Beruflich Dokumente
Kultur Dokumente
Scheduling
Construction Management
Project planning
n a planner:
q begins with a result (i.e. a facility design)
q must synthesize the steps required to yield this result.
n Essential aspects of construction planning include
q the generation of required activities,
q analysis of the implications of these activities, and
q choice among the various alternative means of performing
activities.
n a useful approach
q is to simulate the construction process either in the
imagination of the planner or with a formal computer based
simulation technique
Alternative Emphases in Construction
Planning
Aspects contribute the breakdown of the project
n Methods used to place the work
n skills needed for the work
n crafts involved
n critical resources (cranes,crews,etc)
n administrative actions that require time
(obtaining permits,inspections,etc)
n deliveries or approvals that must be
considered (approval of shop
drawing,delivery of piles,etc.)
n special activities (cure concrete,etc.)
WBS (Work Breakdown Structure)
n A deliverable-oriented hierarchical decomposition of the
work to be executed by the project team to accomplish
the project objective and create the required
deliverables.
n It organises and defines the total scope of the project.
Each descending level represents an increasing detail
definition of the project work.
n The WBS is decomposed into work packages. The
deliverable orientation of the hierarchy includes both
internal and external deliverables
n Source: A guide to the Project Management Body of
Knowledge, 3rd ed ver 1.3, 2004 Glossary
Starting point of construction
planning
n Scope Definition Document
n WBS
n Method Statement
n Plan
n Duration/resource estimation
n Schedule
n Resource loading
Ilustrative Hierarchical Activity Divisions
for a Roadway Project
Defining Precedence Relationships
Among Activities
n Once work activities have been defined, the
relationships among the activities can be
specified.
n Precedence relations between activities
signify that the activities must take place in a
particular sequence.
n Numerous natural sequences exist for
construction activities due to requirements for
structural integrity, regulations, and other
technical requirements
Illustrative Set of Four Activities with
Precedences
Types of project planning
n Bar chart
n Linear scheduling method
n Network planning
Bar chart
n Gantt chart
n Representation of a project activity as a time-
scaled bar whose length represents the
planned duration of the activity
n Easy to make, read and effective for
communicating in field
n Project information illustration is limited,
where :
q Interdependency between activities are not
shown
q Critical activities are not shown
Example of Bar (Gantt) Chart
Bar chart
Planned duration
Project
work item
50% complete
Project
work item
Percent complete
0 25 50 75 100 scale
LINEAR SCHEDULING METHOD
Units of
production
100
80 Planned rate
of progress
60
40
Actual rate of
progress
20
Project
month
5 10 15 20 25
NETWORK DIAGRAM
n Activity :
q A duration (time) is needed to finish an activity
q The length or size of the arrow does not represent
any meaning, but the arrow shows the sequence
of activities.
q An activity is started from a node, and ended in
another node.
q Example of activities: soil excavation, waiting for
the concrete to dry, etc.
Terms in Arrow Diagram
n Event (a node)
q An event starts and ends an activity
q An event does not have a duration
q Example: soil excavation starts, soil excavation
finishes, etc
n Milestone (target): An event that has an
important meaning, example: start, finish, and
other event that is viewed to be essential to
be controlled/monitored.
Terms in Arrow Diagram
n Dummy activity: An activity that does not
need any duration and resources. It is
needed for assisting the logics between
activities.
n Critical Path:
q A path in a network that consists of activities
which have the longest total duration.
q The total float (TF) = 0 (consists of activities with
TF = 0)
Terms in Arrow Diagram
n i - event i
n j - event j
n TiE - early time of event n TjE - early time of event j
i
n TjL - late time of event j
n TiL - late time of event i
n tij - duration of activity
ARROW DIAGRAM
Dummy Activity
Example
Arrow diagram
(need for dummy arrow)
n Activity A precedes B
n Activity C precedes B
A B
n Activity C precedes D
A B A B
C D
C D
Arrow diagram (example)
Activity Title Duration Preceding
(days) Activities
A Mobilize 10 -
B Obtain permits 15 -
C Site works 8 A
D Exterior utilities 12 A
E Excavate catch basin 2 B,C
F Excavate footers 5 B,C
G Excavate foundation peers 6 B,C
H Pour footers 8 D,E,F,G
I Erect building frame 10 H
Arrow diagram (example)
D
12
A C E H I
1 2 3 6 7 8
10 8 2 8 10
4 F
B 5
15
G
5
6
Analyze project network to:
D
12
0 10 18 24 32 42
A C E H I
1 2 3 6 7 8
10 8 2 8 10
4 F
B 18 5
15
G
5
6
18
Backward-pass algorithm
D
12
0 0 10 10 18 18 24 24 32 32 42 42
A C E H I
1 2 3 6 7 8
10 8 2 8 10
4 F
B 18 19 5
15
G
5
6
18 18
FLOAT
n A duration where an activity can be allowed
to be delayed or can be called as delay
tolerance time
n Float gives some flexibility in a scheduling
network, which can be used for optimizing the
resources allocations.
FLOAT (TENGGANG WAKTU)
2 2
D
12
0 0 10 10 18 18 24 24 32 32 42 42
A C E H I
1 2 3 6 7 8
10 8 2 8 10
0 0 0 0 4 4 0 0 0 0
4 F
B 18 19 5 1 1
15
3 3 G
5 Note:
6
18 18 0 0 FF TF
Critical path
2 2
D
12
0 0 10 10 18 18 24 24 32 32 42 42
A C E H I
1 2 3 6 7 8
10 8 2 8 10
0 0 0 0 4 4 0 0 0 0
4 F
B 18 19 5 1 1
15
3 3 G
5 Note:
6
18 18 0 0 Critical activity
PRECEDENCE DIAGRAM
n A network diagram using nodes to illustrate activities
n Multiple logic relationships can occur on this type of
diagram, which are:
q Finish to start (FS) = The start of an activity depends
on the ending (finish) of its predecessor (activity
before it)
q Start to start (SS) = The start of an activity depends on
the start of its predecessor
q Finish to Finish (FF) = The ending/finish of an activity
B C
4 6
EST A EFT F
LST 2 LFT 8
D E
5 2
Precedence diagram
TF = 0 TF = 0
2 B 6 6 C 12
2 4 6 6 6 12
TF = 0 FF = 0 FF = 0 TF = 0
0 A 2 12 F 20
0 2 2 12 8 20
FF = 0 FF = 0
TF = 3 TF = 3
2 D 7 7 E 9
5 5 10 10 2 12
FF = 0 FF = 0
Precedence diagram
TF = 0 TF = 0
2 B 6 6 C 12
2 4 6 6 6 12
TF = 0 FF = 0 FF = 0 TF = 0
0 A 2 12 F 20
0 2 2 12 8 20
FF = 0 FF = 0
TF = 3 TF = 3
2 D 7 7 E 9
5 5 10 10 2 12
FF = 0 FF = 0
P.E.R.T
Program Evaluation Review
Technique (PERT)
n PERT:
q developed by U.S. Navy Polaris Program for the
Polaris Fleet Ballistic Missile in 1957
q Using probabilistic approach in determining
duration
Probability in PERT
n Optimistic duration: o
n Most likely duration: m
n Pessimistic duration: p
o + 4m + p
te =
6
Probability in PERT
n Example: n Example:
o=4 o=4
m=6 m=5
p=7 p = 18
te = (4 + 24 + 7) / 6 te = (4 + 20 + 18) / 6
=7 > 5
= 5.8 < 6
Variance (te)
n is a measure of difference
n described uncertainty associated with the
time-estimating
n the larger the variance, the bigger the
uncertainty
n te = [(p - o) / 6]2
Variance (te)
A: A1:
n o=4 n o = 4
n m=6 n m = 5.5
n p=8 n p = 10
4 + 24 + 8 4 + 22 + 10
te(A) = =6 te(A1) = =6
6 6
2
p-o
TE = v te2 = v 6
Example
A B C D
1 2 3 4 5
o =4 o =3 o =2 o =4
m=6 m=8 m=4 m=5
p =8 p =9 p =7 p =6
8 - 4 2
te2 = 6 te2 = 12 te2 = 0.8332 te2 = 0.3332
2 2
= 3
TE = v te2
Schedule duration = TS
Expected project duration = TE
Use of standard normal distribution table
n Example:
from previous example what is the probability of
finishing the project at TS = 21.5
TS - TE 21.5 - 22.5
Z= = = -0.67
TE 1.5
n Exercises on CPM