Beruflich Dokumente
Kultur Dokumente
Republic of Iraq
Ministry of Electricity
Summary
TOTAL PAGES: 18
Including this page
Page 1 of 18
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Annexes:
1. Drawings and Documentation
2. Siemens Scope of Supply Appendix 1
3. Siemens Scope of Supply Appendix 2
4. Siemens Scope of Supply Appendix 3
5. Tests and Inspections
6. Siemens preferred Codes and Standards
7. Connection Points with National Dispatch Center Specifications
Page 2 of 18
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
1 General
The works necessary for the correct operation of the open cycle plant are classified as follows:
- Works external to the plant fence will be the scope of work of others and the Contractor
has no responsibility upon, unless otherwise specified in the following tables.
- Equipment supplied by Siemens are stored in warehouses (the power island and
switchyard equipment listed in the following Chapters). Their in-land transport in Iraq will
be arranged by M.O.E, who will make them available to the Contractor, at the site. The
Contractor shall be responsible for:-
taking over the material, securing them in a suitable manner as recommended.
Installation, testing, commissioning and put into operation as per Siemens drawings
& vendors erection instructions. Operation-tests and commissioning will be witnessed
by Owner representatives. All critical erection (such as gas turbine unit shaft
alignment) & commissioning activities will be subject to site reports according to Site
Quality Plan & Procedures to be developed by the Contractor and to be presented to
Owners Engineer & Siemens Technical Advisors prior to works.
- Balance of Plant (BOP) & Electromechanical Systems necessary to complete the power
station shall be procured & installed by the Contractor. The Contractor shall be
responsible for:-
- Civil Works of Siemens supply items and all other civil works, as per the Technical
Specifications of this contract shall be the responsibility of the Contractor .
Designs of all Civil Works other than those provided by Siemens, construction and
erection (as defined below).
The installation works of all plant items up to the terminal points indicated in Chapter
3.4.2, including Siemens furnished equipment. Operation tests of all systems will be
witnessed by Employer representatives;
Page 3 of 18
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
- The Contractor shall be responsible for health and safety management during
construction, erection and commissioning period.
- The Contractor shall be responsible to meet obligations of the defects liability period and
to submit as-built drawings.
With the above exception, in particular regarding the power island, the power station shall be
constructed on a full design and build, turnkey basis, and it shall be the responsibility of the
Contractor to ensure that all equipment (procurement) excluded from the Siemens scope of supply
are provided in order to render the power plant fully complete and functional for safe and reliable
commercial operation under all conditions and respects.
All material, plant and equipment supplied by the Contractor shall be brand-new and of a class
suitable for the purposes specified. Equipment shall be selected to ensure high reliability and
availability of the complete plants with low forced outage rates and minimal maintenance.
Permanently installed safe access to all items of plants shall be provided by the Contractor for
inspection, operation and maintenance. The Contractor shall be responsible to check and suggest
modifications, if necessary, for the proposed general arrangement with the exception of the power
island.
The Contractors scope of work includes all interconnections between the Siemens supplied Gas
Turbine Generators and their off base auxiliary skids and includes piping, cabling, terminations,
conduits, cable trays as well as the installation and testing of the same.
Particular attention shall be given to the design of the underground works, additional to foundation
works, namely to all mechanical and electrical items to be buried under the ground such as pipes,
cable ducts and drainage works. The number of overlapped underground layers shall be limited to
reduce installation and maintenance problems. In principle the maximum number of acceptable
overlapped layers shall be three, not including the lowest layer, which shall be the grounding
system. Where such number would be exceeded, external racks, not shown in the available layout
shall be considered and included in the Contractor scope of work without any extra cost to the
Employer.
3.1.1 General
Items excluded from Siemens scope of supply and services but necessary for proper operation of
the plant, shall be included in the Contractor scope of supply and services. Any other items deem
necessary to accomplish the plant shall also be included in the Contractor scope of supply and
services.
In the following paragraphs all the plants systems are indicated, and notes are added giving
references to annexed documentation. All systems inside the plant fence shall be installed by the
Contractor. For most of the listed systems, only one package is required, but in some cases two or
Page 4 of 18
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
more are required; relevant indications for this requirement are given in other chapters where
detailed scope of works of the systems ares given.
It is intended that each system shall be complete, when applicable, with a local Programmable
Logic Controller (PLC), the necessary electrical motors, the necessary protections, the
instrumentation for local and remote indication, as well as with on skid necessary piping and cables.
The contractor shall supply off-skid piping, complete with required insulation and heat tracing, and
cables inside the power island for equipments in Siemens scope of supply, and install the machinery
and equipment.
Systems located outside the fence are also listed in the tables; the Contractor is not responsible for
these works with the only exception indicated in the tables relevant to the electrical interconnection
for the provisional feeding during site works.
Page 5 of 18
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Electrical power dispatch from the gas turbine generator packages, shall be through the facility
provided by the Employer under a separate contract. The Contractors scope of work shall cover the
electrical connections up to the power station switchyard outgoing gantry after step up transformer
to match with the voltages provided by the Employer. The Terminal point of the Contractors works
shall be up to and including the outgoing gantry structure where it terminates to the facility provided
by the Employer. Further in liaison with the Electrical Transmission Projects (ETP) of MoE
Communications, SCADA and Protection shall be compatible to the MoE system and protocols shall
be compatible and acceptable to ETP of MoE.
2.4 Communications
All connections to the public telephone network shall be the responsibility of the Contractor. The
Contractor shall ensure that all communication systems used during construction and operation of
the Site meet appropriate regulations and do not cause interference with any communication or
electrical equipment on the surrounding site.
2.5 Drainage
The termination points for the drainage systems shall be sub-divided into surface water, sewage
water, chemical and oily water systems as per the following paragraphs.
Page 6 of 18
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Gas Turbine
- Two (2) numbers of Siemens SGT5-2000E (Heavy Duty, Single Casing, Axial Flow
Design) Gas Turbine Units, each comprising of
Compressor :1
Turbine :1
Bearings :2
Turning Gear :1
Mechanical Control & Protection System :1
Gas Turbine Instrumentation and actuation :1
(Gas turbine package is described in Section 4.2 and further explained in Section 7 of
Appendix 1; Annex 2)
Page 7 of 18
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
3.1.3.1.1.2 Gas turbine Systems (Auxiliaries)
All items listed below are given in Section 2.1.2.2 and explained in Section 7.3, 7.4 of
Appendix 1; Technical Proposal.
Noise control installation at gas turbine: Scope per gas turbine comprises
- Structural steel with corrosion protection : 1 set
- Noise hoods for combustion chambers with silencer on top and with doors
to the gangways : 1 set
- Mobile sound barrier wall enclosing the combustion chamber elbows : 1 set
- Sound barrier panels alongside the gas turbine and at the pipe rack including : 1 set
insulation of piping penetrations and windows or shutters where accessibility
is necessary
3.1.3.1.1.3 Equipment common for all offered gas turbines (belongs also to
auxiliaries)
(As given in Section 2.1.2.1 of Appendix 1; Technical Proposal)
- Fuel gas flow metering for performance tests only (provision of material only) : 1
Page 8 of 18
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
- Water pump test for compressor cleaning system :1
- Set of standard tools :1
- Set of tools for assembly and inspection :1
Turbine Controller
Page 9 of 18
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
- Redundant automation processor for closed loop : 1 set per GT
control functions
- I/O modules : as per I/O
I&C Cables
- turbine related special I&C cables (Flame monitoring cable) : 1 lot per GT
I&C Software
- I&C software (system & application programs) on disks : 1 set per GT
Page 10 of 18
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
The Gas turbine and Generator Package along with its auxiliaries as listed above
(and described in Section 2 of Appendix 1, Siemens Technical Proposal) will be
supplied to EPC contractor as a free issue item from the customer.
The following items excluded (As given in Section 3.3 of Appendix 1; Technical
Proposal) in Siemens offer need to be incorporated in the scope of work in the EPC
offer.
Platforms, ladders and stairs around the GT enclosures, PCC, generator and GT
Skids
Exterior lighting
Civil works
Vent piping from skids to the roof, drains
First filling of accumulators with nitrogen incl. adapters and pressure reducer
Lifting beams or any other lifting aids
Grounding and lightning protection (App 3)
Communication systems (App 3)
Touch up painting
Power Plant noise protection concept / calculations
Erection and Commissioning
Technical Field Assistance (TFA) services
Tools and instruments for erection and commissioning except those specified in
section 2.11.2
Lube Oil Cooler (Fin Fan) Oil side piping between lube oil skid and heat
exchanger
- Exhaust Gas System - Noise provisions such as sound walls or enclosures
for the diffuser
Noise Enclosures
- Ventilation air inlet filters
- Heating systems
GT Fire Protection and Extinguishing System
- Signal cabling from local GT firefighting panel to plant firefighting system
(Refer Appendix 3)
- Full discharge test of CO2 firefighting system
- Portable fire extinguishers
-
Instrumentation and Control
Operating and Monitoring Equipment
- Local operating push buttons for actuators
- Local indicators for measurements
Special I&C functions
- Data management for maintenance
Other Equipment, Functions and Services
- I&C Systems (hardware, software) for any plant system outside of Siemens
scope
- Signal exchange to other I&C systems than the Plant DCS
Generator
- Assembly platform, no additional supports for rotor insertion/removal
Generator Forced Cooling System
- Piping between Generator, heat exchanger and pump skid
Electrical Equipment
Page 11 of 18
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
The details are given in Section 3.3 (page 4 of 4) of Appendix 1: Technical Proposal
Distribution Transformers
Four (4) pieces 2000kVA, AN, 6.6/0.42kV, NLTC Dry type Distribution T/f
Two (2) pieces 800kVA, AN, 6.6/0.42kV, NLTC Dry type Distribution T/f
Page 12 of 18
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
220V & 48VDC station batteries, battery chargers, DC power distribution
system, Inverters, Static switches, manual by-pass switches and power
panels (Ref sec. 10.7 of Appendix 3)
Medium and Low Voltage Power Cables with trays and conduits
Cables and cable trays for the electrical Balance of the Plant (Ref sec.
10.10 of Appendix 3)
Spare Parts for Two Years of Operation (Ref. Sec. 10.13 of Appendix 3)
Page 13 of 18
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
The Electrical Balance of Plant and Central Control System Package as listed above
(and described in Sections 10 and 11 of Appendix 3, Siemens Technical Proposal) will
be supplied to EPC contractor as a free issue item from the customer.
All the following items excluded (as per Section 11.14) in Siemens scope of supply need
to be incorporated in the scope of work in the EPC offer.
Any control equipment , material, installation & testing tools other than specified
within the given quantities. Control Room Architectural design and layout drawings
Any field equipment/ instrument (pressure, temperature, level and flow equipment,
field mounted converters, solenoid valves/ MOV, air filter regulator/ pressure
regulator, control/ relief/ on-off valves, control drives, safety valves, heat tracing, etc.
Vibration monitoring system
Instrument Air System and pipes
Fire detection and/or protection system for the entire plant
Any kind of local control panel, local PLCs and local HMI
Recorders, Analyzers, Control Desks (Pults) & Conventional Control Equipment,
Local Announciates
Redundancy in I/O levels
Control room architectural design and layout drawings
Plant performance calculations
Reconfiguration or writing of any plant specific application programs within 3 rd party
systems (Black boxes) interfacing to the Siemens offered Central Control System
Erection, erection supervision and commissioning
Condition monitoring system
Station earthing and lightning protection system (for areas not covered by the
Siemens offer)
Plant lighting system consisting of lighting distribution boards, lighting transformers,
lighting panels, lighting fixtures, switches and power receptacles, lighting
poles/towers, conduits, cables, wires and accessories (for areas not covered by the
Siemens offer)
Local control panels for all the mechanical and electrical systems as indicated in
relevant equipment/system chapters
Local AC distribution boards consisting of isolating switches and emergency push
buttons
Miscellaneous equipment like space heating panels, junction boxes etc.
AC, DC motors for the required auxiliaries and valve actuators
All standard instrumentation, hookups, transmitters, local indicators, instrument
cables, compensating cables, junction boxes as necessary to make the system
complete and functional
Electrical lab equipment
Construction power supply system
Page 14 of 18
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
The following systems are necessary for the successful operation of the power
plant but not included in Sections 3.4.3.1, 3.4.3.2 & 3.4.3.3 above and in
Appendices 1,2 and 3 of Siemens Technical Proposal.
Fuel gas pressure reducing and heating station with fuel gas pipes and supports
between gas station and consumers (gas turbines and heating systems)
LDO road tanker unloading, metering and storage facility, and forwarding facility.
HFO road tanker unloading, metering and storage facilities and Fuel Oil Treatment
Plant FOTP
Fire detection, fire alarm, protection systems and portable fire extinguishers The fire
fighting systems shall be complete with fire water pressure regulation, fire fighting
piping and hydrants outdoors and indoors, hydrants along the transformer access
roads and the buildings access roads etc. (Fire alarm system, consisting of fire
detectors and alarms for GIS, Control & Relay building is supplied under Scope of
Supply in Section 2.5 of Siemens, Technical Proposal Appendix 2. Fire detections
system for gas turbine unit, including fire detection & control system with local panel
is provided by Siemens.)
Water treatment systems to cater the needs of fire fighting water supply, drinking
water supply (for staff and for GT washing where applicable) and supply of de-
mineralized water for spray cooling of coolers and of turbine hall and for turbine
washing and for DENOx water injection etc.
Oil side piping between lube oil skid and heat exchanger
Related Equipment
Storm water pumps
Lighting and lightning protection for all buildings (including Non-Technical-
Buildings as shown in the plant layout drawings)
Touch-up paint for exhaust, air intake systems and all others where necessary.
Small auxiliary tanks for GT (wash water tanks and false start oil tanks etc)
Page 15 of 18
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
Sensors for oil and water storage tanks (for temperature, level etc.)
False floors for CCR`s,
Cranes & lifting devices in buildings as necessary for maintenance and GT
overhaul works
Platforms and ladders
Embedded parts for stack foundation
Supports for GCB and IPB
Compressed air system (same capacity as air intake pulse filter compressor
system to be used as a back-up in case one pulse filter compressor fails and can
supply air for tools in workshop)
Material for blower door test and one full discharge test of CO2 fire fighting
system of the GT enclosure
Integration of above mentioned systems and items into the overall plant layout
and detailed interconnection design between the offered systems and the
remaining power plant equipment.
Page 16 of 18
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
1. Topographical survey
2. Soil investigation & other tests required for foundation designs
3. Site Development works; flood protection works, fencing & boundary wall, Plant
internal roads, drain and culverts, sewage disposal system and landscaping/
ground cover
4. Construction enabling works
5. Hydrological Survey
6. Approach road to site from main road.
Page 17 of 18
MINISTRY OF ELECTRICITY General Directorate For DIBIS Tender
Gas Power Plant Projects 2011
37. Interconnecting structures as required
38. Switchyard associated civil works including foundations & buildings
39. Painting (shop paint, touch-up paint and final paints at site after erection) of all
the steel structural works as per the approved colour scheme of Owner / Owners
Engineers
40. Thermal insulation, acoustic insulation and cladding as required for entire plant
41. Temporary site building
42. Foundations bolts, base plates, anchor bolts, sub sole plates and all foundations,
inserts with anchor fixed to the plate and grouting for all equipment
43. Pedestals for fire hydrants, deluge valves etc. Other misc structures.
44. Non-plant buildings and associated works
Page 18 of 18