Sie sind auf Seite 1von 57

Edge Lane West

Highway and Environmental Improvement Scheme


Bill Of Principal Quantities

CONTENTS

PREAMBLES

SERIES 100: PRELIMINARIES 100 / 1

SERIES 200: SITE CLEARANCE 200 / 2

SERIES 300: FENCING 300 / 1

SERIES 400: ROAD RESTRAINT SYSTEMS (VEHICLE & 400 / 1


PEDESTRIAN)

SERIES 500: DRAINAGE & SERVICE DUCTS 500 / 1

SERIES 600: EARTHWORKS 600 / 1

SERIES 700: PAVEMENTS 700 / 1

SERIES 1100: KERBS, FOOTWAYS & PAVED AREAS 1100 / 1

SERIES 1200: TRAFFIC SIGNS & ROAD MARKINGS 1200 / 1

SERIES 1300: ROAD LIGHTING COLUMNS & BRACKETS,


CCTV MASTS & CANTILEVER MASTS 1300 / 1

SERIES 1400: ELECTRICAL WORK FOR ROAD LIGHTING &


TRAFFIC SIGNS 1400 / 1

SERIES 1700: STRUCTURAL CONCRETE 1700 / 1

SERIES 2700: ACCOMMODATION WORKS, WORKS FOR


STATUTORY UNDERTAKERS, PROVISIONAL SUMS & PRIME
COST ITEMS 2700 / 1

SERIES 3000: LANDSCAPE & ECOLOGY 3000 / 1

GRAND SUMMARY G.S.

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities
Edge Lane West
Highway and Environmental Improvement Scheme
Preamble to Bill of Quantities

Preambles to Bill of Quantities

Project Specific Directions This bill of quantities has been prepared using the drawings, specification
and other relevant documentation referred to within the Tender. The detail of
the works proposed is likely to change as the design is finalised and
particularly during the Early Contractor Involvement (ECI) phase when the
contractors value engineering and buildability proposals may be
incorporated into the scheme. It is therefore anticipated that the section
totals may change accordingly up to award of the construction contract.
However, some items are likely to vary in quantity but only within reasonable
and acceptable limits. The rates and prices provided within this BQ are
therefore deemed to be sufficiently robust to cater for these changes and as
such will be used to compile the contract sum in accordance with Option B
(Firm Price) of the NEC Standard form incorporating bespoke amendments.

Reference within this Preamble and BQ to the Overseeing Organisation


shall mean the same as the Project Manager under the NEC Standard Form

Introduction of new BQ items will be priced, when appropriate, at rates


prorata to those provided within the Tender BQ. Where the work item is such
that tender rates are inappropriate then new rates will be agreed between
the contactor and the Employers Project Manager and/or his designated
representative.

Rates and Prices contained within this BQ are deemed to be sufficient to allow
for the works items described as Provisional or Provisional Sums to be
incorporated within the assumed project construction period of 18 months.

The contractor is required to price separately in the schedules provided in


Volume 0 Appendix I his fully inclusive site supervisory staff costs for:

(i) the main construction works


(ii) the defect correction/maintenance period
(iii) landscaping and aftercare period

The sum total of each of these sections should be carried forward to the Grand
summary page as indicated within this BQ.

The contractor should ensure no duplication of costs for supervisory staff


between the work items and Appendix I schedules.

When finalizing the rates and prices within this BQ the contractor should make
reference to the Project Risk Register contained within Volume 2 of the Tender
documentation. The contractor is required to insert his risk evaluation for those
items indicated as being contractor owned. The values should be derived in
accordance with the risk evaluation matrix provided and the summation of the
risks carried forward to the Grand Summary of the BQ.

The risk register will be subject to a further review during ECI Stage 1 when
mitigation proposals will be agreed to reduce/remove the risk.

Edge Lane West


Highway & Environmental Improvement Scheme
Preamble to Bill of Quantities; Volume 3 Rev 0
Edge Lane West
Highway and Environmental Improvement Scheme
Preamble to Bill of Quantities

General 1 The Bill of Quantities has been prepared in accordance with the Method of
Directions Measurement for Highway Works published by The Stationery Office as Section
1 of Volume 4 of the Manual of Contract Documents for Highway Works. The
relevant publication date of each page of the Method of Measurement for
Highway Works is given in the Schedule of Pages and Relevant Publication
Dates.

2 (05/01) In the Bill of Quantities the sub-headings and item descriptions identify
the work covered by the respective items, read in conjunction with the matters
listed against the relevant marginal headings Item coverage in Chapter IV of
the Method of Measurement for Highway Works, these Preambles and the
amendments to the Method of Measurement immediately following these
Preambles. The nature and extent of the work is to be ascertained by reference
to the Drawings, Specification and Conditions of Contract. The rates and prices
entered in the Bill of Quantities shall be deemed to be the full inclusive value of
the work covered by the several items including the following, unless expressly
stated otherwise:

(i) Labour and costs in connection therewith.

(ii) The supply of materials, goods, storage and costs in connection


therewith including delivery to Site. Taking delivery of materials and
goods supplied by others, unloading, storage, and costs in connection
therewith.

(iii) Plant and costs in connection therewith.

(iv) Fixing, erecting and installing or placing of materials and goods in


position.

(v) Temporary Works.

(vi) The effect on the phasing of the Works or any element of the Works
to the extent set forth or reasonably implied in the documents on
which the tender is based.

(vii) General obligations, liabilities and risks involved in the execution of


the Works set forth or reasonably implied in the documents on which
the tender is based.

(viii) Establishment charges, overheads and profit.

(ix) Waste.

(x) Testing carried out by the Contractor in accordance with the particular
requirements of Appendix 1/5 including supplying results of tests,
reports and certificates.

(xi) Supply and delivery of samples to the Overseeing Organisation in


accordance with the particular requirements of Appendix 1/6.

(xii) Checking, inspecting, examining, measuring and verifying goods,


materials and workmanship including supplying results, reports and

Edge Lane West


Highway & Environmental Improvement Scheme
Preamble to Bill of Quantities; Volume 3 Rev 0
Edge Lane West
Highway and Environmental Improvement Scheme
Preamble to Bill of Quantities

certificates.

(xiii) Attendance and transport for sampling and testing carried out by the
Overseeing Organisation.

(xiv) Complying with Quality Assurance requirements of the contract and


providing certificates of conformity.

(xv) Preparation and supply of detailed working drawings.

(xvi) Awaiting approvals and consent.

(xvii) Where stipulated complying with the particular requirements of


Appendix 1/24.

Measurement 3 (i) The measurement of work shall be computed net from the
dimensions stated in the Contract unless otherwise stated in the
Method of Measurement.

(ii) (11/06) Where the tender documents specify the Type of Pavement to
be constructed then the measurement of work shall be based upon
the thinnest pavement construction and surfacing over structures
permitted by the Contract for that Type of Pavement. Where the
tender documents provide for the Contractor to select the type of
safety barrier, pavement or buried structure (where the structure is
not within Designated Outlines) to be constructed then the
measurement of all work in each area so affected shall be based
upon the thinnest pavement construction and surfacing over
structures permitted by the Contract in that area for the particular
type of safety barrier, pavement or buried structure the Contractor
has elected to construct.

Pricing of Items 4 Each individual item shall have a rate or price entered against it. Rates and
prices shall be expressed to two decimal places.

Alternative 5 Where in the Contract a choice of alternatives is permitted:


Specified
Materials, (i) the description billed and the rates and prices inserted shall be
Designs and deemed to cover any of the permitted alternative materials or designs
Options within the Contractor may elect to use;
Types of
Pavement (ii) and where separate Bills of Quantities are provided within Series
600: Earthworks for each Type of Pavement permitted by the
Contract the rates and prices inserted in respect of the earthworks for
the particular Type of Pavement shall be deemed to cover the
earthworks for any inherent permitted option within the Type of
Pavement elected to be constructed by the Contractor;

(iii) and where separate Bills of Quantities are provided within Series
700: Pavements for each Type of Pavement permitted by the
Contract the rates and prices inserted in respect of the particular
Type of Pavement shall also be deemed to cover any inherent
permitted option within the Type of Pavement elected to be

Edge Lane West


Highway & Environmental Improvement Scheme
Preamble to Bill of Quantities; Volume 3 Rev 0
Edge Lane West
Highway and Environmental Improvement Scheme
Preamble to Bill of Quantities

constructed by the Contractor.

In all cases the rates and prices inserted in all Series of the Bill of Quantities
shall be deemed to include for any adjustments of work content, rates, costs
and the like occasioned by the choice of alternatives elected to be used or
constructed by the Contractor.

Privately and 6 The information in the Contract as to the whereabouts of existing services and
Publicly Owned mains is believed to be correct but the Contractor shall not be relieved thereby
Services or of his obligations under the Contract. The Contractor shall include in his rates
Supplies and prices for locating and taking measures for the support and full protection of
pipes, cables and other apparatus during the progress of the Works, obtaining
the written consent of the appropriate authority to interrupt the service or supply
and for keeping the Overseeing Organisation informed of all arrangements he
makes with the owners of privately owned services or supplies, Statutory
Undertakers and Public Authorities as appropriate.

Labours 7 Labours in connection with Nominated Sub-contractors shall include:

(i) in the case of work or services executed - for affording the use of existing
working space, access, temporary roads, erected scaffolding, working
shelters, staging, ladders, hoists, storage, latrines, messing, welfare and
other facilities existing on Site and the provision of protection, water,
electricity for lighting and clearing away rubbish and debris arising from
the work;

(ii) in the case of goods, materials or services supplied - for taking delivery,
unloading, storing, protecting and returning crates, cartons and packing
materials.

Roadworks 8 The Contractor shall allow in his rates and prices for complying with
Overall requirements in respect of pavement construction, horizontal alignments,
Requirements surface levels and surface regularity of pavement courses, dealing with changes
in weather conditions, use of surfaces by traffic and construction plant, and
general requirements for sub-bases and road bases.

Work within and 9 Not required.


below non-tidal
open water or
tidal water

Dealing with 10 Not required.


Flow

Reimbursement 11 The Contractor will be reimbursed the actual price paid by the Contractor in
of Fees, Rates, respect of:
Taxes and
Overseeing (i) fees, rates and taxes - the sums certified as properly repayable to the
Organisations Contractor in accordance with the Contract;
Telephone Calls
Any other cost, charge or expense in respect of these items shall be allowed for
in the rates and prices for temporary accommodation.

Site Limitations 12 The Contractor shall allow in his rates and prices for complying with any

Edge Lane West


Highway & Environmental Improvement Scheme
Preamble to Bill of Quantities; Volume 3 Rev 0
Edge Lane West
Highway and Environmental Improvement Scheme
Preamble to Bill of Quantities

and Constraints limitations and constraints on the use of the Site.

Hard Material 13 For the purposes of the Contract the following are designated as Hard Material
in accordance with Chapter 1 Definitions, paragraph 1(h)(i):

(a) .......* strata;

(b) those deposits designated by limits shown on the Drawings;

(c) existing pavements, footways, paved areas (but excluding unbound


materials) and foundations in masses in excess of 0.20 cubic metres.

Equivalent 14 Where the Contractor offers an equivalent product or material in place of the
Products and one identified or specified, then the rates and prices in the Bill of Quantities shall
Materials be deemed to include for all the obligations and costs associated with the
incorporation of the equivalent into the Works, including design, provision of
data and drawings, certificates, awaiting acceptance, resubmissions and
modifications and amendments to the Works.

Unless specifically stated to the contrary in the Contract the measurement of the
Works affected by the incorporation of the equivalent products and materials
shall be based on the Tender documents and not on the Works as amended and
completed to incorporate the equivalent products and materials.

Permanent 15 (05/01) Where the Contract requires part(s) of the Permanent Works to be
Works Designed designed by the Contractor, the rates and prices in the Bill of Quantities shall
by the include for all the obligations and costs associated with the incorporation of the
Contractor Contractors design into the Works, including design, provision of data and
drawings, certificates, awaiting approvals, resubmissions and modifications and
amendments to the Works.

Additionally the rates and prices in the Bill of Quantities shall include for the
costs of all testing and sampling to be carried out by the Contractor in respect of
workmanship, goods and materials incorporated into the Works or to prove the
Contractors design.

Structures 16 In respect of each priced Bill of Quantities comprising a single item for a
Designed by the structure designed by the Contractor, the Contractor shall prepare a priced
Contractor schedule of quantities. This priced schedule shall be prepared in accordance
with the relevant Chapters and Series of the Method of Measurement and
submitted to the Overseeing Organisation.

The quantities, rates and prices in the priced schedule of quantities shall in each
case, when extended and totalled, give the amount entered in the priced Bill of
Quantities against the item for the relevant structure designed by the Contractor.

The priced schedule of quantities shall only be used for Payment Applications
and for the valuation of variations ordered under the Contract in connection with
structures designed by the Contractor.

Edge Lane West


Highway & Environmental Improvement Scheme
Preamble to Bill of Quantities; Volume 3 Rev 0
Edge Lane West
Highway and Environmental Improvement Scheme
Preamble to Bill of Quantities

Unless specifically stated to the contrary in the Contract the measurement of the
Works affected by the incorporation of the Contractors design shall be based on
the Tender documents and not on the Works as amended and completed to
incorporate the Contractors design.
The parts of the Works included by the Contractor in the priced schedule of
quantities shall include all the parts of the Works within the Designated Outline
except those designed and scheduled by the Overseeing Organisation as not to
be included.

National 17 Where a paragraph in Chapter IV of the Method of Measurement for Highway


Alterations for Works (Units and Methods of Measurement) or in the Notes for Guidance on the
The Overseeing Method of Measurement for Highway Works or in the Library of Standard Item
Organisations of Descriptions for Highway Works is prefixed by # this indicates that this particular
Scotland, Wales paragraph has a National Alteration for one or more of the Overseeing
and Northern Organisations of Scotland, Wales or Northern Ireland. The use of national
Ireland paragraphs is permitted only within the countries to which they specifically apply
and they are deemed to replace corresponding paragraphs in the main body of
Chapter IV of the Method of Measurement for Highway Works (Units and
Methods of Measurement) or in the Notes for Guidance on the Method of
Measurement for Highway Works or in the Library of Standard Item Descriptions
for Highway Works as appropriate. The National paragraphs correspond to the
particular requirements of the National Alterations for the Overseeing
Organisations of Scotland, Wales or Northern Ireland contained in Volume 1 of
the Manual of Contract Documents for Highway Works. The substitute or
additional paragraphs are located at the end of the relevant Series.

Testing 18 (05/01) Testing as paragraph 2(x) above, is in respect of tests to be carried out
by the Contractor to verify workmanship, goods and materials incorporated into
the permanent works and testing of the permanent works in order to prove the
Overseeing Organisations design as set out in Appendix 1/5.

Checking, inspecting, examining, measuring and verifying goods, materials and


workmanship incorporated in the permanent works, as paragraph 2(xii) above, is
in respect of other operations set forth or reasonably implied in the Contract to
be carried out by the Contractor to demonstrate compliance with the particular
requirements of the Contract, or to prove the Overseeing Organisations design
where not separately listed in Appendix 1/5, but excluding trial erection of
structural steelwork which shall be measured separately in accordance with
Series 1800.

Procedural trials, trial panels and trial areas required to be carried out or
constructed as separate operations in advance of the permanent works in order
to verify goods, materials and workmanship shall not be measured separately
but are included within the item coverage for the relevant Series.

Testing of existing structures and other investigative works shall be individually


measured within the relevant Series.

Landscape and 19 (05/01) The rates and prices inserted in the Bill of Quantities for new Planting,
Ecology Seeding and Turfing measured in accordance with Volume 4 - Series 3000
include for all post-planting maintenance work required to be carried out in
accordance with the Specification and the relevant Appendices.

Edge Lane West


Highway & Environmental Improvement Scheme
Preamble to Bill of Quantities; Volume 3 Rev 0
Edge Lane West
Highway and Environmental Improvement Scheme
Preamble to Bill of Quantities

In order to properly reflect the scope and duration of the planting and post-
planting requirements a series of staged payments for the various items of
planting, seeding and turfing will be made in accordance with the Staged
Payments Schedule.

The Staged Payments Schedule is to be inserted in the Bill of Quantities


immediately preceding the collection page for Landscape and Ecology and shall
be used for assessing payments due to the Contractor in accordance with the
Contract.

Amendments to (05/01) For the purposes of the Contract the Method of Measurement for
the Method of Highway Works is amended in accordance with the pages immediately following.
Measurement
(05/01)

Edge Lane West


Highway & Environmental Improvement Scheme
Preamble to Bill of Quantities; Volume 3 Rev 0
Edge Lane West
Highway and Environmental Improvement Scheme
Preamble to Bill of Quantities

Method of Measurement for Highway


Works
Schedule of Pages and Relevant Publication
Dates
Chapter/Series Page Number Publication Date
Contents 1 November 2004
2 May 2005
3 November 2004
4 to 7 inclusive May 2005
1 to 3 inclusive March 1998
Chapter I 1 March 1998
Chapter II 2 May 2001
1 March 1998
Chapter III 2 May 2001
3 to 12 May 2004
13 November 2006
14 to 16 inclusive May 2005
17 to 19 inclusive November 2006
1 March 1998
1 to 2 inclusive March 1998
3 to 7 inclusive May 2001
Chapter IV 8 November 2004
100 9 to 11 inclusive May 2001
12 November 2004
13 to 15 inclusive May 2001
1 May 2001
2 to 3 inclusive May 2004
4 May 2001
1 to 5 inclusive May 2001
1 to 2 and 4 to 8 inclusive November 2004
200 3 November 2006
1 to 5 inclusive May 2001
6 November 2004
7 to 13 inclusive May 2001
300 14 May 2005
400 15 May 2001
16 to 17 inclusive May 2005
18 May 2001
500 19 November 2003
1 May 2002
2 May 2001
3 March 1998
4 to 11 inclusive November 2004
12 May 2002
13 to 14 inclusive November 2004
15 to 38 inclusive May 2001
N1 to N3 inclusive May 2002

600

Edge Lane West


Highway & Environmental Improvement Scheme
Preamble to Bill of Quantities; Volume 3 Rev 0
Edge Lane West
Highway and Environmental Improvement Scheme
Preamble to Bill of Quantities

700 1 May 2001


2 May 2002
3 May 2001
4 to 5 inclusive May 2002
6 May 2001
7 to 9 inclusive May 2002
10 May 2001
11 May 2002
12 to 13 inclusive May 2001
14 May 2002
15 to 18 inclusive May 2001
)
) Not taken up
)
800 1
900 2
1000 3 May 2001
1100 4 to 5 inclusive November 2004
6 May 2001
7 to 8 inclusive May 2002
1 to 2 inclusive May 2001
3 to 5 inclusive May 2005
6 to 11 inclusive May 2001
1 to 3 inclusive March 1998
1 to 2 inclusive May 2001
1200 3 November 2003
4 to 8 inclusive May 2001
9 May 2005
1 to 2 inclusive May 2001
1300 3 May 2005
1400 4 to 7 inclusive May 2001
8 to 12 inclusive May 2005
1 to 2 inclusive February 2003
3 to 6 inclusive May 2001
7 March 1998
1500 8 to 19 inclusive May 2001
1 March 1998
2 May 2001
3 May 2004
4 to 11 inclusive May 2001
1600 1 May 2004
2 to 5 inclusive May 2001
1 March 1998
1 May 2001
2 to 3 inclusive May 2003
1700 1 May 2002
Not taken up May 2001
1 to 3 inclusive March 1998
May 2004
1800 March 1998

Edge Lane West


Highway & Environmental Improvement Scheme
Preamble to Bill of Quantities; Volume 3 Rev 0
Edge Lane West
Highway and Environmental Improvement Scheme
Preamble to Bill of Quantities

Chapter/Series Page Number Publication Date


2400 1 to 3 inclusive May 2001
4 March 1998
2500 1 to 2 inclusive May 2001
2600 Not taken up
2700 1 May 2001
3000 1 to 15 inclusive May 2001
5000 1 to 2 inclusive May 2003

Edge Lane West


Highway & Environmental Improvement Scheme
Preamble to Bill of Quantities; Volume 3 Rev 0
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 100: PRELIMINARIES

Temporary Accommodation

1.01 Erection of offices for the Overseeing item 1 -


Organisation until completion of the works

1.02 Erection of offices and messes for the item 1 -


Contractor until completion of the works

1.03 Erection of stores and workshops for the item 1 -


Contractor until completion of the works

1.04 Servicing of offices for the Overseeing item 1 -


Organisation until completion of the works

1.05 Servicing of offices and messes for the item 1 -


Contractor until completion of the works

1.06 Servicing of stores and workshops for the item 1 -


Contractor until completion of the works

1.07 Dismantling of offices for the Overseeing item 1 -


Organisation until completion of the works

1.08 Dismantling of offices and messes for the item 1 -


Contractor until completion of the works

1.09 Dismantling of stores and workshops for the item 1 -


Contractor until completion of the works

Communication System for the Overseeing


Organisation

1.10 Communication System for the Overseeing item 1 -


Organisation as Appendix 1/3 of the
Specification

Page Total carried forward to Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 100 / 1
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 100: PRELIMINARIES - continued

Information Board

1.11 Project information board as Appendix 1/21 of no. 2 -


the Specification

Traffic Safety and Management

1.12 Traffic safety and management item 1 -

1.13 Traffic safety and management for landscape item 1 -


and aftercare period

Progress Photographs

1.14 Progress photographs; as Appendix 1/22 of item 1 -


Specification

Supervisory Staff

1.15 Contractor's Supervisory Staff for the duration item 1 -


of the Main Construction Works

1.16 Contractor's Supervisory Staff for the duration item 1 -


of the Defects Correction / Maintenance Period

1.17 Contractor's Supervisory Staff for the duration item 1 -


of the Landscaping and Aftercare Period

Page Total carried forward to Summary -


Edge Lane West
Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 100 / 2
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 100: PRELIMINARIES - continued

Summary

100 / 1 -
100 / 2 -

Page Total carried forward to Grand Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 100 / 3
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 200: SITE CLEARANCE

Take Up or Down and Set Aside for Re-use


or Remove to Store or Tip off Site

2.01 Take up PCC kerbs and remove off site m 2037 -

2.02 Take up pedestrian guardrail and remove to m 13 -


Newton Road Depot

2.03 Take up existing granite kerbs and remove to m 240 -


Newton Road Depot

2.04 Take down and set aside 250mm wide; 1.8m m 40 -


high stone wall next to property No.115

2.05 Demolish 250mm wide; 1.8m high brick wall m 57 -


and metal fence and cart to tip

2.06 Take down 2m high stone wall and set aside m 28 -


for property No. 115. Metal fence and 4 No.
gates take down and remove to Newton Road
Depot

2.07 Take down 1.3m high stone wall and set aside m 38 -
for property No. 115. Metal fence take down
and remove to Newton Road Depot

2.08 Take up PCC flags and remove off site m 5260 -

2.09 Take up PCC Tactiles and remove off site m 27 -

2.10 Take up granite setts and remove to Newton m 27 -


Road Depot

2.11 Take up block paving and remove off site m 50 -

2.12 Disconnect Lamp Column and remove to no. 22 -


Newton Road Depot

2.13 Disconnect Traffic Signal, remove lamps and no. 6 -


pole to Newton Rd Depot

2.14 Take up PCC bollard and remove off site no. 9 -

2.15 Take down traffic sign and pole and remove to no. 8 -
Newton Road Depot

Page Total carried forward to Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 200 / 1
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 200: SITE CLEARANCE - continued

Take Up or Down and Set Aside for Re-use


or Remove to Store or Tip off Site -
continued

2.16 Disconnect and take down illuminated sign and no. 1 -


pole and remove to Newton Road Depot

2.17 Demolish 3.2m high brick wall and cart to tip m 40 -

2.18 Demolish 2.9m high brick wall and cart to tip m 24 -

2.19 Demolish 2m high brick wall and cart to tip m 25 -

2.20 Take down and re-use pallisade fence. Re-use m 435 -


as part of relocated school boundary treatment

2.21 Demolish assumed 2m high 140mm thick m 4 -


concrete block wall and cart to tip

2.22 Demolish assumed 2m high 150mm thick m 12 -


concrete retaining wall and cart to tip

2.23 Remove corrugated steel fence to Newton m 68 -


Road Depot

2.24 Remove iron post and rail fence to Newton m 23 -


Road Depot

2.25 Demolish assumed 2.8m high 200mm thick m 6 -


stone wall and cart to tip

2.26 Remove existing tarmac footway and cart to tip m 723 -

2.27 Remove and set aside for re-use concrete pin m 309 -
kerbs as part of re-aligned pallisade fencing for
school

2.28 Existing traffic signal controller to be removed no. 3 -


to 2020 Traffic Systems Workshop, Boaler St

2.29 Existing Haldo pillar to be removed off site no. 2 -


once mains supply has been disconnected

2.30 Existing traffic signal equipment to be removed no. 10 -


and cart to tip; incl 3m of existing cabling

Page Total carried forward to Summary -


Edge Lane West
Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 200 / 2
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 200: SITE CLEARANCE - continued

Take Up or Down and Set Aside for Re-use


or Remove to Store or Tip off Site -
continued

2.31 Existing Pedestrian studs to be removed m 22 -

2.32 Existing Stopline demarcation to be removed m 14 -

2.33 Existing Zig Zag demarcation lines to be m 160 -


removed

2.34 Existing dropped kerbs to be removed off site m 12 -

2.35 Existing lighting column to be removed and no. 43 -


stored at Newton Road Depot

2.36 Existing illuminated bollard to be removed and no. 5 -


stored at Newton Road Depot

2.37 Existing illuminated traffic sign to be removed no. 19 -


and stored at Newton Road Depot

2.38 Existing 6m column to relocated no. 2 -

2.39 Existing 8m column to relocated no. 19 -

2.40 Existing WATC No. 1 Cabinet to be removed no. 2 -


off site

2.41 Existing Pavement Boxes to be removed off no. 14 -


site

2.42 Take up cover and frame to drainage gully and no. 37 -


dispose off site

2.43 Take up, including cutting out, redundant tram m 800 -


track and dispose off site

Page Total carried forward to Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 200 / 3
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 200: SITE CLEARANCE - continued

Demolition of Individual or Groups of


Buildings or Structures

Demolition in connection with Highways


Works - The following works are to be
carried out in accordance with the
Demolition Specification. Location as
drawing 000041/ELW/200/05/02

2.44 Demolish Block A in accordance with Clause item 1 -


270AR and Appendix 2/1 of the Specification

2.45 Demolish Block B in accordance with Clause item 1 -


270AR and Appendix 2/1 of the Specification

2.46 Demolish Block C in accordance with Clause item 1 -


270AR and Appendix 2/1 of the Specification

2.47 Demolish Block D in accordance with Clause item 1 -


270AR and Appendix 2/1 of the Specification

2.48 Demolish Block E in accordance with Clause item 1 -


270AR and Appendix 2/1 of the Specification

2.49 Demolish Block F in accordance with Clause item 1 -


270AR and Appendix 2/1 of the Specification

2.50 Demolish Block G in accordance with Clause item 1 -


270AR and Appendix 2/1 of the Specification

2.51 Demolish Block H in accordance with Clause item 1 -


270AR and Appendix 2/1 of the Specification

2.52 Demolish Block I in accordance with Clause item 1 -


270AR and Appendix 2/1 of the Specification

2.53 Demolish Block O in accordance with Clause item 1 -


270AR and Appendix 2/1 of the Specification

Page Total carried forward to Summary -


Edge Lane West
Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 200 / 4
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 200: SITE CLEARANCE - continued

Summary

200 / 1 -
200 / 2 -
200 / 3 -
200 / 4 -

Page Total carried forward to Grand Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 200 / 5
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 300: FENCING

Fencing, Gates and Stiles

3.01 Weld mesh fencing 2m above ground; all as m 810 -


Appendix 3/1 to the specification and drawing
reference 000041/ELW/300/01

3.02 Access gate within weld mesh fencing; all as no. 3 -


Appendix 3/1 to the specification and drawing
reference 000041/ELW/300/01

3.03 Steel hoop fencing; all as Appendix 3/1 to the m 1165 -


specification and drawing reference
000041/ELW/300/01

3.04 Steel hoop detachable fencing; all as Appendix no. 10 -


3/1 to the specification and drawing reference
000041/ELW/300/01

3.05 Relocate alley gate; all as Appendix 3/1 to the no. 1 -


specification and drawing reference
000041/ELW/300/01

Page Total carried forward to Grand Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 300 / 1
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 400: ROAD RESTRAINT SYSTEMS


(VEHICLE & PEDESTRIAN)

Pedestrian Parapets and Pedestrian


Guardrails

4.01 Pedestrian Guardrails all as shown on drawing m 5 -


00041/ELW/400/01 and as Appendix 4/1 of the
Specification; in 0.5m panels

4.02 Pedestrian Guardrails all as shown on drawing m 15 -


00041/ELW/400/01 and as Appendix 4/1 of the
Specification; in 1.0m panels

4.03 Pedestrian Guardrails all as shown on drawing m 142 -


00041/ELW/400/01 and as Appendix 4/1 of the
Specification; in 2.0m panels

Page Total carried forward to Grand Summary

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 400 / 1
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 500: DRAINAGE & SERVICE DUCTS

Drains and Service Ducts (excluding Filter


Drains, Narrow Filter Drains and Fin Drains)

5.01 150mm internal diameter pipe in pvc-u or equal m 682 -


and approved on bed Type Z in trench, depth
to invert not exceeding 2m, average depth to
invert 1.09m

5.02 225mm internal diameter pipe in vitrified clay or m 1032 -


equal and approved on bed Type S in trench,
depth to invert not exceeding 2m, average
depth to invert 1.64m

5.03 225mm internal diameter pipe in vitrified clay or m 128 -


equal and approved on bed Type S in trench,
depth to invert exceeding 2m but not exceeding
4m, average depth to invert 2.55m

5.04 300mm internal diameter vitrified clay extra m 149 -


strength drain on bed Type S in trench, depth
to invert not exceeding 2m, average depth to
invert 1.61m

5.05 300mm internal diameter vitrified clay extra m 11 -


strength drain on bed Type S in trench, depth
to invert exceeding 2m but not exceeding 4m,
average depth to invert 2.1m

Connections

5.06 Connection of 150mm diameter pipe to existing no. 3 -


150mm diameter drain or existing piped culvert,
depth to invert not exceeding 2m.

5.07 Connection of 225mm diameter pipe to existing no. 2 -


chamber; depth to invert not exceeding 2m

5.08 Connection of 225mm diameter pipe to existing no. 2 -


chamber; depth to invert exceeding 2m but not
exceeding 4m
5.09 Connection of 300mm diameter pipe to existing no. 1 -
chamber using standard dropshaft; depth to
invert exceeding 2m but not exceeding 4m

Page Total carried forward to Summary -


Edge Lane West
Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 500 / 1
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 500: DRAINAGE & SERVICE DUCTS -


continued

Chamber and Gullies

5.10 Precast concrete trapped gully Type G1, with no. 131 -
Class D400 captive hinge cover and frame as
per drawing 000041/ELW/500/03

5.11 Chamber 1200mm internal diameter with class no. 23 -


D400 cover and frame depth to invert
exceeding 1m but not exceeding 2m

5.12 Chamber 1200mm internal diameter with class no. 1 -


D400 cover and frame depth to invert
exceeding 2m but not exceeding 3m

5.13 Chamber 1200mm internal diameter with class no. 1 -


D400 cover and frame; depth to invert
exceeding 1m but not exceeding 2m;
incorporating dropshaft

5.14 Chamber 1200mm internal diameter with class no. 1 -


D400 cover and frame; depth to invert
exceeding 2m but not exceeding 3m;
incorporating dropshaft

5.15 Chamber 1200mm internal diameter with class no. 1 -


D400 cover and frame; depth to invert
exceeding 3m but not exceeding 4m; on
existing drain run incorporating dropshaft

5.16 Chamber 1200mm internal diameter with class no. 1 -


D400 cover and frame depth to invert
exceeding 3m but not exceeding 4m; on
existing drain run incorporating two dropshafts

5.17 Chamber 1200mm internal diameter with class no. 1 -


D400 cover and frame; depth to invert
exceeding 4m but not exceeding 5m; on
existing drain run incorporating dropshaft

5.18 Chamber 1200mm internal diameter with class no. 1 -


D400 cover and frame depth to invert
exceeding 4m but not exceeding 5m; on
existing drain run incorporating two dropshafts

Soft Spots and Other Voids

5.19 Excavation of soft spots and other voids in m 250 -


bottom of trenches, chambers and gullies.

Page Total carried forward to Summary -


Edge Lane West
Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 500 / 2
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 500: DRAINAGE & SERVICE DUCTS -


continued

Soft Spots and Other Voids - continued

5.20 Filling of soft spots and other voids in bottom of m 250 -


trenches, chambers and gullies with acceptable
material class 6F1.

Renewal, Raising or Lowering of Covers


and Gratings on Existing Chambers and
Gullies

5.21 Renewal of existing manhole cover and frame no. 15 -


on precast concrete chamber 1200mm
diameter with class D400 cover and frame

5.22 Raising the level of existing manhole cover and no. 20 -


frame on precast concrete chamber 1200mm
diameter with class D400 cover and frame; not
exceeding 150mm

5.23 Raising the level of existing manhole cover and no. 10 -


frame on precast concrete chamber 1200mm
diameter with class D400 cover and frame;
exceeding 150mm but not exceeding 300mm

Grouting Up of Existing Drains and Service


Ducts

5.24 Grouting up of existing drains, 150mm diameter m 40 -


grouting with 1:10 cement/PFA

5.25 Grouting up existing gullies; grouting with 1:10 no. 37 -


cement/PFA

Excavation in Hard Material

5.26 Extra over excavation for excavation in Hard m 250 -


Material in drainage

Cleaning Existing Drainage System

5.27 Cleaning of existing piped drainage system m 1000 -


300mm diameter

5.28 Cleaning of existing access chambers nr 25 -

Page Total carried forward to Summary -


Edge Lane West
Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 500 / 3
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 500: DRAINAGE & SERVICE DUCTS -


continued

Summary

500 / 1 -
500 / 2 -
500 / 3 -

Page Total carried forward to Grand Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 500 / 4
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 600: EARTHWORKS

Excavation

6.01 Excavation of unacceptable material Class U1A m 9030 -


in cutting and other excavation 0m to 3m in
depth.

6.02 Excavation of unacceptable material Class U1B m 250 -


in cutting and other excavation 0m to 3m in
depth.

Excavation in Hard Material

6.03 Extra over excavation for excavtion in Hard m 3712 -


Material in cutting and other excavation.

Deposition of Fill

6.04 Deposition of imported acceptable material; m 2681 -


6F1

Disposal of Material

6.05 Disposal of unacceptable material Class U1A m 9530 -


off site.

6.06 Disposal of unacceptable material Class U1B m 250 -


off site.

6.07 Disposal of tram track m 800 -

Imported Fill

6.08 Imported acceptable material; 6F1 capping m 2931 -


layer

Compaction of Fill

6.09 Compaction of accepted material; 6F1 capping m 2681 -


layer

Page Total carried forward to Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 600 / 1
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 600: EARTHWORKS - continued

Soft Spots and Other Voids

6.10 Excavation of soft spots and other voids. m 250 -

6.11 Filling of soft spots and other voids. m 250 -

Completion of Formation

6.12 Completion of Formation m 7660 -

Page Total carried forward to Summary -


Edge Lane West
Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 600 / 2
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 600: EARTHWORKS - continued

Summary

600 / 1 -
600 / 2 -

Page Total carried forward to Grand Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 600 / 3
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 700: PAVEMENTS

Sub-base

7.01 Type 1 sub-base to Clause 803 in carriageway. m


3 1768 -
Minimum CBR = 30%

7.02 ST4 concrete sub-base in carriageway to m


3 49 -
clause 1030

Pavement

7.03 Dense bitumen macadam base 230mm thick in m2 7660 -


carriageway to Clause 929

7.04 Dense bitumen macadam binder course 65mm m2 8219 -


thick in carriageway to Clause 929

7.05 Thin surface course 35mm thick in carriageway m2 16343 -


to Clause 942.

Regulating Course

7.06 Dense bitumen macadam binder course as m


3 769 -
regulating course in carriageway

7.07 Dense bitumen macadam base course as m3 69 -


regulating course minimum 80mm in
carriageway

Surface Treatment

7.08 Epoxy resin binder high friction surfacing buff m2 3995 -


colour in carriageway to clause 924

7.09 Epoxy resin binder high friction surfacing grey m2 273 -


colour in carriageway to clause 924

7.10 Epoxy resin binder high friction surfacing red m2 101 -


colour in carriageway to clause 924

7.11 Epoxy resin binder high friction surfacing red m 140 -


colour in carriageway to clause 924; at bus
stops

Page Total carried forward to Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 700 / 1
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 700: PAVEMENTS - Continued

Tack Coat

7.12 Bituminous spray as appendix 7/4 of the m


2 8585 -
specification; at a rate of 0.4 -0.6 litre per
square metre

Cold Milling

7.13 Milling Pavement 35mm depth. m2 1270 -

7.14 Milling Pavement 100mm depth. m2 4915 -

Page Total carried forward to Summary -


Edge Lane West
Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 700 / 2
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 700: PAVEMENTS - Continued

Summary

700 / 1 -
700 / 2 -

Page Total carried forward to Grand Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 700 / 3
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 1100 : KERBS, FOOTWAYS AND


PAVED AREAS

Kerbs, Channels, Edgings

11.01 Granite kerbs Type A 300 x 200mm laid m 3715 -


straight or curved exceeding 12m radius on
150mm ST4 concrete to 100mm upstand

11.02 Granite kerbs Type A 300 x 200mm laid curved m 124 -


not exceeding 12m radius on 150mm ST4
concrete to 100mm upstand

11.03 Granite kerbs Type A 300 x 200mm laid curved no. 10 -


to complete circle 1.0m radius to base of
lighting column on 150mm ST4 concrete to
100mm upstand

11.04 Precast concrete kerbs Type B half battered m 522 -


125 x 255mm laid straight or curved exceeding
12m radius on 150mm ST4 bed and Haunch

11.05 Precast concrete kerbs Type B half battered m 17 -


125 x 255mm laid to curves not exceeding 12m
radius on 150mm ST4 bed and Haunch

11.06 Precast concrete Type C square topped edging m 928 -


150 x 50mm laid straight or curved exceeding
12m radius on 150mm ST4 concrete

11.07 Precast concrete Type C square topped edging m 67 -


150 x 50mm laid to curves not exceeding 12m
radius on 150mm ST4 concrete

11.08 Granite channel Type D 300 x 200mm laid m 251 -


straight or to curves exceeding 12m radius;
flush on 150mm ST4 concrete

11.09 Granite channel Type D 300 x 200mm laid to m 46 -


curves not exceeding 6m radius; flush on
150mm ST4 concrete

11.10 Granite channel Type D 300 x 200mm laid to m 30 -


curves not exceeding 3m radius; flush on
150mm ST4 concrete

Page Total carried forward to Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 1100 / 1
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 1100 : KERBS, FOOTWAYS AND


PAVED AREAS - continued

Kerbs, Channels, Edgings - continued


11.11 Precast concrete bullnose kerb Type E laid m 16 -
flush, upside down 125 x 150mm laid straight
or curved exceeding 12m radius on 150mm
ST4 concrete bed
11.12 Precast concrete bullnose kerb Type E laid m 1 -
flush, upside down 125 x 150mm laid to curves
not exceeding 12m radius on 150mm ST4
concrete bed
11.13 Granite "bus access" kerb on 150mm ST4 m 56 -
concrete

11.14 Granite transition kerb at bus access; in pairs; no. 4 -


laid straight or to curves exceeding 12m; on
150mm ST4 concrete
11.15 Granite transition kerbs; in pairs; laid straight or no. 3 -
to curves exceeding 12m radius; on 150mm
ST4 concrete
11.16 Granite transition kerbs; in pairs; 9.0m radius; no. 9 -
on 150mm ST4 concrete
11.17 Granite transition kerbs; in pairs; 6.0m radius; no. 4 -
on 150mm ST4 concrete

11.18 Granite transition kerbs; in pairs; 3.0m radius; no. 1 -


on 150mm ST4 concrete

11.19 Granite crossover kerb; in complete circle to no. 14 -


lighting column base; 1.0m radius; on 150mm
ST4 concrete

11.20 Granite crossover kerb; in pairs; 2m radius; on no. 1 -


150mm ST4 concrete

11.21 Granite crossover kerb; in pairs; 3m radius; on no. 9 -


150mm ST4 concrete

11.22 Granite crossover kerb; in pairs; 6m radius; on no. 3 -


150mm ST4 concrete

11.23 Granite quadrant 0.5m radius; on 150mm ST4 no. 4 -


concrete

Page Total carried forward to Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 1100 / 2
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 1100 : KERBS, FOOTWAYS AND


PAVED AREAS - continued

Footways and Paved Areas

11.24 Paved footway Type A comprising natural m2 10555 -


coloured PCC paving flags (600 x 450 wide x
63mm thick) on 25mm 3:1 full sand/cement
mortar bed on Type 2 granular material 75mm
thick. Surface sloping at 10 or less to the
horizontal.

11.25 Paved footway Type B comprising 450 x 450 x m2 183 -


70mm thick precast concrete red coloured
tactile blister paving on 25mm 3:1 sand /
cement full mortar bed on 100mm D.O.T. type
2 sub base, surface sloping at 10 or less to the
horizontal.

11.26 Paved footway Type C comprising 400 x 400 x m2 36 -


65mm thick precast concrete buff coloured
tactile blister paving on 25mm 3:1 sand /
cement full mortar bed on 100mm thick ST4
concrete sub base, surface sloping at 10 or
less to the horizontal.

11.27 Paved footway Type D comprising 200 x 100 x m2 20 -


63mm thick precast concrete red coloured
block paving on 50mm sand bedding on Type 2
granular material 75mm thick, surface sloping
at 10 or less to the horizontal.

11.28 Paved footway Type E comprising mild grey m2 966 -


granite G654 sawn and flamed paving 150 x
150 x 150mm thick on 50mm 3:1 sand/cement
full mortar bed on ST4 concrete 100mm thick,
surface sloping at 10 or less to the horizontal.

11.29 Paved footway Type E comprising mild grey no. 24 -


granite G654 sawn and flamed paving 150 x
150 x 150mm thick; to lighting column bases;
within 1.0m radius kerb (measured elsewhere)
on 50mm 3:1 sand/cement full mortar bed on
ST4 concrete 100mm thick, surface sloping at
10 or less to the horizontal.

Page Total carried forward to Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 1100 / 3
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 1100 : KERBS, FOOTWAYS AND


PAVED AREAS - continued

Footways and Paved Areas

11.30 Paved footway Type F comprising mild grey m2 343 -


granite G654 sawn and flamed paving 250 x
150 x 150mm thick on 15N/mm cement
aggregate bed on ST4 concrete 200mm thick,
surface sloping at 10 or less to the horizontal.

11.31 Paved footway Type G comprising 5mm thick m2 2585 -


resin bonded 1-3mm dark Chinese bauxite on
75mm of 14mm dense bitumen macadam
binder on 150mm Type 1 granular sub-base.

11.32 Install Silver grey 400 x 200 x 80mm, granite m


2 2847 -
paving slabs; joints to be 2-4mm filled with
sand to BS 7533 pt7; laid on 50mm compacted
sand to BS 7533 pt7; on terram 1000
membrane on top of 150mm Type 2 sub base

11.33 Install Type B Blister paving flags Poppy m2 36 -


granite 400 x 400 x 80mm laid on 40mm fine
bedding concrete on 40mm DBM layer on
150mm type 2 sub base

Page Total carried forward to Summary -


Edge Lane West
Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 1100 / 4
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 1100 : KERBS, FOOTWAYS AND


PAVED AREAS - continued

Summary

1100 / 1 -
1100 / 2 -
1100 / 3 -
1100 / 4 -

Page Total carried forward to Grand Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 1100 / 5
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 1200: TRAFFIC SIGNS & ROAD
MARKINGS

Permanent Traffic Signs


12.01 Supply and erect road sign Diag 545 in nr 2 -
accordance with the Traffic Signs Regulations
and General Direction 2002; illuminated
12.02 Supply and erect road sign Diag 602 in nr 5 -
accordance with the Traffic Signs Regulations
and General Direction 2002; illuminated
12.03 Supply and erect road sign Diag 606 in nr 2 -
accordance with the Traffic Signs Regulations
and General Direction 2002; illuminated

12.04 Supply and erect road sign Diag 608 in nr 2 -


accordance with the Traffic Signs Regulations
and General Direction 2002; illuminated

12.05 Supply and erect road sign Diag 616 in nr 5 -


accordance with the Traffic Signs Regulations
and General Direction 2002; illuminated

12.06 Supply and erect road sign Diag 639 in nr 24 -


accordance with the Traffic Signs Regulations
and General Direction 2002

12.07 Supply and erect road sign Diag 642.2A in nr 2 -


accordance with the Traffic Signs Regulations
and General Direction 2002; illuminated
12.08 Supply and erect road sign Diag 674 in nr 2 -
accordance with the Traffic Signs Regulations
and General Direction 2002; illuminated

12.09 Supply and erect road sign Diag 675 in nr 2 -


accordance with the Traffic Signs Regulations
and General Direction 2002; illuminated

12.10 Supply and erect road sign Diag 974 in nr 4 -


accordance with the Traffic Signs Regulations
and General Direction 2002

12.11 Standard 2.14m steel traffic signal pole; nr 43 -


external diameter of 115mm and a minimum
internal diameter of 100mm; steel thickness
shall be 3.2mm minimum

Page Total carried forward to Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 1200 / 1
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 1200: TRAFFIC SIGNS & ROAD


MARKINGS - continued

Road Markings

12.12 Intermittent 1.5m long white marking lines with m 251 -


1m gaps.
12.13 Intermittent 0.5m long white marking lines with m 174 -
2.5m gaps.

12.14 Intermittent 0.5m long white marking lines with m 166 -


0.5m gaps.

12.15 Continuous double yellow lines m 1532 -

12.16 Continuous single yellow line m 922 -

12.17 Intermittent 0.2m white give way lines with m 54 -


0.1m gaps

12.18 Continuous white 0.25m thick stop lines. m 103 -

12.19 Continuous zig zag 2m lines approaching road m 192 -


crossing; white marking

12.20 Solid hatched area which separates lanes; m2 208 -


contains chevrons of varying sizes. Refer to
drawing 000041/ELW/1200/01/01 A

12.21 30m continuous yellow line with 'School (No nr 1 -


Parking)' letter marking

12.22 Bicycle symbol in white line marking. Refer to nr 4 -


Diag. No 1001.2 on Drawing
000041/ELW/1200/03/01 B

12.23 8m Lane separation symbol (straight ahead nr 4 -


and right turn arrows) line markings. Refer to
drawing 000041/ELW/1200/01/01 A

12.24 4m straight ahead arrow symbol line markings. nr 8 -


Refer to drawing 000041/ELW/1200/01/01 A

12.25 4m straight ahead and left turn arrow symbol nr 9 -


line markings. Refer to drawing
000041/ELW/1200/01/01 A

12.26 4m right turn arrow symbol line markings. Refer nr 12 -


to drawing 000041/ELW/1200/01/01 A

Page Total carried forward to Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 1200 / 2
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 1200: TRAFFIC SIGNS & ROAD


MARKINGS - continued

Traffic Signal Installations

12.27 Permanent traffic signal installations at item 1 -


Marmaduke Street/ Jubilee Drive. Please refer
to drawing 000041/ELW/1200/02/04 Rev B.

12.28 Permanent traffic signal installations at Dorothy item 1 -


Street Puffin Crossing. Please refer to drawing
000041/ELW/1200/02/05 Rev A.

12.29 Permanent traffic signal installations at item 1 -


Durning/ Holt Street. Please refer to drawing
000041/ELW/1200/02/06 Rev B.

Permanent Bollards

12.30 Dual aspect Keep Left / Keep Left bollard no. 8 -


internally illuminated

Page Total carried forward to Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 1200 / 3
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 1200: TRAFFIC SIGNS & ROAD


MARKINGS - continued

Summary

1200 / 1 -
1200 / 2 -
1200 / 3 -

Page Total carried forward to Grand Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 1200 / 4
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 1300: ROAD LIGHTING COLUMNS &


BRACKETS, CCTV MASTS & CANTILEVER
MASTS

Lighting Columns

13.01 Provide and install 12m tapered steel column no. 12 -


with 1.0m single arm projection bracket, D.W.
Windsor Dover Luminaires complete with 250W
SonT Lamps CAT. No.
DO5SP250S20D(5/25)C.

13.02 Provide and install 12m twin door parallel shaft no. 2 -
steel column with 1.0m single arm projection
bracket and spiked finial, D.W. Windsor Dover
Luminaires complete with 250W SonT Lamps
CAT. No. DO5SP250S20D(5/25)C.

13.03 Provide and install 12m tapered steel column no. 7 -


with 1.0m double arm projection brackets, D.W.
Windsor Dover Luminaires complete with 250W
SonT Lamps CAT. No.DO5SP250S20D(5/25)C
with illuminated finial column

13.04 Provide and install 12m tapered steel column no. 7 -


with 1.0m double arm projection brackets, D.W.
Windsor Dover Luminaires complete with 250W
SonT Lamps CAT.
No.DO5SP250S20D(5/25)C.Complete with
illuminated finial and removable banner arms.

13.05 Provide and install 12m tapered double door no. 3 -


steel column with 1.0m double arm projection
brackets, D.W. Windsor Dover Luminaires
complete with 250W SonT Lamps CAT.
No.DO5SP250S20D(5/25)C complete with
illuminated laser cut 'Edge Lane' text and an
illuminated finial.

13.06 Provide and install 12m tapered double door no. 3 -


steel column with 1.0m double arm projection
brackets, D.W. Windsor Dover Luminaires
complete with 250W SonT Lamps CAT.
No.DO5SP250S20D(5/25)C with illuminated
laser cut 'Edge Lane' text and illuminated finial
and removable banner arms

Page Total carried forward to Summary -


Edge Lane West
Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 1300 / 1
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 1300: ROAD LIGHTING COLUMNS &


BRACKETS, CCTV MASTS & CANTILEVER
MASTS - continued

Lighting Columns - continued

13.07 Provide and install 12m twin door parallel shaft no. 4 -
steel columns with 1.0m double arm projection
brackets, D.W. Windsor Dover Luminaires
complete with 250W SonT Lamps CAT.
No.DO5SP250S20D(5/25)C complete with
illuminated finial to be shared use with traffic
signals.

13.08 Provide and install 8m parallel shaft tubular no. 9 -


steel column complete with tubular steel single
bracket arm of 170mm projection and Urbis
Evolo 2 Luminaire complete with 140 W
cosmopolis lamp.

CCTV

13.09 Take up and relocate CCTV mast 10m high no. 2 -

13.10 Provide and install 10m high CCTV mast no. 1 -

Page Total carried forward to Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 1300 / 2
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 1300: ROAD LIGHTING COLUMNS &


BRACKETS, CCTV MASTS & CANTILEVER
MASTS - continued

Summary

1300 / 1 -
1300 / 2 -

Page Total carried forward to Grand Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 1300 / 3
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 1400: ELECTRICAL WORK FOR


ROAD LIGHTING & TRAFFIC SIGNS

Trench for Cable or Duct (Street Lighting)

14.01 Trench for duct exceeding 300mm but not m 1083 -


exceeding 450mm wide, depth not exceeding
1.5m in footways.

14.02 Trench for 100mm dia black duct for Regional m 13 -


Electricity Company service cable, exceeding
300mm but not exceeding 450mm wide, depth
not exceeding 1.5m

Cable and Duct (Street Lighting)

14.03 Provide and install 4mm2 PVC/SWA/PVC cable m 240 -


installed in orange 'Street Lighting' duct 50mm
dia in footways.

14.04 Provide and install 16mm2 PVC/SWA/PVC m 92 -


cable installed in orange 'Street Lighting' duct
100mm dia in carriageways.

14.05 Provide and install 16mm2 PVC/SWA/PVC m 751 -


cable installed in orange 'Street Lighting' duct
100mm dia in central reservations.

14.06 Provide and install 100mm diameter black duct m 13 -


for Regional Electricity Company service cable.

Cable, Joints and Terminations

14.07 Provide and install single/multiway termination no. 12 -


4mm 2 core PVC/SWA/PVC electrical cable
type 101

14.08 Provide and install single/multiway termination no. 15 -


16mm 2 core PVC/SWA/PVC electrical cable
type 101

14.09 Provide and install single/multiway termination no. 21 -


4mm 2 core PVC/SWA/PVC electrical cable
type 102

Page Total carried forward to Summary -


Edge Lane West
Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 1400 / 1
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 1400: ELECTRICAL WORK FOR


ROAD LIGHTING & TRAFFIC SIGNS -
continued

Cable, Joints and Terminations - continued

14.10 Provide and install single/multiway termination no. 29 -


16mm 2 core PVC/SWA/PVC electrical cable
type 102

14.11 Provide and install single/multiway termination no. 2 -


16mm 2 core PVC/SWA/PVC electrical cable
type 105

Feeder Pillars

14.12 Provide and install Feeder Pillar Haldo Type nr 2 -


210.

14.13 Provide and install Feeder Pillar Haldo Type nr 4 -


210; in yellow

Page Total carried forward to Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 1400 / 2
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 1400: ELECTRICAL WORK FOR


ROAD LIGHTING & TRAFFIC SIGNS -
continued

Summary

1400 / 1 -
1400 / 2 -

Page Total carried forward to Grand Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 1400 / 3
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 1700: STRUCTURAL CONCRETE

In Situ Concrete

17.01 Retaining wall to back of footpath along School m 58.0 -


Lane including all excavation, backfilling and
disposal; Reinforced concrete foundation 750 x
275mm; reinforced concrete core 230mm wide
x 1000mm with 80mm recess for brickwork;
B1131 Mesh 1.5m high and 1.2m high to the
length of the wall; half brick thick facing
brickwork 1.0m high and 225mm high pointed
one side; 310mm wide PCC coping stone with
full width dpc; 2 coats of liquid waterproofer to
surfaces below ground

Page Total carried forward to Grand Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 1700 / 1
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 2700: ACCOMMODATION WORKS,


WORKS FOR STATUTORY UNDERTAKERS,
PROVISIONAL SUMS & PRIME COST ITEMS

Works for Statutory Undertakers

Trench for Cable or Duct

27.01 Trench for duct not exceeding 300mm wide; m 2267 -


depth not exceeding 1.5m; in footways

27.02 Trench for duct exceeding 300mm but not m 2055 -


exceeding 450mm wide; depth not exceeding
1.5m; in footways

27.03 Trench for duct exceeding 450mm but not m 249 -


exceeding 600mm wide; depth not exceeding
1.5m; in carriageways

Cable and Duct

27.04 Provide and install 1 no. 50mm diameter 5mm m 50 -


thick walled medium density smooth bore
polyethylene duct in existing trench depth not
exceeding 1.5m

27.05 Provide and install 1 no. 50mm diameter 5mm m 2194 -


thick walled medium density smooth bore
polyethylene duct in existing trench depth not
exceeding 1.5m

27.06 Provide and install 1 no. 50mm diameter 5mm m 1078 -


thick walled medium density smooth bore
polyethylene duct in existing trench depth not
exceeding 1.5m

27.07 Provide and install 1 no. 50mm diameter 5mm m 834 -


thick walled medium density smooth bore
polyethylene duct in existing trench depth not
exceeding 1.5m

27.08 Provide and install 1 no. 50mm diameter 5mm m 415 -


thick walled medium density smooth bore
polyethylene duct in existing trench depth not
exceeding 1.5m

Page Total carried forward to Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 2700 / 1
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 2700: ACCOMMODATION WORKS,


WORKS FOR STATUTORY UNDERTAKERS,
PROVISIONAL SUMS & PRIME COST ITEMS

Accommodation Works

Fencing, Gates and Stiles

27.09 1500mm high brick dwarf wall and railings. m 153 -


Refer to Wall Type A Detail A on Drawing
000041/ELW/100/04/02 Rev A. Walls are
450mm below ground, on an 800mm wide,
300mm deep concrete footing.

27.10 2500mm high Ibstock Cheshire brick wall. m 181 -


Refer to Wall Type B Detail C on Drawing
000041/ELW/100/04/02 Rev A. Walls are
450mm below ground, on an 800mm wide,
300mm deep concrete footing.

27.11 1500mm rendered dwarf wall and railings. m 69 -


Refer to Wall Type C Detail A on Drawing
000041/ELW/100/04/04 Rev A. Walls are
450mm below ground, on an 800mm wide,
300mm deep concrete footing.

27.12 1500mm stone wall using stone previously set m 52 -


aside and railings as Wall Type A; Detail A on
Drawing 000041/ELW/100/04/04 Rev A; Walls
are 450mm below ground, on an 800mm wide,
300mm deep concrete footing.

27.13 1500mm brick dwarf wall and railings; Wall type m 51 -


E; Walls are 450mm below ground, on an
800mm wide, 300mm deep concrete footing.

27.14 Close boarded timber fence 2m high m 58 -

27.15 Steel hoop fencing; all as Appendix 3/1 to the m 72 -


specification and drawing reference
000041/ELW/300/01

27.16 Steel hoop detachable fencing; all as Appendix no. 1 -


3/1 to the specification and drawing reference
000041/ELW/300/01

Page Total carried forward to Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 2700 / 2
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 2700: ACCOMMODATION WORKS,


WORKS FOR STATUTORY UNDERTAKERS,
PROVISIONAL SUMS & PRIME COST ITEMS -
continued

Accommodation Works - continued

Fencing, Gates and Stiles

27.17 Galvanised steel gate as per Detail C on -


drawing 100/04/02 no. 6

27.18 1700mm high, 500mm wide, 440mm thick brick no. 24 -


gate pillars; pillars are 500mm below ground on
1m square footing

Remove from Store and Re-erect Fencing,


Gates and Stiles

27.19 Remove from store and re-erect galvanised no. 4 -


steel gate as per Detail C on drawing
100/04/02

27.20 Remove from store and re-erect 2.4 m high m 189 -


Pallisade fencing

Page Total carried forward to Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 2700 / 3
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 2700: ACCOMMODATION WORKS,


WORKS FOR STATUTORY UNDERTAKERS,
PROVISIONAL SUMS & PRIME COST ITEMS -
continued

Provisional Sums

27.21 Allow the Provisional Sum of 45,000 for soft item 1 45,000.00 45,000.00
landscaping at School Lane

27.22 Allow the Provisional Sum of 20,000 for 3 no. item 1 20,000.00 20,000.00
Automated Sliding Security Gates

27.23 Allow the Provisional Sum of 300,000 for item 1 300,000.00 300,000.00
Ground Remediation Works at the site of the
former Petrol Station

27.24 Allow the Provisional Sum of 80,000 for a item 1 80,000.00 80,000.00
Layby and drop off area at the school

Page Total carried forward to Summary 445,000.00

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 2700 / 4
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 2700: ACCOMMODATION WORKS,


WORKS FOR STATUTORY UNDERTAKERS,
PROVISIONAL SUMS & PRIME COST ITEMS -
continued

Summary

2700 / 1 -
2700 / 2 -
2700 / 3 -
2700 / 4 445,000.00

Page Total carried forward to Grand Summary 445,000.00

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 2700 / 5
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 3000: LANDSCAPE & ECOLOGY

Seeding and Turfing

30.01 100mm thick MOT type 1 sub base m 14871 -

30.02 100mm thick topsoil m 14871 -

30.03 Grass Seeding; Seed from British Seed m 14871 -


Houses, mixture reference A18; 20g/m; pre-
emergent herbicide

30.04 Extra over seeding for turf adjacent to m 1165 -


pavements; 750mm wide

Planting

30.05 Carpinus betulas "Frans Fontaine"; 25 - 30cm no. 19 -


girth; in 2.0m wide continuous trench; to
include all excavation and disposal; 150mm
free draining gravel at base; trench to be part
lined with root barrier fabric; back fill material to
be Amsterdam tree soil/sand; root aeration and
feed pipe and tree anchoring system to each
tree

30.06 Ulmus Lobel; 25 - 30cm girth; in 2.0m wide no. 61 -


continuous trench; to include all excavation and
disposal; 150mm free draining gravel at base;
trench to be part lined with root barrier fabric;
back fill material to be Amsterdam tree
soil/sand; root aeration and feed pipe and tree
anchoring system to each tree

30.07 Acer campestre "Elsrijk"; 25 - 30cm girth; in no. 5 -


2.0m wide continuous trench; to include all
excavation and disposal; 150mm free draining
gravel at base; trench to be part lined with root
barrier fabric; back fill material to be
Amsterdam tree soil/sand; root aeration and
feed pipe and tree anchoring system to each
tree

Page Total carried forward to Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 3000 / 1
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 3000: LANDSCAPE & ECOLOGY-


continued

Planting - continued

30.08 Liriodendron tulipifera "fastigiatum"; 25 - 30cm no. 4 -


girth; in 2.0m wide continuous trench; to
include all excavation and disposal; 150mm
free draining gravel at base; trench to be part
lined with root barrier fabric; back fill material to
be Amsterdam tree soil/sand; root aeration and
feed pipe and tree anchoring system to each
tree

30.09 Galvanised steel trays 2.0m x 2.0m; Arboslot or no. 5 -


equal and approved; 40mm deep drilled to aid
free drainage and filled with resin bound gravel
infill; porous and breathable resin bound gravel
adjacent to tree; resting on 150 x 125mm ST4
concrete support

30.10 Galvanised steel trays 2.0m x 2.0m with offset no. 61 -


centre; Arboslot or equal and approved; 40mm
deep drilled to aid free drainage and filled with
resin bound gravel infill; porous and breathable
resin bound gravel adjacent to tree; resting on
150 x 125mm ST4 concrete support

30.11 Galvanised steel trays 1.5m x 1.2m with offset no. 19 -


centre; Arboslot or equal and approved; 40mm
deep drilled to aid free drainage and filled with
resin bound gravel infill; porous and breathable
resin bound gravel adjacent to tree; resting on
150 x 125mm ST4 concrete support

Page Total carried forward to Summary -


Edge Lane West
Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 3000 / 2
Edge Lane West
Highway and Environmental Improvement Scheme
Bill Of Principal Quantities
Ref Item Description Unit Quantity Rate Amount

SERIES 3000: LANDSCAPE & ECOLOGY-


continued

Summary

3000 / 1 -
3000 / 2 -

Page Total carried forward to Grand Summary -

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities Series 3000 / 3
Edge Lane West
Highway and Environmental Improvement Scheme
Instructions for Tendering

GRAND SUMMARY Page Total

SERIES 100: PRELIMINARIES 100 / 1 -

SERIES 200: SITE CLEARANCE 200 / 5 -

SERIES 300: FENCING 300 / 1 -

SERIES 400: ROAD RESTRAINT SYSTEMS (VEHICLE & 400 / 1 -


PEDESTRIAN)

SERIES 500: DRAINAGE & SERVICE DUCTS 500 / 4 -

SERIES 600: EARTHWORKS 600 / 3 -

SERIES 700: PAVEMENTS 700 / 3 -

SERIES 1100: KERBS, FOOTWAYS & PAVED AREAS 1100 / 5 -

SERIES 1200: TRAFFIC SIGNS & ROAD MARKINGS 1200 / 4 -

SERIES 1300: ROAD LIGHTING COLUMNS & BRACKETS, 1300 / 3 -


CCTV MASTS & CANTILEVER MASTS

SERIES 1400: ELECTRICAL WORK FOR ROAD LIGHTING & 1400 / 3 -


TRAFFIC SIGNS

SERIES 1700: STRUCTURAL CONCRETE 1700 / 1 -

SERIES 2700: ACCOMMODATION WORKS, WORKS FOR 2700 / 5 445,000.00


STATUTORY UNDERTAKERS, PROVISIONAL SUMS & PRIME
COST ITEMS

SERIES 3000: LANDSCAPE & ECOLOGY 3000 / 3 -

CONSTRUCTION RISK SCHEDULE

GRAND TOTAL 445,000.00

Edge Lane West


Highway and Environmental Improvement Scheme
Volume 3 Bill of Principal Quantities G.S

Das könnte Ihnen auch gefallen