Sie sind auf Seite 1von 5

Applications and Extensions of the

Earned Value Analysis Method


Frank T. Anbari, Ph.D., PMP,The George Washington University

Introduction ilar quantity that can be used as a common measurement of the


values associated with project work.
The Earned Value Analysis Management Method (often referred This paper presents the major aspects of EVM, and provides
to as EVM or EVA) integrates three critical elements of project logical extensions and practical applications of this important
management: scope management, cost management and time method in project management.
management. It requires the periodic monitoring of actual ex-
penditures and physical scope accomplishments. EVM supports
the periodic evaluation of project performance against the time Background
schedule and cost plan, and allows forecasting of project cost and
schedule at completion. A basic form of EVM can be traced back to industrial engineers
EVM provides early indications of expected project results on the factory floor in the late 1800s (Fleming & Koppelman,
based on project performance and highlights the possible need 2000; Kim, 2000). Around 1967, EVM was introduced by agen-
for corrective action. As such, EVM allows the project manager cies of the U.S. Federal Government as an integral part of the
and project team to adjust project strategy based on cost and Cost/Schedule Control System Criteria (C/SCSC) and used in
schedule requirements, actual project performance and trends, large acquisition programs. Use of EVM in industry and support
as well as the environment within which the project is being by popular project management software packages have been
conducted. limited but growing in recent years. To encourage wider use of
This powerful tool uses cost as the common measure of proj- EVM in the private sector, the U.S. Federal Government de-
ect cost and schedule performance. It allows the calculation of cided to discard C/SCSC by the end of 1996 and is turning to-
cost and schedule variances, performance indices, and forecasts ward a more flexible Earned Value Project Management System
of project cost and schedule at completion. It allows the mea- (EVPMS). Project Management Institutes PMBOK Guide (PMI,
surement of cost in dollars, hours, worker-days, or any other sim- 1996) provided the basic terminology and formulas of EMV. The

Exhibit 1. Planned Value

Cost

Budget At
Completion
(BAC)
Planned
Value (PV)

Time

Proceedings of the Project Management Institute Annual Seminars & Symposium


November 110, 2001 Nashville,Tenn., USA
Exhibit 2. Planned Value and Actual Cost

Cost
Planned
Value (PV) Budget At
Completion
(BAC)

Actual
Cost (AC)

Status date
Time

Exhibit 3. Planned Value, Actual Cost, and Earned Value

Cost
Planned
Budget At
Value (PV)
Completion
(BAC)

Actual
Cost (AC)

Earned
Value (EV)

Status date Time

terminology was simplified and more details on Earned Value Planned Value (PV): This is the time-phased budget base-
Management (EVM) were provided in the 2000 edition of the line. It is the approved budget for accomplishing the activity,
PMBOK Guide (PMI, 2000). This paper uses the simplified ter- work package, or project related to the schedule. It can be viewed
minology and relates it to previously used terminology. The as the value to be earned as a function of accomplishments up
paper provides extensions and applications of EVM using the to a given point in time. A graph of cumulative PV is often re-
simplified terminology.
ferred to as the S-curve (because, with a little imagination, it
looks like an S). This was previously called the Budgeted Cost of
Key Components of EVM Work Scheduled (BCWS).
Budget at Completion (BAC): This is the total budget baseline
The Earned Value Analysis method uses the following project pa- for the activity, work package, or project. It is the highest value
rameters to evaluate project performance: of PV, and the last point on the cumulative PV curve.

Proceedings of the Project Management Institute Annual Seminars & Symposium


November 110, 2001 Nashville,Tenn., USA
Exhibit 4. Variances

Cost
Planned
Budget At
Value (PV)
Completion
(BAC)
CV
Actual SV
Cost (AC)

Earned
Value (EV) Status date

TV Time

Actual Cost (AC): This is the actual cost spent to accomplish ment rate or the PV Rate. SV can be translated to time units by
an activity or project and to earn the related value up to a given dividing SV over the average PV per time period. The result is the
point in time. This was previously called the Actual Cost of SV in time units or the Time Variance (TV):
Work Performed (ACWP). TV = SV / PV Rate (i.e., TV = SV / Spend Rate)
Earned Value (EV): This is the earned value for the work The above can also be performed and reported graphically as
completed to a point in time. It represents the amount budgeted shown in Exhibit 4.
for performing the work which was accomplished by a given Graphs of variances over time provide valuable indicators of
point in time. This was previously called the Budgeted Cost of trends in project performance and impact of any corrective ac-
Work Performed BCWP. tions.
Performance Indices
Performance Measurement The following equations are used to calculate the performance
indices, generally based on cumulative data:
Cost performance is determined by comparing the Earned Value The Cost Performance Index is a measure of the conformance
(EV) to the Actual Cost (AC). Schedule performance is deter- of actual cost of work performed to the budget:
mined by comparing the Earned Value (EV) to the Planned CPI = EV / AC
Value (PV). Calculating the variances and the performance in- The Schedule Performance Index is a measure of the confor-
dices allows us to do this. mance of actual progress to the schedule:
SPI = EV / PV
Variances
In the above equations,1 indicates performance is on target.
The following equations are used to calculate the variances, gen- More than 1 indicates good performance. Less than 1 indi-
erally based on cumulative data: cates poor performance. As such, the performance indices can be
The Cost Variance (CV) is a measure of the conformance of thought of as efficiency ratios.
actual cost of work performed to the budget: The inverse of the equations given above has also used to fa-
CV = EV - AC cilitate the use of the indices in forecasting.
The Schedule Variance (SV) is a measure of the conformance Graphs of performance indices over time provide valuable in-
of actual progress to the schedule: dicators of trends in project performance and impact of any cor-
SV = EV - PV rective actions. These graphs can be very effective in project
In the above equations,0 indicates performance is on target. reviews.
A negative value indicates poor performance. A positive value in-
The Critical Ratio
dicates good performance.
The average PV per time period is often referred to as the The Critical Ratio is the product of CPI and SPI. It can also be
Spend Rate. A better name may be the planned accomplish- called the Cost-Schedule Index (CSI), and has been used as an

Proceedings of the Project Management Institute Annual Seminars & Symposium


November 110, 2001 Nashville,Tenn., USA
indicator of the overall project health (Meredith & Mantel, 2000; The Variance at Completion (VAC) gives an indication of the
Lewis, 2001): estimated cost underrun or overrun at the end of the completion
CR = CPI x SPI of the project:
A CR of 1 indicates that the overall project performance is VAC = BAC EAC
on target. This may result from both CPI and SPI being close to In the above equation,0 indicates that the project is forecasted
target, or if one of those indices is indicating poor performance, to be completed on budget. A positive value indicates a forecasted
then the other must be indicating good performance. This allows underrun. A negative value indicates a forecasted overrun.
some tradeoffs to reach the desired goals. Heinze (1996) provides the following additional formula for
A CR of more than 1 indicates that the overall project per- calculating EAC:
formance is good. This may result from both CPI and SPI being EAC = BAC / CPI x SPI
better than target, or if one of those indices is indicating poor Based on the above definition of the critical ratio (CR), and
performance, then the other must be indicating outstanding further defining EACs as the EAC adjusted for schedule perfor-
performance. This allows extensive tradeoffs to reach the desired mance, the above equation can be restated as follows:
goals. EACs = BAC / CR
A CR of less than 1 indicates that the overall project perfor- The above formula may be mathematically questionable.
mance is poor. This may result from both CPI and SPI being However, it acknowledges that cost performance and schedule
worse than target, or if one of those indices is indicating good performance are inseparable. As examples (1) project schedule
performance, then the other must be indicating extremely poor can be crashed at an additional cost, or (2) less experienced re-
performance. This limits the use of effective tradeoffs and high- sources may be used on the project, reducing the cost and pos-
lights significant difficulty in attempting to reach the desired sibly extending the duration. As such, this formula may provide
goals. a better indication of forecasted project cost at completion.
A graph of the critical ratio over time provides a quick indi- Forecasting of Completion Time
cator of trends in the overall project performance and impact of
any corrective actions. These graphs may be effective in project Using the same logic, EVM can be used to calculate the projects
reviews. total Time Estimate At Completion (TEAC) and the Time
Variance At Completion (TVAC), based on the baseline Schedule
At Completion (SAC) and actual performance up to any given
point in the project (Anbari, 1997). The following equations can
Forecasting
be used to calculate these forecasts. These terms and equations
have been used implicitly, but have not been documented as such
Project decisions are mainly concerned with the future.
in popular textbooks on the subject:
Therefore, forecasting is an extremely important aspect of proj-
Time Estimate at Completion:
ect management. EVM is particularly useful in forecasting the
TEAC = SAC / SPI
cost and time of the project at completion, based on actual per-
Time Variance at Completion:
formance up to any given point in the project.
TVAC = SAC TEAC
Forecasting of Cost at Completion Project Forecasting
EVM has been widely used to estimate the total cost of the project Forecasting in project management may well be a self-defeating
at completion and the cost to complete the remainder of the proj- prophecy. Large deviations usually attract managements atten-
ect, based on actual performance up to any given point in the proj- tion and result in corrective action. Small deviations are usually
ect. The following equations are used to calculate these forecasts: left alone. By quantifying such deviations, EVM helps focus
Several assumptions can be used to calculate the Cost Estimate managements attention on projects or work packages that need
at Completion. The 2000 edition of the PMBOK Guide (PMI, most attention. As a result, EVM supports effective manage-
2000) gives the following formula for the Estimate at Completion ment of projects and work packages collectively, and enhances
(EAC), based on cumulative data, and based on the assumption the management of the enterprises project portfolio.
that past performance and efficiency will continue into the fu-
ture:
EAC = AC + (BAC - EV) / CPI Further Extensions and Applications
The above equation can be appropriately simplified as follows:
EAC = AC + (BAC - EV) / CPI Using the above definitions, the following is derived:
= AC + BAC / CPI - EV / CPI % Complete = EV / BAC
= AC + BAC / CPI - AC % Spent = AC / BAC
= BAC / CPI Taking the ratio of the above two equations:
Thus: % Complete / % Spent = (EV / BAC) / (AC / BAC)
EAC = BAC / CPI = EV / AC

Proceedings of the Project Management Institute Annual Seminars & Symposium


November 110, 2001 Nashville,Tenn., USA
Thus: Fleming, Q.W., and Koppelman, J.M. 2000. Earned Value Project
CPI = % Complete / % Spent Management, Second Edition. Newtown Square, PA: Project
Similarly: Management Institute.
CPI = Planned Unit Cost / Actual Unit Cost Harrison, F.L. 1992. Advanced Project Management: A Structured
Approach, Third Edition. England: Gower Publishing Company Limited.
The above formulas provide a more intuitive understanding
Heinze, Kurt. 1996. Cost Management of Capital Projects. New York:
of CPI based on information readily available in many organi-
Marcel Dekker, Inc.
zations. Kerzner, H. 2001. Project Management: A Systems Approach to
EVA can be applied to projects of various sizes. It can be ap- Planning, Scheduling, and Controlling, Seventh Edition. New York: John
plied at various levels of a projects Work Breakdown Structure Wiley & Sons.
(WBS) and to various cost components, such as labor, material, Kerzner, H., Anbari, F.T., Cleland, D.I., and Zeitoun, A. 2001. Project
subcontractors, and other cost components. Management IQ, Release 3.2. New York: International Institute for
Learning.
Kim, E.H. 2000. A Study on the Effective Implementation of Earned
Comprehensive Example Value Management Methodology, Ph.D. Dissertation. Washington, DC:
The George Washington University.
Lewis, J.P. 2001. Project Planning, Scheduling, & Control: A Hands-On
A project has a baseline budget of $100,000, and a baseline
Guide to Bringing Projects In On Time and On Budget. Third Edition.
schedule of 40 weeks. The baseline indicates that by the end of
New York: McGraw-Hill.
week 20 the project is planned to be 50% complete. As of the end Meredith, J.R., and Mantel, S.J. 2000. Project Management: A
of week 20, it is reported that 40% of the project work has been Managerial Approach. New York: John Wiley & Sons.
completed at a cost of $60,000. Using the EVM method: Project Management Institute. 1996. A Guide to the Project
BAC = $100,000 Management Body of Knowledge (PMBOK Guide). Upper Darby, PA:
SAC = 40 weeks Project Management Institute.
% Complete = 40% Project Management Institute. 2000. A Guide to the Project
% Spent = AC / BAC = $60,000 / $100,000 = 60% Management Body of Knowledge (PMBOK Guide). Newtown Square, PA:
PV = 50% x $100,00 = $50,000 Project Management Institute.
AC = $60,000
EV = 40% x $100,00 = $40,000
CV = EV - AC = $40,000 - $60,000 = - $20,000
SV = EV - PV = $40,000 - $50,000 = - $10,000
CPI = EV / AC = $40,000 / $60,000 = 0.67
CPI = % Complete / % Spent = 40% / 60% = 0.67
SPI = EV / PV = $40,000 / $50,000 = 0.80
CR = CPI x SPI = 0.67 x 0.80 = 0.53
EAC = BAC / CPI = $100,000 / 0.67 = $150,000
VAC = BAC EAC = $100,000 - $150,000 = - $50,000
EACs = BAC / CR = $100,000 / 0.53 = $187,500
TEAC = SAC / SPI = 40 weeks / 0.80 = 50 weeks
TVAC = SAC TEAC = 40 weeks - 50 weeks = - 10 weeks

Conclusion

EVM helps focus managements attention on projects that need


most attention and enhances the enterprises project portfolio
management. EVM provides important information for project
or work packages decision-making. Its effectiveness and accep-
tance may depend on better understanding of its capabilities and
limitations. Simplification of EVM calculations and its success-
ful application in industry are important to the growth of its ef-
fective use.

References
Anbari, F.T. 1997. Quantitative Methods for Project Management.
New York: International Institute for Learning.

Proceedings of the Project Management Institute Annual Seminars & Symposium


November 110, 2001 Nashville,Tenn., USA

Previous Menu

Das könnte Ihnen auch gefallen