Beruflich Dokumente
Kultur Dokumente
DESIGN GUIDE
REINFORCING SOLUTIONS DESIGN GUIDE
NZ EDITION
1. Introduction 3
2. Application Examples 4
3. Reinforcing 6-17
3.1 Features and Benefits 6
3.2 ReidBar Specifications and Sizes 7
3.3 Anchoring in Concrete 8
3.5 Performance Comparisons 10
3.6 ReidBar Components 11
3.7 Typical Construction Details 14
4. Formwork 18-19
4.1 Features and Benefits 18
4.2 Typical Construction Details 19
Using ReidBar Grout Sleeves and couplers each floor of this building took
only three days to construct. This grouting method provides continuity in
reinforcement.
More detail on ReidBar components can be found on product specific technical datasheets available from
Reid. They can also be downloaded from www.ramsetreid.com.
Reinforcing
Soil Nails/Anchors
Used to provide soil stabilisation in
earthwork construction.
ReidBar Couplers
A threaded method of providing continuity in reinforcement.
Rockbolts Mining
Used for rock stabilisation in mining
and civil construction.
Fastening Bracing
Can be used to provide bracing and stabilising of any structure. Ideal
retrofit to improve the performance of existing structures.
Typical Characteristics
800
600
Stress (MPa)
400
200
DETAIL 1
Ldh Detail 1a
Ldh
Standard 90 or
180 hook Local crushing
Bar Slip
Standard 90 or 180hook
Common starter detail in a thin panel where
embedment length may not meet code requirements
Research at New Zealand University of Auckland by Maureen Ma Threaded Insert effective depth he.
in 1999 into Methods of Joining Precast Concrete components to
form Structural Walls highlighted the performance of Reid Inserts
compared to that of conventional hooked bar construction. Apart
from requiring significantly less embedment to develop the full
capacity of the reinforcing bar, ReidBar Inserts effectively remove
the issue of localised concrete crushing.
For further information on the ReidBar system for Slab to Wall connections, please refer to:
Patrick, M / Wheeler, A / Gonzales, A / Marsden, W
Innovative Testing Procedures for a High-Performance, Pre-formed Mechanical Connection System between Concrete Slabs and Walls,
Proceedings Concrete 05, Concrete Institute of Australia, 2005
150
LOAD +
120
Wall Panel
RB12@300
1000
RB12@150
1400
Interface left by Steel Cone
270
150
RB12
70
50
150
LOAD +
120
RB12@150
Wall Panel
1000
RB12 @ 300
1400
Base Block
70 RB12@300
Hook Bar
300
150
70
A C
A C
ReidBar
ReidBar Domed Base Plates & Spherical Washers Suitable for RB12TI, RBA16TI & RB20TI only.
Refer to P17 for details.
Typical cantilevered footing detail Domestic basement wall - Using masonry construction
Masonry Block
HD PVC tube around bar if wanting
to screw in verticals after laying blocks
Typically RB12 at
600mm centres
Header block
DPC
2/RB12 bars
RB12 at 600mm centres (typical) Previous pour Current pour
The typical construction details are examples only. All details should be designed and checked by a suitably qualified
engineer to ensure the detail is fit for the purpose it is intended.
ReidBar Coupler
Fillet Strip
Fillet Strip ReidBar ReidBar
Timber Liner Threaded Insert
Plastic plug
Always ensure that the coupler is firmly screwed onto nail plate.
Nail plates WILL NOT support foot traffic.
Support the bar close to the coupler.
Typical slab to insitu wall detail - Single Row Typical slab to insitu wall detail - Double Row
L mm
ReidBar RB _ TI at S CTRS.
L mm If required, set Insert into rebate
to maintain min cover
ReidBar RB _ TI at S CTRS.
Reid offers various rebate solutions to fix and locate Inserts to suit all construction methods.
Please contact Reid for more information.
ReidBar
Setting Hardware WILL NOT support foot traffic. Support the bar close to the grout sleeve.
Setting Hardware WILL NOT support foot traffic. Support the bar close to the grout sleeve.
Horizontal structural joint for two precast panels Horizontal structural joint for rebated precast panels
Pre-Pour Pressure Grouting
Arrangement Arrangement
ReidBar ReidBar
High Strength Grout poured into Flood joint with approved grout
Grout Sleeve immediately before
High Strength Flowable Grout
panel installation
pumped via. inlet until Grout
Sleeve full
ReidBar
Screw starter bars into coupling before ReidBar
lowering into position
(Alternatively, vertical bars could extend
into the grout sleeve, provided this does
not cause handling problems)
ReidBar
Typical Shear Wall Connection Threaded Insert to Near Face of Precast Panel
NP12RB
INFILL POUR
Panel 1
Panel 2
RB12 Headed
Stud or Insert
RB12
RB12TI IN 125 PANEL
Coupler
NP16RB
RB___WN
RB___
RB___TI
RB___WN
RB___
ReidBar Nuts
eg, RB20N
ReidBar
eg, RB20
th
Leng etres
Bond 1.5 M
m .
No
The free length is commonly grouted after the anchor has been stressed.
Alternatively the free length can be sleeved during installation and the anchor
grouted up to the surface. This effectively removes the bond over the free
length allowing it to preload during the subsequent stressing operation.
The accurate simulation of actual long term performance on site Fusion bonded epoxys are affected by ultraviolet radiation. Where
during testing is virtually impossible. However a series of accelerated part of an embedded bar is required to remain exposed some
corrosion tests have been undertaken to provide a comparison of the powdering may become evident.
relative performance of hot dip galvanising and fusion bonded epoxy.
The ultraviolet light in normal sunlight will degrade Fusion Bonded
The tests show that in the accelerated corrosion environment fusion Epoxy coatings at approximately 2 microns per year.
bonded epoxy continues to provide corrosion protection for at least
Where Fusion Bonded Epoxy coatings are required to remain
20 times longer than a hot dipped galvanised surface.
exposed to sunlight throughout a long working life then they
These tests were carried out in a Q-Fog Cyclic Corrosion Tester (salt should be overcoated with a 2 pack polyurethane paint system
spray cabinet) in accordance with the test method ASTM B 117 3. approximately 60 microns thick.
The fusion bonded epoxy top coat was applied over a zinc rich fusion Due to the coating flexibility straining of up to 75% of the bar yield
bonded epoxy base coat to give a combined total coating thickness will not crack the epoxy coating. At these high loads there may be
of 270 microns. This coating system provided corrosion protection some damage to the coating surfaces within the nut.
for at least 10,000 hours.
References
The hot dipped galvanised surface showed serious distress at
1. Australian Tunneling Conference, Sydney Australia, August 1997
350 hours and was completely destroyed at 500 hours.
2. After Fabrication Hot Dip Galvanising, Galvanizing Association of
The tests showed that the difference in corrosion resistance between
New Zealand
the fusion bonded epoxy only coating and the zinc rich plus fusion
bonded epoxy coating was only apparent after 5000 hours. At this 3. Orica Powder Coatings lab report # 0096 of 18 March 2002
time small blisters of 0.5mm diameter started showing on the bar
4. BS 8081:1989 British Standard Code of Practice for Ground
surface but still no rusting.
Anchorages
5. A.S.T.M. Atmospheric Corrosion data Table 3.40
Q - How far into the Coupler must the bar be threaded? Q - What is the best way of cutting ReidBar before joining?
A - Tests show that to achieve the ultimate strength of the A - It is best practice to cut ReidBarTM with a Bandsaw, Electric
connection the thread engagement must be at least 80% of the Hacksaw or Abrasive Wheel. Hydraulic cropping of ReidBarTM is not
maximum thread depth available in the fitting. Correct bar insertion recommended.
is critical to the performance of the ReidBar system and it is
recommended that good practice requires the user to mark the bar Q - What end treatment is required before coupling?
at half coupler length back from the inserted end so that a visual A - If ReidBarTM is cut as per the above recommended method,
check is available. there should be no need to linish or dress the bar end. If threading
difficulty is encountered because of burring, a light linishing should
Q - Is tightening torque critical in the performance of be all that is required.
ReidBar components?
A - Provided the bar is screwed tightly against the centre stop, Q - What type of nuts should I use and when?
or fully through the component, whichever is appropriate, the full A - A1. For most splicing and anchoring applications the primary
breaking strength of the bar will be developed. Reid recommends fittings (couplers, inserts and grout sleeves) may be used without
using a wrench with a minimum length of 300mm to ensure the bar additional nuts.
is fully engaged. A2. Nuts are used for all designs where the nut is required to develop
the full breaking strength of the bar e.g. terminations for rock bolts,
ground anchors, hold down bolts, tensioning applications, etc.
Q - How is the correct preload applied?
A - One possible method is to run the nut against the coupler by Q - What testing has been done for ReidBar?
hand then rotate the nut a further fixed amount. A - During the development of ReidBar and like products,
RB12N: 120 degrees after hand tight. extensive tests were conducted by Reid. These tests include cyclic
RBA16N: 100 degrees after hand tight. tension load tests, pullout tests to check embedment anchorage and
slip tests. The systems quality is continually monitored by Reid,
RB20N: 70 degrees after hand tight. along with the steel mills and fitting manufacturers, using inhouse
RB25N: 60 degrees after hand tight. testing laboratories in an ongoing program of quality assurance
RB32N: 30 degrees after hand tight. and development while specific research programs continue to be
undertaken.
Q - How hard is it to apply the preload? Contact Reid for copies of tests concerning specific applications for
A - In the larger sizes the correct preload requires the use of a very your project.
large spanner up to 1.5 metres long with very stiff jaws, otherwise
the corners of the nut will be turned and torque will be insufficient.
A 48 crescent spanner with a length of pipe is a good tool for this
application, however, you will also need a good strong vice bolted to
the floor to hold the coupler. If you are applying these sorts of loads
to a coupler in a precast element you need have sufficient concrete
strength to resist the torque.
Q - Can you bend and rebend ReidBar? Q - How do I connect one precast concrete element to
another using ReidBar?
A - Rebending reinforcing steel is not recommended because
steel strain hardens when it is bent and loses some of its ductility, A - The best way to join to concrete elements is by casting a
an effect that is usually increased when the steel is rebent. It is ReidBar Grout Sleeve into the top of the lower element and a
important that reinforcing steel used in concrete structures remains ReidBar Coupler into the bottom of the upper element. This
ductile, especially when the structure could be subjected to seismic eliminates the need for any starter bars protruding from the precast
loads. The importance of this has been highlighted by recent failures elements that are liable to damage and bending. Immediately prior
of concrete structures under seismic loads in California, Kobe and to final placing a starter bar of the correct length is screwed into the
Newcastle. ReidBar is highly ductile and can be cold bent and coupler and non-shrink grout is poured into the grout sleeve cup.
rebent around the minimum former diameters specified in AS/ The two elements are then brought together into the final position,
NZS4671:2001 and NZS3402:1989 without fracture (Note Q/A levelled and propped.
on HD Galvanised Bar). However, while a very common detail uses Note: This pre-grout method avoids the necessity for casting in grout
bent bars as starters for moment connections, the ReidBar system tubes and the need for a separate grouting operation.
can solve structural connection problems often encountered in thin
NOTE: TO EFFECTIVELY ANCHOR A GROUT SLEEVE IT REQUIRES A
sections or joints without bending the reinforcement.
LAP LENGTH OF BAR PROTRUDING FROM AND SCREWED INTO THE
Q - Can I weld cast ReidBar fittings? THREADED END.
A - Although cast SG Iron fittings can be welded using specialised Q - What grout can I use in ReidBar grout sleeves?
techniques however, it is not a recommended practice because it
A - Most general purpose grouts with a 28 day compressive
will degrade the strength and ductility of the fitting and it will no
strength exceeding 65MPa can be used. Reid Grout Sleeves have
longer meet the performance characteristics stated in this manual.
been tested with Ramset Premier Grout MP and Ramset Poziflo
If you have further questions regarding welding contact Reid for
Grout HS.
clarification.
Q - How does a ReidBar grout sleeve joint compare with a
Q - How do ReidBar starter bars compare with metric Drosbach joint?
threaded starter bars?
A - Set Out
A - There are three factors to consider: Joints formed with corrugated formers such as Drosbach tubes
A1. The minimum core diameter of reinforcing bars does not allow derive their strength from the integrity of the surrounding concrete.
the same diameter metric thread to be cut to a full profile. As with lapped joints, they must be staggered if used in high stress
A2. The thread cutting process will induce a notch effect at the base zones. ReidBar Grout Sleeves are simple and easy to use and the
of the thread and further reduce the bar strength. reusable setting hardware encourages both quick and accurate
placing in boxing and precast forms. The expanding rubber ferrule
A3. ReidBar threaded inserts have an effective depth allowing
positively excludes latents from the Grout Sleeve cavity.
ductile failure at full bar strength. Metric threaded inserts tend to be
Grout Sleeves have grout tube holes included in the casting.
shorter.
On-site
ReidBar Grout Sleeves have a short embedment depth, meaning
Q - Can I weld ReidBar ? that protruding starter bars are shorter, making on-site installation
easier and safer.
A - ReidBar is produced by the TEMPCORE process in Australia
and is Micro-Alloyed in New Zealand. Welding of ReidBar shall be Transport
carried out in accordance with AS/NZS 1554.3: 2002. The designer Protruding starters for Grout Sleeves are shorter, which reduces the
must determine the acceptability of bar welding in their design, and overall heights and widths of precast units to be transported. As a
should specify the welding process to be adopted, as some types of result, freight can be easier, safer and cheaper.
welded splices can reduce the ductility of the connected bars. Pricing
When all the costs for a completed joint are accounted for, size for
size, Grout Sleeves and Drosbachs will be a similar price. While
Drosbach tubes have a lower initial cost in practice the smaller grout
volume and lower grouting labour costs in a completed joint will
compensate for the higher initial cost of the grout sleeve. Since the
security of a ReidBar Grout Sleeve joint is completely independent
of the concrete it is the ideal solution for full strength joints in thin
sections.
ReidBar Grout Sleeves have been tested with 500 grade bar.
Q - What are the minimum cover requirements for ReidBar Q - Can I use SG Iron ReidBar components for lifting?
and components?
A - NO. SG Iron ReidBar components are not developed for this
A - ReidBar: Code requirements for Reinforcing must be observed. purpose and do not comply with the approved Code of Practice
Refer to NZS3101:2006 Concrete Structures Standard. published by The Department of Labour for lifting inserts.
Components: Q - What is the relationship between torque applied to the
Because the two main factors to be considered are Fire and nut and tension induced in the bar?
Corrosion sufficient protection for the components should be
specified by the designer according to the requirements of the A - The relationship of Torque versus tension in ReidBar systems
application, taking into consideration the relevant codes and the is reasonably linear up to about 25% of the bar yield strength. Refer
following notes. to the following graph.
Fire:
The temperature of the steel reinforcing is affected by the cover of
concrete over the full extent of the embedded bar. The temperature
is averaged over the steel by conduction along its length which
acts to quickly dissipate any localised temperature variations.
A minor reduction in the cover in a very localised area (e.g. at a
coupler) would therefore not lead to any significant increase in steel
temperature and no increased reduction in strength.
Corrosion:
(1) Those metal ReidBar components not made of ductile iron
require the same cover as the bar itself unless galvanised or
otherwise protected.
(2) ReidBar components in sizes larger than RB12 are generally
manufactured from specially alloyed high strength ductile iron.
Ductile iron corrodes at about 30% of the rate of reinforcing steels
and the products of the corrosion are not expansive. Therefore
it does not lead to the spalling and flaking problems commonly
associated with the corrosion of steels in concrete. Because of this
good corrosion resistance cover for Ductile Iron components can
be reduced, although it is suggested that cover be maintained to at
least 50% of code requirements for reinforcing steel. The exception
to the better corrosion resistance of ductile iron is sea water and in
that case it is preferable to use the same cover limitation as the bar.
Please contact your local ramsetreid Engineer on 0800 88 22 12 should you have any other questions regarding ReidBar design solutions.
80
70
60
Tension (kN)
50
40
30
20
10
0
0 100 200 300 400 500 600 700 800 900 1000 1100
GENERALNOTATION STRENGTHLIMITSTATENOTATION
a = actual anchor spacing (mm) Nuc = characteristic ultimate concrete
am = absolute minimum anchor spacing (mm) tensile capacity (kN)
ec = critical edge distance (mm) Nur = design ultimate tensile capacity (kN)
em = absolute minimum edge distance (mm) Nurc = design ultimate concrete tensile capacity (kN)
fsy = reinforcing bar steel yield strength (MPa) Nus = characteristic ultimate steel tensile capacity (kN)
Xnae = anchor spacing effect, end of a row, tension Vuc = characteristic ultimate concrete
edge shear capacity (kN)
Xnai = anchor spacing effect, internal to a row, tension
Vur = design ultimate shear capacity (kN)
Xnc = concrete compressive strength effect, tension
Xne = edge distance effect, tension Vurc = design ultimate concrete edge shear capacity (kN)
Xva = anchor spacing effect, concrete edge shear Vus = characteristic ultimate steel shear capacity (kN)
Xvc = concrete compressive strength effect, shear = capacity reduction factor
Xvd = load direction effect, concrete edge shear
Xvn = multiple anchors effect, concrete edge shear
CHECK 1 Determine applied loading and check absolute minimum edge and spacing distances of ReidBarTM fittings
Table 3.3.1a - Absolute minimum edge Distance and anchor spacing mm - em, am
ReidBarTM Insert RB12TI RBA16TI RB20TI RB25TI RB32TI
em 40 50 60 75 100
am 40 50 60 75 100
Step 4 Continued
Table 3.3.4e - Multiple Anchor Effect - Xvn