22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

SkipHeaders

OracleEnterpriseAssetManagementUser'sGuide
Release12.2
Contents Previous Next
PartNumberE4878907

eAMWorkManagement
Thischaptercoversthefollowingtopics:

OvervieweAMWorkManagement
eAMWorkOrders
RoutineWorkOrders
UsingEncumbranceAccountingwithMaintenanceWorkOrders
ExpressWorkOrders
PreventiveMaintenanceWorkOrders
RebuildWorkOrders
EasyWorkOrders
eAMWorkOrderStatuses
DefiningWorkOrderDocuments
eAMOperationsandTasks
DefiningAssetShutdownStatuses
PreparingWorkOrderOperations
ViewingWorkOrderOperations
DefiningInventoryMaterialRequirements
DefiningDirectItemMaterialRequirements
ViewingMaterialRequirements
DefiningResourceRequirements
ViewingResourceRequirements
WorkOrderRelationships
ParentChildRelationship
EndtoStartDependency
CostRelationships
FollowupWorkRelationship
eAMWorkOrderTransactions
OperationCompletion
WorkOrderCompletion
RebuildWorkOrderCompletion
TransactingMaterial

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 1/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

ViewingResourcesTransactions
ClosingWorkOrders
eAMWorkOrderPlanning
UsingtheMaintenanceWorkbench
CapitalizingWorkOrders

OvervieweAMWorkManagement
Theworkorderisthefoundationforallmaintenanceorganizations.Workordersdefinetheresourcesanditemsthatareneededtoconductwork.Theycan
automaticallygeneratethroughtheuseofPreventiveMaintenanceSchedules,theissueofaninventoriedrebuildable,breachofqualityresults,ormanually
generatedasaroutineworkorder.TheseworkordersarethenreviewedandsharedwithOperationstoproduceanestimatedschedule.

OracleEnterpriseAssetManagementintegrateswithOracleQuality.UseQualitycollectionplanstopredefinerequiredfeedbackinformationthatmustbe
enteredintoOracleEnterpriseAssetManagement,uponaworkorder'scompletion.Forexample,datatocollectmayincludeinspectionpointsforasset
numberanddowntimevariables.Ifavarianceisrecordedtothequalityplan,aworkrequestorworkorderiscreated.Youcandefinequalitycollectionplans
directlyontheworkorder,ordefinethemasattributesofanactivitytoultimatelydefaultintofutureworkordersthataregeneratedforspecificassetnumber
andactivitycombinations.

Foreachworkorder,theestimatedcostsaggregate,fromtheassociatedBOMandresources,todevelopacostingprofileforthecurrentworkorder.Youcan
useCostingProfilesforfutureBudgetingandForecasting.

Foreachworkorder,theactualcostsaggregateduringtheworkorder'slifecycle.Thesecostsrollup,basedonthehierarchyofthecurrentworkorder's
associatedassetnumber.Viewtheseactualcostsbyperiodatatransactionleveloratasummarylevel.Costscanrollup,basedonthehierarchyofwork
orders.Youcanviewthecosts(bothactualandestimates)byperiod,atatransactionorsummarylevel.

Thischapterisdividedintothefollowingsections:

eAMWorkOrders

eAMOperationsandTasks

WorkOrderRelationships

eAMWorkOrderTransactions

eAMWorkOrderPlanning

eAMWorkOrders

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 2/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

OracleEnterpriseAssetManagementworkordersarecreatedforassetsandrebuildableinventoryitems.Theyaredefinedmanually,orgenerated
automaticallybasedonascheduledactivity.Ifyouattachanactivitytoamanuallycreatedworkorder(normallytheroleofaPlanner),theworkorderinherits
theactivity'sattributes,suchasthemaintenanceBOM,maintenanceroute(operations),attachments,qualityplans,costinformation,andschedulingrules.
Whenpreplannedworkordersarecreatedforassets,theactivityinformationassociatedwiththeworkorder'scurrentassetnumberautomaticallyattaches
materialandresourcerequirementinformationtotheworkorder.

Youcanprintworkpackets(workorderswithattachments)throughanAutovueserverusingtheEnterpriseAssetManagementorMaintenanceSuperUser
responsibility.

SeeMaintenanceWorkOrderPackagePrintwithAutovueorPrintingWorkPacketsUsingAutovue.

Thissectionincludesthefollowingtopics:

RoutineWorkOrders

UsingEncumbranceAccountingwithMaintenanceWorkOrders

ExpressWorkOrders

PreventiveMaintenanceWorkOrders

RebuildWorkOrders

EasyWorkOrders

eAMWorkOrderStatuses

DefiningWorkOrderDocuments

RoutineWorkOrders
RoutineworkordersarenormallycreatedbyaplannerfromtheMaintenanceWorkbench(See:UsingtheMaintenanceWorkbench),andarealsocreatedusing
amenuoption.Materialandresourceplanning(See:OverviewofPlanningandScheduling)isusedateachstatusoftheroutineworkorder(See:eAMWork
OrderStatuses).

Tomanuallycreateaworkorder

1.NavigatetotheFindWorkOrderswindow(WorkOrders>WorkOrders).

Note:Thisfunctionisavailableforthoseuserswithresponsibilitiesandrolesthatincludefunction,EAM_WO_DETAILS_MODE,withtheirassociated
menu.Otherwise,youcanonlyviewworkorders,andcannotupdateassociatedassethierarchy,workorderhierarchy,material,resource,operation,

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 3/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

cost,collectionplanresults,workrequest,andattachmentinformation.See:ImplementingFunctionSecurity, OracleApplicationsSystemAdministrator's
GuideSecurity .

2.ChooseNew.

WorkOrder

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 4/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

Theheaderinformationdisplaysgeneralinformationabouttheassetnumberandthetypeofworkrequired.

3.TheWorkOrdernumberisassigned,butyoucanupdateit.

4.Enteranassetnumberrequiringmaintenance.Theassetgroupdefaults(See:DefiningAssetNumbers).
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 5/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

5.SelectanAssetActivity.Onlyassetactivitiesassociatedwiththisassetnumberareavailable.

Note:Ifthisworkorderwaspreviouslycreated,youcanaddanassetactivity,aslongastheworkorderisatanUnreleasedorDraftstatus,oran
assetactivitywasnotpreviouslydefined.Ifanytasks,material,orresourcerequirementsexist,thesemustbedeletedbeforeaddinganassetactivityto
anexistingworkorder.

Afterselectinganassetactivity,theassociatedmaintenanceBOM(material)(See:SettingUpMaintenanceBillsofMaterial)andmaintenanceroute
(resources),associatedwiththeactivity(See:DefiningMaintenanceRoutes),attachtotheworkorder.Afteranassetactivityissavedtoaworkorder,
youcannolongerchangeordeleteit.

6.EnteraClasscodetorepresentthecharge(expense)accountsassociatedwiththeassetnumber.Thisdefaultsfromtheassetnumber,butyoucan
updateit.

SelectamaintenanceWIPAccountingClassthatcontainsanencumbranceaccountifwanttouseencumbranceaccounting.

7.EntertheStatus.Forexample,Unreleased,Released,OnHold,andDraft.Certaintransactionsupdatethisstatusautomatically,includingWorkOrder
Completion,forexample(See:eAMWorkOrderStatuses).

8.ThePendingcheckboxvaluedetermineswhethertheworkorderhasreachedthestatusaboveorisstillpending,duetoworkflow.Thisvalueissetby
theWorkOrderWorkflowApprovalprocess.Ifthecheckboxisclear,theStatusreflectsthecurrentstate.Ifthecheckboxisselected,theStatus
reflectsadesiredtargetstatethatisnotyetreachedduetopendingactivity,suchasaworkflowapprovalthatisstillinprogress.

9.IfthisisachildworkorderinaworkordernetworkandParentChildispopulatedintheRelationshipTypefield,theparentworkorderispopulatedin
thisfield.

10.TheRelationshipTypefieldindicatesthetypeofRelationshipassociatedwiththeworkorder.ValidrelationshipsareParentChild,EndtoStart
Dependency,Cost,andFollowupWork.Managecomplexmaintenancejobsthroughthesefourtypesofworkorderrelationships.See:WorkOrder
Relationships.

ParentChild:Thisrelationshipenablesanetworkofworkorders,whichincludesonetoplevelworkorderthatdefinesthetimelineofallits
childrenworkorders.Thestartandenddatesofthechildrenworkordersarewithinthestartandenddatesoftheparentworkorder.Achild
workordercanbeparenttoanotherworkorder.Oneparentcanhavemultiplechildren,butonechildcanhaveasingleparent.Therecanbean
infinitenumberofparentchildworkorderlevels,withintheParentChildrelationship.

EndtoStartDependency:Youcancreateworkorderswithschedulingdependencyrelationships(includingchildsiblingworkorders).Forexample,
oneworkorder'sscheduledstartdateisdependentonanotherworkorder'scompletion.Withthisrelationship,thenextworkordercannotstart
untilthepriorworkorderiscompleted.

Cost:Youcanrollthechildworkordercostsintotheparentworkorder,forreportingpurposes.Youcanbasethecostrollup,withinahierarchy,
onschedulingrelationships.Schedulingrelationshipsarenotrequiredtorollupcostswithinahierarchy.Youcancreateacostreportinghierarchy
thatisdifferentfromtheschedulinghierarchy.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 6/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

FollowupWork:YoucancreateaworkorderforthecurrentcapitalassetnumberorRebuildableItem,whileexecutingworkfortheasseton
anotherworkorder.Forexample,asecondproblemwiththeassetisdiscoveredwhileexecutingaworkorder.Afollowupworkorder,associated
withtheoriginalworkorder,iscreatedfortheissue.Thisisindependentofschedulingorcostrelationships.

11.IntheScheduledDatesregion,entertheworkorder'sscheduledStartdateifitisbasedonaforwardschedule.Theschedulingprocessusesthisdate
asastartingpointtocalculatethescheduledenddateanddurationforallocatedresourcesandmaterial.Ifthematerial/resourcesarenotavailableby
thisdate,theschedulingprocessmovesthestartdateforward.

12.EnterascheduledCompletiondateforbackwardscheduling.Thisdateindicatestherequestedendbydateforthework.Theschedulingprocessuses
thisdateasastartingpointtocalculatethescheduledstartdateanddurationforallocatedresourcesandmaterial.Ifthematerialandresourcesare
notavailablebythatdate,theschedulingprocessmovesthestartdatebackwardstoensurecompletionbytherequiredenddate.

Note:Actualdatesareenteredatoperationandworkordercompletion.ScheduleddatesarecalculatedbytheEnterpriseAssetManagementscheduler
ifyouhaveOracleProductionSchedulingenabled(See:OverviewofSettingUp, OracleProductionSchedulingUser'sGuide
).Otherwise,theEAM
schedulercalculatesthedates.

SeeeAMSchedulingformoreinformation.

13.WithintheMaintab,theDepartmentvaluedefaultsfromtheselectedassetnumber.(See:DefiningAssetNumbers).Thisindicatesthepersonsor
departmentresponsibleforthisassetnumber.

Youcanchangethedepartmentattheoperationlevelifnotransactionshavebeenrecordedfortheworkorder.

14.OptionallyselectaPlannerforthisworkorder.

15.OptionallyselectaPriority,suchasHigh,Medium,orLow.

16.OptionallyselectaWorkOrderType.Workordertypesenableyoutodifferentiateworkorders,forexample,Routine,Preventive,Rebuild,Emergency,or
Facilities.Maintenancemanagementcanusethisinformationtosortandmonitorworkactivitiesforreportingandbudgeting.Workordertypesare
referencedintheworkorder.Forinformationonhowtocreatevalidvalueswithintheavailablelistofvalues,See:WorkOrderTypes.

17.TheShutdownTypedefaultsfromtheactivity.Thishelpstheplannergroupworkordersthatmayrequireshutdowns,sothattheyareplannedtogether.

18.IftheFirmcheckboxisselected,planningandschedulingdoesnotautomaticallyadjusttheschedule,regardlessofmaterialorresourceavailability
OverviewofeAMPlanningandScheduling.Thischeckboxdefaultsasselectedorcleared,dependingontheAutoFirmonReleaseandAutoFirmon
Createcheckboxsettings,establishedintheEnterpriseAssetManagementParameterssetupforthecurrentorganization(See:DefiningeAM
Parameters).ThisdefaultsaftertheworkorderisReleased,ifyouselecttheAutoFirmonReleasecheckbox,anddefaultsimmediatelyifyouselected
theAutoFirmonCreatecheckbox.

Ifthecheckboxisselected,theenddateiscalculated,basedontheworkorderduration.Theschedulerautomaticallycalculatesthedurationbasedon
theoperations(resourcedurationsetup)ontheworkorder.YoucanupdatethischeckboxforworkordersatDraft,Released,Unreleased,OnHold,or
Cancelstatuses(See:eAMWorkOrderStatuses).
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 7/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

IftheFirmcheckboxisselected,youcanstillmanuallyreschedulearesourceontheworkorder,therebyupdatingthedatesonitscorresponding
operationandworkorder.

19.OptionallyselecttheNotificationRequiredcheckbox.

20.OptionallyselecttheTagoutRequiredcheckboxtoindicatethattheAreamustbesecuredforoperationsrequiredtoexecutethisworkorder.Tagsare
generallyprintedandplacedonanasset,warningtheplantthatitisshutdownandshouldnotbestarted.Thischeckboxhelpstheplannerisolatethose
jobsthatrequireatagout.

SelectthepaperclipAttachmentsicontoattachrelevanttagoutdocuments.YoucanattachURL,file,ortextattachments.See:DefiningWorkOrder
Documents.

21.ThePlannedcheckboxisselectedifthecurrentworkorderwascreatedfromforecastedworkorders(See:PreventiveMaintenanceWorkOrders).

22.OptionallyselecttheEnableMaterialIssueRequestscheckboxtoenableeAMtomanagematerialavailabilityforthecurrentworkorder.Materialis
physicallyavailabletoaworkorderviathematerialrequestandverificationprocess.ThischeckboxisselectedbydefaultifitisselectedontheeAM
Parameterswindow.

23.TheConstructionEstimatefieldwilldisplayiftheworkorderwascreatedbyusingtheConstructionEstimateWorkbench.Thefieldisdisplayonly.

24.OptionallyenterFailureInformation(See:FailureAnalysisOverview).TheFailureInformationregionappearsifthe FailureCodeRequiredvalueissetto
Yes
,withintheFailureSetdefinition(See:DefiningFailureCodesandSets).

IftheFailureEntryRequiredcheckboxisselected,FailureCodeentryismandatoryduringworkordercompletion.

25.TheMaterialShortageregionenablesyoutoviewmaterialavailability.Thisregionpopulates,afteryouhavesavedtheworkorder.

TheMaterialShortagefielddisplayswhetherthereisashortageofthematerial(atthatmomentintime)thatisneededtocompletetheworkorder's
operations.Thisstatushelpsyoutodeterminewhentostartwork.Forexample,ifthereisamaterialshortage,youtypicallywouldnotstartwork.The
processthatpopulatesthisfieldconsidersbothstockedanddirectitems.Forstockeditems,theWorkOrderMaterialShortageprocessdetermines
whetheralloftheinventoriedmaterialwithintheworkorder'sassociatedBOMisavailabletotransact(ATPisnotconsidered).Fordirectitems,theWork
OrderMaterialShortageprocessdeterminesifallofthedirectitemsthatareincludedwithintheworkorder'sassociatedBOMarereceivedinto
Inventory.Thisprocessshouldbesettoautomaticallyexecuteperiodically,butyoucanexecuteitfromthemenuatanytime.

YoucanchooseCheckShortagetoviewtheshortagedetails.

26.SelecttheActivitytabtoselectalternate,predefinedBOMsandRoutings.See:SettingUpMaintenanceBillsofMaterialandDefiningMaintenance
Routes.

AfterthealternateBOMandRoutingareselected,thesystemusestheassociateditemsandassignstheassociatedresourcesneededtoexecutethe
workorder.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 8/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

27.OptionallyselectanActivityType.Thiscodeindicatesthetypeofmaintenanceforthisactivityandisusedwhendefiningajoborastandardjob,for
example,Inspection,Overhaul,Lubrication,Repair,Servicing,orCleaning.Thisvaluedefaultsfromtheactivity(See:DefiningActivities).

28.OptionallyselectanActivityCausetospecifywhatsituationcausedthisworktogenerate,forexample,Breakdown,Vandalism,NormalWear,or
Settings.Thisvaluedefaultsfromtheactivity.

29.OptionallyselectanActivitySourcetospecifyreasonsthatactivitiesrequireexecution,forexample,WarrantyCompliance,OSHACompliance,orMilitary
SpecificationRequirements.

Thisvaluedefaultsfromtheactivity.

30.OptionallyselecttheProjecttab.ThistabisenabledonlyifProjectManufacturingisinstalledandenabled.

a.OptionallyselectaProject.

b.OptionallyselectaTask.

31.YoucanselecttheRebuildtabifthisworkorderiscreatedforarebuildableitem.See:RebuildWorkOrders.

32.OptionallyselecttheRequesttabtodisplayserviceandworkrequestsassociatedwiththisworkorder.

Youcanaddserviceorworkrequeststoaworkorderbyselectingaservicerequestorrequestnumber,respectively.OnlyworkrequestsatanAwaiting
WorkOrderstatusandMaintenanceTypeservicerequestsatanOpenstatusareavailableforassociation.Youmayassociatemultipleworkrequeststo
asingleworkorder,butonlyoneworkordercanassociatewithaservicerequest.Youcanassociateaservicerequesttomultipleworkorders.Youcan
dissociateaworkrequestfromaworkorder.

Ifyouwanttoviewaworkrequestattachment,highlighttheworkrequestandthenselectView,Attachments.Ifthereareanyattachmentsassociated
withtheworkrequest,youwillbeabletoviewthem.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 9/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

Todeleteaworkrequest:

a.Highlighttheworkrequest.

b.ChooseDelete.

33.OptionallyselecttheApprovalHistorytabtoviewtheworkorder'sapprovalhistory.Aworkordermightrequireapprovalsornotificationsatdifferent
stagesofitslifecycle.Forexample,organizationstypicallywantanapprovalprocessinplacebeforeaworkorderisreleased.Workflowautomatesthis
process.YoucaninitiateWorkflowtogeneratenotifications,approvals,transactions,andupdateaworkorderstatus.YoucanenableWorkflowforWork
OrderswithintheeAMParameters(See:DefiningeAMParameters).YoucansetupBusinessEventsandEventSubscriptions(oruseseededeventsand
subscriptions)withinOracleWorkflowtoindicatewhateventstriggerWorkflow.SeededeventsthatyoucanenabletotriggerWorkflowareWorkOrder
creation,WorkOrderreleaseapproval,WorkOrdercompletion,WorkOrderstatuschange,Operationcompletion.See:SettingUpOracleWorkflow,
OracleWorkflowUser'sGuide,SettingUptheBusinessEventSystem, OracleWorkflowUser'sGuide
,andDefiningWorkOrderStatuses).

34.OptionallychooseOperationstopreparenecessaryoperations.Theseoperationsdefaultfromthemaintenanceroute(See:DefiningMaintenance
Routes)associatedwiththecurrentactivity,butyoucanupdateandaddtothem(See:PreparingWorkOrderOperations).

Youcanchangetheoperationsifnotransactionshavebeenrecordedfortheworkorder.

35.OptionallychooseMaterialstovieworadditemsfromtheassociatedassetnumber'sitemslist(See:SettingUpMaintenanceBillsofMaterialand
DefiningMaterialRequirements).FromtheMaterialRequirementswindow,youcanoptionallychooseSelectMaterialstoaddmaterialsfromthisAsset
BOMtothematerialrequirementsforthecurrentworkorder.

36.OptionallychooseResourcestoview,add,orupdatetheresourcesassignedtoeachoperation.See:DefiningResourceRequirements.

Youcanchangetheresourcesforthisworkorderattheoperationlevelifnotransactionshavebeenrecordedfortheworkorder.

37.OptionallychooseRelationshipstomanageworkorderschedulesandviewworkorderdetails.See:WorkOrderRelationships.

38.OptionallychooseAssetRoutetoviewtheassetrouteassociatedwiththecurrentworkorder'sassetgroup.Youmayneedtoperformoneactivityon
multipleassetnumbers.Toeliminatethepossibilityofcreatingmultipleworkordersforthesameactivity,youcandefineassetroutes.See:Defining
AssetRoutes.

YoucanchooseAssetRouteifanassetrouteisassociatedwiththecurrentassetnumber.

39.OptionallychooseCoststoviewthecostsofworkordersfallinginthespecificaccountingperiods,specifiedintheAccountingInformationbyPeriod
region.AccountingPeriodsaredefinedwithinOracleGeneralLedger.See:DefiningPeriodTypes, OracleGeneralLedgerUser'sGuide
andDefining
Calendars, OracleGeneralLedgerUser'sGuide
.

a.Optionallyselectaworkorder,thenchooseValueSummarytoviewasummaryoftheactual,estimated,andvariancecostsforlaborhours,
equipmenthours,andmaterialagainstthecurrentworkorder.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 10/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

ActualCosts:Thisistheaccumulationofallcostsformaterialandresourcetransactionsfortheassetnumber'sassociatedmaintenance
workorders,basedonaspecifiedperiod.

Estimates:ABOM(materialpartslist)androuting(resources)canassociatewithaworkorder.
WhenyouselecttheEstimatestab,theestimatedcostsofallmaterialandresourcesassociatedwithaworkorderappear,enablingyouto
budgetcosts.

Variances:Thedifferencebetweentheactualcostsrecordedandestimatedcosts.
Material:Allmaterialandmaterialoverheadtransactioncosts.
Labor:Allresourceandresourceoverheadtransactioncostsassociatedwithpersonnel.
Equipment:Allmaterialresourceandresourceoverheadtransactioncosts.
b.OptionallychooseDetailstoviewactual,estimated,andvariancecostsforlaborhours,equipmenthours,andmaterialforspecificoperationsof
thecurrentworkorder.

40.Optionallyselectaworkorder,thenchooseValueSummarytoviewasummaryoftheactual,estimated,andvariancecostsforlaborhours,equipment
hours,andmaterialagainstthecurrentworkorder.

41.Saveyourwork.

Aftersavingaworkorder,youcanoptionallyassociateassetattachments:(M)Tools>CopyAssetAttachments.

RelatedTopics

DefiningAssetDocuments

OverviewofeAMCostManagement

FailureAnalysisOverview

UsingEncumbranceAccountingwithMaintenanceWorkOrders
YoumustspecifyanencumbranceaccountfortheWIPAccountingClassusedformaintenance(shopfloor)workorders.

TodefineaWIPAccountingClasstouseencumbranceaccounting

1.NavigatetotheWIPAccountingClasswindow(EnterpriseAssetManagement>WIPAccountingClasses).

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 11/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

2.Definealltherequiredfieldsonthepage.

SeeDefiningWIPAccountingClasses, OracleWorkinProcessUser'sGuide).
3.SelecttheEncumbranceAccountingfield,andentertheencumbranceaccounttobeusedtocapturetheexpenses.

4.Saveyourwork.

ExpressWorkOrders
Youcanusethenewexpressworkorderfeaturetocaptureworkthathasbeencompleted.Thesetypesofworkordersarealsoknownas'emergencywork
orders.'

Youcancreateanewworkorder,chargetimetoitandcompleteitatthesametime.

RelatedTopics

CreatingExpressWorkOrders

PreventiveMaintenanceWorkOrders
OracleEnterpriseAssetManagementenablesyoutogenerateworkordersautomaticallybasedonmeterreadings,runtimeintervals,andcalendardays.
Preventivemaintenanceactivitiesreducetheprobabilityoffailureordegradationoftheassets'physicalconditions.Theseactivitiesareexecutedperiodically,
byusage,orbasedontheconditionofanassetnumber(assetorrebuildableserialnumber).Metersareenteredtomeasureanyassetnumberthatneedsto
bemeasuredandperiodicallyserviced,basedonthemeasurement.Forexample,apipemaystartoutat12millimeters,butwhenitwearstoonlyfour
millimeters,itneedstobereplaced(See:Meters).

Schedulingdefinitionsaredefinedtocreateforecasted,scheduledworkorders,basedonmeterreadings.YoucancreateaPreventiveMaintenancescheduling
definition(See:PreventiveMaintenanceScheduling)foranassetnumberorrebuildableitemandactivitycombination(See:AssociatingAssetNumberswith
Activities),oranassetroute(See:DefiningAssetRoutes).AfteryouhavedefinedPreventiveMaintenanceschedulingdefinitions,thePreventiveMaintenance
schedulerprocessmayexecute.YoucanviewtheseforecastedworkordersusingtheMaintenanceWorkbench(See:UsingtheMaintenanceWorkbench).You
canexecutetheGeneratePreventiveMaintenanceWorkOrdersprocess.Whenthisprocessexecutes,workordersarecreatedwithastatusofUnreleased.
(See:GeneratingWorkOrders).YoucanchoosetheImplementbuttontochangethestatusoftheUnreleasedworkorderstoReleasedworkorders.

ForecastedWorkOrders

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 12/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

RelatedTopics

PreventiveMaintenanceOverview

RebuildWorkOrders
Rebuildworkordersarecreatedaschildworkorders.

Forexample,aworkorderwasissuedfortheinspectionofapump.Duringthepumpinspection,youfoundthatthemotor,oneofthecomponentsofthe
pump,isproblematic.Youhavetwooptions:Youcanrepairandthenreinstallthismotor(rebuildableitem),oryoucanreplacetherebuildableitembyissuing
anewmotorrebuildableitemfrominventory.Ifyouchoosetoperformamaterialissuefrominventory,theoldmotorrebuildableitemattachestothework
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 13/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

order,automaticallycreatingthechild,therebuildworkordernumberassociatedtotheparentworkorder.Inthiscase,theassetnumbergenealogywould
automaticallyupdatetoidentifythisnewitemnumber.See:OverviewofInventoryTransactions, OracleInventoryUser'sGuide
.

Ifyouchoosetorepairandthenreinstalltheproblematicmotorrebuildableitem,youcanmanuallycreatethechildrebuildworkorderfortheoldmotor
(rebuildableitem).

Theinstructionsbelowshowyoutheoptionofcreatingarebuildworkorderwithoutissuinganynewmaterial.Therebuildableitemisreplacedbackintothe
asset(motorplacedbackintothepump,forexample),anddoesnotgotoasubinventorywhentheworkorderiscompleted.Inthiscase,theassetnumber
genealogyisnotupdated.

Tocreaterebuildworkorders

1.NavigatetotheRebuildWorkOrderswindow(WorkOrders>RebuildableWorkOrders).

Note:Thisfunctionisavailableforthoseuserswithresponsibilitiesandrolesthatincludefunction,EAM_WO_DETAILS_MODE,withtheirassociated
menu.Otherwise,youcanonlyviewworkorders,andcannotupdateassociatedassethierarchy,workorderhierarchy,material,resource,operation,
cost,collectionplanresults,workrequest,andattachmentinformation.See:ImplementingFunctionSecurity, OracleApplicationsSystemAdministrator's
GuideSecurity .

2.ChooseNew.

RebuildWorkOrder

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 14/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

Theheaderinformationdisplaysgeneralinformationabouttherebuildableitemandthetypeofworkrequired.

3.Aworkordernumberisassigned,butyoucanupdateit.

4.OptionallyenteraDescriptionforthisworkorder,upto240characters.
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 15/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

5.OptionallyselectanAssetNumber(serialnumber)fromthelistofvalues(See:DefiningRebuildableItemsandGeneratingSerialNumbers, Oracle
InventoryUser'sGuide
.

6.EnterorselectaRebuildItemrequiringmaintenance.

7.OptionallyselectaRebuildActivity.

OnlyactivitiesassociatedwiththisRebuildableItemareavailable(See:RebuildableItem/ActivityAssociation).Ifanactivitydoesnotexist,youcanadd
operations,andmaterial/resourcerequirementstothisworkordermanually.See:DefiningMaterialRequirements,DefiningResourceRequirements,and
PreparingWorkOrderOperations.Ifanactivitydoesexist,youcanupdatethematerialandresourcesbychoosingtheMaterialsorResourcesbuttons
fromthiswindoworbyutilizingtheMaintenanceWorkbench(See:UsingtheMaintenanceWorkbench).

8.EnteraClasscode.

Thisrepresentsthecharge(expense)accountsassociatedwiththeassetnumber.Thisdefaultsfromtheassetnumber(See:DefiningAssetNumbers)
andcanbeupdated.

9.EntertheStatus.Forexample,Unreleased,Released,OnHold,andDraft.Certaintransactionsupdatethisstatusautomatically,includingWorkOrder
Completion,forexample(See:eAMWorkOrderStatuses).

10.ThePendingcheckboxvaluedetermineswhethertheworkorderhasreachedthestatusaboveorisstillpending,duetoworkflow.Ifthecheckboxis
clear,theStatusreflectsthecurrentstate.Ifthecheckboxisselected,theStatusreflectsadesiredtargetstatethatisnotyetreachedduetopending
activity,suchasaworkflowapprovalthatisstillinprogress.

11.IfthisisachildworkorderinaworkordernetworkandParentChildispopulatedintheRelationshipTypefield,theParentworkorderispopulatedin
thisfield.

ThisfieldisalsopopulatedifyouselectedaRebuildSourceworkorder,withintheRebuildtab.

12.TheRelationshipTypefieldindicatesthetypeofRelationshipassociatedwiththeworkorder.

ValidrelationshipsareParentChild,EndtoStartDependency,Cost,andFollowupWork.Managecomplexmaintenancejobsthroughthesefourtypesof
workorderrelationships.See:WorkOrderRelationships.

ParentChild:Thisrelationshipenablesanetworkofworkorders,whichincludesonetoplevelworkorderthatdefinesthetimelineofallitschild
workorders.

Thestartandenddatesofthechildworkordersarewithinthestartandenddatesoftheparentworkorder.Achildworkordercanbeparentto
anotherworkorder.Oneparentcanhavemultiplechildren,butonechildcanhaveasingleparent.

EndtoStartDependency:Youcancreateworkorderswithschedulingdependencyrelationships(includingchildsiblingworkorders).Forexample,
oneworkorder'sscheduledstartdateisdependentonanotherworkorder'scompletion.Withthisrelationship,thenextworkordercannotbe

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 16/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

createduntilthepriorworkorderforthecurrentassetiscompleted.

Cost:Youcanrollthechildworkordercostsintotheparentworkorder,forreportingpurposes.
Youcanbasethecostrollup,withinahierarchy,onschedulingrelationships.Schedulingrelationshipsarenotrequiredtorollupcostswithina
hierarchy.Youcancreateacostreportinghierarchythatisdifferentfromtheschedulinghierarchy.

FollowupWork:YoucancreateaworkorderforthecurrentcapitalassetnumberorRebuildableItem,whileexecutingworkfortheasseton
anotherworkorder.Forexample,asecondproblemwiththeassetisdiscoveredwhileexecutingaworkorder.Afollowupworkorder,associated
withtheoriginalworkorder,iscreatedfortheissue.Thisisindependentofschedulingorcostrelationships.

13.IntheScheduledDatesregion,entertheworkorder'sscheduledStartdateifitisbasedonaforwardschedule.

Theschedulingprocessusesthisdateasastartingpointtocalculatethescheduledenddateanddurationforallocatedresourcesandmaterial.Ifthe
material/resourcesarenotavailablebythisdate,theschedulingprocessmovesthestartdateforward(See:eAMScheduling).

Note:Actualdatesareenteredatoperationandworkordercompletion.ScheduleddatesarecalculatedbytheEnterpriseAssetManagementscheduler
ifyouhaveOracleProductionSchedulingenabled(See:OverviewofSettingUp, OracleProductionSchedulingUser'sGuide
).Otherwise,theEAM
schedulercalculatesthedates.

14.EnterascheduledCompletiondateforbackwardscheduling.Thisdateindicatestherequestedendbydateforthework.

Theschedulingprocessusesthisdateasastartingpointtocalculatethescheduledstartdateanddurationforallocatedresourcesandmaterial.Ifthe
materialandresourcesarenotavailablebythatdate,theschedulingprocessmovesthestartdatebackwardstoensurecompletionbytherequiredend
date(See:eAMScheduling).

Note:Actualdatesareenteredatoperationandworkordercompletion.ScheduleddatesarecalculatedbytheEnterpriseAssetManagementscheduler
ifyouhaveOracleProductionSchedulingenabled(See:OverviewofSettingUp, OracleProductionSchedulingUser'sGuide
).Otherwise,theEAM
schedulercalculatesthedates.

15.WithintheMaintab,theDepartmentdefaultsfromtheselectedassetnumber(See:DefiningAssetNumbers).Thisindicatesthepersonsordepartment
responsibleforthisassetnumber.

16.OptionallyselectaPriority.Forexample,High,Medium,orLow.

17.OptionallyselectaWorkOrderType.Workordertypesenableyoutodifferentiateworkorders,forexample,Routine,Preventive,Emergency,orFacilities.

Maintenancemanagementcanusethisinformationtosortandmonitorworkactivityforreportingandbudgeting.WorkOrderTypesarereferencedin
theworkorder.Forinformationonhowtocreatevalidvalueswithintheavailablelistofvalues,See:WorkOrderTypes.

18.TheShutdownTypedefaultsfromtheRebuildActivity.Thishelpstheplannergroupworkordersthatmayrequireshutdowns,sothattheyareplanned
together.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 17/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

19.IftheFirmcheckboxisselected,planningandschedulingdoesnotadjusttheschedule,regardlessofmaterialorresourceavailability(See:Overviewof
PlanningandScheduling).

Thischeckboxdefaultsasselectedorcleared,dependingontheAutoFirmonReleaseandAutoFirmonCreatecheckboxsettings,establishedinthe
EnterpriseAssetManagementParameterssetupforthecurrentorganization(See:DefiningeAMParameters).Thisdefaultsaftertheworkorderis
Released,ifyouselecttheAutoFirmonReleasecheckbox,anddefaultsimmediatelyifyouselectedtheAutoFirmonCreatecheckbox.

Ifthecheckboxisselected,theenddateiscalculated,basedontheworkorderduration.Theschedulerautomaticallycalculatesthedurationbasedon
theoperations(resourcedurationsetup)ontheworkorder.YoucanupdatethischeckboxforworkordersatDraft,Released,Unreleased,OnHold,or
Cancelstatuses(See:eAMWorkOrderStatuses).

IftheFirmcheckboxisselected,youcanstillmanuallyreschedulearesourceontheworkorder,therebyupdatingthedatesonitscorresponding
operationandworkorder.

20.OptionallyselecttheNotificationRequiredcheckbox.

21.OptionallyselecttheTagoutRequiredcheckboxtoindicatethattheareamustbesecuredforoperationsrequiredtoexecutethisworkorder.

Tagsaregenerallyprintedandplacedonanasset,warningtheplantthatitisshutdownandshouldnotbestarted.Thischeckboxhelpstheplanner
isolatethosejobsthatrequireatagout.

SelectthepaperclipAttachmentsicontoattachrelevanttagoutdocuments.YoucanattachURL,file,ortextattachments.See:DefiningWork
OrderDocuments.

22.ThePlannedcheckboxisselectedifthecurrentworkorderwascreatedfromforecastedworkorders(See:PreventiveMaintenanceWorkOrders).

23.OptionallyselecttheEnableMaterialIssueRequestscheckboxtoenableeAMtomanagematerialavailabilityforthecurrentworkorder.

Materialisphysicallyavailabletoaworkorderviathematerialrequestandverificationprocess.

24.OptionallyenterFailureInformation(See:FailureAnalysisOverview).

TheFailureInformationregionappearsifthe FailureCodeRequiredvalueissettoYes,withintheFailureSetdefinition(See:DefiningFailureCodesand
Sets).

IftheFailureEntryRequiredcheckboxisselected,FailureCodeentryismandatoryduringworkordercompletion.

25.TheMaterialShortageregionenablesyoutoviewmaterialavailability.Thisregionpopulates,afteryouhavesavedtheworkorder.

TheMaterialShortagefielddisplayswhetherthereisashortageofthematerial(atthatmomentintime)thatisneededtocompletetheworkorder's
operations.Thisstatushelpsyoutodeterminewhentostartwork.Forexample,ifthereisamaterialshortage,youtypicallywouldnotstartwork.The
processthatpopulatesthisfieldconsidersbothstockedanddirectitems.Forstockeditems,theWorkOrderMaterialShortageprocessdetermines
whetheralloftheinventoriedmaterialwithintheworkorder'sassociatedBOMisavailabletotransact(ATPisexcluded).Fordirectitems,theworkorder
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 18/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

MaterialShortageprocessdeterminesifallofthedirectitemsthatareincludedwithintheworkorder'sassociatedBOMarereceivedintoInventory.This
processshouldbesettoautomaticallyexecuteperiodically,butyoucanexecuteitfromthemenuatanytime.

YoucanchooseCheckShortagetoviewtheshortagedetails.

26.OptionallyselecttheActivitytabtoselectalternate,predefinedBOMsandRoutings.See:SettingUpMaintenanceBillsofMaterialandDefining
MaintenanceRoutes.

AfterthealternateBOMandRoutingareselected,thesystemusestheassociateditemsandassignstheassociatedresourcesneededtoexecutethe
workorder.

a.OptionallyselectanActivityType.Thiscodeindicatesthetypeofmaintenanceforthisactivityandisusedwhendefiningajoborastandardjob,
forexample,Inspection,Overhaul,Lubrication,Repair,Servicing,orCleaning.Thisvaluedefaultsfromtheactivity(See:DefiningActivities).

b.OptionallyselectanActivityCausetospecifywhatsituationcausedthisworktogenerate,forexample,Breakdown,Vandalism,NormalWear,or
Settings.Thisvaluedefaultsfromtheactivity(See:DefiningActivities).

c.OptionallyselectanActivitySourcetospecifyreasonsactivitiesneedexecution,forexample,WarrantyCompliance,OSHACompliance,orMilitary
SpecificationRequirements.Thisvaluedefaultsfromtheactivity(See:DefiningActivities).

27.OptionallyselecttheProjecttab.ThistabisenabledifProjectManufacturingisinstalledandenabled.

a.OptionallyselectaProject.

b.OptionallyselectaTask.

28.YoucanselecttheRebuildtabtoselecta RebuildSource
workorder.Thisworkorderistheparenttothecurrentchildworkorder.The ChargeAsset
fieldispopulatedwiththeparentworkorder'sassociatedasset.

29.OptionallyselecttheRequesttabtodisplayserviceandworkrequestsassociatedwiththisworkorder.Youcanaddserviceorworkrequeststoawork
orderbyselectingaservicerequestorrequestnumber.WorkrequestsatanAwaitingWorkOrderstatusandMaintenanceTypeservicerequestsare
availableforassociation.Youmayassociatemultipleworkrequeststoasingleworkorder,butoneworkordercanassociatewithaservicerequest.You
canassociateaservicerequesttomultipleworkorders.Youcandissociateaworkrequestfromaworkorder.

a.HighlighttheWorkRequest.

b.ChooseDelete.

30.OptionallyselecttheApprovalHistorytabtoviewtheworkorder'sapprovalhistory.Aworkordermightrequireapprovalsornotificationsatdifferent
stagesofitslifecycle.Forexample,organizationstypicallywantanapprovalprocessinplacebeforeaworkorderisreleased.Workflowautomatesthis
process.YoucaninitiateWorkflowtogeneratenotifications,approvals,transactions,andupdateaworkorderstatus.YoucanenabletheWorkflowfor
WorkOrdersoptionwithintheeAMParameters(See:DefiningeAMParameters).YoucansetupBusinessEventsandEventSubscriptions(oruse

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 19/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

seededeventsandsubscriptions)withinOracleWorkflowtoindicatewhateventstriggerWorkflow.Seededeventsthatyoucanenabletotrigger
Workfloware:WorkOrdercreation,WorkOrderreleaseapproval,WorkOrdercompletion,WorkOrderstatuschange,Operationcompletion.See:Setting
UpOracleWorkflow, OracleWorkflowUser'sGuide
,SettingUptheBusinessEventSystem, OracleWorkflowUser'sGuide
,andDefiningWorkOrder
Statuses).

31.OptionallychooseOperationstopreparenecessaryoperations.Theseoperationsdefaultfromthemaintenanceroute(See:DefiningMaintenance
Routes)associatedwiththecurrentactivity,butyoucanaddorupdatethem(See:PreparingWorkOrderOperations).

32.OptionallychooseMaterialstoview,add,orupdatetheassociatedassetnumber'sitemslist(See:SettingUpMaintenanceBillsofMaterialandDefining
MaterialRequirements).FromtheMaterialRequirementswindow,youcanoptionallychooseSelectMaterialstoaddMaterialsfromtheAssetBOMtothe
materialrequirementsforthecurrentworkorder.

33.OptionallychooseResourcestoview,add,orupdatetheresourcesassignedtoeachoperation.See:DefiningResourceRequirements.

34.OptionallychooseRelationshipstomanageworkorderschedulesandviewworkorderdetails.ThisbuttonisenabledifaRelationshipTypewas
previouslyselected.See:WorkOrderRelationships

35.OptionallychooseAssetRoutetoviewtheassetrouteassociatedwiththeassetgroupforthecurrentworkorder.Youmightneedtoperformone
activityonmultipleassetnumbers.Toeliminatethepossibilityofcreatingmultipleworkordersforthesameactivity,youcandefineassetroutes.See:
DefiningAssetRoutes.

YoucanchooseAssetRouteifanassetrouteisassociatedwiththecurrentassetnumber.

36.OptionallychooseCoststoviewthecostsofworkordersfallinginthespecificaccountingperiods,specifiedintheAccountingInformationbyPeriod
region.AccountingPeriodsaredefinedwithinOracleGeneralLedger.See:DefiningPeriodTypes, OracleGeneralLedgerUser'sGuide
andDefining
Calendars, OracleGeneralLedgerUser'sGuide
.

a.Optionallyselectaworkorder,thenchooseValueSummarytoviewasummaryoftheactual,estimated,andvariancecostsforlaborhours,
equipmenthours,andmaterialagainstthecurrentworkorder.

MaintenanceWorkOrderValueSummary

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 20/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

ActualCosts:Thisistheaccumulationofallcostsformaterialandresourcetransactionsfortheassetnumber'sassociatedmaintenance
workorders,basedonaspecifiedperiod.

Estimates:ABOM(materialpartslist)androuting(resources)canassociatewithaworkorder.
WhenyouselecttheEstimatestab,theestimatedcostsofallmaterialandresourcesassociatedwithaworkorderappear,enablingyouto
budgetcosts.

Variances:Thedifferencebetweentheactualcostsrecordedandestimatedcosts.
Material:Allmaterialandmaterialoverheadtransactioncosts.
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 21/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

Labor:Allresourceandresourceoverheadtransactioncostsassociatedwithpersonnel.
Equipment:Allmaterialresourceandresourceoverheadtransactioncosts.
b.OptionallychooseDetailstoviewactual,estimated,andvariancecostsforlaborhours,equipmenthours,andmaterialforspecificoperationsof
thecurrentworkorder.

37.Saveyourwork.

Aftersavingaworkorder,youcanoptionallyassociateassetattachments:(M)Tools>CopyAssetAttachments

Note:Arequirementforrebuildworkordersthatarecreatedautomaticallyviaamaterialtransactionisthatthecompletionsubinventorymustbean
expensesubinventory(See:SubinventoryGeneralLedgerAccountFields, OracleInventoryUser'sGuide
andWorkOrderCompletion).

Note:Arebuildworkorder'sowningdepartmentdefaultsfromtheowningdepartmentofitsparentworkorder.Thisisviewablewhenyouselectthe
Maintab.

RelatedTopics

DefiningAssetDocuments

OverviewofeAMCostManagement

FailureAnalysisOverview

EasyWorkOrders
Easyworkordersareunplannedworkorders,andenableyoutoavoidoperationandresourceplanning.Anactivitydoesnotdefaultintotheworkorder,based
ontheassetnumberandactivityassociationaswithplannedworkorders,however,youcanaddanactivitytoaneasyworkorder.Theseworkordersare
onlycreatedinMaintenanceUser.Workorderscanbecreatedatanystatus,suchasReleased(See:eAMWorkOrderStatuses),enablingyoutoexecutethe
workorderbyrequestingmaterialandcharginglabor.

eAMWorkOrderStatuses
AnEnterpriseAssetManagementworkordermayprogressthroughseveralstatuses,throughoutitslifecycleduration.Thediagrambelowillustrateshow
EnterpriseAssetManagementworkordersmightstartataDraftstatus,thenmovetoReleased,Complete,andfinallyClosed.Thesestatusescanvary,
dependingonthetypeofworkorderthatiscreated.Forexample,expressworkordersarecreatedinaReleasedstatus,bypassingtheDraftstatus.

eAMWorkOrderLifecycle

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 22/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

Status Description
Draft InfiniteresourcecapacityschedulingofworkordersataDraftstatusmaytakeplace.Youcannotchargelabor,orrequestmaterialforworkordersatthisstatus.
Released AfteraworkorderisReleased,youcanexecuteaworkorder.Youcanchargelabor,requestmaterial,andschedulingforthisworkordertakesplace(See:eAM
Scheduling)tocreatethescheduledstartorenddate.YoucanreleaseaworkorderfromtheWorkOrderswindow(See:RoutineWorkOrders),andtheMaintenance
Workbench(See:UsingtheMaintenanceWorkbench).
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 23/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

Ifyoucreateaworkorderwithafuturedateandthenreleaseit,thereleasedateisthesystemdate.Ifyoucreateaworkorderwithadateinthepastandthen
releaseit,thereleasedateisthescheduledstartdate,sinceyoucanposttransactionsduringanytimeafterthescheduledstartdate(evenifitisinpast).Therelease
datehasadirectrelationshipwithcosting,andtransactionsforaworkordercannotbepostedbeforeitsreleasedate.Thereleasedatemightappeardifferentfrom
thestartdate,becauseoftimezoneconversions.

Unreleased YoucanmoveanEnterpriseAssetManagementworkorderinDraftorReleasedstatustoUnreleased.Schedulingcantakeplacefortheseworkorders(See:eAM
Scheduling)butyoucannotchargelabororrequestmaterial.AnUnreleasedworkordercannotbechangedtoaDraftstatus.
Pending IftheSchedulerisenabled,theworkorderstatuschangestoPendingScheduling,ifastatusofReleasedischosen.AftertheSchedulerprocessfinishesrunning,the
Scheduling statuschangesbacktoReleased.
Complete ACompletestatusforanEnterpriseAssetManagementworkorderdoesnotrequireanycompletedoperations.Whenaworkorderiscompleted,youcanstillcharge
labor,receivedirectitems,issueremainingmaterialallocationsand/ordeleteremainingmaterialallocations.Demandwillremainforunissuedmaterialsunlessthese
aredeleted.YoucanuncompleteaworkorderthistransitionsittoaReleasedstatus.Uncompletionisperformedwithintheworkordercomplete/uncompletepages
intheMaintenanceSuperUserresponsibility(SeeWorkOrderCompletion.Youcancloseanduncompleteworkorderswiththisstatus.
Complete ACompleteNoChargesstatusforanEnterpriseAssetManagementworkorderdoesnotrequireanycompletedoperations.Youcannotchargelaboratthisstatus
No norissuematerials.Remainingmaterialallocationswillbeautomaticallydeleted.Validationofopenpurchasingrequirementswilloccurduringworkorderupdateto
Charges 'completenocharges'status.
Youcannotupdateassociatedassethierarchy,workorderhierarchy,material,resource,operation,cost,collectionplanresults,workrequest,andattachment
informationonaworkorderthatisataCompleteNoChargesstatus.WorkordersinthisstatuscanbeclosedandcanbeupdatedtoaCompletestatus.Applicable
workordersinthisstatusareeligibleforWorkOrderBillingandWorkOrderCapitalization.
Closed YoucannotchargeanyaccountsafteranEnterpriseAssetManagementworkorderisclosed.Youcancloseanduncompleteworkorderswiththisstatus.Ifawork
orderwasataCompletestatusatthetimeofclosingit,youcanuncompletetheworkordertobringitbacktoaCompletestatus.Forallotherstatusesduringwork
orderclosing,theworkorderistransitionedtosamestatusithadwhileclosing.See:ClosingWorkOrders.
Youcannotupdateassociatedassethierarchy,workorderhierarchy,material,resource,operation,cost,collectionplanresults,workrequest,andattachment
informationonaworkorderthatisataClosedstatus.
OnHold EnterpriseAssetManagementworkordersatReleasedandUnreleasedstatusescanbeputonhold.Youcannotchargelabororrequestmaterialforaworkorderat
thisstatus.
Cancel YoucancancelanEnterpriseAssetManagementworkorderatanystatusinitslifecycle.
Youcannotupdateassociatedassethierarchy,workorderhierarchy,material,resource,operation,cost,collectionplanresults,workrequest,andattachment
informationonaworkorderthatisataCancelstatus.

DefiningWorkOrderDocuments
Youcanattachexistingdocumentstoaworkorder,andcreatetexttoassociatewithaworkorder.Youcanattachtextandfiles,suchasspreadsheets,
graphics,andOLEobjects.

Todefineworkorderdocuments

1.NavigatetotheEAMWorkOrderDocumentswindow.

EAMWorkOrderDocuments
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 24/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

2.SelectaDataType.

RelatedTopics

WorkingWithAttachments, OracleApplicationsUser'sGuide
eAMOperationsandTasks
Operationsonaworkorderaretheinstructionsortaskstoperformarepair.Theseoperationsareassignedresources,forexample,tradespeople,outside
serviceproviders,andequipment.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 25/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

Thissectionincludesthefollowingtopics:

DefiningAssetShutdownStatuses

PreparingWorkOrderOperations

ViewingWorkOrderOperations

DefiningInventoryMaterialRequirements

DefiningDirectItemMaterialRequirements

ViewingMaterialRequirements

DefiningResourceRequirements

ViewingResourceRequirements

DefiningAssetShutdownStatuses
Shutdownofanassetissometimesnecessarytoperformamaintenanceactivity.Youcancreatenewshutdowninformationassociatedwithanasset,orview
existingshutdownhistoryinformationalreadyrecordedtoanasset.Shutdowninformationconsistsofstartandenddates,workordernumbersrequiring
maintenanceontheasset,andspecificoperationsequences.Whilecompletingaworkordertoitsoperations,youcanviewassetshutdowninformationinthe
AssetStatuswindow.

AllshutdowninformationenteredwithintheAssetStatuswindowisforinformationpurposesonly.

Toviewanddefineshutdowninformationforanasset

1.NavigatetotheAssetStatuswindow.

2.SelectanAssetNumber,andclicktheFindbutton.

AllshutdowninformationforthecurrentassetappearsintheShutdownDetailsregion.

3.SelectaStartdatetoaddnewshutdowninformationforthecurrentasset.

4.SelectanEndDate.

5.Optionallyassociatetheshutdowninformationtoaspecificworkorderrequiringmaintenanceonthecurrentasset.

Onlyworkorderscreatedforthecurrentassetareavailable.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 26/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

AssetStatus

6.Optionallyassociateshutdowninformationtotheoperationlevelofaworkorderbychoosingaspecificoperationsequence.

7.Optionallyenterashutdowndescription.

8.Saveyourwork.

PreparingWorkOrderOperations
Operations(alsoknownastasks)aretheinstructionstoperformmaintenanceactivities.Eachoperationisassignedtoadepartment(See:Defining
DepartmentsandResources),associatedwithassignedresources(tradespeople,outsideserviceproviders,andequipment).Whenyoucreateaworkorder

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 27/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

foranassetnumber,youcanattachtheassetnumber'sassociatedactivitiesandrelatedmaintenanceroutetoworkorder.(See:DefiningMaintenance
Routes)andBOM.Themaintenancerouteiscomprisedofoperationsnecessarytocompletetheactivity.Youcanviewandupdatetheseoperationsfromthe
workorder.

Toprepareoperations

1.NavigatetotheSelectworkorderwindow(workorderDetails>Operations).

Note:Thisfunctionisavailableforthoseuserswithresponsibilitiesandrolesthatincludefunction,EAM_WO_DETAILS_MODE,withtheirassociated
menu.Otherwise,youcanonlyviewworkorders,andcannotupdateassociatedassethierarchy,workorderhierarchy,material,resource,operation,
cost,collectionplanresults,workrequest,andattachmentinformation.See:ImplementingFunctionSecurity, OracleApplicationsSystemAdministrator's
GuideSecurity .

2.Selectaworkorder.

3.ClicktheContinuebutton.

Operationscanbescheduledtoruninparallel,sequence,orthroughdependentsteps.Inthescreenshotbelow,forexample,Operation20isdependent
onOperation10,sincethereisalineconnectingtheoperationsOperation20cannotbeperformeduntilOperation10iscomplete.Operations30and40
runinparalleltoeachother.Operation40isindependentitcanbeperformedatanytime.

Operations

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 28/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

4.ChoosetheOperationicon,thenclicktheheadertodisplaytheNewOperationwindow.

a.Optionallyenterorupdateanoperationsequence,orletitgenerateforyou,accordingtoyourprofilesetup(See:ItemandOperationSequence,
OracleBillsofMaterialUser'sGuide
).Operationsaregenerallyassignedinincrementsoften,enablingyoutoinsertadditionalsteps.

b.OptionallyenteraDescriptionforthisoperation.

c.Optionallytocopyorreferencestandardoperationsintoarouting,selectanOperationCode.Ifyouuseastandardoperationcode,theoperation
Oracle
informationforthatcodeiscopiedintothecurrentoperation.Youcanthenupdatethatinformation(See:CreatingaStandardOperation,
BillsofMaterialUser'sGuide
).

d.SelectanAssignedDepartment.
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 29/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

Theassigneddepartmentidentifiestheroleresponsibleforperformingthetask.

e.SelectascheduledStartDateforthisoperationtobaseonaforwardschedule.

TheEnterpriseAssetManagementschedulingprocessusesthescheduledstartdateasastartingpointtocalculatethedurationoftheoperation,
basedontheresourcesandmaterial.Ifthematerialandresourcesarenotavailablebythisdate,theschedulingprocessmovesthestartdateof
theworkorderforward.Theplanningprocessusesthescheduledstartdatetorecommendcreationofpurchaseordersforthematerial(See:
OverviewofPlanningandScheduling).

f.SelectascheduledCompletiondateforthisoperationtobaseonabackwardschedule.

TheEnterpriseAssetManagementschedulingprocessusesthescheduledenddateasastartingpointtocalculatethedurationoftheoperation,
basedontheresourcesandmaterial.Ifthematerialandresourcesarenotavailablebythisdate,theschedulingprocessmovesthecompletion
dateoftheworkorderbackward.Theplanningprocessusesthescheduledcompletiondatetorecommendcreationofpurchaseordersforthe
material(See:OverviewofPlanningandScheduling).

Note:Actualdatesareenteredatoperationandworkordercompletion.ScheduleddatesarecalculatedbytheEnterpriseAssetManagement
schedulerifyouhaveOracleProductionSchedulingenabled(See:OverviewofSettingUp, OracleProductionSchedulingUser'sGuide
).Otherwise,
theWIPschedulercalculatesthedates.

g.OptionallyselectaShutdownTypetohelptheplannergroupworkordersthatmayrequireshutdowns.

Whentheworkordersaregrouped,theyareplannedtogether.

h.ClicktheOKbuttontoreturntotheOperationswindow.

Theoperationsenteredinthepreviouswindowappearatthebottomofthiswindow.Scrollovertothefarrightfield.

TheDurationidentifiesthedurationoftheoperationandismeasuredinhours.Youcanmanuallyenterthis,orletitcalculateasthedifference
betweentheestimatedStartDateandestimatedEndDate.

5.Afterallnecessaryoperationsareentered,youcancreatedependenciesasnecessary.

OptionallychoosetheConnecticontoconnectdependentoperations.Afterchosen,youcandrawalinebetweendependentoperations.

Youmightneedtomoveoperationsaround.OptionallychoosetheDragicontomoveanoperation.

6.OptionallychooseDependenciestosetdependenciesbetweenoperations.

Forexample,Operation30isdependentonOperation10completing.

DependentOperations

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 30/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

7.OptionallychooseMaterialstovieworupdatetheassociateditemslistforthecurrentoperation(See:SettingUpMaintenanceBillsofMaterialand
DefiningInventoryMaterialRequirements).

MaterialRequirements

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 31/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

8.OptionallychooseResourcestovieworupdatetheresourcesassignedtothecurrentoperation.

Resources

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 32/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

IfyouselecttheSchedulingtab,foreachresourceoperation,youcanchooseifitisincludedinscheduling.

Youcanscheduleattheresourcelevelwithinanoperation.See:DefiningResourceRequirements.

SelectYesorNofromtheScheduledlistofvalues.

Note:Youcanviewworkorderoperationsinaviewonlymode.See:ViewingWorkOrderOperations.

ViewingWorkOrderOperations

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 33/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

Youcanviewtheoperationsrequiredtoperformarepair.Theseoperationsareassignedresources(tradespeople,outsideserviceproviders,andequipment),
aswellasmaterial.TheViewOperationswindowdoesnotenableyoutoupdatetheoperations.Forinstructionsonupdatingoperations,See:PreparingWork
OrderOperations.

Toviewoperations

1.NavigatetotheViewOperationswindow.

a.WithintheSelectWorkOrderwindow,selectaworkorder.

b.ChooseContinue.

2.ChooseDependenciestoviewoperationdependencyinformation.

3.ChooseMaterialstoviewmaterialrequirements.See:DefiningMaterialRequirements.

4.ChooseResourcestoviewresourceassignment.See:DefiningResourceRequirements.

RelatedTopics

PreparingWorkOrderOperations

DefiningInventoryMaterialRequirements
Whenenteringaworkorderforanassetnumber,theactivityassociatedtotheassetnumberattachestherequiredmaterialandresourcestocompleteits
operations.However,youcanupdate,add,view,anddeletematerialrequirementsforaspecificworkorder.

YoucanalsospecifyasourcesubinventoryandsourcelocatorattheBOMlevelortheworkordermaterialrequirementlevel.IftheAutoRequestMaterial
optionisselectedattheBOMlevel,materialallocationwillbeinitiatedwhentheworkorderisreleased,andthesourcesubinventoryandsourcelocatorvalues
youenterwilloverridethesevaluesintheInventorysourcingrules.IftheAutoRequestMaterialoptionisnotselected,youcanspecifyasourcesubinventory
andsourcelocatorforyourmaterialwhenyouperformamaterialrequestoraOneStepMaterialIssue.

Todefineworkordermaterialrequirements

1.NavigatetotheSelectWorkOrderpage(WorkOrderDetails>MaterialRequirements).

Note:Thisfunctionisavailableforthoseuserswithresponsibilitiesandrolesthatincludefunction,EAM_WO_DETAILS_MODE,withtheirassociated
menu.Otherwise,youcanonlyviewworkorders,andcannotupdateassociatedassethierarchy,workorderhierarchy,material,resource,operation,
cost,collectionplanresults,workrequest,andattachmentinformation.See:ImplementingFunctionSecurity, OracleApplicationsSystemAdministrator's
GuideSecurity .

2.Selectaworkorder.
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 34/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

3.ClicktheContinuebutton.

MaterialRequirements

4.Optionally,withintheInventoryItemsregion,youcanvieworupdatetheitemlistassociatedwiththeassetnumber.(See:SettingUpAssetBillsof
Material)byplacingyourcursorintheMaterialfieldorbychoosingSelectMaterials.WhenyouchooseSelectMaterials,thecurrentassetnumbers
associatedAssetBillofMaterialitemsareavailabletobeaddedtotherequiredmaterialforthecurrentworkorder.

SelectMaterials

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 35/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

5.OptionallyselecttheMaintabtochangeoperationsequenceandthedaterequired.

Note:IfyouareaccessingtheSelectMaterialspageviatheOperationspage,youcannotchangeoperationinformation.IfyouareaccessingtheSelect
MaterialspageusingtheWorkOrderpage,youcanchangeoperationinformation.

6.OptionallyselecttheQuantitiestabtoupdatethequantitiesRequired.

7.OptionallyselecttheSupplytabtoselectasupplyType.YoucanoptionallyspecifyavaluefortheSourceSubinventoryandSourceLocatorfields.

Supply

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 36/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

8.OptionallyselecttheCommenttabtoenterinformationforthecurrentMaterial.

9.OptionallychoosetheATPtabtodefineavailabletopromiseinformationforthecurrentmaterial.IfyouselecttheATPAllowedcheckbox,availableto
promiseinformationcanbecalculatedforthecurrentmaterial.

10.OptionallychooseCheckATPtocheckavailabletopromiseinformationfortheselectedmaterial.

ATPResults

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 37/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

11.OptionallychooseDirectItemtocreaterequisitionsfordirectitems,andaddthemtoyouritemslist.OracleSelfServicePurchasingdefaultstheWork
OrderNumberandOperationNumber,aswellastheclasscodeinformationforcorrectexpensing.DirectItemsareonetime,noninventorieditemsthat
arepurchaseddirectlyfromthesupplier.AfteryouchooseDirectItem,thecurrentWorkOrderandoperationreferencevaluesarepassedtothe
requisitioncreated.IftheWorkOrderisprojectrelated,theprojectandtaskinformationiscapturedinthepurchaserequisition(See:OverviewofDirect
ItemProcurementforeAMWorkOrders).YoucanexitSelfServicePurchasingandreturntotheMaterialRequirementspagebychoosingReturnTo
Portal.

UponreinquiryofthisWorkOrder,theDirectItemsregionreflectsanyrequisitionandpurchaseorderdetails.

Note:YoumusthaveOracleSelfServicePurchasinginstalledforthisfunctionality.YoucanpurchasedirectitemsfromaRequisitionorPurchaseOrder
pageifyouhaveOraclePurchasinginstalled(See:EnteringPurchaseOrdersforDirectItems).

Note:YoucanprocuredirectitemstoWorkOrdersatReleasedstatuses.
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 38/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

12.ChooseCopytoAssettodynamicallyupdatetheBOMassociatedtotheassetgroupwithanyitemslistchanges(See:SettingUpAssetBillsofMaterial).

13.Saveyourwork.

Note:YoucanviewWorkOrdermaterialrequirementsinaviewonlymode.See:ViewingMaterialRequirements.

RelatedTopics

ViewingATPInformation, OracleInventoryUser'sGuide
DefiningDirectItemMaterialRequirements
Directitemsrepresentitemswithinfrequentuseorcriticalitytheyarenotincludedintheinternalcatalogasstockeditems.Theseitemsareconsideredas
"oneoff",boughtdirectlyfromavendorforaspecificworkorderandoperation.Theseitemsaredelivereddirectlytotheshopfloorformaintenancework
orderexecution.

Tosetupnonstockdirectitems,accesstheMasterItemwindowwithinOracleInventory,andsetuptheitemwiththeStockablecheckboxcleared.See:
DefiningItems, OracleInventoryUser'sGuide
.DescriptionbaseddirectitemsarenotsetupwithinOracleInventory.

Youcanaddnonstockbaseddirectitemstoasset,maintenance,andrebuildableBOMs.Youcanaddnonstockanddescriptionbaseddirectitemsdirectlyto
thematerialrequirementsforanexistingworkorder.

IfdirectitemsexistonanactivityBOM,theyappearasdefaultmaterialrequirementswhencreatingaworkorderforthatactivity.However,youcanadd
additionaldirectitemmaterialrequirementstoanexistingworkorder.

SettingUpAssetBillsofMaterial

SettingUpMaintenanceBillsofMaterial

DefiningRebuildableBillsofMaterial

Toadddirectitemmaterialrequirements

1.NavigatetotheSelectWorkOrderwindow.

2.Chooseaworkorder.

3.ChooseContinue.

MaterialRequirements

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 39/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

4.WithintheCreateDirectItemsregion,selectanOperation.

5.SelectanItemType.

DescriptionBasedItem:ThisdirectitemtypeisnotstoredinOracleInventory.
NonStockItem:ThisdirectitemtypeisstoredinOracleInventory.ItsMasterItemrecord'sStockablecheckboxiscleared.
6.IfyouselectedaNonStockItemType,selectanItem.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 40/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

ThisfieldisdisabledifaDescriptionBasedItemTypewaspreviouslyselected.

7.EnteraDescription,ifyoupreviouslyselectedaDescriptionBasedItemType.

8.SelectaUOM.IfyoupreviouslyselectedaNonStockItemType,thisvaluedefaultsfromtheMasterItem.

9.SelectaPurchasingCategory.See:SettingUpPurchaseOrderCategoryAssociationsforDirectItems.

10.EnteraNeedByDatethesystemdatedefaults.

11.Clickthehorizontalscrollbar.

12.Selectorenteravalueforthefollowingfields:

SupplierContact

SupplierSite

ContactPhone

13.Saveyourwork.

ViewingMaterialRequirements
Whenyouenteraworkorderforanassetnumber,theactivityassociatedwiththeworkorderattachestherequiredmaterial(See:SettingUpMaintenance
BillsofMaterial)andresourcestocompleteitsoperations.Youcanviewmaterialrequirementsforaspecificworkorder.

Toviewworkordermaterialrequirements

1.NavigatetotheViewMaterialRequirementswindow.

a.FromtheSelectWorkOrderwindow,selectaworkorder.
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 41/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

b.ClicktheContinuebutton.

ViewMaterialRequirements

2.IntheInventoryItemsregion,youcanviewinventorieditemsonthisworkorder'srequireditems.

Youcanviewthembywarehouse,andatthesubinventorylevel.

a.IntheMaintab,youcanviewoperationsequenceandtheDateRequired.

b.IntheQuantitiestab,youcanviewthequantitiesRequired.
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 42/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

c.IntheSupplytab,youcanviewsupplyTypeinformation,suchasmaterial,subinventoryandsourcelocator,ifapplicable.

Supply

d.IntheCommenttab,youcanviewcommentinformation.

e.IntheATPtab,youcanviewdefinedavailabletopromiseinformation.

RelatedTopics

DefiningMaterialRequirements

DefiningSubinventories, OracleInventoryUser'sGuide
DefiningResourceRequirements
Youcanview,update,add,ordeleteresourcerequirementsforaworkorder.Resourcesareusedtoperformataskforamaintenanceoperation.Aresource
isaperson,pieceofequipment,orcontractorserviceusedtoperformanoperation.Aresourceandusagerateforallscheduledactivitiesisrequiredina
routing.

Contractorservicesaredefinedasworkservicesprovidedbyanorganizationorpersonwhoisnotanemployeeofyourcompany.Contractorsarepaidfor
theirwork,basedonanagreeduponcontractoragreement.Forexample,withinmaintenanceworkenvironments,itisoftenimportanttoincludelandscaping
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 43/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

serviceswithinaworkorder.Itisalsoimportanttorelatethepurchasingtransactions,suchastherequisitionandpurchaseordertotheworkorder.Inorder
forthistoexecute,theappropriatestepsarecompletedinPurchasingandEnterpriseAssetManagement.

Whendefiningdepartments,availableresourcesareassignedineachdepartmentandtheshiftsthateachresourceisavailable.Foreachoperationdefined,
youspecifyadepartmentandlistofresourcesandusages.Anoperationcanuseanyresourcethatisavailableinthedepartment,butnotallresourcesare
assignedtothedepartment.Anoperationcanuseresourcesthatareownedorborrowedfromotherdepartments.(See:DefiningDepartmentsand
Resources).

Todefineresourcerequirements

1.NavigatetotheSelectWorkOrderwindow(WorkOrderDetails>ResourceRequirements).

Note:Thisfunctionisavailableforthoseuserswithresponsibilitiesandrolesthatincludefunction,EAM_WO_DETAILS_MODE,withtheirassociated
menu.Otherwise,youcanonlyviewworkorders,andcannotupdateassociatedassethierarchy,workorderhierarchy,material,resource,operation,
cost,collectionplanresults,workrequest,andattachmentinformation.See:ImplementingFunctionSecurity, OracleApplicationsSystemAdministrator's
GuideSecurity .

2.ChooseaWorkOrder.

3.ChooseContinue.

TheresourcesthatappearonthefollowingResourceswindowareassignedtothedepartment,andassignedtothecurrentoperationoftherouting.
See:DefiningDepartmentsandResources.

Resources

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 44/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

4.SelectanOperation.Onlyvalidoperations,associatedwiththerouting,areavailable.See:PreparingWorkOrderOperations.

Note:IfyouaccesstheResourceswindowviatheOperationswindow,youcannotchangeoperationinformation.IfyouaccesstheResourceswindow
viatheWorkOrderwindow,youcanchangeoperationinformation.

5.EnteraResourceSequence.Youcanhavemultipleresourcesforanoperation.

6.SelectaResource.

7.IntheMaintab,theUOMdefaultsbasedontheResourcedefinition.See:DefiningDepartmentsandResources.YoucanupdatethisiftheBOM:Update
ResourceUOMprofileoptionissettoYes.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 45/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

TheUOMrequiresatimebasedmeasure,forthisWorkOrdertoschedule.Itmustbethesameasthesitelevelprofileoption,BOM:HourUOM.See:
BillsofMaterialProfileOptions, OracleBillsofMaterialUser'sGuide
.

OracleBillsofMaterial
8.SelectaBasistochargeandscheduletheresource.ThisdefaultsbasedontheResourcedefinition.See:DefiningaResource,
User'sGuide
.

Item:Chargeandscheduletheresourcewheretheresourceusagequantityistheamountrequiredperassemblyunityoumake.
Lot:Chargeandscheduletheresourcewheretheresourceusagequantityistheamountrequiredperjoborschedule.
IfyouselectLot,theBasiswillbebasedontheresourceitemwhentheworkorderiscreated.

9.EntertheUsageRateorAmountValuefortheresource.Youcanpostusagetimeforpersons,equipment,andmiscellaneousmaterial.

10.SelecttheQuantitiestab.YoucanviewtheRequiredquantityofthisresourcetouse.ThisinformationdefaultsfromtheUsageRate/Amount
information.YoucanalsoviewtheAppliedamountorrateoftheresourcealreadyused.TheOpenamountorrateidentifiestheamountoftheresource
lefttouse(thedifferencebetweentheRequiredandApplied).

11.SelecttheSchedulingtab.Thisinformationdefaultsfromthecurrentoperation'ssetup.See:PreparingWorkOrderOperations.

SelectYesintheScheduledfieldtoindicatethatthisresourcecanbescheduled.

12.SelecttheCostingtab.Youcanviewandupdatethisresource'scostinginformation.

a.SelectaChargeType.

Manual:Youcanmanuallyenterthecost.
POreceipt:Thecostdefaultsasthecostonthepurchaseorderreceipt.
b.TheDepartmentdefaultsastheareathecurrentresourceisassignedto.See:DefiningDepartmentsandResources.

13.OptionallychooseInstancestovieworupdatealistofspecificpeopleorequipmentassignedtothisresource.ThePersontabdisplayspersonsgrouped
inspecificroles.TheEquipmenttabdisplayssimilartypesofequipmentgroupedbyresource.Youcandefinespecificmachinestoanyofyourmachine
typeresourcesandyoucandefinespecificpersonstoanyofyourlabortyperesources.Whenaresourcehasinstancesdefined,youcanviewthe
resourceloadandcapacityintheSchedulerWorkbench(See:UsingtheSchedulerWorkbench).

Forexample,youcandefineallmachinesbelongingtotheresource,GRINDERS.Anindividualgrindermachinecanthenbeaspecificresource
requirementandscheduled,andcanhaveitsownuniquecapacitydefinition.

Thisinformationdefaultsfromyourcurrentresourcedefinition.Youcanaddpersons(includingcontingentworkers)andequipmentthatareassociated
withthecurrentresource.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 46/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

See:DefiningaResource, OracleBillsofMaterialUser'sGuide.
14.Saveyourwork.

RelatedTopics

DefiningaResource, OracleBillsofMaterialUser'sGuide
ViewingResourceRequirements
Youcanviewresourcerequirementsforaworkorder.Resourcesdefinethetimeanassemblyspendsatanoperationandthecostyouincurfortheoperation.
Aresourceisaperson,pieceofequipment,orcontractorserviceusedtoperformanoperation.Aresourceandusagerateforallscheduledactivitiesare
requiredinarouting.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 47/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

Toviewresourcerequirements

1.NavigatetotheViewResourceRequirementswindow.

2.FromtheSelectWorkOrderwindow,selectaworkorder.

3.ChooseContinue.

ViewResourceRequirements

4.Viewthelistofoperationsandtheirresourcesassociatedtothecurrentworkorder.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 48/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

RelatedTopics

PreparingWorkOrderOperations

DefiningDepartmentsandResources

DefiningResourceRequirements

DefiningaResource, OracleBillsofMaterialUser'sGuide
WorkOrderRelationships
Workorderrelationshipsenableyoutomanageanetworkofrelatedworkorders,enablingyoutomanagecomplexprojects,suchasplannedorfacility
shutdowns.Thedifferentrelationshipsprovideseparateschedulingrulesthatareusedtomanagelargeprojects.AGanttchartenablesyoutomanagework
bydisplayingworkorderschedulesandasummaryofworkorderdetails.TheGanttChart'sdraganddropfunctionalityenablesyoutomanagescheduleswith
ease.

Thissectionincludesthefollowingtopics:

WorkOrderRelationshipDefinition

ParentChildRelationship

EndtoStartDependency

CostRelationship

FollowupWorkRelationship

WorkOrderRelationshipDefinition
Workordersfordifferentassetsmayassociatetoeachotherinahierarchy.ValidrelationshipsareParentChild,EndtoStartDependency,Cost,andFollowup
Work.Managecomplexmaintenancejobsthroughthesefourtypesofworkorderrelationships.See:RoutineWorkOrders.AGanttchartenablesyouto
manageworkbydisplayingworkorderschedulesandasummaryofworkorderdetails.TheGanttChart'sdraganddropfunctionalityenablesyoutomanage
scheduleswithease.

ParentChildRelationship
TheParentChildRelationshipenablesanetworkofworkorders,whichincludesonetoplevelworkorderthatdefinesthetimelineofallitschildworkorders.
Thestartandenddatesofthechildworkordersarewithinthestartandenddatesoftheparentworkorder.Theparentworkorderdatesarescheduled,
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 49/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

whileitschildworkordersautomaticallyschedule,aswell.Achildworkordercanbeaparenttoanotherworkorder.Oneparentcanhavemultiplechildren,
butonechildcanhaveonlyasingleparent.Youcanhaveaninfinitenumberofparentchildworkorderlevels.

Tocreateparentworkorders

1.NavigatetotheWorkOrderspage(MaintenanceSuperUser:WorkOrderstab).

2.Queryaworkorder(See:ViewingWorkOrders).

3.ClicktheworkorderandselecttheWorkRelationshipssubtab.Thispagegraphicallydisplaystheworkorder'sschedule.Thetabenablesyoutoview
theschedulingrelationshipsfortheworkorderinagraphicalformatandliststheworkorder'spossiblerelationships.

WorkRelationships

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 50/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

4.Selecttheworkorderforwhichyouwanttodefineachildworkorder,andclickUpdateWorkHierarchy.

UsetheUpdateWorkHierarchypagetoaddachildworkorder.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 51/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

5.IntheSelectWorkOrderfield,dependingonyourrequirement,selecttocreateanewchildworkorderoraddanexistingworkorderasachild.

6.Enterdetailsofthenewchildorderyouwanttocreate,oraddtheexistingworkorderthatyouareaddingasachild.

7.ClicktheApplybutton.

Aconfirmationmessagedisplaysthattheworkorderhasbeenaddedasaschedulingchild.

EndtoStartDependency
Youcancreateworkorderswithschedulingdependencyrelationships(includingchildsiblingworkorders).Forexample,oneworkorder'sscheduledstartdate
isdependentonanotherworkorder'scompletion.Withthisrelationship,thenextworkordercannotstartuntilthepriorworkorderiscompleted.Notethatto
createanendtostartdependencybetweentwoworkorders,theyshouldbesiblingssharingacommonparent.

TocreateEndtoStartdependencies:

1.NavigatetotheWorkOrderspage(MaintenanceSuperUser>WorkOrders).

2.Queryaworkorder.(See:ViewingWorkOrders).
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 52/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

3.ClicktheworkorderandselecttheWorkRelationshipssubtab.

4.SelectaworkorderandintheSelectWorkOrderfield,andchoosetheoptiontoUpdateDependencies.

5.IntheWorkOrderDependenciespage,clicktheAddDependenciesbutton.

SelectaworkorderintheDependentWorkOrderfield.IntheDependencyTypefield,selectPriororNext.

6.ClicktheApplybutton.

CostRelationships
Youcanoptionallyrollachildworkorder'scostsintotheparentworkorderforreportingpurposes.Youcanperformcostrollupsonadhocworkorders
becausethecostrollupisindependentofschedulingrelationships.Youcanbasethecostrollup,withinahierarchy,onschedulingrelationships,aswell.
Schedulingrelationshipsarenotrequiredtorollupcostswithinahierarchy.Youmaycreateacostreportinghierarchythatisdifferentthanthescheduling
hierarchy.

Tocreateworkordercostingrelationships:

1.NavigatetotheWorkOrderspage(MaintenanceSuperUser>WorkOrders).

2.Queryaworkorder(See:ViewingWorkOrders).

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 53/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

3.ClicktheworkorderandselecttheWorkRelationshipssubtab.

4.Toviewthecostrollupofachildworkorder,clickViewCosts.

5.ClicktheUpdateAlternateCostHierarchytocreateacostreportinghierarchy.Youcancreatenewworkordersoraddexistingworkorders.

Alternatively,toestablishacostreportinghierarchybyimportingtheparentchildworkorderhierarchy,clicktheImportWorkHierarchybutton.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 54/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

6.Aconfirmationmessagedisplaysandtheworkorderisaddedasacostchild.

FollowupWorkRelationship
YoucancreateaworkorderforacapitalAssetNumberorRebuildableItem,whileexecutingworkfortheassetonanotherworkorder.Forexample,asecond
problemwithanassetisdiscoveredwhileexecutingaworkorder.Afollowupworkorder,associatedwiththeoriginalworkorder,iscreatedfortheissue.This
isindependentofschedulingorcostrelationships.

Tocreateandviewfollowupworkorders:

1.NavigatetotheWorkOrderstab(MaintenanceSuperUser>WorkOrders).

2.Queryaworkorder(See:ViewingWorkOrders).

3.SelectViewFollowupWorkOrdersfromtheSelectWorkOrderlistofvalues.

4.ChooseGo.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 55/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

5.SelectavalueintheSelectWorkOrderfieldlistofvaluestocreateafollowupworkorder.

6.ClickGo.

7.UsetheCreateFollowUpWorkOrderpagetoenterdetailsofthefollowupworkorderthatyouarecreating.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 56/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

8.ClickApply.

Aconfirmationmessagedisplaysthatafollowupworkorderhasbeencreated.

RelatedTopics

eAMScheduling

eAMWorkOrderTransactions
TherearetwotypesofEnterpriseAssetManagementworkordertransactions:materialandresource.Amaterialtransactionisusedwhenyouissuematerial
frominventorytoaworkorder.Aresourcetransactionisusedwhenyouchargeresources(forexamplelabor,orequipment)toaworkorder.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 57/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

Thissectionincludesthefollowingtopics:

OperationCompletion

WorkOrderCompletion

RebuildWorkOrderCompletion

TransactingMaterial

ViewingResourceTransactions

ClosingWorkOrders

OperationCompletion
Operationsaretheinstructionsortaskstoperformarepair.Everyoperationisassignedtoadepartment(See:DefiningDepartmentsandResources),
associatedwithassignedresources(tradespeople,contractorservices,andequipment).WhenyouenteraWorkOrderforanAssetNumber,theAsset
Number'sassociatedactivity(See:AssociatingAssetNumberswithActivities)attachestotheworkorder,deliveringitsrelatedmaintenanceroute(See:
DefiningMaintenanceRoutes)andBOM.Themaintenancerouteiscomprisedofoperationsnecessarytocompletetheactivity.YoucanCompleteand
Uncompleteoperations.Afteranoperationiscomplete,youcanperformanOperationUncompletion.Ifanoperationisdependentuponanotheroperation,you
cannotuncompletethatoperation'sdependencyifthecurrentoperationiscomplete.Forexample,operation20isdependentonoperation10completing.You
cannotuncompleteoperation10afteroperation20hasbeencompleted.

YoucancompleteoruncompleteanoperationusingtheMaintenanceSuperUserresponsibility.

Tocompleteanoperation

1.NavigatetotheMaintenanceSuperUserresponsibility.

2.SelecttheWorkOrdertab.

3.Queryworkordersandselectaworkorderfromthelist.

4.SelectanOperationandchooseComplete/Uncomplete.Thisistheoperationyouwishtocomplete.

Operations

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 58/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

5.EntertheActualStartDateandTimeoftransactionthesystemdateappearsasdefaultvalues.

6.EnterActualDuration(hours)information.

7.TheActualEndDatedefaultsasthecurrentsystemdate.Youcannotchangethisvalue.

8.OptionallyenteraReconciliationCode.

Thisisadescriptionofwhyyouarecompletingthisoperation.Forexample,OperationCompletedorOperationPartiallyCompleted.

9.ClicktheApplybutton.

Touncompleteanoperation

1.NavigatetoMaintenanceSuperUserresponsibility.

2.SelecttheWorkOrdertab.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 59/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

3.Queryworkordersandselectaworkorderfromthelist.

4.SelectanOperationandchooseComplete/Uncomplete.Iftheoperationwaspreviouslycompleted,thenyoucanUncompletetheoperation.

5.ClicktheApplybuttontouncompletetheoperation.

RelatedTopics

PreparingWorkOrderOperations

DefiningMaintenanceRoutes

OperationCompletionMoves, OracleWorkinProcessUser'sGuide
WorkOrderCompletion
OracleeAMworkordersarecreatedagainstassets.Theyaredefinedmanually,orgeneratedautomaticallybasedonascheduledactivity.Ifyouattacha
manuallycreatedworkordertoanactivity(normallytheroleofaplanner),theworkorderinheritstheactivity'sattributes,suchastheassetBOM,assetroute
(operations),attachments,qualityplans,costinformation,andschedulingrules.

Theoperationswithinaworkorderdonotneedtobecompletetocompleteaworkorder.However,thedateyoucompleteaworkordermustbegreaterthan
(later)orequaltotheenddateoftheoperationthathasthelatestenddate.Likewise,thedateyoustartaworkordermustbeearlierthanorequaltothe
startdateoftheoperationwiththeearlieststartdate.YoucanuncompleteaComplete,CompleteNoCharges,Cancelled,PendingCloseorFailedClose
workorder.IfyouuncompleteaworkorderwithastatusofCompleteorCompleteNoCharges,transitionstoaCompletestatusforallotherstatuses,the
workordertransitionstothestatusithadwhenclosed.See:eAMWorkOrderStatuses).

Forplannedworkorders,thedefaultworkordercompletiondatevalueisthescheduledcompletiondate.

However,theprofileoption,EAM:ActualWorkCompletionDatePreference,canbesettousethesystemdateasthedefaultworkordercompletiondate.See
EAMProfileOptionsinthe OracleEnterpriseAssetManagementImplementationGuide.
Plannersorcrewsupervisorscancompleteoruncompleteworkorders,usingtheMaintenanceWorkbench(UsingtheMaintenanceWorkbench),fromthe
EnterpriseAssetManagementresponsibility,orbyaccessingtheWorkOrderCompletionmenuoption.Aftercompletingaworkorder,thecompletion
transactionrecordiscreatedwithanelectronicsignature(UserName).Duringcompletion,arecordiscreatedwiththissignatureforanymandatorycollection
planresultsormandatorymeterreadings.

Tocompleteaworkorder

1.NavigatetotheWorkOrderCompletionwindow(MaintenanceSuperUserorMaintenanceUserWorkbench:WorkOrderstaborEnterpriseAsset
Management:WorkOrderPlanning>MaintenanceWorkbench).

2.Selectaworkorder.
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 60/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

3.SelecttheCompleteWorkOrdervalueintheSelectWorkOrderdropdown.

4.OptionallyenteraReconciliationCode.

Thisisasimpledescriptionofwhyyouarecompletingthisworkorder.Forexample,WorkOrderCompletedorWorkOrderPartiallyCompleted.

5.OptionallyenterActualDuration(hours)information.

Youmustentertwovalueswithinthisregion:ActualDurationandActualStartDateandTime.Thevaluethatyoudonotenterisautomatically
calculated.

ActualDurationidentifiesthetotalelapsedtimeoftheworkorder.ItisautomaticallycalculatedasthedifferencebetweentheScheduledStartDateand
ScheduledEndDate.

6.TheMetersregionenablesyoutoenterreadingsformetersassociatedwiththisAssetNumber.Readingsformetersdefinedasmandatorymustbe
entered.Youcanoptionallyenternonmandatoryreadings.

Atworkordercompletion,meterreadingsaremandatoryforworkordersgeneratedbythePreventiveMaintenanceschedulingengine.Afteraworkorder
iscompleted,meterreadingsarerequiredforallruntimeintervalmetersassociatedwiththeAssetNumberinthePreventiveMaintenancescheduling
definition.See:PreventiveMaintenanceScheduling.IfthereisameterassociatedwiththisAssetNumber,youarepromptedtoenteraCurrentReading
oraReadingChange.IfyouenteraCurrentReading,theReadingChangedefaults.IfyouenteraReadingChange,theCurrentReadingdefaults.See:
EnteringMeterReadings.

SelecttheResetcheckboxtoindicateifyouwouldliketoResettheCurrentReadingtozero.

7.OracleQualitycollectionplansassociatedwiththecurrentworkorder'sassetnumberandrequiringcompletionappearintheQualityPlansregion.When
thecollectionplanwascreated,itwasspecifiedifthecollectionplanrequiredcompletion.Also,duringtheEnterpriseAssetManagementcollectionplan
creationprocess,triggersmighthavebeenspecifiedtomakeonlycertainassetseligibleforthecollectionplan.See:QualitySetup.

RequiredfieldsaredependentontheCollectionPlan'scollectionelementspecifications.See:QualitySetup.

8.ChooseApplytosaveyourwork.

Touncompleteaworkorder

1.NavigatetotheWorkOrderCompletionwindow.

2.Selectacompletedworkorder.

3.SelecttheCompleteWorkOrdervalueintheSelectWorkOrderdropdowntouncompletethisworkorder.

4.OptionallyenteraReconciliationCode.Thisisasimpledescriptionofwhyyouareuncompletingthisworkorder.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 61/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

5.OptionallyenteranActualDurationorActualStartDateandTime.ActualDurationidentifiesthetotalelapsedtimeoftheworkorder.Itisautomatically
calculatedasthedifferencebetweentheEstimatedStartDateandEstimatedEndDate.Changingthetimesanddurationaffectsresourceusagefor
employeesandequipment.

6.ChooseApplytosaveyourwork.

RelatedTopics

EnteringMeterReadings

RebuildWorkOrderCompletion
Therearetwowaystocreaterebuildworkorders.Inthescenariothatanewrebuildableitemisissuedfrominventorytobeplacedintotheasset,arebuild
workordercreatesfortherebuildableitemthatwastakenoutwithaneedforrepair,giventherequiredinformationwasenteredintothematerialtransaction
(See:TransactingMaterial).Thischildworkorderoftheparentworkordercancomplete,independentoftheparentworkorder.However,iftherebuildable
itemneedingrepairisremovedfromtheasset,repaired,thenreinstalled,thatmanuallycreatedchild,rebuildworkordermustfirstbecompletedbeforethe
parentworkordercancomplete.Inthisscenario,firstcompleteallrebuildorchildworkorders(See:RebuildWorkOrders)beforeyoucancompleteaparent
workorder(See:WorkOrderCompletion).Theoperationswithinaworkorderdonotneedtobecompleteinordertocompleteaworkorder.However,the
dateyoucompleteaworkordermustbegreaterthan(later)orequaltotheenddateoftheoperationthathasthelatestenddate.Likewise,thedateyou
startaworkordermustbeearlierthanorequaltothestartdateoftheoperationwiththeearlieststartdate.Youcanuncompleteaworkorderafteritis
completed,transcendingittoaReleasedstatus(See:eAMWorkOrderStatuses).

PlannersorCrewSupervisorscancompleteoruncompleteworkordersusingtheMaintenanceworkbench(See:UsingtheMaintenanceWorkbench),orby
accessingtheRebuildableWorkOrderCompletionmenuoption.Aftercompletingaworkorder,thecompletiontransactionrecordiscreatedwithyour
electronicsignature(UserName).Arecordiscreatedwiththissignature,duringcompletion,foranymandatorycollectionplanresultsormandatorymeter
readings,aswell.

Tocompletearebuildworkorder

1.NavigatetotheRebuildCompletionwindow(MaintenanceSuperUserorMaintenanceUserWorkbench:WorkOrderstab,orEnterpriseAsset
Management:WorkOrderPlanning>MaintenanceWorkbench).

2.Queryandselectarebuildworkorder.

3.SelecttheCompleteWorkOrderintheSelectWorkOrderdropdown.

RebuildWorkOrderCompletion

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 62/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 63/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

4.Selectarebuildworkorder.

Onlyrebuildworkordersareavailable.

5.OptionallyenteraReconciliationCode.

Thisisadescriptionofwhyyouarecompletingthisworkorder.Forexample,WorkOrderCompletedorWorkOrderPartiallyCompleted.

6.EnteranactualDurationandActualStartDateandTime.

ActualDurationidentifiesthetotalelapsedtimeoftheworkorder.ItautomaticallycalculatesasthedifferencebetweentheScheduledStartDateand
ScheduledEndDate.Changingthetimesanddurationaffectsresourceusageforemployeesandequipment.

7.IftherebuildworkorderisgeneratedfromamaterialissueorisastandalonerebuildworkorderforaRebuildableItem'sserialnumberthatresidesout
ofinventory,thenentertheCompletionLocationinformation.

a.EntertheCompletionSubinventory.Forrebuildworkordersthatarecreatedfromamaterialtransaction,thismustbeanexpensesubinventory.

b.Iftherebuildableitemislocatorcontrolled,enteraCompletionLocator.See:InventoryAttributeGroup, OracleInventoryUser'sGuide.
c.Iftherebuildableitemislotcontrolled,enteraCompletionLot.See:InventoryAttributeGroup,OracleInventoryUser'sGuide.

8.ChooseApplytosaveyourwork.

Touncompletearebuildworkorder

1.NavigatetotheRebuildCompletionwindow.

2.Selectacompletedrebuildworkorder.

3.SelecttheCompleteWorkOrderfromtheSelectWorkOrderdropdowntouncompletetheworkorder.

4.OptionallyenteraReconciliationCode.

Thisisadescriptionofwhyyouareuncompletingthisworkorder.

5.ChooseApplytosaveyourwork.

RelatedTopics

DefiningSubinventories, OracleInventoryUser'sGuide
TransactingMaterial
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 64/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

Youmightneedtoissuearebuildableitemorassetfrominventorytoamaintenanceworkorder.Forexample,aworkorderwasissuedfortheinspectionofa
pump.Duringthepumpinspection,youfoundthatthemotor,oneofthecomponentsofthepump,isproblematic.Youcanreplacetherebuildableitemby
issuinganewmotorrebuildableitemfrominventory.Ifyouchoosetoperformamaterialissuefrominventory,theoldmotorrebuildableitemattachestothe
workorder,automaticallycreatingthechild,rebuildworkordernumberassociatedtotheparentworkorder.Inthiscase,theAssetNumbergenealogy
automaticallyupdatestoidentifythisnewitemnumber.See:OverviewofInventoryTransactions, OracleInventoryUser'sGuide
.

YoucanexecuteamaterialissuetransactionfromtheStorestabpage,withinMaintenanceSuperUser(See:Stores).

RelatedTopics

IssuingandReturningSpecificComponents, OracleWorkinProcessUser'sGuide
ViewingResourcesTransactions
Resourcetransactionsdefinethetimeanassemblyspendsatanoperationandthecostyouincurforanoperation.Therearetwotypesofresources:person
andmachine.Youcantransactbothpersonandmachineresources.Aresourceisanemployee,pieceofequipment,orcontractorservice,usedtoperforman
operation.Youcanchargeresourcestoaspecificworkorder.Youcanviewalltransactionsthathavechargedagainstaspecificresource.

Toviewcompletedresourcetransactions

1.NavigatetotheFindResourceTransactionswindow.

Youcannarrowyourselectionoftransactionsbyanyfieldwithinthiswindow.Forexample,youcanviewallresourcetransactioninformationcharged
duringaspecificperiod,orviewalltransactioninformationtranspiredforaspecificworkordernumber.

TheconcurrentprocesswillalsoconsidertheOTLdatesforthetimeentriesiftheyfallwithinclosedaccountingperiods.

2.ChooseFind.

ViewResourceTransactions

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 65/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

3.SelecttheJoborScheduleHeadertabtoviewresourcetransactioninformationspecifictoaworkorder.

4.SelecttheOperation,Quantitiestabtoviewresourcetransactioninformationspecifictoaworkorderoperation.

5.SelecttheResourceInformationtoviewresourcetransactioninformationspecifictoaresource.

ClosingWorkOrders
YoucancloseamaintenanceworkorderifithasastatusofCancelled,Complete,CompleteNoCharges,PendingClose,orFailedClose.(See:eAMWork
OrderStatuses).Youcancloseoneormanyworkordersatonce.Afteraworkorderoraperiodisclosed,costvariancesarepostedtotheasset'sWIP
accountingclasscodeaccounts,iftheworkorderisassociatedwithanassetroute.VariancesarepostedtotheWIPaccountforeveryassetwithintheasset
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 66/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

routewhentheworkorderisreleased.Theseaccountsarecharged,evenifoneormoreassetsontheassetroutemovebetweenorganizationsbeforethe
workorderisclosed.

Note:IfyouwanttoupdatethequalityresultsforaworkorderwithastatusofClosed,youmustunclosetheworkorder.

IfaworkorderwasataCompletestatusatthetimeofclosingit,youcanunclosetheworkordertotransitionittoaCompletestatus.Forallotherstatuses
duringtheclosingofaworkorder,unclosingtheworkordertransitionstosamestatusithadwhenclosed.

Tocloseaworkorder

1.NavigatetotheFindWorkOrderswindow(EnterpriseAssetManagement>WorkOrders>CloseWorkOrders).

2.Selectaworkorder.Youcanoptionallyenterotherdataselectioninformation.

3.ChooseFind,andtheCloseWorkOrderpageappears.

CloseWorkOrder

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 67/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

4.FromtheToolsmenu,selectCloseWorkOrders.

TheCloseEAMWorkOrderswindowappears.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 68/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

5.SelectaReportType.

Yourselectiondeterminesthetypeofinformationpresentedonthereportthatisproducedbytheconcurrentprocess(CloseDiscreteJobs)closingthe
workorder.Thereportpresentsprojectinformation,workordersclosed,statusinformation,andquantityinformation.

6.SelectanActualCloseDate.

Thisdatemustbegreaterthanorequaltothesystemdate.

7.SelectaSubmissionDate.

Thisdatemustbegreaterthanorequaltothesystemdate.

8.ChooseOK.

Touncloseaworkorder

1.NavigatetotheFindWorkOrderswindow.

2.Selectaclosedworkorder.

Youcanoptionallyenterotherdataselectioninformation.

3.ClicktheFindbutton.
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 69/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

TheCloseWorkOrderwindowappears.

4.FromtheToolsmenu,selectUncloseWorkOrders.

5.Saveyourwork.

Toclosearebuildworkorder

1.NavigatetotheFindRebuildWorkOrderswindow.

2.Selectaworkorder.

Onlyrebuildworkordersareavailable.

3.ChooseFind.TheCloseRebuildWorkOrderwindowappears.

4.FromtheToolsmenu,selectCloseRebuildWorkOrders.

TheCloseEAMWorkOrderswindowappears.

5.IntheReportTyperegion,selectareporttype.Yourselectiondeterminesthetypeofinformationpresentedonthereportthatisproducedbythe
concurrentprocess(CloseDiscreteJobs)closingtheworkorder.Thereportpresentsprojectinformation,theworkordersclosed,statusinformation,as
wellasquantityinformation.

6.SelectanActualCloseDate.Thisdatemustbegreaterthanorequaltothesystemdate.

7.SelectaSubmissionDate.Thisdatemustbegreaterthanorequaltothesystemdate.

8.ChooseOK.

9.Selectaclosedrebuildworkorderfromthelistofvalues.

10.ClicktheFindbutton.

TheCloseRebuildWorkOrderwindowappears.

11.FromtheToolsmenu,selectUncloseRebuildJobs.

12.Saveyourwork.

RelatedTopics

ClosingDiscreteJobsUsingSubmitRequests, OracleWorkinProcessUser'sGuide
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 70/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

eAMWorkOrderPlanning
Aplannerperformsseveralfunctions,includingpurchasingrequiredmaterialforworkorders,approvingworkrequests,creatingworkorders,releasingwork
orders,andcompletingworkorders.Thissectionincludesthefollowingtopics:

UsingtheMaintenanceWorkbench

UsingtheMaintenanceWorkbench
UsingtheMaintenanceWorkbench,aplannercanmassreleaseandmasscompleteworkorders.YoucansettheEAM:MassCompleteworkordersatsystem
dateprofileoptiontoperformamasscompletionforworkorderswithpastandfuturescheduledcompletiondates,withadefaultvalueoftheSystemDate
usingtheMaintenanceWorkbench.SeeProfileOptions, OracleEnterpriseAssetManagementImplementationGuide.
Youcannotcompletemassworkordersthathavemandatorymeterreadingsandmandatoryqualityplansassociatedwithaworkorder(See:WorkOrder
Completion).Aplannercanalsoprocuredirectitems(See:OverviewofDirectItemProcurementforeAMWorkOrders)forworkorders,withouthavingto
leavetheMaintenanceWorkbench.Youcangenerateworkordersfromsuggestedworkorders,manageworkorderrequiredmaterial,resources,andupdate
workorderoperationsasnecessary.

Youcanforecastmultipleassetsatonce.Youcanselectmultipleassetstoforecast,andthenexecutetheforecast.Afterexecution,youcancreateawork
order,associatetheworkorderwithaprojectandtaskforcapitalexpenditures,andassociatetheworkorderwithaparentworkorder.Thisisusefulfor
shutdowns.Whenanorganizationknowsthattheywillbeshuttingdownaportionoftheirplantorfacility,theycanaddthepreventivemaintenancework
orderstotheshutdownandusingOracleProjects,capitalizethecostsintofixedassets.

TousetheMaintenanceWorkbench

1.NavigatetotheMaintenanceWorkbenchpage(EnterpriseAssetManagement>WorkOrderPlanning>MaintenanceWorkbench).

2.Youcannarrowyourdataselectionusinganyofthefieldsavailable.Forexample:

AssetOwningDepartment:Usethisfieldtofilterresultsbasedonforecasts.

OwningDepartment:Usethisfieldtofilterresultsbasedonworkorders.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 71/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

3.ChooseLaunch.
https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 72/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

MaintenanceWorkbench

4.OptionallyintheMaintenanceWorkbenchpane,selecttheResults(Capital)tab,Results(RebuildableInventory)tab,ortheForecastWorktab.

SelectingtheResults(Capital)tabdisplaysassetnumberinformation(See:DefiningAssetNumbers)inatreestructureformat.Ifyouexpandthe
Results(Capital)branch,thetreedetailsassetnumberinformationintothreelowerbranches,includingAllAssets,AssetsWithWork,andRoutes.

AllAssets:Allassets,associatedwiththedataselectionenteredinStep2,appearundertheexpandedAllAssetsbranch.
AssetsWithWork:Allassetswithworkorders(See:eAMWorkOrders),associatedwiththedataselectionenteredinStep2,appearunderthe
expandedAssetsWithWorkbranch.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 73/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

Routes:Allassetswithanassociatedassetroute(See:DefiningAssetRoutes),associatedwiththedataselectionenteredinStep2,appear
undertheexpandedRoutesbranch.

SelectingtheResults(RebuildableInventory)tabdisplaysrebuildableiteminformation(See:DefiningRebuildableItems)inatreestructureformat.If
youexpandtheResults(RebuildableInventory)branch,thetreedetailsrebuildableiteminformationintothreelowerbranches,includingAllRebuildables,
RebuildableswithWorkOrders,andInstanceNumbers.

AllRebuildables:Allrebuildables,associatedwitharebuildworkorder,appear.
RebuildableswithWorkOrders:Allrebuildableitemswithworkorders(See:eAMWorkOrders),associatedwiththedataselectionenteredinStep
2,appear.

InstanceNumbers:AllInstanceNumbersappear.
SelectingtheForecastWorktabdisplaystheForecastWorkOrderswindow,associatedwithassetnumberinformationintheMaintenanceWorkbench
pane.Youcanforecastand/orimplementformultipleassetsatonce.IfyouexpandtheForecastWorkbranch,thetreedetailsassetnumber
informationintothreelowerbranches,includingAllAssets,AssetsWithWork,andRoutes.

AllAssets:Allassets,associatedwiththedataselectionenteredinStep2,appearundertheexpandedAllAssetsbranch.
AssetsWithWork:Allassetswithworkorders(See:eAMWorkOrders),associatedwiththedataselectionenteredinStep2,appearunderthe
expandedAssetsWithWorkbranch.

Routes:Allassetswithanassociatedassetroute(See:DefiningAssetRoutes),associatedwiththedataselectionenteredinStep2,appear
undertheexpandedRoutesbranch.

ForecastedWorkOrders

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 74/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

a.EnteraCutoffDatetoindicatehowfaroutyouwouldliketheworkorderstobecreatedfromthesuggesteddates.

TheHorizondefaultsasthedifferencebetweentheStartDateandCutoffDate.

b.OptionallyselectaSetName.

IfaSetName(See:DefiningSetNames)isentered,theSimulateandRunbuttonsareenabled.IfyouselectSimulate,thenyoucannot
implementworkorders.IfRunisselected,youcanimplementworkordersonlyforforecastedsuggestionsfromdefault.TheDefaultcheckboxis
selectedinthePreventiveMaintenance(PM)Scheduledefinition.See:EnteringPreventiveMaintenanceScheduleDefinitions)PMSchedulesinthe
currentPMSetdefaultPMSchedulesarechosenfromthatPMsetforworkordergeneration.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 75/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

c.OptionallyselecttheIncludeRunToFailurecheckboxtoindicatethattheschedulingprocessshouldincludesuggestedworkordersforRunTo
Lifeassetnumberandactivityassociations.

Ifthischeckboxiscleared,manualworkorderscanbecreated.RunToLifeitemsaretypicallyitemsthatcostmoretomaintainthantheitem
itself.FormoreinformationonRunToLifeitems,See:PreventiveMaintenanceScheduling.

d.ChooseRuntogenerateworkordersuggestionsforthespecifieddateperiod.

TheExpectedStartDateiscalculatedifyouareusingbackwardscheduling,andtheExpectedEndDateiscalculatedifyouareusingforward
scheduling(See:InformationontheReschedulingPointregioninPreventiveMaintenanceScheduling).

e.OptionallychooseImplementtoreleasetheselected(indicatedbythecheckboxontheleftsideofthewindow)forecastedworkorders.

TheworkordersarecreatedatthestatusspecifiedinthePreventiveMaintenanceScheduledefinition.(See:eAMWorkOrderStatusesand
PreventiveMaintenanceScheduling).

Note:YoucanForecastWorkforassets,butnotrebuildableitems.

5.IfyouselectedtheResults(Capital)orResults(RebuildableInventory)tab,youcanoptionally,chooseOperationstoviewthetasksassociatedwitha
specificworkorder.

Youcanviewandupdatethematerialandresourcesassociatedwithaspecificoperation(See:eAMOperationsandTasks).

6.OptionallychooseMaterialstoviewandupdatethematerialrequirementsassociatedwithaselectedworkorder(See:DefiningaMaterialRequirements
PlanName).

a.Optionallyyoucanvieworupdatethecurrentworkorder'sassociatedassetnumber'sitemslistbychoosingSelectMaterials.Thecurrentasset
number'sassociatedAssetBOMitemsareavailabletoaddtotherequiredmaterial.See:SettingUpAssetBillsofMaterial.

b.OptionallychooseDirectItemtoselectdirectitemsfromsuppliercatalogs,createrequisitions,andaddthemtoyouritemslist.

DirectItemsareonetimenoninventorieditemsthatarepurchaseddirectlyfromasupplier.OracleSelfServicePurchasingdefaultstheworkorder
numberandoperationnumber,aswellastheclasscodeinformationforcorrectexpensing.AfteryouchooseDirectItem,thecurrentworkorder
andoperationreferencevaluesarepassedtotherequisitioncreatedusingSelfServicePurchasing.Iftheworkorderisprojectrelated,thenthe
projectandtaskinformationiscapturedinthepurchaserequisition(See:OverviewofDirectItemProcurementforeAMWorkOrders).Youcanexit
SelfServicePurchasingandreturntotheMaintenanceWorkbenchbyselectingReturnToPortal.

Note:Uponreinquiryofthisworkorder,theDirectItemsregionreflectsanyRequisitionandPurchaseOrderdetails.

Note:YoumusthaveOracleSelfServicePurchasinginstalledforthisfunctionality.YoucanpurchasedirectitemsfromaRequisitionorPurchase
OrderwindowifyouhaveOraclePurchasinginstalled(See:EnteringPurchaseOrdersforDirectItems).

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 76/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

c.ChooseCopytoAssettodynamicallyupdatetheBOMassociatedtotheassetgroupwithanyitemslistchanges(See:SettingUpAssetBillsof
Material).

7.OptionallychooseResourcestoview,update,add,ordeleteresourcerequirementsforaselectedworkorder(See:DefiningResourceRequirements).

OptionallychooseInstancestovieworupdatealistofspecificpeopleorequipmentassignedtothisresource.ThePersontabdisplayspersons
groupedinspecificroles.TheEquipmenttabdisplayssimilartypesofequipmentgroupedbyresource.Youcandefinespecificmachinestoanyof
yourmachinetyperesourcesandyoucandefinespecificemployeestoanyofyourlabortyperesources.Whenaresourcehasinstancesdefined,
youcanviewtheresourcecapacityandloadintheSchedulingWorkbench(See:UsingtheSchedulerWorkbench).

Forexample,youcandefineallmachinesbelongingtotheresource,GRINDERS.Anindividualgrindermachinecanthenbeaspecificresource
requirementandscheduled,andcanhaveauniquecapacitydefinition.

Thisinformationdefaultsfromyourcurrentresourcedefinition.Youcanonlyaddpersonsandequipmentthatareassociatedwiththecurrent
resource.

8.OptionallyselecttheCompletebuttontocompleteaselectedworkorder(See:WorkOrderCompletion).

9.OptionallyselecttheOpenbuttontoopentheworkorderdetailsofaspecifiedworkorderSee:eAMWorkOrders).

10.OptionallyselecttheRequestsbuttontoviewallopenserviceandworkrequestsforthecurrentassetnumber.

Note:Youcanviewworkrequestsforassets,butnotrebuildablespares.TheResults(Capital)tabmustbeselectedtoviewworkrequests.

11.OptionallyselecttheMassReleasebuttontoreleasemultipleworkordersatonce.WorkordersatthestatusspecifiedinthePreventiveMaintenance
Scheduledefinitionappear.See:PreventiveMaintenanceScheduling.

MassRelease

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 77/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

Selectthecheckboxesnexttotheworkorderstorelease,thenchooseRelease.Becauseyoucannotcompletemassworkordersthathavemandatory
meterreadingsandmandatoryqualityplansassociated,youcannotreleasetheworkorderiftheseconditionsexist.

12.OptionallychooseMassCompletetocompletemultipleworkordersatonce(See:WorkOrderCompletionandeAMWorkOrderStatuses).Choose
Completetocompleteallworkordersselected.

MassComplete

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 78/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

13.Saveyourwork.

RelatedTopics

DefiningaResource, OracleBillsofMaterialUser'sGuide
CapitalizingWorkOrders

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 79/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

Youcancapitalizepartorallofthecostsincurred,whilemaintaininganasset.Theasset'sbookvalueandusefullifeincrementwiththeadditionalvalue,
withinOracleFixedAssets.Accountantsanalyzethemaintenancecosthistorytodecidewhichcoststocapitalize.Youcanidentifytheworkordersthat
increaseanasset'svalue.Youcancapitalizeonlythecostsofworkordersatthe CompleteNoCharges Closed
or statuses.

Whendefiningamaintainedassetnumber,youcanoptionallyenterFixedAssetinformationtoassociateaFixedAssetCategoryandFixedAssetnumberwith
themaintainedassetnumber,ifOracleFixedAssetsisinstalled.See:DefiningAssetNumbers.

Tocapitalizeworkordercosts

1.NavigatetotheFindWorkOrderswindow(BillingandCapitalization>WorkOrderCapitalization).

2.Queryoneormoreworkorderstocapitalize.

a.Youcannarrowyoursearchcriteria,usingthefieldsatthetopofthewindow.

Forexample,youcanenteraspecificworkorder,assetnumber,orspecifyifyouwanttodisplayonlyworkordersataClosedstatus.

b.OptionallychooseCleartoresetthesearchcriteriatothedefaultsearchcriteria(allfieldsareclearedandtheClosedandCompleteNoCharges
Statuscheckboxesareselected).

c.ChooseFind.TheWorkOrdersregiondisplaysqueriedworkorders,dependentonyoursearchcriteria.

3.Selectaworkorder.

YoucansearchusinganumberofsearchparameterssuchasWorkOrderandconstructionEstimateNumber.Ifyousearchbyestimatenumber,the
valuesavailableforselectionareonlytheconstructionestimatesthathaveworkorderscreatedforthem.

FindWorkOrders

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 80/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

4.ClicktheCapitalizeWorkOrderbutton.

Thisbuttonisenabledforonlythoseworkordersthathaveamountsavailabletocapitalize.

WorkOrderCapitalization

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 81/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

5.EnteraCapitalization%.

ThecostsassociatedwiththeselecteditemsandresourceswithintheCapitalizationregionarecapitalizedbythispercentage.

6.AfterselectingitemsorresourcestocapitalizewithintheCapitalizationregion,chooseCalculateAmountstoviewtheprojectedamounttocapitalize,
basedonwhatyouhadenteredwithintheCapitalization%field.

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 82/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

Theasset'sbookvalueandusefullifewillincrementwiththisadditionalvaluewithinFixedAssets.

7.OptionallychangethedefaultedOffsetAccount.Capitalizedmaintenancecostsarecreditedtotheirassociatedmaintenanceexpenseaccounts,while
thisOffsetAccountisdebitedbythesameamountwithinFixedAssets.

Maintenanceexpensesthatarecapitalizedareconsideredcapitalassetvalueandnotmaintenanceexpenses,withintheGeneralLedger.

8.TheCommentfieldcontainstheworkordernumber,Asset,andAssetDescription,concatenatedtogether.

9.ChooseInitiateCapitalizationtoexecuteaconcurrentprocessthatcapitalizesthecurrentworkorder'smaintainedasset'sassociatedFixedAsset
withthecalculatedamounts.

10.OptionallychooseViewPastDetailstoviewallpastcapitalizationtransactionsforthemaintainedasset'sassociatedFixedAsset.

ViewPastDetails

11.ClicktheClosebutton.

12.Closethewindows.

Contents|Previous|TopofPage|Next

https://docs.oracle.com/cd/E26401_01/doc.122/e48789/T259967T259972.htm#worelation 83/84
22/10/2017 OracleEnterpriseAssetManagementUser'sGuide

Copyright2001,2017,Oracleand/oritsaffiliates.Allrightsreserved.