Beruflich Dokumente
Kultur Dokumente
com
a
Department of Building Services Engineering, The Hong Kong Polytechnic University, Hung Hom, Kowloon, Hong Kong
b
School of Thermal Engineering, Shangdong University of Architecture, Jinan, Shandong, China
Received 12 March 2007; received in revised form 7 August 2007; accepted 14 August 2007
Available online 19 September 2007
Abstract
System power reliability under varying weather conditions and the corresponding system cost are the two main concerns for designing
hybrid solarwind power generation systems. This paper recommends an optimal sizing method to optimize the congurations of a
hybrid solarwind system employing battery banks. Based on a genetic algorithm (GA), which has the ability to attain the global opti-
mum with relative computational simplicity, one optimal sizing method was developed to calculate the optimum system conguration
that can achieve the customers required loss of power supply probability (LPSP) with a minimum annualized cost of system (ACS). The
decision variables included in the optimization process are the PV module number, wind turbine number, battery number, PV module
slope angle and wind turbine installation height. The proposed method has been applied to the analysis of a hybrid system which supplies
power for a telecommunication relay station, and good optimization performance has been found. Furthermore, the relationships
between system power reliability and system congurations were also given.
2007 Elsevier Ltd. All rights reserved.
Keywords: Hybrid solarwind system; Optimization; LPSP; Annualized cost of system; Genetic algorithm
0038-092X/$ - see front matter 2007 Elsevier Ltd. All rights reserved.
doi:10.1016/j.solener.2007.08.005
H. Yang et al. / Solar Energy 82 (2008) 354367 355
Nomenclature
conditions in terms of investment and system power reli- PV and wind turbine) were included in the optimization
ability requirement. process.
Various optimization techniques such as the probabilis- Yang et al. (2003, 2007) have proposed an iterative opti-
tic approach, graphical construction method and iterative mization technique following the loss of power supply prob-
technique have been recommended by researchers. ability (LPSP) model for a hybrid solarwind system. The
Tina et al. (2006) presented a probabilistic approach number selection of the PV module, wind turbine and bat-
based on the convolution technique to incorporate the uc- tery ensures the load demand according to the power reli-
tuating nature of the resources and the load, thus eliminat- ability requirement, and the system cost is minimized.
ing the need for time-series data, to assess the long-term Similarly, an iterative optimization method was presented
performance of a hybrid solarwind system for both by Kellogg et al. (1998) to select the wind turbine size and
stand-alone and grid-connected applications. PV module number needed to make the dierence of gener-
A graphical construction technique for guring the opti- ated and demanded power (DP) as close to zero as possible
mum combination of battery and PV array in a hybrid over a period of time. From this iterative procedure, several
solarwind system has been presented by Borowy and Sal- possible combinations of solarwind generation capacities
ameh (1996). The system operation is simulated for various were obtained. The total annual cost for each conguration
combinations of PV array and battery sizes and the loss of is then calculated and the combination with the lowest cost
power supply probability (LPSP). Then, for the desired is selected to represent the optimal mixture.
LPSP, the PV array versus battery size is plotted and the Eftichios Koutroulis et al. (2006) proposed a methodol-
optimal solution, which minimizes the total system cost, ogy for optimal sizing of stand-alone PV/WG systems. The
can be chosen. Another graphical technique has been given purpose of the proposed methodology is to suggest, among
by Markvart (1996) to optimize the size of a hybrid solar a list of commercially available system devices, the optimal
wind energy system by considering the monthly average number and type of units ensuring that the 20-year round
solar and wind energy values. However, in both graphical total system cost is minimized subject to the constraint that
methods, only two parameters (either PV and battery, or the load energy requirements are completely covered,
356 H. Yang et al. / Solar Energy 82 (2008) 354367
resulting in zero load rejection. This methodology can nd 2. Model of the hybrid system components
the global optimum system conguration with relative
computational simplicity, but the congurations are some- A hybrid solarwind power generation system consists of
times not cost eective, because sometimes a tiny amount PV array, wind turbine, battery bank, inverter, controller,
of load rejections are tolerable to the customers in order and other accessory devices and cables. A schematic diagram
to gain an acceptable system cost. of the basic hybrid system is shown in Fig. 1. The PV array
A common disadvantage of the optimization methods and wind turbine work together to satisfy the load demand.
described above is that they still have not found the best When energy sources (solar and wind energy) are abundant,
compromise point between system power reliability and the generated power, after satisfying the load demand, will
system cost. The minimization of system cost function is be supplied to feed the battery until it is full charged. On
normally implemented by employing probability program- the contrary, when energy sources are poor, the battery will
ming techniques or by linearly changing the values of release energy to assist the PV array and wind turbine to
corresponding decision variables, resulting in suboptimal cover the load requirements until the storage is depleted.
solutions and sometimes increased computational eort In order to predict the hybrid system performance, indi-
requirements. Also, these sizing methodologies normally vidual components need to be modeled rst and then their
do not take into account some system design characteris- mix can be evaluated to meet the load demand.
tics, such as PV modules slope angle and wind turbine
installation height, which also highly aect the resulting
energy production and system installation costs.
2.1. PV system model
In this paper, one optimal sizing model for a stand-alone
hybrid solarwind system employing battery banks is
The power generation simulation model for the PV sys-
developed based on the loss of power supply probability
tem is composed of three parts: PV array power model,
(LPSP) and the annualized cost of system (ACS) concepts.
solar radiation on PV module surface and PV module tem-
The optimization procedure aims to nd the conguration
perature model.
that yields the best compromise between the two consid-
ered objectives: LPSP and ACS. The decision variables
included in the optimization process are the PV module
number, wind turbine number, battery number, and also 2.1.1. PV array power model
the PV module slope angle as well as the wind turbine PV module performance is highly inuenced by weather
installation height. The congurations of a hybrid system conditions, especially solar radiation and PV module tem-
that can meet the system power reliability requirements perature. A simplied simulation model (Zhou et al., 2007)
with minimum cost can be obtained by an optimization with acceptable precision is used to estimate the actual per-
technique the genetic algorithm (GA), which is an formance of PV modules under varying operating condi-
advanced search and optimization technique; it is generally tions. Five parameters (a, b, c, Rs and nMPP) are
robust in nding global optimal solutions, particularly in introduced to take account for all the nonlinear eects of
multi-modal and multi-objective optimization problems, the environmental factors on PV module performance.
where the location of the global optimum is a dicult Using the denition of ll factor, the maximum power out-
task. put delivered by the PV module can be written as
2.1.3.3. Convective heat transfer. The convection may be a 2.3. Battery model
combination of free and forced convection eects. For
the free convection eects, an approximation given by Hol- The battery bank, which is usually of the lead-acid type,
man (1992) is used. For forced cooling, it is approximated is used to store surplus electrical energy, to regulate system
as a linear function of wind speed. Then, the total convec- voltage and to supply power to load in case of low wind
tive energy exchange for the PV module is speed and/or low solar conditions. Lead-acid batteries used
in hybrid solarwind systems operate under very specic
Qconoutput hc;free hc;forced conditions, and it is often very dicult to predict when
2A 1:31 T PV T air
1=3
0:5 vwind energy will be extracted from or supplied to the battery.
Here in this paper, several factors that aect the battery
T PV T air 10 behaviors have been taken into account, such as the
H. Yang et al. / Solar Energy 82 (2008) 354367 359
charging current rate, the charging eciency, the self-dis- inverter. In this case, the wind turbine is assumed to have
charge rate as well as the battery capacity. DC output, so the use of a rectier is not necessary. But
Most battery models mainly focus on three dierent if the wind turbine is designed to connect to an AC grid,
characteristics, i.e. the battery state of charge (SOC) as well then the rectier losses should be considered for the part
as the oating charge voltage (or the terminal voltage) and of wind energy that has been rectied from AC to DC.
the battery lifetime.
2.3.2. Battery oating charge voltage
2.3.1. Battery state-of-charge (SOC) The battery oating charge voltage response under both
Energy will be stored in the batteries when the power charging and discharging conditions is modeled by the
generated by the wind turbine and PV array is greater than equation-t method, which treats the battery as a black
the load. When power generation cannot satisfy the load box and expresses the battery oating charge voltage by
requirements, energy will be extracted from the batteries, a polynomial in terms of battery SOC and battery current
and the load will be cut o when power generation by both
3 2
wind turbine and PV array is insucient and the storage is V 0bat A SOC B SOC C SOC D 16
depleted.
Like all chemical processes, the battery capacity is tem- where V 0bat is the battery oating charge voltage, in order to
perature dependent. Generally, the battery capacity take into account the temperature eect on battery voltage
changes can be expressed by using the temperature coe- predictions, the temperature coecient dV is applied (Bern-
cient dC (Berndt, 1994): dt, 1994)
C 0bat C 00bat 1 dC T bat 298:15 13 V bat V 0bat dV T bat 298:15 17
where C 0bat
is the available or practical capacity of the bat- where Vbat is the calibrated voltage of the battery, after the
tery when the battery temperature is Tbat, Ah; C 00bat is the temperature eects have been considered. The temperature
nominal or rated capacity of the battery, which is the value coecient dV is assumed to be a constant of 4 mV/C per
of the capacity given by the manufacturer as the standard 2 V cell for the considered battery temperature range in this
value that characterizes this battery, Ah; a temperature research.
coecient of dC = 0.6% per degree, is usually used unless Parameters A, B, C and D in Eq. (16) are functions of
otherwise specied by the manufacturer (Berndt, 1994). the battery current I, and can be calculated by the follow-
For perfect knowledge of the real SOC of a battery, it is ing second degree polynomial equations:
necessary to know the initial SOC, the charge or discharge 0 1 0 1
time and the current. However, most storage systems are A a1 a2 a3 0 2 1
not ideal, losses occur during charging and discharging BBC Bb b b C I
B C B 1 2 3 CB C
and also during storage periods. Taking these factors into B CB C@ I A 18
@ C A @ c1 c2 c3 A
account, the SOC of the battery at time t + 1 can be simply 1
D d1 d2 d3
calculated by
r Dt The parameters a1, a2, a3, . . . , d1, d2, d3 can be determined
SOCt 1 SOCt 1 using the least squares tting method by tting the equa-
24
tions to battery performance data (usually available from
I bat t Dt gbat
14 the manufacturer). The parameters for the battery used
C 0bat in the following project analysis are calculated to be:
where r is the self-discharge rate which depends on the 0 1
a1 a2 a3
accumulated charge and the battery state of health (Guasch Bb b b C
and Silvestre, 2003), and a proposed value of 0.2% per day B 1 2 3C
B C
is recommended. It is dicult to measure separate charging @ c1 c2 c3 A
and discharging eciencies, so manufacturers usually spec- d1 d2 d3
ify a round-trip eciency. In this paper, the battery charge 80 1
> 0:00152 0:05509 0:15782
eciency is set equal to the round-trip eciency, and the >
>B
>
>
> B 0:00165 0:05758 0:39049 C
C
discharge eciency is 1. >
> B C I >0
>
> @ 0:00024 0:01018 0:52391 A
The current rate of the battery at time t for the hybrid >
>
>
< 0:00014
solarwind system can be described by 0:00795 1:86557
0 1
P PV t P WT t P AC load t=ginverter P DC load t >
> 0:00130 0:00093 0:03533
>
>
I bat t >
> B 0:08716 C
V bat t >
> B 0:00201 0:00803 C
>
> B C I <0
15 >
> @ 0:00097 0:00892 0:22999 A
>
:
0:00021 0:00306 1:93286
The inverter eciency ginverter is considered to be 92%
according to the load prole and the specications of the 19
360 H. Yang et al. / Solar Energy 82 (2008) 354367
where I > 0 represents the battery charging process, and an insucient power supply results when the hybrid system
I < 0 for the discharging process. Once these parameters (PV array, wind turbine and battery storage) is unable to
are estimated, the battery model can be used for the satisfy the load demand (Yang et al., 2003). It is a feasible
simulations. measure of the system performance for an assumed or
known load distribution. A LPSP of 0 means the load will
2.3.3. Battery lifetime always be satised; and an LPSP of 1 means that the load
Two independent limitations on the lifetime of battery will never be satised. Loss of power supply probability
banks (the battery cycle life Ybat,c and the battery oat life (LPSP) is a statistical parameter; its calculation is not only
Ybat,f) are employed. focused on the abundant or bad resource period. There-
Battery cycle life Ybat,c is the length of time that the bat- fore, in a bad resource year, the system will suer from a
tery will last under normal cycles before it requires replace- higher probability of losing power.
ment; it depends on the depth of discharge of individual There are two approaches for the application of LPSP in
cycles. During the battery lifetime, a great number of indi- designing a stand-alone hybrid system. The rst one is
vidual cycles may occur, including the charging and dis- based on chronological simulation. This approach is com-
charging process, and every discharging process will putationally burdensome and requires the availability of
result in some depletion of the battery. Here the equivalent data spanning a certain period of time. The second
full cycles (EFC) concept (Ashari and Nayar, 1999) has approach uses probabilistic techniques to incorporate the
been taken, an average EFC will be given, and after all uctuating nature of the resource and the load, thus elim-
the equivalent cycles, the battery will need to be replaced. inating the need for time-series data. Considering the
The battery oat life Ybat,f is the maximum length of energy accumulation eect of the battery, to present the
time that the battery will last before it needs replacement, system working conditions more precisely, the chronologi-
regardless of how much or how little it is used. This limita- cal method is employed in this research. The objective func-
tion is typically associated with the damage caused by cor- tion, LPSP, from time 0 to T can then be described by
rosion in the battery, which is strongly aected by PT
temperature. Higher ambient temperatures are more con- Power failure time
LPSP t0
ducive to corrosion, so a battery installed in warm sur- T
PT
roundings would have a shorter oat life than one TimeP available t < P needed t
installed in air-conditioned surroundings. t0 20
T
Considering these two lifetime aspects or limitations, the
battery will be exhausted either from use or from old age, where T is the number of hours in this study with hourly
depending on which one is shorter. weather data input. The power failure time is dened as
the time that the load is not satised when the power gen-
2.3.4. Battery simulation constraints erated by both the wind turbine and the PV array is insuf-
The battery SOC was used as a decision variable for the cient and the storage is depleted (battery SOC falls below
control of battery overcharge and discharge protections. the allowed value SOCmin = 1 DOD and still has not
The case of overcharge may occur when higher power is recovered to the reconnection point). The power needed
generated by the PV array and wind turbine, or when by the load side can be expressed as
low load demand exists. In such a case when the battery P AC load t
SOC reaches the maximum value, SOCmax = 1, the control P needed t P DC load t 21
ginverter t
system intervenes and stops the charging process. On the
other hand, if the state of charge decreases to a minimum and the power available from the hybrid system is
level, SOCmin = 1 DOD, the control system disconnects expressed by
the load. This is important to prevent against batteries
shortening their lifetime or even their destruction. Also, P available t P PV P WT C V bat
for longevity of battery life, the maximum charging rate, 0:2C 0bat C 0bat SOCt SOCmin
Min I bat; max ;
SOC/5, is given as the upper limit. Dt Dt
22
3. Power reliability model based on LPSP concept
where C is a constant, 0 for battery charging process and 1
Because of the intermittent solar radiation and wind for battery discharging process. SOC(t) is the battery state-
speed characteristics, which highly inuence the resulting of-charge at time t, and it is calculated based on the battery
energy production, power reliability analysis has been con- SOC at the previous time t 1 by using Eq. (14). The wind
sidered as an important step in any system design process. turbine, as mentioned before, is assumed to have DC out-
A reliable electrical power system means a system has suf- put, so the rectier is not used. But if the wind turbine is
cient power to feed the load demand during a certain per- designed to have AC output, then the rectier losses should
iod or, in other words, has a small loss of power supply be considered for the part of wind energy that has been rec-
probability (LPSP). LPSP is dened as the probability that tied from AC to DC.
H. Yang et al. / Solar Energy 82 (2008) 354367 361
Using the above developed objective function according The annual real interest rate i is related to the nominal
to the LPSP technique, for a given LPSP value for one interest rate i 0 (the rate at which you could get a loan)
year, a set of system congurations, which satisfy the sys- and the annual ination rate f by the equation given below.
tem power reliability requirements, can be obtained. i0 f
i 26
1f
4. Economic model based on ACS concept
The optimum combination of a hybrid solarwind sys- 4.2. The annualized replacement cost
tem can make the best compromise between the two con-
sidered objectives: the system power reliability and The annualized replacement cost of a system component
system cost. The economical approach, according to the is the annualized value of all the replacement costs occur-
concept of annualized cost of system (ACS), is developed ring throughout the lifetime of the project. In the studied
to be the best benchmark of system cost analysis in this hybrid system, only the battery needs to be replaced peri-
study. According to the studied hybrid solarwind system, odically during the project lifetime.
the annualized cost of system is composed of the annual- C arep C rep SFFi; Y rep 27
ized capital cost Cacap, the annualized replacement cost
Carep and the annualized maintenance cost Camain. Five where Crep is the replacement cost of the component (bat-
main parts are considered: PV array, wind turbine, battery, tery), US$; Yrep is the component (battery) lifetime, year;
wind turbine tower and the other devices. The other devices SFF is the sinking fund factor, a ratio to calculate the fu-
are the equipments that are not included in the decision ture value of a series of equal annual cash ows. The equa-
variables, including controller, inverter and rectier (if it tion for the sinking fund factor is
is necessary when the wind turbine is designed to have i
AC output). Then, the ACS can be expressed by SFFi; Y rep Y 28
1 i rep 1
ACS C acap PV Wind Bat Tower Others
C arep Bat C amain PV Wind Bat 4.3. The maintenance cost
Tower Others 23
The system maintenance cost, which has taken the ina-
tion rate f into account, is given as
4.1. The annualized capital cost C amain n C amain 1 1 f
n
29
The annualized capital cost of each component (PV where Camain(n) is the maintenance cost of the nth year.
array, wind turbine, battery, wind turbine tower and the The initial capital cost, replacement cost, maintenance
other devices) has taken into account the installation cost cost in the rst year and the lifetime of each component
(including PV array racks and cables et al.), and they are (PV array, wind turbine, battery, tower and other devices)
calculated by in this study are assumed as shown in Table 3.
The conguration with the lowest annualized cost of
C acap C cap CRFi; Y proj 24 system (ACS) is taken as the optimal one from the cong-
where Ccap is the initial capital cost of each component, urations that can guarantee the required reliability of
US$; Yproj is the component lifetime, year; CRF is the cap- power supply.
ital recovery factor, a ratio to calculate the present value of
an annuity (a series of equal annual cash ows). The equa- 5. System optimization model with genetic algorithm
tion for the capital recovery factor is
Y Due to more variables and parameters that have to be
i 1 i proj
CRFi; Y proj 25 considered, the sizing of the hybrid solarwind systems is
1 iY proj 1 much more complicated than the single source power
Table 3
The costs and lifetime aspect for the system components
Initial capital cost Replacement cost Maintenance cost Lifetime Interest rate i 0 Ination rate f
in the rst year (year) (%) (%)
PV array 6500 US$/kW Null 65 US$/kW 25 3.75 1.5
Wind turbine 3500 US$/kW Null 95 US$/kW 25
Battery 1500 US$/kAh 1500 US$/kAh 50 US$/kAh Null
Tower 250 US$/m Null 6.5 US$/m 25
Other components 8000 US$ Null 80 US$ 25
362 H. Yang et al. / Solar Energy 82 (2008) 354367
generating systems. This type of optimization includes eco- MinN PV ; N wind ; N bat P 0 30
nomical objectives, and it requires the assessment of long- H low 6 H WT 6 H high 31
term system performance in order to reach the best
0 6 b0 6 90 32
compromise for both power reliability and cost. The mini-
mization of the cost (objective) function is implemented
An initial population of 10 chromosomes, comprising the
employing a genetic algorithm (GA), which dynamically
1st generation, is generated randomly and the constraints
searches for the optimal system congurations.
described by inequalities (30)(32) are evaluated for each
chromosome. If any of the initial population chromosomes
5.1. Genetic algorithm
violates the problem constraints then it is replaced by a new
chromosome, which is generated randomly and fulls these
A genetic algorithm (GA) is an advanced search and
constraints.
optimization technique. It has been developed to imitate
The PV array power output is calculated according to
the evolutionary principle of natural genetics. Compared
the PV system model by using the specications of the
with traditional methods (the direct exhaustive search
PV module as well as the ambient air temperature and solar
method and the gradient-directed search method) for func-
radiation conditions. The wind turbine performance calcu-
tion optimization, one of the main advantages of the GA is
lations need to take into account the eects of wind turbine
that it is generally robust in nding global optimal solu-
installation height. The battery bank, with total nominal
tions, particularly in multimodal and multi-objective opti-
capacity C 0bat (Ah), is permitted to discharge up to a limit
mization problems.
dened by the maximum depth of discharge DOD, which
Generally, a GA uses three operators (selection, crossover
is specied by the system designer at the beginning of the
and mutation) to imitate the natural evolution processes.
optimal sizing process.
The rst step of a genetic evaluation is to determine if
The system conguration will then be optimized by
the chosen system conguration (called a chromosome)
employing a genetic algorithm, which dynamically searches
passes the functional evaluation, provides service to the
for the optimal conguration to minimize the annualized
load within the bounds set forth by the loss of power sup-
cost of system (ACS). For each system conguration, the
ply probability. If the evaluation qualied chromosome has
systems LPSP will be examined for whether the load
a lower annualized cost of system (ACS) than the lowest
requirement (LPSP target) can be satised. Then, the lower
ACS value obtained at the previous iterations, this system
cost load requirement satised congurations, will be sub-
conguration (chromosome) is considered to be the opti-
ject to the following crossover and mutation operations of
mal solution for the minimization problem in this iteration.
the GA in order to produce the next generation population
This optimal solution will be replaced by better solutions, if
until a pre-specied number of generations has been
any, produced in subsequent GA generations during the
reached or when a criterion that determines the conver-
program evolution.
gence is satised.
After the selection process, the optimal solution will
So, for the desired LPSP value, the optimal congura-
then be subject to the crossover and mutation operations
tion can be identied both technically and economically
in order to produce the next generation population until
from the set of congurations by achieving the lowest
a pre-specied number of generations have been reached
annualized cost of system (ACS) while satisfying the LPSP
or when a criterion that determines the convergence is
requirement.
satised.
The following optimization model is a simulation tool to The proposed method has been applied to analyze one
obtain the optimum size or optimal conguration of a hybrid project, which is designed to supply power for a
hybrid solarwind system employing a battery bank in telecommunication relay station on a remote island, Dal-
terms of the LPSP technique and the ACS concept by using ajia Island in Guangdong Province, China. A 1300 W
a genetic algorithm. The ow chart of the optimization GSM base station RBS2206 (24 V AC), and a 200 W
process is illustrated in Fig. 3. microwave (24 V DC) are needed for the normal operation
The decision variables included in the optimization pro- of the telecommunication station. According to the project
cess are the PV module number NPV, wind turbine number requirements and technical considerations, a continuous
NWT, battery number Nbat, PV module slope angle b 0 and power consumption of 1500 W (1300 W AC and 200 W
wind turbine installation height HWT. A year of hourly DC) is chosen to be the hybrid system load requirement.
data including the solar radiation on the horizontal sur- The technical characteristics of the PV module and bat-
face, ambient air temperature, wind speed and load power tery as well as the wind turbines power curve used in the
consumption are used in the model. studied project are given in Tables 4 and 5 and Fig. 4.
The initial assumption of system conguration will be The lead-acid batteries employed in the project are
subject to the following inequalities constraints: specially designed for deep cyclic operation in consumer
H. Yang et al. / Solar Energy 82 (2008) 354367 363
Table 6
Optimal sizing results for the hybrid solarwind system for LPSP = 1% and 2%
Desired LPSP NWT NPV Nbat b 0 () HWT (m) Cost (US$) LPSP (%)
1% 1 128 6 24.5 31.0 10,600 0.97
2% 1 115 5 24.0 32.5 9708 1.96
Fig. 6. Battery SOC distribution probability for optimal result. The relationship between system power reliability and
system congurations are also studied. The calculation
results (PV module and wind turbine congurations under
dierent battery capacities) for dierent desired power reli-
abilities (LPSP = 1% and 2%) are shown in the solid sym-
bols in Figs. 9 and 10. The areas above the curves are the
congurations that can ensure the required power reliabil-
ity. In this study, because the load consumption is 1500 W
constantly, then 1 days battery storage equals to 1.5
strings of battery cells (1500 Ah, 24 V) based on battery
nominal capacity terms.
For a desired LPSP of 1% (Fig. 9), it shows that when
the battery storage is higher, the system conguration
(PV module and wind turbine power) is lower. A similar
situation happens to the system with an LPSP of 2%
(Fig. 10), but compared to the system with an LPSP of
Fig. 7. Variations of ACS during GA optimization process. 1%, the PV module and wind turbine power are more mod-
erate; this shows the impact of system power reliability
The optimal sizing method can also be applied to design requirements on the system congurations.
systems whose power source consists either only of PV The annualized cost of system (ACS) under dierent
modules or only of wind turbines. And the optimal sizing congurations was also given by the hollow symbols in
results for PV alone and wind turbine alone systems for Figs. 9 and 10. In the case of Fig. 9, the ACS for four
the LPSP = 2% are given in Table 7. It is obvious that in and ve days battery storage are lower than the three
both cases, the optimal congurations result in a higher days, but the lowest ACS point happened on the four
annualized cost of system compared to the hybrid solar days line, this shows that in all likelihood the optimal
wind system given in Table 6. value is someplace around four days battery storage, and
this is the case given in Table 6 where four days battery
storage (six strings of battery cells) has been chosen. In
6.2. Power reliability and annualized cost of system Fig. 10, the ACS lines at the lowest point are almost on
top of each other, this would indicate that the real optimal
The minimum annualized costs of system for dierent should be somewhere in the middle between three and ve
LPSP (power reliability requirements) are calculated by days storage, which is also constant with the optimization
Table 7
Optimal sizing results for PV alone and wind turbine alone system for LPSP = 2%
Item NWT NPV Nbat b 0 () HWT (m) Cost (US$) LPSP (%)
PV alone Null 182 8 25.0 Null 11,145 1.96
Wind turbine alone 4 Null 17 Null 30.0 16,889 1.98
366 H. Yang et al. / Solar Energy 82 (2008) 354367
7. Conclusions
References
result in Table 6 where around 3.3 days battery storage
(ve strings of batteries) is selected. Ashari, M., Nayar, C.V., 1999. An optimum dispatch strategy using set
Generally speaking, for the studied area, the hybrid points for a photovoltaic (PV)dieselbattery hybrid power system.
solarwind system with 35 days battery nominal storage Solar Energy 66 (1), 19.
H. Yang et al. / Solar Energy 82 (2008) 354367 367
Berndt, D., 1994. Maintenance-free Batteries. John Wiley & Sons, Perez, R., Ineichen, P., Seals, R., 1990. Modeling of daylight availability
England. and irradiance components from direct and global irradiance. Solar
Borowy, B.S., Salameh, Z.M., 1996. Methodology for optimally sizing the Energy 44, 271289.
combination of a battery bank and PV array in a wind/PV hybrid Schott, T., 1985. Operational temperatures of PV modules. In: 6th PV
system. IEEE Transactions on Energy Conversion 11 (2), 367373. Solar Energy Conference. pp. 392396.
Due, J.A., Beckman, W.A., 1980. Solar Engineering of Thermal Process. Tina, G., Gagliano, S., Raiti, S., 2006. Hybrid solar/wind power system
John Wiley & Sons, USA. probabilistic modeling for long-term performance assessment. Solar
Eftichios, Koutroulis et al., 2006. Methodology for optimal sizing of Energy 80, 578588.
stand-alone photovoltaic/wind-generator systems using genetic algo- Van Dyk, E.E. et al., 2002. Long-term monitoring of photovoltaic
rithms. Solar Energy 80, 10721188. devices. Renewable Energy 22, 183197.
Gipe, Paul, 1995. Wind Energy Comes of Age. John Wiley & sons, p. 536. Yang, H.X., Burnett, L., Lu, J., 2003. Weather data and probability
Guasch, D., Silvestre, S., 2003. Dynamic battery model for photovoltaic analysis of hybrid photovoltaicwind power generation systems in
applications. Progress in Photovoltaics: Research and Applications 11, Hong Kong. Renewable Energy 28, 18131824.
193206. Yang, H.X., Lu, L., 2004. Study on typical meteorological years and their
Holman, J.P., 1992. Heat Transfer. McGraw-Hill. eect on building energy and renewable energy simulations. ASHRAE
Kellogg, W.D. et al., 1998. Generation unit sizing and cost analysis for Transactions 110 (2), 424431.
stand-alone wind, photovoltaic and hybrid wind/PV systems. IEEE Yang, H.X., Lu, L., Zhou, W., 2007. A novel optimization sizing model
Transactions on Energy Conversion 13 (1), 7075. for hybrid solarwind power generation system. Solar Energy 81 (1),
Luis, C., Sivestre, S., 2002. Modeling Photovoltaic Systems using PSpice. 7684.
John Wiley & Sons Ltd, Chichester. Zhou, W., Yang, H.X., Fang, Z.H., 2007. A novel model for
Markvart, T., 1996. Sizing of hybrid PV-wind energy systems. Solar photovoltaic array performance prediction. Applied Energy 84 (12),
Energy 59 (4), 277281. 11871198.