IMPLEMENTATION OF
REC MECHANISM
NLDC 1
INDEX
REDEMPTION OF RECs
NLDC 2
Schematic for REC Implementation
Procedures
NLDC 3
Model Guidelines / Procedure for Accreditation
Verification Prior
2 to Accreditation
1 3b
Eligible Entity Application for State Agency Intimation of SLDC
Accreditation Accreditation
3a Confirmation of
Accreditation
3c
Intimation of
Accreditation
Central Agency
Procedure for Registration
6b 6c
Intimation of
Intimation of
Registration
Registration
Application for 4
Registration
Central Agency
6d
Confirmation of
6a Power Exchange
Registration Verification 5
Prior to Intimation of
Registration Registration
Procedure for Issuance
Intimation of
State Agency Issuance
5b
Verification
2
Pre-Condition
3
Regular Injection Central
SLDC Report Agency
Intimation of Meter Issuance of
Reading REC
4
4c
Application for
4b 1 5a
Issuance
Distribution
Licensee
4a
Eligible Entity
Joint Meter
Reading
Procedure for Redemption
Central
Agency
Confirmation
Verification
2 Of REC validity &
Conditions
quantity
(By 15:30)
(by 16:00)
Market Clearance
Intimation of Trade results (Volume & Price)
For Extinguishing REC 3
(By 17:00)
4
Central
Reports
Agency
MODEL GUIDELINES FOR
ACCREDITATION BY STATE AGENCY
NLDC 8
Model Guidelines: Contents
Objective
Applicability & Scope
Step wise description
Functions, roles and responsibilities of entities
involved
Information requirement – application form & content
R
Report:
t fformatt ffor accreditation
dit ti certificate
tifi t
Timelines
Fees and charges
Event of default and consequences thereof
Powers to remove difficulties
NLDC 9
Model Guidelines: Applicability & Scope
NLDC 10
Model Guidelines: Information Requirement
Owner
Operator
RE Station
Connectivity
Metering
Statutory Clearance
General
Fees & Charges
Declaration
Online generation of Application, print & submit to State Agency along with
enclosures
NLDC 11
Model Guidelines: Timelines, Fees & Charges
Timelines:
Undertake accreditation of those g
generatingg facilities which
are proposed to be commissioned within period not
exceeding 6 months from the date of application.
State Agency to inform the applicant with regard to the
incompleteness of the application within 2 working days.
¾ Applicant to respond within 7 working days.
NLDC 12
REGISTRATION BY CENTRAL
AGENCY
NLDC 13
NLDC 13
Registration: Applicability and Scope
Undertake registration
Not earlier than 3 months prior to proposed date of
commissioning
After receipt of Certificate of Accreditation
NLDC 14
Registration: Information Requirement
Online
O li generation
ti off Application,
A li ti print
i t & submit
b it to
t Central
C t l Agency
A along
l with
ith
enclosures
NLDC 15
Registration: Time Line
Furnishing the
Central Agency
requested
Application details by the
accompanied applicant
with fees and Grant of
charges Registration
3 Months
2 days
7 days
15 days 15 days
Intimation Process of
regarding Registration
g Payment of
Incompleteness applicable
of application registration
Charges
NLDC 16
Registration: Fees and Charges
NLDC 17
ISSUANCE OF RECs BY CENTRAL
AGENCY
NLDC 18
Issuance of RECs
Information Requirement
Renewable Energy Injection Report
The Registration Number issued by Central Agency
Details of Fee and Charges
Compliance Auditor report, if any
Denomination
1 REC = 1 MWh
NLDC 19
Issuance of RECs: Timelines
The application
Th li ti for
f issuance
i off Renewable
R bl Energy
E
Certificates may be made on a fortnightly basis
NLDC 20
REDEMPTION OF RECs AFTER
TRADE IN POWER EXCHANGE(s)
NLDC 21
Redemption of RECs
3/19/2010 NLDC 22
Draft Procedures for REC Implementation
www.forumofregulators.org
www.cercind.gov.in
www nldc in /
www.nldc.in www nldcindia in
www.nldcindia.in
www.forumofloaddespatchers.in / www.forumofld.in
NLDC 23
Thank you !!