Beruflich Dokumente
Kultur Dokumente
Laura N. Lowes
Dawn E. Lehman
Anna C. Birely
University of Washington
Daniel A. Kuchma
Christopher R. Hart
Kenneth P. Marley
University of Illinois, Urbana-Champaign
NEESR Complex Walls: Planar Wall Test Program
Table of Contents
CHAPTER 1: Introduction .......................................................................................................................... 5
CHAPTER 2: Test Specimens ..................................................................................................................... 6
2.1 Dimensions.......................................................................................................................................... 6
2.2 Shear Demand/Lateral Load Distribution ........................................................................................... 6
2.3 Reinforcement Design......................................................................................................................... 7
2.3.1 Shear Design................................................................................................................................. 8
2.3.2 Flexural Design ............................................................................................................................. 9
2.3.3 Detail Design .............................................................................................................................. 13
2.4 Splice Design ..................................................................................................................................... 15
2.5 Test Matrix ........................................................................................................................................ 16
2.6 Foundation/Wall Cap Design ............................................................................................................ 16
2.6.1 Foundation Block ....................................................................................................................... 17
2.6.2 Wall Cap ..................................................................................................................................... 17
2.7 Specimen Construction ..................................................................................................................... 18
2.7.1 Foundation Construction ........................................................................................................... 18
2.7.2 Wall Construction ...................................................................................................................... 18
2.7.3 Cap Construction........................................................................................................................ 19
2.7.4 Concrete Casting ........................................................................................................................ 20
CHAPTER 3: Material Properties ............................................................................................................. 21
3.1 Concrete Material Properties ........................................................................................................... 21
3.2 Reinforcing Steel Properties ............................................................................................................. 25
3.2.1 Development of #2 Bars............................................................................................................. 26
CHAPTER 4: Test Setup ........................................................................................................................... 29
4.1 Description of Test Setup .................................................................................................................. 29
4.2 Placement of Wall ............................................................................................................................. 30
4.3 Description of Connection Details .................................................................................................... 31
4.3.1 Connection to Strong Floor ........................................................................................................ 31
4.3.2 Loading Beam Connection ......................................................................................................... 31
4.3.3 Cap Connection .......................................................................................................................... 32
4.3.4 Side Mounted Actuators Connection......................................................................................... 33
CHAPTER 5: Loading and Displacement History ..................................................................................... 34
2
NEESR Complex Walls: Planar Wall Test Program
3
NEESR Complex Walls: Planar Wall Test Program
4
NEESR Complex Walls: Planar Wall Test Program
CHAPTER 1: Introduction
This document provides detailed documentation of the design, testing, and preliminary results of the
planar wall test program of the project "Behavior, Analysis, and Design of Complex Wall Systems", a
joint effort between the University of Washington (PI Laura Lowes and co-PI Dawn Lehman) and the
University of Illinois Urbana-Champaign (co-PI Dan Kuchma). Funded by NEES (George E. Brown, Jr.
Network for Earthquake Engineering Simulation) and the Charles Pankow Foundation, the project seeks
to establish the seismic performance of modern mid-rise reinforced concrete structural walls and to
develop the tools and technologies to advance performance based design of these systems.
In the experimental component of the project, large-scale wall sub-assemblages were tested to improve
the understanding of seismic behavior of walls in modern buildings. Walls were tested at the NEES
MUST-SIM (Multi-Axial Full-Scale Sub-Structured Testing and Simulation) Facility at the University of
Illinois. Use of this facility allowed collection of high resolution data to assist in characterizing the
performance of walls. Equipment at the facility allowed for testing of the sub-assemblages with force
and displacement control in six-degrees of freedom. This allowed for the testing of large-scale (1/3 scale
of prototype walls) in that axial load, lateral load, and overturning moment could be applied to the top
of the specimens in a manner such that the base reactions were equivalent to that of a much taller wall
with a specified lateral load distribution. The actual specimens represented the bottom three stories of a
ten story prototype wall. The full experimental test program consisted of 8 specimens: 4 planar (or
rectangular) walls, 1 coupled wall, and 3 C-shaped (or U-shaped) walls. This document is limited to the
planar wall test program; similar documents are available for the coupled and C-shaped wall test
programs.
The contents of the document are as follows. Chapter 2 provides an overview of the test specimens,
including test variables considered, design of the specimens, construction drawings and details on
construction of the specimens. Chapter 3 provides material properties data and expected material
strengths. Chapter 4 discusses the experimental test set-up, application of loads, and displacement
histories. Chapter 5 discusses the data collected including traditional and non-contact instrumentation,
high-resolution images, and crack width measurements. Chapter 6 presents the loading and
displacement histories applied to the wall specimens. Chapter 7 presents basic experimental results for
the tests. Chapter 8 discusses data processing and the availability of the data in the NEES Project
Warehouse. The contents of this document are limited to the observed behavior of the tests; results of
analysis of the experimental data can be found in the dissertations of Birely (2012), Hart (2011), and
Marley (2011).
5
NEESR Complex Walls: Planar Wall Test Program
2.1 Dimensions
A prototype wall was developed based on a review of west coast building; details of the building review
are provided in Birely (2012). The prototype wall was 120 feet (36.58 m) tall (10 12-foot (3.66 m) tall
stories), 18 inches (45.72 cm) thick, and 30 feet (9.14) long. The specimens tested in the laboratory were
one-third scale of the prototype wall. Use of the UIUC MUST-SIM facility (see Section 5.1) allowed
application of loads to the specimens in a manner that allowed only the bottom three stories of the one-
third scale walls to be tested, yet create base reactions equal to that of a ten-story specimen. The test
specimens were 12 feet (3.66 m) tall (3 stories at 4 feet (1.22 m) tall), 6 inches (15.24 cm) thick, and 10
feet (3.05 m) long.
The first lateral load distribution considered was the ASCE 7-05 (2005) equivalent lateral force
distribution. This load distribution, shown in Figure 2-1 is essentially an inverted triangular load
distribution and acts at an effective height of 0.71h10, where h10 is the height of the 10-story scaled
prototype wall. At the design nominal strength (see Section 2.3.1), the shear demand on the specimen is
2.75Agf'c, or 0.67Vn, where Vn is the design nominal shear strength of 210 kips (934 kN).
6
NEESR Complex Walls: Planar Wall Test Program
The second lateral load distribution considered was a uniform distribution of lateral forces. This load
distribution, shown in Figure 2-2, acts at an effective height of 0.50h10. At the design nominal strength
(see Section 2.3.1), the shear demand on the specimen is 3.90Agf'c, or 0.95Vn.
Figure 2-3: Target cross-section of specimens with boundary element reinforcement layout.
7
NEESR Complex Walls: Planar Wall Test Program
Given these initial assumptions, the following process was used to complete the design of the
specimens:
The following sections discuss the design of the wall for shear and flexure, as well as detailing of wall
confinement, lap splice and anchorage lengths.
Vn = Acv ( c f 'c + t f y )
where, Vn is the nominal strength of the wall, Acv is the gross area of concrete section bounded by web
thickness and length of section in the direction of shear force (720 in2), c is the coefficient defining the
relative contribution of concrete strength to wall strength (2.0), f ' c is the specified compressive
strength of concrete (5000 psi), t is the ratio of area distributed transverse reinforcement to gross
concrete area perpendicular to that reinforcement (0.0025), and f y is the specified yield strength of
reinforcement (60,000 psi). This yielded a result for nominal shear resistance of:
Vn = 209.8 kips or 4.12 Acv f ' c (from code specified minimum reinforcement)
The shear demand on the structure was back calculated from this value, assuming that:
Vu = Vn
where Vu is the shear demand and is the strength reduction factor (0.60). This yielded a result for
shear demand of:
8
NEESR Complex Walls: Planar Wall Test Program
In computing flexural strength, a moment-curvature analysis method was used. For design purposes, the
steel was modeled as elastic perfectly plastic and the concrete followed a parabolic curve up to its
specified compressive strength. The following sections detail the steps used in determining the final
design of the flexural reinforcement.
M u = eff h10Vu
where eff is the effective height of wall (0.71 from ASCE 7 lateral load distribution), h10 is height of
the ten-story wall (480 inches), and Vu is the shear demand (125.9 kips). This yielded a result for
moment demand of:
Mu = 42,900 in-kips
M u M n (4)
where is the strength reduction factor (0.9). This yielded a result for moment capacity of:
Mn 47,700 in-kips
9
NEESR Complex Walls: Planar Wall Test Program
compressive stress and subsequently exhibits a linear decrease in strength down to 20% of the
maximum compressive stress. The nominal moment was the moment at the point where the extreme
compressive fiber reached a strain of 0.3%. The resulting value of M n was 49,000 in-kips, which
corresponds to an over-strength of 2.7% above the code requirements.
lw
c
600( u / h10 )
where c is the distance from the extreme compression fiber to neutral axis, calculated for the factored
axial force and nominal moment strength, consistent with the design displacement u , resulting in the
largest neutral axis depth (24.5 inches), l w is the length of the wall (120 inches), and u is the design
displacement ( u / hw = 0.02; conservative assumption). Since 24.5 10 , the statement is true and
boundary elements are required.
Second, it must be determined if the length of the boundary elements are long enough.
c 0.1l w
lbe
c / 2
where l be is the length of the boundary element (19.5 inches). The length of the boundary element is
greater than both 12.5 in and 12.25 in from equation 6. Therefore, the specified boundary element
length is sufficient.
Third, the amount of transverse steel must be checked. ACI 318-05 Section 21.7.6.4 refers to sections
21.4.4.1 through 21.4.4.3 (moment frame members). ACI 318-05 equation (21-3) need not be satisfied.
Since #2 bar is the smallest size that is to be used, the maximum spacing requirements control the
design. The following calculations demonstrate this.
The vertical spacing must satisfy the following requirements at one-third scale:
One quarter of minimum dimension = 0.25 * 19.5 in = 4.9 in
Six times longitudinal bar diameter = 6 * 0.5 in = 3 in
s (7)
14 hx
4 + 14 3in
= 4+ = 7.7 in
3 3
2 in
10
NEESR Complex Walls: Planar Wall Test Program
where hx is the maximum horizontal spacing of hoop or crosstie legs on all faces of the column. Thus,
the vertical spacing, s , is 2 in. The spacing of ties and overlapping hoops shall not exceed 4.67 inches (at
one-third scale) in the direction perpendicular to the longitudinal axis of the structural member.
Therefore, in the plane that cuts along the width of the wall, (3) #2 @ 2 are required. However,
providing (2) legs will be considered sufficient, because it is within of the spacing requirement. In the
plan that cuts along the length of the wall, (7) #2 @ 2 are to be provided.
The area of steel provided in each direction must satisfy the following equation:
where Ash is the total cross-sectional area of transverse reinforcement (including crossties) within
spacing s and perpendicular to dimension bc , s is the spacing of transverse reinforcement measured
along the longitudinal axis of the structural member, bc is the cross sectional dimension of boundary
element core measured center-to-center of confining reinforcement, and f yt is the yield strength of
transverse reinforcement. In the plane that cuts along the width of the wall, the values are:
Lastly, the region of the wall where special boundary elements are required must be determined.
Section 21.7.6.3 states that they must extend the larger of l w or M u / 4Vu above the critical section (the
base). For the wall and design load case,
eff h
M u / 4Vu = = 85 in (9)
4
11
NEESR Complex Walls: Planar Wall Test Program
and l w is 120 in. Therefore, the ties must extend 120 in above the base. Also, for a mat or footing
foundation, ACI 318 Section 21.7.6.4 states that the ties must extend 4 in (at one-third scale) into the
support.
Figure 2-4: Design drawings for boundary element distribution of longitudinal reinforcement.
12
NEESR Complex Walls: Planar Wall Test Program
They are designed according to the full-scale representation. A #4 bar corresponds to a #12 bar at full
scale, which is fictitious. While #14 and #18 bars are prohibited from being lap spliced by the code, it is
assumed that the lap splice provisions for #11 bars may be applied to the #4 bars in the scaled
specimens.
Chapter 21 specifies that lap splices and embedment lengths are to be designed according to Chapter
12, including a factor of 1.25 for development length at places where yielding is expected to occur due
to seismic loading. The procedure in 12.2.3 was used, which specifies that the development length is:
13
NEESR Complex Walls: Planar Wall Test Program
3 1.25 f y t e s
ld = d b
40 f ' c cb + k tr
d b
and,
Atr f yt
k tr =
1500sn
where t is the reinforcement location factor (1.0), e is the coating factor (1.0), s is the
reinforcement size factor (0.8 for #2 bars; 1.0 for #4 bars), is the lightweight aggregate concrete
factor (1.0), cb is the spacing or cover dimension (0.875 in for #2 bars; 1.0 for #4 bars), d b is the
diameter of the bar (0.25 in for #2 bars; 0.5 in for #4 bars), n is the number of bars being spliced, and
k tr is the transverse reinforcement index (0.0 for #2 bars and unconfined #4 bars). A 1.25 f y factor is
used to account for over-strength in the steel. This yielded a result for #2 bars of:
ld = 6.4 in = 25.6 d b
k tr = 0.109
ld = 17.9 in = 35.8 d b
ld = 19.9 in = 39.8 d b
Therefore, the embedment length to be provided was 7 in for #2 bars and 20 in for #4 bars. This also
indicates that embedment of the horizontal #2 bars in to the confined region of the boundary element
will provide sufficient anchorage, because the length of the confined region is greater than the required
embedment length. Therefore, hairpins are not required.
Lap splices were to be incorporated in the test specimens at the first and perhaps third stories. Their
design was governed by section 12.14.2.1. Since all of the bars were spliced at the same level, a factor of
1.3 was applied to the development length for the bars. Therefore, the lap splice length was 9 in for the
#2 bars and 24 in for the #4 bars. Table 2-1 summarizes the embedment and lap splice lengths for the
bars.
14
NEESR Complex Walls: Planar Wall Test Program
#2 7 in = 28 db 9 in = 36 db
#4 20 in = 40 db 24 in = 48 db
15
NEESR Complex Walls: Planar Wall Test Program
Table 2-2 provides a summary of the test program and the parameters varied for each specimen. The
first wall tested, PW1, was constructed with the boundary element steel layout and a splice at the base
of the wall. An ASCE 7 load distribution, 0.71H10 was applied. The construction of PW2 was identical, but
had loading representative of a uniform load distribution, or 0.5H10. PW2 served as the reference wall
for the test program, as it shared at but one design parameter in common with each wall. PW3 was
loaded with a uniform load distribution, was spliced at the base, but was constructed with a uniform
distribution of steel. The final test, PW4, had boundary element distribution of steel, was loaded with a
uniform load distribution, but was not spliced at the base (longitudinal reinforcement was continuous
from the foundation block to the wall cap). An axial load of 0.1Agf'c was specified all walls.
16
NEESR Complex Walls: Planar Wall Test Program
units, respectively. Additionally, these served as means to provide adequate anchorage and
development of the longitudinal steel in the wall specimens.
PVC tubes were provided to provide ducts for post-tensioning rods used to secure the specimen to the
strong floor. Two rows of 5 PVC pipes were provided at 36 inches (91.44 cm) to align with the holes in
the strong floor. The PVC tubes were 3 inch (7.62 cm) diameter and were supported by #3 spirals (10
inch (25.4) diameter with 4 inch (10.16) pitch).
The wall specimen was located off center from the center of foundation block to allow the specimen to
be centered beneath the loading units. Figure 2-8 shows a photograph of the foundation block for one
of the spliced wall specimens. AutoCAD files with the detailed design of the foundation blocks can be
found on the NEES Project Warehouse (see Section 8.5 for details).
The cap was detailed similar to the foundation. There were two mats of reinforcing steel with vertical
stirrups. Smaller PVC tubes were used as anchoring ducts, approximately 2 inch (5.08 cm) diameter. The
17
NEESR Complex Walls: Planar Wall Test Program
cap was symmetric and centered about the wall. AutoCAD files with the detailed design of the wall caps
can be found on the NEES Project Warehouse (see Section 8.5 for details).
The foundation block was cast using a self-consolidating concrete mix (SCC); the design mix and material
properties of this concrete are provided in Section 3.1. Two trucks of concrete were needed to cast
each foundation block. The concrete was directly cast into the formwork from a shoot, with an inverted
cone diameter ranging from 16-22 inches (40.64-55.88 cm). After initial set of the concrete, the surface
was scoured with 0.5 inch (12.7 mm) groves at 2 inch (5.08 cm) spacing; this provided a mechanical
shear key to aid in shear transfer at the wall-foundation interface.
The confinement hoops and horizontal reinforcement were erected from the bottom to the top in
layers. The confinement hoops were placed over the top of the longitudinal steel and then tied into
position. Hoops were tied to the longitudinal reinforcement with at least four ties; two in the front and
two in the back. Hooks were tied in two places and horizontal shear reinforcement was typically tied to
every other longitudinal bar between the boundary elements. Wood blocks were used to space the
different layers of reinforcement. At the second and third floor levels, a system of steel pipes was tied
into the cage to allow for the application of floor loads via steel dowels (see Section 4.3.4). After the wall
reinforcement was completed, strain gauge wires were bundled together and routed through the top of
the wall.
18
NEESR Complex Walls: Planar Wall Test Program
Figure 2-11: Formwork and rebar cage for wall cap. Figure 2-12: Casting a typical wall cap.
19
NEESR Complex Walls: Planar Wall Test Program
The concrete was brought into the lab in standard concrete trucks and placed with a large 1/3-cubic
yard hopper. Typically, the foundation block was cast directly out of the shoot, but the wall and cap
were constructed by craning up the hopper. The concrete for the wall was cast with flexible tremmy
tubes. The tremmy tubes were placed in two locations within the web near the boundary elements,
which can be seen in Figure 2-13. The tremmy tubes were 6 inches (15.24 cm) in diameter and were
attached to a concrete hopper affixed to the top of the wall. Concrete was placed into a 1/3-yard
hopper that was craned up and emptied into the hoppers attached to each tremmy tubes.
When form work was removed from Specimen PW4, some minor damage to the concrete at the bottom
east corner of the wall occurred. Damage occurred only to the cover concrete and no reinforcement was
exposed. This concrete was patched using aesthetic mortar (details are available on the Project
Warehouse for Specimen PW4).
20
NEESR Complex Walls: Planar Wall Test Program
Cement 450 lb
A local ready-mix concrete supplier helped batch and test the concrete mix. After adjusting mix
properties to hone in on the target design strength, the flowability of the mix was investigated. Mock
rebar cages, shown in Figure 3-1, of the most congested area of steel were built to assess the flowability
of the mix. Three separate concrete trucks with two cubic yards of concrete were shipped to the lab
and, for each batch, superplastizer was until a target inverted cone ring diameter of 20, 24, or 28 inches
(50.8, 60.96, or 71.12 cm) was reached. Figure 3-2 shows the inverted cone test for a batch test. It was
determined that a large ring diameter around 28 inches (71.12 cm) was needed for the concrete to
naturally flow through the tight rebar cage without the help of hydrostatic pressure or manual vibration.
A ring diameter larger than 28 inches (71.12 cm) was susceptible to segregation. This was noted by slight
ponding within the middle of the inverted cone test.
21
NEESR Complex Walls: Planar Wall Test Program
For the foundation and wall cap concrete batches, 4 inch (10.16 cm) by 8 inch (20.32 cm), or 4x8,
cylinders were cast. For the wall concrete batches, both 4x8 and 6 inch (15.24 cm) by 12 (30.48) inch, or
6x12, cylinders, were cast. Additionally, modulus of rupture (MOR) beams were cast with every wall
pour. Cylinders were cast in the same environment as the specimen with wet burlap and covered with a
plastic tarp. All compressive cylinder tests were conducted in a Forney testing machine according to
ASTM specification C39. For PW-1, 4x8 cylinders were tested on days 1, 7, 14, 21, 28, and test day. A
strength development curve can be seen in Figure 3-3.
6000
5000
Compressive Strength (psi)
4000
3000
2000
1000
0
0 5 10 15 20 25 30
Time (Days)
22
NEESR Complex Walls: Planar Wall Test Program
On test day, 6x12 inch cylinders were tested to obtain a concrete strength at the time of testing. These
were the only material tests performed on the day of testing. However, more detailed material tests
were conducted after the tests to measure the stress-strain response and the tensile strength of the
concrete. To determine the stress-strain response of the concrete two surface strain gauges were
attached to three 4x8 cylinders for each wall and tested in compression. Figure 3-4 through Figure 3-7
show the stress-strain response of the cylinders tested for each specimen. Table 3-2 provides material
properties, where f'c is the compressive strength on the day of testing, c0 is the strain at peak
compressive strength, Ec is the modulus of elasticity (57,000f'c), and ft is the tensile strength of the
concrete as determined from the MOR tests.
Specimen f'c, psi (MPa) c0, in/in*10-3 Ec, ksi (MPa) ft, psi (MPa)
PW1 5231 2.27 4123 1030
PW2 5843 2.51 4357 1065
PW3 4980 2.85 4022 1016
PW4 4272 2.07 3726 878
4
Stress (ksi)
0
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5
Strain (milli-strain)
Figure 3-4: Concrete cylinder (4x8) stress-strain response of Specimen PW1 (Tested 6-12-2008).
23
NEESR Complex Walls: Planar Wall Test Program
4
Stress (ksi)
0
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5
Strain (milli-strain)
Figure 3-5: Concrete cylinder (4x8) stress-strain response of Specimen PW2 (Tested 6-12-2008).
4
Stress (ksi)
0
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5
Strain (milli-strain)
Figure 3-6: Concrete cylinder (4x8) stress-strain response of Specimen PW3 (tested 6-12-2008).
24
NEESR Complex Walls: Planar Wall Test Program
4
Stress (ksi)
0
0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5
Strain (milli-strain)
Figure 3-7: Concrete cylinder (4x8) stress-strain response of Specimen PW4 (tested 7-18-2008).
Standard tension tests were performed on each batch of steel to determine the as built properties of
the steel. Tension tests were conducted in a MTS uniaxial testing frame with hydraulic grips. A
calibrated extensometers with a 4 inch or 8 inch gauge length were clamped onto the side of each
specimen to measure strain in the bars; a 4 inch (10.16 cm) gauge length was used to measure strain up
to the yield point and an 8 inch (20.32 cm) gauge length was used to measure strain up to failure. Only
if the specimen ruptured within the gauge length was the measurement considered valid.
For each batch of steel 2-6 bars were tested. For each value, the values corresponding to yield, strain
hardening, maximum stress, and ultimate strain were determined. The average values for each batch
are provided in Table 3-3. Figure 3-8 shows the experimental stress-strain. An elastic modulus of Es =
29,000 ksi (200 MPa) was assumed for all bars. The yield strength was determined by drawing a line with
slope Es offset at 0.2% strain. The stress at which this line crosses the test data is the yield stress, fy. The
corresponding yield strain is y = fy/Es. To capture the yield plateau behavior, the strain at which strain
hardening (sh) was reported. A stress, fsh, was associated with this point that is larger than the yield
stress; this creates a slight slope in the yield plateau, which eliminates issues associated with a zero
slope when performing sectional analysis of the specimens. The maximum stress (fmax) and the
25
NEESR Complex Walls: Planar Wall Test Program
corresponding strain (max) were also recorded. The ultimate strain, u, was reported as that at a stress of
0.9fmax.
Specimen(s) Bar size fy, ksi y, in/in fsh, ksi sh, in/in fmax, ksi m, in/in fu, ksi u, in/in
PW1 & PW2 #4 84.0 0.0029 84.9 0.015 100.8 0.086 91.2 0.12
PW3 #4 51.3 0.0018 52.0 0.0115 77.9 0.140 70.2 0.20
PW4 #4 67.1 0.0023 68.1 0.0075 109.5 0.094 99.0 0.13
All #2 75.7 0.0026 77.0 0.015 84.6 0.050 76.3 0.058
(a) #2 bars (All specimens) (b) #4 bars (Specimens PW1 and PW2)
26
NEESR Complex Walls: Planar Wall Test Program
The research group decided that it would be beneficial to add deformations to standard smooth bar
stock and heat treat the steel to give it a hot-rolled response. The steel was purchased in a large round
spool that was fed through a special machine that stamped on external deformations in a helical
pattern. The deformation pattern that was stamped on the bar was comparable to conventional
reinforcing steel such that it had a similar relative rib area defined as:
Then the bars were cut to 15 foot straight lengths, bundled and shipped to a special heat treating
facility. The 15 foot lengths were the maximum length that the oven at the heat treatment place could
accommodate. The cold-rolled stress-strain response of these bars is shown in Figure 3-9.
Figure 3-9: Cold-rolled stress-strain response of #2 reinforcing bars prior to heat treatment.
To augment the response of this steel, a series of heat treatments were applied to small samples about
12 inches long, varying both heating temperature and duration. After achieving acceptable results by
heating a sample to 1125 degrees for one hour, a test run on a 2,500-pound portion of the total lot was
performed by Exotic Metal Treatment, Inc., of Indianapolis, Indiana. Thermocouples were attached at
six locations within the lot, and temperatures were recorded as the forced air heating chamber was
activated. The lot remained in the chamber until all thermocouples indicated that temperatures were
within 25 degrees of the target 1125 degrees for one hour, after which time the lot was allowed to air
cool. This lot of steel inside the heating chamber and the attached thermocouples are shown in Figure
3-10.
27
NEESR Complex Walls: Planar Wall Test Program
Twelve-inch samples from varying locations were cut and tested for their stress-strain behavior, with
results shown in Figure 3-11. While some of the samples exhibited acceptable behavior, the level of
variation between all the samples was unacceptable. Steel samples taken from the ends of the bars in
particular showed a much lower strength than the interior portions due to the fact that the ends were
exposed to elevated temperatures the longest. While the interior reached 1125 degrees for one hour,
the end regions experienced this temperature for up to 2.5 hours.
To correct for this imbalance, a new two-stage heating regimen was developed by the heat treaters.
First, the entire lot of steel would be brought uniformly to a temperature beneath the stabilization
temperature, 1000 degrees in this case. Once achieved, the chamber would resume heating until the
thermocouple requirements were satisfied for a 1100 degrees target for one hour. After applying this
scheme to another 2,500-pound lot, samples were cut and tested, and the results are presented in
Figure 3-12. As shown, the behavior of the #2 reinforcement was now more uniform throughout the
entire heat treatment batch. After the second heat treatment regimen was performed on the remaining
5,000-pound lot of steel, all three loads were shipped to the Illinois for use in constructing the test
specimens. No reinforcement from the first load was used in construction.
Figure 3-11: #2 rebar behavior from first large heat Figure 3-12: #2 rebar behavior from final heat
treatment batch. treatment batch.
28
NEESR Complex Walls: Planar Wall Test Program
Figure 4-1: Plan view of typical experimental set-up of specimens at the NEES MUST-SIM Facility.
Loads were primarily applied to the specimens using Load and Boundary Condition Boxes (LBCBs) that
allow application of forces in six-degrees of freedom. The LBCBs are described in detail in Section 5.2.
The wall specimens were strong enough in their in-plane direction that two LBCBs were needed to test
the walls to failure. Each LBCB was mounted to the strong wall with 36 high strength 1.5 inch diameter
threaded rods. The threaded rods were post-tensioned with a double acting center hole jack to 100 kips
for a total tie down force of 3600 kips. This tie down force guaranteed that the boxes would not slip
during loading. To further prevent the boxes from moving upward under extreme downward force,
29
NEESR Complex Walls: Planar Wall Test Program
simple shear keys were installed at the top of the LBCBs. External sensors were used to measure slip,
and no significant movements were observed.
In addition to the loads applied by the LBCBs, two side mounted actuators were used to impose lateral
force at the second and third stories for PW2, PW3, and PW4. Two 100 kip double acting servo
controlled hydraulic actuators were used to impose these forces. These two actuators were controlled
with separate Instron controllers in force control utilizing a proportional, integral and derivative or PID
control loop. PW1 did not utilize side mounted actuators.
Instrumentation reference columns were placed around the specimen to mount instruments and high-
resolution cameras. Two camera reference columns were placed in front of the wall specimen to mount
six cameras. These two camera columns can be seen in Figure 4-1. Also a reference column was placed
on the west side of the specimen to affix instruments to measure absolute displacements. A reference
stand was needed to mount the Krypton system to maximize the field-of-view of the system. This
system is discussed in detail in Section 6.2.1.
Because the LBCBs were attached to the strong wall prior to placement of the wall specimen, the
specimens could not be fully moved into place using the lifting rig. Once the specimens were moved as
close to the final resting place as possible, the final movement was accomplished by pushing on the
specimens using standard double acting jacks that reacted against shear keys in the strong floor.
Figure 4-2: Moving test specimen into the testing location underneath the LBCBs.
30
NEESR Complex Walls: Planar Wall Test Program
This intermediate connection element is referred to as the loading beam, or connection beam. In
addition to accommodating the appropriate connection tolerances, it rigidly connected the two LBCBs
together. The beam was designed to remain elastic and evenly distribute the load from each LBCB such
that any fighting between the boxes would be absorbed by the loading beam. The connection beam
was a heavy duty W14x132 steel section. Two additional 62 inch (157.48 cm) by 26 inch (66.04 cm) by 2
inch (5.08 cm) thick spreader plates were attached flush against the wide flange beam with 1 inch (2.54
cm) bolts running through a counterbored hole. One inch (2.54 cm) thick web stiffeners were placed at
12 inches (30.48 cm) on center to resist buckling. The beam was directly connected to the LBCBs with 1
inch (2.54 cm) high strength socket head cap screws placed at 6 inches (15.24 cm) on center on either
side of the beam. A total of 40 bolts were used to make this connection (2 rows of 10 for each LBCB).
Figure 4-3 through Figure 4-5 show the connection of the LBCBs to the connection beam and the
connection of the connection beam to the specimen cap (see Section 4.3.3). AutoCAD files with
complete details of the connection are available in the NEES Project Warehouse (see Section 8.4).
31
NEESR Complex Walls: Planar Wall Test Program
32
NEESR Complex Walls: Planar Wall Test Program
thick layer of wet low shrinkage hydrocal or grout on its surface created a smooth bearing surface
transition from the loading plate to the concrete cap. Once the grout or hydrocal cured, high strength
1.5 inch (38.1 mm) diameter post tension rods were torque onto the cap. Thick 1 inch (25.4 mm)
washers were used to transfer the load across the 2 inch (50.8 mm) diameter PVC ducts.
During the connection process, concrete surface strain gauges were used to monitor the response of the
wall. For all specimens there was no significant external load introduced into the specimen during the
connection.
The side-mounted actuators were connected to the flanges of W14x132 beams that were post-
tensioned to the reaction wall. The other end of the actuators were connection to HSS 16x8x3/8
spreader beams, which in turn were connected to two HSS 4x4x1/2 extension arms. The extension arms
were connected to the specimen by ten 1.5 inch (38.1 mm) diameter high strength threaded. A six inch
(15.24 cm) space between the wall surface and the rigid loading arms was used to allow the threaded
rods to deform such that there was an even distribution of force across all ten threaded rods. Figure 4-6
shows a detail of the side-mounted actuator connection.
33
NEESR Complex Walls: Planar Wall Test Program
In the large-scale lab, the LBCBs can be oriented as needed on either the reaction floor or reaction wall.
The reaction wall is a five foot thick, 28-foot tall L-shaped post-tensioned concrete wall, with legs
measuring 50 and 30 feet long. The large-scale facility with the strong wall and three LBCBs is shown in
Figure 5-1, with a closer view of an LBCB shown in Figure 5-2. Examples of structural components tested
in the MUST-SIM facility include concrete bridge piers, steel frames, steel beam-column assemblies, and
the concrete structural walls discussed herein.
Figure 5-1: Illinois MUST-SIM facility. Figure 5-2: LBCB resting on lab floor.
The small-scale facility that has a 1/5 scale reaction structure with three 1/5 scale LBCBs. The small-
scale facility provides researchers the opportunity to conduct pre-test verifications with various load and
displacement scenarios. The small-scale laboratory is essential to the operation of the large-scale facility
in that it allows users to understand the capabilities and limitations of the laboratory and the control
systems prior to conducting experiments using the large-scale facility.
The MUST-SIM facility is capable of conducting hybrid simulation tests, whereby displacement demands
are computed by analytical tools and are updated with feedback from experimental data. Hybrid
34
NEESR Complex Walls: Planar Wall Test Program
simulation coupled with six degree-of-freedom loading units allows the facility to conduct versatile
component testing where the structural component of interest is tested experimentally and the
remainder of the structure is modeled analytically.
The overall dimensions of the reaction box are approximately 11.8 feet (3.60 m) long, 6 feet (1.83 m)
wide and 6 feet (1.83 m) high. The loading platform is approximately 7.2 feet (2.19 m) long and 6.2 (1.89
m) feet wide. Each individual actuator has a capacity of 225 kips in tension and 311 kips in compression.
While every actuator moves and contributes to each single degree-of-freedom, the majority of each
force and displacement limit is controlled by the actuators in the principal direction. The three vertical
actuators (Z1, Z2, and Z3) are primarily used to control the z, x (roll) and y (pitch) position of the
loading platform. Each of these actuators is anchored to the base of the reaction box and attached to
the underside of the loading platform. Two horizontal actuators (X1 and X2) that are attached to the end
of the reaction box are used to primarily control the x and z (yaw) position of the loading platform. One
additional horizontal actuator (Y1) is used to control the y-direction position of the loading platform.
35
NEESR Complex Walls: Planar Wall Test Program
The capacity and displacement limits of the six degrees-of-freedom can be seen in Table 5-1. Pillow
Block Spherical Bearings have been selected so that the motion of the loading platform is not unduly
restricted in any of the six degrees of motion.
36
NEESR Complex Walls: Planar Wall Test Program
5.3.1 SimCor
SimCor (Simulation Coordinator) is the main program that coordinates the entire experiment. The
program was developed at the University of Illinois using Matlab. The user inputs a desired loading
protocol into SimCor and it divides it up into loading steps, sometimes referred to as SimCor steps. The
main function of this program is to communicate with all the other computers and software packages by
sending triggers and messages at the start and/or completion of each loading step. For example, at the
completion of a loading step SimCor sends a message to the data acquisition software to take a series of
measurements to record step data. A screen shot of this software package can be seen in Figure 5-5.
37
NEESR Complex Walls: Planar Wall Test Program
38
NEESR Complex Walls: Planar Wall Test Program
The Operation Manager is a LabView based program developed at the University of Illinois. It is
continuously receiving displacement, rotation, and force targets from the LBCB Plugin and directly
communicates with the Shore Western software, hardware and servo valves to physically move the
actuators. The LBCB Plugin is used to send substep commands to the Operations Manager, then the
Operation Manager executes the commands and sends back the measured displacement and force
readings from the system which the LBCB Plugin then checks against user defined tolerances before
proceeding to the next substep. Figure 5-7 shows a screen shot of the Operation Manager.
39
NEESR Complex Walls: Planar Wall Test Program
displacement command it receives. This type of force control is referred to as a discrete iterative
control loop, rather than traditional proportional integral, and derivative (PID) force control algorithms.
40
NEESR Complex Walls: Planar Wall Test Program
Table 5-2 summarizes the intended loads applied to the wall specimens. Section 5.4.1 discusses the
applied axial load. Section 5.4.2 discusses the applied lateral load and overturning moment. The loading
protocol was reverse cyclic with increasing displacement levels; details on the displacement history are
provided in Section 5.4.3.
Figure 5-9: Elevation view of wall specimen with loading units. The control point for the LBCBs is shown
at the base the wall cap. The two side-mounted (or ancillary) actuators were not used for Specimen
PW1. Units are shown in cm.
The design axial load for the walls was 360 kips (1601 kN), or N = 0.10Agf'c. The axial loads were applied
by the LBCBs and held at an approximately constant force throughout the tests. Table 5-2 specifies the
intended and actual axial forces (N or Fz) and axial load ratios (N). The actual values presented are the
mean of all load steps. For Specimen PW2, a calibration error resulted in a higher load than intended;
once noticed, it was decided to keep the load constant rather than to change the intended load.
The ultimate control of the tests was displacement controlled, with the control displacement being that
of the top center of the wall specimen (the control point shown in Figure 5-9). The displacement history
was specified by the control software (see Section 5.3). The software determined the lateral shear force
necessary to achieve the necessary displacement and ensured that the applied moment was a constant
relationship to this force. The relationship between the applied moment and shear at the top of the wall
was determined based on the specimen geometry and the desired relationship between the base
moment and the base shear.
For Specimens PW2, PW3, and PW4, two side-mounted actuators double acting servo controlled
hydraulic actuators (see Section 4.3.4) were used to impose horizontal shear at the first and second
story levels. These forces, V1 and V2, were force-controlled during the test by using an individual Instron
controller; the input voltage was determined from the Operation Manager and was slaved to the
horizontal shear force at the top of the wall (Vtop or Fx). The floor level shear forces were accounted for
in determining the relationship between forces at the top of the wall specimens. To provide an
equivalent uniform lateral load distribution, it was necessary to apply floor shears equal to 1/8Vtop; due
to a calibration error, Specimen PW2 had actual floor shears equal to approximately 1/12Vtop. The side-
mounted actuators were not used for Specimen PW1.
Table 5-2 summarizes the intended and actual loads applied to the specimens. The values for the actual
loads are the mean values from all load steps. The variable eff is the effective height of the base shear
(Vb or Vbase), and is calculated as
Mb
eff =
Vb h10
where Mb and Vb are the base moment and shear, respectively, and h10 is the height of the scaled 10-
story prototype specimen (480 inches or 12.2 m).
42
NEESR Complex Walls: Planar Wall Test Program
The walls were tested by applying a prescribed lateral displacement history for the top of the wall
subassemblage (3rd floor of the scaled prototype). The loads applied to achieve this displacement were
held a constant ratio to achieve the desired relationship between the base reactions. The magnitude of
the displacement for each drift level was determined to meet the following states: i) displacement at
theoretical cracking, ii) twice the theoretical cracked displacement, iii) 50% of the theoretical yield
displacement, iv) 75% of the theoretical yield displacement, v) 125% of the theoretical yield
displacement, and vi) third story drift of 0.5%, 0.75%, 1.0%, 1.5%. The theoretical displacements were
calculated using the design properties of the wall, the boundary element reinforcement layout, and
effective loading height of eff = 0.71 (from ASCE 7-02 load distribution). The yield moment of the wall
was determined from the moment-curvature analysis used in the design process. The drift at this
moment was computed from a VecTor analysis of the wall. Assuming the wall cracked at a stress fcrack =
7.5f'c the cracking moment at the base was calculated as:
f crack I g
base
M crack =
0.5lw
where Vtop and Mtop are the third floor shear and moment, respectively, required to achieve the base
cracking moment. Table 5-3 and Figure 5-10 summarize the prescribed displacement history, including
the number of cycles at each displacement level. The intended displacement history was the same for all
walls, however, the actual displacement history of PW1 is different than that of the other walls. This was
due to an error in conversion from voltage to inches during the first few cycles of the test. Table 5-4 and
Figure 5-11 summarizes the displacement history of PW1.
Prior to beginning the displacement history described above, ten steps were taken that did not apply a
lateral displacement to the wall. These "zero-displacement" steps were used to check the
communications between computers and to apply the axial load to the wall. Displacements were first
applied to the east (referred to as the ER+ loading direction) and then to the west (referred to as the
WL+ loading direction).
43
NEESR Complex Walls: Planar Wall Test Program
Figure 5-10: Applied displacement history for Specimens PW2 (last step = 1305), PW3 (last step = 1287),
and PW4 (last step = 1250).
44
NEESR Complex Walls: Planar Wall Test Program
45
NEESR Complex Walls: Planar Wall Test Program
Reinforcing bars were instrumented with Texas Measurements Inc. (TML) high-elongation strain gauges,
YEFLA-5-5LT. The gauges were 5 mm in length and are shown in Figure 6-1. A typical layout of the strain
gauges on reinforcing bars can be seen in Figure 6-2. Strain gauges were attached to the reinforcing bars
by first mechanically grinding and sandpapering the rebar to a smooth, rounded surface. The small
gauge length was selected in order to minimize the effects of installing the gauge itself. The gauge
location was then cleaned of any debris, and the gauge was affixed with a cyanoacrylate adhesive. The
gauge was next coated with polyurethane for moisture protection and covered with a layer of butyl
rubber for protection from handling damage. The strain gauge wire was finally strain-relieved by
securely zip tying it to the bar.
Figure 6-1: Steel gauge (below) and concrete surface gauge (above).
46
NEESR Complex Walls: Planar Wall Test Program
Large gauge length strain gauges were affixed to the concrete surface to measure strain on the concrete
surface. The gauges were 30 mm in length and are shown in Figure 6-1. These gauges also came from
TML and were PFL-30-11-5LT. A typical layout of the strain gauges affixed to the concrete surface is
shown in Figure 6-3. Concrete surface gauges were attached by first cleaning the surface and applying
an epoxy base layer. After setting, the base was smoothed with sandpaper and cleaned. The concrete
gauge was then affixed with more epoxy onto the base and left to set. No additional protective
measures were taken since concrete gauges were only installed in the final stages of test the test
specimen loading preparations.
47
NEESR Complex Walls: Planar Wall Test Program
Gauges with a 1, 2, or 6 inch gauge stroke were used depending upon predicted damage and gauge
length. Figure 6-5 shows examples of the gauges used. The gauges were from Celesco and were either
the CLP and MLP model. All of these instruments used direct current (DC) voltage. The gauges were
mounted to a threaded post that was anchored into the wall with an embedded threaded rod that was
cast in the concrete. A ball joint at each end of the instrument accommodate minor rotations, and
aluminum tubing was used to limit unwanted out-of-plane buckling of the measurements.
48
NEESR Complex Walls: Planar Wall Test Program
High tension string potentiometers were used to perform elastic deformation calculations due to their
high accuracy over a large stroke length (see Figure 6-6 (right)). String potentiometers were also used to
measure absolute displacement of the West (left) side of the specimens (see Figure 6-6). LVDTs were
used to measure absolute slip and rotation of the foundation block (see Figure 6-6). These instruments
were provided by the TransTek group.
Figure 6-6: Typical instrumentation layout of absolute measurements. The instruments shown on the
left were used to measure absolute displacement in-plane and out-of-plane. The instruments on the
right were used for control of the tests.
49
NEESR Complex Walls: Planar Wall Test Program
Figure 6-7: High-tension (left and top) and regular (right) string pots.
50
NEESR Complex Walls: Planar Wall Test Program
Figure 6-10: Typical layout of LED targets for Krypton measurement system.
51
NEESR Complex Walls: Planar Wall Test Program
The K600s dynamic frame capabilities are used to measure the motion for both LBCBs relative to the
specimens coordinate system. After making these observations, the data can be operated on to
produce a transformation matrix that augments the LBCB motion to align with each other and the
specimen. In a similar manner, the control points (or centers of rotation) of the LBCBs can be observed
and transferred to the appropriate place on the specimens.
K600 data was recorded and stored separate from the traditional instruments. The Krypton system
collected continous data at approximately 1 Hz, depending on the total number of LEDs used. The data
was manually post-processed and averaged over 5 seconds to obtain cleaned step data; this process is
documented in Section 6.5.
52
NEESR Complex Walls: Planar Wall Test Program
The photos taken by the high-resolution cameras were used for digital photogrammetry, in which a
collection of digital photographs taken by calibrated cameras and stitches them all together using a set
of unique targets affixed to a surface. Assembly requires an overlap of targets among the photos. This
can be achieved by either taking lots of pictures with one camera, or taking one picture on each of many
stationary cameras. It is the second method that is used on the wall tests, with the aid of the
commercial package PhotoModeler. The finished product is a single image mapped to a defined
coordinate system that removes camera lens distortions. This composite picture then provides both a
single image of the specimen surface and the coordinates of all photogrammetric targets. In order for
PhotoModeler to assemble the images, all targets must be visible in three different pictures from three
different points of view. The positions of individual targets are calculated by triangulation, similar to the
K600 system. While performing the same basic function of the K600 system, photogrammetric accuracy
is lower. Post-processing can also be labor intensive as many targets need to be identified in situations
of poor resolution or lighting. In the end, it is the assembled pictures themselves that is the best
combination of uniqueness and usefulness to the project. Through the duration of the wall tests, crack
formation tracked on the specimens surfaces with a permanent marker. Photomodeler provides a
finished product that shows the damage progression of the entire specimen, which is useful for
comparison against analytical predictions or for visualizing specimen damage states. Additional
information on the use of photogrammetric data is provided by Hart (2011).
The NEES DAQ software works around this problem by also recording data samples at discrete times. By
linking to the control software over a network connection, the DAQ program is automatically notified
when a load step is completed. When such a signal is received, the DAQ program takes a separate
reading for each instrument and stores them to a step log. In this way, step data is readily available at
the end of testing, while continuous data is also logged in case a significant event occurs between load
steps.
The data acquisition (DAQ) system is made up of National Instruments (NI) hardware primarily utilizing
two SCXI-1001 chassis daisy-chained together. Signal conditioning is provided by a series of modules
and terminals that connect into each chassis. The modules used are the SCXI-1540, SCXI-1520, SCXI-
1521b, and SCXI-1104c which are connected to the following respective terminal blocks SCXI-1513, SCXI-
1314, SCXI-1317, and the BNC-2095. The two chassis are connected directly to a dedicated DAQ
computer via a NI PCI-6289 card. Raw data can occupy about 2 gigabytes of disk space, with digital
photos taking up about 20 gigabytes. All data is recorded locally within the MUST-SIM data repository,
and instrument step data is uploaded to the NEES data repository.
53
NEESR Complex Walls: Planar Wall Test Program
In additional to the robust DAQ software, organizing and setting up a large number of channels is critical
and can be quite difficult and tedious to researchers. Because of this, a script was developed to help
synthesize metadata and channel parameters to eliminate tedious work that can easily lead to a channel
mislabel. The researcher inputs and organizes all of the instrumentation parameters in an Excel
spreadsheet that is used to generate input files for the NI hardware and NEESdaq. This information is
also necessary to run Realtime Data Viewer (RDV), and organize data within project warehouse on
NEEShub and DataTurbine.
Observed damage.
Crack width measurements.
Photograph numbers taken on the roaming camera.
Any problems encountered with instrumentation, the DAQ, or control software.
54
NEESR Complex Walls: Planar Wall Test Program
z grid
x grid
sgw01 f 1a sgw
01 f
1 a
type floor
The first characters are letters that identify the type of instrumentation (see Table 6-1). The first two
letters indicate the instrument type. The third letter of the identification string serves as either further
clarification of the instrument type or as an indicator of orientation.
Following the three letter identification are five characters denoting the location of the instrument. This
is broken down into i) a two character numerical identification, from 00 to 12, of the location of the
instrument along the length of the wall, ii) the floor location, from f0 (foundation) to f3 (third floor), and
iii) the location along the height of the wall within the floor, identified as a letter from A to G.
Although the intent of the instrument layout was to align the vertical and horizontal labeling systems for
each type of instrument with each other, ultimately this did not happen. The naming scheme for the
Krypton/Metris LED targets follows the same format as the other instrumentation, but the naming grid
numbers, spacings and labels are significantly different. X grids range from 01 to 15 and z grids range
from f1a to f2e.
Table 6-1 lists the three letter identification for the types of instruments used, provides a brief
description, and indicates the number of instruments on each wall.
55
NEESR Complex Walls: Planar Wall Test Program
56
NEESR Complex Walls: Planar Wall Test Program
The specimen drift was calculated as the displacement of the control point (measured by a string pot
attached to the bottom center of the wall cap) divided by the height of the wall (hw). The rotation and
lateral slip of the foundation block with respect to the strong floor was found to be negligible and the
affect s of these movements were not removed from the total displacement of the specimens.
The base reactions were calculated from the experimentally applied shear (Vtop or Fx) and moment (Mtop
of My) at the top of the specimen and from the side-mounted actuators at the first (V1) and second (V2)
floor levels. The base moment calculation included consideration for the P- effect of the applied axial
load (N or Fz).
Table 7-1: Summary of intended and actual loads applied to the wall specimens.
Sections 7.1 through 7.4 provide a summary of the results of each planar wall test. For each specimen,
the following is provided i) a summary of the specimen design and construction, including drawings and
basic material properties, ii) applied axial load and the base moment to base shear ratio (load
distribution), iii) summary of general response of the wall, including force-drift hysteresis plots, drift
capacity, and failure mode, and iv) a brief summary, including images, of the damage progression. In
summarizing the damage, the aim is to a) identify when key damage states occur, ii) show the crack
pattern, iii) identify the key locations of damage and provide images to illustrate the extent of damage,
and iv) describe the failure and show the final damage state of the wall.
57
NEESR Complex Walls: Planar Wall Test Program
58
NEESR Complex Walls: Planar Wall Test Program
An average axial load of N = 359 kips (1597 kN) or N = 0.095, was applied to the wall. Lateral force (Vtop)
and overturning moment (Mtop) were applied to the top of the specimen. Throughout the test, the ratio
of the lateral force to the overturning moment was held constant such that the base reactions (base
shear Vb and base moment Mb; measured at the wall-foundation interface) were equivalent to those of
a 10-story wall with a lateral load distribution calculated from the Equivalent Lateral Force procedure in
ASCE 7-05. The applied load ratio (Mtop/Vtop) was 16.5 feet (0.42 m) and the ratio of the base reactions
was 28.8 feet (0.73 m). The effective height of the load was 0.71h10, or 2.37hw. Details on the application
of the loads to the wall can be found in Section 5.4. The test was displacement-controlled, with the top
center of the specimen (elevation of hw = 144 inches (3.66 m)) as the control point. The displacement
history is presented in Section 5.4.3.
The following sections provide an overview of the test. Section 7.1.1 provides a general overview of the
test, including load-drift response, failure mode, and comparison of the maximum strength to the
expected strength. Section 7.1.2 provides an overview of the wall damage.
59
NEESR Complex Walls: Planar Wall Test Program
At the base of the wall, the maximum shear demand (Vb) was approximately 0.73Vn, where Vn is the
expected shear strength of the cross section (see Section X). The maximum moment demand (Mb) was
approximately 1.08Mn, where Mn is the expected moment strength of the cross section (see Section X).
7.1.2 Damage
A brief summary of the wall damage is presented here. A detailed description of the damage
progression for Specimen PW1, including a large set of images depicting the damage, can be found in
Birely (2012). A time-lapse movie of damage in the first floor (lower one-third of the specimen) can be
viewed at http://www.youtube.com/user/NEESRWallProject#p/u/1/KC7b-k3ZRjs. The following lists
when key damage states first occurred:
60
NEESR Complex Walls: Planar Wall Test Program
10. Damage (crushing) of the confined core of the boundary element was observed above the splice
during cycles to 1.5% drift.
11. Failure occurred due to bar fracture during the second cycle to 1.5% drift.
Although cracking initiated in the 0.10% drift cycles, a distinct crack pattern, shown in Figure 7-4, was
not developed until the 0.25% drift cycles. Damage other than horizontal and diagonal cracking was
spread from the wall-foundation interface to a height of approximately 36 inches (91.4 cm), or 12 inches
(30.5 cm) above the top of the splice, but was restricted to the edges of the wall and the wall-
foundation interface. The extent of the damage along the edges of the wall was i) greater above the top
of the splice than in the splice region and ii) greater in the west (left) boundary element than in the east
(right) boundary element. Figure 7-5a shows damage to the west (left) edge of the wall at 1.0% drift;
above the top of the splice, bars were buckled, however, within the spliced region, the cover was spalled
but the longitudinal reinforcement was not exposed. Figure 7-5b shows the damage to the east (right)
edge of the wall at 1.5% drift; the longitudinal reinforcement was exposed in the spliced region and one
bar was buckled at the top of the splice, but to a lesser extent than on the west (right) side of the wall.
Figure 7-4: Specimen PW1 crack pattern in lower 2 stories following three cycles to 0.25% drift.
61
NEESR Complex Walls: Planar Wall Test Program
(a) Bar buckling at final WL- peak at 1.0% drift (b) Bar buckling on way to first ER+ peak at 1.5%
(Step 620) drift (Step 680).
Figure 7-5: Specimen PW1 damage along wall edges. Damage was more severe above the top of the
splice and in the west boundary element.
Leading up to the final cycle, the major observed damage was concentrated above the west boundary
element splice, however, failure of the wall ultimately occurred along the wall-foundation interface in
the east boundary element. In the second half (WL- peak) of the second cycle to 1.5% drift, at 1.38%
drift, loss of lateral load carrying capacity occurred when bars fractured at the base of the east (right)
boundary element. The bars fractured along the crack at the wall-foundation interface, which had been
observed previously, but the width of which increased significantly at this step. In the steps to complete
the cycle to the WL- peak, additional bars fractured. Ultimately all the bars on the front of the east
boundary element, expect the extreme bar, had fractured. Figure 7-6 shows the fractured bars on the
front east side of the wall at the final peak. Figure 7-7 shows a photograph and the final crack pattern of
the wall at the end of the test.
62
NEESR Complex Walls: Planar Wall Test Program
Figure 7-6: Specimen PW1: Longitudinal bar fracture on front face of east boundary element at final
peak (-1.52% drift, Step 740).
(a) (b)
Figure 7-7: Specimen PW1 final damage state and crack pattern.
63
NEESR Complex Walls: Planar Wall Test Program
64
NEESR Complex Walls: Planar Wall Test Program
An average axial load of N = 546 kips (2426 kN) or N = 0.130, was applied to the wall. Lateral force (Vtop)
and overturning moment (Mtop) were applied to the top of the specimen. Throughout the test, the ratio
of the lateral force to the overturning moment was held constant such that the base reactions were
equivalent to those of a 10-story wall with a uniform lateral load distribution. The applied load ratio
(Mtop/Vtop) was 11.9 feet (0.30 m), ancillary actuators provided first and second floor lateral loads of
8.7% and 8.6% of Vtop, respectively, and the ratio of the base reactions was 21.4 feet (0.54 m). The
effective height of the load was 0.54h10, or 1.80hw. Details on the application of the loads to the wall can
be found in Section 5.4. The test was displacement-controlled, with the top center of the specimen
(elevation of hw = 144 inches (3.66 m)) as the control point. The displacement history is presented in
Section 5.4.3.
The following sections provide an overview of the test. Section 7.2.1 provides a general overview of the
test, including load-drift response, failure mode, and comparison of the maximum strength to the
expected strength. Section 7.2.2 provides an overview of the wall damage.
65
NEESR Complex Walls: Planar Wall Test Program
At the base of the wall, the maximum shear demand (Vb) was approximately 1.06Vn, where Vn is the
expected shear strength of the cross section (see Section X). The maximum moment demand (Mb) was
approximately 1.05Mn, where Mn is the expected moment strength of the cross section (see Section X).
7.2.2 Damage
A brief summary of the wall damage is presented here. A detailed description of the damage
progression for Specimen PW2, including a large set of images depicting the damage, can be found in
Birely (2012). A time-lapse movie of damage in the first floor (lower one-third of the specimen) can be
viewed at http://www.youtube.com/user/NEESRWallProject#p/u/2/Miepayt10Vk. The following lists
when key damage states first occurred:
66
NEESR Complex Walls: Planar Wall Test Program
9. Failure occurred due to extensive bar buckling and core crushing in the west (left) boundary
element above the splice at 1.05% drift in the first WL- cycle to 1.05% drift.
Figure 7-11 shows the crack pattern in Specimen PW2 following three cycles to 0.21% drift. Damage
other than horizontal and diagonal cracking primarily occurred at the top of the splice (24-36 inches
(61.0-91.4 cm)), although some minor spalling of the concrete was observed at the toes of the wall.
Damage above the splice was greater in the west (left) boundary element than in the east (right)
boundary element; the damage to both boundary element following cycles to -0.75% and 1.0% drift are
shown in Figure 7-12.
Figure 7-11: Specimen PW2 crack pattern in lower two stories following three cycles to 0.21% drift.
67
NEESR Complex Walls: Planar Wall Test Program
Specimen PW2 successfully sustained one half cycle to 1.5% drift in the ER+ direction. When the
specimen was loaded in the WL- direction, bar buckling and core crushing progressively increased above
the west (left) boundary element splice. Damage at this location is shown in Figure 7-13a at -1.06% drift
(one step beyond the previous maximum drift in the WL- loading direction). While loading the wall to
the next step (Step 1305, 1.10% drift, the axial load dropped from 560 to 220 kips (2491 to 979 kN)),
longitudinal bars buckled in the entire west boundary element (previously only the outer bars were
buckled), the region of crushed concrete grew from the boundary element into the web and longitudinal
and horizontal bars in the web buckled. A reduced axial load was necessary to complete the step. Figure
7-14 shows a photograph and the final crack pattern of the wall at the end of the test.
68
NEESR Complex Walls: Planar Wall Test Program
(a) -1.06% drift (Step 1304); one step prior to loss of lateral load carrying capacity.
(b) -1.10% drift (Step 1305) following loss of lateral load carrying capacity.
Figure 7-13: Specimen PW2 damage in the first floor before and after loss of lateral load carrying
capacity.
69
NEESR Complex Walls: Planar Wall Test Program
(a) (b)
Figure 7-14: Specimen PW2 final damage state and crack pattern.
70
NEESR Complex Walls: Planar Wall Test Program
71
NEESR Complex Walls: Planar Wall Test Program
An average axial load of N = 360 kips (1601 kN) or N = 0.10, was applied to the wall. Lateral force (Vtop)
and overturning moment (Mtop) were applied to the top of the specimen. Throughout the test, the ratio
of the lateral force to the overturning moment was held constant such that the base reactions were
equivalent to those of a 10-story wall with a uniform lateral load distribution. The applied load ratio
(Mtop/Vtop) was 11.8 feet (0.30 m), ancillary actuators provided first and second floor lateral loads of
12.4% and 12.5% of Vtop, respectively, and the ratio of the base reactions was 20.2 feet (0.51 m). The
effective height of the load was 0.51h10, or 1.70hw. Details on the application of the loads to the wall can
be found in Section 5.4. The test was displacement-controlled, with the top center of the specimen
(elevation of hw = 144 inches (3.66 m)) as the control point. The displacement history is presented in
Section 5.4.3.
The following sections provide an overview of the test. Section 7.3.1 provides a general overview of the
test, including load-drift response, failure mode, and comparison of the maximum strength to the
expected strength. Section 7.3.2 provides an overview of the wall damage.
72
NEESR Complex Walls: Planar Wall Test Program
At the base of the wall, the maximum shear demand (Vb) was approximately 0.90Vn, where Vn is the
expected shear strength of the cross section (see Section X). The maximum moment demand (Mb) was
approximately 1.16Mn, where Mn is the expected moment strength of the cross section (see Section X).
7.3.2 Damage
A brief summary of the wall damage is presented here. A detailed description of the damage
progression for Specimen PW3, including a large set of images depicting the damage, can be found in
Birely (2012). A time-lapse movie of damage in the first floor (lower one-third of the specimen) can be
viewed at http://www.youtube.com/user/NEESRWallProject#p/u/3/WVtKmeCOFPU. The following lists
when key damage states first occurred:
73
NEESR Complex Walls: Planar Wall Test Program
9. Damage (crushing) of the confined core of the boundary element was observed above the splice
during the second (and final) cycle to 1.0% drift.
10. Failure occurred due to extensive bar buckling and core crushing in the east (right) boundary
element above the splice at 1.28% drift during the first ER+ half cycle to 1.5% drift.
Figure 7-18 shows the crack pattern in Specimen PW3 following three cycles to 0.21% drift. Damage
other than horizontal and diagonal cracking was concentrated above the top of the splice in the
boundary elements and in the web. The initial spalling occurred along the edges of the wall above the
top of the splice in the boundary elements, however, the most apparent damage to the wall was in the
web of the wall. The cover concrete in the web spalled but did not immediately fall of the wall, forming
a bulged region in the web at the top of the splice; the bulged region was identified by tapping the wall
and listening for a hollow sound, and was marked on the wall with a dashed blue line. Figure 7-19a
shows the wall after the second ER+ peak at 1.0% drift; Figure 7-19b and Figure 7-19c show the damage
in the web and boundary element.
Figure 7-18: Specimen PW3 crack pattern in lower two stories following three cycles to 0.21% drift.
74
NEESR Complex Walls: Planar Wall Test Program
(b) Close-up of damage in east (right) side of web (c) Close-up of damage in east (right) boundary
above the splice. element above the splice.
Figure 7-19: Specimen PW3 damage at WL- peak at 1.0% drift (1230).
75
NEESR Complex Walls: Planar Wall Test Program
Specimen PW3 failed during the first half cycle (ER+ direction) to 1.5% drift. At 1.28% drift, the axial load
dropped from 360 kips (1601 kN) to 190 kips (845 kN). This drop in load was accompanied by extensive
bar buckling and core crushing in the east boundary element and increased damage to the concrete in
the web. Figure 7-20 shows a photograph and the final crack pattern of the wall at the end of the test.
(a) (b)
Figure 7-20: Specimen PW3 final damage and crack pattern.
76
NEESR Complex Walls: Planar Wall Test Program
77
NEESR Complex Walls: Planar Wall Test Program
An average axial load of N = 360 kips (1601 kN) or N = 0.117, was applied to the wall. Lateral force (Vtop)
and overturning moment (Mtop) were applied to the top of the specimen. Throughout the test, the ratio
of the lateral force to the overturning moment was held constant such that the base reactions were
equivalent to those of a 10-story wall with a uniform lateral load distribution. The applied load ratio
(Mtop/Vtop) was 11.2 feet (0.28 m), ancillary actuators provided first and second floor lateral loads of
12.2% of Vtop, and the ratio of the base reactions was 21.0 feet (0.53 m). The effective height of the load
was 0.52h10, or 1.73hw. Details on the application of the loads to the wall can be found in Section 5.4.
The test was displacement-controlled, with the top center of the specimen (elevation of hw = 144 inches
(3.66 m)) as the control point. The displacement history is presented in Section 5.4.3.
The following sections provide an overview of the test. Section 7.4.1 provides a general overview of the
test, including load-drift response, failure mode, and comparison of the maximum strength to the
expected strength. Section 7.4.2 provides an overview of the wall damage.
78
NEESR Complex Walls: Planar Wall Test Program
At the base of the wall, the maximum shear demand (Vb) was approximately 0.84Vn, where Vn is the
expected shear strength of the cross section (see Section X). The maximum moment demand (Mb) was
approximately 0.98Mn, where Mn is the expected moment strength of the cross section (see Section X).
7.4.2 Damage
A brief summary of the wall damage is presented here. A detailed description of the damage
progression for Specimen PW4, including a large set of images depicting the damage, can be found in
Birely (2012). A time-lapse movie of damage in the first floor (lower one-third of the specimen) can be
viewed at http://www.youtube.com/user/NEESRWallProject#p/u/4/auU03q70EVg. The following lists
when key damage states first occurred:
79
NEESR Complex Walls: Planar Wall Test Program
8. Bar buckling was observed at the toe of the wall during the third cycle to 0.75% drift.
9. Damage (crushing) of the confined core of the boundary element was observed during the third
cycle to 0.75% drift.
10. Failure occurred due to extensive bar buckling and core crushing in the east (right) boundary
element at the toe of the wall during the second ER+ half-cycle to 1.0% drift.
Figure 7-24 shows the crack patter in Specimen PW4 following three cycles to 0.21% drift. Damage other
than horizontal and diagonal cracking primarily occurred in the boundary elements at the wall-
foundation interface. In the east (right) boundary element, at a height of approximately 4 inches (10.2
cm), cracking and spalling occurred primarily where the cover concrete was patched. Throughout the
test, damage in the east (right) toe of the wall was greater than that in the west (left) toe of the wall.
Figure 7-25 shows the damage to the toes of the wall during the first cycle to 0.75% drift.
Figure 7-24: Specimen PW4 crack pattern in lower two stories following three cycles to 0.21% drift.
80
NEESR Complex Walls: Planar Wall Test Program
(a) Bar buckling and core damage in east (right) (b) Exposed longitudinal reinforcement in west
toe of wall. (left) toe of wall.
Figure 7-25: Specimen PW4 damage to wall following three cycles to 0.75% drift (Step 1070).
Specimen PW4 lost lateral load carrying capacity during the second cycle to 1.0% drift, at 0.85% drift
(Step 1187). The loss of lateral load carrying capacity was associated with a significant increase in bar
buckling and core crushing in the east (right) boundary element; the damage extended the full length of
the boundary element, where on the previous cycle, the damage extended only a few inches in from the
edge of the wall. On the back side (north face) of the wall, buckled horizontal and longitudinal steel was
observed in the web. Figure 7-26 shows the base of the east (right) and west (left) boundary elements at
the second ER+ peak. The test was officially concluded following a return to zero displacement (Step
1250), although additional loading in the WL- direction was done to evaluate the wall behavior in that
direction. Figure 7-27 shows a photograph and the final crack pattern of the wall at the end of the test.
(a) West (left) boundary element. (b) East (right) boundary element.
Figure 7-26: Specimen PW4 damage at base of wall at the second ER+ peak at 1.0% drift (Step 1230).
81
NEESR Complex Walls: Planar Wall Test Program
(a) (b)
Figure 7-27: Specimen PW4 final damage state and crack pattern.
82
NEESR Complex Walls: Planar Wall Test Program
This chapter provides an overview of the data and documentation available in the project warehouse.
Section 8.1 discusses the data available in the data directories required by NEES; this includes
photographs. Section 8.1.3.1 discusses the archival of material data. Section 8.3 discusses the archival of
sensor metadata. Section 8.4 discusses the available documentation, including student dissertations.
Section 8.6 discusses the inDEED data visualization sessions provided to make the project a NEES
Enhanced Project.
The four planar wall tests are archived in the Project Warehouse as 'Experiment-1' (Specimen PW1),
'Experiment-2' (Specimen PW2), 'Experiment-3' (Specimen PW3), and 'Experiment-4' (Specimen PW4).
To reduce the length of this chapter, links are provided only for Specimen PW1; the data for the other
specimens can be changed by modifying the experiment name in the links.
This folder contains the data that had one more level of processing beyond that in the converted data
folder. This included i) correcting of any errors in channel names, ii) conversion of data from voltage, iii)
removal of bad data points, and iv) application of offsets. The details of the data processing are provided
in a document in the Corrected_Data directory for each specimen; for Specimen PW1 this file is available
at https://nees.org/data/get/NEES-2005-0104/Experiment-1/Trial-1/Rep-
1/Corrected_Data/CorrectedDataDocumentation.pdf.
83
NEESR Complex Walls: Planar Wall Test Program
The data in the Corrected_Data directories represent a portion of the final data set used for data
analysis by Birely (2012). The files available are summarized in Table 8-1.
Table 8-1: Data files available in the Corrected_Data directory for each experiment.
The data in the Derived_Data directories represent a portion of the final data set used for data analysis
by Birely (2012). The files available are summarized in Table 8-2.
84
NEESR Complex Walls: Planar Wall Test Program
Table 8-2: Data files available in the Derived_Data directory for each experiment.
For the concrete used for the walls, a description of the mix and material properties are provided. An
Excel file containing the measured stress-strain response of the cylinders is available as well
(https://nees.org/data/get/NEES-2005-0104/Experiment-1/Specimen-2722/Component-301/Material-
438/Wall1%20-%20Concrete%20Stress%20vs%20Strain.xlsx).
For the reinforcing bars (#2 and #4 bars), a description of the material and material properties are
provided. The measured stress-strain response of the bars is available in .txt files for the #2
(https://nees.org/data/get/NEES-2005-0104/Experiment-1/Specimen-2722/Component-301/Material-
439/AllWalls_no_2bar.txt) and #4 bars (https://nees.org/data/get/NEES-2005-0104/Experiment-
1/Specimen-2722/Component-301/Material-440/Wall1_no_4bar.txt).
Material data for concrete and reinforcing steel used for the foundation blocks and wall caps are not
available.
85
NEESR Complex Walls: Planar Wall Test Program
8.4 Drawings
The drawings section of each experiment (specimen) provide .jpg images of the design drawings,
instrument layouts, and experimental set-up. These drawings are also provided in .pdf and/or .dwg
(AutoCAD) format in the documentation folder.
8.5 Documentation
The following provides a list of the documentation available for each experiment:
1. Drawings
a. A .pdf containing drawings of the test specimens. For Specimen PW1, this can be
downloaded at https://nees.org/data/get/NEES-2005-0104/Experiment-
1/Documentation/PW1%20Test%20Specimen.pdf
b. A .pdf containing drawings of the test setup. For Specimen PW1, this can be
downloaded at https://nees.org/data/get/NEES-2005-0104/Experiment-
1/Documentation/PW1%20Test%20Setup.pdf
c. A .pdf file containing the instrumentation layout (same as provided in the appendix of
this document). For Specimen PW1, this can be downloaded at
https://nees.org/data/get/NEES-2005-0104/Experiment-
1/Documentation/PW1%20Instrumentation%20Layouts.pdf
d. A .dwg file containing the drawings in the files above. For Specimen PW1, this can be
downloaded at https://nees.org/data/get/NEES-2005-0104/Experiment-
1/Documentation/Planar%20Walls%20CAD.dwg
e. A .dwg file containing details for the foundation block. For Specimen PW1, this can be
downloaded at https://nees.org/data/get/NEES-2005-0104/Experiment-
1/Documentation/PW_Foundation_Typ.dwg
f. A .dwg file containing details for the wall cap. For Specimen PW2, this can be
downloaded at https://nees.org/data/get/NEES-2005-0104/Experiment-
1/Documentation/PW_Cap_Beam_Typ.dwg
2. Testing Notes: A .pdf file containing testing notes is provided for each wall. Only steps for which
notes were taken are provided. Each step is one row in a table. For each step the following is
provided: i) the cycle in which the step occurred (the letter indicates the first, second or third
cycle), ii) the specimen drift, iii) comments, and iv) picture number for the roaming camera
pictures (not always available). For some specimens, crack width measurements are also
86
NEESR Complex Walls: Planar Wall Test Program
provided in the testing note document. The testing notes for Specimen PW1 can be found at:
https://nees.org/data/get/NEES-2005-0104/Experiment-
1/Documentation/TestingNotesPW1.pdf
3. Sensor Database: A .xls file containing the original sensor database used by the project team (as
provided by the UIUC team to the UW team). This is provided in addition to sensor metadata
provided per the NEES Project Warehouse project requirements.
IMPORTANT NOTE: At the time this document was written, these files are not accessible from the
experiment main page (the analysis section indicates no files) but these files can be accessed using the
file browser.
CHAPTER 9: References
American Society of Civil Engineering. (2005). Minimum Design Loads for Buildings and Other Structures.
ASCE/SEI 7-10. ASCE, Reston, Virginia.
American Concrete Institute. (2005). Building Code Requirements for Concrete (ACI 318-05) and
Commentary (ACI 318R-05), American Concrete Institute, Farmington Hills, MI.
Birely, A.C. (2012). Seismic Performance of Slender Reinforced Concrete Walls. Ph.D. theis in progress,
University of Washington, Seattle, Washington.
Hart, C.R. (2011). Tensile Response of Reinforced Concrete Structural Walls Under Reversed Cyclic
Loading. Ph.D. thesis in progress, University of Illinois at Urbana-Champaign, Champaign, Illinois.
Marley, K.P (2011). Evaluation of Concrete Compressive Models Applied to Large-Scale Structural
Walls. Ph.D. thesis in progress, University of Illinois at Urbana-Champaign, Champaign, Illinois.
87