Delivery Schedule
April 2012 March 2014
&
Forward Plan
2014 - 2017
1
Strategic Objective 1: Retain and maintain existing facilities that are highly valued by the community
2
Action Actions Lead Who else is Evidence of By when Consequence of action
Plan Ref: critical to deliver commitment to not being delivered
the action deliver
1.3 Assess satisfaction with sport BDBC Policy BDBC to commission Unit Service Plan During Feedback unavailable to help
and recreation facilities through Hub survey 2012 inform decision making
resident satisfaction surveys Sport England
Refresh asset management plans Relevant Facility providers and Facility provider By March Lack of forward planning for
and identify service / funding facility facility managers service plans / core 2014 major items of replacement /
1.4
implications for all key facilities providers funding agreements refurbishment may lead to
facility closures and loss of
services
1.5 Produce a pavilions investment / BDBC BDBC Community Relevant Unit By March Investment in facilities is not
disposal strategy for all council Resources Unit Services Unit Service Plans 2014 directed to facilities that are well
owned pavilions (link to action used and meet local needs
3.3 review of playing pitches)
1.6 Replace Tennis Centre roof in BDBC BDBC Community Relevant Unit By March Condition of the Tennis Centre
accordance with Asset Resources Unit Services Unit ; Totally Service Plans 2014 deteriorates; may lead to facility
Management Plan Tennis, LTA closure; would be in breach of
Tennis action plans
funding agreement with LTA
1.7 Evaluate pilot scheme to transfer BDBC Hants FA Unit Service Plan By July 2013 Impact of pilot arrangements not
some management functions to Community known; changes may not meet
Services Unit FDC Hants FA Plan
Hants FA at Winklebury Stadium the needs of the community,
BDBC, Hants FA
1.8 Develop a funding strategy to Basingstoke External grant Basingstoke & By August Lack of forward planning to
meet the asset management and District funders District Sport Trust 2013 secure long term funding for
needs identified at Basingstoke Sports Trust Service Plan; Core essential works at the sports
Sports Centre 2015-2025 Funding Agreement centre
1.9 Establish Fields in Trust sites and BDBC BDBC- Resources Relevant Unit December Risk that opportunities to secure
governance / protection Community Unit Service Plans 2012 Playing Fields under the scheme
arrangements Services Unit are not realised
Fields in Trust
website
3
Strategic Objective 2: Improve the quality and capacity of facilities that are highly valued by the community
4
Action Actions Lead Who is critical to Evidence of By when Consequence of action
Plan deliver the action commitment not being delivered
Ref: to deliver
2.2 i) Carry out survey of use of BDBC Community Schools Unit Service July 2012 Lack of understanding of
indoor sports halls in the Community Plan sports hall capacity and
Services Unit Community Sports Clubs
borough; ii) carry out survey demands; opportunities to
among clubs to assess unmet match club needs with
demand for sports hall use; available opportunities
iii) work with providers and missed
clubs to match availability
with identified need
2.3 Develop plans in consultation Basingstoke BCOT for shared BRFC Website Complete Lack of public engagement
with local residents and Rugby sports facilities consultation & may have adverse impact
BCoT Strategy
stakeholders on enhanced Football club negotiations to on the Clubs plans to
Sport England / RFU as
facilities for Basingstoke RFU meeting commence develop options to enhance
funding partners and
Rugby Club at Down Grange minutes of improvement the facilities
rugby participation
support for scheme by
objectives
new club house December
BDBC as Land owner, 2013
Report:
and planning authority
713/CSL
and for participation Improvements to
objectives Down Grange
Sports Complex
2.4 Implement scheme to provide BDBC Basingstoke Rugby Club Unit Service March 2014 Need for additional car
additional car parking facilities Community (Links to 2.3 outcome Plan and parking not addressed;
at Down Grange within Services Unit of consultation for Capital earlier implementation
approved council budgets improvements to BRFC) programme does not take account of
BRFC scheme
2.5 Progress scheme to provide Barlows Park Tadley Calleva FC Barlows Park By start of BPMA is unable to generate
social facilities at Barlows Management primary user Management 2012-13 sufficient income to
Park Football Complex Association Association football season support running of the
BDBC and BPET
Business Plan facilities
(landlords)
West Berks - Planning
authority
5
Action Actions Lead Who else is critical to Evidence of By when Consequence of action
Plan deliver the action commitment not being delivered
Ref: to deliver
2.6 Develop a funding strategy BDBC BDBC Resources Unit LTA Facilities September Tennis Centre continues to
to deliver improvements to Community Totally Tennis , LTA Strategy 2013 deliver poor customer
the Indoor Tennis Centre Services Unit experiences particularly for
Collaborative approach Relevant Unit
children and people with
to funding Service Plans
disabilities due to separation
of courts from changing and
reception facilities
2.7 Agree a plan for BDBC BDBC Community Relevant Unit March Investment decisions will not
refurbishment of the Resources Unit Services Unit Service Plans 2014 be available to inform
Aquadrome, including procurements options and
Community Leisure
replacement flumes, beyond specification for management
Trust - operator
expiry of the current beyond current contract
contract in 2018 Service implications need period
to be assessed
2.8 Agree a plan for BDBC BDBC Community Relevant Unit March Investment decisions will not
refurbishment of Tadley Resources Unit Services Unit Service Plans 2014 be available to inform
Swimming Pool, beyond Community Leisure procurements options and
expiry of the current Trust - operator specification for management
contract in 2018 beyond current contract
Service implications need period
to be assessed
2.9 Deliver Mini golf feature at Community BDBC as landowner CLT 2011-2 Spring Loss of income against Trust
Basingstoke Golf Centre Leisure Trust business Plan 2012 business plan
2.10 Investigate potential asset BDBC Netball League Unit Service Plan Summer Lack of long term
transfer of pavilion at Community 2013 management / investment
Services Unit England Netball
Russell Howard Park to plan for the netball facilities;
Netball League as part of condition of courts and
wider aim to improve pavilion deteriorate.
netball provision (also link
to Pavilion Strategy)
6
Action Actions Lead Who else is critical to Evidence of By when Consequence of action
Plan deliver the action commitment not being delivered
Ref: to deliver
2.11 Develop plans and Basingstoke UKA External funding Feasibility Study By March No prospect of a stand
funding strategy for a and Mid Hants initiated by the 2013 without feasibility and funding
BDBC as landowner
spectator stand at Down Athletics Club Club strategy in place
Grange Athletics Track
2.12 Develop a business case Basingstoke BDBC as landowner Verbal By March No prospect of a second
and explore funding Hockey Club commitment to 2013 pitch without feasibility and
England Hockey
options for a second date funding strategy in place
artificial pitch at Down
Grange
2.13 Progress Scheme to Oakley Bowls BDBC Capital Grant Feasibility Study September Club are unable to expand /
provide new clubhouse Club Application and scheme 2012 attract new members due to
for Oakley Bowls Club developed by the limitation of the
Club clubhouse
7
Strategic Objective 3: Where there is evidence of need that cannot be met by existing provision, enable the
development of new provision
For sufficient Sport and Recreation facilities to be provided in % of S106 agreements securing on site sport and recreation provision or a developer
the planning stages of any new developments contribution to local and / or strategic sport provision
For a long term plan to be in place to enhance facilities at the Increase in resident satisfaction with the Leisure Park resident survey
Leisure Park
9
Action Actions Lead Who else is critical Evidence of By when Consequence of action
Plan to deliver the action commitment to not being delivered
Ref: deliver
3.7 Progress scheme to Basingstoke British Canoe Union Basingstoke Canoe By March No facilities for outdoor
provide a club house for Canoe Club Club action plan 2014 water based pursuits
Hart District Council
Basingstoke Canoe Club available to local residents
British Canoe Unit
Community Club
funding programme
3.8 Promote provision of BDBC BDBC Policy Hub Inclusion in GI Strategy Ongoing Opportunity to significantly
new way marked walks Community and transport planning increase participation and
and cycle routes in the Services Unit policies improve wellbeing by
town area through Green providing better access to
Infra-structure and facilities and open spaces not
Transport policies met
3.9 Progress scheme to Testbourne Sport England Testbourne March Opportunity to increase
deliver multi functional Community External Funding Community School 2014 community use of
hall at Testbourne school School Application Plan Testbourne School is not
and explore met, opportunities for the
HCC Education
opportunities for residents of Whitchurch and
Authority
collaboration between Overton benefit from
sports providers in Long Meadow Sports coordinated programming
Whitchurch and Overton Trust and facility planning are not
Whitchurch Town developed
Council
Overton Parish Council
10
Strategic Objective 4: Drive up participation in sport and physical activity to increase the number and frequency
of people taking part on a regular basis, ensuring there are choices that offer low cost options.
For participation in physical activity by people with disabilities and Recorded % of people with disabilities and people from minority groups
by people from minority groups to increase undertaking 3 x 30 minutes physical activity per week (Active People Survey)
For the scope of opportunities for older people to take part in Feedback from Older Persons groups and facility providers
sport to be extended
To achieve an increase in the number of high quality Clubmark Number of accredited clubs in the borough registered with Sport England
accredited sports clubs
For there to be a broad range of sport and recreation Number of actions delivered over the life of the Strategic Plan for Sport and
opportunities that meet the needs of local residents Recreation
For the range and promotion of low cost activity options to be Reduction in the % of people who say cost is the main barrier to participation
increased (Resident survey)
11
Action Actions Lead Who else is Evidence of By when Consequence of action
Plan critical to deliver commitment to not being delivered
Ref: the action deliver
Undertake a comprehensive review BDBC BDBC Resources Relevant Unit September True cost of council
of fees and charges for all council Community Unit Service Plans 2012 provision of sports facilities
4.2 Services Unit
owned facilities to assess cost of not known, subsidies not
provision vs income from charges fairly applied to support
and develop a policy on public participation objectives
subsidy to support participation
4.3 Establish performance indicators to BDBC Key sport and Unit Service Plan March Social and economic
evidence the value of sport to Community recreation providers 2013 benefits of sports not
individuals, communities and places Services Unit evidenced and impact of
services provided unknown
4.4 Identify and promote potential BDBC Local Sports Unit Service Plan Ongoing Opportunities to attract
external funding sources to support Community Council funding to support building
initiatives improving access and Services Unit schemes and participation
participation in sport projects are missed
4.5 Commission training programmes BDBC Local Sports Unit Service Plan March Clubs and volunteers feel
for clubs to strengthen volunteer Community Council 2013 then unsupported and under
Services Unit Local Sports
recruitment, retention and skills annually valued, number of
Council Aims and
volunteers decline, skills
Objectives
and experience of voluntary
groups decline
4.6 Investigate development of a centre Shin Gi Tai BDBC Community Verbal commitment July 2012 Clubs unable to respond to
for martial arts clubs and other Martial Arts Services Unit initial to meet and growing demand for Martial
compatible indoor sports Academy; coordination of clubs explore options Arts activity and growth in
(particularly Table Tennis) through Overton & Other clubs as Table Tennis
collaboration by relevant sports Basingstoke Tai relevant
providers Kwondo, Table
Tennis League
12
Action Actions Lead Who else is Evidence of By when Consequence of action
Plan critical to deliver commitment to not being delivered
Ref: the action deliver
4.7 Work with British Cycling to BDBC British Cycling Unit Service Plan April 2012 Lost opportunity to
establish recreational cycling sessions Community increase participation linked
Services Unit British Cycling
for women, using existing cycle to an initiative by British
Breeze strategy
networks, to encourage Cycling
and local champion
participation particularly among
older people and minority groups
4.8 Develop a clear procedure and BDBC BDBC Community Establishment of March Lack of clarity relating to
criteria for the commissioning of Commissioning Services Unit BDBC 2013 specification and outcomes
sports services (eg through core Unit Commissioning for sports services
funding, grants, purchasing Unit procured by the council
arrangements) by the council
13
3 Year Forward Plan
2014 2017