POWERMECH PROJECTS LTD

2x660MW SURATGARH POWER PROJECT


ERECTION PLAN FOR THE MONTH OF JUNE-2016 OF UNIT # 7 Date-02/06/2016
TARGET ERECTION
SL No. Activity REMARKS
WEIGHT

1 ESP 10MT

2 BOILER STRUCTURES 350MT

3 ROTATING PARTS 20MT

4 COAL PIPING 30MT

5 PRESSURE PARTS & SOOT BLOWER 30MT

6 PENT HOUSE 20MT

7 DUCTING 180MT

8 CRITICAL PIPING 218MT

9 AUXILIARY BOILER 44MT

10 INSULATION & CLADDING 143MT


11 I & T PIPING & OIL SYSTEM PIPING 16MT

TOTAL TONNAGE :- 1060MT


POWERMECH PROJECTS LTD
2x660MW SURATGARH POWER PROJECT
ERECTION PLAN FOR THE MONTH OF JUNE-2016 OF ESP UNIT # 7 Date-02/06/2016
PGMA
SL No. Activity TARGET ERECTION WEIGHT REMARKS
DETAILS
1 INSULATOR HOUSING AS 79-906 1.00MT

2 GAS DIST. ASSY 79-908 2.00MT

4 COLL ELEC RAPP DRIVE 79-926 2.00MT

5 GEARED MOTORS FOR RAPPING MECH 79-931 5.00MT

TOTAL TONNAGE(A,B,C&D PASS) 10.00MT


POWERMECH PROJECTS LIMITED

2x660MW SURATGARH POWER PROJECT


Erection Plan of Boiler Structures for the Month of JUNE-2016, Unit # 7 Boiler
Date-02/06/2016
Target Erection
SL No. Activity PGMA Remarks
weight
BUNKER BAY COLUMNS & BUNKER BAY
1 34-100 & 400,500 100.00MT
HORZ.BEAMS
NON-MBL FLOOR BETWEEN MBL II AND
2 36-323,324 &325,26 60.00MT
III

3 MISCELLANEOUS PLATFORMS 36-391 50.00MT

FLOORGRILLSANDGUARDPLATE
4 36-812 50.00MT
MIDDLE

NON-MBL FLOOR BETWEEN MBL I AND


5 36-315 & 36-316 50.00MT
II

6 MILL HANDLING MONORAILS 38-299 40.00MT

Total Tonnage 350.00MT


POWERMECH PROJECTS LTD
2x660MW SURATGARH POWER PROJECT

ERECTION PLAN FOR THE MONTH OF JUNE-2016 OF ROTATING MACHINES UNIT # 7


Date-02/06/2016
PGMA TARGET ERECTION
SL No. AREA Activity REMARKS
DETAILS WEIGHT
BUNKER OUTLET GATE 36" MTR
1 67-272 10.00MT
OPRTED CIR
ROTOR ASSY WITH STAND W/O
2 55-215 10.00MT
BLADES

TOTAL TONNAGE 20.00MT


POWERMECH PROJECTS LTD
2x660MW SURATGARH POWER PROJECT

ERECTION PLAN FOR THE MONTH OF JUNE-2016 OF COAL PIPINGUNIT # 7


Date-02/06/2016
PGMA
SL No. Activity TARGET ERECTION WEIGHT CIRCUIT NO
DETAILS

1 ST PIPES&SHOP BENDS FOR A & B MILL 47-200&221 15.00MT

ST PIPES&SHOP BENDS FOR C & D MILL &


2 47-266 15.00MT
ST PIPES & SHOP BENDS FOR E & F MILL

TOTAL TONNAGE 30.00MT


POWERMECH PROJECTS LTD
2x660MW SURATGARH POWER PROJECT

ERECTION PLAN FOR THE MONTH OF JUNE-2016 OF PRESSURE PARTS UNIT # 7


Date-02/06/2016
PGMA TARGET ERECTION
SL No. Activity CIRCUIT NO
DETAILS WEIGHT

1 SH VERT SPCD FRONT COIL ASSY-LEFT 11-074 10.00MT

2 SEAL BOXES FOR FURNACE OPENING 09-004 2.00MT

3 WALL BLOWER 20-501 15.00MT

4 RECIRCULATION PUMP 07-

5 SH STEAM COOLED SPACER TUBES 12-803 2.00MT

6 MTM CLAMPS AND PADS 97-297 0.50MT

TOTAL TONNAGE 29.50MT


POWERMECH PROJECTS LTD
2x660MW SURATGARH POWER PROJECT

ERECTION PLAN FOR THE MONTH OF JUNE-2016 OF PENT HOUSE UNIT # 7


Date-02/06/2016
PGMA
SL No. Activity TARGET ERECTION WEIGHT CIRCUIT NO
DETAILS

FIRST PASS DECK SPRT AND SEAL & SECOND 30-233 & 30-
1 234 20.00MT
PASS DECK SPRT AND SEAL

TOTAL TONNAGE 20.00MT


POWERMECH PROJECTS LTD
2x660MW SURATGARH POWER PROJECT
ERECTION PLAN FOR THE MONTH OF JUNE-2016 OF DUCTING UNIT # 7 Date-02/06/2016
PGMA
SL No. Activity TARGET ERECTION WEIGHT REMARKS
DETAILS
DUCT - ECONOMISER TO
1 48-382 20.00MT
AIRHEATER2NOP
DUCT - S PRI FAN TO AIRHEATER
2 48-112 40.00MT
PRISID

3 DUCT - BET F.D FAN AND AIRHEATER 48-012 30.00MT

DUCT - BOILER OUTLET TO ELEC


4 48-462 30.00MT
PRECP
DUCT - AIRHEATER BOILER OUTLET-
5 48-432 40.00MT
GAS
DUCT - SAIRHEATER TO
6 48-202 20.00MT
WINDBOXDUCT

TOTAL TONNAGE 180.00MT


POWERMECH PROJECTS LTD
2x660MW SURATGARH POWER PROJECT
ERECTION PLAN FOR THE MONTH OF JUNE-2016 OF CRITICAL PIPING UNIT # 7 Date-02/06/2016

PGMA
SL No. Activity TARGET ERECTION WEIGHT ELEVATION NO REMARKS
DETAILS
MS FROM BOILER STOP VALVE TO ESV B
1 80-301 50.00MT 21 MTR
ROW UPTO B-ROW
MS PIPING TO PRDS & DE-SUPERHEATING
2 80-303 5.30MT 19.5 MTR
STATION
HRH FROM INTERCEPTOR VALVE(PART-1) B
3 80-310 41.00MT 25 MTR
ROW UPTO B-ROW

4 CRH REHEATER TO Y PICE UPTO NRV 80-320 40.00MT 5.650 MTR


AB-BAY,EL-5MTR

5 CRH HEADER TO AUXL PRDS 80-324 1.40MT 26 MTR

6 DEARATOR TO MDBFP SUCTION LINE 80-420 4.00MT 2.530 MTR

RECIRCULATION LINE OF MDBFP TO


7 80-421 7.00MT 2.7 METER
DEARATOR
BOILER FEED PUMP TO HPH INCLUDING
8 80-423 12.00MT 20MTR
BYPASS UP TO HYDROTEST
BFD BETWEEN HTRS AND GROUP
9 80-424 16.00MT 23MTR
PROTECTION
10 BFD FROM FINAL HPH TO SG TP 80-425 15.00MT 20MTR
UPTO BOILER NRV

11 HP BAYPASS SPARY PIPING 80-430 4.00MT 20MTR

80-928 & 80-


12 HANGERS & SUPPORTS 17.00MT 20MTR TO 80MTR
913
13 CD BAY STRUCTURES 80-940 5.00MT 25MTR

TOTAL TONNAGE 217.70MT


POWERMECH PROJECTS LTD
2x660MW SURATGARH POWER PROJECT

ERECTION PLAN FOR THE MONTH OF JUNE-2016 OF AUXILIARY BOILER UNIT # 7


Date-02/06/2016
SL No. Activity PGMA DETAILS TARGET ERECTION WEIGHT

1 BOILER ROOF SHEETING 35-611 2.00MT

2 CHIMNEY 87-150,300,950&100 30.00MT

3 FD FAN 56 10.00MT

4 PIPING 80-345 2.00MT

TOTAL TONNAGE 44.00MT


7

CIRCUIT NO
POWERMECH PROJECTS LTD
2x660MW SURATGARH POWER PROJECT

ERECTION PLAN FOR THE MONTH OF JUNE-2016 OF INSULATION & CLADDING BOILERUNIT # 7
Date-02/06/2016
SL No. Activity PGMA DETAILS TARGET ERECTION WEIGHT CIRCUIT NO
ESP INSULATION

1 ESP HOPPER FUNNE50 MM THICK 79967 26.00MT

CLADDING SH FOR ESP AL


2 89615 5.00MT
0.711MMX1,219

BOILER INSULATION

3 BLR PR PARTS MINERAL WOOL 33-021 100.00MT

4 BLR OUTER CASING COMPONENTS 37-810 10.00MT

SKIN CASING COMPS WELDED TO


5 PRESSURE & FURNACE REAR ARCH SKIN 31-010 & 31-104 1.50MT
CASING
TOTAL TONNAGE 142.50MT
POWERMECH PROJECTS LTD
2x660MW SURATGARH POWER PROJECT

ERECTION PLAN FOR THE MONTH OF JUNE-2016 OF I&T PIPING OIL SYSTEM PIPING UNIT # 7
Date-02/06/2016
PGMA
SL No. Activity TARGET ERECTION WEIGHT CIRCUIT NO
DETAILS

1 RECIRCU PUMP DISCHARGE LINE 24-808 6.00MT

42-070, 42-
858, 42-154,
2 FUEL OIL SYSTEM - SHOP ITEMS 42-152, 42- 10.00MT
158, 42-030 &
42-020

TOTAL TONNAGE 16.00MT