Sie sind auf Seite 1von 4

EI-FACT SHEET 2013 - 02 1

SECURITY OF ELECTRIC POWER SUPPLY


The ongoing debate on security of electric power supply in The focus of this factsheet is on system adequacy in Belgium. The
Belgium has mostly been related to the discussion about the supply side, generation and network adequacy combined, must
operation of the Belgian nuclear units. The discussion came meet the inherent fluctuations in demand, taking into account the
onto the political agenda in the summer of 1999, culminating non- storability of electricity and limited dispatchable nature of
in the Federal Act of 31 January 2003, which embedded the wind and solar power generation.
Belgian nuclear phase out. However, the option was left open
to deviate from this calendar if security of supply is at risk. Latest publications on the topic
The topic gained more attention in 2008-2010 when the phase
out was first delayed, and even more so after the Fukushima Rapport over de middelen voor elektriciteits productie 2012-
nuclear accident in 2011, when yet a different calender was 2017 - FOD Economie
decided upon in June 2012. Finally, the temporary closure of
Doel 3 and Tihange 2, due to observed indications pointing The Federal Energy Observatory made an estimate on the evolution
to possible flaws in the reactor vessels, even intensified the of both demand and generation capacity in the period 2012-2017 in
debate on whether the electic power supply is still secured. Belgium, taking into account different options for the nuclear phase
out. Different scenarios concerning the evolution of demand
and flexible generation are used in both a deterministic and a
What are we talking about?
probabilistic model.
According to Eurelectric, Security of electricity supply is the Conclusions:
ability of the electrical power system to provide electricity to
end-users with a specified level of continuity and quality in a Ever y scenario without impor t capacity requires large
sustainable manner. The concept of security of electric power investments in new flexible generation capacity;
supply is subdivided depending on the time frame: No scenario with impor t capacity, without new flexible
generation capacity by the year 2017 and the closure
Short-term: Operational security (also referred to as of nuclear generation capacity meets the criterion for
operational reliability) the ability of the system to security of the electric power supply;
withstand sudden disturbances such as electric shor t The Belgian generation portfolio faces challenges concerning
circuits or unanticipated loss of system elements; flexibility caused by a combination of non-flexible base load
and the rising share of renewables.
Long-term: Adequacy the ability of the system to supply
the aggregate electrical demand of customers at all times,
Studie (F)120801-CDC-1167 : Studie van de bevoorradingszekerheid
taking into account scheduled and reasonably expected van aardgas en elektriciteit bij de laagste temperaturen sinds de
unscheduled outages. Long-term adequacy is furthermore vrijmaking van de markten (februari 2012)
subdivided as shown in figure 1.
The CREG study used data collected during the cold spell of Feb-
ruary 2012 to look whether Belgium would be able to guaran-
tee supply of electricity if the temperatures were more extreme
(-11C) when having normal economic activity.

Conclusions:

Under extreme temperatures and normal economic activity


security would not have been guaranteed from 7 until 10
February.
Under extreme temperatures Belgium depends on generation
from pumped-hydro1;
1
Which is not really generation but storage and also needed for grid
Figure 1: Definitions of adequacy (source: Eurelectric) services.

Lessons learned:
Belgium structurally depends on imports to meet peak demand;
The loss of flexible generation capacity in the near future will amplify the challenge of integrating the growing share of
renewables in the system;
Market signals such as price spikes, although negatively perceived by the end consumers, have an important impact on
investments to meet short and long-term system reliability.

KU Leuven Energy Institute EI Fact sheet Security of Electric Power Supply


EI-FACT SHEET 2013 - 02 2

ENTSO-E, Winter Outlook 2012/2013 Flexible generation: gas-fired power plants and hydro with
dam, having load following capabilities or used to respond to
ENTSO-E publishes annually the Summer Review and Winter fluctuations in demand or renewable power generation;
Outlook Report which assesses the adequacy of the power Renewable energy: hydro run of river, wind and solar power.
system for the next winter period and provides an overview of They are characterized by their non-dispatchable nature.
the main events occurred during the previous summer.
Capacity Evolution:
Conclusions:
As shown in figure 3, the first step of the nuclear phase out in
Under the defined normal and severe conditions, the European 2015 (according to the decision of June 2012) represents a loss
power system as a whole has adequate generation capacity to of 866 MW of generation capacity (Doel 1 & 2). Then there is the
meet demand. Due to the unavailability of approximately 2000 announced significant loss of flexible generation capacity of 2200
MW nuclear capacity, Belgium will remain structurally dependent MW) by the year 2017.The main reason for the closure of several
on imports during the entire winter period; flexible generation power plants (CCGTs, and coal due to the EU
The effect of the nuclear phase out in Germany has an impact Large Combustion Plants Directive) is said to be of an economic
on power system adequacy during the 2012/2013 winter period, nature. The loss of flexible generation capacity in the near future
not only at the national, but also at European level. Germany may will amplify the challenge of integrating the growing share of
require imports during certain weeks of the winter, to maintain renewables in the system.
adequacy.
Not all installed generation capacity is available for generation;
The reflections made above, lead to a structured, threefold analysis of the available generation capacity decreases with the reserves
security of electric power supply including Belgian generation capacity, (ancillary services) held by the TSO and the(un)planned outages.
peak demand levels and import. The last aspect considers both
available interconnections and generation capacity in neighboring Outages
countries.
The available generation capacity is influenced by the planned
Belgian generation capacity and unplanned outages. The planned outages are scheduled
maintenances. For the winter 12-13, the maximum capacity loss
Figure 3 provides a clear view on the available generation due to planned outages is 430 MW (scource: Elia) and is used as
capacity and its expected evolution for the upcoming years. measure for the analysed period. The loss of generation capacity
Next to the quantity of the generation capacity it is necessary due to unplanned capacity is unpredictable. Due to the extended
to get acquainted with certain properties of different generation outage of Doel 3 and Tihange 2, the capacity of unplanned outages
technologies. has exceeded 2000 MW in the winter 12-13.

Peak demand levels


Elia holds 3 different reserves to maintain bal-
ance: The Belgian generation capacity should be operated in order to
Primary control: frequency stabilization in a time satisfy electricity demand levels in real time. A historical data analysis
frame of seconds (+/- 100 MW); of the winter 11-12 has incidated that the top 25 demand levels
Secondary control: frequency restoration is a time all occurred in February 2012, being significantly colder than usual.
frame of minutes (+/- 140 MW), fast- response reserves The highest demand levels occurred during the typical evening peak
procured from spinning conventional generators; between 6 and 8 PM.
Tertiary control: assist secondary reserves inside
time frame of 15 minutes (settlement period), (+/- 400 Knowing that the highest demand levels occurred during the
MW generation side excluding inter-TSO agreements typical evening peak between 6 and 8 PM in winter time, the
and interruptible load contracts). available generation capacity must be reduced by the total
installed solar power capacity which is then idle. Also, in accordance
Generation technologies: with the scenarios of the Federal Energy Observatory and the CREG,
mentioned above, the installed wind power capacity is subtracted
The available generation capacity can be divided into base load, from the available generation capacity, assuming windless moments.
flexible generation and renewable energy as follows:
Historical peak demand levels3 have not drastically changed in
Base load: coal and nuclear power;2 the last 6 years (Figure 2). Additionally, there is an unclear linkage

2
Baseload due to the usual merit order; these plants can participate in
3
These demand levels include active power absorbed by all installations
load following if needed. In case of low gas prices (cfr USA), gas-fired connected to the transmission network or to the distribution network,
plants may become part of base load. including losses.

KU Leuven Energy Institute EI Fact sheet Security of Electric Power Supply


EI-FACT SHEET 2013 - 02 3

Interconnection capacity

Belgium is physically connected with the Nederlands and France.


The physical interconnection capacity is limited to 6000 MW
(Belgium-the Nederlands) and 5000 MW (Belgium-France). This
physical capacity is restricted because of safety precautions (N-1
restrictions4). The available commercial capacity (=Net Transfer
Capacity; NTC) offered to the market does not equal the physical
capacity. The physical capacity contains a significant margin for
possible outages (Transmission Reliability Margin of 250 MW) and
loop flows (=difference between the scheduled and actual power
flow). Next to these reducing factors, the commercial capacity
can be reduced due to the capacity of the national grid (internal
congestion).

Figure 2: Historical peak demand levels, ref: ENTSO-E As a result, the commercial interconnection capacity between the
Nederlands and Belgium is limited to 1701 MW in both directions
between the total yearly power consumption and peak demand (including recent upgrade of 300 MW). The import capacity from
levels. Following trends in the total energy usage may also influence France is limited to 2300 MW, while export capacity is as high as
future peak levels: 3400 MW. Difference between import and export capacity is due
to the limited capacity of the national grid in France.
Energy efficiency may reduce the total electricity consumption;
Economic growth or the economic slowdown are directly Belgian simultaneous import capacity is limited to 3000 MW
correlated with electricity demand levels; during summer and 3500 MW during winter.To allow the parties to
Further electrification of society like electric mobility or heating optimize their import and export strategies, a number of allocation
(heat pumps) may also influence future electricity consumption. mechanisms are provided covering different time scales: yearly,
monthly, daily and intra-day.

Figure 3: Evolution total (firm and non-firm) generation capacity 2012-2017

4
This criterion on system robustness expresses the ability of the power
system to lose a single network element without causing an overload
failure elsewhere.

KU Leuven Energy Institute EI Fact sheet Security of Electric Power Supply


EI-FACT SHEET 2013 - 02 4

Generation capacity in neighboring coun- puts upward pressure on the electricity price levels
tries in day-ahead, as well as intraday or balancing markets.
Market signals such as price spikes, although negatively
When looking to the European Union, ENTSO-E estimates perceived by the end consumers, have an important positive
that the EU as a whole has a surplus generation capacity of 95 impact on the short and long-term system
GW under normal winter conditions (28 GW under severe reliability. There is one important condition: European market
winter conditions). ENTSO-E uses, in its overall European prices should be reflected in the end consumer prices. This is
approach, a minimum level of availability for wind. Belgium has already the case for large consumers but is also needed for the
a relatively large import capacity during winter, but are our small consumers. Better metering and more responsive pricing
neighboring countries capable of exporting electricity? The are key to guarantee sufficient import in the short run and
Nederlands have a large amount of surplus generation capacity capacity in the long term.
during winter, even when facing severe winter conditions.
When facing shortages in Belgium imports from the Nederlands Peak power plants are not economically viable during most
should be possible. of the time. With rising electricity prices, more generation
capacity is activated in the short-term. Whereas peaking
The situation in France is different.Under normal winter conditions, price levels increase the supply of electrical energy, demand
France has a comfortable surplus margin. But due to the high levels may be lowered. Typically large industrial consumers have
sensitivity of its load to low temperatures (2300 MW/C), the opportunity to adjust or delay electricity demand. Also
caused by the high share of electric heating, France faces smart grid developments are expected to contribute to the
shortages during severe conditions and must rely on imports. responsiveness of consumers to fluctuating electricity prices.

Combined impact on security Electricity price spikes also allow generation companies to
recover their investment costs. This ensures that, in the long-
Figure 3 combines all elements that are in play concerning security term, new investments in generation capacity are
of electric energy supply for the period 2012-2013. As previously attracted. Put differently, a cap on the electricity price, limiting
referred to, the available generation capacity must be reduced those price spikes, would suppress economic signals and
by the total installed power capacity based on renewable energy. prevent utilities from investing in additional generation
Combined with the temporary loss of Doel 3 and Tihange 2 capacity. Capacity markets are often suggested to remunerate
(2014 MW) Belgium lacks generation capacity to meet the available power generation capacity and stimulate new build,
highest demand level of 2012, 14191 MW. but caution is needed not to start yet another subsidy
scheme to balance intermittent generation with zero marginal
Meeting these high demand levels Belgium depends on imports cost that was exogenously put into the market by strong
from neighboring countries. In the near future the dependency support schemes. More reflection is needed for good
tends to grow, even with the full generation capacity of Doel 3 operating reserve markets. A factsheet with special focus on
and Tihange 2 back online. the links between capacity remuneration of some kind and
reserve markets is forthcoming.
Impact on the electricity market

Having enough generation capacity in Belgium or in neighboring


countries (taking into account interconnection capacity) is a
conditio sine qua non to securily operate the electrical energy
system. However, market forces in the electricity sector will
also contribute to balance generation and demand levels in
real-time.

Limited available generation capacity, endangering secure


operation of the electricity system, will be refected in the
electricityprice on different markets. This scarcity

KU LEUVEN ENERGY INSTITUTE


Celestijnenlaan 300 box 2421
B3001 Heverlee
www.kuleuven.be/ei

KU Leuven Energy Institute EI Fact sheet Security of Electric Power Supply

Das könnte Ihnen auch gefallen