Sie sind auf Seite 1von 16

SPE/IADC 25758

An Improved Method for Grinding and Reinjecting of Drill Cuttings


Gunnar Sirevag and Arthur Bale, Statoil AlS
SPE and lADe Members

Copyright 1993, SPElIADC Drilling Conference.

This peper was prepered for presentation at the 1993 SPElIADC Drilling Conference held in Amsterdam 23-25 February 1993.

This paper was selected for presentation by an SPElIADC Program Commillee following review of information contained in an abstract submilled by the author(s). Contents of the paper,
as presented, have not been reviewed by the Intemational Association of Drilling Contractors or the Society of Petroleum Engineers and are subject to correction by the author(s). The
meterial, as presented, does not necessarily reflect any position of the SPE or IADC, their officers, or members. Papers presented at SPElIADC meetings are subject to publication
review by Editorial Committees of the SPE and IADC. Permission to copy is restricted to an abstract of not more than 300 words. Illustrations may not be copied. The abstract should
contam conspicuous acknowledgment of where and by whom the paper Is presented. Write Librarian, SPE, P.O. Box 833836, Richerdson, TX 75083-3836, U.S.A. Telex, 163245 SPEUT.

ABSTRACT cuttings, waste mud and oily waste water from drilling was a
following-up project to virtually eliminate the discharge of oily
A successful reinjection of oil-wet drill cuttings has been waste from Statoil's drilling and production platforms. As of
performed on the Norwegian Gullfaks Field. The reinjection November 1st 1992, a total of 6500 Sm3 (40880 BBL) of
was carried out in the annulus between two casing strings waste drilling fluids and cuttings have been reinjected into
through a wear-protected wellhead. An effective way of shallow formations on the Gullfaks Field. Reinjection of
grinding cuttings and mixing slurry by use of a new patent cuttings by use of the new crushing and mixing system is now
pending method known as SMACCC - Statoil Method for planned on several Statoil platforms in the North Sea.
Autogenous Crushing and Classifying of Cuttings has been
developed. This paper

The paper discusses reservoir aspects and presents simulated 1. discusses simulated reservoir and rock mechanical data
fracture geometries as a result of rock mechanical and slurry together with fluid/slurry properties in conjunction with
in-put property data. Further, the paper describes a 1000 hour down-hole disposal operations
wear test, involved equipment, and gives a derived formula
describing wear from sand slurries on internal wellhead 2. describes a lOOO-hour combined wellhead and centrifugal
components. pump sand erosion test. An equation relating erosion to
velocity and sand concentration is given.

3. describes the size and capacity of the new SMACCC


INfRODUCTION system, including an improvedand wear-resistant centrifugal
pump
The basic background to the cuttings reinjection project was
4. presents actual field test data and performance analyses for
1. Statoil's environmental policy to cause the least possible
offshore disposal operations
pollution of the environment, and

2. the company's policy to develop technologies and concepts


meeting low crude prices. RESERVOIR MODELLING AND
SIMULATION RESULTS
The increasing demand for highly deviated and longer wells
currently necessitates the use of oil-based mud, which is neither General Considerations
permitted to be discharged into the sea nor to be bomed. With
newly realized environmental concerns, about disposal prob- Subsurface injection is a world wide common method of waste
lems for drill cuttings and drilling solids residue for oil based disposal!", and many injection wells have been operating for
mud systems, several new disposal methods are currently being years with massive volumes of material being injected. The
considered and investigated by the oil industry. major difference between such "normal" disposal operations
and disposal of drilling cuttings and impure mud is the high
Since 1988, Statoil has reduced the use of oil-based mud by percentage of solids to be injected, with the corresponding
about 95% on the Gullfaks Field. The project of reinjecting requirement for injection above fracture closure pressure - e.g.
it will be necessary to open and probably extend hydraulic
fractures and/or open and extend existing natural fractures.
References and illustrations at the end of paper However, one example of sustained injection above fracture

n3
2 AN IMPROVED METHOD FOR GRINDING AND REINJECTION OF DRll..L CUTTINGS

pressure exists in many waterflood operations where injection PPG). This fluid pressure inside the fracture would be much
pressures are sufficient to open/extend fractures. Thus one higher than the actual mud weight being used to drill any new
might (very loosely) compare the expected behavior of long wellbore which might intersect the "disposal fracture" , thus the
term injection disposal wells with the observed behavior of waste drill cutting slurry would start to enter the intersecting
these waterflood fields. wellbore. This influx, however, should be of a fairly limited
volume (though the initial influx rate could easily be fairly
One common phenomena observed in waterflood operations high) as the disposal fracture starts to close in the area of the
conducted above frac pressure (when injection water tempera- intersection. That is, slurry flowing into the intersection
ture is similar to or hotter than the formation temperature) is wellbore will reduce the pressure in the fracture and the
a continuing increase in injection pressure as reservoir pressure fracture will start to close. Eventually fluid pressure in the
builds. Eventually, it seems that all such floods culminate with fracture right at the intersection must equal the mud weight in
bottomhole injection pressure equal to about 1.0 to 1.1 psi/ft the drilling well, and the fracture will be completely closed in
(0.23-0.25 bar/m) depth, i.e just about the normal weight of the area of the intersection. Thus, after an initial influx, one
the overburden, implying that horizontal fractures are probably would not expect continued flow from the injection disposal
being opened or propagated. Injection pressure at this level well into any temporarily intersecting wellbore.
then becomes quite constant and injection can continue for
years. A second common occurrence in the vicinity of floods
operated above frac pressure is the "super charging" of Slum Prooerties and Volumes
shallower permeable formations. That is, it appears that
significant vertical fracture height growth can occur, allowing The initial proposal for cuttings disposal via subsurface
the injection to communicate with overlying formations. injection involved creating a drilling cuttings/sea water slurry
(DCSWS) by first grinding the cuttings, then mixing with sea
This first phenomena was judged possible in conjunction with water to give a 1.25 S.G (10.4 PPG) slurry containing 30%
disposal injection on Gullfaks, and tubular pressure limits (WIW) solids. Preliminary testing showed that such a slurry
were comparedto eventual injection with a bottomhole pressure would have typical properties, as outlined in Table 1, where
slightly above the overburden gradient. However, the effect of fluid viscosity data is from the lab measUrements seen in
injection on pore pressure in overlying formations probably Figure 1. Interngly. the properties of the DCSWS were
should not materialize. Should vertical fracture height occur, found identical to a typical pre-snud mud. In hydraulic
and should the fracture encounter a shallower permeableforma- fracturing "terms", the 75 micron (150 US Mesh) size would
tion, fluid loss will immediately start to occur from the solids correspond with typical silica flour size fluid loss additives
laden slurry and a filter cake will form on the fracture face. while 1000 microns is approximately equal to the average grain
Thus, relatively little of the fluid will actual enter the forma- diameter of 16/30 US Mesh proppant (e.g. about 50% larger
tion. Continued fluid loss will then tend to dehydrate the than quite common 20/40 US Mesh size proppant used in many
slurry, eventually plugging the fracture and forcing fracture propped fracturing applications).
growth in some new direction. Thus while the continued
fracture growth may, or may not, be a problem, the fracture Typical required slurry injection rates were estimated to vary
encountering any porous, permeable formations should not from 3 BPM (475 LPM) for 12-1/4" holes to 1 BPM (160
significantly effect the pore pressure in these contacted zones - LPM) during drilling of an 8-1/2" hole to establish continuous
if the reservoir zone is of "any" extent. Even should the disposal (e.g. injection rate in-excess of drill cuttings produc-
fracture encounter some shallow gas bearing zone, the fluid tion rate).
pressure inside the slurry driven fracture will be greater than
the gas formation pressure, thus all fluid movement will be Fluid loss properties of the DCSWS were tested for fluid loss
fluid loss from the fracture into the formation - again resulting into rocks with "darcy" matrix permeability and the lab results B
in a filter cake formation and eventual plugging of the fracture. are discussed in Appendix-A. The fluid loss coeffisient (as
expressed in hydraulic fracturing terms), C, was measured as
In fact, should the slurry filled fracture remain vertical, 0.004 ftI(min.)~ (0.001 m/(min.)11'l) with no significant spurt
permeable zones will essentially act as "semi-barriers" to loss.
further vertical propagation. That is, the slurry inside the
fracture will tend to dehydrate due to fluid loss into a porous
permeable zone, eventually plugging the fracture and forcing Choice of Disposal FormationlProcedure
fracture extension in a new direction. For a vertical fracture,
this new extension might occur in the form of additional lateral For the Gullfaks Field, injection directly into the massive
growth in the impermeable zones underlying the permeable Utsira Sand, typically found at a depth of 900 m (2950 ft)
sand. This lateral growth will, of course, allow "bypassing" of (TVD), and/or injection into the shales underlying the Utsira
the older, plugged fracture, and new height growth might again appeared to be possible disposal scenarios.
allow the fracture to contact the permeable formation, where
the slurry will dehydrate, etc., etc. On Gullfaks, the 20" casing is set at l1oo m (3610 ft)
(fVD) and cemented in place with cement back to surface.
Another concern in conjunction with downhole disposal After drilling to a deeper depth, 13-3/8" casing is cemented in
fracturing could be for future wellbores to penetrate an "open" the well; however, in some instances unplanned cement slurry
fracture with internal high pressure. However, in general, it loss has resulted in a failure to circulate cement all the up into
appears that such consequences would be relatively minor. the 20" x 13-318" annulus, as illustrated in Figure 2. This was
Fluid pressure inside the fracture would at most be on the hoped to leave some formations exposed in the annular region,
order of the overburden gradient, giving a fluid pressure with and thus allowing disposal injection through the subject annulus
an equivalent mud weight on the order of 1.9 gram/cc (15.8 . while simultaneously producing from (or injecting throuP
774
SPE 25758 GUNNAR SIREVAG AND ARTHUR BALE 3

tubing into) the main reservoir. claystones and siltstones. For the initial fracture modelling, it
was assumed that a vertical fracture would be created in this
An approximate "Pressure(s) vs. Depth" diagram for the formation, and that this fracture would, at least initially, be
Gullfaks area is seen in Figure 3. For injection at TVD depths confined to the Dtsira - giving a fracture height of about 130
of 1000 m (3280 ft) (TVD), reservoir pressure should have feet (40 m) (TVD). The modelling assumed an injection of 1
an essentially normal gradient (e.g. 0.43 psi/ft or 0.1 bar/m), million DS gallons (i.e 1000 M-Gal or 4000 or, representative
with an estimated overburden gradient of about 0.85 psi/ft of half a year "production" of mud and crushed cutting
(0.19 bar/m) and an essentially normal fracture gradient of disposal volumes) at a constant, average rate of 3 BPM (475
about 0.7 psi/ft (0.16 bar/m). Assuming bottomhole injection LPM). Since some of the particles in the DCSWS are similar
pressure would eventually exceed the overburden pressure by in size to typical proppants used in fracturing, the slurry was
loo psi (7 bar) gives a maximum bottomhole pressure of modelled as a 0.5 PPG (0.5 pound of proppant per gallon of
2900 psi (200 bar). With a hydrostatic head of seawater, this liquid) (60 kg/m3) stage of a frac treatment. A 0.5 PPG
gives a surface pressure of 1400 psi (96 bar). With slurry would have about 2 percent total solids, thus modelling
wellhead pressure limits on the order of 1600 psi (110 bar) the DCSWS as a 0.5 PPG frac job stage somewhat implies that
for injection down the 20" x 13-3/8" annulus (i.e. top-side about 5 to 6 percent of the total ground cuttings solids consists
collapse pressure of the 13-3/8" casing), higher surface of the larger size particles. In actual frac, about 5 percent of
pressures could be handled by increasing the pressure in the 9- the DCSWS will consist of particle size greater than 75
5/8" x 13-3/8" annulus. microns (150 DS Mesh). It should be noted that in this
analysis, it was assumed that the bulk of the solids (e.g. all
particles <75 micron diameter) were deposited on the filter
Utsira Sand Jnjeetion cake. In actual fact, however, after the initial filter cake is
formed, the rate of filter cake build-up will probably decrease,
One "class" of shallow injection zones for disposal of the oil such that additional loss of clean sea water through the cake
based mud drill cuttings was originally into shallow sand will tend to partially dehydrate the slurry - as well as, of
formations, with the Dtsira Sand, as mentioned above, being a course, continuing to build the cake. Thus totally ignoring the
possible target for the Gu1lfaks Field. Such shallow sands fines (particles < 75 microns) in predicting the fracture
generally posses relatively high porosity and permeability, with behavior is probably optimistic (i.e the slurry will tend to
the Dtsira probably being typical with porosity on the order of possibly dehydrate and plug the fracture somewhat earlier than
35 percent and "darcy" permeability. Also, since sands predicted). Actually, as discussed below, even this "optimistic"
generally tend to have lower fracture closure pressures than modelling shows slurry dehydration/fracture plugging occur-
claystones, siltstones, shales, etc., one might generally expect ring virtually immediately, such that any "error"from ignoring
injection would (at least initially) preferentially break down and the fines becomes essentially meaningless.
enter such zones in cases where all types of formations are
exposed to fracturing fluid/slurry. The first stage of a propped fracture treatment, the pad, is
generally pumped as a sacrificial fluid loss stage, and also
Assuming a normal reservoir pressure gradient (e.g. 0.43 psi/ft serves to create sufficient fracture width to allow the proppant
(0.1 bar/m) of TVD depth) and a fracture closure pressure to enter the formation. Since a significant volume of the
gradient of 0.7 psi/ft (0.16 bar/m), this would give a DCSWS consists of particles similar in size to normal
reservoir pressure of 1280 psi (88 bars) and a fracture closure proppant, some type of "pad" stage should also be used in
pressure on the order of 2070 psi (143 bars) for the Dtsira initiating any disposal injection. Thus, for the modelling, a pad
Sand. For modelling of a fracture rate injection into such a stage was assumed of 180 BBL (29 m~ ( one third of an
sandstone formation, the major variables governing fracture average 20"x 13-3/8" annulus volume) of seawater injected at
behavior are the modulus of the rock, the fluid loss coefficient, 6 BPM (950 LPM). Despite this high injection rate, the
fluid viscosity (and, of course, fluid volumes & rates), and model predicted pressure behavior, as seen in Figure 4, shows
most importantly, the fracture height. the slurry dehydrating and plugging the fracture (forcing an
increased injection pressure) almost immediately.
The fluid and fluid loss data, as discussed above, and a
"dynamic" Young's modulus of 2x1OS psi (138.000 bars), This modelling has shown injection pressure increasing
based on a sonic log travel time, Ate, of 150 microseconds essentially without limit since the model does not allow any
per foot (p.s/ft), were used in the simulatiotf. Based on lab data "new" fracture to form. For the actual case, the pressure will
for Young's modulus from other high permeability, high only increase until: 1) injection pressure limits are reached and
porosity sand formations in the area, this estimate for in-situ the pumps must be shut down; 2) the fracture breaks out of the
"static" Young's modulus may be high by possibly as much as Dtsira Sand and begins to grow vertically into the overlying
a factor of 4 or 5. Calculations discussed below show possible (presumably impermeable) shales and siltstones; or 3) bottom-
fracture lengths on the order of 1300 ft (400 m), and the effect hole pressure reaches a level equal to the weight of the
of the actual rock modulus being less than the estimated value overburden and a horizontal fracture is formed. Of course it
would be to reduce this anticipated fracture penetration, e.g. might also be possible for a new vertical fracture in the Dtsira
for "softer" rock the fracture width will be greater and thus Sand to open, however, this new fracture would also immedi-
fracture length or radius will be decreased. However, this will ately "screenout" until eventually one of the three above cases
not be a "1 to 1" effect, that is, reducing modulus by a factor would occur.
of four might give a calculated fracture penetration reduction
on the order of 25 percent. The effects of "Case 1" are obvious (e.g. no further injection
would be possible) and clearly undesirable. However. this
A "type" log for the Dtsira Sand will reveal a discrete sand possibility was bome in mind. particularly if the slum
formation of 130 feet (40 m) (TVD) thickness surrounded by dehydration would occur near the weUbore such that the
775
4 AN IMPROVED METHOD FOR GRINDING AND REINJECTION OF DRILL CUTTINGS

entrance into the vertical fracture would be restricted or permeable formation - although it is possible that the injection
closed; the possibility of this would probably make direct might require slightly increasing pressure with time until, as
injection into a permeable sandstone a low priority pros- mentioned above, a horizontal fracture may form. Also, during
pect. The possibility of this near wellbore plugging would also lengthy shutdowns, solid settling in the main vertical fracture
be increased by the "startJstop" nature of injections, e.g. semi- could cover the injection interval forestalling further injection.
frequent, long, shut/down periods which would occur during In order to aid in preventing this, a significant seawater
breaks in drilling activity. Such a shut down period would overflush should be pumped immediately prior to any lengthy
allow the sluny in the near well fracture to dehydrate, building shutdown. A considerable sea water overflush would also
an unnaturally thick filter cake in this critical near wellbore prohibit fluid/sluny segregation and consequentplugging inside
area of the fracture. Eventually, this would totally destroy the casing annulus.
wellbore/fracture communication and prohibit any additional
injection into the sandstone from that wellbore. Also, it should be noted that the problems associated with
solids settling would be avoided in the case of a horizontal
Ignoring the high fluid loss Utsira Sand, the remaining two fracture. Injection into the potential "high stress" shales
cases were modelled as injection of sluny into a radial fracture underlying the Utsira Sand could occasion bottomhole pressures
which might represent either unconfined vertical growth or a equal (or near equal) to the weight of the overburden - making
horizontal fracture initiated from a structural level equal to the a horizontal fracture in the impermeable shale a high probabil-
Utsira Sand. For a horizontal fracture in the impermeable shale ity. For that case, as discussed above with Figure 5, it should
above (or below) the Utsira, 4000 m3 (25160 BBL) of be possible to inject on the order of 10,000 m3 (629oo BBL)
injected sluny would create a fracture with a radius of 25Om of sluny into a fracture covering a relatively small area
(82Oft), as seen in Figure 5. For unconfined vertical growth, (fracture radius on the order of 1300 ft (4oo m.
fracture propagation will tend to be slightly more "up" rather
than "down" due to the natural increase in fracture closure Further, injection into the shaly Hordaland Group below the
pressure with depth. This would result in a final fracture Utsira Sand would at least have three other major advantages:
geometry, as seen in Figure 6, with the fracture top reaching
to 21oo ft (700 m) TVD. This modelling assumed a very I. Existing producers and injectors with "open" and formation
small fluid loss to give a final "fluid efficiency" of 95 percent. exposed 20" x 13-3/8" annulus could be used for disposal
In actual fact, a fracture covering this much area will un- injection since most 20" casings had been set and cemented
doubtedly encounter small permeable streaks, natural fractures, at 50 - 200 m (150 - 650 ft) (TVD) below the Utsira
etc. and there would probably be more fluid loss than estimated Sand.
in the simulation. Thus these radial fracture extents should be
considered as "upper bound" numbers. In addition, for the case 2. The shale/claystone interval was according to (sonic) log
of vertical fracture growth, the fracture would almost certainly studies (ate"" 160 p.s/ft) believed to exhibit ductile prop-
encounter shallower, permeable zones. Fluid loss into these erties and thus behave plastically during and after injection
zones will again tend to dehydrate the sluny and plug the periods; hence the claystone could act as a "non-return
fracture over the permeable sand - stopping vertical growth at valve" after shut-in and fracture closure. With reducing
that point. This would tend to put a vertical growth cap on the downhole pressures as a consequence of dehydration of the
fracture as discussed below. fracture (due to fluids slowly leaking off through the filter
cake - primarily at the tip of the fracture in the permeable
Utsira Sand), no constant "back-pressure" would be
Injection below the <High Permeable) Utsira Sand observed on surface. Thus, execution of wellhead wear
inspection programmes would not be complicated by high
Another possible injection scenario for the Gullfaks Field surface wellhead pressure. Nor, would solids flow back
would be to inject into the shaly Hordaland Group at a point towards the wells and potentially plug the lower part of the
150 to 650 ft (50 to 200 m) (TVD) below the Utsira Sand injection annulus. Also, the expected embedment character-
(or injection into some other formation at a location below a istic of the soft/low stiffness claystone would be favourable
porous, permeable sand). Since "shales" tend to have higher in context of solids/crushed cuttings storage.
fracture closure pressure than sands, fracture gradient in these
zones could approach the overburden gradient, giving a surface 3. Injection through the 20" x 13-3/8" annulus would also
injection pressure (assuming only a hydrostatic head of sea enhance safety precautions during disposal injection periods
water) of 1500 psi ( 100 bar). However, assuming that this since the 9-5/8 x 13-3/8" annulus would act as a "barrier"
pressure limit could be realized, such injection could give a or buffer if a production/injection tubing leak or 13-3/8"
favourable final fracture geometry. Illustratively, this fracture casing leak would occur during the disposal operations.
geometry might develop as seen in Figure 7, where initially a
vertical fracture would expand as a "penny" shaped or radial The above discussed potential risks associated with disposal
fracture until the top of the fracture encountered the permeable injection directly into the permeable Utsira Sand and the
Utsira Sand. Shortly after that, as discussed above, the cuttings advantages linked to injection into the underlying non-per-
laden sluny would start to dehydrate, plugging the portion of meable Hordaland Group, called for the choice of the latter
the fracture which is in contact with the fluid loss. Additional disposal scenario in the Gullfaks Field.
lateral fracturing would then occur (probably at a slightly
higher pressure) as illustrated by fracture "2" until again the
fracture could grow vertically up into the permeable formation
- where it would again screenout, etc. Thus this fracture
geometry could conceivablyallow significantly larger quantities
of injection than might be possible for injection directly into a
ns
SPE 25758 GUNNAR SIREVAG AND ARTHUR BALE 5

IDENTIFICATION OF DISPOSAL WELL CAN- Displacement Tests


DIDATES AND DESCRIPTION OF FIELD
TEST PROCEDURES Pressure fall-off data after the Displacement Test, visualized in
Figure 9, clearly show a fracture in communication with a
Ev~uation of the 13-3/8" casing cement jobs, with a view to major permeable sand which, in case of a vertical fracture and
according to modelling results, would be the overlying Utsira
est~ated top cement, TOC, behind the subject casing, was the
key Issue for selection of disposal well candidates. Several Sand. An apparent closure stress can be picked at 50 bar (725
"?ld" wells on each platform were identified as potential future psi) surface pressure, corresponding to 2347 psi (161.8 bar),
dISposal wells. A two step testing program consisting of 1) a or !.43~ g/cc (11.96 PPG) (RKB) equivalentmudweight, at the
short-term "Communication Test" in order to confirm. forma- 20 casmg shoe after having corrected for the sea water head
tion communication in the annulus and 2) a long-term "Dis- in the annulus. Also, deducting a reasonable value of net
fracturing pressure from the observed pumping pressures at the
placement Test" (if communication was established) in order to
end of the injection period will substantiate the stress level.
overdisplace the annulus volume down to the 20" casing shoe
Results from other successful Displacement Tests substantiated
(basically consisting of mud with unknown characteristics) by
approximately 50 percent. the above minimum horizontal formation stress level - well
below the estimated overburden stress of minimum 3000 psi
(207 bar) at the 20" casing shoe and thus confirming the
Wellhead pressure and pump rate were recorded/loggedby use
geometry of a vertical fracture.
of a PANEX 1100A Quarts Capasitance gage and the cement
unit chart recorder, respectively.
Interestingly, the observed stress level in the shaly upper
Hordaland Group, 0.671 psilft (MSL) (0.152 bar/m (MSL)
turned down the possibility of significant shale/sand stress
Communication Tests
differences, as discussed in the introduction of this paper.
The "Communication Tests" have shown that communication
The surface.injection data from well 34/10-C-3, visualized in
to the shaly Hordaland Group below the 20" casing shoe was
Figures 8 and 9, represent the ideal case of an injection
established in approximately fifty percent of the chosen
disposal well: The stable shut-in pressures after the limited
~~didate wells; the remaining wells were obviously plugged
"Communication Test" suggest that (relatively confined) sand
mSlde the annulus - caused by either barite settling or cement
lenses in the vicinity of the 20" casing shoe, or below the
plugs. The "Communication Test" procedure is well identified
major Dtsira Sand, are not present. Such sand bodies may over
in Figure 8: After bleeding of the nitrogen cushion in the
annulus, sea water with corrosion inhibitor was injected with time exhibit charged post-injection pore pressures and cause
problems such as high shut-in surface annulus pressures, as
rates vlllYing between 0.6 BPM (95 LPM) and 6 BPM (950
well as counteract the potential advantage, as discussed
LPM). Injection was shut-in for approximately two minutes
introductory, associated with a pure shale acting as a post-
after each 25 bar (360 psi) increase in annulus pressure
injection non-return valve. Also, according to the "Displace-
basically in order to execute operation control. A programmed
ment Test" any disposal injection slurry volume is proven to
pressure increase in the 9-5/8" x 13-3/8" annulus rendered the
communicate with the overlying Dtsira Sand as a result of
possibility for surface pumping pressures up to 2030 psi (140
overdisplacing the 20" x 13-3/8" annulus - implying a rapid
bar). However, testing experience revealed that communication
pressure decline/fracture closure after shut-in.
through the 20" casing shoe was never established if surface
pressure exceeded 113 bar (1640 psi).

In wells with an "open" annulus a total volume of approximate- ONSHORE PRESTUDIES OF GRINDING AND
ly 20 m3 was pumped during the "Communication Test". ,PUMPING EOUIPMENT
Injection rates typically varied between 0.6 BPM (95 LPM)
and 6 BPM (950 LPM), the latter rate, as shown in Figure January 1990, one of the authors, Gunnar Sirevig, found by a
8, established during the second half of the injection period. coincidence a new and very effective crushing mill in a local
The wells were normally shut-in for at least one hour. In quarry, which, with certain modifications, looked promising
hindsight, the pressure fall-off data gave valuable information for crushing cuttings. This led to contact with universities and
with respect to geology, formation stress and fracture industries for evaluation and testing of alternative potential
geometry. As an example, the pressure fall-off performance, cuttings crushing equipment. The research and pilot testing has
identified in Figure 8, is indicative of a tight formation proved negative and the autogenous crushing mill found in use
surrounding the "relatively small" induced fracture; "signifi- in the quarry was left as the only viable solution.
cant" permeable sand lenses below the major Utsira Sand body
contributing to a steady leak-off (and corresponding pressure The SMACCC project was started by testing the modified
fall-oft) can not be identified from the subject data. Further, autogenous crushing mill lO , Figure 10 and Figure 11, and a
the low surface injection and shut-in pressures strongly indicate locally made heavy duty fertilizer centrifugal pump, Figure 12,
the presence of a vertical fracture, perpendicular to an in-situ referred to as the SPASER - Slurry Pump Agitator and Star
minimum horizontal stress on the order of 70 psi (5 bar) less Feeder Erosion Resistant - pump in the text below. Full scale
than the stable shut-in pressure (actual pressure minus net testing of the mill and ancillaIY equipment started in October
fracturing pressure). Unfortunately, at this stage, the corre- 1990 and lasted for two weeks, 16 hours a day.
sponding downhole pressures can not be accurately estimated
due to the unknown characteristics of the mud still present in The mill was modified for wet processing and Veslefrikk Field
most of the annulus. cuttings were used. Different running modes were tried and
grinding efficiency was analyzed. The goal of grindin~ the

777
6 AN IMPROVED METHOD FOR GRINDING AND REINJECTION OF DRil"L CUTTINGS

cuttings to maximum 5% above 100 micron (150 US Mesh) In cooperation with a firm of consulting engineer~ I, a thumb-
and no grain bigger than 1 rom was achieved. It was also found rule formula describing the relation between erosional wear,
that separate sand grains were hard to grind and that the velocity and sand content was developed, Equation 1. It should
grinding process was slow due to the low kinetic energy in be noted that this equation is only valid for a slurry funnel
small size separate grains of 300 - 600 microns (50-30 US viscosity (FV) above 40 sec..
Mesh) and smaller. Hard clay stone with variable sand content
was easily ground down. E = 1.1 x 10-s x C x t X V2.1 Eq. 1

Slurry design was also evaluated at this stage. Different where,


viscosifiers, thinners and defoamers were tested. XC-polymer
proved useful for viscosity building. Thinners had no effect. E = Assumed maximum erosional wear (rom)
since aU particles are oil wet. Defoamers had very little C = API test sand concentration (% by volume, VV)
effect. t = Injection time (hours)
V = Injection velocity (m1sec.)

Pre-studies of Erosion Wear on Wellhead and Centrifugal Reinjection offshore proved that the formula is useful to
~ determine maximum allowable injection velocity for the slurry.

The studyll was conducted in the Stavanger area from March *****
to August 1991. High and low-velocity sand slurry jets were
tested against the casing hanger, as shown in Figure 13, the The examples below are included to illustrate applications of
latter mounted in a wellhead rigged up in a workshop. Veloc- Equation 1.
ities in the wellhead varied between 23 and 2.1 m1sec. (15 -
6.9 ftIsec.) into one side of the wellhead. Total time for testing Example 1
of the wellhead and directional jet nozzles was ahout 1000
hours. Directionaljet nozzles of different configurations were C = 10%
tried in the wellhead to avoid erosion on the casing hanger. t = 400hrs
V = 6 m1sec.
Testing with directional jet nozzles proved to be difficult and E = 1.1 x 10-s x 10 x 400 X 621 = 1.89 rom
time consuming. High rates of erosional wear were found with
most nozzles tried and a decision was therefore taken to go If 2 rom is set as maximum allowable wear on the casing
ahead with an open wear bushing to protect the valve-removal hanger, the injection should be suspended.
threads in the wellhead housing. Consequently, only open wear
bushing results are described in this paper. Example 2

Tests run with funnel viscosities (FV) of 40 and 120 seconds, C = 10%
and a velocity of 23 m1sec. (15 ftIsec.) indicated that the 3 fold t = 1100 hrs
increase of FV reduced the wear by half. This viscosity effect V = 2 m1sec.
seems to be strictly valid for velocities as low as 10 m1sec. (33 E = 1.1 x lO-s x 10 x 1000 X '}!-1 = 0.52 rom
ftIsec.), as shown in Figure 14. The phenomenon is assumed
to be an effect of the centrifugal force in the 90 tum of the Example 2 highlights the importance of low rate injection in
slurry stream inside the wellhead housing; high centrifugal order to minimize erosion on the casing hanger.
force (high velocity) and low slurry viscosity will force more
of the sand in the slurry stream to collide with the casing Example 3
hanger. The "W" erosional scar on the casing hanger proved
erosion to be most si~cant on the low side of the eroded Problem:
surface, identified as (3) in Figure 15. What will be the maximum volume of cuttings slurry to be
- .
injected if the maximum allowable wear on the casing hanger
The sand used was a rounded, well sorted naturally occurring is 1.6 rom (1116").
beach quartz sand from the Orre area (outside Stavanger,
Norway) with 90% of the particle sizes ranging between 100 Answer:
and 400 micron ( 150-40 US Mesh). Sieve analyses of the Eroded wear from each cutting slurry batch pumped should be
sand taken after each test showed insignificant size reduction, ealculated by using Equation 1 and organized as shown in
identifying equal test conditions throughout the testing pro- Table 2. Further, this theoretical approach should be supple-
gramme. The sand concentration was kept constantly at 13 mented by frequent wellhead inspections using a horoscope. An
percent by adding "new" sand when needed. inline dummy wellhead on the rig can also be used for inspec-
tion purposes.
A practical experience gained from the erosion testing was that *****
to avoid excessive wear, the slurry velocity in the wellhead
annulus opening should be below 2 m1sec. (6.6 ftIsec.), The project decided to apply a simplified practical erosional
equivalent to pumping 159 lImin (1 BPM) through one port wear theory to support the use of Equation 1. The equation was
with a diameter of 40.08 rom (1-37/64"). Also, cuttings used with the following rules of thumb:
slurries with high sand concentrations should have a funnel
viscosity of 60 to 120 sec. to minimize the centrifugal force a) Differentiation between steel types is not significant 12.
factor in the slurry stream. b) Sand used in the test is representative of field sand
na
SPE 25758 GUNNAR SIREVAG AND ARTHUR BALE 7

cuttings. oilfield centrifugal pump had a simple packing box sealing


c) Maximum erosion penetration for steel occurs at impact which caused a lot of spill on deck and demanded frequent
angles of about 20 - 30, Appendix-B. maintenance. Later, this packing box was replaced by an
d) The geometry of the eroded surface and surroundings must expensive high-tech mechanical sealing which is still in
be roughly identical. operation.
e) No correction is made for reduced erosion due to high FV.
The SMACCC Unit autogenous wet-crushing mill proved to
be very effective in grinding the cuttings. Particle and fluid
The Bean Duty "SPASER" Centrifugal Pump velocity can be up to 100 m/sec. in the mill, comparable to that
achieved through a drill-bit nozzle. In addition to autogenous
A well proven Norwegian type centrifugal pump, used for inter-particle collisions, very high hydrodynamic shear forces
fertilizer mass in farming, was tried for pumping the cuttings help to degrade the cuttings particles. The high shear forces are
slurry. The initial tests were so promising that the pump was also very efficient in making micro-emulsions from oil and
tested for over 1000 hours in parallel with the erosion wear water, giving a very stable cuttings slurry.
testing ofthe wellhead. The following modifications were made
after about 500 hours of testing: Trash containers and big bags were used as a back-up solution
for storage of cuttings if problems occurred during crushing
* Small modifications to the pump housing geometry and reinjection of cuttings, visulized in Figure 16. The trash
* Hard-facing of the entire inside pump housing and containers could also be used for intermediate storage of ready
impeller cuttings slurry. This proved to be a safe, simple, low-eost, and
* Improvement to bearings and lubrication system good solution.
* Improvement to sealing system
On two occasions, the cuttings had to be temporarily stored in
The hard-facing method and material were based on experience the trash containers. The filled containers.were then hooked in
from earlier company projects on diverter lines and valves. the crane hook, and an air-operated 3-tons chain winch was
After these modifications the pump was run for 500 more mounted between the hook and one end of the container. The
hours without problems with a bentonite/seawatermud contain- cuttings could then easily and safely be dumped into an open
ing 36 percent quartz sand by weight. The pump was driven by screw conveyor tray ahead of the crushing mill. Cuttings from
the power outlet of a farming tractor. big bags hanging in the crane hook were also safely transported
to the crushing mill via the open screw conveyor tray.

GULLFAKS FIELD TRIAL OF CUTTINGS From the SMACCC unit and down to the high-pressure (HP)
AND WASTE FLUID REINJECTION stationary completion pump, two rubber hoses were used. This
permitted circulation through the suction manifold in the event
Description of Equipment Involved Offshore of suction loss problems.

From the shale shakers to the cuttings mill, hydraulically From the (HP) pump, flexible HP hoses were used down to the
driven reinforced farming screw conveyors were used. This is wellhead where aT-piece allowed pumping into both sides of
low-eost standard equipment with 1-2 weeks' delivery time. the annulus. The pop-off valve was reduced to 110 bars
The conveyors were driven by a variable-speed hydraulic (1600 psi) on the HP pump. In addition, a torque limit
motor, powered from the pipe-handling hydraulic powerpack switch on the pump was used as a back-up device.
already on the rig. The screw-eonveyors were easily installed
by simply hanging them in chains hooked up to a superclamp The valve-removal plug threads in the wellhead housing
grip device which fits all steel beam profiles and is mounted in opening were protected by a specially designed thread-protector
minutes. wear bushing. This wear bushing was easily put in place with
or without pressure in the annulus, with standard VR plug
Grinding of the cuttings, plus mixing and shearing it with tools, described in Figure 18.
waste water or seawater, was efficiently performed with the
newly developed SMACCC unit l3 , visualized on Figures 16 and On both sides of the wellhead, a back-pressure valve and two
17, standing on the open deck. Pumping between the four tanks gate valves, as shown in Figure 19, were installed to prohibit
of the SMACCC unit was easily done by means of the heavy- flowback from the well in case of leakage between the HP
duty SPASER centrifugal pumps. pump and the wellhead.

The SPASER pumps had excellent capacity even when handling


slurry as thick and dense as "toothpaste". In fact suction was Job Planning? Operations and Safety Aspects
never lost in the pumps during the Gullfaks operation. How-
Before the reinjection programme was approved, a Hazop 14
ever, there were some problems with bearing failures on the
crusher tank SPASER pump which was found and corrected safety study had to be performed. The Hazop analysis, which
after 10 days of operation. Since then the SMACCC unit involved most leading personnel, identified 10 relations that
SPASER pumps were operated without problems. had to be improved or clarified. The "Hazoped" programme
was then sent to all leading personnel involved for final
A common heavy-duty oilfield centrifugal pump, was installed approval.
as a supercharge pump for the high-pressure injection pump,
mainly to compare the two types of centrifugal pumps. The Safety meetings and pre-job meetings were held regularly and
whenever needed. Local safety aspects were discussed, written
779
8 AN IMPROVED METHOD FOR GRINDING AND REINJECTION OF DRILL CUTTINGS

down and instructions distributed to all personnel involved. by iron content in the barite reacting with the H2S - the latter
formed as a result of polymer degradation.
Written and approved work instructions were given to the
following personnel: SMACCC operator, HP pump operator,
reinjection operation engineer, drilling supervisor. Special log Injection Guidlines and Data Acquisition
sheets were also made for all personnel instructed.
All events, pressures, pump rates and relevant slurry properties
The equipment was rigged up according to plan15 Hard cement were recorded and logged'3 .
from the 12-114" casing shoe and formation cuttings from the
800m (2624 ft) 8-112" horizontal section in well 34/10-A-34, The 20"xI3-3/8" annulus pressure was logged for the nearest
penetrating a Lower Brent sand formation interbedded with wells. Typical slurry specifications are given in Table 2.
claystone and limestone stringers, were ground and injected
through the 20" x 13-3/8" annulus of well 34/10-A-29. The The following slurry specifications limits were given:
20" casing shoe in well 34/10-A-29 had been set and cemented
back with an inclination of 60. The reinjection did not cause FV 60 to 200 sec.
any drilling delays, despite minor reinjection operational Weight no limit
problems, as discussed below. Maximum API test sand concentration equal to 13% VV.
(Later operations excluded this limit).
No cuttings fragments to be observed on the 10 mesh screen
Involved Personnel on FV funnel.

The following personnel were involved in the operation on each The following limitations were set on pump rate through the
shift: two 40.08 mm (1-37/64") openings in the wellhead housing:

2 SMACCC operators Sand content below 1% VV implied a maximum rate of 480


"0.5" Reinjection operation engineer LPM (3 BPM) (later increased to 1000 LPM (6 BPM.
"0.5" HP pump operator
"0.5" Well pressure logger Sand content above 1% VV implied a maximum rate of 160
LPM (1 BPM) (later increased to 240 LPM (1.5 BPM.
Extra service was given by roustabouts when needed.
(Slurry jet velocity in wellhead with sand concentration
above 1% VV should always be below 2 mlsec.(6.6 ftlsec.
Concentrations of Chemicals Used in the Cyttinp Slurry
when Viscosifiers were Emploved The following annulus pressures limitations were given:

Since mainly sandstone was drilled, some viscosifiers had to be Annulus Max Pressure
used. It was observed that the effect of XC-polymer as a visco-
sifier was reduced when contamination with 5 - 10% oil-based 32" X 26" 15 bar (218 psi)
mud was present in the seawater. A polymeric viscosifier 26" x 20" 30 bar (435 psi)
similar to XC-polymer proved to be more effective in building 20" x 13-3/8" 110 bar (1595 psi)*
viscosity when the seawater was contaminated with oil-based 13-3/8" x 9-518" 90 bar (1305 psi)
mud l3 9-5/8" x tubing" 70 bar (1015 psi)

Additions of dry and prehydrated bentonite were tested out for * 140 bar (2030 psi) with pressurized 13-3/8" x 9-518"
viscosity building while drilling sand, but proved to be less annulus
efficient than use of the polymeric viscosifier.
During the period of 28 September through October 26, 1991,
The following additives were used: 45 batches of crushed cuttings were injected. Total pumping
time accumulated to 40 hours. Average pump rate was 0.25
Spesific weight of slum under 1.40 eSG) 01.7 PPG): m3/min (1.6 BPM), implying a slurry velocity of 1.67 mlsec.
(5.44 ftlsec.) into both sides of the wellhead. The Wellhead
Idvis 4 - 6 kg/or (1.4-2.1 PPB) (viscosity) injection pressure varied between 45 bar (650 psi) and
Ironite Sponge 3 kg/m3 (1.1 PPB) (H~ scavenger) 75 bar (1090 psi), dependent on injection rate, time
Biocide 0.7 - 2 kg/m3 (0.25-0.7 PPB) (fracture geometry) and slurry consistancy (the wellhead
pressure throughout the two hours "Displacement Test" for the
Spesific weight of slurry over 1.40 eSG): subject well was constantly 60 bar ). A total of 4590r (2887
BBL) of slurry, including 75m3 (472 BBL) of cuttings and hard
Idvis 4 - 6 kgIor drilled cement from inside the casing shoe, was reinjected.
Biocide 0.7 - 2 kgIm3
Post injection wellhead inspection of the 13-3/8" casing hanger
Ironite sponge and Biocide were only used if polymeric with the boroscope showed no detectable wear13 Pictures taken
viscosifiers were used. The reason for not using ~S scavenger showed that rust, scale and dry mud-cakes were still present on
when injecting high density slurry was that ~S is seldomly the hanger, indicating very low erosion from the slurry jet.
observed in polymer-rich drilling muds with specific gravity in Theoretical wear was calculated to be 0.005 mm. The maxi-
excess of 1.4 (S.G); the absence of ~ is presumedly caused mum allowable wear was set to (only) 1.6 mm (1116").
780
SPE 25758 GUNNAR SIREVAG AND ARTHUR BALE 9

Equipment & Operational Problems and Solutions ECONOMICS


Problems: The project used some old equipment to reduce the price.
However, the system proved to be a high quality solution with
1. Three bearing failures of recirculation SPASER pump for a high redundancy and safety level. Saved disposal cost for the
crushing mill tank. 8-112" section of well GFA 34/l0-A-34 was USD 233,000.
The investment to get the whole cuttings reinjection system up
2. Constraints (SD&P-Procedures) on number of activities and running was USD 9oo,000. Hence, cuttings and drilling
related to drilling and production operations undertaken waste fluid from another four 8-112" hole sections on GFA will
simultaneously on the rig caused intermittent stops during be required to be injected before the installationloperationcosl
the reinjection process. of the cuttings reinjection system will be paid off.

3. Bad/rainy weather causing unpleasant working conditions on Reinjection of cuttings and drilling waste fluid from recent
the SMACCC unit. wells drilled on other Statoil operated fields have proved much
higher cost savings by eliminating onshore disposal costs. On
4. Difficult to measure and quantify possible wear on the one well, for example, USD I million was saved, excluding
casing hanger with a Statoil-designed inspection tool, operational and investment cost for reinjection equipment.
described in Figure 20.
It took six months from ordering the first prototype SMACCC
5. Diaphragm pumps for transfer of cuttings slurry were found unit until it was built and in operation on the rig. This included
impractible. initial full scale testing onshore and some waiting for the
delayed well to be drilled. As mentioned earlier, the operatior
6. Suction problems on the HP-pump. cost of the SMACCC system included two extra men.
Compared to onshore transport of the cuttings in big bags and
Respective solutions: containers only two more hands were used, one cementer and
one injection data logger. However, these two are easily taken
I. a) New rig-up of pump on the baseplate to avoid bend in away when the operation is established and optimised on the
drive shaft. b) Changed to heavy duty grease. platform. Therefore, reinjection of drilling waste fluid and
cuttings is less manpower demanding than onshore transport
2. The cuttings from the well or ready cuttings slurry were and disposal.
stored in open trash containers when reinjection operations
intermittently were called to a halt.

3. To make working conditions more pleasant on the SMA-


FlITURE WORK
CCC unit in bad/rainy weather, a scaffolding and tarpaulin The goals for the future work will be:
stored on the platform were rigged up in a few hours.
Train operators to fully understand the reinjection process.
4. The tool for measuring casing hanger wear proved to be
accurate but impractical in use. The tool consisted of a Simplify rigging-up procedures of reinjection equipment.
graded flange mounted on the inner gate-valve flange.
Through the flange a pressure sealed arrangement permitted Continue to improve and simplify programmes and routine!
a measuring bar to be pushed through the gate valve and for reinjection jobs to reduce the risk of plugging the
against the casing hanger. If the measuring bar was just one injection annulus and near wellbore area. Post injectioll
mm out of position between repeated measuring points, plugging of three disposal well candidates, including well
deviations were observed. The reason for this was that the 34/1O-A-29, occurred during the early time reinjectioJ::
casing hanger surface is rounded and also was covered with period; April 4, 1992 well 34/10-A-29 was shut-in for a fev.
rust, scale and old dry mud even after 40 hours of re- hours with a mixture of sea water and waste drilling fluid!
injection. It was obviously not possible to clearly measure in the annulus. Upon resuming pumping, injection could nol
a few mm wear on this rough surface. be established due to .downhole plugging. However, thE
change to a high rate sea water flush programme (includin~
If erosional wear had been present, the casing hanger surface 50 percent annulus volume overflush) seems to have
would have been a shining steel surface. It was therefore overcome this problem.
concluded that pictures taken with a boroscope could be used
to prove whether or not erosion had been present, although Find good ways to avoid wear on wellhead, such as direct-
not to exactly quantify the wear. ing nozzles, hard-faced casing hanger and in-line dummy
wellhead.
5. Suction problems in the HP pump were eliminated by
lowering the FV of the slurry to below 200 sec. and install- Establish practical subsea reinjection wellhead solutions.
ing a coarse screen ahead of the suction manifold to catch
bigger rubber fragments from cement plugs and mud motor. Further optimisation of the SMACCC system.

781
10 AN IMPROVED METHOD FOR GRINDING AND REINJECTION OF DRILL CUTTINGS

CONLUSIONS and fracturing theory. AlIlo, Dr. O. Kvernevold, Det Norske


Veritas IndUlltri, Norge AlS, is mentioned for invaluable
Annular reinjection is proved to be a comfortable, econ- technical contribution related erosional wear evaluations and
omical, safe and environmentally optimal method, and is theory.
found overall superior to offshore cleaning and/or onshore
disposal of cuttings.
REFERENCES
Continuous subsurface injection of drilling fluid waste and
crushed cuttingll through a vertical fracture initiated at a 1 McCaskill, C.: "Well Annulus Disposal of Drilling Waste". Proceed-
ing of a National Conference on Disposal of Drilling Waatea, 1985.
depth of 1000m TVD (3280 ft TVD) below the 20"
cuing shoe in the Gul1fakIl Field hall proved sucellllful. 2 Freeman, B.D. and Wakim, P.G.: "API Survey Results on 1985
Onshore Waatea Volume and Disposal Practices within the US
The combination of the plutic nature of the fracture initi- Petroleum Extraction Industry", 1988 International Conference on
ation zone and fracture communication to a mullive overly- Drilling Wastes.
ing IlaDd formation rellervoir occuion fracture embedment
and fracture dehydration. Thus, wellhead wear inspection 3 E. Malachosky, B.E. Shannon and J .E. Jackson, An:o Oil and Gas
programmes may easily be undertaken after surface pressure Inc.: "Offshore disposal of oil based drilling fluid waste. An environ-
mentlllly acceptable solution", SPE Paper 23373 November 10, 1991.
bleed off. As of November lilt 1992, no maintained surface
pressure (or surface pressure build-up) hall been obllerved on 4 A.S. Abou-8ayed, Areo Oil and Gas Inc., D.E. Andrews, Areo
exillting Gullfakll disposal well candidatell. Alaska Inc., and I.M. Buhinta, Areo Oil and Gas Inc.: "Evaluation of
oily waste injection below the permafrost in Prudboe Bay field". SPE
A high rate 50 percent annulus volume Ilea water overtlush paper 18757. Presented at the SPE California, April 5-71989.
prior to any (lengthy) Ilhutdown Ileems to 1lO1ve problems
5 Bill Klemt, Sam Pole and Rhonda MacKinnon, Texas Water Com-
related to plugging inside the lowermollt annulus or in the
misaion: "Industrial Waste Disposal Wells: Mechanical Integrity."
near wellbore formation region. Proceedings of the International Symposium on Subsurface Injection
of Liquid Waatea, New Orleans, La. 1986.
A new and effective method for wet autogenous crushing
and clusification of cuttings hall been developed. 6 Belter, W.G.: "Deep Disposal Systems for Radioactive Wastes" in
UndergroundWaste Managementand Environmental Implications, AA
An equation for elltimating erosional wear on the calling PO Publications, 1972.
hanger from a 1l1urry jet containing sand has been derived.
7 JeffReddoch, Apollo Services, Lafayette, La.: "Closing the loop with
onsite cuttings disposal" . Petroleum Engineer International, July 1991.
A low cost, foolproof, heavy duty, combined agitator,
centrifugal pump and Iltarfeeder hall been developed for 8 "Fluid Loss Teats With Ground Cuttings Against Formation Cores",
pumping thick 1l1urries (with high IlaDd concentrations) Report No. SN0-090-S181 , Dowell Schlumberger Norway Labora-
without erollional wear problems of concern. tories, December 14, 1990, Statoil Internal Document.

9 "Feasibility Study - Drill Cuttings/Sea Water Slurry Injection, Gull-


A new Valve Removal Thread Protector Wear Bushing hall fab, Statfjord and Veslefrikk Fields", NSI Technologies, Inc. Tulsa,
been developed and used with success. The Protector Oklahoma, January, 1991
Bushing can be inIltalled in the wellhead housing with
Iltandard oilfield tools under pressure or under atmospheric 10 Statoil Internal Report. Read Process Engineering AlS, Ankerlskken
conditions. Mamn AlS. Statoil Project Order no. T181442. "Grinding of
Cuttings", November 1990.
The borollCOpe hall been verified all a practical tool for
11 O. Kvemvold, P. Jensen, Veritas Offshore Technology and Services
examination of erosional wear. The borollCope/lltem mUllt be AlS (Veritec), B. Dale, Moi AlS, "Veritec Rapport, Erosjonateater i
about 1 m (3.28 ft) long, rigid, Iltraight and have a view Vetco Gray Bmnnhode, Re-injekajon av Borekaka. Veritec Rapport nr.
angle of 45 to get good quality picturell. Video cameru can 91-3442", October 10, 1991.
a1IlO be used with the borollCope.
12 K. Haugen, O. Kvemvold, R. Sandberg and H. Trandem: Det noralte
Annular reinjection practice, training of people and rig Veritas Industri, Norge AS "Erosion Characteristics of materials
routines are critical for a good job. exposed to sand particle impact", Veritas Report No. 92-3444,
October 10, 1992.

13 Statoil internal Final Well Report: "Reinjeksjon av borekaks fra


ACKNOWLEDGMENT Gullfaksbronn A-34 ved bruk av SMACCC". Author: Gunnar Sirevig
B&B BRT, project manager reinjection. Fagomdder: Reinjekajon av
The authors wish to thank the management of Statoil AlS and borekaka, SMACCC. Milj" aktivitet boring. Utslipp kontroll. GFA-
34. GFA-29. kontrakt nrlProsjekt nr: T-181902/335517, November
the partners in the Gullfakll License Group, Norsk Hydro AlS 29,1991.
and Saga Petroleum AlS for permission to publish thiIl paper.
Arvid Loksy and Asmund Hovda, Statoil, are specially 14 K.Y. DavangerS-K DDB Statoil Bergen. "Hazop analyse. Reinjekajon
mentioned for important contribution to the success of the av borekaka i bronn 34/10-A-29". Statoil internal report. Report no.
project. S-K 910608R, Apri129, 1991.

A special thanks is given to Michael B. Smith, NSI-Tecbnol- 15 A. Lokey BBT-DDB, Statoil Bergen. "Program for reinjekajon av
borekaks i bronn 34/1Q-A-29". Statoil internal report. Report No.
ogies, for technical contribution related to reservoir enginering BBT/B910511R. Reinjeksjon borekab, September 3, 1991.

782
SPE 25758 GUNNAR SIREVAG AND ARTHUR BALE 11

APPENDIX-A E Eq. B-1

Fluid Loss Behavior Where;

Fracturing rate injection behavior of Drill Cuttings/Sea Water mp = Mass flow rate of particles (kg/s)
Slurry (DCSWS) into any porous, permeable formation will be K = Material constant
largely controlled by the rate of fluid loss into the matrix of the F( oc) = Function of impact velocity
formation. As the injection creates and propagates a hydraulic Vp = Impact velocity (m/s)
fracture (or opens and extends existing natural fractures), the oc = Impact angle
solids in the DCSWS will form a filter cake on the fracture n = Exponent
faces, with clean sea water then leaking-off through this filter
cake into the formation. With time, the continued fluid loss The coefficients "K, F(oc)" and On" are the parametres which
will serve to dehydrate the cuttings laden slurry, finally characterize the material being eroded. These parametres are
resulting in "plugging" the fracture and stopping any future generally determined experimentally. The function F( oc),
fracture growth. Figure B-2, includes the characteristics of the material with
respect to ductile/brittle behaviour. Ductile materials obtain
The proposed sea water/drill cuttings slurry was tested for fluid maximum erosion attacks at impact angles on the order of 20-
loss behavior through two Gullfaks reservoir cores and one 30 0 , while brittle materials obtain maximum erosion attack at
artificial, high permeability (6 darcy) core. The results', 90 0 impact angle. Steel qualities belong to the ductile materials
plotted in Figure A-I, show that fluid loss was fairly linear while ceramics tungsten carbides and different carbides
with the square root of time which is the typical behavior generally are brittle.
expected for a fluid system which forms a "filter cake". In
addition to the "root time behavior" indicating the formation of Experiments, ref. Equation B-1, have shown that all the most
a cake, it was also noted in the lab results that no solid standard steel qualities will obtain the same erosion attack for
particulate was recovered in the effluent from the tests - e.g. condition where erosion is the dominating material degradation
the particles formed the filter cake on the surface of the high mechanism. This means that the results obtained for the C-steel
permeability formation as expected. The approximate fit line, wellhead in the subject investigation also will be applicable for
seen in Figure A-I, yields a calculated fluid loss coefficient of similar wellheads made of other steel qualities.
C = 0.004 ft/(min.)'h (0.001 m/(min.)I~ for use in fracturing
calculations. This is actually a fairly high value for fluid loss *****
coefficient; however, even this relatively high value ignores the
one late time and "lab quoted" questionable data point showing
even higher fluid loss. The fluid loss coefficient was calculated
from Equation A-I.

C (ft/(min.)'h) = 0.0164 m / A Eq. A-I

where Om" is the slope of the fluid loss curve in ml/(minute)'h


and" A" is the flow area (taken to be 5.07 cm2 for a 2.54 cm2 Table 1 DSCWS Rheology Properties
(1 inch) diameter core plug.

Solids 30%
APPENDIX-B 95 % Less Than 75 microns
5% Up to 1000 microns
Erosion. General Aspects J2
Viscosity -
The resulting erosion attack on a material exposed to sand Plastic Viscosity = 15 cp
particle impact depends on a number of parameters; the most Yield Point = 60 lb/loo if
important being:
Power Law Properties
Sand particle impact velocity, (Vp)
n' = 0.26
Sand particle impact angle, oc
Mass of sand hitting the surface (m'~ K' = 0.148Ib/if/sec
Characteristics of the material being eroded.
Apparent Viscosity
The impact velocity and impact angle, described in Figure B-1, at 170 lIsec = 143 cp
are generally determined by solving equations giving the
velocity field for the liquid and equations' determining the Density-
particle trajectories by taking in to account the forces acting on 10Alb/gal
the individual particles from the carrying liquid. SG = 1.25
Generally, model equations used for estimating the resulting
erosion rate are given in the form,

783
12
Table 2 Log Chart for Reinjection of Cuttings

REINJECTION OF CUTTINGS. LOGCHART FOR INJECTION ENGINEER.

Rig: GFA Well drilled: A-34 Injector Well A-29. 20-13 3/8 annulus 10 wellhead opening: 40mm
Seclion: 8 1/2 HP pumpoperalor: Jan Svensson I B. Vatnemo
Mud system: oil mud Injection engineer: G. Sirevag

Date Tine Slurry FV Send Volume CLm. Max. Max. Max. Calculat. Max. Ofw Slurry Pump Cum. Inject.
weight pumped wlume pump pump well1ead erosion ennukls content hours hours Balch
pumped rate press. velocity hanger press. Solids PV YP Gels pLmped no.
SG sec. % m' m' Vmin. Bar mlsec. mm Bar %

10110 22.10 1.SO 60 10 15.5 54.5 375 50 2.50 0.0007 SO 21/79 24 14 57 1 7.14 11
11/10 14.07 1.53 80 18 12.0 66.5 224 'SO I.SO 0.0004 SO 24/76 25 26 81 32180 1 8.14 12
12110 18.35 1.42 82 15 8.0 74.5 190 45 1.30 0.0003 45 29/71 21 13 59 25130 1 9.14 13

13110 15.18 1.27 180 8 13.0 87.5 230 SO 1.SO 0.0002 60 13187 14 29 57 281110 1 10.14 14

14110 01.50 1.45 100 15 13.5 100.5 270 SO 1.79 0.0005 80 21/79 20 19 43 30142 1 11 15

14110 10.41 1.33 90 18 12.0 112.5 191 65 1.27 0.0003 65 12/88 20.5 24 73 27/53 1 12 16

14110 17.23 1.48 90 18 13.0 125.5 224 55 1.49 0.0004 65 22/78 21 35 66 45/SO 1 13 17
15110 00.26 1.12 90 6 13.5 139.0 245 57 1.63 0.0002 85 12188 5 13 57 25/31 1 14 18

15110 15.40 1.51 87 18 11.0 150.0 220 67 1.46 0.0004 1 15 19

15110 20.05 1.57 90 15 13.0 163.0 220 70 1.46 0.0003 37/63 22 40 80 25126 1 16 20
16110 11.08 1.36 65 13 14.0 177.0 220 65 1.46 0.0003 18/82 13 37 43 73/85 1 17 21
16110 16.02 1.23 SO 125 13.5 190.5 245 63 1.63 0.000001 15 42 20125 1 18 22
16110 21.30 1.10 45 125 14.5 205.0 242 57 1.61 0.00003 8 27 14140 1 19 23
17/10 08.30 1.20 45 5 13.5 218.5 225 64 1.33 0.0001 15/85 11 10 34 14/27 1 20 24
17/10 11.35 1.14 48 3 12.0 230.5 225 59 1.33 0.0001 7/93 16 10 36 16/22 1 21 25
17110 18.10 129 54 4 13.5 244.0 225 61 1.33 0.0001 19/81 15 19 56 24/25 1 22 26

Total calculated erosional wear O.004331mm this sheet. Total cummulalive erosion now: O.004555mm.

-
....
C'
III
DEPTH(mJ
TVD MD
WELLHEAp tWHl 4QmMp
REINJECTION ANNULUS
ESTIMATED Toe AT 115mMD

o 100.0
o
.......... 32. CONQUCIQR SHOE

g
\
Slope -
III
III

-
Power Law n' - 0.26
....CD 26- CASING SHOE

en FrT 1.30 SG EMW

.... PV - 15 cp
til

. . . . _--'
YP - 60 CUTTINGS REINJECTION
CD ANNULUS VOLUME 13D.7m
.r:;
en 1 0.0 L-.-.....__~...J...._-~-------
aD- CASING SHOE
20.0 100.0 1000.0 LOT' .56 SG EMW
"-
Shear Rate (1/sec) ESTIMATED TOe AT 1825mMD

Figure 1 Rheology Data for 1.25 SG Drill Cuttings Slurry ESTIMATED Toe AT 2103mMD
'3 u- CASm SHQE
FrT 1.eo SG EMW

TOP OF PACKER
TOP OF r LINER
I sm- CASINO SHOE
FIT 1.113SG EMW

rLINERSHOE
T.O.

Figure 2 Wellbore Schematic - illustration of Disposal Injection


784 Through Casing Annulus into Open Formation(s)
PRESSURE GRADIENTS GM/C:::-EQUIVALE:-JTS 13

1.0 I~ 2.0
4000

\ ' ...
..\ OVERBURCE~
rn
.:; 3000 /
/
FRACTURE ""... ...
\
\
"0
0..
! \
\
:r 1000 PORE PRESSURE \,
\ 2000

/
\
t- \
...oa. \ \, ...
Q)

, ::J

\ \,
rn
rn
...
Q)
1000
\ ,
I
I
I
0..
U,pressure Exceeds
Weight of
\ , '. \ o
Overburden

200 \\ o 200 400


Slurry Volume (M-Gal)

Figure 3 Predicted Formation Pressure Gradients, Figure 4 Net Fracturing Pressure Response for
Gullfaks Area Utsira Sand Injection

400 1000 Stres5 losJl 2500 -1.00 WIdth !lni UO


Rate .
Unconfined Height lor Horizontal) Fracture
3 BPM
Fluid Elf - 0.95
1900

] 300 2000
2100
rn
::J
'6 2200
~ 200 2300
0
\ 2400
...
til
2500
I
r
l
LL 100
2500
2700
2800
"
r
., ...
I
I

0
0 2000 4000 6000 8000 2900
Slurry Vol (M**3) 3000
3100
Figure 5 Fracture Radius Versus Injected Slurry Volumes
3200
3300
3400
. Permeable Sand . 3500
3500
3700
:
3800 ~

3900
Max Width UB In

Figure 6 Fracture Width Geometry For Unconfined


Vertical Growth

Impermeable Shale

Figure 7 illustrative View of Possible Fracture Behaviour


for Injection Below the Permeable Utsira Sand 785
14 r-----------------------,

120 --=r--.,-----,r----rr_-;su=.,~Ac;:;(~P;;;:.IlO(=-:;"2--;I:;;,.:;,. rr---------,


WELL NO . .34/10-C-J
8 .06bor 05,-06. l.IAY 1991

I
1/:II: I~ /"Instantonej>us shut -in
Inst n(oneou shul-i

:I '-(" _lnSlantoneo s shut-in pressure


" I 'I( V-Bleed 0 on
II

I:"
I
I
I
adjacent annulus
..
10 ~ =="t-----''r+---f--+--i '0
!
"'+.*+--t-=-t--==!====lO.'

J' 0' 3.' .,

Figure 8 Annulus "Communication Test" for Well 34/10-C-3 Figure 9 Annulus "Displacement Test" for Well 34/10-C-3

Recycle Feed , , , Crushing sane Rotor Feed


With Seawater ....:~ :~~: t - J u t t i n g s and Seawater
~ ..J.~.tt:;. -L
:. .:..~ .~....~. T
.. 'i..~...~..~:
... ~~t.i

Crushing Chamber
~~~~ \ . High Velocity
CultingsWall Rotating Rotor

2024mm

Total cruscher weight: 2.5 ton


Grinding capasity dry rock: up to 75 tonlhr (dry grinding) Figure 11 Cross Section of the Crushing Mill Chamber
Grinding capasity wet rock: over 15 tonlhr (wet grinding)

Figure 10 Wet Autogeneous Crushing Mill Used on


SMACCC Unit for Gullfaks

1 2" rubber hose wah sand slurry


Z Annulus opening in well head
J 13 3/8" casing hanger
~ Cement retum ports
.5. Steel ring
3
Outlet of sand slurry
Z Support leg

Figure 13 Cross Section of Wellhead and Casing Hanger


Figure 12 5" Heavy Duty SPASER" Centrifugal Pump Rig Up for Erosional Wear Testing
786
SPE25758
5 Tj- - - - - - - - - - - - - - - - - - - - - - ,
15
I
I -<l- Low vlSCosily (FV 40 sec.)
41 .-:-- High VISCOSity (FV 120 sec.)

E
,5.3

i
-0/-
~ 2 Point of I
.2
highest erosion 2
E
w on hanger I
surface
(highest flow)
9-11
.,-r,"77777"Tr..-r ErOSion profile
12 18 20 24 on hanger "W"
S1uny joI volocily (.....)

Figure 14 Measured Erosional Wear on Casing Hanger as a Figure 15 Schematic Drawing and Measuring Points of
Function of Slurry Jet Velocity During a 40 Eroded Surface Area on Casing Hanger
Hour Test with 13 % Quarts Sand

Wet Autogenous crushing mill


Classifier

Work
platform
E
Stair E
o
o
co
M
Heavy duty
SPASER pumps

6000mm 3000mm

Slurry Pump Agitator and


Starfeeder Erosion Resistant
Figure 16 Gullfaks A - SMACCC Unit

1 ray for emptying cuttings from


big bags or trash containers.

.oo
Cutting screw conveyor ....

.' -1r
Seawater
. !~
,y
A29

r HP-pum~p ..

20" - 13318" annulus

Transfer pump
Utsirasand
900-9SOrnTVD
CD Back-up storage cuttings, in big bags or trash containers. Claystone

Back-up trash containers (four off) for storage of slurry.

Figure 17 Gullfaks A - SMACCC Hook-Up


787
SPt25758
16
Wellhead houslng

POS DESCA"""'"
2 1I,..v.&l..VE
LTV.AQ1!02a.w:
,.CIot OC:V: veFIGt M1r~
X~2'/1r E %"FlGl!!102N
:r FIG'.
B.SOW:r FO 1502

. SPACER 111S"

,,".. X-O FIG 1


3"AG15O:f ..-Fill

Figure 18 Wear Bushing for VR-Plug Threads in


..'" x.o~FlO 1
,.HP
AW
.c' HP HOSE PROM NP
PIG ' .

Wellhead Housing
Figure 19 Wellhead Hook-Up for Reinjection
Well, 341l0-A-29

- - - Core --8-- Core --9-- 6 Darcy


215 216 Core

60.0

Wellhead housing
-
:
50.0

40.0
CIJ ,
CIJ ,, l/"
0 30.0
...J
~
Gate valve
'tl .~
'S 20.0
ii:
10.0
MOl ~
- - - - - Measuring rod 0.0
~~
0.0 5.0 10.0 115.0 20.0 25.0 30.0 35.0

Measuring tool with Root Time (min)


pressure seals
Degree graded scale
Figure A-I Fluid Loss Testing of DCSWS
Erosion measure
points

Figure 20 Statoll Hanger Erosion Measuring Tool


(a)
cilctile

~
e
w

v p .: impact velocity (m1s) (j 30 60 90


impact angle
a =impact angle
Figure B-1 Definition of Erosion Parameters Figure B-2 Erosion Behaviour of Brittle and
788 Ductile Materials

Das könnte Ihnen auch gefallen