a manner which is very
close to pure crossflow. The reheating steam is supplied
to the upper header of each tube element and condenses
on the inside of the tube. The condensate is piped from
the bottom header and passed to the feed train. The
heating steam supply to the elements through which the
separator exhaust steam first passes, is obtained from
a tapping on the HP cylinder. The shell-side steam, then
passes through further elements, which derive their
heating steam from the live steam pipework upstream
of the HP stop valves. The heating elements impart a
small degree of superheat to the shell-side steam, which
then enters the LP cylinders through the LP inter-
ceptor valves in a condition almost identical to LP
inlet conditions in a fossil-fired plant.
Occasionally a small percentage of inlet steam from
the separator exhaust is allowed to pass on either side,
and also around the top and bottom, of the tube bank
and finally exits with the superheated outlet steam.
This by-pass steam cools the reheater outer shell and
I I \ II minimises the vessel deformation which can be caused
by the temperature rise in the shell-side steam as it
BLED
STEAM
LIVE
STEAM
passes from one side of the vessel to the other.
DRAINS DRAINS On NEI-Parsons reheaters in Canadian machines,
all components, with the exception of the tube element
FIG. 2.105 Vertical type reheater header-gaskets, are made from carbon steel. In order
to protect the heat transfer surfaces on the inside
and outside of the tubes from rusting during pro-
longed shutdown periods, heated air is blown through
dicular to the direction of the shell-side steam flow. the reheater elements on the shell side to keep the
This results in the minimum shell diameter, and faci- ambient internal temperature above the dew point.
litates element interchangeability and ease of manu- This prevents rust forming on the outside of the tubes
facture, erection, leak detection and replacement of and the shell internals. The tube bores are protected
elements, if necessary. during shutdown periods by nitrogen blanketing. Ex-
Steam condenses as it passes down the tubes and ternal erosion-corrosion of the tubes, tubeplates and
the vertical tube arrangement obviates problems of vessel at full and part-load is minimised by limiting
slug-water flow that can occur with horizontal con- the venting and flow velocities. Wet steam erosion of
figurations. Complete drainage during shut down or the tube bores is minimised by using low reheating
element isolation is also ensured by the vertical steam velocities of the order of 1 m/s and a downward
arrangement. flow direction which results in a steady annular flow
The heat transfer coefficients are very different on pattern.
the inside and the outside of the reheater tubes. On The tube length or support has to be arranged to
the inside, where the heating steam is condensing, the ensure that the natural frequency of the tube bundles
heat transfer coefficient is much higher than on the is clear of machine frequency, low harmonics of ma-
outside which is in contact with the nominally dry chine frequency, flow-induced Karman vortex shedding
steam at low pressure. Externally-finned tubing is frequencies and acoustic standing wave frequencies.
therefore used to enhance the heat transfer capability Tube diameters are normally chosen to ensure that
on the shell-side and hence reduce the total number the tube natural frequencies are clear of aeroelastic
of tubes, reheater size and shell-side pressure loss, frequencies, but tube first-mode natural frequencies
compared with an unfinned tube arrangement. The have been found close to acoustic standing wave fre-
length and number of tubes and the fin profile are quencies. In an attempt to avoid this, horizontal sup-
chosen on the basis of a cost optimisation. The critical port plates adjacent to and within the tube element are
variable in this cost optimisation procedure has been sometimes split and wedged apart with spacer bars to
found to be the pressure drop across the reheater, brace the tubes against the tube support plates. The
234
Wet steam turbine plant

plates must be fitted with care to ensure that no floor. Shell-side relief is normally accommodated on
damage occurs to the tube fins on assembly. By ad- vertical reheaters by a combination of bursting dia-
justing the spacing of these plates, the vibrational phragms and pressure relief valves in the hot reheat
characteristics of the tube can be arranged to be lines between the reheater and the interceptor valves.
clear of damaging vibrations, whether mechanically
or flow-induced.
On-load detection of tube leakage can be deter- Horizontal moisture separator reheaters
mined by isolating each tube element and comparing The overall size of the MSR vessels incorporating wire
the internal 'settle-out' pressure with the prevailing mesh separators was originally governed by the pro-
shell-side pressure. vision of sufficient area of horizontal mesh. It was
On Canadian units, in the event of any tube leak- most convenient to dispose the vessels horizontally
age, the particular tube element is isolated until it and position the heater elements above the mesh. The
can be replaced by a spare element at a convenient steam distribution system was below the mesh and the
outage: the leaking element tubes are then plugged. steam inlets were therefore positioned in the bottom
Tube elements are removed by taking off the shell of the vessel. The hot reheat connections were posi-
cover, cutting the tube-side steam supply and drain tioned on the top of the vessel.
pipes (live or bled), and lifting out the tube element. With one vessel located each side of the LP cylinders
The replacement of a tube element is simply the re- at engine room floor level, the cold reheat pipework was
verse of element removal. routed from the HP turbine exhaust to the bottom of
A problem with vertical reheaters is that the maxi- the MSR and the hot reheat pipework from the top of
mum height of the crane hook has to be sufficient the vessel to the LP cylinders.
to lift the heating elements out vertically. To reduce With the adoption of inclined chevron separators,
the amount of cutting during dismantling, the live it was no longer necessary to limit the steam distri-
and bled-steam pipework normally enters the shell bution system to the lower section of the vessel. A
through the side wall rather than through the shell typical schematic arrangement of a two-stage MSR is
cover. This pipework from the shell wall to the ele- shown in Fig 2.106. The steam is introduced into the
ment inlet headers, and the drain pipework from the vessel through connections located at the end of the
bottom headers through the domed base, has to be shell nearest the HP turbine.
sufficiently flexible to permit relative thermal expan- This arrangement has the dual advantage of reduc-
sion of pipework, heater elements and shell. Occasion- ing both the length and complexity of cold reheat
ally, expansion bends are incorporated to provide pipework and the associated pressure drops. The wet
the required flexibility. steam flows along the length of the vessel within the
Manholes are normally provided for inspection of annulus formed by the shell and an internal support
the reheater internals and the vessel is generally rigidly frame, before passing through the distribution plates
supported on its own foundation from the basement and the separator elements. To achieve efficient op-

BLEDSTEAM
HEADER

COLD
REHEAT
STEAM
INLET

r , CHEVRON \/ SHELL DRAIN \ /V v JL


A \
'Wry
y

I N L ET
DRAIN
SEPARATOR
PACKETS
^f / V
SHELL
DRAIN
vv
\ 7
STEAM
LIVESTEAM
DISTRIBUTION
BLEDST tfi M DRAIN
PLATES

FIG. 2.106 Typical horizontal two-stage moisture separator reheater

235
Turbine plant systems Chapter 2

eration, it is necessary to segregate the incoming cool sides of the tubes. The relatively low rate of heat
steam from the reheated steam. A close-fitting shroud transfer between superheated steam and the tube gen-
is therefore often provided to guide the steam from the erally dictates the use of externally-finned tubes.
reheater to the outlet connections. Where the hot shroud Early designs of MSR were based on published
is in close proximity to the outer shell, it may require predictions of the heat transfer and pressure drop for
a thermal shield to prevent local heating and distortion flow across tubes. However, the condensation process
of the shell. To cater for temperature differentials, which inside the tube produces a two-phase flow which at
could cause unacceptable distortion, the earlier shroud the time was not fully understood. The conditions
designs were divided into a number of panels held in were therefore simulated in tests which showed that
place by clamps, which permitted relative movement the flow was initially stratified and progressed through
without significant leakage. In a Swedish unit, a com- wave-flow and slug-flow to plug-flow at the tube outlet.
bination of pressure differential, thermal distortion and Early designs of reheater in the UK, using hairpin
discontinuity of shape was sufficient to cause a section tubes in carbon steel, suffered extensively from erosion
of shroud to collapse away from the clamps. The of the inside of the tubes, particularly at the hairpin
section then vibrated in the steam flow and failed by bends, and the impact of high velocity steam from
fatigue. Shrouds are now designed to avoid similar leaks in these tubes caused consequential damage to
failures. adjacent tubes. Major retubing with erosion resistant
Current designs of MSR have an outer shell welded material was necessary in certain reheater s, with re-
together from cylindrical plate sections and dished strictions on internal steam flow and hence performance.
ends, designed and constructed in accordance with Some reheaters had to be scrapped completely.
pressure vessel codes. The vessels are generally mounted Some early American MSR designs used cupro-
on two supports, one of which is anchored to the nickel tubes but, at elevated operating temperatures,
foundations. The other support is free to expand this material produced high levels of copper in the
longitudinally but is restrained from moving in a reactor feed water. Since carbon steel tubes suffered
transverse direction by means of a longitudinal key. from erosion and had to be protected against rusting
MSR vessels are always provided with manholes during shutdown periods, 18/8 stainless steels were
for access and inspection, and penetrations through provided in some continental units. This option was
the shell for connections to the tubenest headers are expensive, particularly when compared to carbon steel,
normally provided with devices to allow for relative and occasionally suffered from cracking caused by salts
thermal expansion. The number of reheated steam which leaked out of the condenser. Seawater could be
outlet connections from the vessel is governed by ex- carried around the feed circuit and since the reheater is
ternal layout considerations and the number of LP the only significant drying unit in a wet steam cycle,
turbines. sodium chloride was ultimately deposited in the reheater.
With precautions taken to avoid high velocity wet The reheater tubing in present machines is now
steam, especially at the steam inlet, mild steel is a 18% ferritic stainless steel. This has a greater tolerance
satisfactory material for the containing vessel and the both to the deposition of salts and to general corrosive
internal support frames. It is obviously desirable to and erosive conditions. Since tubeplates continue to
limit the need for erosion protection and therefore it be made from carbon steel, the tubeplate surface is
is necessary to avoid high velocities within the shell. normally clad with a layer of Inconel to facilitate
Any areas of the shell and main support frame which welding of the tubes to the tubeplate. Both the tube-
are exposed to wet steam erosion are always protected plate cladding process and tube welding are followed
by stainless steel. by full NDT procedures.
An internal support provides a framework for weld- Present designs of reheater are sized using heat
ing the separator sub-assemblies and a support for transfer and pressure drop data obtained from tests
the tubenests and steam shroud. Longitudinal mem- on existing units for both the internal and external
bers which add stiffness to the frame often serve as surfaces of reheater tubes under operational conditions.
runners for rollers which assist in the insertion of These tests have enabled higher operating velocities
tubenests into the frame. These rollers also allow the to be used without impairing the integrity of the tube
tubenests to expand longitudinally during operation. wall. Higher velocities lead to enhanced heat transfer
The costs of the separator and reheater are governed coefficients and consequently permit a more compact
mainly by the reheater bundle, in other words by the and economic MSR design.
size of the heating surface serving the heat exchange. Current reheater tube banks are based on hairpin
The residual water after the separator must be eva- tubes arranged in rectangular-shaped nests as in earlier
porated before reheating. This requires additional designs. In earlier machines, the limited length of tube
heating surfaces and both live and bled-steam re- available from the manufacturers resulted in multi-
heating. ple-nest arrangements and central headers. Since tube
To determine the type and the size of the reheater manufacturers can now provide longer tubes, headers
heat-transfer surface, it is necessary to establish the can be placed at the ends of the vessel, making main-
heat transfer and pressure drop correlations for both tenance and withdrawal of tubenests more convenient.
236
Wet steam turbine plant

Sufficient space must, of course, be allowed at both priate tubes, to balance the pressure drop through
ends of the vessel to permit tubenest replacement: the nest to the extent that, with a small vent flow, the
this should be a rare occurrence and might not be tube temperature differentials are maintained at an
necessary in the life of the plant. Leaking tubes de- acceptable level and thermal strains are minimised.
tected by increased heating steam flow would normally Vent lines are normally led to heaters in the feed
be taken out of service by plugging. trains for thermodynamic recovery, but on start-up
The tubes are supported by drilled plates spaced so and low-loads it is sometimes necessary to provide
that under the most extreme conditions of operation a slightly enhanced vent flow. An additional line is
there are no harmful vibrations. The distance between then provided which is usually routed to the condenser.
tube supports is such as to limit any vibrationally- It is possible for conditions to arise which cause
induced stresses and the effect of the gas flow across a pressure rise in the HP turbine and consequently in
the tube to acceptable levels. the MSR, these are:
The natural frequency and mode shape of the tube,
as supported in the nest, are calculated to avoid the A turbine trip from full-load, resulting in the entrained
primary modes. It is not possible to eliminate all forms steam between the stop valves and the interceptor
of tube vibration, as successively higher modes occur valves settling at a pressure level between normal
at small frequency intervals and the actual frequency pressure and the HP cylinder inlet pressure.
is influenced by factors such as alignment of the tube
support plates and the amount of clearance in the Operating with HP feedheaters by-passed and MSR
support plate holes, both of which are variable over reheating tubenests isolated.
the operational life of the unit. In order to avoid
binding of the tubes in their support plates, which Leaking tubes in a live steam reheater tubenest
caused tube failure in some MSR designs, it is es- allowing steam to by-pass the turbine stop valves.
sential that the plates maintain their alignment when
Leakage across the turbine stop valves in excess
the tubenest is subjected to operational temperature
of corresponding leakage through the LP turbine
gradients.
valves.
The temperature difference between the cold and
reheated steam, as it flows across the hot tubes of the Closure of all six LP turbine interceptor valves, whilst
reheater, produces temperature differentials which are an HP turbine stop valve and governing valve remain
many times greater in the first tube row than in the open.
final tube row at full-load, with even greater differ-
entials at part-load. By arranging the heating steam flow
through a hairpin tubenest such that one leg has a low The MSR is, therefore, fitted with a relief capacity
rate of condensation and the corresponding leg a high sufficient for the full reactor steam output. Relief
rate, it is possible to achieve a reasonable balance in valve capacity is provided to cater for a nominal
the steam condensed per tube. Even so, a sufficient number of burst tubes, with a setpoint above the
differential exists to induce the steam, which has not maximum normal operating pressure, and bursting
been condensed by the inner hairpin, to flow via the diaphragms to cater for the total steam flow at a suit-
drain section of the header into the lower leg of the able higher pressure.
outer hairpin. Obviously, whilst operating in such a
manner, the outer tubes are not adequately drained
or vented and a section of tube is intermittently de-
prived of heating steam. This section would then be 13.5 Steam supply and drains systems
transiently cooled by the external steam until the The heating steam for the majority of modern re-
heating steam flow is re-established. Such a cyclic heaters is bled from the HP turbine to the first-stage
operation has been shown to be capable of causing reheat and supplied from the live steam pipework for
fatigue failure on MSR tubes. the second-stage reheat. Reheater steam temperature
In early designs, this mode of operation was avoided control is designed to be completely automatic and
by venting sufficient steam from the drain section of requires no intervention from the operator. A typical
the header to ensure a continuous flow through all diagrammatic arrangement of the live and bled-steam
the tubes. To vent such a flow external to the reheater supply and drains system for a combined separator/
would result in large thermal losses, so the reheaters reheater is shown in Fig 2.107.
were fitted with a vent element. This comprised a
layer of tubes, located prior to the main tubenest, which
condensed the necessary flow of steam. The vent was 13.5.1 First-stage reheat
independently vented and drained. The bled-steam to each reheater is conveniently sup-
Current designs incorporate the simpler solution of plied from a bleed-off (usually the first) from one of
controlling the distribution of steam into the tubes. the flows of the HP turbine. Since the bled-steam is
Suitable restrictions are placed at the inlet to appro- wet, the supply lines usually incorporate some form
237
Turbine plant systems Chapter 2

LIVE STEAM

BLED STEAM

VALVE A: ISOLATING VALVE CLOSED BY HIGH WATER LEVEL SIGNAL


IN ASSOCIATED HEATER

VALVE B: NORMAL DRAIN TO HEATER FLASHBOX

VALVE C: ALTERNATIVE DRAIN TO CONDENSER

STEAM LINE
DRAIN LINE
CONTROL SIGNAL

FIG. 2.107 Steam supply and drains system for a combined separator/reheater

of water separation device, close to the HP turbine: are rarely fitted with safety valves, but motor-operated
to safeguard the HP turbine from any possible ingress isolating valves are always included which close if
of large slugs of this water, non-return valves are the water in the reheater drains tank rises to the extra
normally included. On the most recent machines, these high water level.
non-return valves are often power-assisted and close
in the event of a turbine trip or a load rejection. 13.5.2 Second-stage reheat
They may also be triggered to close from a signal The live steam supply to the second-stage reheater
initiated by an extra high water level in the associated tube banks is obtained direct from the main steam
reheater drains tank. Bled-steam lines to the reheater pipework immediately upstream of the HP stop valves.
238
Wet steam turbine plant

To prevent excessive LP turbine back-end tempera- Separated water from each separator vessel, or from
tures during low-load operation when the hot reheat each MSR shell, and from the cold reheat pipes is
steam flow is low, the live steam reheat supply is drained by gravity into the separator drains tank.
controlled by a valve which regulates the live steam flow Commoning of drains pipes before the drains tank is
according to the temperature of the hot reheat steam. not acceptable, since pressure differences between
In certain designs, this control valve does not open individual pipes and vessels can cause water to back-up
until the machine has reached a particular load. At in the pipework. Water levels can become unstable and
full-load, the valve is fully open and could be subject oscillation or hunting can occur in the drains system
to wear. A by-pass valve is therefore sometimes pro- leading to vibration and sometimes failure, particularly
vided so that the temperature control valve is not of the pipework supports. It is normal practice there-
in use during full-load operation. At a hot reheat fore to provide an individual separator drains tank
temperature slightly below the normal full load tem- and drains control system for each vessel containing a
perature the control valve closes as the by-pass valve separator.
opens. A small warming connection may also be Horizontal drains tanks are often chosen for economy
provided to enable the pipework to be pre-warmed but vertical tanks have the advantage of a constant
to reduce the degree of thermal shock to the reheater surface area and have greater hydraulic stability in
and pipework when the temperature control valve level control. The layout of the drains pipework to the
opens. drains tanks should be chosen with care, particularly
In common with the bled-steam supply, isolating where loop seals are included. The lowest point of
valves are always included in the live steam pipework, the loop must be far enough below the floor of the
but non-return valves are generally not fitted. vessel to permit free drainage during any tank transient
pressure rise. Any transition in the bore of the drains
pipework should also be well below the floor of the
13.5.3 Performance monitoring vessel to inhibit any tendency to flashing at this point
The most satisfactory method of detecting tube leaks of sudden pressure reduction. Drains tanks are nor-
in steam-to-steam reheaters is by monitoring the live mally fitted with vent pipework, level indicators, high
and bled-steam flow rates. Both live and bled-steam level switches and pressure indicators.
supply lines to the reheaters are therefore usually fitted Water from the drains tanks may be discharged to
with flow measuring devices, such as orifice plates a heater in the feed train via a flashbox, or pumped
or pitot tubes. Tube leaks are identified by a sudden to the de-aerator, in which case the pump flow is
increase in the heating steam flow rate. Thermocouples regulated by a level controller on the drains tank. A
are sometimes fitted to tubenest headers to ensure recirculation valve is then necessary to satisfy the mini-
that start-up procedures produce acceptable thermal mum flow requirements of the pump and to guard
stresses, and thermocouples are also sometimes fitted against cavitation. Forward flow may be prevented
to reheater tubes to confirm that the tubenest is not completely in the event of high level in the de-aerator
subject to unacceptable thermal cycling. by a motor-operated isolating valve in the pump
discharge line. In this case, drains are routed to the
condenser. Drains are also normally routed to the
13.5.4 System drains condenser during start-up to prevent contamination
Both the live steam and bled-steam supply lines must of the de-aerator inventory. Pump discharge lines are
be adequately drained at all times. Drain lines usually always provided with isolating valves and non-return
include a dirt trap at the take-off tapping and some valves.
form of steam trap arrangement. Under normal con-
ditions, water is drained away via the steam trap to a
drain vessel. However, steam traps have a history of 13.5.6 Reheater drains
poor reliability and, in the case of the bled-steam sup- The location of the drains receivers, control valves
ply line, are often inadequate to cope with the water and the routing of the drain pipes, requires careful
flow at low-loads. Water traps are therefore always consideration to ensure stable and safe operation of
provided with valved by-passes, sized to pass the the system.
maximum possible flow under all operating conditions. Condensate from each bled-steam tubenest header
is drained by gravity to a bled-steam reheater drains
tank. One tank per vessel is the usual arrangement.
13.5.5 Separator drains In the case of multiple headers, as in NEI-Parsons
Both cyclone separators and MSR internal separators type vertical reheaters, drains pipes are not commoned
are normally situated close to engine room floor level. but individual pipes lead the condensate from the
This provides sufficient height to accommodate the headers to the drains tank, thus avoiding the problems
drains tank, sufficient net positive suction head for a of instability mentioned above. Similarly, drainage
separator drains pump (if fitted) and a falling drain from from the tubenests in the MSR vessels are kept quite
the drains tank to the condenser. separate and are not cross-connected.
239
Turbine plant systems Chapter 2

Condensate from the drains tanks is normally routed The arrangement and control of the live steam drains
to a heater flash vessel or drains cooler for ther- is very similar to the bled-steam drains except that
modynamic gain. If however the heater bank is out of the condensate is finally routed to a heater flash vessel
service, either a three-way valve routes the drains to further along the feed train.
the condenser flashbox, or a motorised valve in the
line to the heaters closes and an emergency drain
valve in the line to the condenser flashbox opens in
response to a high level signal from the level controller 14 References
in the drains tank. This emergency drain valve also [1] Heilbronn, F. S.: Effects of stored steam and water upon the
opens in response to a high water level in the heaters. overspeed of large steam turbines after sudden loss of load:
All valves and drain pipework must be sized to pass Proc. IMechE, Volume 180, Part 3J: 1965-66
the bled-steam drains at maximum turbine capacity. [2] Kearton, W. J.: Steam turbine theory and practice: Pitman
Drains tanks are sized such that the time taken to fill [3] Nelson, W. G. and Waterman, A. W.: Advances in commer-
the volume bounded by the tank walls, and the upper cial aeroplane hydraulic fluids: SAE Committee A6, Aerospace
and lower limits of the control band, will be several Fluid Power and Control Technologies, Boston: 1974
times the control valve stroking time. [4] Brodie, J. K.: Entrainment studies PhD thesis: Heriot-Watt
Non-return valves are usually provided in the line University: 1969
to the heater flashbox to prevent possible refluxing
of water during transient operation, or backflow to
the condenser flash vessel from the heaters in the
event of valve malfunction. Since MSR vessels are 15 Additional references
situated at or near engine room floor level, sufficient Bergstrasser, G.: Reinforced concrete foundations for steam turbines
height is available underneath the vessel to accommo- Elekt: wirts, Volume 59 pp 805-809: November 1960
date adequately-sized drain tanks and provide a falling Fitzherbert, W. A. and Barnett, J. H.: Causes of movement in
drain to all possible destinations. The base of a vertical reinforced concrete turbo-blocks and development in turbo-block
design and construction: Proc. IMechE, Volume 181, Part 1 No 22,
reheater, however, may be low in the turbine hall pp 589-614: 1966-67
and a positive static head may not be possible for all
Flint, I. J.: Plant aspects of turbine generator foundations: Proc.
operating conditions. In this case, it might be necessary IMechE, Volume 181, Part 1 No 22, pp 567-578: 1966-67
to provide a pump which would have to be sited in the Haupt, L. and Probst P. H.: Civil engineering and vibration aspects
basement, or even in a pit, in order to provide the of steam turbine generator foundations in Germany: Proc. IMechE,
appropriate net positive suction head. Otherwise par- Volume 181, Part 1 No.22, pp 579-588: 1966-67
ticular drains might have to drive against an adverse Praefcke, R. O.: Steel foundations for the support of high-speed
static head. machinery: Proc. IMechE, Paper C7: 1983

240
C H A P T E R 3

Feedwater heating systems

Introduction 6.4.1 Length of U-tubes


6.4.2 Tube support plates
1 Feed system design
6.5 Bled-steam inlet
1.1 Introduction 6.6 Thermal design
1.2 Functional needs of the system 6.6.1 Desuperheating section
1.3 System configuration 6.6.2 Condensing section
1.4 Component design parameters 6.6.3 Drain cooling section
1.5 Component levels 6.6.4 Other factors affecting thermal design
1.6 Maintenance of system water content 6.7 Horizontal high pressure heaters
1.7 Protection against use of contaminated feedwater 6.8 Vertical high pressure heaters
1.8 Protection against ingress of water/steam to 6.9 Alternative designs of heater construction
turbines 7 De-aerating feedheaters
1.9 Summary
7.1 Introduction
2 HP feed system 7.2 Thermal/hydraulic design
2.1 Introduction 7.3 De-aerator construction
2.2 System parameters 8 Low pressure heaters
2.3 System configuration 8.1 Introduction
2.4 HP heater drains system 8.2 Surface type low pressure heaters
2.5 Pipework arrangement
8.3 Construction of low pressure heaters
3 De-aerator system 8.4 Water header, tube bundle and shell
8.4.1 Tube thickness
3.1 Introduction
8.4.2 Flow area
3.2 De-aerator heater
8.4.3 Tubeplate thickness
3.3 De-aerator storage tank
8.4.4 Water header wall thickness
3.4 De-aerator elevation
8.4.5 Water header branch thickness
3.5 Protection systems
8.4.6 Compensations for openings in the waterbox
3.6 Protection valves
8.4.7 Shell and dished end thickness
3.7 Pipework
8.5 Heater tube length and tube supports
3.8 Boiler feed pump suction filters
8.5.1 Tube support plates
4 Low pressure feed system 8.6 Bled-steam inlets and drain outlets
4.1 Introduction 8.7 Thermal design
8.8 External drain coolers
4.2 Low pressure system configuration
8.8.1 Thermal/hydraulic design of a flashing drain cooler
4.3 Pipework and valves
8.8.2 Thermal/hydraulic design of a water-to-water drain
5 Designs of feedheaters cooler
8.9 Direct contact low pressure heaters
6 High pressure feedwater heaters
9 Evaporators and other means of water treatment
6.1 Functional needs
6.2 Construction of high pressure heaters 9.1 Introduction
6.3 Water header, tube bundle and shell 9.2 Types of bled-steam evaporator
6.3.1 To find tube thickness 9.3 Surface type evaporator
6.3.2 Area required for flow through the tube bundle 9.4 Flash type evaporators
6.3.3 Tubeplate thickness 10 Future developments
6.3.4 Water header wall thickness
10.1 HP feed system
6.3.5 Header branch thickness
10.2 De-aerator system
6.3.6 Compensation for openings in the water header
10.3 LP feed system
6.3.7 Shell and dished end thickness
6.4 Heater tube length and tube supports 11 References

241
Feedwater heating systems Chapter 3

Introduction For all stations, the SVP is 160 bar; the SVT is
Regenerative feedheating has long been recognised as 565C for coal-fired boilers and 538C for oil-fired
a means of improving turbine-generator plant effi- boilers. The cold reheat pressure varies between 42
ciency and the first practical installation was on a and 44 bar. As all feed systems for these units use
3 MW set in a British power station at Blaydon Burn cold reheat (HP turbine exhaust) to supply steam to
near Newcastle-upon-Tyne in 1916. the final heater, the final feed temperature (FFT) can
From this modest beginning the modern feedheating only vary by a small amount due to the effects of
system has evolved, a typical feed system consisting of small variations in cold reheat pressure and the ter-
six to eight heat exchangers, each bleeding steam from minal temperature difference (TTD) of the final HP
the appropriate turbine cylinder. heater.
The economic justification for the use of a parti- Because of the economics of the advanced gas
cular configuration of feedheaters is given in Chapter cooled reactor (AGR) cycle, a lower final feed tem-
1 of this volume, in which it is explained how the perature of about 156C was specified (see Chapter 1)
theory of regenerative feedheating is combined with which has resulted in a feed system having the de-
the economic information the purchaser makes avail- aerator as the final heater.
able to the manufacturers to determine the most The relevant cycle details for the feed system for the
appropriate number and disposition of feed stages. pressurised water reactor (PWR) are also shown in
When the ideal cycle has been evolved, it is then used Fig 3.6.
as a basis for the determination of a practical design. The steam conditions for the 660 MW PWR of
The economic need to replicate proven turbine and 67 bar, 0.25% wet, result in the stop valve flow being
feed system components, whenever practical, places approximately twice that of a conventional 660 MW
restraints on the manufacturer. Usually these are of a unit and, in consequence, all flow components must
minor nature and will only change the ideal bleed be approximately 1.5 times their normal size to ac-
point pressures by a few tenths of a bar. The minor commodate the doubled flow. The PWR feed cycle
loss in efficiency is accepted in return for the use of is also more complicated than conventional fossil-
proven plant and the lower cost resulting from the fired units as provision has to be made to absorb
replication of existing designs. reheater and separator drains into the feed system under
The main parameters for the feedheating systems all conditions of operation, as shown in Fig 3.6.
of a range of typical modern 500 and 660 MW units Table 3.1 shows that the latest stations, such as
are shown in Table 3.1. The corresponding heater Littlebrook D and Heysham 2, are provided with tu-
arrangements are shown on Figs 3.1 to 3.6. bular surface type heaters to the exclusion of the
The turbine/boiler main cycle parameters of stop 'direct contact' (DC) heaters (i.e., feedwater and heating
valve pressure (SVP) and stop valve temperature (SVT) steam in direct contact within the heater shell). The
have been standardised for all modern fossil-fired 500 change in design philosophy was the result of a re-
and 660 MW units. view, in the early 1970s, of the cost effectiveness of

TABLE 3.1
Cycle parameters for modern power stations

Station Unit Fuel Stop Stop HP Final Number of Type of Fig ref
size valve valve exhaust feed stages LP
pressure temp pressure temp heater
MW (bar) (Q (bar) (Q HP LP
*
Ince B 500 Oil 159.6 538 44.02 252.2 3 4 DC 3.1
Grain 660 Oil 159.6 538 42.06 252.0 2 3 DC 3.2
Littlebrook D 660 Oil 159.6 538 42.0 251.1 2 3 Surface 3.3
Drax
Completion 660 Coal 159.6 565 43.4 254.7 2 5 Surface 3.4

Heysham 2 660 Nuclear 159.6 538 45.2 156.4 0 4 Surface 3.5

Projected
PWR units 660 Nuclear 66.77 + 5.86 226.7 3 4 Surface 3.6

* De-aerator not included in number given


+ 0.25% wet at stop valve

242
Introduction

the DC LP heater systems which were then currently route was provided for the BFPT exhaust to the con-
being employed. denser, the BFPT could also be run-up with the main
It was concluded from the review that tubular sur- unit. To increase cycle efficiency, heater bleed points
face type LP heater feed systems were more cost on the BFPT are provided. However, more than one
effective and they have been used for all subsequent heater attached to the BFPT can cause difficulties
660 MW units. in the feedheaters downstream of the heaters from the
As unit size increases, so does the power needed BFPT. The manner in which the BFPT has been
to drive the boiler feed pump (BFP), which is about integrated into the various feed systems is shown in
2 to 3% of main unit output. Multiple electrically- Figs 3.1 to 3.6.
driven BFPs could have been used but a more cost Cooling of the generator by condensate is not
effective solution at the time was to provide a tur- employed for the latest units. The complex and costly
bine driving a full-duty feed pump. From Figs 3.1 arrangements needed to ensure maintenance of prime
to 3.5 it is seen that each system uses a back pres- and freedom from boiling of stagnant condensate in
sure turbine as the BFP drive. Steam is taken from generator coolers on cessation of condensate system
the HP exhaust, expanded through the turbine and flow was the reason why a simple cooling package,
exhausted to the main turbine or to a heater. A live with indirect coolers using condenser cooling water
steam supply from the main boiler is provided on (CW), was developed and is now used. The loss in
the latest generation of boiler feed pump turbines efficiency is accepted in return for increased opera-
(BFPTs) to enable the turbine to drive the feed pump tional integrity and simplification, with consequent
under all conditions of unit load. As an alternative reduced maintenance costs for the condensate system.

243
244
BOILER
HOT REHEAT STEAM

GENERATOR
Feedwater heating systems

. . . . MAIN STEAM SUPPLY


REHEAT/BLED STEAM
FEEDWATER/CONDENSATE
DRAINS

DC3 EXTRACTION
PUMP

FIG. 3.1 Arrangement of feedheaters at Ince B power station


Chapter 3
GENERATOR

-^
pS
TURBINE
MOISTURE
- - " MAIN STEAM SUPPLY EXTRACTION ;
REHEAT/BLED STEAM CONDENSERS HsS
FEED WATER/CONDENSATE
DRAINS
5^^^-^
%

HP HEATERS

FIG. 3.2 Arrangement of feedheaters at Grain power station

245
Introduction
246
GENERATOR
Feedwater heating systems

L-^NSSNE& TWO ELECTRICALLY DRIVEN


BOILER FEED PUMPS
- - - . MAIN STEAM SUPPLY
_ REHEAT/BLED STEAM
. FEEDWATER/CONDENSATE
HP HEATERS DRAINS LP HEATERS

FIG. 3.3 Arrangement of feedheaters at Littiebrook D power station


Chapter 3
GENERATOR

-s^-^g-- 1

HP HEATERS LP HEATERS DRAIN COOLER - - - MAIN STEAM SUPPLY


REHEAT/BLED STEAM
FEED WATER/CONDENSATE
DRAINS

FIG. 3.4 Arrangement of feedheaters at Drax Completion power station

247
Introduction
248
BOILER

Wi GENERATOR
Feedwater heating systems

[S

CONDENSERS
(THREE OFF)

HS
GLANDl
STEAM[
ICONDENSER]

POLISHING
BOILER FEED BOILER PLANT
PUMP O. M F DE E
TURBINE Jj PUMP
TURBINE
LP MOISTURE
HEATERS DRAIN COOLER EXTRACTION
CONDENSER

. - - . MAIN STEAM SUPPLY


REHEAT/BLED STEAM
FEEDWATER/CONDENSATE
DRAINS

FIG. 3.5 Arrangement of feedheaters at Heysham 2 AGR power station


Chapter 3
Introduction

BLED STEAM LIVE STEAM


REHEATER REHEATER

-&E&E&-
LP HEATER
DRAINS PUMP

- MAIN STEAM SUPPLY


- REHEAT/BLED STEAM
. FEEDWATER/CONDENSATE
DRAINS

FIG. 3.6 Proposed arrangement of feedheaters for a PWR nuclear power station

249
Feedwater heating systems Chapter 3

1 Feed system design The above functions are the principal aims of feed system
design: how they have been achieved by the systems
installed in modern CEGB power stations is described
in the following sections.
1.1 Introduction
The feedheating system associated with a turbine pro-
vides the means by which the steam condensed in the
main condenser is fed to the boiler. It must also heat 1.3 System configuration
the feedwater by use of a series of heat exchangers as The number of feedheaters is determined by the applica-
demanded by cycle design. To provide both these ser- tion of the relevant economic factors, as explained in
vices requires a complex arrangement of heat exchangers Chapter 1. However, the theoretical bleed point pres-
and pumps, with hundreds of valves interconnected by sures are seldom obtainable because of constraints in
many kilometres of pipework. blading design. The actual points used are determined
Such a network of valves, pipes and heat exchangers by what is possible with current designs of blades and,
has many possible flow paths. The determination of flow in some cases, by standard cylinder modules. On all
paths and elimination of unwanted routes is critical for modern large reheat units, final feed temperature is
the design of a successful system. In this respect, the determined by cold reheat pressure as in all present
system design is analogous to electrical circuit design. fossil-fired plant the ultimate HP heaters are fed from
The configurations which have been developed over the HP cylinder exhaust (i.e., at cold reheat pressure).
the last fifteen years to meet the functional needs of feed A typical tubular surface type LP and HP feed system
system design in the most cost effective manner are is shown in Fig 3.7.
described in this section. In this system, the condensate formed in the condenser
is pumped by the condenser extraction pump through
the gland steam condenser (GSC) and the LP heaters
to the high level de-aerator. The elevated position of
the de-aerator provides the net positive suction head
1.2 Functional needs of the system
(NPSH) needs of the BFPs. In this context, the NPSH
To play its part in the boiler/turbine-generator cycle, needs of the BFP are defined as the head equivalent to
the feedheating system has to perform the following the pressure necessary, over and above the temperature-
functions: dependent saturation pressure at the inlet to the pump,
to prevent the feedwater from flashing into steam within
Provide the required amount of feedwater to the the pump. The capacity of the storage tank is available
boiler at a temperature dictated by cycle design. to meet any fluctuations in boiler demand. The feed
pumps draw from the de-aerator and discharge through
Maintain a stable suction regime for the boiler feed
the feed regulating valves and the HP heaters to the
pumps.
boiler.
Contain a buffer store for water to allow for a short An alternative system with DC LP heaters and tubular
term mismatch between boiler demand and available surface HP heaters is illustrated in Fig 3.8. The con-
feedwater. densate is extracted from the condenser and pumped
through the GSC and the generator coolers up to the
In the longer term, to keep the water content con- first LP DC heater. The condensate cascades from LP1
stant. to LP3 DC heater via LP2. A DC heater extraction
pump, pumps the water from LP3 heater up to the high
Supply water to the boiler with an acceptable oxygen level de-aerator. The BFP draws from the de-aerator tank
content. and discharges to the boiler via the feed regulating valves
and the HP heaters.
Automatically cut off the supply of contaminated
feedwater to the de-aerator, and hence to the boiler,
in the event of ingress of chlorides due to inleakage
of the condenser cooling water or chemicals from the 1.4 Component design parameters
polishing plant. To determine the physical sizes of the various com-
ponents used in the feed system the flows, pressures and
In the event of a turbine trip or sudden reduction of temperatures must be known. These are provided by the
unit load, the stored energy within the feed system turbine manufacturer in the form of a series of heat
must not overspeed the turbine-generator. balances which cover the whole of the range of expected
cycle operation. As the design point for a component
Be so engineered as to protect the turbine from may be other than constant maximum rating (CMR)
possible reflux of water or water/steam mixture from conditions, it is important that the whole spectrum of
the feed system under all conditions of operation. operational duty is examined by the manufacturer be-
250
VENT CONDENSERS
CONDENSATE/FEEDWATER BLED STEAM NON RETURN VALVE (BSNRV)
XXT K f :
. . . . CONDENSATE DRAINS
MAIN STEAM SUPPLY
. . . . HP BLED STEAM
HOT REHEAT STEAM
- H P BLED STEAM
LP BLED STEAM

LIVE STEAM
FROM BOILER
Feed system design

251
FIG. 3.7 A feedheating system incorporating all-tubular surface type feedheaters
CONDENSATE/FEEDWATER
1
HP CONDENSATE DRAINS
MAIN STEAM SUPPLY
-COLD REHEAT STEAM
NORMAL ROUTE FOR

252
HOT REHEAT STEAM
HP HEATER DRAINS
IP BLED STEAM
LP BLED STEAM

CONDENSATE ISOLATING
VALVE (CIV)
Feedwater heating systems

FEED WATER
ISOLATING VALVE
(FWIV)

BANK "A" HP HEATERS

HP HEATER DRAINS LIFT PUMP


Chapter 3

FIG. 3.8 A feedheating system incorporating direct contact LP heaters and tubular surface type HP heaters
Feed system design

fore the component is designed. From the heat bal- heater drains can cascade by gravity to the condenser,
ances, the most appropriate design conditions for each as depicted in Fig 3.11.
part of the system are determined, and the value and Gravity drainage allows operation at low unit load and
cost of special provisions to maintain unit output unit start-up without alternative drainage arrangements,
under abnormal conditions is evaluated. The physical using pumps or special operational procedures.
design of the individual components is discussed in On those stations which use direct contact LP heaters,
detail in Section 5 of this chapter. the method of fixing the heights of the heaters is more
complex. A typical DC heater level diagram is shown
in Fig 3.12.
The elevation between two adjacent DC heaters is
1.5 Component levels arranged to accommodate a column of condensate which
Consideration must also be given to the elevations at forms a seal between adjacent heaters. The seal is
which the various feed system components are placed. provided in the form of a loop. The condensate column
Their relative elevations are of prime importance as they counter balances heater differential steam pressures,
influence the ability of components to meet the func- pipework and waterbox/spray losses.
tional needs of the system. The levels at which the various The height of the condensate column at full-load is
components are installed for a feed system using sur- about half the vertical separation between heaters. The
face type heaters are shown in Fig 3.9. loop seal must be of sufficient depth to withstand the
Taking the LP turbine horizontal centre line as the most severe turbine load changes envisaged; for if it
datum, the vertical height of the condenser and its were ruptured by a temporary reversal of condensate
transition piece, between condenser and turbine, com- flow, two turbine stages would become directly connected
bined with the NPSH needs of the condensate ex- and there would be the possibility of steam and water
traction pump, determine the basement depth needed being transferred to the lower stage.
below the machine. The water level in the condenser Further information on the detailed dynamic be-
hot well is fixed by the individual condenser design. haviour of DC feed systems is to be found in the paper
Assuming a transverse condenser for each turbine LP by Dartnell [1] and the hydrodynamic aspects are
cylinder, the water level is set at a convenient height examined by Kubie, Rowe and Jones [2].
above the condenser bottom. As the traditional split- The height of the de-aerator relative to the boiler feed
casing design of extraction pump usually stands on the pump is important as this provides the static head on
basement floor, the basement depth has to be set to the BFP suction to satisfy its NPSH needs under all
provide the head of condensate needed to satisfy the conditions of operation. The other considerations which
extraction pumps NPSH. However, current practice can influence de-aerator tank height are discussed in
is to use a vertical multistage condensate extraction detail in Section 3 of this chapter.
pump of the 'caisson' type, which is sunk into a local
pit in the basement floor. Use of this pump design
allows the basement floor to be set just below condenser
bottom-plate level as the pump impellers can be placed 1.6 Maintenance of system water content
as far below floor level as needed. The principles in- The de-aerator tank provides a reservoir of water on
volved are illustrated in Fig 3.10. It is evident that the which the feed pump can draw should there be a
use of a caisson type of extraction pump reduces the mismatch between the feed requirements of the boiler
basement depth and thereby reduces station cost. A and the condensate flowing into the de-aerator tank.
detailed description of the various types of extraction There is typically 7-10 minutes' worth of constant
pumps used in CEGB power stations is given in maximum rating (CMR) feed waterflow stored in the
Chapter 4. tank. To allow for normal gains and losses to the
On the latest stations with all surface-type heaters de-aerator tank content, insurge and outsurge systems
(excluding the de-aerator), a horizontal heater attitude are provided to maintain the tank content as near to a
is adopted as opposed to the traditional vertical posi- constant value as is operationally necessary. As illustrated
tion. This allows the heaters to be placed below the in Fig 3.13, the insurge and outsurge connections to
bottom of the turbine cylinders but above the con- and from the reserve feedwater tanks (RFTs) are made
denser water level. The heater levels are set with suffi- to the LP feed system to allow adjustment of the
cient static head for them to cascade by gravity from total cycle water content. During normal operation,
the highest pressure HP heater to the lowest pressure, the large content of the tank smooths out any sudden
and then to the condenser. Even when set at these levels, small changes in demand and so allows the insurge/
by using horizontal heaters it is possible to arrange the outsurge valves to respond in a controlled manner to
bled-steam pipework to have a continuous slope from restore the tank level to normal.
the bleed point on the turbine down to the heater. The In the event of a low level in the de-aerator tank, the
same arrangement is also possible with horizontal LP insurge group feeds into the condenser from where
heaters. This has the important advantage that the it is pumped forward to the de-aerator tank by the
bled-steam lines can drain towards the heaters and the condensate extraction pumps. This continues until the

253
Feedwater heating systems Chapter 3

EXTRACTION PUMPS

TURBINE GLAND STEAM CONDENSER

FIG. 3.9 Pictorial representation of the relative levels of heaters and feed pumps for a power station using horizontal
HP and LP tubular surface type feedheaters

254
Fuel system design

CENTRE LINE OF LP TURBINE

^ ^ $ : & # $ 5 f NPSH AS (

M$mw
O.QP^ri& <>Qc NEEDED ,
>rt'0.: ^*7* BY PUMP -

m i
CAISSON TYPE v ?-
EXTRACTION PUMP ?*.&
CENTRE LINE
OF 1ST IMPELLER

FIG. 3.10 Determination of basement depth


(a) Distance from centreline of LP turbine to bottom of casing determined by manufacturer to allow room for casing, etc.
(b) Depth of condenser neck determined by the need to uniformly distribute steam from the LP turbine exhaust to the
tubeplate ends of the condenser. Angle of flare is fixed to give minimum height conducive with uniform steam distribution.
(c) Tubenest depth is designed to achieve optimim thermal performance by the tubenest commensurate with the distance
between LP cylinders.
(d) Sufficient space must exist at the bottom of the tubenest to allow steam access to the bottom tubes.

water level in the tank is restored to its normal work- caused to turbines by the ingress of water or a water/
ing level. If the de-aerator tank level is higher than the steam mixture from the feed system have been reported
setpoint, the outsurge valve is opened and the excess [3,4,5].
water is discharged from the system to the RFTs until There are several potential sources of water within
normal working level is restored. The method by which the feed system which can flow or be induced into the
these systems are integrated into the LP feed system is turbine. The potential sources are as follows:
described in Section 4 of this chapter.
(a) High water level in an H P or LP feedheater. The
high water level could be caused by a tube leak or
failure of the drainage arrangements.
1.7 Protection against use of contaminated (b) High water level in a de-aerator. If there is a
feedwater mismatch between inflow and outflow the vessel
Should there be an inleakage of cooling water into can flood.
the condenser, the feedwater to the boiler could be (c) Undrained bled-steam lines. When the bled-steam
contaminated. Contamination of feedwater can also is wet, the water in the steam is deposited on the
result from the inadvertent release of chemicals from a pipework walls or is separated when a valve or
polishing plant. bend is encountered. Condensate is also formed
Modern boilers can sustain severe damage from on start-up, while the lines are being warmed to
contaminated feedwater. To prevent feedwater of an operating temperatures.
unsuitable quality being fed to the de-aerator storage
tank and from there to the boilers, or outsurged to
the reserve feedwater tanks, protection valves which In the case of items (a) and (b), if the rising level is
are tripped shut on high conductivity levels are placed allowed to continue unchecked, then it could flood
upstream of the outsurge connection and downstream into the bled-steam line and back to the turbine.
of the polishing plant (if provided), as illustrated in With regard to item (c), if there is continual fall from
Fig 3.14. The hardware and detail design is discussed the points where the water is accumulating towards
in Section 4 of this chapter. the extraction point on the turbine, it will most cer-
tainly flow against the steam flow towards the turbine.
The other means by which water or a water/steam
mixture can be induced into the turbine is by a pres-
1.8 Protection against ingress of water/steam sure reversal between the feed heaters and the turbine
to turbines bleed points. A pressure reversal is caused by a unit trip
Many well documented instances of damage being or a sudden load reduction.
255
Feedwater heating systems Chapter 3

FROM LP HEATERS , ( )
V HEAD J

NORMAL WOflKfNG LEVEL {NWU


bi JIZL

OEAERATOR STORAGE TANK

TO BOILER FEED PUMP SUCTION

TURBINE DRIVEN
BOILER FEED PUMP

RESERVE FEED I
WATER TANK HP5B HEATER

I _ / ^ HP4B
H E A T ER
HP4A f V j I
. . . , _ ASH BOX Y HEATER W _ 7 |

,RTING STANDBY = = :

FIG. 3.11 Component level diagram for tubular surface type HP and LP heaters

256
Feed system design

> -

y-
STORAGE TANK
3
TO FEED PUMP SUCTION

S~\ r~\
DC3 HEATER

7*:

A

L^s^J DRAINS BOILER DC3
FEED EXTRACTION
A PUMP f
PUMP
DRAINS

--
I PUMPAI
iLTITANK
HP CONDENSATE EXTRACTION PUMP

FIG. 3.12 Component level diagram for direct contact LP heaters

On unit trip, the HP turbine pressures decay rapidly the de-aerator tank at just below the saturation equi-
and the IP/LP turbine pressure falls to condenser valent to the turbine bleed point pressure, has the
vacuum almost immediately. The pressures in the feed potential to evolve sufficient steam to overspeed the
system change slowly compared with the turbine, and turbine in the event of a turbine trip. To ensure that
large pressure differentials will be created with the this cannot happen, a power-assisted closing non-return
potential to cause flow towards the turbine from the valve is placed in the steam line between the turbine
feed system. The large quantity of water stored in and the de-aerator. In addition to tripping the non-

257
Feedwater heating systems Chapter 3

OPEN ON CLOSE ON
FALLING RISING
LEVEL LEVEL

FIG. 3.13 Typical insurge and outsurge system

return valve, the bled-steam isolating valve is also Flow in both normal and reverse direction must
arranged to be shut on unit trip. be considered and, where provision to prevent flow
Reverse steam flow can also carry quantities of in one direction is provided, care must be taken to
water from heaters and undrained low points in the ensure that there are no 'sneak' paths to bypass the
bled-steam lines into the turbine and cause damage, protection. It is evident that the protection system
particularly to the large LP turbine blades. These must contain flooding and also prevent back flow of
'back flows' can induce cooler steam into hot cylinders, steam.
with the consequent risk of thermal distortion. The following provisions (illustrated in Fig 3.15)
This is an example of how a system must be have been made on all 500 and 660 MW units within
designed to allow for all conditions of operation. the CEGB to prevent these possibilities:
258
Feed system design

OUTSURGE CONNECTION
i

DUPLICATE PROTECTION
VALVES. AIR OPENING
SPRING CLOSING

INSURGE FROM
RESERVE FEED WATER TANK

CONTAMINATED WATER
SENSORS
00 [00] 00
\ CONDENSER EXTRACTION
PUMPS

POLISHING
PLANT
EMERGENCY INSURGE CONNECTION

M-
CONTAMINATED WATER
SENSORS

VALVE TO MAINTAIN
A CONSTANT WATER
& ~ LEVEL IN CONDENSERS

RECIRCULATION CONNECTION
FOR LOW LOAD OPERATION

GLAND STEAM
CONDENSER

FIG. 3.14 Devices installed as protection against the use of contaminated feedwater

(a) A non-return valve is placed in the bled-steam line cuits to close the protection valves.
as close to the turbine bleed point as practicable.
(e) In some instances the pumps which discharge to
For the de-aerator and HP heaters, these are
a particular heater are tripped.
power-assisted non-return valves. For the LP heater
bleed points, free-acting valves are normally pro- (f) All bled-steam lines have an adequate fall towards
vided. On very low pressure heaters, the omission a drainage point. Each drainage point is capable
of the non-return valve is permissible if the con- of draining by gravity to the drain receiver vessel,
ditions given in (g) have been satisfied. which is at condenser vacuum. Any pockets of
water which can be formed by the closure of valves
(b) Power-operated bled-steam isolating valves are
have drains.
provided on each line between the turbine and a
heater, as close to the heater as is practicable. Again, (g) In the case of very low pressure heaters such as
on very low pressure heaters the isolating valves turbine moisture extraction condensers (which ex-
can be omitted provided the conditions given in (g) tract a steam/water mixture before the last blade
have been satisfied. in the LP turbine), the pressure drop caused by
the isolating and non-return valves as specified
(c) Feed or condensate isolating valves are provided,
in (a) and (b) may be unacceptable so, instead,
where appropriate, to shut off the supply of water
duplicate unvalved drains (which can drain the
to a heater or group of heaters.
heater by gravity alone) are provided between the
(d) Duplicate level sensing devices are provided on heater and the condenser. The feedwater flow to
each heater, either of which will actuate trip cir- the heater is also isolated in the event of a high

259
Feedwater heating systems Chapter 3

CENTRAL CONTROL ROOM


ALARMS

ELECTRICAL SIGNALS

FIG. 3.15 A typical feedheating plant showing protection equipment

water level in the heater. The protection provided of protection relay and associated tripping circuits
is illustrated in Fig 3.16. are described in Volume F, which deals with control
and instrumentation.

Because of the short time scale in which the com-


mencement of water feed back to the turbine can
occur, all protection measures are automatic and the 1.9 Summary
hardware provisions for each type of heater is detailed The previous sections give an outline of the main
in the appropriate section of this chapter. The types principles for overall feed system design: to explain
260
HP feed system

FLOAT SWITCHES

SECONDARY DRAIN
WITH LOOP SEAL

FIG. 3.16 Drainage arrangements for very low pressure heaters without valves in bled-steam lines
In the event of tube leaks causing a rising water level, Level 1 raises an alarm, Level 2 shuts the condenser isolating valves
just before the water reaches level 3, and Level 3 is the point at which the drains commence to flow through the second
emergency drain. The secondary and primary drain combined, have a capacity to discharge the flow of many fractured tubes
in addition to the normal drain flow and, if Level 2 was above Level 3, multiple tube failures would remain undetected.

how these principles are expressed in terms of detailed 2.2 System parameters
system design, the feed system description has been The final feed temperature (FFT) out of the ultimate
split into three sections, viz: HP heater is fixed within a few degrees by the bleed
pressure and steam temperature available to the heater.
HP feed system. On all current 660 and 500 MW units, the bleed point
is the HP exhaust or 'cold reheat' pressure.
De-aerator system and associated plant. The feed temperature out of a heater is conditional
on several factors. First, a bled-steam pipework tem-
LP feed system. perature loss, usually 1.1C, which is subtracted from
the saturation temperature equivalent of the bleed
point pressure. The resultant temperature is the sat-
uration temperature equivalent to the pressure of the
2 HP feed system steam entering the heater shell. The heater thermal
performance and hence its heat transfer surface is
determined by the values of the temperature terminal
differences (TTDs) on the steam and drain sides.
2.1 Introduction The steam TTD is defined as the temperature dif-
The HP feed system is defined as the group of heaters ference between the saturated steam temperature at
and associated equipment which is situated in the feed entry to the heater shell and the feed water leaving the
pipework between the boiler feed pump (BFP) dis- heater. The drain TTD is the temperature difference
charge and the boiler. Their function is to accept water between the feedwater entering the heater and the
from the boiler feed pumps and raise the feedwater drains leaving the heater. To achieve optimum HP
temperature to the final feed temperature. heater performance, it is usually necessary to partition

261
Feedwater heating systems Chapter 3

each HP heater into three zones; namely, the de- The TTDs are determined by the economics of the
superheating, condensing and drain cooling zones. The cycle, the increase in cycle efficiency by use of smaller
effect which TTDs have on the size of these zones TTDs being weighed against the increased cost of heater
is fully explained in Section 6 of this chapter. surface.
By applying the line temperature drops to all HP
heater bled-steam extraction pressures and the steam
TTDs, the feed temperature out of each of the HP
heaters is determined. Once the temperatures out of 2.3 System configuration
the heaters (and hence into the next heater) are known,
the drain temperatures are found by applying the The number of HP feedheater stages is determined by
drain TTDs. However, it should be remembered that cycle economics and can vary between two and four. The
the smaller the TTDs, the greater will be the heat standard configuration of HP heaters at all 660 MW
transfer surface to achieve the intended performance. stations (with the exception of those with three units)
HP heaters which are supplied with steam with a is two banks of half-duty heaters in parallel.
high degree of superheat can have negative TTDs, Conventional hemispherical water headers are dif-
the higher feed temperatures out of the heaters being ficult to manufacture in a size greater than that capa-
made possible by the total steam temperature as seen ble of accepting 50% of the feed flow for a 660 MW
by the desuperheating zone. Figure 3.17 illustrates the unit. However, there is one 660 MW station which has
principles explained above and shows typical TTDs a single line of HP heaters where a special toroidal
for a 660 MW unit and the resultant heater inlet, outlet water head design was used. It has not proved cost
and drain temperatures. It should be noted that the effective and has not been repeated. The limiting fac-
second HP heater draws its steam from the BFP tur- tor is tubeplate thickness which is dependent on tube-
bine which is relatively low in superheat, hence the plate diameter and feed line pressure. To reduce the
steam TTD is larger than that of the ultimate heater diameter, the feed flow is divided between two 50%
which has more superheat in the bled-steam. banks of heaters.

P = BAR ABS
T = TEMPERATURE
P = 42.0 ts = SATURATION TEMPERATURE
ts = 253.2C
T = 340.0C t = BLED STEAM LINE TEMPERATURE DROP
STTD = STEAM TEMPERATURE TERMINAL DIFFERENCE
DTTD = DRAIN TEMPERATURE TERMINAL DIFFERENCE

BOILER FEED PUMP


TURBINE

A t = 1.1C

P = 14.13
ts = 195.4C

ts = 253.2 - 1.1 = 252.1C ts = 195.4 - 1.1 = 194.3C


P = 41.25 AT HEATER P = 13.8 AT HEATER

DRAIN COOLING DRAIN COOLING


SECTION SECTION

252.1 - 1.0 = 251.1C


& 152.0C DISCHARGE FROM
^ BOILER FEED PUMP

DESUPERHEATING SECTION

152.0 - 10.0 =J62.0C T0 DEAERATOR


STORAGE TANK

FIG. 3.17 Application of temperature terminal differences to heaters to find the temperature of feedwater and drains

262
HP feed system

To minimise the greatest pressure to which the HP Considering the functions of the feedwater isolating
water headers are subjected, they are placed down- valves under normal conditions of operation, water
stream of the feed regulating valves. As there are no flows from the boiler feed pumps through the heaters
isolating valves between the HP heaters and the boiler to the boiler. The by-pass is in the closed position, as
with the heaters in this position, the maximum pressure the spring-loaded valve is set such that it does not
they can be subjected to is boiler relief valve pressure commence to open until a heater bank is isolated on
and cannot be subjected to feed pump shut-off head. the water side. Assuming that the feed flow is to be
Nevertheless, the design pressure is in the region of proportioned so that 60% flows through the remain-
207 bar, which results in a typical 50% heater water ing active bank and 40% through the by-pass, the
header shell thickness of about 120 mm and a typical redistribution for a typical pair of HP heaters is
tubeplate thickness of 350 mm. shown in Fig 3.20. Representative friction losses for
The difficulty in the manufacture of a thick tube- each heater are used to demonstrate how the head
plate is in drilling the holes through the tubeplate. loss across the spring-loaded by-pass valve is deter-
Conventional methods of drilling holes do not pro- mined. Should the pressure loss across the by-pass
vide the straightness nor roundness needed. The gun valve be larger than needed, the flow through the
drilling technique originally developed for ordnance active bank will increase to balance the pressure loss,
work, which allows deep drilling with a high degree which leads to excessive steam flows. The larger steam
of hole straightness and without the need for sub- flows could lead to damage of the external tube sur-
sequent reaming or honing, is the usual method used face from greater than design steam velocities within
to deep-drill thick tubeplates. Details of the toroi- the heater. The topic of steam-flow-induced damage
dal water head and of the gun drilling method can to heater tubes is discussed in Section 6.3 of this
be obtained by reference to Spence, Ryall and Mc- chapter. There is also the possibility of erosion damage
Connell [6]. To date, even using the gun drilling to the internal surface of the tubes from high velocity
method, tubeplate thickness has been limited to about feedwater due to the excessive flow through the active
350 mm. bank.
The configurations of a single and double line of The spring-loaded by-pass system is the simplest
HP heaters are shown in Fig 3.18. The main advantage by-pass system in current use; but in the past, diffi-
of a double line of heaters is their flexibility in opera- culties in setting and maintenance of the by-pass
tion. Assuming a typical feed system, where each line valves led to the use of alternative designs of by-pass
or 'bank' normally accepts 50% flow, but on isolation system. Systems using motorised parallel slide valves
of the active bank will accept 60%, then with one for both HP heater isolation and by-pass have been
bank by-passed the FFT will be approximately 215C. provided. This requires a complicated control sequence
On the loss of the top heater of a single bank con- to be provided, using many electrical relays and valve
figuration, the FFT falls to the temperature at the limit switches. A typical isolation sequence would be:
outlet of the next HP heater of 209C. While the
boiler can accept both of these conditions, there is Open by-pass valve.
a consequent loss in cycle efficiency for the lower
final feed temperature. When by-pass valve is fully open, allow sequence
One bank of a double-bank configuration of HP to start closing the isolating valves. (A system which
heaters (as used at Drax Completion) is shown dia- allows by-pass and heater isolating valves to act in
grammatically in Fig 3.19, with all major valves and antiphase has also been used.)
control devices indicated. In the event of a high water Close isolating valves.
level being detected in a heater, the bank associated
with that heater is automatically isolated on the steam
and water sides. The isolation procedure is in accord- Opening the isolating valves is the reverse of the
ance with provisions (a) to (d) of Section 1.8 of this closing sequence:
chapter (Protection against ingress of water/steam to
turbines), and follows from receipt of a signal from Open isolating valves.
any one of the duplicated water level sensing devices
on any heater in the bank: When isolating valves are fully open, allow sequence
to start closing the by-pass valve.
The power-assisted bled-steam non-return valves Shut by-pass valve.
are given a closing signal.

The bled-steam isolating valves close on all heaters In the event of sequence malfunction, it is possible to
in the bank. have both isolating and by-pass valves shut at the
same time. To allow an alternative path to the boiler,
The feedwater isolating valves for the bank are an emergency by-pass spring-loaded valve is sometimes
closed. provided to act if all normal routes to the boiler are
263
Feedwater heating systems Chapter 3

' BANK 'B' BANK

254.7C 254.7C

100%
BYPASS

100% FLOW
50% FLOW 60% FLOW %- 60% FLOW 50% FLOW
(NORMAL) (BYPASS) (BYPASS) (NORMAL)

40% BYPASS
100%
BYPASS

185.4C 185.4C

a) When top heater bypassed feedwater b) One bank bypassed due


temperature to boiler -209C to fault on top heater
in bank
60 x 254.7 + 40 x 185.4 = 215C
100

FIG. 3.18 Configurations of single and double banks of HP heaters

264
HP feed system

ANTI-SYPHON ANTI-SYPHON
VALVE VALVE

BLED STEAM LOOP PIPE

TO'B'HEATER - - TO'B'HEATER

FROM FEED PUMP

VALVES
1. BLED STEAM NON RETURN VALVE HP7A (SPRING ASSISTED CLOSING)
2 BLED STEAM NON RETURN VALVE HP8A (SPRING ASSISTED CLOSING)
3 BLED STEAM ISOLATING VALVE HP7A (MOTOR OPERATED)
4. BLED STEAM ISOLATING VALVE HP8A (MOTOR OPERATED)
5. BANK INLET FEED WATER ISOLATING VALVE (MOTOR OPERATED)
6. BANK INLET FEED WATER ISOLATING VALVE BYPASS VALVE (MOTOR OPERATED)
7. BANK OUTLET FEED WATER ISOLATING VALVE (MOTOR OPERATED)
8. SPRING LOADED BYPASS VALVES

FIG. 3.19 The A bank of heaters at Drax Completion power station


In the event of a high water level in either heater being detected by the duplicated sensing devices (float switches), air is
released from the non-return valves /, 2 and the springs assist valve closure. Feedwater and bled-steam isolating valves, 5, 4y
5, 7 close and water flows forward to the boiler via the by-pass valves 8. The heaters are thus isolated on the bled-steam and
feedwater sides and the turbine is protected against reflux of water from the HP heaters.

isolated. The system as described above is expensive mum closing time of about 20 seconds. The rate of
to provide and maintain, and so the simple spring- flooding of certain designs of vertical HP heater for
loaded by-pass system has been adopted as current the 500 MW units, assuming a double-ended tube fail-
practice with improved methods of setting and main- ure and blocked drains, is about 25 mm/s. With this
taining the spring-loaded by-pass valves. rate of flooding, the time for the water to rise from
Another principle in current use is to utilise the the normal working level (NWL) to the bottom of
energy in the high pressure feedwater to close the the bled-steam connection is about 8 s. To provide a
heater isolating valves. The use of feedwater energy margin, a factor of 2 is used to allow for the valve
'medium'-actuated valves is not an original idea but speed of closure increasing due to operational factors
the method by which it is achieved is new. There were and uncertainties in calculation of flooding rates. To
two reasons why medium-actuated valves were con- meet these needs, valves with a closure time of about
sidered: reliability and speed of actuation. 4 s are required; however, the flooding time of vertical
Motor-operated parallel slide valves of the size HP heaters can be extended by making the steam
required for HP heater isolation duty have a mini- pipework loop vertically to a suitable level before
265
Feedwater heating systems Chapter 3

50% 0% 50% 60% 40% 0%


FLOW FLOW FLOW FLOW FLOW FLOW

K5


(a) Both A & B banks in service (b) Bank B bypassed

FIG. 3.20 Distribution of flows through HP heaters when one bank of a two-bank heater system is by-passed
To maintain design flow in the active bank, friction loss across spring-loaded by-pass valves must equal friction loss through
the active bank. For normal flow, friction losses through A and B banks are equal. Neglecting pipework losses in the by-pass
line as small, friction loss over the active bank is (60/50) times normal operational value. The by-pass valve must pass 40%
flow with a friction loss equal to 1.44 times a normal (50%) bank friction loss.

leading it to the turbine. The shell volume is then pass and isolation in about 12 s from receipt of a
available to contain the flooding water up to the level signal to isolate the heater bank. Figure 3.21 shows
of the top of the bled-steam pipe loop, as shown in the diagrammatic arrangement of the system and gives
Fig 3.27. a brief explanation of how it works.
The medium-actuated feed isolating valves installed Figure 3.22 is a more detailed drawing of the iso-
on the HP heaters at Grain power station are ex- lation valve with a brief description of the salient
amples of these valves and are designed to give by- design features. The most important features to note
266
HP feed system

q p /

a MEDIUM ACTUATED INLET ISOLATING AND BYPASSING VALVE


b MEDIUM ACTUATED OUTLET ISOLATING VALVE
c RESTRICTOR VALVE TO GOVERN SPEED OF VALVE CLOSING
d DIRT TRAP
e SPRING ACCUMULATOR
f VALVE SPINDLE WHICH CARRIES PISTON AND VALVE HEAD
g NON RETURN VALVE
R QUICK ACTING CYLINDER EVACUATION VALVES, AIR ACTUATED - AIR TO CLOSE
I BANK PRIMING VALVE, AIR ACTUATED - AIR TO OPEN - SPRING CLOSED
FEED WATER PUMP VALVES, AIR ACTUATED - AIR CLOSE
ic CONTROL CUBICLE
I HIGH WATER LEVEL SWITCHES ON HEATER BODY
m l & m2 SOLENOID VALVES IN THE ENERGISED STATE
n SOLENOID VALVES IN THE DE-ENERGISED STATE
o FLOW RESTRICTOR
p PRESSURE REGULATOR
q AIR FILTER
r AIR SUPPLY
S LIMIT SWITCH ON VALVES SPINDLE

FIG. 3.21 Dewrance medium-actuated HP feedwater isolating and by-pass valves


If a high water level is detected in either heater, valves h are opened by solenoids ml being de-energised. Feedwater pressure
forces valves h from their seats and the feedwater from below the pistons in valves a and b is released to drain. The feed-
water pressure on top of the valves, forces the valve head to the by-pass and heater isolation position in the main valve 0,
and to the heater isolation position in valve b. The by-pass is now in operation and the heater bank is isolated. The feed
dump valves are now opened by the de-energised solenoid valves m2. The dump valves have light return springs which allow
them to re-seat when the feed side of the bank has depressurised to a nominal value. The restrictors o are provided to give
controlled opening or closing of the pneumatically-operated valves, as required. Limit switches s give indication of valve posi-
tion. When all high water level signals have been cleared and the bank is to be reinstated, the priming valve / is opened by
initiating the priming procedure which energises solenoid valve n (only possible when HWL alarms are removed). The initia-
tion of the priming procedure energises solenoid valves ml and m2 and so closes valves h and j . When pressure in the bank
is equal to feed pressure, valves a and b will return to their initial state (as shown in the diagram) under the action of the
force caused by the unbalanced area of the valve spindle of each valve.

267
Feedwater heating systems Chapter 3

produce whatever closing force is needed to close the


HAND WHEEL SPINDLE
valve as swiftly as the system hydraulics will allow.
(ONLY USED TO LOCK VALVE SHUT)
NORMALLY SCREWED BACK However, the system is complicated and costly, and is
only needed if heater flooding times are measured in
TO UPPER LIMIT

seconds, as with some designs of vertical heaters. The


cost benefits of increased reliability must be included.
The bled-steam lines to the heaters are isolated by
motorised parallel slide valves. The power-assisted non-
return valves are given the signal to close but will re-
MAIN VALVE SPINDLE

main open until the closing spring can overcome the


reducing steam flow tending to keep the valve open.
When the heater bank is isolated on the steam and
GLAND AND SPINDLE
feedwater sides, small heater shell drains are operated
BEARING HOUSING
which discharge to the condenser. Due to the action
of the heater vents, assisted by the shell drains, the
GLAND PACKING

pressure in heaters and the associated steam and drain


SHEAR BLOCKS
pipework within the isolation valves will fall to con-
SEALING RING
BACKING RING
denser vacuum.
SEALING RING The duplicate water level sensing devices which
SHEAR BLOCKS TO
HOLD TOP COVER initiate a bank trip due to a HWL are float switches
UPPER HALF OF
ACTUATING PISTON
PRESSURE FROM SYSTEM
(INTO THE DRILLING) manufactured by Mobrey to meet the plant manu-
LOWER HALF OF
CYLINDER TOP COVER
PISTON RINGS facturers' and CEGB needs (see Fig 3.23). Also illus-
ACTUATING PISTON
trated are the methods used for testing the duplicate
CYLINDER LINER
float switches with the heaters in operation.
The overall electrical control scheme is described
TO QUICK ACTING
CYLINDER EVACUATION in Volume F. This gives full details of the duplicated
VALVE
electrical supplies from the 110 V DC system which
powers the duplicate high integrity master tripping
relays. The master tripping relays initiate all protection
HEAD SECURING RING
valve closures except for the autonomous action of the
bled-steam non-return valve due to a pressure reversal.
In the event of a turbine trip, a separate signal trips
the master tripping relays which shut all the protection
valves on both banks.

FIG. 3.22 Dewrance medium-actuated valve, 2.4 HP heater drains system


outlet valve shown The combined HP heater drains should be discharged
When feedwater is released from the underside of
the piston, the full feed pressure causes the piston to the de-aerator under all possible conditions. The
to move down to close the valve. As the spindle moves simplest method to achieve this is to use the pressure
down, the flow is restricted by the increasing size of differential between the lowest pressure HP heater
the tapered portion of the spindle entering the cylinder
liner exit port which is concentric with the spindle. This
and the de-aerator to overcome the static head and
progressively slows the valve head as it approaches the friction between the HP heaters and the de-aerator
seat, so allowing swift closure without seat impact damage. tank.
This feature also helps prevent hydraulic shock caused by
swift valve closure. Figure 3.24 illustrates a typical drains system, show-
ing the control valves and relative levels of equipment.
A system with the HP heaters in a horizontal attitude
is shown. As the unit load decreases, the pressure
from Figs 3.21 and 3.22 are the provision for the differential between the HP heater and the de-aerator
system to fail safe (i.e., to isolate the feedwater side decreases to a point where there is insufficient pres-
of the heaters), and the slowing down of the closing sure head to raise the drains to the de-aerator storage
stroke over the last few millimetres to ensure that tank. The drains are then diverted to the condenser.
no hydraulic shock can occur due to sudden valve The converse applies on increasing unit load. In this in-
closure. As the feedwater isolating valves have a stance, the level in the heater is used to determine
protective function, high integrity is important. The the destination of the drain water. A rising water level
use of the feedwater as a medium to close these valves, in No. 6 heater opens the control valve to the No. 5
ensures that a pressure source to actuate the valves heater flashbox or to the de-aerator storage tank. The
is always available and the actuator can be made to destination chosen is under the manual control of
268
HP feed system

a ISOLATION VALVE TOP COLUMN 1


b ISOLATION VALVE TOP COLUMN 2
a) Mobrey float switch c ISOLATION VALVE BOTTOM COLUMN 1
d ISOLATION VALVE BOTTOM COLUMN 2
e ISOLATION VALVE TOP COLUMN 3
f ISOLATION VALVE TOP COLUMN 4
g ISOLATION VALVE BOTTOM COLUMN 3
h ISOLATION VALVE BOTTOM COLUMN 4

b) Mobrey float switch arrangement using vacuum to lift the water to on load test the switches c) Mobrey float switch arrangement using condensation method

FIG. 3.23 Mobrey float switches and on-load test facilities for heaters
(a) Mobrey float switch Check that test lamps indicate that float switch
The rising water level lifts the float 1 and causes the actuates correctly
permanent magnet 2 to repel the other permanent magnet 3 Open valve a
on the switch-actuating mechanism. The repulsion force Check that test lamps indicate that water level is now
moves magnet 3 in the directon of the arrow causing the below trip level
switch-actuation rods 4 to open and close the contacts. The Switch columns and repeat procedure
contacts are housed in 5 and 6 in the terminal block. The (c) Mobrey float switch arrangement using condensation
switch assembly is mounted in a waterproof housing 9 method. To on-load-test column 3:
which is attached to the non-magnetic stainless steel Switch column 3 to 'test' state
diaphragm flange 7. The whole assembly is clamped to the Close valve g
standpipe or float switch chamber by the back flange 8. Wait until the test lamps indicate that float switch
(b) Mobrey float switch arrangement using vacuum to actuates correctly, typically up to 30 minutes.
lift the water to on-load-test the switches. To on-load-test Open valve g
column 1: Check that test lamp indicates that water level is now
Switch column 1 to 'test' state below trip level
Close valve a Switch columns and repeat procedure

269
Feedwater heating systems Chapter 3

TO HP 6B HEATER TO DEAERATOR TANK

COMPONENTS
a NO 6A HP HEATER DESUPERHEATING SECTION
b CONDENSING
c DRAIN COOLING
d LEVEL TRANSMITTERS
e DUPLICATE HIGH LEVEL TRIP SWITCHES
f ON LOAD LOCAL TEST PANEL
g NO 5A HP HEATER FLASH BOX
h DESUPERHEATING SECTION
i CONDENSING
j DRAIN COOLING
k LEVEL TRANSMITTERS
I DUPLICATE HIGH LEVEL TRIP SWITCHES
m ON LOAD LOCAL TEST PANEL
n MASTER TRIP RELAYS TO ISOLATE BANK ON HWL
o HP DRAINS DIFFUSERS

FROM
FEED -
PUMPS

DRAINS FROM
HP 5A SHELL DRAIN 'B* BANK

FIG. 3.24 An HP heater drains system for horizontal heaters

the operator and is switched according to system to rise until its level controller sends a signal to open
needs. If the level continues to rise because there is the control valve to the condenser. The drains are
insufficient differential pressure to lift the drains to then discharged to the condenser until such time as
the de-aerator tank, the valve 3 in the line to the the water level falls and the drain discharge route
condenser is commanded to open and the drains dis- reverts to the de-aerator.
charge to the condenser. Backflow through valve 1 An alternative HP heater drains control system
from the de-aerator is prevented by the NRV 75. associated with vertical HP heaters is shown in Fig
Number 5 HP heater drains work on a similar prin- 3.25. The point at which drains switch from being
ciple but, because this is the lowest pressure HP raised to the de-aerator for discharge to the condenser
heater, the destinations available for the drains are flash vessel, or vice versa, is controlled by pressure
the storage tank or the condenser. A rising water level switches on the main turbine. Two pressure switches
in the No. 5 HP heater first opens the drains control are used to determine the changeover point: they are
valve to the de-aerator tank; if the pressure differ- offset by about 10% between falling and rising load
ential is insufficient to lift the HP heater drains to to prevent 'hunting'.
the de-aerator tank, the rising water level then opens The No. 8 HP heater drains route is selected by
the drain control valve in the line to the condenser. use of drains route selection valves 3 and 4, working
On falling unit load, when the water cannot be dis- in antiphase to direct heater drains to the flash vessel
charged to the de-aerator, the water level continues or to the condenser flash vessel; the appropriate route
270
HP feed system

VENT TO CONDENSER DEAERATOR VENT TO CONDENSER

a DESUPERHEATING SECTION
b CONDENSING SECTION
, c DRAINS COOLING SECTION
d LEVEL SENSING DEVICE
e CONVERTER TO CHANGE LEVEL SENSED TO ELECTRICAL SIGNAL
f CONVERTER TO CHANGE ELECTRICAL SIGNAL TO PNEUMATIC SIGNAL
g CONDENSER FLASH VESSEL
h CONDENSER FLASH VESSEL DRAIN PUMPS
i STEAM TRAP
j AIR VENT FOR PRIMING
k FLASH VESSEL

FIG. 3.25 An HP heater drains system for vertical heaters

being determined by a valve sequence initiated by the important to ensure that the allowable thrusts and
action of the pressure switches described above. The moments on the heater and the turbine flanges are
control of the level in No. 8 HP heater is by valves not exceeded and also that they are completely drained
1 and 2, and that for No. 7 HP heater is by valves of any condensate which may form. In the HP pipe-
5 and 6. As the drains flow path is determined by work, condensate should only be present when the
the drains route selection valves there is no need to pipework is cold and is being warmed up. To this
switch signals to the control valves, which simplifies end, drain pots with drain lines controlled by orifices
the level control system. The drains discharged to the or drain traps are provided at each natural collection
condenser flash vessel are pumped by drains pumps point in the pipework.
into the condenser hot well. The pumps are stopped Special care is taken to ensure that sections between
and started, as needed, by float switches mounted valves which could be closed are drained. This prevents
on the tank. pockets of water being swept along the pipework on
opening of an isolation valve. Figure 3.26 shows the
pipework arrangement for a horizontal HP heater
2.5 Pipework arrangement layout and Fig 3.27 for a vertical heater. The horizontal
The correct arrangement of bled-steam pipework is heater layout allows the pipework to be conveniently

271
Feedwater heating systems Chapter 3

FIG. 3.26 Arrangement of HP heater bled-steam pipework for horizontal heaters at Littlebrook D power station

drained to the drains vessel and then to the condenser is shown in Fig 3.28. Feedwater is sprayed or cas-
by gravity alone. caded over a series of trays where it is heated and
de-aerated by the bled steam from the turbine. The
process is described in detail in Section 7 of this
3 De-aerator system chapter.
The non-condensable gases and a certain amount
of steam are drawn off from the vent. The vent con-
3.1 Introduction denser recovers the heat in the steam and non-con-
The de-aerator and associated plant accept feed from densable gases drawn-off from the de-aerator head.
the LP feed train to heat and de-aerate the water The gases are then discharged to the condenser to be
and then supply it as feedwater to the boiler feed extracted finally by the air extraction equipment.
pumps. The de-aerator storage tank also acts as a Other designs of de-aerator heaters, which use other
receiving vessel for the HP drains and boiler feed means of exposing the condensate to the heating and
pump leak-offs. The term de-aerator in the context of scrubbing action of steam, are described in detail in
this section is taken to include the de-aerator head, Section 7 of this chapter, but the principle involved
the storage tank and associate plant. The feed pump is the same in all cases. The heated condensate and
suction pipework is also included in this section, as the condensed steam drain from the head into the
its configuration has an important effect on de-aerator de-aerator storage tank.
behaviour under transient conditions.

3.3 De-aerator storage tank


3.2 De-aerator heater The main function of the de-aerator storage tank is
A cross-section through a typical de-aerator heater to provide a reservoir of de-aerated feedwater which
272
De-aerator system

FIG. 3.27 Arrangement of HP heater bled-steam pipework for vertical heaters at Drax Completion power station

273
Feedwater heating systems Chapter 3

a) Half section of tray type head b) Half section of spray/tray type head
a WATER INLET
b STEAM INLET
c DRAIN OUTLET TO STORAGE TANK
d SPRAY MANIFOLD
e PERFORATED DISTRIBUTION TRAY
f 1ST PERFORATED TRAY
g 2ND PERFORATED TRAY
h 3RD PERFORATED TRAY
i AIR/NON CONDENSIBLE GASES EXTRACTION POINTS

FIG. 3.28 Section through a typical de-aerator heater

can be drawn upon by the boiler feed pumps when The highest level to which the condensate can rise
needed. is determined by the manufacturer, such that the
The capacity of the tank and the quantities of feed- maximum velocity of the steam flowing across the
water stored at the various levels within the tank are surface of the water will not cause water pick-up or
determined by the following functional needs: Sloshing' of the tank content. In this context, water
pick-up is defined as water which is stripped from
(a) To store sufficient feedwater to meet the re- the tank surface and transported to the de-aerator
quirements for flexible operation. head by the action of heating steam. Damage to the
(b) To provide control levels for the operation of the de-aerator head internals can be caused by the impact
insurge and outsurge systems without exceeding of the water which has been carried over. The head
the high water level. can also become flooded due to the drains being un-
able to cope with the extra water burden.
(c) Even when working at the top of the normal 'Sloshing' of the tank content is caused by the
operating level control band, to accept the con- formation of waves in the tank which close the steam
tents of the condenser hotwell in the event of the pathway and are then propelled the length of the tank
condenser level control valve failing to the open by the force created by the heating steam being at-
position, without exceeding the high water level. tracted to the head. For a more complete explanation
of the mechanism, reference should be made to the
(d) From the same initial working level as in (c), to
paper on the subject of de-aerator tank instabilities
accept half-a-minute's-worth of CMR flow without
by Cranfield and Wilkinson [7]. On the latest designs
exceeding the high water level.
of de-aerator, only a fraction of the steam is passed
(e) From the level indicated in (c), to accept water over the tank surface, the majority being introduced
accumulated in the condenser hotwell after a unit local to the head. The small flow across the tank is
trip when the extraction pumps are restarted with- retained to scavenge any oxygen within the tank and
out exceeding the high water level. transport it to the head. The head is vented to remove
any accumulation of non-condensable gases.
The rest of the working levels in the tank are deter-
Figure 3.29 shows a cross-section through a typical mined applying rules (a) to (e), above. From Fig 3.29
de-aerator tank for a modern 660 MW unit. Indicated it will be seen that the insurge and outsurge valves
are the various levels and the resultant actions which have been provided with separate control bands. A
are initiated. dead band is placed between the two control bands
274
De-aerator system

CONDENSATE
INLET

KEY
a DEAERATOR HEATER (HEAD)
b DEAERATOR STORAGE TANK
c DUPLICATE LEVEL COLUMNS WITH ON-LOAD TEST FACILITIES TO ENSURE THE CONTINUED INTEGRITY OF THE FLOAT
SWITCHES WHICH ARE USED AS THE LEVEL SENSING DEVICES
d HIGH WATER LEVEL TRIP FLOAT SWITCHES
e HIGH WATER LEVEL ALARM FLOAT SWITCHES
f LOW WATER LEVEL ALARM FLOAT SWITCHES

^ CONDENSATE
DRAIN
FREEBOARD TO PROVIDE THE AREA NEEDED TO LIMIT STEAM
VELOCITY ACROSS THE WATER SURFACE IN THE TANK SO AS
TO ELIMINATE THE POSSIBILITY OF WATER 'PICK UP' AND
SUBSEQUENT TRANSFER OF WATER TO THE DEAERATING HEAD

VOLUME FILLED AFTER A HIGH WATER LEVEL INITIATES


CLOSURE OF THE CONDENSATE INFLOW ISOLATING VALVE

RANGE OF OUTSURGE (SURPLUS WATER) VALVE CONTROL

DEAD BAND BETWEEN OUTSURGE AND INSURGE VALVES TO


PREVENT POSSIBLE HUNTING BETWEEN VALVES

RANGE OF INSURGE (MAKEUP WATER) VALVE CONTROL

FIG. 3.29 Typical de-aerator tank levels

to allow the insurge and outsurge system to operate during a transient, the water travelling down the suc-
independently without hunting. tion pipework must gain sufficient static head to pre-
vent boiling. The important factors are the rate at
which tank pressure reduces or decays and the rate of
flow down the suction pipework. The limiting case
3.4 De-aerator elevation found for CEGB plant is a hot restart of a feed pump.
The elevation of the de-aerator must be such that In this case the extraction pump is lost, the standby
the suction head requirements of the feed pumps can fails to start and the feed pumps draw down the de-
be satisfied under all credible modes of operation. aerator tank until the unit trips or is shut down. On
A typical de-aerator tank and suction pipework con- unit restart, the water in the condenser which has ac-
figuration is shown in Fig 3.30, the tank content, pipe cumulated after the extraction pump trip, has to be
lengths and component elevations being indicated. pumped forward to refill the depleted de-aerator.
In addition to the static head indicated, there is Assuming that the tank is at full-load conditions but
also the pressure head within the vessel. Under steady only partially full, the 100% cold condensate inflow
state conditions, the water within the feed pump suc- into a hot depleted tank produces a rapid pressure
tion pipework is at the saturation temperature equi- drop within the tank. The feed pump is started on
valent to the pressure within the de-aerator. To ensure leak-off, so the feed velocity is at its slowest and
that boiling within the pipework cannot occur when hence the time for the column of hot water in the
a sudden pressure reduction in the tank takes place suction pipework to gain static head is at its greatest.

275
Feedwater heating systems Chapter 3

DEAERATOR HEAD
b DEAERATOR STORAGE TANK
C FEED PUMP SUCTION FILTERS
d BOILER FEED PUMP DRIVE TURBINE
BOILER FEED PUMP BOOSTER STAGE
f BOILER FEED PUMP PRESSURE STAGE
g PRESSURE BREAKDOWN DEVICE FOR TDBFP
h DRIVE MOTOR FOR STARTING STANDBY (SS) FEED PUMP
I SUCTION STAGE OF SS FEED PUMP
PRESSURE STAGE OF SS FEED PUMP
k PRESSURE BREAKDOWN DEVICE FOR SS FEED PUMP

TO HP FEED SYSTEM

FIG 3.30 A typical arrangement of feed


pump suction and leak-off pipework
The heated and de-aerated water from
the head cascades into the storage
tank from where it flows through the
pipework and filters to the turbine-driven
boiler feed pump. During normal
operation, the transit time of a partical
of water to flow from the storage
tank outlet to the feed pump suction
is dependent on the pipework length
and the flow rate needed to sustain the
boiler drum level. For the start-up
phase of operation for a 50% capacity
starting/standby pump to sustain leak-off
flow through the pump, a flow of about
one eighth of normal CMR flow is
needed (i.e., transit time is eight times
CMR flow value of between about 30 to
40 seconds)

276
De-aerator system

Figure 3.31 shows in graphic form the effect of Further information on the effect of boiling in feed
the hot restart with a typically sized de-aerator tank pipework and the avoidance of 'thermally induced' hy-
and suction pipework configuration. To prevent boil- draulic shock is given by Wilkinson and Dartnell [9].
ing in the suction pipework, the inflow is limited to
a suitable flow rate by controlling the opening of the
condenser level control valve after a unit trip. For 3.5 Protection systems
further information on this aspect of de-aerator sys- If the de-aerator pressure falls rapidly, as would
tem design, reference should be made to Dartnell [8]. happen on a unit trip, steam will be evolved from the

STATIC HEAD DUE TO ELEVATION OF DEAERATOR TANK

EZJ PRESSURE NEEDED TO SUPRESS BOILING AT FEED PUMP SUCTION STAGE

NETT POSITIVE SUCTION HEAD NEEDED FOR BOILER FEED PUMP SUCTION STAGE

EH3 FRICTION IN PIPEWORK AND FILTERS

HEAD AVAILABLE TO SUPRESS BOILING AT FEED PUMP SUCTION

TOTAL HEAD AVAILABLE UNDER STEADY STATE CONDITIONS


= STATIC HEIGHT + PRESSURE HEAD

COMPOSITE CURVE = STATIC HEAD + PRESSURE IN


TANK AT TIME AFTER
START OF TRANSIENT

TIME FOR PARTICAL OF WATER TO FLOW FROM


TANK TO BFP SUCTION

TIME, s

FIG. 3.31 Curves showing rate of pressure decay and transit time for typical hot restart conditions for
a 660 MW turbine-generator
The curves are based on the conditions prevailing after a turbine generator trip with the de-aerator tank assumed to retain
full-load pressure but with the content reduced to the low water level. To restart the feed system, the starting and standby
feed pump (SSFP) is run on leak-off and the condensate extraction pump is started. The condensate, at vacuum temperature
accumulated in the condenser, discharges into the hot depleted de-aerator tank. The small flow rate corresponding to SSFP
leak-off flow gives an extended transit time in the order of 4 - 5 min for a typical feed pump suction pipework layout. For
this transit time, the pressure decay is restricted by limiting the condensate inflow in order that the pressure decay rate is
such that a positive head to suppress boiling is available at the feed pump suction. In general, it has been found that about
one third the normal inflow rate results in an acceptable decay rate. The second cycle starts from a lower initial tank
pressure and, from the shape of the pressure decay curve, it is seen that the result is less onerous than the first cycle.

277
Feedwater heating systems Chapter 3

large mass of stored water within the tank. To pre- the outgoing feed flow from the tank needed to generate
vent the reflux of the steam to the turbine, a non- the drains.
return valve of the power-assisted closing type is
provided in the bled-steam line between the de-aerator
and the bleed point on the turbine. As the amount of
steam evolved would overspeed the turbine, the non- 3.6 Protection valves
return valve is of a high integrity type specially de- The bled-steam non-return valve is power-assisted.
veloped by the manufacturer for this duty. The valve Figure 3.32 shows a typical flap type non-return valve
is air-opened, spring-assisted closed and is commanded with a spring-closing/air-opening actuator. There is
to shut by the action of a switch on the turbine gov- lost motion between the actuator and the valve flap
ernor gear when the unit trips. As a back-up, the which allows the valve to function as a free-acting
bled-steam isolating valve is tripped so that it also non-return valve.
closes. In the event of an HWL in the tank, the bled- The actuator is there primarily to give the valve a
steam and power-assisted non-return valves are shut. positive closing force to overcome any stiffness in
In addition, a high integrity valve in the condensate the bearings, etc., when the valve is commanded to
line to the de-aerator is also shut. The route to the shut. The valve is shut by dumping the air from the
turbine is therefore closed and the source of flooding cylinder which allows the spring to close the valve.
water is isolated. If the air supply is lost, the valve will fail to the
Inflows to the de-aerator tank for which automatic closed position, although it will not shut until the
isolation on a high water level is not needed are the forward steam flow falls to a low value. This is be-
HP heater drains and the feed pump leak-offs. This cause the steam flow on the underside of the disc
is because the feed pump leak-offs are purely circulatory creates an opening force which is greater than the
flows between the tank and the boiler feed pump, and spring-closing force. The bled-steam isolating valve
the incoming HP heater drains are always less than is a butterfly type valve of the spring-closing/air-

SOLENOID VALVE

FIG. 3.32 A power-assisted non-return valve

278
De-aerator system

opening type. Figure 3.33 shows a typical butterfly 3.7 Pipework


isolating valve with a spring-closing/air-opening actu- As the de-aerator is in an elevated position relative
ator. This form of actuator ensures the bled-steam to the turbine, the bled-steam line has to rise at least
isolating valve fails-shut on loss of air pressure. On a 20 to 30 m above the bleed point on the turbine and
signal to trip, the air is dumped from the cylinder and so great care has to be taken to drain all points where
the multiple springs exert sufficient force to close condensate could accumulate. Drain pots are provided
the valve against the full differential between heater at each natural drainage point, with a side take-off
pressure and turbine condenser pressure to keep it which is led with a continuous fall to a suitable low
shut. This is needed as the IP/LP turbine pressure pressure disposal point. The drainage is controlled by
falls to condenser back pressure in approximately one orifices or traps, with by-passes to allow for cold start
second when the interceptor valves close due to a unit conditions when drainage requirements are at their
trip. The heater pressure remains constant for seconds maximum. The steam traps, if used, are set so that
or longer according to circumstances, and then re- they discharge a few degrees above saturation tem-
duces slowly, hence the isolating valve must close perature to prevent condensate build-up. Attention is
against the full differential pressure. also given to those sections of pipe which are isolated

BODY

DISC SHAFT

AIR OPENING SPRING RETURN ACTUATOR, (MAXSEAL)


- VALVE CLOSES ON LOSS OF AIR SUPPLY.

FIG. 3.33 A bled-steam isolating valve with air-opening, spring-closing actuator

279
Feedwater heating systems Chapter 3

by the action of the protection valves, to check that The filters prevent particles greater than 0.2 mm
they have adequate drainage and so ensure that there from passing through the filter mesh. To minimise the
are no trapped pockets of water which can be swept effects on available feed pump NPSH, the filter types
forward on opening of the valves. adopted (Fig 3.34 and Fig 3.35) have a full flow pres-
sure drop in the clean conditions of no greater than
0.1 bar. Backflushing is arranged to operate automa-
tically when the pressure drop across the filter rises
3.8 Boiler feed pump suction filters to 0.4 bar. Timer facilities are also provided to permit
Suction filters are provided to remove any foreign backflushing at fixed time intervals, if required.
matter from the feedwater which could damage either The filter element consists of a stainless steel fine-
the feed pumps or the downstream plant. An arrange- mesh basket, which is readily removable together with
ment with 2 x 100% duty filters in parallel has been the backflush assembly for maintenance and inspec-
provided by the CEGB on fossil-fired stations, each tion. On initiation of the backflushing sequence, the
with automatic backflushing facilities. back wash arm is slowly rotated against the filter

ENTRAINED DEBRIS INTERCEPTED


INSIDE STRAINER CAVITIES

MULTIPLE
SEGMENTED SCREEN

ACCUMULATED SOLIDS
VACUUM-WASHED
BY BACKWASH ARM

CONTAMINATED FLUID
ENTERS HERE

ALL-STEEL
PRESSURE VESSEL

CLEAN FLUID
LEAVES HERE

DEBRIS BACKWASHED AUTOMATIC


THROUGH BACKWASH ARM
HOLLOW SHAFT

FIG. 3.34 One arrangement of a feed pump suction filter

280
Low pressure feed system

mesh. At the same time a dump valve is opened,


creating a back pressure over the section of the mesh MOTOR AND SPEED
covered by the arm. This causes a localised reversal LIFTING LUGS REDUCING GEAR UNIT ACTUATED VALVE

of liquid flow to flush all the accumulated debris


to waste.
Hydraulic instability can occur at the commence-
ment of backflushing if the saturated liquid leaving
the filter is allowed to discharge into an empty drain
line. To prevent this, the line needs to be kept primed
and the major pressure reduction should take place
at the end of the drain line, prior to dissipation into
the unit drains system. These requirements are achieved
by the positioning of the dump control valve together
with a pressure breakdown orifice at the disposal end
of the pipeline.

4 Low pressure feed system

4.1 Introduction
The low pressure (LP) feed system is defined as the
heaters and the equipment between the outlet from
the condenser hotwell and the condensate inlet to the
de-aerator system.
Two types of LP feed system are in current use.
The older systems use direct contact heaters where,
as the name implies, the bled-steam and the conden- V V J HOLLOW

sate mix in the heater and are pumped forward to-


gether, as opposed to the traditional design of system
with tubed surface LP heaters, where the bled-steam
and the condensate are separated by the tube walls. BODY DRAIN

DC LP heaters were originally adopted in pre-


ference to the traditional vertical tubed surface LP FIG. 3.35 Alternative arrangement of a feed
heaters for the following reasons: pump suction filter

Because the steam and condensate are mixed,


zero steam and drain temperature differences are
achieved with a consequent reduction in the heat by the following factors:
rate of about 0.5 to 0.25%. Operational experience has shown that the original
designs needed considerable modifications to make
The cost of a DC heater, which is basically a tank
them perform acceptably. These included increas-
with an internal water distribution system, is con-
ing the depth of the loop seals and the upgrading
siderably less than a tubed LP heater.
of the turbine protection against the possibility of
The boiler feedwater requirements for the AGRs water ingress from the heaters.
necessitated the use of an in-line 100% water treat-
ment (polishing) plant. Heaters downstream of the A high water level in any of the heaters in a DC
polishing plant must not contain copper-bearing heater train results in loss of feed to the de-aerator
materials, so a DC heater of all-steel construction because of closure of the condensate isolating valve
seemed the logical choice. placed just prior to the first (lowest pressure) DC
heater. As a consequence, unless a by-pass is pro-
vided as at Hinkley Point B, Hartlepool, Heysham
As briefly mentioned in the Introduction, a study of 1 and Grain, the unit usually has to be taken off
the cost effectiveness of the DC low pressure heater load with resultant loss of revenue. Even if a by-
system was undertaken in the early 1970s, from which pass is provided, the flow of cold condensate to
it was concluded that the factors which resulted in the de-aerator causes pressure decay in the de-
their adoption in the late 1950s no longer applied aerator tank, with consequent restrictions in unit
and that the gain in cycle efficiency was outweighed operation.
281
Feedwater heating systems Chapter 3

Because of the vertical separation required between This grouping of LP heaters has been chosen so
DC heaters, already illustrated in Section 1 of this that if either LP3 or LP2 and LP1 are by-passed, the
chapter, long condensate and bled-steam lines were resultant steam and condensate flows will not overload
needed. Extensive steelwork was also needed to the individual feed train components. If LP3 heater is
support the heaters at the required levels. These by-passed, the condensate temperature to the de-
extra costs were found to outweigh the cost differ- aerator will be at LP2 heater outlet temperature. The
ence between DC and surface type LP heaters. steam flow to the de-aerator will increase by about
50% to compensate for the greater enthalpy rise now
needed. The de-aerator is designed to allow for this
As it was evident that a revision of traditional prac-
increase in the flow without damage or operational
tice was cost effective, a complete review of previous
practice was undertaken by the manufacturers. A new difficulties. When LP3 heater is by-passed, the drains
concept evolved which followed international practice are also isolated from LP2 heater flashbox. If LP1
of using surface LP heaters in the horizontal attitude. and LP2 heaters are by-passed, condensate at the
Figure 3.36 shows the position finally adopted, which temperature of the gland steam condenser outlet is
allowed easy bled-steam pipework drainage and makes supplied to LP3 heater. LP3 heater then attracts a
use of the entire heater shell to contain condensate in total of approximately three times the normal steam
a flooding situation. Another important factor is the flow. To allow for this large increase in steam flow,
compact layout, which allows the heaters to be factory the steam inlet and heater internals are designed for
built, complete with pipework fittings, etc., and ship- this duty. The drain system is also capable of ac-
ped to site as a unit. The only site work necessary is cepting the abnormal drains quantity.
to connect to the system on the steam and water sides The feed system illustrated has no drain cooling
and to provide air and electricity to the valves and section contained within the heater shells. However,
instruments as needed, with consequent savings in to improve the cycle efficiency, a drain cooler is
erection costs. usually provided to recover as much of the heat from
The cost of modification and upgrading of plant the combined drains out of the lowest pressure LP
after or during construction has vindicated the de- heater as practicable. The drain cooler can be of the
cision to change to surface LP heaters for future water-to-water type or the more usual flashing type.
units: however, there are forty-nine 500 and 660 MW The flash drain cooler is, in effect, an additional
units in operation with DC heaters. To complete stage of LP feedheating, using the steam flashed from
the picture of current plant, Fig 3.37 shows a typical the drains out of LP1 to heat the feedwater. The
DC three-heater cascade as employed at Hartlepool drains from the flash drain cooler are cascaded to
and Hey sham /, both AGR stations. the condenser.
Water is pumped from the condenser hotwell via A development to increase cycle efficiency which
the condensate system up to DC 1 heater. From this is to be used for the current PWR feed system (Fig
heater, it cascades into DC 2 and then cascades into 3.6), is the pumping forward of the drains from a
DC 3 heater, from where it is pumped by the DC group of LP heaters. Because of the large flows in-
heater extraction pump to the de-aerator heater. A volved in the PWR cycle, it has proved economic to
60% capacity by-pass is provided to prevent the unit provide the additional pumps and associated equip-
tripping on low de-aerator water level in the event ment needed to inject the LP heater drains into the
of a DC heater train trip. de-aerator system in order to recover the heat in the
drain water.
The principle of forward pumping of drains is
illustrated in Fig 3.39 and shows how the enthalpy
4.2 Low pressure system configuration into the upstream heater is increased by the injection
Figure 3.38 shows the LP feed system for Littlebrook of the drains water. The consequent decrease in steam
D which uses tubed LP heaters in a horizontal atti- used in the upstream heater improves cycle efficiency.
tude. The heaters are by-passed in two banks, the An alternative drain route to the condenser is also
first group being LP1 and LP2 heaters and the second provided, so that the loss of a heater drain pump or
LP3 heater. Steam is supplied to each of the three the malfunction of associated equipment does not
LP heaters from the LP turbines. Each bled-steam result in the forced isolation of the heaters which are
line contains a free-acting non-return valve and a drained by the drain pump because of lack of an
bled-steam isolating valve. alternative destination for the drains. The short term
The drains formed in LP3 heater are cascaded to loss of efficiency is accepted until the drain pump is
LP2 drains flashbox, from where they are drained returned to service.
into LP1 drains flashbox. The combined drains from Distribution of bleed point pressures and hence en-
LP2 and LP1 flashboxes cascade to the condenser thalpy rises over the heaters, determines the gain in
flash vessel. The drains from LP1 heater are also cas- efficiency by forward pumping of the drains of each
caded to the condenser flash vessel. individual heater or group of heaters (see Chapter 1).
282
Low pressure feed system

LP CYLINDERS

FIG. 3.36 A typical arrangement of horizontal-attitude LP heaters


Pictorial view of horizontal-attitude LP heaters showing the principles adopted to determine their position relative to the
turbine bled-steam extraction points and water level in condenser. The bled-steam pipework is arranged to slope from
extraction point to heater. The heaters cascade by gravity from LP4 to LPl heater and thence to the flash drain cooler.
The drains then cascade to the condenser.

283
Feedwater heating systems Chapter 3

BLED STEAM ISOLATING VALVE (BSIV)


. 35.6m LEVEL
DEAERATOR FLOOR

8.7m LEVEL
TURBINE HOUSE
FLOOR

1 Jk*

u
FROM TMEC
EXTRACTION PUMPS

FIG. 3.37 A typical DC heater cascade

284
Low pressure feed system

PLANT IDENTITIES VALVE IDENTITIES

a -Main condensers 1 - Condenser level control valve


-Condenser extraction pumps of the vertical cassion type 2 Extraction pump recirculation loop control valve
-Gland steam condenser (GSC) 3 - Sectionalising valve
-No.1 LP Heater 4 Condensate dump valve
-No.2 LP Heater 5 Condensate isolating valve in dump to RFT
-No.3 LP Heater 6 - Outsurge valve - controlled by level in deaerator storage tank
-Reserve feedwater tank (RFT) 7 - Non return valve in condensate main - to prevent drain down
-Make-up pump of vertical pipework in line to deaerator storage tank
-Drain tank for GSC with level control by float operated valve 8 - No.1 LP Heater inlet isolating valve
-Condenser flash vessel 9 - No.2 LP Heater outlet isolating valve
-No.2 LP Drains flashbox 10 - N 0 . 1 & 2 LP Heaters bypass valve
No.1 LP Drain flashbox 11 - No.3 LP Heater inlet isolating valve
-Duplicate columns containing LWLA & HWL trip float switches 12 - No.3 LP Heater outlet isolating valve
with on-load testing No.1 LP 13 - No.3 LP Heater bypass valve
Duplicate columns containing LWLA & HWL trip float switches 14 - No.3 LP Heater drains route selection valve - to condenser
with on-load testing No.2 LP 15 - No.3 LP Heater drains route selection valve - to LP 2 flashbox
-Duplicate columns containing LWLA & HWL trip float switches 16 - No.1 LP Heater bled steam isolating valve
with on-load testing No.3 LP 17 No.1 LP Heater bled steam isolating valve
Insurge group of valves 18 No.2 LP Heater bled steam isolating valve
Outsurge group of valves 19 No.3 LP Heater bled steam isolating valve
20 - No.1 LP Heater bled steam non return valve
21 - No.1 LP Heater bled steam non return valve
22 - No.2 LP Heater bled steam non return valve
23 - No.3 LP Heater bled steam non return valve

f
I IH>o-lt*><*r

IL
H' nlWP^
ntxn
fl II1!^

BLED STEAM
FEEDWATER/CONDENSATE
DRAINS

-w-

A
VALVE TYPES

Motorised isolation valve

Manual isolation valve

Air operated control valve

H ^ " Non return valve

Air opening spring closing isolation valve

Thermal relief valve

FIG. 3.38 A typical diagrammatic arrangement of an LP feed system, showing the main control and isolating valves

The grouping of two or more LP heaters into a enquiry document.


bank to provide a common by-pass on the feedwater To meet the functional needs for the protection
side makes it convenient to forward pump the cumu- against water ingress as given in Section 1 of this
lative drains from the lowest pressure LP heater. The chapter, each heater is provided with duplicate level
choice as to which LP heaters are provided with a sensing devices, which can be on-load tested to verify
drains pump is made by the feed system manufac- their health.
turer at the inception of the feed cycle design, taking In the event of an HWL in LP3 heater, it is iso-
into account the factors described above in conjunc- lated and by-passed on the condensate side and also
tion with the value of efficiency given in the relevant isolated on the steam side. An HWL in LPl or LP2
285
Feedwater heating systems Chapter 3

the control valve is determined by the signal from the


level controller on the de-aerator. The maximum ca-
BLED
STEAM pacity of the outsurge valve is normally about 10%.
A non-return valve is provided in the outsurge line
to prevent the contents of the RFT leaking into the
condensate system. A motorised by-pass valve with
an orifice in series is connected around the outsurge
valve to allow the quantity outsurging to be trimmed
by the operator as needed.
To supply the de-aerator with feed from the RFT
under emergency conditions a 30% make-up pump
may also be provided. The pump can also be used to
ENTHALPY
RISE DUE TO
fill the de-aerator, avoiding the use of the extraction
pumps for this duty when initially filling the tank.
Upstream of the make-up pump and outsurge con-
nections is a sectionalising valve, which is used to
CONDENSATE FLOW
AT EXTRACTION PUMP
DISCHARGE PRESSURE
isolate the condensate system during system flushing
: and clean up.

SATURATION
ENTHALPY

ALTERNATIVE DRAIN All of the system components upstream of the


ROUTE TO CONDENSER
IF DRAIN PUMP
UNAVAILABLE
isolating valve are primarily concerned with control-
DRAINS FROM DOWNSTREAM
HEATER ling the flow through the condensate system to main-
tain a constant water level in the condenser.
RISE OVER PUMP NEGLECTED AS SMALL The prescribed level is required to give surge and
cavitation-free extraction pump performance and is
FIG. 3.39 LP heater with drains forward-pumped into maintained by throttling the extraction pump flow.
feed pipework A level control device on the condenser, typically as
manufactured by Fisher and sold under the trade
name 'Level-TroF, is used to give an air signal which
controls the position of a pneumatic control valve and
heaters will result in isolation on both steam and maintains the level in the condenser. The level control
condensate sides, with the condensate by-pass valve valve fails to the 'open' position on loss of air or
opening to supply water to LP3. control signal, thus preventing a unit trip due to loss
Also shown in Fig 3.38 is the portion of the LP of forward flow to the de-aerator and hence eventual
feed system which connects the condenser to the LP loss of feed to the boiler.
feedheaters. Part of this system is the insurge group, The position of the control valve is immediately
by which means feedwater is admitted to the con- upstream of sectionalising valve. Its function in trim-
denser. Water is fed into the condenser from the ming the pump discharge head to suit the system
reserve feedwater tanks (RFT) under the control of resistance is shown in Fig 3.40. To protect the extrac-
the insurge group. tion pump from damage due to low flows, the pump
There are three routes by which feed can be ad- manufacturer specifies a flow below which the ex-
mitted via the insurge group: traction pumps should not be operated. To meet this
need a recirculation connection and a control valve
A fixed orifice which allows 1% CMR flow on a is provided and is commanded to open as the main
continuous basis. Any small leakages and water control valve goes below the 25% flow position. The
losses are made up by this quantity. way in which the recirculation valve operates in anti-
Via the control valve which receives its signal from phase to maintain a minimum flow through the ex-
de-aerator level. The capacity of the valve is usual- traction pump is also illustrated in Fig 3.40.
ly about 2 - 3 % and varies according to the static Between the condenser level control valve and the
head available from the RFT (especially relevant sectionalising valve, a dump connection is provided,
for a low level tank). which is used to discharge contaminated condensate
from the system during system clean up.
A manually-operated by-pass valve which can pass The non-return valve upstream of the control valve
anything from 5-7% and is only used for start-up prevents accidental discharge of water from the de-
or in an emergency. aerator tank into the condenser in the event of an
extraction pump trip with a faulty discharge non-return
valve.
The outsurge valve and associated equipment is con- The gland steam condenser is placed upstream of
nected to the condensate system downstream of the the recirculation connection to ensure a cooling con-
sectionalising valve. The rate of discharge through densate flow at all times. The extraction pumps are
286
Low pressure feed system

pump from the discharge of the duty pump.


On all 500 MW units and the earlier 660 MW units
with DC heaters, cooling of the generator by con-
densate was incorporated in the feed train imme-
diately after the extraction pump, as illustrated in
Fig 3.41.
The reason for placing it in the feed system was to
reclaim the generator losses as heat input to the feed.
In practice, it was found that for large modern power
stations the following difficulties were experienced:
On extraction pump trip, the residual heat in the
generator could boil the condensate in the system and
cause thermally-induced hydraulic shock [10].
To provide an acceptably modest condensate pres-
sure within the coolers on the generator, two pres-
(a) sure stages are needed. Two pumps are used and
the condensate is discharged from the first pump
through the generator coolers and then into the
CONSTANT FLOW
THROUGH GSC
turbine moisture extraction condenser (TMEC) with
consequent complicated pipework arrangement. The
TMEC extraction pump then discharges to the lowest
pressure DC heater.

To prevent limitations on unit output during the


summer when condensate temperatures may be too
high to cool the generator adequately, coolers to
FLOW TO DEAERATOR -
reduce the condensate temperature before it passes
(b) through the generator may be required in the feed
system. The introduction of raw water coolers in
the condensate system carries the risk of leakage
of the cooling water into the system.
LEVEL SENSING DEVICE WITH OUTPUT SIGNAL
IN THE FORM OF VARYING AIR PRESSURE
(TYPICALLY A FISHER "LEVEL-TROL")

Whilst these problems can be overcome, the resultant


plant is expensive and needs special care to operate.
Consequently an auxiliary CW system using indirect
coolers has been developed by the main manufacturers
and is fully described in Chapter 6.
On all modern feed systems, protection against the
use of contaminated feed water is provided. On some
CONDENSATE EXTRACTION PUMP GLAND STEAM
CONDENSER
units, this takes the form of visual alarms to alert
(C)
the operator of high conductivity levels in the feed
leaving the extraction pumps. In this case, the opera-
tor has to use his judgement as to the subsequent
FIG. 3.40 LP feed system resistance curve and function of
recirculation loop at low flows
actions, for example, to close sectionalising valves
Valve A, condenser level control valve maintains a and unload the unit.
constant level in the condenser and hence NPSH on For AGR feed systems, as illustrated in Fig 3.5, a
the extraction pump by throttling flow to match inflow
to the condenser. full-duty polishing plant is provided to ensure high
Valve B, recirculation loop control valve when valve A quality water for boiler feed. As their boilers need
is passing less than 40%, then valve B opens in antiphase special protection against chloride ingress, valves are
such that the combined discharge from A and B is a
constant 40% as illustrated by curve in (b). provided upstream of the polishing plant but down-
stream of the outsurge connection.
In the event of a condenser tube leak, the conduc-
tivity sensors close the protection valves and trip the
provided with isolating valves on both suction and extraction pumps; should there be an accidental re-
discharge to allow isolation for maintenance. Non- lease of chemicals from the polishing plant, the sec-
return valves are provided on the discharge of the ond line conductivity sensors also close the protection
pumps to prevent backflow of water through an idle valves. The valves used for this duty are butterfly
287
Feedwater heating systems Chapter 3

GENERATOR
HYDROGEN COOLERS

TURBINE
MOISTURE
EXTRACTION
CONDENSER
(TMEC)

GH
EXCITER
COOLER TODC1
HEATER
RECTIFIER
COOLER

DISTILLED WATER
COOLING PUMPS
DISTILLED WATER
COOLERS *h
iLf3~irffiiJ TMEC
LEVEL
r~*
" CONTROL

OVERFLOW TO
MAIN CONDENSER
CONDENSATE
POLISHING RECIRCULATION
STATOR WINDING PLANT TO CONDENSER
WATER COOLERS

GENERATOR COOLERS kTMEC


I EXTRACTION
' PUMPS

BFP GLAND ATMOSPHERIC


SEAL WATER GLAND STEAM
COOLER CONDENSER

FIG. 3.41 Diagrammatic arrangement of generator coolers in an LP feed system

valves of the spring closing/air opening type similar pipework is shown in Fig 3.42 and shows clearly
to those used for bled-steam isolating valves. the principle of the heaters being below the cylinder
bottom level and above the condenser level. The
pipework also slopes towards the heater. The bled-
steam isolating valves are of the same design as those
4.3 Pipework and valves used in the de-aerator bled-steam pipework. The non-
The general arrangement of LP heater bled-steam return valves are also similar but are not provided
288
Designs of feedheaters

NON RETURN VALVE BLED STEAM ISOLATING VALVE

FIG. 3.42 Arrangement of LP heaters, showing bled-steam pipework

with assisted-closing devices as these are not manda- average overall heat transfer coefficient has to be
tory for LP heaters. found and used to determine the heat transfer surface
area needed. From the tube size and feedwater flow,
the tubenest diameter is found. With the tubenest
diameter known, the heater diameter and the main
5 Designs of feedheaters structural details of the shell and water heater can be
The aim of feedheater design is to provide a heat determined by use of the appropriate design standard.
exchanger that will raise the temperature of the in- The length of the heater is a function of the heat
coming feedwater to a specified outlet temperature, transfer surface needed. A detailed explanation of
whilst drawing a predetermined amount of steam from thermal/hydraulic design is given in Section 6 of this
the turbine cycle. There are four groups of heat ex- chapter.
changers used in the feed system to fulfil this function: De-aerator head and DC heater sizes are deter-
mined by the need to accommodate the sprays or
High pressure feedwater heaters. trays used to create sufficient water surface area to
transfer the heat from the steam to the water, as
De-aerator heaters. needed by the cycle. The vessel diameter and length
is determined by the need to contain the requisite
Low pressure feedwater tubed heaters. number of sprays or trays.
Low pressure feedwater direct contact heaters. There are long established British Standards for the
structural design of feedheaters and these are used by
the CEGB to specify a uniform design standard for all
The design of each type of heat exchanger is deter- components, materials, welding and testing.
mined by the thermal, hydraulic and structural needs Until 1976, the standard used was BS1500 'Fusion
of its particular function in the feed cycle. The over- Welded Pressure Vessels' supplemented by the ASME
all size of a heat exchanger is fixed by its thermal/ 'Boiler and Pressure Vessel Code', where appropriate.
hydraulic design. In 1976 BS1500 was replaced by BS5500 'Unfired
For a tubular heat exchanger to raise the tem- Fusion Welded Pressure Vessels' [11], which conso-
perature of the feedwater by a defined amount, the lidated and expanded the previous standard. BS5500

289
Feedwater heating systems Chapter 3

has been used for all heaters ordered since 1976 and means by which the consequent heat transfer surface
will be used for all future plant. For a specific heat areas are found is shown in Section 6 of this chapter.
exchanger size, the standard is used to determine the Figure 3.43 illustrates the way in which the feed
thickness of all pressure parts such as shell, tubeplate temperature increases as it passes through a typical
and water header, branches, etc. The materials, weld two-pass horizontal heater of the U-tube type. The
details and procedures, as well as relief valve capacity heater has both integral drain cooling and desuper-
and vessel pressure testing, are also defined. heating sections as shown (Fig 3.44).
In certain specialist areas, such as heater internal The desuperheating section is placed on the outlet
design, the 'Standards of Tubular Exchanger Manu- end of the U-tubes in order that the incoming super-
facturers Association (TEMA) 1978' [12] can also be heater steam can raise the feedwater near to or above
applied. the saturation temperature of the body pressure be-
The heat transfer coefficients are determined by a fore it leaves the heater. The drain cooling section
manufacturer's experience with a particular design of is placed at the inlet end of the tubes to allow the
feedheater. However, a good approximation to the outgoing drains to be cooled to as near to the in-
design values for surface type heaters can be obtained coming feedwater temperature as needed. Steam enters
by reference to the 'Guide to the Design of Feed the desuperheating section and is reduced in tem-
Water Heating Plant (BEMA) 1968' [13] or TEMA perature by transferring its heat to the feedwater to
1978* [12]. within 27C of the temperature of saturation of the
condensing section pressure. The steam then flows to
the condensing section, where it leaves as water at sat-
uration temperature to enter the drain cooling section.
6 High pressure feedwater heaters A water seal is maintained at the inlet to the drain
cooling section by a level control system to prevent
loss of prime in the section.
6.1 Functional needs In the drain cooling section, the condensate is
cooled to the drain outlet temperature and then dis-
The structural design of high pressure (HP) feedwater
charged to the next lowest pressure heater.
heaters is determined by two main needs:
Each section within the heater is provided with
To contain the steam and HP feedwater at the ap- baffles to ensure flow across the outside of the tubes
propriate cycle conditions. by the heating medium.
As the heating steam is condensed in the heater,
To provide the heat transfer surface to raise the feed- non-condensable gases are released. Unless correctly
water temperature by the specified amount. vented these would rapidly blanket the heat transfer
surface and would impair the heater thermal perform-
ance. To remove these gases, vents connected to the
The temperature rise and the TTDs are determined condenser are provided at strategic points throughout
by cycle economics, as shown in Chapter 1, and the the heater tubenest.

TEMPERATURE OUT OF HEATER

TEMPERATURE AT INLET
TO CONDENSING
SECTION

DESUPERHEATING SECTION

'U'TUBE LENGTH

FIG. 3.43 Temperature rise of feed water as it passes through an HP heater

290
High pressure feedwater heaters

WINDOW TO ALLOW FLOW OF STEAM


WATER BOX DESUPERHEATING SECTION OUT'OF DESUPERHEATING SECTION TUBE BUNDLE CONDENSING SECTION
FEED OUTLET

DRAIN COOLING SECTION ^^ SUBMERGED OPENING TO


ALLOW CONDENSATE TO FLOW
INTO DRAIN COOLING
DRAIN OUTLET SECTION

FIG. 3.44 Steam and water flow paths in a typical horizontal HP heater

Special care is needed in the venting of horizontal


heaters, as air pockets can accumulate under baffles,
etc. If lower initial heater cost outweighs the higher
running cost due to the loss of cycle efficiency, heaters CENTRAL DISTRIBUTION DUCT
FOR STEAM FROM
can be constructed without drain cooling sections or DESUPERHEATING SECTION

separate desuperheating sections.


Vertical HP heaters employ the same basic layout
with regard to disposition of the desuperheating and CONDENSING SECTION
drain cooling sections. However, there are some points
of difference in construction which are highlighted
in the following section on construction of specific
ALTERNATIVE POSITION
heater designs. FOR DESUPERHEATING
SECTION

Figure 3.45 shows a typical arrangement of a ver-


tical HP heater. The desuperheating section is below
the working water level in the heater. To prevent water
inleakage, seals are provided between the tubes and TUBE BUNDLE
the end plates of the desuperheating section, trunking
is also needed to carry the steam from the desuper-
heater to the condensing section if needed. These
provisions can be avoided by placing the desuper-
heating section in the dotted position shown in Fig
3.45 but, as it is not now adjacent to the tubeplate, WINDOW TO ALLOW FLOW
the feedwater must travel through tubes immersed
INTO DRAIN COOLING
SECTION

in water at the saturation temperature equivalent to DESUPERHEATING SECTION

the body pressure. This limits the steam TTD as, if DRAIN COOLING SECTION

a negative TTD were employed, the feed would tend


to be cooled back down to saturation temperature.
The horizontal design of heater does not suffer from
DRAIN OUTLET
this problem as the desuperheating section is above
the water level by virtue of the heater attitude.
The reduction in the complication of heater internal
construction is another point in the favour of hori-
zontal attitude HP heaters.
As the high pressure feedwater heaters are on the
discharge side of the feed pumps, the feedwater within
the water headers and the tubes is at boiler pressure
plus the pressure rise between the heater and the boiler. FIG. 3.45 Steam and water flow paths in a typical vertical
To contain this high pressure, various designs of water HP heater
header have been used in the past, but virtually all
current 660 MW units employ hemispherical-headed
heaters with a flat tubeplate. The tubes are welded fusion welding process' illustrated in Fig 3.46. This
onto the back of the tubeplate by the 'Foster Wheeler method of tube attachment has been used for many

291
Feedwater heating systems Chapter 3

TREPANNED S P I G O T _ [ FLUX BACKING


FOR BUTT WELD

WATERSIDE OF TUBEPLATE

TUNGSTEN ELECTRODE
WITHIN CERAMIC TUBE
OF WELDING GUN

STEAM SIDE OF
TUBEPLATE

BUTT WELDING

FIG. 3.46 Foster-Wheeler method of butt-welding HP heater tubes to tubeplate

years and, once initial difficulties with the quality of as BS5500 [11] makes no provision for minimum bend
welds were overcome, it has proved a cost effective radius of the thinning effect when forming a U-tube.
method of tube attachment. The materials normally used in the construction of
Current HP heaters and associated systems use HP heater headers are low carbon steel for the tube-
welded joints wherever practicable, as bolted joints plates with a forged steel or cast steel hemispherical
have proved difficult to maintain leak-free when sub- head (hemi-head). The tubeplate and hemi-head are
jected to thermal cycling. It is now accepted that to welded together to form the feedwater header. An
maintain heater internals, the heater shell has to be alternative which has been used in the past is a one-
cut off and likewise any defective valves, etc., have to piece forged low carbon steel water header of the
be cut from the pipework. The subsequent re-welding 'bottle' type with welded-on feedwater branches. Typi-
of the heater shell has proved to be less difficult than cal examples of these methods of construction are
the reassembly of complicated bolted joints, which shown in Figs 3.47 and 3.48. The tubes used are low
require special techniques to ensure precise bolt ten- carbon manganese steel suitable for fusion welding
sioning and thereafter periodic checking and possible to the back of the tubeplate. The heater shell, dished
retensioning to allow for gasket relaxation. end, baffle plates, etc., are all made from mild steel
In the following section, examples of current HP plate.
heater construction are given for the two main con- The following sections outline how the design codes
tractors who have supplied heaters for 500 and 660 are used to determine the physical size of a typical
MW units, which shows how their designs meet the HP feedwater heater.
feed system needs.

6.3 Water header, tube bundle and shell


6.2 Construction of high pressure heaters The dominant influence in determining the thickness
The construction of the pressure envelope of vertical of various parts of a water header for an HP heater for
and horizontal HP heaters is very similar and the a given pressure on the feed side is the tube bundle
only differences are the arrangement of the heater diameter, which is governed by the number of tubes
internals, support feet, etc. needed to provide the flow area for the feedwater.
The water header is very similar in both, although The following calculations illustrate the design pro-
the tubeplate tube hole pattern may differ to allow cess to find the relevant thickness of the pressure
for the different arrangements of the drain cooling and parts which are needed to contain the feed pressures
desuperheating sections. In all cases, BS5500 [11] is and flows.
used to determine the thickness of the water header,
tubeplate, shell, etc. The U-tube wall thickness can 6.3.1 To find tube thickness
be found by application of BS1113: 'Design and manu- All modern CEGB HP feedheaters use 19.05 mm
facture of water tube steam generating plant' [14], (0.75 in) outside diameter low carbon manganese steel

292
High pressure feedwater heaters

where e = minimum thickness of straight tube, mm


p = calculation pressure, N/mm 2
f = allowable design stress, N/mm 2
D = outside diameter of tube, mm

For a typical 660 MW unit


p = 217.2 bar or 21.72 N/mm 2
D = 19.05 mm outside diameter

The heater tubes are manufactured to conform to


ESI Standard 2 3 - 4 82 [15] (which supersedes GDCD
Standard 56-80 [16]).
(a) Forged hemispherical head and tubepiate with welded constuction
The tube material conforms to the Type 400' which
appears in the allowable design stress Table 2.3 (k) in
BS5500 [11], giving 96 N/mm 2 at 300C and 88 N/mm 2
at 350C for this material.
If the temperatures used to determine the allowable
stress in the tubes are taken as that experienced by the
ultimate heater, then the worst case is considered.

Steam temperature (assumed) 370C


Outlet feed temperature 253C
Average temperature 312C
By interpolation f at 312C = 97.8 N/mm 2

(b) Cast hemispherical head welded to forged tubepiate


Then tube wall thickness: t = (21.72 x 19.05)/
[(2 X 97.8) + 21.72]
= 1.90 mm
FIG. 3.47 Typical cast and forged HP heater water headers
of the hemispherical type
From BS1113 Clause 3.7.3, the thickness (e b ) allowing
for bends is given by e b = 1.125 e, so e b = 1.90 x
1.125 = 2.14 mm.

Using the nearest standard tube thickness of 203 mm,


tube bore = 19.05 - 4.06 = 14.99 mm, say 15 mm.
Having determined the tube thickness and hence the
bore, the area for flow per tube is known and so the
number of tubes required for a specified HP feed flow
can now be calculated.

6.3.2 Area required for flow through the tube


bundle
As all HP heaters employ U-tubes, the number of holes
FIG. 3.48 Typical forged HP heater 'bottle' water to give the flow area needed is equal to the number of
header monobloc construction with welded-on branches Us. Taking a typical 660 MW feed flow and two-
bank heater configuration:

tubes. Tube thickness is found from application of Flow/heater = 273.5 kg/s


Clauses 3.7.1.1 and 3.7.3.1 of BS1113 [14]. Heater feed inlet temperature = 191C
From Clause 3.7.1.1 but using the same notation Internal tube diameter = 15 mm
as BS5500 [11], Clause 3.5.1.1:
Average feed temperature = 222C
From ERA 1967 Steam Table, = 1.17 x 10~ 3 m 3 /kg
e = pD/(2f + p) specific volume

293
Feedwater heating systems Chapter 3

The missing parameter to find the flow area is the hemispherical head heater, the water head shape is
velocity of the feedwater in the tubes. assumed to approximate to half a sphere and the
For the purpose of this specimen calculation, a water formula from BS5500: 'Minimum thickness for pressure
velocity of 2 m/s is taken, but the actual value varies loading only for spherical shells', Clause 3.5.1.2 [11]
with individual manufacturer's practice; however, is used.
the 'Standards for Closed Feedwater Heaters (HEI) Using the same notation as on Fig 3.49, the wall
1979' [17] recommend not more than 2.4 m/s (8 ft/s) thickness (e) is given by pDj/(4f - 1.2p) where Dj
at maximum flow conditions. = internal diameter.
If, for instance, one bank of HP heaters is by- In practice, the calculated wall thickness is increased
passed in a two-bank system and the feed split is by the manufacturer as appropriate to the method of
60/40, with 60% through the active bank, the feed- construction, i.e., to allow for tolerances on forgings
water velocity will increase to 1.2 times normal ve- or the geometry needed to produce a sound casting.
locity, which would give (1.2 x 2) = 2.4 m/s (i.e.,
the HEI maximum recommended feedwater velocity).
6.3.5 Header branch thickness
Area per tube = (/4)(14.77/1000) 2 The branches can be considered as cylindrical pressure
= 1.713 X 1 0 " 4 m2 vessels and the formulae from Clause 3.5.1.2 (given
in (d) above) used:
Volumetric flow = 273.5 X (1.17 x 10" 3 )
thickness e = pDj/(2f - p)
= 0.32 m 3 /s

Required area = 0.32/2 The bore of the branch must be found first: if a velo-
= 0.16 m2 city of 3 m/s is assumed, the cross-sectional area is
0.32/3.0 = 0.107 m 2 , giving a 0.37 m bore. Therefore,
Number of holes/flow = 0.16/(1.713 x 10~ 4 )
e = (21.72 x 370)/[(2 x 104.8) - 21.72] = 42.8 mm
= 934

The thickness calculated is that needed for pressure


The heater needs 934 U-tubes and the tubeplate has considerations alone. In practice, the branch wall thick-
1868 holes. If a tube pitch of 25.4 mm is taken with a ness is increased to compensate for the opening needed
60 triangular pattern, then allowing for a typical (see Clause 3.5.4 of BS5500 [11]) and also to ensure
minimum U-tube bend and gaps for internal fittings, that it is adequate to withstand the forces imposed on
etc., the tube bundle can be assumed to have an it by the pipework to which it is attached. The end
overall diameter of 1300 mm. of the branch is reduced to a thickness suitable for
welding to the HP feed pipework, which has a typical
wall thickness of 32 mm (see Figs 3.47 and 3.48).
6.3.3 Tubeplate thickness
The tubeplate thickness is found by application of
BS5500, the calculation being shown in Fig 3.49, using 6.3.6 Compensation for openings in the water
the suggested working form for U-tube tubesheet design, header
page 3/96. The thickness calculated for the hemispherical part
The values of the coefficients, which are given in of the water head is based on a vessel wall without
Table 3.9 of BS5500, are also shown in graphical openings. Any openings, such as the branches and
form to demonstrate how they are obtained during access door, have to be allowed for by thickening the
the course of the calculation. If a single bank of HP walls adjacent to the openings (Figs 3.47 and 3.48).
feedwater heaters is considered in place of the double The amount of the compensation is found by ap-
bank, for the same velocity of water in the tubes, the plication of Clause 3.5.4 of BS5500 [11]. Since the
flow area would have to be doubled. amount of compensation will vary with individual
If it is assumed the area required to accommodate manufacturer's designs, a specific example is not given
the doubled number of tubes is twice that previously here.
needed, then the tube bundle diameter will be V2 times
the original diameter, with a consequent increase of
tubeplate thickness to 550 mm. 6.3.7 Shell and dished end thickness
The shell thickness is calculated from the formulae
used to determine branch thickness. The dished end
6.3.4 Water header wall thickness thickness is found using the method detailed in [11]
For the purpose of finding the wall thickness of a Clause 3.5.2 'Domed Ends'.
294
High pressure feedwater heaters

CONFINED HEAD: FLOATING HEAD OR U-TUBE TUBESHEET DESIGN TYPICAL HP HEATER


LOAD CASE: FEED SIDE PRESSURE ONLY - WORST CASE CLAUSE REFERENCE
CONSISTENT UNITS: DIMENSIONS = mm :pftE = N/mm2 BS5500
SHELLSIDE TUBESIDE
DESIGN PRESSURE P, P2 20.7 U-TUBE TUBESHEET THICKNESS 3.9.3
CORROSION ALLOWANCES 1.5 1.5 PRESSURE ACTING ON
TUBESHEET DESIGN TEMPERATURE 255 P = \P2- *M 20.7 3.9.3.1
TUBESHEET MATERIAL 1503

*-[]"
20.7 = 0.486
221 - 410
ALLOWABLE STRESS
AT DESIGN TEMPERATURE
BENDING
SHEAR
/t 104.8
52.4 R = D/D0 if Pi>p2
DESIGN STRESS FACTOR (3.9.2.3) rv 2 = D2/D0\ip2>p1 R = 1473/1300 = 1.133
TUBESHEET E 3 = MAX. OF ABOVE IF p,=p 2
193.4 x 10
c0

TUBES E 0.602 TABLE 3.9
t
LIGAMENT EFFICIENCY REF. 3.9.2.1 AC 0.011 TABLE 3.9
IF TUBES EXPANDED TO FULL-DEPTH AND E^E No C = C0 + 0.613
M=A=|P-(d h-e,)|/P= - BENDING eB=CD0V 0.613 x 1300 x 0.486 = 387mm 3.9.3.1
OTHERWISE 0.155 D.p 0.155 x 1300 x 20.7 _ i q n mm
SHEAR e s = M 1 9 0mm 3.9.3.1
M = \ = |P-cfh]/P=|25.4 - 14.771/25.4 = 0.418 0.418x52.4
PRESSURE FACTORS REF. 3.9.1 MIN. ACCEPTABLE THICKNESS"
-e 387
= GREATER OF e VALUES
2
X2 = J - N\(d - 2etyD0\> = 1-18001(19.05-2x2.14)/1300l = 0.768 TUBESHEET THICKNESS = e+ALLOWANCES
X2 = 1 - N{{d/D0\2 = M80019.05/1300I2 = 0.613 = 387 + 3 = 390mm
S = X3 - X, = 0.768 - 0.613 = 0.754
FS = 0.5(X, + X2) = 0.5(0.768 + 0.613) = 0.69
TUBESHEET EDGE SUPPORT

N = 1800 TUBES (900 Us)


on P = 25.4 PITCH
mm welded

VALUES OF C AS A FUNCTION OF F s AND R FOR TUBESHEETS, AND C 0 FOR U-TUBESHEETS ONLY FROM BS 5500
TABLE 3.9 STATIONARY TUBESHEET - SIMPLY SUPPORTED

FIG. 3.49 Suggested working form for U-tube tubesheet design from BS5500, showing worked example for typical HP heater

6.4 Heater tube length and tube supports Average U-tube length between tubeplates
The thermal performance needed from the heater fixes = 1450/(0.06 x 934)
the heater surface in accordance with the methods = 25.9 m
given later in Section 6 of this chapter.
Average tube bundle length = 12.94 m, which deter-
Assuming a heater surface of 1450 m 2 as typical
of the highest pressure heater for a 660 MW unit, the mines the shell length.
heater length and tube bundle support-plate pitch is
found as follows.
6.4.2 Tube support plates
The tubes are supported by a series of tube support
6.4.1 Length of U-tubes plates in the form of mild steel drilled with the same
Number of U-tubes = 934 (as calculated previously) pattern of holes as the tubeplate. The hole size is a
close fit over the outside diameter of the tubes. The
The tubes are 19.05 mm outside diameter so the clearance between tube and tubeplate varies according
surface area per metre length is i x 0.01905 to the manufacturer's practice, but general guidance
= 0.06 m 2 /m is given in TEMA 1978 [12].

295
Feedwater heating systems Chapter 3

The tube support plates are distributed along the tribute and guide the steam as it flows through the
length of the tube bundle to meet three requirements: desuperheating section and into the condensing section.
The drains water is guided through the drain cooling
To guide the steam or water across the tubes to section by another series of baffles. Initial maximum
provide efficient heat transfer. permissible values of baffle pitch are usually found
from a design code, such as TEMA [12].
To support the tubes so that they are not damaged In any tubular heat exchanger with fluid flow across
by the fluid flow expected to occur within the heater the tubes, there is the possibility of tube damage due
shell. to flow-induced vibration. When fluid flows perpen-
dicular to a cylindrical object, vortices are periodically
To form the ends of the drain cooling and shed downstream, the shedding frequency being pro-
desuperheating section. portional to the fluid velocity. The cylindrical object
will vibrate and if the shedding frequency is equal to
Figure 3.50 shows the layout of the tube support plates the natural frequency of the object, a resonant con-
within a HP heater with drain cooling, condensing dition will occur. There is also the possibility that
and desuperheating sections. The sketch illustrates because tubes are long slender objects, they may under
how the tube support plates act as baffles to dis- certain conditions be excited by random eddies from

DRAIN OUTLET

DRAIN COOLING SECTION

FIG. 3.50 Typical arrangement of tube support plates in the desuperheating, condensing and drain cooling sections
of an HP heater

296
High pressure feedwater heaters

vortices within the tube bundle and a resonant vibra- 6.6 Thermal design
tion could occur. These phenomena are the basis for Earlier in this section it was explained how the tem-
a method given by Thorngren [18], which calculates perature of the high pressure feedwater varies as it
two dimensionless damage numbers N B D and N C D . passes through an HP heater. The heater temperature
N B D is a factor which determines the possibilities limits, combined with the physical size of tube bundle
of damage due to fatigue of the tube material at the diameter, shell diameter, tube size, etc., are the factors
baffle hole. which determine the heat transfer surface area of a
N C D is a factor which is used to predict if collision heater.
damage will occur between adjacent tubes. Figure 3.51 (a) shows typical heat balance informa-
If the damage numbers are both less than unity, tion for the ultimate stages of feedheating for a 660
then the distance between baffle plate supports is MW unit. Also shown, is the associated temperature
adequate. If the damage numbers are greater than profile for the ultimate stage of feedheating (Fig 3.51
unity, then the distance between the baffles needs (c)). The basic equation used to find the surface area
to be decreased. However, reducing the distance de- (A) for each section is A = (q m h)/K(LMTD):
creases the steam flow area and therefore increases the
velocity, which in turn influences thermal design. For where A = heat transfer area, m2
further information, reference can be made to Section
q m = mass flow rate, kg/s
12 Recommended Good Practice' of the TEMA 1978
[12] which gives further references and advice. h = specific enthalpy change through zone,
The baffles are spaced either by means of tie rods, J/kg
which take the form of long screwed bars projecting K = overall heat transfer coefficient, W/m 2 K
from the tubeplate with the baffles set at fixed dis- LMTD = log mean temperature difference, as
tances apart by tubular spacers at appropriate inter- defined in Fig 3.51 (d)
vals, or by welding them to a structure within the
heater shell which is anchored to the heater tubeplate. Figure 3.51 (a) and (b) illustrate how the heat
The baffles are close together in the desuperheating balance information is used to find the enthalpy rise
and drain cooling sections, but wider apart in the through each section in turn and the resultant tem-
condensing section to achieve the best velocity profile perature profile.
and to maximise the heat transfer process. The ideal From this information, the surface area for each
arrangement of baffles is only found by an iterative section is calculated in the manner described below.
process involving both thermal and mechanical design.
The relevant aspects of the thermal design are found
in Section 6 of this chapter. 6.6.1 Desuperheating section
The bled-steam has a high degree of superheat which
allows the feedwater at the exit of the desuperheating
section to approach very near to, or to be slightly
above, the saturation temperature equivalent of the
6.5 Bled-steam inlet
pressure at inlet to the desuperheating section.
Attention must also be given to ensuring that local To prevent erosion due to wet steam flowing through
high velocities are not present at the steam inlet to the exit of the desuperheating section it is established
the heater. There must be ample area to allow the practice to retain about 28C of superheat at the end
steam into the desuperheating section and also to of the desuperheating section, so T 2 is made equal
flow across and along the tube bundle without causing to the saturation temperature equivalent to the pres-
excessive local velocities. The escape area should be sure in the condensing section plus 28C. Figure 3.51
at least equal to the steam inlet area. (c) is based on this assumption.
TEMA 1978 [12] specifies the maximum permissible The temperatures in the desuperheating section are
velocity at the exit from the steam inlet branch into used to evaluate the LMTD as shown in Fig 3.51 (d),
the heater shell without provision of an impingement so the only unknown in the equation to find the
plate or baffle to protect the tubes in terms of the surface area is the heat transfer coefficient.
limiting values of ( 8 ) 2 where is the steam density The methods of calculating the heat transfer co-
(kg/m 3 ) and v ns is the velocity of dry steam (m/s), as efficient for a particular tube bundle are given in
detail in BE AM A 1968 [13] or TEMA 1978 [12]: for a
v ns (max) = V(2250/Q) m/s typical desuperheater in the last stage HP heater its
value is about 500-600 W/m 2 K.
The heat transfer coefficient increases with the in-
If a velocity greater than this value is to be en- creased velocity across the tube bundle. The higher
countered, even for short periods of operation (e.g., the velocity, the greater the pressure drop across the
previous heater by-passed), the provision of a larger desuperheating section, which in turn reduces the sat-
branch or some form of impingement plate is needed. uration temperature within the condensing section.

297
Feedwater heating systems Chapter 3

340C
70.0 kg/s
41.25 Bar a

340C (STEAM TEMPERATURE)

^ HP1 I

7 / I 252.2C X I

/
(a) Heat balance for top two HP Heaters (b) Heat balance for individual sections ultimate heater

K
SH = Degree of
superheat in steamm
at exit from D/S
section {usually 28C)
8C)

\ ^s^ _T d0 Ts - T -

t'

\ T0

DESUPER- DRAIT^^W
HEATING COOLING ^ t,
SECTION CONDENSING SECTION SECTION

(c) Temperature profile for ultimate heater

THE MEAN TEMPERATURE DIFFERENCE FOR CONDENSING, DESUPERHEATING AND DRAIN COOLING SECTIONS
FEEDHEATER SECTION LMTD em
(T-t0 )- ( T d o- t c o)

/ T - to \
INTEGRAL DESUPERHEATING SECTION
T
^ V * > - co/
t t cl

T
CONDENSING SECTION WITH INTEGRAL DESUPERHEATING AND DRAIN / s - c \
lo
COOLING SECTIONS 9e 1 1
V s - co /
(
5 - ^ , ) - ( To ~ 1
,>

INTEGRAL DRAIN COOLING SECTION


x
\ \ ~ y )

WHERE T IS THE TOTAL STEAM TEMPERATURE AT HEATER INLET


Tdo IS THE STEAM TEMPERATURE AT OUTLET FROM THE DESUPERHEATING SECTION
t, IS THE FEED WATER INLET TEMPERATURE
to IS THE FEED WATER OUTLET TEMPERATURE
To IS THE DRAIN TEMPERATURE AT HEATER OUTLET
t IS THE FEED WATER TEMPERATURE AT INLET TO CONDENSING SECTION, AND IS CALCULATED BY
HEAT BALANCE
t IS THE FEED WATER TEMPERATURE AT OUTLET FROM CONDENSING SECTION, AND IS CALCULATED
BY HEAT BALANCE
IS THE SATURATION TEMPERATURE OF THE STEAM AT THE INLET TO A HEATER WITH INTEGRAL
DESUPERHEATING SECTION

IF A CONDENSING FEED WATER HEATER HAS AN INTEGRAL DESUPERHEATING SECTION, THERE IS A LOSS OF
PRESSURE FROM THE HEATER INLET TO THE DESUPERHEATING SECTION OUTLET WHICH REDUCES Ts TO Ts
THUS Ts = Ts. T
WHERE T IS THE DIFFERENCE IN SATURATION TEMPERATURE OF THE STEAM BETWEEN THE STEAM INLET
AND THE DESUPERHEATING SECTION OUTLET

(d) Determination of LMTD

FIG. 3.51 Thermal design

298
High pressure feedwater heaters

The heat exchanger designer has to reach a cost as the mean effective length of a U-tube in deter-
effective compromise between increased condensing mining the heater shell length.
surface area against decreased desuperheating surface The baffles within the heater shell, which form the
area, the velocity being dependent on the pitch of the compartments through which the steam or condensate
baffles in the desuperheating section for a given tube flow, have windows so that the fluid can pass longi-
pattern. Once an acceptable compromise has been tudinally. The area used is equal to, or greater than,
reached, a check can be made to ensure that the pitch that available for cross-flow.
chosen is equal to or less than that allowed by con- From the references given to find the heat transfer
sideration of tube damage due to flow-induced vibra- coefficients [14], it will be seen that the theoretical
tion (as described earlier in this section). values are modified to allow for leakage through the
The surface area can now be calculated. From the tube/baffle plate clearances, lack of true cross-flow and
area, number of tubes and surface area/metre length the stagnant areas in the corners of the compartments
of tube, the length of the desuperheating section is formed by the baffles.
found. The baffle pitch may need slight readjustment The heat transfer coefficients obtained by using
to meet the overall length requirement. these references, assume that the condensing section
within the heater is adequately vented to the condenser
to avoid the accumulation of air or non-condensable
6.6.2 Condensing section gases within the section. The heat transfer coefficient
The condensing section uses the method of calculating used to determine surface area is significantly influ-
LMTD as illustrated in Fig 3.51 (d) but with T! = T 2 enced by non-condensables which tend to form a
= T s , the saturation equivalent of the pressure in the gaseous muff around the condensate film on the out-
condensing section. The effect of the 28C of super- side diameter of the tube. The slowing of the diffusion
heat may be neglected as its effect on the surface area of vapour into the condensate by the non-conden-
will be small. The overall heat transfer coefficient is sables, significantly affects the condensing section per-
dependent on the condensing heat transfer process formance. This is a most important factor in heater
and can be found by reference to BE AM A 1968 [13] performance, and an unexpectedly poor performance
or TEMA 1978 [12]. The baffle pitch is determined from a new heater can be usually traced to incorrect
by the need to distribute the steam throughout the air venting. The usual vent rate is about 0.5% of the
condensing section and is usually about the maximum bled-steam flow to the heater.
permissible without the risk of tube vibration. The Accumulation of air can also occur in the drain
length of the condensing section is determined from cooling section and cause pockets in the corners local
the heat transfer surface needed, the external area of to the baffle plates. This reduces the available heat
the tube per unit length and the number of tubes. transfer surface which again reduces heater performance.
In a two-flow U-tube heater, as illustrated in Fig For an overview of the complete thermal/mechanical
3.44, the condensing section includes the return bend design of HP heaters, reference should be made to
of the 'U' and part of the bottom return leg. the Heat Exchanger Design Handbook 1984 [19].
Should cycle economics dictate a low first-cost feed
system, then HP heaters can be used with no drain
6.6.3 Drain cooling section cooling section and/or no desuperheating section. Where
In this section the condensate formed in the con- no desuperheating section is provided, a small section
densing section has further heat removed by transfer local to the steam inlet is baffled to help to absorb the
to the incoming feedwater. The equation for the calcula- superheat, but is not allowed for in the calculation of
tion of the surface area is as before. The LMTD is the surface area.
found using the temperatures shown in Fig 3.51 (c). The omission of the drain cooling section means
The heat transfer coefficient is found by the methods that the drains are discharged from the heater at sat-
given in BEAMA 1968 [13] or TEMA 1978 [12]. The uration temperature and there is no need for a fixed
velocity of the drains condensate across the tubes is im- water level in the heater shell to protect the drain
portant in determining the heat transfer coefficient, so cooling section from erosion. The design procedures
again baffle pitch is important and the subject of an to determine the surface area of each section is the
iterative process during the design. same whatever combination of sections is used.
A typical figure for the heat transfer coefficient in Vertical-attitude heaters differ slightly in the inter-
the drain cooling section will be about 1900 W/m2 K. nal arrangement of components but use the same
Again, tube length is found from the drain cooling design principles for mechanical and thermal design.
surface as explained above.

6.6.4 Other factors affecting thermal design 6.7 Horizontal high pressure heaters
The total length of the heater U-tube is the sum of An HP heater, as manufactured by GEC for the
the lengths of the three sections. This length is taken Littlebrook D 660 MW units, is shown in Fig 3.52.
299
300
(b) Desuperheating section
Feedwater heating systems

DIP TUBES
(d) Part section of heater

(c) Drain cooling section PRESSURE RELIEF VALVE OUTLET FLANGE TUBENEST
BLED STEAM CONDENSING SECTION

AIR VENT SIGHT GLASS ISOLATOR


STANDPIPE ISOLATOR

WATER LEVEL STANDPIPES & 'B'

STEAM INLET DIFFUSER


BLED STEAM INLET
DESUPERHEATING SECTION \
TUBEPLATE LIFTING TRUNNION

FEEDWATER OUTLET \ STAY ROD


LIFTING EYE
\ SLIDING FOOT
LEVEL SETTING SCREW
BAFFLE PLATE
DIVIDING PLATES HORIZONTAL & SIDE BAFFLES
INSPECTION COVER
^ CONDENSING SECTION MAIN SUPPORT
HIGH WATER LEVEL SWITCH
WATERBOX MANHOLE fJ
DOOR SIGHT GLASS ASSEMBLY
SIGHT GLASS DRAIN
AIR SUCTION DRAIN COOLING SECTION (a) Cutaway perspective
LEVEL CONTROL TAPPING of complete heater
0=TJ STEAM DIVIDING BAFFLE DRAIN COOLING INLET POT
4 _ FEEDWATER MAIN SHELL DRAIN
FIXED FOOT
CONDENSATE / DRAIN COOLING SECTION TOP PLATE
FEEDWATER INLET \ DRAIN COOLING INLET POT
SHELL START-UP DRAIN
DRAIN COOLING SECTION OUTLET VENT
CONDENSING SECTION OUTLET VENT

FIG. 3.52 Horizontal HP heater, Littlebrook D power station


Chapter 3
High pressure feedwater heaters

The flow paths for feedwater, bled-steam and drain and the holes through which the tubes pass.
water are indicated. The heater illustrated has a steel Figure 3.52 (c) and (d) shows how the 'dip tubes',
hemispherical water head with mild steel U-tubes weld- which form the seal between the condensing and drain
ed to the tubeplate by the Foster-Wheeler method. The cooling sections, are welded to the drain cooler shroud.
shell, baffles, etc., are all made from mild steel. The The dip tubes and the bellows piece which seals the
heater is of all-welded construction, except for items drain cooler outlet are welded in position after the
such as inspection doors, etc., which need regular shell has been placed over the tubenest.
removal. The heater has desuperheating, condensing The space below the tube bundle in the condensing
and drain cooling sections provided in the form of section is used to maintain a fixed water level above
suitably-baffled compartments. To provide a steam the drain cooling section dip-tubes by means of the
flow path in the condensing section above the top drain water level control system.
of the tubenest and also a space below the tubenest The drains from the bottom of the condensing sec-
for drain flow, a segment at the top and the cor- tion flow via the two dip-tubes into the drain cooling
responding segment at the bottom of the tubeplate section, from where they flow to the centre and are
which could be used for tubes is left blank. This discharged by the central drain branch.
shows as a 'flat' on the top and bottom of the gen- The venting arrangements are illustrated in Fig 3.53
erally circular tubenest. A dividing baffle is placed which shows the vent paths within the heater. The air
in the water head to provide the two-pass flow path and non-condensables in the condensing section are
for the feedwater. vented by the hollow tubes incorporated in the hori-
The horizontal dividing plate which runs the full zontal centre baffle. The drain cooling section also has
length of the tubenest is used to support the baffle air vents just above the drain cooler outlet.
plates and also to carry the air extraction ducts. The heater has a single relief valve sized in accord-
The desuperheating section is in the form of a ance with BS5500 Appendix J [11].
shroud over the return half of the water flow adjacent Support feet are provided at each end of the heater;
to the tubeplate encompassing nine baffles. A plate the fixed foot is at the water header end, with the
is provided to seal the bottom to form a steam-tight other foot being free to slide to allow for thermal
compartment. The steam inlet is at the top centre of expansion.
the desuperheating section. A diffuser is provided to A water header manhole door is provided to allow
prevent direct impingement of steam on the desuper- access to the feed side of the tubeplate for inspection
heating section tubes. The steam flows in both di- and tube plugging. The heater internals are not in-
rections from the central entry point, the baffles having tended to be maintained in situ, but to have the whole
cut-outs (illustrated in Fig 3.52 (b)) to provide as heater cut out of the pipework and moved to some
near cross-flow of the heating steam as attainable. convenient maintenance area for the shell to be cut
The end baffles have no cut-outs and form the end adjacent to tubeplate and removed. This is only ne-
of the section. The end baffles are also thicker than cessary if a heater has to be retubed.
normal baffles and have combined sealing and anti-
vibration clips fitted in the clearance between the
tubes and the holes through which the tubes pass. A
removable bellows piece connects the steam inlet of 6.8 Vertical high pressure heaters
the heater and the stub branch on the desuperheating A 500 MW unit vertical HP heater, as manufactured
section, the bellows piece being welded in place after by NEIP for Ince B power station, is illustrated in
the shell is in position over the tubenest. The steam Fig 3.54. Because of the economic factors prevailing
leaves the desuperheating section by four windows cut when the overall turbine/feed system was evaluated,
in the shroud as shown in Fig 3.52 (b). The condensing it was found that the provision of drain cooling sec-
section baffles have no cut-outs but take advantage tions was not cost effective. The heater does, however,
of the space between the tube bundle and the shell have a desuperheating section. The water header is of
to distribute the steam over the length of the con- the all-forged 'bottle' construction, with the inlet and
densing section where it is condensed, the condensate outlet branches and the support feet welded to the
draining to the bottom of the shell. A drain water main forging. The desuperheating section is at the
level is maintained in the shell by the external drain bottom of the heater surrounding the tubes on the
control system. outlet side of the U-tube bundle. As the desuperheat-
The drain cooling section occupies the space directly ing section wrapper plate and end section will be in
below the desuperheating section. It comprises 13 contact with the drains water, a double-skin con-
baffles with cut-outs suitable to promote cross-flow of struction is used to prevent direct contact between
the drains, all enclosed by a semicircular shroud, with metal at steam superheat temperature on one side
the full baffles at each end forming the end of the and condensate at saturation temperature on the
drain cooling section. A plate is provided to seal the other (see Fig 3.54 (a)).
top of this section. The end baffles have combined A baffle plate is provided at the bled-steam inlet
sealing and antivibration clips fitted between the tubes to prevent tube erosion/vibration and, as a further

301
Feedwater heating systems Chapter 3

TUBEPLATE DESUPERHEATING CONDENSING SECTION CONDENSING SECTION


SECTION CENTRE BAFFLE MAIN SUPPORTS

WATERBOX \ DRAINS COOLING TUBENEST


SECTION VENTS

CONDENSING
SECTION
CENTRE BAFFLE

DRAINS COOLING
SECTION
TOP PLATE
TYPICAL VIEW DRAINS COOLING
ON ARROW ' SECTION TYPICAL VIEW
ON ARROW 'B'

VENT FROM DRAINS


COOLING SECTION CONDENSING SECTION HEATER
END BAFFLE SHELL
VENT FROM REAR CONDENSING SECTION
CONDENSING SECTION SIDE BAFFLE

CONDENSING SECTION
HORIZONTAL BAFFLE

STEAM

AIR

WATER

TYPICAL VIEW
ON ARROW ' C

CONDENSING
SECTION
DISHED END BAFFLE

FIG. 3.53 Venting system for a typical HP heater

302
High pressure feedwater heaters

AIR RELEASE CONNECTION

BLED STEAM PIPE ,^%


VENT CONNECTION

BAFFLE PLATE
(HAIRPIN TYPE)

STIFFENERTUBE

BOLLARD
ATTACHMENT PLATE

CONDENSING SECTION

DISTANCE TUBE

(d) Condensing section drains flow


STAY

RELIEF VALVE CONNECTION


DEFLECTION PLATE

BODY

BOLLARD FACING
TUBE NEST
AIR RELEASE CONNECTION

TUBE SUPPORT
CONNECTING SLEEVE PLATES

WRAPPER PLATES
PACKER (DRAIN COOLER SECTION)

SPACER T
SEALING PLATE
(DRAIN COOLER SECTION)

INSPECTION BRANCH

OUTER WRAPPER (c) Condensing section steam flow


ANTI-VIBRATION
PLATE
(DESUPERHEATER SECTION) STRIPS

DRAIN CONNECTION
(BODY)
INNER WRAPPER
PLATE
DRAIN CONNECTION
(DRAIN COOLER SECTION)
BAFFLE PLATE

INLET RING WATER INLET

STEAM INLET CONNECTION SUPPORT FOOT

DIVISION PLATE
BELLOWS UNIT

INSERT PIPE DRAIN CONNECTION


(CAVITY SECTION)
DRAIN POT

DRIAN CONNECTION COVER PLATE


(DESUPERHEATER SECTION)

DRAIN CONNECTION
(DRAIN POT) (b) Desuperheating section steam flow

(a) Heater arrangement


WATER OUTLET VENT CONNECTION
(DRAIN POT)

FIG. 3.54 Vertical HP heater, Ince B power station

precaution, antivibration strips are placed between the a port cut in the back wall of the wrapper plate at
tubes opposite the steam inlet branch. The steam inlet the top. The steam and drains then follow the route
is sealed to the shell by a bellows piece which is indicated in Fig 3.54 (c) and (d). In both sections,
welded to the wrapper plate and the inlet branch. The the steam is constrained to flow across the tubes in
steam flows through the desuperheater (as shown in such a manner as to maximise heat transfer. As the
Fig 3.54 (b)) and into the condensing section through steam condenses, the drains flow down into the bot-

303
Feedwater heating systems Chapter 3

torn of the heater to accumulate in that half of the HP heater is the water header. To reduce its cost
shell not occupied by the desuperheating section. A and also its thermal inertia, designs incorporating a
water level is maintained in the bottom of the heater, drum-type water header have been constructed.
the purpose being to seal the drain outlet to prevent Figure 3.55 (a) and (b) shows two different solu-
erosion due to two-phase flow adjacent to the drains tions for constructing an HP heater without a con-
outlet. The air vents are placed at the top of the shell ventional water head. The heater shown on Fig 3.55 (a)
as all non-condensable gases and air will rise to that was constructed for Thorpe Marsh power station and
point. employed a central header with the mild steel tubes
These two short descriptions of current HP heaters radially disposed, the tubes being welded to the header
illustrate how the design principles, explained earlier by the Foster-Wheeler method. The length of the tubes
in this section, are implemented in practice. was such that they had to be constructed from several
lengths of pipe butt-welded together. This length of
tube was difficult to handle and adequate provisions
had to be made within the shell to support the tubes.
6.9 Alternative designs of heater construction The only drawback to this design was its high cost of
A brief description of older heater designs is included construction.
to indicate how other approaches to provide cost ef- The heater illustrated in Fig 3.55 (b) was constructed
fective HP heaters have been tried. by GEC and used mild steel tubes manually-welded to
The most expensive component in the construction bifurcation pieces which were, in turn, welded to boiler
of a conventional hemispherical water header type of superheater type headers. The bifurcation pieces were

FEED WATER FEED WATER


INLET OUTLET

CYLINDRICAL
HEADER DE SUPER HEATING
SECTION

AIR VENT
CONNECTIONS
2
DIAMETRICALLY SUPPORTING
OPPOSITE FOOT

DRAIN OUTLET

=3
(a) (b)

FIG. 3.55 HP feedheaters with cylindrical headers

304
De-aerating feedheaters

used to allow a smaller number of attachments to to the de-aerator tank is used. Chapter 4, Section
be made to the header to gain access for the attachment 14.7 of this volume describes the system and how
weld to the headers. it functions.
These heaters suffer from some tube erosion in the
region of the bifurcations but, in general, have been a Accept the HP heater drains.
successful design. Because of the high cost of con-
Heat the tank content from cold to provide hot
struction, the development of this design was not
de-aerated water for unit start-up.
pursued.

The following examples of different manufacturers'


de-aerators show how they achieve these objectives
7 De-aerating feedheaters by different design philosophies.

7.1 Introduction 7.2 Thermal/hydraulic design


Figure 3.56 shows a typical de-aerator and feedwater
Water from the condenser (condensate) which has storage tank, the head of which heats and de-aerates
been heated by the LP feedheaters is supplied to the the incoming condensate before it drains by gravity
de-aerator to be further heated and de-aerated into the storage tank. The design uses spray nozzles
preparatory to being fed to the boilers by the boiler to produce a fine film/spray to maximise the surface
feed pump, via the HP feed train. De-aerators on area of the water available to the steam for heat
modern large units are designed to provide feedwater transfer and to minimise the distance that the oxygen
at exit from the storage tank with not more than 5 has to travel to be released. Any residual oxygen is
micrograms per kilogram (/ig/kg) of oxygen. released while the water is further heated as it passes
De-aeration is achieved by the application of Henry's over a series of perforated trays, which causes the
Law which states that the quantity of gas dissolved in condensate to fall as a continuous 'rainfall' from tray
a given quantity of solution is proportional to the to tray.
partial pressure of that gas over the solution. When
this law is applied to the removal of oxygen from feed The heat transfer coefficient in the fine film/spray
water, where the atmosphere above and around the zone is about five to ten times the value for the drop
condensate contains no oxygen, then the dissolved phase of approximately 14 kW/m2K. As nearly 90% of
oxygen will escape to that atmosphere in an attempt the temperature rise occurs in the film phase, the
to achieve equilibrium. temperature difference between the water drops cas-
To construct a de-aerating heater to release the cading from the lower trays and the steam is small. The
maximum amount of oxygen from the incoming con- additional trays, however, are needed to allow time
densate, the following factors have to be considered: for the residual oxygen to escape and also to heat the
water to the saturation temperature equivalent to the
The time for the dissolved oxygen to travel to the prevailing pressure.
surface of the water. The steam flow path is shown by the arrows in
Fig 3.56. A small flow of steam, along with the oxy-
A dwell time is needed for the steam to heat the gen and non-condensable gases, is extracted by vents
condensate and so increase the equilibrium pressure on the top of the head. The mixture of steam and
of the dissolved oxygen in order to release it. oxygen, if vented directly to the condenser, would
constitute a heat loss. To save this heat, a vent con-
The surface tension of the water. denser is provided to heat the incoming feed by con-
densing the vapour and extracting the heat from the
The time taken for the diffusion of the oxygen oxygen and non-condensable gases.
from the water into the steam atmosphere. The oxygen and non-condensable gases are extracted
from the vent condenser by venting it to the conden-
The storage tank associated with de-aeration has to ser, from where the gases are discharged by the main
meet the following needs: air extraction pumps.
The storage tank associated with the de-aerating
Store approximately 7-10 minutes' worth of CMR function stores about 300 tonnes of feedwater in a
flow, as defined in Section 3.3 of this chapter. tank of approximately 4.5 m diameter by 32 m long:
it is accommodated on an elevated floor in an annexe
Accept the leak-off flows from the boiler feed between the boiler house and turbine hall.
pumps, when needed. At low loads, when the flow Diffusers are provided to discharge the leak-offs
through the feed pump would be less than about and the HP drains into the tank, as indicated on Fig
25%, a special leak-off system which discharges 3.56.
305
Feedwater heating systems Chapter 3

SECTION THROUGH X-X


TYPICAL CENTRIFUGAL SPRAY NOZZLE

DEAERATOR WATER
DISTRIBUTION HEADER

STEAM INLET -

, STEAM INLET
(TO PURGE TANK)

STEAM HEATING TUBE NEST DISTRIBUITON PIPES STEAM HEATING TUBE NEST STORAGE TANK
TO ENSURE MIXING
OF TANK CONTENT

FIG. 3.56 Section through a typical spray/tray type de-aerator and associated storage tank

The steam coils used to boil and thereby de-aerate Vertical baffles are also needed to prevent possible
the tank content prior to unit start-up are also shown Sloshing' of the tank content from end to end under
in Fig 3.56. conditions of abnormal steam flows across the tank
Unless provision is made to induce movement of surface. The transfer pipes between the tank and the
the tank contents, stagnant areas of subcooled water de-aerator head are of generous size to allow flow of
will result. A distribution system is provided to pre- vapour to the head when the tank content boils due
vent direct discharge of the incoming heated and de- to a reduction in de-aerator tank pressure.
aerated feedwater from the boiler feed pump suction The de-aerating head shown in Fig 3.57 employs a
pipe connection. By use of a distribution system, ade- different design philosophy, using trays only to obtain
quate mixing of the tank content is ensured. the de-aeration of the feedwater. The incoming feed

DEAERATOR

WATER
(CONTAINMENT
TROUGH
FOR CLARITY VENT CONDENSER WATER DRAIN PIPE DISTRIBUTION
NOT SHOWN IN THIS VIEW CONTAINMENT FROM CONTAINMENT TROUGH
TROUGH TROUGH
SECTION A'-A'

FIG. 3.57 Section through a typical tray-only type de-aerator and associated storage tank

306
De-aerating feedheaters

is heated by a large vent condenser which contributes shows a section through a typical Stork de-aerator,
an appreciable proportion of the temperature rise over with the steam and water paths indicated.
the heater. This reduces the heating required during There is no de-aerating head as such, but in the
transit through the trays. space above the working water level in the top of the
The condensate is directed onto the top tray from storage tank there is a series of specially designed
where it cascades through the rest of the trays to flow sprayers, which spray the incoming feedwater onto a
by gravity into the storage tank. The steam/water flow ring of plates which further breaks up the water.
paths are indicated on the figure. The sprayers are designed to create sufficient spray
The steam flow to the vent condenser is about area and water droplets to provide the necessary heat
25-30% of the bled-steam flow: any oxygen and transfer surface to heat the incoming feed to as near
non-condensable gases are swept away in this vent to the saturation temperature (corresponding to the
flow. The vent condenser is vented to the main con- pressure within the de-aerator) as practicable. In prac-
denser, as indicated, and the gases are discharged tice, the temperature of the feedwater in the tank has
from the main condenser by the air extraction pumps. been measured to be within 1-2C of the saturation
The feedwater storage tank associated with the temperature. The stored water in the tank is therefore
de-aerating heater on Fig 3.57 is similar in size and heated to the saturation temperature of the incoming
the provisions for leak-offs, HP drains, etc., to heating steam as it enters the tank through the sprays.
that described for Fig 3.56. The other features de- A steam distribution system in the form of a 'rake'
scribed for the first de-aerator storage tank are also is provided, the teeth of which are vertical tubes per-
provided. forated at their ends. The end which is perforated is
A design of de-aerator currently intended for use positioned to be always below the lowest working
within a CEGB power station is the 'Stork' de-aerator. feedwater level. The heating steam introduced into
This type of de-aerator employs a different approach the tank content via the steam 'rake' is nearly at the
to the task of extracting the oxygen and other non- same saturation temperature as the tank content and
condensable gases from the condensate. Figure 3.58 is therefore not condensed, but bubbles through the

AIR VENT AIR VENT


CONDENSATE _ ^ i ^ A
INLET 1 ^ ^T

STEAM DISTRIBUTION P I P E S -
PERFORATED TO ALLOW DISCHARGE OF STEAM
BELOW WATER LEVEL

DETAIL OF PERFORATIONS

FIG. 3.58 Section through a typical 'Stork' de-aerator

307
Feedwater heating systems Chapter 3

water where it absorbs any residual oxygen and non- sion into the tubeplate. The shell and other details
condensable gases not liberated in the spray phase. are made of mild steel.
The oxygen and non-condensable gases are released De-aerators ordered prior to 1976 were designed
from the steam and incoming feed in the spray area and constructed in accordance with BS1500 and after
and are extracted from the air vent on the top of 1976, to BS5500 [11]. The thickness of the tank walls,
the shell. The 'Stork' de-aerator has no vent con- dished ends, sizes of branch compensations, allowable
denser as the loss due to the heat in the vapour/air size and positions of support feet, etc., are all deter-
mixture is too small to warrant its cost. mined by use of BS5500 [11].
The sprayers on the top of the vessel are a Patented Appendix J of BS5500 [11] is used to determine
'Stork' design (as shown in Fig 3.58) and create a relief valve capacity.
uniform spray pattern between maximum and mini- As already indicated, the de-aerator tank is a large
mum condensate flow rates. vessel and therefore cannot be transported and erected
HP drains are sprayed into the top of the tank above in one piece. The tank is made in segments rolled
the water level through dispersers. The leak-offs are from mild steel plate, with the axial joints made by
introduced below the water level by means of pipes welding. When the segments are joined to form the
of the same design and vertical attitude as those which tank, these joints are positioned so they do not coin-
form the teeth of the steam rake. Steam coils are cide. This prevents a continuous line of weld in the
provided for start-up heating with electrical heaters horizontal direction and the crossing of two welds.
to maintain tank temperature. The tank is site-erected in segments and welded to-
In the event of sudden unit load reduction, the gether when in place.
bled-steam pressure will fall and the tank content will
boil. The small auxiliary connection is provided to
equalise the pressure between the space above the
water level in the tank and the steam rake and dis- 8 Low pressure heaters
tribution pipework. The connection prevents the water
being forced into the steam distribution system.
Vertical baffles which extend to the high water
8.1 Introduction
level are provided to prevent the formation of waves
on the water surface and to preclude the possibility of The current generation of surface type U-tube low
'sloshing'. The action of the steam bubbling through pressure (LP) heaters has developed from the tradi-
the tank content prevents the formation of stagnant tional surface LP heater, which has been in use for
areas where subcooled water could collect. the last 70 years. The design has been updated to
Baffles adjacent to the drain outlets shield the areas take advantage of modern manufacturing techniques
around them from disturbance by the steam discharg- and materials. The latest designs of heaters are also
ing from the steam rake. The drain outlets are internal constructed to take full advantage of a horizontal
to the tank and have a flare to promote smooth flow attitude.
into the feed pump suction pipework. The other design of LP heater currently in use on
the 500 MW units and the early 660 MW units is the
direct contact type. They are similar in design and con-
struction to the de-aerating head of a de-aerator.
7.3 De-aerator construction
The de-aerating heads and tanks shown in Figs 3.56
to 3.58 are cylindrical pressure vessels, with dished
ends constructed of mild steel. The spray nozzles and 8.2 Surface type low pressure heaters
trays are made of stainless steel to prevent corrosion Because LP heater extraction points are normally on the
attack. LP turbine cylinders, the superheat (even on the highest
The spraywater distribution system and tray support pressure LP heater) does not justify the provision of
structure, shown in Figs 3.56 and 3.57, are made of desuperheating sections within the heaters.
mild steel and the perforated stainless steel trays are Drain cooling sections could be provided but the com-
supported and held by this structure. The trays have plication and cost of a drains level control system can
to be fixed firmly, as they are subjected to the forces seldom be justified. It is usual practice to have the
created by the steam as it flows across the trays. LP heaters constructed as condensing-only heaters,
Because the head on the de-aerator illustrated in and to provide a drain cooler upstream of the lowest
Fig 3.56 is supported on steelwork, the connections pressure heater to recover some of the heat in the
to the tank are all provided with bellows joints to drains.
allow for relative movement. The vent condensers are The drain cooler used is usually of the hashing'
similar in construction to the LP heaters described type. A flashing drain cooler is a separate heater
in Section 8 of this chapter. They have mild steel placed in the feed train upstream of the lowest pres-
tubeplates with stainless steel tubes fixed by expan- sure LP heater. It is a small heater with no bled-steam
308
Low pressure heaters

supply but has a chamber at one end where the com- 8.3 Construction of low pressure heaters
bined LP drains are flashed into steam and water. The construction of vertical and horizontal LP heaters
The steam is condensed on the heater tubes and the is very similar. The following descriptions are for
drains are discharged to the condenser via a loop horizontal heaters but any significant points of dis-
seal. similarity between horizontal and vertical heaters are
To reduce the water burden of the steam flowing included.
to the last row of LP turbine blades, a special pur- Figures 3.60 and 3.61 show arrangements of two
pose heater called the turbine moisture extraction typical U-tube two-flow LP heaters as manufactured
condenser (TMEC) is provided. The TMEC is designed by NEIP and GEC, respectively.
to extract the steam/water mixture from the water ex- The maximum head that the condenser extraction
traction belt situated immediately before the last row pump can generate occurs at the no flow condition
of LP turbine blades. Modern TMECs, if required, and is sometimes called the Closed valve head'. The
are provided in the form of a multi-compartment LP heaters are designed on the feedwater side to
LP surface type heater. Each compartment is con- withstand the extraction pump 'closed valve head'.
nected to a low pressure cylinder. This prevents inter- On a typical 660 MW unit this is a pressure of about
connection of cylinders and consequent difficulties 40 bar. Because of this modest feed water pressure
caused by recirculation of a water/steam mixture (compared with HP heaters), LP heaters can be de-
between cylinders. signed to take full feed flow without the resultant
As the construction of a TMEC is so similar to an tube bundle diameter leading to an unacceptably thick
LP heater, its detailed construction is not described. tubeplate.
The steam inlet size of an LP heater is large com- The general form of the LP heater is similar to HP
pared with the heater body size due to the rapid heaters but, because the feedwater side pressure is
increase in the specific volume of the steam as the modest, the water header can be of cylindrical design
pressure decreases. On some of the lower pressure with a dished end. The shell side pressures are also
heaters, this results in multiple inlets with steam belts modest, so again the shell is cylindrical in section with
to keep the inlet velocity to the tube bundle to an a welded dished end. A fixed and a sliding foot is
acceptable value. provided to support the heater. The shell, tubeplate
A current development in LP heater design, which and water header are all made of mild steel.
has not yet reached service, is to place the two lowest An all-welded construction is used and it is ac-
pressure LP heaters in the condenser neck. Figure 3.59 cepted that in the unlikely event of access being re-
shows this diagrammatically. The heaters are of the quired to the heater internals, the shell will have
duplex type (i.e., LP1 and LP2 combined) with gravity to be removed by cutting close to the back of the
drains into the condenser. The general construction tubeplate. The tubes are roller-expanded into the
is similar to other LP surface type heaters. The main tubeplate.
advantage of this arrangement is the saving in tur- The tubes of LP heaters may be of 70/30 brass
bine hall space. Small savings are also made due to or stainless steel as dictated by steam temperature
elimination of the pressure drop associated with the or boiler feedwater chemistry requirements. Brass may
bled-steam isolating and non-return valves. The pres- be used in LP heaters where the steam temperature
sure drop in the bled-steam pipework is also virtually is not greater than 150C. Above this temperature
eliminated. stainless steel is used. For AGR feed systems, where

DRAINS TO DRAIN COOLER

DRAINS FROM LP2 DRAINS FROM LP2 TO LP1

O = OVERFLOW DRAIN USED WHEN DRAINS FLOW IS ABOVE LEVEL OF NORMAL DRAIN OUTLET
N = NORMAL DRAIN

FIG. 3.59 Combined LP1 and LP2 heaters in the condenser neck
The LP1 and LP2 tubenests are placed in the same shell. The LP2 half of the tubenest is enclosed in an inner shell which
isolates it from LP1 on the steam and drain sides. The water box is divided into three parts.

309
Feedwater heating systems Chapter 3

CONDENSATE
OUTLET STEAM INLET STEAM INLET

STEAM IMPINGEMENT
PLATE

AIR VENT
TO CONDENSER

SECTION THROUGH
STEAM INLET
CONDENSATE
INLET

FIG. 3.60 Section through a typical horizontal LP heater, Heysham 2 power station

WATER LEVEL STANDPIPE '

STANDPIPE ISOLATOR

E
SIGHT GLASS
^ ISOLATOR
SIGHT GLASS
' ASSEMBLY
MAGNETIC
LEVEL SWITCH
STANDPIPE
ISOLATOR
SIGHT GLASS
ISOLATOR
AIR VENT FROM CENTRE DUCT

LIFTING EYE
WATER LEVEL STANDPIPE 'B'
WATER EXPANSION SLIDING FOOT

WATERBOX VENT

TUBEPLATE
BAFFLE PLATE
SIDE BAR SUPPORT
WATERBOX DIVISION x
PLATE STAY ROD
~~ SHELL DRAIN
INSPECTION COVER
- FIXED FOOT

FEEDWATER INLET
FEEDWATER OUTLET MANHOLE ACCESS
WATERBOX

FIG. 3.61 Section through a typical horizontal LP heater, Littlebrook D power station

full flow polishing plant is needed, copper-bearing 8.4 Water header, tube bundle and shell
materials should not be employed downstream of the A significant factor in determining the thickness of
polishing plant: so stainless steel is used for all LP the various parts of the heater is the tube bundle
heater tubes, including the drain cooler and TMEC. diameter. To find this the number of U-tubes needed
Until 1976, LP heaters were designed to comply with to pass the feed flow has to be found. Each LP feed
BS1500; heaters specified since that date have been heater passes full feed flow.
constructed to BS5500. The heaters shown in Figs 3.60
and 3.61 are constructed to comply with BS5500 [11].
The methods used to determine the physical size of 8.4.1 Tube thickness
an LP heater to fulfil a particular duty, as defined As the LP heater U-tubes are roller-expanded into
by feed cycle needs, is very similar to that illustrated the tubeplate, the tube wall thickness is determined
for HP heaters in Section 6 of this chapter. Using by the need to have a long term leak-free joint be-
the same order of calculation as for HP heaters, the tween the tube and the tubeplate. Experience has
details are shown in the next section. shown that tubes expanded into a mild steel tube-
310
Low pressure heaters

plate, as used for LP heaters, need a tube wall thick- do not allow for the effects of openings in the vessel
ness of at least 1.2 mm to prevent the tube wall walls. The compensations needed around the various
relaxing under conditions of thermal cycling. openings to compensate for the penetration are
While the thickness of 1.2 mm is greater than is calculated, as for HP headers, by the application of
needed for feed water pressure requirements, it never- Clause 3.5.4 of BS5500 [11].
theless allows for corrosion damage and also makes
the U-tubes easier to handle while the heater is being
8.4.7 Shell and dished end thickness
manufactured.
The tubes are fully expanded into the tubeplate The pressure range over which LP heaters operate
for a depth of approximately 50-75 mm from the is from maximum bleed point pressure to full vacuum.
water side of the tubeplate and then lightly expanded If the shell thicknesses were determined by differen-
for the rest of the depth of the tubeplate. The light tial pressure alone, the thickness of the lower pressure
expansion is to close the gap between the tube and heater shells would be insufficient to withstand loads
tubeplate, where water could penetrate and possibly from pipework or being lifted into place during the
cause crevice corrosion. The mechanism of roller- course of plant erection. In practice, shell thickness
expanding tubes into tubeplates is described in depth is not made less than about 12 mm but this again
in Chapter 4, Section 3 which deals with the methods depends on individual manufacturer's practice. Ex-
of fixing tubes in condenser tube sheets. ternal stiffening rings are sometimes also used to
permit the use of slightly thinner shells. The dished end
thickness is chosen to suit the shell thickness.
8.4.2 Flow area
The calculation to find the flow area is the same as
that described in the section on HP heaters. The
maximum velocity used in the tubes depends upon 8.5 Heater tube length and tube supports
the manufacturer's practice but usually does not ex- The procedure used is again similar to that already
ceed 1.8 m/s. described for HP heaters. However, for LP heaters,
For a 660 MW unit, a typical LP heater has about this usually only involves consideration of a condensing
1000 U-tubes with a tube bundle diameter of about section. If integral drain coolers were to be used,
1.4 m. the procedure would be the same as that used for HP
heater drains coolers. An average U-tube length between
8.4.3 Tubeplate thickness tubeplates on an LP heater for a modern 660 MW unit
The tubeplate thickness is found from BS5500 [11], is about 18 m, giving an average tube bundle length
using the suggested working form for U-tube tube- of 9 m.
sheet design on Page 3/96.
The calculation is very similar to that shown on 8.5.1 Tube support plates
Fig 3.49, the only difference being that allowance From Figs 3.60 and 3.61, it will be seen that there is
is made for the stiffening effect of the tubes where a divergence of design philosophy in the method of
they pass through the tubeplate. Using this method of providing support for the tube bundles. The heater
calculation, a typical 660 MW LP heater tubeplate in Fig 3.60 has a vertically-disposed structure extend-
with a tube bundle diameter of 1.4 m has a thickness ing the length of the tube bundle, made of plate
of about 200 mm. and hollow square-section tube which carries the tube
support plates. Attached to lugs on the periphery of
8.4.4 Water header wall thickness the tube support plates are radial side support bars,
which locate the tube bundle in the shell. The support
The formula from BS5500 Clause 3.5.1.2(a) Cylin-
plates also take the weight of the tube bundle while
drical Shells' [11], is used to find the wall thickness
it is being inserted or withdrawn from the shell.
for the water headers illustrated in Figs 3.60 and 3.61.
With corrosion and other allowances, a typical wall The heater shown in Fig 3.61 uses six stays, over
thickness is 32 mm. which fit hollow cylindrical spacers to maintain the
intended distance between baffle plates. The baffle
plates are cropped at top and bottom, as shown in
8.4.5 Water header branch thickness the section through the heater, to allow steam to flow
The same formula as that quoted above for water transversely along the top of the shell and drains to
header wall thickness is used to determine the branch flow along the bottom of the heater. The main steam
wall thickness. and drain flow paths are indicated on the figure. Two
guide rails are provided inside the shell to take the
tube bundle weight via the baffle plates. They also
8.4.6 Compensations for openings in the waterbox support the tube bundle when it is inserted or with-
The thickness calculated for the various components drawn from the shell.
311
Feedwater heating systems Chapter 3

The distance between the tube support plates is purpose of calculating the LMTD. Using the equation
determined by the following needs: given in Section 6 of this chapter, the heat transfer
surface is determined.
To guide the steam across the tubes to provide Baffle pitch is again determined by the need to
efficient heat transfer. distribute the steam throughout the heater and is
usually close to the maximum allowable without risk
To support the tubes so that they are not damaged
of damage to the tubes due to flow-induced vibration.
by the action of the steam flowing across them.
The U-tube length is found from tube outer surface
area/metre length, number of tubes and the surface
The rules used to determine distance between baffles needed.
is the same as those given in Section 6.4 of this The need to vent the heaters to prevent the heat
chapter for HP heaters. The Thorngren [18] damage transfer process being reduced in efficiency due to the
numbers are normally used to determine if the dis- presence of non-condensable gases has already been
tance between baffles is such that flow-induced vibra- discussed for HP heaters. It is just as important to
tion damage is unlikely. have the LP heater adequately vented: this may be
more difficult in some cases than with HP heaters,
as some LP heaters work under vacuum and the vents
have to cope with any slight air inleakage which may
8.6 Bled-steam inlets and drain outlets occur local to the heater. For the heaters illustrated
As with HP heaters, high local velocities adjacent in Figs 3.60 and 3.61, the air is extracted from the
to the bled-steam inlets must be avoided to prevent centre of the nest for its full length to ensure that
damage to tubes. no pockets of air can be trapped between the baffles.
Impingement plates are provided under the bled-
steam inlet branches on the heater illustrated in Fig
3.60. The manufacturer of the other heater, however,
has chosen to provide steam inlet belts with ports 8.8 External drain coolers
placed around the circumference of the shell to pro- Two types of heat exchanger can be used as external
vide a large flow area and consequent low inlet velo- drain coolers to extract the maximum amount of heat
cities. A drain is provided on the bottom of the steam from the combined drains of the LP heaters.
inlet belt to prevent water accumulation. Figure 3.62 shows diagrammatically the two types
As condensate is formed in the heater, it is drained of drain cooler. The flashing type is similar to an
from the bottom of the heater shell. LP heater, as the steam fraction of the flashed drains
The drainage of horizontal heaters depends upon is condensed on the U-tubes of a heat exchanger. As
the water flowing from each end of the heater to a seen from Fig 3.62 (c), the pressure in the shell is
drainage point on the bottom of the shell. equal to the saturation pressure equivalent to the
A natural water level is established which is de- drains temperature. It is the temperature difference
pendent upon outlet diameter, rate of flow of conden- between the incoming feedwater and the drains outlet
sate out of the vessel and the radius of the horizontal that determines the size of the heater. At the design
vessel. The relationship is complex and reference should point, the heat transfer surface is sized to maintain
be made to Gardner and Crow [20], Kubie, Rowe and the drain cooler outlet temperature at the specified
Jones [2] and Cranfield [21] for a full explanation value.
of the influence that various parameters have on the The general construction of a flashing drain cooler
depth of water in the heater. The determination of is the same as an LP heater. The shell is extended to
the natural water depth is important. The water level provide a flash chamber where the drains can flash
must be below the bottom tubes or the heat transfer into steam and water at the pressure determined by
surface will be lost. The level at which the high water the thermal performance of the heaters. The steam will
level switches should be set is also dependent on the be about 30 to 40% of the incoming quantity and,
maximum working level under the permitted operating because of the low pressure, volume will be large.
conditions. U-tubes are roller-expanded into a mild steel tube-
plate and the shell is of all-welded mild steel con-
struction. Internal baffles are provided to prevent the
flashing steam and water impinging on the shell or
8.7 Thermal design tubes and causing erosion damage. The path taken by
The determination of the surface area of a condensing the steam and water is indicated in Fig 3.62 (a).
type LP heater is similar to the method already out- The alternative type of drain cooler uses the heat
lined in Section 6 of this chapter, which refers to the in the drain water to heat the incoming condensate
thermal design of the HP heater condensing section. by making the drains flow across the tube bundle
Although the higher pressure LP heaters have some through which the feed is flowing (Fig 3.62 (d)). In
superheat in the bled-steam, it is ignored for the principle this is identical to the drain coolers already
312
Low pressure heaters

CONDENSATE , DRAINS FROM


STEAM EVOLVED BY CONDENSATE LP HEATERS
DRAINS FLASHING DIFFUSER
DRAINS FROM
LP HEATERS

JLJl

r
DRAIN TO IMPINGEMENT
PLATE TO

CONDENSER
PREVENT DAMAGE
CONDENSATE TO " U " T U B E S CONDENSATE DRAIN TO
INLET INLET CONDENSER

(a) Flashing type drain cooler (d) Water-to-water drain cooler

(b) Temperature diagram (e) Temperature diagram

DRAINS FROM LP HEATERS DRAINS FROM LP HEATERS

-HN
X
Where t is the feed water inlet temperature Where I is the feed water inlet temperature

t is the feed water outlet temperature tQ is the feed water outlet temperature

T is the saturation temperature of the flashed steam T is the mean temperature of drains at inlet to drain cooler

T is the mean temperature of drains at inlet T Q is the drain temperature at heater outlet

T is the drain temperature at heater outlet

(c) Heat balance (f) Heat Balance

FIG. 3.62 External drain coolers

313
Feedwater heating systems Chapter 3

described for HP heaters. The heat balance to deter- of the incoming condensate for presentation to the
mine the rise over the drain cooler is shown in Fig heating steam. The maximum heat transfer coefficient
3.62 (0 and the resultant temperature gradient is is obtained by using sprays or trays to form film/
illustrated by inset (e) of the figure. Again, U-tubes droplet flow.
are roller-expanded into a mild steel tubeplate. The The shells and dished ends are constructed of mild
shell is of all-welded steel construction. steel. As the last station to be constructed with DC
The baffle arrangement, however, is different as heaters was ordered before 1976, all the DC heaters
the baffles are required to guide the water across were constructed in accordance with the now super-
the tubes and to prevent leakage between the shell seded BS1500. The size of the heater shell is deter-
and baffle. The baffles are semicircular and a close mined by the need to accommodate the sprays or
fit in the shell. The path needed to be taken by the trays to pass the feed flow, and so varies from heater
drain water is shown in Fig 3.62 (d). to heater. Figure 3.63 shows a typical horizontal atti-
tude DC heater of NEIP manufacture, employing a
system of jets which impinge on plates to produce
8.8.1 Thermal/hydraulic design of a flashing a fan-shaped film. The feedwater from the previous
drain cooler heater is introduced into the channels which run along
the axis of the vessel. These distribution channels
The temperature of the feedwater leaving the heater
are bridged by pipes across the inside of the shell.
for a specified temperature difference is found by
Holes of the appropriate size and position direct jets
performing a heat balance over the drain cooler (Fig
of water onto the 'spray plates'. Sufficient depth below
3.62 (c)).
the spray plates is provided for the steam to heat the
The temperatures required to complete the diagram
water to the saturation temperature corresponding to
shown in Fig 3.62 (b) are now available. Assuming the heater body pressure.
that all the condensate flows through the drain cooler
tubenest, then the tubenest will have the same number A small baffle which runs the length of the shell
of tubes as the LP heaters in the feed system. The at each side forms a ledge from under which the air
overall diameter will also be the same. The LMTD is extracted. The heater is continuously vented to the
calculation is shown in Fig 3.62 (b). The heat transfer condenser. The steam inlet has a baffle which directs
surface is then found using the same method as for a the steam along the axis of the shell.
normal LP heater. The drain outlet is at the centre of the heater and
is fitted with an antivortex device. As discussed earlier
in this section for horizontal LP heaters, a natural
drainage level in the heater exists dependent on the
8.8.2 Thermal/hydraulic design of a water-to-
flow rate into the heater, the heater shell diameter,
water drain cooler
etc.
The temperature out of the drain cooler is found by The DC heater illustrated in Fig 3.64 was manu-
a heat balance over the drain cooler as shown in factured by GEC. The design philosophy is similar
Fig 3.62 (f); however, in this case the drains flow is to the de-aerator head shown in Fig 3.57, but with
treated as hot water. minor differences to adapt the principles for DC
The heat transfer coefficient is calculated as for an heater service.
HP or LP internal drain cooler, using the temperatures A water distribution header directs the incoming
indicated in Fig 3.62 (e). condensate through perforated windows in its under-
The tubenest will have the same number of tubes side onto perforated trays below. The resultant rain-
as the first LP heater for full condensate flow, and will fall is heated by the condensation of the steam to
have the same shell diameter as the LP heaters. the saturation temperature equivalent to the shell
The baffle pitch is determined by the need to main- pressure.
tain the velocity of the water across the tubes to give The illustration shows the provision made to allow
the needed heat transfer coefficient. the steam free access to the water cascading over
The drain cooler actually used depends on the the trays. Steam flow is directed to the lower half
manufacturer's assessment of the most cost effective of the heater to ensure that water cascading from
type for a particular installation. the bottom trays is heated to the full saturation tem-
perature. Air is vented to the condenser from each
nest of trays from just below the cold water entry
point.
8.9 Direct contact low pressure heaters Double drain outlets are provided to ensure ade-
In both thermal and mechanical design, direct contact quate drainage, taking into account the principles
(DC) LP heaters are very similar to a de-aerator heater discussed earlier in this section for horizontal LP
head. They are cylindrical vessels arranged in either heaters.
the horizontal or vertical attitude, equipped internally The trays and perforated distribution inlet window
with a means to maximise the heat transfer surface are made of stainless steel to prevent erosion/corrosion.
314
Evaporators and other means of water treatment

SPRAY TUBE

PRESSURE GAUGE CONNECTION RELIEF VALVE CONNECTION


WECTION SPRAY TUBE SUPPORT
SPRAY PLATE
CONDENSATE INLET HEATER BODY

OFF LOAD SWITCH


TEST CONNECTION
BLANK CONNECTION STANDPIPE AIR RELEASE MANHOLE ACCESS DOOR
CONNECTION

tal direct contact LP heater, Ince B power station


FIG. 3.63 Typical arrangement of a horizontal

9 Evaporators and other means of water Current practice is to use a chemical raw water
treatment treatment plant followed by filters and mixed-bed
deionisation plant. For the AGRs and for the pro-
jected PWR, a full-flow polishing plant in the feed
train is provided to ensure the high quality of boiler
9.1 Introduction feedwater.
The traditional method of producing high quality A full description of the raw water treatment plant,
water for boiler feed was to distil water by the eva- filters and mixed-bed deionisation plant, and a full-
poration of treated raw water. Treated water is boiled flow condensate polishing plant is given in Volume E.
in the evaporators by the application of heat in the However, to provide a complete description of modern
form of LP bled-steam from the turbine or a steam plant, the following section gives details of typical
supply from the auxiliary boiler. The resultant vapour steam evaporating equipment which is currently in
is condensed and can be used to replenish the reserve use in large CEGB power stations.
feedwater tanks or fed directly to the condenser as To provide the operational water needs of modern
a make-up water; however, the lower cost of water power stations, a raw water treatment plant is needed
treatment by the deionisation method has made it with a daily output of about 3% CMR steam flow.
uneconomic to install bled-steam evaporators for the The water treatment plant has also to provide water
latest plant. to meet the additional losses of two-shift operation,
315
Feedwater heating systems Chapter 3

TRAY SUPPORT CONDENSATE


CHANNEL BOX

CONDENSATE
CONDENSATE
INLET

CONDENSATE
INLET

FIG. 3.64 Typical arrangement of a horizontal direct contact LP heater, Heysham 1 power station

the filling of boilers and the feed system after main- stage and is finally removed by means of an extraction
tenance, and the special needs of chemical cleaning pump.
and commissioning.

9.2 Types of bled-steam evaporator


VAPOUR OUTLET

Two types of evaporator have been used by the CEGB


(discounting the horizontal submerged coil type as WATER RETURN

inappropriate for large modern power station feed-


VAPOUR/WATER
water treatment). MIXTURE EJECTED

The first is the surface 'Vertical-tube' type invented


by Kestner in 1909. Figure 3.65 shows the arrange-
ment of a typical vertical-tube evaporator. The water
inside the tubes is boiled by the heating action of
the bled-steam on the outside of the tubes and a
mixture of vapour and water is expelled from the
top of the tubes. The water spills into the central
WATER LEVEL
FLOAT CONTROL
VALVE
downcomer and the process continues by natural cir-
culation. The rising vapour passes through baffling INCONDENSABLE
to reduce the quantity of entrained droplets thrown GAS OUTLET

up by ebullition and is then condensed in an external


vapour condenser. Any non-condensable gases carried
CONDENSATE OUTLET
MAKE-UP INLET
out with the vapour are vented.
The second type is the 'Flash' evaporator. A sche-
matic diagram of a two-stage flash evaporator is CONTINUOUS
BLOW DOWN

shown in Fig 3.66. The raw water is heated near to HEATING STEAM
saturation temperature of the heating steam and is I L P VAPOUR
I FEEDWATER
then cascaded through the evaporator in series, which , CONTINUOUS
1
BLOWDOWN
is at a lower pressure than the water. A proportion
of the hot raw water flashes in each stage and is
condensed by the raw water on its way to the heat FIG. 3.65 Typical arrangement of a 'vertical-tube'
input section. The distillate cascades from stage to evaporator

316
Future developments

of the evaporator plant which provides the necessary


HEATING STEAM
temperature variation through the evaporator for effi-
cient heat transfer.
HEAT INPUT
SECTION J
1 COLLECTION
TRAY
The vapour chamber of the evaporator is connected
to a blowdown system which allows a calibrated flow
Jr K. /
of water to be pumped out of the vapour chamber. This
y
Y RAW WATER IN

A
H ^ - ^ DISTILLATE OUT
fixed flow rate maintains the correct body concentra-
| VAPOUR 1
tion when the evaporator is on-load.
CONDENSATE
DRAIN The purified water vapour from the evaporator is
7-x condensed in the condenser by heat exchange with
^^^^^H^^M
condensate from the turbine. It is then drawn from the
condenser by a distillate pump and pumped through
a cooler/heat er to the system discharge point. The
FIG. 3.66 Schematic diagram of a two-stage 'flash'
evaporator distillate raises the temperature of the incoming feed-
water as already described. After leaving the heater/
cooler the temperature, pressure and conductivity of
the distillate are checked.
9.3 Surface type evaporator
The flow diagram for a typical single-stage evaporator
is shown in Fig 3.67 and the associated evaporator
assembly in Fig 3.68. The principle involved is similar 9.4 Flash type evaporators
to that described for the vertical-tube type evaporator. Flash evaporators have been available for many years.
However, the natural circulation is replaced by a small They have only emerged within the last two decades
pump which ensures circulation to the heating cham- as a viable proposition for large scale distillation,
ber. Various heat exchangers are also added to increase due to the fact that multiple-effect or multistage
the thermal efficiency of the process. plant can now be built in the very large sizes required
Treated feedwater is pumped successively through for potable water in arid countries. Thanks to modern
four heaters/coolers, a preheat and a vent vessel to methods of raw water pre-treatment they can also
an evaporator. After vaporisation in the evaporator, operate continuously for long periods.
it is condensed into distillate and delivered to the Large multistage evaporators can be built econo-
system discharge point by a distillate pump. mically on the 'egg crate' principle, each stage con-
During its passage from the feedwater pump to sisting of a narrow vertical compartment in the crate
the evaporator, the temperature of the feedwater is with raw water on its way to the heat input section
raised by heat exchange, first by distillate from the traversing each compartment in straight tubes. Figure
condenser, secondly by condensate from the evapora- 3.69 illustrates the construction of an experimental
tor and, thirdly, by bled-steam from the turbine. 10-stage flash evaporator which has been in service
Feedwater is also used (by the second cooler in the with the CEGB.
line) to cool non-condensable gases vented from the Since heat consumption varies inversely with the
vent vessel, evaporator and condenser. number of stages, the flash evaporator can compete
Gases are vented from the feedwater in a vent successfully with other forms of evaporation plant
vessel, positioned between the preheater and the eva- by having multiple compartments or stages in a single
porator, after which it enters the vapour chamber of vessel. However, even this economic form of water
the evaporator. It is then circulated to the heating treatment plant is not as cost effective as a modern
chamber of the evaporator by a circulation pump. polishing plant for the production of boiler feedwater
The feedwater is vaporised by heat exchange with and no further installations are planned.
bled-steam from the turbine. The vapour rises, re-
enters the vapour chamber and then passes to the
evaporator vapour condenser.
Bled-steam condensate from the heating chamber, 10 Future developments
which includes that from the preheater, passes through The development of feed system design and its asso-
two of the heaters/coolers where it exchanges heat ciated components is dependent upon the cycle steam
with the incoming feedwater as already described. conditions and the turbine-generator unit capacity
The drain from the heater/coolers is taken to the chosen for the next generation of power stations to
condenser flash vessel. be constructed by the CEGB. Present indications are
A vacuum system connected through the inconden- that non-nuclear stations will be coal-fired, with sub-
sable gas cooler to the evaporator, vapour condenser critical or supercritical steam conditions and a unit
and vent vessel; draws gases, together with some vapour, capacity of about 1.5 times the current 660 MW units.
from these vessels and discharges to atmosphere. The need for the development of systems and com-
The system maintains a vacuum at the back end ponents for a number of specific plant areas has been
317
318
TO ATMOSPHERE

0 SILENCER
M VACUUM
g 2 r-, PUMP
Feedwater heating systems

TREATED FEED T FEED WATER PUMP


WATER INLETt

FEED WATER
DISTILLATE
SEAL WATER
- BLED STEAM
BLED SYSTEM CONDENSATE
INCONDENSABLE GASES & CONDENSATE
CONDENSATE
INCONDENSABLE GASES

FIG. 3.67 Schematic diagram of a typical single-stage evaporator


Chapter 3
Future developments

WATER OUTLET
BRANCH
INSPECTION MANHOLE

SUPPORT FOR
GAS COOLER

TOP WATER BOX

SIGHT GLASS

REINFORCING RING BLED STEAM INLET

DEMISTER PAD

BLOWDOWN TANK VENT

PREHEATERVENT

VENTVESSEL BALANCE

SIGHT GLASSES
SUPPORT PLATE

SUPPORT FOR THERMOMETER


VENT VESSEL POCKET

FEEDWATER INLET
FROM VENT VESSEL

THERMOMETER
POCKET

CONDENSATE FROM
PREHEATER

LOWER WATER BOX

RECIRCULATING WATER OUTLET

- INSPECTION
MANHOLE
VAPOUR CHAMBER

HEATING CHAMBER

FIG. 3.68 Details of evaporator assembly, vapour chamber and heating chamber

CONDENSATE
OUTLET

MAKE-UP WATER
INLET

FIG. 3.69 Diagrammatic arrangement of a 10-stage flash evaporator

319
Feedwater heating systems Chapter 3

identified to meet the increased flows and pressures Although thermal transients can be reduced to a
to be used for the projected plant. minimum by individual by-passing of preceding heaters
The current generation of designs are adequate for and rigorous reinstatement procedures, with specified
projected nuclear power stations, although any ap- rates of temperature increase for a cold heater, the
propriate developments made for future coal-fired use of such measures imposes cost penalties due to
plant would be utilised. the extra equipment involved as well as imposing op-
The feedheating system can be conveniently divided erational restrictions.
into three sections; HP feed system, de-aerator system The limitations imposed by the thermal inertia of
and LP feed system: consider each in turn. the large mass of metal in a conventional hemi-head
type of heater can be overcome by using a modern
version of the header type of heater similar in prin-
ciple to that illustrated in Fig 3.55. The use of the
10.1 HP feed system latest manufacturing techniques for a similar design
The increase in unit size and possible use of super- has resulted in heaters which are currently giving satis-
critical steam conditions will increase the HP heater factory service in Europe and America as shown in
hemi-head diameter and thickness. With current HP Fig 3.70. To increase throughput of feedwater in
header design using a hemi-head with U-tubes, the such a heater, the number of tubes is increased and
tubeplate thickness will increase because of the heater the header length is adjusted to allow the attachment
diameter being 1.25 times that of present units to of these extra tubes. The heater shell diameter has
maintain the velocity of feed in heater tubes at exist- to be increased to accommodate the extra tubes but,
ing values. A further increase in tubeplate thickness as the shell is only subjected to bleed pressure, it
will be needed for heaters used in a supercritical will require only a modest increase in thickness. As
cycle as the feedwater pressure will be approximately the header diameter is small, an increase in pressure
1.5 times that used when steam conditions are sub- of 1.5 times does not result in a header wall thickness
critical. The increased tubeplate thickness will also which imposes operational restrictions due to thermal
need further development of present techniques for transients inducing unacceptable stress levels within
deep-hole (gun) drilling. One disadvantage of thicker the header. The use of header type heaters is con-
tubeplates and hemi-head walls is the increased sus- sidered to be an option for future stations as an alter-
ceptibility to damage caused by thermal transients native to conventional hemi-head HP heaters.
inducing high stress levels.
The perforated area of the tubeplate responds al-
most immediately to the feedwater temperature change
caused when preceding heaters are by-passed. The un- 10.2 De-aerator system
perforated volume and the hemi-head respond slowly, Traditionally the de-aerator storage tank capacity and
thereby creating a temperature gradient between the height have been determined by the constraints de-
perforated and unperforated sections of the tubeplate scribed in Section 3 of this chapter. For increased unit
with the potential of creating high local stress levels. size, it becomes increasingly costly to accommodate

FEEDWATER ^
INLET ^

FEEDWATER ^
OUTLET ^

FIG. 3.70 Arrangement of HP header-type heater

320
References

the storage tank size and weight at the traditional have to be determined for each case. However, in
high level. general, it is expected that tank size can be reduced
Design studies indicate that a decreased tank ca- to about 5 minutes' worth of CMR flow at normal
pacity may be acceptable. A review of the boiler needs working level, with the tank placed at a significantly
for hot de-aerated water during start-up, storage capacity reduced elevation.
to meet normal rates of load change and topping up
the boiler after a unit trip, has indicated that a tank
of about half the previously accepted capacity would
be adequate (i.e., about 5 minutes CMR worth of flow). 10.3 LP feed system
The rate of pressure decay (and hence the ability of It is expected that future large coal-fired units will
a given de-aerator system to avoid boiling in the feed use an LP feed system similar to that already illus-
pump suction pipework during transients) depends trated in Fig 3.6 for the PWR cycle (i.e., forward
on the amount of stored heat (i.e., hot water) in the pumping of higher pressure LP heater drains with
tank and the rate of introduction of cold feed to the the lower pressure heaters mounted in the condenser
tank. As the amount of hot water is reduced, so is the neck). There will therefore be no significant changes
stored heat. in existing system design or components.
Provision has to be made to prevent common mode
failure of LP heater bled-steam isolating valves causing
loss of heating steam to the LP heaters, as this intro-
duces condensate at a reduced temperature to the 11 References
tank which could cause an unacceptable rate of pres- [1] Dartnell, L.: review of the operational behaviour and
sure decay. Diversity of operation or the provision of design of direct contact feed water heating plants for large
stored energy local to the valves would be a suitable thermal power stations': Proc. IMechE., Vol. 187: 1973.
solution. [2] Kubie, J., Rowe, M. and Jones, E. W.: 'Hydrodynamic aspects
All other conditions can be avoided by good op- of the design of feed heaters and de-aerator storage tanks':
Paper C140/79 'Steam Turbines for 1980s, IMechE Sym-
erational techniques and suitable sequences to avoid posium': 1979
pumping cold condensate into a hot depleted tank.
[3] Downs, J. E.: 'Forced outages of large steam turbines an
An alternative solution is to provide a 'pegging' analysis of causes': Vol. 32, Proceedings of the American
steam supply which would maintain the de-aerator Power Conference: 1970
pressure from an alternative steam supply (say cold [4] Dickinson, J. D. and McKinley, D. E.: Turbine effects
reheat) in the event of an unacceptable rate of pres- from steam and water abnormal cooling': Proceedings of the
sure decay being detected. American Power Conference: 1970
Modern boiler feed pumps for large capacity tur- [5] Reinhard, K. G. and Schatzmann, G. P.: 'Turbine water dam-
bine-generators being supplied by UK manufacturers age prevention': Proceedings of the American Power Con-
ference: 1972
to customers overseas, require less suction head than
those currently installed in CEGB power stations. The [6] Spence, J. R. Ryall, M. L. and McConnell, A.: 'The develop-
ment and production of high pressure feed heaters for modern
height at which the de-aerator tank must be placed central power stations': Proc. IMechE, Volume, 182: 1967/68
relative to each boiler feed pump depends upon the [7] Cranfield, R. R. and Wilkinson, D. H.: 'Analysis of power
suction head requirements of the pump, plus an plant de-aerator storage tank instabilities': Proc. IMechE,
allowance for friction and transients. Any reduction Vol. 195: 1981
in suction head requirement allows a corresponding [8] Dartnell, L. M.: The thermal-hydraulic design of main feed water
reduction in tank elevation. The elevation at which pump suction systems for large thermal power plant': Proc.
the tank is placed is also influenced by the need to IMechE, Vol. 199: 1985
have a suitable floor or steelwork to support the weight [9] Wilkinson, D. H. and Dartnell, L. M.: 'Water hammer
of the tank. phenomena in thermal power station feed water systems':
Proc. IMechE, Vol. 194: 1980
When the measures to prevent unacceptable rates
[10] Dartnell, L. M.: 'Hydraulic and thermal hydraulic instability
of pressure decay during a transient are combined with in condensate feed systems for large thermal power stations':
the new generation of feed pumps which require re- Proc. IMechE, Vol. 186: 1972
duced suction heads, then the combination of a small- [11] BS5500: 'Specification for unfired fusion welded pressure vessels':
er de-aerator tank at a lower level can be achieved. 1985
However, the overall system must withstand any tran- [12] 'Standards of tubular exchanger manufacturers association', Sixth
sients which could cause loss of suction or boiling within Edition: Addenda Address, Tubular Exchanger Manufacturers
the pipework between the de-aerator tank and the feed Association, Inc., 25, N. Broadway, Tarrytown, New York,
10591: 1978 and 1982.
pump suction stage. This ability to withstand transient
conditions can be demonstrated using the calculation [13] 'Guide to the design of feed water heating plant': Publication
No. 226, the British Electrical and Allied Manufacturers'
methods outlined in Section 3 of this chapter, allowing Association Limited, 8 Leicester Street, London: 1968
for any special features used to minimise pressure [14] BS1113: 'Design and manufacture of water-tube steam gen-
decay during normal operation. erating plant (including superheaters, reheaters and steel tube
The de-aerator storage tank capacity and elevation economisers)': 1985

321
Feedwater heating systems Chapter 3

[15] ESI Standard 2 3 - 4 : 'Seamless steel feed water heater tubes carbon Processing, Page 129: April 1970
for high pressure applications': Electricity Supply Industry:
[19] 'Heat exchanger design handbook': Hemisphere Publishing
March 1982
Corporation: 1984
[16] CEGB Standard 234102; GDCD Standard 56, Issue 2: 'Carbon
[20] Gardner, G. C. and Crow, I. G.: 'Onset of Drawdown of
and Alloy Steel Feed Water Heater Tubes': December 1980
Supernatent Fluid in Surge Tanks': Chemical Engineering
[17] 'Standards for closed feedwater heaters': Heat Exchange In- Science, Volume 26, Pages 211 to 219: 1971
stitute, Inc., Fourth Edition: Heat Exchange Institute, 1230, Keith
[21] Cranfield, R. R.: 'Drain discharge characteristics of horizontal
Building, Cleveland, Ohio, 44115: 1984
drums': Journal of Mechanical Engineering Science, Volume,
[18] Thorngren, J. T.: 'Predict exchanger tube damage': Hydro- 23, No. 2: 1981

322
C H A P T E R 4

Condensers, pumps and cooling water


plant

CONDENSERS 8 Plant testing


8.1 Introduction
1 Introduction
8.1.1 Test codes and practices
2 Economics 9 Future developments
2.1 Condenser surface area, turbine exhaust pressure and 9.1 Aims and objectives
CW flow 9.2 Research and development
2.1.1 Input data 9.2.1 Tubenest layout
2.1.2 Computation 9.2.2 Thermal performance properties of tubing
3 Historical development and layout
PUMPS
3.1 Phase 1
3.2 Phase 2 10 Air extraction equipment
3.3 Phase 3 10.1 Introduction
10.2 Determination of air extraction quantity
4 Environmental considerations 10.2. 1 The mechanism of air extraction
4.1 Cooling water quality 10.2.:2 The condenser air cooling section
4.1.1 Corrosion prevention 10.3 Review of air extraction equipment
4.1.2 Other copper-alloy tube failure mechanisms 10.3 1 Hydraulic air pumps
4.1.3 Material selection 10.3.:2 Liquid-ring type air pump
10.3.3 Air ejector/pump systems
5 Thermal design
10.3.4 Steam ejector/pump systems
5.1 Theory 10.4 Quick-start plant requirements
5.1.1 Heat rejected 10.4. 1 Type of plant
5.1.2 Heat transfer 10.4.:2 Starting times
5.2 Design codes, standards and specifications
5.2.1 H El Standards 11 Hydraulic aspects of centrifugal pumps
5.2.2 BEAMA design recommendations 11.1 Specific speed
5.2.3 CEGB specifications 11.2 Net positive suction head
5.3 Influence of tubeplate and tubenest geometry on thermal 11.3 Suction specific speed
performance 12 Circulating water pumps
5.3.1 Subjective design evaluation
5.3.2 Computer assisted design evaluation 12.1 Introduction
12.2 Horizontal split-casing pumps
6 Mechanical design 12.3 Vertical pumps
6.1 Introduction 12.3.1 Vertical metal-casing pumps
6.2 Constructional development 12.3.2 Concrete volute pumps
6.2.1 Construction materials 12.4 Gearboxes
6.2.2 Design forces and stresses 12.5 Shaft seals
6.2.3 Methods of manufacture and construction 12.6 Pump testing
6.3 Protection and cleanliness of condensers 12.7 Materials
6.3.1 Debris filter 13 Condenser extraction pumps
6.3.2 Condenser tube cleaning system
14 Boiler feed pumps
6.4 Special considerations
14.1 Introduction
7 Operational life limiting constraints 14.2 Feed pump developments
7.1 Condenser air inleakage 14.3 Advanced class feed pump construction
7.1.1 Locating air leaks 14.4 Axial thrust
7.1.2 Measurement of air leakage rate 14.5 Gland sealing
7.2 Cooling water leakage in condensers 14.6 Pump layout and drive
7.2.1 Fluorescein method 14.7 Light load protection
7.2.2 Foam or film methods 14.8 Testing
7.2.3 Bubbler devices 14.9 PWR feed pumpsets
7.2.4 Tracer gas methods 14.10 Future trends
7.2.5 Flame and smoke methods 15 Miscellaneous pumps
7.2.6 Ultrasonic method
7.3 Condenser fouling and cleaning 15.1 Service water pumps
7.3.1 Condenser fouling 15.2 Chemical injection pumps
7.3.2 On-load condenser cleaning 15.3 Fire pumps
7.3.3 Off-load condenser cleaning 16 References

323
Condensers, pumps and cooling water plant Chapter 4

CONDENSERS Figure 4.2 indicates the component terminology


for the two typical arrangements of the evaporative
1 Introduction cooled and heated water systems which will be used
The ultimate heat sink for a large thermal power throughout this chapter, and it is intended to be used
station is the atmosphere. There are various options for reference purposes. The following paragraphs
available, using different processes to achieve the briefly describe the functional requirements of some
most effective heat sink, and therefore meet the re- of the plant components.
quirements of the condensing plant and cooling water The screening plant must remove any debris from
(CW) system. the cooling water which is large enough to block the
Typical atmospheric heat dissipation systems are condenser or auxiliary cooler tubes. It must be easy
illustrated in Fig 4.1. Those most commonly used are: to keep clean, even during periods of excessive debris.
The cooling water (CW) pumps must circulate the
Process (a) evaporative cooling, associated with water against system resistance, or pumping head,
closed systems (cooling towers) for heat dissipation. under all conditions encountered at a particular site.
To ensure efficient and flexible CW pump operation,
Process (b) heated water discharges, associated with
valves are usually provided to allow any combination
direct cooled systems (river or seawater) for heat
of pumps, condensers and cooling towers to operate
dissipation.
together.
In the heated water discharge direct-cooled system,
When considering a new site for a power station, it the cooling water (river or seawater) is used once and
is important at the planning stages to ensure that then discharged. In the evaporative-cooled closed cool-
it has adequate cooling water facilities. With increas- ing tower and mixed cooling systems, the cooling
ingly high station output and unit rating, the choice towers transfer heat from the plant to the atmosphere
of location is narrowed by the necessity to match and the cooled water is recirculated. In this case the
available water resources. This along with equally water requirements are for make-up and purge pur-
important factors, such as type of fuel and selection poses only.
of steam conditions, are the major features con- In addition to the condenser satisfying the primary
sidered when assessing the suitability of any site.
functions, its design must also be capable of meeting
In order for a steam power station to operate an the following objectives:
efficient closed cycle, the condensing plant, CW sys-
tem, and associated pumps must extract the maximum To provide the turbine with the most economic
quantity of heat from the exhaust steam of the LP back pressure consistent with the seasonal variations
turbines. in CW temperature or the heat sink temperature
The primary functions of the condensing plant are: of the CW system.
To provide the lowest economic heat rejection To effectively prevent chemical contamination of
temperature for the steam cycle. the condensate either from CW leakage or from
To convert the exhaust steam to water for reuse inadequate steam space gas removal and condensate
in the feed cycle. de-aeration.

To collect the useful residual heat from the drains The aim of the designs is to ensure that these objec-
of the turbine feedheating plant, and other aux- tives are met within the framework of the following
iliaries. practical considerations:

The aim of the CW system is to maintain a supply Economies of size, space and pumping power.
of cooling medium to extract the necessary heat, in
order that the condensing plant can meet its objec- Ease of maintenance and construction.
tives. It achieves this by the use of effective screen-
ing equipment, circulating water pumps, valves, and
(where necessary) cooling towers.
The economics, design, construction and functional 2 Economics
requirements of the above systems and associated The detailed design of the condenser and its asso-
plant components are discussed in detail in the sec- ciated CW system requires careful optimisation of
tions which follow. parameters which include material selection, cooling
Since many pumps of different types and duties water flowrate, condenser surface areas, and turbine
feature in the above systems, aspects of their design exhaust pressure, etc., in order to harmonise the
are collectively considered in later sections of this performance inter-relationships between all the dif-
chapter. These include condensate extraction pumps, ferent plant components, and to produce a design
cooling water pumps, circulating water pumps and offering maximum efficiency and reliability, and mini-
feed pumps. mum running and maintenance costs.

324
Economies

COOLING
TOWER m ATMOSPHERIC
AIR FLOW

e
! ! ! ! (a) Evaporative cooling
PUMP

'////////A

DRY COOLING
TOWER

(c) Indirect air cooling

PUMP

(d) Direct cooling

FIG. 4.1 Typical atmospheric heat dissipation systems

325
Condensers, pumps and cooling water plant Chapter 4

(a) Heated water discharge system

POND WATER
RETURN TO
CW INLET
FOREBAY

(b) Evaporative cooled system

KEY

1. FOREBAY AND GATE AREA 13. INLET END WATERBOX


2. COOLING WATER (CW) SCREENS 14. OUTLET END WATERBOX
3. DRAFT TUBE 15. TUBEPLATE ASSEMBLY
4. CW PUMP 16. WATERBOX ACCESS DOOR
5. CW PUMP DISCHARGE VALVES 17. TUBE SUPPORT PLATES
6. CW CULVERTS 18. TUBES
7. CONDENSER INLET ISOLATING VALVE 19. CONDENSATE OUTLET
8. CONDENSER SHELL 20. EXPANSION BELLOWS
9. CONDENSER OUTLET ISOLATING VALVE 21. AIR EXTRACTION BAFFLE
10 SURGE CHAMBER 22. AIR EXTRACTION
11. SEAL WEIR 23. AIR COOLING SECTION
12 COOLING TOWER 24. ACCESS LANE

FIG. 4.2 Terminology for major plant components

326
Economies

Particular attention must be paid to direct-cooled Cooling water flowrate.


systems, where condenser cooling water is taken from
Number and size of condenser tubes hence tube
the sea or from an estuary, since there are large varia-
length and flow velocity in the tubes.
tions in the quality of the water from site to site, which
may adversely affect the choice of certain materials Basement height.
for example. On the other hand, cooling tower sta-
tions operate in a controllable closed-system, where the Seal pit weir height.
quality of the cooling water is more uniform from site Culvert flow velocity hence culvert size.
to site.
River and lake cooled stations (of which there is Culvert length usually fixed by external con-
only one large example in Britain) take an interme- siderations, e.g., avoiding recirculation between
diate position as far as water quality is concerned. inlet and outlet.
Having identified these technical inconsistencies,
the basis of an optimisation study is to achieve a From the culvert velocity and length, and other para-
balance between capital costs and operating costs, meters, the CW pumping requirements can be deter-
giving the lowest overall lifetime cost. mined. A typical assessment procedure is illustrated
in Fig 4.3.

2.1.1 Input data


2.1 Condenser surface area, turbine exhaust
Referring to Fig 4.3, headings 1 to 6 represent the
pressure and CW flow
different items of input data which should be as
In developing proposals for a new power station, representative as possible. Listed under each heading
it is necessary to optimise the design of the various are the different parameters which collectively con-
component parts, and of the total system. stitute the item of input data. Relevant information
Traditionally, all the main component parts of the or estimates should be available on parameters such
system are assessed separately, each being optimised as station load factor and seasonal variations in sea-
according to its own set of design rules, using 'fixed' water temperature, and values must be decided for
interface parameters based on a combination of pre- parameters such as auxiliary power consumption, and
vious experience and engineering judgement. However, the capital costs of different plant items. Finally,
some of these 'sub-optimisations' are in fact inter- pump characteristics and system resistances are re-
dependent, for example, variations in the civil costs quired, from which pumping costs can be input.
of the CW system may have a significant effect on
the true optimum size of condenser. The problem is
best approached by applying an iterative process, each 2.1.2 Computation
sub-optimisation being repeated with revised values The problems to be solved can be classified into three
until the system design is fixed. This is very time basic types:
consuming by hand calculation, but one which lends
itself ideally to calculation by computer. The first type of calculation is based on a single
A computer program has been developed to assess set of parameters to determine the predicted per-
the most economic condenser surface configuration, formance of the system. This can be used to com-
pare the overall costs of a small number of discrete
turbine exhaust pressure, and CW flow for any given
options.
site. It creates a mathematical model of the system,
taking into account the cost and performance inter- The second type of calculation is a true optimisation.
relationships between the different plant components, The single calculation described above is repeated
simultaneously. It can evaluate both direct-cooled many times for a grid of values defining possible
systems and closed systems (cooling towers), and per- CW flows and configurations of condensing surface
forms the repetitive calculations necessary to ultimate- (i.e., number and length of tubes). The program
ly arrive at the lowest lifetime costs by balancing the identifies the lowest overall (capital and operating)
capital costs and operating costs of each individual cost at each stage and, after a number of iterations,
item of plant. homes in on the optimum within the applied con-
The paragraphs which follow, highlight the specific straints. This type of calculation is important for
aims and objectives of a typical computer optimisation determining the most appropriate CW flow and
study for a seawater-cooled station, and describe the condenser size for a new site. Figure 4.4 shows
assessment procedure involved in achieving a realistic typical graphical presentation of the results.
analysis.
The main parameters to be optimised are: The third type of calculation is the sensitivity study.
This involves repeating the optimisation process
Condenser surface area hence the vacuum, assum- for a range of values of one particular parameters,
ing that an efficient tube layout is adopted. such as power cost, to examine how this affects

327
Condensers, pumps and cooling water plant Chapter 4

^ DESIGN CW INLET TEMPERATURE T] COST DERIVATION |

COOLING TOWER PERFORMANCE POWER - /kW


CW INLET TEMPERATURE HEATRATE - /kW
WEIGHTED MEAN CW INLET TEMP INTEREST CHARGES
LOAD FACTOR

V w

3| CW SYSTEM CIVIL AND PLANT COSTS

CULVERTS
FOREBAY
SCREENS
VALVES
PUMPS
COOLING TOWERS - /m3/s

1 CONDENSER COSTS

SURFACE AREA-/m2

5| PUMPING COSTS

CW SYSTEM RESISTANCE
STATIC HEAD
CONDENSER FRICTION
PUMP CHARACTERISTICS - /kW

1 TURBINE HEAT RATE COSTS

VACUUM CORRECTION CURVE - /kW

|f

COMPUTATION

_ . ,_
)

J ENGINEERING JUDGEMENT AND


PRACTICAL CONSTRAINTS

CONDENSING PLANT DESIGN


CW SYSTEM
COOLING TOWER

\r

\r r

RT~ STATION LAYOUT 10| ENQUIRY SPECIFICATION ]

AVAILABLE CW FLOW
CW SYSTEM - STATION DESIGN DESIGN CW INLET TEMP
CONDENSER CW VELOCITY

FIG. 4.3 Turbine exhaust pressure assessment procedure

328
Historical development and layout

EQUAL COST
CURVES

CONDENSER
SURFACE AREA

COOLING WATER FLOW RATE

FIG. 4.4 Typical graphical presentation of optimisation study

the optimum design (i.e., optimum CW flow, con- about 3 m head of water under normal conditions,
densing surface, etc.). It is also possible to carry and pressures higher than normal may be necessary
out a sensitivity study to show the effect of simul- if other studies indicate that water hammer may prevail
taneous variations of two independent variables. under unstable conditions such as pump tripping, or
This type of calculation is particularly useful where valve closure.
one or two parameters are not known precisely, Sometimes special external limitations exist; for
or for carrying out broad-range generic studies. example, the temperature of cooling water discharge
Referring again to Fig 4.3, the final stage of may be of particular concern in rivers with important
assessment is covered under the heading 'Engineer- fishing interests, especially of migratory species such
ing Judgement and Practical Constraints'. It is as salmon.
important at this stage in the study to identify the On completion of a successful study, data is avail-
limitations of various parameters, before recom- able which can be used in the assessment of a par-
mendations can be made for condensing plant ticular station layout, and also as the basis for Enquiry
design, CW system design, and cooling tower design. Specifications.
For example, with aluminium brass tubes it is not
considered advisable for the cooling water velocity
to exceed approximately 2.5 m/s or to be less than
1.5 m/s in order to avoid undue tube fouling under
unfavourable conditions. Another limitation is the 3 Historical development and layout
lowest value of absolute CW system pressure which Since the mid-1940s the turbine manufacturing and
can be permitted at any point in the hydraulic cir- electricity supply industries have benefited from a
cuit. It is usual to avoid pressures of less than continuing policy of standardisation, which has re-

329
Condensers, pumps and cooling water plant Chapter 4

suited in consistent concepts of condensing plant ments were made in several other aspects. A general
layout. feature of these condensers was that they were all of
The costs incurred in extensive design work, and single-shell design; otherwise they differed considerably.
the development of special manufacturing techniques, The most obvious differences relate to the basic tube
have been spread over a large number of units which arrangement. Figure 4.5 (a) illustrates a transverse
have progressively benefited from minimised commis- arrangement, and Fig 4.5 (b) an axial arrangement.
sioning problems, and increases in service reliability Each of these has advantages, as will be seen from
and maintainability. During this period the size of later sections. When considering thermal performance
generating plant has also progressively increased from the transverse design is simpler and easier to predict.
120 MW to units of 660 MW. A difficulty with the axial condenser is that the long
Standardisation of approximately fifty machines tubes naturally result in a rather large difference in
was achieved in two stages; first at a unit size of 120 thermal performance between inlet and outlet ends,
MW, and later at a unit size of 500 MW. The latest so making the effective extraction of non-condensables
machines of 660 MW size represent an evolutionary more difficult.
development: at present, there are some 23 machines The axial arrangement, however, has a capital cost
at this rating either in service or under construction advantage because of the smaller number of (longer)
in the CEGB. tubes involved. This results in a saving in the cost
Certain features associated with 660 MW turbines of manufacture of the expensive tube plates. It also
have had a major influence on the development of allows a simple turbine-generator foundation arrange-
condenser design and layout. In order to appreciate ment in which the LP turbines are supported by
the significance of these features, a slight digression parallel foundation walls, one along each side. The
to highlight the development of their design is worth- process of tubing the condenser can use the space
while. under the electrical generator, which is kept free of
Single shaft turbines running at speeds of 3000 major plant items for this purpose.
r/min have become increasingly complex, as set rat- Again, due to the length of tubing involved with
ings have increased by increasing the steam mass an axial design, it becomes necessary to take mea-
flow. Increasing the steam mass flow has demanded sures to avoid large scale axial migration of steam
a need for multiple LP exhausts with last row turbine towards the cold end, which may involve adopting
blades approximately 914 mm long, and an exhaust opposed cooling water flow. This can be done by
area of approximately 6.7 m2. having two separate water passes with the flows in
While the turbine manufacturers (each of which opposite direction, as illustrated in Fig 4.6. Such an
has developed its own blading design) have made arrangement can complicate the culvert layout, cooling
improvements to details such as aerodynamic per- water pipework and valve layout, and result in ad-
formance, erosion shield vibration characteristics and ditional costs. Designing the condenser as a series
root fixings, the main dimensions have remained largely of compartments to give a multi-vacuum design has
unchanged until recently when the development of new generally been found to provide a more satisfactory solu-
exhaust blading has increased the operating capability tion and is now standard British practice for axial
to very much higher specific steam loadings. condensers.
Economic considerations have also favoured substan-
tially increased turbine exhaust specific loadings. This
is reflected in the 660 MW machines at Littlebrook D,
where a four LP turbine exhaust design (of approximate- 3.2 Phase 2
ly 7.8 m2 annulus area per exhaust) has been adopted. This phase covers the remaining 500 MW units and
Structural relationships between turbine and condenser, all except the most recent 660 MW units. Compared
and the method of overall support, have also developed with Phase 1, it is characterised by a radically dif-
as unit ratings have increased. ferent design: the axially-tubed side-mounted conden-
Three main phases of design exist within a period of ser. The development of the side-mounted condenser
development which covers early 120 MW plant right coincided with a general move towards the use of
through to the present 660 MW plant design. Justifica- steel foundations.
tion for these various changes are now discussed. In some arrangements, this becomes a Cannier'
design as shown in Fig 4.5 (c), in which condenser
and turbine are separated and connected to each
other by short ducts (either rigid or with flexible
3.1 Phase 1 bellows, depending upon the details of the turbine
In this phase, which covers about half the total num- and condenser support arrangements). In other cases,
ber of 500 MW turbines, the underslung condenser the condenser and turbine are combined to form an
arrangement used on previous 120 MW and 200 MW 'integral' condenser design (Fig 4.5 (d)) in which the
units was retained. The reinforced concrete turbine- condenser shell encloses both the condenser tubes and
generator foundation block was kept, but develop- the low pressure turbines.
330
Historical development and layout

//////

(a) Axially underslung

(b) Transverse underslung

/////7?

(c) Axially integral (d) Axially pannier

FIG. 4.5 Condenser configurations for recent British 500 and 600 MW units

331
Condensers, pumps and cooling water plant Chapter 4

CW PUMPS CW PUMPS

TURBINE
HOUSE
>; TURBINE
HOUSE .

INLET

>

H
IT
-o :
-O
BOILER HOUSE
BOILER HOUSE

TRANSVERSE TURBINE LAYOUT LONGITUDINAL TURBINE LAYOUT

SINGLE PASS UNIDIRECTIONAL FLOW

e
- CW PUMPS

TURBINE
HOUSE
TURBINE HOUSE
.
-
INLET


Q' Z
-O -O
BOILER HOUSE
BOILER HOUSE

TRANSVERSE TURBINE LAYOUT LONGITUDINAL TURBINE LAYOUT

SINGLE PASS2-DIRECTIONAL FLOW

FIG. 4.6 The effect of undirectional and two-directional condenser cooling water flow on system layout

The side-mounted and integral design styles have chine and condenser can be reduced quite significantly
several advantages. Compared with the equivalent (typically the condenser tubes are about 20 m long).
underslung condenser, the steam flow path between The turbine centreline height above basement, and hence
the turbine exhaust and the condenser inlet is wider, the crane height and overall turbine house height, can
and the losses smaller. Because of the reduction in also be reduced by, typically, 4 m. However, these
exhaust casing length, the overall length of the ma- advantages are partly offset by other factors. Their

332
Environmental considerations

relative importance depends upon the detailed layout aries of major rivers. Currently, over 40% of operational
adopted, but two of these factors are the increased stations are placed in such locations and are therefore
width of the turbine hall, and the question of acces- subjected to a wide variety of cooling water conditions.
sibility to the LP turbine for maintenance. A typical water analysis can contain abrasive sand
particles and marine life. Debris and cyclic tidal var-
iations affect tube velocity and promote two-phase
flow under syphonic conditions: this is particularly
3.3 Phase 3 damaging to condenser tubes and CW system ma-
As already mentioned, economic considerations have terials. It is against this background of operating
recently led to a preference for increased turbine ex- experience that a broad knowledge of materials has
haust specific loadings and, hence, relatively smaller been accumulated.
condensers. This allows a relaxation in the structural Fortunately, the position is less severe with the
inter-relationship between condenser and turbine. Other operation of inland power stations, where cooling
factors have also promoted a move away from the water quality is generally satisfactory. There are, how-
side-mounted condenser towards an arrangement in ever, instances of condenser tube corrosion due to
which each low pressure turbine is combined with its products of biological decomposition and operation
own transversely-tubed under slung condenser. This in polluted waters.
has the advantage that it allows the development of It is important to secure information concerning
a modular LP turbine/condenser design so that one, CW quality as early on in the planning stage of a
two or three modules can be combined to cover a power station as possible, since it forms the basis
large range of possible ratings, for example, 200 MW upon which material selection will be made later. A
with one module, and 600 MW or more with three survey of other industries using the same water sup-
modules. This modular concept has a strong attraction ply, along with the local water authorities, is of
for turbine manufacturers, particularly where they tremendous value in identifying the history of CW
are competing in world markets. One or two highly quality. Meanwhile, systematic monitoring and dis-
developed basic designs can then meet all practical cussions with local authorities yield information on
requirements. the current situation, and on possible future develop-
In these few remarks, it is clear that the choice of ments which may influence water quality.
condenser for future large turbine-generator plant Lack of attention to this type of detail often leads
appears to favour the transversely-tubed underslung con- to the wrong choice of materials. In condenser tubes,
denser: this seems unlikely to be reversed in the for example, tube perforations and condensate con-
foreseeable future. tamination levels exceeding the boiler water chemical
requirements [1] can have serious economic conse-
quences. If leakage of CW into the condensate per-
sists, costs can be incurred from tube replacement,
4 Environmental considerations loss of availability and consequential damage to other
In addition to the physical size and arrangement of sections of the plant, such as boiler tube failure from
the condenser relative to the turbine, another very feed water chloride contamination.
important consideration which has a direct bearing These problems can be avoided and the associated
on the condenser design adopted is the effect of the costs minimised by combining the detailed knowledge
environment. accumulated on CW quality with that associated with
Of major concern here is the cooling water quality, the known corrosion performance of condenser tube
and also the choice of suitable constructional ma- materials, which forms the basis of material selection
terials to prevent premature corrosion and erosion of strategy discussed later.
plant components, due to dissolved and suspended
solids, respectively.
4.1.1 Corrosion prevention
Copper alloys form the basis of traditional condenser
tube and tubeplate materials, typical chemical composi-
4.1 Cooling water quality tions of which are given in Tables 4.1 and 4.2.
The cooling water quality can have a marked effect Copper-based condenser tube alloys rely for their
on the design and shape of the waterside components, corrosion resistance on the passivating action of a
such as waterboxes, which can influence both the cor- protective film of corrosion product which forms when
rosive and erosive effects of the cooling water. These the tubes enter service. Under conditions of turbulence
aspects are discussed in more detail in the subsections and excessive water velocity, this protective film can be
which follow. corroded/eroded from the tube surface, exposing the
The demand for substantial quantities of cooling bare unprotected surface and thus promoting further
water leads to an increasing tendency for large power attack. Such unfavourable conditions can occur in
stations to be located on the coast and on the estu- condensers operating with high water velocities or

333
334
TABLE 4.1
Condenser tube materials typical chemical compositions

/o /o /o <7o % % % 7o % /o
Alloy
Copper Tin Arsenic Zinc Aluminium Nickel Iron Manganese Chromium Titanium

70/30 brass 70 0.04 Rem


Admiralty brass 70 1 0.04 Rem
Aluminium brass 68 0.04 Rem 2
70/30 cupronickel 70 30
Modified cupronickel 66 30 2 2
Modified cupronickel 64 30 3 3
Cupronickel IN8 38 Rem 18 0.8 0.5 0.4
Cupronickel IN8 48 Rem 30 0.7 0.4
Titanium 100
Condensers, pumps and cooling water plant

(Rem = remainder)

TABLE 4.2
Condenser tubeplate materials typical chemical compositions

Alloy % <7o % Total


Copper Tin Zinc Manganese Lead Iron Aluminium impurities

BS2875-CZ112 61.0-63.5 1.0-1.4 Rem 0.75


Naval brass

Aluminium bronze 88-92.5 0.2 max. 1.0 max. 0.01 max. 1.5-3.5 6.0-8.0
ASTM-B171
Alloy D

Aluminium bronze Rem 0.2 max. 0.3 max. 1.5 max. 2.0-4.0 9.0-11.0
ASTM-B171
Alloy E

(Rem = remainder)
Chapter 4
Environmental considerations

under siphonic conditions which lead to air release (e) Waterborne debris.
and greatly increased local water velocities due to
turbulence. For each material, there is a threshold (f) Mussel fouling.
water velocity above which attack of this type will (a) General impingement attack Impingement attack
occur. For example, the breakdown velocities for the is characterised by an overall surface roughening
protective film on aluminium brass and 70/30 cupro- and horseshoe-shaped undercut pits, the extent of
nickel are 2.5 m/s and 4 m/s respectively, compared which depends upon the extent of local turbulence
with design water velocities of the order of 1.5 m/s. (Fig 4.7). The attack is aggravated by water con-
The most common tube failure event is corrosion/ taining a high suspended-solid burden, as is the
erosion from impingement attack, which develops case with condensers operating in estuarine con-
from a number of causes. These are dealt with under ditions where high tidal rates are experienced. The
the following headings: resistance to impingement attack of conventional
copper materials is illustrated in Fig 4.8. They all
(a) General impingement attack.
exhibit a threshold water velocity value, and are
(b) Tube inlet attack. liable to suffer from attack under conditions of
high water velocity.
(c) Lodged debris.
(b) Inlet end impingement attack Inlet end attack is
(d) Iron oxide scale. a localised form of impingement attack associated

FIG. 4.7 Condenser tube impingement attack

335
Condensers, pumps and cooling water plant Chapter 4

90/10 COPPER
NICKEL IRON

INCREASING PROBABILITY
OF PREMATURE FAILURE IN
SEAWATER IMPINGEMENT
ATTACK

NORMAL WATER VELOCITY m/s

FIG. 4.8 Probability of impingement attack in seawater

with high inlet water velocities and air release. If impingement attack cannot be controlled by pre-
The attack has the same characteristics as general ventive maintenance, consideration can be given to
impingement attack and is aggravated by a high the use of secondary screening in the form of reduced
suspended-solid burden. It has been suggested throat inserts (Fig 4.9). These are nylon inserts with
that annealing of tube ends may lower the resis- an internal profile resembling a venturi. When fitted,
tance of the material to impingement attack. the insert initially absorbs water and effectively locks
itself into the tube.
(c) Impingement attack at lodged debris General debris
There is a 0.24 mm feather edge on the upstream
causes partial blockage of the condenser tubes
edge of the insert which fits closely to the tube wall
and gives rise to high local water velocities of the
to prevent significant disturbance to the water flow.
order of 6 m/s. This exceeds the threshold value
Tests confirm that erosion problems from debris lodged
for conventional copper alloys and causes severe
in these inserts are contained and cause no damage to
highly localised impingement attack.
the tubes.
Tube failures caused by general debris can be
minimised by concentrating attention on removing
the source of the problem.
4.1.2 Other copper-alloy tube failure mechanisms
(d) Iron oxide scale This is produced from the cor- Other types of copper-alloy tube failures can occur
rosion of carbon steel waterbox and CW pipe- and these are briefly reviewed under each of the fol-
work components and is prevented by applying lowing headings:
cathodic protection or by protective coatings (see
Section 6.2.3 of this chapter). The oxide scale (a) Deposit attack.
which forms as easily dislodged 'plate-like' sheets,
becomes lodged in the tubes and causes failures (b) Hot spot corrosion.
due to highly localised impingement attack. (c) Stress corrosion cracking.
(e) General waterborne debris This is produced from (d) Corrosion fatigue.
ineffective screening plant allowing shells, wood
and marine debris to pass, in addition to debris (e) Steamside ammonia corrosion.
from the culverts in the form of concrete spoil.
(f) Mussel fouling This is caused by ineffective (a) Deposit attack Deposit attack on condenser tubes
use of low level CW chlorination or bio-fouling occurs under conditions of stagnant or low water
equipment. velocities, generally less than 1 m/s. Deposition

336
Environmental considerations

FlG. 4.9 Condenser tube reduced throat inserts and tube plugs

337
Condensers, pumps and cooling water plant Chapter 4

of inert materials, such as sand and silt particles, conditions (Fig 4.10).
causes oxygen depletion at the particle-to-tube ma- (b) Hot spot corrosion This form of localised pitting
terial interface, leading to differential aeration and corrosion occurs at 'hot spots' on the condenser
anodic dissolution of the tube material. The pre- tube wall which can occur because of low water
sence of decomposing biological materials and pol- velocity and/or high heat fluxes. These conditions
luted water, particularly sulphide-containing water, can be caused by poor steam distribution or the
accelerates this type of attack. Deposit attack can absence of water on the cooling water side of the
be experienced in both inland and coastal power tube. The cupro-nickel alloys are less resistant than
stations, particularly in locations where polluted aluminium brass to this type of attack. However,
waters are used. this form of attack is rarely experienced in main
By maintaining the cooling water velocity in steam condensers as the steam side temperatures
the tube above 1 m/s and avoiding stagnant con- are not high enough (Fig 4.11 (a)).
ditions in aggressive media by flushing and peri- Problems can be experienced in the dump steam
odically refilling the condenser with town water sections of the condenser or in separate dump
during shut down, major deposit attack may be steam condensers with high superheat, where direct
prevented. However, a permanent solution can be steam impingement on the tubes occurs. Retubing
achieved only by the selection of a more resistant in titanium tubing can provide a satisfactory solu-
material. Such materials are the 70/30 and 90/10 tion or, alternatively, an engineering solution to
cupro-nickels (of which the 90/10 is claimed to avoid direct steam impingement such as redirection
have the better resistance) and titanium. Titanium of steam flow can be found; the introduction of
offers the best solution, as it is immune to this effective steam desuperheating is also considered
type of attack under normal condenser operating to be a satisfactory option.

PITTING POSSIBLE IN CONTACT PITTING PITTING


WITH TEFLON ETC IN POSSIBLE PROBABLE
VERY SHARP CREVICES

CONCENTRATION
OF % NaCI

FIG. 4.10 Pitting resistance of titanium

338
Environmental considerations

(a) Local high temperatures on the outside of tubes


can lead to abnormally rapid corrosion at corresponding
positions on the inside (cooling water side) of the tubes.
Hot spot corrosion takes the form of a highly localised
pitting attack, a characteristic feature being that the pits
often contain metallic copper. The illustration shows a
section through a pit filled with metallic copper produced
by a hot spot attack in a copper/30% nickel alloy tube.

(b) Stress corrosion cracking can arise from the imposition


of longitudinal stresses when certain tubes are rolled into
the tubeplates. It is also important to avoid over-rolling the
tubes to prevent excessive expansion and the consequent
failure by cracking.

(c) Failure of tubes by cracking can occur as a result of


the combined action stress and corrosion. In corrosion
fatigue, the stresses are cyclic or alternating and are
applied in-service, for example, as a result of cyclic
temperature changes or externally-transmitted vibration.

FIG. 4.11 Photomicrographs of hot spot corrosion, stress corrosion cracking and corrosion fatigue cracking in tubes

339
Condensers, pumps and cooling water plant Chapter 4

(c) Stress corrosion cracking Failure of condenser Heat transfer efficiency and thermal performance
tubes by cracking under the combined action of effects.
tensile stress and corrosion has occurred in the
past owing to high residual tensile stresses inad- Compatibility with other CW system materials.
vertently remaining from the tube making process.
However, with modern condenser tube production Experience has indicated that studies of this type
practice, such failures are now uncommon (Fig yield materials which initially appear to be an expen-
4.11 (b)). sive choice, but because of their inherently better
Cracking can result from stress corrosion at corrosion-resistant properties show a higher economic
the tube-to-tubeplate expansion joints. The cracks return when plant availability and retubing costs are
initiate at the edges of the expanded regions on taken into consideration.
the CW side of the tube and propagate into the
tube wall under the influence of residual stresses
remaining from the 'rolling-in' operation. The cor- Copper-based materials
rosive medium is suggested to be ammonia, formed As previously illustrated in Fig 4.9, the copper-based
from the decomposition of organic slime, and con- tube materials are liable to varying degrees of im-
centrated by evaporation during outages. Effective pingement attack, depending upon the operating con-
media control such as washing with clean water ditions. These materials, however, can be usefully
before prolonged outages or fitting protective sleeves, employed providing that a good margin of safety
appears to provide a solution to this problem. is maintained between operating conditions and the
impingement attack threshold, and providing that
(d) Corrosion fatigue Corrosion fatigue can occur steamside corrosion conditions are satisfied. Where
in any tube material and is caused by steam buf- freedom from erosion or steamside corrosion cannot
feting, or structure-borne vibrations, in association be assured, it is necessary to use a material such as
with inadequate tube support. Generally, failure titanium.
occurs at midspan where tube thinning occurs due
to excessive movement and contact with adjacent
Titanium
tubes (Fig 4.11 (c)). Additional support plates or
the fitting of antivibration damping equipment Over the past twenty years, work has progressed in
solves this problem. the development of titanium for use as a condenser
tube material. Its major attribute is a tenacious oxide
(e) Steamside ammonia corrosion Ammonia corrosion film, which rapidly repassivates if ruptured under nor-
usually attacks brass alloy air cooler tubes in the mal condenser operating conditions. Jet impingement
form of pits on the external tube surface, with tests on both welded and seamless titanium tubing at
grooving at points adjacent to tubeplates and sup- water velocities of 10 m/s for 60 days have shown
port plates [2]. Titanium and the copper-nickel the material to be immune to attack. Under these
alloy tubes are highly resistant to this form of conditions, aluminium-brass and cupro-nickel tubing
attack and the problem can be solved by retubing failed rapidly. Titanium tubing manufacturers (Imperial
in an appropriate material. Metal Industries Ltd. [3]) quote impingement attack
threshold values of 20 m/s in clear seawater and 6
m/s in water with a high sand content. Thus, even at
4.1.3 Material selection localised tube blockages where water velocities can
The need for a materials selection strategy has been rise to 6 m/s, the tubing retains its resistance to
touched upon briefly in the consideration of CW qua- impingement attack, whereas this velocity would be
lity. The objectives of such a strategy are to ensure beyond the reliable range of the copper-based materials
that the costs associated with leaking condenser tubes (Fig 4.8).
are minimised throughout the life of the plant. This The use of titanium tubing in condensers designed
can be established by studying the following technical for conventional copper-based tubing materials, how-
and economic considerations: ever, poses a problem of incompatibility between tube/
tubeplate materials.
The estimated life of candidate tube materials from Couples of titanium and naval brass, and titanium and
test rig trials, manufacturer's literature, experience, iron/steel have junction potentials of - 2 8 8 mV and
etc. - 660 mV respectively, in relation to a saturated calo-
mel electrode (SCE) [4]. This creates the potential pro-
The predicted number of outages and associated
blem of anodic attack of the tubeplate material which
costs.
could lead to penetration of the tubeplate within the
The number of retubes required. design life of 30 years. Where naval brass tubeplates
have to be used, such as in retubing situations, the
The capital costs of materials and retubing costs. practice has been to coat the tubeplate and waterbox

340
Thermal design

internals with a multilayer neoprene rubber, thus the temperature difference between the turbine ex-
effectively insulating against galvanic action. haust steam and the cooling water is as low as pos-
For new construction, tubeplates manufactured sible if the benefits of the Rankine cycle are to be
from aluminium bronzes ASTM-B171 Alloy D, and realised, providing that the mechanics used are con-
ASTM-B171 Alloy E, have couple potentials with ti- sistent with previously discussed economics of plant
tanium tubes of -215 mV (SCE) and -133 mV (SCE), optimisation.
respectively. The corrosion rates of aluminium bronze
tubeplates are therefore low enough to allow their use
without any protective coating. The waterboxes, how-
ever, are still protected with suitable coatings as in a
retubing situation.
5.1 Theory
In-service trials have been carried out at a number The condenser is the heat sink for steam power plant.
of power stations, listed in Table 4.3, under various The condensation process is accomplished by the
operating conditions ranging from the particularly transfer of heat from the steam exhausting from the
aggressive sand-laden waters of Bristol Channel power turbine to the water used for cooling. Steam is con-
stations to the polluted environment experienced by densed at substantially constant pressure and its heat
Thameside power stations. content (enthalpy), which is given up, raises the tem-
perature of the cooling water as it flows through the
Following the satisfactory performance of the ti-
tubes (Fig 4.12). Referring to Fig 4.13, which illus-
tanium tubes in these trials, two condensers were
trates a basic heat flow diagram, there are three factors
retubed with titanium; one with seamless tubing and
which determine the enthalpy of the steam at the
one with seam-welded tubing. Results from these
turbine exhaust:
trials confirmed that the tube installation procedures
and subsequent service has been satisfactory.
The conditions and heat content of the steam leaving
Fifteen years ago, titanium was considered extremely
the boiler.
expensive and unlikely to become economic.
The cost constraint on the use of titanium tubing The efficiency of the turbine in converting this heat
can be minimised by a reduction in the required energy into work.
tube wall thickness. This, coupled with savings ex-
pected from leak-free operation, establishes the use The selected heat sink temperature.
of titanium as an economic material for power sta-
tions where aggressive attack is either experienced or
predicted. 5.1.1 Heat rejected
As a result of the favourable in-service trials and Equating the total heat per kilogram of steam leav-
increasing economic competitiveness, titanium tubing ing the boiler h, with subsequent heat losses h r , h b ,
is now used in all new power stations where impinge- h g , and the heat equivalent of turbine-generator work
ment attack of the condenser is considered possible. output h w , then the heat at the turbine exhaust he
On-site rig tests, which are carried out at new power can be represented by the equation:
station sites prior to the ordering of titanium, confirm
that in all cases the corrosion resistance is good, and
that no operating problems are envisaged. he = h - (hw + hr + h b + hg) kJ/kg

The heat flow rate rejected to the cooling water ,


is found from the equation:
5 Thermal design
The preceding sections outline the functional require- = qm (he - hc) kJ/s or kW
ments of condensing and CW systems, and illustrate
how environmental studies into cooling water quality where qm = CW flowrate, kg/s
are taken into consideration when choosing the geo-
graphical location of a new power station, and how
these aspects, in turn, affect the economics of plant Added to this is any heat rejected by drains from
optimisation. feedheaters, etc., which may be discharged within the
Emphasis has been placed on the importance of condenser.
correct selection of materials in order to avoid un-
acceptably high availability and maintenance costs.
Consideration has also been given to the choice of 5.1.2 Heat transfer
turbine and condensing plant arrangements. The heat is transferred to the cooling water across
The objective of thermal design is to ensure that the condenser tubes (Fig 4.14).
341
342
TABLE 4.3
Titanium tube trials
Condensers, pumps and cooling water plant

Location River Usk Blackwater River Thames SE Coasst River Medway River Usk River Thames

CW system Siphonic Siphonic Siphonic Siphonic Siphonic Siphonic Siphonic


No. of tubes 4.0 18.0 6.0 12.0 10.0 10.0 10.0
OD, mm 22.0 25.4 25.4 25.4 25.4 25.4 25.4
Thickness (mm) 1.2 0.7 0.7 0.7 0.7 0.9 0.7/0.9
Type of tube Seamless Seamless Seamless Seamless Seamless Seam-welded Seamless
Date installed 1956 1968 1965 1968 1967 1962 1966
Date inspected 1967 1972 1971 1970 1964 1970
Condition As new As new As new As new As new As new
Chapter 4
Thermal design

EXHAUST STEAM

TO AIR PUMPS

AIR POCKETS FORMED WHERE


OPPOSING STEAM FLOWS MEET

FIG. 4.12 Typical steam flow pattern in a condenser

In any heating or cooling process, the resistance to the outlet.


heat transfer determines the relative temperature of Wet steam enters the condenser and condenses
the heated and cooled fluids. completely at a constant temperature tsK, as it passes
The total resistance of the tube to heat transfer is over the condenser tubes. These processes are re-
determined by the sum of: presented in Fig 4.16.
Consider an element of tube length d where the
cooling water is at t w and the condensing fluid is at
Rs = the resistance of the condensate film on the t s . The temperature difference is (ts - t w ) = , and
steamside of the condenser tube, m2 K/W a small amount of heat, , is transferred across
the element. From Newton's Law of cooling,
Rm = the tube metal resistance, m2 K/W
= UA (ts - t w ) (4.1)
Rv the waterside film resistance, m K/W

and therefore
The total resistance to heat transfer RT of the tube
is therefore given by:
= (TTD df)Ue (4.2)

RT = R< + Rm + Rw m2 K/W
where D = mean diameter of tube.

The overall heat transfer coefficient U, is inversely


The coolant increases in temperature d6w along element
proportional to R j therefore:
dl, and the heat received is

U = 1/RT W/m 2 K
d$ = q m w c w d6w (4.3)

Logarithmic mean temperature difference (LMTD)


where q mw mass flow rate of coolant, kg/s
Consider Fig 4.15 which represents a condenser. The
cw specific heat of coolant, kJ/kgK
cooling water enters the condenser tubes at tempera-
ture t wl K, and its temperature is raised to t w2 K at de w temperature increase of coolant, K

343
Condensers, pumps and cooling water plant Chapter 4

hr

r|Wh
HEAT IN

\i TURBINE

^ ^ ^

\L/
WORK
OUT

~t 2
- CW OUT

CONDENSER X J _ HEAT
REJECTED
- ^ CWIN

CONDENSATE
EXTRACTION PUMP

h - TOTAL HEAT OF STEAM LEAVING THE BOILER


h r - THE RADIATION HEAT LOSS
h b - THE BEARING HEAT LOSS AND MECHANICAL LOSSES
h a - THE GENERATOR GAS AND LIQUID COOLER HEAT LOSSES
ho - HEAT AT TURBINE EXHAUST
h c - TOTAL HEAT OF THE CONDENSATE
h w - HEAT EQUIVALENT OF TURBINE GENERATOR WORK OUTPUT

FIG. 4.13 Basic heat flow diagram

Let the incremental increase in fluid A temperature Substituting this in Equation (4.2),
dt w = dO, then substituting into Equation (4.3),
d0/(l/q m w c w ) = (irDdOUe
d0 = d<i>/qmwcv (4.4)
therefore d0/0 = TTDU ( l / q m w c w ) d i (4.6)

Integrating Equation (4.4) between sections 1 and 2


(Fig 4.16), Integrating Equation (4.6) between sections 1 and 2,

2 - = <>(l/qmwcw) (4.5)
logn 1/2 = *DOJ (l/q m w c w ) (4.7)

Also from Equation (4.4), (where i is the total length of the tube)

d<i> = d0/(l/q m w c w ) From Equation (4.5),


344
Thermal design

K = (tW2 - t w l )/[log n (t s - t w l )/(t s - t w2 )] (4.9)


TOTAL RESISTANCE RT

Qm is known as the logarithmic mean temperature


difference (LMTD).

Finally, the total surface area of the tubes can be


expressed by

A = / (4.10)

where A = total mean surface area of the tubes, m2


= rate of flow of heat, kW
CONDENSATE FILM
U = overall heat transfer coefficient, W/m 2 K
0 m = LMTD, K

5.2 Design codes, standards and


FOULING/WATERSIDE
specifications
FILM
Documents exist which are based on the design theory
outlined above. They are generally used as a guide in
establishing condenser size and design. The validity
of these documents is sufficient to ensure that con-
denser selections will meet specified performance. They
include:

The Heat Exchanger Institute (HEI) Standards for


Steam Surface Condensers [5].

FIG. 4.14 Heat transfer resistances and films The British Electrical and Allied Manufacturers
Association (BEAMA) publication on the Recom-
mended Practice for the Design of Surface Type
Steam Condensing Plant [6].
1/qmwCw = ( - 2)/

These documents provide a comprehensive treatment


Hence substituting into Equation (4.7), of surface condenser performance and describe levels
of performance which can be obtained from well de-
signed condensers.
log n / 2 = - 2 )/ The objectives of thermal design procedures will
be reviewed in relation to the relevant codes and
standards.
Therefore = TTDRJ (, - 2 )/( 1 / 2 ) (4.8)

5.2.1 HEI Standards


Comparing Equation (4.8) with Equation (4.1), = These standards [5] use four basic equations in sizing
UA (ts - t w ), it can be seen that the mean temperature condensers:
difference, 0 m , is given by
Mean temperature difference The logarithmic mean
temperature difference is expressed as follows:
K = ( - e^/iog^/e^
t7-t,
(4.11)
Since dx = (t s - t w l ) and 2 = (t s - t w 2 ) lognfts-tO/its-t) l0gn(e,/e2)

345
Condensers, pumps and cooling water plant Chapter 4

WET
STEAM

^L

^L_

=>

^1

=>

=>

CONDENSATE
OUT

FIG. 4.15 Water cooled surface type condenser

WET STEAM t s STEAM/CONDENSATE t s CONDENSATE

i 1 i1
F
()

LU
ce !
w2
Z>
I- tw
<
OC
LU
CL

d*
f

*W1

4/
COOL NG
WATEER

^
CONDENSER TUBE LENGTH

FIG. 4.16 Graph of steam/water temperature variation against tube length

346
Thermal design

Coefficient of heat transfer The coefficient of heat 5 Cooling water outlet temperature.
transfer recommended by HEI is expressed by the
heat transfer resistance summation equation:
6 Cooling water velocity through tubes.

U = Fj F 2 F 3 C (V)i (4.12) 7 Effective heat transfer surface, which is a func-


tion of:
where C = correction factor for tube diameter, Number of tubes.
numeric
Tube length.
V = tube water velocity, m/s
Tube diameter.
Tube thickness.
The Fourier Equation The Fourier equation for
unidirectional heat transfer is used to express the Tube material.
rate of heat flow in terms of heat transfer surface Number of cooling water passes.
area, coefficient of heat transfer and mean tem-
perature difference and is written as follows:
8 Service conditions:
Tube cleanliness.
qmsL = AU6m (4.13)
Air inleakage.

where qms = mass flow rate of condensed steam,


kg/s 5.2.2 BEAMA design recommendations
L = specific latent heat, kJ/kg The thermal design procedures set down in the BEAMA
design recommendations [6] are very similar to those
followed by the HEI, except differences occur in the
Heat Balance Equation This equation is usually statements regarding tube cleanliness, and the correction
written as: factor for cooling water temperature as applied to the
overall heat transfer coefficient (Fig 4.17).
The curves for the BEAMA heat transfer coefficients
qmsL = qmwC6r (4.14) are based on tubes in the brushed-clean condition and
include an allowance for the normal oxide film coat-
ings which are an inherent feature of any tube during
where qmw = mass flow rate of cooling water, kg/s its operational life, whereas the HEI curves relate to
c = specific heat of cooling water kJ/kgK tubes in the clean, as-new condition. In addition, the
BEAMA curves for cooling water temperature cor-
rection are based on a mean temperature, and not on
tube inlet temperature as in the HEI curves.
By suitable manipulation of these equations, a con-
Taken collectively, these departures have very little
denser design can be established for a given performance
effect on any design, providing due recognition of
rating, based on eight principal variables, which are:
these differences is made.

1 Total heat transferred, which is a function of:


5.2.3 CEGB specifications
Weight of steam to be considered. Specifications for plant include a requirement for the
Enthalpy of steam less enthalpy of condensate. contractor to guarantee the thermal performance of
the condenser. The contractor is expected to guarantee
Enthalpy loss or gain of drains and make-up. an absolute pressure at the turbine exhaust under the
conditions of design steam flow, minimum cooling water
quantity at the design cooling water inlet temperature
2 Absolute static steam pressure. and with the tubes in the brushed-clean condition.
The temperature of condensate leaving the condenser
3 Cooling water flow rate. and the air suction temperature, with the design air
loading, are also guaranteed.
As a way of comparing how the design standards
4 Cooling water inlet temperature. produced by the HEI and BEAMA reflect the level of
347
Condensers, pumps and cooling water plant Chapter 4

y y^

y
^ TRANSFER
^ AT21C-HEI

y
HEAT TRANSFER
COEFFICIENT kW/m2K 3.0

y
^ ^ ^ ^ H E A T TRANSFER
^ r AT 21 C - BEAMA

20

1.0 1.5 2.0


TUBE VELOCITY m/s

1.0

MEAN COOLING WATER ^


TEMP-BEAMA ^ ^ S
^ y
0.9 */-
/ I N L E T COOLING WATER
> TEMP-HEI

DESIGN CORRECTION JL
FACTOR /
/
/
-/-
/

40 C

FIG. 4.17 Graphs indicating differences in assumptions made by HEI [5] and BEAMA [6] design documents

348
Thermal design

performance which can be obtained from well designed condensers, further development work has resulted
condensers, Fig 4.18 shows the test results of a number in a single individual formulae being established for
of condensers of over 4600 m 2 , as presented by Steel each design code which equates the total heat trans-
[7]. Superimposed on these data are the values for fer coefficient based on the data and formulae of
the heat transfer coefficients, as recommended by the each code as shown in Fig 4.18. These equations are:
HEI and BE AM A standards.
It can be seen that the Standard procedures closely
U = 2.15 (v'5)(0.7586 + 0.0135T-0.0001T 2 ) kW/m 2 K
represent the mean of test results obtained in practice.
Furthermore, it should be recognised that these test
results also incorporate the complexities of thermal and U = 2.70 (v05)(0.5707 + 0.0274T- 0.00036T2) kW/m 2 K
aerodynamic processes present in large condensers, and
cover the diverse arrangement of tubenest geometry and for BEAMA [6] and HEI [5], respectively.
differences in operating conditions.
Recognising the proven use of the BEAMA [6] This not only simplifies the use of these design codes,
and HEI [5] design codes to obtain well designed but lends them ideal for use in computer analysis.

HEI RECOMMENDED
HEAT TRANSFER
4.0 COEFFICIENT-(F3= 0.95)

BEAMA RECOMMENDED
HEAT TRANSFER
COEFFICIENT - (BRUSHED
TUBES)

BEST FIT CURVE

o
OPERATING DATA
X S FROM EXISTING
< OPERATIONAL
CONDENSERS

CONDENSER HEAT
+
TRANSFER RATE - kW/m 2 K

X
o A A
o A

-
I
1.5 2.0

VELOCITY THROUGH TUBES - m/s

FIG. 4.18 Typical condenser test results of heat transfer coefficient plotted against water velocity in tubes

349
Condensers, pumps and cooling water plant Chapter 4

More recently, however, calculated values of heat been illustrated in Fig 4.19, i.e., the choice between
transfer coefficient, based on laboratory measurements side-mounted and under slung condenser dispositions,
of steam and waterside coefficients, indicate that con- which depends mainly on turbine design and turbine
denser performances better than those predicted by layout factors. Other factors which are also generally
present design codes, i.e., HEI [5] or BEAMA [6], fixed at an early stage, without special reference to
should be possible with careful attention to the tube- tubenest arrangement, include the condenser envelope
nest geometry. interaction with the turbine support structure, operat-
ing floor height above basement, overall turbine hall
dimensions, CW flow direction, number of passes,
and the condenser alignment (i.e., axial or transverse).
5.3 Influence of tubeplate and tubenest In addition, before the tubenest arrangement is
geometry on thermal performance developed in detail, the main performance character-
It has been shown that the HEI and BEAMA docu- istics of the condenser must be agreed, following
ments give recommendations for the design of water- optimisation studies as mentioned in Section 2 of
cooled surface type condensing plant, and describe the this chapter. The main parameters settled at this stage
levels of performance which can be achieved. However, are:
omissions on the separate treatment of tubeplate
geometry and tubenest ventilation arrangements make Design heat load.
it difficult to use this data when calculating new designs
Design CW inlet temperature.
which have tubenests and venting systems differing
from those for which the empirical dependence was Design CW flow.
obtained.
Two methods of design evaluation can be applied Design condenser pressure.
in the assessment of tubeplate geometries; there is Total surface area.
the general subjective treatment, which involves eval-
uating the total pressure within the steam space and Tube length.
tubenest, and there is more recently the rigorous
mathematical analysis using computer-aided numerical Tube outside diameters, wall thickness, and material.
solutions which solve the heat and mass transfer equa- Number of tubes.
tions for individual tubenests.
Each method is discussed in turn, the general prin- CW velocity in tubes.
ciples of tubenest arrangement are outlined, and their
practical application illustrated by reference to large
Apart from the performance parameters, the type of
condensers designed over the last 15 years.
tube/tubeplate fixing will have been decided, which
in turn determines the minimum pitch of the tubes
5.3.1 Subjective design evaluation (Section 6 of this chapter), and also design values for
the amount of air entering the condenser in the steam
The tubenest geometry and its disposition relative to
will have been established.
the turbine exhaust have a considerable effect on
the distribution of steam over individual groups of
tubes which, in turn, influences local heat transfer Preliminary considerations of tubenest arrangement
rates, and tubenest ventilation. More perhaps than
any other feature of large condensers, tubeplate and A number of decisions relevant to tubenest arrangement
tubenest arrangements may differ considerably between can be taken at this stage:
one design and another. This can be seen from the
many arrangements employed on the 500 MW series, Subdivision of the total number of tubes This is the
Fig 4.19. Each manufacturer of condensing plant ar- extent to which the total number of tubes may be
rives at his own solution independently. This high- subdivided into separate banks, each associated with
lights a point which emerges from experience, that its own tubeplates and water boxes, air extraction
tubenest arrangements which are apparently quite dif- points and cooling waterside isolation. It is common
ferent can be of equally good performance, providing nowadays to restrict the number of tubes supplied
that proper attention is paid to a number of general from any waterbox to around 5000, which has been
principles. found through experience to be a number which does
not inconvenience on-load leak searching or tube
External constraints cleaning.
In designing the tubenest arrangement, a number of
external influences and constraints have to be taken Subdivision of banks Consideration may also be
into account. The main external constraint has already given to subdividing the individual banks into two
350
Thermal design

EXHAUST STEAM

I I I I I I
-CONDENSER

SINGLE-PASS
TUBENEST

THREE-PASS
- AIR COOLING
SECTION

DIVISION PLATE

(a) Section through axial underslung tubenest

mm
EXHAUST STEAM

CONDENSATE TRAYS

SINGLE-PASS TUBENEST

EXHAUST
STEAM

(b) Section through transverse underslung tubenest (c) Section through sidemounted tubenest

FIG. 4.19 Typical tubenest configurations for 500 MW condensing plant

351
Condensers, pumps and cooling water plant Chapter 4

or more sub-banks, each with its own air extraction High pressure drop before tubenest, and ineffec-
point (Fig 4.19 (b)). tive use of the incident velocity of the approaching
steam.
Compartmentalisation of the condenser Steam from Air blanketing and stagnation in the tubenest.
each LP turbine can be condensed in two or three
separate compartments, which are baffled from each Inundation of tubes by condensate, and undercool-
other on the steamside and operate at different back ing of condensate.
pressures, the lowest being at the end corresponding
to the CW inlet. An alternative to this arrangement Three-dimensional effects.
is the 'opposed flow' concept whereby the CW flow
is in one direction in half the banks, and in the op-
posite direction in the remainder. This avoids the The main options open to the designer will now be
need for large-scale axial redistribution of steam within discussed briefly in relation to the various causes of
the condenser, towards the CW inlet end. poor performance listed above:

Detailed considerations of tubenest arrangement High pressure drop in the tubenest This is mainly
As a first stage in tubenest design, it is necessary to concerned with the pressure drop in the main con-
choose a basic concept. The two main features by densing section of the tubenest. Once the inconden-
which the various possible concepts can be most easily sable gases and residual steam have reached the air
characterised are the steam flow approach pattern cooling section, it might be assumed that the volu-
to the tubenest and the disposition of the air cooling metric flow is small, and that the pressure drop is
section: therefore no longer a significant problem. This how-
ever can be a dangerous assumption (Fig 4.19 (b)).

The steam flow approach pattern to the tubenest The


steam may enter the tubenest from just one direction, High pressure drop before the tubenest This aspect
i.e., from the turbine exhaust, or it may be allowed of large condenser design originally tended to receive
to pass around the nest and enter it from all sides. little attention, though its significance is now well
Figure 4.19 (c) clearly indicates that, for side-mounted recognised. If high velocity steam entering the con-
condensers, a unidirectional steam approach has al- denser is not travelling naturally in the direction in
ways been the natural choice, since the face area of which the designer would like it to go, the effective
the tubenest is fairly large. However, Fig 4.19 (b) pressure drop caused by forcing it to turn in a dif-
indicates how underslung condensers have a small face ferent direction may be substantial. Figure 4.20 shows
area to a unidirectional steam approach, and a more how one condenser designer has developed his tube-
common arrangement is for a substantial percentage nest layout to improve the use of the incident velocity
of the steam to be allowed to pass round one or both in the steam. This problem is more apparent in
sides of the nest, thereby increasing the face area over underslung condensers than side-mounted or integral
which the steam finally enters. condensers. Conversely, due to irregularities in the
velocity profile of the approaching steam, the pressure
drop through the condensing section of the tubenest
The disposition of the air cooling section In most should not be too low. A moderate pressure drop
condensers the air cooling section is a block of tubes helps to redistribute the steam flow beneficially and
located between the main condensing section and the prevent high velocity jets of steam penetrating straight
air extraction point (or points), representing some through into the air cooling section.
10% of the total number of tubes (Fig 4.19 (a)). In
other condensers, however, the air cooling section is
arranged adjacent to the CW inlet tubeplate, and con- Air blanketing and stagnation in the tubenest Since
sists not of separate tubes, but of the cold ends of all air is a poor conductor of heat, it is essential to
the tubes. The steam must travel axially along the con- ventilate the tubenest adequately if a thermal per-
denser to reach the air cooling section, and this type of formance, close to theoretical, is going to be achieved.
condenser requires design in three dimensions. Some air blanketing in the air cooling section is ac-
ceptable, but good ventilation will ensure that blanket-
ing is minimised within the main condensing section.
Causes of poor condenser performance Briefly, the main function of the air cooling section,
There are a number of possible reasons for poor con- apart from cooling the vapour/air mixture passing to
denser performance, the main parameters being: the air extraction equipment, is to ensure that the
condensing section is properly ventilated. Therefore,
High pressure drop in the tubenest. the total pressure drop between the turbine exhaust
352
Thermal design

EXHAUST STEAM

f T T t T T T T

\^ry
(a) Axial underslung condenser for 500MW unit

EXHAUST STEAM

AIR SUCTION

(b) Transverse underslung condenser for 660MW unit (one of two condensers)

FIG. 4.20 Comparison of tubenest designs to improve use of the incident velocity of the steam

353
Condensers, pumps and cooling water plant Chapter 4

and the condenser air extraction point can be envi-


saged as being divided into two parts; one across
the main condensing section, the other across the air
cooling section. This concept is complicated by three- EXHAUST STEAM

dimensional effects which are discussed later, but are


the basis of two important general principles (see
Fig 4.21):
1 I I 1 II
The resistance to steam flow along all actual flow
paths between the turbine exhaust and the entry
to the air cooling section should be equal. High
resistance paths tend to cause stagnation, resulting
in the poor thermal performance of associated
tubes.

There should be no major routes whereby steam can


reach the air cooling section directly, without first
passing through the main condensing section. If
this occurs, it may become impossible to maintain
a satisfactory pressure difference across the con-
densing section and it will tend to stagnate as a
whole. Also the air cooling section will become
overloaded with steam, and will itself manifest a
high pressure drop.
(a) Before modification

Inundation of tubes This is a problem which is


directly related to the number of tubes in the tube-
TUBES REMOVED TO FORM
nest. Reduce the number of tubes in each bank NEW AIR SUCTION PASSAGES
TUBES REMOVED TO FORM (ORIGINAL SUCTION PASSAGES
(particularly in the vertical plane) and inundation NEW STEAM LANE BLANKED OFF)

is reduced.
An alternative is to place collecting trays at key
positions within the tubenest which will catch the
condensate and divert it directly into the bottom of
the condenser (condenser hotwell) through a system
of gutters.
Condensate drainage can cause undercooling. Al-
though this is not generally a serious problem, it can
be avoided by allowing a small amount of steam to
enter below the tubenest to reheat the condensate
before it finally falls into the condenser hotwell.

1 I C

'Three-dimensional' effects These effects have a sig-


nificant detrimental effect on the performance of
large condensers. The problem arises from the fact
that, theoretically, the amount of steam which con-
denses at the cold end of the condenser is greater
than the amount which condenses at the hot end.
(b) After modification

However, in practice this frequently cannot exist, be-


cause it requires that the pressure drop through the
tubenest should be greater at the cold end than at
the hot end, and this is not possible if the air ex- FIG. 4.21 Alternative arrangements for steam-flow/air-
suction in underslung condensers
traction point pressures are the same at both the
cold end and the hot end.
Although this phenomenon is sometimes accepted
as a fundamental factor in condenser performance, Use of a low CW temperature rise, and avoidance
various measures can be taken to minimise its effect: of close approach between CW outlet temperature
354
Mechanical design

and vacuum temperature. This means the difference configuration, and cooling water flow, together with the
between the theoretical cold and hot end perform- CW inlet temperature.
ances is not large, and the three-dimensional ef- For a more detailed understanding of the com-
fect is therefore inherently small. puter techniques currently being researched, the reader
should refer to a paper presented at the International
Use of compartmented condensers. As already Symposium on Condensers: Theory and Practice [8].
briefly mentioned, this is a variation where the
condenser is divided up into two or three com-
partments, one corresponding to each double-flow
LP turbine, the total CW temperature rise is, 6 Mechanical design
therefore, divided into a number of separate steps.
The various compartments operate at different
vacua, and to achieve balance in the air extraction
rates, it is usual to connect the air pumps directly 6.1 Introduction
to the cold end compartment, and then allow the Present day power station steam turbines require very
other compartments to vent into the air suction large condensers: the basic problems are those asso-
line via restriction orifices. ciated with translating conceptual ideas into func-
tional mechanical designs. As already discussed in
Use of three-dimensional design Figure 4.22 shows previous sections, the disposition of condensers has
an example of the use of three-dimensional air largely been influenced by the generic development
cooling sections. of turbines. This has made it impractical to specify
In addition, 'disc' baffles can be installed in the a unique set of design rules which will completely
central axial passage. Steam which is flowing axial- cover the diversity in constructional designs. How-
ly from the hot end of the condenser is forced ever, there are many features common to all designs,
back into the tubebank, thereby increasing the
and these will be discussed in detail with reference,
resistance of the steam flow path from the hot end,
where applicable, to relevant design codes, standards
and helping to achieve correct balance of pressure
and specifications.
drops.
Section 10 of this chapter, looks at the position
and functional requirements of the air cooling sec-
tion in more detail, and describes its influence on
6.2 Constructional development
the design of the air extraction equipment.
The main areas of mechanical design are discussed
under three main headings, these are:
5.3.2 Computer assisted design evaluation
The second and more recent design evaluation meth- Construction materials.
od uses computer techniques to assess the perform-
ance of steam condensers. The computer program Design forces and stresses.
simulates the fluid flow, heat transfer and air con-
centration processes locally through the condenser. Methods of manufacture and construction.
Since the interaction of these processes is very com-
plex, the program begins by representing the con- 6.2.1 Construction materials
denser as a series of parallel slices perpendicular to The construction materials may be conveniently di-
the CW flow. Each slice is divided into a number of vided into those used in contact with the steam, and
control volumes so as to represent both the tubenest those used in contact with the cooling water. Gen-
and the steam access lanes. The program first finds erally, plate materials, hollows and bars comply with
the steam flow pattern, and calculates the local con- BS4360: 1972 [9] and BS1501: 1964 [10].
densation rates starting at the CW inlet. The laws Details of materials for components, such as con-
of conservation of mass, momentum and energy are denser tubes and tubeplates which are in contact with
applied to each control volume to produce a large the cooling water, are thoroughly discussed in Section
number of simultaneous equations for each slice. 4 of this chapter. In addition, an interface clearly
The program also calculates whether air pockets exist exists between selection of tube material and struc-
in the tubenest, and identifies where they will form. tural design. It is important, therefore, to select these
The sizes of the air pockets are determined by the materials early in the design stage in order that tube
pressure at the air vent points the higher the vent support arrangements and the effects on structural
pressure, the larger the air pockets. From the solu- stiffness may be finalised.
tion the condenser vacuum can be predicted for given On conventional power stations, condensing plant
rates of steam flow, air leakage, condenser surface components which are in contact with steam are nor-
355
Condensers, pumps and cooling water plant Chapter 4

EXHAUST STEAM


pipi AIR SUCTION ZONE

as ^ E

CW INLET
CW OUTLET

EXHAUST STEAM

I I I 1
AIR EXTRACTION DUCTS

(NOTE ALL ROUND STEAM ACCESS TO THE TUBE BANK, AND THE
SIMILARITY OF THIS ARRANGEMENT WITH THE MODIFIED
CONDENSER SHOWN IN FIG. 4.21b)

FIG. 4.22 Transverse underslung condenser for 660 MW unit showing three-dimensional air cooling sections

356
Mechanical design

mally constructed from either ferrous or non-ferrous sideration. These include forces resulting from various
materials. Recent specifications for a Pressurised Water connections, such as CW connections to the water-
Reactor (PWR) power station have indicated that boxes, and operational loads of the condenser struc-
non-ferrous metals should not be used, since the ture which must be considered when designing the
build-up of deposits from corrosion/erosion effects LP turbine mountings and support foundations. These
associated with non-ferrous materials, could be passed latter loads are of particular importance in the design
through the feedheating plant, and jeopardise the of integral and side-mounted condensers, where struc-
inverted tube bundle of the steam generator. The tural stability is necessary to secure turbine alignment.
steam generator, unlike conventional boilers, has much Design stresses for the structures are given in BS1501:
greater restrictions on the frequency of blowdown 1964 [10]. In practice, however, these stress levels are
operations. rarely realised, since the plate thicknesses are usually
optimised well within the limits of stress to satisfy
minimum deflection criteria, and to comply with the
6.2.2 Design forces and stresses economics of manufacture.
The main forces acting on condensers are shown in
Fig 4.23 for various condenser configurations.
6.2.3 Methods of manufacture and construction
The methods used in the manufacture and assembly
A = anchor point of large condensers are outlined, and the factors
influencing the extent of manufacture carried out at
works and site are discussed.
Fv = force due to vacuum loading, N Traditionally, condensers for British turbines of
120 MW rating and above have always been shop
Fw = force due to cooling water static loading, N manufactured as a multitude of components which
are transported to site for final assembly and tubing.
Ft = reaction force on turbine exhaust flange, N As already highlighted in Section 3 of this chapter,
however, economic considerations have recently led to
a preferred arrangement in which each LP turbine is
Fc = Sc = reaction force on condenser foundation
combined with its own transversely-tubed underslung
steelwork, N
condenser. This has allowed the development of a
modular condenser design so that one, two or three
Frw = reaction force due to static and dynamic modules can be combined to cover a large range of
loadings from flowing cooling water, N possible turbine ratings. This modular concept has
a high attraction for turbine manufacturers, parti-
Ftc = Stc = reaction force on turbine/condenser cularly where they are competing in world markets.
foundation steelwork, N Now, before dispatch from the works, the condenser
shell sections, tubeplates, support plates, baffles and
waterboxes are temporarily assembled and carefully
Fs = reaction force due to springs, N
aligned so that final welding of the shell sections can
proceed rapidly and efficiently in the power station
Fws = force on waterbox support, N prior to tubing.
There are a number of advantages to be gained
mc = mass of condenser, N from maximum fabrication and assembly of condensers
at the manufacturer's works:
mt = mass of LP turbine, N It enables fabrication and erection to be carried
out in favourable environmental conditions, with
mtc = combined mass of LP turbine/condenser ready access to specialised machinery, welding, fitting,
inspection and test facilities.
mw = mass of waterboxes
It provides a location where there is a high density
of skilled labour and supervision in the various
disciplines.
As can be seen from Fig 4.23, the largest single force
which ultimately affects the design of the condenser Conflicting requirements between contractors for
shell is that which results from the vacuum, Fv. In space, access, cranage, etc., do not exist. These can
addition to the forces illustrated in Fig 4.23, there lead to reduced productivity which is detrimental to
are external loads which are also taken into con- the overall station construction programme.
357
Condensers, pumps and cooling water plant Chapter 4

Ft

4- J
Fs
(a) Axial underslung configuration
ui, Fs
Ft
Y

Fws Fws * W -
f Fw

me
mm me mc

i mw I
mc
^ Fws Fws
mc mc mc

T / ) /1 T T fnr^|/TJ77|/TfT7|l F
Fs Fs Fs Fs

(b) Transverse underslung configuration

-I i "*
Ftc

o
Ftc Ftc

f T

mc,
lp 11
VTSJ
(c) Integral configuration

__? IfLlfLlfl l,(


tH?tI14(

Fv
t t t t t t t
Fs Fs Fs Fs Fs Fs Fs

(d) Side-mounted configuration

FlG. 4.23 Major forces acting on condenser shells

358
Mechanical design

Manufacturers have not only lifted workshop limita- (Fig 4.25) turns the top half of the condenser into a
tions, which once restricted a modular method of stiff bridge structure incorporating the LP cylinders
manufacture, but have also overcome problems con- and bearings, the turbine weight being carried by the
cerning transport to site. Figure 4.24 shows an ex- bridge to the foundation piers at either end. The con-
ample where the modular concept of condenser de- denser is supported upon coil springs, and to avoid the
sign has been successfully employed at Heysham 2 weight of the condenser or its contents being trans-
power station. mitted to the turbine exhaust casing, the waterboxes
Methods used in the manufacture and assembly of and tubes are filled with water and the springs ad-
the individual major components which form a com- justed to their normal operating position by levelling
pleted transverse underslung condenser will now be bolts before welding the main exhaust joint.
outlined under the headings listed earlier. The tubenest is arranged so that the tubes are
transverse to the turbine axis. The operational weight
of the integral bridge structure exceeds 2200 tonnes.
The shell is stiffened against the vacuum load using
General structural design plates and ribs which are optimised for strength and
The transverse underslung (bridge) condenser design economics of fabrication.

FIG. 4.24 Heysham 2 condenser modular construction


(see also colour photograph between pp 482 and 483)

359
360
TRANSVERSE
BEARING BEAM
CANTILEVER
KEY STRUCTURE
MAIN LONGITUDINAL BEAM BEAM BEARING BEAM
(GLAND STEAM SIDE) SUPPORT PADS MAIN LONGITUDINAL BEAM
(BEARING OIL SIDE)
Condensers, pumps and cooling water plant

WATER BOX
DRAIN

AIR AND CONDENSATE FLASH BOX


BAFFLES PLATE
CONDENSER FLASH BOX , - 1_ , /
TUBES WEIR PLATE FLASH BOX
WATER BOX DOUBLE TUBE PLATE WtlHMLAlb H E A D ER
INSPECTION ASSEMBLY
WATER BOX
MANHOLE DRAIN

(a)

FIG. 4.25 Transverse underslung (bridge) condensers, showing main constructional features of single
and two-pass configurations
Chapter 4
EXPANSION BELLOWS BLED STEAM OUTLET
CONNECTION TO No. 3 L P HEATER
TO L P CYLINDER

NECK SIDE PLATE BLED STEAM OUTLET


SUPPORT STRUTS TO No. 2 L P HEATER

NECK END PLATE BLED STEAM OUTLET


SUPPORT STRUTS TO No. 1 L P HEATER

STEAM SPACE INSPECTION DOOR


VENT FROM IP. DRAINS
VESSEL

AIR EXTRACTION PIPES

OUTLET WATER BOX


CONDENSER

MAIN C.W. OUTLET PIPE

L P TURBINE SUPPORT COLUMNS

SAFETY GRID

VENT FROM HP. DRAINS VESSEL


EXPANSION JOINT

SAGGING PLATES (15 PAIRS) DOUBLE TUBEPLATE


ASSEMBLY
CONDUCTIVITY PROBE
C.W. CONNECTING PIPE

DEAERATING PLATE BUTTERFLY TYPE ISOLATING VALVE

WEIR PLATE MAIN C.W. INLET PIPE


AIR SUCTION SUPPORTING ISOLATING VALVE
OUTLET DUCTING STEELWORK MOTORISED ACTUATOR

(b)

FIG. 4.25 {cont'd) Transverse underslung (bridge) condensers, showing main constructional features of single

361
Mechanical design

and two-pass configurations


Condensers, pumps and cooling water plant Chapter 4

Waterboxes facture of condensers, but also on knowledge derived


Depending on the number of passes, transverse from model tests and from tests on other large con-
underslung condensers may have inlet, outlet and re- densers in Britain, and overseas.
turn waterboxes. In every case the waterbox dimensions Clean conditions are established within the conden-
are sufficient to allow easy access for inspection via ser shell prior to commencement of tubing. Tubing
bolted and hinged manhole covers. The major design is usually started at the bottom rows, working pro-
objectives to be realised in their construction, in ad- gressively upwards. When the bottom rows are com-
dition to access, are those of pressure and vacuum plete, it is possible to remove personnel as these rows
loading, and support. then act as supporting guides when inserting subsequent
The static and dynamic forces generated by the rows of tubes. Guide bullets in the leading end of the
flowing cooling water are taken by the waterbox struc- tube greatly assist the tubing operation.
ture (Fig. 4.23), which is shaped to promote a smooth
flow of water through the tubeplate and tubes, and Tubeplates
prevent erosion at the inlet. Flange rotation is pre-
The provision for double tubeplates has been mandatory
vented by selecting plate sizes of adequate stiffness
for UK power station contracts over the past years to
or, alternatively, the plates are stiffened by external
eliminate any possibility of cooling water entering the
reinforcement, usually in the form of ribs.
steam space of the condenser. Each tubeplate inter-
The waterbox flanges are jig or template drilled to space is drained to a low level drain vessel which is
ensure matching with the tubeplate and shell flange. maintained at the condenser absolute pressure by
Earlier waterboxes were generally protected against means of a connection to the air pump suction line. This
corrosion in service by cathodic protection, with pro- equalisation of pressure on either side of the inner
tection bosses provided to receive anodes. It is now tubeplate ensures that no leakage occurs across it.
normal practice to offer protection against iron oxide Therefore, any leakage into the interspace will be
scale by means of a rubberised coat, applied to grit- cooling water, which is drained to waste. The tubeplate
blasted surfaces prior to dispatch to site. interspace can be hydraulically tested to a pressure
of 0.7 bar during maintenance overhaul via 25 mm
Condenser shell water connections on the tubeplate periphery. A vent
is fitted at the top of the tubeplate interspace to
The condenser shell forms the boundary of the steam
ensure that it is full of water.
envelope. The structure comprises a floor, two side-
walls, and end plates with provision for expansion The formulae and rules governing the sizing of
and location of tubeplates. The build-up of a con- tubeplates have been based on the following standards
denser shell varies between manufacturers. British and codes which have been progressively amended in
experience has shown, however, that the various line with tubeplate developments:
manufacturing practices produce end products which BS1500 [11].
are comparable in quality, cost and construction time.
The sections making up the condenser shell are BS1515 Parts 1 and 2 [12].
invariably built up from steel plates welded together,
the only exception to this being the tubeplate attach- TEMA Standards: Tubular Exchanger Manufacturers
ment, which is arranged for bolting or studding to Association Standards, Fourth Edition 1959, Fifth
shell and flanges. The shell is sometimes stiffened for Edition 1968 [13].
vacuum and structural loading by separate stiffening
ASME VIII Standards: American Society of Me-
members, but more generally the necessary support
chanical Engineers Boiler and Pressure Vessel
is provided by welding the intermediate tube support
Code Section 8, Divisions 1 and 2 [14].
plates direct to the shell. After welding, all shell
envelope and major structural welds are crack-detected,
using magnetic particle non-destructive testing or an The wider use of computer techniques in the design
equivalent check. of tubeplates is presently being researched. An ex-
ample which has been used is a beam element program
which is based on the theory of beams on elastic
Tubenests foundations, and analyses the effects of pressure and
The design and layout of tubenests is extensively edge loading from the waterboxes.
covered in Section 5 of this chapter, which empha- The methods of manufacturing of the tubeplates
sises how the disposition of the tubes within the shell vary. The steel (inner) tubeplate is often drilled first
is the heart of any condenser design. The present and used as the jig for drilling the non-ferrous (outer)
tubenest arrangement consists of an upper and lower tubeplate. Sometimes, however, inner and outer tube-
tubenest, each taking the form of a 'folded band* plates are drilled together, even where they are of
of tubes (Fig 4.20 (b)). This design draws not only dissimilar materials, to ensure accurate tube-hole
on the experience gained during many years of manu- matching between the two tubeplates. The reason for

362
Mechanical design

using dissimilar materials is purely one of economy; porting structure for the plate. Leak-tight sliding
however, as already mentioned, it is a requirement joints are used to compensate for expansion. Various
that non-ferrous materials are not to be used for the methods may be used in combination to provide
inner tubeplate of a PWR design. Bolt hole drilling of characteristics consistent with the design requirements
the tubeplate is carried out either by a jig or template and specific service conditions. Details of configura-
to ensure matching with the waterbox and shell flange tions commonly used on large condensers are shown
holes. on Fig 4.27. Figure 4.27 (a) shows a typical double
The joint between the inner steel tubeplate and tubeplate arrangement, using a combination of the
the condenser shell is crucial and requires particular fixed and sliding joint, the inner and outer tubeplates
care as it cannot be easily renewed once tubing is being of the same material. This design was extensively
complete. Figure 4.26 shows a typical detail of a used on the 500 MW condensing plant.
bellows and flange joint. This joint is sealed with a Figure 4.27 (b) shows another typical double tube-
neoprene-proofed fibre cloth and cord-filled dumb-bell plate arrangement, using rolled fixings at each joint;
gasket which is manufactured in one piece. The bolt the tubeplates are of dissimilar metals, hence the need
holes in the tubeplate are jointed up with a water test for the wide interspace gap to accommodate bending
groove, and a drilling from the hydraulic connection movements and to reduce shear stress in the tubes.
on the tubeplate periphery breaks into this groove, This is the method proposed for the PWR design.
enabling the joint to be hydraulically tested prior to Figure 4.27 (c) shows a double tubeplate arrange-
tubing. Access for tubeplate inspection may be gained ment of similar design to Fig 4.27 (b), but here the
from the waterbox, which is fitted after all tube fixings tubeplates are of similar materials and the need for
are complete. After complete erection, when all tube the wide interspace gap is eased.
ends have been expanded and packed, the space be- Figure 4.27 (d) shows a typical double tubeplate ar-
tween the tubeplates is filled with a fluorescent solution rangement, using a combination of fixed and sliding
under pressure, and the tubeplates examined from both joints, with dissimilar metals for the inner and outer
sides under ultraviolet light to prove the absence of plates, as used on the more recent Heysham 2 and
leakage. Torness power station designs.
Each of the above arrangements has been employed
successfully. Typical tube sizes are 25.4 mm OD and
Tube/tubeplate joints 1.2 mm wall thickness; tubeplate materials are mild
The method selected for securing tubes to the tube- steel and rolled naval brass, Muntz metal or aluminum
plates provides leak-tightness and strength as a sup- bronze for the outer plates (see Table 4.2). Titanium

SINGLE CONVOLUTION
EXPANSION BELLOWS

JOINTS

m\\\ w
r
SHELL SHELL
k WATER BOX
3
MILD STEEL ALUMINIUM
(INNER) TUBEPLATE- - BRONZE (OUTER)
TUBEPLATE

FIG. 4.26 Details of bellows and flange joints

363
Condensers, pumps and cooling water plant Chapter 4

EXPANDED PACKED GLANDS

-^" -<**
INLET - OUTLET

(a) Double tubeplate assembly using single tubeplate technology

BRASS OUTER BRASS OUTER

INLET OUTLET

(b) Double tubeplate assembly using plates of dissimilar metals

EXPANDED EXPANDED

INLET OUTLET

(c) Double tubeplate assembly using tubeplates of similar metals

MILD STEEL MILD STEEL

v
BRASS OUTER INNER INNER BRASS OUTER

PACKED GLANDS
r~H PACKED GLANDS

OUTLET

(d) Double tubeplate assembly using a combination of fixing types and metals

FIG. 4.27 Tube-to-tubeplate fixing arrangements for large condensers

364
Mechanical design

tubes of 25.4 mm OD and 0.7 mm wall thickness


have been fixed successfully into a similar configura-
tion to that shown in Fig 4.27 (d).
Properly made joints provide the necessary integrity
to meet the design criteria for remaining leak-free in TURBINE
service; however, the uniformity of holding strength
will vary between the methods used and it is diffi-
cult to see how this can be readily compensated in
the design of the tubeplates unless some other form of
fixing which possesses inherent uniformity, such as
welding, can be adopted.
Tube expansion is carried out at the inlet end inner
tubeplate first, using electrically-controlled roller ex-
panders. Particular care is taken in setting up the
expanders to ensure that over-expansion beyond the CONDENSER

edge of the tubeplate does not occur. On completion


of the inner tubeplate, the inlet end outer tubeplate -CONDENSER
is then packed, or expanded and belled as appro- NECK

priate. The procedure for the outlet end is similar,


except that the tubes are not belled. Manufacturers
adopt different expanding patterns for the outlet end
based on individual experience; however, a predeter- FIG. 4.28 Turbine to condenser joint (for underslung
mined sequence is always adopted in order to minimise condensers)
tubeplate distortion at the outlet end.

Shell/tube expansion purposes. They support the tubes in order to control


The shell and tube material thermal expansion co- vibration, and provide means for bowing the tubes
efficients can be markedly different, except where to assist drainage. Also, they provide a convenient
titanium tubes are used. Collectively, under normal method of reinforcing the shell against the external
operating conditions, the cumulative effects aie suf- pressure forces.
ficiently large to generate theoretical stresses high The spacing of support plates is controlled by the
enough to cause failure of the tube joint. The differ- criteria governing tube vibration, but usually the maxi-
ential movement between shell and tubes on a large mum dimension does not exceed 60 tube diameters.
single-pass condenser can be as high as 22 mm. A With the introduction of titanium tubing, the spacing
tube-to-tubeplate fixing arrangement similar to Fig 4.27 can be as low as 35 tube diameters which satisfies
(d), but using only packed gland joints, along with the criteria of freedom from fundamental frequency
tube bowing, was examined as a possible solution to vibration from both machine and steam-flow-induced
this tube movement problem, but has been abandoned sources.
due to inherent unreliability. The practical solution Where support plates are used as inherent stiffness
has been to rely on the use of expansion bellows members for shell reinforcement, the plate strength
between the shell and tubeplate carrier at one end, usually and attachments receive consideration as edge-loaded
of the single convolution type (Fig 4.26). perforated diaphragms and are stiffened to avoid
buckling, if required. The plate thicknesses can vary
from 16 mm to 38 mm, depending on the design cri-
Condenser/turbine joint teria. The tube hole drilling is carried out by multi-
A transverse underslung condenser is attached to the spindle numerically-controlled drilling machines, and
turbine by welding. it is common practice to 'stack drill' up to seven
A typical closing weld is shown in Fig 4.28; this is support plates at a time.
a single-sided butt weld, welded from the inside, with
an external backing strip. After completion, the weld is
usually magnetically crack-detected for soundness. Branches, connections and reinforcement
Side-mounted condensers are bolted to the turbine Ordinarily, reinforcement may be dispensed with be-
exhaust flanges via flexible bellows joints. cause plate thicknesses are in excess of those that
require compensation. Details of any opening or branch
connection to the shell which requires compensation
Support plates and reinforcement must comply with the standards
Condenser tube support plates serve a number of set out in BS1500 [11].
365
Condensers, pumps and cooling water plant Chapter 4

Hydraulic tests from the filter ranges from 3 to 10% of the main
There are mandatory requirements for hydraulic tests CW flow, over a rinsing period of 5 to 10 minutes.
on the components of the condensing plant, and these
are summarised in Table 4.4. 6.3.2 Condenser tube cleaning system
Figure 4.29 shows how oversized rubber balls are
continuously pressed through the condenser tubes by
TABLE 4.4
the water flow. Screens located downstream of the
Condensing plant component tests
condenser waterboxes extract the balls from the main
Component Test pressure, bar
CW discharge flow. They are then drawn off and
pumped through a collector to be subsequently dis-
Waterboxes 4.1 (hydraulic) charged into the CW inlet to the condenser.
This system removes fouling and even hard deposits
Tubes 3.4 (pneumatic) from the internal surface of the tubes, which would
otherwise lower the heat transfer characteristics of
Pumps, pipework 1.5 times max. working the tubes, with a resulting loss in condenser efficiency.
and valves pressure

Condenser structures, NDT, dye penetrant


welds testing 6.4 Special considerations
In addition to the normal function of condensing
the steam which is discharged from the LP turbines,
condensers on nuclear power stations are designed to
6.3 Protection and cleanliness of condensers provide a heat sink for the removal of heat from the
During plant manufacture, storage, transport to site reactors. These condensers are fitted with steam and
and site erection, special precautions are taken to water dumping facilities of the pressure breakdown
ensure that all plant items remain clean and reasonably type. The condenser structures are suitably reinforced
protected. To achieve this, condenser internal surfaces to take the reaction forces and erosion effects of high
are usually grit-blasted at the works and a temporary velocity flows from the steam dump diffusers. Con-
protective coating applied, i.e., a type of coating which densing tube surfaces are protected by impingement
does not require to be removed prior to the unit enter- plates and desuperheating sprays. A more detailed
ing service. Tube holes are protected by a lacquer account of the steam and water dumping requirements
which is removed immediately prior to condenser on nuclear power stations is covered in Chapters 1 and
tubing. External ferrous surfaces are either grit-blasted 2 of this volume.
or wire-brushed and degreased, and a suitable primer
is applied to the cleaned surface.
In the post-erection period, until commissioning,
deterioration of internal surfaces is minimised by 7 Operational life limiting constraints
keeping the condenser surfaces dry. If the condenser The main constraints which limit the operational life
is used and has to be put into storage again before of a condenser are summarised under the following
commissioning, steps are taken to ensure that all water headings:
is removed from the condenser.
In order to operate a condenser at its optimum Condenser air inleakage.
level, on-load cleaning methods are used which ensure Cooling water inleakage.
the high availability of condensing plant (Fig 4.29).
Condenser fouling and cleaning.

6.3.1 Debris filter An awareness of these problems at the design stage can
Coastal power station condensers are more vulnerable significantly reduce lifetime running costs and
to the intake of debris such as mussels, fish, wood, plas- maintenance costs. Operational experience of the var-
tic and fibrous materials, than inland power station ious techniques employed for each of the three con-
condensers. One solution to prevent the blockage of straints listed are now discussed.
condenser tubes is the installation of a debris filter in
the CW inlet side of the condenser.
All particles in the cooling water larger than 10 mm
are kept in the filter and rinsed away through the 7.1 Condenser air inleakage
debris discharge. Throttling of the filter inlet isolating Techniques used for the location of leaks are outlined,
valve causes a change in flow direction near the screen, and methods for measuring the rate of air inleakage in
creating a rinsing effect. The discharge water quantity condensers are described.
366
Operational life limiting constraints

CONDENSER TUBES

SPONGE RUBBER
BALLS DISTRIBUTED
IN CIRCULATING WATER
; 4 . *
-tlft-t 1-

f t* t * t f 4 *^\ .
___Z_________________J V !
BALL
INJECTION
POINT
DEBRIS FILTER
SCREENS FOR
BALL RECOVERY

WPmm 1
. DEBRIS
OUT

cw X
3-
OUT '
CW
IN

BALL
COLLECTOR
BALL
RECIRCULATING
PUMP DRAIN

MAP'

FIG. 4.29 On-load condenser cleaning system

The reasons why it is desirable to minimise air 7.1.1 Locating air leaks
inleakage are: Air leakage can occur in any part of the condensing
system which operates near or below atmospheric
To improve condenser heat transfer performance. pressure, and is often caused by failure of joints, at
flanges, and also by weld and material failures. When
To reduce the capital cost of the air extraction the turbine is off-load, detection of air leakage is
equipment required. made in some parts of the system by flooding with
water. Water seepage from sections normally under
To reduce air extraction plant running costs.
vacuum indicate leakage areas.
When the turbine is on-load, however, different
Tests have indicated that with well ventilated con- techniques must be employed. These include: audible
denser tubenests, air inleakage within the capability methods (if the leak is large enough and the back-
of the air extraction plant installed (100-200 kg/h ground noise low); visible means, by observing the
for 500 MW units) does not adversely affect the action of a lighted taper when in the proximity of air
condenser heat transfer performance. The objectives flowing towards a leakage point; and the spraying of
for minimising air inleakage rates on new condensing suspect areas of plant with a tracer gas which is
plant are, therefore, aimed at reducing capital costs easily detected by careful monitoring of the air ex-
and running costs. traction equipment. The last method is the most
Operational levels of air inleakage, however, vary common technique employed today.
between different station designs. For example, stations The tracer gas detectors generally used in power
with underslung condensers and indirect feedheating stations are the RILO, AEI and LEYBOLD types.
plant have an advantage over stations with pannier These are known as halogen leak detectors as they
condensers and direct-contact feedheating plant. are capable of detecting low concentrations of halo-

367
Condensers, pumps and cooling water plant Chapter 4

genated compounds in an air stream. For minimum The final technique relies on temporary instrumenta-
toxicity and maximim sensitivity the halogenated com- tion to make direct measurements of air leakage on
pounds chlorofluorocarbon and dichlorofluoro- a periodic basis, or when a condenser performance
methane (trade names Freon 12, Isceon 12 or Arcton problem exists. The methods employed include the
12) are used. use of Pitot tubes, anemometers, hot wire anemo-
Of the leak detectors mentioned above, only the meters, rotameters and orifice plate assemblies.
LEYBOLD equipment has a detector probe which can Measurements are made both on the air suction
be immersed in the gas to be tested. This equipment pipe and at the air extraction plant discharge. Care is
is used by installing the probe in the air extraction needed at both locations. The assumption made when
pipe from the condenser, whereas the other detectors measuring in the condenser air suction pipe is that the
sample from the air extraction system discharge. water vapour present is saturated. When measuring at
Most leakage points are found at flanges and joints, the air extraction plant, if more than one pump is
and are usually small cracks or holes. These can nor- operating, the flow between the pumps is not always
mally be sealed with any of a number of proprietary evenly distributed.
metallic resin or rubber-based sealing compounds.

7.1.2 Measurement of air leakage rate 7.2 Cooling water leakage in condensers
Apart from the air extraction system (see Section 10 The methods employed in British power stations for
of this chapter), air leakage measuring equipment is the detection of leakage of cooling water into the
generally not installed as permanent instrumentation condenser, and of the consequent pollution of the
on British power stations. As in locating the air leaks, condensate are:
there are several techniques available to measure the
rate of air leakage. Condensate conductivity.
Operational techniques are used to determine whether Sodium contamination.
a reduction in condenser performance is due to con-
denser fouling, or air inleakage overloading the air
extraction equipment. The operations carried out, which Location of condenser leakage is influenced by the
only require measurement of condenser back pressure, following factors:
are:
CW supply, i.e., fresh, estuarine or seawater.
Isolation of the air extraction equipment from the
condenser on-load, and monitoring the subsequent Condenser design, i.e., underslung or pannier.
rate of vacuum decay.
Experience has shown that the techniques used to
Changing the number of vacuum pumps in service,
locate the region of leakage in fresh water condensers
and establishing the effect of this on the vacuum.
are not sufficiently sensitive to locate leakages in
seawater condensers. Also, the introduction of pannier
Typical unacceptable vacuum decay rates are 4 mbar/ type condensers for the 500 MW units meant that
min and above, as compared with expected rates of flooding the steamside with fluorescein solution, the
approximately 1 mbar/min. most popular method of off-load detection with
Where these techniques are not either favoured underslung types, was no longer possible. Underslung
or practical, other diagnostic techniques are often transverse condensers, however, have an advantage in
employed which require measurement of: that they can have up to six separate sections which
can be isolated and monitored using condensate con-
Air temperature in the air extraction line from the ductivity probes. This means that on-load location and
condenser; increase in air quantity handled reduces elimination of leaks is considerably simplified, often
the mixture temperature because of low water vapour without output loss.
partial pressure. The method of locating condenser CW leakage with
a unit on-load has three separate stages:
Undercooling of the condensate outlet from the
condenser; high air partial pressures give increased Location of the affected tubenest by condensate
undercooling in some condensers. conductivity measurement (desirable conductivity of
condensate approximately 0.1 /iS/cm).
Differential pressure between LP cylinder exhaust
and air extraction plant; low differential pressures Location of the physical level of the leakage within
indicate that the air extraction plant is controlling the waterbox.
the vacuum and not the condenser heat transfer
performance. Location of the leaking tube or joint.
368
Operational life limiting constraints

The first stage is carried out using conductivity probes Flame and smoke techniques; the flame from a
with the unit on-load. The tubenest causing the pro- taper (or smoke) is used to indicate a flow of air
blem is identified by an increase in condensate con- into a leaking tube.
ductivity. This is simplified in transverse underslung
condensers, where multi-sectioning means that local Ultrasonics; the noise generated by air passing through
increases in condensate conductivity will be signifi- a leak is detected.
cant at the location of the leak, and therefore easily
detectable. The sensitivity and application of these techniques
Having identified which condenser tubenest is at are discussed below.
fault, the second stage is to determine the level of
the leakage in that nest. This can be found either by
altering the cooling water level in the waterbox and 7.2.1 Fluorescein method
monitoring the condensate conductivity or by intro- The steam side of the condenser is flooded to above
ducing a tracer gas into the waterbox, dropping the the tubenest with a 10 mg/kg solution of the sodium
cooling water level, and monitoring at the air extrac- salt of fluorescein. A search is carried out in the
tion plant for the appearance of the gas as the leak is waterbox using ultra-violet light to detect traces of
uncovered. fluorescein. The tube which is leaking is therefore
It is interesting to note that these two methods are identified. There are, however, disadvantages of this
not suitable for all power stations, e.g., the former method:
method is satisfactory at sea-cooled stations, but, it is It is restricted to underslung condensers off-load.
unsuitable for freshwater-cooled stations where the
latter method is adopted. The revers'e action of water pressure on the tubes
These procedures are adequate for narrowing the compared with normal operation is known to close
field of search to within two or three rows of tubes, up the leak in some cases.
but stage three provides techniques which will precise-
ly locate the source of the leak. The water pressure is low at the top of the condenser
The techniques used include: and small leaks may escape detection.

Fluorescein method; the steam side of the condenser Residual fluorescein can affect feedwater and boiler
is flooded with a fluorescein solution. water analysis, and impair judgement as to whether
repair of the leak was successful.
Foam or film methods; the condenser tubeplates
are covered with a foam or thin film material whilst This method requires an operator to carry it out.
a vacuum is maintained on the steam side.
Bubbler devices; air bubbling through a jar of water 7.2.2 Foam or film methods
is used to detect a tube leak. The principle of this method (Fig 4.30) relies on the
development of a vacuum in a leaking tube. If the
Tracer gas methods; a halogen gas detector is tube is then sealed at each end, the vacuum draws in
situated at the air extraction equipment and the a foam blanket or a film of polythene or paper, and
suspect tubes sprayed with gas. thus identifies the location of the leak.

VACUUM FOAM

WATERBOX

^ \ / ^ TUBE LEAK

TUBE PLATE

FIG. 4.30 Tube leak detection by foam/film method

369
Condensers, pumps and cooling water plant Chapter 4

Generally two operators, each with a foam generator, methods of on-load and off-load cleaning of con-
are required. Pin-hole leaks with a leakage rate of densers are now described.
400 ml/h can be located, and 5000 tubes/hour can be
tested.
The success of this method relies on being able to 7.3.1 Condenser fouling
establish a vacuum of 330 mbar. Various forms of fouling have already been covered
in detail in Section 4 of this chapter, which looked
at the erosion/corrosion of condenser tubes from
7.2.3 Bubbler devices impingement attack.
Figure 4.31 shows the two different types of bubbler Basically there are three aspects of fouling which
which are used for tube leak detection. are beyond the scope of the CW screening plant
Figure 4.31 (a), the conventional bubbler, monitors installed:
the flow of air through a hole when the leaking tube
is under vacuum. The method will detect leaks down Blockage by debris.
to 175 ml/h, and an arrangement is adopted where Biological slimes.
10 tubes are monitored simultaneously, enabling 700
tubes/hour to be checked. Two operators are required Scaling.
for this method which is suitable for off-load use
providing a vacuum of 330 mbar can be obtained.
Figure 4.31 (b), the MEL bubbler, is similar in prin- Blockage by debris of tube and tubeplates was ex-
ciple to the conventional bubbler except that the tensively covered in Section 4 of this chapter.
suspect tube is evacuated with atmospheric pressure Biological fouling refers to marine life which con-
on the outside of the tube. This method can locate tribute to the formation of the slimy deposits on the
leakage rates of only 35 ml/h, the test rate being up heat transfer surfaces of condensers. These include
to 200 tubes/hour. bacteria, fungi and algae. The slimes formed by these
micro-organisms adhere to the metallic surface, resist
heat flow and form a layer to which other suspended
7.2.4 Tracer gas methods
matter can adhere to reduce condenser performance
further. Some forms of marine life, such as mussels
Detectors for halogen organic gases are extensively and barnacles, can cause problems by restricting flow
used for both air and cooling water leakage loca- and blocking tubes.
tion; Section 7.1 of this chapter gives details of the Scale formation is caused by the deposition or
method. reaction of inorganic material on heat transfer sur-
Generally leakage rates of around 1000 ml/h can faces. It usually occurs at inland river-cooled stations,
be detected with the unit on-load or off-load, as long using cooling tower systems. The scales are usually
as a vacuum can be obtained. One operator can carry calcium carbonate or calcium phosphate, or mixtures
out a search using a transmitter/detector, although of both, and arise from variations in their solubility
more normally two operators are employed. products with temperature and pH changes (Fig 4.32).
The temperature effect is due to the inverse solubility
characteristics of calcium salts. The pH changes arise
7.2.5 Flame and smoke methods by carbon dioxide stripping in the cooling towers.
These methods are fairly insensitive and involve the
use of lighted tapers or smoke tubes. Due to their
insensitivity, these are generally used as primary meth- 7.3.2 On-load condenser cleaning
ods of detection when massive leaks are suspected. Two principal methods of on-load fouling prevention
are employed to avoid unnecessary costly shutdown
of condenser plant, in order that efficient throughlife
7.2.6 Ultrasonic method costs are realised:
Again, this is a fairly insensitive method which is
not generally used. It involves the use of ultrasonic Chlorination of the cooling water.
detectors to pick up turbulence effects of the air
near a pin-hole. Owing to the noise from the steam Fine filtration, plus tube cleaning using rubber balls.
flow, and to an extent tube vibration, only leaks
close to the ends of the tube can be detected. Intermittent chlorination of the cooling water entering
the condenser is carried out on all British power
stations, and forms the accepted on-load fouling
preventive technique. It is effective in controlling the
7.3 Condenser fouling and cleaning growth of mussels in seawater systems, and the forma-
The types of fouling encountered in condensers, and tion of slime in freshwater systems.
370
Operational life limiting constraints

r^i

VACUUM
ATMOSPHERIC
PRESSURE

/
m
m mm -PLUG
^ =3^=

/
AIR
FLOW

TUBE PLATE

(a) Conventional bubbler

ATMOSPHERIC PRESSURE

AIR FLOW

DC


TO VACUUM //A\\
PUMP

BUBBLER

RESERVOIR

TUBE PLATE

(b) M.E.L. bubbler

FIG. 4.31 Tube leak detection using bubblers

371
Condensers, pumps and cooling water plant Chapter 4

100 H

50 H

20 H CONSTANT
200 mg/kg

PHOSPHATE
P0 4 1<H
mg/kg

FIG. 4.32 Graph of solubility of calcium phosphate with changes in temperature and pH

At coastal sites, marine fouling is significantly which becomes irrecoverable when the plant is re-
reduced by continuous chlorination of the cooling commissioned.
water. The degree of chlorination required is in- Late filling of the fine debris filters immediately
versely proportional to the CW flowrate, a chlorine upstream of condenser waterboxes may allow marine
concentration of 0.5 mg/kg of CW being required at fouling to occur, necessitating tubeplate picking to
1.5 m/s. remove debris.
At inland sites, slime control is maintained by Except in a few exceptional circumstances, off-
intermittent dosing of chlorine (a few minutes every load condenser cleaning is done during outages. The
four to eight hours) at a level which leaves a resi- techniques used are now discussed.
dual of chlorine of 2 mg/kg at the condenser CW
outlet. Bulleting
Fine filtration plus tube cleaning, however, is in-
stalled in some 10% of all locations, and is becoming This is the most extensively used method of cleaning
more widely used following experience on power sta- the inside surface of condenser tubes, and involves
tions with recirculating systems. A detailed account forcing bullets down the tubes to brush off surface
of this method is given in Section 6 of this chapter. deposits. Depending on the form of deposit to be
Other methods, including the use of flocculants, removed, the bullets vary from hollow and solid rub-
acid dosing, and toxic paints have all been considered ber balls, to nylon and steel bristle designs.
as possible remedies, but so far none has proved to Compressed air or water pressure, or a combination
be a viable alternative to those outlined above. of both, forces the bullets down the tubes from
lightweight guns which are designed to develop a seal
at the tubeplate without effort from the operator.
7.3.3 Off-load condenser cleaning
Although improvements in the on-load techniques Acid cleaning
continue to be made, off-load cleaning is frequently This method is restricted to condensers suffering
required for various reasons. from scaling problems, e.g., Midland stations which
Failure to cope (or breakdown) of the on-load draw their make-up water from the River Trent. Cal-
equipment, may cause a fouling condition to develop cium carbonate and phosphate scales form the de-
372
Plant testing

posits and have been cleaned using a variety of acids, 8 Plant testing
including hydrochloric, citric, acetic, and EDTA
(ethylene diamine tetra-acetate).
It is important when adopting this technique that
8.1 Introduction
the condenser steam space is subsequently flooded
with demineralised water to prevent acid entering the Condenser thermal performance tests are carried out
condensate when the unit is recommissioned. for two reasons:
Some stations have experienced stress-corrosion crack-
ing of expanded tube ends from acid cleaning. As acceptance tests to establish that a condenser
meets its specified performance, and is capable
of producing the desired condenser steam inlet pres-
Grit cleaning sure when operating under specified conditions.
An alternative to bulleting, this method is known As routine operational tests to monitor the con-
as sinusoidal grit blasting; it involves blasting graded denser performance periodically, and to verify that
silica-free mineral grit through the condenser tubes. station thermal efficiency is not being adversely
A special grit blasting nozzle incorporates a venturi affected by a deterioration in the condensing plant
which accelerates the grit and causes it to follow a heat transfer coefficient.
sinusoidal path through the tube, stripping off deposits
which have accumulated. This method has a 90%
effectiveness in cleaning tubes, and requires a charge In both acceptance tests and routine tests, a high
of grit at approximately 1 m/s. standard of instrumentation is required, particularly
in the measurement of the condenser steam inlet pres-
sure, and the cooling water temperatures. Routine
Water washing tests generally use less instrumentation than acceptance
This method uses either high or low water pressure, tests, but only when it is certain that this is not
depending on the application. detrimental to accuracy.
To remove surface deposits, a high pressure lance
with forward and side-facing jets is passed down
each tube, blasting water at a pressure of 700 bar. 8.1.1 Test codes and practices
This method has an advantage over acid or grit Condensing plant is the only major item of power
cleaning method, since its action does not have a plant which is at present not covered by a British
detrimental effect on the tube surface. However, its Standard code for thermal performance testing.
operation is awkward within the confines of the water- For this reason, the CEGB has compiled its own
boxes, and is therefore generally not used. test code, entitled 'Performance of surface-type steam
Low pressure water washing is effectively used to condensers' Site Test Code No. 3, 1981 [15].
remove loose sludge and sediment deposits prior to
leaving the condenser dry during overhaul. Often a
combined water/compressed air gun (similar to the Scope
type used in bulleting) is employed, having a dis- This Code covers requirements for acceptance, routine
charge pressure of 7 bar. and diagnostic testing of water-cooled surface-type
steam condensing plant, including multi-pressure de-
signs. It specifies procedures for testing condensers,
Thermal methods
and for calculating and reporting the results, so that
These have been used to control mussel growth in the condenser performance may be checked against
seawater station CW culverts, and to clean condenser contractual obligations. In addition, the performance
tubes by drying internal deposits prior to flushing of different condensers may be readily compared, and
with water. the operational performance of condensing plant may
The former application controls marine fouling by be assessed.
raising the temperature to 40C for one hour every Within this Code, reference is made in particular
six weeks. This restricts mussel growth to sizes which to the BEAMA design code [6] and to BS752: 1974
will not lodge in condenser tubes. The heating is Test Code for Acceptance of Steam Turbines' [16].
achieved either by introducing an auxiliary steam
source in the CW culvert, or by reversing the flow of
CW through the condenser. General outline
Drying the deposits in condenser tubes prior to The assessment as to whether a condenser meets its
flushing has also been successful: fan heaters are used guaranteed performance is based on comparison of
to blow warm air through the condenser waterbox the condenser inlet pressure measured on the accept-
access doors. ance test (corrected to specified conditions of CW
373
Condensers, pumps and cooling water plant Chapter 4

inlet temperature and flow, heat load, tube cleanliness be determined, as this is the most practical means
and tube surface area) with the guaranteed condenser of obtaining the fall in temperature through the
pressure. tubenest, and also the air extraction pressures.
When the test conditions differ from those speci-
fied, the Code describes a correction procedure which (b) Temperature measurement Temperatures re-
relies on validated curves or formulae and imposes quired are those of CW inlet, CW outlet, con-
close limits for permitted deviations when these are densation outlet, steam and air suction. All are
not available. The corrections are applied to the test measured directly except that of steam, for which
logarithmic mean temperature difference (LMTD) and it is preferable to assume saturation and to derive
allowance is made for variation in steam temperature the steam temperature from the corresponding
through the tubenest. pressure.
A method is also given for the routine assessment The accuracy of the CW inlet temperature
of condenser performance, in which the actual con- measurement equipment is specified as 0.05C.
denser inlet pressure is compared with that recorded Cooling water inlet temperature to the condenser
during the acceptance test and corrected for the is generally constant across the pipe section and
changes from acceptance test conditions to those the temperature measurement is made either by a
obtaining at the time of the routine test. thermometer in a pocket or by extracting a con-
A section dealing with test accuracy is included. tinuous flow of water through a vessel containing
The assessment of accuracy is based on the effect a thermometer.
of systematic errors only, the random errors being At the entry to the condenser CW outlet pipes,
effectively eliminated by the proposed frequency of however, the temperature of the water is stra-
readings. tified. To allow mixing to occur, the temperature
measurement point is sited as far as possible
downstream.
Acceptance test procedures Temperature sampling probes on two diameters
Before testing, a meeting is held between all parties are used in each condenser outlet. The probes are
involved to discuss the testing programme, and to either thermopiles or multi-hole probes through
make arrangements for any necessary preliminary work. which water is drawn into a mixing vessel. The
For example, discussions include reaching agreement holes or thermocouples are situated at centres
with the manufacturer on: of equal areas, one hole or thermocouple to each
0.2 m2 of pipe area.
Interpretation of contractual guarantees.
(c) Flow measurement The flowrates of cooling water,
Location, type, and calibration of test instruments
condensate and extracted air may be required
(Fig 4.33).
when assessing condenser performance. Methods
Means of obtaining the desired operating conditions. of determining the CW flowrate include:

Isolation of the plant for test purposes. Condenser heat balance.

The procedures to be followed for calculating results. Velocity/area methods.

Differential pressure methods.


By agreement, the official report of an acceptance
test may be produced by either party to the test, or Tracer methods.
by representatives of the parties working together.
These are listed in descending order of preference,
and the Site Test Code No. 3 [15] should be
Test measurements
consulted for qualifications.
(a) Pressure measurement The test pressure mea- Several methods are available for measuring
suring system must give the mean static pressure the rate of air leakage into the condenser, and
at the condenser inlet from each individual LP reference should be made to Section 7 of this
turbine cylinder to within 0.3 mbar, Fig 4.33. chapter which covered these aspects. Generally,
It usually consists of separate sets of pressure the preferred position for measurement is at the
sensing holes linked by manifolds to which the air pump discharge (Fig 4.33), because measure-
test manometers or transducers are connected. ments at the air pump suction require determina-
The same plane should be used for measuring tion of the steam/air ratio, and are made difficult
both the condenser pressure and the turbine LP by the low density of the steam/air mixture.
cylinder exhaust pressure, Fig 4.34. The measurement of condensate flowrate is
In addition, the steamside pressure drop should described in CEGB Site Test Code No. 2 [17].
374
Plant testing

.+-

AIR SUCTION PIPE

c^4.
4
CW IN
CWOUT
p) PRESSURE

fj) TEMPERATURE

(APJ DIFFERENTIAL PRESSURE

FLOW

FIG. 4.33 Points of measurement for condenser test

(d) Condenser heat load determination Site Test Code milar to that on the rest of the condenser. The
No. 3 recommends that condenser heat load should common inlet temperature and individual tube out-
be derived from a calculation of the heat rejected let temperatures and flowrates are measured, from
by the turbine-generator, preferably using heat rate which the cleanliness factor of each sample fouled
data obtained concurrently with the condenser test. tube is calculated according to Site Test Code
No. 3 [15], Appendices A and B.
(e) Tube cleanliness and air blanketing Both on-load The off-load method requires sample tubes to
and off-load methods for the determination of be withdrawn from the condenser. In a laboratory,
condenser tube cleanliness are required, and also the cleanliness factor is determined by measuring
the occurrence and location of air blanketing need the thermal resistance of the fouled tubes and
to be identified. comparing this with the thermal resistance of some
Figure 4.35 illustrates the on-load method for of the tubes after acid cleaning.
determining condenser tube cleanliness. Briefly, Air leaking into an inadequately vented con-
sample tubes in groups of three or four are se- denser will blanket the tubes, impede condensation
lected such that operating conditions throughout and increase the condenser pressure. The position
the condenser are represented. Separate supplies of air blanketing can often be inferred from mea-
of CW are provided for each sample tube by surement of the CW outlet temperature distri-
means of insulated pipes passing through the bution at the tubeplate.
waterboxes, and one tube in each group is selected An abnormally low temperature rise indicates
as a clean tube which is acid-cleaned before the probability of air blanketing somewhere along
commencement of the test. the condenser. A more precise indication of the
Cooling water is pumped through the clean position of the air blanketing can be made by
and corresponding fouled tubes at a flowrate si- inserting a small probe into the steam space to
375
Condensers, pumps and cooling water plant Chapter 4

<^ ^ 1 ^% 1
-
PLANE OF
PRESSURE
MEASUREMENT

^'
CONDENSATE
OUT
r CWOUT

(a) Transverse underslung condenser

PLANE OF
PRESSURE
MEASUREMENT

CWIN
CWOUT

(b) Axial underslung condenser

FIG. 4.34 Plane of pressure measurement for underslung condensers

measure the temperature and pressure within the (a) Minimise the size of the condenser.
tubenests, as shown in Fig 4.36.
(b) Maximise the thermal performance of the condenser.
(c) Secure reliability and availability.

9 Future developments
9.2 Research and development
In order to increase the specific condensing capacity
9.1 Aims and objectives (Q/m3) of future plant designs, research and develop-
In general, the aims and objectives for future designs ment work is being carried out to achieve a better
of condensing plant are to: understanding of the thermal performance of steam
376
Future developments

TUBE EXTENSION (INSULATED) TUBE EXTENSION (INSULATED)


cr^
FOULED
TUBE

CLEAN
TUBE

cw
INLET
j-XH
MX*

COOLING WATER MEASUREMENT POINTS


RECIRCULATING WATER FOR DETERMINATION
OF LOCAL STEAM TEMPERATURE 0 TEMPERATURE

FLOWRATE

FIG. 4.35 On-load determination of cleanliness factor

condensers, and hence improve the overall heat and increasing economic competitiveness, titanium
transfer coefficient (U). tubing is now used in all new power stations where
Two areas where such work is being conducted, impingement attack of the condenser is considered
include the layout of tubes in the tubenest, and the possible.
thermal performance properties of the tubing.
Advanced geometry tubing
9.2.1 Tubenest layout Another development in condenser tubing which is
All UK condenser manufacturers recognise the need currently being investigated is the use of advanced
to optimise the design of condenser tubenest layouts geometry (roped) tubing, to satisfy items (a) and (b)
by computer analysis techniques, in order to realise in the list of aims and objectives given in Section
improvements in thermodynamic efficiency. 9.1 of this chapter.
Details of a condenser optimisation programme Figure 4.37 is an example of roped tubing. It has
presently under development are outlined in Section a rolled helical ridge on both steam and water sides
5 of this chapter, which also covers the design of of the tube. One effect of this advance design is
plant components to minimise air blanketing, and to augment the waterside heat transfer coefficient
steamside pressure losses in the tubenest. by perturbing the water flowing in the tube, so that
boundary layers do not build up along the tube wall
and inhibit the transfer of heat. It also augments
9.2.2 Thermal performance properties of tubing
the steamside heat transfer coefficient by assisting
condensate drainage.
Tube material The total increase in overall heat transfer coeffi-
Section 4 of this chapter covers condenser tube ma- cient is estimated to be approximately 30% above
terial selection with regard to improving its resistance plain tubing; however, waterside frictional losses are
against the effects of corrosion/erosion. In-service increased.
titanium tubing trials were carried out at a number By maximising tube performance, the design allows
of power stations under varying operating conditions, the overall tube length and tubeplate size to be re-
see Table 4.3. As a result of the success of the trials duced, without incurring operational penalties.
377
Condensers, pumps and cooling water plant Chapter 4

PRESSURE MEASURING

THERMOCOUPLE
JUNCTION SLIGHTLY
WITHDRAWN INTO
TUBE

FIG. 4.36 Air blanketing surveys by inserting a probe into the condenser tubenest

Optimisation studies have been carried out on a A comparison of the mechanical behaviour between
transverse underslung condenser, using 25 mm OD roped and plain tubing is given in reference [18].
roped titanium tubing, and 25 mm OD plain tita- As far as reliability and availability are concerned,
nium tubing. Water velocities varied from 1.2 m/s research continues in the following areas:
to 2.2 m/s, and tube lengths varied from 12 m to
18 m. Tube maintenance.
Table 4.5 shows the minimum cost, optimum CW Tube cleanliness.
quantity and condenser parameters possible within
the constraints imposed on the system being studied, Modular construction.
i.e., a CW flowrate of not less than 1.68 m/s and
a CW temperature rise of less than 12C. In particular, the maintenance of condenser tubes
This suggests, for the two optima in Table 4.5, without access to the waterbox is being investigated.
savings of 200 000 by using roped tubes, however,
when compared to the existing condenser using conven-
tional tubing materials, savings in the order of 2.6 PUMPS
million are calculated.
An improvement in the overall heat transfer co- 10 Air extraction equipment
efficient of roped tubes is clearly illustrated by the
defined reduction in tube length and CW quantity,
and hence the size of tubeplate required to achieve 10.1 Introduction
these savings. The objectives of the air extraction plant are:
378
Air extraction equipment

FIG. 4.37 Photograph of plain and roped tubing

TABLE 4.5
Optimisation study results for plain and roped titanium tubing

Total Heat Tube CW flowrate


Tube Tube optimum cost transfer velocity, per set CW
design length (3 sets), area/set, m/s kg/s ATC
m million m2

Plain 15.2 43.2 29590 1.68 17790 11.0

Roped 12.2 43.0 21786 1.68 16379 12.0

379
Condensers, pumps and cooling water plant Chapter 4

To remove air which has leaked into the condenser The design air leakage rates presented in Table
via flanges and glands effectively. 4.4 are known to be higher than those adopted in
some other countries and, in many instances, are
To remove other incondensable gases that are pre- considerably in excess of air leakage rates realised
sent in the steam exhausting from the LP turbines. on British plant in practice.
However, experience has shown that, on balance,
the adoption of these ratings has been economically
It is important that both are removed from the con-
justified as a means of counteracting the following:
denser, as their presence in any quantity impairs the
heat transfer performance of the condenser. Con- High air leakage, due to valve packing failures,
versely, excessive air extraction capacity should be joint leaks, etc.
avoided, and reasons for this are discussed later.
The air extraction plant must be capable of func- Higher than design pressure loss through the con-
tioning under two regimes: one during normal opera- denser and air extraction pipework.
tion, the other when raising vacuum on the turbine-
generator unit. Excessive steam penetration through the air cooling
When raising vacuum, the air extraction equipment system.
is faced with a large quantity of air which must be
removed, and must therefore have the capacity for Adverse effects of part-load operation and low
reducing the pressure in the condenser quickly to a cooling water temperature conditions.
level which allows the turbine to be started.
The considerable experience gained, particularly
from 500 MW turbine condensers, has led to a much
10.2 Determination of air extraction quantity greater understanding of the factors influencing air
inleakage and its effective removal from large con-
To ensure adequate removal capacity under operating
densers.
conditions, the capacity of the air extraction plant
The limiting difference between the condensing
must be greater than the maximum amount of air
temperature and the cooling water deserves brief
and non-condensable gases expected to be removed
mention. This limit is aimed at ensuring reasonable
from the condensate.
CW outlet-end condensing zone and air cooling section
The main parameters which determine the quantity performance. Most large condensers in operation have
of air to be extracted from the condenser and, hence, temperature differences in excess of this figure; latest
the design of the condenser air cooling system and air thinking suggests that a temperature difference closer
removal equipment are: to 5C is desirable if pressure loss on the steamside
and/or excessive steam carryover to the air extraction
The design air leakage into the condenser. equipment is not to become a critical factor in deter-
mining condenser performance.
The degree of sub-cooling of the air/steam mixture
leaving the air cooling section.

The limiting approach temperature difference 10.2.1 The mechanism of air extraction
between the saturation temperature 0PcC cor- The mechanism by which non-condensable gases are
responding to the absolute pressure p c in the transported between the points of entry to the con-
condenser, and the CW outlet temperature. denser shell and the discharge to atmosphere can be
subdivided into three stages:
Table 4.6 indicates recommended values for typical Transfer of incondensable gases from the main
fossil-fired power stations of varying size. condensing zone to the air cooling section of the
condenser.
TABLE 4.6
Cooling of the incondensable gases and associated
Design air leakage rates for typical fossil-fired stations
steam in the air cooling section.
Turbine size, MW 300 500 600 Extraction and compression of the incondensable
gases from condenser vacuum to atmosphere.
Design air leakage rating, kg/h 73 120 161

Design air suction V - 4-2


temperature at outlet, C In order to meet the objectives outlined earlier, it
Limiting CW outlet temperature V - 3.3 is important that all three stages in the process are
carried out efficiently.
380
Air extraction equipment

Details of how this is achieved are described, and the tions of vacuum maintaining and vacuum raising,
different equipment types are reviewed. either in full or in part, depending upon the volume
to be evacuated and the time specified for synchro-
nising the machine.
10.2.2 The condenser air cooling section It is interesting to note that the last-row blades
In order for the air cooling section to perform ef- of a 660 MW turbine will overheat if they run at
ficiently, its position within the condenser and the speed and at low load in a poor vacuum. Therefore,
method of venting must be optimised, and the trans- a vacuum of 677 mbar(a) must be obtained before
port of incondensable gases from the condensing zone steam is admitted to the turbine, and a vacuum of
must be effective. 880 mbar(a) for full speed. It is important that the
This ensures that the air cooling process is achieved time taken to bring boiler and turbine plant on-
with minimum pressure loss through the condenser, load shall not be increased by insufficient extraction
and without creating stagnation regions within the capacity.
main condensing zone or introducing excessive steam The main systems in use today are:
penetration into the air cooling section.
Two different air cooling section designs have been Rotary pumps (e.g., Le Blanc), which use water
adopted in the UK. One extracts incondensable gases as the motive fluid for vacuum maintaining duties,
and steam from the cooling water inlet end of the with separate booster pumps for vacuum raising.
condenser; the other uses multi-point extraction from
various points along the condenser length; these are Hydraulic pumps, which work on the water-jet
illustrated for a pannier condenser in Fig 4.38. principle, for vacuum maintaining. Pumps of this
Air cooling sections designed on the first principle type have reasonable vacuum raising characteristics,
have the basic features of a redistribution passage but usually require to be supplemented by liquid-
for the steam and incondensable gas mixture in the ring pumps for vacuum raising duties.
tube axial direction, together with a baffling arrange-
ment towards the cold end of the condenser to force A system which consists of an ejector and a pump.
the mixture across the tubenest before final extraction. The ejector provides the first stage of compression,
In multi-point extraction condensers, the steam and and a liquid-ring pump provides the final stage of
incondensable gas mixture usually make one trans- compression to atmospheric pressure. This system
verse pass of the air cooling section tubes, and no uses both the ejector and the pump for vacuum
facilities are provided for reintroduction of the mix- maintaining duties, but the pump is used in iso-
ture into the air cooling section tubenest. lation for vacuum raising.
Condensers with single and multiple water passes,
and with single and multiple vacuum arrangements
have adopted both types of air cooling section, and A summary of the development of air extraction
have generally operated satisfactorily. equipment is given in Table 4.7, which indicates the
The single-point air extraction concept generally number of installations of each type of equipment
requires a higher pressure drop in the condenser to associated with 500-660 MW turbines in the UK.
ensure satisfactory flow through the air cooling section It is quite clear from Table 4.7 that the use of
than the multi-point arrangment, but it reduces the rotary and hydraulic air pumps has virtually been
probability of excessive steam carryover to the air phased out in the 660 MW designs. The reasons for
extraction equipment. this change in policy are discussed below.
With the introduction of air extraction equipment In the initial stages of the 500 MW programme,
which incorporates a direct contact pre-condenser, orders were placed for two air pump systems on
the carryover of steam is not such a critical factor which there was previous British experience; these
in determining the air extraction capacity. being Le Blanc pumps and hydraulic air pumps. Both
systems, however, could only offer a small contri-
bution during vacuum raising, and relied on supple-
mentary equipment to enable units to be loaded within
10.3 Review of air extraction equipment 20 minutes.
The main development of air extraction equipment The 'ejector plus pump' extraction system was
for large condensers has evolved through the use of introduced into Britain during the early 1960s. Initially
air extraction pumps. Steam-jet air ejectors were in this system only used atmospheric air as the motive
common use, but, for the higher pressure and fluid in the ejector stage, and incorporated a liquid-
temperature cycles adopted today, these have proved ring pump for second stage compression. This gave
to be less economic than air pumps, both in capital better vacuum raising characteristics than the hy-
and running costs. draulic air pump, which offset the slightly higher
Many different air extraction equipment designs operating costs of the system for vacuum maintain-
have been developed, all of which combine the func- ing duties.
381
Condensers, pumps and cooling water plant Chapter 4

STEAM

AIR EXTRACTION
DUCTS
/ I\
AIR
SUCTION

L I I
/ZONE

H-T I'V'U''
* Pfl
SE
tfe
P^

CW
OUTLET

(a) Single-point air extraction

AIR
EXTRACTION
DUCTS

ONE PANNIER SHOWN ONLY

(b) Multi-point air extraction

FlG. 4.38 Single and multi-point air extraction

382
Air extraction equipment

TABLE 4.7 barometric loop in the air suction line as a further


Air extraction equipment associated with 500-660 MW safeguard.
turbines in the UK As already mentioned, the requirement of a 660
MW turbine to reach full speed at no-load within
Unit size, MW 500 550 600 660 20 minutes of start of vacuum raising is beyond the
capability of hydraulic air pumps alone; the installa-
Rotary Le Blanc pumps 17 0 0 0
tion of supplementary vacuum raising booster pumps
Hydraulic air pumps 16 2 4 0 overcomes this problem. On their own, hydraulic air
Ejector/pump systems:
pumps will take in excess of 40 minutes to achieve
desired vacuum levels. In some cases the booster
air ejector 18 0 0 5
steam ejector 0 0 0 21
pumps are supplied on a unit basis, but it has become
increasingly popular to adopt common booster equip-
ment for two or more turbines, therefore reducing
capital costs.
Developments in ejectors have more recently pro- Separate electrical control systems are provided for
duced an alternative design which uses low pressure the hydraulic air pumps and booster pumps. The op-
waste steam from the de-aerator vent. This system eration of the pumps and their ancillary equipment
has proved to be very competitive and has captured is semi-automatic and sequence controlled to ensure
a large percentage of the 660 MW market, largely that start-up and shutdown procedures are correctly
due to its low power requirement (about 0.727 implemented. When common booster pumps are in-
kW/kg/h of air), which is approximately half that stalled, the system is interlocked to prevent the pumps
of other systems. being connected to a running turbine. Booster pumps
are generally arranged to shut down automatically
A more detailed account of these systems follows,
when the condenser vacuum reaches a predetermined
with the exception of the rotary Le Blanc pumps
level.
which are now of little relevance to modern UK
practice.
10.3.2 Liquid-ring type air pump
This is essentially a centrifugal displacement pump.
10.3.1 Hydraulic air pumps
A multi-blade impeller revolves within an offset casing
A typical hydraulic air pump arrangement is shown which is partially full of water. The rotating impeller
in Fig 4.39. The hydraulic pump unit is a water- throws the liquid outwards, resulting in a solid ring
operated ejector, which uses a motor-driven single- of liquid revolving in the casing at the same speed
stage recirculating lift pump, and a covered water as the rotor, but following the shape of the casing.
seal and air separation tank. Figure 4.40 shows how this alternately causes the
The water tank serves the dual function of acting liquid to enter and recede from the interblade spaces
as a heat sink for the air and vapour drawn from the on the impeller. The provision of inlet and outlet
condenser and providing a suction supply for the lift ports enables this pump action to be used for eva-
pump to recirculate the sealing water. cuation of air from the condenser. The advantages
Make-up water is introduced to the tank at the of this type of pump are that it is simple and reliable,
bottom to replace any losses, and maintain the tank at with large clearances on rotating parts, and no valves
a steady temperature. The tank overflow is controlled or pistons.
by a weir, and is discharged to waste.
Sealing water from the tank is circulated to the
hydraulic air pump where it is fed into a series of 10.3.3 Air ejector/pump systems
nozzles. Streams of water leaving the nozzles pass Figure 4.41 shows a typical arrangement, using air
over the blades of a spinner which is mounted on as the motive to the ejector. The system comprises
the end of a shaft, and is free to rotate. The blades an ejector stage and a liquid-ring pump stage, which
are formed so that the sealing water propels the combines to give two stages of compression of the
spinner and, in doing so, is broken into slugs. The condenser air/vapour mixture.
water which discharges from the spinner seals poc- Figure 4.41 (a) illustrates the system when operating
kets of air in the diffuser, pressurises them, and to maintain vacuum in the condenser. The air/vapour
discharges the mixture into the tank. The tank is suit- mixture from the condenser is first drawn through
ably vented, and the sealing water is recirculated to the vapour cooler. This is a direct condenser which
the lift pump. receives recirculated seal water, of towns water qua-
The air suction line to the water-operated ejector lity. This cooler reduces the vapour quantity of the
incorporates an electrically-operated isolation valve mixture before compression by the ejector stage. The
and disc-type non-return valve to prevent backflow ejector uses atmospheric air as the motive fluid and
of air and water to the condenser in the event of compresses the air/vapour mixture to a pressure of
pump failure. Some arrangements also include a about 135-170 mbar.

383
Condensers, pumps and cooling water plant Chapter 4

NOZZLES

r\
SPINNER

BAROMETRIC
LOOP

CONDENSER
AIR
SUCTION

SEAL AND
AIR SEPERATION
TANK

RECIRCULATING
LIFT PUMP
bMMMMt^MM^MiUaMlHkt

DRAIN

COOLING AND MOTIVE WATER

AIR VAPOUR MIXTURE

USUAL NUMBER OF UNITS 3 x 50% OR 4 x 337,%

FIG. 4.39 Typical hydraulic air pump arrangement

384
Air extraction equipment

PUMP INLET

IMPELLER
ROTATION

INTERNAL INLET PORT


INTERNAL DISCHARGE PORT

ALTERNATE PUMP DISCHARGE No. 1 ALTERNATE PUMP DISCHARGE No. 2

C> AIR FLOW

USE WATER

FIG. 4.40 Typical liquid-ring type air pump

The condensate from the vapour cooler and the 10.3.4 Steam ejector/pump systems
compressed air/vapour mixture pass to the single- Figure 4.42 shows a typical arrangement, using steam
stage liquid-ring pump, where the air is compressed as the motive fluid to the ejector. The system com-
to atmospheric pressure and discharged to a separate prises an ejector stage and a two-stage liquid-ring
tank, along with the seal water. The tank is vented to pump which combine to give three stages of com-
atmosphere, and there is also an air connection back pression of the condenser air/vapour mixture for the
to the air ejector. Seal water in the tank is pumped vacuum maintaining duty.
back to the vapour cooler and liquid-ring pump via a The condenser air/vapour mixture is first drawn
CW-cooled heat exchanger. through a direct contact pre-condenser to reduce the
For vacuum raising duties, the air ejector stage quantity of water vapour before compression by the
is automatically isolated until a condenser pressure ejector. The pre-condenser uses main CW as the
of 85 mbar is attained. Figure 4.41 (b) illustrates the cooling medium, which is drawn from a break tank
flow paths necessary to achieve this duty. by the condenser vacuum, and sprayed into the
If vacuum maintaining equipment is inadequate pre-condenser. The condensate from this condenser
for fast vacuum raising, booster pump arrangements is pumped to waste by a cooling water extractor
(similar to those described for hydraulic air pump pump.
systems) are incorporated, these booster pumps are The motivating steam for the ejector is vent steam
arranged to shut down automatically at about 50 from the de-aerator which would otherwise be dumped
mbar. to the main condenser. Since de-aerator pressure varies

385
Condensers, pumps and cooling water plant Chapter 4

VACUUM SWITCH

I5- VAPOUR
COOLER

hXW-
irfcs.'
CONDENSER

=fl
|
V VACUUM PUMP
\ STARTER SWITCH
1
BAROMETRIC
LOOP

VACUUM
PUMP

II ywvw\ ISEALWATER
J
RECIRCULATION
PUMP

CWOUT CWIN
(a) Vacuum maintaining operation

VACUUM SWITCH

A
I
I

-3- VAPOUR
COOLER

CONDENSER
HXtH-
WH >

-H
l _L
BAROMETRIC
LOOP

\ VACUUM PUMP
, STARTER SWITCH VACUUM
PUMP

II
COOLER
ISEALWATER
J RECIRCULATION
PUMP

COOLING WATER

TOWN WATER OR CONDENSATE

ELECTRICAL (b) Vacuum raising operation


AIR

AIR VAPOUR MIXTURE USUAL NUMBER OF UNITS 3 x 50% OR 4 x 33V3%

FIG. 4.41 Air ejector and liquid-ring pump vacuum systems

386
Air extraction equipment

OVERFLOW
AND DRAIN

USUAL NUMBER OF UNITS 2 x 100%

COOLING WATER
DRAIN TOWNWATER OR CONDENSATE

STEAM

AIR VAPOUR MIXTURE

FIG. 4.42 Steam ejector and liquid-ring pump air extraction maintaining system

with load, a control valve maintains the steam pres- cooling medium which is drawn from a break tank
sure to the ejector at a minimum pressure of 1.22 bar using the condenser vacuum. Condensate from the
which corresponds to the minimum operating pressure inter-condenser is cascaded to the pre-condenser for
of the de-aerator. removal by the cooling water extraction pump. The
On leaving the ejector, the compressed condenser air/vapour mixture from the inter-condenser is passed
air and ejector steam discharge to an inter-condenser to the two-stage liquid-ring pump where it is com-
where the steam is condensed, and the remaining pressed to atmospheric pressure.
air/vapour mixture passes to the liquid-ring pump. The liquid-ring pump operates with a recirculation
The inter-condenser also uses the main CW as its service water supply which comes from the service
387
Condensers, pumps and cooling water plant Chapter 4

tank. Water from the tank passes via a CW cooled unit with a two-stage vacuum raising and maintaining
heat exchanger to the liquid-ring pump. For vacuum unit.
raising duty, the ejector steam valve is isolated. This new unit (Fig 4.43) consists of two stages with
The advantages of this system are due to the both rotors being mounted on a common shaft, a
compression across the steam ejector, combined with seal water cooler, and an air/water separator. In the
effective pre- and post-condensing which increases hogging mode, only the first-stage vacuum pump op-
the liquid-ring pump suction pressure. The reduced erates and it handles the entire system load, as con-
mixture quantity handled by the pumps, therefore, denser pressure is pulled down from atmospheric to
makes it economically attractive for vacuum holding about 235 mbar(a). During hogging, the volume of
duties. However, the effect is to reduce the vacuum air handled by the first stage is greater than the inlet
raising capability of the liquid-ring stage, and larger capacity of the second stage, and is discharged through
vacuum raising pumps are required with this system. a check valve into a separator and to atmosphere.
At approximately 235 mbar(a), the second-stage
vacuum pump handles the entire volume of gas dis-
charging from the first stage. Figure 4.43 illustrates
10.4 Quick-start plant requirements how the second-stage pump suction closes the check
valve, and the two-stage combination pulls the con-
denser down to operating pressure. The second stage
10.4.1 Type of plant discharges into the separator and then to atmosphere
More recently, a new design of liquid-ring pump has and, because the interstage pressure is sub-atmos-
led to improvements in the flexibility of air extraction pheric, the suction at the first stage of the pump can
equipment by replacing the single-stage quick-start be lower than 34 mbar(a).

AIR OUTLET

CONDENSATE
OVERFLOW

CWIN

FIG. 4.43 Quick-start two-stage vacuum raising and maintaining unit

388
Air extraction equipment

Other design differences incorporated in this sys- 5 yrs 15 yrs 25 yrs Totals
tem include stationary inlet and outlet ported cones /min
which fit inside a rotor, instead of suction and dis- Cost incurred (/min) 5000 15 000 40 000
charge end plates, and the provision of a plate-type
DCF at 5% 0.7835 0.4810 0.2950
titanium seal water cooler instead of a tubular cooler.
DCF at 10<Vo 0.6210 0.2394 0.0923

PV at 5% DCR (/min) 3918 7215 11 800 22 933


10.4.2 Starting times PV at 10% DCR (/min) 3105 3591 3692 10 388
The economics of sizing vacuum raising and main-
taining plant are described below, using an example
with figures taken from a typical power station study. At discount rates of 5% and 10%, the present value
It identifies the possibility of vacuum raising and costs of vacuum raising over 25 years is 22 933/min
maintaining plant size being determined by the quick- and 10 388/min, respectively.
start requirement referred to earlier. The costs per The options available are pumps A, B and C which
start per machine incurred by holding the boiler in have corresponding pumping capacities in the ratio
the start condition whilst waiting for vacuum to be of 3, 2 and 1. Table 4.8 indicates an evaluation which
raised are given as 600 per 20 minutes. was carried out on the three pump options and their
associated costs against pump A, which was chosen as
the datum design.
Expressed as cost per minute holding = 30/minute
This study suggests that, by reducing the size of
the vacuum pumps, and hence the capacity available
Number of starts anticipated over for quick-starting, the vacuum raising time may be
life of plant (25 years) = 2000 increased without incurring an economic penalty.
Pump C, the lowest capacity pump option capable
Assuming a typical distribution curve (Fig 4.44), deter- of dealing with a leakage rate of 40 kg/h, appears
mine the present value (PV) cost of quick-starting to be the best economic choice. However, no allow-
over the 25 year life of the plant, for discounted ance is made for the associated increases in turbine-
cash flow (DCF) discount rates (DCR) of 5% and generator, feedheating, and condensing plant costs
10%. necessary to ensure that a 40 kg/h air inleakage rate

HOLDING COSTS x 1 0 4
PER MINUTE

PLANT LIFE (YEARS)

FIG. 4.44 Typical 660 MW plant lifetime distribution costs incurred when holding boiler in start condition
during vacuum raising

389
Condensers, pumps and cooling water plant Chapter 4

TABLE 4.8
The economics of sizing vacuum raising and maintaining plant

Pump A B C

3 x 50% pump cost/unit, 148 500 132 000 81 000


Cost saving, DATUM - 1 6 500 - 6 7 500

Power per two pumps, kW 298.4 111.9 55.75


Power reduction, kW DATUM -74.6 -187
Cost saving at 1500/kW DATUM - 1 1 2 000 - 2 8 0 000
2
Space occupied, m DATUM -7.15 -12.54
Cost saving at 1260/m 2 DATUM -9010 -15800

Cost savings in terms of pump


size, power and space (1), DATUM 137 510 363 300

Quick start times, min 13 20 35


Additional times, min DATUM 7 22

For internal accounting


10% DCF is used, i.e.,
10 388/min

Cost of quick starting


(2), DATUM 72 716 228 536

Overall cost saving,


(1) - (2), DATUM 64 794 134 764

is not exceeded. These costs could offset the apparent in pump design head, flow and speed. All geo-
cost savings of 134 764. metrically similar pumps have the same specific speed
It would appear that the intermediate vacuum which is calculated in non-dimensional units from
pump size (pump B) can meet the traditional vacuum the following formula:
raising time of 20 minutes, and offers some cost
saving, although not as significant as pump C. is = 27rn(q v ) 0 - 5 /60(gH) 0 7 5
The extra pumping capacity of the option would
be more tolerant to any increases in air inleakage where n = pump speed, r/min
above 40 kg/h, and therefore less emphasis would
Qv flowrate per impeller eye, m3/s
need to be placed on achieving and sustaining low
air inleakage rates from the associated plant. H generated head per impeller, m
g = acceleration due to gravity, m/s2

There is no firm demarcation between the various


pump types. Each merges into the next, so that for
11 Hydraulic aspects of centrifugal
a given specific speed there can be two pumps of
pumps differing construction. However, specific speed can
be defined as falling into the following categories:

11.1 Specific speed Type of pump Specific speed range


Centrifugal pumps are traditionally divided into three (ISO notation)
basic types: radial flow, mixed flow and axial flow. Radial flow 0.2 to 1.8
The names indicate the direction of flow of liquid Mixed flow 1.8 to 3.0
through the impeller. The term specific speed (ns)
can be used as an aid to the classification of the Axial flow 2.8 to 8.0
pump type and is indicative of the shape of the im-
peller and the pump hydraulic characteristics (Figs It is evident from Fig 4.45 that to optimise the hy-
4.45 and 4.46), which are taken from Steponoff [19]. draulic selection on an efficiency basis, a specific
The expression involves the three fundamental factors speed around 0.8 is necessary. For high-head large
390
Hydraulic aspects of centrifugal pumps

Over 10OOOgpm

"lOOOOgpn^H

1
EFFICIENCY % 70

1.0

SPECIFIC SPEED n

FIG. 4.45 Pump efficiency versus specific speed and pump size

flow pumps, optimum efficiency when using low 11.2 Net positive suction head
speed prime movers necessitates a large number of The net positive suction head (NPSH) is an im-
stages. portant concept in judging the suction behaviour of
By comparison, efficiency optimisation could be a centrifugal pump. A distinction needs to be made
achieved by using single-stage high speed machines. between the NPSH available to the pump and the
Both these extreme options, however, can have their NPSH required by the pump.
own potential disadvantages. The high speed ma-
chine can lead to excessive impeller tip speeds and The NPSH available is the difference between the
consequential erosion problems, while the slow speed inlet head to the pump and the saturation pressure
arrangement results in a flexible shaft design unable of the liquid being handled. As the available NPSH
to cater for transient operational requirements. Thus is reduced, cavitation commences, first at flowrates
the pump hydraulic design is usually a compromise away from best efficiency and eventually over the
to take account of all relevant factors, including complete operating range. This is a result of the local
mechanical limitations and suction head considerations. pressure falling to the vapour pressure of the liquid
The effect of moving away from best efficiency can at the particular temperature condition. Operation
be seen in Fig 4.46. A specific speed below optimum in a cavitating mode for extended periods results in
reduces the peak level of efficiency, but there is a erosion damage, regardless of impeller material. Feed
consequential improvement in the spread of higher pumps with a high head per stage are most liable to
efficiency. This can be of use when plant is required cavitation damage because of the higher energy input
to operate frequently over a large flow range. to the fluid.
Moving to high specific speeds is seen to produce Cavitation performance breakdown has been shown
a steeper head/flow characteristic. This can be ad- to be directly proportional to (shaft speed)2 for a
vantageous when operating pumps in parallel as it centrifugal impeller. It has also been shown that the
minimises the risk of unstable operation. One dis- head drop at which unacceptable cavitation damage
advantage of the high specific speed designs is the in pump impellers occurs, increases with pump speed.
shape of the power/flow characteristic which can be From these findings, it is evident that the suction
highest at closed valve. This results in excessive motor head levels needed for high speed pumps are signi-
ratings to cater for start-up requirements. ficantly greater than those for lower speed machines.
391
Condensers, pumps and cooling water plant Chapter 4

200-
>w 6
\7

180-

160-
. 5
kW*2
140-
75 4
HEAD %
EFFICIENCY % U\5 OF NORMAL
OF NORMAL 16 120- 3
7 ?_ -
50
-^" ""
J
^3

7V '5
25 50 75 100 125 25 50 75 100 125

CAPACITY % OF NORMAL CAPACITY % OF NORMAL

EFFICIENCY HEAD-CAPACITY

250
.7
CURVE SPEED PUMP TYPE

u 1 0.33
2 0.55
150 3 0.80 DOUBLE
BRAKE 4 1.10 SUCTION
HORSEPOWER % 1 5 1.46
OF NORMAL
100
i3
lb 6 2.09 SINGLE
[4 ^ "^6 7 3.37 SUCTION
50 ->
7

X
50 75 100 125 150

CAPACITY % OF NORMAL

BRAKE-HORSEPOWER

FIG. 4.46 Effect of specific speed on head power and efficiency

The minimum NPSH required can be defined as that to avoid cavitation problems [20].
value of NPSH needed by the pump under long term Visual cavitation tests are carried out on a special
load conditions to prevent the occurrence of harmful test facility, where, for example, a perspex window
cavitation effects, in particular that required to avoid allows an uninterrupted view of the impeller eye, and
cavitation damage and ensure satisfactory operation. enables visual observations to be made under
Normal practice for determining the NPSH re- stroboscopic lighting. This is an important tool,
quired to limit cavitation damage to an acceptable allowing the exact cavitation inception point to be
level is based on head drop tests. For high duty feed determined, which effectively defines the zero cavi-
pumps, the assessment of visual test data is now also tation damage line. Although observations of the
used as an additional means of assessing the adequacy pressure face of the blade are difficult, this problem
of NPSH margins. can be overcome by using acoustic inception tech-
The NPSH head drop test can be included as niques to establish the onset of cavitation. When
a standard proof of performance test, with mea- checking NPSH adequacy using the visual technique,
surements being taken to establish the NPSH at current practice requires the available NPSH to have
which a 3% drop in generated head occurs. From a margin over the visual appearance NPSH, which
data available, it is considered prudent to provide itself is associated with bubble cavities having an
for feed pumps at least 3 x 3 % head drop NPSH agreed maximum length.
392
Circulating water pumps

11.3 Suction specific speed CEGB experience has been generally based on
The term suction specific speed (n ss ) expresses the hydraulic designs where the specific speed has been
suction capability of the pump impeller and is defined limited to 1.6. This reduces the risk of both head/
by: flow characteristic instability and high powers at low
flows. It also gives a good efficiency spread over
n ss = 27rn(q v )' 5 /60(gNPSH) 0 75 the range of operating flowrates. The head/flowrate
and absorbed power characteristics are now controlled
by the following specification:
where n = pump speed, r/min
qv = flowrate per impeller eye, m 3 /s Pumps are designed so that the discharge head
NPSH = net positive suction head, m falls continuously as the flowrate is increased from
zero to rated capacity by a minimum of 1 /o for any
g = acceleration due to gravity, m/s 2 15% increase in discharge flow.

The pumps are capable of sustained running at


High numerical values of n ss are associated with large any point on their head/flow curve from 25% to
impeller diameters and improved suction capabilities the maximum runout condition.
around pump best efficiency (BEP). The large eye
diameter can, however, lead to problems of inlet The input power rises continuously as the flow
flow recirculation under off-duty conditions, with is increased from zero to the rated flowrate.
consequential pulsations in the pump and adjacent
pipework. At flowrates away from BEP, incidence
causes flow separation within the impeller. This se- Circulating water pump speeds are normally in the
parated flow is then directed backwards out of the range 150-300 r/min. Low speed motors, suitable
eye. The larger the impeller eye, the nearer to the for direct coupling to the pumps, are expensive and
BEP is the flow at which this recirculation occurs. it is usually economically justifiable to include a
To prevent the damaging effects of inlet flow re- step-down gearbox between the pump and motor.
circulation, leak-off flowrates need to be sized so as The combined efficiency of a 1000 r/min high speed
to ensure that pump throughput is always in excess motor and associated gearbox can be similar to the
of the amount at which recirculation commences. low speed multi-pole motor. When comparing capital
This applies particularly to both feed pumps and costs of the two options, the costs of extra cranage
extraction pumps. equipment and the additional civil work to support
In the absence of detailed information of pump the heavier motor have to be added to the direct drive
capability at the tender stage, the CEGB normally pumpset costs. The two main advantages of the direct
requires that the suction specific speed based on the drive option are its simplicity, which can lead to higher
NPSH available to the pump should be limited to availability, and the elimination of any noise control
2.4 (ISO). requirements arising from the high speed motor/
gearbox combination.
For flowrates over 10 m 3 /s, main cooling water
pumps are now based on the concrete volute type.
Below around 6 m 3 /s, it is impractical to consider
12 Circulating water pumps
concrete volutes because of physical access limitations
in the mechanical seal area, and metal casing designs
have been used. Between 6 and 10 mVs the CEGB
12.1 Introduction have so far installed only metal casing pumps, al-
The structural design of main circulating water pumps though concrete volutes have been successfully used
in the CEGB has changed over the last 20 years from elsewhere.
horizontal split casing double-entry designs to the
vertical spindle bottom inlet single-entry type. The
horizontal pumps, while easy to maintain, require a
large floor space, and the weight problems on the 12.2 Horizontal split-casing pumps
larger units necessitated the use of multiple casing Double-entry horizontal split-casing type pumps (Fig
castings. The alternative vertical spindle pumps, now 4.47) have been installed on CEGB stations to cover
generally specified, have been developed for both a wide range of duties up to 18 m 3 /s and 24 m gen-
metal casing and concrete volute applications, with erated head. This design of pump has the major
the choice depending on the overall economics of advantage that the top section of casing and the
the installation. They have significant advantages rotating element can be removed without breaking
compared with the horizontal designs in terms of the either the pipe joints or disturbing the alignment.
compactness and cost of mechanical, electrical and While this feature gives good accessibility for both
civil engineering work. overhaul and maintenance work, the horizontal design

393
Condensers, pumps and cooling water plant Chapter 4

FIG. 4.47 Horizontal split-casing extraction pump at Dungeness B power station

394
Circulating water pumps

has a number of disadvantages apart from the large duct. The assembly then acts as both a sealing ring
floor area required. In particular, the preference for for the top cover and also as a central location
installing the unit with the impeller eye below mini- around which the precision-made volute shuttering
mum water level, to eliminate the need for com- framework is assembled prior to concrete pouring.
plicated priming equipment, results in expensive civil The volute shuttering is normally provided by the
excavations. The physical size of the large metal civil contractor to the pump manufacturer's dimen-
casings has also brought about both manufacturing sions, and can be re-used on all pumps on the same
difficulties and flexing problems with the complicated contract. Figure 4.49 shows the various stages of
assembly. construction of the volute. From experience, it has
been found that no special protective coating is re-
quired on the concrete to guard against the effects
of the water being pumped. Both wear and life
12.3 Vertical pumps expectancy of the concrete are excellent and no pro-
blems have been reported on CEGB pumps at inland
12.3.1 Vertical metal-casing pumps or coastal stations over a 20 year operating period.
Volute casing designs have been used by the CEGB A fabricated steel bearing bracket is mounted on
for pumping duties up to around 8 m 3 /s. On low head top of the pump cover and bolted down and dowelled
coastal applications, standard gear-driven units have into position to secure correct alignment. The speed-
been installed, while on the higher head inland cooling reducing gearbox is mounted on top of the bearing
tower applications, it has been possible to use a direct bracket, with the unit incorporating the pumpset
motor drive while still retaining the same equivalent forced lubrication system. The rotating assembly is
specific speed as the equivalent gear-driven units. supported by a combined thrust and journal bearing
Alternative bowl pump designs have been used which can be located within the gearbox. Access to
extensively on overseas applications. With this design, the bottom bearing and mechanical seal is gained
the pump forms part of the piping and its intake is from within the tubing.
from a relatively unsophisticated suction chamber;
it generally has a smaller civil engineering cost than
the equivalent concrete volute design. There is no
complicated volute to construct, and as the pump has 12.4 Gearboxes
a smaller overall diameter than the concrete volute, Gearboxes, when included on vertical pump units,
the pumphouse floor area is smaller. On the debit must be of the coaxial type with the pump, motor
side, the bowl pump arrangement has a much higher and gearbox centrelines positioned vertically above
mechanical pumping equipment cost. each other to ensure an equal load distribution on
Maintenance of the bowl pump is also difficult and the support ring.
the crane normally has to be sized to take the total Coaxial gearboxes may be either of the multi-
pump weight for installation and overhaul. As the layshaft or epicyclic designs. With recent epicyclic
pump is withdrawn vertically for major overhaul designs, it has been possible to combine the gearbox
work, a suction isolating valve is not required. This and the pump by mounting the impeller on the low
however leads to a relatively long pump to facilitate speed output shaft of the gear unit (Fig 4.50). This
vertical isolation. One major technical disadvantage arrangement eliminates the need for one journal
of the bowl pump is the need for submerged shaft bearing, which in turn reduces the overall height of
bearing bushes. These are not readily accessible and the pumpset leading to a more compact arrangement.
can have a relatively short life in silt-laden water. A further reduction in pumpset length is achieved
Casting problems have tended to limit the size of by combining the thrust collar into the coupling hub,
both the volute and bowl pump designs. The standard as shown in Fig 4.50.
use of cast iron necessitates the inclusion of sub- The gearbox is equipped with a complete forced-
stantial allowances on coastal units to allow for lubricating oil system to provide a continuous flow
corrosion/erosion effects over the life of the station. of oil to the gear internals and the thrust and journal
bearings throughout the pumpset. The oil system
includes both gear-driven and standby motor-driven
12.3.2 Concrete volute pumps oil pumps, and the piping and non-return valve layout
Figure 4.48 shows the sectional arrangement of a allows delivery of oil to the bearings and gears,
typical concrete volute pump, which follows the whichever direction the pump is rotating.
same hydraulic principles as the conventional metal
casing designs except for the volute which is formed
on-site on the concrete foundations. The pump casing
consists of permanently-embedded top and bottom 12.5 Shaft seals
seating rings separated by the cutwater and stay Mechanical seals are included to prevent water es-
vanes. These are carefully positioned over the inlet caping from the casing along the pump shaft. Split
395
Condensers, pumps and cooling water plant Chapter 4

TACHOGENERATOR -
-THRUST AND JOURNAL
BEARING

STATOR TERMINAL BOX

-MECHANICAL SEAL

PUMP CASING COVER

DISCHARGE-
FLANGE
IMPELLER

GUIDE VANE

FIG. 4.48 Bottom inlet single-entry impeller concrete volute pump

396
Circulating water pumps

MILD-STEEL TUBBING
UP TO MOTOR FLOOR

CONCRETE-IN TO
TOP OF FLANGE

PACKING
PACKING ALLOWANCE

INTERMEDIATE STEP
BOTTOM OF VOLUTE CAST

STAGE 1
m* STAGE 2
BEFORE SHUTTERING IS
FINALLY POSITIONED BUT STAGE 3
ONLY IF VOLUTE BASE IS FLAT

FIG. 4.49 Construction of concrete volute

type seal designs are used (Fig 4.51). All the com- performance of the full size pump and the cost of
ponents which are subject to wear, are split into two any corrections or adjustments is negligible com-
sections to permit inspection and replacement of worn pared with making modifications to the full size pump
components to be carried out without any major itself. Model tests enable the hydraulic characteristics
dismantling of the pumpset. of the full size pump to be accurately predicted. This
The seal needs to be provided with a clean supply is particularly relevant to concrete volute pumps which
of flushing water which can either be filtered water cannot be works tested.
taken from the pump discharge or a separate towns Scale models are also used to verify design pro-
water supply. Figure 4.52 shows a typical seal flushing posals for the suction intake to the pumps. The model
arrangement on a coastal station, where the filtered normally comprises the forebay, intake screen cham-
water is normally taken from the pump discharge ber, draft tube, volute and discharge pipework. Com-
for flushing purposes while the pump is running. A prehensive tests are carried out to demonstrate the
separate towns water supply is integrated into the acceptability of the intake system over the complete
system which enables the seals to be flushed prior to range of operating conditions, taking account of the
start-up and following shutdown. The towns water combinations of pumps operating and the variation
supply is also available as a back-up supply during in suction water levels.
pump operation should the seawater system fail as In determining the full size pump performance
a result of excessive pressure losses across the fil- from the results of the model tests, the normal affinity
tration system. laws are applied to demonstrate that the guarantees
The seal assembly also includes an additional in- on head and efficiency at the rated flowrate, and the
flatable static seal. This is operated by air and forms shape of the head/flow and power/flow character-
a watertight joint around the shaft to allow disman- istics are likely to be met when the full size pump is
tling of the main seal unit without dewatering the eventually tested on site.
pump. A secure source of air is required and the Site tests on circulating water pumps are carried
use of a standby accumulator eliminates the need for out in accordance with CEGB Site Test Code No. 6.
the station air supply to be available at all times. To overcome any contractual problems in determining
Any water which leaks into the access well of the head losses at suction and discharge, the pump is
concrete volute pumps is removed to the drainage deemed to be that part of the system from the open
sump by either a small submersible pump or an air- water level at draft tube inlet to the discharge mea-
operated ejector system. These can be controlled surement point.
from float switches or an adjustable timer. Flow measurement is considered the most difficult
aspect of circulating water pump site testing, and
various methods are currently employed. On stations
with long straight open culverts, the current meter-
12.6 Pump testing traversing technique has been found to give satis-
It is accepted practice to construct and test a scale factory results and is relatively easy to install and
model of any large new circulating water pump design. use. For other stations where there are no suitable
This is an economic method of evaluating the likely open channels, the isotope dilution method is widely

397
Condensers, pumps and cooling water plant Chapter 4

HIGHSPEED
COUPLING HUB

MAIN OIL PUMP

OIL INLET

ANNULUS RINGS

SUN WHEEL

PLANET CARRIER
PLANET WHEEL-
LOW SPEED HUB

JOURNAL BEARING

THRUST BEARING

FIG. 4.50 CW pump gearbox

used. This involves the injection of a tracer of work, and yields highly accurate results. The principal
known concentration at a constant rate upstream of disadvantage arises from the strict safety precautions
the pump and measurement of the concentration at necessary when using radioactive tracers and the re-
a point downstream of the injection point where sulting inflexibility of the test programme.
adequate mixing will have taken place. The dilution An alternative flow measurement technique now
technique is completely independent of the velocity developed is the use of ultrasonic flowmeters, with
of the pumped fluid, or the dimensions of the pipe- multiple transmission paths being included to take

398
Circulating water pumps

DRIVE ALIGNMENT
BOLTS
FACE CARRIER

ADAPTER PLATE

SPLIT O-RINGS

SEALING
STRIP

CLAMP RING

BELLOWS

FIG. 4.51 Pump shaft seal

account of the velocity profile across the flow path. offers proven superior resistance to attack, with negli-
Although the measurement transducers have to be gible wear after several years' operation.
installed with a high degree of accuracy to ensure On concrete volute pumps, the built-in metal parts
correct flow readings, the facility is then available for must be suitable for the life of the station. Again,
use throughout the life of the station. while grey cast iron can be used for inland fresh-
water sites, austenitic ni-resist cast iron is required
for seawater applications.
Circulating water pump impellers are supplied in
12.7 Materials stainless steel with renewable eye rings to cater for
For fresh water applications, grey cast iron is suitable the erosion effects in this close clearance/high ve-
for pump casings and delivery mains. However, for locity area. Both 13/4 chromium-nickel steel and
seawater and silt-laden water conditions, severe ero- 18/10 chromium-nickel austenitic stainless steel have
sion and corrosion of the cast iron occurs. Although been used successfully in freshwater and seawater
generous allowances can be included in the material applications.
thickness, these may not prevent the need for re- Pump shafts are normally made of carbon steel and
placement of the cast iron parts during the life of are fully protected by stainless steel sleeves through
the station. the waterways. Special attention is required at the
The use of austenitic ni-resist cast irons for the sleeve/sleeve and sleeve/impeller joints to prevent
casing material of cooling water pumps where severe ingress of water onto the shaft surface, which can
conditions exist is now increasing rapidly. This ma- cause corrosion fatigue. On horizontal pump designs,
terial, particularly in its spheroidal graphite form, overlapping sleeves and radial O-rings have been
399
Condensers, pumps and cooling water plant Chapter 4

COUPLING

BEARING

COMPRESSED AIR SUPPLY


TO INFLATABLE MAINTENANCE
SEAL

SUBMERSIBLE DRAINS
PUMP

PUMP
IMPELLER

FIG. 4.52 Typical seal water flushing system

introduced to cater for the effects of shaft static mally provided with the standby being ready for
and dynamic deflections. Mounting the mechanical immediate operation, when required. The extraction
seal on top of the shaft sleeve permits seal refur- pumps are designed to pump condensate from the
bishment without slackening the sleeve nuts, with condenser at a saturation temperature corresponding
resultant loss of axial compression. to the sub-atmospheric pressure within the conden-
ser. Under these conditions, the available positive
suction head is very low and suction conditions are
very stringent. The rotational speed of the pump and
the flow of condensate into the first stage impeller
13 Condenser extraction p u m p s should be kept as low as possible and the impeller
Two 100%-duty condenser extraction pumps are nor- eye must have the maximum capacity for handling
400
Condenser extraction pumps

water in order to provide the minimum NPSH re- With horizontal extraction pump designs, one of
quirements and thus avoid unnecessary depth of the the most important factors is the avoidance of oxy-
extraction pumps below the condenser. gen ingress into the condensate through glands which
For many years, the CEGB relied on horizontal may be required to seal against sub-atmospheric pres-
split-casing type extractions pumps (Fig 4.53) and sures. A secure supply of seal water is necessary
these have generally given satisfactory service. The and this is usually provided from a common mani-
generated heads developed by these pumps were mod- fold which is supplied by connections in each pump
est at around 100 m on 500 MW and early 660 MW volute. This caters for both running and standby
stations with direct-contact heaters. conditions. Water from the manifold can also be used

INTERNAL WATER
SEALING PIPE

SLEEVE NUTS
DRIVE END BEARING
ORING

^ ^ . GLAND PACKING
( <y> ^ C O U P L I N G GUARD
>
^ ^ = ^ SUPPORT
OUTER IMPELLER SLEEVE

KLINGERITE" JOINT

INTERMEDIATE BEARING BUSH

INTERMEDIATE SLEEVE

SUCTION BRANCH
STEADY PIN

OUTER IMPELLER
SLEEVE

FIRST STAGE
DOUBLE SUCTION
IMPELLER

FIG. 4.53 Horizontal split-casing extraction pump

401
Condensers, pumps and cooling water plant Chapter 4

as a supplementary supply to any interstage water- The latter is now preferred, as it ensures an adequate
lubricated bearings. pump throughput even at low unit loads. This mini-
To prevent the accumulation of vapour at the mises the risk of the cavitation erosion problems,
impeller inlet, the first stage impeller eye of a hori- which can occur on the alternative arrangement if
zontal extraction pump should be vented back to the the pumps are operated significantly away from their
vapour space in the condenser, with the vent piping duty points.
having an upward slope to the condenser. Pumps are specified with a requirement that cavita-
In recent CEGB stations, where surface tubular tion erosion does not produce mechanical failure or
LP feedheaters are used, the required pump gen- loss of performance in less than 45 000 hours when
erated head has risen significantly to over 250 m. operating at 80% of rated flowrate. To ensure this
This increase in head produces design problems on objective is achieved, the suction specific speed (nss)
large split-casing pumps, particularly in sealing the is limited to 2.4 (ISO).
main joint and withstanding impeller radial loads.
An alternative caisson type pump (Fig 4.54) has now
been adopted. The multi-stage vertical pump design
has several attractions over the horizontal split casing 14 Boiler feed pumps
pump:
The NPSH available is increased by installing the
pump in a pit, thereby reducing the risk of cavita- 14.1 Introduction
tion erosion. The design and arrangement of boiler feed pumps
has a significant impact on overall unit availability.
An increase in the NPSH available allows the In determining the optimum arrangement of feed-
speed to rise, resulting in a smaller pump for the pumping plant, the economic assessment needs to
same NPSH margin. take account of capital costs, capitalised running
costs, repair and maintenance costs, and the likely
There is no need to take static shaft deflections
effects of loss of availability. Other constraints which
into account on the vertical pump. Radial stresses
should be considered are:
are reduced allowing a slimmer shaft to be used.
Only a single mechanical seal is required which The need to ensure that failure of a single pumpset
operates under pressure, providing less danger of does not impair the start-up of the main unit or
the oxygen ingress that was sometimes encountered affect output capability. Standby capacity equiva-
with the older traditional pumpsets. To prevent lent to the largest duty pumpset is indicated with
oxygen ingress while the pump is on standby, the a rapid start-up capability, sufficient to prevent
inner seal chamber is filled at all times with pres- the loss of boiler drum level and consequent unit
surised water supplied either from the common trip.
discharge manifold or from a back-up reserve feed-
The need to ensure that the plant is able to op-
water supply when both pumps are stopped.
erate satisfactorily during and after a large load
There is a facility for a cartridge-type repair which rejection by the turbine-generator unit. This re-
improves pumpset availability. The pumps are quires that the drives for the duty pumps and their
designed so that, by disconnecting the pipework power supplies must be suitable for this operating
at the discharge branch, the pump element can condition. Alternatively, a suitable rapid start/
be readily removed from the caisson in one piece standby pumpset is necessary.
following removal of the electric motor.
The need to provide adequate NPSH margins,
A more compact layout can be achieved with the taking into account that the pumps are supplied
vertical pumps which take less space than the hori- from a direct contact heater (de-aerator), which can
zontal designs. be subject to pressure decay following a reduction
in turbine load.
To ensure that the extraction pumps have stable There should be at least two pumpsets capable of
head/flow characteristics and are capable of operating starting the unit. If a turbine drive is to fulfil this
in parallel over the complete operating range, the function, then a steam supply independent of the
pumps are now designed so that the generated head main boiler (i.e., an auxiliary boiler) is required.
rises by at least 1% for every 15% reduction in
flowrate between the rated duty point and 25% rated If two or more pumps are required to operate
flowrate. in parallel, then the pumpsets should be able to
Extraction pumps on CEGB stations have been accommodate run-out duties following loss of an
operated on either free suction or recirculation control. operating pump.
402
Boiler feed pumps

MOTOR STOOL

CONE RING COUPLING LOCKNUT


FLEXIBLE COUPLING
COUPLING KEY

DETACHABLE PLATE VERTICAL THRUST AND


JOURNAL GUIDE BEARING

SPINDLE SEALING
ARRANGMENTAND
PUMP DELIVERY- LEAK-OFF SYSTEM

C_OF DELIVERY

MOTOR STOOL VENT PIPE


DRAIN
CAISSON

SOLEPLATE

TAPERED
PIPE

C_ OF SUCTION
DELIVERY
BODY

BUSH

DELIVERY
IMPELLER

TAPERED
DISTANCE PIECE

DISTANCE
PIECE

NUT

STUD

STEADY PINS

SUCTION BODY

BELL MOUTH

LOOSE BELLMOUTH

BEARING BUSH

FIG. 4.54 Vertical caisson extraction pump

403
Condensers, pumps and cooling water plant Chapter 4

The provision of sufficient pumping capacity to were typically as shown in Fig 4.55; they included a
meet flow requirements under all operational cir- long flexible shaft with about six stages and the resi-
cumstances. It is normal practice to include a flow dual thrust from the impellers taken by a conven-
margin to accommodate additional demand by the tional balance disc arrangement. The bearings were
turbine above its design rating during transient mounted on separate pedestals which had to be re-
flow disturbances. A margin on pump generated moved before the main pump internals could be with-
head is also appropriate to cover for deterioration drawn. Glands were of the fixed labyrinth or floating
resulting from internal wear during periods between ring type, and the main bolted casing joint was sub-
overhaul. In the interests of keeping pumpset sizes jected to full discharge pressure.
and powers to a reasonable minimum, consistent with With these designs, loss of water or reduction in
maintaining the pump best efficiency close to the NPSH (even momentarily) is likely to lead to metallic
duty point operation, these margins have been contact resulting in pump seizure. The bolted casing
optimised as 5% on flow and 3% on generated joint arrangement then results in a substantial outage
head. for replacement of the pump internals.
To overcome the shortcomings of the multi-stage
flexible shaft design of feed pump, and with an
awareness of overall economic considerations, a new
14.2 Feed pump developments concept was developed with the emphasis on achieving
Boiler feed pumps installed on early 500 MW units maximum availability coupled with a design life of

DELIVERY

ANTI SWIRL VANE

GRAYLOC SEALING RING SUCTION STOPPER ASSEMBLY

COVER PLATE

ROTATION

1st STAGE IMPELLER

DISTANCE RING
(MIDDLE BODY)
MECHANICAL SEAL

WATER COOLED
SUPPORT PAD

BEARING HOUSING

BALANCE VALVE COVER

CARTRIDGE ALIGNMENT PAD

COOLING WATER CONNECTIONS

FIG. 4.55 500 MW main boiler feed pump

404
Boiler feed pumps

at least 45 000 h for all components. The essential r/min) to achieve the necessary high head per stage.
features were a rugged high speed unit capable of Slow speed booster pumps are therefore required to
surviving dry running and thermal shock operation provide sufficient NPSH to limit cavitation problems
without damage, and having a cartridge construction on the main pump.
that permitted rapid replacement of the complete With regard to NPSH, a conservative design ap-
rotor/stator assembly. proach was adopted. De-aerator storage tank height
A dry running capability, which forms part of the and suction pipework layout were arranged to pro-
design specification, means that the pump must be vide a substantial margin of NPSH over the measured
capable of accepting either of the following conditions pump 3% head drop NPSH, even under the worst
without damage: transient situation.

A transient reduction in suction pressure for as


long as a pump continues to deliver and generate
a substantial head. After this the pump is expected 14.3 Advanced class feed pump construction
to accept, without distress, the re-establishment The pump casing consists of a forged steel barrel to
of normal suction conditions with no necessity for which are welded the suction and discharge branches.
pump shutdown. Extensive areas have stainless steel cladding to give
protection against erosion. Supporting feet are ar-
A complete loss of water due to incidents such ranged at the centreline to give positive restraint to
as the inadvertent complete closure of the suction movement upwards and downwards and yet allow-
valve. In this extreme case, it is recognised that ing for free thermal expansion. Sliding keys control
the pump should be shut down and only restarted thermal movement and maintain alignment with the
after it has been fully reprimed. drive.
The pumps have all their bearings, both thrust
and journal, in housings supported off the pump
These requirements have been met by the develop- casing or internal cartridge. This makes the pump
ment of an advanced class pump which incorporates more immune to the effects of pipework loads and
the following basic features: minimises the effects of shaft misalignment.
The 'cartridge' inner pump assembly, complete with
A substantially stiffened shaft with the number of integral bearings, is designed so that it can readily
stages reduced, preferably to two but not more be transported to a suitable maintenance area as a
than three, giving improved rotor rigidity and lower package unit. The cartridge components are pre-
shaft deflections. assembled on a manufacturing jig so that no subse-
quent adjustment is necessary to ensure component
Internal clearances enlarged to ensure that the concentricity, and minimal adjustment is required to
pump is capable of dry running without damage. achieve the necessary degree of coupling alignment
after the cartridge is installed in the pump barrel.
Replacement of the heavy externally-bolted dis- On insertion into the barrel, the suction and dis-
charge cover by an internal self-sealing high pressure charge ends are slid apart and located at their res-
joint system. pective ends of the barrel. Three joints are made
during this operation; the suction ring section and
Use of a balance drum to oppose the axial hydrau- main cover joints. Although different designs of
lic thrust, with residual unbalance being carried by pump have been adopted (Figs 4.56 and 4.57), car-
an external oil-lubricated thrust bearing. tridge replacement follows the same strict methodical
procedure.
Cartridge' design, permitting rapid replacement of To ensure rapid cartridge changeover, the normally
the pump internals with a spare element (an alter- heavy externally-bolted discharge cover arrangement
native design was also developed using the concept has been replaced by an internal self-sealing high
of removal and replacement of the complete pump pressure joint system. Rapid replacement of the car-
unit, having a special bolted arrangement on the tridge necessitates the use of specially designed with-
adjacent suction and discharge pipework). drawal gear as illustrated in Fig 4.58.
The impellers are of high quality precision-cast
stainless steel, with the castings subject to extensive
The result of the stiff shaft is that, even with the radiographie inspection and stringent dimensional
maximum permitted worn internal clearances, the control to ensure repeatable cavitation performance.
rotor transverse critical speeds in water are well above The first stage impellers are designed to have a ca-
the operating speed range. This permits relatively high vitation life of 45 000 hours when operated in the
rotational speeds (typically in the range 6500-8700 range 80-100% of the rated flow.
405
406
SEAL CLAMP
RING RING

SHEAR
RING

AXIAL
POSITION
INDICATOR
COILS
Condensers, pumps and cooling water plant

DISCHARGE
COVER

FIG. 4.56 Advanced class feed pump (Drax Completion)


Chapter 4
Boiler feed pumps

REAR
COVER

SUCTION
INLET T F|RS

\ ? FRONT GU.DEWHEEL

SEAL HOUSING AND


GLAND SLEEVE

INNER RING
BELLOWS
REAR COVER
CLAMP
BAFFLE PLATE

OIL DRAIN
CONNECTION

WATER DRAIN
CONNECTION

THRUST
PAD

PUMP FOOT
OIL
OUTLET

BALANCE
GLAND SEAL' BUSH
PLATE LAST
GUIDEWHEEL

FIG. 4.57 Advanced class feed pump (Heysham 2)

Diffusers can be either axial or radial; both ar- to be returned to service and full generation to be
rangements have been successfully used on advanced restored, as soon as possible.
class feed pumps. The inclusion of axial diffusers
avoids the generation of large pressure pulses between
the impeller and diffuser blades, which on these high
head per stage machines could constitute a fatigue 14.4 Axial thrust
hazard. Alternatively, radial diffusers result in better The balance drum and external thrust bearing has
head/flow stability characteristics. They also give a proven to be a more reliable device than the balance
slightly higher peak efficiency than the axial design, disc, and this has led to its widespread adoption on
although this can be masked by the effects of gland large boiler feed pumps.
leakage losses. Normal practice is to react around 95 % of the
Forced cooling of feed pumps has been provided impeller axial load by the balance drum, leaving the
on stations where there is not full standby capacity, remaining 5% to be carried by the double-acting
and where power generation is lost following the tilting pad type oil-lubricated thrust bearing. This ar-
outage of the main 100% feed pump. Forced cool- rangement gives the essential security against vapor-
ing reduces pump downtime and enables the machine isation or foreign matter compared with the balance
407
Condensers, pumps and cooling water plant Chapter 4

SWING JIB-.

WITHDRAWAL TROLLEY

HYDRAULIC RAM WITH EXTENSION

HYDRAULIC RAM

HYDRAULIC PUMPS

FIG. 4.58 Cartridge withdrawal equipment

disc device. The preferred practice is to ensure that Thrust bearings (Fig 4.59) can be of the 'flooded'
the residual thrust is unidirectional to avoid any pos- or 'directed' lubrication type. For high speed appli-
sibility of axial shuttling. This is essential for pumps cations, the directed arrangement offers considerable
with mechanical seals to prevent possible over/under power savings by significantly reducing parasitic churn-
loading of the seal faces. ing losses. In addition, the directed arrangement pro-
Theoretical formulae have been derived to calcu- vides an increased oil wedge thickness, which leads to
late the range of the individual components of the greater operational margins against bearing failure.
axial thrust over the complete flow range. Although
there may not be any large errors in the calculation
of these individual thrusts, care is required by the
designer to ensure that there is not an exaggerated 14.5 Gland sealing
overall error which could lead to an overloading of Glands on early advanced class feed pumps were of
the thrust assembly. For all new designs, the CEGB the labyrinth type, with fixed bushes and leak-in/
requires axial thrust tests to confirm that the thrust leak-out connections (Fig 4.60). Consideration was
bearing catalogue rating is never exceeded over the given to the use of floating ring glands as these
complete range of the pump operating envelope, tak- would be more efficient than the fixed bush type
ing into account both the effects of pump overspeed when new. They were, however, rejected as being
and internal wear. Measurements are taken using a vulnerable to loss of water supply, they would not
simple load cell attached to the pad carrier within the comply with the specified dry running requirement.
thrust assembly. Under dry running conditions, the fixed bushes op-
408
Boiler feed pumps

SHAFT NUT THRUST PAD

PAD STOP THRUST COLLAR

JOURNAL BEARING

THRUST PAD

JOINT RING

END COVER

LOCKING PLATE

OIL THROWER

OIL OUTLET

FIG. 4.59 Arrangement of thrust and journal bearing

erate satisfactorily without an external supply of labyrinth seals can be provided in one of two ways.
sealing water, and no significant erosion damage will In the first, feedwater is tapped from the discharge
occur when accepting flashing flow for short periods of the suction stage pumps and passed through a
of time. cooler, where it is cooled by condensate. In the sec-
A secure supply of gland injection water for the ond, the low temperature gland injection water is
409
Condensers, pumps and cooling water plant Chapter 4

STANDSTILL SEAL
COVER

INLET GUIDE

INTERMEDIATE
PLATE

HYDRO GLAND
BUSH

WATER THROWER

LOCK-NUT-

STANDSTILL SEAL

FIG. 4.60 Labyrinth gland and standstill seal

taken from the condenser extraction pump discharge of these long slender shaft designs, in addition to
and fed direct to the feed pump glands. The injection minimising running and standby leakage. As a result
pressure would be controlled at approximately one of the early satisfactory performance of mechanical
bar above the gland unloading pressure. To cater for seals, there has been a progressive development of
start-up conditions and interruptions in the supply mechanical seal systems up to the high speed vapour
from the condenser extraction pump, a back-up sup- lock requirements of the advanced class feed pumps.
ply is available from a standby injection pump which Recent CEGB policy for new stations has been to
takes its source of water from the reserve feedwater install mechanical seals on the starting and standby
tanks. feed pumps, while retaining labyrinth arrangements
Since the leakages through labyrinth seals are on the main feed pumps. For a 3 x 50% pump ar-
relatively high, it can be desirable to reduce the rangement, mechanical seals are accepted where it
leakage flow when the pumps are stationary. This can be demonstrated that the seals have a design life
is particularly relevant to standby feed pumps. There- of at least 15 000 h.
fore standby seals are included which operate when A typical high duty mechanical seal arrangement
the pumps come to rest. The standby seals consist of is shown in Fig 4.61. The 'cartridge' design enables
three segments which are held together on the shaft it to be assembled as a complete unit into the pump,
to form a closed seal when the pump is stationary. thus minimising installation errors. A pumping ring
They are opened by centrifugal force at a predeter- is incorporated into the rotating part of the seal,
mined speed to minimise rubbing contact during pump which circulates water around a closed loop, through
operation. For base-load feed pumps, it is possible a heat exchanger and returning to the seal face area.
to replace the centrifugal seal arrangement with an This recirculation enables the correct seal face tem-
extended labyrinth. This reduces on-load leakage losses peratures and stable face conditions to be achieved.
at the expense of higher leakage while the pump is The heat exchangers are normally positioned above
stationary. A labyrinth bush outboard of the injection the seals in order to obtain a good thermal syphon
point controls leakage of water to a clean drains effect during hot standby conditions. An inner cool-
vessel, from where it can be recovered to the system. ing jacket is also included to reduce the heat flow
Problems with labyrinth glands on some earlier into the seal chamber. In certain designs, the effec-
feed pump designs led to a programme of conversion tiveness of this inner barrier eliminates the need to
to mechanical seals. These reduced the risk of tem- thermal syphoning. A simple magnetic separator is
perature stratification problems in the labyrinth area also installed into the seal pumping loop to ensure
410
Boiler feed pumps

LOCK PIN

SEAL FLANGE
GASKET

SHAFT SLEEVE

O' RING

' RING SEAL FLANGE


BUSHING

DRIVE COLLAR

SET SCREW

SHAFT SLEEVE
GASKET

ROTATING FACE SHAFT

STATIONARY FACE

LOCK RING COIL SPRING

SEAL FLANGE SPRING HOLDER


GASKET

INNER SEAL BACK-UP


FLANGE RING
OUTER SEAL
FLANGE

FIG. 4.61 Mechanical seal

that any magnetic particles, which could abrade the feed pumps has resulted in the need for an NPSH
seal faces, are removed. well in excess of that available, even from high level
The face materials used on early feed pump seals de-aerators. This can be provided by slow speed boost-
were tungsten carbide rotating against a stationary er pumps, driven either separately or in tandem with
carbon face. While this combination proved very sat- the pressure stage pump.
isfactory on low speed applications, on certain high Separately-driven booster pumps necessitate the
duty seals a selective corrosion/erosion process was use of a common discharge manifold to ensure that
found to occur on the tungsten carbide binder ma- at all times the pressure stage pumps, with their
terial. This process can lead to excessive face wear independent prime mover, have sufficient NPSH to
and premature failure. The reliability of feed pump prevent vapour locking in the event of failure of
seals was improved by the introduction of silicon one of the working booster pumps. This arrangement
carbide in place of tungsten carbide. Since silicon (Fig 4.62) also requires any stationary booster pumps
carbide is chemically inert against conventional feed- to be protected with non-return valves, and the pres-
water additives, use of this material eliminates this sure stage pump leak-off valves to be closed when the
potential failure mode. pump is standing to prevent recirculation back to the
de-aerator.
Tandem sets (Fig 4.63) require less complex pipe-
work arrangements, less complex feed systems and
14.6 Pump layout and drive take up less turbine hall space. Being dependent on
The increasing head per stage in the high head boiler a single drive, they are also more reliable than the
411
Condensers, pumps and cooling water plant Chapter 4

TO
DEAERATOR

PRESSURE
REDUCER

Q LEAK OFF
VALVES

-Oh
MAIN PRESSURE
STAGE PUMP

D W-

D
50% STARTING
AND STANDBY PUMPS

W-

FIG. 4.62 Feed pump arrangement with separately-driven feed suction pumps

arrangement with separately-driven booster and pres- In assessing the number and capacity of pumps to
sure stage pumps. be employed, normal CEGB practice on fossil-fired
For part-load operation, a fixed-speed booster units has been to ensure that failure of a single pump
pump is preferred as it enables the NPSH to be train must not impair the start-up of a unit or affect
maintained as the load is reduced. Where pumps are output. This has led to the installation on most sta-
to be capable of operation well in excess of the rated tions of a 100% turbine-driven set, plus 2 x 50%
duty, variable-speed booster pump would provide motor-driven sets.
better cover for the pressure stage pump, although Back pressure turbines have been standard on
this may require some increase in the NPSH available CEGB stations for feed pumping duties and these
to the booster pump itself. have proved very reliable (see Chapter 1 for tech-
The choice of unit often dictates the basic type nical description). Back pressure turbines permit the
of drive to be employed. On 660 MW units, be- feed pumps to be driven at speeds in excess of
cause of start-up problems, motor drives (even when 7000 r/min. The alternative condensing steam turbine
supplied from an 11 kV supply) are unacceptable drives, while offering a potential improvement in
on technical grounds for pump trains substantially heat rate, are limited to less than 6000 r/min to
greater than 60% MCR duty. Thus any 100% pump prevent last-stage blade erosion. Their use with two-
group has to be driven by a steam turbine. stage advanced class feed pumps would therefore
412
Boiler feed pumps

FIG. 4.63 Typical tandem feed pump arrangement

necessitate the additional complication of a step-up Better speed control resolution.


gearbox.
The electric motor drive is simpler than the steam Greater motor reliability by the elimination of the
turbine drive from both physical and operational sliprings, brushgear and the liquid resistance con-
requirements. The pump can be used during any phase troller.
of operation and the control arrangements are more
Elimination of frequent outages for brushgear
straightforward. Initially, slipring induction motors
maintenance.
with liquid resistance controllers were used to drive
50% feed pumps on starting/standby duties. In ad-
dition to providing variable speed, the resistance When using the fluid coupling, the power developed
controller on these units also limits the starting cur- by the driving motor is transmitted by the kinetic
rent, which has a direct effect on starting torque energy of the oil flowing between the input impeller
and run-up time. Slipring induction motor drives and the output turbine of the coupling. The output
have now been replaced by the fixed speed motor/ speed is controlled by the operation of an adjustable
fluid coupling arrangement which has the following scoop tube, which varies the quantity of oil transmit-
advantages: ting the torque between the input and output elements.

413
Condensers, pumps and cooling water plant Chapter 4

The overall unit (Fig 4.64) comprises, within the flow to the boiler and the leak-off flow. Also, high
casing, a fluid coupling and step-up gears. For the pressure differential tappings are not required in this
high output speeds required on advanced class pumps, position.
step-up gearing is included on both the input and Electrically-operated valve actuators have been used
output sides of the coupling. on many stations but as failure of the electrical sup-
The fluid coupling incorporates two separate oil plies would render them inoperative and pump pro-
systems drawing from a common sump. One system tection would be lost, the electrical supply for each
provides lubricating oil to the fluid coupling and to valve is taken from separate station switchboards to
the bearings of the booster and pressure stage pumps improve security. In recent years, improvements in
and the driving motor. The oil is drawn from the electropneumatic systems have resulted in a preference
sump by a gear-driven pump with a motor-driven for this fail-safe method of actuation, where the
pump provided for start-up and standby duties. In valves open on loss of air supply. A further advantage
the second system, oil used as the working fluid is of the pneumatic system is that the speed of opera-
circulated by the dynamic head generated at the scoop tion is readily adjustable.
tip in a closed loop. Make-up for this closed loop is To provide maximum protection to the pump and
provided by a gear-driven centrifugal pump during piping system under all foreseen operating conditions,
normal operation and a motor-driven gear type pump the valves must be capable of opening rapidly. On
for starting and standby duties. Both circuits include the other hand, very fast opening can lead to un-
oil coolers. acceptable shock loadings on the feed system. From
experience, valve opening times of up to 15 s have
been found acceptable, dependent on the feed system
layout. Consequently, valve actuators need to include
14.7 Light load protection a facility for varying and resetting the opening/closing
The temperature rise across a pump is caused by times after installation, to suit local conditions and
two separate phenomena; the isentropic compression operating practices.
temperature rise and the rise generated by the in- To permit on-load maintenance of the leak-off
efficiency of the pump. As throughput diminishes, system, sufficient manual isolating valves are included
efficiency falls and the temperature rises. If a pump and any parts subject to in-service wear, for example,
runs for any length of time without an adequate leak-off valve seats, are designed to be readily re-
flow of water passing through it, overheating will placeable without cutting or re welding the pipework.
occur which can lead to vapour locking. To prevent All isolating valves should have a locking facility to
this, a leak-off system is provided which opens auto- avoid malfunction.
matically at the minimum safe flow and allows the
pump to discharge to the de-aerator. Pressure in the
leak-off piping is broken down through a pressure
reducing vessel, which consists of a series of orifice 14.8 Testing
plates, and finally with an orifice plate positioned at CEGB specifications require that the 100% main
the inlet to the de-aerator and sized to avoid flashing boiler feed pump is tested at a load corresponding
in the leak-off pipework. to turbine MCR to prove conformity with the guar-
Low throughput can also lead to random pressure antee, and also at part-load to confirm that the
pulsations being generated by the pump. These can pump performance characteristics are satisfactory.
excite low frequency resonances in the adjacent feed Site tests, however, are of necessity late in the station
system pipework, leading to unacceptable pipework construction programme, so that any shortfalls in
vibration. The minimum leak-off flow is therefore pump performance found at this stage would cause
chosen to minimise the risk of these effects and, disproportionately large disturbances in the overall
hence, to protect both the pump and the feed system. construction target. Alternative works testing is there-
Experience with high speed feed pumps indicates that fore required to demonstrate that the pump perform-
the leak-off quantity should be set to at least 25% ance is acceptable before any systematic site testing,
of pump best efficiency flow to avoid any pipework which is interrelated with the station as a whole, is
vibration problems. commenced.
The configuration commonly used on CEGB stations For steam turbine driven pumps, it is not practical
(Fig 4.62) consists of 2 x 100% parallel slide leak-off to specify full works testing and instead part-speed
valves, arranged in parallel, with a separate pressure interim hydraulic performance tests are carried out at
reducing vessel downstream of the valves. The ini- the manufacturer's works to demonstrate that the
tiation signal for leak-off valve operation is taken pumps have reasonable prospects of achieving their
from an orifice plate located in either the suction specified requirements on site in terms of rated duty
or discharge pipework. Installation in the suction and hydraulic characteristics. These interim tests are
pipework is preferred since this location senses total followed by full-load acceptance tests on site with the
pump throughput, i.e., the summation of forward plant in service.
414
BEARING
HOUSING

RUNNER
OUTPUT ASSEMBLY
SCOOP
ADJUSTMENT IMPELLER
SPEED CONTROL COVER LIFTING LUG
INPUT ASSEMBLY

VIEW ON ARROW'X OUTPUT SHAFT


STANDBY OIL
OIL LEVEL GAUGE PUMP FILTER

OIL FILLER CAP

MOTOR DRIVEN
STANDBY OIL PUMP

MAIN OIL
PUMP FILTER SCOOP
UNIT LIFITNG LUG

- _ - SCOOP CHAMBER
ff/yS OIL OUTLET
Uj TO COOLER
ALIGNMENT
JACKING SCREW

LUBRICATING
OIL FILTER

OIL SUMP LOW LEVEL


WARNING SWITCH

OIL SUMP TANK


OIL OUTLET
TO COOLER
ALIGNMENT
JACKING SCREW

415
Boiler feed pumps

FIG. 4.64 Fluid coupling construction


Condensers, pumps and cooling water plant Chapter 4

Manufacturers works test facilities are generally design, and a reduction in internal leakage losses.
suitable for full-load acceptance testing of electrically- The adoption of a 3 x 50% arrangement, with
driven feed pumps. The suction and pressure stage booster pumps driven in tandem to provide the
pumps are first tested individually to confirm the necessary NPSH, is in line with overseas practice. The
head/efficiency guarantees, the 3% head drop cavita- use of fixed-speed motors and fluid couplings is well
tion performance guarantees, and the shape of their within the experience of plant already operating on
hydraulic characteristics. These are followed by testing starting/standby duties on CEGB fossil-fired stations.
of the complete pumpset, including the motor and Double-entry feed pumps (Fig 4.65) can retain all
gearbox/fluid coupling assembly. In each case, hydraulic the features of advanced class construction, i.e., a
performance tests are undertaken using the method stiff shaft, Cartridge' design, with vapour lock and
of measurement laid down in BS5316 [21]. thermal shock capability. The provision of mechani-
Hydraulic output control tests are included on cal seals is intended to minimise leakage in the
electrically-driven pumpsets to determine the thres- running and shutdown modes without prejudicing
hold response, repeatability and input/output char- pumpset reliability. The seals themselves are designed
acteristics of the fluid coupling arrangement. For to have a minimum life of 15 000 h between over-
starting/standby feed pumps, tests may also be re- haul. A Cartridge' seal assembly reduces downtime
quired to demonstrate compliance with run-up time for any seal maintenance and minimises installation
guarantees. These would include the time from test type faults.
to full-speed and also acceleration from part-speed To prevent any axial shuttling of the shaft, which
conditions. could damage the mechanical seals, a deliberate im-
For new pump designs, supporting tests are required peller wear-ring diameter differential is introduced
to demonstrate that the plant offered will satisfactorily to create a known unbalanced unidirectional thrust
accommodate any possible thermal shock, vapour lock which is taken by an external thrust bearing. To cater
or axial thrust condition that can arise during op- for radial loadings acting on the pump, the casing
eration. In addition, a visual cavitation test is carried designs can either include radial diffusers or are of
out on the pressure stage first-stage impeller to de- the double volute type.
monstrate compliance with NPSH visual cavitation
guarantees.
The thermodynamic method of determining pump
efficiency has now been successfully applied to CEGB 14.10 Future trends
feed pumps. This method compares the isentropic The CEGB has placed great emphasis in recent years
enthalpy rise across the pump with the measured on design to achieve maximum availability. This has
enthalpy rise, and has the advantage over the con- led to the provision of robust advanced class pumps
ventional torquemeter method in that it is suitable with 10097 standby capacity and substantial spares
for continuous on-line monitoring of plant perform- provisions. The alternative overseas policy, by com-
ance. Accurate measurements of the temperature and parison, has tended towards low pump costs and a
pressure parameters at pump suction and discharge premium on high hydraulic efficiency. This has
are required, and suitable equipment is now installed necessitated very tight internal running clearances and
on new plant. In calculating the thermodynamic resulted in pumps having less margin against rubbing
efficiency, losses resulting from gland sealing, balance and seizure than the advanced class design, and an
water, bearing friction and heat transfer have all to inability to withstand vapour lock or thermal transient
be taken into account. These secondary losses can conditions.
be derived at the initial commissioning test by com- A comparison of operating experience has demon-
paring the conventional torquemeter acceptance test strated the effectiveness of providing rugged reliable
results with those obtained from the thermodynamic feed pumps and highlighted the strong financial in-
method. centives of installing spare capacity to maximise feed
pump availability. It is now evident that overseas
ultilities are moving towards CEGB practice.
When determining standby requirements, the cur-
14.9 PWR feed pumpsets rent trend is to provide 3 x 50% pumpsets. This
The feed pump generated head requirement on a arrangement meets the basic objectives listed in the
water reactor unit is in the region of 900 m. This is introduction to this section and achieves them on
considerably lower than that necessary on a fossil- larger fossil-fired plant without any excessive extra-
fired station and allows the use of a single-stage polations of existing technology, by taking maximum
double-entry pump. Changing to the simpler double- advantage of UK manufacturer's international ex-
entry design, eliminates the need for any balance perience to produce reliable plant.
drum to react against large impeller loadings. This A 3 x 507o configuration with quick-start variable-
leads to an improvement in pump hydraulic efficien- speed motor-driven units represents a low capital and
cy compared with the equivalent multi-stage pump through life cost option for a practical plant arrange-
416
Miscellaneous pumps

THRUST
BEARING

SHAFT
SLEEVE

FIG. 4.65 PWR feed pump

ment. It also provides a simple layout with complete very tight control of axial tolerance build-up on all
interchangeability. The advantages of this form of components relating to the self-seal joint, which is
drive compared with the fixed speed motor/fluid necessary to achieve complete interchangeability of
coupling package or the turbine drive options, are cartridges and barrels, is relaxed. There are also ma-
fully discussed in Chapter 2. jor cost savings to be obtained from the simpler bolted
In assessing feed pump designs for any new gen- discharge cover incorporating spiral-wound sealing
eration of larger fossil-fired units, it is envisaged gaskets.
that feed pumps incorporating advanced class con-
cepts will be continued, but with a limitation on
impeller speed to minimise risks of impeller erosion
during off-duty operating conditions. A likely eco- 15 Miscellaneous pumps
nomic solution is a three-stage machine with booster
pump, resulting in a speed where both condensing
steam turbines and inverter-fed variable-speed motor
drives become viable options. By reverting to a three- 15.1 Service water pumps
stage design (Fig 4.66) and decreasing the head per In every power station, there are a large number of
stage, there are further benefits to be gained in terms pumps supplying service water to main plant items
of a relaxation of pumpset NPSH requirements. This and as part of auxiliary systems, e.g., water treatment
can lead to a drop in the necessary height of the plant. These pumps can be classified under two se-
de-aerator with consequent reductions in station civil parate categories, pipeline-mounted pumps and sump
costs. pumps.
The development of lightweight hydraulic ten- Pipeline-mounted pumps up to around 0.1 m 3 /s
sioning gear for high tensile bolting permits the re- and 160 m head can be supplied as either horizontal
introduction of bolted cover joints in place of the end suction or vertical in-line designs. In both in-
self-sealing joint arrangements, without significantly stances interchangeability is important and pumps are
affecting the time to change cartridges. An additional manufactured to standard dimensions. End suction
benefit from the production viewpoint is that the designs are covered in BS5257 [22]. These pumps
417
Condensers, pumps and cooling water plant Chapter 4

PULL-UP RING
SUCTION CLOSURE
BUILD RING

MAIN COVER
JOINT

SHAFT

SUCTION
BRANCH

FIG. 4.66 Modern feed pump construction

should include a back pull-out feature which greatly casing type as described in Section 12 of this chapter.
assists maintenance activities with no disturbance of In the past, sump pumps have been of a design in
pipework during dismantling. The use of spacer coupl- which the pump casing was suspended into the sump
ings eliminates the need for removal of the motor from columns, the impeller being driven from a high
during work on the pump. level motor through a long multi-bearing shaft sys-
Vertical in-line pumps are detailed in BS4082 [23]. tem. This design caused severe problems when pump
All pumpsets in this range are close-coupled, with failure occurred, particularly that of dismantling,
the pump impeller mounted directly onto an extended which is difficult and often very complicated.
motor shaft (Fig 4.67). This arrangement requires a Increasing use is now being made of submersible
special motor with a non-standard shaft and stronger sump pumps (Fig 4.68), particularly for low and me-
bearings to carry the pump hydraulic forces. Although dium power outputs. Ease of withdrawal and replace-
there is an initial cost penalty compared with the ment are good and reliability excellent, considering
equivalent end suction designs, the vertical pumpsets the arduous conditions often associated with sump
take up less floor space and experience indicates drainage work.
they are more reliable and require significantly less
maintenance. This is attributed to several factors,
including the elimination of coupling alignment pro-
blems which can result in a reduced seal life. 15.2 Chemical injection pumps
Larger pipeline pumps are of the horizontal split- These are used to pump a measured quantity of
418
Miscellaneous pumps

MECHANICAL SEAL

COMMON
MOTOR/PUMP SHAFT

RENEWABLE
SHAFT SLEEVE

RENEWABLE
WEARING RINGS

FIG. 4.67 Vertical in-line pump construction

chemical into the boiler feed water. The pump must use of an air vessel.
retain repeatable accuracy over long periods and po-
sitive displacement designs are used for this pur-
pose, built with suitable corrosion-resistant materials. 15.3 Fire pumps
The principle of operation of a normal metering Fire pumps are of simple robust construction to
pump is that a plunger displaces a certain amount ensure high reliability when called upon to operate
of liquid with each stroke. Liquid is drawn into the in an emergency. The pumpsets are usually self-
pump head through a non-return valve and displaced contained packages driven by diesel engines with the
out of another non-return valve. The gear drawing start-up motors supplied from a local battery pack.
the plunger has a mechanism for altering the stroke Water for engine cooling is taken from the pump
length to effect a variation in pump delivery, there- discharge. Shaft leakage is controlled by traditional
by allowing close control of the amount of chemical soft-packed glands rather than the more sophisticated
injected. The positive displacement action results in mechanical seals. This eliminates any risk of enforced
a series of pulsations of flow rather than a steady shutdown which could arise from failure of a me-
feed. This can be smoothed out, if necessary, by the chanical seal.

419
Condensers, pumps and cooling water plant Chapter 4

CAST IRON STATOR


HOUSING

CAST IRON
PUMP HOUSING

IMPELLER

FIG. 4.68 Submersible pump construction

16 References [7] Steel, T. F. (CEGB): 'The Thermal Design of Condensers


[1] CEGB:'Chemical control of boiler feedwater, boiler water and from the users point of view'; taken from a report of a meet-
saturated steam for drum-type and once-through boilers': Genera- ing at NEL on the Thermal Design of Condensers: January
tion operation memorandum (GOM)72 Issue 4: 1975 1966
[2] Popplewell and Bates: 'Corrosion Performance of some Copper [8] International Symposium on Condensers, Theory and Practice:
Alloy Condenser Tube Materials in Ammoniated Condensate': UMIST Manchester: March 1983.
National Association of Corrosion Engineers, Paper 102, Cor- [9] BS4360: Specification for Weldable Structural Steels: 1972
rosion: 1974
[10] BS1501: Specification for steels for fired and unfired pressure
[3] 'Titanium Information Bulletin': Imperial Metal Industries vessels, Part 1 , Carbon and Carbon Manganese Steels: 1964
(Kynoch) Ltd.: 1974
[11] BS1500 (Withdrawn), now BS5500: Specification for Unfired
[4] Hanson, C. F.: 'Materials in Power Plant': Institute of Fusion Welded Pressure Vessels: 1976
Metallurgists, 98-103: April 1975
[12] BS1515 (withdrawn), now BS5500: Specification for Unfired
[5] 'Standards for Steam Surface Condensers': The Heat Exchanger Fusion Welded Pressure Vessels: 1976
Institute (HEI)
[13] Tubular Exchanger Manufacturers Association (TEMA) Stand-
[6] 'Publication on the recommended practise for the design of ards: Fourth Edition 1959, Fifth Edition 1968
surface-type steam condensing plant': The British Electrical
and Allied Manufacturers Association (BEAMA) [14] American Society of Mechanical Engineers (ASME) Boiler

420
References

and Pressure Vessel Code, Section 8, Divisions 1 and 2 of Specific Speed': Trans ASME: 1943
[15] CEGB: Performance of Surface-type Steam Condensers: Site [20] Grist, E.: 'Nett positive suction head requirements for avoid-
Test Code No. 3: 1981 ance of unacceptable cavitation erosion in centrifugal pumps':
[16] BS752: 'Test Code for Acceptance of Steam Turbines': 1974 IMechE C163: 1974

[17] CEGB: 'Steam Turbine-Generator Heat Rate Tests': Site Test [21] BS5316: 'Specification for Acceptance Tests for Centrifugal,
Code No. 2: 1978 Mixed Flow and Axial Pumps'
[18] American Society of Mechanical Engineers (ASME): 'Structural [22] BS5257: 'Specification for End-suction Centrifugal Pumps
Characteristics of Helical-Corrugated Heat Exchanger Tubes (16 bar)': 1975
by ASME': 1975 [23] BS4082: 'Specification for External Dimensions for Vertical
[19] Stepanoff, A. J.: 'Centrifugal Pump Performance as Function In-Line Centrifugal Pumps'

421
C H A P T E R 5

Hydraulic turbines

1 Definitions and concepts 3 Pumped-storage


1.1 Output 3.1 IFfestiniog power station
1.2 Specific speed 3.2 The reversible pump-turbine
1.3 Cavitation 3.3 IDinorwig power station
1.4 Running speed 3.3.1 The site
3.3.2 Runner submergence
2 Types of turbine 3.3.3 Operational requirements
3.3.4 Design life
2.1 The Pelton turbine
3.3.5 Machine layout
2.2 The Francis turbine
3.3.6 Valves
2.3 The Kaplan turbine
3.3.7 Testing
2.4 Tubular turbines
3.3.8 Some details of the Dinorwig pumped-storage station
2.4.1 The bulb turbine
2.4.2 The tube turbine 4 References
2.4.3 The rim generator design 5 Additional references

1 Definitions and concepts 1.2 Specific speed


Turbines vary widely in form and application. At
one extreme is the pure impulse machine (such as
the Pelton turbine), where the flow is generally low
1.1 Output but the head is large. Reaction turbines, in which
The water turbine is a device which transforms the the pressure drop takes place in both fixed and ro-
potential energy of a head of water into mechanical tating parts of the machine, cover the remaining
work in accordance with the relationship: types. These range from radial flow turbines (such
as the Francis turbine), for medium heads and flows,
P = 0.0098lq m (H - h)e to axial or propeller types (such as the Kaplan turbine)
for low head, high flow application such as rivers.
The turbine operating parameters of head, flow
where P = turbine output, kW
and rotational speed thus cover a wide range of com-
Qm = water flow rate, kg/s binations. In order to characterise them for com-
H = head difference between upper and tail parison and selection purposes, the concept of specific
water levels, m (see Fig 5.1) speed (ns ) is used. This is defined as:

h = hydraulic losses in pipes, m


= turbine efficiency nc = n P 0 5 / Hr l . 2 5
e

Note: The value (H - h) is referred to as the net where nP = turbine rotational speed, r/min
head.
This quantity is of great importance in turbine
The efficiency varies considerably between various selection as it is found that, by its use, many of the
turbine types and sizes but is in the range 0.9 to turbine's design and operating parameters can be
0.94 for large machines. correlated.

422
Types of turbine

pressure may be affected by suitable location of the


turbine in relation to the tailwater level. This height

y- T~
. UPPER WATER
LEVEL
is called the suction head (H s ) and is governed by the
relation H s < B - .

where B = difference in head between barometer


and water saturation vapour pressure, m
= Thoma's cavitation parameter

H s is positive when the tailwater level is below the


pump runner as shown in Fig 5.1 and negative when
above. An indication of how varies with n s is given
in Fig 5.3.
f TAIL WATER
From the information given in Figs 5.2 and 5.3 it
LEVEL is evident that for a given n s , the type of turbine
employed can be influenced by the ability of the ap-
plication to accommodate the suction head require-
ments. These influences may result from physical,
performance or cost considerations.

FIG. 5.1 Determination of available head 1.4 Running speed


This should be as high as possible for economical
turbine design and the generator is the dominant
influence in its selection. In the event of disconnec-
Figure 5.2 shows how specific speed and head are tion of electrical load, the acceleration of the com-
related for turbines of good efficiency. Superimposed plete turbine-generator rotor system is extremely rapid
is an indication of the range of application of each and stabilises at a maximum called the runaway speed.
of the types of turbine in use. It will be noted that, Since water hammer effects would, in most cases,
although there is a consistent trend in the application preclude shut-off of the water supply in sufficient
of these various types, there is considerable overlap. time to prevent the rotor reaching runaway, this speed
must therefore be acceptable to the generator which
is the most vulnerable component.
The ratio of runaway speed to normal speed varies
1.3 Cavitation between different turbine types as follows:
Cavitation is a very complicated physical phenome-
Reversible pump turbines: 1.35 to 1.45
non resulting from the water flow in the passages
of a turbine. It can occur whenever the local fluid Francis turbines: 1.7 to 2.0
pressure falls below a value corresponding to the
water vapour pressure at the prevailing temperature. Kaplan turbines: 2.0 to 2.2 (guide blades/runner
Under these conditions, boiling and steam bubble blades linked)
formation may occur. When these vapour bubbles 2.4 to 3.0 (guide blades inde-
have travelled to some other point in the fluid path pendent of runner
where the pressure is higher, violent collapse of the blades)
bubbles can take place. In such circumstances, severe
erosion and loss of metal in pump components and Hence the normal running speed of the turbine can
blades can occur, even though materials such as stain- be determined. The final turbine runaway speed is
less steel are employed which are resistant to cavita- usually determined from model tests.
tion attack. Cavitation is often responsible also for
noisy operation and vibration within the set, and
may be associated with a reduction of output and
efficiency. 2 Types of turbine
Avoidance of erosion damage is the aim of the
set design and may require restricting the range of
turbine operation. It is also important to ensure that 2.1 The Pelton turbine
the water pressure is sufficiently above saturation. The Pelton turbine (Fig 5.4) is generally used in
This is particularly so at the turbine outlet where applications where there is a relatively small rate-
the system pressure is lowest. Adjustment of this of-flow at a large head, typically above 250 m.

423
Hydraulic turbines Chapter 5

\ \

RANGE OF OPERATING
CONDITIONS FOR
FRANCIS AND KAPLAN
1 JET 4 JE"
TURBINES

PELTON TURBINES

PELTON TURBINES |
| FRANCIS TURBINES | \
KAPLAN AND PROPELLER TURBJNES |

n
10 50 100 200
500 u
1000

SPECIFIC SPEED n

PELTON TURBINES FRANCIS TURBINES KAPLAN AND PROPELLER TURBINES

\
1 JET 4 JET HIGH HEAD LOW HEAD

FIG. 5.2 Typical variation of specific speed with head for various turbine types

424
Types of turbine

CAVITATION
PARAMETERS
(
-

2_

1 0-

/ OPERATING RA MGE

0 1

0.02 -

0.01 100 200 1000


10
SPECIFIC SPEED

FIG. 5.3 Relationship between cavitation parameters and specific speed (n s )

It is an example of the pure impulse machine in shaped lobes; the central ridge which divides them
which the whole of the pressure head is converted splits the water jet and guides each of the two flows
to velocity in one or more nozzles in parallel, the through an angle of about 165. Ideally, for maxi-
jets from them impinging on buckets mounted on mum momentum transfer, the jet would be turned
the runner. Each bucket consists of a pair of spoon- 180 but this is precluded by the need to direct the

425
Hydraulic turbines Chapter 5

RUNNER

HIGH PRESSURE
WATER INLET

FIG. 5.4 Pelton wheel turbine

discharged water away from the runner and from disposed around the full circumference. The angle of
the path of the following bucket. For similar reasons, these vanes can be varied to control machine output
the central ridge is scalloped at the tip to give a clear and the water is uniformly distributed to them by a
path to the jet impinging on the working bucket. spiral casing.
Theoretically the maximum efficiency of this type After being directed onto the runner, the water
of turbine occurs when the bucket peripheral speed flows radially inwards, being turned by the runner
is one half that of the impinging jet. This is im- blades so that it discharges axially into the draft
practical, however, since it requires also that the tube. The purpose of the draft tube is to allow ef-
absolute velocity of the water leaving the bucket be ficient recovery of the velocity energy leaving the
zero and so the fluid would not clear the runner as turbine so that turbine efficiency is maximised. The
required. In practice, the ratio of blade-to-jet speed lies maximum efficiency of Francis turbines is 9 4 - 9 5 % .
between 0.46 and 0.47. Both horizontal and vertical shaft mounting can be
The efficiency of the Pelton turbine can be of the employed.
order of 92%. Control of end thrust is important. This derives
Water is directed onto the buckets by means of largely from the different pressures between the front
nozzles, the flow of water, and hence the output, being and rear shrouds and their respective casings. For the
controlled by a central needle, or spear, whose bulbed rear shroud, the source of pressurisation is solely the
head varies the flow area as it moves axially within high pressure at guide vane exit, whereas the front
the nozzle. One of several nozzles may be used de- shroud pressure is influenced by the guide vane exit
pending upon the flow and output of the machine. pressure at the outer diameter and by the draft tube
Rapid shutdown of the turbine, as would be re- pressure at the inner (or front shroud seal) diameter.
quired after loss of load from the driven machine, As well as this varying pressure distribution, the
cannot be effected by rapid closure of the spear front face of the impeller also experiences draft tube
due to the water hammer effects referred to earlier. pressure over the whole eye (i.e., the area of the
Shutdown is therefore effected by inserting into the impeller facing the draft tube).
jet either a cut-off to destroy its kinetic energy or a Since the areas involved are often large, the thrust
deflector to direct the jet away from the bucket. The resulting from even small pressure differences can be
jet of water is then shut off at suitably safe rate. considerable. It is usually reduced by control of the
pressures on the top and bottom shrouds, through
seals placed at the draft tube diameter and at a
suitable diameter on the rear shroud. The pressure
2.2 The Francis turbine inboard of this latter seal is maintained at draft
In this type of machine (Fig 5.5), the water is fed tube pressure by the use of balance pipes connecting
radially to the runner from guide vanes which are these two regions and/or holes drilled in the rear

426
Types of turbine

SPIRAL CASING

GUIDE VANE
OPERATING RAM

FRONT SHROUD &o . Jft^.t

FIG. 5.5 Francis turbine for low head applications

shroud. Complete elimination of the thrust is not tary types of balanced axial seal, in which a sealing
possible over the complete range of running conditions, ring is held by gravity against the conical face of a
however, and the balance is taken out on a thrust shaft collar. A small seepage of water is desirable for
bearing. On large machines, this is usually of the heat dissipation and the prevention of excessive wear
tilting pad variety. and this water is ducted away by the drain system.
On small machines, rolling bearings are often em- Machine output is controlled by the guide vanes,
ployed or may even be omitted altogether; in such a typical number of 24 being employed. They are dis-
cases the runner is overhung from the generator posed in a complete annulus surrounding the runner
bearings. On larger machines, and particularly on and are variable in angle. When fully closed, each
vertical shaft machines where bearing stability can vane touches its neighbour and effectively shuts off
be a problem, tilting pad journal bearings are often all flow to the runner. The degree of opening con-
employed. These are usually self-contained units with trols the quantity and direction of the water flow,
integral water cooled oil coolers, with oil circulation and hence the output. Very high loads can be ex-
maintained by the head generated from shaft rota- perienced by guide vanes, especially during transient
tion. Water lubrication with rubber or wooden bear- changes of load or hydraulic conditions, substantial
ing shells is also a feature. bearings are therefore provided on the spindles pro-
Sealing of the shaft, where it emerges from the top jecting from each side of the vane.
casing, must accommodate shaft axial movement. These Movement of the guide vanes is effected by a
seals are either conventional packed glands or proprie- crank attached to the end of one of the spindles,
427
Hydraulic turbines Chapter 5

the other end of the crank being located in a regu- 2.4 Tubular turbines
lating ring. Rotation of the regulating ring moves The Kaplan turbine has been widely used in river
the cranks, and hence the guide vanes, in synchronism and tidal power schemes, where a comparatively low
through the required angle. This rotation is pro- head of water is available. However, there are dis-
duced by one or, more usually, two hydraulic rams advantages:
or servomotors acting at each end of a diameter of
the regulating ring. Some form of slipping device is The submersion of the runner to avoid cavitation
normally incorporated in the crank/guide vane con- requires excavation for the draft tube, with con-
nection so that if a foreign body (such as a log) sequent increased civil costs.
gets jammed between two vanes, the remainder can
be closed normally. A warning device is often fitted Several changes of direction occur in the intake
to indicate that the slipping device has operated. and draft tube system which raises hydraulic losses.

This led to the development of the tubular turbine


in which the Kaplan type of runner is used, with
2.3 The Kaplan turbine fixed or variable blades, and installed with its axis
The essential feature of the Kaplan turbine (Fig 5.6) more or less horizontal. The water path thus de-
is that the water flow through the runner is in an viates from the axial direction as little as possible.
axial direction. The inlet spiral casing and the guide The efficiency of the tubular turbine is similar to
vanes are similar in layout and operation to the that of the Kaplan machine.
Francis turbine. After leaving the guide vanes, how- The principal subdivisions of the tubular machine
ever, the water turns into the axial direction before are as follows:
meeting the runner.
The runner resembles a ship's propeller whose The bulb turbine.
blades (typically four to six in number) are adjustable
in pitch to present the optimum angle of attack to The tube turbine.
the water flow. It is this ability to optimise the
runner performance that enables the Kaplan turbine The rim generator.
to maintain its efficiency over a much greater range
of speeds and power outputs than the Francis type.
A peak efficiency of about 94% is achieved in large 2.4.1 The bulb turbine
machines. This derives its name from the 'bulb' in the water
The blades are most conveniently adjusted by means path which contains the electrical generator (Fig 5.7).
of a lever arm within the hub. Axial movement of Normally the bulb is placed upstream of the turbine
a cross-head connecting with each of the lever arms and is supported in the water path by struts which,
rotates the blades. The servomotor system which op- since they are hollow and large enough to gain access
erates the cross-head can be within the hub or outside to the generator for maintenance, must be carefully
the machine, connecting with the cross-head by hy- designed if unnecessary hydraulic losses and flow
draulic means (Fig 5.6) or through a control rod disturbances are to be avoided.
within the hollow shaft. The optimum relationship Guide vanes, sometimes called wicket gates, are
between runner blades and guide vane angle is con- located in the annulus between bulb and casing to
trolled by a cam system in the operating mechanism. control the flow of water to the runner.
Installation is usually as a vertical shaft machine. Several combinations of guide vane/runner blade
This configuration has the following advantages: control are possible:
Bearing and lubrication system layout is simple.
Variable guide vanes and runner blades
Electrical generator installation, access and
maintenance is made easier. This combination provides the best efficiency over
the load range. It also allows a useful variant for
Turbine support and secure embedding of parts, tidal power schemes. Thus, as well as operating as a
such as the inlet volute, in a heavy concrete mass turbine in either the ebb or flow direction, there is
are facilitated. the capability for pumping in either direction to
improve the head available for the next generation
Equipment can be mounted on the top cover and
cycle.
is easily accessible for maintenance.
Submersion of the runner below the tailwater level
to obviate cavitation is achieved with minimum Variable guide vanes, fixed runner blades
civil costs, compared with submersion of the com- Load is satisfactorily controlled over the complete
plete set. operating range by varying the guide vane angle,
428
Types of turbine

SPIRAL
CASING

VARIABLE ANGLE '^^


RUNNER BLADES

TURBINE SHAFT

HUB SERVOMOTOR PISTON

TORQUE PIN
PISTON ROD

TRUNNION
LEVER

RUNNER BLADE
(REMOVABLE)

LINK

BLADE BOLT

CROSS HEAD

THIS SPACE IS FILLED WITH OIL AT


STATIC PRESSURE FOR LUBRICATION HUB CONE
PURPOSES

FIG. 5.6 Kaplan turbine with detail of the hub mechanism for varying the blade angle shown on the inset

429
Hydraulic turbines Chapter 5

SUPPORTING STRUTS
AND SERVICES ACCESS SUPPORTING STRUTS WICKET GATES RUNNER BLADES

ELECTRICAL GENERATOR

FIG. 5.7 Bulb turbine

but the fixed runner blades cause a rapid fall-off Maintenance of the generator is hampered by the
of efficiency with change of load on either side of the limited space and access available within the bulb.
design point.
The low inertia of the rotating parts (small diameter
generator and runner made possible by the higher
Fixed guide vane, variable runner blades specific speed) means that, on some generating
It has been found that both efficiency and the way networks, there may be synchronising problems or
that it is maintained over the power range is nearly speed and frequency fluctuations.
as good for this combination as for variable guide
vanes and runner blades. A disadvantage is that the
For these reasons, the tube turbine has evolved,
turbine cannot be shut down by closure of the guide
mainly differing from the bulb turbine in transferring
vanes and some form of flow shut-off, such as stop
the generator outside the water path and driving it
gates, must therefore be provided.
through an extended shaft. Suitable gearing can also
be interposed to allow generator speed or size to be
optimised. Access to the generator and gearbox is
2.4.2 The tube turbine considerably improved over the bulb design. Various
There are two major disadvantages of the bulb turbine: arrangements have been constructed: one such is
430
Pumped-storage

shown in Fig 5.8. The long drive shaft can, how- their vital task under the normal and transient
ever, create shaft whirling and bearing arrangement rotor movements associated with hydraulic con-
problems. ditions and vibration.
Using fixed runner blades, the cost of these units is
extremely competitive with other types. The narrow
2.4.3 The rim generator design peak efficiency range of fixed blade designs, however,
In this type, the turbine and generator rotor form a may require that the total output be met by a
single unit in the same plane (Fig 5.9). The runner multiplicity of small units or that variable blade design
blades are shrouded by a circumferential ring to which is used with its flatter efficiency. Employment of such
the electric generator poles are attached and these, methods, does however, detract from the financial
in turn, are surrounded by the generator stator. competitiveness of this arrangement.
Bearings are housed in bulbs on either side of the
runner.
This design is marketed by Escher Wyss under the
name 'Straflo'. The efficiency of these units is com- 3 Pumped-storage
parable with other tubular turbines. Pumped-storage offers a means of storing electricity
The concept has the following features: in the form of the potential energy of water held at
high level. The main advantages and reasons for its
Generator accessibility is very good and the large installation can be stated as follows:
diameter ensures high inertia, and hence stability.
Its design is, however, dictated by turbine rather For electrical generation in the 'peak lopping' role.
than electrical considerations and balancing must Being comparatively simple, it can provide a rapid
be rigidly controlled on these large diameters. start for peak lopping or emergency reserve, with a
higher reliability than thermal plant such as gas
Seals are required between the rotating shroud ring turbines or diesel engines.
of the turbine and the static casing of the water
passage to prevent ingress of water to the electrical On a system containing thermal generating plant
generator. These seals have been the subject of it reduces the requirement for sets on 'hot standby'
intense development to enable them to perform or 'spinning reserve'.

STOP
GATES

FIG. 5.8 Tube turbine

431
Hydraulic turbines Chapter 5

GUIDE VANE
OPERATING RING ELECTRICAL
CUBICLE

VARIABLE ANGLE
INLET
GUIDE VANE

RUNNER BLADE

FlG. 5.9 Rim generator ('Straflo') turbine

It provides a convenient form of system frequen- pumping at periods of low system demand. A
cy regulation especially during periods of rapidly corollary of this is that margins on system capability
changing demand. can be reduced.

It facilitates load curve smoothing by using con- Operation of the system requires two lakes or water
ventional or nuclear plant to provide power for storage reservoirs. During generation, water is ad-
432
Pumped-storage

mitted to the turbines from the top lake, discharging Pump casings are in cast steel welded to a plate steel
into the lower. The sets can be run in this mode volute.
until demand is met or other plant can be started. Whilst pumping, the drive must take place from the
At off-peak periods the water is pumped up from motor through the turbine, which is filled with air to
the lower into the upper lake ready to meet the next reduce pumping losses. The pump is disengaged whilst
demand. the turbine is in operation in the generating mode
The requirements of the set for both a turbine and a coupling is provided for this purpose. System
and pumping role can be met in two ways; either by requirements did not justify the expense of a coupling
using separate pumps and turbines or by a single capable of engagement/disengagement at full speed
pump-turbine which combines both duties in one and so these operations are conducted whilst the ma-
rotor, and which reverses direction between roles. chine is stationary. A toothed gear, sliding-muff type
of coupling is used, engagement being actuated by oil
pressure and a positive mechanical lock inserted during
periods of rotation.
3.1 Ffestiniog power station
This station, part of the CEGB system in England
and Wales, is an example of the separate pump and
turbine system and was completed in the 1960s. The 3.2 The reversible pump-turbine
pump and turbine are mounted in tandem on coaxial Such a machine enables both pumping and turbining
shafts, at one end of which is a unidirectional motor- to be performed by the same runner or runners. It is
generator. effectively a Francis turbine whose runner geometry is
The upper reservoir operates between extreme levels a compromise between the optimum for pumping and
of 483 and 502 m above sea level and encloses a generation. During generation, the turbine output is
storage volume of 1.7 million cubic metres giving a absorbed by the generator; whilst pumping, the gen-
generation time of some 4.5 hours. The lower reser- erator acts as a motor, driving the runner in the
voir level correspondingly fluctuates between 182 and opposite direction.
188 m. A desirable feature of this design is that it is
The cross-sectional arrangement of the sets and considerably cheaper than a type employing a se-
their relationship to the lower lake are shown in Fig parate pump and turbine and the necessity for a
5.10. Four pump-turbines, each of 90 MW maximum clutch between the two is also eliminated. Also, since
generating capacity, are arranged in an overground the same runner is employed in both the turbining and
building to reduce civil costs and to facilitate flood pumping directions, the need for separate suction and
water disposal in the remote event of a burst. discharge piping for the two components with the
Each pump-turbine is arranged in a vertical con- associated mechanical and civil costs is similarly un-
figuration with the pump mounted below the turbine necessary. The efficiency of such a unit as a pump or
so that it may have maximum submergence for mini- turbine is usually some 1 /o lower than a corresponding
misation of cavitation. The piping system, connecting optimally designed machine of similar size. Typical
to the upper lake, bifurcates, as shown in Fig 5.10. maximum values for very large machines might be
The upper branch connects to the turbine inlet via 92 93% when pumping, and 93-94% when turbining.
a hydraulically-operated inlet valve and the lower to Subsequent to the construction of Ffestiniog power
the pump outlet through a similar valve. station, considerable worldwide experience had been
Each single-stage Francis turbine runs at 428 r/min obtained with single-stage reversible pump-turbines.
with a maximum efficiency of over 93%. The high- Therefore, for their pumped-storage station at Dinor-
tensile steel spiral casings are constructed in halves wig, the CEGB decided to install such machines. The
with site-bolted flanged joints. The variable guide first sets were commissioned in 1982 and, since it
vanes in cast stainless steel are operated through a represents one of the world's major pumped-storage
lever and link system which is automatically grease- schemes in terms of both unit capacity and operat-
lubricated. The runner is in 13% chromium steel and ing head, it is used as an example of modern practice
has a maximum diameter of 1.93 m. in this field.
The vertical two-stage pump is of double-entry
design. Thus the second-stage impellers are disposed
back-to-back as a single rotor and the first stages 3.3 Dinorwig power station
must be mounted outboard of it (see Fig 5.11). Suc-
tion from the lower lake is therefore via a breeches
pipe which conveys water to the suction of each of 3.3.1 The site
the first-stage impellers. Each of the two 2.5 m This station is located near Llanberis in Wales, in the
diameter first-stage impellers and the 2.6 m diameter Snowdonia National Park; an area renowned for its
double-entry second stage are manufactured in 13% natural beauty. This fact dictated some of the design
chromium steel and are keyed to the pump shaft. features of the station.

433
Hydraulic turbines Chapter 5

TRANSFORMER SWITCHGEAR GENERATOR / MOTOR

RESERVOIR
WATER LEVEL

NORMAL MIN LEVEL 4 CONCRETE 4 STEEL 4 STEEL NORMAL MIN LEVEL


482.5 m LINED TUNNELS LINED TUNNELS PENSTOCK PIPES 182.3 m
3.25 m 2.8 m 2.3 m
INTERNAL DIAMETER INTERNAL DIAMETER INTERNAL DIAMETER

FIG. 5.10 Cutaway perspective of Ffestiniog power station showing the arrangement of the pump-turbine

434
Pumped-storage

FIG. 5.11 Section through the two-stage double-entry pump used at Ffestiniog power station

The upper storage reservoir was created by the an enlargement of an existing lake at the foot of
construction of a low rockfill dam across a corrie the mountain with the level varying between 92 and
within the Elidir mountain, thus enlarging a natural 106 m above sea level.
lake to contain a water volume of 6-7 million cubic The station, constructed within the mountain itself,
metres. The operating levels fluctuate between 633 m was designed on the basis of six machines, each pro-
and 600 m above sea level. The lower reservoir is ducing 300 MW at minimum net head and the ability
435
Hydraulic turbines Chapter 5

to refill the upper reservoir by pumping from the lower In order to meet such short loading times, it is ne-
in a six-hour period. cessary for the machine to be kept for long periods
A schematic plan and elevation of the site is shown at synchronous speed. In the generation direction,
in Fig 5.12 whilst a section through the underground this could be effected by allowing a small throughput
station itself is shown in Fig 5.13. of water to generate sufficient power to overcome
machine losses. This is unattractive since:

3.3.2 Runner submergence It wastes water and its corresponding pumping


As referred to in Section 1.4 of this chapter, the power.
economics of turbine design improve with increase
At low flows, the water strikes the runner blades at
of speed. Since the runaway/normal speed ratio is
off-design angles, promoting erosion and wear.
smallest for pump-turbines, the running speed be-
comes higher for a pump-turbine than for any other There is the fear that, in a closed system, the
type operating at similar output and head. power losses could raise reservoir temperature in
In the pumping mode, the increased speed coupled the long term.
with the high head, requires considerable submergence
of the impeller below tail water level to avoid cavi-
tation. Similarly, submersion was also required in Similarly, in the pumping mode, the churning gen-
the turbining mode to obviate column separation a erated by running against closed guide vanes causes
condition in which inertia effects can cause cavities a loss of power of about 70 MW.
within the water flow with severe water hammer on The problem has been overcome, in both modes,
recombination. For these reasons, a runner submer- by filling the runner space with air at tailwater pres-
gence of some 60 m was required. This was obtained sure: the windage losses are then reduced to some
by placing the machines in a machine hall below 2 MW. With the main inlet valve (MIV) on the high
ground and within the mountain itself. As well as pressure side of the pump-turbine and the guide vanes
being environmentally desirable, it was found that the closed, air from air bottles is blown into the runner
small increase in civil costs was more than compen- space through a connection in the top cover and
sated for by the lower machine costs through using automatically maintained by a level control valve in
reversible pump-turbines. the draft tube. The machine can then be held spin-
ning at synchronous speed indefinitely in either the
pumping or turbining direction (known as spin/pump
3.3.3 Operational requirements and spin/generation modes respectively). Whilst the
In order to meet CEGB system needs the pump- runner is spinning in air, a small supply of cooling
turbine has a load regime which involves: water is supplied to the seals at the top and bottom
shrouds, the centrifuged water being led away to drain
Generating in the range of zero to a full-load of 317 from a connection at the runner periphery. Reversion
MW with up to five hours of continuous, constant to pump or turbine operation is initiated by simply
output generation. opening the MIV and guide vanes, and the air bubble
Pumping, using one or more units at full-load. is quickly dispersed by the water flow.

Emergency reserve. This provides 1320 MW to the


system in the event that two of the largest units of 3.3.4 Design life
660 MW each are simultaneously lost to the grid. Each machine is designed to undergo a number of
Frequency regulation, which involves operation mode changes per year, viz:
over the range of zero to full-load to correct for Routine pumping starts and stops, up to three times
system frequency deviations as they occur. per day.
Routine generation starts and stops, up to four times
Associated with the above is a requirement to meet
per day.
these system needs within certain time scales. Whilst
it was never envisaged that there would be any de- Change from spin-generation to generation and vice
mand for rapid adoption of the pumping role it is versa, up to 13 times per day.
essential that the machine is capable of changing
modes within very short time scales as follows: Emergency loading and change from pumping to
generation.
Standstill to no-load generation 90 s
Pump and turbine trips.
No-load synchronised to 1320 MW output 10 s
Emergency pumping to spinning-in-air (both In total, this represents 7500 loading/unloading cycles
in the pumping direction) 10 s per annum. A fundamental consideration is the fact
436
HEADWORKS HEADGATES LOW PRESSURE TUNNEL SURGE SHAFT
TiAii co. \ INSTALLATION SURGE POND
TWL 634m
LWL 600m

UPPER RESERVOIR
MARCHLYN MAWR

TAILGATES
INSTALLATION TWL 106.25m
ALL HEIGHTS
LWL 92m
ABOVE ORDNANCE
DATUM
HIGH PRESSURE SHAFT

LOWER RESERVOIR
LYN PERIS
TAILRACE TUNNELS
700m 470m
HIGH PRESSURE SYSTEM LOW PRESSURE SYSTEM

STOP GATES

MAIN GATES

UPPER RESERVOIR SURGE POND & SHAFT HIGH PRESSURE


MARCHLYN MAWR INTERMEDIATE MAIN GATES STOP GATES
PENSTOCKS PENSTOCKS

HEADGATES
INSTALLATION

LOWER RESERVOIR
LYN PERIS

STATION COMPLEX y~.


TAILGATES INSTALLATION

BASCULE GATES INSTALLATION

437
FIG. 5.12 Dinorwig power station site plan and elevati.
Pumped-storage
438
MACHINE HALL UNIT 2 TRANSFORMER HALL
HEATING AND
Hydraulic turbines

VENTILATION PLANT 400 kV SWITCHGEAR

CABLE TUNNEL

CABLE FLAT

GENERATOR.
MOTOR
MIV GALLERY
OIL PLANT ACCESS
CONNECTIONS \ TUNNEL
PUMP
TURBINE GENERATOR - MOTOR
TRANSFORMER
MAIN
INLET v
VALVEN

INTERMEDIATE PENSTOCK
K

FROM TO TAILWORKS AND


UPPER LOWER RESERVOIR
RESERVOIR

DRAFT TUBE
No 1 MAIN SUMP
VT CUBICLE BUSBAR GALLERY

11 70 m AOD

FIG. 5.13 Section through Dinorwig power station


Chapter 5
Pumped-storage

that during each of these cycles the MIV shuts, thus shaft and the upper shroud seal which admit blow-
depressurising the penstock and turbine casing to the down air into the system, together with the peripheral
tailwater pressure of some 6 bar, then re-opens to drain pipes which are opened under these conditions to
pressurise them again to 50 bar. Over its 40-year design discharge the cooling water supplied to the upper and
life, the machine is thus subjected to 300 000 cycles lower seals.
of pressurisation. Figure 5.15 shows the guide vane apparatus, in-
The requirement to design for a fatigue life is un- dicating the substantial bearings employed and also
usual in water turbines. In this instance, consequently, the manner in which the regulating ring rotates the
it was thought necessary to use a fracture mechanics vane through the lever and locking assembly, which
approach to the design, adopting the ASME standards incorporates a friction clutch. Seals are fitted on the
applicable to nuclear pressure vessels. Essentially this end faces of the guide vane blade to minimise water
assumes that defects present in the steel, which are leakage and both these and the guide vane bearings
smaller than those detected by non-destructive test are equipped with an automatic greasing system.
methods and consequently repaired during manufac- In the turbining direction, the guide vanes are
ture, will grow under the varying stress field. Over infinitely variable between fully closed and about 32
the plant life, these initial defects must not grow to of opening rotation to achieve the required output.
a size approaching the critical defect size, where the In the pumping direction, however, the guide vanes
crack can grow in an uncontrolled manner. Due to are opened to a nominally fixed postion, although
the inherent uncertainties of crack detection during pump performance can be optimised for varying speed
manufacture, the design allows for inspection of cri- and head by minor variations in the angle between
tical areas during the life of the plant. As shown in 20 and 30 open.
Fig 5.14, one such area is the spiral casing, which
has not been invested in concrete over critical welds
such as occur between the spiral casing and the 3.3.6 Valves
stayring. In turn, this has necessitated placing a rub- The valves placed either side of the pump-turbine
ber membrane between spiral casing and concrete to are similar to those used in many types of turbine.
absorb panting and flexure of the spiral casing dur- Those used at Dinorwig will be described in detail
ing its pressure cycle whilst still providing adequate as an example of modern practice.
restraint of the spiral by the concrete. Provision is
also made in the design for grout injection should
any gap develop with time. The main inlet valve (MIV)
Since the pump casing and inlet spiral are com- Each MIV is a 2.5 m bore rotary valve, interposed
plicated structures, the stresses in them were deter- between the main and intermediate penstocks, which
mined both by finite element methods and photoelastic isolates the turbine from high pressure water at each
analysis of a plastic model. shutdown (see Fig 5.16). The valve rotor rotates
within the valve body on two trunnions to which are
attached the operating lever arms and closing weights.
3.3.5 Machine layout The valve is held open by the upward thrust on the
The nine-bladed runner in cast stainless steel has a lever arms from two servomotors (or rams) filled with
maximum diameter of 3.8 m and an eye diameter of oil under pressure. The system is thus 'fail-safe' since
2 m (see Fig 5.14). The vertical drive shaft is mounted the valve closes under the action of the weight alone.
in a single guide bearing of tilting-pad design. Lu- The rate of closing is controlled by restrictors in the
brication of the bearing is by a self-contained system with oil discharge line.
an oil reservoir and integral water-cooled oil coolers The MIV is closed each time the machine shuts
disposed within the bearing housing. Oil circulation down and, in this condition, leakage between the
through the coolers is maintained by the head gen- near-spherical valve rotor and body is prevented by
erated by shaft rotation. The thrust from the pump- a service seal. This is in the form of a stepped ring
turbine runner and motor-generator to which it is which slides axially in its stainless steel housing to
rigidly coupled is taken by a tilting pad thrust bearing seat against a ring attached to the rotor on its inter-
mounted in the motor casing. It must be sized to mediate penstock face. The seal is operated, as well
accept the widely varying thrusts achieved during pump as being held on and off, by penstock water pressure
and turbine operation and, in particular, those tran- acting on the appropriate face of the stepped ring.
sients which occur during mode changes. Leakage of The seals between stepped ring and valve body are
high pressure water from the upper shroud of the D-shaped to prevent rotation within their grooves:
runner along the clearance between the shaft and they were the subject of considerable testing to ensure
the pump inner top-cover is minimised by a balanced that they met the six-year life required of them.
seal of the type referred to in Section 2.2 of this A similar seal is provided on the penstock face of
chapter. the valve rotor but it is only operated to provide
Shown also in Fig 5.14 are the pipes between the additional safety during maintenance. Under these

439
440
BLOW DOWN
GUIDE BEARING SHAFT AIR PIPE
Hydraulic turbines

GUIDE VANE
SERVOMOTOR

GUIDE
VANE
BLADE
PERIPHERAL DRAIN
SYSTEM OPERATED SHAFT SEAL BOTTOM COVER
BALANCE DURING SPINNING AND
PIPE OPERATIONS INNER COVER
Chapter 5

FlG. 5.14 Section through the pump-turbine used at Dinorwig power station
Pumped-storage

FRICTION CLUTCH LEVER LINK


LOCKING ASSEMBLY

REGULATING RING

BEARING

" RING
SEAL

CHEEK PLATE

PACKING PIECE

GUIDE VANE
LOWER SPINDLE

FIG. 5.15 Guide vane assembly

441
Hydraulic turbines Chapter 5

BODY END

PENSTOCK FLANGED
STUB PIPE CONNECTORS STUB PIPE
FLANGED PIPE

LOOSE SEAL RING


FLANGE ^
MOVABLE ASSEMBLY STUD
FLANGE
FLANGED PIPE
SERVICE SEAL
SEATING RING /^
FLANGED PIPE

HOUSING ASSEMBLY SERVICE SEAL AND DISMANTLING JOINT ASSEMBLY

MAIN GUIDE
BUSH
MAINTENANCE
SEAL
MAINTENANCE SEAL
ASSEMBLY

SERVICE SEAL POSITION


INDICATOR

LOCKING PIN ASSEMBLY

FLOW
WHEN
PUMPING SERVICE SEAL
OPERATING
ASSEMBLY

SERVOMOTOR

FIG. 5.16 Main inlet valve at Dinorwig power station

conditions, a portion of the intermediate penstock insertion of packing pieces and the valve locking
can be removed and the valve blanked off with a pin applied.
bolted-on dome. When necessary, both service and Since the MIV operates each time the machine
maintenance seals can be positively locked shut by shuts down, it is subject to cyclic pressure variation.

442
Pumped-storage

These valves were therefore subjected to design by culations are of the utmost importance in establishing
fracture mechanics principles in the same manner as station safety during occurrences such as simultaneous
the turbine. Stresses were determined by tests on a trip of all machines from full-load generation. A diagram
photo-elastic model. The valve bodies are manufac- showing the valve opening and closing times is shown
tured in Carbon-Manganese steel. in Fig 5.17.
Valve opening and closing times must be carefully At Dinorwig, transient machine and hydraulic char-
selected to avoid undesirable surges or hydraulic tran- acteristics determined during tests of single and simul-
sients within the system. Such considerations formed taneous trips of two, three and four machines were
part of the hydraulic/water hammer analysis which so closely predicted by the theoretical hydraulic ana-
examined the interaction of factors such as the tunnel lyses, that it was not considered necessary to subject
system, surge shafts, valve and guide vane closing the system to a practical demonstration of a simul-
rate and pump head/flow char act eristcs. Such cal- taneous six-machine trip from full-load.

MIV ANGLE 0

VALVE FULLY OPEN

VALVE FULLY CLOSED

GV ANGLE 0

MAX GV ANGLE - TURBINING

MAX GV ANGLE - PUMPING

TIME S

FIG. 5.17 Main inlet valve and guide vane opening and closing times at Dinorwig power station

443
Hydraulic turbines Chapter 5

The draft tube valve 3.3.7 Testing


The draft tube valve (DTV) (see Fig 5.18), is placed Full-size testing of the installed pump-turbine to
on the tailwater side of the pump-turbine and is verify efficiency guarantees, requires measurement of
provided to isolate the machine from the lower re- power, net head and water flow as detailed in Section
servoir during maintenance, and to close in the event 1.1 of this chapter. Difficulties and costs in provid-
of a major burst to prevent station flooding. It is ing for the accurate measurement of the large flows
normally left open and does not form part of any involved make such an undertaking unattractive from
automatic operating sequence. both practical and contractual considerations.
Each DTV is a 3.75 m diameter butterfly valve, For this reason the comprehensive tests carried out
the rotor being of the lattice type. Integral eccentric by the manufacturer on the one-eighth scale homo-
trunnions ensure that should it be inadvertently left logous model of the pump-turbine and corrected to
shut during turbining, it will flip open under the tur- full-sized machine values by established means [1] were
bine flow. Opening and closing is performed by a accepted by the CEGB as evidence of the machine's
servomotor and lever and weight system, in a similar ability to meet efficiency guarantees. However, as con-
manner to the MIV. firmation of this and to establish a reference point

BLADE
SLIDING JOINT

BODY

T*L
STUB PIPE

LEVER ARM

TO TAILWORKS
AND
LOWER
RESERVOIR
CLOSING WEIGHT

- LOCKING PIN

TO
PUMP * MANHOLE
TURBINE

s
BYPASS VALVE

BYPASS PIPE

BYPASS VALVE
BYPASS VALVES

CLOSING WEIGHT SERVOMOTOR

LEVER ARM

FIG. 5.18 Draft tube valve at Dinorwig power station

444
Additional references

to enable performance deterioration to be monitored Station output


during service, each machine is equipped with tap- Average generated station output 1680 MW
ping points in the intermediate and lower penstocks
Generating period at constant output 5h
enabling thermodynamic testing of the machine ef-
ficiency to be undertaken. Average individual pump power input 283 MW
This method does not require any flow measure- Pumping period 6.3 h
ment. It measures the internal efficiency of the ma-
chine by comparing the actual enthalpy change of
the water due to the work done in passing through Pump-Turbines (six off)
the machine, with that which would be experienced Type Reversible Francis
if the water experienced an isentropic change from
its initial to final pressure or head. The ratio of these
Turbining (Generating)
values gives the machine efficiency. The main problem
of the method is that of accurate measurement of Maximum output/net head Up to 317 MW/535.8 m
the small temperature difference (typically 1 to 2C) Minimum output/net head Up to 280 MW/487.9 m
upon which enthalpy changes depend but for this, Maximum flow 70 m3/5
and other details of the method, see [2]. Synchronous speed 500 r/min
Maximum transient
runaway speed 735 r/min
3.3.8 Some details of the Dinorwig pumped-
storage station
Pumping
Upper reservoir Rated discharge/head 50 m3/523 m
Storage volume 6.7 million m3 Maximum power input 318 MW
Maximum water height 634 m Synchronous speed 500 r/min
Minimum water height 600 m Min/max frequency 49/51 Hz

Lower reservoir
Maximum tail water level 106 m
4 References
Minimum tailwater level 92 m
[1] 'International Code for Model Acceptance Tests of Hydraulic
Turbines': IEC Publication No. 193
Tunnel diameters (concrete lined) [2] Thorn, A. S.: Thermodynamic Testing of Turbines and Pumps'
IMechE Vol. 7 No. 3: 1965
Low pressure tunnel 10.5 m
Surge shaft 30 m
High pressure shaft 10 m
High pressure tunnel (manifold) 9.5 m
5 Additional references
Tailrace tunnels (three off) 8.25 m
Guthrie-Brown, J. (Ed): 'Hydro-Electric Engineering Practice':
Blackie & Son
Tunnel diameters (steel lined) Headland, H.: 'Blaenau Ffestiniog and other Medium-Head Pumped
Storage Schemes in Great Britain': IMechE Proc. Volume 175
High pressure penstock 2.5 m No. 6: 1961
Intermediate penstock 2.3 m The Dinorwig Power Station': Papers presented at a major achieve-
Draft tube (six off) 3.75 m ment symposium: IMechE: 1985

445
C H A P T E R 6

The generator

1 Introduction 6.1.8 Main exciter protection


1.1 Types of generator 6.2 Brushless excitation systems
6.2.1 System description
1.2 Historical background
6.2.2 The rotating armature main exciter
1.3 Standards and specifications
6.2.3 Telemetry system
2 Synchronous generator theory 6.2.4 Instrument sliprings
6.2.5 Rotating rectifier protection
2.1 Electromagnetic induction
6.3 Static rectifier excitation equipment
2.2 Speed, frequency and pole-pairs
6.3.1 Introduction
2.3 Load, rating and power factor
6.3.2 General description of static diode rectifier equipment
2.4 MMF, flux and magnetic circuit
6.3.3 Rectifier protection
2.5 Rotating phasors
6.3.4 Static thyristor rectifier schemes
2.6 Phasor diagrams
6.4 The voltage regulator
2.6.1 Rated voltage, no stator current, open-circuit
6.4.1 Historical review
conditions
6.4.2 System description
2.6.2 Rated voltage, rated stator current and rated power
6.4.3 The regulator
factor
6.4.4 Auto follow-up circuit
2.7 Torque
6.4.5 Manual follow-up
2.8 Three-phase windings
6.4.6 Balance meter
2.9 Harmonics: distributed and chorded winding
6.4.7 AVR protection
3 Turbine-generator components: the rotor 6.4.8 Thyristor converter protection
6.4.9 Fuse failure detection unit
3.1 Rotor body and shaft
6.4.10 The digital AVR
3.2 Rotor winding
6.5 Excitation control
3.3 Rotor end rings 6.5.1 Rotor current limiter
3.4 Wedges and dampers
6.5.2 MVAr limiter
3.5 Sliprings, brushgear and shaft earthing 6.5.3 Overfluxing limit
3.6 Fans 6.5.4 Speed reference controller
3.7 Rotor threading and alignment 6.6 The power system stabiliser
3.8 Vibration 6.6.1 Basic concepts
3.9 Bearings and seals 6.6.2 Characteristics of GEP
3.10 Size and weight 6.6.3 System modes of oscillation
4 Turbine-generator components: the stator 6.6.4 Principles of PSS operation
6.6.5 The choice of stabiliser signal
4.1 Stator core
6.7 Excitation system analysis
4.2 Core frame
6.7.1 Frequency response analysis
4.3 Stator winding
6.7.2 State variable analysis
4.4 End winding support 6.7.3 Large signal performance investigations
4.5 Electrical connections and terminals
4.6 Stator winding cooling components 7 Generator operation
4.7 Hydrogen cooling components 7.1 Running-up to speed
4.8 Stator casing 7.2 Open-circuit conditions and synchronising
5 Cooling systems 7.3 The application of load
7.4 Steady state stability
5.1 Hydrogen cooling 7.5 Capability chart
5.2 Hydrogen cooling system 7.6 Steady short-circuit conditions, short-circuit ratio
5.3 Shaft seals and seal oil system 7.7 Synchronous compensation
5.3.1 Thrust type seal 7.8 Losses efficiency and temperature
5.3.2 Journal type seal 7.9 Electrically unbalanced conditions
5.3.3 Seal oil system 7.10 Transient conditions
5.4 Stator winding water cooling system 7.11 Neutral earthing
5.5 Other cooling systems 7.12 Shutting down
6 Excitation 8 Mechanical considerations
6.1 Exciters 8.1 Rotor torque
6.1.1 Historical review 8.2 Stress due to centrifugal force
6.1.2 AC excitation systems 8.3 Alternating stresses, fretting and fatigue
6.1.3 Exciter transient performance 8.4 'Slip-stick' of rotor windings
6.1.4 The pilot exciter 8.5 Noise
6.1.5 The main exciter
6.1.6 Exciter performance testing 9 Electrical and electromagnetic aspects
6.1.7 Pilot exciter protection 9.1 Flux distribution on load

446
Introduction

9.2 Control and calculation of reactances 10.5 Protection


9.3 The cause and effect of harmonics 10.5.1 Class 1 trips
9.4 Magnetic pull 10.5.2 Class 2 trips
9.5 Shaft voltage and residual magnetism 11 Maintenance, testing and diagnosis
9.6 Field suppression
9.7 Voltage in the rotor winding 11.1 Maintenance and tests during operation
9.8 Stator winding insulation 11.2 Maintenance and tests when shut down for a short
outage
10 Operational measurement, control, monitoring and 11.3 Maintenance during a longer outage
protection 11.4 Maintenance and tests with the machine dismantled
11.5 Reassembly
10.1 Routine instrumentation
11.6 Diagnosis
10.1.1 Temperature
10.1.2 Pressure 12 Future developments
10.1.3 Flow 12.1 Extension of present designs
10.1.4 Condition monitoring 12.2 Extension of water cooling
10.1.5 Electrical 12.3 Slotless generators
10.1.6 Vibration 12.4 Superconducting generators
10.2 Logging and display 12.5 Auxiliary systems
10.3 Control
10.4 On-load monitoring, detection and diagnosis 13 Other types of generator
10.4.1 Air gap flux coil 13.1 Turbine-type generators of lower rating
10.4.2 Core or condition monitor 13.2 Water turbine driven salient-pole synchronous generators
10.4.3 Insulation discharge 13.2.1 Excitation and control
10.4.4 Rotor winding earth fault indication 13.2.2 Other features
10.4.5 Shaft current insulation integrity 13.3 Diesel engine driven salient-pole generators
10.4.6 Stator winding water analysis 13.4 Induction generators

1 Introduction of the 19th century, and the rapid growth of AC


systems led to a demand for AC generators. At first,
these were slow speed machines driven by recipro-
cating engines but, by 1900, generators driven directly
1.1 Types of generator by high speed steam turbines were being introduced
The CEGB transmission system operates at a fre- in what are recognisably the forerunners of modern
quency of 50 Hz: so do all the generators connected machines, the benefits being principally in the prime
synchronously to it. The larger generators are almost mover.
all directly driven by steam turbines rotating at 3000 The early turbine-generators were made both in
r/min; a few operate at 1500 r/min. vertical and horizontal shaft configurations. The ver-
These high speed generators are commonly known tical shaft design required a large thrust bearing, and
as turbine-generators, or cylindrical rotor generators; was quickly abandoned. The development of hori-
in this chapter, such machines are implied unless zontal shaft machines was rapid; unit outputs had
otherwise stated. risen from a few hundred kW to 20 MW by 1912
The CEGB has for many years standardised on (see Fig 6.2).
generating units of 500 and 660 MW electrical output. The rate of increase in output slowed subsequently,
At these ratings, there have been six different designs but unit outputs had risen to 50 MW by the 1930s.
of generator, each design incorporating minor changes The 60 Hz frequency standardised in the USA re-
as time progressed. However, they are all sufficiently quired the speed of American two-pole generators
similar for a generalised description to be applicable. to be 3600 r/min, and the losses caused by air friction
Where a design departs radically from that being de- at this speed made the much-less-dense gas hydrogen
scribed, this will be noted (see Fig 6.1). attractive as a cooling medium. In the UK, hydrogen
The bulk of this chapter deals with generators of cooling was used on 3000 r/min units of 50 MW and
this size; the theory applies to all synchronous gen- above from about 1950.
erators. Brief descriptions of other types of generator Later, the search for increasingly effective means
in use on the CEGB system will be found at the end of heat (loss) removal led first to the use of hydrogen
of this chapter. at higher pressure, then insulating oil, and finally,
pioneered in the UK, water in direct contact with the
winding conductors. By these means, generators with
the increasing outputs demanded were able to be
1.2 Historical background manufactured, transported and installed in a power
The advantages of AC over DC as a means of elec- station as single units, which was both economically
tricity distribution were established towards the end and operationally attractive (see Fig 6.3).
447
448
The generator

STATOR WINDING STATOR ENDWINDING STATOR -CURRENT TRANSFORMERS


WATER INLET MANIFOLD SUPPORT BRACKET RETAINING RING

PTFE HOSES s -TERMINAL BUSHINGS NEUTRAL

STATOR ENDWINDING
GAS BAFFLE *
ENDSHIELD^ . STATOR END CONNECTORS
OUTER FAN
BAFFLE STATOR ENDWINDING
HOUSING COVER ROTOR FAN
OIL CATCHER BEARING TOP HALF CAP
SUPPORT RING * ; BEARING ASSEMBLY
SEAL CARRIER RING
SEAL CARRIER
, RING EXTENSION-

GENERATOR-TURBINE INNER
HALF COUPLING FAN BAFFLE

HYDROGEN COOLER -

FLANGE CONNECTIONS
TO CONDENSATE SYSTEM TERMINAL BUSHING MAIN
FLANGE CONNECTIONS TO
STATOR WINDING WATER SYSTEM

FIG. 6.1 Sectional view of a 660 MW generator


Chapter 6
Introduction

FIG. 6.2 20 MW air cooled generator

Both the pace of development and the rate of Other parameters, such as hydraulic pressure and
increase in unit output has slowed markedly in re- dielectric loss test values, are specified in various
cent years, as greater emphasis has been placed on CEGB Standards.
the reliability achieved by proven designs, and on Specific requirements for a new generator are con-
the advantages of interchangeability of major plant tained within its own specification, which covers items
components. peculiar to its location or duty, for example, tem-
perature of cooling water, power factor and reactances.
Where necessary, these requirements may differ from
those in the appropriate Standard. The expected op-
1.3 Standards and specifications erational life is quoted in the specification; this is
The British Standard covering generators is BS5000, currently 200 000 hours, with 104 start/stop cycles.
which refers to many parts of BS4999. The corre- These values are used in design calculations, e.g., crack
sponding international standard is IEC 34. Standards growth rate by fatigue.
specific for turbine-generators are BS5000 Part 2 and The following Standards are relevant:
IEC 34 Part 3. These standards specify acceptable
characteristics, values of temperature, vibration, noise,
IEC 3 4 - 1 : Rotating electrical machines rating and performance.
phase unbalance, harmonic content, excitation control
limits and tolerances, and test conditions, e.g., high IEC 34-2: Rotating electrical machines methods for determining
voltage test levels. losses and efficiency from tests.

449
The generator Chapter 6

YEAR

1930 1940 1950 1960 1980


I

IN SERVICE

SUPERCONDUCTING

2.0 H
WEIGHT/RATING AIR
kg/kVA COOLED

1.5

DIRECT ROTOR
COOLING

DIRECT GAS OR LIQUID COOLING


OF STATOR AND DIRECT ROTOR COOLING '
0.5
LIQUID COOLING OF STATOR AND ROTOR -

SUPERCONDUCTING -
ROTOR
T-
10 20 100 200 2000 5000

MVA RATING

FIG. 6.3 Development of generator size, weight and cooling arrangements

IEC 34-3: Ratings and characteristics of 3-phase 50 Hz turbine 2 Synchronous generator theory
type machines. Some basic principles of theory and design are es-
IEC 34-4: Methods for determining synchronous machine quan-
tablished in this section in order that the descriptive
tities from tests. matter in later sections may be more easily understood.

IEC 34-6: Methods of cooling rotating machinery.

BS4999: General requirements for rotating electrical machines. 2.1 Electromagnetic induction
BS4999 Part 106: Classification of methods of cooling. In a synchronous generator with the rotor running
at constant speed, the instantaneous voltage induced
BS4999 Part 101: Specification for rating and performance. in a stator conductor is proportional to the magnetic
flux density experienced by the conductor.
BS4999 Part 142: Mechanical performance vibration.

BS4999 Part 109: Noise levels. dB


i n
e = k i
BS5000: Specification for rotating electrical machines of particular dt
types or for particular applications. where e = instantaneous voltage induced along the
BS5000 Part 2: Turbine type machines.
length of the conductor, V
dB
BS2757: Classification of insulating materials for electrical machinery. rate of change of magnetic flux density,
dt tesla/s
BS5500: Specification for unfired fusion welded pressure vessels.
length of conductor exposed to the flux, m
BS601: Steel sheets for magnetic circuits of power electrical apparatus. k constant
BS1433: Copper for electrical purposes: rod and bar.

BS3906: Electrolytic compressed hydrogen. In order to operate synchronously with the inter-
connected AC transmission system, the generated
ESI Standard 44-7: Testing the insulation system of bars. voltage is required to vary sinusoidally. The magnetic
450
Synchronous generator theory

flux density experienced by the stator conductors must poles operating at 1500 r/min. Salient-pole generators
therefore also vary sinusoidally. This is achieved by usually have more than four poles, for example, the
arranging, on the rotor, excitation coils which produce Dinorwig hydraulic turbine-generators have 12 poles
a flux whose density varies approximately sinusoidally and operate at 500 r/min. Generators producing other
around the circumference. frequencies are used for special purposes; those whose
As the rotor rotates inside the stator bore, a con- output is rectified for use as an excitation supply
ductor fixed in the stator will be subjected to an commonly operate at 150 Hz or 400 Hz.
approximately sinusoidally varying magnetic flux den-
sity, and will have an approximately sinusoidal voltage
generated along its length (Fig 6.4). The magnitude
of the flux density, which determines the magnitude 2.3 Load, rating and power factor
of the generated voltage, can be changed by varying Root-mean-square (RMS) values of alternating volt-
the direct current supplied to the excitation coils on ages and currents are implied in this chapter, unless
the rotor. specifically noted otherwise.
A single AC generator supplying a load has its
voltage/current relationship dictated by the nature of
that load. For any load which is not purely resistive,
2.2 Speed, frequency and pole-pairs the sinusoidal voltage and current will not be in
The relationship between speed, number of pole- phase.
pairs and the frequency of the generated voltage is: The rated output of a single-phase generator is
the product of its rated voltage and its rated current,
expressed in volt-amps, kVA or MVA. The rated
f pn power is the rated output times the rated power factor,
expressed in watts, kW or MW.
where f frequency, Hz The rated power of a three-phase generator is three
n rotational speed, r/s times rated phase voltage times rated phase current
times power factor. Virtually all CEGB generators
P number of pole-pairs
have their three phases connected in star, so that:

Cylindrical rotor 50 Hz generators have two poles line voltage = V3 x phase voltage
and operate at 3000 r/min, or less commonly four and line current = phase current.

CONDUCTOR
IN STATOR

MAGNETIC FLUX
PRODUCED BY
ROTOR WINDINGS

FIG. 6.4 Production of sinusoidal voltage

451
The generator Chapter 6

The MVA rating is then: which provide a source of magneto-motive force


V3 x rated line voltage x rated line current x 10 ~ 6 (MMF); the driving force' behind the magnetic flux.
The value of MMF depends on the maximum flux
density required at the stator conductors to produce
The MW rating is then: rated MWA x rated power the required voltage and on the reluctance of the
factor. magnetic circuit. The magnetic circuit consists of
paths of low reluctance in the iron of the rotor and
The present CEGB rating for large turbine-generators is: stator, with an air gap of high reluctance between
them. The air gap reluctance is effectively constant,
660 MW, 0.85 power factor lagging, 23 500 V, 3- but that of the iron paths increases at high values
phase, 50 Hz of magnetic flux density, when the iron becomes
magnetically saturated.
The MVA rating is therefore 660/0.85 776 MVA
and the rated line current is:

776 x 106 2.5 Rotating phasors


= 19 076 A
3 X 23 500 A sinusoidally-varying voltage has an instantaneous
value v at time t expressed by:
The output is specified as a maximum continuous
rating (MCR), which implies no guaranteed sustained v = V sin (27rf)t
overload capacity. The standards specify very short
term overcurrent capability, and acceptable variations where V = maximum value of v
in voltage and frequency. Some sustained overload
f = frequency in Hz
capability may be possible by operating at a hydrogen
pressure greater than the rated value, by agreement.
Although operation at 0.85 power factor (lagging) The same relationship can be derived by rotating a
is specified, generators on the CEGB network gen- phasor of constant magnitude V at a constant speed
erally operate at power factors of 0.9 or higher, and (Fig 6.6). At time t, when the phasor is at an angle
this allows operation at higher than rated MW if to the horizontal axis, v = V sin , i.e., the pro-
this is available from the turbine, up to the limit of jection of V on to the vertical axis.
rated MVA (see Fig 6.5). In a synchronous machine, all the sinusoidally-
varying quantities (voltage, current, etc.) can be re-
presented by phasors rotating together at synchronous
speed. The rotating phasor diagram can be thought
2.4 MMF, flux and magnetic circuit of as a snapshot of a set of phasors which all rotate
Direct current circulating in coils wound into the together while maintaining the relationships to each
rotor poles, causes them to act as electromagnets, other.
In a three-phase machine, with balanced electrical
output, conditions in one phase are repeated exactly
OPERATION ABOVE RATED MW in the other two, with time delays of l/(3f) and 2/
PERMISSIBLE IN THESE AREAS
(3f) For clarity, one phase is chosen, and its phasors
are taken as representative of the phase quantities
for all the other phases in a diagram of rotating
phasors.

2.6 Phasor diagrams


0.85 POWER FACTOR
LAGGING

2.6.1 Rated voltage, no stator current, open-


circuit conditions
Let a phase voltage be represented by the phasor
V (Fig 6.7). Since it is the rate of change of flux
MVAR density which produces V, the phasor for flux den-
sity, B, is drawn 90 out-of-phase with V. The
MMF, F, producing this flux density is in phase
FIG. 6.5 Operation at high MW and power factor with B.
452
Synchronous generator theory

INSTANTANEOUS
VOLTAGE

v = Vsin (2irf) t
= Vsin

FIG. 6.6 Rotating phasors

^ \ ^ - - ^ b = Bsin (100-TT) t

7* I f
X X \ \ ^ ^ ^ v = Vsin(100-rr)t

\ ~ \
L__--^~"" v
o / \ TIME I I

FIG. 6.7 Phasors for open-circuit conditions

453
The generator Chapter 6

2.6.2 Rated voltage, rated stator current and reactance. The term synchronous reactance (Xd + Xe)
rated power factor is used to express this effect, the IXd drop being
If the power factor is expressed as cos 0, is the added to the lXe drop in the diagrams.
angle between the voltage and current phasors, as As the lagging power factor of the load worsens,
shown in Fig 6.8 for a lagging power factor. i.e., cos is smaller and larger, the required MMF,
Current circulating in the stator winding results in F, increases, i.e., more current is required in the
voltage drops: IR due to the winding resistance R, in rotor winding (Fig 6.9 (a)). Conversely, if the lagging
phase with I, and IXf due to the winding 'leakage power factor increases or goes beyond unity into the
reactance', Xf, lagging I by 90. R is negligibly small, leading regime, the rotor current must be reduced
and the resistive voltage drop is neglected henceforth. (Fig 6.9 (b)).
An 'internal' voltage E must be generated in the
winding such that after subtracting (phasorially) the
leakage-reactance drop, the rated voltage V is pro-
duced at the terminals. 2.7 Torque
In order to generate E, flux density Be and MMF
The mechanical torque provided by the prime mover
Fe are required, such that the voltage, flux and MMF
is balanced by an electromagnetic torque caused by
phasor triangles are all similar. The physical meaning
the interaction of the magnetic flux and the current
of this is discussed later.
flowing in the stator windings.
Current in the three-phase stator winding produces
The rotor shaft must be designed to transmit rated
its own MMF, Fd, which acts in the same direction
torque, and the stator must be able to withstand a
as FX. An MMF, F, must be provided, such that,
similar torque reaction. In practice, the design must
when the Fd component is subtracted vectorially,
cope with the very much higher torques produced
the resultant is Fe. This is achieved by increasing the
during certain fault conditions.
rotor winding current and by the rotor moving ahead
of its open-circuit alignment, by the 'load angle', ,
as shown.
This demagnetising effect of the stator winding
current is known as armature reaction, and can be 2.8 Three-phase windings
seen from the diagram to be similar in effect (though The voltages and currents produced in each phase
much larger in magnitude) to that of the leakage must be identical, apart from their phase displace-

MMF PHASORS ROTATED BACK


THROUGH 90 TO SHOW
SIMILARITY OF TRIANGLE TO
VOLTAGE PHASORS

FIG. 6.8 Phasor diagram for load conditions

454
Synchronous generator theory

PROPORTIONAL
TO F

PROPORTIONAL
TO F

(a) Lagging current: (b) Leading current:


Excitation current on Rotor angle larger,
load is proportional to F load excitation current smaller

FIG. 6.9 Phasor diagrams for lagging and leading loads

ments, in order to avoid the damaging effects of profile which cannot be shaped to produce a sin-
unbalance. usoidal flux density variation (as can, approximately,
In this and the next section, a complete two-pole a salient pole on a multi-polar slow speed generator).
generator is considered, for simplicity. In a machine The flux density variation in a turbine-generator is
with 2n poles, a two-pole segment is exactly repeated of a stepped rectangular form (Fig 6.11), which con-
n times, and can be considered as electromagnetically tains a fundamental with odd harmonics of significant
equivalent to a two-pole machine. amplitude. The voltage induced in a single stator con-
An economic design of stator winding has many ductor would contain similar unacceptable harmonic
conductors connected in series, so the individual con- components.
ductor voltages are additive. Each 'go' conductor is In a series-connected winding occupying several
connected to a Return' conductor, acted on by the adjacent slots in the stator, the voltage induced in
pole of opposite polarity, and thence to a third con- one conductor will be displaced from that induced
ductor adjacent to the first, and so on through the in its neighbour by the electrical angle subtended
phase. The Return' conductors are disposed in a layer by the two slots, a in Fig 6.12. The sum of n such
displaced radially from the 'go' conductor, both in voltages is V + 2Vcos a + 2Vcos 2a + ... + 2Vcos
the slots and in the end region. (n - -j )a if n is odd, or, 2Vcos a / 2 + 2Vcos 3 a / 2
The usual and most economic arrangement is for + ... 2V cos (2n - -y)cx, if n is even. The ratio of
the winding-of one phase to occupy one-sixth of the this to nV is the distribution factor Kd ( < 1 ) .
circumference, with a parallel section of the same The effect of distribution on the third harmonic
phase occupying the position diametrically opposite voltage is to triple the effective angle, so that the
(see Fig 6.10). summated voltage is:

V 3 + 2V 3 cos 3a + 2V3 cos 6a + etc.

2.9 Harmonics: distributed and chorded and the resultant third harmonic voltage is very much
winding reduced. A similar argument applies even more effec-
A cylindrical rotor generator has a circular rotor tively to harmonics of higher order.

455
The generator Chapter 6

3 Turbine-generator components: the


rotor
STATOR CONDUCTORS
NEAREST TO BORE The rotor must carry the excitation winding, provide
a low reluctance path for the magnetic flux, and
transfer the rated torque from the turbine to the
electromagnetic reaction at the air gap. Steel is the
only material which meets these requirements
economically. A single steel forging is used, from
which the central cylindrical body and its supporting
shafts are machined.

3.1 Rotor body and shaft


The high rotational speed produces large centrifugal
forces in the rotor body, and a high-strength steel is
necessary. Typical alloying constituents are:

2.5% nickel 0.25% carbon


1.2% chrome 0.2% silicon
STATOR CONDUCTORS 0.6% manganese 0.1% vanadium
FURTHEST FROM BORE
0.5% molybdenum
SPACES FOR
PARALLELED
PHASE A WINDING

The steel is vacuum-degassed, which minimises the


possibility of hydrogen-initiated cracking, and the
forging is hardened by reheating and quenching under
closely controlled conditions. Rough machining is
followed by a stress-relieving heat treatment.
Mechanical properties as high as 800 MN/m2 at 0.2%
proof stress, with 940 MN/m2 ultimate tensile strength,
are obtained in forgings for the largest
ratings. A reduction in area of 40%, elongation 15%,
Charpy V-notch impact level of 40 Joules, and a
fracture-appearance transition temperature of 20C,
are typical of this material, though specified pro-
perties are allowed to differ at different parts of the
CONNECTION OF PHASES
forging and in different test piece orientations. Stresses
in a rotor at 3000 r/min limit the practicable diameter
to about 1150 mm.
FIG. 6.10 Arrangement of stator conductors The rotor is examined ultrasonically from the sur-
face at various stages, and any significant defects
are reported. These are most likely to occur near the
cylindrical axis, and may be cleared by machining a
A somewhat similar effect is produced by the central axial hole, not usually larger than 100 mm
common practice of chording, or short-pitching. Here diameter, through all or part of the rotor. The critical
the return conductor is at an angle less than 180 defect size is established from considerations of crack
from its connected conductors. If is the angle by growth by fatigue, recognising that there will be a
which this falls short of 180 (Fig 6.13): small, but significant, once-per-revolution alternating
bending stress superimposed on the steady stress.
the ratio (1 - cos)/2 is the pitch factor, Kp (<1) Magnetic permeability tests are carried out at flux
densities up to 2.2 tesla, i.e., well into magnetic
saturation.
Hence, in the usual distributed short-pitched winding, The rough-turned forging is further turned by the
the generated voltage is nVKdKp, the harmonic con- generator manufacturer. The winding slots are then
tent is acceptably small, and the stepped rectangular cut, using accurately indexed milling cutters working
flux density wave generates a substantially sinusoidal at a controlled cut rate to minimise residual surface
voltage of fundamental frequency. stresses (see Fig 6.14).
456
Turbine-generator components: the rotor

FUNDAMENTAL

DEVELOPED VIEW
SHOWING STEPPED MMF WAVE
AND FUNDAMENTAL SINE WAVE

FIG. 6.11 The stepped magneto motive force wave

The shape and size of the winding slots are deter- keeping a low current density to minimise the loss
mined by an optmisation process, taking into account and temperature, as much of the area as possible
the following factors, and considering a radial cir- must be allocated to the winding copper.
cumferential section:
The winding insulation must be mechanically strong
The more ampere-turns the rotor can carry, the to withstand centrifugal and bending stresses, and
smaller the generator. Together with the need for stable to withstand load cycling. Adequate electrical
457
The generator Chapter 6

THE EFFECT ON THE


FUNDAMENTAL VOLTAGES

THE EFFECT ON THE


THIRD HARMONIC VOLTAGES

FIG. 6.12 The effect of distributing the stator winding over several slots

tracking distances from the winding to the rotor The whole centrifugal force of the slot contents, the
body must be provided, since the winding is in retaining wedge and the tooth is resisted by the
direct contact with the ventilating gas, and dirt narrowest section of the tooth, normally the tooth
and oil may collect on insulation surfaces. The root. There must be an adequate safety margin
insulation must therefore be more substantial than between the maximum tooth stress at overspeed and
the operating voltage of about 600 V would require the proof stress of the steel.
in other applications.

Passages for an appropriate flow of cooling gas The optimisation of these conflicting requirements
must be provided in the winding copper section, has led, in the latest designs, to a departure from
and also in the steel body section in some designs, parallel-sided slots to slots of trapezoidal section (Fig
to ensure that the specified temperature rise is 6.15).
not exceeded. The winding slots are cut in diametrically opposite
pairs, equally pitched over about two-thirds of the
The magnetic flux in the rotor is unidirectional periphery, leaving the pole faces without winding slots.
and normally substantially constant, so there is The resulting difference in stiffness in the two per-
no loss due to magnetic hysteresis or eddy currents, pendicular axes would produce a twice-per-revolution
but there must be an adequate magnetic section vibration; this is avoided by cutting equalising slots
particularly in the area of the winding slots. A in the pole faces (Fig 6.16). These are either similar to
high degree of saturation in the teeth would result the winding slots and are subsequently filled with short
in unacceptably high excitation requirements and steel blocks to restore the magnetic properties, or
losses. slits cut with a large diameter cutter in the radial

458
Turbine-generator components: the rotor

EFFECT ON
FUNDAMENTAL VOLTAGE

EFFECT ON
THIRD HARMONIC
VOLTAGE

EFFECT ON
FIFTH HARMONIC
VOLTAGE

FIG. 6.13 The effect of short-pitching the stator winding

circumferential plane, at intervals axially along the Because the rotor winding slots are cut radially,
pole faces. it is not possible to fit a preformed coil into the slots
During a three-phase sudden short-circut at the since the span of a coil is smaller the lower down
generator terminals, torque peaks of four to five the slot it is, and considerable distortion would be
times full-load torque are experienced between the required to get the coils in. Each turn is therefore
LP turbine and generator shafts. The generator rotor assembled separately, either as half-turns or in more
shaft and coupling at the turbine end must be designed pieces, with joints either at the centres of the end-
to withstand this peak torque with an adequate safety turns or at the corners, being brazed together after
margin. The coupling is usually shrunk on and keyed each turn is assembled, to form a series-connected
or dowelled, and has oil-injection grooves for removal. coil. Hard, high conductivity copper, with a small silver
A proportion of the coupling bolts are fitted, the content to improve its creep properties, is used for
others have a clearance to the coupling holes. the coils. Depending on the method of ventilation,
Journal and journal-type shaft seal surfaces are rectangular sections with grooves and/or slots, or
ground and polished to a high degree of circularity. tubular rectangular sections are used. When a trape-
Overall, good surface finishes and absence of sharp zoidal slot is used, the sections may be of several
blemishes are called for. Radii are made as large as different sizes. One or two turns in the width of the
practicable to minimise stress concentrations. slot are normally used. Radially-aligned slots provide
gas exit passages (see Fig 6.17).
The coils are not individually wrapped with insula-
tion. Instead, slot liners of moulded glassfibre, or a
3.2 Rotor winding composite of glassfibre and a more flexible insulating
Winding coils are assembled into pairs of rotor slots material, insulate the coils from the sides and bottoms
symmetrically disposed about the pole axis, but in of the slots, and a block of insulation separates the
opposite senses in the two poles, i.e., clockwise cur- top turn from the wedge. Between each turn, thin
rent flow for the 'north' pole and counterclockwise separators of glassfibre or similar material, serve to
for the 'south' pole. insulate against the 10 V or so between adjacent turns
459
The generator Chapter 6

FIG. 6.14 Cutting winding slots in a rotor

(Fig 6.18). Thick layers of insulation material on the Fans mounted on the rotor, primarily to circulate
inside surfaces of the end ring and end disc insulate hydrogen through the stator, assist the natural flow
them from the end windings. The spaces between through the rotor (see Fig 6.19).
turns in the end windings are partially filled with The ends of the winding are connected to flexible
insulating blocks, which ensure that the coils do not leads, made from many thin copper strips, which run
distort, and which contain holes and passages for radially inwards onto the shaft at the exciter end.
the transfer of ventilating gas. These leads are housed in two shallow slots in the
Because direct current circulates in the winding, shaft and are retained by wedges. At a point axially
there are no eddy current or other frequency related beyond the end windings, the leads connect with
losses in the rotor winding. The resistance (I2R) loss, radial copper studs and thence to D-shaped copper
amounting to 2 MW at rated load, together with the bars housed in the shaft bore. Seals against hydrogen
rotational (windage) loss, must be dissipated, and the leakage are provided on the radial studs. From the
average winding temperature must not be allowed D-leads, connections are taken either to sliprings
to exceed 115C. A cooling system is used, in which or to the shaft-mounted exciter connections in a
hydrogen is in direct contact with the copper con- brushless machine (see Fig 6.17).
ductors, for optimum heat transfer. The high ro-
tational speed produces a pressure head through the
rotor slots which causes hydrogen to flow from both
ends, under the end windings and axially through sub- 3.3 Rotor end rings
slots in the rotor and channels in the coils, whence Thick end rings are used to restrain the rotor end
it emerges radially through the wedges into the airgap. windings from flying out under the action of centri-
460
Turbine-generator components: the rotor

GAS EXIT

CURRENT CARRYING
CONDUCTORS

COOLING GAS DUCTS

MAGNETIC
FLUX

FIG. 6.15 Optimisation of a rotor section

fugal force. For electromagnetic reasons, these rings because of the coarse grain structure, particularly
have traditionally been made from non-magnetic steel, where the shape is complex.
typically a 18% Mn, 4% Cr austenitic steel. A 0.2% An austenitic steel, containing 18% Mn 18% Cr,
proof stress of 1000 MN/m2 is available to cope with has recently been developed which has shown virtual im-
the high operating stresses. A ring is machined from munity to stress-corrosion cracking in exhaustive
a single forging, and is attached to the end of the tests, while maintaining other properties at least as
rotor body with a shrink fit designed to provide a good as the older material. This alloy is being used in
small residual interference at 20% overspeed. The new machines and for replacement rings, eliminating
material has proved to be liable to stress-corrosion the need for periodic inspection.
cracking at the stresses involved, and all the surfaces ex- The end ring is prevented from moving axially
cept the shrink fit are given a protective finish to either by means of lugs mating with similar lugs on
ensure that hydrogen, water vapour, etc., does not the rotor body, or by small spring-loaded plungers
have access to the surfaces. Even so, it is recom- locating into grooves (see Fig 6.20). In both these
mended that rings are removed occasionally for de- designs, the ring must be rotated through a small
tailed surface crack detection using a fluorescent angle, when fully home axially, in order to lock. In
dye. Ultrasonic scanning is not entirely satisfactory, a different design, a screwed ring is used to pull the
461
The generator Chapter 6

SLIPRING
TERMINAL STUD
END BELL

POLE FACE

INERTIA SLITS SLIPRINGS

END BELL

ROTOR BLOWER

WINDING SLOTS
AND WEDGES

TURBINE
HALF COUPLING

FIG. 6.16 Stiffness compensation

462
POLE FACE
POLE SLOT POLE FACE DAMPING WINDING
END WEDGE VENTILATION HOLE p 0 LE F A CE
POLE SLOT \ \ E N D CAP KEY PACKING R A D 1 AL
iK,-rCD -r, .DM BALANCING
WEDGE PACKING INTER TURN R ) NG END WINDING
POLE SLOT
ROTOR BODY INSULATION INSULATION SUPPORT BLOCK
/ FILLER BLOCK
BALANCE WEIGHT SLOT
BALANCE RING
LOCKING SCREW
SLIPRING LEAD WEDGE
BOLT
LOCKING PLATE
SLIPRING LEAD

INSULATING TUBE

RADIAL
CONNECTION BOLT

SLIPRING LEADS

WINDING
VENTILATION HOLES

TOOTH
PACKING INSULATING
BALANCING / WEDGE SEPARATOR
PLUG HOLES / PACKING
SLIPRING , n m ,
DAMPING 7
BAR AND TAG RADIAL
CONNECTING CONNECTION
RING

COOLING GAS FLOW


COMPENSATING END CAP
WEIGHT WITHDRAWAL HOLES

FIG. 6.17 Rotor winding

463
Turbine-generator components: the rotor
The generator Chapter 6

a small taper to facilitate assembly and removal. It


is insulated from the end winding with either a
moulded-in glass-based liner or a loose cylindrical
sleeve.
The outboard end of an end ring is partially closed
by a shrunk-on annular steel disc which encloses the
EPOXIDE GLASS STRIPS
end wnding. Clearance between the end winding and
the shaft allows hydrogen to pass into entry ports
in the winding copper. No contact between the out-
EPOXIDE GLASS
board end of the ring and the shaft is permissible,
CAPPING since the shaft flexure could promote fatigue and
fretting damage at the interfaces. The end disc com-
monly contains facilities for adjusting the mechanical
balance of the rotor.
DOUBLE STRAP
COPPER COIL TURNS

NYLON PAPER 3.4. Wedges and dampers


INSULATION STRIPS
BETWEEN TURNS The winding slot contents are retained by a wedge,
which must be designed to withstand the crushing
stress on its lands and the bending stress across its
width, bearing in mind that it contains holes or slots
through which hydrogen passes. It must also be non-
magnetic in order to minimise flux leakage around
the rotor circumference, and to ensure a reasonable reac-
EPOXIDE GLASS
tance value.
SLOT LINER Extruded aluminium section is generally used, ma-
chined in the regions of high stress. If short axial
lengths are used, the potentiality for localised crack
initiation in the rotor teeth exists. One continuous
wedge per slot is therefore commonly used, although
these are more difficult to fit.
During conditions of rapidly changing flux, for ex-
ample, during system faults, or when an alternat-
ing flux links the rotor during unbalanced electrical
loading, when negative phase sequence currents and
fluxes occur, current is induced in the surface of
the rotor. Because the 'skin depth' of the magnetic
rotor steel is about 1 mm whereas that of the non-
magnetic wedges is an order of magnitude greater,
current flows preferentially in the wedges, which
form a 'damper winding' analogous to the rotor cage
of an induction motor. The wedges are of suffi-
cient cross-sectional area to carry the current cor-
responding to the expected unbalanced load, without
FIG. 6.18 Rotor slot damage due to overheating, but the areas of current
transfer into the end rings (which act as the short-
circuiting rings) have to be carefully designed. Thin cop-
per sheets with 'tongues' fitting under the ends
ring through its final few millimetres, and this also of the wedges form an interleaved ring under the
locks it circumferentially. inboard end of the end ring, and assist in the avoid-
The ring must be heated to about 300C to expand ance of localised areas of preferential current transfer
it sufficiently for the shrink surface to pass over its and hot spots.
mating area on the rotor. The heat is applied by a In pole faces having axial compensating slots, a
special cylindrical electrical heater. If a gas heater is similar arrangement is provided. In those with cross-
used, the ring surface is protected from the direct pole slits, a few very shallow axial slots are cut to
flame by a thin metal cover. accommodate copper damper strips, which are re-
The inner diameter of the ring is machined with tained by wedges, to transfer the surface current across
464
Turbine-generator components: the rotor

STOP KEY VANE BACK PLATE KEY

GAS
RESTRICTOR

OUTBOARD
END

ROTOR SHAFT

VENTILATION
SLOT

FIG. 6.19 Rotor fan

the slits, and prevent hot spots at the ends of the several brushes and holders on one of several re-
slits. movable brackets, each of which can be withdrawn
for brush replacement while running on-load, if spe-
cial precautions are observed (see Fig 6.22 inset).
Brush pressure is maintained by constant pressure
3.5 Sliprings, brushgear and shaft earthing springs. A brush life of at least six months should
Connections are taken from the D-leads in the bore, be obtained.
through radial copper connectors (which may have The brushgear is housed in a separate compartment
back-up hydrogen seals) and flexible connections, onto of the excitation housing, separately ventilated by a
the sliprings (Fig 6.21). For a 660 MW generator, shaft-mounted fan so that brush dust is not distri-
the rated excitation current is about 5000 A, and buted into other excitation components. Small leakages
sliprings must have a large surface area and run cool of hydrogen past the connection seals which might
in order to transfer this current satisfactorily. One accumulate in the brushgear compartments during pro-
design uses two sliprings of the same polarity in longed shutdown periods, are safely diluted by the
parallel. The ring surface is grooved and drilled to im- fan on start-up before excitation current is applied. Win-
prove its surface cooling. dows in the cover permit easy inspection of the
The brushgear shown in Fig 6.22 is arranged with brushgear.
465
The generator Chapter 6

FlG. 6.20 Rotor end ring

Monitoring of excitation current and voltage and It is normal for a large generator to produce an
rotor winding temperature by resistance measurement, on-load voltage of 10-50 V between its two shaft
is simply achieved in a generator with sliprings, using ends, due to magnetic dissymmetry and other causes.
a current shunt and voltage connections in one of This voltage would drive current axially through the
the excitation cubicles. Rotor earth fault detection, rotor body, returning through bearings and journals,
and the application of tests such as the recurrent causing damage to their surfaces, and insulation bar-
surge method for shorted-turn detection, are also riers are provided to prevent such current circulation.
simply arranged. These need only be at one end, the exciter end, but
Where no main excitation sliprings are fitted (Fig must be present wherever the shaft would otherwise con-
6.23), signal may be transmitted from the shaft, via tact earthed metal, for example, at bearings, seals, oil
telemetry. Alternatively, a set of light current sliprings scrapers, oil pipes and gear-driven pumps. In
and brushgear may be provided for signal monitoring some designs, two layers of insulation are provided,
and protection purposes. with a 'floating' metallic component between them,

466
' RING
LOCKING PLATE CLAMP NUT
RADIAL CONNECTION BOLT
COMPRESSION RING
LOCKPLATE
' RING / / SLIPRING CONNECTION STRIP
SLIPRING
CONNECTION TUBE SLIPRING CONNECTION RING

SEALING RINGS SLIPRING AXIAL LEAD

INSULATION UNDER SLIPRING

' RING

INSULATING BUSH

LOCKING SCREW

PLUG

ROTOR SHAFT

SLIPRING

SLIPRING AXIAL LEAD

TAPERED NUT
RETAINING PIN
INSULATING SEPARATOR

RETAINING DISC
INSULATING TUBE

SEALING GASKET

COMPRESSION PLATE
AXIAL LEAD TO
SLIPRING ' & '

AXIAL LEAD TO
SLIPRING 'B' & C

METHOD OF CONNECTING SLIPRINGS IN PARALLEL TO AXIAL LEADS


Turbine-generator components: the rotor

467
FIG. 6.21 Sliprings and connections
The generator Chapter 6

RUBBER GLOVE

INSULATED HANDLE

BRUSHGEAR SUPPORT BRACKET


PLASTIC RING
WASHER
BONDED INSULATING
TUBE
STEEL WASHER INSULATING CAP
INSULATING RING
TAPER PIN
BRUSHGEAR PALM
SPRING

INSULATING CAP TUBE SPANNER


LOCKING SCREW CONNECTING STUD

TUBE SPANNER

SPRING PROTECTION
COVER
RELEASE
STUD TRIGGER SECURING SCREW
METHOD OF SECURING BRUSHGEAR PALMS BRUSHARM
TO BRUSHGEAR SUPPORT BRACKET CRINKLE WASHER
CLAMPING BOLT- LOCKING PIN
GRUB SCREW
SPRING CLIP

FLEXIBLE
CONNECTION
DOWEL |-f- BRUSH BOX
LOCKING BAR' MILLED RECESS
CAIM
CARBON BRUSH
PLASTIC BUSH '
RIVET"
CONSTANT PRESSURE
SPRING

FLANGED INSULATING
BUSH

INSULATING CAP

EYEBOLT

MAIN GENERATOR
ROTOR SHAFT

SLIPRING

FIG. 6.22 Slipring brushgear and brushes

468
Turbine-generator components: the rotor

RETAINING RING INSULATION SPRING LOADED EXTENSION BAFFLE


\PLUNGER

ROTOR SHAFT END


STUD CONNECTOR

SHAFT BORE
CONDUCTORS

FIG. 6.23 Brushless rotor connections

so that a simple resistance measurement between the It is important that the shaft at the turbine end
floating component and earth confirms the integrity of the generator is maintained at earth potential,
of the insulation. and a pair of shaft-riding brushes connected to earth
While all the insulation remains clean and intact, through a resistor achieves this. Because carbon
a voltage will exist between the shaft at the exciter brushes develop a high resistance glaze when op-
end and earth, and this provides another method erated for long periods without current flow, a spe-
of confirming the integrity of the insulation. A shaft- cial circuit passes a 'wetting' current into and out
riding brush enables this shaft voltage to be moni- of the shaft through the brushes; this circuit also
tored, and an alarm is initiated when this falls below detects when brush contact is lost (Fig 6.24). A
a predetermined value. different scheme, in which a current carrying contact

TURBINE
GENERATOR
MAIN EXCITER 0 IL P U MP A ND
PIIOTFXCITER
PILOT EXCITER BARRING GEAR

JUNCTION BOX VOLTAGE MONITOR BRUSH - _ ^


JUNCTION BOX J-* I

RESISTORS -
FUSE HOLDER
LINK 1 OHM
-ZD- STATION
EARTH

DIAGRAM OF EARTHING BRUSH CONNECTIONS

FIG. 6.24 Shaft earthing and monitoring

469
The generator Chapter 6

or rub anywhere along the turbine-generator shaft slings throughout the operation. The use of a support
system can be detected, has also been used. trolley running on wheels of insulation material in
the bore is deprecated because of the core damage it
can cause. Adequate space for rotor insertion and
removal must be provided.
3.6 Fans The whole turbine-generator line of rotors is non-
Fans circulate hydrogen through the stator and coolers. flexibly coupled together and must be allowed to
Identical fans are mounted at each end of the shaft, attain its natural catenary shape if the bearing load-
each ventilating half the axial length of the generator. ings are to be satisfactory. The supports for the
Fans are either of the centrifugal type, with many generator (and exciter) rotors must be set up so that
vanes in one annular assembly, or of the axial-flow these rotors form part of the catenary. Coupling
type in which the propeller vanes may be separate alignments are accurately set by the use of bridge
bolted-on components (Fig 6.25). The diameter over gauges and concentricity checks, and the stator is set
the blade tips may exceed that of the stator bore, up so that the radial airgap is approximately constant.
necessitating the fitting of one fan after the rotor The axial position of the rotor train is fixed by
has been threaded through the stator. Inlet and outlet the thrust bearing, which is located in the turbine.
conditions are far from ideal, and though stationary Axial expansion of the turbine rotors downstream of
guide vanes are used to reduce swirl, the fan effi- the thrust face, and of the generator rotor, due to
ciency is low. Noise reduction is not a major concern, temperature changes, may amount to 25 mm or more,
since the massive stator casing is an effective acoustic and this must be accommodated in bearings, seals,
barrier. fan baffles, oil scrapers, etc.

3.7 Rotor threading and alignment 3.8 Vibration


The rotor must be inserted into the stator bore, which Rotors for generators of 500 and 660 MW operating
is about 250 mm larger than the rotor diameter. This at 3000 r/min are relatively flexible, and pass through
is accomplished by supporting the inserted end of two main critical speeds (natural resonances in bending)
the rotor body on a thick steel skidplate which slides during run-up to rated speed. Simple two-plane bal-
in the stator bore, while supporting the outboard end ancing techniques are not usually adequate to attain
from a crane (Fig 6.26). The skidplate spreads the the high degree of balance demanded at speed and
load over its area and prevents high local pressures to maintain reasonable vibration levels during run-up
being applied to the stator core laminations. The and run-down. Facilities for balancing are therefore
rotor and skidplate are pulled in using jacking ar- provided along the length of the rotor in the form
rangements until the inboard end emerges and can of tapped holes in the cylindrical surface, as well
also be supported in a sling. as in the closing discs of the end rings, and in other
Other methods are also in use; short lengths of locations at the ends.
extension shaft which are successively bolted onto The rotor is balanced at speeds up to 3000 r/min
the inboard end enable the rotor to be supported by in the manufacturer's works. The winding is then

FIG. 6.25 Axial flow fans on rotor

470
Turbine-generator components: the rotor

STAGE 1

Tt
er
S
STAGE 2

X3
It^frM ttpjf QflOnswi

STAGE 3
5 STAGE 4

2X
STAGE 5 STAGE 6

FIG. 6.26 Rotor insertion and withdrawal

heated and the rotor is run at 20% overspeed. This ally be partially offset by balancing, so that conditions
subjects the rotor to stresses greater than it would at operating temperature are optimised (see Fig 6.27).
experience in service, and also causes the winding Imperfect equalisation of the stiffnesses (see Section
and end rings to settle into their final positions. 3.1 of this chapter) will cause 100 Hz vibration to
Trim balancing is then carried out, if found to be occur, superimposed on the normal 50 Hz. It is im-
necessary. portant to distinguish between these components when
Some rotors exhibit a relationship between vibra- presenting or analysing vibration amplitude readings.
tion amplitude and temperature. A few degrees dif- A significant crack in the rotor will have a com-
ference in temperature between one pole and the paratively greater effect on the double frequency vibra-
other, due to inequalities in ventilation, for example, tion component; 'run-down' traces are recorded and
can cause this. If the effect is consistent, it can usu- analysed, to provide assurance that no significant
471
The generator Chapter 6

ORIGINAL HOT
OPERATING POINT

ORIGINAL
INCREASES
INCREASE WITH WITH TEMPERATURE
TEMPERATURE

ORIGINAL COLD BALANCE

1000 3000 AFTER OFFSET BALANCE, COLD


SPEED, r/min

(a) Typical speed-vibration curve (b) Vector plot of offset balancing

VECTORS REPRESENT AMPLITUDE AND PHASE ANGLE OF


SHAFT DISPLACEMENT OR SINUSOIDAL VELOCITY

FIG. 6.27 Rotor vibration

change has occurred since the previous run down. and are connected to the same lubricating oil system.
Oil whirl in bearings can cause vibration at 25 Hz. Seals are provided in both endshields to prevent
Vibration amplitude and phase are recorded at the escape of hydrogen along the shafts. Most of
generator and exciter bearings by accelerometers these seals are like small thrust bearings, in which
mounted on the bearing supports and by proximity a non-rotating white-metalled ring bears against a
probes which respond to the shaft movements. Var- collar on the shaft (Fig 6.28). Oil fed to an annular
ious degrees of sophistication, up to complete Fourier groove in the ring flows radially inwards across the
analysis, are available. face into a collection space at frame gas pressure,
The torsional resonance of the generator rotor while the radially outward flow is collected in an
coupled to the turbine rotors is of the order of atmospheric air compartment. The seal ring must be
13 Hz. It is important that this is significantly dif- held against the rotating collar, and must therefore
ferent from the frequency of torsional exciting in- be able to move axially to accommodate the thermal
fluences, of which the excitation and steam governor expansion of the shaft.
control (1-2 Hz), and transmission system resonances Some machines have seals which resemble small
are the most important. journal bearings (Fig 6.29), in which oil is applied
Transient oscillations in torque occur during elec- centrally and flows axially inboard to encounter the
trical disturbances, e.g., during switching operations, hydrogen pressure and axially outboard into an at-
lightning strikes, imperfect synchronising events, etc. mospheric compartment. Such a seal does not have
Some of the torque cycles may be large enough to to move axially, since the shaft can move freely inside
cause plastic deformation in the turbine-end shaft it. Details of the seal oil system are given in Section
and at the generator/exciter coupling. 5.3 of this chapter.

3.9 Bearings and seals 3.10 Size and weight


The turbine-end bearing is located in a common ped- A rotor for a 660 MW generator is up to 16.5 m
estal with the LP turbine outboard bearing. The ex- long and weighs up to 75 tonnes. It is provided with
citer-end bearing is either located in the endshield a cradle for transport. The rotor must never be al-
or in a separate pedestal. The white-metalled bearings lowed to be supported on its end rings; the weight
are spherically seated for ease of alignment, are pres- must be taken by the body surface leaving the end
sure lubricated and are provided with jacking oil tap- rings free. Lifting slings must only be used over the
pings. They are similar to the turbine bearings (see body length. It must be protected from water con-
Chapter 1), except that the outboard and exciter bear- tamination, while in transit or storage, by the use of
ings are insulated (see Section 3.5 of this chapter), a weatherproof container with an effective moisture
472
Turbine-generator components: the stator

OIL DEFLECTOR DIAPHRAGM OUTER INSULATING RINGS


RING RETAINING RING

WHITE METAL
SEAL FACE

FIG. 6.28 Thrust-type shaft seal

absorbent. If left inside an open stator, dry air must be transported. The completed core and core frame
be circulated. assembly was inserted into a substantial outer casing
Protection applied to journals, sliprings, etc., must for in-works testing and finally at site. Although
be removed before operation. Blanking tape and one-piece stators for 660 MW generators can now
collars, designed to prevent ingress of foreign ma- be transported, the two-piece concept has been con-
terial into the winding, must also be removed before tinued (see Fig 6.1).
operation.

4.1 Stator core


4 Turbine-generator components: the The core provides paths for the magnetic flux from
stator one rotor pole around the outside of the stator wind-
The stator must carry the output winding, provide a ing and back into the other pole.
low reluctance path for the magnetic flux, and with- As the rotor rotates, carrying its flux distribution
stand the torque produced, both at rated load and with it, all points in the stator core experience a
during faults. sinusoidally-varying 50 Hz flux density. This would
When generators rated 300 MW and above were induce a 50 Hz voltage of about 700 V axially in a
first specified, it was found that the smallest prac- solid core, and to prevent large circulating currents
ticable stator core, assembled into the lightest pos- with their associated losses, the core is made of thin
sible casing was too heavy for transport by road steel plates coated with an insulating material; the
in the UK, within the statutory limitation of that voltage induced axially in each plate is about 50 mV.
time. Since it is not practical to design a core in The sheet steel from which core plates are cut
sections for on-site assembly, and complete core conforms to BS601, which specifies dimensional lim-
building and winding on site has disadvantages, a its, magnetic properties, silicon content (normally 3%)
design evolved in which the core and windings were and state of annealing, and test methods. Sheet thick-
assembled into a skeletal core frame, which could nesses used are 0.35 and 0.5 mm, with a specific
473
The generator Chapter 6

GAS SIDE OIL


WIPERS

SEAL HOUSING

BEARING AND OIL


CATCHERS
SEAL RETAINING RING

SEAL CARRIER RING

SEAL OIL DRAIN


(GAS SIDE)

AIR SIDE OIL FLOW

GAS SIDE OIL FLOW

FIG. 6.29 Double-flow ring seal

total loss value at 1.5 tesla and 50 Hz of 3.55 W/kg, where required, for the passage of cooling gas, by
or better. building in a ring of thicker plates to which small
Core plates are cut to form segments of an annular steel bars have been welded. These bars are aligned
ring, twelve segments per ring being common. Wind- in a mainly radial orientation, and serve to distribute
ing slots, location notches and holes for ventilation the gas through the ducts. Holes in the plates are
(if required) are cut in one pressing operation. The arranged to be in axial alignment and thus form axial
use of dedicated dies is justified, since nearly a quar- ventilation ducts in some designs. At intervals during
ter of a million core plates are used in each 660 MW core building, heavy pressure is applied to consolidate
generator. The punched plates are ground to remove the assembly of plates.
edge burrs, and are then coated all over with one or When the build is almost complete, and with pres-
more thin layers of a baked-on insulating varnish. sure applied at the top end, the core is subjected to
With the core frame axis vertical, and one core a peripheral 50 Hz magnetic flux, which causes the
end plate in position at the lower end of the frame, plates to shake down further, following which the
a ring of core plates is assembled, located on dove- space created is filled with more core plates and the
tail-shaped keys on the inside periphery of the frame. top end plate is assembled and pulled down. Core
The radial butt joint between plates has as small flux tests are also carried out on the completed core,
a gap as possible to minimise magnetic flux distor- with a flux density in the back of the core 90-100%
tion. The next ring of core plates is assembled so of the rated value, in order to demonstrate freedom
that its butt joints do not coincide with those of from significant faults (Fig 6.31). If sufficient acci-
adjacent rings (see Fig 6.30). dental contacts between adjacent plates occur, it is
Gaps in the build-up of core plates are created, possible for current to flow, causing local hot spots.
474
Turbine-generator components: the stator

FIG. 6.30 Stator core assembly

An infra-red camera is used to scan the stator bore The net axial length of magnetic steel presented to
for areas of higher than normal temperature during the flux is less than the measured stacked length by
such a test. a factor between 0.9 and 0.95, known as the stacking
Some designs include a bonding agent between factor. This is because of the varnish layers (and
layers of core plates to ensure that individual plates, adhesive if present), and the air spaces between core
and particularly the teeth, do not vibrate independ- plate layers due to uneven plate thickness and im-
ently. Any wavyness in core build-up is corrected by perfect consolidation.
the use of suitable packing material. Slots for the stator winding conductors (bars) extend
Grain-oriented sheet steel, whose magnetic pro- radially from the bore. These slots have parallel sides,
perties are deliberately made different in the two so that the deep bars can be inserted radially, the
perpendicular axes, is used in some designs (Fig 6.32). teeth between them therefore increase in section with
Flux in a circumferential direction behind the winding increasing radial distance. The flux density in the
slots is arranged to coincide with the low loss orienta- teeth is therefore greatest at the bore, at the tooth
tion, which enables the back of the core to be op- tips, and is usually about 2 tesla for an acceptable
erated at a higher flux density than with non-oriented specific loss in the teeth. Since the slots and teeth
core steel, for the same specific loss. The opposite is are roughly equally wide at the gap, the mean peak
true for the teeth, where the flux is radial and the flux density in the air gap is typically 1 tesla. The
specific loss is higher than normal. A reduction in peak flux density in the core back is typically 1.5
outside diameter should be possible from magnetic tesla. Some leakage flux in the end winding regions
considerations, but the mechanical properties are ad- penetrates into the ends of the core. The axial com-
versely affected. Core plates of grain-oriented steel ponent of this flux induces alternating voltages in the
must be specially annealed after punching. teeth, and current flows around the teeth, as shown
475
The generator Chapter 6

FIG. 6.31 Flux test on completed core


(see also colour photograph between pp 482 and 483)

in Fig 6.33, causing unacceptable additional losses. perature at the bore, as well as the final steady
To reduce this effect, one or more radial slots are temperature.
punched in the teeth for a few centimetres at the As noted earlier, if accidental contacts occur (at
ends of the core, referred to as Pistoye slots. the tooth tips or due to burrs at, or damage to, the
The rotating magnetic field results in a rotating slot surfaces), a circuit may possibly exist for a cir-
radially-inward force being applied to the core across culating current. The current level depends, inter alia,
a diameter, causing an ovalising distortion moving on the contact resistances between the back of the
synchronously. The strength of the core and core core plates and the core frame bars on which the
frame assembly must be able to resist this force with plates are assembled. In some designs, all these bars
minimum strain, which is transmitted to the windings (except one which earths the core) are covered with
and the outer casing as a 100 Hz vibration. It is also insulating material, minimising the chance of current
important that the assembly has no resonances near circulation (Fig 6.35). In others, there is no insu-
to the exciting frequency. lation, and the contact resistance is not only random,
Hysteresis and eddy current losses in the core form but may vary with load as the torque reaction is
a significant proportion of the total loss. In UK transferred, causing a hot spot in the core to Switch*
designs, the heat produced by these losses is removed on and off.
by hydrogen circulating radially in the ducts and
axially through holes, where these are provided (Fig
6.34). Thermocouples are built into the core, parti-
cularly in regions expected to be hotter than average, 4.2 Core frame
to ensure that the maximum detected core temperature The fabricated steel core frame is designed to be as
does not exceed the specified value. If a hot spot light as possible consistent with its required functions,
exists, or develops in service, it is unlikely that there as previously explained. As well as the functions
will be a thermocouple sufficiently close to it to already noted, it must be able to resist elastically the
provide an unambiguous alarm. An occasional flux axial pressure applied to the core.
test, when opportunity occurs, offers a better chance A core end plate assembly consists of a thick disc
of hot spot detection. A deep-seated hot spot may of non-magnetic steel, with (usually) separate non-
be detectable by observing the rate of rise of tem- magnetic 'fingers' to support the teeth. Because bolts
476
Turbine-generator components: the stator

relieved, these additional welds are not.


Even though the axial frame members are outside
the core diameter, they link with the low level of
leakage flux existing in this area, and voltages are in-
duced axially along them. Near to the ends, elec-
tromagnetic end-effects tend to force the resulting
currents into the core and, if the assembly bars are
not insulated, core back burning and welding can oc-
cur. To prevent this, copper short-circuiting connec-
tions are fitted between assembly bars at the core
ends. Where the bars are insulated, the currents flow
into and around the core end plate.
The outer surfaces of the core end plates are
covered by conducting screens of copper or alumi-
nium, about 10 mm thick (see Fig 6.37, end plate flux
shield). Leakage flux impinging onto these screens
sets up circulating currents within them which prevent
the penetration of an unacceptable amount of flux
into the core end plate or the ends of the core. The
high conductivity and good surface exposure to
cooling hydrogen ensures that screen temperatures are
not excessive. The leakage flux is produced by a
DIAGRAMMATIC REPRESENTATION OF MAGNETIC FLUX
IN STATOR CORE, OPEN-CIRCUIT CONDITIONS
combination of stator and rotor MMFs, and there-
fore varies with load angle, or, roughly, with power
factor, the effect on the screens being most intense
at leading power factors.
AREA OF
MODERATE
The core end plate assembly carries the end winding
FLUX DENSITY ROLLING DIRECTION
support structure, and the design must ensure that
axial forces due to differential thermal expansion be-
tween core and winding do not force the end plates
into a position where core pressure is significantly
reduced.
The completed core and core frame assembly must
be jacked into position inside the casing, where it is
supported on feet with resilient mountings, or by flat
vertical support plates, either of which provide some
attenuation of vibration. The holding down bolts must
be designed to withstand the overturning torque pro-
duced during a sudden three-phase fault at the ter-
GRAIN-ORIENTED
CORE SEGMENT minals, which may be four to six times the full-load
torque.
FIG. 6.32 Flux in stator core

4.3 Stator winding


passing through the core would have high voltages The stator winding must be able to carry the rated
induced in them, the only permissible axial members current without exceeding specified temperatures and
are located outside the core back; these include the be able to withstand the voltage to earth induced in
core plate assembly bars. In order to apply pressure it. The currents and voltages in the three phases
uniformly over the core ends with such an arrange- must be exactly the same, but with a 2/3 time dis-
ment, the end plates are machined with tapered inner placement for balanced conditions, and so the wind-
faces, so that when they are pulled towards each ings associated with each phase must be identical
other they distort until they present a truly plane but separated by 27r/3 around the stator circumfer-
surface to the core, at which point the design pressure ence. It is convenient in large two-pole generators
is being applied to the core (Fig 6.36). to arrange each phase winding in two identical paral-
The core plate assembly bars are loose as the lel circuits, located diametrically opposite each other,
core is assembled, and are progressively welded to and, because they are influenced by rotor poles of
the frame as core building proceeds, using location opposite senses, connected back-to-back with each
plates. Thus, although the core frame may be stress- other (see Fig 6.10).

477
The generator Chapter 6

COOLANT MANIFOLD
WINDING FLANGED JOINT COOLANT INLET
CORE CORE FRAME CORE END LEAD W | N D | N G LEAD ' ' M A N I F 0 LD
P L A TE
/ CLAMP I

v
FLEXIBLE HOSE

-INSULATING SLEEVE

-INSULATING CAP

CONNECTING LINK

^CONDUCTOR NOZZLE

MAIN
FLUX

SUPPORT CYLINDRICAL GAS BAFFLE . PISTOYE


SADDLE FLASH SUPPORT RING SLOT
BARRIER

AXIAL VIEW OF
STATOR TEETH

FIG. 6.33 Pistoye slots in stator teeth

Slots must therefore accommodate six similar the slot next to the previous one, and the winding
winding circuits, differing only in phase displacement; continues in this manner until one-sixth of the slots
and 42, 48 or 54-slot arangements are commonly used. are filled. Because of short-pitching, some slots con-
A two-layer arrangement is adopted, in which a tain a top bar of one phase and a bottom bar of a
winding progresses from a top conductor (bar nearest different phase.
the bore) in a slot, bending in two planes after it A 776 MVA, 23.5 kV generator has a rated RMS
emerges from the core to span nearly a quarter of current of 19 080 A, i.e., a current of 9540 A per bar.
the circumference. At this point it is connected to a By cooling with water in contact with the conductor,
similar bar which continues the span but on a larger a current density of 8 A/mm2 of cross-sectional area
conical diameter, and re-enters the core as a bottom can be achieved. With a slot width of about 45 mm,
conductor almost opposite the first (not exactly op- and allowing for insulation, the effective conductor
posite because of short-pitching). This bottom bar is width is restricted to about 30 mm. Sufficient area
then connected, at its other end, to the top bar in must be allocated for satisfactory water flow, and
478
* DENOTES COLD GAS
~* DENOTES HOT GAS

FIG. 6.34 Stator ventilation


Turbine-generator components:
the stator

479
The generator Chapter 6

INSULATION

CLAMPING POSITION CLAMPING POSITION

EARTHING POSITION

CORE FRAME

CORE

DETAIL SHOWING CLAMPING AND EARTHING POSITIONS


VIEWED FROM TURBINE END OF CORE

FIG. 6.35 Insulated core frame bars

480
Turbine-generator components: the stator

ANNULAR RIB

LONGITUDINAL
BEAMS
CORE SUPPORT
BARS

CORE

CORE ENDPLATE

ENDPLATE FLUX
SHIELD

SIDE BEAMS

TRUNNION
MOUNTINGS

FRAME FEET

HOLDING-DOWN
BOLT HOLES

FIG. 6.36 Core frame

the radial conductor dimension becomes about 40 mm, effect is not quite nullified since leakage fluxes occur
with the overall radial bar dimension about 80 mm. in the end winding areas also, and some designs use
A current carrying conductor embedded in a nar- a transposition of greater than 360 in order that these
row slot in a magnetic material drives magnetic flux end effects shall not be additive.
around itself, mainly confined to the magnetic teeth, A differential eddy current voltage still exists bet-
but completing its circuit by crossing the 'airgap' ween the top and bottom of each strip, and current
represented by the slot width, further up the slot than will flow around it. The loss due to this current varies
the conductor (Fig 6.38). If the conductor is viewed as the fourth power of the radial dimension of the
as an assembly of separate strips, it can be seen that strip, so the incentive is to make the strip very thin.
the leakage flux density experienced by each strip However, the space required for insulation then
increases linearly with distance from the bottom strip. becomes excessive and compromise is needed. Water
This alternating leakage flux induces alternating volt- is circulated in rectangular section tube, which must
ages along the lengths of the strips, in quadrature with have a considerable depth, and in some designs an op-
the main voltage, and varying as the square of the timised mixture of tubes and thinner solid strips is
distance of the strip from the slot bottom. If a solid used (see Fig 6.40).
conductor were used, or if the strips were connected Conductors are made of high conductivity hard-
together at the core ends, these unequal voltages drawn copper. Each strip or tube has a thin coating
would circulate current around the bar, causing un- of glassfibre insulation, and is cranked to enable
acceptable eddy current losses and heating. all the strips in a bar to be assembled with the
In order to minimise this effect, the conductor Roebel transpositions correctly made. The bar ends
is divided into strips, which are lightly insulated, are bent using formers to give the required shape of
arranged in two or four stacks in the bar width. The end winding. The strips are bound together and the
strips are transposed along the length of the bar by main insulation is applied; a tape of mica powder
the Roebel method (Fig 6.39), in which each strip oc- loaded with a synthetic resin, with a glassfibre back-
cupies every position in .the stack for an equal axial ing, is wound without breaks along the length of
length, so that the eddy current voltages are equalised the bar. The straight part of the bar is pressed in
and no eddy currents circulate between strips. The a heated mould to cure the resin and obtain the
481
The generator Chapter 6

lidated and free from significant voids, and electrical


tests confirm the integrity of the insulation. The
insulation is very hard and the insulated bar has
little flexibility.
The slot length of each bar is treated with semi-
conducting material to ensure that bar-to-slot elec-
trical discharges do not occur, and a high resistance
stress grading finish is applied to the ends to control
surface discharge, particularly during high voltage
tests.
Bars carrying such large currents experience large
forces; in the slots these are directed radially out-
wards towards the bottom (closed end) of the slot,
and alternate at 100 Hz. The closing wedges therefore
are not required to restrain the bars against these
forces, but it is important that the bars do not
vibrate, and the wedges are arranged to exert a radial
force, either by tapered packers or by a corrugated
glass spring member. Some designs use a corrugated
glass spring packer in the slot side to provide side-
ways restraint. Packers of insulation material, se-
CORE parators and drive strips, and layers of conformable
ENDPLATE
thermo-setting dough are also used in the slot fill
(see Fig 6.40). Support of the end windings and the
arrangement of connections are dealt with in later
sections.
The electrical loss due to the stator winding is
STATOR INNER FRAME RIB
traditionally separated into the I 2 R loss, using the
measured DC resistance of the winding phases at the
operating temperature, and the 'stray' loss, in which
FIG. 6.37 Core end-plate and screen are included components due to:

AC resistance being greater than DC resistance


design dimensions, while the curved ends are con- (skin effect).
solidated using heat-shrinkable tape. Tests are carried
out to ensure that the insulation is properly conso- Eddy currents, as already noted.

DISTANCE FROM
SLOT BOTTOM, X

SLOT (a) CURRENT BELOW X (a) FLUX LINKAGE AT X DISTRIBUTION OF


CONTAINING (b) MMFAT X (b) EDDY VOLTAGE AT X EDDY CURRENT
IDENTICAL
CONDUCTORS

FIG. 6.38 Illustrating the variation of eddy currents in stator conductors

482
FIG. 4.24 Heysham 2 condenser - modular construction

FIG. 6.31 Flux test on completed core


FIG. 6.41 View of a 660 MW generator stator end-windings
FIG. 6.90 Condition monitor (NEI Parsons Ltd)
FIG. 6.97 Dinorwig motor-generator during site winding
Turbine-generator components: the stator

FIG. 6.39 Roebel transpositions

Currents induced in core end plates, screens, and forces are produced, both at rated load and parti-
end teeth. cularly when large current peaks occur during fault
conditions. The end turns must be strongly braced
Harmonic currents induced in the rotor and end to resist the peak forces and also to minimise the
ring surfaces. 100 Hz vibration.
Currents induced in frame, casing, endshields, fan The MMF produced in the end winding region by
baffles, etc. the combined effect of the stator and rotor end wind-
ings produces a considerable magnetic flux in the
end regions. Paramagnetic material would tend to
These individual losses have to be assessed so that concentrate the flux into itself, and electrically-con-
the appropriate cooling medium is directed to their ducting material would have eddy currents induced
sources, in order to avoid unacceptable localised hot in it, causing both additional loss and potential hot
spots. spots. Metallic inserts and fastening devices can be
caused to vibrate and loosen, or wear away their
surrounding medium. Consequently non-metallic com-
ponents are used, mainly moulded glassfibre.
4.4 End winding support Substantial support brackets are bolted to the core
In the end windings, bands of conductors are arranged end plate and provide a support for a massive glass-
side-by-side, all carrying the same current although fibre conical support ring. The outer layer of end
not all in phase, and considerable electromagnetic turns is pulled onto a bedding of thermosetting con-
483
The generator Chapter 6

EACH BAR COMPRISES


BOTTOM INSULATION
2 GROUPS OF
2 STACKS OF STRAPS PACKING STRIP AND
CONFORMABLE DOUGH
V t t t t t t ft///t /

CROSSOVER INSULATION

- PACKER

.STACK VERTICAL
SEPARATORS
ALTERNATE SOLID
AND HOLLOW
GROUP BINDING TAPE
COPPER CONDUCTORS

RIPPLE SPRING
-ASBESTOS FINISHING TAPE

BOTTOM COIL -

INSULATION PACKING STRIPS


AND CONFORMABLE DOUGH
BETWEEN COILS

GROUP VERTICAL
SEPARATOR

ALL HOLLOW - MAIN INSULATION WRAP


COPPER CONDUCTORS -

- STRAP INSULATION

TOP COIL

PROTECTIVE DRIVING STRIP

CLOSING WEDGE
- OPPOSED TAPER WEDGES
APPLYING RADIAL RESTRAINT

FIG. 6.40 Stator slot

484
Turbine-generator components: the stator

formable material between it and the support cone, nals are housed on the external stems of the bushings.
and packers between the bars arch-bind the structure The connections from the generator terminals to the
circumferentially. The inner layer is treated similarly, generator transformer are described in Volume D.
with a ring of blocks pulled down onto the cone Phase isolated connections are always adopted, so
by through-bolts, completing the very rigid structure. that an electrical fault at the connections must start
Some designs use sheets of insulation material to as a line-to-earth fault, which is much less damaging
enclose any spaces and prevent the accidental ingress to the generator than a line-to-line fault.
of any foreign material. Magnetic material is parti-
cularly unwelcome, since it can be caused to vibrate
and abrade, or be heated by eddy currents and de-
grade the adjacent insulation (see Fig 6.33). Vibration 4.6 Stator winding cooling components
of the end windings must be minimised, since it can Water is the best of the commonly available media
promote fatigue cracking in the winding copper. This for cooling the stator winding, and imposes only one
is particularly serious if it occurs in a water-carrying condition that would not also apply to other fluids: it
tube, since hydrogen will leak into the water circuit. must be pure enough to be effectively non-conducting
Resonances close to 100 Hz must be avoided, since (electrically). It is continuously degassed and treated
both the core ovalising and the winding exciting force in an ion exchanger, with the following target values
occur at this frequency. Accelerometers in the end being aimed for:
winding structure allow any increase in vibration due
to support slackening to be monitored. Vibration am- Conductivity: 100 /*S/m
plitude is highly current dependent. Any looseness
developing after a period in operation can be cor- Dissolved oxygen: 200 /tg/litre max (in some
rected by tightening the bolts, by inserting or tighten- systems >2000 is acceptable)
ing wedges, and/or by pumping a thermosetting resin Total copper: 150 /ig/litre max.
into rubber bags located between conductor bars.
Figure 6.41 shows the stator core and end windings pH value: 9 max.
for a 660 MW generator.
At these levels, no aggressive attack on the winding
copper has been noticed after very many years' ex-
perience. Any erosion of copper is detected by the
4.5 Electrical connections and terminals monitoring equipment.
Electrical connections between one conductor bar and Water is passed into one or more inlet manifolds,
the next in series are made differently in different which are copper or stainless steel pipes running cir-
designs. In one, a common electrical and water con- cumferentially around the core end plate. From the
nector is formed by a copper tube bent into a U-shape, manifolds, flexible PTFE hoses are connected to all
and brazed onto small copper waterboxes into which the water inlet ports on the stator conductor joints.
all the bar subconductors are brazed. In another, the In a two-pass design, water passes through both bars
electrical joint is made by a solid copper bolted joint, in parallel and is transferred to the two connected
with the water connections separate. It is common bars at the other end, returning through similar hoses
practice to insulate the joint or to enclose it in a to the outlet manifold which adjoins the inlet mani-
rubber housing. fold. This design minimises the number of hoses,
The conductor bars at the high voltage end (line but requires a larger pressure head of water across
end) and the low voltage end (neutral end) of a phase the winding (see Fig 6.43). In a single-pass arrange-
band are electrically connected to tubular connectors ment, hoses connect both ends of a bar to the
which run circumferentially behind the end windings manifolds, which are located at opposite ends.
at the exciter end, to the outgoing terminals, usually Thin metallic-sleeved components are crimped in-
with line terminals at the bottom and neutral ter- side and outside the ends of the PTFE hoses, and
minals at the top, although other arrangements do these are then attached to bosses on the manifolds
exist. These connectors are internally water cooled, and winding connectors, using sere wed-up olives,
and must be insulated for line voltage. O-rings or brazed joints. The casing hydrogen pressure
Terminal bushings (Fig 6.42) are proprietary paper- is everywhere greater than the water pressure in the
insulated items, with internal water cooling from the winding circuit, so that any leakage is of hydrogen
stator winding water system. Their insulation must into water, rather than the reverse, which would be
be capable of withstanding the hydrogen pressure in damaging to the winding insulation.
the casing, with no perceptible leakage. It is common The loss input into the water circuit at rated load
practice to flange-mount the terminals on a plate of is designed to raise the water temperature by less
non-magnetic material, and to arrange for a terminal than 30C. With an inlet temperature of 40C, there
to be withdrawable from outside the casing. Current is plenty of margin before the\temperature at which
transformers for instrumentation and protection sig- boiling would occur, 115-120C at the working pres-
485
The generator Chapter 6

FIG. 6.41 View of a 660 MW generator stator end-windings


(see also colour photograph between pp 482 and 483)

486
Turbine-generator components: the stator

GAS SIDE

CONNECTION PALM

AIR SIDE

FIG. 6.42 Generator terminals

487
The generator Chapter 6

^ EXCITER END

COIL-TO-PHASE
RING CONNECTIONS

COIL-TO-COIL
CONNECTIONS

FIG. 6.43 Stator winding water cooling system components

sure. Monitoring the temperature of each bar by horizontally inside the casing; they consist of banks
thermocouples, either in the slots or in the water of finned or wire-wound tubes through which water
outlets, enables a reduction or stoppage of water flow flows in one or two passes while hydrogen flows over
in a bar to be detected. them. The coolers are arranged so that their headers
are accessible (for tube cleaning) without degassing
the casing. The tubes and the cooler frame must be
supported so as to avoid resonances close to the
4.7 Hydrogen cooling components principal exciting frequencies of 50 Hz and 100 Hz.
The advantages of hydrogen cooling, and its para- It is most important that moisture does not con-
meters, are described in Section 5 of this chapter. dense on the stator end windings, since electrical
Hydrogen enters the generator casing through an breakdown may then occur. The dewpoint of the hy-
axially-oriented distribution pipe at the top, carbon drogen (at casing pressure) must be at least 20C
dioxide for scavenging being admitted through a simi- lower than the temperature of the cooled hydrogen
lar pipe at the bottom. emerging from the coolers, and this is continuously
The rotor fans circulate hydrogen over the end monitored by a hygrometer. In normal on-load op-
windings and through the stator core, while a parallel eration, the stator winding water maintains the wind-
flow passes through the rotor. At rated load, the ing temperature above 40C; if condensation occurred
hydrogen temperature increases by about 25C during it would be on the hydrogen coolers first. During
the few seconds taken to complete this circuit. Two run-up, however, the stator winding water is likely
or four hydrogen coolers are located vertically or to be cold, and it is either pre-heated electrically, or
488
Turbine-generator components: the stator

circulated for a lengthy period, to warm the winding runners to accommodate the hydrogen coolers. At
before the generator is excited. the ends, thick rings provide facings for the separate
end shields. Internal supports for the core frame, in
the form of horizontal footplates or spring plate fix-
ings, are provided, and external feet support the
4.8 Stator casing complete assembly. Lifting trunnions are usually made
The casing contains the stator core and core frame, detachable.
and must resist the load and fault torques. It must The design of the welded joints is carefully con-
also provide a pressure-tight enclosure for the hy- trolled to avoid the presence of unfused lands wherever
drogen. Historically, casings have been made strong possible. The main welds have to be leak-tight against
enough to withstand the pressure developed by an hydrogen at 4 bar, which is a very exacting require-
ignition of the most explosive mixture of hydrogen ment. The complete casing may be too large to be
and air, without catastrophic failure. stress-relieved in an annealing oven, in which case
Because any mixture of hydrogen and air within it must be assumed that stresses up to yield stress
the explosive range is not allowed to occur, attain- exist in the welds. In one design, the casing is con-
ment of explosion pressure is not a credible condition, structed in two halves, which are stress-relieved before
and to specify the casing on the basis of withstanding being welded together.
such a pressure without leaks, as would be required The end shields are thick circular fabricated steel
by BS5500, is unrealistic. Consequently, the full re- plates, ribbed to withstand the casing pressure with
quirements of the pressure vessel code are not invoked, minimal axial deflection. They house the shaft seal
though some of them are applied. This pragmatic stationary components and, in some designs, the out-
approach has been justified by worldwide experience over board bearing. Leak-free sealing of the end shield/
fifty years. casing joints against the hydrogen pressure, as with
Casings are fabricated steel cylinders of up to all other casing joints, is effected by gaskets, O-rings
25 mm thickness, reinforced internally with annular rings and sealing compounds injected into grooves.
and axial members which strengthen the structure and The completed casing assembly is hydraulically pres-
form passages for the flow of hydrogen (see sure tested, and finally must be demonstrated to be
Figs 6.44 and 6.45). Internal spaces are provided with leak-tight to a level corresponding to a fall from

COOLER ENCLOSURE
POCKET
FRAME WRAPPER NEUTRAL TERMINAL
TURBINE END PLATE ENCLOSURE
RUBBER
SEALING RING

ROTOR
COOLING GAS
COOLER SEAL DUCTS
BARS /

INNER STATOR
SUPPORT PLATFORM

FRAME
FEET
JACK SUPPORT
BRACKET

MAIN TERMINAL
ENCLOSURE

FIG. 6.44 Outer stator casing

489
The generator Chapter 6

FIG. 6.45 Core frame being inserted into casing

490
Cooling systems

rated hydrogen pressure of not more than 0.035 bar ductivity and specific heat of hydrogen, the effect
in 24 h. is that heat removal from heated surfaces is up
Some of the core vibration is transmitted to the to ten times more effective, resulting in lower tem-
casing, and rotor vibration is transmitted through the peratures. Coolers can also be considerably smaller.
end shield and the foundations. The casing assembly
must be designed to avoid resonances in the range The use of hydrogen imposes the need for herme-
of these exciting frequencies. tic sealing and condition control, which helps to
Drains are arranged so that any oil or water col- ensure that the original electrical clearances are
lecting in the bottom of the casing is piped to liquid maintained.
leakage detectors, which initiate an alarm. Distri- More importantly: the degradation of insulation
bution pipes for hydrogen and C 0 2 are built-in; a by oxidation processes cannot occur in a hydrogen
temperature sensor at the C 0 2 inlet initiates an alarm atmosphere.
if the incoming gas has not been adequately heated
and could chill the fabricated casing locally. Electrical
heaters are fitted in the lower half of the casing to The disadvantages are:
maintain dry conditions during outages. Since concentrations of from 4% to 76% of hy-
The casing is bolted down to the supporting steel- drogen in air are explosive, hydrogen must not be
work on packing plates which are machined after allowed to escape from the stator casing and its
trial erection to provide the correct alignment. Axial associated pipework in significant quantities and
and transverse keys prevent subsequent movement. become trapped in potentially explosive pockets.
The weight of the casing, complete with core frame, The casing and end shields have to be of rugged
coolers and water, is up to 450 tonnes. construction and leak proof, demanding meticulous
welding techniques. Penetrations such as the rotor
shafts, and all outgoing connections, must be posi-
tively sealed, the former requiring a sophisticated
5 Cooling systems sealing system.
A generator of this type has an efficiency of about
98.5%. Even though the losses are low in terms of A comprehensive gas control system is required.
the output, they amount to some 10 MW, all of For generators rated much above 100 MW, air cool-
which must be removed by the cooling systems; the ing is not practical; more than half the total loss
heat lost by convection and radiation from the casing would be due to fan and rotor windage. At 500
is not significant. and 660 MW, hydrogen pressures of 4 or 5 bar are
In some stations, most of the generator (and exciter) economic; higher pressures than this have little or
losses are transferred into the boiler feedwater system no advantage. The only practical alternative at
by using condensate in the heat exchangers. While these ratings is complete water cooling including
such an arrangement can be economic, there is a the rotor, which has not been adopted in the UK,
penalty in the form of added complication, and the and only rarely elsewhere, because of leakage pro-
most modern stations do not have this feature. blems at the very high water pressures produced
by the rotation.

5.1 Hydrogen cooling


Hydrogen has several advantages over air as a means 5.2 Hydrogen cooling system
of removing heat from turbine-generators: It is necessary to ensure that potentially explosive
mixtures of air and hydrogen do not occur when filling
The density of hydrogen is the lowest of all gases the casing with hydrogen, or when emptying it.
and is one-fourteenth that of air. Even at the rated The usual method is to use carbon dioxide as a
pressure (4 or 5 bar) and with the allowable level buffer between the two other gases, in a process known
of gaseous impurities, it is still only half as dense as scavenging, or simply gassing-up and degassing.
as air at normal temperature and pressure (NTP). Carbon dioxide, stored as a liquid under pressure,
The large loss due to the gas being churned by is expanded to a suitably low pressure above atmos-
the rotor, and to its circulation through the fans pheric. It is also heated, because the expansion causes
and cooling passages, is minimised by the use of it to cool and it would otherwise freeze. With the
hydrogen as a coolant. rotor stationary, C 0 2 is fed into the bottom of the
stator casing through a long perforated pipe, and
The heat transfer capability of hydrogen is up to because it is more dense than air it displaces air from
twice that of air in similar conditions, though, as the top via the hydrogen inlet distribution pipe to
with all gases, it increases with increasing pressure. atmosphere outside the station. Some mixing of gases
Together with the several times higher thermal con- occurs at the interface. A gas analyser is used to
491
The generator Chapter 6

monitor the proportion of C0 2 in the gas passing to tored by several thermocouples, whose readings should
atmosphere; when this is sufficiently high, the C0 2 be averaged, at the inlets to and outlets from the
inlet is closed (see Fig 6.46). hydrogen coolers. Typically, hydrogen is circulated
High purity hydrogen from a central storage tank at 30 m 3 /s which, with a full-load loss input of about
or electrolytic process is then fed through a bus main 5000 kW, results in a temperature rise of the order of
at about 10 bar to the gas control panel, where its 30C. The cooled gas should not be hotter than 40C,
pressure is reduced before being fed to the casing so the temperature of the gas entering the coolers
through the top admission pipe (Fig 6.47). Being very should not exceed 70C.
much lighter, it displaces the C0 2 from the bottom Water cannot normally leak into the casing from the
of the casings via the C0 2 pipe to atmosphere, again stator winding water circuit or the hydrogen coolers,
with some degree of mixing. When the proportion since the water pressure is lower than the gas pressure
of C0 2 in the vent is low enough, the proportion in both circuits. It can be released from the shaft
of air left in the casing will be very low, and if the seal oil, particularly if the oil is untreated turbine
casing is then pressurised with hydrogen to its op- lubricating oil which has picked up water from the
erating pressure (say 4 bar), the proportion of air turbine steam glands. It is important that the mois-
will be reduced to a quarter of this low value. The ture content of the casing hydrogen be kept low
complete process normally occupies a few hours. enough to prevent condensation occurring on the
Separate procedures are followed to ensure that coldest component, which may be the water cooled
other components, such as tanks, are properly scav- winding. The differential pressure is used to circulate
enged, so that dangerous mixtures do not occur. The a flow of hydrogen continuously through a dryer,
reverse of the foregoing procedure, using C0 2 and typically of the twin-tower type, using activated alu-
then dry compressed air, is followed to remove mina, with automatic changeover and regeneration. A
hydrogen from the machine for inspection or for a motor-driven blower maintains the flow through the
prolonged outage. rotor when the rotor is not running at speed (see Fig
In one design of 500 MW generator, air is removed 6.49).
from the casing by drawing a vacuum, using the Continuous monitoring of the humidity of the cas-
pump normally used to degas the seal oil. The shaft ing gas is provided by means of a hygrometer. The
seals are arranged to seal effectively under this unusual maximum permissible dewpoint is not less than 20C
operating condition. When the vacuum is as low as below the cold gas temperature, measured at casing
can be achieved, hydrogen is admitted, the resulting pressure. It is important that this caveat is observed,
purity when pressurised being sufficiently high. particularly if the dewpoint is being compared with
Normally, hydrogen purity remains high, since air that of a sample drawn from the casing and measured
cannot leak into the pressurised system. Some air at atmospheric pressure.
may, however, be released from the shaft seal oil Hydrogen is circulated by the fans through the
flowing into the casing hydrogen space. Replacement stator core and end windings, the precise paths being
hydrogen to make up for leakage is usually sufficient different in different designs. The rotor acts virtually
to maintain the required purity. as its own fan, hydrogen being drawn through the
The differential pressure developed across the windings and exhausted into the airgap, again dif-
rotor fans is used to circulate a sample of casing ferently in different designs. The hydrogen removes
hydrogen continuously through a katharometer-type the electrical loss in the rotor winding, the Iron loss'
purity monitor, which initiates an alarm if the purity in the stator core, the windage loss produced by the
falls below a preset value, typically 97%. The purity rotor and fans, and most of the electrical losses gen-
monitor (and the gas analyser) can be calibrated with erated in the frame and end winding structures.
pure gases from the piped supplies. A check on the Because it is impractical to ensure that potentially
purity is also possible by monitoring the differential explosive mixtures of hydrogen and air never occur
pressure developed by the fans, which responds in the small bore instrumentation pipework, those
markedly to the change in density produced by air instruments and devices containing electrical circuits
impurity. in contact with the gas, such as katharometers, must
A pressure sensitive valve admits hydrogen from be intrinsically safe in such mixtures. This means that
the bus main if the casing pressure falls below a pre- a sudden break in an electrical circuit must not be
determined level, while a spring-loaded relief valve capable of providing enough spark energy to ignite
is set to release hydrogen to the outside atmosphere the gas.
if the pressure becomes excessive. It is important It is impossible to ensure complete freedom from
that these two pressures are not set so close that leakage of hydrogen over the lifetime of the plant,
wastage occurs, particularly as the gas temperature and the areas near to potential leakage sources are
and pressure changes when on-load cycling. Monitoring classified into zones of differing degrees of hazard,
of the hydrogen consumption is a recently introduced described in detail in CEGB Code of Practice 098/34:
feature on some units (see Fig 6.48). 'Code of Practice for the Design Principles relating
The temperature of the hydrogen is normally moni- to the use of Hydrogen in Large Generators'. Zones 0
492
Cooling systems

PERFORATED ADMISSION PIPE


EXCITER
GENERATOR STATOR CASING END

t~~n
TO
ATMOSPHERE

-M-
Hxh

LIQUID
ALARM
'CHAMBERS

C 0 2 KATHAROMETER

rO-o*&
I
M-

-M-

H 2 KATHAROMETER
L X

- -M-
GENERATOR GAS
DRYING SYSTEM

H
HXH
-*H GAS CONTROL

CH
EMERGENCY PANEL

INTEGRATING
FLOW METER , FROM C0 o
-M M- f ^ - SUPPLY2

x
-M-
-tx-
1 -M-
-M-
FROM
-HYDROGEN LP
DELIVERY MAINS

"AIR
-co

FIG. 6.46 Generator gas system displacing air with C 0 2

493
The generator Chapter 6

INTEGRATING
FLOW METER FROM C0 0
SUPPLY ^

FROM
* - HYDROGEN LP
DELIVERY MAINS

"2
C0 o

FIG. 6.47 Generator gas system displacing C 0 2 with H 2

494
Cooling systems

PERFORATED ADMISSION PIPE

m n
TURBINE EXCITER
END GENERATOR STATOR CASING END


TO

t i
ATMOSPHERE

-M-
-M
Hxh

X
-M- -M-
LIQUID


ALARM HXP
'CHAMBERS

-M-

C 0 2 KATHAROMETER

-M-

L
-M-

X GENERATOR GAS
DRYING SYSTEM

H 2 KATHAROMETER
H -M-

[>i

HX- **H GAS CONTROL

CH EMERGENCY PANEL

INTEGRATING hXI-
FLOW METER FROM CO,
-M- -M- (^-SUPPLY 2

x

-XH
-M-
-X-
FROM
*- HYDROGEN LP
DELIVERY MAINS
#"

C0 o

FIG. 6.48 Generator gas system in normal operation

495
The generator Chapter 6

H2 OUTLET
PURGE AIR
VENT PRESSURE ,
H E R
. DIVERSION
DIVERSION
VALVE TO DIFFERENTIAL PRESSURE
SWITCH/SAMPLING POINT

PRESSURE GAUGE

PRESSURE GAUGE
STOP VALVE

TOWER 'B'

HEATER SUPPLY
CABLES
PURGE AIR PRESSURE
REDUCING VALVE

THERMOMETER

THERMOMETER

CONTROL
PANEL
CO,
REGULATOR

5-PORT
SHUTTLE VALVE

DIVERSION
DIVERSION VALVE
DIVERSION VALVE
V A L VE
DIFFERENTIAL
FLEXIBLE PRESSURE
BLOWER BELLOWS SWITCH
1 1 FLEXIBLE UNIT
MOTOR COUPLING

FIG. 6.49 Gas dryer and blower

and 1, in which explosive mixtures exist continuously virtually impossible to eliminate some potential igni-
or occur in normal operation, should not be present tion sources, such as the rotating shaft rubbing an oil
if the principles outlined above are followed. Zone 2, scraper ring, or sparking at brushgear.
in which explosive mixtures are unlikely to occur Another potential source of ignition occurs where
and, if they do will only exist for a short time, covers currents are induced in pipework loops, as may be
instrumentation as previously noted; the hydrogen the case when pipes are routed near to main con-
dryer and blower, the detraining tanks, and the in- nections. Here, flanged joints are insulated to break
terior of the control cubicle to which hydrogen is the possible current path.
piped. Also classified as Zone 2 are the areas into If a serious rupture occurs, e.g., the break-up of
which hydrogen may leak, through gaskets, seals, etc., a shaft seal, hydrogen may escape very rapidly, and
knowing the normal pressure behind the gas and its if it encounters a source of ignition, say the shaft
propensity for rapid upward movement. Sources of rubbing, it will burn intensely in the ambient air. In
ignition are not located in such areas. It is, however, order to vent the casing to atmosphere outside the
496
Cooling systems

station, and to admit C0 2 to the casing, duplicated in the white-metalled ring, and flows along the clear-
valves are provided, one set being located remote from ances between the shaft and the bore of the seal,
where any fire is conceivable (see Fig 6.50). both outwards to the drain and inwards to the hy-
Hydrogen has been used universally for 50 years drogen pressurised space. The inward flow rate is
for high speed generator cooling, and incidents such much greater than that for the thrust type, because
as this have been very rare. The meticulous attention it is not inhibited by centrifugal force, and it would
to safety precautions both in design and operation be capable of contaminating the hydrogen purity to
have been largely responsible for this good record. an unacceptable extent. To prevent this, all the oil
fed to the seals is subjected to vacuum treatment, in
which much of the air and water is removed. Against
this disadvantage, it is claimed that the journal type
5.3 Shaft seals and seal oil system seal is inherently better able to withstand disturbances
Seals prevent the escape of hydrogen where the rotor of the shaft by expanding to provide a larger clear-
shafts emerge through the casing end shields. What- ance for oil flow if it is heated by excessive shaft
ever their design, they are located in the end shields, movement.
and are inboard of the bearings. Two types of seal More sophisticated versions of the journal type seal,
have been commonly used: the thrust seal and the one of which has two separate oil supplies for inward
journal seal. and outward flow, have been developed to avoid the
need for vacuum treatment (see Fig 6.29). It is also
possible to keep the oil supplies separate from the
5.3.1 Thrust type seal main turbine lubricating oil supply, which is the source
of most of the entrained water.
In the thrust type seal (Fig 6.28), the seal ring acts
like a thrust face, bearing onto a collar on the shaft.
Turbine lubricating oil is fed to a central circum-
ferential groove in the white-metalled face of the 5.3.3 Seal oil system
seal ring, at a pressure controlled to be greater than In the conventional seal oil system (see Fig 6.51), the
that of the casing hydrogen. Most of the oil flows main seal oil supply is taken from the shaft-driven
outwards over the thrust face and drains into a well. lubricating oil pump, with its pressure suitably re-
A small proportion flows inwards, against centrifu- duced. The pressure is further controlled by diaphragm
gal force and with only the oil/hydrogen differential valve which maintains a constant differential pressure
pressure behind it, into a drainage compartment which above casing gas pressure at the seals. The oil is cooled
is at casing hydrogen pressure. This oil can release in a water-cooled heat exchanger, and finely filtered
entrained air and water at this point, thus contami- to prevent metallic particles gaining access to the small
nating the casing hydrogen, as noted earlier, and it clearances at the seal faces.
is therefore important that the inward oil flow is Because it is necessary to maintain the shaft sealing
small. oil at standstill, to prevent hydrogen escape, motor-
The seal ring is attached to a housing which must driven seal oil pumps are also provided; these act as a
be free to move axially to accommodate the 30 mm back-up in emergencies, and are initiated by falling
or so of axial movement imposed on the shaft by seal oil pressure. They are commonly vertical pump-
thermal expansion of all the coupled rotors down- motor units mounted on the top of the lubricating
stream from the turbine thrust bearing, as they pass oil settling tank with the pumps submerged. A battery
from cold to hot conditions. The housing is arranged fed DC motor-driven pump may be provided as a
to move inside a stationary member, using rubber back-up in case of supply failure, but this would
sealing rings to contain the oil and to create an axial be expected to operate only a few hours while the
pressure at the seal face. hydrogen is scavenged.
In some designs, an additional chamber between The oil flowing to the casing side of the seal is
fixed and sliding components is fed with oil at a in a pressurised hydrogen environment and must be
separately controllable pressure so that the overall collected in a 'break pressure' tank, which releases it
pressure at the seal face can be varied. In another through a float controlled valve and enables it to be
variation, additional pressure is provided by springs. returned to the drain tank. The possibility of hydrogen
entering the drain tank is recognised; low level alarms
give a first warning (some form of pressure loop is
5.3.2 Journal type seal usually provided) and a blower exhausts the gas above
Here the seal resembles a short journal bearing float- the oil in the 'hydrogen section' of the tank to at-
ing on the shaft. In this case the shaft can freely mosphere. This blower also serves to reduce the
move axially through the seal, and it therefore does pressure in the bearing housings (communicated via
not have to accommodate the thermal expansion of the half empty drain pipes) below atmospheric, thus
the shaft. Again, oil is fed to a central annular groove reducing egress of oil vapour at the bearings.
497
The generator Chapter 6

PERFORATED ADMISSION PIPE


TURBINE EXCITER
END GENERATOR STATOR CASING END


TO
ATMOSPHERE

X t
-M

t
-M- -M-
.
W
. LIQUID
ALARM
I CHAMBERS H***

-M-

C0 2 KATHAROMETER

\f
-M-

i
-M-

X GENERATOR GAS
DRYING SYSTEM
M-

H 2 KATHAROMETER
A- -M-

V%

hM- 4H GAS CONTROL


EMERGENCY PANEL
CH
INTEGRATING hM-
FLOW METER . ^ . FROM C0 0
-M- -M- SUPPLY^

-M-
Hx>
1 -M-
-<XH
FROM
- HYDROGEN LP
DELIVERY MAINS

2
C0 o

FIG. 6.50 Generator gas system emergency scavenging

498
Cooling systems

TO OIL-GAS DIFFERENTIAL
I SEAL OIL SUPPLY PRESSURE GAUGES

3-WAY COCK (WITH L PORT)

| A | ALARM ON GAS CONTROL CUBICLE

(P) PRESSURE GAUGE

[Is] LIMIT SWITCH

' TRANSMITTER

|PS| PRESSURE SWITCH

MAIN OIL TANK HYDROGEN


COMPARTMENT

FIG. 6.51 Seal oil system

499
The generator Chapter 6

5.4 Stator winding water cooling system From the manifold, PTFE hoses connect to the elec-
Water in direct contact with the winding conductors trical joint ('nose') between a top and bottom con-
is the most effective and economic means of heat ductor bar, through which the water flows in parallel.
removal, and is used throughout the range of gen- At the exciter end, the water in each bar is trans-
erators under consideration (see Fig 6.52). Five main ferred through the electrical connector to a return
criteria must be observed: bar, and thence via another PTFE hose to the outlet
manifold, located alongside the inlet manifold. A
The conductivity of the water must be very low, small flow is tapped-off to cool the terminal bushings
to prevent current flow and electrical flashover. and phase connections. This is a double-pass system,
requiring higher pressure than a single-pass system,
The means used to transfer water into the conduc- but half the number of hoses with their potential for
tors must be of high integrity insulation material, leakage.
not easily degraded. In the single-pass arrangement, the manifolds are
The velocity of the water must be low enough to at opposite ends, and the water flows through only
prevent erosion, and the design must not allow cor- one bar in series. This system allows smaller water
rosion to occur, either of which could lead to a passages in the conductors to be used because a
build-up of conducting material, causing an elec- higher pressure drop per bar can be tolerated.
trical flashover. Other variations may be seen in obsolescent designs.
In one, all the conductors comprising a phase group
The maximum water pressure must be lower than were brought to a common waterbox, consisting of a
the casing hydrogen pressure, so that if any leakage large cast resin chamber with a bolted-on lid, inside
occurs, it is of hydrogen into the water circuit, since which electrical connections between conductors were
leakage of water into the winding insulation could made. In another, the water passed through five con-
lead to an electrical breakdown. ductor bars in series before returning to the manifold.
This required a high pump pressure but minimised
The maximum temperature in the water circuit the number of hoses.
must be low enough to provide an adequate margin If the flow is significantly reduced, the water tem-
below boiling point (commonly about 115C at perature rises rapidly. Reduction in flow is therefore
the pressure involved). The design aims for an inlet sensed, usually by differential pressure across an ori-
temperature of just above 40C, with an outlet fice plate or across the stator winding itself, and is
temperature of 65-70C. used to bring in the standby pump, and to trip the
unit, if flow is not restored quickly.
Demineralised water is used, which is obtained ini- Water pressure is determined by the height of the
tially, and made up, from the turbine condensate. A header tank and the pressure developed by the pump.
proportion is circulated through a dminraliser (Fig These are not controlled, since it is expected that
6.53) to ensure that the water quality described in the casing hydrogen pressure will not be allowed to
Section 4.6 of this chapter is maintained. All the fall much below its rated value in operation. During
metal with which the water is in contact is either start-up, the hydrogen pressure must be established
non-ferrous or stainless steel. Even small components before the water pump is started, to prevent a reverse
made of mild steel are not permissible because of pressure differential.
the propensity for magnetite to form and be held by The water circuit is tested initially to ensure that
electromagnetic forces. it has a very low leak rate, but hydrogen will enter the
Flexible hoses made of extruded PTFE (polytetra- water in small quantities. It is detected by arranging a
fluorethylene) are used to transfer water into and out settling tank on the outlet side of the generator, before
of the conductors. This material has good electrical the header tank connection, where gas will largely
properties, is chemically inert and has a long life in detrain. It is collected in a chamber equipped with
the ambient conditions, has an extremely low friction timed release valves, and an alarm is initiated if the
factor so that particles are less likely to adhere, and release rate exceeds an acceptable level (see Fig 6.54).
is partially translucent in the thicknesses used, so Thermocouples in each winding slot provide a means
that flow (containing bubbles) can be observed. The of detecting a low flow through one (or both) of the
low friction has a disadvantage in that attachments conductor bars in that slot. More recent machines have
are more difficult to arrange, but leak-free crimped a thermocouple in each outlet hose, which provides a
joints have been satisfactorily developed (see Fig 6.33). more direct indication of incorrect flow. Water flow
The water is circulated by duplicated pumps, through does differ somewhat between different paths, and
a water-cooled heat exchanger and fine filter, to the outlet temperatures also differ; the best indication is
generator inlet connection. Designs differ from this a departure from normal operational experience for
point. In one, the main supply goes to a circular a similar condition of loading and primary cooling
manifold supported from the stator core end plate. water temperature.

500
MAKE-UP HEAD TANK

-I ^ M STATOR COOLANT
GAS RELEASE
DRAIN, PRESSURE, TEMPERATURE
__- CONTROL AIR
ELECTRICAL

TO GENERATOR AUXILIARIES
CW SYSTEM

TO
GENERATOR
AUXILIARIES
CW SYSTEM

PURIFYING
PLANT

FIG. 6.52 Stator winding water cooling system

501
Cooling systems
The generator Chapter 6

AIR VENT

GASKET

UNTREATED WATER
INLET VALVE

RATE OF FLOW INDICATOR

TREATED WATER
OUTLET VALVE

DEMINERALISER COLUMN

U-BOLT CLAMP

AIR INLET VALVE

RESIN
OUTLET PIPE
ASSEMBLY

RESIN REMOVAL VALVE

DRAIN VALVE

BOTTOM COVER

FIG. 6.53 Dminraliser

502
Cooling systems

GAS OUTLET

FLOAT OPERATED
SWITCH

BODY

WATER GAUGE

FLOAT OPERATED
SWITCH

FIG. 6.54 Gas-in-water detection chamber

As noted earlier, it is important that condensation epoxy resin insulation systems do not absorb mois-
does not occur on the windings. Some machines have ture, and a low IR is usually indicative of surface
an electrical heating element, or an automatic cooler contamination, which can be removed by warmed air
bypassing system, to prevent water that is too cold circulation.
from circulating in the windings during start-up and
early loading.
It is not easy to measure the insulation resistance
(IR) of a winding which has multiple high resistance 5.5 Other cooling systems
paths to earth through the water-filled hoses, and even Casing hydrogen is cooled by passing it through water-
draining out the water does not ensure that the inside cooled heat exchangers arranged horizontally or ver-
surfaces of the hoses are dry. Attempts have been made tically in the casing. The heat exchangers consist of
to use a specially designed resistance measuring device many tubes of non-ferrous metal with either metallic
which uses the water manifolds as 'guard rings', but strip fins or wire loops brazed to their outside sur-
this is not always satisfactory. Fortunately, modern faces (Fig 6.55). These coolers have a double-pass
503
The generator Chapter 6

water circulation, so that inlet and outlet water con- 6 Excitation


nections are at the same end. They are equipped with
sealing devices so that access to the header box can
be gained for inspection, even though the casing is
pressurised. Some form of air venting system is also 6.1 Exciters
provided. The coolers can be withdrawn from the
casing when it has been scavenged. 6.1.1 Historical review
Water for these coolers (and other auxiliary coolers) When the first AC generators were introduced a
may be condensate or distilled water in a self-contained natural choice for the supply of the field systems was
system, or both; it is undesirable to use raw cool- the DC exciter. These direct current commutator ma-
ing water because of the danger of corrosion. The chines were not only used as main and pilot exciters
water pressure is arranged to be less than the rated but later also as a control amplifier, known as a
pressure of hydrogen in the casing, so that in the rotating amplifier or amplidyne.
event of leakage, hydrogen will leak into the water The DC exciter suffered from commutation and
circuit. In the latest machines, hydrogen detectors are brushgear problems but also offered certain advan-
provided in the water circuit (Fig 6.56). Operation tages; in particular, a capability for equal voltage
is usually possible with one hydrogen cooler valved- output of either polarity, which was used to improve
off; this provides some redundancy. Loss of primary generator transient performance. The main exciter ar-
water is detected by rise of hydrogen temperature, mature also provided a path for the commutation
which may be so rapid that the protection is arranged of induced currents, regardless of polarity, which ap-
to trip the unit. pear in the generator field winding during pole-slipping
Air cooling systems are provided for the rotating and other severe system disturbances, thereby limiting
exciters, and for the slipring/brushgear or rotating the induced voltage.
rectifier chambers. The rotating exciter components Gear-driven exciters were introduced to extend the
have a closed air circuit with a water-cooled heat application of these machines, however, increased
exchanger; the sliprings usually have open air venti- demand for higher excitation currents paralleled by
lation. advances in semiconductor technology brought about

STATOR END CORNER MEMBER


WALL
HORIZONTAL FRAME
END BAR
COOLER
SUPPORTS

SEALING GASKET

INLET AND OUTLET


WATERBOX DOOR

LARGE HOLE FIXED


TUBEPLATE
FIXED GASKET

RETURN
N
WATERBOX DOOR

FIG. 6.55 Hydrogen cooler

504
Excitation

r-txl L fe -tXl-i

2x100% EXCITER AIR/ T LIQUID f


RECTIFIER COOLERS f LEAKAGE
DETECTOR

TREATED WATER SUPPLY


FROM HIGH LEVEL HEAD TANK
\

L
-CXh

COOLING WATER INLET


DISTILLED WATER
BY-PASS
MAKE UP WATER

FIG. 6.56 Distilled water cooling system

505
The generator Chapter 6

the introduction of the rectified AC exciter. These Exciter response ratio =


were either static semiconductor diode rectifiers sup-
plying the generator field winding via sliprings, or The average rate of increase in excitation
brushless systems which carry the diode rectifier on open-circuit voltage (V/s)
the shaft. Developments have continued and excita- Nominal excitation voltage
tion powers now range from 70 kW for 20 MW gas
turbine-generators to 3500 kW for the 660 MW steam Typically, exciters are required to increase output volt-
turbine-generators. age from 100% to 200% in less than 0.3 seconds,
Where generators are connected to the main corresponding to a response ratio of 3.5.
transmission system over long transmission links, it The average rate of increase of the excitation open-
is necessary to provide a high response excitation circuit voltage is given by the slope of AC in Fig 6.58.
system capable of satisfying system transient stability
requirements. In these circumstances, a static thyris-
Slope of AC = BC/AB but AB = 0.5 seconds.
tor excitation system capable of step changes in field
Hence AC = 2BC (average rate of increase of ex-
voltage is generally specified.
citer voltage) and the nominal exciter response ratio
is given by 2BC/OA.
6.1.2 AC excitation systems
The excitation requirements of all CEGB 500 and 660
6.1.4 The pilot exciter
MW turbine-generators are provided by AC excitation
systems. A typical AC excitation scheme, showing the A shaft-driven excitation system consists of a main
shaft-mounted main and pilot exciters together with and pilot exciter, the pilot exciter providing the input
associated brushgear is shown in Fig 6.57. power to the AVR. A number of different types have
been developed including salient pole, inductor type
The CEGB currently operates 660 MW turbine-
homopolar and heteropolar designs. System require-
generators with either static or rotating excitation
ments for complete independence from external sup-
equipment. Detailed descriptions of these are given
plies during 'black start' conditions have led to a trend
in Sections 6.2 and 6.3 of this chapter respectively,
in favour of the permanent magnet generator (PMG)
while this section concentrates on exciter plant which
pilot exciter design. The salient pole design has gained
is common to both.
favour on all recent 660 MW units and forms the
To maximise plant availability under 'black start'
basis of the following discussion.
conditions, reliance on external electrical supplies is
kept to a minimum by using direct-driven perma- The salient pole PMG is a three-phase medium
nent magnet pilot exciters. For many years, DC pilot frequency machine, providing an essentially constant
exciters were used, but the low currents involved voltage supply to the thyristor converter and AVR
introduced commutation problems due to brushgear control circuits. A typical salient pole PMG is shown
glazing and, as a consequence, they were superseded on Fig 6.59.
by AC machines. The permanent magnet poles of the generator are
The pilot exciter provides power for the excitation manufactured from high energy material, such as
AVR control equipment which, on present 660 MW Alcomax. The permanent magnet pieces are bolted
plant, is of a salient pole design with ratings approach- to a steel hub and held in place by pole shoes. The
ing 100 kW. bolts are generally made from non-magnetic steel to
Both the main and pilot exciters are air cooled prevent the formation of a magnetic shunt. In some
machines, cooling air being drawn through the ma- designs of PMG, the pole shoes are also skewed one
chine by shaft-mounted fans. Temperature measure- pole pitch over the stator length to improve the
ments are taken at the inlet and outlet of the cooling waveform of the output voltage and reduce electrical
circuit to monitor performance. noise.
The stator core is constructed from a stack of low
loss sheet steel laminations, assembled within a fabri-
6.1.3 Exciter transient performance cated steel frame. Radial and axial cooling ducts are
Exciters must operate over a wide voltage and current provided at intervals along the core length to allow
range as ceiling requirements are considerably in excess cooling of the core and windings. To facilitate re-
of rated full-load conditions. The exciter is required moval, certain designs of pilot exciter can be split along
to respond quickly to changes in excitation at its own the horizontal centre line.
rotor terminals. This requirement for a fast response The stator winding is a two-layer design, each
characteristic is achieved by the use of a short air stator conductor comprising a number of small dia-
gap and a laminated rotor body. meter copper wires insulated with polyester enamel.
Exciter transient performance is characterised by The coils are connected together to give the rated
the exciter response ratio defined in BS5000 Part 2, three-phase voltage output, and insulated with Class
as follows: F (BS5000 Part 2) epoxy glass material.

506
GENERATOR ROTOR MAIN EXCITER MAIN EXCITER SLIPRING PILOT EXCITER
SLIPRING BRUSHGEAR ROTOR BRUSHGEAR ROTOR
GENERATOR
ROTOR BEARING PEDESTAL MAIN OIL PUMP

LTmPLpw

FIG. 6.57 Section through main and pilot exciters


Excitation

507
The generator Chapter 6

layer of punchings in the core is made from a number


of these segments, coated with insulating varnish and
laid side-by-side to form a circle. All the joints on
adjacent layers are staggered.
The stator winding is of a three-phase, four or
six-pole design, formed by copper coils which are
contained in conductor slots in the core, and retained
in position by insulating slot wedges. Each coil is
made from individually-insulated copper strips, con-
tained within a moulded insulating tube. To restrict
eddy currents in the coil, the copper strips in each coil
are transposed.
The rotor consists of a hollow-bored alloy steel
forged shaft which carries the silicon steel laminations
forming the rotor core. The rotor body is generally
laminated to reduce poleface losses in the exciter.
The reduction of this loss is important, as in the ex-
citer, the ratio of stator slot opening/gap length is
comparatively large, a short airgap length being ne-
cessary to lighten the burden on the main exciter ex-
citation system. The stator slots form indentations in
the airgap boundary; therefore, as the rotor flux moves
across the stator teeth, the changing permeance due
FIG. 6.58 Concept of the exciter response ratio to the slot openings introduces medium frequency
pulsations. These pulsations induce harmonic voltages
in the surface of the stator teeth but due to the
A steel enclosure is fitted over the PMG stator, laminated construction, the resultant losses are kept
which provides mechanical protection and serves to to a minimum.
reduce the medium frequency noise emitted from the The rotor windings are retained in position by cylin-
PMG to an acceptable level, as defined in BS4999 drical rotor endcaps. A fan is mounted on a seating
Part 51. machined in the balance ring to circulate cooling air.
Cooling of the PMG is achieved by drawing air At the exciter outboard end, two slipring units are
through mesh-covered apertures in the enclosure; the connected to the end winding, via radial connections
air is then circulated by the rotor or shaft-mounted and upshaft leads.
fans.

6.1.6 Exciter performance testing


6.1.5 The main exciter Exciters are required to undergo a number of tests
The main AC exciter is generally of a four or six- within the manufacturer's works to ensure that all
pole revolving field construction. The exception is the of the functional requirements are fulfilled. These
revolving armature main exciter used in a rotating include open- and short-circuit tests, overspeed bal-
rectifier scheme, which is described in detail in Sec- ancing and HV testing. PMG exciters are stabilised
tion 6.2 of this chapter. by applying short-circuits across the stator terminals
The exciter magnetic circuit is designed to operate to ensure that there is no appreciable loss of output
on or near the unsaturated part of its characteristic. voltage over the plant life.
This preserves a linear relationship between the con- The full exciter test requirements are contained with-
trolled excitation of the main exciter and the gen- in BS5000 which covers routine and type testing.
erator slipring voltage. The armature is designed for
low voltage operation, with comparatively high current
levels. A typical rotating field main exciter arrange- 6.1.7 Pilot exciter protection
ment is shown on Fig 6.60. The pilot exciter is now invariably a permanent mag-
The stator core and windings are air cooled, the net generator with windings only on the stator. These
ventilation circuit being formed by the end cover windings are insulated to 1.1 kV and tested at 3.2 kV,
and ducting in the stator casing. Thermometers are 50 Hz for 1 minute, which is well in excess of the
fitted to the casing to measure inlet and outlet air normal operating voltage of 220 V.
temperatures. The pilot exciter is only ever called upon to deliver
The core is constructed from a large number of its full current output during field forcing. Modern
segmented plates stamped from core plate material of AVR equipment is fitted with a time/current limiter
high magnetic quality and low electrical loss. Each which allows the pilot exciter to deliver maximum
508
Excitation

STATOR WINDINGS

CENTRE SECTION
STATOR CASING

STIFFENING STRAP

INBOARD END COVER


CORE CLAMPING RING

CORE

ROTOR

LOCKING SCREW

PERMANENT MAGNET
POLE

TERMINAL BOX

CLAMPING RING
BAFFLE
STATOR
WITHDRAWAL
EQUIPMENT
MAIN EXCITER
END

PEDESTAL

OIL THROWER RING

LOCATING DOWEL

HOLDING DOWN
STIFFENING PLATE
BOLT
FAN TIPPING
RING

BAFFLE

AIR SCOOP

FIG. 6.59 Salient-pole permanent magnet generator

current for a pre-set time, after which the current is The rated current is well below maximum current;
ramped back to a safe value. therefore, for reasons similar to those given for the
The result of these measures is a pilot exciter having pilot exciter, no additional protection is provided.
a considerable design margin for normal duties. It is
not, therefore, CEGB practice to provide additional
pilot exciter protection.
6.2 Brushless excitation systems

6.1.8 Main exciter protection


The main exciter, like the pilot exciter, has con- 6.2.1 System description
siderable inbuilt margin compared with its normal The development of the solid state silicon diode, with
duties, the AC windings being insulated for 3.3 kV, its inherent robustness and reliability, made possible
even though normal working voltages are around 500 the design of a compact rectifier system that can be
V. During ceiling conditions, this rises to approxi- rotated at rated generator speed. This alternative to
mately 1000 V. the conventional slipring excitation system eliminates
509
The generator Chapter 6

CORE KEY
TRANSFER HOLE LIFTING LUG
STATOR CASING
INNER END EXCITER LEAD
COVER y SUPPORT CLEAT
CORE END RING OUTER END COVER
DIVIDING PLATE
BOLT STIFFENING STRAP
STATOR CORE BAFFLE

BAFFLE RING ASSEMBLY

STIFFENING RING

WHITE METAL BEARING

END WINDING
SUPPORT RING

SUPPORT RING"'
BRACKET
VENTILATION DUCT
HAND HOLE COVER
THERMOCOUPLE
ACCESS DOOR

DOWEL HOLE

LEAD SUPPORT CLEAT

EXCITER TERMINAL LEAD

FIG. 6.60 Main exciter

the need for brushgear maintenance and reduces the the bridge operates normally. In the unlikely event
overall unit size. of two diodes failing in the same bridge arm, a moni-
Basically, the brushless scheme consists of a re- toring circuit in the field of the main exciter detects
volving armature AC exciter supplying a rotating recti- the fault and trips the machine.
fier mounted on the same shaft, which itself is directly Because of the high excitation power requirements
coupled to the main generator shaft. of a 660 MW generator, a number of diodes are con-
The rotating excitation system does not use field nected in parallel in each rectifier bridge arm. A fuse
suppression switches and discharge resistors. The main is connected in series with each diode to isolate it
generator field is de-energised by suppressing the ex- if it fails. Present CEGB requirements include built-
citer field which can be done rapidly by inverting the in redundancy of rectifier components so that, should
thyristor bridge which supplies it. The exciter time two of the parallel paths in each arm fail, full MCR
constants are short; therefore the time taken to sup- excitation requirements can still be supplied. This
press the generator field is only slightly longer than increase in components has meant the use of larger
in a conventional system. diameter diode wheels. Diodes and their associated
All modern gas turbine units are fitted with brushless components have therefore to be designed to with-
excitation systems, where the pilot exciter, main exciter stand centrifugal forces in the region of 6000 g.
and diode wheel are overhung; this arrangement means Measurements of essential quantities, such as ro-
the equipment is readily accessible for inspection. The tor earth fault indication, field voltage and current
complete rotating system is balanced as a unit. The are obtained via a telemetry link or instrument slip-
rotating diodes are connected in a three-phase bridge rings.
arrangement, the bridge arm consisting of two diodes Recent designs of rotating diode wheel have taken
in series, so that if one fails by going short-circuit, advantage of continued developments in semiconduc-
the other diode will continue to operate and hence tor diode technology to reduce the number of com-
510
Excitation

ponents. This has led to a simplified mechanical radial ventilation ducts.


arrangement. The armature windings are held in place by wedges
driven into dovetail slots formed when the winding
slots are punched. The armature winding overhang is
6.2.2 The rotating armature main exciter cooled by axial vents in the teeth in each end packet.
The main exciter is a brushless machine which, in The three-phase two-layer winding is secured in place
conjunction with the other units of the brushless ex- by wedges made from epoxy glass mat. In order to
citation system, supplies power to the main generator minimise losses caused by eddy currents, the conduc-
rotor. By dispensing with commutators, sliprings and tor is made from braided strips in parallel. A Roebel
brushgear, the brushless machine requires less main- transposition is used in the slot portion to reduce
tenance than the conventional machine and there are eddy current losses.
no sliding or rubbing electrical contacts to cause Each of the phase ends of the three-phase winding
sparking or carbon dust. is connected to the appropriate phase conductor in
The machine is a three-phase rotating armature AC the AC shaft connection assembly by six laminated
generator driven directly from the main generator copper connecting straps. A copper ring under the
through a solid coupling. The DC field system is outboard endwinding forms the neutral point.
mounted in the stator and the AC winding is on the The AC shaft connections between the exciter and
rotor. A laminated pole construction is used, giving a rectifier consist essentially of three cylindrical con-
field circuit with a short time constant to produce a centric conductor assemblies which pass through the
fast response. wall of the shaft. The conductor bars are insulated
The AC output from the main exciter is rectified from each other and from the shaft.
by diodes on the shaft and, in order to reduce diode Figure 6.62 shows the rotating rectifier unit of a
commutation reactance, a fully interconnected damper 660 MW generator which is mounted outboard of the
winding is fitted to the exciter polefaces. Figure 6.61 main AC exciter. Three-phase AC power is supplied
shows a typical rotating armature main exciter. to the silicon diode rectifier from the main exciter
The stator consists essentially of a fabricated support by conductors taken axially along the surface of the
structure which carries the laminated magnet frame shaft. The components within the rectifier are con-
and the associated field windings. The support frame tained against the high centrifugal forces by a steel
is formed from two steel end plates connected by retaining ring.
rectangular steel axial tie bars. The tie bars are equally The diode modules are accommodated within the
spaced around the bore to form a cage into which retaining ring in two circular rows, the complete
the magnet frame laminations are assembled. rectifier being a ' 3 - 2 - 1 - 9 ' connection of 54 diodes.
The stator core consists of a laminated magnet The notation signifies three AC connections, two
frame with the laminated field poles bolted into the DC connections, one diode in series per arm, and the
bore of the frame. The magnet frame is built up from last number indicates that there are nine paths per
segmental laminations of sheet steel. Each ring of phase.
laminations is made up of six segments; the segments The rotating rectifier includes a 20% standby ca-
in adjacent rings are half overlapped so that the pacity, this ensures continued unrestricted operation
radial joints do not coincide. Ventilation spacers are in the unlikely event of diode failure. Anode-based
inserted during manufacture to form radial ventilation diodes are used in the positive arm and cathode-based
ducts. diodes in the negative arm of the bridge. The diodes
The field poles are laminated and assembled onto are of a compression bonded construction.
key bars which allow the bolting of the poles onto Individual diodes are protected by two HRC (high
the bore of the magnet frame. The poles are built rupturing capacity) fuses, connected in parallel, which
up from T-shaped laminations clamped between end- isolate the diode should it become faulty, leaving the
plates by axial rivets. remaining healthy diodes to carry the full excitation
The exciter armature is formed from laminations current. Each diode module has a resistance-capaci-
of low loss electrical sheet steel, shrunk onto a shaft tance spike voltage suppression circuit and an indi-
forged from annealed carbon steel. Each segment is cator fuse. The indicator fuse, in conjunction with the
thinly insulated on both sides with a varnish, baked blown fuse detector equipment, is designed to detect
on to give a durable insulation. The shrink-fit is such the operation of the main diode protection fuses.
that the stampings are always in contact with the The rectifier retaining ring is shrunk onto the out-
shaft. The laminations are clamped between heavy side of the hub. A thick cylinder of insulation is
endplates of non-magnetic steel with strong finger moulded onto the inside bore of the retaining ring,
supports for the armature teeth. and the circular rows of diodes are attached to it via
Radial ventilation ducts are formed by spacer plates the diode module heat sinks.
at intervals along the rotor body. Cooling air from The anode-based diode modules, situated at the
both ends flows axially along slots machined in the hub end of the retaining ring each consist of a heat
shaft to feed air into the interpolar gap through the sink, diode, capacitor, capacitor fuse and main fuse.
511
The generator Chapter 6

MAIN ENCLOSURE

AIR FILTERS

AIR TEMPERATURE
MEASUREMENT PROBES
AIR COOLER

COLLECTING TROUGHS
STATOR FRAME

AIR TEMPERATURE MAGNET FRAME


GAUGE LAMINATIONS

STATOR FIELD POLE

STATOR FIELD COILS

GENERATOR/EXCITER ENDSHIELD
COUPLING FAN

ARMATURE SHAFT

ARMATURE RETAINING
RING
I 0 ^ ARMATURE BODY
AC SHAFT
11 CONNECTION
DRAIN FROM COLLECTING
TROUGHS

ANTI-CONDENSATION
HEATER

DRAIN VALVE

COOLING WATER
INLET
EXCITER
BEDPLATE

FIG. 6.61 Rotating armature main exciter

The cathode-based diode modules are situated at bushes. Laminated copper straps connect the positive
the open end of the retaining ring, and in addition and negative rings to insulated radial studs in the
to the anode based components have two indicator shaft. These studs are screwed into the shaft bore
fuses mounted on the heat sink. Figure 6.63 shows a insulated D-leads.
typical cathode-based module. With a rotating rectifier system, diode condition
The DC output from the rectifier is connected to monitoring is not as simple as it is on the equivalent
copper alloy rings shrunk onto bushes on the shaft, static rectifier scheme. A method of indirect measure-
with insulation between the connection rings and the ment is required to indicate a diode failure. The blown
512
Excitation

ANODE-BASED CATHODE-BASED
DIODE MODULE DIODE MODULE

INSULATION
CYLINDER

ALUMINIUM
SEGMENTS
RADIAL
CONNECTING STRAPS

INSULATION
CYLINDER

INSULATED
' LEADS
NEGATIVE RADIAL
TERMINAL STUD
-(UNDER)

INSULATED CLAMPING
BOLT
STEEL COUPLING
BUSH AND BOLT

COOLING-AIR FLOW

FIG. 6.62 Rotating rectifier

fuse detector performs this function; it consists of taining the three photoelectric cells associated with
two main units, an optical detector head and a ter- three separate light sources, two on the bottom face
minal unit containing the detection equipment, shown and one (the datum) on the top face. The light beams
diagrammatically in Fig 6.64. on the bottom face pass over the path traversed by
The optical detector head consists of a unit con- the tips of the diode failure indicator fuses as the
513
The generator Chapter 6

EPOXY RESIN
GLASS STEADY
STRAP

* INDICATING
FUSES

DIODE
MAIN FUSES

INSULATION
PLATES
ALUMINIUM
BASE PLATE

BALANCE
WEIGHTS
CONNECTION
STRAPS
CAPACITOR
FUSE

CAPACITOR

FIG. 6.63 Negative DC diode module

rectifier rotates. Under normal operating conditions, detector circuit, where an alarm signal is generated.
these light beams remain unbroken and the light shines To distinguish between the two rows (positive and
continuously on the photoelectric cell immediately op- negative) of indicator fuses, the light beams from the
posite, thus maintaining a constant signal. However, two probes are offset by an amount equal to half the
should a diode fail, the associated indicator fuse op- circumferential distance between fuses. Without this
erates and ejects a striker pin which interrupts the arrangement, signals from the two rows of fuses would
appropriate beam of light on each revolution. This be coincident and therefore unidentifiable.
interruption produces a pulsed DC signal at the output To establish the angular position of a failed diode
of the photoelectric cell which is fed to the blown fuse on the rotating rectifier, a fixed datum point is con-
514
Excitation

LIGHT GUIDE LIGHT BEAM

DATUM DATUM
REF1
DATUM

DATUM
SIGNAL DETECTOR
CIRCUIT
PHOTO
ELECTRIC
CELL OSCILLOSCOPE

BLOWN
FUSE
OPTICAL PROBE SIGNAL
INDICATOR
FUSE PIN

TUNGSTEN - HALOGEN
LIGHT SOURCE
3=1) (BACK ROW)

BLOWN
FUSE REMOTE
DETECTOR ALARM
CIRCUIT CIRCUITS

BLOWN FUSE
(FRONT ROW) SIGNAL

PEC

LOCAL ALARM
1
INDICATOR
LAMP

FIG. 6.64 Blown fuse detector system

tinuously scanned by the third photoelectric cell. Current measurement A current shunt is built into
The datum detector output is compared with the the rotor winding, giving a mV output correspond-
blown fuse detector signal and the relationship be- ing to the 0-5000 A flowing in the field winding.
tween the two establishes the position of the failed
diode. Earth leakage A DC supply is produced in the
Generators fitted with brushless exciters employ tele- rotating electronic equipment, the positive supply
metry systems to provide measurement of generator of which is connected to the negative end of the
rotor winding quantities, including rotor current, volt- field winding via a resistor R3. The negative is con-
age, temperature and most importantly earth fault nected to the rotor shaft through a high value
resistor R4. Leakage to earth will result in current
indication.
flowing through these resistors which is measured
The equipment uses solid state electronics, some
by the voltage drop across R3.
of which are shaft-mounted and the remainder rack-
mounted within the AVR. The rotating units are com-
pletely encapsulated and accommodated in transverse The output from the current channel is fed to a volt-
holes in the exciter shaft. Plugs and sockets are used age controlled oscillator that produces a frequency
for connections. The power supply for the rotating modulated (FM) signal, which is then conveyed to
electronics is supplied from the stationary unit at me- the stationary unit by the aerial assembly. Voltage
dium frequency via windings on the aerial assembly. and earth leakage signals are treated similarly. Values
The overall schematic of the telemetry system is shown of winding resistance and average winding temperature
on Fig 6.65: are derived from the voltage and current signals.
The signal from the field voltage demodulator is
Voltage measurement The field voltage is obtained also fed to an active filter tuned to the exciter funda-
from a voltage divider circuit connected across the mental frequency. Should a complete rectifier bridge
field winding. This comprises resistors Rl and R2 arm fail, signals at this frequency appear in the field
which have a voltage output of 0.6 V corresponding winding causing the filter output to increase, initiating
to the generator field voltage. an alarm.
515
The generator Chapter 6

ROTATING PARTS STATIONARY PARTS

VOLTAGE TO FREQUENCY
FREQUENCY TO VOLTAGE
CONVERTERS CONVERTERS
VOLTAGE
DIVIDER
FIELD
WINDING

v. SIGNAL
r OUTPUTS

D
FUNDAMENTAL
FREQUENCY
DETECTOR
(150Hz)
BRIDGE ARM
EARTH FAILURE
LEAKAGE

EARTH
LEAKAGE
DEMODULATOR
D EARTH
< LEAKAGE

n
a
EARTH
EARTH LEAKAGE LEAKAGE
LIMITING RESISTOR SOURCE

HZ> 9kHz
7 OSCILLATOR
ROTOR


EARTH DC SUPPLY
FOR
ROTATING
ELECTRONICS

AERIAL
ASSEMBLY

FIG. 6.65 Rotational telemetry overall schematic diagram

An alternative brushless exciter design consisting The need for the two diodes in series was deter-
of a rectifier with a 3 - 2 - 2 - 8 arrangement of connec- mined from consideration of two diodes failing simul-
tions totalling 96 diodes is also in common use. The taneously in the same phase of the rectifier. If the
notation signifies three AC connections, two DC con- series diodes were not present, the result would be a
nections with two diodes in series and eight parallel short-circuiting of the generator rotor.
paths per bridge arm. The rectifier is designed to Indicator fuses are connected in parallel with the
maintain rated output following the failure of up to main fuses as a secondary method of determining
two paths in any bridge arm. diode failures. When the generator is shut down, in-
A circular row of fuse modules and two circular spection of the indicator fuses readily identifies failed
rows of diode modules are contained against the cen- diodes.
trifugal forces by a steel retaining ring. The diode For cooling purposes, air is circulated in a closed
modules consist of anode and cathode units, which are ventilation system which contains a water cooled heat
used in the positive and negative arm of the bridge. In exchanger. Air from the outlet side of the cooler cir-
contrast to the mark 1 systems, the mark 2 is fused on culates within the main enclosure. The self-fanning
the AC side of the rectifier and advantage has been action of the fuse and diode modules draws air from
taken of the improved peak inverse voltage capability the main enclosure through the rectifier.
of modern diodes to eliminate the capacitor fuse cir-
cuits. A typical mark 2 diode module is shown on
Fig 6.66. 6.2.3 Telemetry system
Fusing on the AC side means a reduction in fuse The telemetry system employed on this design of
size, as the elements are no longer subjected to the rectifier makes use of the principle of frequency di-
high induced generator field voltages which occur vision multiplexing and includes a number of addi-
during system faults and pole slipping incidents. tional features. The most significant of these is the

516
Excitation

LAMINATED
COPPER STRAP

DIODE

HOLDING DOWN
BOLT HOLES (2)

INSULATION
STRIPS

INSULATION
BASE

BASEPLATE
AND HEATSINK

FIG. 6.66 Rectifier module (anode)

indication and phase location of up to three blown fier is fed via the mixer unit 4 to the transmitter
fuses per phase, making a total indicating capacity 10 to give direct frequency modulation of the trans-
of nine blown fuses. The other changes are the use mitted carrier frequency.
of a single transmitter, directly modulated by the The transmitter output is transferred via the aerial
field voltage, to which are added sub-carriers contain- to a carrier amplifier 16 and demodulator 17 to give a
ing the rotor current, blown fuse and earth leakage mean output voltage proportional to the carrier fre-
information. quency. The output is then smoothed and scaled to
produce an output corresponding to the DC field
voltage.
Voltage
The field voltage measurement is taken differentially
at each end of the shaft, as shown on Fig 6.67. Earth leakage detection
Voltage measurement is made via a voltage divider Rotor earth leakage is detected as a voltage devel-
and differential amplifier 1. The output of this ampli- oped across a resistor R6 which produces a frequency
517
518
EARTH
* * * * * * * * BLOWN FUSE
LEAKAGE
DISPLAY
DISPLAY
The generator


'
3 ri

STROBE LOGIC
GENERATOR UNIT

EIGHT SERIES EIGHT SERIES


CONNECTED CONNECTED FIELD
TRANSISTOR TRANSISTOR WINDING
SWITCHES SWITCHES PEAK TO THREE LEVEL
PEAK LEVEL l- DETECTOR
AND CURRENT AND CURRENT
RECTIFIER COMPARATOR
TRANSFORMERS TRANSFORMERS
LV^IAJT

LOW PASS LOW PASS SMOOTHING


FILTER FILTER SECTION
6 r i DC -1kHz DC -1kHz


FIELD BLOWN EARTH
15 CURRENT FUSE LEAKAGE
LA-AJSJI DEMODULATOR DEMODULATOR DEMODULATOR


8 rf BANDPASS BANDPASS BANDPASS
INTEGRATING
FILTER FILTER FILTER
AMPLIFIER
21-32 kHz 4 - 10kHz 100Hz-1kHz
* * * * * * * *

3_
SUMMING DIFFERENTIAL
UNIT AMPLIFIER
VOLTAGE
TO
FREQUENCY
CONVERTER

VOLTAGF VOLTAGE 4-95


kHz TRANSMITTER CARRIER CARRIER
TO TO INPUT TRANSMITTER
FREQUENCY AMPLIFIER HDEMODULATOR
FREQUENCY MIXER
CONVERTER 700- CONVERTER
300Hzl
T:

12 kHz
12kHz
POWER POWER
TUNED
SUPPLY DRIVER
FILTER

FIG. 6.67 Telemetry system block diagram


Chapter 6
Excitation

change at the output of a voltage-to-frequency con- of these sliprings.


verter 3. This output is added to the voltage signal The brushes are designed to operate continuously in
in the transmitter input mixer 4. The earth leakage order to achieve uninterrupted rotor earth fault pro-
signal is isolated from the carrier demodulator 17 out- tection. This arrangement is lightly loaded and would,
put by a band-pass filter 22 and processed to provide after a short period of operation at low current,
an earth leakage alarm signal. develop a high resistance contact film, resulting in
incorrect readings. To overcome this difficulty, a
constant current is circulated through the two brushes
Field current measurement (<brush-wetting,). This continuous flow of current
Field current is measured by means of eight series- maintains the interface resistance constant at normal
connected current transformers (T1-T8) in phase A levels.
of the main exciter output. Since each current trans- A signal proportional to generator rotor current
former (CT) surrounds a conductor between the fuses is obtained from a search coil mounted in the
and the associated rectifier in one phase, the total quadrature axis of the exciter field coils. The output
output from the current transformers corresponds to signal is filtered and converted from a voltage to a
the total phase current. The CT output modulates the standard 4 - 2 0 m A current signal suitable for use
voltage-to-frequency converter 5 over a range of field with the station central logging computer. The field
currents from 0-6000 A DC. The signal carrying the voltage signal is similarly conditioned and buffered
current information is selected by a band-pass filter to protect the instrumentation from the high voltages
20, demodulated and rectified to give field current induced in the rotor field following incidents, such
indication. as pole slipping. The current and voltage signals are
subsequently processed to provide an average rotor
winding temperature measurement.
Blown fuse indication Continuous monitoring of the rotating diode equip-
Eight CTs (T9-T16) in each phase, identical to those ment is considered unnecessary, given the proven
used for current measurement, are each loaded by a operational reliability of the equipment. This is the
transistor switch (TRS1-TRS8), shunted by a resistor simplest and most robust of the described schemes
(R17-R24). The resistors are connected in series but to monitor essential rotor quantities. It has the added
under normal operating conditions each one is shorted advantage that generator rotor RSO (recurrent surge
out by its associated transistor switch. The resistance oscilloscope) testing can be carried out, a facility not
of the circuit is therefore low. If a fuse operates, available with equivalent telemetry schemes.
the associated transistor switches off and the circuit
resistance increases; further fuse failures result in fur-
ther increases in resistance. This arrangement is re- 6.2.5 Rotating rectifier protection
peated on each of the three phases and connected to The main exciter is protected against the effect of
the summing unit 40 which, by supplying a current diode failure by the provision of fusing, either on the
to each of the circuits, provides an output voltage AC or DC side of the rectifier. When a diode fails, it
proportional to the number of blown fuses in each usually fails to short circuit, blowing the high rupture
phase. The output of the summing unit controls the capacity (HRC) fuse, which in turn blows an ejector
output of the voltage-to-frequency converter. pin indicator fuse to initiate an alarm. On the mark 1
The blown fuse information is selected from the system, the pin is detected by a photoelectric cell,
receiver carrier demodulator 17 by a band-pass filter and an alarm is raised in the control room. In contrast,
21. The signal is then recovered by the demodulator the mark 2 system can identify up to nine individual
24. The output waveform for the circuit corresponds diode failures.
to the number of blown fuses so the waveform is On the basis of the proven high operational relia-
analysed to give the number of fuse failures. Phase bility of the rotating diodes, it is not now considered
identification is carried out by a strobe generator 30 necessary to continuously monitor the rotating system
which produces three separate pulses that coincide for failure. Present practice is to examine the indica-
with the centres of each positive phase current period. tor fuses on an opportunity basis and during planned
maintenance overhauls.
Should a major fault occur, such that a complete
6.2.4 Instrument sliprings bridge arm is either short- or open-circuited, major
An alternative scheme is shown diagrammatically on damage can be caused to the excitation system. To
Fig 6.68 and uses shaft-mounted sliprings. Connec- protect the unit in the event of such a failure, it is
tions are taken from the exciter upshaft leads through CEGB practice to provide bridge arm failure protec-
the shaft bore to instrument sliprings mounted on tion. This device initiates a turbine trip on detection
the permanent magnet generator shaft. These slip- of a failure.
rings permit direct measurement of field voltage. The The detector monitors the amount of ripple induced
rotor earth fault indicator relay is connected to one in the main exciter field, which in a healthy rectifier

519
The generator Chapter 6

AUXILIARY SUPPLY
110V 50Hz

FIG. 6.68 Arrangement of instrument sliprings

is the sixth harmonic of the exciter fundamental fre- excitation system. Early equipment contained diodes
quency. This ripple is associated with the normal of relatively low rating, where up to three diodes were
three-phase full wave rectification of the exciter ar- required in series to meet reverse voltage requirements
mature voltage. Should a bridge arm fail (to either during pole slipping. This, together with a cautious
open- or short-circuit), a component of ripple at the design approach, resulted in high spare capacity.
exciter fundamental frequency appears in the exciter The rapid development of semiconductor techno-
field. This is detected by a band-pass filter tuned to logy has resulted in a reduced number of simpler,
the exciter fundamental frequency. Once the input is more compact devices, capable of operating at high
of sufficient magnitude to overcome an internal bias voltage and current levels. Equipment of this type
signal, which is set to prevent spurious operation, a has a record of high reliability on the CEGB system,
relay is energised which initiates a Category B unit and is currently in use on a number of 660 MW units.
trip. With the introduction of the thyristor, the role of
the static rectifier has radically changed. The thyristor
rectifier plays an active role in the control of excita-
tion power to the generator field. Like the diode,
6.3 Static rectifier excitation equipment the thyristor conducts current in one direction only;
however, unlike the diode, the point at which con-
duction takes place can be controlled.
6.3.1 Introduction Excitation power modulation is achieved by con-
Excitation systems based on the static semiconductor trolling the thyristor firing angle, eliminating the need
diode bridge were the first alternatives to the DC for a main AC exciter. As the time constant asso-
520
Excitation

ciated with the exciter is the principal cause of delay, voltages appear across the rectifier in the reverse
its removal greatly improves the speed of excitation direction, it is CEGB practice to use diodes with a
system response, enhancing generator transient stability peak inverse capability of 3.4-4.2 kV, thus providing
margins. ample margin.
A feature of all static excitation equipment is the To protect the diodes against voltage spikes (caused
need for sliprings and brushgear which require regular by diode commutation effects and external switching),
maintenance. As this is carried out on-load, an inter- each diode is provided with a dV/dt suppression cir-
lock system is normally provided so that access to cuit, consisting of a capacitor and series resistor. In
the slipring enclosure is prevented, unless a safety addition, each rectifier section has a resistor-capacitor
procedure has been followed. No further mention of suppression network connected across the DC output
sliprings or brushgear will be made here, as a detailed to limit voltage transients coming from the DC side
account of the equipment is given in Section 3 of this of the rectifier to within the peak transient voltage
chapter. rating of the diodes.
The rectifier diodes are easily damaged by over-
currents and are therefore individually protected by
6.3.2 General description of static diode rectifier high speed, high rupturing capacity fuses, with micro-
equipment switches for fuse failure indication. These fuses op-
A static rectifier system is an assembly of diodes and erate for an internal fault to isolate the faulty diode
diode protective equipment. Typical 660 MW rectifier and allow continued operation of the remaining diodes
units consist of up to four self-contained, three-phase, in the arm. The most severe fault experienced by the
full wave bridges. The number of diodes per section are diode is a short-circuit on the DC side of the rectifier;
selected so that MCR requirements can be met with one this is cleared by HRC fuse operation.
section out of commission. Each section is provided Overcurrents due to system faults or slipring flash-
with AC and DC isolators, and an interlock system overs are cleared by DC circuit-breaker operation.
ensures that, during on-load operation, access can be
gained to one section only.
Diode rating is based on the continuous and peak 6.3.4 Static thyristor rectifier schemes
inverse voltages, together with the current/time rating The thyristor has radically changed the role of static
on overload. A typical rectifier bridge has a number rectifier equipment, as it no longer plays a passive
of parallel paths per arm (the diodes being specially but an active role in the control of generator excita-
selected to ensure satisfactory current sharing) with tion. One of the principal features of this form of
one diode in each parallel path. excitation control is its very fast rate of response
To dissipate the heat generated during rectifica- due to the elimination of a main exciter. A typical
tion, the diodes are mounted on heat sinks. Cooling thyristor excitation scheme is shown on Fig 6.69.
is provided by either forced or natural air circula- Excitation power is generally taken from an excita-
tion and alarms are generally provided to warn op- tion transformer which is connected to the generator
erators of high temperature conditions which require output terminals. With this arrangement, the trans-
investigation. former primary voltage follows the generator terminal
Busbars are used for the AC connections from the voltage during normal and fault conditions. Under
main exciter, and for the DC rectifier output to the fault conditions the excitation power transformer must
generator field winding. The busbar system, like the be capable of meeting the field forcing requirements
exciters, is rated for 110% MCR and is capable of at reduced terminal voltage, and of withstanding the
withstanding the mechanical forces arising from the overvoltage experienced following a load rejection.
worst overcurrent fault conditions. An alternative scheme, which is not subject to
All rectifier equipments supplied to the CEGB must system voltage variations, is the compound source
meet the requirements of BS4417 which covers both rectifier system. These static systems use both current
routine and type testing. and voltage sources (generator terminal quantities) to
make up the excitation power source.
To ensure integrity under 'black start' conditions,
6.3.3 Rectifier protection however, a scheme based on shaft-mounted exciters is
Diodes are susceptible to overcurrent, which causes an attractive alternative. The exciter runs continuously
excessive heating of the element, and to overvoltages at ceiling output with low power factor, providing
which can pierce the rectifying element and cause com- the thyristor converter with a constant voltage source
plete breakdown. It is therefore essential for system of excitation power.
integrity that both the operating and ceiling voltages The thyristor rectifier unit is arranged in several
are within the capacity of the diodes. isolatable sections so that any one section can be ser-
During generator pole slipping or asynchronous op- viced while the remaining sections provide full MCR
eration, the peak voltages appearing at the slipring excitation requirements. Thyristor free-wheel and pole-
are about 2000 V on a 660 MW machine. Since these slip crowbar circuits are generally included to protect
521
The generator Chapter 6

EXCITATION
TRANSFORMER

MVAR
LIMIT REVERSIBLE
-oo
CURRENT
INPUT
FROM STATOR
POWER
SYSTEM
STABILISER!
MAIN

VOLTAGE FEEDBACK
<x>
CURRENT FEEDBACK
-3

THYRISTOR
CONVERTER
AUTO THYRISTOR
VOLTAGE SIGNAL CURRENT
CONTROL CONTROL CONTROL
SIGNAL
VOLTAGE - .BASE EXCITATION
REFERENCE GENERATOR/MOTOR
SIGNAL

VOLTAGE AUTO/MANUAL MANUAL


SETTING CHANGEOVER POT

ROTOR
HEATING
CURRENT
LIMIT AVR EXTERNAL PLANT

FIG. 6.69 Typical thyristor excitation system

the thyristors from excessive overvoltages. Direct cur- to connect a number of thyristors in parallel. This
rent voltage transformers (DCVTs) trigger the crow- presents difficulties, since individual thyristors have
bar into operation on detection of an overvoltage different forward path characteristics, causing one to
condition. Free-wheel thyristors provide a path for conduct the majority of current; if allowed to con-
stored energy in the rotor during thyristor commu- tinue, this would cause breakdown. Forced current
tation and system fault conditions. The pole-slip crowbar sharing, by the addition of a low value resistance or
provides a path for the induced reverse direction pole- inductance in series with each anode, is normally used
slip current, so avoiding excessive pole-slip voltage to obviate this.
developing across the rotor terminals. Thyristor cooling is provided by a natural or forced
The DC output of the thyristor rectifier is provided air scheme. Temperature detectors mounted within the
with voltage and current surge suppression circuits air circuit provide early warning of high temperature
which are designed to protect the thyristor from volt- conditions, allowing appropriate operator action to be
age spikes generated during thyristor commutation or taken. On future large plant, the higher current ratings
field circuit-breaker operation. In addition, individual and associated losses may make it necessary to use
thyristors are protected against dV/dt breakdown by water cooled thyristor equipment.
a capacitor-resistor suppression circuit connected in Thyristor excitation systems can improve the steady
parallel (identical to the circuit used to protect diodes). state and transient stability limits considerably because
Overcurrent protection is provided by a series-connected of their ability to change the generator field voltage
HRC fuse. In the event of an individual thyristor almost instantaneously. They are therefore finding gen-
drawing excessive current the series fuse will rupture, eral application on generating plant which is connected
ejecting a striker pin which initiates an alarm. Over- to the periphery of the main transmission system,
current excursions are normally controlled by the AVR where the inversion mode of operation, in which the
to within the rotor heating limit; however, in the field current is rapidly reduced by the reversal of
event of a prolonged overcurrent condition, the ex- energy flow, is exploited to the full. The rapid field
citation is tripped through the field circuit-breaker. suppression achieved following isolation from the sys-
To meet the high current requirements of large tem under load rejection or fault conditions is illus-
turbine-generator excitation systems, it is necessary trated on Fig 6.70.

522
Excitation

GENERATOR FIELD
VOLTAGE V c n

V F D - FIELD VOLTAGE

T f -FIELD TIME CONSTANT

V SUPPRESSION TIME FOR A THYRISTOR EXCITER

FIG. 6.70 Field suppression time

6.4 The voltage regulator erators and continue to provide reliable operation.
The rapid developments in the field of semiconduc-
tor technology brought about the introduction of the
6.4.1 Historical review transistor amplifier and the thyristor output ampli-
Early designs of voltage regulator equipment had a fier, which have increased the speed of response and
large deadband, were slow to respond to system changes improved the overall system performance. Subsequent-
and required regular maintenance. This was due main- ly, the discrete component operational amplifier has
ly to the use of moving mechanical components within been replaced by integrated circuit equivalents. A
the automatic voltage regulator (AVR). To eliminate typical modern dual channel arrangement is shown
these difficulties, AVR systems were developed which on Fig 6.71.
made use of the cross-field generator or amplidyne. Future developments in the field of AVR design will
The amplidyne was used as the regulator output stage centre around the use of digital microprocessor tech-
and controlled the field of the DC exciter. niques. These discrete time controllers offer a number
The amplidyne and DC exciter were, in turn, super- of potential advantages, most notably the introduction
seded by the magnetic amplifier and AC exciter. In of adaptive control strategies.
this scheme, the magnetic amplifier was used as the
regulator output stage controlling the main exciter
field. The output from the exciter was rectified by a 6.4.2 System description
diode bridge and taken, via slipring connections, to The AVR is an essential part of the operation of a
the generator field winding. Schemes of this type were modern electrical power system. It is at the heart of
successfully employed on all the CEGB 500 MW gen- the excitation control systems around which the re-

523
The generator Chapter 6

VT VT CT CT
B A B A
Le-i EXCITER j
MONITORING
VT mm
uUUu uwu uUUu
nnmnnnnnnnn
ROTOR ANGLE
MEASUREMENT
UP-TO-FREQ
DETECTOR
F
MAIN
RECTIFIER
ARM
O/C
TRIP/ALARM
CHANNEL
CHANNEL
A
AVR
UT^ A
CONVERTER

PILOT EXCITER
SUPPLY
CHECKING
ALARM/TRIP

CHANNEL CHANNEL
B B
AVR CONVERTER

VOLTAGE
LOWER REFERENCE

MANUAL

OVERFLUX


EXCITATION
TRIP & ALARM
TOTAL CURRENT

FIG. 6.71 Dual channel AVR

maining equipment operates. The central function of terminal voltage also changes, increasing the error sig-
the AVR is to maintain constant generator terminal nal. The error is amplified by the regulator and used
voltage under conditions of changing load. There are, to increase or reduce excitation, as necessary, to bring
however, a number of other functions which are the voltage back to its original value. The need for a
required from the AVR, if a large generator is to rapid, stable response following such changes is of
operate satisfactorily under all operational conditions. paramount importance and, since control systems us-
The CEGB currently specifies dual channel AVR ing such high steady state gains would rapidly become
equipment complying fully with EES 1980 together with unstable, special signal conditioning networks are in-
manual back-up control on all 660 MW plant. This cluded. These consist of phase advance and phase
provides maximum reliability as the loss of one chan- lag circuits which have adjustable time constants al-
nel does not inhibit operational performance. Facilities lowing accurate tuning of the voltage response. To-
are provided to repair the faulty channel while the gether, these circuits act as a notched filter, reducing
generator remains in service. On small gas turbine gain at generator electromechanical oscillation frequen-
plant, single channel AVR equipment is specified. cies, whilst permitting the high gains necessary for
accurate voltage control. The setting of the time con-
stants is of great importance, as transmission system
6.4.3 The regulator dynamic stability is sensitive to AVR settings. For
The AVR is a closed loop controller which uses a this reason, sophisticated analytical techniques (see
signal proportional to the generator terminal voltage Section 6.7 of this chapter) have been developed and
and compares it with a steady voltage reference. The applied in order to obtain optimal performance.
difference or error voltage obtained is then used to The AVR accepts the generator terminal voltage
control the exciter output. signal via its own interposing voltage transformer.
If the load on the generator changes, the generator The voltage signal is then rectified and filtered before
524
Excitation

being compared with the reference voltage. Provision minal voltage and, if it exceeds a safe level (normally
is made for the operator to change the reference 1.3 pu), the thyristor converter is immediately switched
voltage in response to system requirements. into the inverting mode, which reduces the field cur-
In addition to the basic voltage control require- rent in minimum time. This relay is only active during
ment, the AVR includes control loops which perform unsynchronised operation.
other vital tasks. These controllers, which include the The overfluxing relay is also only active during un-
MVAr limiter and over fluxing limiter, are discussed synchronised operation, when there is a chance that
in detail in Section 6.5 of this chapter. the generator transformer could be overfluxed if the
safe voltage/frequency ratio is exceeded. A special
relay detects this condition and initiates an alarm.
6.4.4 Auto follow-up circuit Control loops within the AVR will act to reduce this
With a dual channel design, both regulator channels to a safe level but, if the condition persists, the thy-
can be active at the same time, each providing half ristor converter is switched to the inverting mode and
the total generator excitation requirements. An alter- the excitation is tripped.
native arrangement allows for one channel to be active, Most faults within the regulator loop give rise to
whilst the other follows passively. Should a channel either an over or under excitation condition. There-
trip in either scheme, then the other picks up the fore comparator circuits are used to monitor regulator
full excitation requirement of the generator in a and converter bridge input and output levels. Alter-
'bumpless' manner. This is achieved using follow-up natively, a single comparator monitors the thyristor
circuits which track the primary (or active) channel output current and compares it with maximum and
and drive the standby channel output while a dif- minimum field current limits allowed. Transiently, these
ference exists between the two. limits are exceeded during system faults, but the chan-
nel is tripped if the condition persists beyond a few
seconds.
6.4.5 Manual follow-up
This is similar to the auto follow-up but is used to
adjust the manual control system in response to 6.4.8 Thyristor converter protection
automatic channel changes. In the event of an AVR In addition to the above, AVR channels are tripped
failure, the manual control takes over in a smooth if any of the indicator fuses protecting the converter
bumpless manner. thyristor s rupture. The thyristor converter is further
protected by a temperature sensing device which op-
erates in the event of excessive heating.
6.4.6 Balance meter
A balance meter is provided in the power station
control room and in the AVR cubicle. This monitors 6.4.9 Fuse failure detection unit
the difference between the automatic and manual The regulator relies upon a signal from the generator
control output settings. During automatic control, the voltage transformers for its controlling action. Loss
follow-up circuits ensure this error is minimal, whereas of the signal is due in general to failure of the fuses
during manual control no such facility exists to adjust in the voltage transformers. A fuse failure detector
the AVR, and a large discrepancy can therefore exist. unit monitors the input to each channel and compares
During manual operation and prior to selection of it with that of a check or reference transformer. If
AVR control, the balance meter is consulted and an a fuse fails in the voltage transformer supplying the
adjustment is made so as to avoid large MVAr dis- reset voltage, the channel is tripped; a fuse failure
turbances following control changeover. in the reference transformer initiates an alarm.

6.4.7 AVR protection 6.4.10 The digital AVR


The AVR plays a vital role in the unit overall pro- The rapid development of the microprocessor has
tection scheme, as it controls suppression of the gen- brought about the increased use of digital electronic
erator field after faults. In addition, it is necessary techniques in a number of industrial control appli-
to protect against AVR component failure which would cations. While the present generation of solid state
otherwise jeopardise generator operation. AVRs meet all existing CEGB functional requirements,
The field suppression circuit accepts signals from there are advantages to be gained if microprocessor
the main unit overall protection scheme, in addition schemes are considered.
to signals from the overvoltage and transformer over- High reliability, which has been a feature of pre-
fluxing relays. The circuit switches the AVR thyristor sent AVR equipment, can be expected to improve
converters to their inversion mode of operation and still further due to the reduction in the number of
then trips the excitation. components, since much of the control logic, at pre-
The overvoltage relay monitors the generator ter- sent carried out by electromechanical relays, will be
525
The generator Chapter 6

software specified. Cost advantages are also envisaged 6.5 Excitation control
as standard memory circuits replace the present cus- In addition to the basic voltage control loop, modern
tomised printed circuit boards. However, the principal excitation equipment includes a number of additional
motivation lies in the range of sophisticated control- limiter circuits. These limiters operate as parallel con-
ler designs that the microprocessor makes physically trollers, in that their signals replace the generator
realisable. One class of controller is the adaptive voltage as the controlled variable whenever those in-
regulator, which (as the name suggests) is capable of put signals exceed predefined limits.
adjusting its structure to take account of changing
plant conditions. This type of regulator, shown sche- 6.5.1 Rotor current limiter
matically on Fig 6.72, consists of a recursive real- All exciters are capable of supplying generator field
time parameter estimator (based on a form of least current well in excess of that required for normal
squares structure) which is used to identify the con- MCR operation. This field forcing capability or mar-
trolled plant. The estimated plant model is then used gin is necessary during system fault conditions, where
by the regulator to form the control law. A wide the additional reactive power provides the much needed
choice of regulator/control law designs exists; typical boost of synchronous torque. However, this current
strategies include pole placement and minimum var- must be restricted in duration because of the danger
iance. Both have a very flexible structure, making it of overheating the generator rotor which would cause
a simple matter to include additional input signals, insulation system degradation. To prevent overheat-
such as machine accelerating power (which has been ing, the exciter field current signal is applied to the
demonstrated to enhance transmission system dyna- rotor current limit circuit which detects values of
mic performance), and post-fault recovery. field current in excess of 110% MCR.

CONVENTIONAL
SPEED GOVERNOR

1r i1

GOVERNOR
VALVE REF ^ POWER
* ^
TURBINE GENERATOR
GENERATOR OUTPUT

-VOLTAGE

]f 1f

DIGITAL TO ANALOGUE TO
ANALOGUE DIGITAL
CONVERTER CONVERTER

1r
i1

RECURSIVE
1 PARAMETER
ESTIMATOR COMPARATOR ... 0 REF
-^^~

ESTIMATED ,
SYSTEM ' f
F3ARAMETER

CONTROLLER
WITH ADAPTIVE
U n IMML GAI NS
CONTROL
SIGNAL

FIG. 6.72 Block diagram of adaptive excitation controller

526
Excitation

During system fault conditions, the AVR reacts to at one end of a transmission line oscillate with respect
boost excitation; normally this situation lasts only to those at the other end. These oscillations, known
milliseconds before circuit-breaker operation clears as power system oscillations, are load dependent and,
the fault. However, it is necessary to allow for the if not prevented, severely limit the MW transfer across
longest back-up protection clearance times and hence a the transmission system. To obtain a solution to this
delay of up to 5 s is specified. After this delay, the problem, an understanding of the basic machine tor-
rotor current limit circuit generates a signal which que relationships is necessary.
opposes that from the AVR and ramps excitation For a generator to remain in synchronism following
current back to a safe value. system faults, it must produce a braking torque to
balance the accelerating torques introduced by changes
to the electrical transmission system. The braking tor-
6.5.2 M V A r limiter que can be separated into two components:
Modern AVR equipment is capable of controlling
generator operation at rotor angles of 130 to 140. The synchronous torque, which is in-phase with
This mode of operation is not, however, tenable when rotor angle changes and is necessary to ensure res-
transient stability criteria are taken into account; it is toration of rotor angle following displacements.
therefore customary to limit the generator operation
The damping torque component, which is in-phase
to a rotor angle of 75.
with rotor speed changes and provides damping of
The permissible leading MVAr varies with the square
rotor oscillations.
of the generator terminal voltage, the limit line being
defined by the following equation:
Where generating units are connected to the grid over
MVAr + MW = V2 high reactance tie lines, fast response excitation sys-
tems are vital to maintain system transient stability.
VI sin</> 4- VI cos</> = V2 This has the effect, however, of reducing the inherent
generator damping torque; consequently, under cer-
The in-phase and quadrature components of stator tain load conditions, generator rotor swings following
current are obtained from a form of phase sensitive system changes will have little damping.
rectifier. The signals are then compared with the As the component of torque in question is strongly
generator terminal voltage bias and, if the limit set- associated with rotor speed, a logical starting point
ting is exceeded, an output is generated which acts to for investigation is the generator torque speed loop
boost excitation and reduce rotor angle. shown in Fig 6.73 (a).
The introduction of an AVR, while enhancing syn-
chronising torque, has a deleterious effect on the small
6.5.3 Overfluxing limit inherent generator damping torque (the latter is ob-
In addition to the overfluxing protection circuit, mod- tained by means of poleface windings or induced eddy
ern AVR equipment includes overfluxing limiter cir- current effects). This presents some difficulty, as from
cuits. This is a closed loop controller which monitors considerations of transient stability a fast response
the voltage/frequency ratio during unsynchronised op- high gain excitation system is necessary, however, its
eration. Should a predefined ratio be exceeded, the implementation could result in reduced power system
limiter generates a signal which acts to reduce ex- damping and a consequential reduction in load trans-
citation and thereby prevent generator transformer fer capability.
overfluxing. To counteract this, a device known as a power
system stabiliser (PSS) has been developed. Figure
6.73 (b) shows the addition of such a device to the
6.5.4 Speed reference controller torque speed loop. A signal derived (in this case) from
In accordance with current CEGB functional require- shaft speed is used as the input to the stabiliser; this
ments, this feature controls the application of excita- is then processed and conditioned to provide sufficient
tion during the turbine run-up sequence. This limiter phase lead to compensate for the phase lags inherent
unit ensures that voltage is brought up to nominal and in the generator plant and transmission system. The
the unit synchronised with the minimum delay. output of the stabiliser is superimposed onto the AVR
demand signal in order that an increased damping
torque component is produced.
A comprehensive linearised generator and power sys-
6.6 The power system stabiliser tem stabliser representation is shown on Fig 6.73 (c),
where it can be seen that the PSS signal is fed to the
block denoted as GEP. This represents the generator,
6.6.1 Basic concepts exciter and power system, detailed knowledge of which
Situations have occurred where groups of generators is vital if the PSS is to compensate for the phase
527
The generator Chapter 6

SYNCHRONISING TORQUE SYNCHRONISING TORQUE


CONTRIBUTION CONTRIBUTION

MS MS

AVR AVR
AND AND
EXCITER EXCITER

PSSu

E ref COMP
(a) (b)

ATm -CHANGE IN MECHANICAL TORQUE - CHANGE IN ROTOR ANGLE


TD - CHANGE IN DAMPING TORQUE COMP - COMPARATOR
T - CHANGE IN SYNCHRONISING TORQUE PSS - POWER SYSTEM STABILISER
D s - GENERATOR DAMPING FACTOR ABSOLUTE MACHINE SPEED
-CHANGE IN SPEED AVR DEMAND SIGNAL

K1 - PARAMETER RELATING CHANGE IN ELECTRICAL


TORQUE FOR A CHANGE IN ROTOR ANGLE
Ko - PARAMETER RELATING CHANGE IN ELECTRICAL
TORQUE FOR A CHANGE IN MACHINE FLUX
LINKAGE
K3 - IMPEDANCE FACTOR
K4 - DEMAGNETIZING EFFECT OF A CHANGE IN
ROTOR ANGLE
Kc - PARAMETER RELATING CHANGE IN TERMINAL
VOLTAGE WITH CHANGE IN ROTOR ANGLE
K6 - CHANGE IN TERMINAL VOLTAGE WITH CHANGE
IN MACHINE FLUX LINKAGE
Tdo - MACHINE FIELD OPEN CIRCUIT TIME CONSTANT
EXC(S) - VOLTAGE REGULATOR SYSTEM
(c) COMPREHENSIVE LINEARISED
GENERATOR AND POWER SYSTEM STABILISER

FIG. 6.73 Simplified torque-speed loop diagrams

528
Excitation

lag within GEP and produce a component of gen- if uncorrected, will result in prolonged rotor swings
erator torque in phase with speed changes. This in- in the region of 0.9-1.6 Hz.
formation can be obtained in a variety of ways, nota-
bly by on-load frequency response analysis, using pulse Intra-plant modes
injection techniques and by computer simulation tech- Intra-plant modes of oscillation occur between units
niques based on representative system models. within the same power station. Unlike the above,
these are not power transfer dependent but result from
6.6.2 Characteristics of GEP interaction between generator excitation systems. If
action is not taken, intra-plant interactions will limit
Extensive system investigations are used to establish
the available PSS gain and hence its effectiveness.
the characteristics of GEP. All operating modes of
the plant are examined to identify the conditions
under which stability is marginal. In general, operation 6.6.4 Principles of PSS operation
at leading power factor during times of low system PSS action is inhibited during steady state trans-
demand are the most critical. However, in the case of mission system conditions, as it has a detrimental
pumped-storage plant, which will generally be operat- effect on voltage control. A steady state voltage offset
ing in the pumping mode during these periods, the is prevented by the use of a washout circuit at the
situation can be more critical because of the large PSS input. The washout circuit, shown on the PSS
machine rotor angle with respect to the rest of the block diagram on Fig 6.74, is essentially a differen-
system. tiating circuit which attenuates low frequency changes.
A series of simulation studies is then conducted, The time constant of the circuit, Tw, is chosen to
using detailed plant representation (including the AVR washout low frequencies but not to interfere with
and PSS), the results being assessed by the analytical the signal conditioning networks at system electro-
techniques described in Section 6.7 of this chapter. mechanical frequencies.
The model PSS settings are adjusted until optimum The signal conditioning network provides the phase
excitation performance is achieved at all critical op- compensation, so that a torque is produced in phase
erating conditions. These settings are then used as a with speed changes. This network essentially shapes
basis for plant commissioning tests, thereby reducing the PSS characteristic to provide the best damping
expensive on-site testing. performance at all electromechanical modes. Generally
this is achieved by maximising stabiliser gain (within
6.6.3 System modes of oscillation
the constraints imposed by the power system control
loop) and shaping the phase characteristic so that it
Examination of the basic torque-speed-angle loop in has a slightly lagging value at the particular inter-
Fig 6.73 yields Wn (natural frequency of electro- area oscillation frequencies of concern. To prevent the
mechanical oscillations) = V(wKie/M) rad/s. For intra-plant interaction, tuning should ensure that the
typical values of machine inertia (M) and synchron- overall phase characteristic is not greater than 90
ising torque coefficients (Kie), the frequency range of
lagging at frequencies up to 4.0 Hz.
interest is 0.2-4.0 Hz. Within this frequency range,
It is important to emphasise that PSS action is
the oscillatory modes can be broadly divided into
intended to improve the system damping following
three main components.
small disturbances. PSS action following system faults
will degrade AVR performance, and hence system
Inter-area or inter-tie oscillations recovery; therefore, the stabiliser output is limited, so
Inter-area oscillations range typically from 0.2-0.6 Hz that AVR action is dominant during the first post-
and occur where two generation groups are connected fault cycles.
by a weak tie line; they tend to be power transfer
dependent. Inadequate damping of these modes will
6.6.5 The choice of stabiliser signal
result in operational difficulties, since power transfer
capability is reduced. These low frequency inter-tie An obvious choice for the stabiliser input signal is
oscillations have been initiated by random events oc- rotor shaft speed, measurements being generally made
curring during periods of high MW transfer over weak at the HP turbine pedestal. The drawback with this
transmission links and/or unusual load distribution. form of signal is its inherent susceptibility to shaft
torsional frequencies. This term refers to the reso-
nance conditions on the shaft line which cause one
Local mode oscillations section of shaft to oscillate with respect to another
These occur where a single generator is exporting with little natural damping. These frequences act
power over a high reactance transmission link. In through the PSS and excitation system to set up elec-
these situations the need for static thyristor excitation tromechanical torques which tend to aggravate the
systems (because of transient stability requirements) situation and, in the extreme, to cause shaft damage.
aggravates the problem of steady state stability which, To eliminate this potential problem, detailed infor-
529
The generator Chapter 6

STABILISER
LIMITS

STABILISER GAIN SIGNAL CONDUCTIVITY WASHOUT POWER TRANSDUCER

(1 +T a S)(1 +T b S) TwS

(1 + T S ) ( 1 +T d S) 1 +T S
STABILISER
OUTPUT

VT CT
GRID

FIG. 6.74 Power system stabiliser block diagram

mation is required of the shaft torsional conditions 6.7 Excitation system analysis
so that, if possible, speed probes can be mounted at Trends in modern generator design, with the empha-
a torsional node and suitable torsional filtering can sis on large thermally-efficient but electrically-remote
be applied. centres of generation, have combined to reduce trans-
Because of these considerations, use is made of a mission system stability margins. As a consequence,
signal derived from generator electrical power which the primary responsiblity for power system dynamic
is related to shaft speed by the following relationship: and transient stability rests with the generator excita-
tion system.
P e )dt (6.1)
> Dynamic stability refers to the system performance
following small load changes which, under conditions
where is shaft speed change, P m is mechanical of high MW transfer over long distances, can result in
input power, P e is machine electrical power and M is sustained oscillations in the region of 0.5 Hz. If these
the angular momentum. If the mechanical power is oscillations are not rapidly attenuated, severe limits
assumed to remain constant, Equation (6.1) is sim- will be imposed on transmission system operation.
plified to:
Transient stability is concerned with the ability of a
=
i >* (6.2) generator or group of generators to maintain syn-
chronous operation following system faults. Under
such operating conditions, the generator requires a
The major advantage of this form of stabilising signal boost of synchronous torque. This is provided by the
is its insensitivity to torsional oscillations and the transmission system in the form of a synchronous
simplicity of measurement. Its adoption, therefore, component of the post-fault infeed. However, as the
has both technical and cost advantages. reactance of the transmission line connecting the gen-
530
Excitation

erator to the system increases, the synchronous tor- oscillatory response. It is possible to simplify the
que component is reduced. Under these circumstances, interpretation of the root locus diagram by consider-
the AVR bucks and/or boosts the generator field ing those poles which lie furthest to the right as
current in such a way that the generator itself develops dominating the system response.
the additional synchronising torque. This approach is extended to the multivariable situ-
A properly tuned AVR therefore performs a vital ation by making use of modern state variable theory.
role in the maintenance of stable system operation The system considered is first linearised about the
under all operating conditions, and this section is operating point of interest and the equations of state
concerned with the methods developed and employed formed.
to analyse AVR performance, and hence to arrive at
tuned settings. X = AX + CV Input equation
Y = DX + FV Output equation
6.7.1 Frequency response analysis
Frequency response analysis is based on the injection where X is the vector of state variables, Y is the
of a sinusoidal signal at the input to the AVR and vector of output variables, A is the state matrix and
the corresponding measurement of generator terminal C,D,F are the feedback, input and output matrices,
voltage magnitude and phase shift. This procedure is respectively.
repeated over the range of frequencies necessary to A series of simulations is conducted over the com-
identify the plant, which in the case of the generator plete generator operating regime, using a detailed
excitation system is 0.2-4.0 Hz. Results are plotted model of the turbine-generator and excitation sys-
in the form of inverse Nyquist or Bode diagrams, from tem. The dominant poles (or equation solutions) are
which information on system stability and damping plotted for a range of control settings, and those iden-
can be obtained. These tests can be repeated for a tified as providing optimal damping at the most critical
range of AVR settings until an acceptable system operating condition are selected for commissioning
response is established. Performance indices used in purposes. This method of analysis therefore provides
this form of analysis are system gain and phase mar- advanced information regarding equipment settings
gins, both of which are measures of relative stability. and plant performance, thus reducing expensive com-
In general, a phase margin of 40 or more, and a missioning time.
gain margin of 6 decibels is considered good design
practice for most feedback control systems.
An alternative approach is the injection into the 6.7.3 Large signal performance investigations
AVR summing junction of a short duration rectan- The foregoing methods are based on the response of
gular pulse. The corresponding machine terminal volt- the excitation system to small signals; hence non-
age response is measured and harmonically analysed linearities can be ignored and the system assumed to
by a computer, using a fast Fourier transform pack- be linear.
age. The results are then plotted in the form of an It is equally important, however, to investigate the
inverse Nyquist diagram from which measurements performance of the turbine-generator plant following
can be made of relative stability and damping. This substantial changes in operating conditions. In these
approach has a number of distinct advantages, par- situations the non-linear characteristics of the plant
ticularly during on-load testing as, unlike variable must be taken into account to obtain realistic results.
frequency techniques, pulse injection testing can be These large signal performance investigations pro-
undertaken without the risk of exciting power system vide a means of evaluating excitation system response
oscillations. following a major transmission system disruption (gen-
erally a three-phase fault at the generator transformer
high voltage terminals is used for standard studies
6.7.2 State variable analysis and investigations), which could jeopardise system
A common method used to assess the performance transient stability.
and stability of feedback control systems is to track Transient stability analysis is primarily concerned
the path taken by the roots or poles of the closed with the effect of transmission line faults on genera-
loop transfer function. Changes in system parameters, tor synchronism. While certain simplistic approaches
such as gain and time constants, cause these poles exist dealing with the case of a single machine operating
to move. The path taken by the poles in response onto an infinite bus (such as the equal area stability
to control system changes can be plotted and are criteria), a full multi-machine solution is generally
known as a root locus. Referring to Fig 6.75 any necessary requiring the use of digital computer simula-
roots appearing on the right hand side of the S-plane tion techniques. These simulation packages represent
imply an unstable system. Roots on the real axis in- in detail the generator, transmission and excitation
dicate an exponential or overdamped response, and systems, and solve the governing non-linear differen-
roots containing an imaginary component imply an tial equations by numerical integration.
531
The generator Chapter 6

STABLE UNSTABLE
FORM OF TIME-DOMAIN
RESPONSE

-T-J15

LOCATION OF EIGENVALUE
OR ROOT IN S-PLANE - h i 10

FIG. 6.75 S-plane showing possible root locations with corresponding time response

The ability to simulate these situations is essential the windings are not colder than their ambient hy-
to the CEGB, because generator excitation system drogen. Cooling water to the hydrogen, distilled water,
performance under system fault conditions cannot be winding water, seal oil and excitation heat exchangers
demonstrated by test methods, due to the potential is established. The lubricating oil system (common
risk to system stability. with the turbine) must also be operating, and also the
jacking oil system if the shaft is at standstill.
The run-up cycle is primarily determined by the
requirements of the steam turbine, and may be under
7 Generator operation the control of an automatic run-up system. It is ad-
In this section, the operation of the generator under visable to pass through the first and second critical
all common conditions is considered. Electrical and speeds of the generator rotor (roughly, 800 and 2200
other parameters are introduced as necessary in order r/min) quickly to avoid subjecting the bearings to
to describe the condition. the increased vibration amplitudes which may occur
at these speeds (see Fig 6.27).
As the rated speed is approached, excitation may be
automatically applied by the voltage regulator (or this
7.1 Running-up to speed may be manually applied) by closing the exciter and
Before running-up to speed, the casing and other main field switches. The resulting voltage will be pre-
components will have been scavenged of air and filled vented, by a voltage/frequency control device, from
with hydrogen to a pressure approaching the rated. being greater than would maintain rated voltage/fre-
Hydrogen pressure increases with increasing tempera- quency, so as to prevent overfluxing of the generator
ture and the objective is to achieve rated pressure transformer. At rated speed, rated voltage should be
when on steady load. The seal oil system must be generated, with the machine on open-circuit, unless
operating in order to contain the hydrogen. The stator some other voltage condition is required. Speed is
winding water system is established, taking care that under the control of the turbine governor. Vibration
532
Generator operation

levels are monitored at all the bearing housings and


at the shafts adjacent to the generator bearings during
run-up.
AIRGAP
LINE

7.2 Open-circuit conditions and STATOR VOLTAGE %

synchronising 100
Generators are usually operated at or near their rated
voltage, any departure demanded by the transmission
system being accommodated by the transformer tap-
changer. A generator voltage range of 5% is speci-
fied. For the same MVA output, a higher voltage
results in greater losses and temperatures in the core
but lower current in the stator winding, so the overall
thermal conditions are not much changed.
Since these large generators are invariably connected
to the grid through generator transformers, the rated
voltage of the generator can be determined by the
manufacturer to give the most economic design. Once
the first of a new rating has been decided, a degree
of standardisation is imposed to allow generator trans-
former units to be made interchangeable, 22 kV being ROTOR CURRENT
standard for 500 MW units and 23.5 kV for 660 MW
units, on the CEGB's system.
FIG. 6.76 Open-circuit characteristics
The electrical phasor diagram for this excited, open-
circuit condition is shown in Fig 6.7, though, at this
stage, the machine is not running synchronously with
the transmission system. ference voltage would cause a large current to circulate
The open-circuit characteristic will have been es- from the system through the stator windings, causing
tablished during running tests in the manufacturer's high forces in the windings. If the frequencies were
works. The rotor currents for several values of stator significantly different, the sudden pulling into syn-
voltage are measured and plotted (Fig 6.76). The chronism would impose a large torque on the rotors.
relationship is virtually linear (the airgap line) up to A back-up check synchronising device inhibits the
about 75% rated voltage, demonstrating that the air- circuit-breaker from closing if the voltages, angular
gap reluctance is constant, whereas the iron circuits positions and speeds do not match within predeter-
depart markedly from constant reluctance as the flux mined tolerances.
density increases above the point at which saturation Once synchronised, the speed is effectively con-
starts to occur. After a long shutdown, it is reas- trolled by the transmission system and the steam ad-
suring to check a few points on the open-circuit mitted to the turbine produces just sufficient power
characteristic with the unit on manual excitation. Note to overcome the mechanical and magnetisation losses.
that direct measurement of rotor current is not possi-
ble on brushless machines.
Synchronising is effected either manually or by
means of an automatic synchroniser. The speed of 7.3 The application of load
the unit is adjusted by controlling the speed governor If the voltages and angular positions match exactly,
until the generated frequency closely matches the no current flows in the windings and no electrical
system frequency. The generator voltage is adjusted torque is produced. In order to generate load, an
by the setpoint of the voltage regulator until it closely imbalance in the phasors must be created.
equals the voltage of the system, as monitored by a The turbine steam inlet valves are therefore gradu-
voltage transformer with the same ratio as the ally opened further; the extra torque thus produced
generator transformer, or directly where a low volt- starts to accelerate the rotors so that they move for-
age switch is used. The main circuit-breaker is closed ward relative to their no-load (direct axis) position,
when the two voltage phasors are almost coincident, though still in synchronism with the system. The volt-
and the generator will then pull into and remain in age phasor difference created by this angular change
synchronism with the system. If the voltage phasors results in current circulating from the system through
were significantly different in magnitude or angular the stator windings, producing an electrical torque
position when the circuit-breaker is closed, the dif- which balances the increased mechanical torque, re-
533
The generator Chapter 6

suiting in a new state of synchronous equilibrium at


a 'load angle' (see also Section 2.6 of this chapter).
Because the generated voltage effectively depends
on the system voltage and the load being generated,
action by the voltage regulator cannot change the
generated voltage directly. However, if the rotor cur-
rent is changed, the phase relation between the gen-
erated voltage and current is changed, and the required
power factor can be maintained by voltage regulator
action. These processes of control of generated load
and power factor continue to meet the requirements
of the transmission system, as long as the unit remains
synchronised. Phasor diagrams for various on-load
conditions are shown in Figs 6.8 and 6.9. 62 90
ROTOR ANGLE &
(a) Illustrating stable equilibrium

7.4 Steady state stability


The power produced by a synchronised generator can
be expressed as (VE sin )/(Xd). For a given machine,
operating at a terminal voltage V, the synchronous
reactance Xd is a constant parameter, and if the
'internal voltage' E, or rotor current, is kept constant,
power varies as sin . At rated conditions, is about
45-55.
From this position, a sudden increase in steam
throughput, or (more likely) a sudden demand for
more power into the system, perhaps because of a
fault on the lines, results in an increase in and in
generated power until a new equilibrium position is &1 90
ROTOR ANGLE &
reached (Fig 6.77 (a)). (b) Illustrating instability

This is valid if is less than 90 before the sudden


change. Once is greater than 90, a demand for
more power cannot be met by an increase in load
angle, and the generator rotors cannot attain a posi-
tion of equilibrium (Fig 6.77 (b)). The rotor then INCREASED EXCITATION
accelerates to just above synchronous speed and op-
erates in a non-synchronous mode ('pole slipping'),
with large power and voltage oscillations which are
unacceptable to either the transmission system or the ORIGINAL EXCITATION

boiler controls. The situation may be retrievable if


the voltage regulator can initiate a rapid increase in
the field current, increasing E in the equation, to
prevent instability (Fig 6.77 (c)).
Load angles approaching 90 are associated with
operation at leading power factor, which is not a
normal requirement in the UK. However, studies of 61 62 90
the transmission system under all credible conditions ROTOR ANGLE 6

of loading, line outages and faults are carried out to


(c) Maintaining stability by increasing excitation

ensure that the system will not fall into instability,


and the required values of synchronous reactance FIG. 6.77 Steady state stability
and excitation response are based on these studies,
which may recommend different values in different
locations. In practice, because of magnetic saturation,
Xd is reduced as the load angle moves towards 90, unit in the quadrature axis.
the 'quadrature axis' position, so that the limiting Operation at leading power factors requires re-
condition is ameliorated slightly. Values for CEGB duced rotor current. Operation with zero rotor current,
machines are about 1.8 per unit, falling to 1.7 per at zero MW, and a leading reactive output = Rated
534
Generator operation

MVA/Xd (or strictly Rated MVA/Xq where Xq is scale of a vector meter, across which cursors travel
the quadrature axis synchronous reactance), determines parallel to the axes, representing generated MW and
the theoretical limit of stability. The practical values MVAr, the operating point being where the cursors
of leading reactive outputs, allowing a margin for intersect. Permissible operating areas are indicated
overshoot, with different types of excitation control on the instrument.
(see Section 5 of this chapter), can be plotted on a It can be seen that the capability chart is another
MW-MVAr diagram. The example shown in Fig 6.78 manifestation of the generator phasor diagram. Op-
allows for instantaneous increases in MW of 4% at eration at rated load and about 0.95 power factor
rated load and 10% at zero load. leading is possible, though rarely required.

7.5 Capability chart 7.6 Steady short-circuit conditions, short-


The capability chart is a MW-MVAr diagram, for circuit ratio
which the limits of leading MVAr were discussed Another relationship that is established during works
above. testing, is between the field current and the stator
A constant MW limit can be drawn at the rated current with the three stator line terminals short-
power output of the turbine, though the maximum circuited (Fig 6.79). In this condition, the voltage re-
power capability of the steam system may be signi- quired to circulate, say, rated current through the wind-
ficantly greater than this. The circular locus of rated ings is very low (= Xtf, say 0.15 per unit) and there-
stator current cuts the rated MW line at the rated fore the flux is also very low and conditions are lin-
MVA and power factor point, but does not in prac- ear, since there is no magnetic saturation. Most of the
tice impose a limit. The rated rotor current, also a considerable magneto motive force (MMF) produced
circular locus but with its origin at the 0 MW, by the rotor is required to counteract the armature
Rated MVA/Xq MVAr point, imposes a limit at con- reaction MMF produced by the stator winding.
ditions of MW and lagging power factor both lower Running under these conditions in order to cir-
than rated. Such a capability chart is used as the culate current through the windings to dry out the

RATED STATOR
CURRENT

RATED CONDITIONS

TURBINE RATING

THEORETICAL
STABILITY -
LIMIT

RATED ROTOR
CURRENT

- RANGE OF MVAR FOR SYNCHRONOUS COMPENSATION -


MVAR

FIG. 6.78 Capability chart

535
The generator Chapter 6

(Note that different considerations apply to a salient


pole machine, where the geometry of the magnetic
OPEN CIRCUIT paths is very different when operating near the quad-
rature axis from that in the direct axis, and Xd and
Xq have dissimilar values.)

100 7.7 Synchronous compensation


While operation in this mode is not foreseen for
generators of this rating in the UK, a note here is
included for completeness. A generator, synchronised
STATOR to the system, may be used to generate or absorb
CURRENT
% reactive MVA, while drawing its loss power from the
system. By varying its excitation, it can be operated
over the range shown on Fig 6.78, to meet the re-
quirements of the system. It is not normally possible
to drive the turbine at rated speed with no steam flow,
ROTOR CURRENT
and smaller generators operated in this way are de-
coupled from their turbines. At large values of leading
FIG. 6.79 Open- and short-circuit characteristics reactive generation, stator core end temperatures may
be high, because the axial components of MMF from
both stator and rotor windings become more in phase,
resulting in higher values of axial leakage flux.
insulation is not a normal requirement for these large
generators. It may, however, be necessary to demon-
strate the capability of the connections between gen-
erator and transformer, in which case the short- 7.8 Losses, efficiency and temperature
circuit would be applied at the transformer terminals. Many separate components of loss can be identified,
Manual control of excitation is essential. some of which are substantially constant irrespective
The open- and short-circuit characteristics enable of load; others can, for simplicity, be assumed to
certain parameters to be established. Short-circuit ra- vary approximately as (stator current)2. These com-
tio (SCR)
ponents are listed below, with kW values given for a
typical 660 MW generator at rated conditions:
Rotor current for rated voltage on open-circuit
Rotor current for rated current on short-circuit Constant losses Coolant loss, kW
_ Wo Fan loss Hydrogen 600
Ifs Rotor windage loss Hydrogen 350
Other windage loss Hydrogen 150
Open-circuit core (iron) loss Hydrogen 950
This rough measure of steady state stability is nearly Bearing loss Lub oil 600
the reciprocal of Xd; minimum values of 0.4 and
Shaft seal loss Seal oil 100
0.5 are specified for the 500 and 660 MW units, re-
spectively. Rotating exciter constant 1oss Exciter air 100
Auxiliary system losses, e. g., motors 100
Synchronous reactance Xd may be quoted as the
reciprocal of short-circuit ratio, in which case it is Variable losses Coolant loss, kW
the value corresponding to the degree of saturation Stator copper loss Stator winding water 1600
at rated voltage on open-circuit (which is not the same Eddy current loss in
as that at rated load). It is of interest when discussing windings Stator winding water 600
operation close to the stability limit, in which case Additional core loss, >
its unsaturated value is appropriate and given by: due to higher flux and
end loss
Hydrogen 1600
Rotor current for rated current on short-circuit Loss in core end plates
Rotor current for rated voltage on airgap line and frame
Loss in rotor surface J
Rotor copper loss Hydrogen 2400
Ifg Variable excitation loss Exciter air 150

536
Generator operation

The total loss is typically 9300 kW, and the effi- nents of concern are the negative sequence components.
ciency is 98.6%. The efficiency is slightly higher at In order to circulate negative sequence currents
about 80% than at 100% MW load, and also im- through the generator stator and transformer wind-
proves as the power factor increases towards unity. ings, a system of negative sequence voltages must be
The losses shown in the list are removed by the var- produced by negative sequence flux, i.e., flux rotating
ious cooling systems described in Section 5 of this at synchronous speed but in the opposite direction of
chapter. The total loss removed by each system is rotation to the main flux. This cuts the rotor at twice
therefore known, and the flow rates are designed to the rotational speed, and induces a 100 Hz voltage in
maintain an appropriate temperature. In the hydro- the rotor surface. 100 Hz current flows in the outside
gen system, 30 m 3 /s of hydrogen is circulated, being 'skin' of the rotor body, in the wedges and in the
cooled to about 40C by the heat exchangers, and top winding conductors, as if these components were
reaching about 65C on entry to the coolers. The part of the squirrel cage of an induction motor.
stator core will attain about 75C, except at the ends, Additional heating therefore occurs in these regions;
which are likely to be hot, but within the BS limit in particular, in positions where current transfers
of 120C. The rotor winding will reach an average from one component to another, such as at the wedge
temperature of 105C with local hot spots perhaps ends, and at the endring shrink faces.
20C higher than this, which poses insignificant ther- Because of the potentially damaging effect of this
mal stresses on the insulation and creep conditions on extra heating, limits on the extent of unbalance have
the copper and aluminium components. to be established. These are conservatively set to ini-
In the stator winding water system, conditions differ tiate alarms when the negative sequence component
between single and double pass arrangements, but exceeds 5% of the rated current and to trip at above
with inlet water cooled to 40C, the outlet water will 10%. The component is detected by a three-phase cir-
not exceed 70C. Hence the winding copper will bare- cuit designed to respond to negative sequence current.
ly exceed 70C, and then only at the water outlet In some designs, copper shims are placed in the
end, and the winding insulation will nowhere exceed ends of the rotor slots, below the wedges, and extend-
100C. CEGB specifies Class F insulation with Class ing outboard of the rotor body to form a continuous
B rises, which are very comfortably met in these ring, in order to assist circumferential current flow
designs. and to minimise the small intense hot spots where
A considerable advantage of water cooled windings current transfer is concentrated. Where circumfer-
is that the temperatures are inherently constrained to ential slots are cut into the pole faces (Section 3 of
be very low, thus maximising the intrinsic life of the this chapter), means for transferring surface current
insulation. Also, since the temperature rises of the across the slots are provided, usually in the form of
core and windings are similar, problems associated copper strips retained by wedges in shallow 'pole
with differential thermal expansion are minimised, face slots', to avoid overheating at positions of current
and it has not been found necessary to incorporate concentration.
features in the end windings to accommodate axial The shallow surface current paths must also handle
movement. the very much larger, short duration currents imposed
by unbalanced conditions during transient faults. A
rough criterion of acceptability is provided by assuming
that the heating is proportional to E(I 2 ) 2 t, where
12 is the negative sequence stator current (per unit)
7.9 Electrically unbalanced conditions
and t the time (in seconds) for which the condition
The amplitudes and phase displacements of the three- persists. This is only approximately valid for times
phase voltages and currents in the transmission system short enough for heat dissipation to be ignored. Per-
are usually symmetrical to within about 1%, which missible values of (I 2 ) 2 t of about 3 are usual for
does not impose any significant difficulties in the 500/660 MW generators, and 'instantaneous' trip-
generator. However, it is possible for much larger ping is initiated if this value is exceeded (see Fig
unbalances to exist, for example, if one phase of a 6.81).
circuit-breaker remains closed while the others are The surface current paths are also involved in any
open for considerable lengths of time, then the ability condition in which the generator is connected to the
of the generator to withstand such conditions must system but is not operating synchronously. This may
be established. happen on total or partial loss of excitation, and
The well known method of resolution of unbal- can usually be tolerated by the generator for a short
anced phasors into systems of symmetrical components time, although slip frequency surges will occur on
is used in the analysis shown in Fig 6.80. Because the system. Because the induced currents are at slip
generators are invariably connected to transformers frequency, they are able to penetrate further into the
whose LV windings are arranged in delta, which there- rotor, wedges and winding, and the thermal conditions
fore do not have a neutral connection, zero sequence are not as critical as with the 100 Hz currents pro-
voltages and currents cannot exist. The only compo- duced by unbalanced operation.
537
The generator Chapter 6

Vc-
UNBALANCED VOLTAGE SET

AN UNBALANCED VOLTAGE SET CAN BE


RESOLVED INTO THE FOLLOWING:

A Va+
Vb-


Vc+, Vb+

(a) Balanced (b) Balanced (c) Zero-sequence


positive-sequence negative-sequence components
components components (normally negligible)

FIG. 6.80 Unbalanced phase conditions

7.10 Transient conditions vious position, i.e., changes, so that the electrical
Changes in the load demand, system operation con- power generated changes to restore equilibrium. The
ditions and the response of other generating units, combined effect of similar load changes occurring in
mean that conditions at the unit transformer terminals many units acts to restore the system frequency to its
are constantly changing. Increase in overall demand original value.
causes a fall in frequency to which the speed gover- Coincident with the change of load will be a change
nors of all the connected turbines respond. Their rate in system voltage, which causes the voltage regulator
of response depends on the settings of the individual to adjust the excitation to restore the original voltage
governors, some units being deliberately arranged to value. (A large voltage change may require a trans-
act more responsively than others. former tapchanging operation to maintain the gen-
A highly responsive unit varies its steam inlet valve erator terminal voltage near its rated value.)
position frequently, causing the steam throughput to Flux cannot change in the machine instantaneously,
change and altering the torque equilibrium. The ro- and the rate-of-change is influenced by the transient
tors move forward or backward relative to their pre- reactance X^' This depends largely on the flux paths

538
Generator operation

PERMISSIBLE FAULT CURRENT


- TIMES MCR CURRENT

3.0


I
_ \
\

2.0

N . P HASE-T O-PHAi>E FAUL TCURF ENT


1.0

PH ASE-TO-EARTH FAULT
CURRENT
~^!%1^

DECRFASiMn 1700/
^ ' ' J ' ^v\\ i INUUUSLY

40 50 100

TIME-S

FIG. 6.81 Duration of fault currents

embracing the stator winding slots, the airgap and change of flux induces currents in the rotor surface
the rotor slots, with a small component associated paths, and for the first few cycles, say up to 200 ms,
with the end windings, and is affected by the degree conditions depend more on a reactance linking these
of magnetic saturation. The normal value for un- surface flux paths with the stator winding. This is
saturated transient reactance is of the order of 0.3 referred to as the sub-transient reactance, X d " , with a
per unit. value of about 0.2 per unit. It is this reactance which
It is this reactance which controls the initial rise- limits the current in the first few peaks after a fault.
of-voltage when load is suddenly tripped off; typi- For a three-phase fault at the generator terminals from
cally the voltage rises instantaneously to 1.3 per unit rated voltage open-circuit, the RMS value of the initial
and finally reaches a value determined by the pre- current peak will be V / X d " , i.e., 1/(0.2) = 5 per unit.
vailing value of rotor current. Also, transient reactance The peak value is V2 times this, and, if the par-
is used in calculations involving the stability of the ticular phase experiences full asymmetry (depending
unit with the system during a transient fault situation. on the instant at which the fault occurred), it is pos-
Such studies require accurate representation of gen- sible for the first peak to reach 2V2 x 5 = 14.14
erator parameters, and in this context it is important times rated current. In practice, flux decay results in
that its specified value has been met (see Fig 6.82). the maximum current being about 90% of this value,
During conditions of massive change, such as those but if the short-circuit is applied from a condition of
that occur during a close-up fault, when the terminal load, i.e., with increased flux and a higher Internal'
voltage may be suddenly reduced to half its rated voltage, the peak current could be greater.
value (or even to zero for a fault at the generator or Such peaks of current result in enormous forces
transformer low voltage connections), the very rapid on the stator windings in the slots and end windings

539
The generator Chapter 6

<
^ INSTANTANEOUS
RISE
100

VOLTAGE
%

ROTOR CURRENT FOR


RATED LOAD

/
ROTOR CURRENT TIME

OPEN-CIRCUIT CHARACTERISTIC ASSUMES NO VOLTAGE REGULATOR ACTION

FIG. 6.82 Voltage rise on rated load throw-off

(since force varies as current squared), and in the between two phases. Here, the phasors become highly
connections, which would result in considerable move- unbalanced, and the 'negative sequence reactance',
ment if the components were not adequately sup- X 2 , helps to determine the peak current, which may
ported to resist them. It is therefore vital to establish attain a maximum of 2V2 x V3(V/Xd- + X2) which
the value of sub-transient reactance. (It should be is of a similar magnitude to that in the three-phase
noted that the thermal effects are not troublesome case.
because of the rapid rate-of-decay of current.) In a line to earth fault, the 'zero sequence reactance',
Another reason is to ensure that the main circuit- X 0 , is involved, and the peak current may be 2V2 x
breaker (and low voltage switch, if fitted) is able to V3 (V/Xd" + X2 + X0) usually considerably lower
withstand these very large through-currents and that than the three-phase value, depending very much on
it can, if necessary, break them although, in practice, the neutral earthing arrangement.
it rarely breaks on the first peak of current. Works tests for X2 and X 0 are not normally carried
To measure the transient and sub-transient re- out, even on prototype designs, since X2 is easily
actances and their associated time constants, a three- derived from the positive sequence reactances, and
phase short-circuit is suddenly applied to the prototype the value of X 0 is not as critical as the others.
generator running at speed during the in-works tests, Another factor involved in transient stability repre-
while excited to one or more agreed voltage values, and sentations is the inertia of the rotating masses, usually
the resulting three-phase currents recorded. Figure quoted as the 'inertia constant' H, with units of MW
6.83 shows a typical trace and how the X d ' and X d " seconds/MVA (or simply seconds). For these ratings,
values are deduced, while Fig 6.84 shows how the H will be of the order of 3.0, of which the generator
reactances vary with initial voltage due to saturation. contributes only about 0.8. The higher the inertia,
A generator terminal fault, though physically vir- the longer the time taken to accelerate the rotors
tually impossible, imposes the most severe of the into instability, allowing more time for corrective
three-phase conditions, with the effective voltage 1.0 action and hence a bigger margin.
per unit, or higher. More likely is a fault on the
system which, because of the interposed reactance
of the generator transformer, imposes short-circuit
currents similar to those from a terminal fault at a 7.11 Neutral earthing
voltage equal to X d "/(X d " + X e ), where Xe is the The neutral ends of the three phases of the stator wind-
reactance of the transformer and that part of the ing are connected together, outside the casing, by the
system between it and the fault. 'star-bar', which may be located underneath the cas-
A type of fault more likely to occur, particularly ing alongside the line connections, or above it in a
inside the generator, is one involving a short-circuit special enclosure. The star point is connected to earth
540
Mechanical considerations

through a neutral earthing device, designed to limit


the fault current in the event of a stator winding fault
TERMINAL
>ANl to earth.
The neutral earthing device of earlier generators
VOLTS

consisted of a water resistor, designed to limit the cur-


rent in a line to earth fault to a maximum of 300 A.
More recent machines use a small single-phase dis-
tribution type transformer with its primary connected
I/IMA)\AAAAAA/\/WVVWWWVVWI between the generator star point and earth, and its
secondary loaded onto a resistor. This arrangement
limits the fault current to about 15 A, and was ori-
3-PHASE SHORT-CIRCUIT CURRENT WAVES ginally intended to allow an internal fault to be sus-
tained while load was reduced, rather than requiring
an instantaneous trip. Modern practice is to trip in-
stantaneously on fault detection, even with this form
of earthing. In both cases the sensitivity of protection
10
1 is such that a fault at less than 10% from the neutral
point is not detectable, and could persist, though the
H low voltage to earth in this part of the winding makes
8
1 fault initiation less likely and fault current compara-
VALUES OF STATOR
' \ \
FULL LOAD J
1 \ \ tively low.
CURRENT AND ROTOR
NO-LOAD CURRENT
H
L \ >>
fc% \ s
H E ~
5A ^ S f c > ^ ^ 2 . T 0 R
FIELD CURRENT
x d.
H 7.12 Shutting down
H
4-J

0 2
1 1 1 1 i i i I i i 1 1 1 1 1 The process of load reduction is the reverse of that for
INSTANT OF
4 6 8 10 15 20 25 30 35 40
NO OF CYCLES
50 100 200 300
load increase except that, when the load has reached
a low value, the main circuit-breaker (or the LV
SHORT CIRCUIT

switch, if fitted) is opened, and with it the turbine


STATOR AND ROTOR SHORT-CIRCUIT CHARACTERISTICS
WITH 100% ASYMMETRY

steam valve and the excitation crcuit-breakers. The


FIG. 6.83 Three-phase short-circuit current characteristics unit runs down in a time determined by the inertia
of the rotors and the windage and friction losses. At
some stage, the motor-driven lubrication pump is
switched in to take over from the shaft-driven pump.
The turbine must usually be barred for some hours
on shutdown, and lubricating oil must be maintained
to all the bearings during this process.
REACTANCE
It is usual to leave the hydrogen in the generator
%
30 H casing, unless a prolonged shutdown is envisaged or
access to the casing is required in order to avoid
wastage of gas. The pressure will fall as the tem-
perature drops, but it is not usual for the pressure to
be maintained exactly at rated value, nor for water to
be circulated in the coolers and windings. It is essential
SUB-TRANSIENT
REACTANCE
that the shaft seals are supplied with oil both during
barring and when stationary, to prevent hydrogen leak-
age, and, because of the possibility of moisture ingress
from the seal oil, the blower may be run in order to
circulate hydrogen through the dryer.

I
50

INITIAL VOLTAGE %
8 Mechanical considerations
Some aspects of torque, stresses, vibration, etc., were
mentioned in Sections 3 and 4 of this chapter, and
these and other mechanical aspects are considered in
FIG. 6.84 Transient and sub-transient reactances more detail in this section.
541
The generator Chapter 6

8.1 Rotor torque life. Results from models do not scale accurately and
At a constant load (electrical output and generator at the most extreme (and therefore most damaging)
losses) of P kW, the torque (Nm) experienced at the stress, the highly non-linear effects of material damp-
turbine-generator coupling is 9545P divided by (r/min). ing must be considered.
The coupling must be capable of transmitting the In the UK, where high speed reclosure is not prac-
torque associated with rated output continuously with- tised, sub-synchronous resonance due to the use of
out deformation. These couplings commonly have series capacitors is not a problem and the operation
four of their bolts closely fitted into both coupling of the transmission system is under close control,
flanges, while the other bolts have smaller diameter it is thought that the combination of very high stresses
and a clearance in the coupling holes. The torque is and very low probability of occurrence results in an
transmitted partly through the fitted bolts and partly acceptable risk for rotors designed to conventional
through friction between the flange faces. The full specifications, and that lifetime monitoring is not
torque must also be transmitted through the shaft justified.
end at the turbine end, which must therefore be de- The exercise has highlighted the need to avoid
signed to withstand it. stress raisers such as unnecessarily small radii, and to
In the very much larger section of the rotor body, ensure a high quality surface finish. It has also drawn
shear stress due to torque is very much less than in attention to the need to design the generator to ex-
the shaft ends and is not of significant magnitude. citer coupling to withstand torques of the order of
Also, the transmitted torque reduces in a linear man- the rated generator torque, since it has been shown
ner along the length of the rotor body, so that at that these can exist during transient conditions.
the exciter end, only the small torque required to The requirement for torque transmission places a
drive the rotating exciters (and any other coupled equip- limit on the minimum diameter of the shaft and therefore
ment) has to be transmitted. of the journal. An acceptable compromise between
As noted previously, during electrical faults, stator the higher loss associated with a large diameter and
currents of many times rated value occur, and these adequate hydrodynamic stability results in a bearing
cause electromagnetic torques of a similar magnitude. somewhat shorter than its diameter for these ratings.
The torque reaction at the turbine to generator cou- Bearing performance is described in Chapter 1.
pling and in the associated shafts depends, among
other things, on the ratio of inertias of the turbine
and generator rotors, but can also be several times
rated torque. The specification requires that the shaft 8.2 Stress due to centrifugal force
and coupling shall be designed to withstand stipulated All rotating components are subjected to stresses due
fault conditions, without failure, though not neces- to centrifugal forces, and are designed so that the
sarily without permanent distortion of components yield stress of the material exceeds the stress at over-
such as coupling bolts. It is not unknown for the speed by an adequate safety factor. Usually the com-
fitted coupling bolts to exhibit distortion after a severe ponents closest to the limit are the rotor teeth, rotor
electrical fault. wedges, end rings and outermost winding conductors.
Materials subjected to repeated high stresses ex- The tensile stress in the rotor teeth was considered
hibit a lifetime, during which damage is accumulated, as part of the rotor optimisation in Section 3 of this
and at the end of which failure occurs fairly rapidly. chapter. It is greatest at the tooth root, but will have
Much effort has been devoted to establishing models local concentrations at the wedge dovetail. There will
of turbine-generator shaft systems in order to be able also be a high local stress where the wedge transfers
to predict their remaining 'life' (i.e., ability to with- the centrifugal force (CF) load of the slot into the
stand further faults), knowing the history of the faults tooth. Detailed finite element analysis is carried out
to which they have already been subjected. This has to ensure that unacceptable stress concentrations are
been done analytically, knowing the torsional char- avoided. These stresses are constant at constant speed,
acteristics of the rotor system, and computing the so that the only cyclic factor is the number of stop-
shaft torques due to postulated electrical transients. start cycles, which is relatively few (<10 4 ) over the
It was found that in the case of rapid reclosure of a lifetime of the machine. Thus crack propagation by
circuit-breaker following clearance of a faulty line, high cycle fatigue from this mechanism alone is not
the magnitude of the peak of torque depends very of concern.
critically on the timing of the instant of reclosure. Similar considerations apply to the slot wedges, in
This has also been demonstrated, during transient which the loading pattern is similar to that in a short
conditions, using values of stress obtained from strain beam in bending, uniformly loaded on its underside,
gauges fixed to the shafts. Devices which calculate and with built-in ends. Aluminium alloy wedges are
shaft torques from electrical inputs have also been commonly made from extruded sections, but have
used. the outermost layer (1 mm, or so) machined away
It is difficult to relate measured or calculated torque where stresses are high, so that the properties of the
peaks accurately to damage caused, or to remaining parent metal are fully realised. It would be necessary
542
Mechanical considerations

to take the creep behaviour of aluminium into con- rotational hoop stress due to the rotation of the
sideration at temperatures in excess of 100C, but ring. At rated speed and overspeed, the stress at
it is not usual for wedge temperatures to exceed this the shrink-fits may be less than that in the centre.
value (see Fig 6.85). There is also an axial stress due to the higher thermal
Pole face wedges are much less stressed, and are expansion of the copper in the end winding relative
commonly made of steel. to that of the steel ring. As noted in Section 3.3 of
The most inboard of the field lead wedges may this chapter, direct contact of the end disc onto the
be unusually highly stressed because of the extra CF shaft is not normal, since the flexure of the shaft
loading imposed on it by the section of connector would transmit a small alternating stress onto the
leading into the winding. highly stressed ring which could promote crack pro-
The shrink-fits of the end ring onto its seatings pagation by high cycle fatigue. Again, it is important
on the rotor body and end disc reduce as speed that the stresses under all conditions are analysed in
increases, and are greatest at standstill. There are detail, and this may necessitate a three-dimensional
therefore large circumferential strains at the ends of finite element computation in order to ensure free-
the rings, and correspondingly high stresses, at stand- dom from high stress concentrations, particularly at
still. As speed increases, the centrifugal force of the the sudden changes of section involved (see Fig 6.86).
rotor end windings imposes a load and stress in the In the rotor conductor nearest the wedge, it is the
central part of the ring, which combine with the compressive stress produced by the centrifugal force

FIG. 6.85 Finite element mesh for tooth-wedge stress calculations

543
The generator Chapter 6

8.3 Alternating stresses, fretting and fatigue


A stationary rotor sags under its own weight, causing
a compressive stress in the outermost fibres at the
top and at the axial centre of about 15 MPa, with
a corresponding tensile stress at the bottom of the
same magnitude. As the rotor rotates, each fibre ex-
periences a compressive/zero/tensile/zero/compres-
sive stress cycle once per revolution. Since a rotor
operating at 3000 r/min accumulates 1.5 x 109 cycles
in a year, alternating stress due to bending has to
be considered in the design. Though its magnitude
is small, it is superimposed on the high steady stresses
in the rotor and wedges identified above, and can pro-
mote the growth of cracks by high cycle fatigue.
One source of crack initiation may be fretting. If
a once per cycle movement can occur, say at the gap
between two short slot wedges, the resultant localised
damage may be sufficient to intensify the local stress
field at a minute 'crack-tip', from which the alter-
nating bending stress can propagate. Such features are
avoided wherever possible, and particularly near the
axial centre where alternating bending stresses are
highest. The concepts of fracture mechanics are used
to study such crack tip stress intensification.

8.4 'Slip-stick' of rotor windings


One effect not mentioned in Section 3.8 of this chap-
ter is the behaviour of the rotor winding during a
loading cycle. The rotor is run up from cold, and
though the windings and rotor body are warmed by
gas friction, there is little differential in thermal effect
at this stage. At speed, the winding conductors are
locked together and to the wedge by the centrifugal
force, unless an axial force can overcome the friction
between them.
When current is applied to the rotor winding, it
reaches a higher temperature than the rotor body,
and as the coefficient of thermal expansion of copper
is nearly twice that of steel, the conductors experience
an axial force directed outwards from the axial centre.
As the differential temperature increases, the axial
forces increase, until slippage occurs at a point where
the build-up of axial force is able to overcome the
friction. Because the 'bottom' conductor experiences
the least centrifugal load, it is most easily able to
overcome friction, and a shorter length of it remains
FIG. 6.86 End ring lug area finite element mesh and frictionally-locked than those of coils further up the
stress contours slot. Slippage in most windings appears to occur in
small steps, apparently randomly, though possibly re-
peatably, so that the release of the axial forces does
not result in sudden changes in vibration of sufficent
of all the other conductors in the slot which is of magnitude to be significant. In some rotors, however,
ed
concern, particularly where the copper area is reduced due to higher frictional restraints having to be over-
by ventilation grooves and slots. Some creep of the he come, the release of much larger axial forces appears
irs
copper may be observed at such slots after many years to cause the bending moment to change significantly,
in operation. resulting in a noticeable sudden change in vibration.

544
Electrical and electromagnetic aspects

One feature of this is that the rotor must usually be second increases the required flux magnitude; both
run down in speed before the changed vibration dis- increase saturation, the effects of which are highly
appears, when the cycle can be repeated. non-linear (see Fig 6.87). One result of this is that
Once the rotor is at speed and temperature, it does overall iron losses will be higher than those calculated
not tend to suffer from high cycle effects. It is more for no-load conditions, and their distribution will dif-
vulnerable to effects promoted by relative movement, fer. Another is that the calculation of the required
such as abrasion, when running at lower speeds and MMF (rotor current) required for any load condition
while barring, when the centrifugal locking-up is cannot be accurately based on the simple phasor
absent. diagram. Since the rotor is necessarily designed with
little margin, accurate calculation of the rotor current
needed for rated conditions is essential.

8.5 Noise
The generator rotor, with its fans, generates very
high noise energy at speed. The spectrum is wide, but
contains peaks at frequencies related to the number
of fan blades and slots.
The other main source of noise is generated by
the stator core when magnetically excited. As pre-
viously noted, the magnetic forces valise' the stator
core, causing vibration and noise at 100 Hz and mul-
tiples. The main component of magnetic noise, how-
ever, arises from distortions on a much smaller scale,
that of the magnetised iron crystals, in the pheno-
menon known as magnetostriction, at 50 Hz and
multiples thereof.
The robust stator casing acts as an effective sound
attenuator, and little can be achieved to reduce the
transmitted noise further, for example, by the acoustic
treatment of the inside surfaces. In practice, the major
sources of high noise intensity tend to occur in the
driven components such as exciters, which have fans
operating in air and no heavy steel surround. Some-
times the complete line of driven units is housed under FIG. 6.87 Flux distribution on load
an acoustic cover to attenuate these sources. Access
doors and windows must be provided, and these can
reduce the effectiveness of the covers.
A sound power level of 93 dBA is specified at A method previously used took as its basis the
1 m distant from the plant. Legislation may require simple no-load unsaturated phasor diagram, and de-
this to be reduced for new plant in the future. fined an imaginary reactance, the Totier' reactance,
empirically derived, which was used to define a Totier'
voltage drop, IX p , for the given load conditions. An
internal voltage required to overcome this voltage
drop, the Totier voltage' was thus established. The
9 Electrical and electromagnetic aspects MMF difference between the airgap and open-circuit
Some electrical and magnetic aspects of generators, characteristics at the Totier voltage' was then pha-
not previously considered, are dealt with in this section. sorially added to the unsaturated MMF phasor. In this
way, the increasing and non-linear effects of sat-
uration were taken into consideration (see Fig 6.88).
Present methods use finite element calculations,
9.1 Flux distribution on load which can be reduced to two dimensions for the
When, in previous sections, magnetic flux densities central part of the machine. Even so, the detailed
have been mentioned, operation at rated voltage, geometry and non-linear magnetic characteristic make
no-load has been assumed, where the load angle is the calculation complex.
zero and the rotor operates in the 'direct axis'. In In the end regions, a three-dimensional approach
practical load situations, the load angle is 40-50 is almost essential, although various schemes have
and the effective flux level must be large enough to been devised in which simplifications can be made.
overcome the leakage reactance voltage drop. The In addition to the difficulties already noted, the thick
first effect distorts the flux pattern markedly; the conducting plates in which non-linear eddy currents
545
The generator Chapter 6

ADDITIONAL ROTOR
CURRENT REQUIRED
FOR POTIER REACTANCE DROP

ROTOR CURRENT

FIG. 6.88 Potier construction for on-load excitation current

are induced, and other conducting components, must tance. If higher values are required than the 'natural'
be included in the modelling. It has reached the design produces, the leakage reluctance can be re-
stage of refinement where detailed changes, say, in the duced by making the slots narrower, and/or sinking
thickness of magnetic screens, can be modelled in them deeper into the core. Again, this is extravagant
order to optimise the design, and to indicate where and results in a larger design.
potential hot spots may occur due to unwanted flux If lower values are required, it is not usually suf-
concentrations. ficient to manipulate the slot geometry, and a more
basic change to the design might be needed.
Using computer programs similar to those men-
tioned in the previous section, more accurate repre-
9.2 Control and calculation of reactances sentation of the reactances can be made, over the
The reactance of an inductive circuit determines its range of load conditions, than is possible by simple
voltage/current relationship. In a generator, different calculation.
reactances are identified in order to model or de-
scribe voltage (or flux)/current relationships under
different circumstances.
The synchronous reactance, X d , relates the arma- 9.3 The cause and effect of harmonics
ture reaction MMF (proportional to stator current) to As explained earlier, stator winding distribution is
the MMF needed for rated flux in the air gap. For a designed to minimise the generation of harmonic volt-
given design of machine, increasing the radial length ages and currents.
of the air gap proportionately reduces Xd and im- The stator winding is invariably star connected, so
proves steady state stability. This results in a larger that triple harmonics cannot occur in the line voltage
outside diameter, and a higher rotor current at full or current. Since one pole of the rotor is identical
load. with the other, it cannot produce second-order flux
The stator leakage reactance, X^, is not a specified harmonics, which would make the two halves of the
quantity, and its value is a matter of economic design. flux wave dissimilar. The only harmonics of signi-
The transient and sub-transient reactances, X d ' and ficant magnitude which will appear are those of order
X d ", are specified. They describe the flux/current rela- 5, 7, 11, 13, etc., with diminishing amplitudes, and
tionships during transient changes, and under these cir- those near to the rotor slot pitch, e.g., 41 and 43
cumstances, the amount of flux encircling the sta- for a 42-pitch rotor slotting. The no-load rated volt-
tor slots, rotor slots and end windings are of impor- age wave must not contain a greater total harmonic
546
Electrical and electromagnetic aspects

content than that specified in BS5000, in which cer- source impedance, and can circulate significant cur-
tain ranges of frequency are more highly weighted rent through bearings, seals, etc., causing eventual
than others because of their effect (in the transmission break-up of white-metalled surfaces.
system) on communications lines. This now rather out- Voltages of the same frequency as the shaft-driven
dated concept is still accepted as an agreed and useful excitation machines can be measured on the generator
criterion, since high harmonic levels can induce high shaft, but these are capacitively coupled, have a high
local losses in parts of the generator, e.g., the rotor source impedance and will not sustain a large current.
surface. The steam turbine rotors may develop a voltage
In practice, harmonics are generated by the con- due to the electrostatic action of steam and water
nected loads, a recent trend being the even-order droplets on the blades, and one function of the shaft
harmonic requirements of equipment using thyristors. earthing brushes is to ensure that this is discharged.
This must be supplied by the generators and must A phenomenon which has occurred (rarely) on tur-
therefore appear in the flux wave, causing rotor surface bines is that, where a rotor or rotors have a degree of
losses similar to those produced by unbalanced load permanent magnetism and there are contacts of low
conditions. resistance between shaft and earth at suitable axially-
Rotor windings occasionally develop short-circuits separated locations, the small generated voltage can
between adjacent turns in a coil, and while this is not circulate a small current through the turbine casing,
usually of great concern, the difference in flux pat- which, in certain designs, can act as a partial 'turn'
tern from the two poles is detectable, using a small of a winding encircling the shaft. This then produces
flux coil mounted in the airgap. When the signal from an MMF and therefore a higher shaft voltage, the
one pole is offset against the signal from the other, whole process building up until many thousands of
differences reveal any abnormality. Another method amperes circulate, causing damage at the contacts. It
which has been suggested uses the presence of second is therefore important to ensure that deliberate con-
harmonics in the stator current, as noted above, but tacts, such as earthing brushes, have a resistance (say,
this has to be able to reject those imposed by the load 1 ohm) deliberately included in series, and that heavily
requirements. magnetised shafts are de-magnetised (see Fig 6.24).
The residual magnetism of a generator rotor will
normally produce a voltage of several hundred volts
at speed, even without external excitation; and access
9.4 Magnetic pull to terminals, connections, etc., must not be allowed.
If the rotor is exactly centred in the bore of the sta-
tor, the magnetic pull between one pole of the rotor
and the stator will be exactly balanced by that of
the other. If not centred, there will be an unbalanced 9.6 Field suppression
pull acting as an attractive force on the pole with If an electrical fault occurs in the generator, the
the smaller air gap. However, the air gap of these connections, or on the generator transformer, the
large machines is so large (80 to 130 mm), in order protection will act to trip the main circuit-breaker.
to achieve the required synchronous reactance, that This will extinguish the stator current within one
centring the rotor to a readily achievable accuracy cycle of circuit-breaker operation but the flux cannot
does not impose a magnetic pull at all comparable be reduced so quickly. In all except brushless ma-
with the gravitational force on the rotor. chines, a field circuit-breaker is connected in circuit
Similarly, the net axial magnetic force on the rotor between the excitation source and the rotor winding.
is zero if it is axially centred in the stator, and this If this were to be opened, the instantaneous reduc-
is the condition normally achieved at rated load with tion in current would induce a large (several kV)
voltage in the rotor winding, with the risk of insulation
the rotors at their normal temperatures. With the
breakdown.
usual axial offset which occurs with the rotors cold,
Instead, a field suppression resistor is inserted in
the axial magnetic pull is only of the order of a few
series with the rotor winding, the excitation source
thousand Newtons and is not a significant additional
circuit being opened subsequently. The resistor has
load on the thrust bearing. an ohmic value of 1 to 3 times that of the winding,
and reduces the current (and flux) rapidly, without
imposing an excessive voltage. Thus the ability of the
flux to prolong the current in the fault is safely
9.5 Shaft voltage and residual magnetism minimised.
The production of a voltage (predominantly at 50 Hz) In brushless machines, direct suppression of the
from one end of the generator rotor to the other oc- rotor winding current is not possible. The exciter field
curs because of some asymmetry, either of the position current is rapidly reduced by the operation of the
of the rotor in the stator, or some difference in mag- exciter field switch (this also applies in a non-brush-
netic properties. This mechanism has a low effective less machine), or by inversion of the thyristors, but
547
The generator Chapter 6

the rotor current has an effectively zero resistance ing, a large fault current would flow, with danger to
path through the rotating diodes, and decays with the maintenance operator. It is considered prefer-
the natural time constant of the winding (see Fig 6.89). able not to apply an earth, but to ensure that the
operator is properly clothed and is using special in-
sulated equipment.

9.7 Voltage in the rotor winding


At rated load, the voltage required to circulate rated
rotor current is of the order of 500 V. During field 9.8 Stator winding insulation
forcing, this may rise to almost twice this value for In normal operation, the highest voltage to earth
a few seconds. The rapid decay of current during field occurs in the winding bar (and connection) at the high
suppression may possibly induce 1500 V briefly in voltage ('line') end of each phase. This amounts to
the winding. During transient fault conditions, the 23.5/3 = 13.5 kV (RMS) for the 660 MW units.
requirement of maintaining the previous flux level may Voltage to earth on the other conductor bars is re-
cause large currents to be induced into the winding, duced through the winding to effectively zero at the
with correspondingly high voltages (1500 V or so). neutral end. The electrical stress in the insulation is
The highest voltages are likely to be applied during not high even on the line-end bars; all the bars are
asynchronous operation, during which the induced similarly insulated.
alternating rotor current (at slip frequency) seeks to The system of insulation has to undergo searching
reverse. This possibility is blocked by the excitation type tests before it is approved for general use, and
diodes and high voltage peaks occur (>2000 V) at even then, quality control tests on production bars
the sudden changes in current. include the destructive cutting up of two sacrificial
The winding insulation of a new rotor is finally bars per machine to ensure freedom from cavities in
tested at 3500 V, having withstood higher test voltages the insulation, among other quality checks.
during manufacture. However, the arduous operating In operation, electromagnetic forces cause the bars
conditions may cause insulation to become physically to vibrate at 100 Hz in the slots and end windings,
damaged, displaced, or just oily or dirty from con- to an extent limited by their restraining devices. If
tamination, and such high voltages are less easily bars become loose in their slots due to relaxation
withstood in an older rotor. of ripple springs or wedges, the layers of insulation
When brushes are being changed with the generator tape may become locally de-laminated, in spite of
on-load, it is common practice to ensure that the the bonding resin. Electrical discharges can occur at
excitation control is on 'manual', so that the rotor such sites which might eventually lead to electrical
cannot be subjected to field forcing voltages, and to breakdown of the bar to earth. Fortunately, in a hy-
disconnect the earth fault indication biasing voltage. drogen atmosphere, carbonisation of the surfaces does
It may be thought to be advantageous to earth the not occur as readily as it would in air, and break-
slipring being worked on deliberately, but if this were downs from this cause are uncommon. Discharge on
done and an earth fault developed in the rotor wind- the bar surface, either in the slot, or across the end

SLIPRINGS
AND BRUSHGEAR MAIN FIELD
I SUPPRESSION
SWITCH

<Lp

ft
FIELD
SUPPRESSION
SWITCH

GENERATOR MAIN FIELD FROM


'SUPPRESSION BRIDGE
ROTOR AVR
RESISTOR RECTIFIER
WINDING

I
FIG. 6.89 Field suppression circuits

548
Operational measurement, control, monitoring and protection

winding surfaces, may occur, particularly where the 10 Operational measurement, control,
semi-conducting surface treatment layers become bro- monitoring and protection
ken or damaged, but again this does not normally Many of these subjects have been mentioned in pass-
lead to breakdown. Much more likely is mechanical ing. In this section, each group is considered as a
damage to the insulation by pieces of core punching co-ordinated whole.
which become detached, magnetic debris (which can
cut 'wormholes' into the end winding insulation un-
der electromagnetic forces), and abrasion of packing
blocks into insulation. For these reasons, insulation 10.1 Routine instrumentation
thicknesses have not been reduced to take advantage Provisions vary between manufacturers and have chang-
of the superior electrical properties available with ed over the years, but the following is representative.
modern insulation systems.
Considerable effort has been devoted to devising
means of detecting signs of insulation deterioration, 10.1.1 Temperature
for instance, by observing discharge activity in a Thermocouples are used to detect the temperature
permanently installed, capacitively coupled device, or in:
by radio frequency aerials inside the casing; both
methods are still being developed. Discharge energy is Stator core in teeth, back of teeth, core ends
predominantly in the 1 MHz range, whereas corona and axial centre.
discharge, which also occurs, is predominantly at a
higher frequency. Occasional 'fingerprint' measure- Core end plates and end plate screen these are
ments can show whether either activity is increasing permitted to attain higher temperatures than the
with time. core if not in contact with insulation.
Similarly, an overall measure of the insulation Hydrogen inlet to and outlet from coolers
integrity of a whole phase can be gained by mo- several, to allow averaging.
nitoring the capacitative component of current at
various voltage levels, usually expressed as 'tan delta' Stator winding, either one per slot or in water outlet
values, i.e., a measure of (very low) power factor. hose basically to monitor water flow in in-
Breakdown, however, is most likely to occur from dividual bars.
one local area of damage, as already noted, and the
poor results from this local area are swamped by the Hydrogen seal faces to detect rubbing, or oil
better measurements of the rest, so that such methods starvation.
are relatively insensitive. Stator frame, at C0 2 inlet to detect freezing.
Stator insulation withstands more than twice its
rated line voltage, i.e., >2[V3 x maximum (phase)
operating voltage], and an insulation sample will with- Resistance elements or other thermometers are used
stand at least twice this again, so there is a huge for:
safety margin on intact insulation. Even so, testing
at high voltage is destructive, and repeat testing in Water inlet and outlet temperatures in all water
service is deprecated. cooling systems.
If an earth fault occurred at one of the phase Oil outlets from bearings and seals.
ends, the voltage at the neutral would be elevated,
and that at the other phase ends could rise to V3 x Seal oil at outlet from cooler.
normal. This condition would persist for only a few
seconds, at most, before the protection acted to trip Hydrogen to and from cooler, as back-up to ther-
the unit and suppress the flux. In normal operation, mocouples.
the maximum voltage a winding can attain is limited
An ohmmeter is used to display rotor winding
to about 35% above rated, for example, if rated
temperature.
load were tripped, but again this would quickly be
suppressed. Temperatures are monitored during works tests
Surges arising from switching or other operations and during on-load commissioning, to ensure that
on the system are greatly attenuated in the generator the specified limits have not been exceeded. The
transformer, and do not pose a significant hazard to alarm level would normally be set above the high-
the generator winding. These large machines do not est temperature attained at rated load with the
have multi-turn coils, which are more at risk from warmest ambient conditions, but recent thoughts
surges. The surge withstand voltage is quoted at about are that this practice may miss early warnings of
85-90 kV, but surge withstand tests are never carried developing abnormalities. If a measured tempera-
out. ture is related to other parameters, such as current
549
The generator Chapter 6

and cooling water temperature, or even compared Vectormeter (on control desk).
to other similar signals to see that its magnitude
in the established scatter pattern is correct, by using Excitation voltage, current.
a dedicated microprocessor, a more informative AVR indications (locally, on AVR panel).
indication can be provided to the operator.
Diode failure.

10.1.2 Pressure Shaft voltage.

Pressures are monitored as follows:


10.1.6 Vibration
Hydrogen in supply bus.
Bearing and shaft movement.
Hydrogen in casing.
End winding vibration, using accelerometers on sup-
Carbon dioxide in supply line. port beams.
Stator winding water.
Seal oil (and thrust oil, if separate). 10.2 Logging and display
Transducer outputs are received as inputs to the com-
Vacuum in seal oil treatment plant (if used).
puter at intervals determined by consideration of what
event could have caused a signal different from nor-
Differential pressures are monitored between: mal, and in what time scale this could cause damage.
Hydrogen and stator winding water. Readings may be logged only when outside the normal
range or, alternatively, readings within the range may
Hydrogen and seal oil. be logged at intervals.
The most modern stations display only the essen-
Fan inlet and outlet. tial information continuously to the control room
operator. Some systems display 'by exception', i.e.,
when a parameter falls outside its expected range.
10.1.3 Flow All information is available on demand, on VDU
Flow rates of the following are measured: screens or printers.

Stator winding water, by flowmeter or by differen-


tial pressure across either an orifice or the winding.
10.3 Control
Make-up hydrogen (in some machines). The load and excitation control systems have already
Hydrogen through katharometer. been described. The following quantities are common-
ly controlled automatically:
Hydrogen pressure, by spring-loaded valve, backed
10.1.4 Condition monitoring
up by spring-loaded overpressure valve.
Purity of hydrogen (katharometer). Seal oil pressure, by pump pressure control and
Humidity of hydrogen (hygrometer). differential control valve.

Humidity of exciter air (hygrometer). Stator winding water pressure, by spring-loaded


bypass valve.
Conductivity of stator winding water.
Cooling water temperature, by heaters and bypass
Composition of scavenging gases (katharometer). valve.
Quantity of particulate matter in hydrogen (condi- Gas-in-water detection, by timed operation of
tion monitor). solenoid valve.
Regeneration of dryer, by timer and automatic
Fig 6.90 shows a typical condition monitor console. valves.

10.1.5 Electrical Other parameters, such as water temperature, are


commonly controlled manually, adjustments to valves
MW, MVAr, voltage, current, power factor (in being made as necessary when indicated values exceed
control room). given limits.
550
Operational measurement, control, monitoring and protection

FIG. 6.90 Condition monitor (NEI Parsons Ltd)


(see also colour photograh between pp 482 and 483)

551
The generator Chapter 6

10.4 On-load monitoring, detection and of one or more turns in a coil becoming short-
diagnosis circuited. (In some machines, this condition may be
Detection of abnormal conditions is divided between continuously monitored.) The condition normally re-
two sections: on-load detection techniques, described quires remedial action but it is prudent to check that
here, and techniques which are applied off-load, at the situation is stable.
standstill, or during maintenance, which are grouped
with Tests under Section 11 of this chapter.
Some equipment is provided so that on-load checks 10.4.2 Core or condition monitor
can be carried out periodically on a routine basis in In this device (Fig 6.90), hydrogen is drawn from
order to ensure that previously established conditions the casing through a chamber in which a radioactive
have not changed. source emits a normally constant rate of electrons.
Ionised particles in the hydrogen stream, due to dust
or liquid aerosol droplets, cause the collected current
10.4.1 Air gap flux coil to fall, and initiates an alarm at a given level. It is, in
A search coil monitors the rate of change of leakage effect, a sophisticated smoke detector. The particles
flux in the air gap as the rotor rotates (Fig 6.91). may be from areas of overheating stator core (hence
The signal from one pole is subtracted from the signal the name) or from insulation; they can be trapped in
from the other; significant differences are indicative a filter and analysed.

FIG. 6.91 Airgap search coil and waveforms

552
Operational measurement, control, monitoring and protection

SEARCH COIL WAVEFORM

VOLTAGE (V) 0

I
b
3.0-
\
2.5-
I
VOLTAGE (V) 2.0- DIFFERENCE
WAVEFORM

1.5-

1.0-
b b
0.5-

w\r\j HP^vWlrvJ ri
2C

r\ A / / /\ / / fti\

-0.5-
v\l
a and b are the two sides of the faulted coil

FIG. 6.91 (contd.) Airgap search coil and waveforms

10.4.3 Insulation discharge and the condition investigated. If it is decided that


These techniques were discussed in Section 9 of this a calculated risk can be taken to enable generation
chapter. to be continued, a protection device developed in
1987 can be installed. This will initiate a Class 1 trip
on the occurrence of a second rotor earth fault, and
10.4.4 Rotor winding earth fault indication minimise the damage from the high circulating current
The rotor winding and its connected excitation circuits that this would otherwise cause (see Fig 6.93).
are not earthed. In order to detect a low value of
insulation resistance while on-load, a biasing voltage
of about 30 V DC is applied to the 'positive' end 10.4.5 Shaft current insulation integrity
of the winding through a current relay, causing the In a machine with 'islanded' insulation (see Section 3
entire circuit to have a negative voltage to earth (Fig of this chapter), the integrity of its insulation can be
6.92). If the overall insulation resistance to earth falls checked with a megger.
below 100 000 ohm (the actual value depends on
the position of the 'fault' in the circuit), the relay
operates to initiate an alarm. Operation of the rotor 10.4.6 Stator winding water analysis
may be continued but it is recommended that the This water must be checked for oxygen and copper con-
unit should be taken off-load as soon as convenient tent at recommended intervals.

553
The generator Chapter 6

of its trip initiation:


Class 1 protection initiates a main circuit-breaker
trip as fast as can be arranged. Taking the trip
relay and circuit-breaker operating times into ac-
-530V
count, this means about 120 ms (6 cycles) after
initiation. With the most modern circuit-breakers,
this time may be reduced to about 80 ms.
Class 2 protection initiates the closing of the tur-
bine stop and interceptor valves. The load reduces
to 1% or less within a few seconds; this situation
is detected by a low forward power' relay which,
after a short delay, initiates a main circuit-breaker
EXCITATION SUPPLY
5 0 0V 4 0 0 0 A DC lf TYPICALLY <0.75mA
trip. The process takes 4-5 s from the original
EARTH
LEAKAGE initiation and is intended to prevent a possible speed
CURRENT
DETECTION runaway if the overspeed governor does not func-
RELAY
tion correctly on load rejection. Consequently, those
-30V BIASSING VOLTAGE conditions in which a 5 s delay can be tolerated
before tripping are arranged to be protected by a
STATION Class 2 trip.
EARTH

FIG. 6.92 Rotor winding earth fault detection 10.5.1 Class 1 trips
Electrical failure damage propagates so quickly that
Class 1 tripping is essential. The following situations
are commonly protected by Class 1 trips:
Generator transformer winding fault This causes
imbalance between currents in the HV side of the
transformer and the generator neutrals. (Note that,
for faults beyond the transformer, no damage in-
K IS ACTUAL
FAULT POSITION ternal to the generator and transformer is expected,
K1 IS APPARENT
FAULT POSITION and tripping is not initiated.)
Unbalanced load (negative sequence) faults These
are described in Section 7.9 of this chapter.
Stator winding earth fault With high impedance
neutral earthing fault current could be tolerated for
the 5 s of a Class 2 trip, but this condition has
been found to be the forerunner of a more serious
SWITCH CLOSED:
Vi ' + V

\ APPARENT CHANGE K = K1 - K
2'
fault in the windings and Class 1 tripping is now
recommended.
VOLTAGE V1 ACROSS FAULT RESISTANCE Rf
= . ve = AK (V^ + Vg1)
CURRENT If IN FAULT RESISTANCE = V2' High hydrogen temperature The most positive
Rm method of protection against a complete loss of
FAULT RESISTANCE R, : raw cooling water to the generator cooling circuits
is to trip on high hydrogen temperature. Gas tem-
HENCE BOTH FAULT POSITION AND FAULT RESISTANCE CAN BE peratures and stator winding water temperatures
COMPUTED AND COMPARED WITH PREVIOUS VALUES
rise to a dangerous level so quickly that activating
an alarm to advise an operator to take action is
unlikely to result in action which is fast enough
to be effective.
FIG. 6.93 Second rotor earth fault protection
Split phase protection This is not yet fitted except
experimentally. It is intended to detect a difference
in the currents in the two parallel paths of a stator
10.5 Protection phase winding, which are normally equal. A bar-
Protection, here defined as equipment designed to to-bar fault in one path would result in a detect-
trip the unit when necessary, is classified by the speed able imbalance, which could trip the unit before
554
Maintenance, testing and diagnosis

the fault had time to develop into a more damag- stator water.
ing fault between phases. Any sudden departure from normal conditions
should be investigated. Changes in shaft or stator
Second rotor earth fault winding overhang vibration should be correlated with
load and temperature, and changes in stator core or
casing vibration with voltage and temperature. Con-
10.5.2 Class 2 trips dition monitor excursions should require samples to
be analysed. Such information may be invaluable
Loss of stator winding water flow This is time when assessing the condition of the machine at the
delayed to allow the standby pump to start. next major outage, or when planning remedial work.
Exciter rectifier bridge-arm failure This protects
against the loss of all the diodes in one arm of the
excitation rectifier. 11.2 Maintenance and tests when shut
Loss of excitation Detected by a mho relay after down for a short outage
the rotor has moved into a pole slipping mode. During outages as short as 2 - 5 days, the casing would
not normally be scavenged, and the shaft would be
High vibration This is described in Chapter 2. barred for much of the time. Therefore the generator
and its systems are not much more accessible than
Emergency pushbutton This is described in Chap- when in operation.
ter 2.
Cleaning of brushgear and the slipring area can be
carried out to remove built-up deposits of carbon,
possibly soaked with oil, which can form electrical
11 Maintenance, testing and diagnosis tracking paths. It may be possible to grind the slip-
rings.
If the brushes are lifted clear of the sliprings and
a pair of insulated brushes fitted, a test on the rotor
11.1 Maintenance and tests during operation windings can be made with a recurrent surge oscillo-
Sliprings and brushgear require regular maintenance scope (RSO). In this test, a steep-fronted pulse is
to ensure trouble-free operation. The selective pass- applied to one end of the winding. Any abnormality
age of more current through one particular brush in the winding, such as a short-circuit between turns,
can lead to excessive wear on that brush, so that will cause a smaller surge to be reflected back to the
even though an average brush life is 6 months, one source, just as if the winding were a transmission
brush may wear to the point where spring pressure line. Figure 6.94 shows typical waveforms of signals
is lost within 2 weeks. Facilities for on-load brush reflected from each end. By subtracting the signals,
changing are provided, and are necessary for base an abnormality may be detected. Such tests can be
load units. Occasionally, sliprings may require re- very sensitive, and must be interpreted with care.
surfacing by grinding, but this cannot be done on-
load and must await a shutdown. Shaft riding earthing
brushes, and the instrumentation brushes provided
on some 'brushless' units, also need regular attention. 11.3 Maintenance during a longer outage
There is little other maintenance work which can If the outage is known to be longer than a week or
be carried out with the machine on-load, apart from so, the casing can conveniently be scavenged. When this
keeping clean components such as pedestal and exciter has been properly carried out, access to the inside of
insulation shims, emptying drains when necessary, and the casing can be gained by withdrawing a cooler,
noting what they contain, cleaning or replacing filter or to the end winding area by taking off a cover
elements where possible, and ensuring that pumps, in the endshields.
control valves, etc., are functioning correctly. Visual examination of the interior may reveal ex-
Apart from monitoring both the regular and more cessive amounts of oil, indicative of a malfunctioning
specialised instrumentation, as described earlier, there shaft seal, or of water, indicating a cooler or cooling
are few tests which can usefully be carried out. Cal- circuit leak. Signs of overheated insulation may be
ibrating checks can be made on the purity meter evident, or of powdered glass or mica, indicative
by diverting pure hydrogen through it, and manual of abrasion of insulation. Excessive burning or welding
sampling can provide samples of casing hydrogen for between core bars and the core back may indicate
back-up monitoring of impurities and moisture con- an embedded core fault. Loose packers, bolts or
tent, and of stator winding water for pH value, oxy- hoses in the end winding may be apparent, and loose
gen and copper content, and conductivity. In some debris may be visible. The effort involved in such
stations, means are provided for the on-load testing an inspection is worthwhile to preserve confidence
of certain protection devices, for example, flow of in the continuing good performance.

555
The generator Chapter 6

" ^^

6- ^
J -'*
.i

3*~
VOLTS 4H
1 '
/ 1

* - ^ ' 1
1

DEVIATION

-2-J
50 60

TIME

FIG. 6.94 Recurrent surge test

All such examinations of the interior must be sub- stator is possible. Inspection of the rotor surface,
ject to the rigorous enforcement of rules concerning particularly where crack initiation sites are suspected,
tools, the wearing of overshoes, etc., to ensure that such as the gaps between short wedges, should be
foreign materials are not left inside. The stator casing carried out. Inspection down the radial ventilation
heaters should be kept on once degassing has been holes to check that insulation packing has not moved
completed. to block the gas cooling passages, is recommended,
At these outages, seals and bearings may be dis- following which the holes should be sealed with a
mantled for inspection, both for signs of wear and continuous strip of adhesive tape, to prevent the
damage, and of electrical discharges due to the pass- ingress of debris.
age of shaft current. The inside of exciters can also Limited inspection of the end winding is also pos-
be inspected, as can components in the various aux- sible, and signs of fretting, looseness, distortion of
iliary systems. coils, or movement of insulation, blades or coils
A limited amount of testing can be carried out, e.g., should be looked for. If the pole-to-pole crossover
the insulation resistance of the rotor winding, using a is visible, it is advisable to examine it for signs of
500 or 1000 V megger, and the IR of the shaft current fatigue cracking.
insulation if islanded. End rings should be examined for surface cracking
and, by using ultrasonic techniques, for embedded
defects. The CEGB guidelines recommend that those
end rings which are not of 18/18 material should be
11.4 Maintenance and tests with the removed after about 80-90 000 h in operation, and
machine dismantled skimmed to a depth of about 0.25 mm over the cyl-
If the outage is to be long enough for the rotor to indrical surfaces (but not the shrink face), following
be withdrawn, much better access to both rotor and which a fluorescent dye ('Zyglo' or equivalent) ex-
556
Maintenance, testing and diagnosis

amination is made. Defects greater than 2 mm should be performed on the rotor winding, with slipring
be ground out, blending in the ground area so that brushes lifted.
there are no discontinuities. Finally, the ring must If any hot spots in the stator core are suspected,
be re-treated with its protective finish before being or as a reassurance exercise, a core flux test can be
refitted. The whole operation requires great skill and carried out. This may take the form of an hour long
experience, and though it can be carried out at site, test with about rated flux in the core, using about
it is better done at the manufacturer's works, fol- 10 turns of 11 kV cable wrapped around the core
lowing which the rotor can be subjected to over speed and fed from a suitable 11 kV source, and using
and balancing runs. These comments also apply to an infra-red camera to scan the bore to monitor its
exciter end rings. temperature. Easier, but less positive, is a low flux test
Examination of the stator core can be carried out using one turn of light current cable and a magnetic
by inspecting the bore for loose areas, which can imperfection detector.
be tightened by insertions of hard insulation, or by It is not easy to ensure that the stator winding
treating with an epoxy-based liquid having low sur- is dry enough to make an insulation resistance test
face tension which will penetrate between the la- meaningful, though a technique of applying a vacuum
minations. Ventilation ducts should be inspected for to the winding has been used. A 2 or 2.5 kV motor-
debris, blockages and broken spacer bars. The back ised megger should be used, monitoring one phase at
of the core will reveal excessive welding of core to a time, and maintaining the test for 10 minutes so
core bars, or damaged core bar insulation, where that the polarisation index can be obtained. It is
this is fitted. Some core back burning, and some not normal to apply a high voltage test, the only ex-
fretting products (e.g., 'cocoa dust') seems to be ception being after some damage has occurred, possi-
innocuous. The core frame can be inspected for ob- bly with partial replacement of the winding, when an
vious signs of damage, and patches of overheated agreed HV test on the remaining bars gives some
paint or metal should be investigated. reassurance.
Every stator slot wedge should be checked for tight-
ness along its whole length, using a tightness tester
developed in 1985, or by tapping with a coin or simi-
lar object to observe the expected 'ringing', indicative 11.5 Reassembly
of a tight slot. Airgap flux coils can be fitted or With the rotor reassembled, mechanical checks such
renewed at this stage. as alignment, axial clearances and concentricity of cou-
Stator end windings can be more thoroughly checked plings, and of the rotor in the stator, are carried out,
than as described in the previous section. Signs of and that all locking plates and other devices are pro-
looseness of packings, fretting, slack fastenings, etc., perly assembled. All jointing materials, such as gaskets,
are all indicative of movement. If there are unfilled O-rings, jointing compound, etc., should be renewed,
bags between coils, these can be filled with epoxy and the appropriate leakage tests carried out.
resin at this stage. The surfaces should be cleaned using It is so important that small metallic items do not
a proprietary cleaner suitable for electrical windings, fall into, or get left inside, the generator, where they
but it is not recommended that repainting is under- could be drawn into the windings, that a strict ac-
taken without the manufacturer's advice. If a 'worm- counting system for such items is recommended.
hole' (made by small conducting particles) is found, Several expensive failures have occurred a short time
the particle should be removed and the insulation after a major maintenance outage, due to this cause.
patched rather than left in, possibly to break through
into the copper.
The state of the hoses and their connecting joints
should be checked. A leakage test on the stator wind- 11.6 Diagnosis
ing, using vacuum or pressurised air with a tracer If the reading of any instrument has been outside its
gas, will reveal any significant leaks. It may be expected limit, or caused concern in other ways, it is
considered prudent to renew all the rubber O-rings, sensible to investigate its possible causes during an
both in these locations and elsewhere, if they have outage. It may be tempting to extend the operating
been in service for several years. Care must be taken regime beyond its normal level, before such an out-
to follow the assembly instructions meticulously, as age, in order to observe the effects, but this is not
overtightening may damage the joints. recommended, since a 'stable' fault has been known
The opportunity should be taken to clean the sta- to become 'unstable' during such operation, causing
tor casing, particularly at the bottom, noting if water problems when the unit is recommissioned.
has collected, and checking that the flow to the leak- Specialised techniques, some in their development
age detector is unobstructed. phase, may be available to assist in suspected fault
Insulation resistance tests should be carried out location, and up to date advice should be sought.
on the rotor winding, using a 500 or 1000 V megger, Sometimes readings of more than one type may
and on excitation windings. An RSO test could also be high, though not so high as to be alarming in
557
The generator Chapter 6

themselves. When judged jointly, clues may be ob- which the plumbing and insulated connections have
tained which individual readings might not have re- to withstand with no detectable leakage. Stainless
vealed. steel pipes, with some welds having to be made in
situ, were found to be necessary in the UK experience.
Nevertheless, water cooling the rotor winding and
other parts, for example, the stator core, may be an
12 Future developments answer if unit ratings much above 1300 MW are en-
visaged. One difficulty, that of aqueous stress cor-
rosion of rotor end rings, has been removed with
the advent of 18/18 rings. A major advantage is
12.1 Extension of present designs that in an all-water-cooled generator, hydrogen is
The choice of 3000 or 1500 r/min for future turbine- no longer necessary, and the casing can be of much
generators is made almost entirely from considerations lighter construction. The rotor can operate in a partial
of the steam turbine and its steam cycle. In general, vacuum to reduce windage losses.
if a two-pole generator can be designed and manu-
factured at a particular rating, then so can a four-
pole generator, its overall dimensions will be a little
larger. 12.3 Slotless generators
The present UK designs with water cooled stator The very large radial dimension of the air gap in the
windings and hydrogen cooled stator core and rotor 660 MW design appears to be a waste of space, and
can be extended to at least 1300 MW by extrapola- prompted much activity in the 1970s into the design
tion. Increases of the order of 10% to the rotor and of generators with slotless stators and even slotless
casing diameters, electrical loading (ampere conductors rotors. In a slotless stator, winding conductors oc-
per metre of circumference), magnetic densities and cupied a radial dimension of about half the stator slot
voltage, and perhaps 25% on length over the pre- depth, and since there were no teeth, could occupy
sent designs, would be envisaged (see Fig 6.3). The twice the circumferential distance. This is economical
increased diameter and length of the rotor result in on outer core diameter, and because the conductor
the critical speeds and alternating bending stesses bars are not embedded in iron slots, a more eco-
being similar to those of the present machines. A nomical design of insulation should be possible.
judgement would have to be made about the number The idea has not been pursued, largely because
of parallel paths in the stator winding of a two-pole it was overtaken by the superconducting generator
machine. If only two paths are used, the number concept, which promised greater economies of size,
of slots and bars is low, but the bar forces become better efficiency and the prospect of much larger unit
very large; if four are used the circuits cannot be ratings than any other design.
exactly balanced, and circulating currents and losses
are generated. Parameters, such as reactances and effi-
ciencies, would not be very different from those of
the present machines. 12.4 Superconducting generators
The phenomenon of superconductivity can be applied
to DC circuits, but cannot sensibly be used with the
rapidly changing fluxes and currents involved with
12.2 Extension of water cooling 50 Hz (see Fig 6.95). It is therefore used only in the
Since water cooling has been used so effectively for
rotor windings, where it has two advantages:
the stator winding, it may be wondered why it is not
used in the rotor winding where space is at such
The rotor I2R loss is reduced to zero.
a premium. Water cooled rotor windings have been
successfully operated; in the UK in a 500 MW unit The rotor current and MMF can be very large, so
with an experimental rotor for a few months, and that higher levels of flux density can be used than
internationally in a few units commercially. are permitted by iron saturation.
The more intensive cooling provided by water means
that smaller winding copper sections can be used, but
this increases the resistance and therefore the I2R The need to maintain the rotor winding at a tem-
loss. In a hydrogen cooled 660 MW rotor, this loss perature of 10 K means that only that amount of
is about 2.5 MW at rated load, so a worthwhile heat which can be removed by the refrigerant can
reduction in section brings an expensive loss penalty. be allowed to pass into the rotor, so that elaborate
There are difficult problems to be solved in feeding heat shields are necessary. Liquid helium is used as
the water into and out of the rotating rotor, but the the refrigerant, the windings being made of a ni-
major concern is that the centrifugal force imposes obium-tin alloy embedded in a copper matrix. The
very high pressures (20 MPa) in the water circuit, rotor body is made from a stainless steel forging.
558
Other types of generator

LAMINATED IRON CORE

CONCRETE STATOR

STATOR WINDING
DRIVE END NON-DRIVE END
OUTER ROTOR

INNER ROTOR WITH


SUPERCONDUCTING WINDING
VACUUM
SEAL HELIUM
TRANSFER

TURBINE 7#sy//y//^^^
MAIN BEARING MAIN BEARING TAIL BEARING
^0- :i'X$tf;'!

FIG. 6.95 Prototype superconducting 500 MW generator

At the higher flux densities envisaged, an iron core chines from an established design achieve a settled
offers no advantages and the disadvantage of the reliability of better than 99%, and operate at an
magnetic core loss, so a cast 'concrete' core is en- efficiency of better than 98.5%. Those breakdowns
visaged. Some form of outer environmental screen which do occur are generally due to lapses in quality
around the core is necessary to prevent leakage flux control, or if in old machines, to practices long since
from inducing currents in support steelwork, etc., overtaken. Thus the impetus for embracing new ma-
this can take the form of an annular magnetic or terials and technologies is not great.
conducting copper screen.
Many problems remain to be solved, and develop-
ment is ongoing in several countries. If the technique
reaches the stage where reliability is as good as for 13 Other types of generator
conventional machines, it offers the possibility of up Generators, other than the 500 and 660 MW turbine-
to 5000 MW in one generating unit, a prospect not generators and direct coupled AC exciters for tur-
available through any other known technology. bine-generators, described in the previous sections, in
operation by the CEGB include:

Turbine-generators of lower rating.


12.5 Auxiliary systems
The most likely other areas for new developments Water turbine driven salient-pole synchronous
are those of instrumentation, control and diagnosis. generators.
New techniques are continually being investigated
Diesel engine driven salient-pole generators.
for instrumentation, and in the environment of a gen-
erator, the means of communicating the signal non- Induction generators.
electrically in order to avoid the pick-up of spurious
electromagnetic signals and noise are very well worth
pursuing. Here, fibre optics are expected to be pro- A very brief survey of these groups follows.
minent. Also, the use of microprocessors to relate one
parameter to others, as previously noted, will become
more common. Perhaps automatic diagnostic tech- 13.1 Turbine-type generators of lower rating
niques will reach a stage where they can be used with Virtually all the steam turbine driven turbine-generators
confidence, and selective recording of non-standard now in operation are hydrogen cooled. At the lower
signals will be introduced more widely. end of the range, machines of 60 MW have a rated
It should be recognised that generator design and pressure of 0.1 bar, i.e., just above atmospheric.
manufacturing techniques are old-established. Ma- Above 200 MW, water cooled stator windings are used,

559
The generator Chapter 6

though there are some units in which higher pressure The comparatively low speed meant large diameters,
hydrogen is blown through the hollow conductors of and on-site assembly of the stators was essential (see
the stator winding. Fig 6.97). Air cooling was adopted, mainly for rea-
In other respects, the generators are very similar sons of reliability. Partly on account of this, the
to the larger, more modern units, except that they are stator winding bars were unusually deep, with a large
less intensively rated. In some cases, a degree of number of subconductors, necessitating a 540 Roebel
refurbishment has been carried out to extend their transposition. The core was stacked in situ, being com-
operating lives beyond the 25 years or so already pressed with hydraulic jacks at intervals, and bonded
achieved. together for mechanical stability.
There are also a number of gas turbine driven A fabricated steel spider surrounds the forged steel
generators intended for peak load and synchronous shaft and carries the keyed-on laminated rim and poles.
compensation duty. These have ratings up to 70 MW, Great care was taken to ensure the integrity of the
and are usually air cooled. The single-piece stators are welds, which are subject to an unusual amount of
of lighter construction than is necessary in hydrogen cyclic stressing.
cooled units, and the auxiliary systems are minimal. Ventilation is provided by motor-driven fans blow-
In some cases they were designed for unmanned sta- ing cooled air onto the stator end windings top and
tions, so manual monitoring equipment and sophis- bottom, with some booster fans for the centre of the
ticated logging is minimal. Brushless excitation is core. Water cooled heat exchangers are mounted at
universal, for reasons of minimum maintenance, and the outside diameter of the core.
even the fuses protecting the excitation diodes have The thrust bearing has an arduous duty, having
been omitted. a load of 510 tonnes and requiring larger thrust
A noteworthy feature of the most recent of these pads, at the specific loading, than had previously
units is the facility to disengage the prime mover, been used at the specific loading and speed. Each
or, in the case of the Quad-Olympus units (Fig 6.96) pad rests on a 'mattress' of coiled springs, and is
in which the generator is driven at both ends, both arranged to pivot centrally to allow for rotation in
prime movers. Then, after a period of peak load gen- both directions. Lubrication is by oil bath and natu-
eration, the synchronous clutches are disengaged, leav- ral oil circulation, with an immersed water cooled
ing the generators operating as synchronous compen- heat exchanger.
sators, with excitation controlled to suit the require-
ments of the system. When peak load or emergency
generation is next required, the gas turbines are run- 13.2.1 Excitation and control
up to speed and the clutches moved into engagement. Two variable-frequency starting equipments are pro-
vided for the station, each rated at 14.8 MVA, consist-
ing of air cooled thyristor rectifier/AC connector/
inverter banks.
13.2 Water turbine driven salient-pole syn- On starting as a pump, the stator winding is fed
chronous generators with low frequency AC from the starter, using forced
There are only a few of these on the CEGB system, commutation at speeds below 10% and natural com-
but the most recent, the pumped-storage units at mutation thereafter. It is run to just above 500 r/min
Dinorwig, rate a brief description to complement the and is synchronised as it runs down through syn-
water turbine section in Chapter 5. chronous speed. There are also arrangements for start-
The six generators are each rated at 330 MW, 0.95 ing one unit as a pump from another, being driven
power factor, 18 kV, 500 r/min, and have a motor up to speed by its turbine.
rating slightly lower when operating in the reverse Excitation power is taken from the generator ter-
direction. minals, through a transformer to a thyristor bridge,
The very onerous requirements included: whose output is controlled by the AVR, and then to
the sliprings which are located at the top end of the
Full speed, no-load to full-load, in 10 s. rotor shaft.
The synchronous operation of such machines fol-
From rest to full-load in 100 s.
lows very closely that of steam-driven turbine-gen-
From full-load pumping to full-load generating in erators. The electromagnetic loading is considerably
90 s. less, leading to a smaller radial air gap. The very
different magnetic path presented by a pole centre
5000 stop/start cycles per year. line and an inter-pole gap results in marked differ-
Multiple load cycling from 50% to 100% for system ences in direct axis and quadrature axis synchronous
frequency regulation. reactances, compared to a turbine-generator in which
they are almost identical; this is the 'saliency' effect.
Availability of 98% and mode change reliability of By applying excitation in the reverse direction to
99%. normal, an increase in the steady state stability can
560
AUTOMATIC DRY ROLL TYPE GAS GENERATOR AIR
AIR INTAKE FILTERS INTAKE FILTER HOUSE
BYPASS DOORS

A C GENERATOR AIR
INTAKE FILTER HOUSE

GAS GENERATOR
ACOUSTIC CELL
POWER TURBINE AND GENERATOR
LUB. OIL PACKAGE
POWER TURBINE ACOUSTIC SCREEN
EXHAUST SILENCING
A C GENERATOR

POWER TURBINE EXHAUST DUCTING MAIN GENERATOR CONNECTIONS

BRUSHLESS EXCITER
OLYMPUS GAS GENERATOR
GAS GENERATOR INSTRUMENTATION CLUTCH AND BEARING ASSEMBLY
PANEL POWER TURBINE ASSEMBLY
GAS GENERATOR LUB. OIL SYSTEM

FUEL VALVE CABINET CORNER BEND

561
FIG. 6.96 Quad-Olympus generator
Other types of generator
The generator Chapter 6

FlG. 6.97 Dinorwig motor-generator during site winding


(see also colour photograph between pp 482 and 483)

be gained, i.e., operation further into the leading stalled in a few stations for emergency duty. The
reactive regime becomes possible. generators are standard industrial units with proven
high reliability. The need for sudden run-up after long
periods at standstill means that brushless excitation
13.2.2 Other features and casing heaters are essential.
Other features peculiar to these machines include the
continuing integrity of stator bar insulation in an air
environment, the continuing stability of the bonded
stator core and the built-up rotors, the vacuum ex- 13.4 Induction generators
traction of dust from the shaft brakes, and the very These machines, rated usually at less than 1 MW,
high overspeeds possible; e.g., a transient value of 1.5 are used in remotely controlled run-of-the-river hydro
for Dinorwig. plants, and in wind generators on an experimental
basis. Such machines do not operate synchronously,
but have a characteristic similar to induction motors
except that they run at above synchronous speed. A
greater input from the prime mover increases the
13.3 Diesel engine driven salient-pole power output. Like all induction machines, they draw
generators their magnetising current from the system and there-
These machines, with ratings of a few MW, are in- fore do not require an excitation supply.
562
SUBJECT INDEX

Acceleration Austenitic steels


feedback blading, 72
governors, 130 wet steam turbines, 229
Acceptance tests rotors
condensers, 373 endrings,461
procedures, 374 Automatic voltage regulators, 523
Acid cleaning auto follow-up circuit, 525
condensers, 372 digital, 525
Actuator pistons dual channel, 524
governor valve relays, 145 manual follow up, 525
Adiabatic flow with friction protection, 525
pressure control valves rotor angles, 527
noise, 211,216 steam turbines
Advanced gas-cooled reactors run-up, 134
feedwater Auxiliary systems
temperature, 46 generators, 559
steam turbines instrumentation, 174
sizes, 122
Air Back-pressure turbines
inleakage feedwater heaters, 46
condensers, 366 Baffle plates
leakage feedwater heaters
measurement, 368 vertical, 301
leaks Baffles
location, 367 de-aerating feedheaters, 308
Air blanketing feedwater heaters, 297
condensers, 375 Balance meters
tubenests automatic voltage regulators, 525
condensers, 352 Balancing
Air cooling rotors, 96,470
condensers, 352,381 dynamic, 97
Air ejector/pump systems multi-plane, 97
condensers, 383 static, 97
Air extraction Ball-jointed tip ties
condensers blades, 68
equipment, 381 Bars
mechanism, 380 stators, 475,482
multi-point, 382 vibration
quantity determination, 380 stator windings, 548
single, 382 Base level governors, 141
Air extraction pumps Base load
condensers, 378-390 steam turbines, 217
Air gap flux coils Baumann exhaust
generators blading, 68
monitoring, 552 Baumann exhaust turbines, 4
Air pumps Bearing pedestals
liquid-ring on-line monitoring, 104
condensers, 383,388 vibrations
Air stagnation instrumentation, 173
tubenests Bearing supports
condensers, 352 foundations
Alarms slave units, 175
governing systems, 134 Bearings {see also Journal bearings; Thrust bearings)
steam temperatures, 174 boiler feed pumps, 405
Alignment forced lubrication, 181
rotors, 103 rotors, 106,472
technique, 104 steam turbines, 105-112
Ammonia Blades
steam side corrosion clearances
condensers, 340 efficiency, 12
Amplidynes efficiency, 9
exciters erosion, 75
turbine generators, 504 fixed
voltage regulation, 523 construction, 65, 66
Annulus loss ideal impulse-stage
steam turbines efficiency, 10
efficiency, 13 ideal reaction-stage
Anti-foaming agents efficiency, 10
lubricating oils, 194 length
Arcton 12 turbine efficiency, 29
air leak detection moving
condensers, 368 construction, 65, 66

563
Subject Index

efficiency, 8 maintenance, 555


root attachments, 68 rotors, 465
profile loss Bubbler devices
efficiency, 12 cooling water
secondary loss leakage, 369,370
efficiency, 12 tube leak detection
tip leakage condensers, 371
efficiency, 12 Bulleting
tip restraint, 67 cleaning
vibration condensers, 372
control, 73 Butterfly valves, 228
natural frequencies, 73 By-pass systems
sources, 73 capacity, 61
B lading fossil-fired plant, 213
aerodynamic constraints, 67 malfunctions, 62
design nuclear plant, 212
feedwater heating systems, 250 pressure control valves, 211
impulse pressurised water reactors, 62
high pressure turbines, 93 problems, 215
impulse stages, 65 start-up, 63
low pressure stages, 67 steam turbines, 59, 211-216
materials, 71 wet steam plant, 64
mechanical constraints, 67 By-pass valves
modern designs, 10 feedwater heating systems, 265,267
reaction stages, 66
steam turbines, 65-76 Caisson extraction pumps
developments, 123 vertical, 403
double-flow, 3 Calcium phosphate
low pressure, 10 solubility, 372
reversed-flow, 3 Campbell diagrams
single-flow, 3 blades
velocity-compounded stage, 65 vibration, 75
Blaydon Burn Capability charts
feedheating generators, 535
regenerative, 242 Capital costs
Bled-steam connections turbine-generators, 41
steam turbine casings, 86 Carbon dioxide
Boiler feed pumps, 243,402^17 hydrogen cooling systems
advanced class, 406 turbine-generators
construction, 405 Camot cycles
axial thrust, 407 reheat, 30
bearings, 405 Carrier rings
casings cylinders, 87
construction, 405 Cartridge filters
designs, 417 lubricating oil, 190
developments, 404 Casings
diffusers, 407 stators, 489
drives, 411 core frame, 490
efficiency, 416 steam turbines, 76-90
feed suction pumps, 412 alignment, 87
forced cooling, 407 alignment keys, 88, 89
future trends, 416 construction, 76
glands glands, 87
sealing, 408 high pressure, 77
impellers, 405 horizontal joints, 81
layout, 411 intermediate pressure, 78
light load protection, 414 low pressure, 79
suction filters, 280 materials, 86
testing, 414 supports, 87, 88, 89
thrust bearings, 408 Category A trips, 165
Boilers exhaust pressure, 167
master load controllers, 129 Category B trips, 165
pressure control, 129 low relay fluid pressure, 167
turbine master load controllers, 129 Cavitation
Bolting hydraulic turbines, 423
steam turbine casings, 84 specific speed, 425
Bolts pumps
couplings, 102 governing systems, 150
high temperature visual tests
steam turbine casings, 87 air extraction pumps, 392
tightening Cavitation performance breakdown
flanges, 84 air extractor pumps
British Electrical and Allied Manufacturers Association condensers, 391
condenser design, 345 CEGB
Brittle fracture condensers
rotors, 98 specifications, 347
Brushgear cycles, 31
generators Central Electricity Generating Board see CEGB

564
Subject Index

Centrifugal force Condensers {see also Integral condensers; Pannier condensers;


stress Underslung condensers), 323-421
generators, 542 air cooling, 381
Centrifugal pumps air inleakage, 366
hydraulic aspects axial
condensers, 390-393 steam turbine casings, 79
net positive suction head, 391 branches, 365
Centrifugal separation bridge
lubricating oil, 191 steam turbine casings, 79
Chemical injection pumps, 418^19 by-pass steam, 61
Chevron separating elements capital costs, 42
wet steam turbines, 233 cleaning, 370
Chlorination off-load, 372
cooling water on-load, 370
condensers, 370 cleanliness, 366
Chlorofluorocarbons compartmentalisation, 352
air leak detection use, 355
condensers, 368 computer-assisted design, 355
Chording connections, 365
harmonics, 456 construction, 357
Chromium alloy steel construction materials, 355
blading cooling water
wet steam turbines, 229 leakage, 368
Chromium molybdenum vanadium steels design
rotors, 94 phase 1,330
Chromium steels phase 2,330
blading, 71 phase 3,333
super 12% design codes, 345
blading, 72 design forces, 357
Circulating water pumps, 393^400 economic optimisation, 42
casings economics, 324-329
materials, 399 extraction pumps, 400-402
horizontal split-casing, 393 feedwater heating systems, 253
impellers filters
materials, 399 debris, 366
materials, 399 fouling, 370
scale models, 397 future developments, 376-378
testing, 397 heat load
vertical, 395 determination, 375
vertical metal-casing, 395 heat rejected, 341
Cleaning {see also Acid cleaning; Grit cleaning) heat transfer, 341
condensers, 370 historical development, 329-333
Cleanliness integral
condenser tubes, 375 steam turbine casings, 79
condensers, 366 layout, 329-333
Clearances length
blading economics, 44
efficiency, 12 manufacture, 357
steam turbine casings, 87 mechanical design, 355-366
Closed-loop control mounting position, 4
steam turbines operational life, 366
electrical load, 131 outlet temperature
Coal-fired plants economics, 43
feedheating pannier
number of stages, 46 steam turbine casings, 79
Coefficient of heat transfer poor performance
condensers, 347 causes, 352
Cold reheat pressure practices, 373
feedwater heating systems, 250 protection, 366
Cold reheat steam, 50 reinforcement, 365
Combined-cycle plant shells, 362
dual pressure, 121 tubeplate joints, 363
steam turbines, 118 shells/tube expansion, 365
Combined heat and power size
turbine-generators, 116 costs, 43
Computer-assisted design specifications, 345
condensers, 355 standards, 345
Computers stresses, 357
condensers support, 177
configuration, 327 support plates, 365
Concrete surface area, 327
thermal expansion, 177 test codes, 373
Concrete volute pumps thermal design, 341-355
air extraction theory, 341
condensers, 395 thermal performance tests, 373
materials, 399 three-dimensional effects, 354
Condensate extraction pumps use, 355
spray water, 61,206 titanium

565
Subject Index

economics, 45 thermal design, 341-355


transverse underslung, 360, 361 velocity
design, 359 economics, 44
waterboxes, 362 Cooling water plant, 323^21
tube leak detection Copper alloys
bubblers, 371 condensers, 333,340
tube surface area tube failure, 336
economics, 43 Core end plates
tube-to-tubeplate fixing, 364 stators, 482
tubenests, 362 Core frame bars
tubeplates, 362 stators
tubes insulation, 480
cleaning systems, 366 Core frames
inundation, 354 stators, 476,481
tubeplate joints, 363 casings, 490
tubing Core monitors
thermal performance, 377 generators, 552
turbine joints, 365 Core plates
Condition lines stators, 474
steam turbines, 13 grain-oriented steel, 475
Condition monitoring Corrosion {see also Fireside corrosion; Hot spot corrosion;
generators, 550,552 Waterside corrosion)
instrumentation, 551 cooling water
instrumentation, 174 prevention, 333
Conductors cyclone separators
stators, 481 wet steam turbines, 230
Contamination inhibition
chemical lubricating oils, 193
hydraulic fluids, 153 journal bearings, 108
water Corrosion fatigue
hydraulic fluids, 153 condensers, 340
Control unit type 1 Corrosion fatigue cracking
governor valve relays, 145,146 condensers, 339
Control unit type 2 Corrosion resistance
governor valve relays, 147, 148 chromium steels
Control unit type 3 blading, 72
governor valve relays, 149 titanium
Control valves blading, 72
feedwater heating systems Couplings
low pressure feed systems, 285 bolts, 102
Coolers flexible, 101
hydraulic fluids half, 102
governing systems, 151 rigid, 101
Cooling {see also Air cooling; Forced-air cooling) semi-flexible, 101
rotors shaft length, 100
intermediate pressure, 93 shrink-on, 102
steam turbines, 224 steam turbines, 90-105
thyristors, 522 Cover seals
Cooling systems {see also Exhaust spray cooling systems) steam chests, 158
heated water discharge direct-cooled, 324 Coverbands
turbine generators, 491-504 arch
Cooling towers blades, 68
economics, 44 blades
heat dissipation, 324 steam turbines, 65
Cooling water Creep
culvert system rotors, 92,94
capital costs, 42 Creep strength
economic optimisation, 42 blading
facilities, 324 chromium steels, 72
flow Critical speed bands
condensers, 327 steam turbines
foundation movement governing systems, 133
monitoring, 175 Critical speeds
historical development, 329-333 rotors, 97
inlet temperature Current measurement
economic optimisation, 44 excitation system, 515
economics, 43 Cyclone separators
layout, 329-333 high velocity
leakage wet steam turbines, 231
condensers, 368 wet steam turbines, 230
pumping Cylinders
costs, 43 bolting, 84
pumps, 324 efficiency, 13
capital costs, 42 steam cycle, 22
quality expansions
environment, 333 instrumentation, 173
temperature external efficiency, 13
generators, 550 internal efficiency, 13

566
Subject Index

low pressure Diodes


steam turbine casings, 86 excitation, 510
steam turbines, 4 protection, 511
supports, 87 negative DC
Cylindrical rotor generators, 447 excitation, 514
Disc stack
Dampers pressure control valves
rotors, 464 noise, 211
Damping Disc windage
vibration steam turbines
blades, 75 efficiency, 13
Damping torque, 527 Display units
De-aeration generators
feedwater, 49 instrumentation, 550
De-aerators (see also Stork de-aerators) Distribution factor, 455
construction District heating
feedwater heating systems, 308 steam turbines, 118
elevation, 275 Double reheat
feedheaters, 305-308 Rankine cycle, 30
feedwater heating systems, 250, 272-281, 289, 320 Draft tube valves
water level, 253 pump-turbines, 444
heaters, 272, 274 Drain valves, 210
pipework, 279 Drains (see also System drains)
protection systems, 277 continuous, 209
storage tank, 272 feedwater heating systems, 268
tanks low pressure feedwater heating systems
sloshing, 274 forward pumping, 282
waterspray/steam injection-type, 50 start-up, 209
Debris stators, 491
condensers, 370 water flow
filters control, 209
condensers, 366 Drains cooling, 46
Degassing Drains pumping
hydrogen cooling systems feedheating, 46
turbine generators, 491 Drains systems, 209-210
Dehydration wet steam turbines, 237
hydraulic fluids Drax Completion power station
governing systems, 154 feedheaters, 247
Deionisation feedwater heaters
feedwater heating systems, 315 pipework, 273
Demineralisers Droop adjustment
water speed loop, 128
stator winding cooling systems, 502 Drum rotor, 9
Desuperheaters Dry stage efficiency
gland sealing systems steam turbines, 16
cooling water, 202 Ductility
gland steam, 203 blading
gland temperature control, 200 chromium steels, 72
Detergents Dump pistons
lubricating oils, 194 governor valve relays, 145
Diaphragms Dump tubes
construction, 70 by-pass systems, 212
cylinders, 87 Duplex filters
kinematic support, 70 lubricating oil, 190
radial support pads, 70 Dynamic stability
steam turbines excitation systems, 530
glands, 87
support, 70 Earth leakage
Dichlorofluoromethane detection
air leak detection excitation systems, 517
condensers, 368 excitation systems, 515
Diesel engines Eccentricity
salient-pole generators, 562 shafts
Differential expansion instrumentation, 173
steam turbines steam turbines
run-up, 133 protection, 164
Diffusers run-up, 133
boiler feed pumps, 407 Economics
Dinorwig power station condensers, 324329
fatigue life, 439 Economisers
guide vanes, 443 feedheating, 45
machine layout, 439 Eddy current losses
main inlet valves, 442,443 stator cores, 476
pump-turbines, 440 Eddy currents
pumped storage, 433 stator conductors, 482
section, 438 Efficiency
site plan, 437 instrumentation, 173
statistics, 445 Electric motors

567
Subject Index

feed pumps turbine-generators, 504


variable speed, 55 section, 507
variable-speed drives, 55 Exhaust pressure
variable-speed feed pump drives by-pass systems, 61
efficiency category A trips, 167
Electrical erosion economic optimisation, 42
journal bearings, 108 high
Electrical tripping trips, 170
turbine protection, 167 optimum
Electricity distribution economics, 41
AC vs DC, 447 Rankine cycle, 28
Electromagnetic induction, 450 steam cycle
Ellipse law economics, 40
output, 8 steam turbines
Emergency stop heat rate, 41
turbine protection, 172 protection, 164
Emergency trip valves trips, 165
on-load testing, 166 unloaders, 137
turbine protection, 166 unloading gear, 130
End rings Exhaust spray cooling systems
rotors, 460 low pressure, 206-209
End windings temperature control
stators automatic, 207
supports, 483 Exhaust steam
Enthalpy-entropy diagrams low pressure
Rankine cycle, 18 temperature control, 207
Entropy, 18 Exhausts
Environment steam turbine casings, 85
condensers, 333-341 steam turbines, 4
Erosion External efficiency
blades, 75 cylinders, 13
progression, 76 Extraction pumps
shield materials, 76 condensers, 400-402
cyclone separators
wet steam turbines, 230 Fans
hydraulic turbines, 423 rotors, 465,470
protection Fatigue
wet steam turbines, 229 rotors
EssheteCRM 12 generators, 544
blading, 72 Fatigue cracking
Evaporators journal bearings, 108
bled-steam Fatigue strength
feedwater heating systems, 316 blading
flash, 316 chromium steels, 72
vertical-tube type, 316 Fault currents
feedwater heating systems, 315-317 generators, 539
assembly, 319 Feed pumps
flash back-pressure
feedwater heating systems, 319 steam turbines, 115
flash type condensing-type
feedwater heating systems, 317 steam turbines, 116
single-stage duty, 54
feedwater heating systems, 318 economics, 53
surface type elevation, 254
feedwater heating systems, 317 fluid-coupling drive
Excitation economics, 57
AC turbine generators, 506 induction-motor-driven
adaptive controllers, 526 capital costs, 57
control, 526 economics, 57
future developments, 560 running costs, 57
turbine generators, 504-532 margins, 54
Excitation equipment motor-driven
static rectifiers, 520 thermodynamic effects, 56
Excitation systems number
analysis, 530 economics, 53
brushless size
turbine generators, 509 economics, 53
Exciter field switches steam turbines, 115
field suppression, 547 through-life costs, 58
Exciters {see also Main exciters; Pilot exciters) turbine governors, 156
AC voltage regulation, 523 turbines
DC turbine generators, 504 exhaust route, 156
DC voltage regulation, 523 power rating, 157
gear driven steam supply, 156
turbine-generators, 504 variable speed, 54
performance testing, 508 variable-speed drives
transient performance capital costs, 55
turbine-generators, 506 electric motors, 55

568
Subject Index

running costs, 55 thermal-hydraulic design, 314


variable-speed-motor-driven Feedwater heating
capital costs, 57 bled-steam connections
economics, 57 steam turbine casings, 86
running costs, 57 number of stages, 45
Feed suction pumps coal-fired plant, 46
boiler feed pumps, 412 oil-fired plant, 46
Feedwater regenerative, 242
contamination economics, 45
protection, 255,259,287 Rankine cycle, 21
de-aeration, 49 wet steam cycle, 46
temperature Feedwater heating cycle
advanced gas reactors, 46 CEGB, 33
Feedwater headers Feedwater heating plant
low pressure protection equipment, 260
flow area, 311 Feedwater heating systems, 241-322
tube thicknesses, 310, 311 component design parameters, 250
shells component levels, 253
construction, 310 configuration, 250
Feedwater heaters design, 250-261
all-tubular surface type, 251 direct contact LP heaters, 252
alternative designs functional needs, 250
construction, 304 future developments, 317-322
bled-steam, 115 high pressure, 261-272
bled-steam inlets, 297 parameters, 261
British Standards, 289 high pressure feed system, 320
condensing sections, 299 low pressure, 321
de-aerating, 305-308 low pressure feed systems
de-aerators, 289 tubular surface type HP heaters, 252
designs, 289-290 water content
desuperheating sections, 297,301 maintenance, 253
developments, 53 Ferritic stainless iron
direct contact LP blading
component level diagram, 257 wet steam turbines, 229
drain cooling sections, 299,301 Ffestiniog power station
drains, 270 pumped storage, 433,434
Drax Completion power station, 247 Field current measurement
elevation, 254 excitation systems, 519
final feed temperatures, 28 Field lead wedges
flooding, 51 rotors
flow-induced vibration, 296 generators, 543
Grain power station, 245 Field suppression
Heysham 2 AGR power station, 248 generators, 547
high pressure, 46,51, 289-305 Films
construction, 292 cooling water
horizontal, 299 leakage, 369
thermal design, 297 Filters (see also Cartridge filters; Oil filters; Suction filters)
tube thickness, 292 lubricating oil, 190
vertical, 301 Filtration
Ince B power station, 244 cooling water
Littlebrook D power station, 246 condensers, 372
low pressure, 51, 308-314 hydraulic fluids
bled-steam inlets, 312 governing systems, 151
construction, 309 Final feed temperature
direct contact, 314 feedwater heating systems, 250, 261
dished ends, 314 Fir-tree roots
drain outlets, 312, 314 blades, 69
external drain coolers, 312 Fire pumps, 419
horizontal-attitude arrangement, 283 Fire-resistant fluids
shells, 314 conditioners, 155
surface type, 308 hydraulic fluids
thermal design, 312 governing systems, 149
tube lengths, 311 packaged units, 156
tube support plates, 311 Fire risk
tube supports, 311 hydraulic fluids
low pressure direct contact, 289 governing systems, 149
low pressure tubed, 289 Fireside corrosion
on-load test facilities, 269 boiler tubes
pipework, 273 feedwater de-aeration, 49
pressurised water reactors, 48, 249 Flames
shells, 292 cooling water
thermal efficiency, 22 leakage, 369, 370
tube lengths, 295 Flange bolts
tube supports, 295 tightening, 84
tubeplate-type horizontal high pressure, 52 Flange heating
tubular surface type, 254 steam turbines
component level diagram, 256 flexibility, 222
water-to-water drain coolers Flange heating systems, 204-206

569
Subject Index

control, 205 Fuses


Flanges blown
steam turbine casings, 82 detector system, 515, 516, 519
Flashing drain coolers failure
low pressure feedwater heaters, 308, 312 detection unit, 525
thermal hydraulic design, 314 FV448
Flexibility blading, 72
steam turbines FV507
design, 217 blading, 72
efficiency, 39
Flow Gas-in-water detection
condensers generators, 550
measurement, 374 Gas-in-water detection chambers
generators stator windings
instrumentation, 550 water cooling
measurement Gas turbines
circulating water pumps, 397 combined-cycle plant, 118
turbines Gassing-up
direction, 2 hydrogen cooling systems
Fluid coupling slip turbine generators, 491
feed pumps Gearboxes
variable speed drives, 57 air extraction pumps, 395
Fluorescein circulating water pumps, 398
cooling water feed pumps
leakage, 369 variable speed drives, 57
Flux Generator phasor diagrams, 535
synchronous generators, 452 Generators, 446-562
Flux distribution 20 MW
generators air cooled, 449
on load, 545 660 MW, 448
Foaming Generators {see also Quad-Olympus generators; Synchronous
inhibition generators; Turbine-generators; Wind generators)
lubricating oils, 193 condition monitoring, 550
Foams control, 549-555
cooling water future developments, 560
leakage, 369 DC, 114
Forced-air cooling diagnosis, 555-558
main turbines, 224 efficiency, 536
Forging electrical aspects, 545-549
titanium electrical measurement, 550
blading, 73 electrically unbalanced conditions, 537
Fossil-fired plant electromagnetic aspects, 545-549
by-pass systems, 213 exciter and power systems, 527
Fouling characteristics, 529
biological fixed speed AC, 114
condensers, 370 future developments, 558-559
condensers, 370 induction, 562
Foundations losses, 536
concrete, 177 maintenance, 555-558
flexible, 176 mechanical considerations, 541-545
resonances, 176 monitoring, 549-555
spring, 180 on-load monitoring, 552
steam turbines, 175-181 open-circuit conditions, 533
movement, 175 operation, 532-541
steel, 179 operational measurement, 549-555
stiff, 176 outages
tuning, 176 maintenance, 555
Fourier equation protection, 549-555
heat transfer reassembly, 557
condensers, 347 running up to speed, 532
Fracture appearance transition temperature salient-pole
rotors, 96 diesel engines, 562
Francis turbines, 422,426 shutting down, 541
end thrust, 426 slotless, 558
Freon 12 specifications, 449
air leak detection standards, 449
condensers, 368 steady short-circuit conditions, 535
Frequency response analysis steady state stability, 534
excitation systems, 531 superconducting, 558
Fretting synchronising, 533
rotors temperature, 536
generators, 544 testing, 555-558
Fuels transformers
costs winding faults, 554
turbine-generators, 42 turbine-type
Fuller's earth lower rating, 559
filtration types, 447-450
hydraulic fluids, 154 unbalanced load faults, 554

570
Subject Index

water turbine driven salient-pole synchronous, 560 Heat balance equation, 347
Gland sealing systems, 200, 201 Heat dissipation
pressure control, 200, 203 atmospheric, 324, 325
steam turbines, 198-204 Heat Exchanger Institute standards
temperature control, 200 steam surface condensers, 345
Gland steam condensers, 204 Heat load
Glands (see also Labyrynth glands) condensers
boiler feed pumps determination, 375
sealing, 408 Heat rate
steam turbines, 198 instrumentation, 174
Governing steam cycle, 22, 23
electronic, 134 steam turbines
high pressure, 128 exhaust pressure, 41
high pressure plus intermediate pressure, 128 test instrumentation, 174
parallel, 128 Heaters (see also Feedwater heaters)
Governing systems, 125-157 de-aerators, 272, 274
digital processing, 140 feedwater
functions, 125 elevation, 253
mechanical high pressure
reliability, 134 feedwater heating systems, 297
steam turbines Heysham 2 AGR power station
overspeed protection, 164 feedheaters, 248
Governor valve relays, 142 Heysham 2 power station
control unit type 1, 145, 146 condensers, 359
control unit type 2, 147, 148 Hogging
control unit type 3, 149 air extraction
Governor valves, 160, 162 condensers, 388
forces, 145 Hood loss
guided flow type, 163 Rankine cycle, 28
high pressure steam turbines, 15
on-load testing, 132 Hot spot corrosion
intermediate pressure condensers, 338, 339
on-load testing, 132 Humidity
mushroom type, 163 hydrogen cooling systems
pressure drop, 8 monitoring, 492
reverse flow, 163 Hydraulic fluid systems
throttling governing systems, 149
flexibility, 222 Hydraulic fluids
Governors (see also Base level governors) contamination
acceleration feedback, 130 governor valve relays, 142
characteristics, 126 Hydraulic pumps
failure air extraction
protection, 164 condensers, 381,383
inter-valve monitoring, 137 Hydraulic tightening
speed reference, 131 flange bolts, 84
speed setpoints, 129 Hydraulic turbines, 422-446
steam turbines axial flow, 422
modular arrangement, 157 impulse, 422
turbines propeller types, 422
feedpumps, 156 radial flow, 422
Grain power station reaction, 422
feedheaters, 245 running speed, 423
Greases (see also Lithium-based greases; Silicone-based specific speed, 422
greases) Hydrogen
types, 194 drying, 496
Greasing systems purity
steam turbines, 196 monitoring, 492
Grit cleaning safety, 497
condensers, 373 temperature
Guide vanes monitoring, 492
Dinorwig power station, 443 Hydrogen cooling
pumped storage, 441 stators
variable windings, 488
tubular turbines, 428 temperature
Gun drilling trips, 554
water headers turbine-generators, 447,491
tubeplates, 263 Hydrogen embrittlement
rotors, 94
Half-speed machines, 229 Hydrogen pressure
Halogen leak detectors generators
air leaks instrumentation, 550
condensers, 367 Hydrogen seals
Hand barring generators
turning gear, 111 lubricating oil, 183
Harmonics lubricating oil, 188
chorded windings, 455 Hysteresis
distributed windings, 455 stator cores, 476
generators, 546

571
Subject Index

Impellers steam turbines, 198


boiler feed pumps, 405 stepped, 199
Ince B power station tip thickness, 199
feedheaters, 244 vernier, 199
Instrumentation Labyrinth seals
auxiliary systems, 174 boiler feed pumps, 409,410
condition monitoring, 174 Lacing wires
efficiency, 173 blades
generators, 549 tip restraint, 67
journal bearings, 105 steam turbines
post-incident records, 175 efficiency, 13
protection and control equipment, 175 Lagging
turbines, 172-175 steam turbine casings, 90
classification, 173 Leading power factor
supervisory, 173 generators, 534
Insulation Leakage flows
generators by-pass systems, 216
maintenance, 557 Leaving losses
monitoring, 553 Rankine cycle, 28
rotor windings, 459 steam turbines, 15
rotors Life expenditure monitors
windings, 548 steam turbines, 224
stator windings, 548 Light-water reactors
deterioration, 549 half-speed machines, 229
Integral condensers, 4 Lithium-based greases
Inter-valve monitoring steam turbines, 194
governors, 137 Littlebrook D power station
Internal efficiency feedheaters, 246
cylinders, 13 Load
Iron oxide application
condensers, 336 generators, 533
Isceon 12 Load angles
air leak detection generators, 534
condensers, 368 Load cycling
Isolating valves steam turbines, 217
by-pass systems, 211 Load rejection controllers
feedwater heating systems, 266, 267 by-pass systems
low pressure feed systems, 285 nuclear plant, 212
Load shedding
Jacking oil pumps, 185 throttling, 8
Jacking oil systems Loading systems
steam turbines, 194,197 governing systems, 132
Joints Logarithmic mean temperature differences
bolted covers condensers, 343
boiler feed pumps, 417 Logging
condensers generators
bellows, 363 instrumentation, 550
flange, 363 Loop pipes, 157-164
horizontal Loop pipework, 160
turbine casings, 81 Low pressure feed systems
horizontal bolting feedwater heating systems, 281-289
wet steam turbines, 229 configuration, 281-289
welded control valves, 283
stator casings, 489 isolating valves, 283
Journal bearings Lubricating oils
construction, 105 acidity, 194
performance, 105 failure
steam turbines, 105 tripping, 165
life, 108 low pressure trips
Journal type seals turbine protection, 170
hydrogen cooling systems purification, 192
turbine generators, 497 regeneration, 195
steam turbines
Kaplan turbines, 422 protection, 164
blades requirements, 196
adjustment, 428 types, 193
Katharometers Lubrication
safety, 492 steam turbines
Kinematic support arrangements, 181
diaphragms, 70 requirements, 181
Lubrication systems
Labyrinth glands steam turbines, 181-198
axial-radial, 199
diameters, 200 Machine levels
flow, 200 instrumentation, 174
plain, 199 Machining
radial clearance, 200 titanium
spring-back, 199 blading, 73

572
Subject Index

Magnetic amplifers Oil coalescers


excitation systems, 523 lubricating oil, 191
Magnetic circuits static, 193
synchronous generators, 452 Oil coolers
Magnetic pull lubricating oil, 189
generators, 547 Oil filters
Magnetostriction, 545 lubricating oil, 189
Main exciters, 510 Oil-fired plants
protection, 509 feedheating
rotating armature, 512 number of stages, 46
turbine generators, 511 Oil pumps
turbine generators, 508 lubrication
Main inlet valves main, 184,185
Dinorwig power station, 442,443 main bearings, 183
pump-turbines, 439 steam turbines, 184
Maintenance motor-driven auxiliary, 185
steam turbines Oil purifiers
efficiency, 39 lubricating oil, 191
turbine-generators static, 193
costs, 42 Oil sealing
Majority voting circuits, 137 pedestals, 111
Master load controllers Oil strainers
boilers, 129 lubricating oil, 189
steam turbines Oil tanks
boiler pressure control, 129 lubricating oil, 187
Material damping On-load testing
blading governing systems, 132
chromium steels, 72 Operational flexibility
titanium steam turbines, 216-226
blading, 73 Oscillations {see also Power system oscillations)
Maximum continuous rating inter-area, 529
synchronous generators, 452 inter-tie, 529
Mean temperature differences intra-plant modes, 529
condensers local modes, 529
standards, 345 system modes, 529
Mineral fibres Outages
lagging generators
steam turbine casings, 90 maintenance, 555
Mineral oils Output
steam turbines, 194 steam turbines
Mobrey float switches limitations, 8
feedwater heating systems, 269 Overfluxing
Moisture separator reheaters automatic voltage regulators, 527
horizontal Overspeed
wet steam turbines, 235 proof test
wet steam turbines, 230 turbine protection, 170
Mollier diagrams protection
CEGB cycles, 31 steam turbines, 164
Multi-exhausts protection systems
blading, 68 governing systems, 132
Mussels testing
condensers governing systems, 132
control, 373 Overspeed trips
cooling water, 336 governing systems, 125
steam turbines
Network frequency governing systems, 165
power generation turbine protection, 170
governing systems, 125 Oxidation
Neutral earthing inhibition
generators, 540 lubricating oils, 193
Noise Oxidation inhibitors
generators lubricating oils, 193
rotors, 545 Oxygen
pressure control valves feedwater
by-pass systems, 211 corrosion, 49
fossil-fired plant, 216
Non-return valves Pannier condensers, 4
de-aerators steam turbine casings, 79
bled-steam power-assisted, 278 Partial admission
Notch sensitivity steam turbines
blading efficiency, 16
chromium steels, 72 Pedestals
Nuclear plant bearings, 108
by-pass systems, 212 oil sealing, 111
Nuclear steam supply system, 33 steam turbines, 105-112
Pelton turbines, 422,423
Oil booster pumps Phasor diagrams, 452
turbine-driven, 184 Phosphate esters

573
Subject Index

hydraulic fluids Protective devices


governing systems, 149 steam turbines, 164-172
viscosity, 151 Pump-turbines
Pilot exciters Dinorwig power station, 440
protection, 508 testing, 444
turbine generators, 506 Pumped-storage, 431445
section, 507 Pumps {see also Air extraction pumps; Air pumps; Boiler feed
Pinned roots pumps; Caisson extraction pumps; Centrifugal
blades, 69 pumps; Chemical injection pumps; Circulating
Pipework {see also Loop pipework) water pumps; Concrete volute pumps; Condensate
crossover, 163 extraction pumps; Extraction pumps; Feed pumps;;
de-aerators, 279 Feed suction pumps; Fire pumps; Hydraulic pumps;
feedwater heaters, 273 Jacking oil pumps; Oil booster pumps; Oil pumps;
feedwater heating systems, 271 Priming pumps; Rotary pumps); 323421
governing systems condensers, 378-390
stainless steel, 154 historical development, 329-333
low pressure feedwater heating systems, 288 layout, 329-333
reheaters screw-type
pressure loss, 27 governing systems, 150
Piping submersible
lubricating oil, 188 construction, 420
Piston rings
steam turbine casings, 85 Quad-Olympus generators, 561
Pistoye slots
stators, 476,478 Radial support pads
Pitch factor, 456 diaphragms, 70
Plant operation Rankine cycle, 17
turbine-generators final feed temperatures, 28
costs, 42 superheat, 19
Plant trip controllers Reactances
by-pass systems generators
nuclear plant, 213 calculation, 546
Pole face wedges control, 546
generators, 543 Rectifier equipment
Post-incident records static diodes
instrumentation, 175 excitation equipment, 521
Power generation Rectifiers {see also Rotating rectifiers; Static rectifiers;
mechanical drive Thyristor rectifiers)
steam turbines, 114 excitation systems, 516,517
network frequency protection, 521
governing systems, 125 static thyristors
steam turbines, 112 excitation systems, 521
Power system oscillations, 527 Reheat
Power system stabilisers, 527 Carnot cycle, 30
operation, 529 conditions
Pressure steam cycle, 26
condensers double
acceptance tests, 374 Rankine cycle, 30
generators first-stage
instrumentation, 550 wet steam turbines, 237
Pressure cascading second-stage
feedheating, 46 wet steam turbines, 238
Pressure control Reheat cycle, 20, 26
boilers, 129 CEGB, 33
Pressure control valves Reheaters
by-pass systems, 211 drains
nuclear plant, 212 wet steam turbines, 239
spraywater economics, 59
fossil-fired plant, 215 governing valves, 128
Pressurised water reactors pipework
feed pumpsets, 416 pressure loss, 27
feed systems pressure loss, 27
cycle details, 242 relief valves, 149
feedheaters, 249 steam supply
feedwater heaters, 48 wet steam turbines, 237
steam cycles, 33 steam-to-steam
turbine-generators, 40 performance monitoring, 239
wet steam cycle, 46 wet steam turbines, 233
wet steam plant, 62 valves
Priming pumps pressure loss, 27
lubrication, 185 vertical
Profile loss wet steam turbines, 233
blades Reheating
efficiency, 12 steam turbines
Protection efficiency, 114
condensers, 366 Reheating plant
Protection and control equipment double-stage, 37
instrumentation, 175 single-stage, 37

574
Subject Index

Relay fluids shafts, 456


category B trips, 167 shrink-on, 91
Release valves sizes, 472
reheaters, 149 steam turbines, 90-105
Reliability flexibility, 223
governing systems voltages, 547
definition, 134 teeth
steam turbines tensile stress, 542
efficiency, 39 testing, 96,456
Relief valves thermal stability, 96
reheaters, 149 threading, 470
Residual magnetism torque
shafts generators, 542
generators, 547 turbine-generators, 456
Resistance elements vibration, 470
temperature measurement weight, 472
generators, 549 welded disc, 91
Resonances windings, 459,463
foundations, 176 coils, 459
Reversible pump-turbines, 433 earth fault indication, 553
Rigidity slip-stick, 544
foundations, 176 temperature measurement, 466
Rim generator turbines, 432 voltage, 548
design, 431 Routine operational tests
Root locus condensers, 373
excitation systems, 531 Run-up
Rotary pumps automatic
air extraction governing systems, 132
condensers, 381 steam turbines
Rotating amplifers governing systems, 125
exciters Runaway speed
turbine-generators, 504 hydraulic turbines, 423
Rotating diodes Runner blades
excitation systems tubular turbines, 428
monitoring, 519 Rust inhibitors
Rotating phasors lubricating oils, 193
synchronous generators, 452
Rotating rectifiers Safety
excitation hydrogen cooling, 497
turbine-generators, 513 Scale
excitation systems condensers, 370
protection, 519 cleaning, 372
Rotors Scavenging
alignment, 103,470 hydrogen cooling systems
axial position turbine-generators, 491
instrumentation, 173 Screening plant
balancing, 96 cooling water, 324
body, 456 Screens
brushless stators, 482
connections, 469 Seal oil pressure
built-up, 91 generators
construction, 90 instrumentation, 550
cooling, 93 Seal oil systems
critical speeds, 97 hydrogen cooling systems
current limiters, 526 turbine-generators, 497
drum type, 91 Seals (see also Labyrynth seals)
end rings, 460 mechanical
fans, 465 boiler feed pumps, 411
fast fracture rotors, 472
risk assessment, 98 steam turbines, 198
generators Seasons
maintenance, 556 cooling water
residual magnetism, 547 temperature, 44
high pressure Secondary loss
materials, 94 blades
stress control, 129 efficiency, 12
high temperature operation, 92 Self-shifting synchronous clutches
integral, 90 turning gear
intermediate pressure steam turbines
materials, 94 Semiconductors
low pressure static rectifiers
materials, 94 excitation equipment, 520
main exciters, 508 Separators (see also Cyclone separators)
materials, 93,456 chevron
monobloc, 90 wet steam turbines, 232
non-destructive examination, 95 corrugated-plate
overspeed testing, 96 wet steam turbines, 232
reassembly, 557 drains

575
Subject Index

wet steam turbines, 239 governors, 129


wet steam turbines, 230 overwound, 128
wire mesh Spheroidal graphite iron
wet steam turbines, 231 bearing pedestals, 108
Service water pumps, 417-418 Split phase protection, 554
Servo-valves Sprayers
control unit type 1,145 de-aerating feedheaters, 307
electrohydraulic Spraywater
electronic governing, 142 condensate extraction pumps, 61, 206
Shaft end glands distribution systems
live steam, 226 de-aerating feedwater heaters
Shaft seals nozzles, 208
air extraction pumps, 395 pumps, 206
hydrogen cooling systems Spraywater control valves
turbine generators, 497 by-pass systems
Shafts nuclear plant, 213
boiler feed pumps, 405 Stabiliser signals
circulating water pumps choice, 529
materials, 399 Stage efficiency
current insulation steam turbines, 13
instrumentation, 553 Standard nuclear unit power plant system, 46
eccentricity Standards {see also Heat Exchanger Institute standards)
instrumentation, 173 feedheaters, 289
length Standstill seals
couplings, 100 boiler feed pumps, 410
rotors Start-up
earthing, 465,469 by-pass systems, 61-63
monitoring, 469 once-through boilers, 62
speed State variable analysis
instrumentation, 173 excitation systems, 531
vibration Static diodes
instrumentation, 174 rectifier equipment
voltage excitation equipment, 521
generators, 547 Static rectifiers
Short-circuit ratio excitation equipment, 520
generators, 535 excitation systems, 521
Short-pitching Static thyristors
harmonics, 456 rectifiers
Shutting down excitation systems, 521
generators, 541 Stator cores
Silicone-based greases cooling, 508
steam turbines, 194 Stator leakage reactance
Sinusoidal grit blasting generators, 546
condensers Stator slots, 484
cleaning, 373 Stator winding conductors, 475
Slip-stick Stator windings
rotors water pressure
windings, 544 generators, 550
Slipring induction motor Stators
feed pumps casings, 489
variable-speed drives, 55 maintenance, 557
Sliprings conductors
generators eddy currents, 482
maintenance, 555 core frame bars
instrument insulation, 480
excitation systems, 519, 520 cores, 473
rotors, 465 flux, 477
brushes, 468 maintenance, 557
brushgear, 468 electrical connections, 485
connections, 467 end windings
Slot wedges maintenance, 557
rotors insulation
generators, 542 deterioration, 549
Smoke Pistoye slots, 478
cooling water slot wedges
leakage, 369,370 maintenance, 557
Specific speed terminal bushings, 485
hydraulic turbines terminals, 485
cavitation, 425 turbine-generators, 473-491
Speed ventilation, 479
sensing winding
governors, 138 water analysis, 553
proximate transducers, 139 windings, 477
Speed reference controllers 660 MW, 486
automatic voltage regulators, 527 cooling, 485
Speed of rotation earth faults, 554
steam turbines, 4 generators, 546
Speed setpoints insulation, 548

576
Subject Index

main exciters, 508 closed-loop control, 131


water cooling systems, 488, 500, 501 exhaust area
Steady short-circuit conditions economics, 44
generators, 535 exhaust pressure
Steady state stability economics, 40
generators, 534 exhausts, 4
Steam extraction, 116
critical pressure, 31 feed pumps
ingress back-pressure boilers, 115
steam turbines, 255 condensing-type, 116
strainers, 158 variable-speed drives, 55
supply flow
wet steam turbines, 237 direction, 2
wet foundations, 175-181
turbines, 226 full-speed
Steam chest valves, 158 efficiency, 38
mating faces, 158 governing systems
spindles, 158 overspeed protection, 164
Steam chests, 157-164 half-speed
construction, 157 economics, 40
materials, 158 efficiency, 38
Steam cycle heat rate
economics, 40-64 exhaust pressure, 41
efficiency, 22 impulse-type, 8
pressurised water reactors, 33 maintenance
terminal conditions, 25 efficiency, 39
thermodynamics, 16-40 master load controllers
Steam ejector/pump systems boiler pressure control
condensers, 385 multi-cylinder, 5
Steam header controllers operational flexibility
by-pass systems efficiency, 39
nuclear plant, 213 output, 8-16
Steam inlets pass-out, 116
steam turbine casings, 85 power generation, 112
Steam-jet air ejectors protective devices, 164-172
condensers, 381 radial-flow, 2, 3
Steam pressure reaction-type, 9
blade length, 29 relative thermal efficiencies, 39
instrumentation reliability
efficiency, 174 efficiency, 39
steam turbines, 122 reversed-flow, 3
Steam temperature rotors, 90-105
blade length, 29 single-flow, 3
Steam temperatures size
instrumentation efficiency, 38
efficiency, 174 speed of rotation, 4
Steam turbines, 1-123 stage efficiency, 13
applications, 112-120 steam ingress
axial-flow, 2, 3 protection, 255
backpressure, 116 tandem-compound, 4,6
blading thermodynamic optimisation
developments, 123 exhaust pressure, 40
low pressure, 10 types, 2-8
boiler feed pumps variable-speed, 7
cycle diagram, 47 water ingress
by-pass systems, 59 protection, 255
capital costs weight
economic optimisation, 42 efficiency, 38
casings, 76-90 Steam valve relays
horizontal joints, 81 pumping systems, 149
combined-cycle plant, 119 Steam valves, 157-164
condensers closing time
joints, 365 governor valve relays, 142
condition lines, 13 electronic governing, 134
construction governing systems, 125
efficiency, 38 governor valve relays, 142
cooling, 224 grease points, 198
critical speed bands linearisation characteristics, 140
governing systems, 133 positions
cross-compound, 4,6 instrumentation, 173
cylinders, 4 pressure drop, 8
flexibility, 222 relays, 126
design tripping, 165
efficiency, 9 Steel (see also Austenitic steels; Chromium alloy steels;
steam cycles, 33 Chromium molybdenum vanadium steel;
double flow, 3 Chromium steels; Super 12% Cr steels)
efficiency, 8-16 foundations, 179
electrical loads grain-oriented sheet

577
Subject Index

stators, 475 Synchronous reactance


Stiffnesses generators, 536, 546
rotors Synchronous torque, 527
vibration, 471 System drains
Stop valve pressure wet steam turbines, 239
standardisation, 242
Stop valve relays Telemetry
emergency, 145 excitation systems, 516, 518
Stop valve temperature Temperature differentials
standardisation, 242 steam turbines
Stop valves protection, 164
control unit type 1, 145 Temperature-entropy diagrams
emergency, 161 Rankine cycle, 18
high pressure Temperature measurements
on-load testing, 132 instrumentation, 173
intermediate pressure Temperature terminal differences
on-load testing, 132 feedwater heating systems, 261
on-load testing, 160 Temperatures
tripping, 165 condensers
Stork de-aerators measurement, 374
feedheaters, 307 generators
Straflo turbines, 431,432 instrumentation, 549
Strain gauges Terminals
alignment generators, 487
rotors, 104 Thermal cycling
Stress steam turbines, 217
centrifugal force Thermal fatigue
generators, 542 rotors, 92
monitors Thermal shocks
flexibility, 224 by-pass systems, 216
Stress corrosion cracking Thermal skirts
condensers, 339, 340 steam turbine casings, 85
Stresses Thermal stresses
rotors steam turbines
generators, 544 two-shifting, 222
Subsoils Thermal tightening
elasticity, 176 flange bolts, 84
Suction filters Thermocouples
boiler feed pumps, 280 generators, 549
Suction specific speed Thermodynamics
air extractor pumps, 393 steam cycle, 16-40
Super 12% Cr steels Thermometers
blading, 72 generators, 549
Superconductivity Throttling
generators, 558 load shedding, 8
Supercritical plant Thrust bearings
steam turbines, 122 boiler feed pumps, 408
Superheat failure
Rankine cycle, 19 protection, 164
Superheat cycles, 29 steam turbines, 108
feedheating, 45 tilting-pad, 109
Superheaters wear
economics, 59 instrumentation, 173
Support plates Thrust pads
condensers, 365 wear
Surface current paths measurement, 110
generators, 537 Thrust type seals
Surge pads hydrogen cooling systems
thrust bearings, 108 turbine generators, 497
Swallowing capacity Thyristor converters
steam turbines protection, 525
output, 8 Thyristor output amplifiers
Synchronisation excitation systems
generators, 533 voltage regulation, 523
governors Thyristor rectifiers
speed reference, 131 excitation systems, 521
steam turbines Thyristors
governing systems, 125 cooling, 522
Synchronous compensation Tightening
generators, 536 hydraulic
Synchronous generators flange bolts, 84
frequency, 451 thermal
load, 451 flange bolts, 84
pole-pairs, 451 Tip leakage
power factor, 451 blades
rating, 451 efficiency, 12
speed, 451 Titanium
theory, 450-456 blading, 72

578
Subject Index

condenser tubing, 379 condensers, 327


condensers, 340,342 Turbine-generators, 447
economics, 45 capital costs, 41
Torque components, 456-473
generators, 454 fuel costs, 41
Torque-speed loop diagrams, 528 historical background, 447
Tracer gas detectors lifetime costs, 41
air leaks maintenance
condensers, 367 costs, 41
cooling water operating costs, 41
leakage, 369,370 pressurised water reactor, 40
Transducers stators, 473-491
on-load testing, 170 Turbine moisture extraction condensers, 309
trip-initiating Turbine plant systems, 124240
turbine protection, 167 Turbine supervisory equipment
Transient reactance steam turbines
generators, 538 run-up, 133
Transient stability Turbine valves
excitation systems, 530 governors, 128
Transient stability analysis Turbines {see also Back-pressure turbines; Bauman exhaust
excitation systems, 531 turbines; Francis turbines; Gas turbines; Hydraulic
Transistor amplifiers turbines; Kaplan turbines; Pump turbines;
excitation systems Reversible pump-turbines; Rim generator turbines;
voltage regulation, 523 Steam turbines; Straflo turbines; Tubular turbines)
Tripping {see also Electrical tripping) governors
governor valve relays, 145 feedpumps, 156
operator facilities high pressure
turbine protection, 171 wet steam, 226
Trips {see also Category A trips; Category B trips; Overspeed instrumentation, 172-175
trips) wet steam, 226-240
mechanically operated Turning gear
turbine protection, 170 electrial
Tube bundles steam turbines, 111
feedwater heaters jacking oil pumps, 186
flow, 293 steam turbines, 105-112
high pressure feedwater heaters, 292 Two-shift regime
low pressure feedwater heaters, 310 steam turbines, 216
Tube support plates Two-shifting
feedwater heaters, 295 steam turbines, 217
Tube turbines, 430
Tubenests Ultrasonics
condensers, 362 cooling water
arrangement, 352 leakage, 369, 370
future developments, 377 Unbalanced phase conditions
high pressure drop, 352 generators, 538
high pressure drop before, 352 Underslung condensers, 4
steam flow approach patterns, 352 Unit ratings
thermal performance, 350 steam turbines
geometry future prospects, 120
condenser design evaluation, 350 Unit sizes
Tubeplates steam turbines
condenser shells future prospects, 120
joints, 363 Unloading gear, 130
condensers, 362 exhaust pressure, 130
manufacture, 362 Upper control level
thermal performance, 350 governors, 141
tube joints, 363
water headers Vacuum degassing
thickness, 263 rotors
Tubes materials, 94
condensers Valve actuators
cleanliness, 375 boiler feed pumps
fireside corrosion light load protection, 414
feedwater de-aeration, 49 Valve servo amplifiers, 137
waterside corrosion Valves {see also Butterfly valves; By-pass valves; Control
feedwater de-aeration, 49 valves; Draft tube valves; Drain valves; Emergency
Tubing trip valves; Governor valves; Isolating valves; Main
condensers inlet valves; Non-return valves; Pressure control
advanced geometry, 377 valves; Release valves; Relief valves; Servo valves;
roped, 377 Spraywater control valves; Steam chest valves;
thermal performance, 377 Steam valves; Stop valves; Turbine valves)
titanium, 379 governing systems
Tubular turbines, 428 on-load testing, 132
bulb, 428 low pressure feedwater heating systems, 288
Tuning pump-turbines, 439
foundations, 176 reheaters
Turbine exhaust pressures pressure loss, 27
assessment, 328 spurious opening, 135

579
Subject Index

Ventilation dished end thicknesses, 311


stators, 479 shell thicknesses, 311
Vibration wall thicknesses, 311
blades Water heaters
control, 73, 75 drum-type
sources, 73 feedwater heating systems, 304
emergency stop Water pressure
turbine protection, 172 instrumentation
flow-induced efficiency, 174
feedwater heaters, 296 Water temperatures
generators instrumentation
instrumentation, 550 efficiency, 174
journal bearings, 107 Water treatment
protection, 164 feedwater heating systems, 315-317
rotors, 470 Water washing
alignment, 103 condensers
balancing, 97 cleaning, 373
shafts Waterboxes
instrumentation, 174 low pressure feedwater heaters
steam turbines openings, compensations, 311
run-up, 133 transverse underslung condensers, 362
Viscosity index improvers Waterside corrosion
lubricating oils, 194 boiler tubes
Voltage measurement feedwater de-aeration, 49
excitation systems, 515 Watersprays
Voltage regulators {see also Automatic voltage regulators) casings
excitation systems, 523 steam turbines, 81
Voltages Wedges
excitation systems, 517 rotors, 464
Welding
Water blading
blading chromium steels, 72
protection, 164 Wet steam cycle, 33
demineralised feedheating, 46
stator winding cooling systems, 500 Wet steam plant
ingress by-pass systems, 64
by-pass systems, 216 pressurised water reactors, 62
steam turbines, 255 Wetness loss
turbine lubricating oils, 194 steam turbines, 16
stator winding cooling, 485 efficiency, 13
steam turbines, 165 Wheel chamber tests
Water-cooled reactors blades
steam turbines vibration, 74
sizes, 122 Willans line
Water cooling 660 MW unit, 24
generators, 558 Wind generators, 562
stators Windings
windings, 500,501 rotors, 459,463
Water cooling systems earth fault indication, 553
stator windings main exciters, 508
turbine generators, 505 slip-stick, 544
Water extraction temperature measurement, 466
steam voltage, 548
turbines, 229 stators, 477
Water headers 660 MW, 486
conventional hemispherical cooling, 485
manufacture, 262 earth faults, 554
feedwater heaters generators, 546
branch thickness, 294 insulation, 548
dished end thickness, 294 main exciters, 508
openings, thickness compensation, 294 water analysis, 553
shell thickness, 294 water cooling systems, 488, 500,501
wall thickness, 294 three-phase, 454
high pressure feedwater heaters, 292
low pressure feedwater heaters, 310 Zigzag spool rods
branch thicknesses, 311 blades, 68

580

Das könnte Ihnen auch gefallen