Sie sind auf Seite 1von 6

Know How

INJECTION MOLDING
Clamp Tonnage:
More Is BetterRight?
Determining the correct tonnage
provides a foundation that must
be rock-solid to avoid flash and
damage. But applying excessive FIG 1

force can create problems with Material selected for this lid was a low-viscosity
LDPE, indicating that the pressure required from the
the part, mold, and machine. injection unit to pack the part would be fairly low.

Many factors must be considered to determine if an injection In the following examples, we will focus on using a Decoupled
molding machine has the capability to mold parts on a consistent Molding II processing strategy. During the process, the filling of
basis. The injection unit must have the the cavity is separate from the pack/hold phase. The filling stage
correct shot volume to avoid degradation should yield a part that is 95% to 98% visually full, resulting in
and unmelt. It must also have pressure in zero pressure at the end of the mold cavity.
abundance and a flow rate high enough to As the machine transfers from velocity to pressure control for the
allow for proper part filling. pack/hold phase, the cavity becomes visually full. Additional material
Plastic variables also must be consid- is packed into the cavity to minimize sinks and decrease dimensional
ered, focusing on how important it is to variation. Inside the cavity, the pressure increases, so the clamp must
process from the plastics point of view. provide enough force to overcome the pressure applied in the cavity.
By Jeremy Williams Its important to dry the material to appro-
priate moisture content, process within DETERMINING CLAMP TONNAGE
the recommended melt temperature, The starting point for determining appropriate clamp tonnage is to
select the correct flow rate for injection, apply adequate hold time calculate the projected area of a single part. Then any cored-out surface
and pressure, and cool long enough to maintain dimensional area shall be removed from the overall surface area of the single part.
stability. However, these variables only focus on the injection Once the total surface area of the part is determined, we must multiply
aspect of the process. it by the number of cavities in the mold. If the mold has a cold runner,
The clamp end of the its entire surface area must be taken into consideration as well.
The starting point machine is responsible for After obtaining the total projected area of all parts plus the
for determining providing force to counter the cold runner, we must then multiply that area by a tonnage factor.
appropriate clamp pressure that is applied from Tonnage factors used to be found on the material specification
tonnage is to calcu- the injection unit. How much sheets, but nowadays that information rarely finds its way onto
late the projected tonnage is applied, location those data sheets. Typical tonnage factors can range from 2 to 10
area of a single part. of that force, type of clamping tons/in.2, but for a starting point we recommend 3 tons/in.2.
mechanism, and size of As an example, lets propose molding a lid for a square leftover
the mold base all affect the dish (Fig. 1) with a hot-runner mold and eight cavities:
success of the molding process. Determining the correct tonnage
is not a simple task. It provides a foundation that must be rock- KNOW HOW INJECTION MOLDING
solid to avoid flash and mold damage. Is it possible to apply too Learn more at PTonline.com
much clamp force, narrowing the process window before molten Get more insights on Injection Molding from our
material is ever injected? expert authors: short.ptonline.com/moldingKH

34 Plastics Technology JUNE 2017 PTonline.com


QuALITy KNOw-HOw
MACHINES TECHNOLOGIES

THE HOME OF
INJECTION MOLDING
MARKET LEADERSHIP
PASSION vISION
INNOvATION

For as long as ARBURG has been involved with injection molding, its aim has always been
to be the home of the process. You wont find another company in the world that is
dedicated to the development and perfection of injection molding with the same level of
consistency and commitment. We always have one objective in mind: your success.

www.arburg.us
Know How

FIG 2 Comparing MFI Range and Melt Viscosity in Molding


2 g/10 min
High
Viscosity 1 g/ 25 g/10 min 1 g/10 min
SIDE-ACTION SYSTEMS 10 min 1 g/
10 min 24 g/10 min
Make Perfect Parts and Medium 14 g/ 2 g/
10 min 10 min
Save Money! Viscosity
68 g/ 1 g/
10 min 2 g/ 10 min 2 g/
10 min 23 g/ 10 min 40 g/
Low 10 min 10 min
Viscosity 23 g/ 53 g/
10 min 10 min
ABS HDPE LDPE PC PMMA POM PP PS
Low MFI numbers indicate high viscosity.
Preload cores for perfect parts. Melt viscosity is related to clamp-tonnage requirements, but MFI does not reliably
Save $$$$ with a smaller cylinder. correspond to actual melt viscosity in molding and cannot be compared accurately
Simplify mold operation and design. between resin types. For example, PC will always show high viscosity in molding,
regardless of whether the MFI is 2 or 25 g/10 min. Also note than an MFI of 10 g/10
Smaller mold base = low cost parts. min for PP does not mean an equal molding viscosity for the same MFI with PC.
Fully Preloads at only 1,500 psi.
Stays locked without hydraulics.
400 F systems available. Cavity Area = length width = 4.6 in 4.6 in = 21.16 in.2
Rush 0-2 day shipping available. Parts Area = cavity area cavities = 21.16 in.2 8 = 169.28 in.2
Tonnage =parts area tonnage factor = 169.28 in.2 3 tons/in.2 = 507.84 tons
KOR-LOK
TRADITIONAL
SIDE-ACTION VS. SIDE-ACTION
SYSTEMS SYSTEMS Now we have a starting point to determine what clamp tonnage is correct for this mold. But
S! Mold OPEN
S! other factors must also be taken into consideration to determine if the tonnage required
YE Core Out
YE
will be above or below 3 tons/in.2.
S! Mold CLOSED Melt flow index or rate (MFI, MFR);
YE
CANT DO IT!
When evaluating the MFI
Core OUT
Flow length;
ES
! or MFR, it is imperative Wall thickness;
S!
Mold CLOSED
Y YE that a comparison be
Core IN
Gate location;
S! Against FULL
Core PRE-LOADED
done only between the Gate size;
YE CANT DO IT!
Injection Pressure
same types of resin. Number of gates;
Volume of resin.

The first item that needs to be considered after calculating the tonnage based on projected
area is how the material flows. MFI or MFR can be found on the material data sheet from the
HYDRA-JAWS

supplier. A material with a high MFI or MFR will require less pressure from the injection
Every Mold,
Every Machine, Every Time! unit to complete the packing phase; therefore, the tonnage required will be lower.
Adjusts to Fit Every Mold When evaluating the MFI or MFR, it is imperative that a comparison be done only
Quick and Secure
Consistent Clamping Force between grades of the same type of resin. The reason for this is the ASTM test has a different
temperature, orifice size, and weight for each type of resin. These values do not corre-
late directly with molding, because of how the ASTM test is performed and how molding
machines actually operate. The MFR or MFI relate more closely to the packing phase since it
is typically at a much lower flow rate than the filling phase (see Fig. 2).
When reviewing our example of molding a lid, the material selected was LDPE. This

pfa-inc.com
N118 W18251 Bunsen Drive
material will likely have a very low viscosity, indicating that the pressure required from the
injection unit to pack the part will be fairly low. Therefore, based on material selection, the
tonnage required will likely be less than the typical 3 tons/in.2.
Germantown, WI 53022 Next, we need to evaluate both the flow length and the wall thickness. This is referred to as
(262) 250-4410
Fax (262) 250-4409 Designed &
Made in USA
the aspect ratio, comparing the flow length (from gate to end of fill) to wall thickness. Generally
KOR-LOK , Hydra-Latch and Hydra-Jaws are trademarks of PFA, Inc.

speaking, an aspect ratio less than 150:1 has a low risk of sinks, short shots, or dimensional issues.
2016 PFA, Inc. All Rights Reserved.
In our example of molding a lid, the flow length is 3.00 in. and wall thickness is 0.100 in.:

36 Plastics Technology JUNE 2017 PTonline.com


September 11-14, 2017: Conference / September 12-14, 2017: Exhibits
Orange County Convention Center / Orlando, Florida

Experience the Future


of the Industry
T ION
TH INN OVA
o rg E G
N SED
X . R
e CAM S T PAS
www
. t h
I N ED SUR
M B UN
C O

REGISTER NOW TO ATTEND

CAMX 2017
ORLANDO, FLORIDA
Know How

FIG 3 Aspect Ratio = flow length/wall thickness = 3.00/0.100 in. = 30:1

With a very low aspect ratio, the required pressure to pack this part will lower, thus further
reducing the required clamp tonnage to hold the mold closed. In addition to lower tonnage,
the probability of molding sinks, short shots, or out-of-tolerance parts is reduced.
Next, we need to evaluate the gate size as well as the number of gates. A larger
gate diameter has a much larger area for material to flow through, thus requiring less
pressure from the injection unit to fill and pack the part. The number of gates will affect
the injection pressure during both filling and packing. If there is a greater number of
This mold was clamped at four gates, a larger gate area, or if sequential filling requires less injection pressure, the result
times the required tonnage, is a lower required tonnage.
resulting in separation of the Our example of an LDPE lid has a single gate with a diameter of 0.030 in.
cavity block in two locations.

Gate Area = diameter x diameter 0.7584 = 0.030 0.030 x 0.7854 = 0.0007 in.2
FIG 4

This is a very small surface area to inject 23 g of material per cavity. Given this amount of mate-
rial and the gate size, expect the injection pressure during the packing phase to be slightly
higher and therefore the tonnage requirements would be a little greater than 3 tons/in.2.
Ultimately, the best method to determine required tonnage is to run a simulation with
correct geometry, characterized material, and full runner system. Without simulation, we can
draw conclusions from evaluating part geometry, material selection, gate size, gate location,
and gate quantity. Based on these factors, an expected range for this mold would most likely
be 339 to 508 tons (at 2 to 3 tons/in.2). A good starting point would be 420 tons of clamp force.

EFFECTS OF TOO MUCH TONNAGE


Now that we have focused on how to determine appropriate clamp tonnage, lets take a
Several factors contributed
to the frame rails breaking on look at the effects of applying excessive tonnage. Here are some typical molding defects
this vertical press. The mold that can be seen on parts almost immediately when tonnage is too high:
required about 10 tons to be Burns;
held shut against the forces
of injection, but the clamp Short shots;

CW
tonnage was set to 100 tons. Gloss level changes.

LARGE ROBOT,
LARGER VALUE
AUTOMATION FOR LARGE PARTS
On the battleground for large part molding, the MaxCW10 MaxCW50
robots offer efficiency, raw strength and fast payback.
Suitable for 470 4000-ton machines
Payloads as high as 264 lbs.
Full servo 3 axis with option for full servo 5-axis A+C
Vertical stroke up to 3000 mm

ABSOLUTE ROBOT
Traverse stroke up to 4500 mm
Aggressively competitive price
Check out our entire line of servo robots for www.absoluterobot.com
machines from 30 to 4000 tons.

38 Plastics Technology JUNE 2017 PTonline.com


INJEC T ION MOLDING

Part quality is not the only item affected sands of dollars for materials alone. If we factored in the labor hours to disassemble and
when excessive clamp tonnage is applied. reassemble nearly the entire machine, and the scrap produced over the years before the
There are long-term effects from over- rails failed, the number could easily exceed $200,000.
clamping that will damage the mold and
machine. First lets review several of the Jeremy Williams has more than 16 years experience in the plastics industry serving the medical,
side effects on the mold: automotive, furniture, and appliance industries. He previously worked as a principal engineer,
taking projects from design concept to saleable products. Jeremy earned his Master Molder II
Crushed vents;
certification in 2011, became an RJG Certified Trainer in 2012, and started at RJG Inc., Traverse
Rolled parting line; City, Mich. in 2016. In addition to his extensive manufacturing background, he holds degrees in
Broken inserts; plastics and business. Contact 231-947-3111; jeremy.williams@rjginc.com; rjginc.com.
Cracked core or cavity block.
Figure 3 is an example of a mold that was
clamped at four times the required tonnage.
Based on surface area, material, and gating,
the mold required roughly 100 tons (at 3
tons/in.2). The molder was inexperienced
WHICH ELBOW PROBLEM
and set the clamp tonnage to the machine DO YOU NEED TO SOLVE?
maximum of 400 tons (12 tons/in.2). Despite
a robust mold design, quality steel, proper
machining, and correct heat treating, the
result of excessive tonnage was that the
cavity block separated in two locations.
Each split ran the entire depth of the cavity PROBLEM Wear and failure when Formation of streamers,
block (roughly 10 in.) from parting line to conveying glass-filled, angel hair and snake
clamp plate. This was a catastrophic failure mineral-filled or other skins when conveying
abrasive pellets plastic pellets
that caused delays in production and
CAUSE Abrasive pellets hit the Plastic pellets skidding
upwards of $100,000 to expedite the manu- outside radius of conventional against the outside radius of
facturing of a new cavity block. impact elbows at high speed, conventional elbows create
continually wearing through friction and heat, melting
Here are some potential failures on the the elbow wall. pellet surfaces.
molding machine when excessive clamp SOLUTION Smart Elbow replacements from
force is applied: HammerTek eliminate these problems
Cracked hydraulic-cylinder mounting by eliminating impact
plates;
Unlike conventional impact elbows and
Deformed platens; plugged-tee elbows that rely on material
Fractured machine frame. impact to change direction, HammerTeks
Smart Elbow design features a spherical
In Fig. 4, there were several contributing chamber that protrudes partially beyond
factors that caused the frame rails to break the desired 90 or 45 pathway, which
causes a ball of pellets suspended in air
on this vertical C-clamp molding machine. to rotate, gently deflecting incoming
pellets around the bend.
First, the mold required about 10 tons to be
held shut against the forces of injection, No impact means no wear and no fines and
no streamers, angel hair or snake skins.
but the clamp tonnage was set to 100 tons.
Second the mold-base size covered less Free, No-Risk Trial Offer
See how Smart Elbow deflection elbows
than two-thirds of the platen in both direc- eliminate conventional and plugged-tee impact
tions. Combining these two poor practices elbow problemsat no cost or obligation.

over years not only fractured the machine 1-610-814-2273


EE-0299

sales@HammerTek.com
rails, but caused molding defects and mold www.HammerTek.com
failure. No one was sure when the failure
occurred on the machine, but they did
identify when it was first discovered and
documented its progression over time. 45 and 90 elbows available in diameters ranging from 1.25 to 18 inch
Replacing both machine rails cost thou-

@plastechmag Plastics Technology 39

Das könnte Ihnen auch gefallen