Beruflich Dokumente
Kultur Dokumente
Since Benjamin had 30% more beads than Chloe, the ratio of the beads
they have is B : C 13 :10 .
Since Benjamin had 50% fewer beads than Annie, the ratio of the beads
they have is B : A 1: 2 .
Hence, the ratio of the beads is A : B : C 26 :13 :10 .
4 12 8 64 cm2.
1
Finally, area of the shaded region
2
5(180) 3(180)
4. We know that GAB and RAB , then
7 5
5(180) 3(180) 144
GAR GAB RAB .
7 5 7
144
180
Now AGR 7 558 x . This implies that x 558 .
2 7 7
5.
At first Morning Afternoon
35u 20u 60
Oranges
21u 14u 240
Apples
5 35
Note that . We may suppose that there were 35u oranges and 20u
3 21
4
apples at first. From the information, there were 35u 20u oranges
7
and 14u apples in the morning. Finally, there were 20u 60 oranges and
14u 240 apples in the afternoon. Since the ratio of the fruits was 1:1 in
the afternoon, we have 20u 60 14u 240 , which implies that u 30 .
Hence there were 21u 630 apples at first.
n 1 2 3 4 5 6 7 8 9 10
d 1 3 6 0 5 1 8 6 5 5
n 11 12 13 14 15 16 17 18 19 20
d 6 8 1 5 0 6 3 1 0 0
Notice that the possible values of d repeat after every 20 numbers. Hence
the last digit of 1 2 3 4 n is 3 when n 2,17, 22, 37, .
17 18
Note that 1 2 3 , 1 2 17 153 ,
2
22 23 37 38
1 2 22 253 and 1 2 37 703.
2 2
From the 1st meeting point to the 2nd meeting point, Heidi has travelled
64 168 232 m.
Distance Distance Total distance travelled
travelled by travelled by both
George by Heidi
Period I: 64 m Distance of route AB.
Start 1st meet
2
Period II: 232 m Double the distance of
1st meet 2nd meet route AB.
Due to uniform speed, the ratio of travelling distance for Heidi in Period I
232
and II should also be 1 : 2 . Hence, Heidi travelled 116 m when she
2
first met George.
The total distance of route AB is 64 116 180 m.
1 1
8. During sunny days, team A and B would complete and of the
12 15
1 1 1
project respectively. Team A would complete more of the
12 15 60
job.
1 40%
1 1
During rainy days, team A would complete of the
12 20
1 10%
1 3
project per day, and team B would complete of the
15 50
3 1 1
project per day. Team B would complete more of the job.
50 20 100
Suppose altogether there are m sunny days and n rainy days, since both
1 1
teams complete the project on the same day, m n . This
60 100
1 1
means that m : n : 3:5.
100 60
1 1 1
If m 3, n 5 , team A would only complete 3 5 of the
12 20 2
project. Therefore, there are 10 rainy days altogether.
9. Refer to the diagram below. Let x FI , y IJ and z JE .
As the ratio of the bases of rectangles is the same as the ratio of the areas
of rectangles, we have
x : ( y z) 12 : 36 1: 3 3 : 9
.
( x y ) : z 24 : 48 1: 2 4 : 8
Note that the area of triangle IJB: the area of rectangle AGFI is 1:6, and
1
so the area of triangle IJB is (12) 2 cm2.
6
Next, the area of triangle IJD: the area of rectangle DHJF is 1:8, and so
1
the area of triangle IJD is (24) 3 cm2.
8
A B A B A B
C D C D C D
+ E F G + 8 F G + 8 F G
9 I J 9 I J 9 6 J
Then E 8 or E 7 .
Now E 8 .
Now I 6 and as HIJ 963 is possible, we need to show that HIJ 967 ,
965 or 964.
Since A B C D F G J 0 1 2 3 4 5 7 22 and,
AB CD FG 10 A C F B D G 9 A C F 22 J and
L K 2s J
Suppose Justin spent t seconds to finish the race. Then Justins speed is
300 288
m s-1. This implies that Kadens and Leons speeds are m s-1
t t
240
and m s-1 respectively. From the condition, it is known that Kadens
t
12 288
speed is 6 m s-1 and hence 6 t 48 s.
2 t
240
Now Leons speed is 5 m s-1 and he has to run for another
48
60
2 10 s when Kaden finishes the race.
5
12. Since AOB BOC COD DOE , every time Adrian moved to the
360 36
next point on the circle, he rotated 81 relative to centre O .
4
Before Adrian reached point A for the second time, the total angle that
rotated relative to centre O should be a common multiple of 81 and
360 . The least common multiple of 81 and 360 is 40 81. Hence, from
the point F , Adrian reached at least 40 5 35 points before he got to
the point A for the second time.
15. Join the points A and F by a line segment. Let the area of triangle AFE be
x cm2 and the area of triangle AFD be y cm2. The area of the quadrilateral
AEFD is ( x y ) cm2. For two triangles with the same height, we know that
the ratio of their areas is equal to the ratio of their bases.
4 x 8 4 x 4 1
Thus and . From the second equation,
y 10 5 y 10 8 2
y 2x 10 , and from the first equation, 20 5x 4y 4(2x 10) , which
60
means that x 20 and y 2x 10 2(20) 10 30 .
3
Now x y 50 .
A
y D
x
E
10
4 F
8
B C
k (k 1)
16. If k is odd, then the number placed in the kth row, kth entry is . Note
2
k (k 1) 63(64)
that if k 63 , the value of is 2016 .
2 2
2016
63th row
2017
64th row
3 r 5 16r 10r
17. As , we have s .
10 s 16 5 3
16 10
If r 1, then 3.2 s 3.33 , so s is not a whole number.
5 3
32 20
If r 2 , then 6.4 s 6.67 , so s is not a whole number.
5 3
48 30
If r 3 , then 9.6 s 10 , so s is not a whole number.
5 3
64 40
If r 4 , then 12.8 s 13.33 , so s 13 .
5 3
18. Suppose 13 N abc 2017 . Then the last digit of N is 9.
Finally, let the 5th last digit of N be s. Note that Figure (b)
13 6 78 . This means 13s 7 100 . So s is 8.
(see Figure (d))
Figure (c)
Figure (d)
19. If statement A is true, then the sum of the digits of the block number should
be a multiple of 9 and so statement C must be false. Hence statement A
and C does not hold at the same time.
which means that 142 196 , 212 441 and 282 784 are the possible 3-
digit number. None of these make statements A or C true.
This means that statement E is true. We are left with 2 possible cases:
(iii) Statements E, C and D are true.
(iv) Statements E, A and D are true.
2
Since statements E and D are true, the 3-digit number is 2r 5s 3t for
If the sum of the digits of the 3-digit number is not a multiple of 9, then the
3-digit number does not contain a factor of 9, which means that it must be
2 5
2
100 , which means the sum of the digits is 1. Hence statement C
is not true.
a 8
16 16
b c 7 1
14 14
19 9 19 9
p u x 6 2
6
20 11 20 11
18 17 12 18
17 12
q r y z 8 3
4 7
(a b c) ( p q r ) ( x y z) u .
The Figure (B) above shows a possible solution when the sum is 52. So
the largest possible sum is 52.