3.1 Consumptions for Plastering, Brickworks, Concreting etc.
Consumption of different materials of construction in the corresponding contract items of works shall
be computed on the basis of the quantities shown in Table: 3-1, subject to a variation of plus / minus
five percent. Where, however, the circumstances of work so require, the Engineer-in-charge shall be
competent to allow (for record reason) for a greater variation.
N.B. :- This statement is based on the following assumptions:
(1) That dry sand with necessary allowance for bulking is used.
(2) That the size of bricks shall be 9 x 4 x 2 .
(3) Volume of 1 bag (50 Kg) cement = 0.035 m3
Stone 1.250 m3
Square & coursed Rubble masonry in cement
14 m3 Cement 89.1 kg
mortar in road & jhora works (1 : 5)
Sand 0.312 m3
167
Section : 3 P.W. (Roads) Directorate
Consumption of Materials Schedule of Rates : 2008-2009
Sl.
Description of items Unit Quantities of materials required.
No.
Stone 1.250 m3
Square & coursed Rubble masonry in cement
15 m3 Cement 76.4 kg
mortar in road & jhora works (1 : 6)
Sand 0.321 m3
Stone chips (6 to 20 mm) 0.860 m3
16 Nominal mix cement concrete (1 : 11/2 : 3) m3 Cement 408.6 kg
Sand 0.430 m3
Stone chips (6 to 20 mm) 0.880 m3
17 Nominal mix cement concrete (1 : 2 : 4) m3 Cement 314.3 kg
Sand 0.440 m3
Stone chips (6 to 20 mm) 0.940 m3
18 Nominal mix cement concrete (1 : 3 : 6) m3 Cement 222.9 kg
Sand 0.470 m3
Stone chips (6 to 20 mm) 0.960 m3
19 Nominal mix cement concrete (1 : 4 : 8) m3 Cement 171.4 kg
Sand 0.480 m3
20 Neat cement punning 100 m2 cement 217.1 kg
21 Single brick flat soling 100 m2 Brick 3228 nos.
22 Brick on edge flooring 100 m2 Brick 5380 nos.
23 75 mm wide brick on end edging 100 m2 Brick 800 nos.
24 75 mm wide brick on edge edging 100 m2 Brick 400 nos.
25 Boulder for pitching apron & sausage work m3 Boulder 0.90 m3