Sie sind auf Seite 1von 34

20/09/2017

BEF 44903 Topic 1

BEF 44903 Industrial Power Systems Topic 1

Outlines

1.1 Plant Distribution Systems

1.2 Voltage and Frequency Considerations

1.3 Types of Plant Distribution Networks

1.4 Power Demand and Load Estimation

1.5 Transformer Sizing

1
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.1 Overview of Electric Power Systems

Generation System
13.8 kV 15.6 kV

Transmission System
132 kV 500 kV
Distribution System
11 kV 66 kV

BEF 44903 Industrial Power Systems Topic 1

1.1 Example of Plant Distribution System

Panelboard
Feeding
240/415V
Harmonic Loads

2
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.1 Planning Distribution Systems

Power system concept: Network calculation: Rating:


Analysis Load flow Transformers
Selection of the network Short-circuit calculation Cables
configuration Energy balance Protective/ switching
Type of connection to devices
ground Provisions for redundant
Technical features supply

Power system planning

BEF 44903 Industrial Power Systems Topic 1

1.1 Planning Distribution Systems

Source: Siemens

3
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.1 Planning Distribution Systems

 An optimum network configuration should


particularly meet the following requirements:
1

4
Simple High Low Favorable
structure reliability losses and
of supply flexible
expansion
options

BEF 44903 Industrial Power Systems Topic 1

1.1 Planning Distribution Systems


Example of Industrial
Power Networks

4
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.1 Planning Distribution Systems

 A distribution system deals with the distribution


of electrical energy to its specific loads.
 The main purposes of planning are:
 To make the system economical (cost effective).
 To minimise power losses and maintain regulation
within permissible limits.
 Load survey and load forecasting of the area are
necessary.

BEF 44903 Industrial Power Systems Topic 1

1.1 Planning Distribution Systems

 Load survey of a particular area is carried out to find out


the present load requirement as well as the expected
load growth over a period of 5 to 15 years. The following
basic data should be collected for starting this work:

 A detailed map of the area showing important features.


 The existing number of houses, population and new construction
anticipated in the area.
 The expected number of shops, post offices, rural health centres,
etc.
 The type of industry and number of industries possible in the
area.
 Development programmes implemented in the area.

10

5
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.1 Planning Distribution Systems

 For the purpose of forecasting load, the prospective


consumers may be categorised as under:
1. Domestic consumers, i.e. residential houses.
2. Commercial consumers, i.e. shops, schools, hospitals, hotels,
and other commercial establishments.
3. Industrial consumers:
a. Small industries
b. Medium industries
c. Large industries
d. Municipal consumers (i.e. street lighting, water works, parks, etc.)
e. Agricultural consumers
f. Mining industries

11

BEF 44903 Industrial Power Systems Topic 1

1.1 Layout of Distribution Systems

Sub-transmission Line
(66kV or 33kV) Distribution
Substation
Primary Secondary
Substation Substation 3 Phase
Consumers
11kV Feeder (415V)

132kV/66kV 66kV/11kV 11kV/415V Single Phase


66kV Feeder 11kV Feeder Consumers
(240V)

Industrial
Consumer

12

6
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.1 Layout of Distribution Systems

 The high voltage from transmission line (132 kV) is step-


down at the Primary Substation to 66 kV or 33 kV.
 From this primary substation, power at 66 kV or 33kV is
carried through sub-transmission lines to different load
centres. The length of a sub-transmission line is about 50
km and they carry about 50 MW of power.
 It has been found that sending power through sub-
transmission lines at 33 kV or 66 kV is economical in
terms of losses (i.e. I2R) and the capital cost (i.e. cost of
conductor, insulators and supports).
 Most domestic, commercial and small-scale industrial
consumers receive power at low voltage, i.e. 240V or
415V. Large-scale consumers having load in excess of
100 kW buy bulk power at 11 kV and above.
13

BEF 44903 Industrial Power Systems Topic 1

1.1 Planning for Connection

 Supplies at Low Voltages of 240V and 415V


 Maximum power requirements in kVA
 Types and number of equipment and its
corresponding connected capacity in kVA
 Shunt connected reactors and capacitors in kVAr
 For single-phase 240V motors with rating of greater
than 6kVA and/or three-phase 415V motors with
rating greater than 75kVA:
 (i) Rating in HP or KVA, (ii) Types of control equipment, (iii)
Methods of starting and starting current, (iv) Frequency of
starting (number/hour), and (v) Rated power factor;
 Voltage sensitive loads (indicating sensitivity)

14

7
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.1 Planning for Connection

 Supplies at 275kV, 132kV, 33kV, 22 kV, 11kV


and 6.6kV
 For all types of loads:
 Maximum Active Power consumption in kW;
 Maximum Reactive Power consumption in kVAR.
 For motor loads:
 Types of control equipment;
 Methods of starting;
 Magnitude and duration of the starting current;
 Frequency of starting (number/hour);
 Under voltage setting and time;
 Negative phase sequence protection;
 Sub-transient and/or locked rotor reactance of the motor.
15

BEF 44903 Industrial Power Systems Topic 1

1.1 Planning for Connection

 For nonlinear loads with harmonic current injections:


 Harmonic current spectrum including harmonic number and
the corresponding maximum current.
 For fluctuating loads:
 The rates of change of Active Power and Reactive Power
consumption in kW/minute and kVAR/minute ,respectively,
both increasing and decreasing;
 The shortest repetitive time interval between fluctuations for
Active Power and Reactive Power in minutes; and
 The magnitude of the largest step changes in Active Power
and Reactive Power in kW and kVAR respectively, both
increasing and decreasing.

16

8
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.1 Planning for Connection

 For voltage sensitive loads:


 steady-state voltage tolerance limits of the equipment in
percentage of the nominal voltage;
 intrinsic immunity limits to short duration voltage variation;
 transient voltage tolerance limits of the equipment in
percentage of the nominal voltage and the corresponding
duration;
 harmonic current emission limit for equipment.
 For Shunt Connected Reactors and Capacitors:
 configuration and sizes of individual banks;
 types of switching and control equipment; and
 types of harmonic filtering reactors.

17

BEF 44903 Industrial Power Systems Topic 1

1.2 Voltage and Frequency Considerations

 Voltage Criteria
 Steady-State Voltage Fluctuation (Normal Condition):
Voltage level % variation
415 V and 240 V -10% & +5%
6.6 kV, 11 kV, 22 kV,33 kV +/- 5%
132 kV and 275 kV -5% & +10

 Steady-State Voltage Fluctuation (Contingency Condition)


Voltage level % variation
415 V and 240 V +/- 10%
6.6 kV, 11 kV, 22 kV,33 kV +10 & -10%
132 kV and 275 kV +/- 10%

18

9
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.2 Supply Voltage Options

 Low Voltage:
 Single-phase, two-wire, 240V, up to 12 kVA maximum
demand
 Three-phase, four-wire, 415V, up to 45 kVA maximum
demand
 Three-phase, four-wire, C.T. metered, 415V, up to
1,000 kVA maximum demand

19

BEF 44903 Industrial Power Systems Topic 1

1.2 Supply Voltage Options

 Medium and High Voltages:


 Three-phase, three-wire and 11 kV for load of 1,000
kVA maximum demand and above
 Three-phase, three-wire, 22 kV or 33 kV for load of
5,000 kVA maximum demand and above
 Three-phase, three-wire, 66 kV, 132 kV and 275 kV
for exceptionally large load of above 25 MVA
maximum demand

20

10
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.2 Voltage and Frequency Considerations

 Frequency Criteria
 The supply frequency is 50 Hz 1%

21

BEF 44903 Industrial Power Systems Topic 1

1.3 Classification of Distribution Systems

 The distribution systems may be classified in


the following ways:
1. According to nature of construction
a. Overhead distribution system (cheaper)
b. Underground distribution system (in crowded area)
2. According to nature of current
a. DC distribution system
b. AC distribution system
3. According to number of wires
2-wire DC system, 3-wire DC system, 1-phase 2-wire AC system,
3-phase 3-wire AC system, 3-phase 4-wire AC system
4. According to the scheme of connections
(a) Radial system
(b) Ring system
(c) Inter-connected system

22

11
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.3 Primary Distribution Lines (Feeders)

 The 33/11 kV secondary substation is established where


the load requirement is approximately 5 MVA. Since
normally a primary distribution line is designed to carry a
load of 1-2 MVA, the number of primary distribution lines
emanating from a 33/11 kV secondary substation is
about 4.
 When the load requirement increases and crosses about
8 MVA, the losses in the 33 kV sub-transmission line
become large. Thus, power must fed from a 66 kV sub-
transmission line. The number of primary distribution
lines emanating from a 66/11 kV secondary substation is
six to ten.

23

BEF 44903 Industrial Power Systems Topic 1

1.3 Primary Distribution Lines (Feeders)

 There are 3 different ways in which the primary


distribution lines can be laid:
1. The radial primary circuit
2. The loop primary circuit
3. The ring main system (or primary network)

24

12
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.3 Primary Distribution Lines (Feeders)

Radial Primary Circuits


When each circuit coming out of a substation is separate
from the other circuits and has no inter-connection with
any other circuit, it is called a radial circuit.

Circuit 1 for Factory Factory having load


of 1 MW at 11 kV

Circuit 2 feeding Substation in the city

Circuit 3 for Rural Areas


Secondary
Substation

25

BEF 44903 Industrial Power Systems Topic 1

1.3 Primary Distribution Lines (Feeders)

Advantages of Radial Feeders:


i. A heavy load very near the secondary substation.
ii. Isolated loads.
iii. An area of low load density such as a village.

Limitations of Radial Feeders:


i. When the load demand on the radial feeder increases, the
length of the feeder has to be extended. This results in a greater
voltage drop which may cause the voltage towards the tail-end
to reach a value below the permissible limit.
ii. When a fault occurs at any point along the length of the feeder,
supply to all the consumers beyond this point towards the tail-
end gets interrupted.

26

13
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.3 Primary Distribution Lines (Feeders)

Loop Primary Circuits


To overcome the limitations of the radial feeders, the
loop primary circuit is taken to use.
Secondary
Substation
11 kV 11 kV

CB4 CB5
Distribution Distribution
Substation 2 Substation 3
CB3 CB6

A
CB2 CB1 Distribution
Substation 1

27

BEF 44903 Industrial Power Systems Topic 1

1.3 Primary Distribution Lines (Feeders)

 Two 11 kV feeders emanate from the secondary


substation.
 In this system, every distribution substation receives
supply from two sides.
 In case of fault, say at point A, the circuit breaker 1 at
distribution substation 1 and circuit breaker 6 at
distribution substation 3 will open, thus isolating the
faulty section. The supply to the substation 1 and 3 is still
uninterrupted and continues to be received from another
side.
 This system is generally used in towns and cities.

28

14
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.3 Primary Distribution Lines (Feeders)

 The reliability of supply in this system has improved in


comparison with that in the radial system as it has an
alternative supply, in case one side fails.
 However, it must be realised that the source of supply for
the whole loop system is a single secondary substation.
If a fault occur in the secondary substation causing a
failure of the 11 kV supply source, the whole of the
system will suffer power interruption.

29

BEF 44903 Industrial Power Systems Topic 1

1.3 Primary Distribution Lines (Feeders)

Ring Main or Network System


A more reliable system is the ring main system.
Secondary Secondary
Substation A Substation B

CB7 CB8 CB9 CB10


11 kV 11 kV
CB4 CB5
Distribution Distribution
Substation 2 Substation 3
CB3 CB6

CB2 CB1 Distribution


Substation 1

30

15
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.3 Primary Distribution Lines (Feeders)

 In the ring main system, there are two different sources


of supply which are indicated as secondary substation A
and B.
 The ring system has the added advantage from loop
system is that should one of the sources of supply fail,
say A, the whole system continues to get supply from the
other source B.
 The ring main system is by far the most reliable for
continuity of supply. It gives a better voltage regulation
and less feeder losses.
 Circuit breakers are used instead of fuses for protecting
the transformer in ring main system due to heavier loads.

31

BEF 44903 Industrial Power Systems Topic 1

1.3 Secondary Distribution Lines (Distributors)

 Distribution substations are a link between


feeders and distributors.
11 kV Feeders
Distribution 415 V Distributors
Substations

 The standard voltage transformation at a


distribution substation is 11 kV/415V. The
declared consumer voltage as per Malaysian
Nasional Grid is 415 V between phases and 240
V between phase and neutral with a permissible
voltage variation of 5%.

32

16
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.3 Secondary Distribution Lines (Distributors)

 A consumer at the near-end of the distribution


substation may have a voltage as high as 436 V
(3-phase) and 252 V (single-phase) during light
load hours whereas a consumer at the far-end
may have a voltage as low as 395 kV (3-phase)
and 228 V (single-phase) at peak load hours.
 The circuits for the secondary distribution
system are essentially the same as those for
primary distribution except that they are on a
smaller scale.

33

BEF 44903 Industrial Power Systems Topic 1

1.3 Secondary Distribution Lines (Distributors)

 When power is supplied to the consumers


through the secondary distribution system, one
of the following arrangements is used:
1. Radial system
2. Looped system
3. Network system (Banked secondary system)

34

17
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.3 Secondary Distribution Lines (Distributors)

Radial System
In this system, the LV distribution lines radiate out from
the distribution substation.

Radial Line 1
LV CB Switch-cum
Fuse Units
11 kV Line
220 kVA 11 Radial Line 2
kV/415V

In this system, the supply is from a single 11 kV feeder.


A fault in the feeder will cause the interruption of supply
to all consumers. Circuit breaker and switch-cum fuse
units are used for protection purpose.

35

BEF 44903 Industrial Power Systems Topic 1

1.3 Expanded Radial Scheme

36

18
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.3 Secondary Distribution Lines (Distributors)

Looped System
In this case, the reliability of supply is better than in the
radial system. In the case of fault on one line, the load
can be fed from the other by connecting switch S.
415/240 V

CB
S
11 kV Line
220 kVA 11
kV/415V
415/240 V

However, a fault in the 11 kV feeder will cause the


interruption of supply to all consumers. Circuit breaker
and the fuse unit provide a protection for the transformer
and line respectively.
37

BEF 44903 Industrial Power Systems Topic 1

Primary Selective Scheme

38

19
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.3 Secondary Distribution Lines (Distributors)

Banked Secondary System


When radial secondary circuits are supplied by a single
transformer, high starting currents of motors may cause
objectionable voltage drops. One of the most effective
and economical means of controlling such a voltage drop
is the banking of distribution transformers.
11 kV Primary Distribution Line

T1 T2 T3 Fuse

415/240 V Secondary Distribution Line

39

BEF 44903 Industrial Power Systems Topic 1

1.3 Secondary Distribution Lines (Distributors)

Transformers are said to be banked when two or more


supplied from the same primary circuit are paralleled to
feed into the same secondary mains.

By this arrangement more than one path is provided


over which high currents can flow. This results in
lowering the extent to which the voltage fluctuates on
the line.

Further advantages of this system:


i. More reliable, have alternative supply from other transformer.
ii. Better load distribution on each transformer.
iii. The voltage drop in the system is reduced.
40

20
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.3 Secondary Distribution Lines (Distributors)

This system is mostly used in areas of low load


densities, where a multiple primary and secondary
network is not justified.

If a fault occurs within one of the transformers, it will be


automatically disconnected from the line by blowing the
two secondary line fuses and the primary transformer
fuse without interrupting service to any consumer.

41

BEF 44903 Industrial Power Systems Topic 1

1.3 Secondary Selective Scheme

42

21
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.3 Sparing Transformer Scheme

43

BEF 44903 Industrial Power Systems Topic 1

1.4 Load Data

 Typical range of Industrial Loads:


 Light Industry 50 kVA to 7000 kVA
 Heavy Industry 1,000 kVA to 200,000 kVA
 Typical Industrial Loads:
 HVAC
 Process equipment, pumps, compressors and fans
 Industrial services such as boiler, water treatment
 Workshop and laboratory equipment
 Motor control centre

44

22
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.4 Initial Maximum Demand Estimation

 2 methods to estimate the maximum power


demand in feasibility/ conceptual design stage:
 VA/m2 or W/ ft2 This is normally apply to commercial
building where the typical loads are lighting, general
power, and HVAC. Example: 50 100 VA/m2 for non-
retail buildings, 60 150 VA/m2 for retail buildings.
0.9 W/ft2 for lighting and 4.7 W/ft2 for Air Condition.
 Maximum demand of a similar building/ industry
Applicable for residential, commercial, and industrial
buildings. Example: Plant A having maximum demand
of 2 MVA then this figure can be used for a plant of
similar capacity.

45

BEF 44903 Industrial Power Systems Topic 1

1.4 Detailed Load Estimation

 Comprehensive load estimate based on actual


load information.
 Can be calculated either in kVA or amperes. If
the output is given in kW, the kVA can be
obtained using following formula:
kVA = kW ( PF )
 Future load should be considered as given in
spare circuits for future use.

46

23
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.4 Diversity Factor (DF)

 For better load estimation, a proper diversity


factor should be considered as not all
equipment/ load operate simultaneously.
 Definition of diversity factor:
DF = Max. Demand Connected Load
 Typical diversity factor values:
Types of load/ circuit Recommended DF
Lighting load 100%
General purpose power circuit 40% - 50%
Main switchboard 80% - 90%
Intermittent duty loads 50%

47

BEF 44903 Industrial Power Systems Topic 1

1.4 Example: Max. Loading for MCC (SB)


Load 3 Duty Motor Ope- PF x Motor Heater 3 1 1 1
description / N or rating rating =K input load load load load
1 S (kW) motor power (kVA) R Y B
power phase phase phase
(kW) (kVA) (kVA) (kVA)

Cooling
3 N 15 12 0.7 17.1 17.1
tower 1 fan
Cooling
3 S 15 12 0.7 17.1 -
tower 2 fan
Heater 3 N 5 - - - 5 5

Fan coil 1 N 1.5 1.3 0.6 2.2 2.2

Water pump 3 N 11 9 0.68 13.2 13.2

Extract fan 1 N 1 0.8 0.6 1.3 1.3

Compressor 1 N 1.5 1 0.6 1.6 1.6

Future pump 3 N 5.5 4 0.6 6.7 6.7

Total load 42.0 2.2 1.3 1.6

Total load on the MCC = 47.1 kVA


48

24
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.4 Example: Max. Loading for LV Switchboard

Load Duty (N/ S) Connected Operating K kVA


description (kW) load (kW)
DB 1 - - - - 30
DB 2 - - - - 78
MCC 1 - - - - 47.1
MCC 2 - - - - 50
Packaging
- 37 31 0.7 44.3
machine
CO2
N 75 68 0.765 88.9
compressor
Water pump 1 N 30 25 0.68 36.8
Water pump 2 S 30 25 0.68 -
Welder N 18 - 0.5 36
Future 50

Total load on LV Switchboard = 461.1 kVA


49

BEF 44903 Industrial Power Systems Topic 1

1.4 Old Supply Schemes for various M.D

50

25
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.4 New Supply Schemes for various M.D

51

BEF 44903 Industrial Power Systems Topic 1

1.4 In-Class Practise (1)

 A small industrial plant has the following loads:


 Twenty (20), 200HP motors (only half of them are running at any
given time), K = 0.78.
 Ten (10), 50 HP motors (8 motors are running at the same time),
K = 0.68.
 500 kW of heating and process loads.
 Two (2), 50 kVA lighting transformers, PF = 0.92, = 95%
 100 HP of small (mostly fractional HP, only 85% are running at
any given time) motors, K = 0.72

TASK
Decide the proper supply voltage from local utility

52

26
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.5 Common Connection for Transformer

53

BEF 44903 Industrial Power Systems Topic 1

1.5 Why Delta Grounded Star

 Delta at primary
 Free of 3rd harmonics of the magnetising currents and
any possible homopolar current are free to circulate
through the sides of the delta, without flowing into the
network; thus, the magnetic fluxes remain sinusoidal
at the secondary.
 In case of unbalanced loads at the secondary
winding, the reaction current absorbed by the primary
flows only through the corresponding winding (as
shown in the figure) without affecting the other two.

54

27
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.5 Why Delta Grounded Star

 Grounded Star at secondary


 To make line and phase voltages easily available.
 For safety reasons, since in the event of a fault
between the MV and LV sides, the voltage at the
secondary remains close to the phase value, thus
guaranteeing higher safety for people and maintaining
the insulation.

55

BEF 44903 Industrial Power Systems Topic 1

1.5 Basic Installation of Industrial Plant

56

28
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.5 Methods of Transformer Installation

 Method 1 Substation with a single transformer

In the case where the


protection device also
carries out switching and
isolation functions, an
interlock must be provided
which allows access to the
transformer only when the
power supply line of the
substation has been
isolated.
Installation of the SMV
switching and isolation
device positioned
immediately to the supply
side of the transformer.

57

BEF 44903 Industrial Power Systems Topic 1

1.5 Methods of Transformer Installation

 Method 2 Substation with two transformers


with one as a spare for the other
The circuit-breakers on the
LV side must be connected
with an I interlock whose
function is to prevent the
transformers from operating
in parallel.
Apart from the switching and
isolation device on the
incoming MV line (IGMV), it is
advisable to provide a
switching, isolation and
protection device on the
individual MV risers of the
two transformers (IMV1 and
IMV2) as well.

58

29
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.5 Methods of Transformer Installation

 Method 3 Substation with two transformers


which operate in parallel on the same busbar
Possible to use two
transformers with lower
rated power.
Operation in parallel of the
transformers could cause
greater problems in
management of the
network.
When coordinating the
protections, the fact that
the overcurrent on the LV
side is divided between the
two transformers must be
taken into consideration.

59

BEF 44903 Industrial Power Systems Topic 1

1.5 Methods of Transformer Installation

 Method 4 Substation with two transformers


which operate simultaneously on two separate
half-busbars
Providing a CLV bus-tie
and an I interlock
which prevents the bus-
tie from being closed
when both the incoming
circuit-breakers from the
transformer are closed.
This management
method allows a lower
value of the short-circuit
current on the busbar.

60

30
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.5 In-Class Practise (2)

 Refer again the problem given in In-Class


Practise (1).

TASK
Design a simple power system (one-line diagram)

61

BEF 44903 Industrial Power Systems Topic 1

1.5 Transformer Sizing

 Transformer sizing is generally based on:


 Total max. demand of individual/ group consumer
 Installed voltage level (kV)
 Method of installation or arrangement
 Short circuit capacity

62

31
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.5 In-Class Practise (3):Transformer Sizing

 Lets calculate voltage drop in transformer 1000


KVA, 11/ 0.480 kV, impedance 5.75% due to starting
of 300 kW, 460V, 0.8 power factor, motor code D
(kVA/HP). Motor starts 2 times per hour and the
allowable voltage drop at transformer secondary terminal
is 10%. Is the transformer size suitable?

63

BEF 44903 Industrial Power Systems Topic 1

1.5 Transformer Sizing


Code Letter (KVA per HP) -Locked Rotor Current
Motor Code Min Max
A 3.15 -
B 3.16 3.55
C 3.56 4
D 4.1 4.5
E 4.6 5
F 5.1 5.6
G 5.7 6.3
H 6.4 7.1
J 7.2 8
K 8.1 9
L 9.1 10
M 10.1 11.2
N 11.3 12.5
P 12.6 14
R 14.1 16
S 16.1 18
T 18.1 20
U 20.1 22.4
V 22.5 -

64

32
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.5 In-Class Practise (4):Transformer Sizing

If the previous motor load is changed to the following:

Total KW of Three Phase Motors: 300 kW


Total KW of Single Phase Motors: 10 kW
Volt (L-L) : 460 Volt
Power Factor: 0.8
Locked Rotor Current: 450% (Max)

Analyse again the suitability of the transformer size


used.

65

BEF 44903 Industrial Power Systems Topic 1

1.5 In-Class Practise (5):Transformer Sizing

 Short circuit capacity with infinite source

Infinite source

FLA = ?
What is %Z?
1000 kVA
ISCmax = ?
11kV 415 V
kVASC = ?
%Z = 5%
kVASC = ?

66

33
20/09/2017

BEF 44903 Industrial Power Systems Topic 1

1.5 In-Class Practise (6):Transformer Sizing

 Short circuit capacity with finite source

500 MVASC

MVASC(TX) = ?
1000 kVA MVASC(SEC) = ?
11kV 415 V ISCmax = ?
%Z = 5%
kVASC = ?

67

BEF 44903 Industrial Power Systems Topic 1

1.5 In-Class Practise (7):Transformer Sizing

 Simple transformer-load connection

FLA = ?
1000 kVA ISCmax = ?
11kV 415 V kVASC = ?
%Z = 5.0%
kVASC = ? Is the given size (1000
kVA) suitable to serve
the motor load?

80% Full load


M Inrush current = 6 times

68

34

Das könnte Ihnen auch gefallen