Sie sind auf Seite 1von 3

Hard Copy Assignment-6 (Scheduling)

ME 431: Decision Modelling, UG level, SK Patel, ME, Autumn, 2017-18


Note: All the following assignments are to be solved in the class note and shown in next class.

Q Date Questions
1 05-10-17 There are four jobs to be processed on a single processor. The processing times
and due dates of all the jobs are tabulated below.
Processing Time, p
Job Due Date, d (Days)
(Days )
J1 3 5

J2 8 10

J3 2 19

J4 9 18
Find the optimal sequencing using shortest processing time (SPT) rule. For each
of the sequencing, compute time schedules (i.e., start and finish times) and all
the efficiency parameters i.e. mean flow time, mean lateness, mean earliness,
mean tardiness, maximum tardiness, number of tardy jobs and makespan.

2 05-10-17 Solve Q.1 using Earliest Due Date (EDD) rule.


3 05-10-17 Solve Q.1 using Moore rule.
4 05-10-17 Solve Q.1 using Weighted SPT rule if the weights of jobs J1, J2, J3, and J4 are
2, 1, 2 and 3 respectively.
5 05-10-17 Solve Q.1 on First Come First Serve basis if the jobs J1, J2, J3, and J4 have
arrived 0, 2, 4, 5 days after today.
6 05-10-17 Solve Q.5 on Last Come First Serve basis. Scheduling is done after all the jobs
have arrived at t = 5.
7 06-10-17 There are 5 jobs and all are to be first turned on a lathe and then finished on a
grinding machine. Their processing times on these two machines and due dates
for delivery to customers are tabulated below. Suggest the optimal job schedule.
Plot Gantt chart. Find idle times of two machines and makespan. Also find mean
flow time, mean lateness, mean earliness, mean tardiness, maximum tardiness,
number of tardy jobs.

Jobs Processing time on


Lathe Grinder Due date
J1 8 6 25
J2 2 3 5
J3 7 7 20
J4 6 3 10
J5 4 7 15
8 06-10-17 Refer Q.7. Find out makespan taking J1-J2-J3-J4-J5 as job sequence.

Dr. S.K. Patel, Mech Engg, NIT Rourkela 4-Sep-15 Page 1 of 3


9 06-10-17 What should be the job sequencing to minimize makespan for a flow shop
having 4 jobs of which all are to be processed in three machines in the order
M1-M2-M3 if the processing times are as tabulated below. Plot Gantt chart.
Find idle times of all three machines and makespan. Also find mean flow time,
mean lateness, mean earliness, mean tardiness, maximum tardiness, number of
tardy jobs and makespan.

Jobs Processing time


Machine J1 J2 J3 J4
M1 8 7 3
5
M2 6 7 2 5
M3 7 8 10 9
Due Date 15 25 10 20
10 06-10-17 What should be the job sequencing to minimize makespan for a flow shop
having 3 jobs of which all are to be processed in four machines in the order M1-
M2-M3-M4 if the processing times are as tabulated below. Plot Gantt chart.
Find idle times of all four machines and makespan.
Jobs Processing time
Machine J1 J2 J3
M1 7 7 5
M2 4 3 2
M3 1 3 2
M4 6 8 6
11 10-10-17 Prepare the schedule using Earliest Due Date rule for 6 jobs on three machines
A, B and C whose routing, processing times and due dates are as tabulated
below.
Job Routing and Processing Times Due Date
1 A-4, B-2, C-1 10
2 A-5, C-3 14
3 B-3, A-4, C-2 12
4 B-2, C-5, A-2 20
5 C-4, B-5,A-1 16
6 C-3, A-3, B-4 18

Plot Gantt chart. Find idle times of two machines and makespan. Also find mean
flow time, mean lateness, mean earliness, mean tardiness, maximum tardiness,
number of tardy jobs. Break tie using FISFS rule. [Ans: makespan = 21]
12 10-10-17 Refer Q. 11. Solve it using Shortest Processing Time rule. [Ans: makespan = 19]

Dr. S.K. Patel, Mech Engg, NIT Rourkela 4-Sep-15 Page 2 of 3


13 10-10-17 Refer Q. 11. Solve it using First Come First Serve rule. [Ans: makespan = 20]

14 10-10-17 Refer Q. 11. Solve it using First In System First Serve rule.[Ans: makespan= 23]

15 10-10-17 Refer Q. 11. Solve it using Least Work Remaining rule. Break tie using EDD
rule [Ans: makespan = 20]
16 10-10-17 Refer Q. 11. Solve it using Least Slack First rule. Break tie using EDD rule
[Ans: makespan = 20]
17 10-10-17 The following table shows routing and processing times of 2 jobs J1 and J2 on 5
machines A, B, C, D and E. What should be the sequencing of jobs so as to
minimize makespan. [Ans: makespan = 17]
Job Routing & processing time
J1 C-2, D-3, B-2, E-4, A-5
J2 A-3, B-2, C-1, E-2, D-2
18 10-10-17 What are the assumptions common to all types of scheduling?
19 10-10-17 Differentiate the following types of scheduling:
i. Flow shop and job shop
ii. Static and dynamic scheduling
iii. Finite and infinite
iv. Forward and backward
v. Deterministic and stochastic
vi. Lateness and tardiness
vii. Critical ratio and slack

Dr. S.K. Patel, Mech Engg, NIT Rourkela 4-Sep-15 Page 3 of 3

Das könnte Ihnen auch gefallen