BAT5-REV1-OCT 16 BATINAH EXPRESS WAY - PACKAGE 5- CONSTRUCTION OF BATINAH EXPRESSWAY PACKAGE.

5
REVISED SCHEDULE (Finish in 2018) REVISED PROGRAMME OF WORKS - DD: 30 OCTOBER 2016
REQUETED ON 19TH OCTOBER 2016 MEETING

Activity ID Activity Name Remaining Performance Start Finish 2017 2018


Duration % Complete Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

BATINAH EXPRESS WAY - PACKAGE 5- REVISED SCHEDULE (Finish in 2018) 426 0% 09-Oct-13 A 31-May-18

CONSTRUCTION 426 0% 09-Oct-13 A 31-May-18

OETC WORKS 426 0% 09-Oct-13 A 31-May-18


OETC Lines 306 0% 09-Oct-13 A 31-Jan-18 31-Jan-18, OETC Lines
B5-CS-OET-S2-A3-010 Contractor Requested NOC 0 100% 09-Oct-13 A
B5-CS-OET-S2-A3-020 OETC Initial Response to Request 0 100% 29-Jan-14 A
B5-CS-OET-S2-A3-030 Continual Corresondence / Meetings /Consultant Quotes 0 100% 16-Feb-14 A 16-Sep-14 A
B5-CS-OET-S2-A3-040 Engineer Confirmed Approval of MM Consultant 0 100% 20-Oct-14 A
B5-CS-OET-S2-A3-050 Discussions / Correspondence / Meetings re Design 0 100% 10-Nov-14 A 18-Feb-15 A
B5-CS-OET-S2-A3-060 DGR & LT Authori se Appointment of MM 0 100% 24-Feb-15 A
B5-CS-OET-S2-A3-070 Ongoing Discussions / Meetings 0 100% 02-Mar-15 A 30-Sep-15 A
B5-CS-OET-S2-A3-080 Assumed date for Civil Worls Start by Sub-Contractor 0 0% 01-Apr-17* Assumed date for Civil Worls Start by Sub-Contractor
B5-CS-OET-S2-A3-090 Assumed date for Diversion of OETC Lines Location 1 (Wadi Jizi) 0 0% 31-Oct-17* Assumed date for Diversion of OETC Lines Location 1 (Wadi Jizi)
B5-CS-OET-S2-A3-100 Assumed date for Diversion of OETC Lines Location 2 (STA: 191) 0 0% 20-Nov-17 Assumed date for Diversion of OETC Lines Location 2 (STA: 191)
B5-CS-OET-S2-A3-110 Assumed date for Diversion of OETC Lines Location 3 (STA: 195) 0 0% 10-Dec-17 Assumed date for Diversion of OETC Lines Location 3 (STA: 195)
B5-CS-OET-S2-A3-120 Assumed date for Diversion of OETC Lines Location 4 (STA: 201) 0 0% 31-Jan-18 Assumed date for Diversion of OETC Lines Location 4 (STA: 201)
Location 1: Wadi Al Jizi 211 0% 01-Nov-17 31-May-18
Piling & Excavation 14 0% 01-Nov-17 19-Nov-17 19-Nov-17, Piling & Excavation
Piling Works 14 0% 01-Nov-17 18-Nov-17 18-Nov-17, Piling Works
B5-CS-PIL-WJ-080 Piling Abutment 2 6 0% 01-Nov-17 08-Nov-17 Piling Abutment 2
B5-CS-PIL-WJ-090 Piling Pier 17 to Pier 19 - East & West Bound 8 0% 08-Nov-17 18-Nov-17 Piling Pier 17 to Pier 19 - East & West Bound
Excavation 8 0% 08-Nov-17 18-Nov-17 18-Nov-17, Excavation
B5-CS-SEC-WJ-070 Excavation Abutment 2 5 0% 08-Nov-17 15-Nov-17 Excavation Abutment 2
B5-CS-SEC-WJ-080 Excavation Pier 17 to Pier 19 - East & West Bound 0 0% 18-Nov-17 18-Nov-17 Excavation Pier 17 to Pier 19 - East & West Bound
Trimming of Pile Heads 3 0% 15-Nov-17 19-Nov-17 19-Nov-17, Trimming of Pile Heads
B5-CS-TRM-WJ-080 Trimming of Piles Pier 17 to Pier 19 0 0% 18-Nov-17 18-Nov-17 Trimming of Piles Pier 17 to Pier 19
B5-CS-TRM-WJ-070 Trimming of Piles Head Abut 2 3 0% 15-Nov-17 19-Nov-17 Trimming of Piles Head Abut 2
Abutment 2 (2nd Half) 37 0% 19-Nov-17 04-Jan-18 04-Jan-18, Abutment 2 (2nd Half)
B5-CS-AB2-WJ-60 Foundation Construction Abut 2 10 0% 19-Nov-17 02-Dec-17 Foundation Construction Abut 2
B5-CS-AB2-WJ-70 Wall Construction Abut 2 15 0% 02-Dec-17 19-Dec-17 Wall Construction Abut 2
B5-CS-AB2-WJ-80 Water Proofing Wall Abut 2 2 0% 19-Dec-17 21-Dec-17 Water Proofing Wall Abut 2
B5-CS-AB2-WJ-100 Back Wall Construction Abt 2 6 0% 21-Dec-17 30-Dec-17 Back Wall Construction Abt 2
B5-CS-AB2-WJ-110 Approach Slab Const Abut 2 4 0% 30-Dec-17 04-Jan-18 Approach Slab Const Abut 2
Piers 61 0% 02-Dec-17 13-Feb-18 13-Feb-18, Piers
Pier 17 (Right Side) 21 0% 02-Dec-17 27-Dec-17 27-Dec-17, Pier 17 (Right Side)
B5-CS-P17-WJ-50 Foundation Construction Pier 17 (Right Side) 4 0% 02-Dec-17 06-Dec-17 Foundation Construction Pier 17 (Right Side)
B5-CS-P17-WJ-60 Columns Construction Pier 17 (Right Side) 5 0% 06-Dec-17 12-Dec-17 Columns Construction Pier 17 (Right Side)
B5-CS-P17-WJ-70 Water Proofing Fnd Pier 17 (Right Side) 2 0% 11-Dec-17 13-Dec-17 Water Proofing Fnd Pier 17 (Right Side)
B5-CS-P17-WJ-80 Backfilling Around Fnd Pier 17 (Right Side) 4 0% 12-Dec-17 17-Dec-17 Backfilling Around Fnd Pier 17 (Right Side)
B5-CS-P17-WJ-90 Pier Cap Construction Pier 17 (Right Side) 10 0% 14-Dec-17 27-Dec-17 Pier Cap Construction Pier 17 (Right Side)
Pier 18 37 0% 06-Dec-17 21-Jan-18 21-Jan-18, Pier 18
B5-CS-P18-WJ-010 Foundation Construction Pier 18 8 0% 06-Dec-17 16-Dec-17 Foundation Construction Pier 18
B5-CS-P18-WJ-020 Columns Construction Pier 18 5 0% 12-Dec-17 18-Dec-17 Columns Construction Pier 18
B5-CS-P18-WJ-030 Water Proofing Fnd Pier 18 2 0% 17-Dec-17 19-Dec-17 Water Proofing Fnd Pier 18
B5-CS-P18-WJ-040 Backfilling Around Fnd Pier 18 4 0% 18-Dec-17 23-Dec-17 Backfilling Around Fnd Pier 18
B5-CS-P18-WJ-050 Pier Cap Construction Pier 18 20 0% 27-Dec-17 21-Jan-18 Pier Cap Construction Pier 18
Pier 19 49 0% 16-Dec-17 13-Feb-18 13-Feb-18, Pier 19
B5-CS-P19-WJ-010 Foundation Construction Pier 19 8 0% 16-Dec-17 26-Dec-17 Foundation Construction Pier 19
B5-CS-P19-WJ-020 Columns Construction Pier 19 5 0% 20-Dec-17 27-Dec-17 Columns Construction Pier 19
B5-CS-P19-WJ-030 Water Proofing Fnd Pier 19 2 0% 26-Dec-17 28-Dec-17 Water Proofing Fnd Pier 19
B5-CS-P19-WJ-040 Backfilling Around Fnd Pier 19 4 0% 27-Dec-17 02-Jan-18 Backfilling Around Fnd Pier 19
B5-CS-P19-WJ-050 Pier Cap Construction Pier 19 20 0% 21-Jan-18 13-Feb-18 Pier Cap Construction Pier 19
Deck & Superstructure Works - East Bound 94 0% 13-Feb-18 17-May-18 17-May-18, Deck & Superstructure
Phase 5 from Pier 16 to Abt 2 49 0% 13-Feb-18 11-Apr-18 11-Apr-18, Phase 5 from Pier 16 to Abt 2
B5-CS-DCK-WJ-EBD-220 Bearings Installation: Pier 15 to Abut 2 7 0% 13-Feb-18 21-Feb-18 Bearings Installation: Pier 15 to Abut 2
B5-CS-DCK-WJ-EBD-230 Precast Beams Installation: Pier 15 to Abut 2 7 0% 21-Feb-18 01-Mar-18 Precast Beams Installation: Pier 15 to Abut 2
B5-CS-DCK-WJ-EBD-240 Diaphragm Construction: Pier 15 to Abut 2 15 0% 01-Mar-18 19-Mar-18 Diaphragm Construction: Pier 15 to Abut 2
B5-CS-DCK-WJ-EBD-250 Deck Construction: Pier 15 to Abut 2 20 0% 19-Mar-18 11-Apr-18 Deck Construction: Pier 15 to Abut 2
Finishing 37 0% 11-Apr-18 17-May-18 17-May-18, Finishing
B5-CS-DCK-WJ-EBD-260 Concrete Barriers Deck 5 0% 11-Apr-18 17-Apr-18 Concrete Barriers Deck
B5-CS-DCK-WJ-EBD-280 Lighting Poles Installation - Wadi al Jizi 2 0% 17-Apr-18 19-Apr-18 Lighting Poles Installation - Wadi al Jizi
B5-CS-DCK-WJ-EBD-270 Water Proofing Deck 6 0% 21-Apr-18 28-Apr-18 Water Proofing Deck
B5-CS-DCK-WJ-EBD-290 Asphalt Pavement Deck 1 0% 28-Apr-18 29-Apr-18 Asphalt Pavement Deck

Date Revision Checked Approved


Remaining Level of Effort Actual Work Page 1 of 3
02-Nov-16 REV.1 M.M D.G
Actual Level of Effort Remaining Work
BAT5-REV1-OCT 16 BATINAH EXPRESS WAY - PACKAGE 5- CONSTRUCTION OF BATINAH EXPRESSWAY PACKAGE.5
REVISED SCHEDULE (Finish in 2018) REVISED PROGRAMME OF WORKS - DD: 30 OCTOBER 2016
REQUETED ON 19TH OCTOBER 2016 MEETING

Activity ID Activity Name Remaining Performance Start Finish 2017 2018


Duration % Complete Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
B5-CS-DCK-WJ-EBD-300 Expansion Joints Installation Deck (Strip Seal) 15 0% 29-Apr-18 17-May-18 Expansion Joints Installation Deck
Deck & Superstructure Works - West Bound 99 0% 21-Feb-18 31-May-18
Phase 5 from Pier 17 to Abt 2 57 0% 21-Feb-18 29-Apr-18 29-Apr-18, Phase 5 from Pier 17 to Abt 2
B5-CS-DCK-WJ-WBD-220 Bearings Installation: Pier 10 to Abut 2 6 0% 21-Feb-18 28-Feb-18 Bearings Installation: Pier 10 to Abut 2
B5-CS-DCK-WJ-WBD-230 Precast Beams Installation: Pier 10 to Abut 2 3 0% 01-Mar-18 05-Mar-18 Precast Beams Installation: Pier 10 to Abut 2
B5-CS-DCK-WJ-WBD-240 Diaphragm Construction: Pier 10 to Abut 2 10 0% 19-Mar-18 31-Mar-18 Diaphragm Construction: Pier 10 to Abut 2
B5-CS-DCK-WJ-WBD-250 Deck Construction: Pier 10 to Abut 2 15 0% 11-Apr-18 29-Apr-18 Deck Construction: Pier 10 to Abut 2
Finishing 61 0% 31-Mar-18 31-May-18
B5-CS-DCK-BJ-WBD-110 Rock & Gravel for Dykes 15 0% 31-Mar-18 15-Apr-18 Rock & Gravel for Dykes
B5-CS-DCK-WJ-WBD-260 Concrete Barriers Deck 5 0% 29-Apr-18 06-May-18 Concrete Barriers Deck
B5-CS-DCK-WJ-WBD-280 Lighting Poles Installation - Wadi al Jizi 2 0% 06-May-18 08-May-18 Lighting Poles Installation - Wadi al Jiz
B5-CS-DCK-WJ-WBD-270 Water Proofing Deck 5 0% 08-May-18 14-May-18 Water Proofing Deck
B5-CS-DCK-WJ-WBD-290 Asphalt Pavement Deck 1 0% 14-May-18 15-May-18 Asphalt Pavement Deck
B5-CS-DCK-WJ-WBD-300 Expansion Joints Installation Deck (Strip Seal) 15 0% 14-May-18 31-May-18
Slope Protection 52 0% 31-Mar-18 30-May-18
B5-CS-SPP-WJ-20 Gabions Wadi Al Ji zi Pier 17 to Pier 19 52 0% 31-Mar-18 30-May-18
Location 2: STA 190+ 920 to STA 191+080 70 0% 20-Nov-17 29-Jan-18 29-Jan-18, Location 2: STA 190+920 to STA 191+080
Earth Works 45 0% 20-Nov-17 04-Jan-18 04-Jan-18, Earth Works
B5-CS-EXC-S2-A3-10 Unclassified Excavation 4 0% 20-Nov-17 27-Nov-17 Unclassified Excavation
B5-CS-EMB-S2-A3-10 Embankment 30 0% 20-Nov-17 02-Jan-18 Embankment
B5-CS-SBG-S2-A3-10 Sub-Grade 3 0% 02-Jan-18 04-Jan-18 Sub-Grade
Sub-Base & Base Course 11 0% 04-Jan-18 17-Jan-18 17-Jan-18, Sub-Base & Base Course
B5-CS-SBB-S2-A3-10 Granural Sub-base Course 3 0% 04-Jan-18 08-Jan-18 Granural Sub-base Course
B5-CS-ABC-S2-A3-20 Aggregate Base Course 2 0% 15-Jan-18 17-Jan-18 Aggregate Base Course
Pavement 5 0% 17-Jan-18 23-Jan-18 23-Jan-18, Pavement
B5-CS-BBC-S2-A3-20 Bituminous Base Course 2 0% 17-Jan-18 20-Jan-18 Bituminous Base Course
B5-CS-BWC-S2-A3-10 Bituminous Wearing Course 1 0% 22-Jan-18 23-Jan-18 Bituminous Wearing Course
Utilities 7 0% 05-Jan-18 11-Jan-18 11-Jan-18, Utilities
B5-CS-UTL-S1-AW-20 Laying of ROP Ducts 2 0% 05-Jan-18 06-Jan-18 Laying of ROP Ducts
B5-CS-DNG-S1-AW-50 Chutes 3 0% 09-Jan-18 11-Jan-18 Chutes
Road Lighting & Electrical Installation 4 0% 06-Jan-18 09-Jan-18 09-Jan-18, Road Lighting & Electrical Installation
B5-CS-ELC-S2-A3-100 Lighting Masts Foundations 2 0% 06-Jan-18 07-Jan-18 Lighting Masts Foundations
B5-CS-ELC-S2-A3-80 Ducting 3 0% 06-Jan-18 08-Jan-18 Ducting
B5-CS-ELC-S2-A3-130 Lighting Masts Installation 1 0% 08-Jan-18 08-Jan-18 Lighting Masts Installation
B5-CS-ELC-S2-A3-110 Cabling 1 0% 09-Jan-18 09-Jan-18 Cabling
Street Furnitures 12 0% 09-Jan-18 22-Jan-18 22-Jan-18, Street Furnitures
B5-CS-STF-S2-A3-70 Concrete Barriers 6 0% 09-Jan-18 15-Jan-18 Concrete Barriers
B5-CS-STF-S2-A3-80 Guard Rails 2 0% 21-Jan-18 22-Jan-18 Guard Rails
Finishing 5 0% 24-Jan-18 29-Jan-18 29-Jan-18, Finishing
B5-CS-FIN-S2-A3-20 Road Marking & Road Studs 5 0% 24-Jan-18 29-Jan-18 Road Marking & Road Studs
Location 3: STA 195+ 860 to STA 196+080 87 0% 02-Jan-18 29-Mar-18 29-Mar-18, Location 3: STA 195+ 860 to STA 196+080
Earth Works 57 0% 02-Jan-18 27-Feb-18 27-Feb-18, Earth Works
B5-CS-EMB-S2-A3-20 Embankment 40 0% 02-Jan-18 21-Feb-18 Embankment
B5-CS-SBG-S2-A3-20 Sub-Grade 5 0% 22-Feb-18 27-Feb-18 Sub-Grade
Sub-Base & Base Course 14 0% 27-Feb-18 15-Mar-18 15-Mar-18, Sub-Base & Base Course
B5-CS-SBB-S2-A3-20 Granural Sub-base Course 5 0% 27-Feb-18 05-Mar-18 Granural Sub-base Course
B5-CS-ABC-S2-A3-30 Aggregate Base Course 3 0% 12-Mar-18 15-Mar-18 Aggregate Base Course
Pavement 7 0% 15-Mar-18 24-Mar-18 24-Mar-18, Pavement
B5-CS-BBC-S2-A3-30 Bituminous Base Course 3 0% 15-Mar-18 19-Mar-18 Bituminous Base Course
B5-CS-BWC-S2-A3-20 Bituminous Wearing Course 1 0% 22-Mar-18 24-Mar-18 Bituminous Wearing Course
Utilities 11 0% 28-Feb-18 10-Mar-18 10-Mar-18, Utilities
B5-CS-UTL-S1-AW-30 Laying of ROP Ducts 2 0% 28-Feb-18 01-Mar-18 Laying of ROP Ducts
B5-CS-DNG-S1-AW-60 Chutes 4 0% 06-Mar-18 10-Mar-18 Chutes
Road Lighting & Electrical Installation 7 0% 28-Feb-18 07-Mar-18 07-Mar-18, Road Lighting & Electrical Installation
B5-CS-ELC-S2-A3-160 Cabling 2 0% 28-Feb-18 01-Mar-18 Cabling
B5-CS-ELC-S2-A3-150 Lighting Masts Foundations 5 0% 28-Feb-18 05-Mar-18 Lighting Masts Foundations
B5-CS-ELC-S2-A3-170 Lighting Masts Installation 2 0% 06-Mar-18 07-Mar-18 Lighting Masts Installation
Street Furnitures 15 0% 06-Mar-18 22-Mar-18 22-Mar-18, Street Furnitures
B5-CS-STF-S2-A3-90 Concrete Barriers 6 0% 06-Mar-18 12-Mar-18 Concrete Barriers
B5-CS-STF-S2-A3-100 Guard Rails 3 0% 20-Mar-18 22-Mar-18 Guard Rails
Finishing 5 0% 25-Mar-18 29-Mar-18 29-Mar-18, Finishing
B5-CS-FIN-S2-A3-30 Road Marking & Road Studs 5 0% 25-Mar-18 29-Mar-18 Road Marking & Road Studs
Location 4: STA 202+ 200 to STA 202+400 119 0% 31-Jan-18 31-May-18
Earth Works 97 0% 31-Jan-18 08-May-18 08-May-18, Earth Works

Date Revision Checked Approved


Remaining Level of Effort Actual Work Page 2 of 3
02-Nov-16 REV.1 M.M D.G
Actual Level of Effort Remaining Work
BAT5-REV1-OCT 16 BATINAH EXPRESS WAY - PACKAGE 5- CONSTRUCTION OF BATINAH EXPRESSWAY PACKAGE.5
REVISED SCHEDULE (Finish in 2018) REVISED PROGRAMME OF WORKS - DD: 30 OCTOBER 2016
REQUETED ON 19TH OCTOBER 2016 MEETING

Activity ID Activity Name Remaining Performance Start Finish 2017 2018


Duration % Complete Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
B5-CS-EMB-S2-A3-30 Embankment 70 0% 31-Jan-18 02-May-18 Embankment
B5-CS-SBG-S2-A3-30 Sub-Grade 5 0% 03-May-18 08-May-18 Sub-Grade
Sub-Base & Base Course 9 0% 08-May-18 19-May-18 19-May-18, Sub-Base & Base Co
B5-CS-SBB-S2-A3-30 Granural Sub-base Course 3 0% 08-May-18 12-May-18 Granural Sub-base Course
B5-CS-ABC-S2-A3-40 Aggregate Base Course 2 0% 16-May-18 19-May-18 Aggregate Base Course
Pavement 6 0% 19-May-18 26-May-18 26-May-18, Pavement
B5-CS-BBC-S2-A3-40 Bituminous Base Course 2 0% 19-May-18 21-May-18 Bituminous Base Course
B5-CS-BWC-S2-A3-30 Bituminous Wearing Course 1 0% 24-May-18 26-May-18 Bituminous Wearing Course
Utilities 7 0% 09-May-18 15-May-18 15-May-18, Utilities
B5-CS-UTL-S1-AW-40 Laying of ROP Ducts 2 0% 09-May-18 10-May-18 Laying of ROP Ducts
B5-CS-DNG-S1-AW-70 Chutes 3 0% 13-May-18 15-May-18 Chutes
Road Lighting & Electrical Installation 3 0% 09-May-18 12-May-18 12-May-18, Road Lighting & Electric
B5-CS-ELC-S2-A3-180 Lighting Masts Foundations 2 0% 09-May-18 10-May-18 Lighting Masts Foundations
B5-CS-ELC-S2-A3-190 Cabling 2 0% 09-May-18 10-May-18 Cabling
B5-CS-ELC-S2-A3-200 Lighting Masts Installation 1 0% 12-May-18 12-May-18 Lighting Masts Installation
Street Furnitures 11 0% 13-May-18 24-May-18 24-May-18, Street Furnitures
B5-CS-STF-S2-A3-110 Concrete Barriers 4 0% 13-May-18 16-May-18 Concrete Barriers
B5-CS-STF-S2-A3-120 Guard Rails 3 0% 22-May-18 24-May-18 Guard Rails
Finishing 4 0% 27-May-18 31-May-18
B5-CS-FIN-S2-A3-40 Road Marking & Road Studs 4 0% 27-May-18 31-May-18

Date Revision Checked Approved


Remaining Level of Effort Actual Work Page 3 of 3
02-Nov-16 REV.1 M.M D.G
Actual Level of Effort Remaining Work

Das könnte Ihnen auch gefallen