Case Analysis Form

Participant Name: Adnan Ahmad


Case Title: Medisys
Main Problem and Reasons The Main Problem is lack of communication and coordination.
for the Problem Nobody was willing to break the bad news to Marketing Manager and
CEO. Another problem was that There was no proper communication
regarding current system requirement and future upgrades.

Solution/Recommendations Proper Road Map for Product to be developed. The Road map to be
properly communicated to Project Team members. Proper Weekly/Bi-
weekly Project meeting to be held to discuss the Project progress

Communication Strategy
Purpose

1. 2. 3.
Key Audiences

Audience 1 Purpose Message Medium

VP sales Approval To Get approval Presentation/


of no modular Meeting
system and
then Up-
gradation to
Modular
system
CEO and VP Approval To Get approval Presentation/
Sales of no modular Meeting
system and
then Up-
gradation to
Modular
system
VP design and Information Complete Presentation
Engineering, Product Road
VP production map
,VP research
and
development,
VP
administration
Project Team
leader
Project Team Instructions To Instruct Memo/Email
members Regarding
Meeting and
Communication
Regarding any
obstacles