Beruflich Dokumente
Kultur Dokumente
Cost
Budget At
Completion
(BAC)
Planned
Value (PV)
Time
Cost
Planned
Value (PV) Budget At
Completion
(BAC)
Actual
Cost (AC)
Status date
Time
Cost
Planned
Budget At
Value (PV)
Completion
(BAC)
Actual
Cost (AC)
Earned
Value (EV)
terminology was simplified and more details on Earned Value Planned Value (PV): This is the time-phased budget base-
Management (EVM) were provided in the 2000 edition of the line. It is the approved budget for accomplishing the activity,
PMBOK Guide (PMI, 2000). This paper uses the simplified ter- work package, or project related to the schedule. It can be viewed
minology and relates it to previously used terminology. The as the value to be earned as a function of accomplishments up
paper provides extensions and applications of EVM using the to a given point in time. A graph of cumulative PV is often re-
simplified terminology.
ferred to as the S-curve (because, with a little imagination, it
looks like an S). This was previously called the Budgeted Cost of
Key Components of EVM Work Scheduled (BCWS).
Budget at Completion (BAC): This is the total budget baseline
The Earned Value Analysis method uses the following project pa- for the activity, work package, or project. It is the highest value
rameters to evaluate project performance: of PV, and the last point on the cumulative PV curve.
Cost
Planned
Budget At
Value (PV)
Completion
(BAC)
CV
Actual SV
Cost (AC)
Earned
Value (EV) Status date
TV Time
Actual Cost (AC): This is the actual cost spent to accomplish ment rate or the PV Rate. SV can be translated to time units by
an activity or project and to earn the related value up to a given dividing SV over the average PV per time period. The result is the
point in time. This was previously called the Actual Cost of SV in time units or the Time Variance (TV):
Work Performed (ACWP). TV = SV / PV Rate (i.e., TV = SV / Spend Rate)
Earned Value (EV): This is the earned value for the work The above can also be performed and reported graphically as
completed to a point in time. It represents the amount budgeted shown in Exhibit 4.
for performing the work which was accomplished by a given Graphs of variances over time provide valuable indicators of
point in time. This was previously called the Budgeted Cost of trends in project performance and impact of any corrective ac-
Work Performed BCWP. tions.
Performance Indices
Performance Measurement The following equations are used to calculate the performance
indices, generally based on cumulative data:
Cost performance is determined by comparing the Earned Value The Cost Performance Index is a measure of the conformance
(EV) to the Actual Cost (AC). Schedule performance is deter- of actual cost of work performed to the budget:
mined by comparing the Earned Value (EV) to the Planned CPI = EV / AC
Value (PV). Calculating the variances and the performance in- The Schedule Performance Index is a measure of the confor-
dices allows us to do this. mance of actual progress to the schedule:
SPI = EV / PV
Variances
In the above equations,1 indicates performance is on target.
The following equations are used to calculate the variances, gen- More than 1 indicates good performance. Less than 1 indi-
erally based on cumulative data: cates poor performance. As such, the performance indices can be
The Cost Variance (CV) is a measure of the conformance of thought of as efficiency ratios.
actual cost of work performed to the budget: The inverse of the equations given above has also used to fa-
CV = EV - AC cilitate the use of the indices in forecasting.
The Schedule Variance (SV) is a measure of the conformance Graphs of performance indices over time provide valuable in-
of actual progress to the schedule: dicators of trends in project performance and impact of any cor-
SV = EV - PV rective actions. These graphs can be very effective in project
In the above equations,0 indicates performance is on target. reviews.
A negative value indicates poor performance. A positive value in-
The Critical Ratio
dicates good performance.
The average PV per time period is often referred to as the The Critical Ratio is the product of CPI and SPI. It can also be
Spend Rate. A better name may be the planned accomplish- called the Cost-Schedule Index (CSI), and has been used as an
Conclusion
References
Anbari, F.T. 1997. Quantitative Methods for Project Management.
New York: International Institute for Learning.
Previous Menu